PROCUREMENT PLAN WEST BENGAL MAJOR IRRIGATION & FLOOD MANAGEMENT PROJECT IRRIGATION & WATERWAYS DEPARTMENT WEST BENGAL May 2019 1 I. General 1. Project information Country : India Borrower : Government of India Project Name : West Bengal Major Irrigation & Flood management Project Project Identification No (ID) : P168999 Project Implementing Agency (PIA): Irrigation & Waterways Department 2. Bank’s last archived approval Date : July 9,2019 Procurement Plan 3. Date of General Procurement Notice: January 17,2017 4. Applicable Bank Guideline: For Goods ,Works ,Consultancy and Non- consulting Services : Procurement Regulations for IPF Borrowers , July 2016,Revised November 2017 and August 2018 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, Revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. 2 II. Goods, Works and Non-Consulting Services Categ Method of Threshold (US$ Equivalent)* Prior review threshold ory Procurement Goods International Contracts more than the equivalent and competitive Bidding of US$ 3 million per contract All ICB, LIB and Framework Non- Contracts . consulti Limited International As per para 6.12 of the Procurement ng Bidding regulations for IPF Borrowers ,July All other contracts equal to service 2016 . or greater than s National competitive Contracts more than the equivalent US$2million equivalent; Bidding of US$ 100,000 but less than the equivalent of US$ 3 million per contract and as per para 6.15 to 6.18 of the Procurement regulations for IPF Borrowers ,July 2016 (with NCB conditions) Shopping ** Contracts equivalent of US$ 100,000 or less per contract. Direct Selection Proprietary software; educational journals and other procurement justified as per para 6.8 to 6.10 of the Bank procurement regulation for IPF Borrowers. Force Account As per para 3.9 of Guidelines Community Driven As per para 6.52-6.53 of Bank Development # procurement regulation for IPF Borrowers Framework As per para 6.57 to 6.59 of Bank Agreements@ procurement regulation for IPF Borrowers Guidelines Works International Civil works more or equivalent of All ICB contracts and Force Competitive Bidding US$40,000,000 per contract Account contracts. National competitive Civil works more than $10000 and Bidding Up to $40,000,000 per contract All other contracts equal to (with NCB conditions) or greater than US$10 Shopping** Civil works Up to $100,000 per million equivalent contract Direct Selection as per para 6.8 to 6.10 of the Bank procurement regulation for IPF Borrowers. Community Driven As per para 6.52-6.53 of Bank Development procurement regulation for IPF (CDD)# Borrowers 3 Categ Method of Threshold (US$ Equivalent)* Prior review threshold ory Procurement Force Account As per para 6.54 to 6.55 of Bank procurement regulation for IPF Borrowers Consult Consultant Contracts Up to $300,000 or less per All contracts equal to or ants’ Qualification /Least contract greater than US$ 1 Million Service cost selection equivalent for firms; and s Direct selection As per para 7.13 to 7.15 of Bank equal to or greater than procurement regulation for IPF US$300,000 equivalent for Borrowers individuals Individual Contracts As per para 7.34 to 7.39 of Bank procurement regulation for IPF Borrowers Quality and cost for All other Contracts Based selection /Quality Based Selection /Fixed Based Selection (i) International >$800,000 shortlist (ii) Shortlist may Up to $800,000 comprise national consultants only * If a transaction comprises several contracts, lots or slices, the aggregate estimated value of all contracts, lots or slices will determine the applicable threshold amount# **State Rate Contracts cannot be used at par with Shopping. If state rate contract exists for an item, the same can be considered as one of the 3 quotations to be sought under shopping procedures. .#Community Driven Development would be based on World Bank “Guidance Note For Management of Procurement Responsibilities In Community-Driven Development Projects dated December 2009 and as included in the Procurement manual. 2. Pre-qualification: Not Applicable 3. Reference to Project Procurement Manual: A Procurement Manual based on World Bank Procurement Regulations for IPF Borrowers, July 2016 shall be prepared. All procurements in the project will be governed by the procedures described in the Manual. In case of any inconsistency between the Procurement 4 Manual and the World Bank Procurement Regulation for IPF Borrower, July 2016 , the provisions of the Regulation shall prevail. 4. Any Other Special Procurement Arrangements (Goods & Works) : A. Contracts procured in advance will be financed under retroactive financing within the specified limits, as agreed to in the Credit Agreement provided they are procured in accordance with agreed processes and procedures for the project and have been cleared as part of procurement plan. B. National Competitive Bidding (NCB) method for procurement of goods, works and non-consulting services as per the above value thresholds will be conducted in accordance with the World Bank Procurement Regulation and the following provisions: National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used.When the Borrower uses national open competitive procurement arrangements it shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: 1) Only the model bidding documents for National Competitive Procurement (NCP) agreed with the GOI Task Force (and as amended for time to time) shall be used for bidding. 2) Open advertising of the procurement opportunity will be required, including giving adequate time for submission of bids. 3) No special preference will be accorded to any bidder either for price or for other terms and conditions when competing with foreign bidders, state-owned enterprises, small-scale enterprises or enterprises from any given State. 4) Except with the prior concurrence of the Bank, there shall be no negotiation of price with the bidders, even with the lowest evaluated bidder. 5) Government e-Marketplace (GeM) set-up by Ministry of Commerce, Government of India will not be acceptable except for procurement under RFQ method. 6) At the Borrower’s request, the Bank may agree to the Borrower’s use, in whole or in part, of its electronic procurement system, provided that the Bank is satisfied with the adequacy of such system. 