Procurement Plan Balochistan Integrated Water Resources Management and Development Project I. General 1. Bank’s approval Date of the procurement Plan March 19,2016 2. Date of General Procurement Notice: January 2016 3. Period covered by this procurement plan: The procurement period of project covered from year January 2017 to December 2018 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Procurement Method Prior Review Comments Threshold US$ 1. ICB (Goods) Above US$ 600,000 All 2. NCB (Goods) Above US$ 100,000 First contract 3. ICB (Works) Above US$ 4 million All 4. NCB (Works) Upto US$ 4 million All 5. (Non-Consultant Services) Below US$ 100,000 First contract 6. Community Driven Development Above US$ 25,000 First contract 2. Pre-qualification. Bidders for $ 15 million shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project issued by Balochistan Government July 9, 2010 5. Any Other Special Procurement Arrangements: Some preparatory activities under retroactive financing 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) [List the Packages which require Bank’s prior review first and then the other packages] 1 2 3 4 5 6 7 Ref. Descripti Estimat Packages Dome Review Comme No. on ed stic by Bank nts Cost Prefe (Prior / US$ rence Post) million (yes/ no) Summary 82 5 No Prior of the ICB (Works) Summary 43.77 15 No Prior of the ICB (Goods) Summary 64.53 18 No Post 1st of the NCB contrac (Works) t for Prior Review Summary 1.86 4 No Post 1st of the NCB contrac (Goods) t for Prior Review Summary 0.45 1 No Prior of the ICB (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 500,000 2. Single Source (Firms) All 3. Individual Above US$ 200,000 July 9, 2010 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_500,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimat Package Review Comment of ed s by Bank s Assignmen Cost (Prior / t US$ Post) million Summary 4.17 7 Prior of number of contracts that will be let under QCBS Summary 0.83 1 Prior CQS of number of contracts that will be let under other methods July 9, 2010 PROCUREMENT Pakistan : PK-Balochistan Integrated Water Resources Management & Development Project PLAN General Information Country: Pakistan 2016-10-14 Bank’s Approval Date of the Original Procurement Plan: 2022-07-26 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P154255 GPN Date: 2017-07-10 Project Name: PK-Balochistan Integrated Water Resources Management & Development Project Loan / Credit No: IDA / 58850 PMU Balochistan Integrated Water Resources Management and Development Project Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned PK-PMU-BIWRMDP-14383-C Component B: Water, Infrast Open - Internationa Single Stage - One E 12,906,271.0 11,689,958. 2020-02-2 W-RFB / Construction of Nari IDA / 58850 ructure and Management In Prior Request for Bids Signed 2017-05-11 2017-05-17 2017-05-16 2017-05-23 2017-06-30 2017-07-10 2017-07-30 2017-08-21 2017-09-03 2017-09-08 l nvelope 0 60 0 Gorge Integrated Scheme vestments PK-PMU-BIWRMDP-14453-C Component B: Water, Infrast Open - Internationa Single Stage - One E 6,475,606.4 2020-03-0 W-RFB / Construction of Gun IDA / 58850 ructure and Management In Post Request for Bids 8,995,675.00 Terminated 2017-05-22 2017-05-26 2017-05-27 2017-05-26 2017-07-11 2017-07-20 2017-08-10 2017-11-06 2017-09-14 2017-11-20 l nvelope 9 2 dacha-Nurg Hingri Integrated vestments Scheme PK-PMU-BIWRMDP-2420-CW- RFB / Nari Gorge Perennial Irr Component B: Water, Infrast Single Stage - One E 2018-12-0 igation Scheme - Package 3 o IDA / 58850 ructure and Management In Post Request for Bids Open - National 2,510,643.00 0.00 Canceled 2017-02-28 2017-03-07 2017-04-06 2017-05-06 2017-06-17 nvelope 9 f 5 (Luni, Kurak, Bakhra Ghul vestments am Bolak and Marghzani Cha nnels) PK-PMU-BIWRMDP-2419-CW- Component B: Water, Infrast RFB / Nari Gorge Perennial Irr Single Stage - One E 2018-09-0 IDA / 58850 ructure and Management In Prior Request for Bids Open - National 1,434,724.00 0.00 Canceled 2017-02-28 2017-03-07 2017-04-06 2017-04-27 2017-06-08 igation Scheme - Package 2 o nvelope 1 vestments f 5 (Dehpal Channel) PK-PMU-BIWRMDP-2432-CW- RFB / Gundacha Nurg Hingri Scheme - Package 2 of 2 (Co nstruction of Irrigation Chann Component B: Water, Infrast Open - Internationa Single Stage - One E 2019-09-0 el, Nurg Hingri Off Take Weir IDA / 58850 ructure and Management In Post Request for Bids 4,601,570.00 0.00 Canceled 2017-05-09 2017-05-19 2017-07-10 2017-08-04 2017-09-17 l nvelope 7 s and Under Sluice, Nurg Hin vestments gri Channels and Guide Bank s, Glacis Fall Structures, Roa d Culverts, Outlet Structures and Drainage Culverts) PK-PMU-BIWRMDP-2431-CW- RFB / Gundacha Nurg Hingri I Component B: Water, Infrast Single Stage - One E 2019-08-1 rrigation Scheme - Package 1 IDA / 58850 ructure and Management In Post Request for Bids Open - National 3,941,491.00 0.00 Canceled 2017-05-09 2017-05-19 2017-06-24 2017-07-15 2017-08-28 nvelope 8 of 2 (Construction of Weir, U vestments ndersluice and Head Regulat or) PK-PMU-BIWRMDP-2427-CW- RFB / Yetabad Flood Irrigatio Component B: Water, Infrast Open - Internationa Single Stage - One E 2021-11-1 n Scheme - Package 2 of 6 (C IDA / 58850 ructure and Management In Prior Request for Bids 6,123,689.00 0.00 Canceled 2018-07-12 2018-07-19 2018-09-07 2018-10-02 2018-11-15 l nvelope 4 onveyance System Including vestments Cross Drainage (RD 0+00 to RD 10+750) PK-PMU-BIWRMDP-2428-CW- RFB / Yetabad Flood Irrigatio Component B: Water, Infrast Open - Internationa Single Stage - One E 2021-11-2 n Scheme - Package 3 of 6 (C IDA / 58850 ructure and Management In Prior Request for Bids 6,123,689.00 0.00 Canceled 2018-07-12 2018-07-19 2018-09-07 2018-10-12 2018-11-25 l nvelope 4 onveyance System including vestments Cross Drainage Structures R D 10+750 to RD 21+500) PK-PMU-BIWRMDP-2423-CW- Component B: Water, Infrast Open - Internationa Single Stage - One E 2021-11-1 RFB / Yetabad Flood Irrigatio IDA / 58850 ructure and Management In Prior Request for Bids 9,014,788.00 0.00 Canceled 2018-07-12 2018-07-19 2018-09-07 2018-10-02 2018-11-15 l nvelope 4 n Scheme - Package 1 of 6 ( vestments Weir & Buildings) PK-PMU-BIWRMDP-69116-C Component B: Water, Infrast W-RFB / Yetabad Flood Irrigat Open - Internationa Single Stage - One E 15,151,815.0 2020-09-0 IDA / 58850 ructure and Management In Prior Request for Bids 0.00 Canceled 2018-08-15 2018-10-31 2018-10-31 2018-08-20 2019-01-09 2019-02-08 2019-03-15 ion Scheme - Package 2 (Con l nvelope 0 5 vestments veyance System KM 6+000 t o KM 21+500) PK-PMU-BIWRMDP-69112-C Component B: Water, Infrast W-RFB / Yetabad Flood Irrigat Open - Internationa Single Stage - One E 148,484,235. 2020-09-0 IDA / 58850 ructure and Management In Prior Request for Bids 0.00 Canceled 2018-08-15 2018-10-31 2018-10-31 2018-08-20 2019-01-09 2019-02-08 2019-03-15 ion Scheme - Package 1 (Wei l nvelope 00 5 vestments r and Conveyance System (K M 0+000 to KM 6+000) PK-PMU-BIWRMDP-79952-C Component B: Water, Infrast Open - Internationa Single Stage - One E 2021-09-0 W-RFB / Construction of Mus IDA / 58850 ructure and Management In Post Request for Bids 7,464,230.00 0.00 Canceled 2018-11-12 2018-11-17 2018-11-12 2019-01-04 2019-02-03 2019-03-10 l nvelope 7 hkaf Flood Irrigation Scheme vestments PK-PMU-BIWRMDP-92413-C W-RFQ / Procurement of Wor Component B: Water, Infrast ks for Production of Plants Th Request for Quota Single Stage - One E 2019-07-3 IDA / 58850 ructure and Management In Post Open - National 145,279.00 109,366.58 Signed 2019-01-05 2019-02-01 2019-09-20 rough Raising of Nurseries U tions nvelope 1 vestments nder B2 Sub Component of BI WRMDP at Uthal, Dhadar & H arnai PK-PMU-BIWRMDP-93196-C Component B: Water, Infrast W-RFB / Procurement of Civil Open - Internationa Single Stage - One E 3,589,182.9 2021-04-1 IDA / 58850 ructure and Management In Post Request for Bids 4,270,000.00 Signed 2019-01-03 2019-03-11 2019-01-08 2019-03-11 2019-02-27 2019-04-29 2019-03-29 2019-09-03 2019-04-26 2020-02-07 Works for Nari Gorge Integrat l nvelope 4 5 vestments ed Scheme (Package-01) PK-PMU-BIWRMDP-93197-C Component B: Water, Infrast Single Stage - One E 2,709,109.5 2021-05-2 W-RFB / Construction of Nim IDA / 58850 ructure and Management In Post Request for Bids Open - National 2,971,014.00 Signed 2019-02-12 2019-03-14 2019-02-17 2019-03-11 2019-03-31 2019-04-15 2019-04-30 2019-07-23 