The World Bank Implementation Status & Results Report Access to Distributed Electricity and Lighting in Ethiopia (ADELE) (P171742) Access to Distributed Electricity and Lighting in Ethiopia (ADELE) (P171742) EASTERN AND SOUTHERN AFRICA | Ethiopia | Energy & Extractives Global Practice | IBRD/IDA | Investment Project Financing | FY 2021 | Seq No: 3 | ARCHIVED on 26-Jun-2022 | ISR51539 | Implementing Agencies: Development Bank of Ethiopia (DBE), Ethiopia Electric Utility, Federal Democratic Republic of Ethiopia, Ministry of Water and Energy Key Dates Key Project Dates Bank Approval Date: 29-Mar-2021 Effectiveness Date: 20-Sep-2021 Planned Mid Term Review Date: -- Actual Mid-Term Review Date: Original Closing Date: 31-Mar-2027 Revised Closing Date: 31-Mar-2027 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) The development objective is to increase access to reliable electricity for households, social institutions, and enterprises in Ethiopia. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Components Table Name 1. Network strengthening for improved reliability of supply in urban areas:(Cost $100.00 M) 2. Solar-hybrid mini grids for rural economic development:(Cost $270.00 M) 3. Solar home systems for households (HHs), small-holder farmers and small businesses:(Cost $50.50 M) 4. Standalone solar systems for health and education facilities:(Cost $55.00 M) 5. Capacity building, technical assistance and implementation support:(Cost $24.50 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Satisfactory Overall Implementation Progress (IP) Satisfactory Satisfactory Overall Risk Rating Substantial Substantial Implementation Status and Key Decisions The Access to Distributed Electricity and Lighting in Ethiopia (ADELE) project was approved by the World Bank Board of Directors on March 29, 2021 and reached effectiveness on September 20, 2021. The implementing entities (Ministry of Water and Energy, Ethiopian Electric Utility, and Development Bank of Ethiopia) are making good progress in setting up the project implementation teams and are currently working towards meeting disbursement conditions for components supporting mini-grids, standalone solar systems for households and small businesses, and institutional electrification.  6/26/2022 Page 1 of 7 The World Bank Implementation Status & Results Report Access to Distributed Electricity and Lighting in Ethiopia (ADELE) (P171742) Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance High High High Macroeconomic Substantial Substantial Substantial Sector Strategies and Policies Moderate Moderate Moderate Technical Design of Project or Program Substantial Substantial Substantial Institutional Capacity for Implementation and Substantial Substantial Substantial Sustainability Fiduciary High High High Environment and Social Substantial Substantial Substantial Stakeholders Moderate Moderate Moderate Other Moderate Moderate Moderate Overall Substantial Substantial Substantial Results PDO Indicators by Objectives / Outcomes To increase access to reliable electricity for households, institutions, and enterprises in Ethiopia IN01144360 ►People provided with new or improved electricity service (Number, Corporate) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 4,950,000.00 Date 01-Mar-2021 17-Dec-2021 21-Jun-2022 01-Mar-2027 IN01144581 ►Enterprises provided with new or improved electricity service through mini grid and off-grid electricity solutions (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 131,500.00 Date 01-Mar-2021 17-Dec-2021 21-Jun-2022 01-Mar-2027 Number of enterprises (farmers, business, commercial, industrial users) provided with access to electricity Comments: through mini grid and off-grid electricity solutions. IN01144582 6/26/2022 Page 2 of 7 The World Bank Implementation Status & Results Report Access to Distributed Electricity and Lighting in Ethiopia (ADELE) (P171742) ►Institutions provided with new or improved electricity service through mini grid and off-grid electricity solutions (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 1,900.00 Date 01-Mar-2021 17-Dec-2021 21-Jun-2022 01-Mar-2027 Number of institutional users (schools, health centers, government buildings) provided with new or Comments: improved access to electricity through standalone systems under the project. IN01144583 ►Interruption frequency per 100 km MV network length per year in Addis Ababa (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 882.00 882.00 882.00 653.00 Date 01-Mar-2021 17-Dec-2021 21-Jun-2022 01-Mar-2027 Number of interruptions per 100 km of MV network length per year in Addis Ababa. It reflects interruptions/ power outages (more than 5 minutes) that are often caused by faults in distribution network. It is the ratio of total number of interruptions to total length of distribution line. Expectation is reduction of Comments: 26 percent. Formula: {(INT of current period)-(INT of corresponding period in previous year)} /(INT of corresponding period in previous year) *100 Where, INT= (Total number of interruptions / Total length of distribution network)*100. Intermediate Results Indicators by Components Network strengthening for improved reliability of supply in urban areas IN01144593 ►Average reduction on interruption frequency per 100 km MV lines across ten towns (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 45.00 Date 01-Mar-2021 17-Dec-2021 21-Jun-2022 01-Mar-2027 Calculated based on the number of interruptions per 100 km of MV network length per year. It reflects interruptions/ power outages (more than 5 minutes) that are often caused by faults in distribution network. It is the ratio of total number of interruptions to total length of distribution line. Expectation is reduction of Comments: 45 percent. Formula: {(INT of current period)-(INT of corresponding period in previous year)} /(INT