PROCUREMENT PLAN Project information: ENHANCING WATERWAY CONNECTIVITY AND WATER SERVICE PROVISION IN COLOMBIA’S PLAN PAZCIFICO Region Project P156880 Project Implementation agency: 1. NATIONAL UNIT FOR THE MANAGEMENT OF DISASTER RISK / UNIDAD NACIONAL DE GESTION DEL RIESGO DE DESASTRES Date of the Procurement Plan: 10/22/2019 Period covered by this Procurement Plan: 10/22/2019 – 12/15/2023 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the documents previously approved with the Bank will be used. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Is not applicable; Works: Is not applicable PROCUREMENT Colombia : Enhancing Waterway Connectivity and Water Service Provision in Colombia’s Plan Pazcifico PLAN General Information Country: Colombia Bank’s Approval Date of the Original Procurement Plan: 2019-12-12 Revised Plan Date(s): (comma delineated, leave blank if2022-08-03 none) Project ID: P156880 GPN Date: 2019-12-09 Project Name: Enhancing Waterway Connectivity and Water Service Provision in Colombia’s Plan Pazcifico Loan / Credit No: IBRD / 87980 National Unit for the Management of Disaster Risk Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned PTSP-BIRF8798-003 / Constr Improving Water Supply and Solicitud de oferta Single Stage - One E 2020-10-3 ucción acueducto Francisco P IBRD / 87980 Sanitation Services in partici Posterior Open - National 3,967,526.00 0.00 Cancelado 2020-01-13 2020-01-18 2020-02-29 2020-03-30 2020-05-04 s nvelope 1 izarro pating municipalities Improving Water Supply and PTSP-BIRF8798-005 / Constr Solicitud de oferta Single Stage - One E 2020-11-1 IBRD / 87980 Sanitation Services in partici Posterior Open - National 4,046,127.00 0.00 Cancelado 2020-01-27 2020-02-01 2020-03-14 2020-04-13 2020-05-18 ucción acueducto Timbiquí s nvelope 4 pating municipalities PTSP-BIRF8798-006 / Constr Improving Water Supply and Solicitud de oferta Single Stage - One E 2020-11-0 ucción alcantarillado municip IBRD / 87980 Sanitation Services in partici Posterior Open - National 3,760,945.00 0.00 Cancelado 2020-01-20 2020-01-25 2020-03-07 2020-04-06 2020-05-11 s nvelope 7 io seleccionado pating municipalities PTSP-BIRF8798-007 / Mante nimiento de las instalaciones Improving Waterway Transp Solicitud de oferta Single Stage - One E 2020-11-1 portuarias y equipos de Seña IBRD / 87980 ort in participating municipal Posterior Open - National 962,000.00 0.00 Cancelado 2020-01-27 2020-02-01 2020-03-14 2020-04-13 2020-05-18 s nvelope 4 lización y Seguridad durante ities el periodo de ejecución de la s obras PTSP-BIRF8798-0060 / Const Improving Waterway Transp Solicitud de oferta Single Stage - One E 2021-07-1 rucción del muelle y terminal IBRD / 87980 ort in participating municipal Posterior Open - National 1,336,814.00 0.00 Cancelado 2020-08-15 2020-08-28 2020-08-20 2020-09-18 2020-10-15 2020-10-06 2020-11-21 s nvelope 9 portuario del municipio de La ities Tola (Nariño) National Procure PTSP-BIRF8798-090 / Constr Improving Waterway Transp ment Document - Solicitud de oferta Single Stage - One E Ejecución p 2023-08-1 ucción del muelle y terminal IBRD / 87980 ort in participating municipal Posterior Open - National 1 Envelope proce 1,700,000.00 0.00 2022-09-28 2022-10-03 2022-11-14 2022-12-14 2023-01-18 s nvelope endiente 8 portuario No. 1 ities ss (Non Bank-SPD ) National Procure PTSP-BIRF8798-091 / Constr Improving Waterway Transp ment Document - Solicitud de oferta Single Stage - One E Ejecución p 2023-10-2 ucción del muelle y terminal IBRD / 87980 ort in participating municipal Posterior Open - National 1 Envelope proce 1,700,000.00 0.00 2022-11-03 2022-11-08 2022-12-20 2023-01-19 2023-02-23 s nvelope endiente 3 portuario No. 2 ities ss (Non Bank-SPD ) National Procure PTSP-BIRF8798-092 / Constr Improving Waterway Transp ment Document - Solicitud de oferta Single Stage - One E Ejecución p 2023-12-1 ucción del muelle y terminal IBRD / 87980 ort in participating municipal Posterior Open - National 1 Envelope proce 1,700,000.00 0.00 2022-12-22 2022-12-27 2023-02-07 2023-03-09 2023-04-13 s nvelope endiente 1 portuario No. 3 ities ss (Non Bank-SPD ) National Procure PTSP-BIRF8798-094 / Constr Improving Waterway Transp ment Document - Solicitud de oferta Single Stage - One E Ejecución p 2023-12-0 ucción del muelle y terminal IBRD / 87980 ort in participating municipal Posterior Open - National 1 Envelope proce 1,700,000.00 0.00 2022-12-15 2022-12-20 2023-01-31 2023-03-02 2023-04-06 s nvelope endiente 4 portuario No. 4 ities ss (Non Bank-SPD ) National Procure PTSP-BIRF8798-095 / Constr Improving Waterway Transp ment Document - Solicitud de oferta Single Stage - One E Ejecución p 2023-12-0 ucción del muelle y terminal IBRD / 87980 ort in participating municipal Posterior Open - National 1 Envelope proce 1,700,000.00 0.00 2022-12-12 2022-12-17 2023-01-28 2023-02-27 2023-04-03 s nvelope endiente 1 portuario No. 5 ities ss (Non Bank-SPD ) National Procure PTSP-BIRF8798-096 / Constr Improving Waterway Transp ment Document - Solicitud de oferta Single Stage - One E Ejecución p 2023-12-2 ucción del muelle y terminal IBRD / 87980 ort in participating municipal Posterior Open - National 1 Envelope proce 1,700,000.00 0.00 2023-01-05 2023-01-10 2023-02-21 2023-03-23 2023-04-27 s nvelope endiente 5 portuario No. 6 ities ss (Non Bank-SPD ) National Procure PTSP-BIRF8798-098 / Obras Improving Water Supply and ment Document - Solicitud de oferta Single Stage - One E Ejecución p 2023-05-2 de optimización del acueduct IBRD / 87980 Sanitation Services in partici Posterior Open - National 1 Envelope proce 2,900,000.00 0.00 2022-02-02 2022-02-07 2022-03-21 2022-04-20 2022-05-25 s nvelope endiente 5 o de Timbiquí pating municipalities ss (Non Bank-SPD ) National Procure PTSP-BIRF8798-099 / Obras Improving Water Supply and ment Document - Solicitud de oferta Single Stage - One E Ejecución p 2023-07-0 de optimización del acueduct IBRD / 87980 Sanitation Services in partici Posterior Open - National 1 Envelope proce 2,900,000.00 0.00 2022-03-17 2022-03-22 2022-05-03 2022-06-02 2022-07-07 s nvelope endiente 7 o de Francisco Pizarro pating municipalities ss (Non Bank-SPD ) National Procure Improving Water Supply and ment Document - PTSP-BIRF8798-100 / Obra al Solicitud de oferta Single Stage - One E Ejecución p 2024-06-1 IBRD / 87980 Sanitation Services in partici Posterior Open - National 1 Envelope proce 3,200,000.00 0.00 2022-10-21 2022-10-26 2022-12-07 2023-01-06 2023-02-10 cantarillado de Timbiquí s nvelope endiente 0 pating municipalities ss (Non Bank-SPD ) National Procure PTSP-BIRF8798-101 / Obra al Improving Water Supply and ment Document - Solicitud de oferta Single Stage - One E Ejecución p 2024-06-1 cantarillado de Francisco Piza IBRD / 87980 Sanitation Services in partici Posterior Open - National 1 Envelope proce 3,200,000.00 0.00 2022-10-21 2022-10-26 2022-12-07 2023-01-06 2023-02-10 s nvelope endiente 0 rro pating municipalities ss (Non Bank-SPD ) National Procure PTSP-BIRF8798-088 / Constr Improving Waterway Transp ment Document - Solicitud de oferta Single Stage - One E Ejecución p 2023-09-0 ucción del muelle y terminal IBRD / 87980 ort in participating municipal Posterior Open - National 1 Envelope proce 2,761,617.00 0.00 2022-08-15 2022-08-20 2022-10-01 2022-10-31 2022-12-05 s nvelope endiente 1 portuario del municipio de La ities ss (Non Bank-SPD Tola (Nariño) ) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Capacity Building and Institu PTSP-BIRF8798-0052 / Adqui tional Strengthening for wat Solicitud de cotiza Single Stage - One E rir motobombas y accesorios IBRD / 87980 erway transport operators a Posterior Open - National 198,804.00 187,812.81 Firmado 2020-07-13 2020-09-07 2020-11-03 2020-10-07 ciones nvelope hidráulicos nd water supply and sanitati on service providers in parti cipating municipalities Capacity Building and Institu PTSP-BIRF8798-0053 / Adqui tional Strengthening for wat Solicitud de cotiza Single Stage - One E rir tanques para almacenami IBRD / 87980 erway transport operators a Posterior Open - National 246,330.00 19,321.73 Firmado 2020-07-13 2020-09-07 2020-11-20 2020-10-07 ciones nvelope ento de agua nd water supply and sanitati on service providers in parti cipating municipalities Capacity Building and Institu PTSP-BIRF8798-0056 / Adqui tional Strengthening for wat Solicitud de cotiza Single Stage - One E rir filtros purificadores de ag IBRD / 87980 erway transport operators a Posterior Open - National 100,274.00 51,899.67 Firmado 2020-07-13 2020-09-07 2020-11-11 2020-10-22 ciones nvelope ua nd water supply and sanitati on service providers in parti cipating municipalities Page 1 Capacity Building and Institu PTSP-BIRF8798-0054 / Adqui tional Strengthening for wat Solicitud de cotiza Single Stage - One E rir plantas de tratamiento de IBRD / 87980 erway transport operators a Posterior Open - National 140,278.00 120,485.00 Firmado 2020-07-13 2020-09-07 2020-10-30 2020-11-06 ciones nvelope agua potable portátiles nd water supply and sanitati on service providers in parti cipating municipalities NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PTSP-BIRF8798-010 / Interve Improving Waterway Transp ntoría de la Ejecución de Obr Selección basada Open - Internationa IBRD / 87980 ort in participating municipal Posterior 1,326,080.00 0.00 Cancelado 2020-01-27 2020-02-17 2020-04-01 2020-04-29 2020-05-29 2020-07-03 2020-08-07 2021-08-07 as de muelles, Obras de Señ en calidad y costo l ities alización y Seguridad en Nav egación PTSP-BIRF8798-011 / Imple Project Management and En Selección basada mentación del plan de inform IBRD / 87980 vironmental and Social Mana Posterior en calificaciones d Open - National 100,000.00 0.00 Cancelado 2020-02-03 2020-02-24 2020-04-08 2020-05-08 2020-06-12 2020-12-09 ación, comunicación y partici gement e consultores pación PTSP-BIRF8798-012 / Actuali Improving Water Supply and Selección basada zacion de estudios Acueduct IBRD / 87980 Sanitation Services in partici Posterior en calificaciones d Open - National 74,600.00 0.00 Cancelado 2020-01-27 2020-02-17 2020-04-01 2020-05-01 2020-06-05 2020-12-02 o Francisco Pizarro pating municipalities e consultores PTSP-BIRF8798-014 / Interve Improving Water Supply and Selección basada ntoria Obras Alcantarillado Fr IBRD / 87980 Sanitation Services in partici Posterior Open - National 275,138.00 0.00 Cancelado 2020-01-13 2020-02-03 2020-03-18 2020-04-15 2020-05-15 2020-06-19 2020-07-24 2021-01-20 en el menor costo ancisco Pizarro pating municipalities PTSP-BIRF8798-015 / Actuali Improving Water Supply and Selección basada zacion de estudios Alcantarill IBRD / 87980 Sanitation Services in partici Posterior Open - National 275,138.00 0.00 Cancelado 2020-01-20 2020-02-10 2020-03-25 2020-04-22 2020-05-22 2020-06-26 2020-07-31 2021-01-27 en el menor costo ado Francisco Pizarro pating municipalities PTSP-BIRF8798-017 / Interve Improving Water Supply and Selección basada ntoría obras Acueducto Timbi IBRD / 87980 Sanitation Services in partici Posterior Open - National 323,690.00 0.00 Cancelado 2020-01-20 2020-02-10 2020-03-25 2020-04-22 2020-05-22 2020-06-26 2020-07-31 2021-01-27 en el menor costo quí pating municipalities PTSP-BIRF8798-018 / Actuali Improving Water Supply and Selección basada zacion de estudios Alcantarill IBRD / 87980 Sanitation Services in partici Posterior Open - National 302,814.00 0.00 Cancelado 2020-01-20 2020-02-10 2020-03-25 2020-04-22 2020-05-22 2020-06-26 2020-07-31 2021-01-27 en el menor costo ado Timbiquí pating municipalities PTSP-BIRF8798-019 / Interve Improving Water Supply and Selección basada ntoría obras Alcantarillado Ti IBRD / 87980 Sanitation Services in partici Posterior Open - National 275,285.00 0.00 Cancelado 2020-01-27 2020-02-17 2020-04-01 2020-04-29 2020-05-29 2020-07-03 2020-08-07 2021-02-03 en el menor costo mbiquí pating municipalities Capacity Building and Institu tional Strengthening for wat PTSP-BIRF8798-020 / Fortale Selección basada Open - Internationa IBRD / 87980 erway transport operators a Posterior 700,000.00 0.00 Cancelado 2020-02-17 2020-03-09 2020-04-22 2020-05-20 2020-06-19 2020-07-24 2020-08-28 2021-08-28 cimiento institucional en calidad y costo l nd water supply and sanitati on service providers in parti cipating municipalities PTSP-BIRF8798-021 / Actuali Capacity Building and Institu zacion de planes maestros d tional Strengthening for wat Selección basada Open - Internationa e acueducto para Olaya Herr IBRD / 87980 erway transport operators a Posterior 900,000.00 0.00 Cancelado 2020-02-24 2020-03-16 2020-04-29 2020-05-27 2020-06-26 2020-07-31 2020-09-04 2021-09-04 en calidad y costo l era, La Tola, Mosquera, Franc nd water supply and sanitati isco Pizarro, Lopez de Micay on service providers in parti and Santa Barbara de Iscuan cipating municipalities de PTSP-BIRF8798-022 / Interve Improving Water Supply and Selección basada ntoría Actualizacion de estudi IBRD / 87980 Sanitation Services in partici Posterior en calificaciones d Open - National 5,425.00 0.00 Cancelado 2020-01-27 2020-02-17 2020-04-01 2020-05-01 2020-06-05 2020-12-02 os Acueducto Francisco Pizar pating municipalities e consultores ro PTSP-BIRF8798-023 / Interve Improving Water Supply and Selección basada ntoría Actualizacion de estudi IBRD / 87980 Sanitation Services in partici Posterior en calificaciones d Open - National 8,447.00 0.00 Cancelado 2020-01-20 2020-02-10 2020-03-25 2020-04-24 2020-05-29 2020-11-25 os Acueducto Timbiquí pating municipalities e consultores PTSP-BIRF8798-024 / Interve Improving Water Supply and Selección basada ntoría Actualizacion de estudi IBRD / 87980 Sanitation Services in partici Posterior en calificaciones d Open - National 22,011.00 0.00 Cancelado 2020-02-03 2020-02-24 2020-04-08 2020-05-08 2020-06-12 2020-12-09 os Alcantarillado Francisco pi pating municipalities e consultores zarro PTSP-BIRF8798-025 / Interve Improving Water Supply and Selección basada ntoría Actualizacion de estudi IBRD / 87980 Sanitation Services in partici Posterior en calificaciones d Open - National 24,225.00 0.00 Cancelado 2020-02-10 2020-03-02 2020-04-15 2020-05-15 2020-06-19 2020-12-16 os Alcantarillado Timbiquí pating municipalities e consultores PTSP-BIRF8798-026 / Evalua Project Management and En Selección basada IBRD / 87980 Posterior Open - National 174,000.00 0.00 Cancelado 2021-02-22 2021-03-15 2021-04-28 2021-05-26 2021-06-25 2021-07-30 2021-09-03 2022-09-03 ción de medio término y final vironmental and Social Mana en calidad y costo gement PTSP-BIRF8798-008 / Estudio Improving Waterway Transp Selección basada Open - Internationa s y Diseños definitivos para l IBRD / 87980 ort in participating municipal Previa 1,169,532.00 925,315.06 Firmado 2020-05-19 2020-06-15 2020-06-09 2020-07-08 2020-07-08 2020-09-21 2020-08-05 2020-11-20 2020-08-20 2021-01-29 2020-09-24 2021-06-01 2020-10-18 2021-10-08 2021-10-18 en calidad y costo l os muelles y señalización ities PTSP-BIRF8798-009 / Interve Improving Waterway Transp Selección basada ntoría de Estudios de muelles IBRD / 87980 ort in participating municipal Posterior en calificaciones d Open - National 350,763.00 0.00 Cancelado 2020-05-19 2020-06-24 2020-06-09 2020-07-23 2020-08-22 2020-10-05 2021-10-05 y estudios de señalización ities e consultores PTSP-BIRF8798-0009 / Interv Improving Waterway Transp Selección basada entoría de Estudios y Diseños IBRD / 87980 ort in participating municipal Posterior Open - National 350,763.00 191,593.71 Firmado 2020-07-07 2020-07-06 2020-07-28 2020-09-10 2020-09-10 2020-10-08 2020-11-09 2020-11-07 2021-01-29 2020-12-12 2021-02-22 2021-01-16 2021-10-08 2022-01-16 en calidad y costo de Muelles y señalización ities PTSP-BIRF8798-0058 / Interv entoría técnica, administrativ Improving Waterway Transp a, financiera, legal, ambienta Selección basada IBRD / 87980 ort in participating municipal Posterior Open - National 230,726.00 0.00 Cancelado 2020-07-21 2020-07-18 2020-08-11 2020-09-24 2020-10-22 2020-11-21 2020-12-26 2021-01-30 2021-10-27 l y social de la construcción d en calidad y costo ities el muelle y terminal portuari o en el municipio de La Tola ( Nariño) Page 2 PTSP-BIRF8798-0059 / Cons ultoría para la estructuración Capacity Building and Institu del modelo de administració tional Strengthening for wat Selección basada n, operación