Procurement Plan WASIS II Credit No.: IDA-57830 I. General 1. Bank’s approval Date of the procurement Plan [Original: December 2007]: Revision 15 of Updated Procurement Plan, June 2010] 2. Date of General Procurement Notice: Dec 24, 2006 3. Period covered by this procurement plan: June 2017 to December 2018 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ 1,500,000 All 2. NCB (Goods) Below US$ 1,500,000 None 3. ICB (Works) Above US$ 5 million All 4. NCB (Works) Below US$ 5 million None 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Not Applicable 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project XYZ 04/01/2010 issued by 5. Any Other Special Procurement Arrangements: [including advance procurement and retroactive financing, if applicable] 5 ICB works packages will be financed under retroactive financing 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Ref. No. Description Estimated Package Domestic Review Comments Cost s Preference by Bank US$ (yes/no) (Prior / million Post) FIPAG Summary of the ICB (Works) 22.43 2 No Prior FIPAG Summary of the NCB (Works) 8.90 2 No Post CRA/WASIS II/G 04/17, CRA/WASIS II/G 05/17, Summary of the NCB CRA/WASIS II/G-04/17 & (Goods) 0.295 4 Yes Post CRA/WASIS II/G 06/17 III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 500,000 2. Individual Above US$ 200,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: None 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Estimated Review Ref. No. Description of Assignment Cost Package by Bank Comments US$ million s (Prior / Post) FIPAG Summary of QCBS 9.42 6 Prior QCBS FIPAG Summary ICS 0.38 2 Prior and IND Post CRA/WASIS II/CON 03/17 Summary of QCBS 0.2 1 Prior QCBS CRA/WASIS II/CON 04/17 Summary of CQS 0.5 1 Prior CQS CRA/WASIS II/CON 07/17 CRA/WASIS II/CON 06/17 Summary ICS 0.20 3 Prior ICS CRA/WASIS II/ CON 05/17 PROCUREMENT Mozambique : Water Services & Institutional Support II PLAN General Information Country: Mozambique 2016-10-18 Bank’s Approval Date of the Original Procurement Plan: 2022-08-04 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P149377 GPN Date: Project Name: Water Services & Institutional Support II Loan / Credit No: IDA / 57830, IDA / D1100, IDA / D4910 Water Supply Asset Holding and Investment Fund Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned FIPAG/WASISII/W-2/15 / Desi Component 1: Rehabilitation gn and build for rehabilitatio and Expansion of Water Sup Open - Internationa Single Stage - One E 22,416,000.0 13,747,363. 2019-05-0 n of existing transmission ma IDA / 57830 Prior Request for Bids Signed 2016-10-17 2016-10-19 2016-10-17 2016-10-27 2016-10-17 2016-12-15 2016-10-17 2017-04-24 2017-04-03 2017-05-22 2017-07-06 2017-10-13 2017-10-31 ply Production and Distributi l nvelope 0 87 4 in and construction of 50 km on of transmission main DN 500 mm, Pemba FIPAG/WASISII/W-9/16 / Desi gn and build of 25km transmi Component 1: Rehabilitation ssion main, DN 350 mm to co and Expansion of Water Sup Open - Internationa Single Stage - One E 10,000,000.0 9,315,309.5 2019-11-0 IDA / 57830 Prior Request for Bids Signed 2017-01-10 2017-01-20 2017-05-29 2017-10-27 2017-07-12 2018-09-04 2017-02-14 2017-04-25 2017-10-09 2018-11-22 2017-11-24 2019-04-09 2018-04-12 2019-05-31 nnect Moatize to Tete system ply Production and Distributi l nvelope 0 1 1 and new pipeline from Nhart on anda to WTP, 1km, DN 500 m m, Tete FIPAG/WASISII/W-7/15 / Desi Component 1: Rehabilitation Single Stage - One E 6,185,997.9 2018-08-2 gn and construction of netwo IDA / 57830 and Expansion of Water Sup Post Request for Bids Open - National 7,763,000.00 Signed 2017-05-08 2017-07-24 2017-05-29 2017-07-24 2017-08-05 2017-10-06 2017-09-19 2017-12-19 2018-02-03 2018-03-14 nvelope 3 5 rk, Beira and Dondo ply Production and Distributi on Component 1: Rehabilitation FIPAG/WASISII/W-1/15 / Drilli Single Stage - One E 2018-01-0 IDA / 57830 and Expansion of Water Sup Post Request for Bids Open - National 1,134,000.00 722,843.63 Signed 2016-12-05 2017-04-25 2016-12-26 2017-05-10 2017-02-16 2017-07-05 2017-03-20 2017-08-29 2017-06-05 2017-12-13 ng Boreholes, Pemba nvelope 2 ply Production and Distributi on Component 1: Rehabilitation FIPAG/WASISII/W-8/18 / Drili Single Stage - One E 2019-02-0 IDA / 57830 and Expansion of Water Sup Post Request for Bids Open - National 1,323,000.00 789,850.46 Signed 2018-04-27 2018-04-13 2018-05-02 2018-04-13 2018-06-15 2018-05-25 2018-07-30 2018-07-10 2018-11-11 2018-09-26 ng boreholes, Tete nvelope 9 ply Production and Distributi on FIPAG/WASISII/W-12/18 / Des Component 1: Rehabilitation ign and build for rehabilitatio and Expansion of Water Sup Request for Quota Single Stage - One E 2,188,687.6 2018-12-2 IDA / 57830 Post Limited 1,500,000.00 Signed 2018-05-02 2018-10-16 2018-06-27 2019-01-29 n of the Mutua pumping stati ply Production and Distributi tions nvelope 6 4 on, Beira (emergency) on FIPAG/WASISII/W-3/19 / Elect Component 1: Rehabilitation romechanical equipment of b and Expansion of Water Sup Open - Internationa Single Stage - One E 19,600,000.0 13,724,398. 