7) Procurement will be open to eligible firms from any country. This eligibility shall be as defined under Section III of the Procurement Regulations. Accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. 8) The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance (in the form attached) at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti- Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. 5 9) Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts 10) The Borrower shall use an effective mechanism for resolving procurement related complaints in a timely manner. When other national procurement arrangements (other than national open competitive procurement) are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: “Not Applicable” Procurement of Second Hand Goods “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works) : Goods/Works : “Not Applicable” Selection of Consultants 1. Methods and Value thresholds for Consultancy Services Consultin Methods Value Review Arrangements g Services Threshold*/Regu lation Provision Consulting i) Quality and Cost All contracts valued above Services Based Selection US$ 1 Million will be (Firms) (QCBS) subject to Prior Review by ii) Quality Based the World Bank. All other Selection (QBS) contracts will be subject iii) Selection based to post review. on a Fixed Budget (FBS) All Direct selection shall iv) Selection Based be in accordance with on Least Cost para 7.13 to 7.15 of the Basis (LCS) Bank Procurement v) (Selection based Contracts Regulation for IPF on Consultant’s estimated to cost Borrowers. Qualification equivalent of US$ (CQS) 300,000 or less per contract. vi) Direct Selection In accordance with para 7.13 to 7.15 Individual i) Competitive Procurement to be All contracts valued above Consultant Selection in accordance with US$ 300,000 will be s para 7.34 to 7.38 subject to Prior Review by of Bank the World Bank. All other procurement contracts will be subject regulation for IPF to post review. Borrowers 6 Consultin Methods Value Review Arrangements g Services Threshold*/Regu lation Provision ii) Direct Selection All Direct selection to be # Prior approved in as per para 7.39 of procurement plan and in Bank procurement accordance with para 7.39 regulation for IPF of the Bank Procurement Borrowers Regulation for IPF Borrowers. * If a transaction comprises several packages, lots or slices, the aggregate estimated value of contracts will determine the applicable threshold amount. # Irrespective of contract value any hiring of Government or Research Institutes of unique and exceptional nature requires prior no objection of the World Bank on case to case basis. 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than US $800,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of Para 2.7 the World Bank Consultant Guidelines. 3. Any Other Special Selection Arrangements (Consulting Services) : (a) Contracts procured in advance will be financed under retroactive financing within the specified limits, as agreed to in the Credit Agreement provided procurement is in accordance with agreed processes and procedures for the project. (b) Requests for Expression of Interest (REOI) for assignments expected to cost more than US$ 300,000 shall be advertised in UNDB online in accordance with Para 2.5 of the Consultant Guidelines. (c) With respect to each contract for the employment of individual consultants estimated to cost the equivalent of US $ 30,000 or more, the qualifications, experience, terms of reference and terms of employment of the consultants shall be furnished to the World Bank for its prior review and No Objection. iv) Implementing Agency Capacity Building Activities with Time Schedule S. Expected outcome / Start Date Comments No. Activity Description 7 1 Training in World Bank online STEP Completed. 12 system June 2017 officials received STEP training 2 Training in New Procurement December 2019 Framework ------------------------------------------------------------------------------------------------------- ---- 8 PROCUREMENT India : West Bengal Major Irrigation and Flood Management Project PLAN General Information Country: India 2017-08-02 Bank’s Approval Date of the Original Procurement Plan: 2022-06-23 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P162679 GPN Date: 2018-12-03 Project Name: West Bengal Major Irrigation and Flood Management Project Loan / Credit No: / , IBRD / 90250, COFN / C1730 Irrigation and Waterways Department Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned IN-IWD-87231-CW-RFB / Floo d Protection Measures on Da modar Left Embankment wit h Flood Wall, Sheet Piles incl Component C: Flood Manage Single Stage - Two E 24,797,923.0 2019-11-1 / Prior Request for Bids Open - National 0.00 Canceled 2018-12-17 2019-01-28 2018-12-22 2019-01-30 2019-02-02 2019-05-13 2019-04-17 2019-05-22 uding Embankment Strength ment nvelope 0 8 ening on Countryside and Ba nk Protection Work on Riversi de in Purba Bardhaman & Ho oghly District (Package-I). IN-IWD-97488-CW-RFB / Floo d Protection Measures on the left embankment of Upper Ra mpur Khal with Flood Walls, Component C: Flood Manage Single Stage - Two E 20,791,468.0 24,997,450. 2020-01-0 / Prior Request for Bids Open - National Signed 2019-01-31 2019-02-18 2019-02-05 2019-02-19 2019-03-19 2019-05-30 2019-06-01 2019-10-18 2019-07-06 2020-01-24 Sheet Piles including Embank ment nvelope 0 24 2 ment Strengthening on Coun tryside and Bank Protection Works on the Riverside in the districts of Howrah and Hoog hly (Package-II) IN-IWD-97489-CW-RFB / Floo d Protection Measures on the left embankment of Hurhura Component C: Flood Manage Single Stage - Two E 12,735,055.0 17,268,299. 