2019-05-28 2019-09-30 nvelope 5 7 mi Perennial Irrigation Schem vestments e PK-PMU-BIWRMDP-96459-C Component B: Water, Infrast W-RFB / Construction of Gan Open - Internationa Single Stage - One E 2021-06-0 IDA / 58850 ructure and Management In Prior Request for Bids 8,915,217.00 0.00 Canceled 2019-02-15 2019-02-20 2019-04-03 2019-05-03 2019-06-07 dacha Nurg-Hingri Integrated l nvelope 6 vestments Scheme (Package-1) PK-PMU-BIWRMDP-97035-C Component B: Water, Infrast Open - Internationa Single Stage - One E 5,931,554.4 2021-05-2 W-RFB / Construction of Mus IDA / 58850 ructure and Management In Prior Request for Bids 7,464,230.00 Signed 2019-02-06 2019-02-11 2019-02-11 2019-02-13 2019-03-25 2019-04-04 2019-04-24 2019-08-21 2019-05-29 2019-09-30 l nvelope 0 8 hkaf Flood Irrigation Scheme vestments s PK-PMU-BIWRMDP-104392-C W-RFB / Construction of Wate Component B: Water, Infrast Single Stage - One E 2019-12-1 r Supply Scheme for 4 village IDA / 58850 ructure and Management In Post Request for Bids Open - National 775,362.00 0.00 Canceled 2019-03-10 2019-05-27 2019-03-15 2019-04-14 2019-04-15 2019-05-14 2019-06-18 nvelope 5 s within the ambit of Nari Gor vestments ge Integrated Scheme, Sibi Page 1 PK-PMU-BIWRMDP-113051-C Component B: Water, Infrast W-RFB / Construction of Gun Single Stage - One E 3,642,140.1 2020-03-0 IDA / 58850 ructure and Management In Post Request for Bids Open - National 3,477,220.85 Signed 2019-05-15 2019-05-27 2019-05-20 2019-07-01 2019-07-04 2019-07-31 2019-10-08 2019-09-04 2020-04-06 dacha Nurg Hingri Integrated nvelope 5 2 vestments Scheme - Package 2 (Works at Nurg Hingri) PK-PMU-BIWRMDP-73478-C W-RFB / Procurement of Wor ks Yetabad Flood Irrigation S Component B: Water, Infrast Open - Internationa Single Stage - One E 34,997,555.0 2020-09-2 cheme - (Weir and Conveyan IDA / 58850 ructure and Management In Prior Request for Bids 0.00 Canceled 2018-08-30 2018-09-27 2018-11-15 2018-11-15 2018-09-04 2019-01-24 2019-02-23 2019-03-30 l nvelope 1 0 ce System (KM 0+000 to KM vestments 6+000) and Conveyance Sys tem and Buildings (KM 6+00 0 to KM 21+500) PK-PMU-BIWRMDP-93985-C Component B: Water, Infrast W-RFB / Water Supply Schem Single Stage - One E 2020-04-1 IDA / 58850 ructure and Management In Post Request for Bids Open - National 469,989.00 0.00 Canceled 2019-01-15 2019-03-13 2019-01-20 2019-03-11 2019-02-19 2019-04-15 2019-03-21 2019-04-18 e for three villages constituti nvelope 7 vestments ng domain of Mushkaf Flood I rrigation Scheme PK-PMU-BIWRMDP-2437-CW- Component B: Water, Infrast Single Stage - One E 2022-02-1 RFB / Flood Protection Works IDA / 58850 ructure and Management In Post Request for Bids Open - National 2,408,021.00 0.00 Canceled 2019-11-15 2019-11-22 2019-12-22 2020-01-12 2020-02-25 nvelope 4 - Package 1 of 5 vestments PK-PMU-BIWRMDP-2435-CW- Component B: Water, Infrast RFB / Water Supply Schemes Single Stage - One E 2021-08-2 IDA / 58850 ructure and Management In Post Request for Bids Open - National 1,842,458.00 0.00 Canceled 2019-11-15 2019-11-22 2019-12-22 2020-01-16 2020-02-29 Package 2 of 4 - 3 Water Sup nvelope 2 vestments ply Schemes in District Loral ai PK-PMU-BIWRMDP-2441-CW- Component B: Water, Infrast RFB / Small Scale Irrigation S Single Stage - One E 2021-12-2 IDA / 58850 ructure and Management In Post Request for Bids Open - National 268,568.00 0.00 Canceled 2020-03-16 2020-03-23 2020-04-22 2020-05-20 2020-07-03 chemes in District Khuzdar - nvelope 5 vestments Khazeni Bent Perennial Irriga tion Scheme PK-PMU-BIWRMDP-2439-CW- Component B: Water, Infrast RFB / Small Scale Irrigation S Single Stage - One E 2021-09-0 IDA / 58850 ructure and Management In Post Request for Bids Open - National 692,764.00 0.00 Canceled 2019-11-30 2019-12-07 2020-01-06 2020-01-27 2020-03-11 chemes in District Khuzdar - nvelope 2 vestments Naik Mohammad Bent Peren nial Irrigation Scheme PK-PMU-BIWRMDP-2433-CW- Component A: Institutions, C Single Stage - One E 2021-06-2 RFB / Drilling & Development IDA / 58850 Post Request for Bids Open - National 947,550.00 0.00 Canceled 2020-03-16 2020-03-23 2020-04-22 2020-05-13 2020-06-26 apacity and Information nvelope 6 of Groundwater Monitoring W ells PK-PMU-BIWRMDP-2429-CW- RFB / Nimmi Perennial Irrigati Component B: Water, Infrast Single Stage - One E 2022-05-2 on Scheme - Package 1 of 2 ( IDA / 58850 ructure and Management In Post Request for Bids Open - National 3,249,665.00 0.00 Canceled 2020-02-20 2020-03-01 2020-03-31 2020-04-21 2020-06-04 nvelope 5 Construction of Weir, Undersl vestments uice, & Head Regulator) PK-PMU-BIWRMDP-2438-CW- Component B: Water, Infrast Single Stage - One E 2022-02-2 RFB / Flood Protection Works IDA / 58850 ructure and Management In Post Request for Bids Open - National 2,323,315.00 0.00 Canceled 2019-11-15 2019-11-22 2019-12-22 2020-01-19 2020-03-03 nvelope 1 - Package 2 of 5 vestments PK-PMU-BIWRMDP-2430-CW- RFB / Nimmi Perennial Irrigati on System - Package 2 of 2 ( Component B: Water, Infrast Construction of Irrigation Can Open - Internationa Single Stage - One E 2022-07-1 IDA / 58850 ructure and Management In Post Request for Bids 4,924,502.00 0.00 Canceled 2020-03-16 2020-03-26 2020-05-15 2020-06-14 2020-07-28 al System, Guide Banks, Fall l nvelope 8 vestments Structure, Road Culverts, Out let Structures, Drainage Box and Pipe Culverts, Regulators and Aquaducts. PK-PMU-BIWRMDP-2434-CW- Component B: Water, Infrast RFB / Water Supply Schemes Single Stage - One E 2021-06-1 IDA / 58850 ructure and Management In Post Request for Bids Open - National 297,186.00 0.00 Canceled 2020-02-29 2020-03-07 2020-04-06 2020-04-27 2020-06-10 Package 1 of 4 - Construction nvelope 0 vestments of 3 Water Supply Schemes i n District Lasbela PK-PMU-BIWRMDP-113054-C Component B: Water, Infrast Single Stage - One E 2020-03-0 W-RFB / Construction of Nari IDA / 58850 ructure and Management In Post Request for Bids Open - National 754,691.00 0.00 Canceled 2019-05-15 2019-05-20 2019-07-01 2019-07-31 2019-09-04 nvelope 2 Gorge Water Supply Scheme vestments PK-PMU-BIWRMDP-68771-C W-RFB / Construction of Com Component B: Water, Infrast mand Area Infrastructure Viz. Single Stage - One E 2021-02-1 IDA / 58850 ructure and Management In Post Request for Bids Open - National 887,000.00 0.00 Canceled 2020-05-03 2020-05-08 2020-06-19 2020-07-19 2020-08-23 WC, WST, KT,EWST, EWC ( Pe nvelope 9 vestments rennial and Spate)( Package 1 of 3) NARI GORGE PIS COM MAND AREA INFRSTRUCTURE WORKS PK-PMU-BIWRMDP-96461-C Component B: Water, Infrast Open - Internationa Single Stage - One E 2021-06-1 W-RFB / Construction Nari Go IDA / 58850 ructure and Management In Prior Request for Bids 5,268,116.00 0.00 Canceled 2019-02-20 2019-02-11 2019-02-25 2019-02-13 2019-04-08 2019-04-08 2019-05-08 2019-06-12 l nvelope 1 rge Integrated Scheme (Pack vestments age-2) PK-PMU-BIWRMDP-143842-C Component B: Water, Infrast Open - Internationa Single Stage - One E 2020-09-1 W-RFB / Construction Nari Go IDA / 58850 ructure and Management In Prior Request for Bids 5,270,000.00 0.00 Canceled 2019-11-30 2019-12-05 2020-01-16 2020-02-15 2020-03-21 l nvelope 7 rge Integrated Scheme (Pack vestments age-2) PK-PMU-BIWRMDP-68772-C W-RFB / Construction of Com Component B: Water, Infrast mand Aare Infrastructures ( Single Stage - One E 2021-01-1 IDA / 58850 ructure and Management In Post Request for Bids Open - National 518,000.00 0.00 Canceled 2020-03-30 2020-04-04 2020-05-16 2020-06-15 2020-07-20 Khuskaba FArming) Package nvelope 6 vestments 1 of 10 NARI GORGE PIS COM MAND AREA INFRSTRUCTURE WORKS PK-PMU-BIWRMDP-144874-C W-RFB / Works for Construc Component B: Water, Infrast tion of Shab-e-Maidan Irrig Open - Internationa Single Stage - One E 2021-12-1 IDA / 58850 ructure and Management In Post Request for Bids 4,683,871.00 0.00 Canceled 2020-03-24 2020-03-29 2020-04-02 2020-05-17 2020-06-21 ation Scheme Package 1 of l nvelope 3 vestments 2 - Construction of Weir and Main Canal and Related Hy draulic Structures PK-PMU-BIWRMDP-144869-C W-RFB / Works for Construc Component B: Water, Infrast Single Stage - One E 3,524,539.8 2022-03-0 tion of Sehan Irrigation Sc IDA / 58850 ructure and Management In Post Request for Bids Open - National 3,848,000.00 Signed 2020-06-01 2020-11-20 2020-06-06 2020-07-06 2020-12-24 2020-08-05 2021-02-19 2020-09-09 2021-04-26 nvelope 5 3 heme Package 2 of 3 - Constr vestments uction of