2021-10-1 oreholes, rehabilitation and c IDA / 57830 Prior Request for Bids Signed 2019-10-31 2020-04-23 2019-11-15 2020-05-05 2020-02-13 2020-07-15 2020-05-13 2020-09-23 2020-07-18 2020-12-07 ply Production and Distributi l nvelope 0 50 1 onstruction of Water Treatme on nt Plant and Pumping Station in Pemba FIPAG/WASISII/W-5/19 / Refu Component 1: Rehabilitation rbishment of existing treatm and Expansion of Water Sup Open - Internationa Single Stage - One E 18,100,000.0 12,986,588. 2022-08-3 ent system, including pre-tre IDA / 57830 Prior Request for Bids Signed 2019-11-20 2020-12-06 2019-12-05 2020-12-21 2020-03-04 2021-02-16 2020-06-02 2021-08-24 2020-08-31 2021-12-09 ply Production and Distributi l nvelope 0 47 1 atment canal, and rehabilitat on ion of the Dingue Dingue wat er intake in Beira FIPAG/WASISII/W-4/19 / Reh Component 1: Rehabilitation Open - Internationa Single Stage - One E 10,793,000.0 9,173,096.4 2022-07-3 abilitation and construction o IDA / 57830 and Expansion of Water Sup Prior Request for Bids Signed 2020-03-27 2020-07-17 2020-04-11 2020-07-24 2020-07-10 2020-09-22 2020-10-08 2021-01-26 2021-03-07 2021-04-01 l nvelope 0 0 0 f distribution centres and net ply Production and Distributi work in Pemba on FIPAG/DRIVE/W-1/19 / Desig Component 1: Rehabilitation n, rehabilitation and construc and Expansion of Water Sup Open - Internationa Single Stage - One E 25,050,000.0 2022-08-0 tion of intake, water treatme IDA / D4910 Prior Request for Bids 0.00 Canceled 2020-06-18 2020-07-03 2020-09-01 2020-11-30 2021-02-13 ply Production and Distributi l nvelope 0 7 nt, transmission main and pu on mping stations in Nacala FIPAG/DRIVE/W-2/19 / Desig Component 1: Rehabilitation n, Rehabilitation and Constru and Expansion of Water Sup Open - Internationa Single Stage - One E 17,550,000.0 2022-10-1 IDA / D4910 Prior Request for Bids 0.00 Canceled 2020-07-30 2020-08-14 2020-10-13 2021-01-11 2021-04-26 ction of Distribution Centers ply Production and Distributi l nvelope 0 8 and Network in Nacala on FIPAG/WASISII/EMERGENCY/ W-13/20 / Borehole equipme Component 4: Contingent E Open - Internationa Single Stage - One E 2021-03-1 IDA / 57830 Post Request for Bids 835,000.00 0.00 Canceled 2020-05-28 2020-06-02 2020-07-14 2020-08-13 2020-09-17 nt and construction of trans mergency Response l nvelope 6 mission mains in Moatize FIPAG/WASISII/EMERGENCY/ Component 1: Rehabilitation Single Stage - One E 2021-03-0 W-7A/20 / Rehabilitation of n IDA / 57830 and Expansion of Water Sup Post Request for Bids Open - National 837,885.00 0.00 Canceled 2020-05-13 2020-05-18 2020-06-29 2020-07-29 2020-09-02 nvelope 1 etwork in Beira and Dondo ply Production and Distributi on FIPAG/WASISII/W-10/22 / Exp Component 1: Rehabilitation Request for Bids - ansion of the wellfields, reha and Expansion of Water Sup Open - Internationa Single Stage - One E Works (without pr 15,000,000.0 Under Revie 2023-01-1 bilitation and expansion of th IDA / D4910 Prior Request for Bids 0.00 2022-04-01 2022-04-06 2022-05-18 2022-06-17 2022-07-22 ply Production and Distributi l nvelope equalification) SP 0 w 8 e water treatment plant and on D pumping stations, Tete and Moatize GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual FIPAG/IGP/G-2/17 / Supply of Component 2: Institutional S Request for Quota Single Stage - One E IDA / D1100 Post Limited 65,000.00 82,081.84 Signed 2017-08-27 2017-09-26 2017-11-23 2018-01-30 2017-12-23 IT equipment upport tions nvelope FIPAG/IGP/G-1/17 / Supply of Component 2: Institutional S Request for Quota Single Stage - One E IDA / D1100 Post Limited 35,000.00 46,398.49 Signed 2018-04-09 2018-06-04 2018-07-06 2019-04-15 2018-08-05 office furniture upport tions nvelope FIPAG/WASISII/G-3/18 / Purc Component 2: Institutional S Request for Quota Single Stage - One E IDA / D1100 Post Limited 65,000.00 0.00 Canceled 2018-11-05 2019-02-26 2019-08-25 hase of motorcycles for Tete upport tions nvelope and Moatize FIPAG/EMERGENCY/G-5/19 / Component 4: Contingent E Request for Quota Single Stage - One E Supply of sand for SSFs in Be IDA / 57830 Post Limited 136,750.00 654,353.83 Signed 2019-10-22 2019-09-09 2019-12-17 2019-11-29 2020-06-14 mergency Response tions nvelope ira, Quelimane, Manica and N ampula Page 1 FIPAG/EMERGENCY/G-2/19 / Supply of electrical and mec Component 4: Contingent E Request for Quota Single Stage - One E Under Imple IDA / 57830 Post Limited 