PROCUREMENT PLAN (Textual Part) Project information: [Haiti] [P163490 - Haiti Rural Accessibility & Resilience Project Project Implementation agency: [UCE] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. • PROCUREMENT Haiti : Haiti Rural Accessibility & Resilience Project PLAN General Information Country: Haiti 2019-02-27 Bank’s Approval Date of the Original Procurement Plan: 2022-06-20 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P163490 GPN Date: Project Name: Haiti Rural Accessibility & Resilience Project Loan / Credit No: IDA / D3230, IDA / D6690 Unité Centrale d'Exécution Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AON-001-PARR/2019 / Trava ux de Traitement de Points cr Improving Resilience of Tran Single Stage - One E 2019-12-0 itiques dans les Département IDA / D3230 sport Connecting Infrastruct A priori Appel d'offres Open - National 0.00 Annulé 2019-02-21 2019-03-01 2019-04-10 2019-05-02 2019-05-26 nvelope 6 s du Sud, des Nippes et de l' ure Ouest en quatre (4) Lots DC-001-PARR/2019 / Protecti Improving Resilience of Tran on du Pont de Trou du Nord d Single Stage - One E 2020-05-0 IDA / D3230 sport Connecting Infrastruct A posteriori Demande de prix Limited 441,342.20 Signé 2019-02-28 2019-11-11 2019-05-05 2020-01-20 ans la Commune du même n nvelope 1 ure om dans le Département du Nord'est DC-002-PARR/2019 / Protecti Improving Resilience of Tran on de la Route Vieux Bourg d Single Stage - One E 2020-03-2 IDA / D3230 sport Connecting Infrastruct A posteriori Demande de prix Limited 0.00 Annulé 2019-08-24 2019-10-20 'Aquin - L'Asile dans la localit nvelope 8 ure é de Kapol dans les Nippes DC-005-PARR/2019 / Protecti on et Réhabilitation de Deux Improving Resilience of Tran Single Stage - One E 2020-03-3 (2) Ponts dans les Commune IDA / D3230 sport Connecting Infrastruct A posteriori Demande de prix Limited 543,462.50 Signé 2019-08-26 2019-11-11 2019-10-22 2020-01-20 nvelope 0 s de Grand-Goâve et de Petit ure -Goâve (Département de l'Ou est) en deux (2) Lots AON-001-PARR/2020 / Prote Improving Resilience of Tran ction de la RD22 (Tronçon Mi Single Stage - One E 2020-07-1 IDA / D3230 sport Connecting Infrastruct A posteriori Appel d'offres Open - National 751,145.00 Signé 2019-10-14 2020-06-02 2019-10-19 2019-11-30 2020-08-07 2019-12-30 2020-09-28 2020-02-03 2020-11-11 ragoane - Petite Rivière de Ni nvelope 2 ure ppes) en deux lots DC-003-PARR/2019 / Protecti Improving Resilience of Tran Single Stage - One E 2020-06-1 IDA / D3230 A posteriori Demande de prix Limited 744,248.50 Signé 2019-11-27 2019-12-17 2020-01-06 2020-04-27 on du Pont de Port-a-Piment sport Connecting Infrastruct nvelope 4 ure DC-004-PARR/2019 / Protecti Improving Resilience of Tran Single Stage - One E 2020-08-1 IDA / D3230 A posteriori Demande de prix Limited 534,415.50 Signé 2019-12-18 2019-12-17 2020-02-12 2020-04-27 on de trois (3) Ponts sur la R sport Connecting Infrastruct nvelope 0 N2 ure AON-002-PARR/2020 / Traite ment des points critiques sur Enhancing Rural Connectivit Single Stage - One E 5,232,264.7 2021-06-0 IDA / D3230 A posteriori Appel d'offres Open - National Signé 2020-10-06 2020-10-06 2020-10-08 2020-11-19 2020-11-25 2020-12-04 2021-01-29 2020-12-28 2021-03-24 le tronçon La Colline - Fond-d y nvelope 8 6 es-Blancs en sept (7) lots AOI-001-PARR/2021 / Travau x de traitement des points cri Enhancing Rural Connectivit Open - Internationa Single Stage - One E 6,268,455.8 2021-08-2 IDA / D6690 A priori Appel d'offres Signé 2020-12-21 2021-06-30 2020-12-26 2021-07-26 2021-02-06 2021-08-30 2021-02-21 2021-11-16 2021-03-17 2022-01-19 tiques sur le tronçon de rout y l nvelope 6 4 e Dessalines - Saint-Michel e n cinq (5) lots AON-003-PARR/2021 / Traite ment des points critiques: Tr Enhancing Rural Connectivit Single Stage - One E 3,756,316.0 2021-08-1 IDA / D3230 A posteriori Appel d'offres Open - National Signé 2020-12-16 2020-12-28 2020-12-21 2021-02-01 2021-02-12 2021-02-16 2021-03-26 