PHILIPPINE RURAL DEVELOPMENT PROJECT LN 8421-PH ORIGINAL LOAN Procurement Plan As of June 2018 I. General 1. Bank’s approval Date of the Procurement Plan : September 9, 2014 2. Date of General Procurement Notice : September 25, 2012 3. Period covered by this procurement plan : July 2018 – June 2019 II. Goods and Works and non-consulting services 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Method Threshold Prior Review No. Procurement Method US$ Threshold US$ International Competitive 1. 3M and above All contracts Bidding (ICB) (Goods) National Competitive Bidding 2. less than 3M 2M and above (NCB) (Goods) packages 3. Shopping (Goods) less than 0.2M None 4. ICB (Works) packages 15M and above All contracts 5. NCB (Works) packages less than 15M 10M and above 6. Shopping (Works) less than 0.2M None Subject to justification in accordance with para. 3.7 of 5. Direct Contracting (Goods) 2M and above Procurement Guidelines at the Procurement Plan stage 6. Commercial Practice less than 0.1M None 7. Community Participation less than 0.05M None 2. Reference to Project Operational/Procurement Manual including Community Participation: Original version dated : May 2014 To be updated by : July 2018 (Revised Operations Manual submitted September 4, 2017) 3. Summary of the Procurement Packages (with international competition, direct contracting, requiring Bank’s prior review): PHILIPPINE RURAL DEVELOPMENT PROJECT Summary of the Procurement Packages LN 8421 PH Procurement Plan Updated June 2018 (with International Competition, Direct Contracting requiring Bank’s prior review) 1 2 3 4 5 6 7 8 9 10 Domest Estimated ic Expected Procurin Procurem Cost Funding Prefere Review Bid Comment Ref. No. Description g ent US$1= Source nce by Bank Opening s Agency Method Php 50) (yes/no Date ) No subprojects for Bank’s prior review III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines on Selection and Employment of Consultants: Prior Review No. Selection Method Method Threshold US$ Threshold US$ 1. Competitive Methods 0.3M & above (may be used for 1m and above (QCBS, QBS, FBS) also less than 0.3M) (Firms) 2. Competitive Method less than 0.3M None CQS (Firms) 3. Individuals Competitive regardless of amount 0.3M and above 2. Single Source (Firms & on exceptional basis subject to Firms: 1M and Individuals) justification in accordance with above; paras. 3.9 and 5.4 respectively of Individuals 0.3M and Consultant Guidelines at the above. Procurement Plan stage 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $500,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Summary of the Consultancy Assignments/Packages (using international competition, single/sole source selection, requiring Bank’s prior review): PHILIPPINE RURAL DEVELOPMENT PROJECT Summary of the Procurement Packages (with International Competition) 1 2 3 4 5 6 7 8 Ref Description of Procurin Expected Bid Estimated Cost (USD Funding Selection Comm . Contract g Opening million) Source Method ents No. Package Agency Date Various PRDP Technical Consultant and Staff (provided with No Objection December 22, 2017) US$1,042,75 Single Source NPCO ( Php53.178 LP/GoP Selection million) US$1,042,75 Single Source Luzon A ( Php59.152 LP/GoP Selection million) LN 8421 PH Procurement Plan Updated June 2018 US$1,042,75 Single Source Luzon B ( Php48.614 LP/GoP Selection million) US$1,042,75 Single Source Visaya ( Php29.612 LP/GoP Selection million) US$1,042,75 Single Source Mindanao ( Php million) LP/GoP Selection Prepared by: Reviewed by: ENGR. ROMEO L. MALONG ENGR. CHRISTOPHER V. MORALES Alternate Procurement Unit Head Procurement Unit Head LN 8421 PH Procurement Plan Updated June 2018 PROCUREMENT Philippines : Philippine Rural Development Project PLAN General Information Country: Philippines 2019-03-11 Bank’s Approval Date of the Original Procurement Plan: 2022-07-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P132317 GPN Date: Project Name: Philippine Rural Development Project Loan / Credit No: IBRD / 88160, IBRD / 92710 Department of Agriculture-Philippine Rural Development Project PSO Luzon A Executing Agency(ies): WORKS Activity Reference No. Procurement Estimated Actual A Bid Evaluation Repo Loan / Credit Market Approa Procurement Pr Prequalificatio High SEA/SH Process Draft Pre-qualificatio Prequalification Eval Draft Bidding Docu Specific Procuremen Bidding Documents Proposal Submission Contract Compl / Description Component Review Type Method Document Ty Amount ( mount ( rt and Recommenda Signed Contract No. ch ocess n (Y/N) Risk Status n Documents uation Report ment / Justification t Notice / Invitation as Issued / Opening / Minutes etion pe US$) US$) tion for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planne d PRDP-IB-RCAR-BEN-013-L Pending I Component 2: Infrastructu Single Stage - Tw 2018-09-0 2018-09-0 2018-10-1 2018-12-3 2019-02-0 2019-08- AT-001-2016-AF / Construc IBRD / 88160 Post Request for Bids Open - National 207,000.00 0.00 mplement re Development o Envelope 1 6 8 1 4 03 tion of Slope Protection of ation Puguis PRDP-IB-RCAR-BEN-016-B Pending I Component 2: Infrastructu Request for Quo Single Stage - On 2018-09-0 2018-11-0 2019-04- OK-001-2018-AF / Constru IBRD / 88160 Post Open - National 90,784.31 0.00 mplement re Development tations e Envelope 6 1 30 ction of Salat-Surek Tramli ation ne PRDP-IB-RCAR-BEN-017-B Pending I Component 2: Infrastructu Request for Quo Single Stage - On 2018-09-0 2018-11-0 2019-04- OK-002-2018-AF / Constru IBRD / 88160 Post Open - National 93,137.25 0.00 mplement re Development tations e Envelope 6 1 30 ction of Wakal Tramline ation PRDP-IB-RCAR-IFU-015-BA Pending I Component 2: Infrastructu Single Stage - Tw 2,449,764. 2018-09-0 2018-09-0 2018-10-1 2018-12-3 2019-02-0 2019-08- N-006-2017-AF / Improve IBRD / 88160 Post Request for Bids Open - National 0.00 mplement re Development o Envelope 71 1 6 8 1 4 03 ment of Viewpoint-San Fer ation nando FMR PRDP-IB-RCAR-KAL-004-0 Pending I Component 2: Infrastructu Single Stage - Tw 4,523,529. 2018-09-0 2018-09-0 2018-10-1 2018-12-3 2019-02-0 2019-08- 00-000-2015-AF / Improve IBRD / 88160 Post Request for Bids Open - National 0.00 mplement re Development o Envelope 41 1 6 8 1 4 03 ment of Bado Dangwa-Guil ation ayon FMR PRDP-IB-RCAR-IFU-021-BA Pending I Component 2: Infrastructu Single Stage - Tw 4,823,549. 2018-11-0 2018-11-0 2018-12-1 2019-03-0 2019-04-0 2019-10- N-011-2018-AF / Construct IBRD / 88160 Post Request for Bids Open - National 0.00 mplement re Development o Envelope 02 1 6 8 2 6 03 ion of Anaba-Ducligan-Ban ation ao FMR with Bridge PRDP-IB-RCAR-IFU-020-00 Pending I Component 2: Infrastructu Single Stage - Tw 2,754,823. 2018-11-0 2018-11-0 2018-12-1 2019-03-0 2019-04-0 2019-10- 0-000-2018-AF / Improvem IBRD / 88160 Post Request for Bids Open - National 0.00 mplement re Development o Envelope 53 1 6 8 2 6 03 ent of Junction Alimit Nattu ation m FMR Improvement PRDP-IB-RCAR-ABR-009-0 Pending I Component 2: Infrastructu Single Stage - Tw 2018-11-0 2018-11-0 2018-12-1 2019-03-0 2019-04-0 2019-10- 00-000-2016-AF / Construc IBRD / 88160 Post Request for Bids Open - National 194,156.86 0.00 mplement re Development o Envelope 1 6 8 2 6 03 tion of Warehouse of Lapa ation z, abra PRDP-IB-RCAR-APA-001-0 Pending I Component 2: Infrastructu Single Stage - Tw 3,884,509. 2018-11-0 2018-11-0 2018-12-1 2019-03-0 2019-04-0 2019-10- 00-000-2015-AF / Improve IBRD / 88160 Post Request for Bids Open - National 0.00 mplement re Development o Envelope 80 1 6 8 2 6 03 ment of Sta. Maria-Mallig- ation Upper Atok FMR PRDP-IB-RCAR-ABR-010-0 Pending I Component 2: Infrastructu Single Stage - Tw 2019-09-0 2019-09-0 2019-10-1 2019-12-3 2020-02-0 2020-08- 00-000-2016-AF / Construc IBRD / 88160 Post Request for Bids Open - National 151,117.65 0.00 mplement re Development o Envelope 1 6 8 1 4 02 tion of Slope Stabilization ation at Tineg, Abra PRDP-IB-RCAR-IFU-004-00 Pending I Component 2: Infrastructu Single Stage - Tw 2019-09-0 2019-09-0 2019-10-1 2019-12-3 2020-02-0 2020-08- 0-000-2016-AF / Constructi IBRD / 88160 Post Request for Bids Open - National 118,274.51 0.00 mplement re Development o Envelope 1 6 8 1 4 02 on of Slope Protection of A ation sipulo, Ifugao PRDP-IB-RCAR-APA-002-0 Pending I Component 2: Infrastructu Single Stage - Tw 2,254,901. 2019-09-0 2019-09-0 2019-10-1 2019-12-3 2020-02-0 2020-08- 00-000-2015-AF / Improve IBRD / 88160 Post Request for Bids Open - National 0.00 mplement re Development o Envelope 96 1 6 8 1 4 02 ment of Cabatacan-San Jos ation e-San Mariano FMR PRDP-IB-R001-LAU-006-00 Pending I Component 2: Infrastructu Single Stage - Tw 1,403,686. 2018-11-0 2018-11-0 2018-12-1 2019-03-0 2019-04-0 2019-10- 0-000-2015-AF / Rehabilita IBRD / 88160 Post Request for Bids Open - National 0.00 mplement re Development o Envelope 27 1 6 8 2 6 03 tion of Parasapas FMR with ation Bridge PRDP-IB-R001-ILN-024-PA Pending I Component 2: Infrastructu Single Stage - Tw 2,480,588. 2019-09-0 2019-09-0 2019-10-1 2019-12-3 2020-02-0 2020-08- O-002-2017-AF / Rehabilit IBRD / 88160 Post Request for Bids Open - National 0.00 mplement re Development o Envelope 24 1 6 8 1 4 02 ation of Paoay Communal I ation rrigation System PRDP-IB-R001-ILS-007-TA Pending I Component 2: Infrastructu Single Stage - Tw 2,352,941. 