1,237,110.00 0.00 2019-10-19 2019-08-26 2019-12-22 2020-06-19 hanical equipament for Beira mergency Response tions nvelope mentation and Dondo, Manica, FIPAG/EMERGENCY/G-4/19 / Component 4: Contingent E Request for Quota Single Stage - One E Supply of Chemicals (HTH, All IDA / 57830 Post Limited 310,000.00 276,357.72 Signed 2020-03-13 2019-07-22 2020-05-08 2019-10-12 2020-11-04 mergency Response tions nvelope uminium Sulphate and Lime) for Beira FIPAG/EMERGENCY/G-1/19 / Supply of Pipes and Fittings f Component 4: Contingent E Request for Quota Single Stage - One E IDA / 57830 Post Limited 1,006,820.00 259,651.56 Signed 2019-10-08 2019-08-15 2019-12-03 2019-11-13 2020-05-31 or Beira, Dondo, Manica, Tet mergency Response tions nvelope e, Moatize, Nampula and Moc uba FIPAG/WASISII/EMERGENCY/ G-6/20 / Supply of electrical a nd mechanical equipament f Component 4: Contingent E Request for Quota Single Stage - One E Under Imple IDA / 57830 Post Limited 1,230,000.00 0.00 2020-05-23 2020-07-18 2021-01-14 or Beira, Dondo, Manica, Chi mergency Response tions nvelope mentation moio, Gondola, Tete and Moa tize and Supply of pipes and fittings FIPAG/WASISII/EMERGENCY/ Component 4: Contingent E Request for Quota Single Stage - One E G-8/20 / Supply of Chemicals IDA / 57830 Post Limited 1,510,000.00 1,246,974.16 Signed 2020-05-17 2020-05-27 2020-07-12 2020-08-28 2021-01-08 mergency Response tions nvelope (HTH, Alluminium Sulphate a nd Lime) for Beira FIPAG/WASISII/EMERGENCY/ Component 4: Contingent E Pending Impl G-10/20 / Supply of Electricit IDA / 57830 Post Direct Selection Direct 550,967.74 0.00 2020-05-12 2020-05-17 2020-06-21 2020-12-18 mergency Response ementation y to Beira by EDM FIPAG/WASISII/EMERGENCY/ Component 4: Contingent E Request for Quota Single Stage - One E G-9/20 / Supply of Sand to Be IDA / 57830 Post Limited 636,707.00 528,158.71 Signed 2020-05-25 2020-05-27 2020-07-20 2020-08-28 2021-01-16 mergency Response tions nvelope ira, Quelimane, Manica and N ampula FIPAG/WAISIS II/G-15/20 / Su Component 2: Institutional S Single Stage - One E Pending Impl pply of equipment and goods IDA / D1100 Post Request for Bids Open - National 300,000.00 0.00 2020-09-21 2020-10-06 2020-12-05 2021-02-03 2021-05-04 2021-12-30 upport nvelope ementation for Nacala dam safety manag ement FIPAG/WASIS II/G-04/20 / Su Component 1: Rehabilitation pply of water meters & fitting and Expansion of Water Sup Open - Internationa Single Stage - One E IDA / 57830 Prior Request for Bids 2,650,000.00 2,904,085.26 Signed 2020-12-01 2021-02-12 2020-12-06 2021-02-17 2021-01-17 2021-04-30 2021-02-16 2021-11-10 2021-03-23 2022-06-20 2021-09-19 s for connections for Pemba, ply Production and Distributi l nvelope Nacala, Tete, Moatize, Beira on and Dondo Component 1: Rehabilitation FIPAG/WASISII/G-6/21 / Upgr Open - Internationa Single Stage - One E Under Imple IDA / 57830 and Expansion of Water Sup Post Request for Bids 315,000.00 0.00 2021-04-30 2022-02-18 2021-05-05 2022-02-19 2021-06-16 2022-04-06 2021-07-16 2021-08-20 2022-02-16 ade of Regional Laboratories l nvelope mentation ply Production and Distributi on FIPAG/WASISII/G-7/21 / Asset Component 1: Rehabilitation Single Stage - One E Pending Impl Management: Software, Mate IDA / 57830 and Expansion of Water Sup Post Request for Bids Limited 350,000.00 0.00 2021-06-24 2021-06-29 2021-08-10 2021-09-09 2021-10-14 2022-04-12 nvelope ementation rials and Equipment ply Production and Distributi on FIPAG/WASISII/G-8/21 / Supp Component 2: Institutional S Request for Quota Single Stage - One E Pending Impl IDA / D1100 Post Limited 50,000.00 0.00 2021-08-13 2022-01-16 2022-07-15 ly of IT Equipment upport tions nvelope ementation NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual FIPAG/WASISII/CON-3/17 / D Component 2: Institutional S Request for Quota Single Stage - One E IDA / D1100 Post Limited 150,000.00 64,350.68 Signed 2017-08-19 2017-08-23 2017-10-23 2017-10-30 2019-10-23 ocuments Translation Service upport tions nvelope s FIPAG/WASISII/CON-26/18 / Component 2: Institutional S Request for Quota Single Stage - One E IDA / D1100 Post Open - National 150,000.00 72,247.06 Signed 2018-10-20 2018-12-17 2018-12-14 2020-12-23 Document translation service upport tions nvelope s FIPAG/WASIS II/CON-36/20 / I mplementation of COVID-19 Component 2: Institutional S mitigation measures in the P IDA / D1100 Post Direct Selection Direct 624,774.00 715,004.07 Signed 2020-09-14 2020-09-14 2020-09-19 2020-09-16 2020-12-01 2020-10-28 2022-12-01 upport HC commercial management system by 2-Business FIPAG/WASISII/G-5/21 / Docu Component 2: Institutional S Request for Quota Single Stage - One E IDA / D1100 Post Limited 80,000.00 46,646.33 Signed 2021-04-13 2021-05-06 