2021-03-12 2021-05-04 onçon de Route Petit Trou - B y nvelope 0 9 aradères en quatre (4) lots AON-004-PARR/2020 / TRAIT EMENT DE POINTS CRITIQUE S SUR LE TRONÇON THIOTTE Enhancing Rural Connectivit Single Stage - One E 1,482,133.5 2021-10-0 -- ANSE-À-PITRES IDA / D3230 A posteriori Appel d'offres Open - National Signé 2021-01-18 2021-01-22 2021-01-23 2021-03-06 2021-03-03 2021-03-27 2021-04-01 2021-04-25 2021-05-14 y nvelope 4 2 Lot 1: Thiotte - Boucan Guilla ume Lot 2: Boucan Guillaume - An se-à-Pitres DP-002-PARR/2021 / RECON STRUCTION D’OUVRAGES EN Enhancing Rural Connectivit Single Stage - One E 1,781,662.5 2021-10-1 IDA / D3230 A posteriori Demande de prix Limited Signé 2021-03-06 2021-03-01 2021-05-10 2021-05-28 DOMMAGÉS PAR LE CYCLONE y nvelope 3 7 LAURA DANS LE SUD-EST EN QUATRE (4) LOTS AON-005-PARR/2021 / Prote Enhancing Rural Connectivit Single Stage - One E 3,025,280.9 2021-11-3 ction et Réhabilitation de qua IDA / D3230 A posteriori Appel d'offres Open - National Signé 2021-03-18 2021-04-05 2021-03-23 2021-05-04 2021-05-07 2021-05-25 2021-06-25 2021-06-23 2021-08-03 y nvelope 5 0 tre (4) Ponts sur la RN2 et la RD25 AON-006-PARR/2021 / Const ruction et Protection de quatr Enhancing Rural Connectivit Single Stage - One E 2021-12-0 IDA / D3230 A posteriori Appel d'offres Open - National 611,797.25 Signé 2021-03-25 2021-05-11 2021-03-30 2021-05-11 2021-06-21 2021-06-01 2021-09-06 2021-06-30 2021-10-06 e (4) Dalots dans les Départe y nvelope 7 ments de l'Artibonite et du S ud AOI-001-UCE-2018-PBCA / Tr avaux de construction de qu atre ponts dans les départem ents du Centre, du Nord et d Enhancing Rural Connectivit Open - Internationa Single Stage - One E 16,979,212. 2020-09-1 IDA / D6690 A priori Appel d'offres Signé 2017-11-14 2021-04-13 2018-06-18 2018-08-24 2018-08-24 2018-12-19 2021-04-13 2019-03-28 2019-03-28 e l'Artibonite (Ponts sur les ri y l nvelope 67 8 vières Bonbon, Rio Frio, Wall ondry et l'Attalaye) Lot 1 - Ri o Frio, Bonbon Lot 2 - Wallon dry, L'Attalaye Request for DC-001-BCA/2019 / Traiteme Quotations - nt des Points critiques dans l Enhancing Rural Connectivit Single Stage - One E Small Works 1,350,342.4 2020-08-1 IDA / D6690 A posteriori Demande de prix Limited Signé 2019-12-18 2019-12-17 2020-02-12 2020-04-27 es Communes de Saint-Miche y nvelope (Emergency) 9 0 l de l'Attalaye et de Saint Ra SPD -Compet phaël en deux (2) lots itive Request for DC-003-BCA/2019 / CONSTR Quotations - Enhancing Rural Connectivit Single Stage - One E 2020-10-0 UCTION D’UN DALOT 4(3.5× IDA / D6690 A posteriori Demande de prix Limited Small Works 339,829.40 Signé 2019-12-17 2019-12-17 2020-04-27 2020-04-27 y nvelope 4 4) SUR LA RIVIÈRE BRETELLE (Emergency) SPD -Compet itive DC002/BCA/2018 / Construct ion de trois dalots en trois Lo Request for ts sur la Ravine Sèche, la Rivi Enhancing Rural Connectivit Single Stage - One E Quotations ( 2019-05-1 ère Yayou et la Rivière Vébri IDA / D6690 A posteriori Demande de prix Limited 466,647.51 Signé 2018-05-30 2018-05-30 2018-11-16 2018-11-16 y nvelope Non Bank-SP 5 ne sur le tronçon de route De D) ssalines - St-Michel - Lot 1 A - Ravine Sèche, Lot 1 B - Rivier e Yayou, Lot 1 C - Riviere Ve brine Page 1 DC003/UCE/BCA/2018 / Trav Request for aux de traitement des points Enhancing Rural Connectivit Single Stage - One E Quotations ( 2,178,143.8 2020-02-1 critiques sur le tronçon de ro IDA / D6690 A posteriori Demande de prix Limited Signé 2018-09-24 2018-09-24 2019-09-11 2019-09-11 y nvelope Non Bank-SP 4 8 ute Titanyen - Saut-d'eau - L D) ot 1, Lot 2, Lot 3, Lot4, Lot 5 AON-007-PARR/2021 / RECO Request for B NSTRUCTION D’OUVRAGES D ids - Small W Enhancing Rural Connectivit Single Stage - One E En cours d'e 2022-06-1 ANS LES DÉPARTEMENTS DE IDA / D3230 A posteriori Appel d'offres Open - National orks SPD (1 e 0.00 2021-09-13 2022-04-29 2021-09-18 2021-10-30 2021-11-20 2021-12-14 y nvelope xécution 2 L’OUEST, DU SUD ET DU SUD nvelope proc -EST EN SIX (6) LOTS ess) AON-008-PARR2/2021 / TRA Request for B VAUX COMPLÉMENTAIRES DE Improving Resilience of Tran ids - Small W Single Stage - One E En cours d'e 2022-08-2 TRAITEMENT DE POINTS CRIT IDA / D6690 sport Connecting Infrastruct A posteriori Appel d'offres Open - National orks SPD (1 e 0.00 2021-11-25 2022-01-04 2021-11-30 2022-01-11 2022-02-21 2022-02-01 2022-02-25 nvelope xécution 4 IQUES DANS LA BOUCLE CEN ure nvelope proc TRE-ARTIBONITE EN DEUX LO ess) TS Request for DC-001-PARR/2021 / AMÉLIO Quotations - RATION DU SEGMENT CANCE Contingent Emergency Resp Single Stage - One E Small Works 1,086,533.2 En cours d'e 2022-07-1 IDA / D3230 A posteriori Demande de prix Limited 2021-12-24 2022-01-19 2022-02-02 - BATTE DANS LE DÉPARTEM onse nvelope (Emergency) 0 xécution 2 ENT DU SUD EN DEUX (2) LO SPD -Compet TS itive Request for DC-002-PARR/2021 / RECON Quotations - STRUCTION DE DIX (10) DAL Contingent Emergency Resp Single Stage - One E Small Works 1,819,493.3 En cours d'e 2022-07-1 IDA / D3230 A posteriori Demande de prix Limited 2021-12-24 2022-01-19 2022-02-02 OTS DANS LES DÉPARTEMEN onse nvelope (Emergency) 3 xécution 2 TS DU SUD ET DES NIPPES E SPD -Compet N QUATRE (4) LOTS itive Request for DC-003-PARR/2021 / RÉHABI Quotations - LITATION DE RUES DANS LA Contingent Emergency Resp Single Stage - One E 2,246,865.0 En cours d'e 2022-07-1 IDA / D3230 A posteriori Demande de prix Limited Small Works 2021-12-24 2022-01-19 2022-02-02 VILLE DES CAYES EN TROIS ( onse nvelope 0 xécution 2 (Emergency) 3) LOTS SPD -Compet itive Request for DC-004-PARR/2021 / RECON Quotations - STRUCTION DE SIX (6) DALO Contingent Emergency Resp Single Stage - One E Small Works En attente d 2022-07-2 IDA / D3230 A posteriori Demande de prix Limited 0.00 2022-01-06 2022-02-16 TS DANS LE DÉPARTEMENT D onse nvelope (Emergency) 'exécution 6 U SUD EN QUATRE (4) LOTS SPD -Compet itive Request for DC-005-PARR/2021 / RECON Quotations - STRUCTION DE SEPT (7) DAL Contingent Emergency Resp Single Stage - One E Small Works En attente d 2022-07-2 IDA / D3230 A posteriori Demande de prix Limited 0.00 2022-01-06 2022-02-15 OTS DANS LE DÉPARTEMENT onse nvelope (Emergency) 'exécution 5 DU SUD EN TROIS (LOTS) SPD -Compet itive Request for DC-006-PARR/2021 / RÉHABI Quotations - LITATION DE BERGES DANS L Contingent Emergency Resp Single Stage - One E Small Works En attente d 2022-07-2 IDA / D3230 A posteriori Demande de prix Limited 0.00 2022-01-06 2022-02-15 A COMMUNE DES CAYES DU onse nvelope (Emergency) 'exécution 5 DÉPARTEMENT DU SUD EN D SPD -Compet EUX (2) LOTS itive MTPTC/UCE/PARR-22/DINEPA /CW/RFQ-002 / Travaux de ré National Proc habilitation des SAEP dans le urement Doc s Nippes en 2 lots : Contingent Emergency Resp Single Stage - One E ument - 1 En En attente d 2022-12-1 IDA / D3230 A posteriori Demande de prix Limited 0.00 2022-04-20 2022-06-15 Lot 1: SAEP de Baco onse nvelope velope proce 'exécution 2 nois ss (Non Bank Lot 2: SAEP de Mat -SPD) hurin et de St. Michel MTPTC/UCE/PARR-22/DINEPA /CW/RFQ-004 / Travaux de ré National Proc habilitation des SAEP dans la urement Doc Grand'Anse en 2 lots : Contingent Emergency Resp Single Stage - One E ument - 1 En En attente d 2023-01-1 IDA / D3230 A posteriori Demande de prix Limited 0.00 2022-05-27 2022-07-22 Lot 1: SAEP du cent onse nvelope velope proce 'exécution 8 re-ville de les Irois ss (Non Bank Lot 2: SAEP de Déra -SPD) nger et Rémy (Abricot) AON-009-PARR2/2022 / CON STRUCTION DES OUVRAGES Request for B DE FRANCHISSEMENT DES RI ids - Small W Enhancing Rural Connectivit Single Stage - One E En cours d'e 2023-01-0 VIÈRES PLATANA ET CARNOT IDA / D6690 A posteriori Appel d'offres Open - National orks SPD (1 e 0.00 2022-02-25 2022-03-10 2022-03-02 2022-04-13 2022-05-04 2022-05-28 y nvelope xécution 3 SUR LE TRONÇON DE ROUTE nvelope proc DESSALINES – SAINT MICHEL ess) DE L’ATTALAYE EN DEUX (2) LOTS Request for B AON-010-PARR/2021 / AMÉLI Improving Resilience of Tran ids - Small W