Main Canal and Related Hydraulic Structure s PK-PMU-BIWRMDP-144876-C W-RFB / Works for Construc Component B: Water, Infrast tion of Shab-e-Maidan Irrig Open - Internationa Single Stage - One E 3,102,667.0 2022-03-0 IDA / 58850 ructure and Management In Post Request for Bids 4,335,483.00 Signed 2020-05-18 2020-08-11 2020-05-23 2020-07-07 2020-09-15 2020-08-06 2020-10-13 2020-09-10 2020-12-15 ation Scheme Package 2 of l nvelope 8 4 vestments 2 - Construction of Main Ca nal, Distributories and Relat ed Hydraulic Structures Page 2 PK-PMU-BIWRMDP-145601-C Component B: Water, Infrast Single Stage - One E 2021-05-0 W-RFB / Civil Works for Const IDA / 58850 ructure and Management In Post Request for Bids Open - National 298,426.00 262,554.67 Signed 2020-01-24 2020-01-28 2020-01-29 2020-02-28 2020-03-02 2020-03-29 2020-04-22 2020-05-03 2020-06-12 nvelope 3 ruction of Nari Gorge Water S vestments upply Scheme PK-PMU-BIWRMDP-143841-C Component B: Water, Infrast Single Stage - One E 2021-04-0 W-RFB / Civil Works for Mush IDA / 58850 ructure and Management In Post Request for Bids Open - National 267,567.00 182,191.01 Signed 2020-01-24 2020-01-28 2020-01-29 2020-02-01 2020-03-02 2020-03-02 2020-04-22 2020-04-06 2020-06-12 nvelope 5 kaf Water Supply Scheme vestments PK-PMU-BIWRMDP-153953-C Component B: Water, Infrast W-RFB / Construction of Gun Single Stage - One E 3,172,325.3 2022-05-1 IDA / 58850 ructure and Management In Post Request for Bids Open - National 3,032,258.00 Signed 2020-02-03 2020-04-30 2020-02-08 2020-03-09 2020-06-10 2020-04-08 2020-06-26 2020-05-13 2020-08-31 dacha Nurg Hingri Integrated nvelope 4 3 vestments Scheme - Package 1 of 2. PK-PMU-BIWRMDP-153957-C Component B: Water, Infrast W-RFB / Construction of Nari Single Stage - One E 2022-05-0 IDA / 58850 ructure and Management In Post Request for Bids Open - National 2,709,677.00 0.00 Canceled 2020-01-24 2020-01-28 2020-01-29 2020-02-28 2020-03-02 2020-03-29 2020-04-22 2020-05-03 Gorge Integrated Scheme - P nvelope 3 vestments ackage 2 of 3 - Lining of Khajj ak Channels. PK-PMU-BIWRMDP-153960-C W-RFB / Construction of Nari Component B: Water, Infrast Single Stage - One E 1,965,335.1 2022-05-0 Gorge Integrated Scheme - P IDA / 58850 ructure and Management In Post Request for Bids Open - National 2,025,806.00 Signed 2020-01-24 2020-01-28 2020-01-29 2020-02-28 2020-03-02 2020-03-29 2020-04-22 2020-05-03 2020-05-19 nvelope 4 3 ackage 3 of 3 - Construction vestments of Arand & Bori Channels PK-PMU-BIWRMDP-153985-C W-RFB / Works for Constructi Component B: Water, Infrast on of Sehan Irrigation Schem Open - Internationa Single Stage - One E 3,680,180.3 2022-01-2 IDA / 58850 ructure and Management In Post Request for Bids 4,625,806.00 Signed 2020-04-13 2020-08-11 2020-04-18 2020-06-02 2020-09-15 2020-07-02 2020-10-13 2020-08-06 2020-12-15 e - Package 1 of 3 - Construct l nvelope 1 8 vestments ion of Weir, Undersluice, Hea d Regulator, Guide Bunds, M ain Canal and Related Struct ures PK-PMU-BIWRMDP-159126-C W-RFB / Works for Plant Prod uction Through Raising of Nu Component B: Water, Infrast rseries and Other Allied Activ Single Stage - One E 2020-12-1 IDA / 58850 ructure and Management In Post Request for Bids Open - National 300,645.00 0.00 Canceled 2020-02-28 2020-02-24 2020-03-04 2020-04-15 2020-05-15 2020-06-19 ities under B2 Sub Compone nvelope 6 vestments nt Of BIWRMDP Second Phas e For Following LOTs. LOT 4 – DADAR LOT 5 – HARNAI LOT 6 - SIBI Lot 7 -Uthal Lot 8 – K huzdar PK-PMU-BIWRMDP-133752-C W-RFQ / Works for Plant Pr oduction Through Raising o f Nurseries and Other Allied Activities under B2 Sub com Component B: Water, Infrast Single Stage - One E 2020-08-0 ponent Of BIWRMDP Second IDA / 58850 ructure and Management In Post Request for Bids Open - National 300,645.00 0.00 Canceled 2019-10-15 2019-11-16 2019-10-20 2019-12-01 2019-12-23 2019-12-31 2020-02-10 2020-02-04 nvelope 2 Phase For Following LOTs. vestments LOT 4 – DADAR LOT 5 – HARNAI LOT 6 - SIBI Lot 7 -Uthal Lot 8 - Khuzdar PK-PMU-BIWRMDP-144858-G O-RFB / Civil Works for Const Component A: Institutions, C Single Stage - One E 2021-01-2 ruction of Measurement Weir IDA / 58850 Post Request for Bids Open - National 451,612.00 0.00 Canceled 2020-02-17 2020-02-22 2020-03-23 2020-04-22 2020-05-27 apacity and Information nvelope 2 / Flume and Guard Houses a s part of Establishing Phase-I of Hydro-met Network. PK-PMU-BIWRMDP-159162-C Component B: Water, Infrast W-RFQ / Civil Works for Plant Request for Quota Single Stage - One E 2020-09-2 IDA / 58850 ructure and Management In Post Open - National 45,500.00 23,101.38 Completed 2020-02-22 2020-03-27 2020-06-18 ation at Nari Gorge and Mush tions nvelope 3 vestments kaf Integrated Schemes in Na ri River Basin PK-PMU-BIWRMDP-167783-C W-RFB / Lining of Water Cour ses in Command Area of Nari Gorge Integrated Scheme - L Component B: Water, Infrast ot-1 & Lot-2 with following de Single Stage - One E 2021-07-2 IDA / 58850 ructure and Management In Post Request for Bids Open - National 795,180.00 745,887.52 Signed 2020-04-13 2020-04-23 2020-04-18 2020-05-18 2020-06-05 2020-06-17 2020-08-28 2020-07-22 2020-11-06 tail: nvelope 1 vestments Lot-1: Water Courses at Bakh ra S.Khan & Ghulam Bolak, G ullu Shaher, Luni & Sib Jarib Lot-2: Water Courses at Khajj ak, Kurak, Mazre & Marghaza ni PK-PMU-BIWRMDP-171492-C W-RFB / Works for Plant Prod uction Through Raising of Nu Component B: Water, Infrast rseries and Other Allied Activ Single Stage - One E 2021-08-1 IDA / 58850 ructure and Management In Post Request for Bids Open - National 300,645.00 295,921.80 Signed 2020-05-04 2020-05-01 2020-05-09 2020-06-08 2020-06-10 2020-07-08 2020-08-10 2020-08-12 2020-09-25 ities under B2 Sub Compone nvelope 1 vestments nt Of BIWRMDP Second Phas e For Following LOTs. LOT 4 – DADAR LOT 5 – HARNAI LOT 6 - SIBI Lot 7 -Uthal Lot 8 – K huzdar PK-PMU-BIWRMDP-172748-C Component B: Water, Infrast W-RFB / Construction of Nari Single Stage - One E 2,880,032.8 2022-05-0 IDA / 58850 ructure and Management In Post Request for Bids Open - National 2,593,750.00 Signed 2020-05-09 2020-05-10 2020-05-11 2020-06-10 2020-06-10 2020-07-10 2020-06-26 2020-08-14 2020-09-05 Gorge Integrated Scheme Pa nvelope 6 6 vestments ckage 2 of 3 - Lining of Khajja k Channels PK-PMU-BIWRMDP-144866-C W-RFB / Works for Construc tion of Sehan Irrigation Sch Component B: Water, Infrast Single Stage - One E 2021-03-1 eme - Lot No.1 Construction IDA / 58850 ructure and Management In Post Request for Bids Open - National 4,567,000.00 0.00 Canceled 2020-05-29 2020-06-03 2020-07-15 2020-08-14 2020-09-18 nvelope 7 of Weir, Undersluice, Head vestments Regulator, Guide Bunds, Mai n Canal and Related Struct ures - Civil Works PK-PMU-BIWRMDP-144870-C W-RFB / Works for Construc tion of Sehan Irrigation Sc Component B: Water, Infrast Single Stage - One E 3,290,941.2 2022-05-0 heme Package 3 of 3 - Constr IDA / 58850 ructure and Management In Post Request for Bids Open - National 3,680,358.00 Signed 2020-11-05 2020-11-20 2020-11-10 2020-12-10 2020-12-24 2020-12-30 2021-02-19 2021-02-11 2021-05-07 nvelope 5 7 uction of Dis tributaries & R vestments elated Hydraulic Structures and Augmentation of Potable Water Supply System of Mek htar Town PK-PMU-BIWRMDP-203186-C W-RFB / Works for Constructi Component B: Water, Infrast on of Shab-e-Maidan Irrigatio Single Stage - One E 3,878,812.1 2022-05-0 IDA / 58850 ructure and Management In Post Request for Bids Open - National 3,850,662.00 Signed 2020-11-05 2020-11-20 2020-11-10 2020-12-10 2020-12-24 2020-12-30 2021-02-19 2021-02-11 2021-04-21 n Scheme Package 1 of 2 - C nvelope 0 7 vestments onstruction of Weir, Main Can al & Related Hydraulic Struct ures PK-PMU-BIWRMDP-143843-C W-RFB / Works for dry-affore Component B: Water, Infrast station, rangeland improvem Single Stage - One E 2022-05-0 IDA / 58850 ructure and Management In Post Request for Bids Open - National 525,078.00 569,125.61 Signed 2020-11-05 2020-11-20 2020-11-10 2020-12-10 2020-12-24 2020-12-30 2020-12-24 2021-02-11 2021-04-22 ent through water harvesting nvelope 7 vestments structures and plantation/ so wing Package 1 - Nari River B asin Page 3 PK-PMU-BIWRMDP-203187-C W-RFB / Works for dry-affore Component B: Water, Infrast station, rangeland improvem Single Stage - One E 2022-05-0 IDA / 58850 ructure and Management In Post Request for Bids Open - National 