2021-06-08 2022-01-31 2021-12-05 ment translation services upport tions nvelope FIPAG/WASISII/ G-8/21 / Com Component 2: Institutional S Request for Quota Single Stage - One E munication and Logistics for IDA / D1100 Post Limited 150,000.00 121,781.19 Signed 2021-06-02 2021-05-25 2021-07-28 2021-09-03 2022-01-24 upport tions nvelope Financiers Conference FIPAG/WASISII/CON-39/20 / Dam Safety Technical Assista Component 2: Institutional S nce Service Provider for ARA- IDA / D1100 Post Direct Selection Direct 120,000.00 0.00 Canceled 2020-11-16 2022-01-01 2020-12-16 2022-03-10 2021-04-15 2023-04-15 upport Norte - Portuguese Laborator y of Civil Engineering (LNEC) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual FIPAG/WASISII/CON-6/15 / D esign check and supervision Component 2: Institutional S Quality And Cost- Open - Internationa IDA / D1100 Prior 1,215,000.00 665,133.53 Signed 2016-10-17 2016-10-19 2016-10-17 2016-12-12 2016-10-26 2017-02-27 2017-01-26 2017-04-03 2017-04-19 2017-08-29 2017-08-23 2017-11-03 2017-10-31 2020-11-16 of rehabilitation and construc upport Based Selection l tion of transmission mains, P emba FIPAG/WASISII/CON-7/15 / D esign and supervision of elec tromechanical equipment of Component 2: Institutional S Quality And Cost- Open - Internationa IDA / D1100 Prior 2,300,000.00 798,480.34 Signed 2016-10-17 2016-10-19 2016-10-17 2016-12-22 2016-11-08 2017-03-06 2017-01-10 2017-04-09 2017-03-24 2017-09-20 2017-08-01 2018-01-09 2018-03-13 2021-02-21 boreholes, rehabilitation and upport Based Selection l construction of treatment pla nt and pumping stations, Pe mba FIPAG/WASISII/CON-9/15 / D esign and Supervision for ref urbishment of existing treat Component 2: Institutional S Quality And Cost- Open - Internationa IDA / D1100 Prior 1,500,000.00 786,012.94 Signed 2016-10-17 2016-10-19 2016-10-17 2017-01-03 2016-12-18 2017-03-17 2017-03-24 2017-06-09 2017-05-31 2017-10-06 2018-01-04 2017-12-11 2018-06-07 2021-02-26 ment system, including pre-t upport Based Selection l reatment canal & rehabilitati on of the Dingue Dingue Wat er Intake, Beira Page 2 FIPAG/WASISII/CON-8/16 / D esign and supervision for Re Component 2: Institutional S Quality And Cost- Open - Internationa IDA / D1100 Prior 1,900,000.00 1,356,578.66 Signed 2016-10-17 2016-10-19 2016-10-17 2016-12-22 2016-12-21 2017-03-10 2017-03-09 2017-04-13 2017-05-03 2017-09-26 2017-12-05 2018-01-15 2018-03-16 2021-09-28 habilitation and Construction upport Based Selection l of Distribution Centre and Ne twork, Pemba FIPAG/WASISII/CON-11/15 / Component 2: Institutional S Quality And Cost- Open - Internationa Design check and supervisio IDA / D1100 Prior 1,500,000.00 771,254.25 Signed 2016-11-10 2016-12-15 2017-02-03 2016-12-21 2017-04-05 2017-05-10 2017-06-21 2017-07-26 2017-12-04 2017-12-06 2018-05-14 2018-02-12 2018-07-05 2020-09-02 upport Based Selection l n of network, Beira and Dond o FIPAG/WASISII/CON-14/16 / Design check and supervisio Component 2: Institutional S Quality And Cost- Open - Internationa IDA / D1100 Prior 1,000,000.00 599,575.00 Signed 2017-01-05 2017-05-22 2017-02-27 2017-07-26 2017-05-31 2018-10-15 2017-08-16 2018-12-04 2017-09-20 2019-04-09 2018-01-31 2019-07-19 2018-04-09 2019-10-07 2020-11-30 n of rehabilitation and constr upport Based Selection l uction of transmission mains, Tete FIPAG/WASISII/CON-15/18 / Design and supervision of ele ctro-mechanical equipment o Component 2: Institutional S Quality And Cost- Open - Internationa IDA / D1100 Prior 3,000,000.00 2,017,083.27 Signed 2018-05-21 2018-10-10 2018-07-05 2018-10-16 2018-08-18 2019-07-29 2018-09-22 2019-09-24 2018-10-22 2020-05-14 2018-12-05 2020-10-29 2019-03-19 2020-12-22 2021-09-04 f boreholes, rehabilitation an upport Based Selection l d construction of treatment p lant and pumping stations, T ete FIPAG/WASISII/CON-16/18 / Design and Supervision for re Component 2: Institutional S Quality And Cost- Open - Internationa IDA / D1100 Prior 2,100,000.00 872,120.31 Signed 2018-05-11 2018-07-17 2018-06-01 2018-07-19 2018-07-15 2019-07-30 2018-08-20 2019-09-26 2018-09-19 2019-12-23 2018-11-02 2020-04-01 2019-02-14 2020-08-10 2021-08-02 habilitation and construction upport Based Selection l of distribution centres and ne twork, Tete and Moatize FIPAG/WASISII/CON-13A/18 / Component 2: Institutional S Consultant Qualifi IDA / D1100 Post Open - National 110,000.00 91,401.88 Signed 2018-09-21 2018-07-24 2018-09-28 2018-11-11 2018-11-05 2018-11-25 2019-01-29 2018-12-16 2019-02-08 2019-05-15 Supervision for drilling boreh upport cation Selection oles in Tete FIPAG/WASISII/CON-24/18 / Component 2: Institutional S Quality And Cost- Open - Internationa Design and supervision of co IDA / D1100 Prior 1,000,000.00 1,301,234.04 Signed 