2019-09-0 2019-09-0 2019-10-1 2019-12-3 2020-02-0 2020-08- G-001-2017-AF / Construct IBRD / 88160 Post Request for Bids Open - National 0.00 mplement re Development o Envelope 18 1 6 8 1 4 02 ion of Jardin-Sawat Bridge ation with Approaches PRDP-IB-R002-ISA-027-00 Pending I 0-000-2016-AF / Constructi Component 2: Infrastructu Single Stage - Tw 2018-09-0 2018-09-0 2018-10-1 2018-12-3 2019-02-0 2019-08- IBRD / 88160 Post Request for Bids Open - National 239,529.41 0.00 mplement on of Warehouse with Sola re Development o Envelope 1 6 8 1 4 03 ation r Dryer at Echague, Isabel a PRDP-IB-R002-ISA-021-00 Pending I 0-000-2016-AF / Constructi Component 2: Infrastructu Single Stage - Tw 2018-09-0 2018-09-0 2018-10-1 2018-12-3 2019-02-0 2019-08- IBRD / 88160 Post Request for Bids Open - National 240,509.80 0.00 mplement on of Warehouse with Sola re Development o Envelope 1 6 8 1 4 03 ation r Dryer at Gamu, Isabela PRDP-IB-R002-ISA-022-00 Pending I 0-000-2016-AF / Constructi Component 2: Infrastructu Single Stage - Tw 2018-09-0 2018-09-0 2018-10-1 2018-12-3 2019-02-0 2019-08- IBRD / 88160 Post Request for Bids Open - National 245,921.57 0.00 mplement on of Warehouse with Sola re Development o Envelope 1 6 8 1 4 03 ation r Dryer at Roxas, Isabela PRDP-IB-R002-ISA-028-00 Pending I Component 2: Infrastructu Single Stage - Tw 2018-09-0 2018-09-0 2018-10-1 2018-12-3 2019-02-0 2019-08- 0-000-2016-AF / Constructi IBRD / 88160 Post Request for Bids Open - National 246,509.80 0.00 mplement re Development o Envelope 1 6 8 1 4 03 on of Warehouse with Sola ation r Dryer at Mallig, Isabela PRDP-IB-R002-NUV-004-A Pending I Component 2: Infrastructu Single Stage - Tw 2,623,490. 2018-11-0 2018-11-0 2018-12-1 2019-03-0 2019-04-0 2019-10- MB-001-2018-AF / Rehabili IBRD / 88160 Post Request for Bids Open - National 0.00 mplement re Development o Envelope 20 1 6 8 2 6 03 tation of Tiblac-Dulli FMR ation PRDP-IB-R002-QUI-007-00 Pending I 0-000-2015-AF / Rehabilita Component 2: Infrastructu Single Stage - Tw 2,551,940. 2018-11-0 2018-11-0 2018-12-1 2019-03-0 2019-04-0 2019-10- IBRD / 88160 Post Request for Bids Open - National 0.00 mplement tion of National Road Junct re Development o Envelope 22 1 6 8 2 6 03 ation ion-Ricarte Sur-Magsaysay Farm to Market Road PRDP-IB-R002-QUI-008-00 Pending I Component 2: Infrastructu Single Stage - Tw 1,038,451. 2018-11-0 2018-11-0 2018-12-1 2019-03-0 2019-04-0 2019-10- 0-000-2015-AF / Rehabilita IBRD / 88160 Post Request for Bids Open - National 0.00 mplement re Development o Envelope 74 1 6 8 2 6 03 tion of Lusod-Sto Nińo Far ation m to Market Road PRDP-IB-R002-ISA-010-SA Pending I Component 2: Infrastructu Single Stage - Tw 2,966,215. 2019-09-0 2019-09-0 2019-10-1 2019-12-3 2020-02-0 2020-08- O-001-2015-AF / Rehabilit IBRD / 88160 Post Request for Bids Open - National 0.00 mplement re Development o Envelope 69 1 6 8 1 4 02 ation of Calaocan-Batal Fa ation rm to Market Road PRDP-IB-R002-ISA-011-SA Pending I Component 2: Infrastructu Single Stage - Tw 1,624,313. 2019-09-0 2019-09-0 2019-10-1 2019-12-3 2020-02-0 2020-08- O-002-2015-AF / Rehabilit IBRD / 88160 Post Request for Bids Open - National 0.00 mplement re Development o Envelope 73 1 6 8 1 4 02 ation of Baluarte-Sinili Far ation m to Market Road PRDP-IB-R002-ISA-031-00 Pending I Component 2: Infrastructu Single Stage - Tw 2019-09-0 2019-09-0 2019-10-1 2019-12-3 2020-02-0 2020-08- 0-000-2016-AF / Constructi IBRD / 88160 Post Request for Bids Open - National 786,235.29 0.00 mplement re Development o Envelope 1 6 8 1 4 02 on of Sinalugan Communal ation Pump Irrigation Project PRDP-IB-R002-ISA-029-00 Pending I Component 2: Infrastructu Single Stage - Tw 2019-09-0 2019-09-0 2019-10-1 2019-12-3 2020-02-0 2020-08- 0-000-2016-AF / Constructi IBRD / 88160 Post Request for Bids Open - National 796,078.43 0.00 mplement re Development o Envelope 1 6 8 1 4 02 on of Gangalan Communal ation Pump Irrigation Project PRDP-IB-R002-ISA-033-RA Pending I Component 2: Infrastructu Single Stage - Tw 2,489,372. 2019-09-0 2019-09-0 2019-10-1 2019-12-3 2020-02-0 2020-08- M-001-2017-AF / Rehabilit IBRD / 88160 Post Request for Bids Open - National 0.00 mplement re Development o Envelope 55 1 6 8 1 4 02 ation of Oscariz-Nagbacala ation n Farm to Market Road PRDP-IB-R003-NUE-021-P Pending I Component 2: Infrastructu Single Stage - Tw 3,763,091. 2019-01-0 2019-01-0 2019-02-1 2019-05-0 2019-06-0 2019-12- AL-001-2017-AF / Construc IBRD / 88160 Post Request for Bids Open - National 0.00 mplement re Development o Envelope 45 2 7 8 3 7 04 tion of Cold Storage ation PRDP-IB-R003-NUE-017-C Pending I AR-006-2016-AF / Improve Component 2: Infrastructu Single Stage - Tw 2018-11-0 2018-11-0 2018-12-1 2019-03-0 2019-04-0 2019-10- IBRD / 88160 Post Request for Bids Open - National 749,873.53 0.00 mplement ment of Poblacion Sur, La re Development o Envelope 1 6 8 2 6 03 ation Torre, Bantug and Maman dil Farm to Market Road PRDP-IB-R003-BUL-005-00 Pending I Component 2: Infrastructu Single Stage - Tw 2018-11-0 2018-11-0 2018-12-1 2019-03-0 2019-04-0 2019-10- 0-000-2015-AF / Improvem IBRD / 88160 Post Request for Bids Open - National 983,392.16 0.00 mplement re Development o Envelope 1 6 8 2 6 03 ent of Sumandig-Bubulong ation Malaki FMR PRDP-IB-R003-PAM-001-0 Pending I Component 2: Infrastructu Single Stage - Tw 1,217,705. 2019-09-0 2019-09-0 2019-10-1 2019-12-3 2020-02-0 2020-08- 00-000-2014-AF / Construc IBRD / 88160 Post Request for Bids Open - National 0.00 mplement re Development o Envelope 88 1 6 8 1 4 02 tion of Calantas-Planas-Sa ation n Jose FMR PRDP-IB-R003-ZAM-004-0 Pending I Component 2: Infrastructu Single Stage - Tw 1,994,078. 2019-09-0 2019-09-0 2019-10-1 2019-12-3 2020-02-0 2020-08- 00-000-2015-AF / Construc IBRD / 88160 Post Request for Bids Open - National 0.00 mplement re Development o Envelope 43 1 6 8 1 4 02 tion of Dirita-San Agustine ation FMR PRDP-IB-R003-BAT-006-00 Pending I Component 2: Infrastructu Single Stage - Tw 2019-09-0 2019-09-0 2019-10-1 2019-12-3 2020-02-0 2020-08- 0-000-2017-AF / Constructi IBRD / 88160 Post Request for Bids Open - National 51,372.55 0.00 mplement re Development o Envelope 1 6 8 1 4 02 on of Multi Commodity Sol ation ar Tunnel Dryers PRDP-IB-R002-NUV-004-A Pending I Component 2: Infrastructu Single Stage - Tw 2,524,490. 2019-08-0 2019-08-1 2019-09-2 2019-12-0 2020-01-0 2020-07- MB-001-2018 / Rehabilitati IBRD / 88160 Post Request for Bids Open - National 0.00 mplement re Development o Envelope 57 5 0 1 4 8 06 on of Tiblac Duli Farm To ation Market Road PRDP-IB-R003-NUE-008-T Pending I Component 2: Infrastructu Single Stage - Tw 2019-08-0 2019-08-1 2019-09-2 2019-12-0 2020-01-0 2020-07- AL-001-2015 / Improveme IBRD / 88160 Post Request for Bids Open - National 721,566.04 0.00 mplement re Development o Envelope 5 0 1 4 8 06 nt of Poblacion Sur-La Torr ation e-Mamandil FMR PRDP-IB-R003-PAM-001-0 Pending I Component 2: Infrastructu Single Stage - Tw 1,188,641. 2019-12-0 2019-12-0 2020-01-1 2020-03-3 2020-05-0 2020-11- 00-000-2015 / Constructio IBRD / 88160 Post Request for Bids Open - National 0.00 mplement re Development o Envelope 51 1 6 7 1 5 01 n of Calantas - Planas Far ation m to Market Road PRDP-IB-RCAR-BEN-006-0 Pending I Component 2: Infrastructu Single Stage - Tw 2,132,075. 2019-12-0 2019-12-0 2020-01-1 2020-03-3 2020-05-0 2020-11- 00-000-2015 / Improveme IBRD / 88160 Post Request for Bids Open - National 0.00 mplement re Development o Envelope 47 1 6 7 1 5 01 nt of Balang-Bocao with br ation idge National Procur PRDP-IB-R001-ILN-025-VI ement Docume Pending I Component 2: Infrastructu Single Stage - On 2022-01-0 2022-01-0 2022-02-1 2022-03-1 2022-04-2 2022-10- N-002-2018-AF2 / Construs IBRD / 92710 Post Request for Bids Open - National nt - 1 Envelope 108,480.00 0.00 mplement re Development e Envelope 1 6 7 9 3 20 tion of Dagupan Level 2 P process (Non B ation WS ank-SPD) National Procur PRDP-IB-R001-ILN-030-PA ement Docume Pending I O-003-2019-AF2 / Constru Component 2: Infrastructu Single Stage - On 2022-01-0 2022-01-0 2022-02-1 2022-03-1 2022-04-2 2022-10- IBRD / 92710 Post Request for Bids Open - National nt - 1 Envelope 272,520.00 0.00 mplement stion of Warehouse with M re Development e Envelope 1 6 7 9 3 20 process (Non B ation ulti-Purpose Drying Pavem ank-SPD) ent National Procur PRDP-IB-R001-LAU-008-B ement Docume Pending I AU-001-2017-AF2 / Rehabil Component 2: Infrastructu Single Stage - On 3,686,860. 2022-01-0 2022-01-0 2022-02-1 2022-03-1 2022-04-2 2022-10- IBRD / 92710 Post Request for Bids Open - National nt - 1 Envelope 0.00 mplement itation and Road Opening re Development e Envelope 00 1 6 7 9 3 20 process (Non B ation of Cabalayangan-Sta. Moni ank-SPD) ca Farm to Market Road National Procur PRDP-IB-R001-LAU-010-00 ement Docume Pending I Component 2: Infrastructu Single Stage - On 2022-01-0 2022-01-0 2022-02-1 2022-03-1 2022-04-2 2022-10- 0-000-2019-AF / Constructi IBRD / 92710 Post Request for Bids Open - National nt - 1 Envelope 358,880.00 0.00 mplement re Development e Envelope 1 6 7 9 3 20 on of Provincial Storage Fa process (Non B ation cility with Solar Dryer ank-SPD) National Procur PRDP-IB-R001-ILS-009-SA ement Docume Pending I Component 2: Infrastructu Single Stage - On 2,260,000. 2022-01-0 2022-01-0 2022-02-1 2022-03-1 2022-04-2 2022-10- M-001-2020-AF2 / Constru IBRD / 92710 Post Request for Bids Open - National nt - 1 Envelope 0.00 mplement re Development e Envelope 00 1 6 7 9 3 20 ction of Cabaroan-Silag-Pa process (Non B ation cang bridge ank-SPD) National Procur PRDP-IB-R001-LAU-012-00 ement Docume Pending I 0-000-2019-AF2 / Improve Component 2: Infrastructu Single Stage - On 2,529,560. 