y mantenimient erway transport operators a IBRD / 87980 Posterior en calificaciones d Open - National 101,414.00 71,457.54 Firmado 2020-07-21 2020-07-18 2020-08-11 2020-09-24 2020-10-06 2020-10-24 2022-01-18 2020-11-28 2022-01-18 2021-05-27 o de los terminales portuario nd water supply and sanitati e consultores s fluviales de los municipios on service providers in parti del Pacífico sur de Colombia, cipating municipalities con aplicación piloto en el m unicipio de La Tola (Nariño). PTSP-BIRF8798-0057 / Actua Improving Water Supply and Selección basada lización, ajuste y complemen IBRD / 87980 Sanitation Services in partici Posterior en calificaciones d Open - National 100,013.00 129,170.81 Firmado 2020-09-30 2020-10-21 2020-10-15 2020-11-22 2021-02-16 2020-12-07 2021-06-10 2021-01-11 2021-06-10 2021-07-10 tación de los estudios y diseñ pating municipalities e consultores os acueducto Francisco Pizar ro PTSP-BIRF8798-072 / CONSU LTORÍA PARA LA ELABORACI ÓN DE LOS ESTUDIOS Y DISE Improving Water Supply and Selección basada ÑOS DEL SISTEMA DE ALCAN IBRD / 87980 Sanitation Services in partici Posterior en calificaciones d Open - National 172,700.00 0.00 En ejecución 2021-03-24 2021-05-06 2021-04-08 2021-05-16 2021-05-31 2021-07-05 2022-03-02 TARILLADO DE LA CABECERA pating municipalities e consultores URBANA DEL MUNICIPIO DE T IMBIQUÍ, DEPARTAMENTO DE L CAUCA PTSP-BIRF8798-073 / CONSU LTORÍA PARA LA ELABORACI ÓN DE LOS ESTUDIOS Y DISE Improving Water Supply and Selección basada ÑOS DEL SISTEMA DE ALCAN IBRD / 87980 Sanitation Services in partici Posterior en calificaciones d Open - National 184,250.00 0.00 En ejecución 2021-03-24 2021-05-20 2021-04-08 2021-05-16 2021-05-31 2021-07-05 2022-03-02 TARILLADO DE LA CABECERA pating municipalities e consultores URBANA DEL MUNICIPIO DE F RANCISCO PIZARRO, DEPART AMENTO DE NARIÑO PTSP-BIRF8798-074 / PREST AR LOS SERVICIOS DE INTER VENTORÍA (SUPERVISIÓN) TÉ CNICA, ADMINISTRATIVA, FIN Improving Water Supply and ANCIERA, LEGAL, AMBIENTAL Selección basada IBRD / 87980 Sanitation Services in partici Posterior Open - National 93,030.00 0.00 Cancelado 2021-03-24 2021-04-14 2021-05-18 2021-05-23 2021-06-07 2021-06-22 2021-07-18 2022-04-22 Y SOCIAL PARA LOS ESTUDIO en calidad y costo pating municipalities S Y DISEÑOS DE LOS SISTEM AS DE ALCANTARILLADO DE LOS MUNICIPIOS DE TIMBIQUÍ , DEPARTAMENTO DEL CAUC A, Y FRANCISCO PIZARRO, D PTSP-BIRF8798-078 / Prestar los servicios de interventoría (supervisión) técnica, admini Improving Water Supply and strativa, financiera, legal, am Selección basada IBRD / 87980 Sanitation Services in partici Posterior Open - National 46,512.00 0.00 Cancelado 2021-05-13 2021-06-03 2021-07-07 2021-07-12 2021-07-27 2021-08-11 2021-09-06 2022-06-11 biental y social para los estu en calidad y costo pating municipalities dios y diseños del sistema de alcantarillado en los municipi os del pacifico sur de los dep artamentos de cauca y nariñ o. PTSP-BIRF8798-080 / PREST AR LOS SERVICIOS DE INTER VENTORÍA (SUPERVISIÓN) TÉ CNICA, ADMINISTRATIVA, FIN Improving Water Supply and Selección basada ANCIERA, LEGAL, AMBIENTAL IBRD / 87980 Sanitation Services in partici Posterior en calificaciones d Open - National 60,550.00 0.00 En ejecución 2021-05-25 2021-06-09 2021-06-09 2021-07-19 2021-10-01 2021-08-03 2021-10-28 2021-09-01 2022-05-29 Y SOCIAL PARA LOS ESTUDIO pating municipalities e consultores S Y DISEÑOS DE LOS SISTEM AS DE ALCANTARILLADO DE LOS MUNICIPIOS DE TIMBIQUÍ , DTO DEL CAUCA, Y FRANCIS CO PIZARRO DTO NARIÑO. PTSP-BIRF8798-082 / PREST AR LOS SERVICIOS DE INTER VENTORÍA (SUPERVISIÓN) TÉ CNICA, ADMINISTRATIVA, FIN Improving Water Supply and ANCIERA, LEGAL, AMBIENTAL Selección basada Open - Internationa IBRD / 87980 Sanitation Services in partici Previa 1,640,447.00 0.00 En ejecución 2021-07-12 2021-10-04 2021-07-16 2021-12-07 2021-08-14 2022-04-06 2021-09-27 2021-10-12 2021-11-16 2021-12-10 2023-12-15 , SOCIAL Y DE SEGURIDAD Y en calidad y costo l pating municipalities SALUD EN EL TRABAJO PARA LOS ESTUDIOS, DISEÑOS Y O BRAS DE LOS SISTEMAS DE A CUEDUCTO Y ALCANTARILLA DO EN LOS MUNICIPIOS DEL PTSP-BIRF8798-089 / Interve ntoría técnica, administrativa Improving Waterway Transp , financiera, legal, ambiental Selección basada Open - Internationa IBRD / 87980 ort in participating municipal Posterior 430,000.00 0.00 En ejecución 2022-03-16 2022-04-23 2022-04-06 2022-05-20 2022-06-17 2022-07-17 2022-08-21 2022-09-25 2023-07-25 y social de la construcción de en calidad y costo l ities l muelle y terminal portuario en el municipio de La Tola (N ariño) PTSP-BIRF8798-093 / Interve ntoría técnica, administrativa Improving Waterway Transp Selección basada Open - Internationa Ejecución pendien , financiera, legal, ambiental IBRD / 87980 ort in participating municipal Posterior 950,000.00 0.00 2022-10-12 2022-11-02 2022-12-16 2023-01-13 2023-02-12 2023-03-19 2023-04-23 2024-02-23 en calidad y costo l te y social de la construcción de ities l muelle y terminal portuario 1, 2 y 3 PTSP-BIRF8798-097 / Interve ntoría técnica, administrativa Improving Waterway Transp Selección basada Open - Internationa Ejecución pendien , financiera, legal, ambiental IBRD / 87980 ort in participating municipal Posterior 950,000.00 0.00 2023-01-05 2023-01-26 2023-03-11 2023-04-08 2023-05-08 2023-06-12 2023-07-17 2024-05-17 en calidad y costo l te y social de la construcción de ities l muelle y terminal portuario 4, 5 y 6 PTSP-BIRF8798-102 / Estruct Capacity Building and Institu uración del esquema de pres tional Strengthening for wat Selección basada tación de los servicios públic IBRD / 87980 erway transport operators a Posterior Open - National 380,000.00 0.00 Cancelado 2022-03-17 2022-04-07 2022-05-21 2022-06-18 2022-07-18 2022-08-22 2022-09-26 2023-07-26 en calidad y costo os de acueducto, alcantarilla nd water supply and sanitati do \ aseo en Timbiquí on service providers in parti cipating municipalities PTSP-BIRF8798-111 / ESTRU Capacity Building and Institu CTURACIÓN DEL ESQUEMA D tional Strengthening for wat E PRESTACIÓN DE LOS SERVI Selección basada erway transport operators a CIOS PÚBLICOS DE ACUEDUC IBRD / 87980 Posterior en calificaciones d Open - National 285,000.00 0.00 En ejecución 2022-04-27 2022-08-01 2022-05-18 2022-07-01 2022-07-31 2022-09-04 2023-07-01 nd water supply and sanitati TO, ALCANTARILLADO Y ASE e consultores on service providers in parti O EN EL MUNICIPIO DE TIMBI cipating municipalities QUÍ, DEPARTAMENTO DEL CA UCA INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PTSP-BIRF8798-001 / Líder d Project Management and En IBRD / 87980 Posterior Individual Open 23,598.00 18,126.11 Firmado 2019-11-25 2020-01-02 2019-12-04 2021-01-08 2019-12-05 2021-01-28 2019-12-15 2020-02-07 2020-04-13 e Conectividad de Transporte vironmental and Social Mana gement PTSP-BIRF8798-028 / Especi Project Management and En IBRD / 87980 Posterior Individual Limited 17,032.00 0.00 Cancelado 2020-01-27 2020-01-28 2020-02-01 2020-02-08 2020-03-07 2020-07-05 alista Ambiental vironmental and Social Mana gement Page 3 PTSP-BIRF8798-029 / Enlace Project Management and En IBRD / 87980 Posterior Individual Open 7,759.00 0.00 Cancelado 2020-01-27 2020-01-28 2020-03-16 2020-03-23 2020-04-20 2020-08-18 Social de Conectividad de Tr vironmental and Social Mana ansporte gement PTSP-BIRF8798-030 / Enlace Project Management and En IBRD / 87980 Posterior Individual Open 7,759.00 0.00 Cancelado 2020-01-27 2020-01-28 2020-03-16 2020-03-23 2020-04-20 2020-08-18 Social de Conectividad de Tr vironmental and Social Mana ansporte gement PTSP-BIRF8798-031 / Apoyo Project Management and En Técnico del Componente de IBRD / 87980 vironmental and Social Mana Posterior Individual Limited 7,759.00 0.00 Cancelado 2020-01-31 2020-01-31 2020-02-05 2020-02-15 2020-03-06 2020-07-04 Conectividad de Transporte y gement Provisión de Agua PTSP-BIRF8798-032 / Apoyo Project Management and En Técnico del Componente de IBRD / 87980 vironmental and Social Mana Posterior Individual Limited 7,759.00 0.00 Cancelado 2020-01-31 2020-01-31 2020-02-05 2020-02-15 2020-03-10 2020-07-08 Conectividad de Transporte y gement Provisión de Agua PTSP-BIRF8798-033 / Especi Project Management and En IBRD / 87980 Posterior Individual Limited 17,032.00 10,993.59 Firmado 2020-01-31 2020-01-31 2020-02-05 2020-02-05 2020-02-15 2020-02-14 2020-03-10 2020-05-26 2020-07-08 alista de Conectividad de Tra vironmental and Social Mana nsporte gement PTSP-BIRF8798-034 / Viabiliz Project Management and En IBRD / 87980 Posterior Individual Limited 17,032.00 10,993.59 Firmado 2020-01-31 2020-01-31 2020-02-05 2020-03-16 2020-02-15 2020-04-15 2020-03-10 2020-05-26 2020-07-08 ador de Proyectos ante INVIA vironmental and Social Mana S gement PTSP-BIRF8798-035 / Especi Project Management and En alista en Agua y Saneamient IBRD / 87980 vironmental and Social Mana Posterior Individual Direct 17,302.00 39,247.38 Firmado 2020-02-26 2020-03-11 2020-03-04 2020-03-23 2020-03-09 2020-07-16 2020-03-19 2020-07-21 2020-07-17 o Básico - Recontratación JAI gement RO ALBERTO PÉREZ GÓMEZ PTSP-BIRF8798-036 / Directo Project Management and En ra Ejecutiva / Coordinadora d IBRD / 87980 vironmental and Social Mana Posterior Individual Direct 17,596.00 67,107.66 Firmado 2020-02-26 2020-02-26 2020-03-07 2020-03-06 2020-03-12 2020-03-10 2020-03-22 2020-03-18 2021-03-21 el Proyecto FTSP - Recontrata gement ción LUZ AMANDA PULIDO PTSP-BIRF8798-037 / Líder A Project Management and En mbiental - Recontratación RU IBRD / 87980 vironmental and Social Mana Posterior Individual Limited 15,009.00 57,644.82 Firmado 2020-02-27 2020-03-11 2020-03-03 2020-03-16 2020-03-08 2020-03-12 2020-03-18 2020-03-18 2021-03-17 TH ALEJANDRA CATACOLI JIM gement ENEZ PTSP-BIRF8798-038 / Líder Fi Project Management and En nanciera - Recontratación CL IBRD / 87980 vironmental and Social Mana Posterior Individual Direct 15,009.00 57,242.20 Firmado 2020-02-26 2020-02-26 2020-03-07 2020-03-06 2020-03-12 2020-03-16 2020-03-22 2020-03-18 2021-03-21 AUDIA AGUDELO SEDANO gement PTSP-BIRF8798-039 / Líder d Project Management and En e Adquisiciones - Recontrata IBRD / 87980 vironmental and Social Mana Posterior Individual Direct 15,009.00 57,242.20 Firmado 2020-02-26 2020-02-26 2020-03-07 2020-03-05 2020-03-12 2020-03-11 2020-03-22 2020-03-18 2021-03-21 ción ELKIN ADOLFO PINILLA C gement AÑÓN PTSP-BIRF8798-040 / Líder d Project Management and En e Seguridad - Recontratación IBRD / 87980 vironmental and Social Mana Posterior Individual Direct 15,009.00 57,242.09 Firmado 2020-02-26 2022-03-11 2020-03-07 2020-03-06 2020-03-12 2020-03-11 2020-03-22 2020-03-18 2021-03-21 WILSON LAVERDE FLÓREZ gement PTSP-BIRF8798-041 / Especi Project Management and En alista Financiera - Recontrata IBRD / 87980 vironmental and Social Mana Posterior Individual Direct 11,355.00 43,304.24 Firmado 2020-02-26 2020-02-26 2020-03-07 2020-03-10 