2018-11-30 2019-12-20 2018-12-14 2020-01-03 2019-04-13 2020-05-31 2019-06-27 2020-08-12 2019-08-11 2020-10-28 2019-10-09 2021-01-21 2019-12-22 2021-03-26 2021-07-12 upport Based Selection l nstruction of distribution cent er in Beira FIPAG/WASISII/CON-19/18 / Development of information and communication technolo Component 2: Institutional S Quality And Cost- Open - Internationa IDA / D1100 Post 650,000.00 677,082.81 Signed 2018-10-28 2018-11-14 2018-12-09 2018-12-17 2019-01-22 2020-06-04 2019-02-19 2020-07-21 2019-03-21 2021-03-10 2019-04-25 2021-04-19 2019-05-30 2021-12-08 2020-05-29 gy master plan and assistanc upport Based Selection l e in the identification of appli cation management solution s FIPAG/WASISII/CON-23A/18- 2 / Design check and supervi Component 2: Institutional S Consultant Qualifi IDA / D1100 Post Open - National 200,000.00 291,710.00 Signed 2018-11-30 2018-12-06 2018-12-30 2019-04-11 2019-02-27 2019-11-05 2019-03-29 2019-12-30 2019-05-03 2020-01-27 2019-12-29 sion of construction of Mutua upport cation Selection emergency pumping station, Beira FIPAG/DRIVE/CON-1/19 / Des ign check and supervision of Component 2: Institutional S Quality And Cost- Open - Internationa Under Implement IDA / D4910 Prior 2,500,000.00 1,772,419.07 2020-04-05 2020-05-13 2020-05-05 2020-05-16 2020-10-17 2021-12-19 2021-01-15 2021-10-25 2021-03-16 2021-12-31 2021-06-14 2022-04-04 2021-12-11 2024-05-29 rehabilitation and expansion upport Based Selection l ation of Nacala water supply syste m FIPAG/WASISII/CON-27/20 / F Component 2: Institutional S Least Cost Selecti IDA / D1100 Post Open 450,000.00 238,954.91 Signed 2020-03-12 2021-01-18 2020-04-02 2020-11-05 2020-05-16 2021-02-05 2020-06-13 2021-03-04 2020-07-13 2021-04-15 2020-08-17 2021-06-08 2020-09-21 2021-05-24 2021-03-20 inancial Audit for 2020, 2021 upport on and 2022 FIPAG/WASISII/CON-34/20 / F Component 2: Institutional S Quality And Cost- Open - Internationa easibility Study and Detailed IDA / D1100 Prior 600,000.00 0.00 Under Review 2020-08-30 2021-08-31 2020-10-14 2021-09-22 2021-02-11 2021-05-12 2021-07-11 2021-10-09 2022-01-28 2022-11-24 upport Based Selection l Design for Nampula FIPAG/WASISII/CON-33/20 / P Component 2: Institutional S Quality And Cost- Open - Internationa reparation of Master Plan for IDA / D1100 Prior 1,500,000.00 0.00 Under Review 2020-11-16 2021-05-03 2020-12-31 2021-05-21 2021-04-30 2022-02-10 2021-07-29 2022-04-08 2021-09-27 2021-12-26 2022-04-16 2023-04-16 upport Based Selection l Pemba and Nacala FIPAG/WASISII/CON-31/20 / P Component 2: Institutional S Consultant Qualifi reparation of Project Manage IDA / D1100 Post Open - National 250,000.00 243,018.57 Signed 2020-09-04 2020-09-28 2020-09-25 2020-11-06 2020-12-24 2021-03-29 2021-01-23 2021-06-21 2021-04-08 2022-03-28 2022-03-10 upport cation Selection ment Platform for FIPAG FIPAG/WASISII/CON-25/18 / Component 2: Institutional S Quality And Cost- Open - Internationa Groundwater management pl IDA / D1100 Post 500,000.00 0.00 Canceled 2018-12-12 2019-01-02 2019-04-02 2019-06-16 2019-07-31 2019-09-13 2019-11-26 2021-06-18 upport Based Selection l an for Tete and Pemba FIPAG/WASISII/CON-12/15 / I Component 3: Output-Based Consultant Qualifi ndependent monitoring verifi IDA / D1100 Payments for Low-Income-H Post Open - National 300,000.00 0.00 Canceled 2018-07-26 2021-08-27 2018-09-15 2018-12-19 2019-06-08 2019-08-13 2025-09-09 cation Selection cation agent for Maputo ousehold Connections FIPAG/WASISII/CON-46/21 / T Component 2: Institutional S Quality And Cost- Open - Internationa echnical Assistance to Centra IDA / D1100 Post 450,000.00 0.00 Canceled 2021-05-28 2021-06-18 2021-08-01 2021-08-29 2021-09-28 2021-11-02 2021-12-07 2022-12-07 upport Based Selection l l Regional Water Utilily FIPAG/WASISII/CON-48/21 / Consultancy for the Refining Component 2: Institutional S Consultant Qualifi Open - Internationa Under Implement IDA / D1100 Post 150,000.00 0.00 2021-04-30 2021-05-21 2021-07-04 2021-08-03 2021-09-07 2022-03-06 and Implementation of Asset upport cation Selection l ation Management strategy FIPAG/WASISII/CON-42/21 / L eagal advisory services for e Component 2: Institutional S Consultant Qualifi Under Implement stablishment of Regional Co IDA / D1100 Prior Open - National 120,000.00 0.00 2021-05-30 2021-12-21 2021-06-20 2022-01-24 2021-08-03 2021-09-02 2021-10-07 2022-04-05 upport cation Selection ation mpanies, and legal assistanc e for PPP Studies up until the transactions FIPAG/WASISII/CON-49/21 / Component 2: Institutional S Consultant Qualifi Pending Impleme Utility Regional Office Project IDA / D1100 Post Open - National 150,000.00 0.00 2021-05-28 2021-06-18 2021-08-01 2021-08-31 2021-10-05 2022-04-03 upport cation Selection