Sample Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan [Original: February 1,2017]: Revision 1 of Updated Procurement Plan, June 21,2017] 2. Date of General Procurement Notice: Dec 24, 2006 3. Period covered by this procurement plan: The procurement period of project covered from year June 2010 to December 2012 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ 500,000 All 2. NCB (Goods) Above US$ 100,000 First contract 3. ICB (Works) Above US$ 15 million All 4. NCB (Works) Above US$ 5 million All 5. (Non-Consultant Services) Below US$ 100,000 First contract [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 4. Reference to (if any) Project Operational/Procurement Manual: Project Operations Manual for World Bank Loan Project P158099 5. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) [List the Packages which require Bank’s prior review first and then the other packages] July 9, 2010 1 2 3 4 5 6 7 Ref. Descripti Estimat Packages Dome Review Comme No. on ed stic by Bank nts Cost Prefe (Prior / US$ rence Post) million (yes/ no) Summary 82 5 No Prior of the ICB (Works) Summary 43.77 15 No Prior of the ICB (Goods) Summary 64.53 18 No Post 1st of the NCB contrac (Works) t for Prior Review Summary 1.86 4 No Post 1st of the NCB contrac (Goods) t for Prior Review Summary 0.45 1 No Prior of the ICB (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 100,000 2. Single Source (Firms) All 3. Individual Above US$ 110,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. July 9, 2010 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimat Package Review Comment of ed s by Bank s Assignmen Cost (Prior / t US$ Post) million Summary 4.17 7 Prior of number of contracts that will be let under QCBS Summary 0.83 1 Prior CQS of number of contracts that will be let under other methods July 9, 2010 PROCUREMENT Pakistan : PK: Punjab Tourism for Economic Growth Project PLAN General Information Country: Pakistan 2017-12-21 Bank’s Approval Date of the Original Procurement Plan: 2022-06-23 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P158099 GPN Date: 2020-08-11 Project Name: PK: Punjab Tourism for Economic Growth Project Loan / Credit No: IDA / 59820 Punjab Tourism for Economic Growth Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned PK-PTEG-40086-CW-RFB / Fa 3. Public Investment Facilit Open - Internationa Single Stage - One E 11,386,666.0 2021-09-3 IDA / 59820 Prior Request for Bids 0.00 Canceled 2018-08-31 2018-09-05 2018-10-17 2018-11-01 2018-11-22 cilities & Amenities up-gradat y l nvelope 0 0 ion at sites PK-PTEG-40077-CW-RFB / Da 3. Public Investment Facilit Single Stage - One E 2019-04-1 rbar sahib road Kartarpur - R IDA / 59820 Prior Request for Bids Open - National 588,219.00 0.00 Canceled 2018-08-06 2018-08-11 2018-09-22 2018-10-07 2018-10-21 y nvelope 9 ehabilitation of secondary & t ertiary roads PK-PTEG-40079-CW-RFB / Ta 3. Public Investment Facilit Single Stage - One E 2019-04-2 xila- Toap Mankila- Mohra - R IDA / 59820 Post Request for Bids Open - National 1,437,133.00 0.00 Canceled 2018-08-13 2018-08-18 2018-09-29 2018-10-14 2018-10-28 y nvelope 6 ehabilitation of roads PK-PTEG-40080-CW-RFB / Na 3. Public Investment Facilit Open - Internationa Single Stage - One E 2019-03-2 nkana Sahib-Farooqabad roa IDA / 59820 Post Request for Bids 5,262,066.00 0.00 Canceled 2018-07-16 2018-07-21 2018-09-01 2018-09-16 2018-09-30 y l nvelope 9 d - Rehabilitation of road PK-PTEG-40081-CW-RFB / E 3. Public Investment Facilit Single Stage - One E 2018-12-1 minabad - Rori roads - Rehab IDA / 59820 Post Request for Bids Open - National 399,228.00 0.00 Canceled 2018-04-04 2018-04-09 2018-05-21 2018-06-05 2018-06-19 y nvelope 6 ilitation of roads PK-PTEG-40084-CW-RFB / Uc 3. Public Investment Facilit Single Stage - One E 2019-04-1 IDA / 59820 Post Request for Bids Open - National 1,199,457.00 0.00 Canceled 2018-08-06 2018-08-11 2018-09-20 2018-10-04 2018-10-18 h Sharif road - Rehabilitation y nvelope 6 of roads PK-PTEG-40085-CW-RFB / Gh 3. Public Investment Facilit Single Stage - One E 2019-03-2 ulam Farid Mithan Kot Rajanp IDA / 59820 Post Request for Bids Open - National 1,024,428.00 0.00 Canceled 2018-07-09 2018-07-14 2018-08-25 2018-09-09 2018-09-23 y nvelope 2 ur - Rehabilitation of roads PK-PTEG-194132-CW-RFB / R 3. Public Investment Facilit Single Stage - One E 4,346,514.4 2021-11-2 oads Rehabilitation in Punjab IDA / 59820 Post Request for Bids Open - National 6,000,000.00 Signed 2020-09-16 2020-09-17 2020-09-18 2020-09-17 2020-10-20 2020-10-20 2020-10-30 2020-11-10 2020-11-20 2020-12-09 y nvelope 3 0 (4 Packages, 6 Roads) PK-PTEG-238517-CW-RFB / R 3. Public Investment Facilit Single Stage - One E Other (with field f Under Imple 2022-08-1 ehabilitation of Roads - Uch S IDA / 59820 Post Request for Bids Open - National 3,300,000.00 0.00 2021-06-08 2021-06-30 2021-06-10 2021-07-14 2021-07-10 2021-07-25 2021-08-22 y nvelope or explanation) mentation 7 harif & Channan Pir PK-PTEG-269512-CW-RFQ / T Request for Quota 3. Public Investment Facilit Request for Quota Single Stage - One E Under Imple 2022-08-0 axila Museum - Design & Con IDA / 59820 Post Open - National tions (Non Bank-S 95,000.00 0.00 2021-12-31 2022-03-25 2022-02-04 y tions nvelope mentation 3 struction of Entrance Gate PD) Request for Bids - PK-PTEG-279723-CW-RFB / C 3. Public Investment Facilit Single Stage - One E Small Works SPD Under Imple 2023-04-2 