2022-01-0 2022-01-0 2022-02-1 2022-03-1 2022-04-2 2022-10- IBRD / 92710 Post Request for Bids Open - National nt - 1 Envelope 0.00 mplement ment of San Gabriel II Far re Development e Envelope 00 1 6 7 9 3 20 process (Non B ation m to Market Road with Bri ank-SPD) dge National Procur PRDP-IB-R002-ISA-031-00 ement Docume Pending I 0-000-2016-AF2 / Construc Component 2: Infrastructu Single Stage - On 2022-01-0 2022-01-0 2022-02-1 2022-03-1 2022-04-2 2022-10- IBRD / 92710 Post Request for Bids Open - National nt - 1 Envelope 530,000.00 0.00 mplement tion of Sianlugan Commun re Development e Envelope 1 6 7 9 3 20 process (Non B ation al Pump Irrigation Project ank-SPD) National Procur PRDP-IB-R002-ISA-042-NA ement Docume Under Imp G-001-2018-AF2 / Rehabili Component 2: Infrastructu Single Stage - On 2,309,735. 2022-01-0 2021-10-1 2022-01-0 2022-06-2 2022-02-1 2021-11-2 2022-03-1 2022-03-0 2022-04-2 2022-10- IBRD / 92710 Post Request for Bids Open - National nt - 1 Envelope 0.00 lementati tation of Quinalabasa-Sant re Development e Envelope 80 1 7 6 9 7 5 9 2 3 20 process (Non B on a Victoria-Bagong Sikat Fa ank-SPD) rm to Market Road National Procur PRDP-IB-R002-ISA-009-00 ement Docume Pending I 0-000-2015-AF2 / Rehabilit Component 2: Infrastructu Single Stage - On 3,573,923. 2022-01-0 2022-01-0 2022-02-1 2022-03-1 2022-04-2 2022-10- IBRD / 92710 Post Request for Bids Open - National nt - 1 Envelope 0.00 mplement ation / Improvement of Sa re Development e Envelope 20 1 6 7 9 3 20 process (Non B ation n Juan - Barucboc - Estrad ank-SPD) a - Dummon FMR National Procur PRDP-IB-R002-ISA-039-00 ement Docume Pending I Component 2: Infrastructu Single Stage - On 2,172,500. 2022-01-0 2022-01-0 2022-02-1 2022-03-1 2022-04-2 2022-10- 0-000-2018-AF2 / Rehabilit IBRD / 92710 Post Request for Bids Open - National nt - 1 Envelope 0.00 mplement re Development e Envelope 00 1 6 7 9 3 20 ation / Improvement of Uni process (Non B ation on - Barcolan FMR ank-SPD) Page 1 National Procur PRDP-IB-R002-ISA-010-SA ement Docume Pending I Component 2: Infrastructu Single Stage - On 3,425,540. 2022-01-0 2022-01-0 2022-02-1 2022-03-1 2022-04-2 2022-10- O-001-2015-AF2 / Rehabili IBRD / 92710 Post Request for Bids Open - National nt - 1 Envelope 0.00 mplement re Development e Envelope 00 1 6 7 9 3 20 tation of Calaocan-Batal Fa process (Non B ation rm-to-Market Road ank-SPD) National Procur PRDP-IB-R002-QUI-009-00 ement Docume Pending I 0-000-2015-AF / Rehabilita Component 2: Infrastructu Single Stage - On 1,268,908. 2022-01-0 2022-01-0 2022-02-1 2022-03-1 2022-04-2 2022-10- IBRD / 92710 Post Request for Bids Open - National nt - 1 Envelope 0.00 mplement tion of PRJ Gundaway-Doñ re Development e Envelope 60 1 6 7 9 3 20 process (Non B ation a Imelda Farm to Market R ank-SPD) oad National Procur PRDP-IB-R002-QUI-010-00 ement Docume Pending I 0-000-2015-AF / Rehabilita Component 2: Infrastructu Single Stage - On 2,328,200. 2022-01-0 2022-01-0 2022-02-1 2022-03-1 2022-04-2 2022-10- IBRD / 92710 Post Request for Bids Open - National nt - 1 Envelope 0.00 mplement tion of NRJ-Dungo-Divisori re Development e Envelope 00 1 6 7 9 3 20 process (Non B ation a Sur Farm to Market Road ank-SPD) National Procur PRDP-IB-R002-ISA-034-SA ement Docume Pending I Component 2: Infrastructu Single Stage - On 1,296,040. 2022-01-0 2022-01-0 2022-02-1 2022-03-1 2022-04-2 2022-10- O-003-2017-AF2 / Rehabili IBRD / 92710 Post Request for Bids Open - National nt - 1 Envelope 0.00 mplement re Development e Envelope 00 1 6 7 9 3 20 tation of Rizal-Abra Farm t process (Non B ation o Market Road ank-SPD) National Procur PRDP-IB-R002-ISA-035-SA ement Docume Pending I O-004-2018-AF2 / Rehabili Component 2: Infrastructu Single Stage - On 1,332,260. 2022-01-0 2022-01-0 2022-02-1 2022-03-1 2022-04-2 2022-10- IBRD / 92710 Post Request for Bids Open - National nt - 1 Envelope 0.00 mplement tation of the Sinsayon - Ca re Development e Envelope 00 1 6 7 9 3 20 process (Non B ation bulay Farm To Market Roa ank-SPD) d National Procur PRDP-IB-R002-ISA-043-DI ement Docume Pending I N-001-2019-AF2 / Rehabilit Component 2: Infrastructu Single Stage - On 4,190,860. 2022-01-0 2022-01-0 2022-02-1 2022-03-1 2022-04-2 2022-10- IBRD / 92710 Post Request for Bids Open - National nt - 1 Envelope 0.00 mplement ation/Construction of Digu re Development e Envelope 00 1 6 7 9 3 20 process (Non B ation mased-Ayod Farm to Mark ank-SPD) et Road (FMR) with Bridge National Procur PRDP-IB-R002-CAG-000-0 ement Docume Pending I 00-000-2021-AF2 / Brgy N Component 2: Infrastructu Single Stage - On 4,400,000. 2022-01-0 2022-01-0 2022-02-1 2022-03-1 2022-04-2 2022-10- IBRD / 92710 Post Request for Bids Open - National nt - 1 Envelope 0.00 mplement anauatan, Pasingan, Battu re Development e Envelope 00 1 6 7 9 3 20 process (Non B ation t and Lattut Farm to Marke ank-SPD) t Road National Procur PRDP-IB-R002-NUV-005-K ement Docume Pending I Component 2: Infrastructu Single Stage - On 4,109,147. 2022-01-0 2022-01-0 2022-02-1 2022-03-1 2022-04-2 2022-10- AS-001-2018-AF2 / Rehabil IBRD / 92710 Post Request for Bids Open - National nt - 1 Envelope 0.00 mplement re Development e Envelope 00 1 6 7 9 3 20 itation of Malabing Valley process (Non B ation Farm to Market Roads ank-SPD) National Procur PRDP-IB-R003-BUL-008-00 ement Docume Pending I 0-000-2017-AF2 / Improve Component 2: Infrastructu Single Stage - On 1,559,100. 2022-01-0 2022-01-0 2022-02-1 2022-03-1 2022-04-2 2022-10- IBRD / 92710 Post Request for Bids Open - National nt - 1 Envelope 0.00 mplement ment of Gabihan-Basuit-Sa re Development e Envelope 00 1 6 7 9 3 20 process (Non B ation pang Putik Farm-to-Market ank-SPD) Road National Procur PRDP-IB-R003-BAT-004-00 ement Docume Under Imp 0-000-2015-AF2 / Improve Component 2: Infrastructu Single Stage - On 1,878,620. 2022-01-0 2021-11-2 2022-01-0 2022-02-1 2021-12-2 2022-03-1 2022-06-2 2022-04-2 2022-10- IBRD / 92710 Post Request for Bids Open - National nt - 1 Envelope 0.00 lementati ment of Sitio Nazareno - C re Development e Envelope 00 1 9 6 7 9 9 2 3 20 process (Non B on ulis Farm to Market Road ank-SPD) National Procur PRDP-IB-R003-BAT-006-00 ement Docume Pending I Component 2: Infrastructu Single Stage - On 2022-01-0 2022-01-0 2022-02-1 2022-03-1 2022-04-2 2022-10- 0-000-2017-AF2 / Construc IBRD / 92710 Post Request for Bids Open - National nt - 1 Envelope 199,457.60 0.00 mplement re Development e Envelope 1 6 7 9 3 20 tion of Multi Commodity S process (Non B ation olar Tunnel Dryers ank-SPD) National Procur PRDP-IB-R003-BAT-008-00 ement Docume Pending I Component 2: Infrastructu Single Stage - On 3,960,000. 2022-01-0 2022-01-0 2022-02-1 2022-03-1 2022-04-2 2022-10- 0-000-2019-AF2 / Construc IBRD / 92710 Post Request for Bids Open - National nt - 1 Envelope 0.00 mplement re Development e Envelope 00 1 6 7 9 3 20 tion of fish landing and tra process (Non B ation ding post ank-SPD) National Procur PRDP-IB-R003-NUE-024-B ement Docume Pending I Component 2: Infrastructu Single Stage - On 4,123,364. 2022-01-0 2022-01-0 2022-02-1 2022-03-1 2022-04-2 2022-10- ON-023-2019-AF2 / Establi IBRD / 92710 Post Request for Bids Open - National nt - 1 Envelope 0.00 mplement re Development e Envelope 10 1 6 7 9 3 20 shment of Onion Cold Stor process (Non B ation age ank-SPD) National Procur PRDP-IB-RCAR-IFU-032-00 ement Docume Pending I Component 2: Infrastructu Single Stage - On 4,926,240. 2022-01-0 2022-01-0 2022-02-1 2022-03-1 2022-04-2 2022-10- 0-000-2020-AF2 / Concreti IBRD / 92710 Post Request for Bids Open - National nt - 1 Envelope 0.00 mplement re Development e Envelope 00 1 6 7 9 3 20 ng of Ubao-Manaot FMR process (Non B ation ank-SPD) National Procur PRDP-IB-RCAR-KAL-011-0 ement Docume Component 2: Infrastructu Single Stage - On 3,051,840. 2,523,203 2022-01-0 2022-01-1 2022-01-0 2022-06-2 2022-02-1 2022-02-1 2022-03-1 2022-04-0 2022-04-2 2022-04-2 2022-10- 00-000-2015-AF2 / Improv IBRD / 92710 Post Request for Bids Open - National nt - 1 Envelope Signed re Development e Envelope 00 .07 1 0 6 9 7 0 9 5 3 9 20 ement of Banneng - Darul process (Non B og - Bawac FMR ank-SPD) National Procur PRDP-IB-R002-ISA-041-RA ement Docume Pending I M-003-2019-AF / Rehabilit Component 2: Infrastructu Single Stage - On 2,826,007. 2022-01-0 2022-01-0 2022-02-1 2022-03-1 2022-04-2 2022-10- IBRD / 92710 Post Request for Bids Open - National nt - 1 Envelope 0.00 mplement ation of General Aguinaldo re Development e Envelope 90 1 6 7 9 3 20 process (Non B ation -Planas Farm to Market Ro ank-SPD) ad National Procur PRDP-IB-R002-ISA-050-RA ement Docume Pending I M-004-2020 / Proposed Wa Component 2: Infrastructu Single Stage - On 2022-01-0 2022-01-0 2022-02-1 2022-03-1 2022-04-2 2022-10- IBRD / 92710 Post Request for Bids Open - National nt - 1 Envelope 909,300.00 0.00 mplement rehouse with Solar Dryer, re Development e Envelope 1 6 7 9 3 20 process (Non B ation Ambatali, Ramon, Isabela ank-SPD) National Procur PRDP-IB-R002-ISA-051-RA ement Docume Pending I M-005-2020 / Proposed Wa Component 2: Infrastructu Single Stage - On 2022-01-0 2022-01-0 2022-02-1 2022-03-1 2022-04-2 2022-10- IBRD / 92710 Post Request for Bids Open - National nt - 1 Envelope 959,940.00 0.00 mplement rehouse with Solar Dryer, re Development e Envelope 1 6 7 9 3 20 process (Non B ation Bugallon Proper, Ramon, I ank-SPD) sabela National Procur PRDP-IB-R002-ISA-052-RA ement Docume Pending I Component 2: Infrastructu Single Stage - On 2022-01-0 2022-01-0 2022-02-1 2022-03-1 2022-04-2 2022-10- M-006-2020 / Proposed Wa IBRD / 92710 Post Request for Bids Open - National nt - 1 Envelope 371,660.00 0.00 mplement re Development e Envelope 1 6 7 9 3 20 rehouse with Solar Dryer, process (Non B ation Burgos, Ramon, Isabela ank-SPD) National Procur PRDP-IB-R002-ISA-053-RA ement Docume Pending I M-007-2020 / Proposed Wa Component 2: Infrastructu Single Stage - On 2022-01-0 2022-01-0 2022-02-1 2022-03-1 2022-04-2 2022-10- IBRD / 92710 Post Request for Bids Open - National nt - 1 Envelope 686,260.00 0.00 mplement rehouse with Solar Dryer, re Development e Envelope 1 6 7 9 3 20 process (Non B ation San Miguel, Ramon, Isabel ank-SPD) a National Procur PRDP-IB-R001-LAU-014-00 ement Docume Pending I Component 2: Infrastructu Single Stage - On 2022-01-0 2022-01-0 2022-02-1 2022-03-1 2022-04-2 2022-10- 0-000-2019-AF2 / Construc IBRD / 92710 Post Request for Bids Open - National nt - 1 Envelope 358,880.00 0.00 mplement re Development e Envelope 1 6 7 9 3 20 tion of Provincial Storage F process (Non B ation acility with Solar Dryer ank-SPD) National Procur PRDP-IB-RCAR-BEN-006-K ement Docume Pending I Component 2: Infrastructu Single Stage - On 2,198,454. 