2020-03-12 2020-03-12 2020-03-22 2020-03-18 2021-03-21 ción SANDRA LORENA PEÑA gement PTSP-BIRF8798-042 / Líder C Project Management and En omponente Agua y Saneamie IBRD / 87980 vironmental and Social Mana Posterior Individual Direct 37,523.00 57,644.82 Firmado 2020-03-24 2020-04-01 2020-04-03 2020-04-07 2020-04-08 2020-04-01 2020-04-18 2020-04-06 2021-04-18 nto Básico - Recontratación F gement ABIOLA IGUARAN ARAUJO PTSP-BIRF8798-043 / Líder S Project Management and En ocial - Recontratación KELLY IBRD / 87980 vironmental and Social Mana Posterior Individual Direct 15,009.00 57,666.59 Firmado 2020-04-06 2020-04-06 2020-04-16 2020-04-06 2020-04-21 2020-04-10 2020-05-01 2020-04-23 2021-04-30 LORENA RUIZ GARCIA gement PTSP-BIRF8798-044 / Especi Project Management and En alista de Adquisiciones BM - IBRD / 87980 vironmental and Social Mana Posterior Individual Direct 56,773.00 43,625.30 Firmado 2020-04-16 2020-02-14 2020-04-26 2020-04-10 2020-05-01 2020-04-15 2020-05-11 2020-05-04 2021-05-10 Recontratación JOHN MAURIC gement IO OTALVARO CORTES PTSP-BIRF8798-045 / Actuali zación, Ajustes y Complemen Improving Water Supply and Selección directa Ejecución pendien to de los Diseños para la Opti IBRD / 87980 Sanitation Services in partici Posterior Direct 69,865.00 0.00 2020-05-07 2020-05-17 2020-06-06 2020-09-19 de consultores te mización y Ampliación del Ac pating municipalities ueducto del Municipio de Tim biquí - Cauca PTSP-BIRF8798-046 / Especi Project Management and En IBRD / 87980 Posterior Individual Limited 11,355.00 0.00 Cancelado 2020-05-07 2020-05-07 2020-05-12 2020-06-02 2020-07-07 2021-01-03 alista de Planeación y Segui vironmental and Social Mana miento gement PTSP-BIRF8798-047 / Líder d Project Management and En e Conectividad - Recontrataci IBRD / 87980 vironmental and Social Mana Posterior Individual Direct 75,046.00 57,644.82 Firmado 2020-05-14 2020-06-12 2020-05-24 2020-05-22 2020-05-29 2020-06-04 2020-06-08 2020-06-08 2021-06-07 ón DIEGO FERNANDO DUQUE gement BASTIDAS PTSP-BIRF8798-052 / Líder d Project Management and En Ejecución pendien IBRD / 87980 Posterior Individual Limited 15,009.00 0.00 2020-06-24 2020-07-04 2020-07-09 2020-07-19 2021-07-18 e Planeación y Seguimiento vironmental and Social Mana te gement PTSP-BIRF8798-048 / Interve ntoría de Estudios y Diseños Improving Water Supply and Acueducto y Alcantarillado d IBRD / 87980 Sanitation Services in partici Posterior Individual Direct 13,932.00 12,466.75 Firmado 2020-06-12 2020-07-09 2020-06-22 2020-07-15 2020-07-02 2020-07-27 2020-07-17 2020-08-26 2021-07-16 e Timbiquí y Francisco Pizarr pating municipalities o - Director de Interventoría PTSP-BIRF8798-049 / Interve ntoría de Estudios y Diseños Improving Water Supply and Acueducto y Alcantarillado d IBRD / 87980 Sanitation Services in partici Posterior Individual Direct 4,917.00 4,509.25 Firmado 2020-06-12 2020-07-09 2020-06-22 2020-07-15 2020-07-02 2020-07-27 2020-07-17 2020-08-26 2021-07-16 e Timbiquí y Francisco Pizarr pating municipalities o - Especialista Electromecán ico PTSP-BIRF8798-050 / Interve ntoría de Estudios y Diseños Improving Water Supply and Acueducto y Alcantarillado d IBRD / 87980 Sanitation Services in partici Posterior Individual Direct 8,072.00 7,294.38 Firmado 2020-06-12 2020-07-09 2020-06-22 2020-07-15 2020-07-02 2020-07-27 2020-07-17 2020-08-26 2021-07-16 e Timbiquí y Francisco Pizarr pating municipalities o - Especialista Estructural PTSP-BIRF8798-051 / interve ntoría de Estudios y Diseños Improving Water Supply and Acueducto y Alcantarillado d IBRD / 87980 Sanitation Services in partici Posterior Individual Direct 5,818.00 5,263.20 Firmado 2020-06-04 2020-07-09 2020-06-14 2020-07-15 2020-06-24 2020-07-24 2020-07-09 2020-08-26 2021-07-08 e Timbiquí y Francisco Pizarr pating municipalities o - Especialista Geotécnia Page 4 PTSP-BIRF8798-061 / AUDIT ORÍA DE LOS ESTADOS FINA NCIEROS DE PROPÓSITO ESP Project Management and En ECIAL Y ASEGURAMIENTO RA Selección directa IBRD / 87980 vironmental and Social Mana Posterior Direct 10,200.00 20,172.50 Firmado 2020-10-19 2020-11-05 2020-11-08 2020-11-19 2021-01-08 2021-02-19 2021-07-07 ZONABLE SOBRE LOS PROCE de consultores gement SOS DE ADQUISICIONES DEL PROYECTO/PROGRAMA FINA NCIADO POR EL BID Y EL BAN CO MUNDIAL A TRAVÉS DE P RÉSTAMOS PTSP-BIRF8798-062 / Directo Project Management and En ra Ejecutiva / Coordinadora d IBRD / 87980 vironmental and Social Mana Posterior Individual Direct 12,900.00 62,078.79 Firmado 2021-02-26 2021-03-15 2021-03-08 2021-03-15 2021-03-13 2021-03-13 2021-03-18 2021-03-18 2022-03-17 el Proyecto FTSP - Recontrata gement ción LUZ AMANDA PULIDO PTSP-BIRF8798-063 / Líder C Project Management and En omponente Agua y Saneamie IBRD / 87980 vironmental and Social Mana Posterior Individual Direct 27,500.00 52,952.63 Firmado 2021-03-01 2021-03-15 2021-03-11 2021-03-15 2021-03-16 2021-03-16 2021-04-08 2021-04-08 2022-04-07 nto Básico - Recontratación F gement ABIOLA IGUARAN ARAUJO PTSP-BIRF8798-064 / Líder d Project Management and En e Adquisiciones - Recontrata IBRD / 87980 vironmental and Social Mana Posterior Individual Direct 11,000.00 52,952.63 Firmado 2021-02-26 2021-03-15 2021-03-08 2021-03-15 2021-03-13 2021-03-16 2021-03-18 2021-03-18 2022-03-17 ción ELKIN ADOLFO PINILLA C gement AÑÓN PTSP-BIRF8798-065 / Líder Fi Project Management and En nanciera - Recontratación CL IBRD / 87980 vironmental and Social Mana Posterior Individual Direct 