Appendix to Annex 3 Procurement Plan I. General 1. Project Information Country : India Borrower : Government of India Project Name : National Hydrology Project Loan Credit No. : 2. Bank’s Approval Date of the Procurement Plan : 3. Date of General Procurement Notice : 4. Period Covered by this procurement plan : 18 months II. Goods, Works, and Non-Consulting Services Thresholds for Method of Procurement for procurement of goods, works and non- consulting services Procurement of Goods, Information technology and non consultancy services: Method of Procurement Thresholds for Methods International Competitive Bidding (ICB) > US Dollars 3 million Limited Competitive Bidding (LIB) Must meet the requirements as per Para 3.2 of the Procurement Guidelines, and with prior agreement in PP with the Bank National Competitive Bidding (NCB) > USD 100,000 and up to USD 3 million Shopping Up to USD 100,000 (INR 6.5 m) Direct Must meet the requirements as per Para 3.7 of the Procurement Guidelines, and with prior agreement in PP with the Bank Framework Agreement Must meet the requirements as per Para 3.6 of the Procurement Guidelines, and with prior agreement in PP with the Bank Procurement of Works: Method of Procurement Thresholds for Methods International Competitive Bidding (ICB) > US Dollars 40 million National Competitive Bidding (NCB) > USD 100,000 and up to USD 40 million Comparison of three quotations / Up to USD 100,000 (INR 6.5 m) Shopping Force Account Must meet the requirements as per Para 3.9 of the Procurement Guidelines, and with prior agreement in PP with the Bank Prior Review Thresholds: The following would be subject to Prior review of the Bank regardless of the Method of selection: (a) Works: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 10 million (b) Goods: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 2 million; and The Prior Review Thresholds will be reviewed and updated during the implementation of the project, and modified based on the risk assessment. 1. In the case of contracts subject to prior review, Project Implementing Entity shall seek the Bank’s no objection before granting/agreeing to (a) an extension of the stipulated time for performance of a contract that either increases the contract price or has an impact on the planned completion of the project; (b) any substantial modification of the scope of works, goods, non-consulting services or consulting services, other significant changes to the terms and conditions of such that the contract,; (c) any variation order or amendment (except in cases of extreme urgency) which singly or combined with all variation orders or amendments previously issued, increase the original contract amount by more than 15 percent; or (d) the proposed termination of the contract.. A copy of all amendments to the contract shall be furnished to the Bank for its record. 2. Prequalification Not Applicable Domestic Preference: The provision of domestic preference is applicable in the evaluation of Goods only. 3. Reference to Procurement Manual The procurement manual for the project is presently under preparation. SBDs agreed between the Project and Bank will be used for all works, goods, and non consultancy procurements. 4. Any Other Special Procurement Arrangements The National bidding method for procurement and goods and works according to the above value thresholds will be conducted in accordance with paragraphs 3.3 and 3.4 of the Bank’s Procurement Guidelines and the following provisions: (a) Only the model bidding documents for NCB agreed with the GOI task force (and as amended for time to time) shall be used for bidding. (b)Invitations to bid shall be advertised in at least one widely circulated national daily newspaper (or on a widely used website or electronic portal with free national and international access along with an abridged version of the said advertisement published in a widely circulated national daily, among others, giving the website/electronic portal details from which the details of the invitation to bid can be downloaded) at least 30 days before the deadline for the submission of bids. (c) No special preferences will be accorded to any bidder either for price or for other terms and conditions when competing with foreign bidders, state- owned