681,818.00 778,316.75 Signed 2020-11-05 2020-11-20 2020-11-10 2020-12-10 2020-12-24 2020-12-30 2020-12-24 2021-02-11 2021-04-22 ent through water harvesting nvelope 7 vestments structures and plantation/ so wing Package 2 - Porali River Basin PK-PMU-BIWRMDP-206305-C Component B: Water, Infrast W-RFB / Construction of Line Single Stage - One E 2021-10-0 IDA / 58850 ructure and Management In Post Request for Bids Open - National 285,000.00 265,094.53 Signed 2020-12-15 2021-05-25 2020-12-20 2021-01-31 2021-07-14 2021-03-02 2021-10-06 2021-04-06 2021-11-03 d Water Courses for Nari Basi nvelope 3 vestments n (Narigurage) package 2 0f 2 PK-PMU-BIWRMDP-206297-C W-RFB / Construction of Wate Component B: Water, Infrast Single Stage - One E 2021-09-2 r storage Tanks and Katcha T IDA / 58850 ructure and Management In Post Request for Bids Open - National 730,348.00 731,204.36 Signed 2020-12-15 2021-05-25 2020-12-20 2021-01-19 2021-07-14 2021-02-18 2021-10-06 2021-03-25 2021-11-03 nvelope 1 racks for Nari Basin Package vestments 1 of 2 (Nari Gorge & Mushkaf ) PK-PMU-BIWRMDP-206302-C W-RFB / Construction of Wate Component B: Water, Infrast Single Stage - One E 2021-09-2 r Storage Tanks and Katcha T IDA / 58850 ructure and Management In Post Request for Bids Open - National 557,156.00 48,418.63 Signed 2020-12-15 2020-12-14 2020-12-20 2021-01-19 2021-01-18 2021-02-18 2021-04-23 2021-03-25 2021-06-28 nvelope 1 racks for Poralis Basin Packa vestments ge 1 of 2 (Gundacha-Nimmi) PK-PMU-BIWRMDP-213890-C Component B: Water, Infrast Single Stage - One E 1,145,751.0 2022-06-1 W-RFB / Construction of Floo IDA / 58850 ructure and Management In Post Request for Bids Open - National 1,313,787.00 Signed 2021-01-18 2021-02-09 2021-01-23 2021-02-22 2021-03-15 2021-03-15 2021-04-21 2021-04-19 2021-07-02 nvelope 4 3 d Protection Works at Porali vestments River Basin PK-PMU-BIWRMDP-213891-C Component B: Water, Infrast W-RFB / Construction of Floo Single Stage - One E 1,399,537.0 2022-06-2 IDA / 58850 ructure and Management In Post Request for Bids Open - National 1,519,027.00 Signed 2021-01-25 2021-02-09 2021-01-30 2021-03-01 2021-03-15 2021-03-22 2021-04-21 2021-04-26 2021-07-02 d Protection Works at Nari Ri nvelope 8 0 vestments ver Basin - Package 1, Works at Tariqabad PK-PMU-BIWRMDP-206313-C Component B: Water, Infrast W-RFB / Civil Works Construc Single Stage - One E 1,038,098.4 2022-05-0 IDA / 58850 ructure and Management In Post Request for Bids Open - National 1,161,795.00 Signed 2021-02-10 2021-02-09 2021-02-15 2021-03-29 2021-03-15 2021-04-28 2021-04-22 2021-06-02 2021-07-02 tion of Check dams for Porali nvelope 7 1 vestments Basin package 2 of 2 PK-PMU-BIWRMDP-220308-C Component B: Water, Infrast Single Stage - One E 2022-06-0 W-RFB / Civil Works for Const IDA / 58850 ructure and Management In Post Request for Bids Open - National 2,848,402.00 0.00 Canceled 2021-02-24 2021-03-25 2021-03-01 2021-03-31 2021-05-03 2021-04-30 2021-06-04 nvelope 4 ruction of Sibi Town Water Su vestments pply Scheme PK-PMU-BIWRMDP-223765-C Component B: Water, Infrast W-RFB / Procurement of Wor Single Stage - One E 2022-06-2 IDA / 58850 ructure and Management In Post Request for Bids Open - National 2,380,000.00 0.00 Canceled 2021-03-25 2021-03-25 2021-03-30 2021-04-29 2021-05-29 2021-06-29 ks for Construction of Perenni nvelope 9 vestments al Irrigation Schemes of Dist rict Khuzdar PK-PMU-BIWRMDP-233709-C Request for Bids - Component B: Water, Infrast W-RFB / Lining of water cours Single Stage - One E Small Works SPD 2022-07-0 IDA / 58850 ructure and Management In Post Request for Bids Open - National 278,823.00 0.00 Canceled 2021-06-07 2021-06-12 2021-07-12 2021-08-05 2021-09-09 es at Nimmi & Gundacha Irri nvelope (1 envelope proce 6 vestments gation Schemes ss) PK-PMU-BIWRMDP-233885-C Request for Bids - Component B: Water, Infrast W-RFB / Construction of Terr Single Stage - One E Small Works SPD 2022-07-0 IDA / 58850 ructure and Management In Post Request for Bids Open - National 212,034.00 0.00 Canceled 2021-05-31 2021-06-05 2021-07-05 2021-08-04 2021-09-08 acing System for Water Harv nvelope (1 envelope proce 5 vestments esting at Nari Gorge and Mus ss) hkaf Schemes PK-PMU-BIWRMDP-237314-C W-RFB / Construction of eart hen water courses & structur es, earthen water storage res ervoirs and terracing system Request for Bids - Component B: Water, Infrast Single Stage - One E Small Works SPD Pending Imp 2022-06-1 Lot 1-Nimmi, Gundacha Sche IDA / 58850 ructure and Management In Post Request for Bids Open - National 901,489.00 0.00 2021-06-08 2021-06-13 2021-07-13 2021-08-03 2021-09-17 nvelope (1 envelope proce lementation 4 mes vestments ss) Lot 2-Nari Gorge & Mushkaf S chemes (water courses & res ervoirs) Lot 3 - Contour Terracing at Nari Gorge & Mushkaf PK-PMU-BIWRMDP-237316-C Request for Bids - Component B: Water, Infrast W-RFB / Civil Works for Const Single Stage - One E Small Works SPD 2022-06-2 IDA / 58850 ructure and Management In Post Request for Bids Open - National 205,098.00 259,194.00 Signed 2021-06-08 2021-06-08 2021-06-13 2021-07-13 2021-07-14 2021-08-03 2021-09-09 2021-08-24 2021-11-17 ruction of Water Supply Sche nvelope (1 envelope proce 0 vestments me for Nimmi and Gundacha ss) PK-PMU-BIWRMDP-206310-C Request for Bids - Component B: Water, Infrast W-RFB / Civil Works for Const Single Stage - One E Small Works SPD 1,324,550.9 2022-06-1 IDA / 58850 ructure and Management In Post Request for Bids Open - National 1,349,953.00 Signed 2021-06-08 2021-06-08 2021-06-13 2021-07-13 2021-07-14 2021-08-03 2021-09-09 2021-09-17 2021-11-26 ruction of Check Dams at Nar nvelope (1 envelope proce 7 4 vestments i Basin Package 1 of 2 ss) PK-PMU-BIWRMDP-241468-C W-RFB / Works for Constructi on of Perennial Irrigation Sch emes of District Khuzdar Request for Bids - Lot 1: Works at Hinamy, Sath Component B: Water, Infrast Single Stage - One E Small Works SPD 2,381,392.4 2022-06-3 Bhai & Khazani Bent; IDA / 58850 ructure and Management In Post Request for Bids Open - National 2,235,066.00 Signed 2021-07-05 2021-07-01 2021-07-10 2021-08-09 2021-08-05 2021-08-27 2021-09-09 2021-10-03 2021-11-10 nvelope (1 envelope proce 9 0 Lot 2: Works at Naik Muham vestments ss) mad & Bazenjo Bent; Lot 3: Works at Budri, Pury & Hasan Bent; Lot 4: Works at Salon & Pepri Bent PK-PMU-BIWRMDP-241470-C Request for Bids - W-RFB / Compact, Cluster & Component B: Water, Infrast Single Stage - One E Small Works SPD 1,186,872.6 2022-06-3 Block Plantation & re-sowing IDA / 58850 ructure and Management In Post Request for Bids Open - National 1,134,240.00 Signed 2021-07-05 2021-07-01 2021-07-10 2021-08-09 2021-08-05 2021-08-27 2021-09-09 2021-10-03 2021-11-17 nvelope (1 envelope proce 6 0 of nurseries vestments ss) Lot 1: Nari River Basin Lot 2: Porali River Basin PK-PMU-BIWRMDP-220308-C W-RFB-2 / Civil Works for Con Request for Bids - Component B: Water, Infrast struction of Sibi Town Water Single Stage - One E Small Works SPD 1,988,414.4 2022-06-2 IDA / 58850 ructure and Management In Post Request for Bids Open - National 3,574,850.00 Signed 2021-09-03 2021-08-31 2021-09-08 2021-10-08 2021-10-14 2021-10-26 2021-11-03 2021-11-21 2022-01-13 Supply Scheme. Lot 1 - Sump nvelope (1 envelope proce 8 9 vestments Well and Conduit Channel, Lo ss) t 2 - Treatment Plant and Cle ar & Overhead Water Tanks PK-PMU-BIWRMDP-251672-C Request for Bids - W-RFB / Construction of lined Component B: Water, Infrast Single Stage - One E Small Works SPD Under Imple 2022-06-2 water courses and unlined w IDA / 58850 ructure and Management In Post Request for Bids Open - National 202,567.00 0.00 2021-09-30 2022-03-16 2021-10-05 2021-11-04 2022-04-14 2021-12-04 2022-06-28 2022-01-15 nvelope (1 envelope proce mentation 9 ater storage tanks at Khuzda vestments ss) r Small Scale Irrigation Sche mes Page 4 PK-PMU-BIWRMDP-251675-C W-RFB / Command Area Dev elopment works at Sehan Irri Request for Bids - Component B: Water, Infrast gation Scheme Single Stage - One E Small Works SPD Under Imple 2022-06-2 IDA / 58850 ructure and Management In Post Request for Bids Open - National 467,403.00 0.00 2021-09-15 2022-03-16 2021-09-20 2021-10-20 2022-04-14 2021-11-19 2022-06-28 2021-12-31 Lot 1. Construction of lined & nvelope (1 envelope proce mentation 9 vestments earthen water courses, earth ss) en reservoirs and terracing s ystems. Lot 2. Construction o f