11,000.00 52,952.63 Firmado 2021-02-26 2021-03-15 2021-03-08 2021-03-15 2021-03-13 2021-03-13 2021-03-18 2021-03-18 2022-03-17 AUDIA AGUDELO SEDANO gement PTSP-BIRF8798-066 / Líder S Project Management and En ocial - Recontratación KELLY IBRD / 87980 vironmental and Social Mana Posterior Individual Direct 11,000.00 52,952.63 Firmado 2021-03-19 2021-03-15 2021-03-29 2021-03-29 2021-04-03 2021-04-03 2021-04-23 2021-04-23 2022-04-22 LORENA RUIZ GARCIA gement PTSP-BIRF8798-067 / Líder d Project Management and En e Seguridad - Recontratación IBRD / 87980 vironmental and Social Mana Posterior Individual Direct 11,000.00 52,952.63 Firmado 2021-02-26 2021-03-15 2021-03-08 2021-03-18 2021-03-13 2021-03-18 2021-03-22 2021-03-23 2022-03-21 WILSON LAVERDE FLÓREZ gement PTSP-BIRF8798-068 / Contra tación Líder Ambiental para l a ejecución y cumplimiento d Project Management and En Selección directa e los Marcos de Gestión Ambi IBRD / 87980 vironmental and Social Mana Posterior Direct 5,496.00 26,476.31 Firmado 2021-03-08 2021-03-15 2021-03-09 2021-03-15 2021-03-22 2021-03-23 2021-09-21 de consultores ental adoptados para la ejec gement ución del Fondo para el desar rollo del Plan Todos Somos P AZcífico - Fernando Rey PTSP-BIRF8649-070 / Especi Project Management and En alista Financiera - Recontrata IBRD / 87980 vironmental and Social Mana Posterior Individual Direct 8,315.00 40,059.14 Firmado 2021-03-08 2021-03-15 2021-03-09 2021-03-15 2021-03-14 2021-03-16 2021-03-18 2021-03-18 2022-03-17 ción Sandra Lorena Peña gement PTSP-BIRF8649-069 / Especi Project Management and En Selección directa alista de Adquisiciones - Cont IBRD / 87980 vironmental and Social Mana Posterior Direct 20,079.00 40,059.14 Firmado 2021-03-08 2021-03-15 2021-03-09 2021-03-15 2021-03-15 2021-03-16 2022-03-14 de consultores ratación Tulio José Fuentes gement PTSP-BIRF8649-071 / Especi alista de Planeación y Segui miento. - Brindar apoyo profe Project Management and En sional en la gestión de planifi IBRD / 87980 vironmental and Social Mana Posterior Individual Open 10,394.00 18,200.98 Firmado 2021-03-11 2021-03-15 2021-03-16 2021-03-22 2021-03-17 2021-03-18 2021-03-25 2021-03-26 2021-09-24 cación, monitoreo y seguimie gement nto a las actividades del Fon do para el Desarrollo del Plan Todos Somos Pazcífico. PTSP-BIRF8798-075 / Contra tación Líder Fortalecimiento I nstitucional para Liderar la i Project Management and En Selección directa mplementación y ejecución d IBRD / 87980 vironmental and Social Mana Posterior Direct 5,496.00 0.00 Cancelado 2021-04-14 2021-04-19 2021-05-17 2021-11-16 de consultores e los componentes de Capaci gement dad y Fortalecimiento Institu cional de Agua y Saneamient o Básico - Jorge Silva PTSP-BIRF8798-076 / Contra tación Líder Fortalecimiento I nstitucional para Liderar la i Project Management and En mplementación y ejecución d IBRD / 87980 vironmental and Social Mana Posterior Individual Direct 5,496.00 26,476.31 Firmado 2021-04-15 2021-04-19 2021-04-22 2021-04-22 2021-04-23 2021-04-23 2021-05-17 2021-05-11 2021-11-16 e los componentes de Capaci gement dad y Fortalecimiento Institu cional de Agua y Saneamient o Básico para el desarrollo de l Plan Todos Somos PAZcífico - Jorge Silva. PTSP-BIRF8798-077 / Especi Project Management and En alista de Adquisiciones - Rec IBRD / 87980 vironmental and Social Mana Posterior Individual Direct 8,315.00 40,059.14 Firmado 2021-04-22 2021-04-26 2021-04-24 2021-04-26 2021-04-26 2021-04-26 2021-05-04 2021-05-06 2022-05-03 ontratación JOHN MAURICIO gement OTÁLVARO CORTÉS PTSP-BIRF8798-079 / Líder d Project Management and En e Conectividad - Recontrataci IBRD / 87980 vironmental and Social Mana Posterior Individual Direct 54,958.00 52,952.63 Firmado 2021-05-18 2021-05-26 2021-05-20 2021-05-26 2021-05-24 2021-05-24 2021-06-08 2021-06-08 2022-06-07 ón DIEGO FERNANDO DUQUE gement BASTIDAS PTSP-BIRF8798-081 / Líder d Project Management and En e Planeación y Seguimiento IBRD / 87980 vironmental and Social Mana Posterior Individual Direct 10,992.00 52,952.63 Firmado 2021-06-09 2021-06-10 2021-06-19 2021-06-19 2021-06-24 2021-06-24 2021-06-30 2021-06-30 2022-06-29 - Recontratación Joan Natalie gement Garzón PTSP-BIRF8798-083 / AUDIT ORÍA DE LOS ESTADOS FINA NCIEROS DE PROPÓSITO ESP ECIAL Y ASEGURAMIENTO Project Management and En Selección directa RAZONABLE SOBRE LOS PRO IBRD / 87980 vironmental and Social Mana Posterior Direct 21,808.00 19,036.57 Firmado 2021-09-06 2021-09-15 2021-09-26 2021-10-04 2021-12-23 2022-01-31 2022-06-21 de consultores CESOS DE ADQUISICIONES D gement EL PROYECTO/PROGRAMA FI NANCIADO POR EL BID Y EL B ANCO MUNDIAL A TRAVÉS DE PRÉSTAMOS PTSP-BIRF8798-084 / Líder A Project Management and En mbiental FTSP - Recontrataci IBRD / 87980 vironmental and Social Mana Posterior Individual Direct 5,935.00 26,476.31 Firmado 2021-09-09 2021-09-09 2021-09-09 2021-09-09 2021-09-20 2021-09-20 2021-09-23 2021-09-23 2022-03-22 ón Fernando Rey gement PTSP-BIRF8798-085 / Especi Project Management and En alista de Planeación y Segui IBRD / 87980 vironmental and Social Mana Posterior Individual Direct 22,425.00 40,059.14 Firmado 2021-09-09 2021-09-09 2021-09-17 2021-09-17 2021-09-17 2021-09-17 2021-09-27 2021-09-28 2022-09-26 miento FTSP - Recontratación gement Natalia García Medina Capacity Building and Institu PTSP-BIRF8798-086 / Líder d tional Strengthening for wat e Fortalecimiento Institucion IBRD / 87980 erway transport operators