ntation Design and supervision FIPAG/WASISII/CON-43/21 / Developing Innovative Fit-for Component 2: Institutional S Consultant Qualifi Open - Internationa IDA / D1100 Post 300,000.00 0.00 Canceled 2021-04-19 2021-08-09 2021-05-10 2021-06-23 2021-07-23 2021-08-27 2022-02-23 -Purpose Public Private Partn upport cation Selection l erships for Four Regional Wat er Utilities FIPAG/WASISII/CON-58/21 / Developing Innovative Fit-for Component 2: Institutional S Quality And Cost- Open - Internationa Under Implement IDA / D1100 Prior 400,000.00 0.00 2021-08-24 2021-11-15 2021-09-14 2021-09-13 2021-10-28 2021-11-26 2021-11-25 2022-01-27 2021-12-25 2022-03-15 2022-01-29 2022-08-03 2022-03-05 2024-02-29 -PurposePublic Private Partne upport Based Selection l ation rship for Four Regional Water Utilities FIPAG/WASISII/CON-59/21 / T Component 2: Institutional S Quality And Cost- Open - Internationa echnical Assistance to Northe IDA / D1100 Prior 1,000,000.00 0.00 Under Review 2021-09-03 2021-09-10 2021-09-24 2021-09-10 2021-11-07 2022-02-07 2021-12-05 2022-03-23 2022-01-04 2022-02-08 2022-03-15 2024-03-15 upport Based Selection l rn and Central Regional Wate r Utility FIPAG/WASISII/CON-60/21 / T echnical Assistance to South Component 2: Institutional S Quality And Cost- Open - Internationa IDA / D1100 Prior 1,000,000.00 0.00 Under Review 2021-09-03 2021-09-11 2021-09-24 2021-09-12 2021-11-07 2022-02-07 2021-12-05 2022-03-24 2022-01-04 2022-02-08 2022-03-15 2024-03-15 ern and Maputo Metropolitan upport Based Selection l Regional Water Utility Page 3 FIPAG/WASISII/CON-47/21 / T Component 2: Institutional S Quality And Cost- Open - Internationa echnical Assistance to Northe IDA / D1100 Post 400,000.00 0.00 Canceled 2021-05-28 2021-08-17 2021-06-18 2021-08-01 2021-08-29 2021-09-28 2021-11-02 2021-12-07 2022-12-07 upport Based Selection l rn Regional Water Utitily FIPAG/WASISII/CON-44/21 / T Component 2: Institutional S Quality And Cost- Open - Internationa echnical Assistance to Maput IDA / D1100 Post 500,000.00 0.00 Canceled 2021-05-28 2021-08-19 2021-06-18 2021-08-01 2021-08-29 2021-09-28 2021-11-02 2021-12-07 2022-12-07 upport Based Selection l o Metropolitan Water Utility FIPAG/WASISII/CON-41/21 / Consultancy services for pre Component 2: Institutional S Consultant Qualifi Open - Internationa paration and installation the IDA / D1100 Post 40,000.00 0.00 Canceled 2021-06-10 2021-07-14 2021-07-01 2021-08-14 2021-09-13 2021-10-18 2022-04-16 upport cation Selection l platform for manage the Grie vance Redress Mechanism (G RM) FIPAG/WASISII/CON-67/22 / F easibility Study and Detailed Component 2: Institutional S Quality And Cost- Open - Internationa Under Implement Design of Additional Intake, IDA / D4910 Post 400,000.00 0.00 2022-01-12 2022-01-26 2022-02-02 2022-03-17 2022-03-18 2022-04-15 2022-05-15 2022-06-19 2022-07-24 2023-07-24 upport Based Selection l ation Water Treatment Plant, Trans mission Main and Distribution System for Tete and Moatize. FIPAG/WASISII/CON-70/22 / Component 2: Institutional S Consultant Qualifi Open - Internationa Dam Safety Technical Assista IDA / D1100 Post 120,000.00 0.00 Under Review 2022-07-21 2022-07-27 2022-08-11 2022-09-24 2022-10-24 2022-11-28 2023-05-27 upport cation Selection l nce Service Provider for ARA- Norte FIPAG/WASISII/CON-69/22 / Detailed Hydrogeological Stu Component 2: Institutional S Quality And Cost- Open - Internationa Pending Impleme dies and Monitoring Systems IDA / D1100 Post 600,000.00 0.00 2022-08-05 2022-08-26 2022-10-09 2022-11-06 2022-12-06 2023-01-10 2023-02-14 2024-02-14 upport Based Selection l ntation Installation in the Aquifers of Pemba, Tete and Moatize INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual FIPAG/WASISII/CON-5/15 / Su Component 2: Institutional S Individual Consult pervision for construction of IDA / D1100 Post Open 80,000.00 51,420.00 Signed 2017-01-16 2017-05-17 2017-04-24 2017-08-02 2017-06-12 2017-12-06 2017-08-02 2018-01-19 2019-02-26 upport ant Selection boreholes in Pemba FIPAG/WASISII/CON-2/17 / Pl Component 2: Institutional S Individual Consult IDA / D1100 Prior Open 400,000.00 549,000.00 Signed 2017-08-10 2017-09-13 2017-09-22 2018-01-09 2017-10-07 2018-02-21 2017-12-10 2018-04-12 2019-12-10 anning and Investment Advis upport ant Selection or FIPAG/WASISII/CON-1/17 / Pr Component 2: Institutional S Individual Consult IDA / D1100 Prior Open 400,000.00 993,225.00 Signed 2017-08-11 2017-08-22 2017-10-14 2018-01-23 2017-11-04 2018-02-21 2018-01-07 2018-05-10 2020-01-07 ocurement Advisor upport ant Selection FIPAG/WASISII/CON-4/18 / El Component 2: Institutional S Individual Consult IDA / D1100 Prior Open 300,000.00 0.00 Canceled 2018-06-08 2018-07-27 2018-08-17 2018-11-06 2020-06-01 ectromechanical