lined storage reservoirs and katcha tracks PK-PMU-BIWRMDP-251677-C W-RFB / Construction Lined Water Courses, Water Storag Request for Bids - Component B: Water, Infrast e Tanks, Unlined Water Stora Single Stage - One E Small Works SPD Under Imple 2022-06-3 IDA / 58850 ructure and Management In Post Request for Bids Open - National 163,104.00 0.00 2021-09-30 2022-07-05 2021-10-05 2021-11-04 2021-12-04 2022-01-15 ge Tanks, Kacha Tracks, Eart nvelope (1 envelope proce mentation 0 vestments hen Water Storage Reservoir ss) s, Earthen water Courses and Terracing System at Shab-e- maidan Irrigation Scheme. PK-PMU-BIWRMDP-251681-C W-RFB / Land Leveling, herb, shrub cleaning and precise la Request for Bids - Component B: Water, Infrast nd leveling Single Stage - One E Small Works SPD 2022-06-2 IDA / 58850 ructure and Management In Post Request for Bids Open - National 1,019,522.00 647,518.62 Signed 2021-09-30 2021-10-24 2021-10-05 2021-11-04 2021-10-20 2021-12-04 2022-02-26 2022-01-15 2022-04-28 Lot 1. Nari Gourge. nvelope (1 envelope proce 9 vestments Lot 2. Mushkaf ss) Lot 3. Sehan Lot 4. Gundacha Lot 5. Nimmi & Shab-e-maida n. PK-PMU-BIWRMDP-251684-C Request for Bids - W-RFB / Lining of Water Cour Component B: Water, Infrast Single Stage - One E Small Works SPD 2022-06-2 ses/ Command Area Develop IDA / 58850 ructure and Management In Post Request for Bids Open - National 253,970.00 0.00 Canceled 2021-09-30 2022-01-05 2021-10-05 2021-11-04 2022-02-08 2021-12-04 2022-01-15 nvelope (1 envelope proce 9 ment Works at Nimmi & Gun vestments ss) dacha Irrigation Schemes PK-PMU-BIWRMDP-251686-C W-RFB / Establish Demo Plots & Tunnel . Lot 1- Nari Gorge/ Request for Bids - Mushkaf (Wheat/Cotton),Lot Component B: Water, Infrast Single Stage - One E Small Works SPD 2022-06-3 2. Nari Gourge/Mushkaf (Orc IDA / 58850 ructure and Management In Post Request for Bids Open - National 554,030.00 0.00 Canceled 2021-09-30 2021-12-05 2021-10-05 2021-11-04 2022-02-08 2021-12-04 2022-01-15 nvelope (1 envelope proce 0 hards & Tunnels),Lot 3. Dem vestments ss) os at Sehan, Lot 4. Gundacha /Nimmi/Shab maidan (Wht/C otton), Lot5 Gundacha/Nimmi /Shab Maidan(Orchard & Tun nels) PK-PMU-BIWRMDP-298511-C Request for Bids - W-RFB / Lining of Water Cour Component B: Water, Infrast Single Stage - One E Small Works SPD Pending Imp 2023-04-0 ses/ Command Area Develop IDA / 58850 ructure and Management In Post Request for Bids Open - National 254,000.00 0.00 2022-06-20 2022-06-25 2022-08-06 2022-09-05 2022-10-10 nvelope (1 envelope proce lementation 8 ment Works at Nimmi & Gun vestments ss) dacha Irrigation Schemes PK-PMU-BIWRMDP-298513-C W-RFB / Establish Demo Plots & Tunnel . Lot 1- Nari Gorge/ Request for Bids - Mushkaf (Wheat/Cotton),Lot Component B: Water, Infrast Single Stage - One E Small Works SPD Pending Imp 2023-04-0 2. Nari Gourge/Mushkaf (Orc IDA / 58850 ructure and Management In Post Request for Bids Open - National 554,030.00 0.00 2022-06-20 2022-06-25 2022-08-06 2022-09-05 2022-10-10 nvelope (1 envelope proce lementation 8 hards & Tunnels),Lot 3. Dem vestments ss) os at Sehan, Lot 4. Gundacha /Nimmi/Shab maidan (Wht/C otton), Lot5 Gundacha/Nimmi /Shab Maidan(Orchard & Tun nels) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-PMU-BIWRMDP-2336-GO- RFQ / Office Equipment for P Component C: Project Mana Request for Quota Single Stage - One E MU - Desktops, laptops, print IDA / 58850 gement and Technical Assist Prior Open - National 50,000.00 49,337.27 Signed 2016-10-08 2016-11-03 2016-11-01 2016-12-03 tions nvelope ers, scanners, cameras, inter ance net devices, multimedia etc. PK-PMU-BIWRMDP-2338-GO- Component C: Project Mana RFQ / Furniture & Fixture for Request for Quota Single Stage - One E IDA / 58850 gement and Technical Assist Post Open - National 34,299.00 39,744.82 Completed 2016-10-27 2016-11-29 2016-11-28 2016-12-27 2017-01-10 PMU at Quetta including Rev tions nvelope ance ersible Split AC for PD Office PK-PMU-BIWRMDP-2406-GO- Component C: Project Mana Request for Quota Single Stage - One E RFQ / Procurement of Diesel IDA / 58850 gement and Technical Assist Post Open - National 15,314.00 19,553.87 Completed 2016-11-14 2016-12-14 2017-04-20 2017-01-13 2017-05-03 tions nvelope Generator for PMU ance PK-PMU-BIWRMDP-2413-GO- Component C: Project Mana Request for Quota Single Stage - One E RFQ / Furniture & Fixture for IDA / 58850 gement and Technical Assist Post Open - National 25,842.00 27,052.71 Completed 2016-11-18 2016-12-24 2017-03-06 2017-01-23 2017-05-04 tions nvelope PIUs at Sibi & Uthal ance PK-PMU-BIWRMDP-2414-GO- RFQ / Field Equipment - Relas Component C: Project Mana Request for Quota Single Stage - One E kops, Clinometers, Range Fin IDA / 58850 gement and Technical Assist Post Open - National 21,535.00 25,063.67 Signed 2016-12-09 2017-01-12 2017-12-22 2017-02-11 tions nvelope ders, Level Machines etc. for ance Watershed & Rangeland Man agement PK-PMU-BIWRMDP-2415-GO- Component C: Project Mana Request for Quota Single Stage - One E RFQ / Procurement of Video IDA / 58850 gement and Technical Assist Post Open - National 12,443.00 13,146.03 Completed 2016-11-10 2016-12-14 2017-05-17 2017-01-13 2017-06-18 tions nvelope Conference Equipment for P ance MU PK-PMU-BIWRMDP-2417-GO- Component C: Project Mana Request for Quota Single Stage - One E RFQ / Purchase of Computer IDA / 58850 gement and Technical Assist Post Open - National 47,856.00 29,805.88 Signed 2016-11-30 2017-01-21 2018-01-15 2017-02-26 tions nvelope Software - GIS & Autocad ance PK-PMU-BIWRMDP-14395-GO Component C: Project Mana Request for Quota Single Stage - One E -RFQ / Purchase of Office Equ IDA / 58850 gement and Technical Assist Post Open - National 72,000.00 72,486.33 Signed 2017-05-11 2017-06-02 2017-06-15 2017-06-30 tions nvelope ipment for PMU & PIUs at Sibi ance & Uthal PK-PMU-BIWRMDP-14456-GO Component C: Project Mana -RFQ / Purchase of Split Air C Request for Quota Single Stage - One E IDA / 58850 gement and Technical Assist Post Open - National 50,500.00 40,052.89 Signed 2017-05-12 2017-06-05 2017-11-23 2017-07-05 onditioners, Refrigerators etc tions nvelope ance for PMU & PIUs and Diesel Ge nerators for PIUS PK-PMU-BIWRMDP-18626-NC Component C: Project Mana -RFQ / Purchase of Software - Request for Quota Single Stage - One E IDA / 58850 gement and Technical Assist Post Open - National 29,400.00 25,688.50 Signed 2017-08-02 2017-09-01 2018-01-15 2017-10-16 MS Office, Adobe Pro, Micros tions nvelope ance oft Project, Autocad Civil 3D etc. Page 5 PK-PMU-BIWRMDP-18629-GO Component C: Project Mana Request for Quota Single Stage - One E -RFQ / Special Desktop Comp IDA / 58850 gement and Technical Assist Post Open - National 9,375.00 7,467.27 Signed 2017-08-05 2017-09-08 2018-01-15 2017-10-23 tions nvelope uters for Arc GIS ance PK-PMU-BIWRMDP-2409-GO- Component C: Project Mana RFQ / Procurement of Office Request for Quota Single Stage - One E IDA / 58850 gement and Technical Assist Post Open - National 43,070.00 0.00 Canceled 2016-11-21 2016-12-25 2017-01-24 Equipment & Generators for tions nvelope ance PIUs at Sibi & Uthal PK-PMU-BIWRMDP-34361-GO Component B: Water, Infrast Request for Quota Single Stage - One E -RFQ / Procurement of Furnit IDA / 58850 ructure and Management In Post Open - National 20,000.00 7,284.88 Signed 2017-11-20 2018-01-15 2018-01-10 2018-07-14 tions nvelope ure for Agriculture Field Offic vestments e PK-PMU-BIWRMDP-34363-GO Component B: Water, Infrast Request for Quota Single Stage - One E -RFQ / Procurement of IT Equi IDA / 58850 ructure and Management In Post Open - National 18,000.00 11,234.74 Signed 2017-11-20 2018-01-15 2018-01-15 2018-05-15 tions nvelope pment for Agriculture Field O vestments ffices PK-PMU-BIWRMDP-34364-GO Component B: Water, Infrast Request for Quota Single Stage - One E -RFQ / Procurement of Surve IDA / 58850 ructure and Management In Post Open - National 80,000.00 39,815.82 Signed 2017-11-20 2018-01-15 2018-01-05 2018-05-15 tions nvelope y Equipment vestments PK-PMU-BIWRMDP-2408-GO- Component C: Project Mana Request for Quota Single Stage - One E RFQ / Procurement of Additio IDA / 58850 gement and Technical Assist Prior Open - National 71,784.00 0.00 Canceled 2016-12-07 2017-01-26 2017-04-26 tions nvelope nal Vehicles for Project - 3 Do ance or Jeeps PK-PMU-BIWRMDP-2418-GO- RFB / Supply/ installation of H dyro-meteorological observat