onstruction/Rehabilitation of IDA / 59820 Post Request for Bids Open - National 1,950,000.00 0.00 2022-02-22 2022-03-25 2022-02-27 2022-03-29 2022-03-29 2022-04-13 2022-04-27 y nvelope (2 envelope proce mentation 2 Toilet facilities at Heritage & ss) Tourist Sites GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-PTEG-32430-GO-RFQ / Ve 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 40,000.00 0.00 Canceled 2018-02-05 2018-04-02 2018-09-29 hicles Procurement onitoring and Evaluation tions nvelope PK-PTEG-32431-GO-RFQ / Of 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 58,650.00 23,294.21 Signed 2018-02-04 2018-04-01 2018-05-18 2018-09-28 fice Furniture onitoring and Evaluation tions nvelope PK-PTEG-40059-GO-RFQ / Po 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 9,600.00 6,930.48 Signed 2018-03-03 2018-04-28 2018-06-01 2018-10-25 wer Generator onitoring and Evaluation tions nvelope PK-PTEG-40060-GO-RFQ / Of fice Equipment 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 17,000.00 5,280.80 Signed 2018-01-13 2018-06-30 2018-03-10 2018-06-01 2018-09-06 (Telephone Exchange, CCTV, onitoring and Evaluation tions nvelope Air conditioners, refrigerators etc.) PK-PTEG-40065-GO-RFQ / M 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 600.00 0.00 Canceled 2018-01-24 2018-03-21 2018-09-17 otor Bike onitoring and Evaluation tions nvelope PK-PTEG-40054-GO-RFQ / IT Equipment 4. Project Management, M Request for Quota Single Stage - One E (Laptops, Desktops, Server, P IDA / 59820 Post Open - National 39,000.00 22,115.80 Signed 2017-12-30 2018-02-14 2018-02-24 2018-06-01 2018-08-23 onitoring and Evaluation tions nvelope rinters, Scanner, Multimedia Projector etc.) PK-PTEG-40058-GO-RFQ / Ne 4. Project Management, M Request for Quota Single Stage - One E tworking for IT connectivity & IDA / 59820 Post Open - National 7,000.00 2,693.07 Signed 2018-02-25 2018-04-22 2018-06-01 2018-10-19 onitoring and Evaluation tions nvelope Telephone Exchange PK-PTEG-40067-GO-RFB / Hu 1. Policy, Institutions and Open - Internationa Single Stage - One E IDA / 59820 Post Request for Bids 200,000.00 0.00 Canceled 2018-04-16 2018-04-21 2018-06-02 2018-06-18 2018-07-02 2018-12-29 man Resource Information Sy Governance for Tourism Dev l nvelope stem elopment PK-PTEG-93484-GO-RFB / To 1. Policy, Institutions and Open - Internationa Single Stage - One E IDA / 59820 Prior Request for Bids 3,500,000.00 0.00 Canceled 2019-02-04 2019-02-09 2019-03-23 2019-04-22 2019-05-27 2019-11-23 urism Mobile Application Governance for Tourism Dev l nvelope elopment PK-PTEG-151606-GO-RFQ / P urchase of new IT Equipment and software for project staf 4. Project Management, M Request for Quota Single Stage - One E Pending Impl f. IDA / 59820 Post Open - National 15,000.00 0.00 2019-12-24 2019-12-28 2020-01-31 onitoring and Evaluation tions nvelope ementation 7 Laptops Core i-5 8GB ram 1 3.3" Screen size 256/512 GB HDD Windows 10 + MS Office 1 Tablet Page 1 PK-PTEG-161181-GO-RFQ / I 4. Project Management, M Request for Quota Single Stage - One E Pending Impl IDA / 59820 Post Open - National 17,300.00 0.00 2020-03-14 2020-05-09 2020-11-05 T Equipment onitoring and Evaluation tions nvelope ementation PK-PTEG-161189-GO-RFQ / O 4. Project Management, M Request for Quota Single Stage - One E Pending Impl IDA / 59820 Post Open - National 11,800.00 0.00 2020-03-14 2020-05-09 2020-11-05 ffice Equipment onitoring and Evaluation tions nvelope ementation PK-PTEG-161192-GO-RFQ / O 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 16,000.00 10,960.00 Signed 2020-03-14 2020-03-17 2020-05-09 2020-03-20 2020-11-05 ffice Furniture onitoring and Evaluation tions nvelope PK-PTEG-186934-GO-RFB / Si 3. Public Investment Facilit Single Stage - One E Under Imple IDA / 59820 Post Request for Bids Open - National 1,000,000.00 0.00 2020-08-13 2020-08-31 2020-08-18 2020-09-03 2020-09-29 2020-10-05 2020-10-14 2020-10-19 2020-11-04 2023-10-20 gnboards - Supply and Install y nvelope mentation ation (FA) PK-PTEG-200114-GO-RFQ / P 3. Public Investment Facilit Request for Quota Single Stage - One E IDA / 59820 Post Limited 2,500.00 2,580.69 Signed 2020-10-20 2020-10-26 2020-11-05 2020-10-30 2020-11-12 rofessional Camera y tions nvelope PK-PTEG-200602-GO-RFQ / O 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 36,000.00 19,551.99 Signed 2020-10-27 2020-10-28 2020-11-26 2020-11-11 2021-02-24 ffice Furniture - Tourism Dep onitoring and Evaluation tions nvelope artment PK-PTEG-200605-GO-RFQ / I 4. Project Management, M Request for Quota Single Stage - One E Under Imple IDA / 59820 Post Open - National 25,200.00 0.00 2020-10-30 2020-10-28 2020-12-11 2021-02-09 T Equipment - Tourism Depar onitoring and Evaluation tions nvelope mentation tment PK-PTEG-200606-GO-RFQ / O 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 15,000.00 12,992.20 Signed 2020-10-31 2020-11-19 2020-12-15 2020-12-10 2021-02-13 ffice Equipment - Tourism De onitoring and Evaluation tions nvelope partment PK-PTEG-230268-GO-RFQ / G 3. Public Investment Facilit Request for Quota Single Stage - One E IDA / 59820 Post Open - National 150,000.00 163,734.37 Signed 2021-04-30 2021-05-07 2021-06-04 2021-06-09 2021-12-01 olf Carts for Heritage Sites y tions nvelope PK-PTEG-230269-GO-RFQ / H 3. Public Investment Facilit Request for Quota Single Stage - One E IDA / 59820 Post Open - National 70,000.00 34,537.37 Signed 2021-05-01 