advisor upport ant Selection FIPAG/WASISII/CON-17/18 / Component 2: Institutional S Individual Consult IDA / D1100 Prior Open 400,000.00 268,032.00 Signed 2018-05-31 2019-12-12 2018-08-03 2020-03-13 2018-09-06 2020-04-22 2018-12-19 2020-05-22 2020-12-18 Contract management advis upport ant Selection or FIPAG/WASISII/CON-21/18 / Component 2: Institutional S Individual Consult IDA / D1100 Post Limited 50,000.00 37,830.00 Signed 2018-04-02 2018-05-02 2018-04-09 2018-06-05 2018-04-30 2018-11-13 2018-07-23 2018-11-29 2018-08-22 Dam safety inspection servic upport ant Selection es FIPAG/WASISII/CON-4/17 / U Component 2: Institutional S Individual Consult pdate of FIPAG generic Envir IDA / D1100 Post Open 100,000.00 0.00 Canceled 2018-04-18 2018-06-23 2018-07-25 2018-10-01 2019-03-30 upport ant Selection onmental Management Plan FIPAG/WASISII/CON-10/18 / Component 2: Institutional S Individual Consult Under Implement IDA / D1100 Post Open 150,000.00 0.00 2018-06-15 2021-03-12 2018-08-03 2018-08-31 2018-11-13 2020-06-08 Water treatment process spe upport ant Selection ation cialist FIPAG/WASISII/CON-22/18 / Component 2: Institutional S Individual Consult IDA / D1100 Post Direct 50,000.00 40,775.00 Signed 2018-04-06 2018-05-18 2018-04-16 2018-06-07 2018-05-07 2018-07-06 2018-06-11 2018-07-31 2018-12-08 Update of the RPF upport ant Selection FIPAG/WASISII/CON-20/18 / Component 2: Institutional S Individual Consult IDA / D1100 Post Direct 70,000.00 50,373.75 Signed 2018-04-09 2018-05-28 2018-04-19 2018-07-16 2018-05-10 2018-08-17 2018-07-23 2018-08-31 2018-09-06 Update of the ESMF upport ant Selection FIPAG/WASISII/CON-23/18 / Design check and supervisio Component 2: Institutional S Individual Consult IDA / D1100 Post Open 150,000.00 0.00 Canceled 2018-05-10 2018-06-28 2018-07-28 2018-08-24 2019-04-21 n of rehabilitation of Mutua p upport ant Selection umping station (emergency) FIPAG/WASISII/CON-19/15 / Component 2: Institutional S Individual Consult Pending Impleme Acquisition of commercial sof IDA / D1100 Post Open 300,000.00 0.00 2018-09-15 2019-02-10 2019-04-13 2019-06-19 2021-07-16 upport ant Selection ntation tware and technical assistanc e FIPAG/WASISII/CON-13/18 / S Component 2: Institutional S Individual Consult upervision for construction of IDA / D1100 Post Open 80,000.00 0.00 Canceled 2018-05-30 2018-07-24 2018-07-18 2018-08-21 2018-12-03 2019-03-03 upport ant Selection boreholes in Tete FIPAG/WASISII/CON-27/19 / Component 2: Institutional S IDA / D1100 Post Direct Selection Direct 60,000.00 55,656.00 Signed 2019-05-31 2019-06-20 2019-06-12 2019-09-09 2019-07-29 2020-03-07 Review and update of ESIA fo upport r Nacala FIPAG/WASISII/CON-29/20 / I Component 2: Institutional S Individual Consult IDA / D1100 Post Limited 200,000.00 239,040.00 Signed 2020-07-08 2020-07-31 2020-07-13 2020-08-07 2020-08-03 2020-09-03 2020-09-07 2020-09-22 2021-03-06 nstitutional Advisor upport ant Selection FIPAG/WASIS II/CON-30/20 / Component 2: Institutional S Individual Consult Monitoring and Evaluation Sp IDA / D1100 Post Open 250,000.00 173,484.00 Signed 2020-07-15 2020-11-05 2020-09-02 2021-04-20 2020-09-23 2021-05-07 2020-10-28 2021-05-20 2021-04-26 upport ant Selection ecialist services FIPAG/WASISII/CON-32/20 / P Component 2: Institutional S Individual Consult IDA / D1100 Prior Open 400,000.00 150,422.40 Signed 2020-08-17 2020-11-03 2020-10-16 2021-04-14 2020-10-31 2021-06-10 2021-01-04 2021-06-25 2023-01-04 lanning and Investment Advi upport ant Selection sor FIPAG/WASISII/W-38/20 / Hy Component 2: Institutional S Individual Consult IDA / D1100 Post Open 200,000.00 299,800.00 Signed 2020-08-17 2020-08-13 2020-11-29 2021-01-07 2020-12-29 2021-01-29 2021-03-14 2021-03-02 2023-03-14 dro-mechanical Advisor upport ant Selection FIPAG/WASISII/CON-37/20 / Component 2: Institutional S Individual Consult IDA / D1100 Post Direct 60,000.00 141,493.75 Signed 2020-09-08 2020-10-22 2020-09-18 2020-12-03 2020-10-09 2021-02-26 2021-01-22 2021-03-29 2021-07-21 Dam safety inspection servic upport ant Selection es FIPAG/WASIS II/CON-35/20 / Component 2: Institutional S Individual Consult Groundwater management S IDA / D1100 Post Open 200,000.00 264,101.27 Signed 2020-08-31 2020-12-02 2020-11-13 2021-03-31 2020-12-13 2021-06-04 2021-02-26 2021-06-10 2023-02-26 upport ant Selection pecialist for Tete and Moatize Page 4 FIPAG/WASIS II/CON 40/20 / Component 1: Rehabilitation Preparation and Implementat and Expansion of Water Sup Individual Consult IDA / D1100 Post Open 200,000.00 96,787.50 Signed 2020-11-06 2021-02-17 2020-12-25 2021-06-23 2021-01-15 2021-08-24 2021-02-19 2021-07-28 2021-08-18 ion of the Abbreviated Resett ply Production and Distributi ant Selection lement Action Plan (ARAP) in on