a Posterior Individual Direct 11,870.00 52,952.63 Firmado 2021-10-19 2021-10-20 2021-10-19 2021-10-20 2021-10-26 2021-10-26 2021-11-11 2021-11-11 2022-11-10 al - Recontratación Jorge Ern nd water supply and sanitati esto Silva on service providers in parti cipating municipalities Page 5 PTSP-BIRF8798-087 / Líder S Project Management and En IBRD / 87980 Posterior Individual Open 14,837.00 24,066.33 Firmado 2021-10-27 2021-10-27 2021-11-30 2022-02-22 2021-12-03 2022-02-25 2021-12-22 2022-04-06 2022-06-19 ocial FTSP vironmental and Social Mana gement PTSP-BIRF8798-103 / Realiza r la evaluación de medio tér mino del proyecto “Mejora de Project Management and En la Conectividad y de la Provis IBRD / 87980 vironmental and Social Mana Posterior Individual Limited 12,545.00 0.00 En ejecución 2022-03-10 2022-03-01 2022-03-15 2022-04-05 2022-05-10 2022-08-11 ión de Agua en el Marco del gement Plan PAZcífico” en cumplimie nto de las condiciones establ ecidas en el Contrato de Prés tamo BIRF N° 8798-CO. PTSP-BIRF8798-104 / Recont Improving Water Supply and ratación Líder de Agua BM - F IBRD / 87980 Sanitation Services in partici Posterior Individual Direct 31,342.00 57,727.68 Firmado 2022-03-04 2022-03-04 2022-03-14 2022-03-04 2022-03-19 2022-03-09 2022-04-08 2022-04-08 2023-04-07 abiola del Rosario Iguarán pating municipalities PTSP-BIRF8798-106 / Recont Project Management and En ratación Líder de Adquisicion IBRD / 87980 vironmental and Social Mana Posterior Individual Direct 12,537.00 52,952.63 Firmado 2022-03-04 2022-03-04 2022-03-14 2022-03-14 2022-03-14 2022-03-14 2022-03-18 2022-03-18 2023-03-17 es - Élkin Pinilla gement PTSP-BIRF8798-107 / Recont Project Management and En ratación Líder Financiera - Cl IBRD / 87980 vironmental and Social Mana Posterior Individual Direct 12,537.00 52,952.63 Firmado 2022-03-04 2022-03-04 2022-03-14 2022-03-14 2022-03-16 2022-03-16 2022-03-18 2022-03-18 2023-03-17 audia Agudelo gement PTSP-BIRF8798-108 / Recont Project Management and En IBRD / 87980 Posterior Individual Direct 6,269.00 26,476.31 Firmado 2022-03-04 2022-03-04 2022-03-09 2022-03-09 2022-03-15 2022-03-15 2022-03-23 2022-03-23 2022-09-22 ratación Líder Ambiental - Fe vironmental and Social Mana rnando Rey gement PTSP-BIRF8798-110 / Recont Project Management and En ratación Especialista Financie IBRD / 87980 vironmental and Social Mana Posterior Individual Direct 9,484.00 0.00 Bajo Revision 2022-03-04 2022-03-04 2022-03-05 2022-03-10 2022-03-18 2023-03-17 ra - Sandra Lorena Peña gement PTSP-BIRF8798-105 / Recont Project Management and En ratación Directora Ejecutiva- IBRD / 87980 vironmental and Social Mana Posterior Individual Direct 14,698.00 62,078.79 Firmado 2022-03-04 2022-03-04 2022-03-14 2022-03-14 2022-03-15 2022-03-14 2022-03-18 2022-03-18 2023-03-17 Coordinadora General - Luz A gement manda Pulido PTSP-BIRF8798-109 / Recont Project Management and En ratación Especialista de Adqu IBRD / 87980 vironmental and Social Mana Posterior Individual Direct 23,711.00 43,671.56 Firmado 2022-03-10 2022-03-04 2022-03-20 2022-03-20 2022-03-20 2022-03-07 2022-03-26 2022-03-16 2023-03-25 isiciones - Tulio José Fuentes gement PTSP-BIRF8798-112 / Recont Project Management and En ratación Líder de Seguridad - IBRD / 87980 vironmental and Social Mana Posterior Individual Direct 5,935.00 0.00 En ejecución 2022-04-26 2022-05-05 2022-05-02 2022-05-02 2022-05-04 2022-05-05 2022-11-04 Wilson Laverde gement PTSP-BIRF8798-113 / Liderar los procesos de adquisicione s que adelanta la Unidad Nac ional para la Gestión del Ries Project Management and En go de Desastres como entida IBRD / 87980 vironmental and Social Mana Posterior Individual Limited 11,870.00 0.00 En ejecución 2022-05-23 2022-05-23 2022-05-28 2022-06-15 2022-06-02 2022-06-17 2023-06-16 d ejecutora del Fondo para el gement Desarrollo del Plan Todos So mos PAZcífico, según las Polí ticas, normas y regulaciones del BID y Banco M. PTSP-BIRF8798-114 / Liderar la planificación, estructuració Capacity Building and Institu n, seguimiento y gestión de l tional Strengthening for wat os proyectos de Conectividad erway transport operators a de Transporte que hagan par IBRD / 87980 Posterior Individual Direct 60,000.00 0.00 Bajo Revision 2022-05-27 2022-05-26 2022-05-29 2022-06-02 2022-06-07 2023-06-06 nd water supply and sanitati te del préstamo BIRF 8798 - on service providers in parti CO, ejecutado por la Unidad cipating municipalities Nacional para la Gestión del Riesgo de Desastres como en tidad ejecutora. PTSP-BIRF8798-115 / Liderar la planificación, monitoreo, s eguimiento y gestión de los p réstamos del BID y el Banco Project Management and En Ejecución pendien Mundial, ejecutados por la U IBRD / 87980 vironmental and Social Mana Posterior Individual Direct 11,870.00 0.00 2022-06-16 2022-06-17 2022-06-24 2022-06-29 2023-06-29 te nidad Nacional para la Gestió gement n del Riesgo de Desastres co mo entidad ejecutora del Fon do para el Desarrollo del Plan Todos Somos Pazc PTSP-BIRF8798-116 / Brindar apoyo profesional como Espe cialista de Adquisiciones en l Project Management and En os procesos que adelanta la IBRD / 87980 vironmental and Social Mana Posterior Individual Limited 20,979.00 0.00 En ejecución 2022-07-11 2022-07-19 2022-07-16 2022-08-06 2022-09-10 2023-03-09 Unidad Nacional para la Gesti gement ón del Riesgo de Desastres c omo entidad ejecutora del Fo ndo para el Desarrollo del Pla n Todos Somos PAZcífico. Page 6