2021-05-07 2021-06-05 2021-06-22 2021-12-02 eritage Rikshaws y tions nvelope PK-PTEG-230271-GO-RFQ / C 3. Public Investment Facilit Request for Quota Single Stage - One E IDA / 59820 Post Open - National 100,000.00 80,079.55 Signed 2021-05-01 2021-05-07 2021-06-05 2021-06-07 2021-12-02 oaster - Shuttle Bus y tions nvelope PK-PTEG-228308-GO-RFQ / S 3. Public Investment Facilit Request for Quota Single Stage - One E IDA / 59820 Post Open - National 95,000.00 38,012.80 Signed 2021-05-01 2021-09-03 2021-06-05 2021-10-28 2021-12-02 MD for Taxila Museum y tions nvelope PK-PTEG-231715-GO-RFB / S 3. Public Investment Facilit Single Stage - One E Under Imple IDA / 59820 Post Request for Bids Open - National 700,000.00 0.00 2021-05-05 2021-08-04 2021-05-10 2021-08-05 2021-06-09 2021-06-23 2021-07-14 2022-01-10 olid Waste Management Equi y nvelope mentation pment PK-PTEG-256404-GO-RFQ / O 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 35,000.00 34,327.89 Signed 2021-10-15 2021-10-07 2021-11-16 2021-10-26 2022-05-15 ffice Furniture - Tourism Dep onitoring and Evaluation tions nvelope artment PK-PTEG-256408-GO-RFQ / O ffice Equipment - Tourism De 4. Project Management, M Request for Quota Single Stage - One E Pending Impl IDA / 59820 Post Open - National 24,000.00 0.00 2021-10-15 2021-11-19 2022-05-18 partment onitoring and Evaluation tions nvelope ementation DSLR, AC, Generator 15 KV, Refrigirator, Fax Machine PK-PTEG-256411-GO-RFQ / I T Equipment - Tourism Depar 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 25,000.00 8,175.37 Signed 2021-10-15 2021-10-11 2021-11-19 2021-10-28 2022-05-18 tment onitoring and Evaluation tions nvelope LEDs, Printers, Smart Phones , Video Conferencing System PK-PTEG-271627-GO-RFB / S olid Waste Management Equi 3. Public Investment Facilit Single Stage - One E Under Imple pment IDA / 59820 Post Request for Bids Open - National 200,000.00 0.00 2022-01-05 2022-01-10 2022-01-07 2022-01-13 2022-02-06 2022-02-13 2022-02-27 2022-08-26 y nvelope mentation 10 Mini Tippers 05 Mechanical Sweepers (Tra ctor driven) PK-PTEG-222318-GO-RFB / G 3. Public Investment Facilit Single Stage - One E IDA / 59820 Post Request for Bids Open - National 165,000.00 0.00 Canceled 2021-03-10 2021-03-15 2021-04-14 2021-04-24 2021-05-15 2021-11-11 olf Carts & Heritage Rikshaw y nvelope s PK-PTEG-227444-GO-RFB / S 3. Public Investment Facilit Single Stage - One E olar Power Energy System for IDA / 59820 Post Request for Bids Open - National 410,000.00 0.00 Canceled 2021-04-02 2021-04-06 2021-04-04 2021-04-08 2021-05-06 2021-05-21 2021-06-16 2022-06-11 y nvelope Heritage Sites PK-PTEG-275532-GO-RFB / D 3. Public Investment Facilit Open - Internationa Single Stage - One E Under Imple IDA / 59820 Prior Request for Bids 3,000,000.00 0.00 2022-02-11 2022-05-06 2022-02-16 2022-05-07 2022-04-02 2022-04-16 2022-05-21 2022-11-17 ouble Decker Buses - 9 buses y l nvelope mentation PK-PTEG-283628-GO-RFB / P 3. Public Investment Facilit Single Stage - One E Pending Impl re-fabricated Containers for IDA / 59820 Post Request for Bids Open - National 240,000.00 0.00 2022-03-18 2022-03-23 2022-04-22 2022-04-29 2022-05-20 2022-11-16 y nvelope ementation Rescue Services - Murree Im plementation Plan PK-PTEG-283630-GO-RFB / R 3. Public Investment Facilit Single Stage - One E Pending Impl ecovery Vehicles for Rescue IDA / 59820 Post Request for Bids Open - National 400,000.00 0.00 2022-03-18 2022-03-23 2022-04-22 2022-04-29 2022-05-20 2022-11-16 y nvelope ementation Services - Murree Implement ation Plan PK-PTEG-283631-GO-RFB / A 3. Public Investment Facilit Single Stage - One E Pending Impl mbulances with fabrication R IDA / 59820 Post Request for Bids Open - National 600,000.00 0.00 2022-03-18 2022-03-23 2022-04-22 2022-05-06 2022-05-27 2022-11-23 y nvelope ementation escue Services - Murree Impl ementation Plan PK-PTEG-283632-GO-RFB / R 3. Public Investment Facilit Single Stage - One E Pending Impl escue Equipment for Rescue IDA / 59820 Post Request for Bids Open - National 300,000.00 0.00 2022-03-18 2022-03-23 2022-04-22 2022-05-06 2022-05-27 2022-11-23 y nvelope ementation Services - Murree Implement ation Plan PK-PTEG-283634-GO-RFQ / R 3. Public Investment Facilit Request for Quota Single Stage - One E Under Imple ehabilitation of Takht-e-Babri IDA / 59820 Post Open - National 100,000.00 0.00 2022-03-16 2022-03-16 2022-04-16 2022-06-15 y tions nvelope mentation , Kalar Kahar PK-PTEG-286749-GO-RFQ / A 3. Public Investment Facilit Request for Quota Single Stage - One E Under Imple rcheological Laboratory Equi IDA / 59820 Post Open - National 68,000.00 0.00 2022-03-30 2022-05-16 2022-05-05 2022-11-01 y tions nvelope mentation pment - Directorate of Arche ology PK-PTEG-293035-GO-RFB / V 4. Project Management, M Single Stage - One E Pending Impl ehicles for PTEGP (PMU-Touri IDA / 59820 Post Request for Bids Open - National 750,000.00 0.00 2022-05-09 2022-05-14 2022-06-11 2022-06-18 2022-07-02 2023-06-27 onitoring and Evaluation nvelope ementation sm Department and C&W) & IDAP PK-PTEG-295160-GO-RFB / P 3. Public Investment Facilit Single Stage - One E Pending Impl rocurement of Architectural a IDA / 59820 Post Request for Bids Open - National 725,000.00 0.00 2022-06-26 2022-07-01 2022-07-31 2022-08-14 2022-09-11 2023-03-10 y nvelope ementation nd Civil Engineering related S oftware PK-PTEG-295161-GO-RFB / P rocurement of Computer Equ 3. Public