Component A: Institutions, C Open - Internationa Single Stage - One E ion stations, rain gauging sta IDA / 58850 Post Request for Bids 2,692,000.00 0.00 Canceled 2017-11-19 2017-11-29 2018-01-20 2018-02-19 2018-03-22 2019-09-13 apacity and Information l nvelope tions, stream gauging station s and groundwater observati on wells including establishm ent of Data Centre PK-PMU-BIWRMDP-96456-GO -RFB / Establishment of Hydr Component A: Institutions, C Single Stage - One E Pending Impl o-met networks Pilot Project ( IDA / 58850 Post Request for Bids Open - National 770,000.00 0.00 2019-02-11 2019-02-16 2019-03-18 2019-04-17 2019-05-22 2020-05-21 apacity and Information nvelope ementation Hydro-met Data Collection and Management System) PK-PMU-BIWRMDP-153962-G Component B: Water, Infrast O-RFB / Procurement of Good Single Stage - One E IDA / 58850 ructure and Management In Post Request for Bids Open - National 406,451.00 341,590.17 Signed 2020-03-05 2020-05-10 2020-03-10 2020-04-09 2020-06-10 2020-05-09 2020-08-08 2020-06-13 2020-09-25 2021-02-08 s for Construction of Nari Gor nvelope vestments ge Water Supply Scheme PK-PMU-BIWRMDP-153979-G Component B: Water, Infrast O-RFB / Procurement of Good Single Stage - One E IDA / 58850 ructure and Management In Post Request for Bids Open - National 198,806.00 207,540.98 Signed 2020-03-05 2020-05-07 2020-03-10 2020-04-09 2020-06-10 2020-05-09 2020-08-08 2020-06-13 2020-09-25 2021-02-08 s for Construction of Mushkaf nvelope vestments Water Supply Scheme PK-PMU-BIWRMDP-159160-G Component B: Water, Infrast O-RFQ / Purchase of Plants fo Request for Quota Single Stage - One E IDA / 58850 ructure and Management In Post Open - National 26,000.00 23,717.20 Signed 2020-02-22 2020-03-27 2020-05-29 2020-09-23 r Plantation at Nari Gorge an tions nvelope vestments d Mushkaf Integrated Schem es of Nari River Basin PK-PMU-BIWRMDP-166190-G O-DIR / Procurement of Good s Pkg 2: : Lot 1,Mobile X-Ray Component A: Institutions, C Machines with CR-System / D IDA / 58850 Post Direct Selection Direct 2,017,164.00 1,759,284.64 Signed 2020-03-30 2020-03-25 2020-04-04 2020-04-03 2020-05-09 2020-07-22 2020-11-05 2020-08-21 apacity and Information R-Based Mobil X-Ray Machin es along with Dry Laser Imag ers, Lot 2, Patient Monitors,L ot 3, ICU Ventilators PK-PMU-BIWRMDP-187938-G O-RFQ / Procurement of Misc Component C: Project Mana Request for Quota Single Stage - One E ellaneous Furniture and Equi IDA / 58850 gement and Technical Assist Post Open - National 11,500.00 11,233.61 Signed 2020-08-21 2020-09-26 2021-01-11 2020-11-10 tions nvelope pment e.g Storage Cabinets, ance Voltage Stabilizer, LED TV et c. PK-PMU-BIWRMDP-166183-G O-DIR / Procurement of Good s Package No: 1 Full Fowler Hospital Motorize d/ Manual Beds along with fol Component A: Institutions, C IDA / 58850 Post Direct Selection Direct 73,760.00 0.00 Canceled 2020-03-30 2020-04-04 2020-05-09 2020-11-05 lowing Accessories: a) Mattre apacity and Information ss b) IV Pole (Separate / Buil t-In) c) Over Head Table d) B ed Side Locker e) Bed Side S creen f)Patient Footstep g) P illow & Cover PK-PMU-BIWRMDP-206307-G Component B: Water, Infrast O-RFB / Goods: Procurement Single Stage - One E IDA / 58850 ructure and Management In Post Request for Bids Open - National 250,000.00 252,492.44 Signed 2020-12-15 2020-12-14 2020-12-20 2021-01-19 2021-01-18 2021-02-18 2021-04-23 2021-03-25 2021-07-14 2021-09-21 of PVC Pipelines forPorali Bas nvelope vestments in (Gundacha-Nimmi) PK-PMU-BIWRMDP-233693-G Component B: Water, Infrast O-RFB / Purchase and laying Single Stage - One E IDA / 58850 ructure and Management In Post Request for Bids Open - National 458,412.00 0.00 Canceled 2021-05-31 2021-05-31 2021-06-05 2021-07-05 2021-07-29 2021-09-02 2022-06-29 of PVC Pipe at Nari Gorge, M nvelope vestments ushkaf & Sehan Irrigation Sc hemes. PK-PMU-BIWRMDP-251669-G O-RFB / Purchase and laying Component B: Water, Infrast Single Stage - One E Under Imple of PVC pipelines for Irrigation IDA / 58850 ructure and Management In Post Request for Bids Open - National 441,373.00 0.00 2021-09-15 2021-09-13 2021-09-20 2021-10-20 2021-10-20 2021-11-19 2021-12-30 2021-12-31 2022-06-15 nvelope mentation Schemes vestments Lot 1. Nari Gorge, Lot 2. Mus hkaf Lot 3. Sehan Lot 4. Shab -e-maidan PK-PMU-BIWRMDP-135510-G O-RFB / Procurement of Good s for Establishment of Hydro- met Network Phase-I - Component A: Institutions, C Open - Internationa Single Stage - One E Lot No 1. Design, supply and IDA / 58850 Post Request for Bids 493,103.00 0.00 Canceled 2020-11-09 2020-12-14 2020-11-14 2020-12-15 2020-12-29 2021-04-04 2021-01-28 2021-03-12 2021-11-07 apacity and Information l nvelope installation of 9 No Automati c Stations, Lot No.2 Design, supply and installation of 2 N o Stream flow Gauging Statio ns PK-PMU-BIWRMDP-135510-G O-RFB-2 / Procurement of Go ods for Establishment of Hyd ro-met Network (Phase-I), Pk Component A: Institutions, C Open - Internationa Single Stage - One E Under Imple g 1 of 2, Lot – 1: Design, Sup IDA / 58850 Post Request for Bids 1,612,595.00 1,175,802.97 2021-11-01 2021-11-18 2021-11-05 2021-11-23 2021-12-20 2022-01-17 2022-01-10 2022-02-03 2022-02-05 2022-10-03 apacity and Information l nvelope mentation ply and Installation of 7 AWS and 12 Automatic Rainfall Ga uging Stations, Lot-2: Design, Supply and Installation of 9 S tream Flow Gauging Stations Page 6 PK-PMU-BIWRMDP-279273-G Component C: Project Mana Request for Quota Single Stage - One E O-RFQ / Purchasing of Laptop IDA / 58850 gement and Technical Assist Post Open - National 6,000.00 5,264.22 Signed 2022-03-02 2022-04-09 2022-05-13 2022-05-09 tions nvelope s, Printers, Scanners etc for P ance MU Office PK-PMU-BIWRMDP-280832-G Component C: Project Mana Request for Quota Single Stage - One E Pending Impl O-RFQ / Procurement of Furni IDA / 58850 gement and Technical Assist Post Open - National 8,000.00 0.00 2022-03-05 2022-04-09 2022-05-19 tions nvelope ementation ture for PMU & PIUs Offices ance PK-PMU-BIWRMDP-280842-G Component C: Project Mana O-RFQ / Purchasing Stationar Request for Quota Single Stage - One E Pending Impl IDA / 58850 gement and Technical Assist Post Open - National 5,500.00 0.00 2022-03-20 2022-04-22 2022-07-01 y and Printing Materials(Man tions nvelope ementation ance uals) for WUAs, FOs etc PK-PMU-BIWRMDP-305089-G O-RFB / Procurement of Good s (Design, supply, installation Component A: Institutions, C Open - Internationa Single Stage - One E Pending Impl IDA / 58850 Post Request for Bids 508,000.00 0.00 2022-07-31 2022-08-05 2022-09-16 2022-10-16 2022-11-20 2023-05-19 , testing, commissioning of a apacity and Information l nvelope ementation utomatic Groundwater Monit oring Wells complete in all re spects) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-PMU-BIWRMDP-2442-NC- RFQ / Project Website Design Component C: Project Mana Request for Quota Single Stage - One E Development, Domain Regist IDA / 58850 gement and Technical Assist Post Open - National 2,400.00 2,943.83 Signed 2016-10-20 2016-11-26 2016-11-16 2017-01-10 tions nvelope ration, Hosting, Maintenance ance and Updating fro One Year PK-PMU-BIWRMDP-18623-NC Component C: Project Mana -DIR / Purchase of 0.3m to 0. IDA / 58850 gement and Technical Assist Post Direct Selection Direct 54,600.00 0.00 Canceled 2017-07-26 2017-10-25 2017-07-31 2017-11-06 2017-08-25 2017-10-09 5m Resolution Satellite Imag ance e for Nari Gorge & Gundacha Area. PK-PMU-BIWRMDP-19640-NC Component C: Project Mana -DIR / Purchase of Arc GIS - T IDA / 58850 gement and Technical Assist Post Direct Selection Direct 30,563.00 0.00 Canceled 2017-07-19 2017-10-26 2017-07-24 2017-08-15 2017-09-29 wo Basic & One Standard Ver ance sion PK-PMU-BIWRMDP-38144-NC Component C: Project Mana -RFQ / Baseline sampling(Lab Request for Quota Single Stage - One E IDA / 58850 gement and Technical Assist Post Open - National 6,000.00 28,014.89 Signed 2018-01-05 2018-03-02 2018-01-04 2018-05-01 oratory Testing) of two integr tions nvelope ance ated schemes for ESMP PK-PMU-BIWRMDP-45893-NC -RFQ / Baseline Sampling(Lab Component B: Water, Infrast Request for Quota Single Stage - One E oratory Testing) (Ambient Air IDA / 58850 ructure and Management In Post Open - National 35,000.00 57,805.06 Signed 2018-02-01 2018-02-27 2018-02-21 2018-03-15 tions nvelope /Noise/Water/Soil) for Nur-Hin vestments gri-Gunacha