Pemba FIPAG/WASISII/CON-50/21 / Component 1: Rehabilitation Individual Consult Pending Impleme Mapping of services for survi IDA / D1100 and Expansion of Water Sup Post Open 75,000.00 0.00 2021-05-30 2021-08-28 2021-09-18 2021-10-12 2022-04-10 ant Selection ntation vors of GBV /SEA for WASIS II ply Production and Distributi project on FIPAG/WASISII/CON-51/21 / Component 2: Institutional S Individual Consult IDA / D1100 Prior Open 350,000.00 397,495.00 Terminated 2021-05-26 2021-06-07 2021-07-14 2021-09-15 2021-08-04 2021-10-15 2021-09-08 2021-12-01 2022-03-07 Contract Management Adviso upport ant Selection r FIPAG/WASIS/CON-56/21 / Pr Component 2: Institutional S Individual Consult IDA / D1100 Prior Open 200,000.00 0.00 Canceled 2021-08-06 2021-07-24 2021-11-16 2022-01-13 2021-12-31 2022-02-21 2022-03-22 2023-09-13 ocurement Assistant upport ant Selection FIPAG/WASISII/CON-53/21 / Component 2: Institutional S Individual Consult Under Implement IDA / D1100 Post Open 250,000.00 0.00 2021-08-24 2021-07-13 2021-11-19 2021-12-06 2021-12-19 2022-01-18 2022-03-10 2024-03-09 Business Management Advis upport ant Selection ation or FIPAG/WASISII/CON-54/21 / T echnical Assistance for Imple Component 2: Institutional S Individual Consult Under Implement IDA / D1100 Post Open 150,000.00 0.00 2021-07-16 2021-07-12 2021-10-26 2022-04-14 2021-12-10 2022-05-31 2022-03-10 2024-03-09 mentation of the Environmen upport ant Selection ation tal and Social Safeguards FIPAG/WASISII/CON-52/21 / Component 2: Institutional S Individual Consult Under Implement IDA / D1100 Post Open 150,000.00 0.00 2021-07-20 2021-07-13 2021-10-15 2022-02-02 2021-11-29 2022-03-21 2022-02-27 2023-09-23 Communication Assistant upport ant Selection ation FIPAG/WASISII/CON-57/21 / P Component 2: Institutional S Individual Consult IDA / D1100 Prior Open 400,000.00 0.00 Canceled 2021-08-25 2021-09-08 2021-10-13 2021-11-03 2021-12-08 2023-11-30 rocurement Advisor upport ant Selection FIPEG/WASISII/CON-55/21 / T Component 2: Institutional S Pending Impleme echnical Assistance for Hous IDA / D1100 Post Direct Selection Direct 300,000.00 0.00 2021-08-30 2021-09-14 2022-01-03 2024-01-03 upport ntation ehold Connection program in Nacala FIPAG/WASISII/CON-64/21 / Consultancy services for pre Component 2: Institutional S Individual Consult Under Implement paration and installation the IDA / D1100 Post Limited 40,000.00 0.00 2021-09-16 2021-06-14 2021-09-21 2021-07-14 2021-10-12 2021-11-30 2021-11-16 2022-05-15 upport ant Selection ation platform for manage the Grie vance Redress Mechanism (G RM) FIPAG/WASISII/CON-61/21 / I Component 3: Output-Based Individual Consult Under Implement ndependent Monitoring and IDA / D1100 Payments for Low-Income-H Post Open 100,000.00 0.00 2021-09-28 2021-12-15 2021-11-16 2021-12-07 2022-01-11 2024-06-21 ant Selection ation Verification Agent – Pemba a ousehold Connections nd Nacala /FIPAG/WASISII/CON-62/21 / I Component 3: Output-Based Individual Consult Under Implement ndependent Monitoring and IDA / D1100 Payments for Low-Income-H Post Open 100,000.00 0.00 2021-09-28 2021-12-17 2021-11-16 2021-12-07 2022-01-11 2024-06-21 ant Selection ation Verification Agent – Tete and ousehold Connections Moatize FIPAG/WASISII/CON-63/21 / I Component 3: Output-Based Individual Consult Under Implement ndependent Monitoring and IDA / D1100 Payments for Low-Income-H Post Open 100,000.00 0.00 2021-09-28 2021-12-17 2021-11-16 2021-12-07 2022-01-11 2024-06-21 ant Selection ation Verification Agent – Beira an ousehold Connections d Dondo FIPAG/WASISII/CON-65/21 / Annual Independent Environ Component 2: Institutional S Individual Consult Under Implement IDA / D1100 Post Open 160,000.00 0.00 2021-12-10 2021-12-24 2022-01-28 2022-03-07 2022-02-18 2022-04-21 2022-03-25 2022-09-21 mental and Social Audit for upport ant Selection ation WASIS II Project (2022-2024). FIPAG/WASISII/CON-66/21 / Component 2: Institutional S Individual Consult Under Implement IDA / D1100 Prior Open 350,000.00 0.00 2021-12-31 2022-01-09 2022-02-18 2022-07-04 2022-03-11 2022-08-03 2022-04-15 2024-04-15 Contract Management Adviso upport ant Selection ation r FIPAG/WASISII/CON-68/22 / P Component 2: Institutional S Individual Consult IDA / D1100 Prior Direct 90,000.00 78,300.00 Signed 2022-03-14 2022-03-15 2022-03-24 2022-04-20 2022-04-14 2022-04-29 2022-05-19 2022-05-03 2022-11-15 rocurement Assistant upport ant Selection FIPAG/WASISII/CON-71/22 / P REPARATION AND IMPLEMEN Component 2: Institutional S Individual Consult Open - Internationa Pending Impleme IDA / D1100 Post 120,000.00 0.00 2022-08-05 2022-09-23 2022-10-14 2022-11-18 2023-05-17 TATION OF THE ABBREVIATE upport ant Selection l ntation D RESETTLEMENT ACTION PL AN (ARAP) IN NACALA Page 5