Investment Facilit Single Stage - One E Pending Impl IDA / 59820 Post Request for Bids Open - National 795,000.00 0.00 2022-06-27 2022-07-02 2022-08-01 2022-08-15 2022-09-19 2023-03-18 ip. Drones, Terrestrial Laser y nvelope ementation Scanner & Total Station for I DAP Page 2 NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-PTEG-48673-NC-RFQ / Ev 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 30,000.00 27,702.75 Signed 2018-02-14 2018-02-15 2018-02-26 2018-02-13 2018-03-08 ent Management Firm - Proje onitoring and Evaluation tions nvelope ct Launch PK-PTEG-91147-NC-RFQ / Su 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 35,000.00 10,591.35 Signed 2019-01-12 2019-02-13 2019-03-09 2019-04-22 2019-09-05 rvey Firm for Data collection onitoring and Evaluation tions nvelope PK-PTEG-103229-NC-RFQ / T 4. Project Management, M Request for Quota Single Stage - One E ourism Sector regulation and IDA / 59820 Post Open - National 20,000.00 0.00 Canceled 2019-03-04 2019-04-29 2019-06-30 onitoring and Evaluation tions nvelope Inspection Mapping Exercise -4 Months PK-PTEG-103234-NC-RFQ / D ocumentary Preparation of K 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 100,000.00 0.00 Canceled 2019-03-10 2019-05-05 2019-06-30 artarpur site (Non Consultanc onitoring and Evaluation tions nvelope y Services) 2-Months PK-PTEG-103260-NC-RFQ / T 4. Project Management, M Request for Quota Single Stage - One E raining need assessment of S IDA / 59820 Post Open - National 100,000.00 0.00 Canceled 2019-03-04 2019-04-29 2019-06-30 onitoring and Evaluation tions nvelope kill training 4-Months PK-PTEG-141301-NC-DIR / Pr 4. Project Management, M Pending Impl ocurement of Planning & Mon IDA / 59820 Post Direct Selection Direct 1,260.00 0.00 2019-10-21 2019-10-26 2019-11-08 2019-11-18 onitoring and Evaluation ementation itoring Software (SMARTSHEE T) PK-PTEG-140344-NC-DIR / H all and Auditorium facility ch 1. Policy, Institutions and arges for conduct of Lahore I IDA / 59820 Governance for Tourism Dev Post Direct Selection Direct 50,000.00 0.00 Canceled 2019-10-23 2019-10-28 2019-12-07 2019-12-28 nternational Tourism Expo (LI elopment TE) at Expo center Lahore PK-PTEG-134818-NC-RFQ / H 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 20,000.00 0.00 Canceled 2019-09-19 2019-09-24 2019-09-27 iring of Firm for Event Manag onitoring and Evaluation tions nvelope ement PK-PTEG-159994-NC-RFQ / E 3. Public Investment Facilit Request for Quota Single Stage - One E IDA / 59820 Post Open - National 12,000.00 4,442.20 Signed 2020-02-24 2020-02-25 2020-03-18 2020-03-17 2022-03-08 nvironment Laboratory y tions nvelope PK-PTEG-300757-NC-RFQ / T 3. Public Investment Facilit Request for Quota Single Stage - One E Pending Impl opographic Survey of Archeol IDA / 59820 Post Open - National 100,000.00 0.00 2022-07-01 2022-08-05 2023-02-01 y tions nvelope ementation ogical Sites CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-PTEG-32421-CS-QCBS / H 3. Public Investment Facilit UN Agencies (Dire iring of Heritage Firm IDA / 59820 Prior Direct 500,000.00 2,834,843.00 Signed 2018-01-27 2018-02-19 2021-01-29 y ct) UNESCO PK-PTEG-32423-CS-QCBS / H 1. Policy, Institutions and Quality And Cost- Open - Internationa Under Implement iring of firm for Legal & Regul IDA / 59820 Governance for Tourism Dev Prior 750,000.00 0.00 2017-12-25 2018-07-24 2018-01-15 2018-02-28 2018-03-28 2018-04-27 2018-06-01 2018-07-06 2019-07-06 Based Selection l ation atory Review elopment PK-PTEG-32425-CS-CQS / Int 4. Project Management, M Least Cost Selecti ernal Audit Firm IDA / 59820 Post Open - National 150,000.00 0.00 Canceled 2017-12-18 2018-01-08 2018-02-21 2018-03-21 2018-04-20 2018-05-25 2018-06-29 2022-12-30 onitoring and Evaluation on Estimated cost for 5 years PK-PTEG-32422-CS-QCBS / Fi 2. Private Investment and Quality And Cost- Open - Internationa IDA / 59820 Post 1,500,000.00 0.00 Canceled 2018-01-31 2018-12-28 2018-02-16 2018-03-09 2018-04-23 2018-05-08 2018-05-22 2018-06-05 2020-10-13 rm Hiring for Skills Developm Entrepreneurship Promotion Based Selection l ent PK-PTEG-32418-CS-QCBS / S 3. Public Investment Facilit Quality And Cost- Open - Internationa upervision & Quality Assuran IDA / 59820 Prior 952,380.00 94,799.46 Signed 2018-01-15 2019-02-11 2018-01-30 2019-02-11 2018-02-27 2020-05-08 2018-04-01 2020-04-15 2018-04-17 2020-05-09 2018-05-08 2020-07-17 2018-05-22 2020-07-09 2020-09-29 y Based Selection l ce Firm Civil Works consultant firm - PISC PK-PTEG-32427-CS-CQS / Up 1. Policy, Institutions and Quality And Cost- Open - Internationa gradation of Existing Institute IDA / 59820 Governance for Tourism Dev Prior 750,000.00 0.00 Canceled 2018-02-01 2018-02-16 2018-03-12 2018-04-24 2018-05-09 2018-05-23 2018-06-06 2019-06-06 Based Selection l s - Hiring of firm elopment PK-PTEG-51948-CS-CQS / Int 4. Project Management, M Consultant Qualifi IDA / 59820 Post Open - National 150,000.00 0.00 Canceled 2018-03-06 2018-05-01 2018-03-26 2018-05-10 2018-05-17 2018-06-14 2023-04-30 ernal Audit Firm - 5 Years Co onitoring and Evaluation cation Selection ntract PK-PTEG-64589-CS-CQS / Up 1. Policy, Institutions and Consultant Qualifi gradation of Existing Institute IDA / 59820 Governance for Tourism Dev Post Open - National 400,000.00 0.00 Canceled 2018-06-11 2018-06-19 2018-07-02 2018-08-15 2018-09-14 2018-10-19 2019-06-28 cation Selection s - Restructuring of TDCP elopment