2020-01-0 h Khal with Flood Walls, She / Prior Request for Bids Open - National Signed 2019-02-01 2019-02-14 2019-02-06 2019-02-15 2019-03-20 2019-05-21 2019-06-02 2019-10-18 2019-07-07 2020-01-24 ment nvelope 0 30 3 et Piles including Embankme nt Strengthening on Countrys ide in the districts of Howrah and Hooghly (Package-III). IN-IWD-97491-CW-RFB / Floo d Protection Measures on Da modar Left Embankment wit h Flood Wall, Sheet Piles, Ban Component C: Flood Manage Single Stage - Two E 24,882,122.0 30,282,904. Under Revie 2020-01-0 k Protection & Strengthening / Prior Request for Bids Open - National 2019-02-04 2019-02-14 2019-02-09 2019-02-15 2019-03-23 2019-05-21 2019-06-05 2019-10-18 2019-07-10 2020-01-24 ment nvelope 0 42 w 6 of Embankments, Armouring over Damodar Right Dwarf E mbankment at different locat ions & Bank Protection along Damodar Right Bank in Howr ah. IN-IWD-102267-CW-RFB / De siltation of Mundeswari River Component C: Flood Manage Single Stage - Two E 19,762,707.0 4,465,459.9 2020-01-2 from Ch. 5.00 km to 19.00 k / Prior Request for Bids Open - National Signed 2019-02-25 2019-02-25 2019-03-02 2019-02-27 2019-04-13 2019-07-31 2019-06-26 2019-11-14 2019-07-31 2020-01-31 ment nvelope 0 7 7 m in the districts of Purba B ardhaman and Hooghly - Pak age V. IN-IWD-102283-CW-RFB / De -Siltation of Madaria Khal fro Component C: Flood Manage Single Stage - Two E 3,653,946.4 2020-02-0 / Post Request for Bids Open - National 3,762,988.00 Signed 2019-03-06 2019-03-01 2019-03-11 2019-04-22 2019-08-09 2019-07-05 2019-09-23 2019-08-09 2020-01-24 m Ch. 0.00 km to 4.50 Km in ment nvelope 6 5 the district of Howrah - Packa ge VI IN-IWD-102286-CW-RFB / De -Siltation of Madaria Khal fro Component C: Flood Manage Single Stage - Two E 3,689,952.8 2020-02-0 / Post Request for Bids Open - National 3,719,461.00 Signed 2019-03-06 2019-03-04 2019-03-11 2019-06-25 2019-04-22 2019-08-20 2019-07-05 2019-09-23 2019-08-09 2020-01-24 m Ch. 4.50 km to 8.40 Km in ment nvelope 6 5 the district of Howrah, Packa ge VII. IN-IWD-102291-CW-RFB / De -Siltation of Madaria Khal fro Component C: Flood Manage Single Stage - Two E 3,623,151.7 2020-02-0 / Post Request for Bids Open - National 3,625,386.00 Signed 2019-03-06 2019-03-04 2019-03-11 2019-06-25 2019-04-22 2019-08-27 2019-07-05 2019-09-23 2019-08-09 2020-01-24 m Ch. 8.40 km to 12.90 Km i ment nvelope 3 5 n the district of Howrah, Pack age VIII. IN-IWD-104739-CW-RFB / De siltation of Roner Khal from C Component C: Flood Manage Single Stage - Two E 1,928,250.4 2020-06-0 / Post Request for Bids Open - National 1,817,014.00 Signed 2019-07-09 2019-03-07 2019-07-14 2019-07-12 2019-08-25 2019-08-09 2019-11-07 2019-09-23 2019-12-12 2020-01-24 h. 0.00 Km to 18.66 Km in th ment nvelope 6 9 e districts of Hooghly and Ho wrah, Package - IX. IN-IWD-145973-CW-RFB / De siltation of Mundeswari River Component C: Flood Manage Single Stage - Two E 14,933,523.0 16,376,965. Under Revie 2020-10-2 from Ch. 5.00 Km to 19.00 K / Prior Request for Bids Open - National 2019-11-19 2019-12-05 2019-11-24 2019-12-12 2020-01-05 2020-01-14 2020-03-19 2020-04-17 2020-04-23 2020-07-31 ment nvelope 0 25 w 0 m in the districts of Purba Ba rdhaman and Hooghly - Pack age – V comprising two lots. IN-IWD-161145-CW-RFB / Flo od Protection Measures on D amodar Left Embankment wi th Floodwall Sheet Piles inclu Component C: Flood Manage Single Stage - Two E 24,797,923.0 25,789,621. 2021-01-3 IBRD / 90250 Prior Request for Bids Open - National Signed 2020-02-29 2020-03-05 2020-04-16 2019-05-13 2020-06-29 2021-12-01 2020-08-03 2020-05-20 ding Embankment Strengthe ment nvelope 0 71 0 ning on Countryside and Ban k Protection Work on Riversid e in Purba Bardhaman & Hoo ghly District (Package-I). IN-IWD-182910-CW-RFB / Im provement of Lower Reach of Right Bank Main Canal (RB Component B: Modernizatio Single Stage - Two E 18,382,249.0 20,385,283. 2021-06-1 IBRD / 90250 Prior Request for Bids Open - National Signed 2020-07-15 2020-09-29 2020-07-20 2020-10-01 2020-08-31 2020-11-06 2020-11-13 2021-01-08 2020-12-18 2021-02-08 MC-Lower) from 50.84 km to n of Irrigation Infrastructure nvelope 0 20 6 85.344 km including all its ap purtenant canals within the r each. IN-IWD-182917-CW-RFB / Im provement of Panagarh Bran Component B: Modernizatio Single Stage - Two E 18,096,490.0 19,877,826. 2021-06-1 ch Canal (PBC) from 0.00 km IBRD / 90250 Prior Request for Bids Open - National Signed 2020-07-15 2020-09-25 2020-07-20 2020-09-28 2020-08-31 2020-11-03 2020-11-13 2021-01-08 2020-12-18 2021-02-08 n of Irrigation Infrastructure nvelope 0 94 6 to 91.775 km including all its appurtenant canals within th e reach. IN-IWD-186922-CW-RFB / Im provement of Durgapur Bran Component B: Modernizatio Single Stage - Two E 9,862,318.7 2021-07-1 ch Canal (DBC) from 0.00 k IBRD / 90250 Post Request for Bids Open - National 9,361,126.00 Signed 2020-08-10 2020-10-06 2020-08-15 2020-10-05 2020-09-26 2020-11-05 2020-12-09 2021-01-06 2021-01-13 2021-02-08 n of Irrigation Infrastructure nvelope 5 2 m to 57.912 km including all its appurtenant canals within the reach. (Package-IRR-03) Page 1 IN-IWD-186924-CW-RFB / Im provement of Damodar Main Component B: Modernizatio Single Stage - Two E 19,165,876.0 20,451,378. 2021-07-1 Canal (DMC) from 0.00 km t IBRD / 90250 Prior Request for Bids Open - National Signed 2020-08-10 2020-10-05 2020-08-15 2020-10-08 2020-09-26 2020-11-13 2020-12-09 2021-01-19 2021-01-13 2021-02-10 n of Irrigation Infrastructure nvelope 0 76 2 o 43.34 km including all its a ppurtenant canals within the reach. (Package - IRR-04) IN-IWD-191034-CW-RFB / Im provement of Branches of Lo wer Reach of New Gangur b eyond 37.125 km & Lower Re Component B: Modernizatio Single Stage - Two E 6,668,371.0 2021-08-0 IBRD / 90250 Post Request for Bids Open - National 6,103,399.00 Signed 2020-09-04 2020-10-07 2020-09-09 2020-10-07 2020-10-21 2020-11-09 2021-01-03 2021-01-07 2021-02-07 2021-02-09 ach of Behula from 11.033 k n of Irrigation Infrastructure nvelope 6 6 m to 50.841 km (New Gangu r & Behula-Lower) including all its appurtenant canals wit hin the reach. Package IRR-0 5 IN-IWD-191039-CW-RFB / Im provement of Lower Reache s of Branch-1 (from 23.774 k m to 44.196 km) and Branch Component B: Modernizatio Single Stage - Two E 8,038,283.3 2021-08-0 IBRD / 90250 Post Request for Bids Open - National 7,514,730.00 Signed 2020-09-04 2020-10-08 2020-09-09 2020-10-07 2020-10-21 2020-11-10 2021-01-03 2021-01-08 2021-02-07 2021-02-09 -2 (from 8.352 km to 13.716 n of Irrigation Infrastructure nvelope 7 6 km) of Eden Canal (Branch-1 and Branch-2-Lower) includi ng all its appurtenant canals within the reach. Package IR R-06. IN-IWD-196592-CW-RFB / “D esiltation of Mundeswari Rive r from Ch. 0.00 Km to 5.00 K Component C: Flood Manage Single Stage - Two E 12,027,646.5 11,155,379. 