2021-12-1 2021-12-1 2022-01-2 2022-02-2 2022-04-0 2022-09- AB-001-2016-AF / Improve IBRD / 92710 Post Request for Bids Open - National nt - 1 Envelope 0.00 mplement re Development e Envelope 04 2 7 8 7 3 30 ment of Balang-Bocao FMR process (Non B ation with Bridge ank-SPD) National Procur PRDP-IB-R002-NUV-007-A ement Docume Pending I Component 2: Infrastructu Single Stage - On 1,727,240. 2022-01-0 2022-01-0 2022-02-1 2022-03-1 2022-04-2 2022-10- MB-003-2018-AF2 / Rehabi IBRD / 92710 Post Request for Bids Open - National nt - 1 Envelope 0.00 mplement re Development e Envelope 00 1 6 7 9 3 20 litation of Poblacion-Laba process (Non B ation ng Farm to Market Road ank-SPD) National Procur PRDP-IB-R002-NUV-006-A ement Docume Pending I Component 2: Infrastructu Single Stage - On 4,924,313. 2022-02-0 2022-02-1 2022-03-2 2022-04-2 2022-05-2 2022-11- MB-002-2018-AF2 / Rehabi IBRD / 92710 Post Request for Bids Open - National nt - 1 Envelope 0.00 mplement re Development e Envelope 59 6 1 5 4 9 25 litation of Ammoweg - Ca process (Non B ation mandag FMR ank-SPD) National Procur PRDP-IB-RCAR-APA-002-0 ement Docume Pending I 00-000-2015-AF2 / Improv Component 2: Infrastructu Single Stage - On 2,389,880. 2022-04-2 2022-04-2 2022-06-0 2022-07-0 2022-08-1 2023-02- IBRD / 92710 Post Request for Bids Open - National nt - 1 Envelope 0.00 mplement ement of Cabatacan - San re Development e Envelope 00 2 7 8 8 2 08 process (Non B ation Mariano- San Jose Farm to ank-SPD) Market Road National Procur PRDP-IB-R001-LAU-007-00 ement Docume Pending I Component 2: Infrastructu Single Stage - On 5,221,800. 2022-06-0 2022-06-0 2022-07-1 2022-08-1 2022-09-2 2023-03- 0-000-2017-AF2 / Rehabilit IBRD / 92710 Post Request for Bids Open - National nt - 1 Envelope 0.00 mplement re Development e Envelope 00 1 6 8 7 1 20 ation of Ramot-Puguil Far process (Non B ation m to Market Road ank-SPD) National Procur PRDP-IR-RO03-NUE-038-B ement Docume Pending I Component 2: Infrastructu Single Stage - On 1,957,960. 2022-06-0 2022-06-0 2022-07-1 2022-08-1 2022-09-2 2023-03- ON-001-2020-AF2 / Constr IBRD / 92710 Post Request for Bids Open - National nt - 1 Envelope 0.00 mplement re Development e Envelope 00 1 6 8 7 1 20 uction of Onion Cold Stora process (Non B ation ge Facility ank-SPD) National Procur PRDP-IB-R003-NUE-031-0 ement Docume Pending I Component 2: Infrastructu Single Stage - On 4,199,200. 2022-07-0 2022-07-0 2022-08-1 2022-09-1 2022-10-2 2023-04- 00-000-2020-AF2 / Constru IBRD / 92710 Post Request for Bids Open - National nt - 1 Envelope 0.00 mplement re Development e Envelope 00 1 6 7 6 1 19 ction of Nueva Ecija Onion process (Non B ation Cold Storage Facility ank-SPD) National Procur PRDP-IB-RCAR-MOP-021-B ement Docume Pending I Component 2: Infrastructu Request for Quo Single Stage - On 2022-08-0 2022-10-0 2023-03- AR-021-2021-AF2 / Constr IBRD / 92710 Post Open - National nt - 1 Envelope 137,200.00 0.00 mplement re Development tations e Envelope 6 1 30 uction of Lias PWS Level II process (Non B ation ank-SPD) GOODS Activity Reference No. Bid Evaluation Repo Loan / Credit Market Approa Procurement Pr Prequalificatio Estimated A Actual Amoun Process S Draft Pre-qualificatio Prequalification Eval Draft Bidding Docu Specific Procuremen Bidding Documents Proposal Submission / Description Component Review Type Method rt and Recommenda Signed Contract Contract Completion No. ch ocess n (Y/N) mount (US$) t (US$) tatus n Documents uation Report ment / Justification t Notice / Invitation as Issued / Opening / Minutes tion for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. Bid Evaluation Repo Loan / Credit Market Approa Procurement Pr Prequalificatio Estimated A Actual Amoun Process S Draft Pre-qualificatio Prequalification Eval Draft Bidding Docu Specific Procuremen Bidding Documents Proposal Submission / Description Component Review Type Method rt and Recommenda Signed Contract Contract Completion No. ch ocess n (Y/N) mount (US$) t (US$) tatus n Documents uation Report ment / Justification t Notice / Invitation as Issued / Opening / Minutes tion for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. Short List and Draft Combined Evaluatio Loan / Credit Market Approa Contract Type Estimated Am Actual Amou Process Statu Expression of Intere Request for Proposal Opening of Technica Evaluation of Techn / Description Component Review Type Method Terms of Reference Request for Proposal n Report and Draft N Signed Contract Contract Completion No. ch ount (US$) nt (US$) s st Notice s as Issued l Proposals / Minutes ical Proposal s egotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. Invitation to Identifie Loan / Credit Market Approa Contract Type Estimated Am Actual Amou Process Statu Draft Negotiated Co / Description Component Review Type Method Terms of Reference d/Selected Consulta Signed Contract Contract Completion No. ch ount (US$) nt (US$) s ntract nt Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PRDP-IS-PSO-IB-002-000-2 Component 4: Project Imp Individual Cons Pending Imple 2018-01-1 2018-02-0 2018-03-1 2018-09-1 IBRD / 88160 Post Open 7,058.82 0.00 2017-12-01 018-AF / Water Specialist lementation Support ultant Selection mentation 9 9 6 2 PRDP-IS-PSO-IB-004-003-2 Component 4: Project Imp Pending Imple 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 6,352.94 0.00 2017-12-01 018-AF / Rural Infrastructu lementation Support mentation 1 4 3 re Engineer PRDP-IS-PSO-DPD-001-00 Component 2: Infrastructu Pending Imple 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 4,941.18 0.00 2017-12-01 0-2018-AF / Executive Assi re Development mentation 1 4 3 stant PRDP-IS-PSO-PROC-002-0 Component 4: Project Imp Individual Cons Pending Imple 2018-01-1 2018-02-0 2018-03-1 2018-09-1 03-2018-AF / Project Devel IBRD / 88160 Post Open 4,235.29 0.00 2017-12-01 lementation Support ultant Selection mentation 9 9 6 2 opment Associate PRDP-IS-PSO-MAE-001-00 Component 4: Project Imp Individual Cons Pending Imple 2018-01-1 2018-02-0 2018-03-1 2018-09-1 2-2018-AF / Monitoring an IBRD / 88160 Post Open 6,352.94 0.00 2017-12-01 lementation Support ultant Selection mentation 9 9 6 2 d Evaluation Officer PRDP-IS-PSO-GGU-002-00 Component 4: Project Imp Individual Cons Pending Imple 2018-01-1 2018-02-0 2018-03-1 2018-09-1 3-2018-AF / Project Develo IBRD / 88160 Post Open 4,235.29 0.00 2017-12-01 lementation Support ultant Selection mentation 9 9 6 2 pment Associate PRDP-IS-RCAR-ADM-001-0 Component 4: Project Imp Individual Cons Pending Imple 2018-01-1 2018-02-0 2018-03-1 2018-09-1 IBRD / 88160 Post Open 2,117.65 0.00 2017-12-01 00-2018-AF / Cash Clerk lementation Support ultant Selection mentation 9 9 6 2 PRDP-IS-RCAR-ODP-001-0 Component 4: Project Imp Individual Cons Pending Imple 2018-01-1 2018-02-0 2018-03-1 2018-09-1 02-2018-AF / Project Devel IBRD / 88160 Post Open 3,529.41 0.00 2017-12-01 lementation Support ultant Selection mentation 9 9 6 2 opment Associate PRDP-IS-RCAR-DPD-003-0 Component 4: Project Imp Pending Imple 2017-12-1 2018-02-1 2018-08-1 00-2018-AF / Project Devel IBRD / 88160 Post Direct Selection Direct 3,529.41 0.00 2017-12-01 lementation Support mentation 1 4 3 opment Associate PRDP-IS-RCAR-SES-001-00 Component 4: Project Imp Individual Cons Pending Imple 2018-01-1 2018-02-0 2018-03-1 2018-09-1 3-2018-AF / Project Develo IBRD / 88160 Post Open 3,529.41 0.00 2017-12-01 lementation Support ultant Selection mentation 9 9 6 2 pment Associate PRDP-IS-RCAR-GGU-001-0 Component 4: Project Imp Individual Cons Pending Imple 2018-01-1 2018-02-0 2018-03-1 2018-09-1 02-2018-AF / Project Devel IBRD / 88160 Post Open 3,529.41 0.00 2017-12-01 lementation Support ultant Selection mentation 9 9 6 2 opment Associate PRDP-IS-RCAR-GGU-001-0 Component 4: Project Imp Individual Cons Pending Imple 2018-01-1 2018-02-0 2018-03-1 2018-09-1 03-2018-AF / Project Devel IBRD / 88160 Post Open 3,529.41 0.00 2017-12-01 lementation Support ultant Selection mentation 9 9 6 2 opment Associate PRDP-IS-RCAR-ADM-002-0 Component 4: Project Imp Individual Cons Pending Imple 2018-01-1 2018-02-0 2018-03-1 2018-09-1 IBRD / 88160 Post Open 2,117.65 0.00 2017-12-01 01-2018-AF / Administrativ lementation Support ultant Selection mentation 9 9 6 2 e Staff PRDP-IS-RCAR-ADM-002-0 Component 4: Project Imp Individual Cons Pending Imple 2018-01-1 2018-02-0 2018-03-1 2018-09-1 IBRD / 88160 Post Open 2,117.65 0.00 2017-12-01 02-2018-AF / Administrativ lementation Support ultant Selection mentation 9 9 6 2 e Staff PRDP-IS-RCAR-IB-001-005 Component 4: Project Imp Individual Cons Pending Imple 2018-01-1 2018-02-0 2018-03-1 2018-09-1 IBRD / 88160 Post Open 5,647.06 0.00 2017-12-01 -2018-AF / Rural Infrastruc lementation Support ultant Selection mentation 9 9 6 2 ture Engineer PRDP-IS-RCAR-IB-001-006 Component 4: Project Imp Pending Imple 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 5,647.06 0.00 2017-12-01 -2018-AF / Rural Infrastruc lementation Support mentation 1 4 3 ture Engineer PRDP-IS-R001-GGU-002-0 