Irrigation Schem e Scheme for ESMP PK-PMU-BIWRMDP-68865-NC -RFQ / Procurement of Demo Component B: Water, Infrast Plots (PLL, HEIS, Livestock, T Request for Quota Single Stage - One E IDA / 58850 ructure and Management In Post Open - National 95,500.00 0.00 Canceled 2019-11-20 2020-01-15 2020-07-13 unnel farming, nurseries, cro tions nvelope vestments ps) First Lot GUNDACHA & N ARI GUARGE PIS COMMAND A REA INFRSTRUCTURE PK-PMU-BIWRMDP-144898-N Component C: Project Mana C-RFQ / PROCUREMENT OF FI Request for Quota Single Stage - One E IDA / 58850 gement and Technical Assist Post Open - National 30,000.00 0.00 Canceled 2020-03-03 2020-03-26 2020-09-22 NANCIAL/ACCOUNTING & PAY tions nvelope ance ROLL SOFTWARE PK-PMU-BIWRMDP-65562-NC -RFQ / Environmental Baselin Component C: Project Mana Request for Quota Single Stage - One E e studies (Laboratory Testing IDA / 58850 gement and Technical Assist Post Open - National 100,000.00 81,189.59 Signed 2020-02-05 2020-04-01 2020-08-19 2020-09-28 tions nvelope ) for different schemes regar ance ding ESMPs & Checklists PK-PMU-BIWRMDP-190066-C Component B: Water, Infrast W-DIR / Mangroves Restorati IDA / 58850 ructure and Management In Post Direct Selection Direct 117,420.00 115,335.95 Signed 2020-09-29 2020-10-09 2020-10-01 2020-10-14 2020-10-16 2021-03-29 2021-10-16 on and Plantation in MianiHor vestments (Coastal Area of Porali River Basin) PK-PMU-BIWRMDP-250918-N C-RFQ / Procurement of Servi ces to provide Logistics for C Component B: Water, Infrast ommunity Trainings in Nari & Request for Quota Single Stage - One E IDA / 58850 ructure and Management In Post Open - National 100,000.00 92,913.13 Signed 2021-09-14 2021-10-26 2021-11-05 2022-06-28 Porali River Basins tions nvelope vestments Lot 1 – Nari River Basin at Na ri Gorge & Mushkaf Areas, Lo t 2 – Nari River Basin at Seha n, Lot 3 - Porali River Basin PK-PMU-BIWRMDP-295181-N C-DIR / IMPLEMENTATION OF Component B: Water, Infrast Under Imple RANGELAND RESTORATION/ I IDA / 58850 ructure and Management In Post Direct Selection Direct 528,000.00 0.00 2022-05-30 2022-05-27 2022-06-04 2022-07-09 2023-01-05 mentation MPROVEMENT & ALLIED ACTI vestments VITIES IN NARI AND PORALI R IVER BASIN CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-PMU-BIWRMDP-2240-CS- Component C: Project Mana Quality And Cost- Open - Internationa QCBS / Project Supervision & IDA / 58850 gement and Technical Assist Prior 8,824,655.00 9,592,440.89 Signed 2016-10-18 2016-11-20 2016-11-13 2016-11-23 2016-11-30 2017-04-05 2017-01-05 2017-05-29 2017-02-04 2017-08-29 2017-03-04 2017-09-21 2017-04-03 2017-11-30 2022-10-31 Based Selection l Implementation Assistance C ance onsultancy PK-PMU-BIWRMDP-2335-CS- Component C: Project Mana Consultant Qualifi CQS / Hiring Accountancy Fir IDA / 58850 gement and Technical Assist Post Open - National 103,369.00 180,643.38 Signed 2016-11-15 2017-02-10 2016-12-13 2017-01-06 2017-05-16 2017-01-31 2017-07-18 2017-02-24 2017-10-11 2022-10-31 cation Selection m for Quarterly Internal Audit ance PK-PMU-BIWRMDP-2245-CS- Component C: Project Mana Quality And Cost- Open - Internationa QCBS / Monitoring & Evaluati IDA / 58850 gement and Technical Assist Prior 1,758,231.00 0.00 Canceled 2016-10-24 2017-01-03 2016-11-21 2017-02-26 2016-12-15 2017-01-20 2017-02-19 2017-03-19 2017-04-22 2022-10-30 Based Selection l on Consultancy ance Page 7 PK-PMU-BIWRMDP-2334-CS-I Component C: Project Mana NDV / Hiring of Accountancy Consultant Qualifi IDA / 58850 gement and Technical Assist Prior Open - National 4,786.00 4,173.09 Signed 2016-10-27 2017-02-23 2016-11-21 2016-12-15 2017-08-07 2016-12-25 2017-09-12 2017-01-14 2017-09-22 2017-02-13 Firm for External Audit of Ret cation Selection ance roactive Financing PK-PMU-BIWRMDP-50078-CS -CQS / HIRING A CONSULTIN Component C: Project Mana Consultant Qualifi G FIRM FOR THE PREPARATIO IDA / 58850 gement and Technical Assist Post Open - National 170,000.00 0.00 Canceled 2018-03-15 2018-03-14 2018-04-05 2018-05-19 2018-06-18 2018-07-23 2019-01-19 cation Selection N OF CULTURAL HERITAGE M ance ANAGEMENT PLAN (CHMP) PK-PMU-BIWRMDP-109329-C S-CQS / Hiring of Audit Firm t Component C: Project Mana Consultant Qualifi o Carryout Special Audit of Pr IDA / 58850 gement and Technical Assist Post Open - National 10,000.00 2,437.30 Signed 2019-04-08 2019-04-11 2019-04-23 2019-05-10 2019-05-01 2019-05-17 2019-05-01 2019-05-21 2019-05-03 2019-06-04 cation Selection oject Supervision & Impleme ance ntation Assistance Consultan ts PK-PMU-BIWRMDP-2250-CS- Component C: Project Mana Quality And Cost- Open - Internationa IDA / 58850 Post 765,697.00 0.00 Canceled 2018-10-15 2018-11-14 2018-12-15 2019-01-29 2019-02-23 2019-03-30 2019-04-30 2020-04-29 QCBS / Institutional Reforms gement and Technical Assist Based Selection l Consultants ance PK-PMU-BIWRMDP-135514-C Component C: Project Mana Least Cost Selecti S-LCS / Hiring Monitoring & E IDA / 58850 gement and Technical Assist Post Open - National 550,000.00 0.00 Canceled 2019-10-15 2019-11-05 2019-12-19 2020-01-16 2020-02-15 2020-03-21 2020-04-25 2020-10-22 on valuation Consultancy ance PK-PMU-BIWRMDP-279283-C Component C: Project Mana Consultant Qualifi Under Implement S-CQS / Hiring of Audit Firm f IDA / 58850 gement and Technical Assist Post Open - National 6,000.00 0.00 2022-02-25 2022-02-18 2022-03-18 2022-05-01 2022-06-28 2022-05-16 2022-05-31 2022-07-30 cation Selection ation or PSIA Consultants Yearly A ance udit PK-PMU-BIWRMDP-297211-C Component C: Project Mana Consultant Qualifi Under Implement IDA / 58850 Post Open - National 300,000.00 0.00 2022-06-15 2022-06-17 2022-07-06 2022-08-12 2022-08-22 2022-09-03 2024-03-31 S-CQS / Hiring of M&E Consul gement and Technical Assist cation Selection ation ting Firm ance PK-PMU-BIWRMDP-298755-C S-CDS / Hiring the Consulting Component C: Project Mana Quality And Cost- firm for the feasibility studies IDA / 58850 gement and Technical Assist Post Open - National 500,000.00 0.00 Under Review 2022-07-05 2022-06-27 2022-08-02 2022-09-15 2022-10-13 2022-11-12 2022-12-17 2023-01-21 2024-01-21 Based Selection of additional Irrigation schem ance es (Nari & Porali Basins) of th e BIWMRD Project INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-PMU-BIWRMDP-2315-CS-I Component C: Project Mana Individual Consult IDA / 58850 Post Open 103,369.00 4,178.54 Terminated 2016-10-28 2016-12-08 2016-12-18 2017-04-10 2016-12-25 2017-04-24 2017-01-06 2017-04-25 2022-10-31 NDV / Social Safeguards Spec gement and Technical Assist ant Selection ialist ance PK-PMU-BIWRMDP-2317-CS-I Component C: Project Mana Individual Consult IDA / 58850 Post Open 33,021.00 3,132.42 Terminated 2016-10-28 2016-12-08 2016-12-24 2017-05-17 2016-12-31 2017-01-12 2017-05-17 2022-10-31 NDV / Communications Speci gement and Technical Assist ant Selection alist ance PK-PMU-BIWRMDP-2319-CS-I Component C: Project Mana Individual Consult IDA / 58850 Post Open 87,864.00 6,323.39 Terminated 2016-10-28 2017-01-04 2017-01-11 2017-01-23 2017-12-20 2022-10-31 NDV / Water Resources Speci gement and Technical Assist ant Selection alist ance PK-PMU-BIWRMDP-2320-CS-I Component C: Project Mana Individual Consult IDA / 58850 Post Open 87,864.00 3,613.37 Terminated 2016-11-21 2016-12-08 2017-01-07 2017-10-20 2017-01-14 2017-10-20 2017-01-26 2017-10-23 2022-10-31 NDV / Agriculture Specialist gement and Technical Assist ant Selection ance PK-PMU-BIWRMDP-2321-CS-I Component C: Project Mana Individual Consult NDV / Environmental Safegu IDA / 58850 gement and Technical Assist Post Open 86,141.00 3,611.41 Terminated 2016-10-28 2016-12-08 2016-12-30 2017-07-10 2017-01-06 2017-07-05 2017-01-18 2017-07-14 2022-10-31 ant Selection ards Specialist ance PK-PMU-BIWRMDP-2325-CS-I Component C: Project Mana Individual Consult NDV / Monitoring & Evaluatio IDA / 58850 gement and Technical Assist Post Open 117,152.00 1,993.36 Terminated 2016-11-21 2016-12-08 2017-01-30 2017-02-06 2017-04-13 2017-02-18 2017-05-02 2022-10-31 ant Selection n Specialist ance PK-PMU-BIWRMDP-2326-CS-I Component C: Project Mana Individual Consult IDA / 58850 Post Open 86,141.00 2,184.24 Terminated 2016-11-21 2016-12-08 2017-01-25 2017-04-17 2017-02-01 2017-04-20 2017-02-13 2017-04-27 2022-10-31 2018-09-15 NDV / Matching Grant Special gement and Technical Assist ant Selection ist ance PK-PMU-BIWRMDP-2332-CS-I Component C: Project Mana Individual