2021-09-0 COFN / C1730 Prior Request for Bids Open - National Signed 2020-10-02 2020-10-26 2020-10-07 2020-10-28 2020-11-18 2020-12-02 2021-01-31 2021-02-01 2021-03-07 2021-02-10 m and u/s of bifurcation point ment nvelope 2 99 3 for a length of 370 m in the d istrict of Purba Bardhaman - Package – X” comprising thre e lots. IN-IWD-254397-CW-RFQ / Sp ecial Repair of Inspection Bu Request for Quota ngalow, office building and re Component D: Project Mana Request for Quota Single Stage - One E tions - Small Work Under Imple 2022-05-2 pair of S.D.O. type quarter fo COFN / C1730 Post Open - National 87,438.76 0.00 2021-10-03 2021-12-28 2021-11-28 gement tions nvelope s (Emergency) SP mentation 7 r Project Management Consul D -Competitive tancy Office under Right Ban k Irrigation Division, Sonamu khi, Bankura, Govt. of West B engal. IN-IWD-254433-CW-RFB / Im provement of Upper Reach of Request for Bids - Left Bank Main Canal (LBMC- Component B: Modernizatio Single Stage - Two E Works (without pr 21,676,162.0 24,125,295. 2022-09-0 COFN / C1730 Prior Request for Bids Open - National Signed 2021-09-30 2021-10-08 2021-10-05 2021-11-01 2021-11-16 2021-12-29 2022-01-29 2022-03-15 2022-03-05 2022-05-13 Upper) from 0.00 km to 68.5 n of Irrigation Infrastructure nvelope equalification) SP 6 63 1 8 km including all its appurte D nant L4 canals within the rea ch. IRR-07 IN-IWD-254437-CW-RFB / Im provement of Upper Reaches of Branch-1 (from 0.00 km to Request for Bids - 23.774 km) & Branch-2 (from Component B: Modernizatio Single Stage - Two E Works (without pr 10,079,936.5 9,835,965.9 2022-09-0 COFN / C1730 Prior Request for Bids Open - National Signed 2021-09-30 2021-10-08 2021-10-05 2021-11-08 2021-11-16 2021-12-17 2022-01-29 2022-03-06 2022-03-05 2022-04-13 0.00 km to 8.352 km) of Ede n of Irrigation Infrastructure nvelope equalification) SP 0 5 1 n Canal (Branch-1 & Branch- D 2-Upper) including all its app urtenant canals within the re ach. IRR-12 (Comprising four Lots) IN-IWD-254434-CW-RFB / Im provement of Upper Reach of Request for Bids - Right Bank Main Canal (RBM Component B: Modernizatio Single Stage - Two E Works (without pr 24,583,383.8 27,476,604. 2022-09-0 COFN / C1730 Prior Request for Bids Open - National Signed 2021-09-30 2021-10-08 2021-10-05 2021-11-03 2021-11-16 2021-12-31 2022-01-29 2022-04-14 2022-03-05 2022-05-26 C-Upper) from 0.00 km to 50. n of Irrigation Infrastructure nvelope equalification) SP 0 35 1 84 km including all its appurt D enant canals within the reach -IRR-09 (Comprising three Lo ts) IN-IWD-255664-CW-RFB / Im provement of Lower Reach of Request for Bids - Left Bank Main Canal (LBMC- Component B: Modernizatio Single Stage - Two E Works (without pr 9,769,769.1 2022-09-0 COFN / C1730 Post Request for Bids Open - National 8,768,205.36 Signed 2021-10-07 2021-10-27 2021-10-12 2021-11-02 2021-11-23 2021-12-30 2022-02-05 2022-03-03 2022-03-12 2022-04-29 Lower) from 68.58 km to 96. n of Irrigation Infrastructure nvelope equalification) SP 2 8 62 km including all its appurt D enant L4 canals within the re ach. IRR-08. IN-IWD-255666-CW-RFB / Im provement of No.6 Main Can Request for Bids - al (6 MC) from 0.00 km to 38 Component B: Modernizatio Single Stage - Two E Works (without pr 10,517,178. 2022-09-0 COFN / C1730 Post Request for Bids Open - National 9,024,342.56 Signed 2021-10-07 2021-11-11 2021-10-12 2021-11-16 2021-11-23 2022-01-10 2022-02-05 2022-04-27 2022-03-12 2022-06-08 .10 km including all its appur n of Irrigation Infrastructure nvelope equalification) SP 96 8 tenant canals within the rea D ch. IRR-10 (Comprising four L ots) IN-IWD-255667-CW-RFB / Im Request for Bids - provement of Kana Damoda Component B: Modernizatio Single Stage - Two E Works (without pr 11,490,896.9 10,067,694. Under Imple 2022-09-0 r from 0.00 km to 52.791 km COFN / C1730 Prior Request for Bids Open - National 2021-10-07 2021-11-15 2021-10-12 2021-11-16 2021-11-23 2022-01-25 2022-02-05 2022-06-02 2022-03-12 n of Irrigation Infrastructure nvelope equalification) SP 6 62 mentation 8 including all its appurtenant D canals within the reach. IRR- 14 (Comprising four Lots) IN-IWD-262203-CW-RFQ / Re furbishment of Office Buildin Request for Quota g at Penro Irrigation Campus Component D: Project Mana Request for Quota Single Stage - One E tions - Small Work Under Imple 2022-07-2 COFN / C1730 Post Open - National 70,867.00 0.00 2021-11-30 2021-11-25 2022-01-25 in Block Udaynarayanpur, Ho gement tions nvelope s (Emergency) SP mentation 4 wrah District, under Howrah I D -Competitive rrigation Division, I&W Direct orate Govt. of West Bengal. IN-IWD-273713-CW-RFB / Im provement of Upper Reaches of Br-1 (from 0.00 km to 23.7 Request for Bids - 74 km) & Br-2 (from 0.00 km Component B: Modernizatio Single Stage - Two E Works (without pr 2,014,172.7 2022-12-2 COFN / C1730 Post Request for Bids Open - National 1,722,751.00 Signed 2022-01-27 2022-01-28 2022-02-01 2022-01-27 2022-03-15 2022-03-02 2022-05-28 2022-04-22 2022-07-02 2022-05-19 to 8.352 km) of Eden Canal ( n of Irrigation Infrastructure nvelope equalification) SP 2 9 Br-1 & Br-2-Upper) including D all its appurtenant canals wit hin the reach. IRR-12. Lot-1: f rom 0.00 km to 9.144 km of Br - 1. (2nd Call) IN-IWD-280322-CW-RFQ / To Request for Quota pographical Survey and Geo- Component C: Flood Manage Request for Quota Single Stage - One E tions - Small Work Pending Imp 2022-10-2 COFN / C1730 Post Limited 79,358.40 0.00 2022-03-03 2022-04-28 technical Investigation works ment tions nvelope s (Emergency) SP lementation 5 of Package FM-11. D -Competitive IN-IWD-281992-CW-RFB / Im provement of Kana Damoda r from 0.00 km to 52.791 km Request for Bids - including all its appurtenant Component B: Modernizatio Single Stage - Two E Works (without pr 2,918,337.5 Under Imple 2023-02-0 COFN / C1730 Post Request for Bids Open - National 2,564,234.38 2022-03-05 2022-03-03 2022-03-10 2022-03-03 2022-04-21 2022-04-05 2022-07-04 2022-05-20 2022-08-08 canals within the reach. IRR- n of Irrigation Infrastructure nvelope equalification) SP 2 mentation 4 14, Lot-2: Improvement of D- D 1 canal of Kana Damodar fro m 0.00Km to 48.77Km includ ing all its appurtenant canals (2nd Call). IN-IWD-283731-CW-RFQ / Im Request for Quota provement of Subsided porti Component C: Flood Manage Request for Quota Single Stage - One E tions - Small Work Pending Imp 2022-11-1 on of Madaria Left Bank Road COFN / C1730 Post Limited 97,485.32 0.00 2022-03-21 2022-05-16 ment tions nvelope s (Emergency) SP lementation 2 , near Kanpur, Udaynarayanp D -Competitive ur Block in the district of How rah. Page 2 IN-IWD-292418-CW-RFQ / Me asurement of discharge and Component D: Project Mana