enterprises, small-scale enterprises, or enterprises from any given state. (d)Extension of bid validity shall not be allowed with reference to contracts subject to Bank prior review without the prior concurrence of the Bank (i) for the first request for extension if it is longer than four weeks and (ii) for all subsequent requests for extension irrespective of the period (such concurrence will be considered by the Bank only in cases of force majeure and circumstances beyond the control of the purchaser/employer). (e) Rebidding shall not be carried out with reference to contracts subject to Bank prior review without the prior concurrence of the Bank. The system of rejecting bids outside a predetermined margin or ‘bracket’ of prices shall not be used in the project. (f) Rate contracts entered into by the DGS&D will not be acceptable as a substitute for NCB procedures unless incorporation of right to audit and fraud corruption clauses. DGS&D contracts will be acceptable, however, for any procurement under the shopping procedures. (g)Two or three envelope system will not be used (except when using the e- procurement system assessed and agreed by the Bank). (h)No negotiations are conducted even with the lowest evaluated responsive bidders. 5. The bid evaluation will be carried out according to the agreed timeline in the Procurement Activity Schedule. III. Selection of Consultants 1. Methods and Prior Review Threshold Procurement methods of procurement of Consultants' Services (Firms) Method of Procurement Thresholds for Methods Quality and Cost Based Selection (QCBS) Quality Based Selection (QBS) Must meet the requirements as per Para 3..2 to 3.4 of the Consultant Guidelines Selection based on a Fixed Budget Must meet the requirements as per (FBS) Para 3.5 of the Consultant Guidelines, Selection Based on Least Cost Basis Must meet the requirements as per (LCS) Para 3.6 of the Consultant Guidelines, Selection based on Consultant’s Estimated not to exceed USD Qualification (CQ) 300,000, and must meet the requirements as per Para 3.7 of the Consultant Guidelines. Single Source Selection (SSS) Must meet the requirements as per Para 3.8 to 3.11 of the Consultant Guidelines, and with prior agreement in PP with the Bank. Procurement methods for Selection of Individual Consultants (IC) Method of Procurement Thresholds for Methods Competitive Selection Must meet the requirements of Section V, Para 5.1 to 5.5 of the Consultant Guidelines. Single Source Selection (SSS) Must meet the requirements of Section V, Para 5.6 of the Consultant Guidelines and with prior agreement in PP with the Bank *Shall meet the requirements as stated in Consultant Guidelines Prior Review Thresholds: (a). Consulting Firm: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 1 million. (b). Individual Consultant: all procurements estimated to cost more than USD 0.3 million Terms of Reference (ToR) for all consultant contracts shall be furnished to the Bank for its prior review and No Objection. Note: The Prior Review Thresholds will be reviewed during the implementation of the project and modified. 1. In the case of contracts subject to prior review, before agreeing to: (a) an extension of the stipulated time for performance of a contract; (b) any substantial modification of the scope of services, substitutions of key experts, or other significant changes to the terms and conditions of the contract; or (c) the proposed termination of the contract, the Borrower shall seek the Bank’s no objection. A copy of all amendments to the contract shall be furnished to the Bank for its record. 2. Short List comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than USD 800,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. The Request for Expression of Interest for consultancy services estimated to cost above USD 300,000 equivalent per contract for firms shall be advertised in UNDB online and World Bank external Website and in accordance with other provisions of Para 2.5 of the Consultant Guidelines 4. Any other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable] I. Implementing Agency Capacity Building Activities with Time Schedule No Expected Outcome/Activity Description Estimated Date Duration ASCI training on Procurement Procedures arranged for Executive, Assistant Engineers 1. 