Component 4: Project Imp Pending Imple 2017-12-1 2018-02-1 2018-08-1 02-2018-AF / Project Devel IBRD / 88160 Post Direct Selection Direct 2,941.18 0.00 2017-12-01 lementation Support mentation 1 4 3 opment Associate Page 2 PRDP-IS-R002-ADM-003-0 Component 4: Project Imp Individual Cons Pending Imple 2018-01-1 2018-02-0 2018-03-1 2018-09-1 IBRD / 88160 Post Open 1,411.76 0.00 2017-12-01 00-2018-AF / Chauffer lementation Support ultant Selection mentation 9 9 6 2 PRDP-IS-R002-ADM-004-0 Component 4: Project Imp Individual Cons Pending Imple 2018-01-1 2018-02-0 2018-03-1 2018-09-1 IBRD / 88160 Post Open 5,647.06 0.00 2017-12-01 00-2018-AF / Chauffer lementation Support ultant Selection mentation 9 9 6 2 PRDP-IS-R002-FIN-002-00 Component 4: Project Imp Individual Cons Pending Imple 2018-01-1 2018-02-0 2018-03-1 2018-09-1 IBRD / 88160 Post Open 4,117.65 0.00 2017-12-01 1-2018-AF / Finance Analy lementation Support ultant Selection mentation 9 9 6 2 st I PRDP-IS-R003-PROC-002- Component 4: Project Imp Individual Cons Pending Imple 2018-01-1 2018-02-0 2018-03-1 2018-09-1 003-2018-AF / Project Dev IBRD / 88160 Post Open 3,529.41 0.00 2017-12-01 lementation Support ultant Selection mentation 9 9 6 2 elopment Associate PRDP-IS-R003-FIN-001-00 Component 4: Project Imp Individual Cons Pending Imple 2018-01-1 2018-02-0 2018-03-1 2018-09-1 IBRD / 88160 Post Open 4,941.18 0.00 2017-12-01 0-2018-AF / Finance Analy lementation Support ultant Selection mentation 9 9 6 2 st I PRDP-IS-R003-IB-001-005- Component 4: Project Imp Pending Imple 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 5,647.06 0.00 2017-12-01 2018-AF / Rural Infrastruct lementation Support mentation 1 4 3 ure Engineer PRDP-IS-R003-INF-001-00 Component 4: Project Imp Individual Cons Pending Imple 2018-01-1 2018-02-0 2018-03-1 2018-09-1 0-2018-AF / Project Develo IBRD / 88160 Post Open 3,529.41 0.00 2017-12-01 lementation Support ultant Selection mentation 9 9 6 2 pment Associate PRDP-IS-R003-IB-003-000- Component 4: Project Imp Individual Cons Pending Imple 2018-01-1 2018-02-0 2018-03-1 2018-09-1 IBRD / 88160 Post Open 2,823.53 0.00 2017-12-01 2018-AF / Chaffeur lementation Support ultant Selection mentation 9 9 6 2 PRDP-IS-PSO-IB-001-000-2 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 9,882.35 0.00 Canceled 2017-12-01 018-AF / I-BUILD Compone lementation Support 1 4 3 nt Head PRDP-IS-PSO-IB-003-000-2 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 7,058.82 0.00 Canceled 2017-12-01 018-AF / Roads and Bridge lementation Support 1 4 3 s Specialist PRDP-IS-PSO-IB-004-001-2 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 6,352.94 0.00 Canceled 2017-12-01 018-AF / Rural Infrastructu lementation Support 1 4 3 re Engineer PRDP-IS-PSO-IB-004-002-2 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 6,352.94 0.00 Canceled 2017-12-01 018-AF / Rural Infrastructu lementation Support 1 4 3 re Engineer PRDP-IS-R002-IB-004-001- Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 11,294.12 0.00 Canceled 2017-12-01 2018-AF / Rural Infrastruct lementation Support 1 4 3 ure Engineer PRDP-IS-PSO-IB-005-000-2 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 4,235.29 0.00 Canceled 2017-12-01 018-AF / Project Developm lementation Support 1 4 3 ent Associate PRDP-IS-PSO-DPD-002-00 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 7,058.82 0.00 Canceled 2017-12-01 0-2018-AF / Economist lementation Support 1 4 3 PRDP-IS-R002-IB-004-002- Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 11,294.12 0.00 Canceled 2017-12-01 2018-AF / Rural Infrastruct lementation Support 1 4 3 ure Engineer PRDP-IS-PSO-DPD-003-00 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 7,058.82 0.00 Canceled 2017-12-01 0-2018-AF / Compliance Of lementation Support 1 4 3 ficer PRDP-IS-R002-IB-004-003- Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 11,294.12 0.00 Canceled 2017-12-01 2018-AF / Rural Infrastruct lementation Support 1 4 3 ure Engineer PRDP-IS-PSO-INF-001-000- Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 5,647.06 0.00 Canceled 2017-12-01 2018-AF / Writer lementation Support 1 4 3 PRDP-IS-PSO-INF-002-000- Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 4,941.18 0.00 Canceled 2017-12-01 2018-AF / Lay-Out Artist lementation Support 1 4 3 PRDP-IS-PSO-PROC-001-0 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 6,352.94 0.00 Canceled 2017-12-01 00-2018-AF / Procurement lementation Support 1 4 3 Officer PRDP-IS-R002-IB-004-004- Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 11,294.12 0.00 Canceled 2017-12-01 2018-AF / Rural Infrastruct lementation Support 1 4 3 ure Engineer PRDP-IS-PSO-PROC-002-0 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 01-2018-AF / Project Devel IBRD / 88160 Post Direct Selection Direct 4,235.29 0.00 Canceled 2017-12-01 lementation Support 1 4 3 opment Associate PRDP-IS-PSO-PROC-002-0 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 02-2018-AF / Project Devel IBRD / 88160 Post Direct Selection Direct 4,235.29 0.00 Canceled 2017-12-01 lementation Support 1 4 3 opment Associate PRDP-IS-R002-IB-004-005- Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 11,294.12 0.00 Canceled 2017-12-01 2018-AF / Rural Infrastruct lementation Support 1 4 3 ure Engineer PRDP-IS-R002-IB-004-006- Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 11,294.12 0.00 Canceled 2017-12-01 2018-AF / Rural Infrastruct lementation Support 1 4 3 ure Engineer PRDP-IS-PSO-MAE-001-00 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 1-2018-AF / Monitoring an IBRD / 88160 Post Direct Selection Direct 6,352.94 0.00 Canceled 2017-12-01 lementation Support 1 4 3 d Evaluation Officer PRDP-IS-PSO-FIN-001-000- Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 6,352.94 0.00 Canceled 2017-12-01 2018-AF / Financial Analys lementation Support 1 4 3 t II PRDP-IS-R002-IB-005-000- Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 7,058.82 0.00 Canceled 2017-12-01 2018-AF / Project Develop lementation Support 1 4 3 ment Associate PRDP-IS-R002-ODP-001-0 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 8,470.59 0.00 Canceled 2017-12-01 00-2018-AF / Executive As lementation Support 1 4 3 st. PRDP-IS-R002-ODP-002-0 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 12,705.88 0.00 Canceled 2017-12-01 00-2018-AF / Compliance lementation Support 1 4 3 Officer PRDP-IS-R002-ADM-001-0 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 7,058.82 0.00 Canceled 2017-12-01 00-2018-AF / Admin Office lementation Support 1 4 3 rI PRDP-IS-R002-ADM-002-0 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 00-2018-AF / Project Devel IBRD / 88160 Post Direct Selection Direct 7,058.82 0.00 Canceled 2017-12-01 lementation Support 1 4 3 opment Associate PRDP-IS-R002-FIN-002-00 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 9,882.35 0.00 Canceled 2017-12-01 2-2018-AF / Finance Analy lementation Support 1 4 3 st I PRDP-IS-PSO-FIN-002-001- Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 5,647.06 0.00 Canceled 2017-12-01 2018-AF / Financial Analys lementation Support 1 4 3 tI PRDP-IS-R002-FIN-002-00 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 3-2018-AF / Project Develo IBRD / 88160 Post Direct Selection Direct 7,058.82 0.00 Canceled 2017-12-01 lementation Support 1 4 3 pment Associate PRDP-IS-PSO-FIN-002-002- Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 5,647.06 0.00 Canceled 2017-12-01 2018-AF / Financial Analys lementation Support 1 4 3 tI PRDP-IS-PSO-FIN-002-003- Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 5,647.06 0.00 Canceled 2017-12-01 2018-AF / Financial Analys lementation Support 1 4 3 tI PRDP-IS-R002-FIN-002-00 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 4-2018-AF / Project Develo IBRD / 88160 Post Direct Selection Direct 7,058.82 0.00 Canceled 2017-12-01 lementation Support 1 4 3 pment Associate PRDP-IS-PSO-FIN-001-003- Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 4,235.29 0.00 Canceled 2017-12-01 2018-AF / Budget Analyst lementation Support 1 4 3 PRDP-IS-PSO-GGU-001-00 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 6,352.94 0.00 Canceled 2017-12-01 0-2018-AF / GIS Data Offic lementation Support 1 4 3 er PRDP-IS-R002-PROC-001- Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 11,294.12 0.00 Canceled 2017-12-01 000-2018-AF / Procuremen lementation Support 1 4 3 t Officer PRDP-IS-PSO-GGU-002-00 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 1-2018-AF / Project Develo IBRD / 88160 Post Direct Selection Direct 4,235.29 0.00 Canceled 2017-12-01 lementation Support 1 4 3 pment Associate PRDP-IS-R002-PROC-002- Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 001-2018-AF / Project Dev IBRD / 88160 Post Direct Selection Direct 7,058.82 0.00 Canceled 2017-12-01 lementation Support 1 4 3 elopment Associate PRDP-IS-R002-MAE-001-0 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 11,294.12 0.00 Canceled 2017-12-01 01-2018-AF / M&E Officer lementation Support 1 4 3 PRDP-IS-PSO-GGU-002-00 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 2-2018-AF / Project Develo IBRD / 88160 Post Direct Selection Direct 4,235.29 0.00 Canceled 2017-12-01 lementation Support 1 4 3 pment Associate PRDP-IS-PSO-SES-001-000 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 9,882.35 0.00 Canceled 2017-12-01 -2018-AF / SES Unit Head lementation Support 1 4 3 PRDP-IS-R002-MAE-002-0 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 01-2018-AF / Project Devel IBRD / 88160 Post Direct Selection Direct 7,058.82 0.00 Canceled 2017-12-01 lementation Support 1 4 3 opment Associate PRDP-IS-PSO-SES-002-000 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 