PK-PTEG-93553-CS-QCBS / R 1. Policy, Institutions and Quality And Cost- Under Implement IDA / 59820 Post Open - National 500,000.00 0.00 2019-01-14 2019-01-08 2019-02-04 2019-02-13 2019-03-20 2019-04-17 2019-05-17 2019-06-21 2019-07-26 2020-07-25 e-structuring of TDCP Governance for Tourism Dev Based Selection ation elopment PK-PTEG-110939-CS-CQS / D 4. Project Management, M Consultant Qualifi Under Implement ocumentary Preparation of K IDA / 59820 Post Open - National 100,000.00 0.00 2019-04-22 2019-05-10 2019-05-13 2019-07-08 2019-06-26 2019-08-21 2019-07-26 2019-08-30 2020-04-30 onitoring and Evaluation cation Selection ation artarpur site PK-PTEG-110942-CS-CQS / T 4. Project Management, M Consultant Qualifi Under Implement IDA / 59820 Post Open - National 100,000.00 0.00 2019-04-22 2019-05-10 2019-05-13 2019-07-08 2019-06-26 2019-07-26 2019-08-30 2020-04-30 raining need assessment of S onitoring and Evaluation cation Selection ation kill training PK-PTEG-128723-CS-LCS / Hi 4. Project Management, M Least Cost Selecti IDA / 59820 Post Open - National 250,000.00 0.00 Canceled 2019-08-25 2020-03-09 2019-09-15 2019-10-29 2019-11-26 2019-12-26 2020-01-30 2020-03-05 2023-03-05 ring of Media Firm onitoring and Evaluation on PK-PTEG-103226-CS-LCS / Hi 4. Project Management, M Least Cost Selecti IDA / 59820 Post Open - National 150,000.00 0.00 Canceled 2019-02-27 2019-03-08 2019-03-20 2019-03-11 2019-05-03 2019-07-19 2019-05-31 2019-08-23 2019-06-30 2019-08-04 2019-09-08 2022-06-30 ring of Internal Audit Firm 5- onitoring and Evaluation on Years PK-PTEG-32414-CS-CQS / Me 2. Private Investment and Consultant Qualifi IDA / 59820 Prior Open - National 2,500,000.00 0.00 Canceled 2017-11-20 2018-09-20 2017-12-11 2018-01-24 2018-02-23 2018-03-30 2020-11-23 dia Firm hiring Entrepreneurship Promotion cation Selection PK-PTEG-163250-CS-QCBS / I 1. Policy, Institutions and Quality And Cost- IDA / 59820 Post Open - National 300,000.00 188,305.86 Signed 2020-03-13 2020-03-09 2020-04-02 2020-03-13 2020-04-19 2020-07-29 2020-05-19 2020-08-31 2020-05-29 2020-09-17 2020-06-15 2020-10-20 2020-07-06 2020-12-16 2021-07-01 SMP Qila Kohna Qasim Bagh Governance for Tourism Dev Based Selection elopment PK-PTEG-164014-CS-QCBS / 1. Policy, Institutions and Quality And Cost- IDA / 59820 Post Open - National 250,000.00 544,997.13 Signed 2020-03-12 2020-03-11 2020-04-02 2020-03-13 2020-05-16 2020-07-13 2020-06-13 2020-08-25 2020-07-13 2020-09-16 2020-08-17 2020-10-05 2020-09-21 2021-02-03 2023-09-06 Media Firm Hiring Governance for Tourism Dev Based Selection elopment Page 3 PK-PTEG-183974-CS-QCBS / Destination Investment & Ma 1. Policy, Institutions and Quality And Cost- Open - Internationa nagement Plans (DIMPs) Con IDA / 59820 Governance for Tourism Dev Prior 3,000,000.00 614,175.00 Signed 2020-07-16 2020-07-24 2020-07-26 2020-08-28 2020-08-30 2020-11-26 2020-09-27 2021-01-11 2020-10-12 2021-03-03 2020-11-02 2021-03-16 2020-12-07 2021-05-14 2022-12-07 Based Selection l sultancy Services - elopment IDC (Framework contract) PK-PTEG-206682-CS-CQS / E 3. Public Investment Facilit Consultant Qualifi Under Implement nvironment Impact Assessme IDA / 59820 Post Open - National 100,000.00 0.00 2020-12-01 2020-12-15 2020-12-16 2020-12-30 2021-01-06 2021-02-11 2021-01-13 2021-01-25 2022-01-25 y cation Selection ation nt Services PK-PTEG-223666-CS-QCBS / 3. Public Investment Facilit Quality And Cost- Open - Internationa Pending Impleme Taxila Museum Upgradation - IDA / 59820 Post 450,000.00 0.00 2021-03-19 2021-04-03 2021-04-20 2021-05-18 2021-06-01 2021-06-22 2021-07-13 2022-07-13 y Based Selection l ntation Consulting Firm PK-PTEG-228305-CS-CQS / A 3. Public Investment Facilit Consultant Qualifi Pending Impleme rchitectural Firm for Design o IDA / 59820 Post Open - National 100,000.00 0.00 2021-04-11 2021-04-26 2021-05-17 2021-05-24 2021-06-07 2021-12-04 y cation Selection ntation f New Museum at Harappa PK-PTEG-246068-CS-QCBS / 3. Public Investment Facilit Quality And Cost- Under Implement Design Review and Supervisi IDA / 59820 Post Open - National 550,000.00 0.00 2021-08-02 2021-08-02 2021-08-17 2021-09-07 2021-10-05 2021-10-19 2021-11-02 2021-11-23 2022-11-23 y Based Selection ation on Firm (Roads & Buildings) PK-PTEG-267389-CS-CQS / S 3. Public Investment Facilit Consultant Qualifi Under Implement olar Energy - Design & Super IDA / 59820 Post Open - National 45,000.00 0.00 2021-12-13 2021-12-14 2021-12-28 2022-01-20 2022-01-26 2022-02-09 2022-02-23 2023-02-18 y cation Selection ation vision Firm PK-PTEG-295159-CS-CQS / T 3. Public Investment Facilit Consultant Qualifi Under Implement opographic & Utilities Survey IDA / 59820 Post Open - National 100,000.00 0.00 2022-05-20 2022-05-30 2022-06-04 2022-07-03 2022-07-17 2022-08-14 2023-02-10 y cation Selection ation - IDAP Hiran Minar PK-PTEG-295158-CS-QCBS / Services for Preparation of As 3. Public Investment Facilit Consultant Qualifi Pending Impleme -Built Drawings & Scan-Base IDA / 59820 Post Open - National 175,000.00 0.00 2022-06-26 2022-07-17 2022-08-14 2022-08-28 2022-09-11 2023-03-10 y cation Selection ntation d 3D Models - IDAP Hiran Minar, Rohtas Fort & Ta xila INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-PTEG-32377-CS-INDV / So 4. Project Management, M Individual Consult cial Gender Specialist IDA / 59820 Post Open 189,450.00 26,773.76 Signed 2017-10-17 2017-08-01 2017-12-05 2018-01-02 