2 weeks Continuous who are responsible for Procurement – multiple trainings Contract management training – multiple 2. 2 weeks Continuous trainings Customized training on Procurement Procedures arranged for Executive, Assistant 3. 1 week Continuous Engineers who are responsible for Procurement – multiple trainings PROCUREMENT India : National Hydrology Project PLAN General Information Country: India 2017-10-04 Bank’s Approval Date of the Original Procurement Plan: 2022-06-23 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P152698 GPN Date: 2022-06-17 Project Name: National Hydrology Project Loan / Credit No: IBRD / 87250 Gujarat Ground Water Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned IN-GUJARAT GW-25106-CW- Water Resources Monitoring Single Stage - One E 2018-06-3 RFB / Improvement of Existin IBRD / 87250 Post Request for Bids Open - National 80,769.23 0.00 Canceled 2017-10-01 2017-10-06 2017-11-10 2017-11-27 2018-01-01 System nvelope 0 g Piezometers- 526 Nos NHP-2021-2022-GJ-601849 / National Procure Construction of total 315 Nos ment Document - Water Resources Monitoring Single Stage - Two E Pending Imp 2023-03-1 of piezometers with strong pr IBRD / 87250 Post Request for Bids Open - National 2 Envelope proce 1,696,153.85 0.00 2022-01-18 2022-01-23 2022-03-06 2022-05-19 2022-06-16 System nvelope lementation 3 otection Device in Alluvial So ss (Non Bank-SPD ft Rock and Hard Rock area o ) f Gujarat State National Procure NHP-2021-2022-GJ-253925 / ment Document - Construction of Piezometers i Water Resources Monitoring Single Stage - Two E Pending Imp 2023-05-1 IBRD / 87250 Post Request for Bids Open - National 2 Envelope proce 178,142.26 0.00 2022-03-21 2022-03-26 2022-05-07 2022-07-20 2022-08-17 n Gujarat under National Hyd System nvelope lementation 4 ss (Non Bank-SPD rology Project ( Group -1) ) National Procure NHP-2021-2022-GJ-181145 / ment Document - Construction of Piezometers i Water Resources Monitoring Single Stage - Two E Pending Imp 2023-05-1 IBRD / 87250 Post Request for Bids Open - National 2 Envelope proce 479,743.15 0.00 2022-03-21 2022-03-26 2022-05-07 2022-07-20 2022-08-17 n Gujarat under National Hyd System nvelope lementation 4 ss (Non Bank-SPD rology Project ( Group -7) ) National Procure NHP-2021-2022-GJ-492280 / ment Document - Construction of Piezometers i Water Resources Monitoring Single Stage - Two E Pending Imp 2023-05-1 IBRD / 87250 Post Request for Bids Open - National 2 Envelope proce 186,291.78 0.00 2022-03-21 2022-03-26 2022-05-07 2022-07-20 2022-08-17 n Gujarat under National Hyd System nvelope lementation 4 ss (Non Bank-SPD rology Project ( Group -2) ) National Procure NHP-2021-2022-GJ-563655 / ment Document - Construction of Piezometers i Water Resources Monitoring Single Stage - Two E Pending Imp 2023-05-1 IBRD / 87250 Post Request for Bids Open - National 2 Envelope proce 201,394.04 0.00 2022-03-21 2022-03-26 2022-05-07 2022-07-20 2022-08-17 n Gujarat under National Hyd System nvelope lementation 4 ss (Non Bank-SPD rology Project ( Group -3) ) National Procure NHP-2021-2022-GJ-719476 / ment Document - Construction of Piezometers i Water Resources Monitoring Single Stage - Two E Pending Imp 2023-05-1 IBRD / 87250 Post Request for Bids Open - National 2 Envelope proce 87,645.21 0.00 2022-03-21 2022-03-26 2022-05-07 2022-07-20 2022-08-17 n Gujarat under National Hyd System nvelope lementation 4 ss (Non Bank-SPD rology Project ( Group -5) ) National Procure NHP-2021-2022-GJ-841363 / ment Document - Construction of Piezometers i Water Resources Monitoring Single Stage - Two E Pending Imp 2023-05-1 IBRD / 87250 Post Request for Bids Open - National 2 Envelope proce 164,671.58 0.00 2022-03-21 2022-03-26 2022-05-07 2022-07-20 2022-08-17 n Gujarat under National Hyd System nvelope lementation 4 ss (Non Bank-SPD rology Project ( Group -6) ) National Procure NHP-2021-2022-GJ-888055 / ment Document - Construction of Piezometers i Water Resources Monitoring Single Stage - Two E Pending Imp 2023-05-1 IBRD / 87250 Post Request for Bids Open - National 2 Envelope proce 212,380.14 0.00 2022-03-21 2022-03-26 2022-05-07 2022-07-20 2022-08-17 n Gujarat under National Hyd System nvelope lementation 4 ss (Non Bank-SPD rology Project ( Group -4) ) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-GUJARAT GW-24238-GO-R Water Resources Monitoring Request for Quota Single Stage - One E FQ / Analytical Digital Balanc IBRD / 87250 Post Limited 6,923.08 14,209.42 Signed 2017-08-29 2018-02-08 2017-10-25 2018-03-05 2017-11-17 2018-03-28 System tions nvelope e-3 nos for WQ lab. IN-GUJARAT GW-24242-GO-R Water Resources Monitoring Request for Quota Single Stage - One E FQ / Manual Ground Water Le IBRD / 87250 Post Limited 6,153.85 22,427.23 Signed 2017-08-28 2017-11-07 2017-10-06 2017-12-28 2017-11-02 2018-03-16 System tions nvelope vel Indicator - 10 nos IN-GUJARAT GW-24245-GO-R Water Resources Monitoring Request for Quota Single Stage - One E FQ / Resistivity Meter (Teram IBRD / 87250 Post Limited 38,461.54 0.00 Canceled 2017-11-03 2017-12-28 2018-01-28 System tions nvelope eter Multi Electrode) - 1 No. IN-GUJARAT GW-24253-GO-R Water Resources Monitoring Request for Quota Single Stage - One E IBRD / 87250 Post Limited 6,153.85 0.00 Canceled 2017-09-08 2017-10-26 2017-11-09 FQ / Deep Resistivity Meter - System tions nvelope 1 no. IN-GUJARAT GW-24255-GO-R Water Resources Monitoring Request for Quota Single Stage - One E IBRD / 87250 Post Limited 9,230.77 0.00 Canceled 2017-09-22 2017-11-27 2017-12-27 FQ / Borehole Camera - 1 no System tions nvelope IN-GUJARAT GW-24268-GO-R Water Resources Monitoring Request for Quota Single Stage - One E IBRD / 87250 Post Limited 6,000.00 0.00 Canceled 2017-09-18 2017-10-27 2017-11-27 FQ / Laptop - 3 nos.(Through System tions nvelope GEM) IN-GUJARAT GW-24273-GO-R Water Resources Monitoring Request for Quota Single Stage - One E FQ / Desktop Computers - 10 IBRD / 87250 Post Limited 11,846.15 0.00 Canceled 2017-09-19 2017-11-07 2017-11-27 System tions nvelope nos. (Through GEM) IN-GUJARAT GW-24276-GO-R Water Resources Monitoring Request for Quota Single Stage - One E FQ / Workstations - 2 nos (Th IBRD / 87250 Post Limited 6,153.85 0.00 Canceled 2017-09-28 2017-11-23 2017-12-23 System tions nvelope rough GEM) IN-GUJARAT GW-24281-GO-R Water Resources Monitoring Request for Quota Single Stage - One E FQ / Tablet - 14 nos.,Through IBRD / 87250 Post Limited 5,384.62 0.00 Canceled 2017-10-03 2017-11-13 2017-11-28 System tions nvelope Government E Market(GEM) IN-GUJARAT GW-24283-GO-R Water Resources Monitoring Request for Quota Single Stage - One E FQ / Portable External Hard D IBRD / 87250 Post Limited 923.08 599.09 Completed 2017-09-18 2017-11-21 2017-10-31 2017-11-21 2017-11-27 2017-11-27 System tions nvelope isk - 6 nos. (Through GEM) Page 1 IN-GUJARAT GW-24517-GO-R FQ / Procurement of B/W Prin Water Resources Monitoring Request for Quota Single Stage - One E IBRD / 87250 Post Limited 4,307.69 2,143.74 Completed 2017-09-19 2017-11-15 2017-11-07 2018-01-08 2017-11-27 2018-01-19 ters - 10 nos. And Colour Prin System tions nvelope ter A3 Size - 1 no. (Through GEM) IN-GUJARAT GW-24520-GO-R FQ / Multi function of Colour Water Resources Monitoring Request for Quota Single Stage - One E IBRD / 87250 Post Limited 7,692.31 0.00 Canceled 2017-10-03 2017-11-21 2017-12-12 Printer cum Scanner cum Co System tions nvelope pier of A3 Size - 1 no. And Co pier Machine - 1 no. IN-GUJARAT GW-25110-GO-R Water Resources Monitoring Single Stage - One E FB / Procurement of Telemetr IBRD / 87250 Post Request for Bids Open - National 930,615.38 0.00 Canceled 2017-10-01 2017-10-06 2017-11-10 2017-11-27 2018-01-01 2018-06-30 System nvelope y Digital Water Level Record er - 526 Nos . NHP-2018-2019-GJGW-2091 Water Resources Monitoring Request for Quota Single Stage - One E Under Imple 77 / Procurement of Resistivit IBRD / 87250 Post Limited 44,615.38 0.00 2018-09-29 2018-10-15 2018-11-16 2019-01-15 System tions nvelope mentation y Meter - 5 Nos. NHP-2018-2019-GJGW-6421 Water Resources Monitoring Request for Quota Single Stage - One E Under Imple 26 / Procurement of Water Q IBRD / 87250 Post Limited 22,153.85 0.00 2018-09-29 2018-10-30 2018-12-14 System tions nvelope mentation uality Equipments NHP-2018-2019-GJGW-5606 Water Resources Monitoring Request for Quota Single Stage - One E Under Imple IBRD / 87250 Post Limited 16,615.38 0.00 2018-09-19 2019-03-12 2018-10-06 2018-10-27 97 / Procurement of Workstat System tions nvelope mentation ion - 4Nos NHP-2018-2019-GJGW-6815 