of corresponding period in previous year) *100 Where, INT= (Total number of interruptions / Total length of distribution network)*100 Solar-hybrid mini grids for rural economic development IN01144585 ►Households provided with access to electricity services through mini-grids (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 240,000.00 Date 01-Mar-2021 17-Dec-2021 21-Jun-2022 01-Mar-2027 6/26/2022 Page 3 of 7 The World Bank Implementation Status & Results Report Access to Distributed Electricity and Lighting in Ethiopia (ADELE) (P171742) Comments: Number of households provided with access to electricity services through mini-grids under the project. IN01144592 ►Renewable energy generation capacity of mini-grids supported under the project (Megawatt, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 35.00 Date 01-Mar-2021 17-Dec-2021 21-Jun-2022 01-Mar-2027 Comments: Renewable energy generation capacity (Megawatt) of mini-grids supported under the project. IN01144595 ►Percentage of women among total number of people employed by mini grid companies (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 21.00 21.00 21.00 30.00 Date 01-Mar-2021 17-Dec-2021 21-Jun-2022 01-Mar-2027 Comments: Percentage of female employees among total number of people employed by mini grid companies. IN01144596 ►Volume of private capital mobilized to support delivery of new or improved electricity service through mini grids (Amount(USD), Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 50,000,000.00 Date 01-Mar-2021 17-Dec-2021 21-Jun-2022 01-Mar-2027 Amount of private capital in USD mobilized through the project to support delivery of new or improved Comments: electricity service through mini grids. IN01144597 ►Number of mini grid sites that have adopted a strategy on closing gender gaps in productive uses of energy (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 50.00 Date 01-Mar-2021 17-Dec-2021 21-Jun-2022 01-Mar-2027 Number of mini grid sites that have adopted a strategy on closing gender gaps in productive uses of Comments: energy. Solar home systems for households (HHs), small-holder farmers and small businesses IN01144584 ►Households provided with off-grid electricity access (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 750,000.00 6/26/2022 Page 4 of 7 The World Bank Implementation Status & Results Report Access to Distributed Electricity and Lighting in Ethiopia (ADELE) (P171742) Date 01-Mar-2021 17-Dec-2021 21-Jun-2022 01-Mar-2027 Comments: Number of households provided with electricity connections by off-grid systems. IN01144590 Off-grid systems used in support of small businesses (out of which women-owned 20%) (Number, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 120,000.00 IN01144591 ►Percentage of women among total number of people employed by off-grid solar companies (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 20.00 20.00 20.00 28.00 Date 01-Mar-2021 17-Dec-2021 21-Jun-2022 01-Mar-2027 Comments: Percentage of female employees among total number of people employed by off-grid solar companies. IN01144594 ►Volume of private capital mobilized to support delivery of new or improved electricity service through off-grid solar systems (Amount(USD), Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 50,000,000.00 Date 01-Mar-2021 17-Dec-2021 21-Jun-2022 01-Mar-2027 Amount of private capital in USD mobilized through the project to support delivery of new or improved Comments: electricity service through off-grid solar systems. Standalone solar systems for education and health facilities IN01144586 ►Education and health facilities provided with electricity services through standalone systems (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 1,400.00 Date 01-Mar-2021 17-Dec-2021 21-Jun-2022 01-Mar-2027 Number of schools and health facilities provided with electricity services through standalone systems Comments: under the project. IN01144588 ►Adoption of skills development and job creation roadmap for women for the standalone solar system installation and maintenance for health and education facilities (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No No No Yes Date 01-Mar-2021 17-Dec-2021 21-Jun-2022 01-Mar-2026 Adoption of skills development and job creation roadmap for women for the standalone solar system Comments: installation and maintenance for health and education facilities. 6/26/2022 Page 5 of 7 The World Bank Implementation Status & Results Report Access to Distributed Electricity and Lighting in Ethiopia (ADELE) (P171742) Capacity building, technical assistance and implementation support IN01144587 ►Delivery of ADELE consumer awareness and citizen engagement strategy by MoWIE (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No No No Yes Date 01-Mar-2021 17-Dec-2021 21-Jun-2022 01-Mar-2022 MoWIE will design a and adopt a consumer awareness and citizen engagement strategy for the ADELE Comments: project which will outline minimum standards and requirements for various entities engaged in the service delivery. IN01144589 ►Maintenance of an operational grievance redress mechanism (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No No No Yes Date 01-Mar-2021 17-Dec-2021 21-Jun-2022 01-Mar-2027 Comments: Maintenance of an operational and well-functioning grievance redress mechanism. Performance-Based Conditions Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P171742 IDA-68570 Effective USD 500.00 500.00 0.00 0.00 486.90 0% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P171742 IDA-68570 Effective 29-Mar-2021 23-Apr-2021 20-Sep-2021 31-Mar-2027 31-Mar-2027 Cumulative Disbursements 6/26/2022 Page 6 of 7 The World Bank Implementation Status & Results Report Access to Distributed Electricity and Lighting in Ethiopia (ADELE) (P171742) Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 6/26/2022 Page 7 of 7