2017-12-26 2018-01-01 2018-01-30 2018-02-01 2018-12-20 onitoring and Evaluation ant Selection Estimated amount for 5 year s PK-PTEG-32381-CS-INDV / E 4. Project Management, M Individual Consult nvironmental Specialist IDA / 59820 Post Open 189,450.00 24,361.53 Signed 2017-10-17 2017-07-17 2017-12-05 2017-12-26 2017-12-11 2018-01-30 2018-01-11 2019-01-10 onitoring and Evaluation ant Selection Estimated amount for 5 year s PK-PTEG-32410-CS-INDV / C 4. Project Management, M Individual Consult oordinator DC Bahawalpur IDA / 59820 Post Open 85,714.00 0.00 Canceled 2017-11-06 2018-09-18 2017-12-25 2018-01-15 2018-02-19 2019-01-30 onitoring and Evaluation ant Selection Estimated cost for 5 years PK-PTEG-32411-CS-INDV / C 4. Project Management, M Individual Consult oordinator DC Rajanpur IDA / 59820 Post Open 85,714.00 0.00 Canceled 2017-11-06 2018-09-18 2017-12-25 2018-01-15 2018-02-19 2019-01-30 onitoring and Evaluation ant Selection Estimated cost for 5 years PK-PTEG-40044-CS-INDV / R 4. Project Management, M Individual Consult IDA / 59820 Post Open 85,714.00 5,361.93 Signed 2017-12-18 2017-10-02 2018-02-05 2017-10-27 2018-02-26 2017-11-27 2018-04-02 2017-10-27 2018-09-28 esearch Associate onitoring and Evaluation ant Selection PK-PTEG-40046-CS-INDV / R 4. Project Management, M Individual Consult esearch Associate IDA / 59820 Post Open 85,714.00 5,361.93 Signed 2017-12-18 2017-12-04 2018-02-05 2018-01-03 2018-02-26 2018-01-02 2018-04-02 2018-01-08 2019-04-30 onitoring and Evaluation ant Selection Estimated cost for 5 years PK-PTEG-32376-CS-INDV / Fi 4. Project Management, M Individual Consult nancial Management Speciali IDA / 59820 Post Open 189,450.00 21,440.76 Signed 2017-10-17 2017-12-05 2017-09-11 2017-12-26 2017-09-13 2018-01-30 2017-09-26 2018-10-10 onitoring and Evaluation ant Selection st Estimated amount for 5 year s PK-PTEG-32398-CS-INDV / M 4. Project Management, M Individual Consult & E Specialist IDA / 59820 Post Open 225,000.00 29,233.84 Signed 2017-10-17 2017-07-01 2017-12-05 2017-09-11 2017-12-26 2017-09-25 2018-01-30 2017-09-26 2018-10-01 onitoring and Evaluation ant Selection Estimated cost for 5 years PK-PTEG-32389-CS-INDV / Pr 4. Project Management, M Individual Consult oject Director IDA / 59820 Prior Open 600,000.00 0.00 Canceled 2017-10-17 2018-08-16 2017-12-05 2017-12-26 2018-02-19 2019-02-19 onitoring and Evaluation ant Selection Estimated amount for 5 year s PK-PTEG-32391-CS-INDV / D 4. Project Management, M Individual Consult eputy Project Director IDA / 59820 Prior Open 370,000.00 0.00 Canceled 2017-10-17 2017-12-05 2017-12-26 2018-01-30 2018-10-25 onitoring and Evaluation ant Selection Estimated cost for 5 years PK-PTEG-40047-CS-INDV / R 4. Project Management, M Individual Consult esearch Associate - Account/ IDA / 59820 Post Open 85,714.00 14,616.92 Signed 2017-12-18 2017-09-11 2018-01-21 2017-12-08 2018-01-28 2017-12-11 2018-02-19 2017-12-12 2019-01-02 onitoring and Evaluation ant Selection Admin Estimated cost for 5 years PK-PTEG-68956-CS-INDV / Pu 4. Project Management, M Individual Consult IDA / 59820 Post Open 47,000.00 0.00 Canceled 2018-07-16 2018-09-03 2018-09-24 2018-10-29 2019-04-27 blic Sector Development Spe onitoring and Evaluation ant Selection cialist PK-PTEG-73991-CS-INDV / Pr 4. Project Management, M Individual Consult IDA / 59820 Post Open 47,000.00 17,457.63 Signed 2018-08-16 2019-01-14 2018-10-04 2019-09-20 2018-10-25 2019-09-24 2018-11-29 2019-09-24 2019-05-28 ivate Sector Development Sp onitoring and Evaluation ant Selection ecialist PK-PTEG-93482-CS-INDV / To 4. Project Management, M Individual Consult urism Expert IDA / 59820 Post Open 40,000.00 25,119.61 Signed 2019-01-11 2019-09-30 2019-03-01 2020-02-27 2019-03-22 2019-04-26 2020-04-08 2019-10-23 onitoring and Evaluation ant Selection (One year estimated cost) PK-PTEG-103221-CS-INDV / 4. Project Management, M Individual Consult Monitoring & Evaluation Spec IDA / 59820 Post Open 150,000.00 21,524.65 Signed 2019-02-27 2019-05-04 2019-04-17 2019-11-20 2019-05-08 2019-06-12 2019-11-25 2022-06-30 onitoring and Evaluation ant Selection ialist 3-Years and 4 Months PK-PTEG-103232-CS-INDV / P 4. Project Management, M Individual Consult rocurement & Contract Admi IDA / 59820 Post Open 16,000.00 0.00 Canceled 2019-02-27 2019-04-17 2019-05-08 2019-06-12 2020-04-30 onitoring and Evaluation ant Selection nistration Support 1-Year PK-PTEG-32401-CS-INDV / C 4. Project Management, M Individual Consult oordinator DC Rawalpindi IDA / 59820 Post Open 85,714.00 0.00 Canceled 2017-11-06 2018-09-18 2017-12-25 2018-01-15 2018-02-19 2019-01-30 onitoring and Evaluation ant Selection Estimated amount for 5 year s Page 4 PK-PTEG-32405-CS-INDV / C 4. Project Management, M Individual Consult oordinator DC Gujranwala IDA / 59820 Post Open 85,714.00 0.00 Canceled 2017-11-06 2018-09-18 2017-12-25 2018-01-15 2018-02-19 2019-01-30 onitoring and Evaluation ant Selection Estimated amount for 5 year s PK-PTEG-32407-CS-INDV / C 4. Project Management, M Individual Consult oordinator DC Sheikhupura IDA / 59820 Post Open 85,714.00 0.00 Canceled 2017-11-06 2018-09-18 2017-12-25 2018-01-15 2018-02-19 2019-01-30 onitoring and Evaluation ant Selection Estimated cost for 5 years PK-PTEG-136467-CS-INDV / 4. Project Management, M Individual Consult IDA / 59820 Post Open 170,000.00 0.00 Canceled 2019-10-02 2019-10-03 2019-10-28 2019-11-04 2019-11-18 2022-11-16 Hiring of