Request for Quota Single Stage - One E Other (with field f Pending Imp 2022-12-2 sediment load of River Damo COFN / C1730 Post Limited 6,531.68 0.00 2022-05-07 2022-07-02 gement tions nvelope or explanation) lementation 9 dar at Jamalpur, Purba Bardh aman during the Monsoon' 2 022. IN-IWD-292431-CW-RFQ / Me asurement of discharge and Component D: Project Mana Request for Quota Single Stage - One E Other (with field f Pending Imp 2022-12-2 sediment load of River Rupna COFN / C1730 Post Limited 6,531.68 0.00 2022-05-07 2022-07-02 gement tions nvelope or explanation) lementation 9 rayan at Kolaghat, Purba Me dinipur during the Monsoon' 2022. GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-IWD-56868-GO-RFB / PRO CUREMENT OF IT EQUIPMENT INCLUDING COMPREHENSIVE ANNUAL MAINTENANCE CON Request for Quota Single Stage - One E / Post Open - National 92,223.00 0.00 Canceled 2018-05-02 2018-06-27 2018-12-24 TRACT FOR FOUR YEARS AFT tions nvelope ER WARRANTY PERIOD OF O NE YEAR UNDER WEST BENG AL MAJOR IRRIGATION AND F LOOD MANAGEMENT PROJEC T IN-IWD-153073-GO-DIR / Pro Component A: Irrigation Man curement of ArcGIS Desktop IBRD / 90250 Post Direct Selection Direct 127,910.22 122,728.01 Signed 2020-01-10 2020-01-06 2020-01-15 2019-12-19 2020-02-19 2020-02-26 2020-08-17 agement & ArcGIS Server software for WBMIFMP. IN-IWD-155355-GO-RFQ / Pr Component D: Project Mana Request for Quota Single Stage - One E ocurement of Desktop Comp IBRD / 90250 Post Limited 14,576.32 12,356.93 Signed 2020-03-10 2020-02-06 2020-05-05 2020-04-30 2020-11-01 gement tions nvelope uters for SPMU and DPMU-II u nder WBMIFMP. IN-IWD-155365-GO-RFQ / Pr ocurement of Desktop Comp Component D: Project Mana Request for Quota Single Stage - One E IBRD / 90250 Post Limited 14,691.25 13,438.10 Signed 2020-03-10 2020-10-12 2020-05-05 2020-12-08 2020-11-01 uters for DPIU and DPMU-I at gement tions nvelope Burdwan under WBMIFMP. IN-IWD-162692-GO-RFQ / Pr ocurement of Printer cum Mu Component A: Irrigation Man Request for Quota Single Stage - One E IBRD / 90250 Post Limited 6,793.00 6,190.04 Signed 2020-03-14 2020-07-14 2020-05-09 2020-08-06 2020-11-05 lti-functional Machines (MFM) agement tions nvelope for SPMU, DPMU – II and DPIU ’s under WBMIFMP. IN-IWD-162695-GO-RFQ / Pr ocurement of a Workstation c Component A: Irrigation Man Request for Quota Single Stage - One E IBRD / 90250 Post Limited 6,793.00 5,951.85 Signed 2020-03-14 2020-08-03 2020-05-09 2020-08-19 2020-11-05 um Hardware Server for SPM agement tions nvelope U under WBMIFMP. IN-IWD-162699-GO-RFQ / Pr ocurement of Survey instrum Component C: Flood Manage Request for Quota Single Stage - One E IBRD / 90250 Post Limited 4,997.00 0.00 Canceled 2020-03-14 2020-05-09 2020-11-05 ents and accessories for How ment tions nvelope rah Irrigation Division of DPM U – II under WBMIFMP. IN-IWD-183680-GO-RFQ / Pr ocurement of 10(Ten) Nos. of Black & White Laserjet Multif Component D: Project Mana Request for Quota Single Stage - One E IBRD / 90250 Post Limited 3,004.00 2,483.69 Signed 2020-07-18 2020-07-14 2020-09-12 2020-08-06 2021-03-11 unctional Machine and 01(On gement tions nvelope e) No. Colour Laserjet Multifu nctional Machine for SPMU & DPMU-II, under WBMIFMP. IN-IWD-183686-GO-RFQ / Pr Component D: Project Mana Request for Quota Single Stage - One E ocurement of 20(Twenty) No IBRD / 90250 Post Limited 865.00 414.33 Signed 2020-07-18 2020-08-01 2020-09-12 2020-08-13 2021-03-11 gement tions nvelope s. of UPS for SPMU & DPMU-II , under WBMIFMP. IN-IWD-183709-GO-RFQ / Pr ocurement of 07(Seven) Nos. Component D: Project Mana Request for Quota Single Stage - One E IBRD / 90250 Post Limited 10,847.00 7,874.37 Signed 2020-07-18 2020-09-04 2020-09-12 2020-11-09 2021-03-11 of Laptop for SPMU & DPMU-I gement tions nvelope I, under WBMIFMP. IN-IWD-183726-GO-RFQ / Pr ocurement of 02(Two) Nos. o Component D: Project Mana Request for Quota Single Stage - One E IBRD / 90250 Post Limited 5,015.00 3,780.44 Signed 2020-07-18 2020-07-14 2020-09-12 2020-08-06 2021-03-11 f colour Laser A3 Multifunctio gement tions nvelope nal Machine for SPMU & DPM U-II, under WBMIFMP. IN-IWD-190218-GO-RFQ / Pr ocurement of 12nos Microsof Component A: Irrigation Man Request for Quota Single Stage - One E IBRD / 90250 Post Open - National 4,714.00 5,135.06 Signed 2020-09-06 2020-11-01 2020-12-16 2021-04-30 t Office 2019 standard licens agement tions nvelope e for use in SPMU, DPMUs an d DPIUs of WBMIFMP IN-IWD-190220-GO-RFQ / Pr Component A: Irrigation Man Request for Quota Single Stage - One E Pending Impl ocurement of UPS for DPMU-I IBRD / 90250 Post Open - National 700.00 0.00 2020-09-06 2020-11-01 2021-04-30 agement tions nvelope ementation and DPIU at Burdwan under WBMIFMP IN-IWD-190221-GO-RFQ / Pr ocurement of 8(Eight) Nos. of Black & White Laserjet Multif Component A: Irrigation Man Request for Quota Single Stage - One E unctional Machine and 01(On IBRD / 90250 Post Open - National 3,000.00 711.14 Signed 2020-09-06 2020-11-01 2021-02-09 2021-04-30 agement tions nvelope e) No. Colour Laserjet Multifu nctional Machine for DPMU-I and DPIU at Burdwan under WBMIFMP. IN-IWD-202631-GO-RFQ / Su pply, fitting and fixing of new Component D: Project Mana Request for Quota Single Stage - One E office furniture at the office o COFN / C1730 Post Open - National 2,397.91 2,111.61 Signed 2020-11-11 2021-01-06 2020-10-08 2021-07-05 gement tions nvelope f APD-IV, DPMU-II, WBMIFMP, I&W Dte, 9th floor, Jalasampa d Bhawan, kolkata-700091 IN-IWD-202632-GO-RFQ / Su pplying and installation of vid Component D: Project Mana Request for Quota Single Stage - One E eo conferencing amenities at COFN / C1730 Post Open - National 7,024.47 6,674.91 Signed 2020-11-11 2021-01-06 2020-11-24 2021-07-05 gement tions nvelope 9th floor Conference Hall of S PMU, WBMIFMP, Jalasampad Bhawan, kolkata-700091 IN-IWD-202634-GO-RFQ / Su pplying MS Project Standard Component D: Project Mana Request for Quota Single Stage - One E 2019 with Software Assuranc COFN / C1730 Post Open - National 7,052.68 6,606.60 Signed 2020-11-11 2021-01-06 2020-12-03 2021-07-05 gement tions nvelope e in SPMU and DPIUs under WBMIFMP, I & W Dte, Govern ment of West Bengal Page 3 IN-IWD-215544-GO-RFQ / Pr Component A: Irrigation Man Request for Quota ocurement of ERDAS IMAGIN COFN / C1730 Post 36,906.00 35,919.45 Signed 2021-02-03 2021-03-31 2021-02-12 2021-09-27 agement