ORATION DE L’AXE ROUTIER Single Stage - One E En attente d 2023-01-2 IDA / D3230 sport Connecting Infrastruct A priori Appel d'offres Open - National orks SPD (1 e 0.00 2022-03-15 2022-03-20 2022-05-01 2022-05-22 2022-06-15 BARADÈRES-BONNE FIN-L’ASI nvelope 'exécution 1 ure nvelope proc LE-VIEUX BOURG D’AQUIN E ess) N SIX (6) LOTS National Proc ED-001-DINEPA/PARR/2022 / urement Doc TRAVAUX DE RECONSTRUCTI Contingent Emergency Resp Passation de marc ument - 1 En En attente d 2023-01-1 IDA / D6690 A posteriori Direct 0.00 2022-06-09 2022-06-14 2022-07-19 ON DU CAPTAGE SUR LA RIVI onse hé de gré à gré velope proce 'exécution 5 ERE DE PEDERNALES A ANSE ss (Non Bank -A-PITRE -SPD) DC-001-DINEPA/PARR/2022 / National Proc Travaux de réhabilitation des urement Doc SAEP dans les Nippes en 2 lo Contingent Emergency Resp Single Stage - One E ument - 1 En En attente d 2023-01-0 IDA / D6690 A posteriori Demande de prix Limited 0.00 2022-07-13 2022-09-07 ts onse nvelope velope proce 'exécution 6 Lot 1: SAEP de Bacon ss (Non Bank ois L -SPD) ot 2: SAEP de Mathurin et d e St. Michel National Proc ED-002-DINEPA/PARR/2022 / urement Doc Travaux de réhabilitation des Contingent Emergency Resp Passation de marc ument - 1 En En attente d 2022-11-1 SAEP dans le SUD en 2 lots : IDA / D6690 A posteriori Direct 0.00 2022-06-10 2022-06-15 2022-07-20 onse hé de gré à gré velope proce 'exécution 6 Lot 1: SAEP de St. Louis du S ss (Non Bank ud et Lot 2: SAEP de Ferme-l -SPD) e-Blanc (Torbeck) National Proc ED-003-DINEPA/PARR/2022 / urement Doc Travaux de remise en état du Contingent Emergency Resp Passation de marc En attente d 2022-11-2 IDA / D6690 A posteriori Direct ument - 1 En 0.00 2022-06-12 2022-06-17 2022-07-22 SAEP de Madame Bernard (Il onse hé de gré à gré 'exécution 3 velope proce e-à-Vache) ss (Non Bank -SPD) National Proc ED-004-DINEPA/PARR/2022 / urement Doc Contingent Emergency Resp Passation de marc En attente d 2022-10-2 Travaux de réparation du SA IDA / D6690 A posteriori Direct ument - 1 En 0.00 2022-06-12 2022-06-17 2022-07-22 onse hé de gré à gré 'exécution 4 EP de Roche-à-Bateau velope proce ss (Non Bank -SPD) National Proc ED-005-DINEPA/PARR/2022 / urement Doc Travaux de remise en état et Contingent Emergency Resp Passation de marc En attente d 2022-10-2 IDA / D6690 A posteriori Direct ument - 1 En 0.00 2022-06-15 2022-06-20 2022-07-25 de renforcement du SAEP de onse hé de gré à gré 'exécution 4 velope proce Laurent, Sud ss (Non Bank National -SPD) Proc ED-006-DINEPA/PARR/2022 / urement Doc Travaux de renforcement du Contingent Emergency Resp Passation de marc ument - 1 En En attente d 2022-11-3 IDA / D6690 A posteriori Direct 0.00 2022-06-23 2022-06-28 2022-08-02 SAEP de la Digue à Jérémie (i onse hé de gré à gré velope proce 'exécution 0 nstallation de système solair ss (Non Bank e) -SPD) Page 2 DC-002-DINEPA/PARR/2022 / National Proc Travaux de réhabilitation des urement Doc SAEP dans la Grand'Anse en Contingent Emergency Resp Single Stage - One E ument - 1 En En attente d 2023-02-2 IDA / D6690 A posteriori Demande de prix Limited 0.00 2022-07-04 2022-08-29 2 lots : Lot 1: SAEP du centre onse nvelope velope proce 'exécution 5 -ville de les Irois; Lot 2: SAEP ss (Non Bank de Déranger et Rémy (Abrico -SPD) t) National Proc ED-007-DINEPA/PARR/2022 / urement Doc Travaux d'aménagement de Contingent Emergency Resp Passation de marc En attente d 2022-12-3 IDA / D6690 A posteriori Direct ument - 1 En 0.00 2022-06-22 2022-06-27 2022-08-01 8 points d'eau dans la Grand' onse hé de gré à gré 'exécution 0 velope proce Anse ss (Non Bank -SPD) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GO-001-PARR/2019 / Acquisi Single Stage - One E IDA / D3230 Project Management A posteriori Demande de prix Limited 29,600.00 Signé 2019-03-09 2019-11-26 2019-04-23 2019-12-20 2019-06-22 tion de vehicule nvelope GO-002-PARR/2021 / Acquisi tion de 500 mini kits énergéti Promoting Sustainable Mobil Single Stage - One E ques