Sr. Procurement Sp onitoring and Evaluation ant Selection ecialist PK-PTEG-136466-CS-INDV / 4. Project Management, M Individual Consult Pending Impleme IDA / 59820 Post Open 4,260.00 0.00 2019-10-03 2019-10-12 2019-10-14 2019-10-19 2020-02-16 Hiring of Graphic Designer onitoring and Evaluation ant Selection ntation PK-PTEG-138460-CS-INDV / 4. Project Management, M Individual Consult Hiring of Monitoring & Evalua IDA / 59820 Post Open 76,600.00 0.00 Canceled 2019-10-03 2019-10-29 2019-11-05 2019-11-13 2022-10-31 onitoring and Evaluation ant Selection tion (M&E) Specialist PK-PTEG-139666-CS-INDV / 4. Project Management, M Individual Consult IDA / 59820 Post Open 170,000.00 0.00 Canceled 2019-10-14 2019-11-16 2019-11-26 2019-12-10 2023-10-31 Hiring of Sr. Communication onitoring and Evaluation ant Selection Specialist PK-PTEG-139667-CS-INDV / 4. Project Management, M Individual Consult IDA / 59820 Post Open 87,500.00 8,612.44 Signed 2019-10-14 2019-12-02 2019-11-09 2020-01-22 2019-11-16 2020-01-23 2019-11-30 2020-01-23 2023-10-30 Hiring of Research Associate onitoring and Evaluation ant Selection PK-PTEG-103217-CS-INDV / 4. Project Management, M Individual Consult Senior Communication Speci IDA / 59820 Prior Open 168,000.00 0.00 Canceled 2019-02-27 2019-03-07 2019-04-17 2019-05-08 2019-06-12 2022-06-30 onitoring and Evaluation ant Selection alist 3-Years and 4 Months PK-PTEG-145106-CS-INDV / P 4. Project Management, M Individual Consult IDA / 59820 Post Limited 150,000.00 26,016.25 Signed 2019-11-11 2019-11-08 2019-11-12 2019-11-08 2019-11-13 2019-11-19 2019-11-14 2019-11-19 2022-09-14 roject Manager onitoring and Evaluation ant Selection PK-PTEG-145603-CS-INDV / P 4. Project Management, M Individual Consult rocurement and Contract Ad IDA / 59820 Post Limited 12,000.00 8,863.64 Signed 2019-11-14 2019-10-15 2019-11-15 2021-02-24 2019-11-15 2021-03-22 2019-11-15 2021-03-22 2020-11-14 onitoring and Evaluation ant Selection ministration Support Assistan t PK-PTEG-145698-CS-INDV / 4. Project Management, M Individual Consult IDA / 59820 Post Limited 12,000.00 0.00 Canceled 2019-11-14 2019-11-15 2019-11-15 2019-11-15 2020-02-16 Short Term Media Advisor for onitoring and Evaluation ant Selection YASAT PK-PTEG-32372-CS-INDV / Se 4. Project Management, M Individual Consult nior Procurement Specialist IDA / 59820 Prior Open 255,000.00 0.00 Canceled 2017-10-17 2017-12-05 2017-12-26 2018-01-30 2018-10-08 onitoring and Evaluation ant Selection Estimated amount for 5 year s PK-PTEG-103202-CS-INDV / 4. Project Management, M Individual Consult Senior Procurement Specialis IDA / 59820 Prior Open 170,000.00 0.00 Canceled 2019-02-27 2019-02-28 2019-04-17 2019-05-08 2019-06-12 2022-06-30 onitoring and Evaluation ant Selection t-3 Years & 4-Months PK-PTEG-145723-CS-INDV / 1. Policy, Institutions and Individual Consult Pending Impleme Short Term Media Consultant IDA / 59820 Governance for Tourism Dev Post Limited 12,000.00 0.00 2019-11-14 2019-11-15 2019-11-15 2019-11-15 2019-11-24 ant Selection ntation for YASA&T. Demand Driven elopment PK-PTEG-151717-CS-INDV / Estimated cost for Project Off icer -1 for 3 years 4. Project Management, M Individual Consult IDA / 59820 Post Limited 45,000.00 10,762.33 Signed 2019-12-24 2019-12-02 2019-12-29 2020-01-02 2019-12-30 2020-01-03 2020-01-06 2021-01-02 We will use limited competiti onitoring and Evaluation ant Selection on as we will select a candid ate from existing pool of can didates. PK-PTEG-151720-CS-INDV / P roject Officer -2 . Estimated cost for 3 years USD 45,000. 4. Project Management, M Individual Consult IDA / 59820 Post Limited 45,000.00 12,197.30 Signed 2019-12-24 2019-12-02 2019-12-29 2020-01-06 2020-01-03 2020-01-10 2020-01-06 2021-01-09 We will use limited competiti onitoring and Evaluation ant Selection on since we have existing po ol of consultants to select fro m. PK-PTEG-32404-CS-INDV / C 4. Project Management, M Individual Consult oordinator DC Chakwal IDA / 59820 Post Open 85,714.00 0.00 Canceled 2017-11-06 2018-09-18 2017-12-25 2018-01-15 2018-02-19 2019-01-30 onitoring and Evaluation ant Selection Estimated cost for 5 years PK-PTEG-32385-CS-INDV / Se 4. Project Management, M Individual Consult nior Communication Specialis IDA / 59820 Prior Open 252,000.00 0.00 Canceled 2017-10-17 2018-08-31 2017-12-05 2017-12-26 2018-01-30 2019-01-30 onitoring and Evaluation ant Selection t Estimated amount for 5 year s PK-PTEG-153682-CS-INDV / 4. Project Management, M Individual Consult Hiring of Procurement Specia IDA / 59820 Post Limited 170,000.00 22,959.63 Signed 2020-01-14 2020-01-01 2020-01-17 2020-01-10 2020-01-18 2020-02-10 2020-01-20 2020-02-10 2023-01-19 onitoring and Evaluation ant Selection list PTEGP- cost for 3 years PK-PTEG-115815-CS-INDV / 4. Project Management, M Individual Consult IDA / 59820 Post Open 168,000.00 0.00 Canceled 2019-05-21 2019-07-09 2019-07-30 2019-09-03 2022-06-30 Senior Communication Speci onitoring and Evaluation ant Selection alist PK-PTEG-32387-CS-INDV / In 4. Project Management, M Individual Consult frastructure Development Sp IDA / 59820 Post Open 189,450.00 0.00 Canceled 2017-10-17 2019-01-21 2017-12-05 2017-12-26 2018-01-30 2019-03-29 onitoring and Evaluation ant Selection ecialist Estimated amount for 5 year s PK-PTEG-162559-CS-INDV / 4. Project Management, M Individual Consult IDA / 59820 Post Limited 100,000.00 18,126.90 Signed 2020-03-09 2020-03-09 2020-03-14 