tions E Software under WBMIFMP. IN-IWD-215554-GO-DIR / Pro Component A: Irrigation Man curement of MIKE Software u COFN / C1730 Post Direct Selection Direct 64,658.00 63,858.86 Signed 2021-01-29 2021-01-18 2021-02-03 2021-02-01 2021-03-10 2021-02-12 2021-09-06 agement nder WBMIFMP. IN-IWD-215563-GO-RFQ / Su pply installation & Commissio ning of video conferencing sy Component C: Flood Manage Request for Quota Single Stage - One E stem at office of the Executiv COFN / C1730 Post Limited 2,466.76 2,287.07 Signed 2021-02-03 2021-02-01 2021-03-31 2021-02-11 2021-09-27 ment tions nvelope e Engineer, Hooghly Irrigatio n Division and at office of the SDO, Mundeswari Irrigation S ub Division. IN-IWD-215556-GO-RFQ / Re newal of ArcGIS online for on Component D: Project Mana Request for Quota Single Stage - One E COFN / C1730 Post Open - National 5,677.00 5,533.07 Signed 2021-02-07 2021-04-04 2021-02-12 2021-10-01 e year in connection with dev gement tions nvelope elopment of MIS & Web-GIS u nder WBMIFMP. IN-IWD-211948-GO-RFQ / Pr Component A: Irrigation Man Request for Quota Single Stage - One E ocurement of Storage Access COFN / C1730 Post Limited 845.25 770.86 Signed 2021-02-07 2020-12-29 2021-04-04 2021-01-05 2021-10-01 agement tions nvelope ories for MIS & WebGIS under WBMIFMP. IN-IWD-234294-GO-RFQ / Pr ocurement of Desktop Comp Component D: Project Mana Request for Quota Single Stage - One E Under Imple COFN / C1730 Post Limited 7,972.00 0.00 2021-05-24 2021-07-19 2022-01-15 uters (9 Nos) for Howrah Irrig gement tions nvelope mentation ation Division under DPMU-II, of WBMIFMP IN-IWD-234296-GO-RFQ / Pr ocurement of UPS (9 Nos) for Component D: Project Mana Request for Quota Single Stage - One E Under Imple COFN / C1730 Post Limited 368.00 0.00 2021-05-24 2021-07-19 2022-01-15 Howrah Irrigation Division un gement tions nvelope mentation der DPMU-II, of WBMIFMP IN-IWD-234297-GO-RFQ / Pr ocurement of Multi Functiona Component D: Project Mana Request for Quota Single Stage - One E COFN / C1730 Post Limited 2,413.00 3,611.73 Signed 2021-05-24 2021-07-06 2021-07-19 2021-08-31 2022-01-15 l Printer A4 size (11 Nos) for gement tions nvelope Howrah Irrigation Division un der DPMU-II, of WBMIFMP IN-IWD-234298-GO-RFQ / Pr ocurement of Scanner Legal Component D: Project Mana Request for Quota Single Stage - One E Under Imple COFN / C1730 Post Limited 273.00 0.00 2021-05-24 2021-07-19 2022-01-15 size (4 Nos) for Howrah Irriga gement tions nvelope mentation tion Division under DPMU-II, of WBMIFMP IN-IWD-234299-GO-RFQ / Pr ocurement of Multi Functiona Component D: Project Mana Request for Quota Single Stage - One E COFN / C1730 Post Limited 5,162.00 4,126.70 Signed 2021-05-24 2021-07-05 2021-07-19 2021-08-31 2022-01-15 l Printer A3 size (3 Nos) for H gement tions nvelope owrah Irrigation Division und er DPMU-II, of WBMIFMP IN-IWD-234300-GO-RFQ / Pr ocurement of Toner for Multi Component D: Project Mana Request for Quota Single Stage - One E Functional Printer A3 size (5 COFN / C1730 Post Limited 394.00 5,327.05 Signed 2021-05-24 2021-02-03 2021-07-19 2021-02-09 2022-01-15 gement tions nvelope Nos) for Howrah Irrigation Di vision under DPMU-II, of WBM IFMP IN-IWD-240226-GO-RFQ / Re newal of license of Microsoft Component D: Project Mana Request for Quota Single Stage - One E Under Imple COFN / C1730 Post Limited 12,692.83 0.00 2021-07-19 2021-09-13 2022-03-12 Database Management Syste gement tions nvelope mentation m Software in connection wit h O&M of WBMIFMP MIS IN-IWD-254382-GO-DIR / Pro Component A: Irrigation Man Under Imple curement of High-Resolution COFN / C1730 Post Direct Selection Direct 108,666.12 0.00 2021-09-28 2021-09-29 2021-10-03 2021-11-07 2022-05-06 agement mentation Satellite Imageries from NRS C. IN-IWD-271066-GO-RFQ / Pr Component D: Project Mana Request for Quota Single Stage - One E Pending Impl ocurement of 1(one) no. A0 P COFN / C1730 Post Limited 5,978.50 0.00 2022-01-09 2022-03-06 2022-09-02 gement tions nvelope ementation lotter for SPMU. IN-IWD-271068-GO-RFQ / Pr ocurement of 1(one) no. A3 C Component D: Project Mana Request for Quota Single Stage - One E Pending Impl COFN / C1730 Post Limited 4,703.90 0.00 2022-01-09 2022-03-06 2022-09-02 olour Printer/Photocopier for gement tions nvelope ementation Howrah(I) Division. IN-IWD-271071-GO-RFQ / Pr Component D: Project Mana Request for Quota Single Stage - One E Pending Impl ocurement of 2 (two) nos. A4 COFN / C1730 Post Limited 1,908.00 0.00 2022-01-09 2022-03-06 2022-09-02 gement tions nvelope ementation Laserjet Colour Printer for DP MU-II and SPMU. IN-IWD-271072-GO-RFQ / Pr ocurement of 3(three) nos. Hi Component D: Project Mana Request for Quota Single Stage - One E Pending Impl COFN / C1730 Post Limited 1,550.30 0.00 2022-01-09 2022-03-06 2022-09-02 gh Speed Scanner for SPMU gement tions nvelope ementation and Howrah(I) Division IN-IWD-271073-GO-RFQ / Pr ocurement of 12(twelve) nos. Component D: Project Mana Request for Quota Single Stage - One E Pending Impl COFN / C1730 Post Limited 12,640.80 0.00 2022-01-09 2022-03-06 2022-09-02 Desktop Computer for DPMU- gement tions nvelope ementation I and Howrah(I) Division. IN-IWD-271074-GO-RFQ / Pr Component D: Project Mana Request for Quota Single Stage - One E Pending Impl ocurement of 3(three) nos. A COFN / C1730 Post Limited 989.80 0.00 2022-01-09 2022-03-06 2022-09-02 gement tions nvelope ementation 4 Black & White Printer for D PMU-I IN-IWD-271075-GO-RFQ / Pr ocurement of 12(twelve) nos. Component D: Project Mana Request for Quota Single Stage - One E Pending Impl COFN / C1730 Post Limited 443.70 0.00 2022-01-09 2022-03-06 2022-09-02 Line Intractive UPS with AVR gement tions nvelope ementation for DPMU-I and Howrah(I) Div ision IN-IWD-271077-GO-RFQ / Pr Component D: Project Mana Request for Quota Single Stage - One E Pending Impl ocurement of 2(two) nos. A3 COFN / C1730 Post Limited 2,782.60 0.00 2022-01-09 2022-03-06 2022-09-02 gement tions nvelope ementation Black & White Printer/Photoc opier for SPMU. IN-IWD-271079-GO-RFQ / Pr Component D: Project Mana Request for Quota Single Stage - One E Pending Impl ocurement of 2 (two) nos. La COFN / C1730 Post Limited 3,180.00 0.00 2022-01-09 2022-03-06 2022-09-02 gement tions nvelope ementation ptop for DPMU-I and DPMU-II IN-IWD-291952-GO-RFQ / Pr ocurement of 4 (four) nos. A3 Component D: Project Mana Request for Quota Single