Consult IDA / 58850 Post Open 51,685.00 2,183.20 Terminated 2016-11-21 2016-12-08 2017-01-13 2017-09-25 2017-01-20 2017-02-01 2017-10-03 2022-10-31 NDV / Gender Development S gement and Technical Assist ant Selection pecialist ance PK-PMU-BIWRMDP-2333-CS-I Component C: Project Mana Individual Consult IDA / 58850 Post Open 68,338.00 0.00 Canceled 2016-11-21 2016-12-08 2017-02-09 2017-02-16 2017-02-28 2022-10-31 NDV / Livestock Specialist gement and Technical Assist ant Selection ance PK-PMU-BIWRMDP-2318-CS-I Component C: Project Mana Individual Consult IDA / 58850 Prior Open 117,152.00 0.00 Canceled 2016-10-27 2016-12-01 2016-12-11 2016-12-18 2016-12-30 2022-10-30 NDV / Procurement Specialist gement and Technical Assist ant Selection ance PK-PMU-BIWRMDP-19626-CS Component C: Project Mana Individual Consult -INDV / Hiring of Procurement IDA / 58850 gement and Technical Assist Post Open 275,071.00 3,320.53 Terminated 2017-07-14 2017-09-01 2017-08-16 2017-08-14 2017-08-30 2017-09-29 2017-09-14 2017-09-29 2022-11-06 ant Selection Specialist ance PK-PMU-BIWRMDP-2308-CS-I Component C: Project Mana NDV / Financial Management Individual Consult IDA / 58850 gement and Technical Assist Prior Open 116,769.00 0.00 Canceled 2016-10-08 2016-10-29 2016-11-09 2016-11-08 2016-11-15 2016-11-18 2022-11-01 Specialist at Project Manage ant Selection ance ment Unit Quetta PK-PMU-BIWRMDP-26486-CS Component C: Project Mana Individual Consult -INDV / Hiring of Financial Ma IDA / 58850 gement and Technical Assist Post Open 285,714.00 29,917.08 Terminated 2017-09-07 2017-07-28 2017-10-03 2016-11-23 2017-10-10 2016-11-23 2017-10-22 2016-11-22 2022-10-31 ant Selection nagement Specialist ance PK-PMU-BIWRMDP-38131-CS Component C: Project Mana -CDS / Hiring of Individual Co Individual Consult IDA / 58850 gement and Technical Assist Post Limited 3,000.00 26,196.92 Signed 2017-11-27 2017-11-30 2017-12-02 2017-12-07 2017-12-22 2017-12-15 2017-12-27 2018-01-15 nsultant(Environmental Speci ant Selection ance alist) for short term PK-PMU-BIWRMDP-7458-CS-I Component A: Institutions, C Individual Consult NDV / Hiring of Hydrologist fo IDA / 58850 Post Open 50,000.00 0.00 Canceled 2017-03-01 2017-04-19 2017-05-10 2017-06-14 2017-11-11 apacity and Information ant Selection r Design of Hydro-met Netwo rk PK-PMU-BIWRMDP-2323-CS-I Component C: Project Mana Individual Consult IDA / 58850 Post Open 72,358.00 0.00 Canceled 2016-11-21 2016-12-08 2017-01-19 2017-01-26 2017-02-07 2022-10-31 NDV / Training Management gement and Technical Assist ant Selection Specialist ance PK-PMU-BIWRMDP-60509-CS Component C: Project Mana Individual Consult -INDV / Hiring of Environment IDA / 58850 gement and Technical Assist Post Open 80,000.00 0.00 Canceled 2018-04-24 2018-06-12 2018-07-03 2018-08-07 2019-02-03 ant Selection al Safeguard Specialist ance Page 8 PK-PMU-BIWRMDP-61675-CS -INDV / Hiring of Individual C Component A: Institutions, C Individual Consult IDA / 58850 Prior Direct 9,000.00 0.00 Canceled 2018-05-04 2018-05-04 2018-05-06 2018-05-07 2018-05-08 2018-05-22 onsultant for National Consul apacity and Information ant Selection tative Workshop foe Establis hment of BWRMA PK-PMU-BIWRMDP-61884-CS -INDV / Hiring of Individual C onsultant to Facilitate in Hold Component A: Institutions, C Individual Consult IDA / 58850 Post Direct 9,000.00 7,341.82 Completed 2018-05-08 2018-05-08 2018-05-08 2018-05-08 2018-05-09 2018-05-08 2018-05-09 2018-05-10 2018-05-19 2018-05-18 ing of National Consultative apacity and Information ant Selection Workshop for Establishment of Balochistan Water Resourc e Management Authority. PK-PMU-BIWRMDP-92788-CS Component C: Project Mana Individual Consult -FBS / Hiring of Individual Co IDA / 58850 gement and Technical Assist Post Open 15,652.00 1,714.12 Signed 2019-02-05 2019-03-08 2019-04-09 2019-03-13 2019-03-27 2019-04-22 2020-03-26 2020-04-22 ant Selection nsultant - Financial Managem ance ent Specialist PK-PMU-BIWRMDP-97771-CS Component C: Project Mana Individual Consult -INDV / Hiring of Procuremen IDA / 58850 gement and Technical Assist Post Open 15,652.00 1,701.67 Signed 2019-02-05 2019-03-08 2019-04-21 2019-03-15 2019-04-22 2019-03-30 2019-04-23 2020-03-29 ant Selection t Specialist to work as Individ ance ual Consultant PK-PMU-BIWRMDP-104301-C Component C: Project Mana Individual Consult S-INDV / Selection of Social S IDA / 58850 gement and Technical Assist Post Open 13,043.00 1,697.51 Signed 2019-03-10 2019-03-21 2019-04-28 2019-05-19 2019-06-23 2019-04-23 2019-12-20 ant Selection afeguards Specialist/Individu ance al Consultant PK-PMU-BIWRMDP-104309-C Component C: Project Mana S-INDV / Selection of Environ Individual Consult IDA / 58850 gement and Technical Assist Post Open 13,043.00 1,657.00 Signed 2019-03-10 2019-04-28 2019-04-19 2019-05-19 2019-05-19 2019-06-23 2019-05-13 2019-12-20 mental Safeguards Specialist ant Selection ance /Individual Consultant PK-PMU-BIWRMDP-174159-C Component C: Project Mana Individual Consult S-INDV / Hiring of M&E Speci IDA / 58850 gement and Technical Assist Post Open 18,750.00 1,088.01 Signed 2020-05-21 2020-05-20 2020-07-19 2020-08-07 2020-07-29 2020-08-07 2020-08-19 2020-09-01 2021-08-19 ant Selection alist to work as Individual Co ance nsultant at PMU PK-PMU-BIWRMDP-174177-C Component C: Project Mana S-INDV / Hiring of Gender Sp IDA / 58850 gement and Technical Assist Post Direct Selection Direct 18,750.00 1,070.63 Signed 2020-06-02 2020-05-22 2020-06-12 2020-06-25 2020-07-10 2020-07-01 2021-07-10 ecialist to work at PMU as Ind ance ividual Consultant PK-PMU-BIWRMDP-187935-C Component C: Project Mana Individual Consult S-INDV / Hiring of Environme IDA / 58850 gement and Technical Assist Post Open 19,354.00 1.57 Signed 2020-08-09 2020-08-11 2020-09-12 2020-11-10 2020-09-19 2020-11-11 2020-10-01 2020-11-25 2021-10-01 ant Selection ntal Safeguards Specialist ance PK-PMU-BIWRMDP-215734-C Component A: Institutions, C Individual Consult S-INDV / Hiring of Water Reso IDA / 58850 Post Open 37,500.00 0.00 Canceled 2021-01-27 2021-08-04 2021-03-21 2021-04-11 2021-05-02 2022-05-02 apacity and Information ant Selection urce Specialist PK-PMU-BIWRMDP-218775-C Component C: Project Mana Individual Consult S-INDV / hiring of Gender Spe IDA / 58850 gement and Technical Assist Post Open 18,750.00 1,570.85 Completed 2021-02-15 2021-02-15 2021-04-05 2021-06-28 2021-04-26 2021-06-29 2021-05-31 2021-07-15 2022-06-30 2022-03-15 ant Selection cialist for PMU ance PK-PMU-BIWRMDP-220430-C Component A: Institutions, C Individual Consult S-INDV / Hiring of Water Gov IDA / 58850 Post Open 37,500.00 0.00 Canceled 2021-03-02 2021-04-24 2021-05-08 2021-05-23 2022-05-23 apacity and Information ant Selection ernance Specialist PK-PMU-BIWRMDP-226348-C S-CDS / Technical Assistance Component A: Institutions, C IDA / 58850 Post Direct Selection Direct 320,000.00 320,037.00 Signed 2021-03-30 2021-07-16 2021-04-09 2021-04-06 2021-05-10 2021-09-30 2022-05-10 for Institutional Re-structurin apacity and Information g and Legal Reforms in Wate r Sector PK-PMU-BIWRMDP-229954-C Component C: Project Mana Individual Consult S-INDV / Hiring of Monitoring IDA / 58850 gement and Technical Assist Post Open 21,138.00 1,500.60 Signed 2021-04-22 2021-04-26 2021-05-29 2021-05-07 2021-06-03 2021-08-20 2021-06-15 2021-08-23 2022-06-30 ant Selection & Evaluation Specialist ance PK-PMU-BIWRMDP-247151-C Component C: Project Mana Individual Consult S-INDV / Hiring of Water Reso IDA / 58850 gement and Technical Assist Post Open 18,750.00 1,680.20 Signed 2021-08-16 2021-08-12 2021-10-06 2021-11-24 2021-10-09 2021-11-24 2021-10-18 2021-11-25 2022-06-30 ant Selection urces Specialist to Work at P ance MU PK-PMU-BIWRMDP-265072-C Component C: Project Mana S-INDV / Hiring of Individual Individual Consult IDA / 58850 gement and Technical Assist Post Open 8,571.00 19,793.81 Signed 2021-12-06 2022-01-06 2022-01-21 2022-03-25 2022-01-28 2022-04-04 2022-02-07 2022-04-04 2022-04-08 Consultant to carryout Securi ant Selection ance ty Assessment of Various Proj ect Sites PK-PMU-BIWRMDP-273750-C Component C: Project Mana S-INDV / Hiring a Individual C Individual Consult IDA / 58850 gement and Technical Assist Post Direct 10,000.00 0.00 Canceled 2022-02-22 2022-02-18 2022-03-04 2022-03-09 2022-03-17 2022-06-15 onsultant (Limnologist/Ecolog ant Selection ance ical Advisor/Expert) for Short term Page 9