2020-03-06 2020-04-04 2020-03-16 2020-05-09 2020-03-20 2022-04-29 Civil Engineer onitoring and Evaluation ant Selection PK-PTEG-163247-CS-INDV / 4. Project Management, M Individual Consult IDA / 59820 Post Limited 15,000.00 11,229.64 Signed 2020-03-10 2020-03-24 2020-03-15 2020-10-03 2020-04-05 2020-12-11 2020-05-10 2020-12-17 2021-05-10 Assistant Civil Engineer onitoring and Evaluation ant Selection PK-PTEG-190459-CS-INDV / 4. Project Management, M Individual Consult IDA / 59820 Post Open 75,000.00 14,972.86 Signed 2020-09-02 2020-09-01 2020-10-21 2020-11-12 2020-11-11 2020-12-03 2020-12-16 2020-12-07 2021-06-14 Social Safeguard & Gender S onitoring and Evaluation ant Selection pecialist PK-PTEG-196847-CS-INDV / 3. Public Investment Facilit Individual Consult IDA / 59820 Post Limited 20,000.00 12,496.10 Signed 2020-10-05 2020-10-09 2020-10-10 2020-10-16 2020-10-24 2020-11-15 2020-11-17 2020-11-16 2022-11-17 Content Writer - Informative y ant Selection Signboards PK-PTEG-197173-CS-INDV / 3. Public Investment Facilit Individual Consult Pending Impleme IDA / 59820 Post Limited 20,000.00 0.00 2020-10-09 2020-10-14 2020-11-04 2020-12-09 2021-12-04 Conservation Architect - PCR y ant Selection ntation MP PK-PTEG-228307-CS-INDV / P 4. Project Management, M Individual Consult IDA / 59820 Post Open 20,000.00 12,954.55 Signed 2021-04-26 2021-04-26 2021-05-29 2021-06-04 2021-06-05 2021-06-04 2021-06-19 2021-07-07 2022-06-14 roject Officer - 1 onitoring and Evaluation ant Selection PK-PTEG-228310-CS-INDV / 4. Project Management, M Individual Consult Under Implement IDA / 59820 Post Open 30,000.00 0.00 2021-04-26 2021-09-23 2021-05-29 2021-06-12 2021-06-26 2022-06-21 Architect onitoring and Evaluation ant Selection ation PK-PTEG-232086-CS-INDV / L 4. Project Management, M Individual Consult Under Implement egal Consultant for Tourism IDA / 59820 Post Open 9,500.00 0.00 2021-05-03 2021-04-30 2021-06-05 2021-06-12 2021-06-26 2021-09-24 onitoring and Evaluation ant Selection ation Department Page 5 PK-PTEG-243329-CS-INDV / 4. Project Management, M Individual Consult Under Implement IDA / 59820 Post Open 45,000.00 0.00 2021-07-16 2021-07-07 2021-08-18 2021-09-01 2021-09-18 2023-04-30 Environment Specialist onitoring and Evaluation ant Selection ation PK-PTEG-256619-CS-INDV / 4. Project Management, M Individual Consult Under Implement IDA / 59820 Post Limited 23,500.00 0.00 2021-11-21 2022-03-25 2021-11-26 2021-12-03 2021-12-17 2022-06-15 Consultant for Integrated Tou onitoring and Evaluation ant Selection ation rism Plan PK-PTEG-264216-CS-INDV / 4. Project Management, M Individual Consult Under Implement IDA / 59820 Post Open 20,000.00 0.00 2021-11-28 2021-12-14 2021-12-24 2021-12-31 2022-01-14 2023-01-09 Research Associate - I onitoring and Evaluation ant Selection ation PK-PTEG-264217-CS-INDV / 4. Project Management, M Individual Consult Under Implement IDA / 59820 Post Open 20,000.00 0.00 2021-11-28 2021-12-14 2021-12-24 2021-12-31 2022-01-14 2023-01-09 Research Associate - II onitoring and Evaluation ant Selection ation PK-PTEG-267380-CS-INDV / P 4. Project Management, M Individual Consult Under Implement IDA / 59820 Post Open 100,000.00 0.00 2021-12-17 2021-12-16 2022-01-26 2022-02-09 2022-02-23 2023-04-30 roject Director onitoring and Evaluation ant Selection ation PK-PTEG-274905-CS-INDV / 4. Project Management, M Individual Consult Under Implement Coordination Officer for Touri IDA / 59820 Post Open 21,000.00 0.00 2022-01-31 2022-01-28 2022-02-26 2022-03-05 2022-03-19 2023-03-14 onitoring and Evaluation ant Selection ation sm Department PK-PTEG-274909-CS-INDV / 4. Project Management, M Individual Consult Under Implement IDA / 59820 Post Open 14,000.00 0.00 2022-01-31 2022-01-28 2022-02-26 2022-03-05 2022-03-19 2023-03-14 Data Analyst for Tourism Dep onitoring and Evaluation ant Selection ation artment PK-PTEG-274911-CS-INDV / 4. Project Management, M Individual Consult Under Implement IDA / 59820 Post Open 14,000.00 0.00 2022-01-31 2022-01-28 2022-02-26 2022-03-05 2022-03-19 2023-03-14 Analyst for Tourism Departm onitoring and Evaluation ant Selection ation ent PK-PTEG-279726-CS-INDV / 4. Project Management, M Individual Consult Under Implement IDA / 59820 Post Limited 28,000.00 0.00 2022-02-22 2022-02-18 2022-02-27 2022-03-13 2022-03-27 2023-03-22 Environment Specialist onitoring and Evaluation ant Selection ation PK-PTEG-279729-CS-INDV / L 4. Project Management, M Individual Consult Under Implement IDA / 59820 Post Limited 20,000.00 0.00 2022-02-21 2022-02-18 2022-02-24 2022-03-03 2022-03-17 2023-03-12 iaison Officer onitoring and Evaluation ant Selection ation PK-PTEG-279736-CS-INDV / 4. Project Management, M Individual Consult Under Implement IDA / 59820 Post Open 21,000.00 0.00 2022-02-21 2022-02-18 2022-03-19 2022-04-02 2022-04-16 2023-04-11 Coordination Officer onitoring and Evaluation ant Selection ation PK-PTEG-286751-CS-INDV / 1. Policy, Institutions and Individual Consult Under Implement Economist - Assessment of e IDA / 59820 Governance for Tourism Dev Post Open 16,000.00 0.00 2022-04-25 2022-04-21 2022-05-21 2022-05-28 2022-06-11 2022-09-09 ant Selection ation conomic impact of the PTEGP elopment PK-PTEG-293040-CS-INDV / 3. Public Investment Facilit Individual Consult Pending Impleme IDA / 59820 Post Open 26,000.00 0.00 2022-05-09 2022-06-04 2022-06-11 2022-06-25 2023-06-20 Conservation Specialist y ant Selection ntation Page 6