Stage - One E Pending Impl COFN / C1730 Post Limited 11,842.10 0.00 2022-05-02 2022-06-27 2022-12-24 Colour Printers for SPMU, DP gement tions nvelope ementation MU-I, DPIUs at Burdwan and Howrah. Page 4 IN-IWD-291953-GO-RFQ / Pr Component D: Project Mana Request for Quota Single Stage - One E Pending Impl ocurement of 1 (one) nos. A4 COFN / C1730 Post Limited 789.50 0.00 2022-05-02 2022-06-27 2022-12-24 gement tions nvelope ementation LaserJet Colour Printer for SP MU. IN-IWD-291956-GO-RFQ / Pr ocurement of 11(eleven) nos. Component D: Project Mana Request for Quota Single Stage - One E Pending Impl COFN / C1730 Post Limited 12,552.60 0.00 2022-05-02 2022-06-27 2022-12-24 Desktop Computer for DPIUs gement tions nvelope ementation at Bankura and Burdwan. IN-IWD-291959-GO-RFQ / Pr ocurement of 11(eleven) nos. Component D: Project Mana Request for Quota Single Stage - One E Pending Impl COFN / C1730 Post Limited 3,157.80 0.00 2022-05-02 2022-06-27 2022-12-24 A4 Black & White Printer for gement tions nvelope ementation DPIUs at Bankura and Burdw an. IN-IWD-291960-GO-RFQ / Pr ocurement of 11(eleven) nos. Component D: Project Mana Request for Quota Single Stage - One E Pending Impl COFN / C1730 Post Limited 394.70 0.00 2022-05-02 2022-06-27 2022-12-24 Line Interactive UPS with AV gement tions nvelope ementation R for DPIUs at Bankura and B urdwan IN-IWD-291961-GO-RFQ / Pr ocurement of 4 (four) nos. La Component D: Project Mana Request for Quota Single Stage - One E Pending Impl COFN / C1730 Post Limited 5,789.50 0.00 2022-05-02 2022-06-27 2022-12-24 ptop for DPMU-I, DPIUs at Ba gement tions nvelope ementation nkura, Burdwan and Howrah IN-IWD-291962-GO-RFQ / Pr Component D: Project Mana Request for Quota Single Stage - One E Pending Impl ocurement of Air Conditioner COFN / C1730 Post Limited 11,842.10 0.00 2022-05-02 2022-06-27 2022-12-24 gement tions nvelope ementation Machines in SPMU and DPMU -II. IN-IWD-291963-GO-RFQ / Pr ocurement of Equipment (Cu Component D: Project Mana Request for Quota Single Stage - One E Pending Impl COFN / C1730 Post Limited 2,631.50 0.00 2022-05-02 2022-06-27 2022-12-24 rrent Meter & Rebound Ham gement tions nvelope ementation mer) for DPIUs at Howrah an d Hooghly. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-IWD-254385-NC-RFQ / Sur vey of river Mundeswari and Damodar by using DGPS/RTK Component D: Project Mana Request for Quota Single Stage - One E Pending Impl including fixation of Permane COFN / C1730 Post Limited 9,508.29 0.00 2021-10-03 2021-11-28 2022-05-27 gement tions nvelope ementation nt Kilometre posts on top of r ight embankment of river Da modar under Hooghly Irrigati on Division. IN-IWD-254393-NC-RFQ / Sur vey work along upper Rampu Component D: Project Mana Request for Quota Single Stage - One E Pending Impl r khal by using DGPS/RTK incl COFN / C1730 Post Limited 8,149.96 0.00 2021-10-03 2021-11-28 2022-05-27 gement tions nvelope ementation uding fixation of permanent Kilometre post along the ban k. IN-IWD-254394-NC-RFQ / Sur vey work along lower Harinak Component D: Project Mana Request for Quota Single Stage - One E Pending Impl hali khal and Hurhura khal in COFN / C1730 Post Limited 6,791.63 0.00 2021-10-03 2021-11-28 2022-05-27 gement tions nvelope ementation cluding topographical survey over the concerned catchme nt area. IN-IWD-260316-NC-RFQ / As sessment of earthwork for ca nal renovation & concrete / s tructural steel work of hydra Component D: Project Mana Request for Quota Single Stage - One E Pending Impl COFN / C1730 Post Limited 6,348.57 0.00 2021-11-09 2022-01-04 2022-07-03 ulic structures on LBMC from gement tions nvelope ementation 46.58 to 88.09Km & Br–1 of Eden from 5.77 to 23.77Km, WC – 325 of Br–1, Dy – 1/3 an d Br-2 from 0.00 to 4.63Km u nder B I Division. IN-IWD-260317-NC-RFQ / As sessment of earthwork for ca nal renovation and concrete / Component D: Project Mana Request for Quota Single Stage - One E Pending Impl structural steel work of hydra COFN / C1730 Post Limited 6,148.10 0.00 2021-11-09 2022-01-04 2022-07-03 gement tions nvelope ementation ulic structures on RBMC from 20.84 to 50.84 Km, Suvankar Dara, Suvankar Dara–1 & Dy –1 of RBMC under R B I Divisi on. IN-IWD-260318-NC-RFQ / As sessment of earthwork for ca nal renovation and concrete / Component D: Project Mana Request for Quota Single Stage - One E Pending Impl structural steel work of hydra COFN / C1730 Post Limited 4,343.76 0.00 2021-11-09 2022-01-04 2022-07-03 gement tions nvelope ementation ulic structures on Kana Damo dar from 9.22 to 40.22Km, D/ 1 & D/2 of Kana Damodar un der B I Division. IN-IWD-260319-NC-RFQ / As sessment of earthwork for ca nal renovation and concrete / Component D: Project Mana Request for Quota Single Stage - One E Pending Impl structural steel work of hydra COFN / C1730 Post Limited 4,677.90 0.00 2021-11-09 2022-01-04 2022-07-03 gement tions nvelope ementation ulic structures on 6MC from 0 .00 to 33.45Km along with 6 BMC, 6KMC, 6LMC & 6L/2MC under B I Division. IN-IWD-279564-NC-RFQ / To pographical and Contour Sur vey by using GPS system wit h RTK/ DGPS and hydrograph Component D: Project Mana Request for Quota Single Stage - One E Pending Impl COFN / C1730 Post Limited 13,324.50 0.00 2022-02-27 2022-04-24 2022-10-21 ic survey by using ADCP instr gement tions nvelope ementation ument in River Damodar and Hurhurah Khal including char islands within Hooghly and H owrah District. IN-IWD-279565-NC-RFQ / Sur vey work along KATA KHAL b Component D: Project Mana Request for Quota Single Stage - One E Pending Impl COFN / C1730 Post Limited 5,329.80 0.00 2022-02-27 2022-04-24 2022-10-21 y using RTK/DGPS from Ching gement tions nvelope ementation ra to 26 Bigha within Hooghl y District. IN-IWD-279568-NC-RFQ / Ba nk Line Survey of Both banks of Mundeswari River from Ch. Component D: Project Mana Request for Quota Single Stage - One E Pending Impl COFN / C1730 Post Limited 10,659.60 0.00 2022-02-27 2022-04-24 2022-10-21 -19.00 Km to Ch.