solaires pour un échanti IDA / D3230 A posteriori Demande de prix Limited 35,700.00 Signé 2021-05-08 2021-05-20 2021-06-22 2021-08-04 2021-12-19 ity Development nvelope llon de ménages devant parti ciper à l'enquête Origine-Des tination au Cap-Haïtien ED-006-PARR/2021 / Acquisit ion de Téléphones portables Promoting Sustainable Mobil Passation de marc En cours d'ex pour la conduite d'une enquê IDA / D3230 A posteriori Direct 0.00 2021-05-10 2021-05-11 2021-05-15 2021-06-19 2021-12-16 ity Development hé de gré à gré écution te de mobilité auprès de mén age au Cap-Haïtien NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ED-001-PARR/2019 / Service Improving Resilience of Tran s en vue de Collecte de Donn Passation de marc En attente d' IDA / D3230 sport Connecting Infrastruct A posteriori Direct 0.00 2019-04-25 2019-04-26 2019-04-30 2019-06-04 ées Vidéo Aérienne à l'aide d hé de gré à gré exécution ure e Drones au Cap-Haïtien ED-003-BCA/2019 / RECRUT EMENT D'UNE ÉQUIPE LOCAL Promoting Sustainable Mobil Passation de marc En cours d'ex E POUR EFFECTUER LA COLL IDA / D3230 A posteriori Direct 0.00 2019-07-09 2019-07-16 2019-07-14 2019-07-24 2019-08-05 ity Development hé de gré à gré écution ECTE DE DONNÉES À L'AIDE DE L’APPLICATION COLLECTO R AU CAP-HAÏTIEN ED-004-PARR/2020 / Élabora tion Plan de mobilité, exécuti on des travaux d'entretien et Improving Resilience of Tran Passation de marc de réparation de routes rural IDA / D3230 sport Connecting Infrastruct A priori Direct 42,809,935.00 Signé 2019-10-28 2019-11-04 2019-10-31 2019-11-05 2019-11-13 2019-12-31 2022-03-31 hé de gré à gré es, et renforcement des capa ure cités communautaires dans l es Départements du Sud-Est, des Nippes et du Sud ED-005-PARR/2020 / Service s de Laboratoire en Appui à l Improving Resilience of Tran a Mission de Supervision des Passation de marc IDA / D3230 sport Connecting Infrastruct A posteriori Direct 18,949.40 Signé 2020-04-29 2020-04-10 2020-05-02 2020-04-16 2020-05-13 2020-05-14 2021-02-10 Travaux de Construction des hé de gré à gré ure Ponts Rio Frio, Bonbon, Walo ndry et L'Attalaye de la Boucl e Centre-Artibonite UN-001-PARR/2021 / Renforc ement de la protection et la r ésilience des communautés Enhancing Rural Connectivit Passation de marc des zones de déploiement de IDA / D3230 A posteriori Direct 1,019,789.00 Signé 2021-05-12 2021-05-11 2021-05-17 2021-05-17 2021-06-21 2021-05-28 2023-02-11 y hé de gré à gré s infrastructures routières da ns le Grand Sud en matière d e VBG, notamment les EAS e t le HS ED-008-PARR/2022 / Service s de Laboratoire en Appui à l Contingent Emergency Resp Passation de marc En attente d' a Mission de Supervision des IDA / D3230 A posteriori Direct 0.00 2022-01-17 2022-01-19 2022-02-08 2022-08-07 onse hé de gré à gré exécution Travaux de Construction du P ont provisoire sur la Rivière Grand'Anse ED-007-PARR/2022 / Service s supplémentaires de Labora toire en Appui à la Mission de Improving Resilience of Tran Passation de marc En attente d' Supervision des Travaux de IDA / D3230 sport Connecting Infrastruct A posteriori Direct 0.00 2022-01-17 2022-01-19 2022-02-08 2022-06-08 hé de gré à gré exécution Construction des Ponts Rio Fr ure io, Bonbon, Walondry et l'Att alaye de la Boucle Centre-Art ibonite MTPTC/UCE/PARR-20/INV-00 1 / Fourniture et implémentat Single Stage - One E En attente d' IDA / D3230 Project Management A posteriori Demande de prix Limited 0.00 2021-03-21 2021-05-01 2021-10-08 ion d'un système de comptab nvelope exécution ilité informatisée CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DP-003-PARR/2019 / Réalisat Improving Resilience of Tran Sélection fondée s Open - Internationa ion d'une Etude de vulnérabil IDA / D3230 sport Connecting Infrastruct A posteriori ur les qualification 272,550.36 Signé 2019-02-25 2019-03-11 2019-04-15 2019-06-06 2019-04-29 2020-11-05 2019-05-24 2020-11-30 2019-11-24 l ité (Pilote) du Réseau Routier ure s des consultants en Haiti