7,058.82 0.00 Canceled 2017-12-01 -2018-AF / Social Safeguar lementation Support 1 4 3 ds Specialist PRDP-IS-R002-MAE-002-0 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 02-2018-AF / Project Devel IBRD / 88160 Post Direct Selection Direct 7,058.82 0.00 Canceled 2017-12-01 lementation Support 1 4 3 opment Associate PRDP-IS-PSO-SES-003-000 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 -2018-AF / Environmental IBRD / 88160 Post Direct Selection Direct 6,352.94 0.00 Canceled 2017-12-01 lementation Support 1 4 3 Safeguards Officer PRDP-IS-R002-SES-002-00 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 12,705.88 0.00 Canceled 2017-12-01 0-2018-AF / Social Safegua lementation Support 1 4 3 rd Specialist PRDP-IS-PSO-SES-004-000 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 -2018-AF / Program Develo IBRD / 88160 Post Direct Selection Direct 4,235.29 0.00 Canceled 2017-12-01 lementation Support 1 4 3 pment Associate PRDP-IS-R002-SES-003-00 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 0-2018-AF / Social Environ IBRD / 88160 Post Direct Selection Direct 5,647.06 0.00 Canceled 2017-12-01 lementation Support 1 4 3 mental Safeguard Officer PRDP-IS-PSO-ADM-001-00 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 4,235.29 0.00 Canceled 2017-12-01 0-2018-AF / Administrative lementation Support 1 4 3 Officer I PRDP-IS-R002-SES-004-00 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 0-2018-AF / Project Develo IBRD / 88160 Post Direct Selection Direct 7,058.82 0.00 Canceled 2017-12-01 lementation Support 1 4 3 pment Associate PRDP-IS-PSO-ADM-002-00 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 2,823.53 0.00 Canceled 2017-12-01 1-2018-AF / Administrative lementation Support 1 4 3 Staff PRDP-IS-PSO-ADM-002-00 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 2,823.53 0.00 Canceled 2017-12-01 2-2018-AF / Administrative lementation Support 1 4 3 Staff PRDP-IS-R002-GGU-001-0 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 12,705.88 0.00 Canceled 2017-12-01 00-2018-AF / GIS Specialis lementation Support 1 4 3 t PRDP-IS-PSO-ADM-003-00 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 2,823.53 0.00 Canceled 2017-12-01 0-2018-AF / Cashier Clerk lementation Support 1 4 3 PRDP-IS-PSO-ADM-004-00 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 2,823.53 0.00 Canceled 2017-12-01 1-2018-AF / Chaffeur lementation Support 1 4 3 PRDP-IS-PSO-ADM-004-00 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 2,823.53 0.00 Canceled 2017-12-01 2-2018-AF / Chaffeur lementation Support 1 4 3 PRDP-IS-R002-GGU-001-0 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 11,294.12 0.00 Canceled 2017-12-01 01-2018-AF / GIS Officer lementation Support 1 4 3 PRDP-IS-PSO-ADM-004-00 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 2,823.53 0.00 Canceled 2017-12-01 3-2018-AF / Chaffeur lementation Support 1 4 3 Page 3 PRDP-IS-R002-GGU-002-0 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 01-2018-AF / Project Devel IBRD / 88160 Post Direct Selection Direct 7,058.82 0.00 Canceled 2017-12-01 lementation Support 1 4 3 opment Associate PRDP-IS-R002-INF-001-00 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 12,705.88 0.00 Canceled 2017-12-01 0-2018-AF / Info & Advoca lementation Support 1 4 3 cy Specialist PRDP-IS-R002-INF-002-00 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 8,470.59 0.00 Canceled 2017-12-01 0-2018-AF / Layout Artist lementation Support 1 4 3 PRDP-IS-PSO-ADM-006-00 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 2,117.65 0.00 Canceled 2017-12-01 0-2018-AF / Utility lementation Support 1 4 3 PRDP-IS-R002-INF-003-00 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 0-2018-AF / Project Develo IBRD / 88160 Post Direct Selection Direct 7,058.82 0.00 Canceled 2017-12-01 lementation Support 1 4 3 pment Associate PRDP-IS-PSO-ADM-005-00 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 2,549.02 0.00 Canceled 2017-12-01 0-2018-AF / Messenger lementation Support 1 4 3 PRDP-IS-R002-INF-004-00 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 8,470.59 0.00 Canceled 2017-12-01 0-2018-AF / Photographer/ lementation Support 1 4 3 Videographer PRDP-IS-RCAR-ODP-001-0 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 01-2018-AF / Project Devel IBRD / 88160 Post Direct Selection Direct 3,529.41 0.00 Canceled 2017-12-01 lementation Support 1 4 3 opment Associate PRDP-IS-RCAR-FIN-001-00 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 4,941.18 0.00 Canceled 2017-12-01 1-2018-AF / Financial Anal lementation Support 1 4 3 yst 1 PRDP-IS-R003-SES-001-00 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 5,647.06 0.00 Canceled 2017-12-01 0-2018-AF / Social Safegua lementation Support 1 4 3 rd Officer PRDP-IS-RCAR-FIN-001-00 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 4,941.18 0.00 Canceled 2017-12-01 2-2018-AF / Financial Anal lementation Support 1 4 3 yst 1 PRDP-IS-R003-SES-002-00 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 1-2018-AF / Project Develo IBRD / 88160 Post Direct Selection Direct 3,529.41 0.00 Canceled 2017-12-01 lementation Support 1 4 3 pment Associate PRDP-IS-R003-SES-002-00 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 2-2018-AF / Project Develo IBRD / 88160 Post Direct Selection Direct 3,529.41 0.00 Canceled 2017-12-01 lementation Support 1 4 3 pment Associate PRDP-IS-RCAR-ODP-002-0 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 00-2018-AF / Project Devel IBRD / 88160 Post Direct Selection Direct 3,529.41 0.00 Canceled 2017-12-01 lementation Support 1 4 3 opment Associate PRDP-IS-RCAR-MAE-001-0 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 02-2018-AF / Project Devel IBRD / 88160 Post Direct Selection Direct 3,529.41 0.00 Canceled 2017-12-01 lementation Support 1 4 3 opment Associate PRDP-IS-RCAR-MAE-001-0 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 01-2018-AF / Project Devel IBRD / 88160 Post Direct Selection Direct 3,529.41 0.00 Canceled 2017-12-01 lementation Support 1 4 3 opment Associate PRDP-IS-RCAR-PROC-001- Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 001-2018-AF / Project Dev IBRD / 88160 Post Direct Selection Direct 3,529.41 0.00 Canceled 2017-12-01 lementation Support 1 4 3 elopment Associate PRDP-IS-RCAR-PROC-001- Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 002-2018-AF / Project Dev IBRD / 88160 Post Direct Selection Direct 3,529.41 0.00 Canceled 2017-12-01 lementation Support 1 4 3 elopment Associate PRDP-IS-RCAR-PROC-001- Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 003-2018-AF / Project Dev IBRD / 88160 Post Direct Selection Direct 3,529.41 0.00 Canceled 2017-12-01 lementation Support 1 4 3 elopment Associate PRDP-IS-RCAR-SES-001-00 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 1-2018-AF / Project Develo IBRD / 88160 Post Direct Selection Direct 3,529.41 0.00 Canceled 2017-12-01 lementation Support 1 4 3 pment Associate PRDP-IS-RCAR-SES-001-00 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 2-2018-AF / Project Develo IBRD / 88160 Post Direct Selection Direct 3,529.41 0.00 Canceled 2017-12-01 lementation Support 1 4 3 pment Associate PRDP-IS-RCAR-INF-001-00 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 0-2018-AF / Project Develo IBRD / 88160 Post Direct Selection Direct 3,529.41 0.00 Canceled 2017-12-01 lementation Support 1 4 3 pment Associate PRDP-IS-RCAR-GGU-001-0 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 01-2018-AF / Project Devel IBRD / 88160 Post Direct Selection Direct 3,529.41 0.00 Canceled 2017-12-01 lementation Support 1 4 3 opment Associate PRDP-IS-RCAR-ADM-003-0 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 2,823.53 0.00 Canceled 2017-12-01 01-2018-AF / Chauffer lementation Support 1 4 3 PRDP-IS-RCAR-ADM-003-0 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 2,823.53 0.00 Canceled 2017-12-01 02-2018-AF / Chauffer lementation Support 1 4 3 PRDP-IS-RCAR-ADM-003-0 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 2,823.53 0.00 Canceled 2017-12-01 03-2018-AF / Chauffer lementation Support 1 4 3 PRDP-IS-RCAR-ADM-003-0 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 2,823.53 0.00 Canceled 2017-12-01 04-2018-AF / Chauffer lementation Support 1 4 3 PRDP-IS-RCAR-IB-001-001 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 5,647.06 0.00 Canceled 2017-12-01 -2018-AF / Rural Infrastruc lementation Support 1 4 3 ture Engineer PRDP-IS-R003-GGU-001-0 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 5,647.06 0.00 Canceled 2017-12-01 00-2018-AF / GIS Data Offi lementation Support 1 4 3 cer PRDP-IS-R003-GGU-002-0 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 01-2018-AF / Project Devel IBRD / 88160 Post Direct Selection Direct 3,529.41 0.00 Canceled 2017-12-01 lementation Support 1 4 3 opment Associate PRDP-IS-R003-GGU-002-0 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 02-2018-AF / Project Devel IBRD / 88160 Post Direct Selection Direct 3,529.41 0.00 Canceled 2017-12-01 lementation Support 1 4 3 opment Associate PRDP-IS-R003-PROC-001- Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 5,647.06 0.00 Canceled 2017-12-01 000-2018-AF / Procuremen lementation Support 1 4 3 t Officer PRDP-IS-R003-PROC-002- Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 001-2018-AF / Project Dev IBRD / 88160 Post Direct Selection Direct 3,529.41 0.00 Canceled 2017-12-01 lementation Support 1 4 3 elopment Associate PRDP-IS-R003-PROC-002- Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 002-2018-AF / Project Dev IBRD / 88160 Post Direct Selection Direct 3,529.41 0.00 Canceled 2017-12-01 lementation Support 1 4 3 elopment Associate PRDP-IS-R003-MAE-001-0 