The World Bank Implementation Status & Results Report Vietnam Solar Transition Accelerator (VISTA) (P172974) Vietnam Solar Transition Accelerator (VISTA) (P172974) EAST ASIA AND PACIFIC | Vietnam | Energy & Extractives Global Practice | Recipient Executed Activities | Investment Project Financing | FY 2021 | Seq No: 2 | ARCHIVED on 20-Jun-2022 | ISR51596 | Implementing Agencies: Ministry of Industry and Trade (MOIT), Socialist Republic of Vietnam Key Dates Key Project Dates Bank Approval Date: 13-Aug-2020 Effectiveness Date: 14-Oct-2020 Original Closing Date: 31-Mar-2025 Revised Closing Date: 31-Mar-2025 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) The Project Development Objective is to support the Government of Vietnam in piloting the implementation of a sustainable solar competitive bidding program to mobilize private investments Has the Project Development Objective been changed since Board Approval of the Project Objective? No Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Moderately Satisfactory Moderately Satisfactory Overall Implementation Progress (IP) Moderately Satisfactory Moderately Unsatisfactory Implementation Status and Key Decisions Vietnam Solar Transition Accelerator (VISTA) implementation progress has been delayed due to the uncertain policy and regulatory environment for procurement of new generation capacity. The scope and relevancy of the project will be reviewed at the end of calendar year 2022. Risks Overall Risk Rating Risk Category Rating at Approval Previous Rating Current Rating Overall Moderate Moderate Moderate 5. Results Project Development Objective Indicators 6/20/2022 Page 1 of 4 The World Bank Implementation Status & Results Report Vietnam Solar Transition Accelerator (VISTA) (P172974) IN01146183 ►Pilot solar competitive bidding completed (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No No No Yes Date 06-Jan-2020 04-Dec-2020 06-Jun-2022 11-Feb-2025 IN01146185 ►Note on lessons learnt from the pilot tenders disseminated to key public stakeholders (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No No No Yes Date 28-Jan-2020 04-Dec-2020 06-Jun-2022 11-Feb-2025 IN01146182 ►Private investments mobilized (US$) (Amount(USD), Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 375,000,000.00 Date 06-Jan-2020 04-Dec-2020 06-Jun-2022 11-Feb-2025 Overall Comments PDO There is no progress in the results framework due to overall lack of implementation progress of the project. Intermediate Results Indicators IN01146184 ►Recruitment of transaction advisory firm with required legal, financial and technical expertise for substation-based competitive bidding (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No No No Yes Date 04-Mar-2019 04-Dec-2020 06-Jun-2022 01-Sep-2021 IN01146231 ►Recruitment of transaction advisory firm with required legal, financial and technical expertise for solar park competitive bidding (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No No No Yes Date 27-Feb-2020 04-Dec-2020 06-Jun-2022 25-Oct-2023 Overall Comments RE 6/20/2022 Page 2 of 4 The World Bank Implementation Status & Results Report Vietnam Solar Transition Accelerator (VISTA) (P172974) There is no progress in the results framework due to overall lack of implementation progress of the project. Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P172974 TF-B2332 Effective USD 1.50 1.50 0.00 0.00 1.50 0%% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P172974 TF-B2332 Effective 13-Aug-2020 14-Oct-2020 14-Oct-2020 31-Mar-2025 31-Mar-2025 Cumulative Disbursements Restructuring History There has been no restructuring to date. Related Project(s) 6/20/2022 Page 3 of 4 The World Bank Implementation Status & Results Report Vietnam Solar Transition Accelerator (VISTA) (P172974) There are no related projects. 6/20/2022 Page 4 of 4