DP-001-PARR/2019 / Audit Fi Sélection au moin IDA / D3230 Project Management A posteriori Open - National 78,548.76 Signé 2019-02-22 2019-01-13 2019-02-23 2019-02-25 2019-03-08 2019-03-11 2019-03-25 2019-03-26 2019-04-26 2019-04-05 2019-04-29 2019-04-28 2019-08-01 2022-04-27 nancier du PARR dre coût DP-004-PARR/2019 / Etudes Sélection fondée s Open - Internationa En cours d'exécut de mise en place d'un systè IDA / D3230 Project Management A posteriori ur les qualification 0.00 2019-02-26 2019-03-19 2019-04-14 2019-04-19 2019-05-13 2019-11-13 l ion me d'Archivage électronique s des consultants à l'UCE Page 3 DP-002-PARR/2019 / Recrute ment d'une Firme ou d'un Op Sélection fondée s érateur pour Cartographie et Enhancing Rural Connectivit Open - Internationa IDA / D3230 A priori ur la qualité et le 0.00 Annulé 2019-03-13 2019-03-27 2019-04-21 2019-06-02 2019-06-23 2019-07-10 2019-08-07 2020-02-07 Plans de Mobilité en Zone Ru y l coût rale dans les Départements du Sud, du Sud-est et des Ni ppes QC-001-PARR/2021 / Enquêt Sélection fondée s Promoting Sustainable Mobil e Origine-Destination au Cap- IDA / D3230 A posteriori ur les qualification Limited 90,110.90 Signé 2020-11-10 2020-11-23 2020-11-24 2020-12-07 2020-12-09 2021-03-30 2020-12-20 2021-04-06 2021-02-21 ity Development Haïtien s des consultants DP-005-PARR/2021 / ÉTUDES Sélection fondée s ROUTIÈRES SUR 107 KM DE Enhancing Rural Connectivit Open - Internationa En cours d'exécut IDA / D3230 A posteriori ur la qualité et le 0.00 2021-02-01 2021-04-01 2021-02-22 2021-03-29 2021-08-25 2021-04-26 2021-11-19 2021-05-17 2022-01-31 2021-06-10 2021-07-09 2022-01-05 ROUTES SUR LE TRONÇON T y l ion coût HIOTTE / MARIGOT DP-006-PARR/2021 / Assista nce au Maitre d’Ouvrage dan Improving Resilience of Tran Sélection fondée s Open - Internationa En cours d'exécut s le cadre de la reconstructio IDA / D3230 sport Connecting Infrastruct A priori ur la qualité et le 0.00 2021-03-22 2021-04-01 2021-04-12 2021-05-05 2021-05-26 2021-06-23 2021-07-23 2021-08-27 2021-10-01 2023-08-22 l ion n de quatre ouvrages d’art d ure coût ans les départements de l’Ou est, du Sud et des Nippes QC-002-PARR/2021 / ÉTUDE Sélection fondée s DE PRÉFAISABILITÉ POUR AM Promoting Sustainable Mobil IDA / D3230 A posteriori ur les qualification Limited 255,880.17 Signé 2021-04-23 2021-04-23 2021-05-07 2021-06-28 2021-05-22 2021-10-01 2021-06-03 2021-10-12 2021-11-30 ÉLIORER LA MOBILITÉ SUR LE ity Development s des consultants S PRINCIPAUX CORRIDORS D E PORT-AU-PRINCE DP001/UCE/BCA/2019 / Supe rvision des travaux de constr uction de quatre ponts dans l Sélection fondée s es départements du Centre, Enhancing Rural Connectivit Open - Internationa IDA / D6690 A posteriori ur la qualité et le 1,882,428.96 Signé 2018-08-21 2018-08-21 2018-09-04 2019-04-01 2019-03-27 2019-05-27 2019-05-27 2019-07-05 2019-07-05 2019-08-09 2019-08-09 2019-10-31 2019-10-31 2021-05-23 du Nord et de l'Artibonite (Po y l coût nts sur les rivières Bonbon, R io Frio, Wallondry et l'Attalay e) - Lot 1 - Rio Frio, Bonbon L ot 2 - Wallondry, l'Attalaye QC-001-CIAT-PARR/2020 / R Sélection fondée s éalisation d'une vidéo sur le r Enhancing Rural Connectivit En attente d'exéc IDA / D6690 A posteriori ur les qualification Limited 0.00 2020-06-10 2020-06-24 2020-07-24 2020-08-28 2021-02-24 uissellement de l'eau dans le y ution s des consultants s bassins versants en zone ur baine en Haïti INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDV-001-PARR/2019 / Resp En attente d'exéc onsable conformité et des as IDA / D3230 Project Management A posteriori Individuel Open 0.00 2019-02-11 2019-03-14 2019-03-17 2019-04-01 2019-09-30 ution pects de S&E à l'UCE INDV-003-PARR/2019 / Spéci En cours d'exécut aliste en Genre et en Sauveg IDA / D3230 Project Management A posteriori Individuel Open 0.00 2019-02-11 2019-03-13 2019-03-14 2019-03-17 2019-04-01 2019-09-30 ion ardes Sociales à l'UCE INDV-004-PARR/2019 / Assis En cours