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 00-2018-AF / Project Devel IBRD / 88160 Post Direct Selection Direct 3,529.41 0.00 Canceled 2017-12-01 lementation Support 1 4 3 opment Associate PRDP-IS-R003-MAE-001-0 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 01-2018-AF / Project Devel IBRD / 88160 Post Direct Selection Direct 3,529.41 0.00 Canceled 2017-12-01 lementation Support 1 4 3 opment Associate PRDP-IS-R003-OFP-001-00 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 1-2018-AF / Project Develo IBRD / 88160 Post Direct Selection Direct 3,529.41 0.00 Canceled 2017-12-01 lementation Support 1 4 3 pment Associate PRDP-IS-R003-OFP-001-00 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 2-2018-AF / Project Develo IBRD / 88160 Post Direct Selection Direct 3,529.41 0.00 Canceled 2017-12-01 lementation Support 1 4 3 pment Associate PRDP-IS-R003-IB-001-001- Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 5,647.06 0.00 Canceled 2017-12-01 2018-AF / Rural Infrastruct lementation Support 1 4 3 ure Engineer PRDP-IS-RCAR-IB-001-002 Component 2: Infrastructu 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 5,647.06 0.00 Canceled 2017-12-01 -2018-AF / Rural Infrastruc re Development 1 4 3 ture Engineer PRDP-IS-R003-IB-001-002- Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 5,647.06 0.00 Canceled 2017-12-01 2018-AF / Rural Infrastruct lementation Support 1 4 3 ure Engineer PRDP-IS-RCAR-IB-001-003 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 5,647.06 0.00 Canceled 2017-12-01 -2018-AF / Rural Infrastruc lementation Support 1 4 3 ture Engineer PRDP-IS-R003-IB-001-003- Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 5,647.06 0.00 Canceled 2017-12-01 2018-AF / Rural Infrastruct lementation Support 1 4 3 ure Engineer PRDP-IS-RCAR-IB-001-004 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 5,647.06 0.00 Canceled 2017-12-01 -2018-AF / Rural Infrastruc lementation Support 1 4 3 ture Engineer PRDP-IS-RCAR-IB-002-000 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 -2018-AF / Project Develop IBRD / 88160 Post Direct Selection Direct 3,529.41 0.00 Canceled 2017-12-01 lementation Support 1 4 3 ment Associate PRDP-IS-R003-IB-001-004- Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 5,647.06 0.00 Canceled 2017-12-01 2018-AF / Rural Infrastruct lementation Support 1 4 3 ure Engineer PRDP-IS-R003-IB-002-000- Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 3,529.41 0.00 Canceled 2017-12-01 2018-AF / Project Develop lementation Support 1 4 3 ment Associate PRDP-IS-R001-FIN-001-00 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 4,117.65 0.00 Canceled 2017-12-01 3-2018-AF / Finance Analy lementation Support 1 4 3 st I PRDP-IS-R001-FIN-002-00 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 0-2018-AF / Project Develo IBRD / 88160 Post Direct Selection Direct 2,941.18 0.00 Canceled 2017-12-01 lementation Support 1 4 3 pment Associate PRDP-IS-R003-ADM-001-0 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 2,117.65 0.00 Canceled 2017-12-01 00-2018-AF / Cashier Clerk lementation Support 1 4 3 PRDP-IS-R001-PROC-001- Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 4,705.88 0.00 Canceled 2017-12-01 000-2018-AF / Procuremen lementation Support 1 4 3 t Officer PRDP-IS-R003-ADM-002-0 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 2,117.65 0.00 Canceled 2017-12-01 00-2018-AF / Administrativ lementation Support 1 4 3 e Staff PRDP-IS-R003-ADM-003-0 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 2,823.53 0.00 Canceled 2017-12-01 00-2018-AF / Chaffeur lementation Support 1 4 3 PRDP-IS-R001-PROC-002- Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 001-2018-AF / Project Dev IBRD / 88160 Post Direct Selection Direct 2,941.18 0.00 Canceled 2017-12-01 lementation Support 1 4 3 elopment Associate PRDP-IS-R003-OFP-002-00 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 2,823.53 0.00 Canceled 2017-12-01 0-2018-AF / Chaffeur lementation Support 1 4 3 PRDP-IS-R001-PROC-002- Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 002-2018-AF / Project Dev IBRD / 88160 Post Direct Selection Direct 2,941.18 0.00 Canceled 2017-12-01 lementation Support 1 4 3 elopment Associate PRDP-IS-R003-ADM-004-0 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 2,117.65 0.00 Canceled 2017-12-01 00-2018-AF / Utility lementation Support 1 4 3 PRDP-IS-R001-PROC-002- Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 003-2018-AF / Project Dev IBRD / 88160 Post Direct Selection Direct 2,941.18 0.00 Canceled 2017-12-01 lementation Support 1 4 3 elopment Associate PRDP-IS-R001-INF-001-00 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 4,117.65 0.00 Canceled 2017-12-01 0-2018-AF / Writer lementation Support 1 4 3 PRDP-IS-R001-INF-002-00 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 3,529.41 0.00 Canceled 2017-12-01 0-2018-AF / Videographer lementation Support 1 4 3 PRDP-IS-R001-SES-001-00 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 0-2018-AF / Environmental IBRD / 88160 Post Direct Selection Direct 5,294.12 0.00 Canceled 2017-12-01 lementation Support 1 4 3 Safeguard Specialist Page 4 PRDP-IS-R001-SES-002-00 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 0-2018-AF / Project Develo IBRD / 88160 Post Direct Selection Direct 2,941.18 0.00 Canceled 2017-12-01 lementation Support 1 4 3 pment Associate PRDP-IS-R001-SES-002-00 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 1-2018-AF / Project Develo IBRD / 88160 Post Direct Selection Direct 2,941.18 0.00 Canceled 2017-12-01 lementation Support 1 4 3 pment Associate PRDP-IS-R001-MAE-001-0 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 3,764.71 0.00 Canceled 2017-12-01 01-2018-AF / M&E Officer lementation Support 1 4 3 PRDP-IS-R001-MAE-002-0 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 01-2018-AF / Project Devel IBRD / 88160 Post Direct Selection Direct 588.24 0.00 Canceled 2017-12-01 lementation Support 1 4 3 opment Associate PRDP-IS-R001-MAE-002-0 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 02-2018-AF / Project Devel IBRD / 88160 Post Direct Selection Direct 2,941.18 0.00 Canceled 2017-12-01 lementation Support 1 4 3 opment Associate PRDP-IS-R001-GGU-001-0 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 4,352.94 0.00 Canceled 2017-12-01 00-2018-AF / GIS Data Offi lementation Support 1 4 3 cer PRDP-IS-R001-GGU-002-0 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 01-2018-AF / Project Devel IBRD / 88160 Post Direct Selection Direct 2,941.18 0.00 Canceled 2017-12-01 lementation Support 1 4 3 opment Associate PRDP-IS-R001-OPD-001-0 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 00-2018-AF / Project Devel IBRD / 88160 Post Direct Selection Direct 2,941.18 0.00 Canceled 2017-12-01 lementation Support 1 4 3 opment Associate PRDP-IS-R001-DPD-001-0 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 00-2018-AF / Project Devel IBRD / 88160 Post Direct Selection Direct 2,941.18 0.00 Canceled 2017-12-01 lementation Support 1 4 3 opment Associate PRDP-IS-R001-IB-001-001- Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 4,705.88 0.00 Canceled 2017-12-01 2018-AF / Rural Infrastruct lementation Support 1 4 3 ure Engineer PRDP-IS-R001-IB-001-002- Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 4,705.88 0.00 Canceled 2017-12-01 2018-AF / Rural Infrastruct lementation Support 1 4 3 ure Engineer PRDP-IS-R001-IB-001-003- Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 4,705.88 0.00 Canceled 2017-12-01 2018-AF / Rural Infrastruct lementation Support 1 4 3 ure Engineer PRDP-IS-R001-IB-001-004- Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 4,705.88 0.00 Canceled 2017-12-01 2018-AF / Rural Infrastruct lementation Support 1 4 3 ure Engineer PRDP-IS-R001-IB-001-005- Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 4,705.88 0.00 Canceled 2017-12-01 2018-AF / Rural Infrastruct lementation Support 1 4 3 ure Engineer PRDP-IS-R001-IB-001-006- Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 4,705.88 0.00 Canceled 2017-12-01 2018-AF / Rural Infrastruct lementation Support 1 4 3 ure Engineer PRDP-IS-R001-IB-002-000- Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 2,941.18 0.00 Canceled 2017-12-01 2018-AF / Project Develop lementation Support 1 4 3 ment Associate PRDP-IS-R001-ADM-001-0 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 1,058.82 0.00 Canceled 2017-12-01 00-2018-AF / Cash Clerk lementation Support 1 4 3 PRDP-IS-R001-ADM-002-0 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 2,352.94 0.00 Canceled 2017-12-01 01-2018-AF / Chauffeur lementation Support 1 4 3 PRDP-IS-R001-ADM-002-0 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 2,352.94 0.00 Canceled 2017-12-01 02-2018-AF / Chauffeur lementation Support 1 4 3 PRDP-IS-R001-ADM-002-0 Component 4: Project Imp 2017-12-1 2018-02-1 2018-08-1 IBRD / 88160 Post Direct Selection Direct 2,352.94 0.00 Canceled 2017-12-01 03-2018-AF / Chauffeur lementation Support 1 4 3 PRDP-IS-NLU-002-DPD-00 Component 4: Project Imp Individual Cons Pending Imple 2019-04-1 2019-05-0 2019-06-0 2019-12-0 IBRD / 88160 Post Direct 11,207.55 0.00 2019-04-01 1-2019-AF / Economist lementation Support ultant Selection mentation 1 2 6 3 PRDP-IS-NLU-004-DPD-00 Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 IBRD / 88160 Post Open 6,113.21 0.00 2019-04-01 3-2019-AF / Administrative lementation Support ultant Selection mentation 0 0 5 1 Officer II PRDP-IS-NLU-005-DPD-00 Component 4: Project Imp Individual Cons Pending Imple 2019-04-1 2019-05-0 2019-06-0 2019-12-0 IBRD / 88160 Post Direct 5,094.34 0.00 2019-04-01 4-2019-AF / Administrative lementation Support ultant Selection