-41.50 Km in gement tions nvelope ementation cluding Baligori and Bheutia Circuit within Hooghly Distric t. Page 5 IN-IWD-279571-NC-RFQ / Sur vey work along River Mundes Component D: Project Mana Request for Quota Single Stage - One E Pending Impl COFN / C1730 Post Limited 6,662.30 0.00 2022-02-27 2022-04-24 2022-10-21 wari by using RTK/DGPS from gement tions nvelope ementation Chingra to Pansuli within Hoo ghly District. IN-IWD-280309-NC-RFQ / To pography, Cross section & Lo Component C: Flood Manage Request for Quota Single Stage - One E Pending Impl ng section survey of both em COFN / C1730 Post Limited 5,511.14 0.00 2022-03-03 2022-04-28 2022-10-25 ment tions nvelope ementation bankment of Maja Damodar of Howrah Irrigation Division under WBMIFMP. IN-IWD-280310-NC-RFQ / To pography & Cross section sur Component C: Flood Manage Request for Quota Single Stage - One E Pending Impl vey of Lower Rampur khal & COFN / C1730 Post Limited 3,378.02 0.00 2022-03-03 2022-04-28 2022-10-25 ment tions nvelope ementation Khoribon Khal of Howrah Irrig ation Division under WBMIFM P. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-IWD-18735-CS-QCBS / Pre paration of feasibility study, detailed engineering design and bidding documents for ir Quality And Cost- Open - Internationa / Prior 597,015.00 310,547.14 Signed 2017-06-21 2017-08-07 2017-06-23 2017-08-25 2017-06-27 2017-08-29 2017-06-29 2017-04-05 2017-07-01 2017-09-05 2017-07-05 2019-05-22 2017-07-22 2017-08-31 2018-10-15 rigation rejuvenation and floo Based Selection l d management in the Damod ar Command areas and Lowe r Damodar Sub-basin in the S tate of West Bengal in India. IN-IWD-18748-CS-QCBS / En vironmental and Social Impa Quality And Cost- Open - Internationa ct Analysis by a separate con / Prior 373,134.00 76,544.04 Signed 2017-06-21 2017-08-09 2017-07-01 2017-08-14 2017-08-05 2017-10-25 2017-09-02 2017-11-24 2017-10-02 2017-12-31 2017-11-06 2018-09-27 2017-12-11 2018-02-20 2018-07-09 Based Selection l sultancy organisation to supp lement the feasibility study r eport of WBMIFMP. IN-IWD-44796-CS-LCS / Sele ction of Consultancy firm for "Providing support to the Sta Least Cost Selecti / Post Open - National 183,456.00 0.00 Canceled 2018-01-19 2018-01-19 2018-01-19 2018-02-21 2018-02-01 2018-02-05 2018-03-07 2018-04-03 2018-03-14 2018-04-03 2018-03-28 2018-04-25 2019-02-19 te Project Management Unit ( on SPMU) of WBMIFMP during pr oject preparation period" in t he State of West Bengal in In dia. IN-IWD-61030-CS-LCS / Sele ction of Consultancy firm for "Providing support to the Sta Least Cost Selecti / Post Open - National 183,456.00 41,200.12 Completed 2018-04-27 2018-04-18 2018-05-18 2018-08-23 2018-07-01 2018-07-06 2018-07-29 2018-08-30 2018-08-28 2018-08-30 2018-10-02 2018-09-25 2018-11-06 2018-09-28 2019-05-05 2020-03-31 te Project Management Unit ( on SPMU) of WBMIFMP during pr oject preparation period" in t he State of West Bengal in In dia. IN-IWD-91823-CS-QCBS / "Pr oject Management Consultan t (PMC) for West Bengal Majo Component D: Project Mana Quality And Cost- Open - Internationa / Prior 4,788,732.00 10,561,859.14 Signed 2018-12-17 2019-01-17 2019-01-07 2019-03-05 2019-02-20 2019-10-14 2019-03-20 2020-01-15 2019-04-19 2020-02-17 2019-05-24 2020-04-07 2019-06-28 2020-05-11 2020-06-27 r Irrigation and Flood Manage gement Based Selection l ment Project (WBMIFMP)" in t he State of West Bengal in In dia. IN-IWD-102808-CS-LCS / Sel ection of Consultancy firm for "Providing Human Resource s Component D: Project Mana Least Cost Selecti Open - Internationa upport to the Project Manage / Prior 1,277,731.00 1,311,457.73 Signed 2019-03-06 2019-03-06 2019-03-27 2019-03-11 2019-05-10 2019-10-01 2019-06-07 2019-11-14 2019-07-07 2019-12-27 2019-08-11 2020-02-14 2019-09-15 2020-03-20 2020-03-13 gement on l ment Units of WBMIFMP durin g project implementation per iod" in the State of West Ben gal in India. IN-IWD-204310-CS-CQS / En gagement of the NGO for im Component C: Flood Manage Consultant Qualifi COFN / C1730 Post Open - National 93,828.90 125,536.31 Signed 2020-11-12 2020-11-12 2020-12-03 2020-11-18 2021-01-16 2020-11-27 2021-02-15 2020-12-23 2021-03-22 2020-12-31 2021-09-18 plementation of RAP for the F ment cation Selection lood Packages under WBMIF MP. IN-IWD-225818-CS-QCBS / E ngagement of a Consultant f or implementation and monit oring of Third-Party Inspectio Component C: Flood Manage Quality And Cost- Under Implement n (TPI) Report of different ma COFN / C1730 Post Open - National 765,921.00 0.00 2021-03-30 2021-03-23 2021-04-20 2021-09-09 2021-06-03 2021-09-09 2021-07-01 2021-11-02 2021-07-31 2021-11-16 2021-09-04 2021-12-27 2021-10-09 2022-10-09 ment Based Selection ation terials, procured & to be proc ured by the Agencies, of Worl d Bank funded project, WBMI FMP, Irrigation & Waterways Directorate, Govt of W. B. IN-IWD-274524-CS-QCBS / M athematical Model Study on t he Darakeswar-Rupnarayan Component C: Flood Manage Quality And Cost- COFN / C1730 Post Open - National 335,976.00 0.00 Under Review 2022-02-01 2022-01-24 2022-02-22 2022-04-07 2022-05-05 2022-06-04 2022-07-09 2022-08-13 2023-08-13 River System in the Districts ment Based Selection of Howarh, Hooghly, East and West Midnapore, West Benga l, India. IN-IWD-296688-CS-QCBS / E ngagement of Monitoring & E Component D: Project Mana Quality And Cost- Pending Impleme valuation Consultant for Wes COFN / C1730 Post Open - National 451,089.00 0.00 2022-05-28 2022-06-18 2022-08-01 2022-08-29 2022-09-28 2022-11-02 2022-12-07 2023-12-07 gement Based Selection ntation t Bengal Major Irrigation and Flood Management Project. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-IWD-67394-CS-CDS / Eng agement of Transaction Advi sor in connection with engag ement of Private Operators f or management, operation a / Post Direct Selection Direct 87,427.00 83,305.98 Completed 2018-06-21 2018-06-21 2018-07-01 2018-06-07 2018-09-04 2018-08-10 2019-03-03 2019-02-18 nd maintenance of irrigation delivery system starting from distributary level and extendi ng up to the field (chak) level under WBMIFMP. Page 6 IN-IWD-79411-CS-CDS / Rapi d Irrigation Modernization As Component B: Modernizatio Individual Consult / Post Direct 40,000.00 45,430.00 Completed 2018-09-26 2018-09-26 2018-10-06 2018-09-27 2018-10-27 2018-10-12 2018-12-01 2018-10-22 2019-05-30 2018-11-13 sessment in the D V Comma n of Irrigation Infrastructure ant Selection nd Area under WBMIFMP IN-IWD-215542-CS-CDS / Sel ection of Transaction Advisor Component A: Irrigation Man COFN / C1730 Post Direct Selection Direct 411,137.44 454,106.78 Signed 2021-02-02 2021-01-25 2021-02-12 2021-02-05 2021-04-18 2021-02-15 2021-10-15 in Phase II, in connection wit agement h engagement of the Irrigatio n Service Providers. Page 7