d'exécut IDA / D3230 Project Management A posteriori Individuel Open 0.00 2019-02-11 2019-02-12 2019-03-14 2019-03-17 2019-04-01 2019-09-30 tant en Passation des Marché ion s à l'UCE INDV-005-PARR/2019 / Assis En cours d'exécut IDA / D3230 Project Management A posteriori Individuel Open 0.00 2019-02-11 2019-02-14 2019-03-14 2019-03-17 2019-04-01 2019-09-30 tant Administratif à l'UCE ion INDV-006-PARR/2019 / Com En cours d'exécut IDA / D3230 Project Management A posteriori Individuel Open 0.00 2019-02-11 2019-02-12 2019-03-14 2019-03-17 2019-04-01 2019-09-30 ptable Sénior à l'UCE ion INDV-007-PARR/2019 / Infor En cours d'exécut IDA / D3230 Project Management A posteriori Individuel Open 0.00 2019-02-11 2019-02-14 2019-03-14 2019-03-17 2019-04-01 2019-09-30 maticien à l'UCE ion INDV-008-PARR/2019 / Speci En attente d'exéc IDA / D3230 Project Management A posteriori Individuel Open 0.00 2019-02-11 2019-03-14 2019-03-17 2019-04-01 2019-09-30 aliste en Suivi-Evaluation ution ED-002-PARR/2019 / Assista nce technique pour le renforc Sélection de cons En attente d'exéc ement de l’UCE dans la gesti IDA / D3230 Project Management A posteriori ultants par entent Direct 0.00 2019-06-20 2019-06-30 2019-07-25 2020-05-20 ution on des sauvegardes environn e directe ementales et sociales INDV-002-PARR/2019 / Char IDA / D3230 Project Management A posteriori Individuel Open 0.00 Annulé 2019-02-11 2020-11-06 2019-03-14 2019-03-17 2019-04-01 2019-09-30 gé de Projet du PARR à l'UCE INDV-002-PARR/2021 / Char En attente d'exéc IDA / D3230 Project Management A posteriori Individuel Open 0.00 2020-11-06 2020-12-25 2021-01-15 2021-02-19 2022-02-19 gé de Projet du PARR à l'UCE ution INDV-001-PARR/2021 / Spéci En attente d'exéc aliste en Sauvegardes Enviro IDA / D3230 Project Management A posteriori Individuel Open 0.00 2020-11-06 2020-12-25 2021-01-15 2021-02-19 2022-02-19 ution nnementales INDV-001-CIAT-PARR/2020 / En attente d'exéc Recrutement d'un consultant IDA / D6690 Project Management A posteriori Individuel Limited 0.00 2020-06-10 2020-06-30 2020-07-29 2020-09-02 2021-01-30 ution Charge du monitoring et du r eporting INDV-009-PARR/2021 / Supe rvision des Travaux de Points En attente d'exéc IDA / D3230 Project Management A posteriori Individuel Limited 0.00 2021-05-27 2021-05-30 2021-06-09 2021-06-29 2021-12-06 critiques: Colline d'Aquin - Fo ution nds des Blancs (Lots 1 à 3) INDV-010-PARR/2021 / Supe rvision des Travaux de Points En attente d'exéc IDA / D3230 Project Management A posteriori Individuel Limited 0.00 2021-05-27 2021-05-30 2021-06-09 2021-06-29 2021-12-06 critiques: Petit Trou de Nippe ution s - Baradères (Lots 1 et 2) INDV-011-PARR/2021 / Supe En attente d'exéc rvision des Travaux de Points IDA / D3230 Project Management A posteriori Individuel Limited 0.00 2021-05-27 2021-05-30 2021-06-09 2021-06-29 2021-12-06 ution critiques: Thiotte - Anse-à-Pit res (Lot 1) INDV-012-PARR/2021 / Supe rvision des Travaux de Points En attente d'exéc IDA / D3230 Project Management A posteriori Individuel Limited 0.00 2021-05-27 2021-05-30 2021-06-09 2021-06-29 2021-12-06 critiques: Tikita et 3 Dalots Ja ution cmel-Marigot (Lots 1 à 3) Page 4 INDV-013-PARR/2021 / Supe rvision des Travaux de Points En attente d'exéc IDA / D3230 Project Management A posteriori Individuel Limited 0.00 2021-05-27 2021-05-30 2021-06-09 2021-06-29 2021-12-06 critiques: Colline d'Aquin - Fo ution nds des Blancs (Lots 4 et 5) INDV-014-PARR/2021 / Supe rvision des Travaux de Points En attente d'exéc IDA / D3230 Project Management A posteriori Individuel Limited 0.00 2021-05-27 2021-05-30 2021-06-09 2021-06-29 2021-12-06 critiques: Colline d'Aquin - Fo ution nds des Blancs (Lots 6 et 7) INDV-015-PARR/2021 / Supe rvision des Travaux de Points En attente d'exéc IDA / D3230 Project Management A posteriori Individuel Limited 0.00 2021-05-27 2021-05-30 2021-06-09 2021-06-29 2021-12-06 critiques: Petit Trou de Nippe ution s - Baradères (Lot 3) INDV-016-PARR/2021 / Supe rvision des Travaux de Points En attente d'exéc IDA / D3230 Project Management A posteriori Individuel Limited 0.00 2021-05-27 2021-05-30 2021-06-09 2021-06-29 2021-12-06 critiques: Tikita et 3 Dalots Ja ution cmel-Marigot (Lot 4 - Tikita) INDV-017-PARR/2021 / Supe En attente d'exéc rvision des Travaux de Points IDA / D3230 Project Management A posteriori Individuel Limited 0.00 2021-05-27 2021-05-30 2021-06-09 2021-06-29 2021-12-06 ution critiques: Thiotte - Anse-à-Pit res (Lot 2) MTPTC/UCE/PARR-22/DINEPA /CS/INDV-002 / Un (1) Respo Contingent Emergency Resp En attente d'exéc nsable de gestion administra IDA / D3230 A posteriori Individuel Limited 0.00 2022-03-25 2022-03-30 2022-04-20 2022-05-25 2022-11-21 onse ution tive en appui à la passtion de marchés pour ce projet INDV-001-DINEPA/PARR/202 Sélection de cons 2 / Recrutement d'Un (1) Res Contingent Emergency Resp En attente d'exéc IDA / D3230 A posteriori ultants par entent Direct 0.00 2022-06-06 2022-06-16 2022-08-20 2023-03-16 ponsible de liaison avec l'UC onse ution e directe E et du suivi technique et ad ministratif des activités INDV-002-DINEPA/PARR/202 2 / Recrutement d'Un (1) Env Sélection de cons Contingent Emergency Resp En attente d'exéc ironnementaliste Junior en ap IDA / D3230 A posteriori ultants par entent Direct 0.00 2022-06-08 2022-06-18 2022-08-22 2023-02-18 onse ution pui à la cellule environnemen e directe tale et sociale de la DINEPA INDV-003-DINEPA/PARR/202 2 / Recrutement d'Un (1) Spé Contingent Emergency Resp En attente d'exéc IDA / D3230 A posteriori Individuel Limited 0.00 2022-06-08 2022-06-13 2022-07-04 2022-08-08 2023-02-04 cialiste Junior en appui à la p onse ution asstion de marchés pour ce p rojet RECRUTEMENT D'UN (1) SUP ERVISEUR DES TRA / Recrute ment d'Un (1) Superviseur de Contingent Emergency Resp En attente d'exéc IDA / D3230 A posteriori Individuel Limited 0.00 2022-06-23 2022-06-28 2022-07-19 2022-08-23 2023-03-23 s travaux de reconstruction d onse ution u captage sur la rivière de Pé dernales à Anse-à-Pitre,Sud'E st INDV-005-DINEPA/PARR/202 2 / Recrutement d'un Supervi Contingent Emergency Resp En attente d'exéc seurs des travaux de remise IDA / D3230 A posteriori Individuel Limited 0.00 2022-07-06 2022-07-11 2022-08-01 2022-09-05 2023-02-07 onse ution en état des SAEP de Baconoi s, de Mathurin et de St. Mich el dans les Nippes INDV-006-DINEPA/PARR/202 2 / Recrutement d'un Supervi Sélection de cons Contingent Emergency Resp En attente d'exéc seurs des travaux de remise IDA / D3230 A posteriori ultants par entent Direct 0.00 2022-06-16 2022-06-26 2022-08-30 2023-01-26 onse ution en état des SAEP de St. Louis e directe du Sud et de Ferme-le Blanc dans le Sud INDV-007-DINEPA/PARR/202 2 / Recrutement d'un Supervi Sélection de cons seur des travaux de remise e Contingent Emergency Resp En attente d'exéc IDA / D3230 A posteriori ultants par entent Direct 0.00 2022-06-09 2022-06-19 2022-08-23 2023-01-20 n état du SAEP de Madame B onse ution e directe ernard (Ile-à-Vache) et de ré paration du SAEP de Roche-à -Bateau INDV-008-DINEPA/PARR/202 2 / Recrutement d'un Supervi Sélection de cons Contingent Emergency Resp En attente d'exéc seur des travaux de renforce IDA / D3230 A posteriori ultants par entent Direct 0.00 2022-06-08 2022-06-18 2022-08-22 2023-01-09 onse ution ment des SAEP de Laurent (S e directe UD) et de la Digue à Jérémie (Grand'Anse) INDV-009-DINEPA/PARR/202 2 / Recrutement d'un Supervi Contingent Emergency Resp En attente d'exéc seur des travaux de réhabilit IDA / D3230 A posteriori Individuel Limited 0.00 2022-06-22 2022-06-27 2022-07-18 2022-08-22 2023-01-20 onse ution ation des SAEP du centre-vill e de les Irois de Déranger de Remy à Abricot INDV-001-PARR/2022 / VIDÉ En attente d'exéc ASTE CHARGÉ.E DE LA RÉALI IDA / D3230 Project Management A posteriori Individuel Limited 0.00 2022-06-24 2022-06-29 2022-07-20 2022-08-24 2022-10-20 ution SATION DE PRODUITS AUDIO- VISUELS Page 5