Water Resources Monitoring Request for Quota Single Stage - One E Pending Impl 08 / Procurement of Internet IBRD / 87250 Post Limited 646.15 0.00 2018-09-24 2018-10-22 2018-10-29 System tions nvelope ementation Dongle-5 Nos NHP-2018-2019-GJGW-1093 Water Resources Monitoring Request for Quota Single Stage - One E Pending Impl IBRD / 87250 Post Limited 6,153.85 0.00 2018-12-21 2019-01-04 2019-02-04 66 / Procurement of Server-1 System tions nvelope ementation Nos NHP-2018-2019-GJGW-7283 79 / Procurement of Desktop Water Resources Monitoring Request for Quota Single Stage - One E Pending Impl IBRD / 87250 Post Limited 26,461.54 0.00 2018-10-08 2018-10-22 2018-11-12 computer (14 Nos),Laptop (4 System tions nvelope ementation Nos),B& W Printers(7 Nos),Co lour Printer (1 No) NHP-2018-2019-GJGW-6408 34 / Procurement of Multi-fun Water Resources Monitoring Request for Quota Single Stage - One E Pending Impl IBRD / 87250 Post Limited 10,615.38 0.00 2018-09-20 2018-10-04 2018-10-16 ctional B & W Photocopier (2 System tions nvelope ementation Nos), Multi-functional Color P hotocopier (1 No) NHP-2018-2019-GJGW-1785 48 / Procurement of DWLR wi Water Resources Monitoring Single Stage - Two E Pending Impl IBRD / 87250 Post Request for Bids Limited 1,011,384.62 0.00 2018-09-12 2018-10-12 2018-11-12 2018-12-11 2019-01-08 2020-01-08 th Telemetry - 526 Nos and I System nvelope ementation mprovement of Existing Piez ometer NHP-2018-2019-GJGW-3294 Water Resources Monitoring 82 / Upgradation of Arc-GIS S IBRD / 87250 Post Direct Selection Direct 16,374.77 15,206.62 Completed 2018-11-27 2019-01-11 2018-12-02 2019-01-11 2019-01-06 2019-01-18 2019-02-05 2019-03-16 System oftware - 2 Nos NHP-2019-2020-GJGW-6072 33 / Procurement of 15 Nos o Water Resources Monitoring Request for Quota Single Stage - One E Pending Impl IBRD / 87250 Post Limited 11,538.46 0.00 2019-06-30 2019-08-25 2020-02-21 f Air conditioner machine for System tions nvelope ementation Data Center/Divisional Data c enter NHP-2019-2020-GJGW-9127 Water Resources Monitoring Request for Quota Single Stage - One E Pending Impl 84 / Procurement of Executiv IBRD / 87250 Post Limited 5,384.62 0.00 2019-07-14 2019-09-08 2020-03-06 System tions nvelope ementation e Chairs (5 Nos) and Officer Chairs (20 Nos) NHP-2019-2020-GJ-759789 / DWLR with Telemetry along Water Resources Monitoring Single Stage - Two E Under Imple IBRD / 87250 Prior Request for Bids Open - National 2,976,516.00 0.00 2020-08-10 2020-07-12 2020-08-15 2020-09-07 2020-09-26 2020-11-05 2020-12-09 2021-04-09 2021-01-13 2025-03-31 with improvement of 1000 n System nvelope mentation os. of existing Piezometers NHP-2021-2022-GJ-380614 / Supply Installation ,Testing C ommissioning and Maintenan ce of Digital Water Level Rec Water Resources Monitoring Single Stage - Two E order(DWLRs) with Non vent IBRD / 87250 Post Request for Bids Open - National 726,923.08 0.00 Canceled 2022-01-16 2022-01-21 2022-03-04 2022-05-17 2022-06-21 2027-01-01 System nvelope ed Pressure sensors with Tel emetry system i for Ground water Monitoring and Integr ate with data center located at Gandhinagar, Gujarat NHP-2021-2022-GJ-380614-2 / Supply Installation ,Testing Commissioning and Maintena nce of Digital Water Level Re Water Resources Monitoring Single Stage - Two E Pending Impl corder(DWLRs) with Non vent IBRD / 87250 Post Request for Bids Open - National 726,923.08 0.00 2022-03-07 2022-03-12 2022-04-23 2022-07-06 2022-08-10 2027-02-20 System nvelope ementation ed Pressure sensors with Tel emetry system i for Ground water Monitoring and Integra te with data center located a t Gandhinagar, Gujarat NHP-2022-2023-GJ-236275 / Water Resources Monitoring Pending Impl Procurement of Van for Mobil IBRD / 87250 Post Direct Selection Direct 128,767.12 0.00 2022-05-21 2022-05-26 2022-06-30 2022-08-29 System ementation e Water Quality Lab for Grou nd water NHP-2022-2023-GJ-150613 / Furnishing of Utility vehicle f Water Resources Monitoring Single Stage - Two E Pending Impl IBRD / 87250 Post Request for Bids Open - National 45,205.48 0.00 2022-06-25 2022-06-30 2022-07-15 2022-08-16 2022-09-09 2022-11-08 or developing mobile water Q System nvelope ementation uality Laboratory for Ground Water NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 3