mentation 1 2 6 3 Officer I PRDP-IS-NLU-006-DPD-00 Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 IBRD / 88160 Post Direct 12,452.83 0.00 2019-01-03 5-2019-AF / Compliance Of lementation Support ultant Selection mentation 3 3 0 6 ficer PRDP-IS-NLU-007-ACE-00 Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 IBRD / 88160 Post Direct 9,962.26 0.00 2019-01-03 1-2019-AF / Writer lementation Support ultant Selection mentation 3 3 0 6 PRDP-IS-NLU-009-ACE-00 Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 IBRD / 88160 Post Open 7,132.08 0.00 2019-04-01 3-2019-AF / Media Producti lementation Support ultant Selection mentation 0 0 5 1 on Officer PRDP-IS-NLU-010-PRO-00 Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 IBRD / 88160 Post Open 11,773.58 0.00 2019-04-01 1-2019-AF / Procurement lementation Support ultant Selection mentation 0 0 5 1 Unit Head PRDP-IS-NLU-011-PRO-00 Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 IBRD / 88160 Post Direct 11,207.55 0.00 2019-01-03 2-2019-AF / Procurement lementation Support ultant Selection mentation 3 3 0 6 Officer PRDP-IS-NLU-012-PRO-00 Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 IBRD / 88160 Post Open 9,169.81 0.00 2019-04-01 3-2019-AF / Procurement lementation Support ultant Selection mentation 0 0 5 1 Officer PRDP-IS-NLU-013-PRO-00 Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 4-2019-AF / Project Develo IBRD / 88160 Post Direct 1,358.49 0.00 2019-01-03 lementation Support ultant Selection mentation 3 3 0 6 pment Associate PRDP-IS-NLU-014-PRO-00 Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 5-2019-AF / Project Develo IBRD / 88160 Post Direct 1,358.49 0.00 2019-01-03 lementation Support ultant Selection mentation 3 3 0 6 pment Associate PRDP-IS-NLU-015-PRO-00 Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 IBRD / 88160 Post Open 8,150.94 0.00 2019-04-01 6-2019-AF / Associate Proc lementation Support ultant Selection mentation 0 0 5 1 urement Officer PRDP-IS-NLU-016-MNE-00 Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 IBRD / 88160 Post Open 10,188.68 0.00 2019-04-01 1-2019-AF / M&E Specialist lementation Support ultant Selection mentation 0 0 5 1 PRDP-IS-NLU-017-MNE-00 Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 IBRD / 88160 Post Direct 11,207.55 0.00 2019-01-03 2-2019-AF / M&E Officer lementation Support ultant Selection mentation 3 3 0 6 PRDP-IS-NLU-018-MNE-00 Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 IBRD / 88160 Post Open 9,169.81 0.00 2019-04-01 3-2019-AF / M&E Officer lementation Support ultant Selection mentation 0 0 5 1 PRDP-IS-NLU-019-FIN-001- Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 IBRD / 88160 Post Open 10,188.68 0.00 2019-04-01 2019-AF / Financial Analys lementation Support ultant Selection mentation 0 0 5 1 t III PRDP-IS-NLU-020-FIN-002- Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 IBRD / 88160 Post Open 9,169.81 0.00 2019-04-01 2019-AF / Financial Analys lementation Support ultant Selection mentation 0 0 5 1 t II PRDP-IS-NLU-021-FIN-003- Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 IBRD / 88160 Post Open 9,169.81 0.00 2019-04-01 2019-AF / Financial Analys lementation Support ultant Selection mentation 0 0 5 1 t II PRDP-IS-NLU-022-FIN-004- Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 IBRD / 88160 Post Direct 2,037.74 0.00 2019-01-03 2019-AF / Financial Analys lementation Support ultant Selection mentation 3 3 0 6 t II PRDP-IS-NLU-023-ACT-001 Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 -2019-AF / Financial Analy IBRD / 88160 Post Open 9,169.81 0.00 2019-04-01 lementation Support ultant Selection mentation 0 0 5 1 st II (Accountant) PRDP-IS-NLU-024-ACT-002 Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 IBRD / 88160 Post Direct 1,811.32 0.00 2019-01-03 -2019-AF / Financial Analy lementation Support ultant Selection mentation 3 3 0 6 st I PRDP-IS-NLU-025-ACT-003 Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 IBRD / 88160 Post Direct 1,811.32 0.00 2019-01-03 -2019-AF / Financial Analy lementation Support ultant Selection mentation 3 3 0 6 st I PRDP-IS-NLU-026-ACT-004 Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 IBRD / 88160 Post Direct 9,962.26 0.00 2019-01-03 -2019-AF / Financial Analy lementation Support ultant Selection mentation 3 3 0 6 st I PRDP-IS-NLU-027-BUD-00 Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 IBRD / 88160 Post Direct 9,962.26 0.00 2019-01-03 1-2019-AF / Budget Analys lementation Support ultant Selection mentation 3 3 0 6 t PRDP-IS-NLU-028-GGU-00 Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 IBRD / 88160 Post Direct 11,207.55 0.00 2019-01-03 1-2019-AF / GIS Data Offic lementation Support ultant Selection mentation 3 3 0 6 er PRDP-IS-NLU-029-GGU-00 Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 IBRD / 88160 Post Open 9,169.81 0.00 2019-04-01 2-2019-AF / GIS Data Offic lementation Support ultant Selection mentation 0 0 5 1 er PRDP-IS-NLU-030-GGU-00 Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 3-2019-AF / Project Develo IBRD / 88160 Post Direct 1,358.49 0.00 2019-01-03 lementation Support ultant Selection mentation 3 3 0 6 pment Associate PRDP-IS-NLU-031-GGU-00 Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 4-2019-AF / Project Develo IBRD / 88160 Post Direct 1,358.49 0.00 2019-01-03 lementation Support ultant Selection mentation 3 3 0 6 pment Associate PRDP-IS-NLU-032-SES-001 Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 IBRD / 88160 Post Direct 16,188.68 0.00 2019-01-03 -2019-AF / SES Unit Head lementation Support ultant Selection mentation 3 3 0 6 PRDP-IS-NLU-033-SES-002 Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 IBRD / 88160 Post Direct 2,264.15 0.00 2019-01-03 -2019-AF / Social Safeguar lementation Support ultant Selection mentation 3 3 0 6 ds Specialist PRDP-IS-NLU-034-SES-003 Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 -2019-AF / Social and Envir IBRD / 88160 Post Open 10,188.68 0.00 2019-04-01 lementation Support ultant Selection mentation 0 0 5 1 onmental Safeguard Speci alist PRDP-IS-NLU-035-SES-004 Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 -2019-AF / Environmental IBRD / 88160 Post Direct 2,037.74 0.00 2019-01-03 lementation Support ultant Selection mentation 3 3 0 6 Safeguards Officer PRDP-IS-NLU-036-SES-005 Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 -2019-AF / Social and Envir IBRD / 88160 Post Open 9,169.81 0.00 2019-04-01 lementation Support ultant Selection mentation 0 0 5 1 onemental Safeguards Offi cer PRDP-IS-NLU-037-SES-006 Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 -2019-AF / PSO Project De IBRD / 88160 Post Direct 1,358.49 0.00 2019-01-03 lementation Support ultant Selection mentation 3 3 0 6 velopment Associate SES PRDP-IS-NLU-038-SES-007 Component 4: Project Imp Individual Cons Pending Imple 2019-02-2 2019-03-1 2019-04-1 2019-10-1 IBRD / 88160 Post Open 8,150.94 0.00 2019-01-03 -2019-AF / Associate SES lementation Support ultant Selection mentation 1 4 8 5 Officer PRDP-IS-NLU-039-ADM-00 Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 IBRD / 88160 Post Open 7,132.08 0.00 2019-04-01 1-2019-AF / Administrative lementation Support ultant Selection mentation 0 0 5 1 Officer III PRDP-IS-NLU-040-ADM-00 Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 IBRD / 88160 Post Direct 7,471.70 0.00 2019-01-03 2-2019-AF / Administrative lementation Support ultant Selection mentation 3 3 0 6 Officer II PRDP-IS-NLU-049-ISP-011- Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 IBRD / 88160 Post Open 5,094.34 0.00 2019-04-01 2019-AF / Administrative O lementation Support ultant Selection mentation 0 0 5 1 fficer II PRDP-IS-NLU-050-ISP-001- Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 IBRD / 88160 Post Direct 17,433.96 0.00 2019-01-03 2019-AF / ISUPPORT Comp lementation Support ultant Selection mentation 3 3 0 6 onent Head PRDP-IS-NLU-051-IB-001-2 Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 019-AF / Rural Infrastractu IBRD / 88160 Post Direct 12,452.83 0.00 2019-01-03 lementation Support ultant Selection mentation 3 3 0 6 re Specialist -Roads and Br idges PRDP-IS-NLU-052-IB-002-2 Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 IBRD / 88160 Post Direct 11,207.55 0.00 2019-01-03 019-AF / Rural Infrastructu lementation Support ultant Selection mentation 3 3 0 6 re Engineer (RIE) PRDP-IS-NLU-053-IB-003-2 Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 IBRD / 88160 Post Direct 11,207.55 0.00 2019-01-03 019-AF / Rural Infrastructu lementation Support ultant Selection mentation 3 3 0 6 re Engineer (RIE) PRDP-IS-NLU-054-IB-004-2 Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 IBRD / 88160 Post Open 9,169.81 0.00 2019-04-01 019-AF / Rural Infrastructu lementation Support ultant Selection mentation 0 0 5 1 re Engineer (RIE) PRDP-IS-NLU-055-IB-005-2 Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 019-AF / Project Developm IBRD / 88160 Post Direct 7,471.70 0.00 2019-01-03 lementation Support ultant Selection mentation 3 3 0 6 ent Associate (PDA) Page 5 PRDP-IS-NLU-R001-001-O Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 PD-001-2019-AF / Project IBRD / 88160 Post Direct 7,471.70 0.00 2019-01-03 lementation Support ultant Selection mentation 3 3 0 6 Development Associate PRDP-IS-NLU-R001-003-D Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 PD-001-2019-AF / Project IBRD / 88160 Post Open 4,075.47 0.00 2019-04-01 lementation Support ultant Selection mentation 0 0 5 1 Development Associate PRDP-IS-NLU-R001-005-D Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 IBRD / 88160 Post Open 5,094.34 0.00 2019-04-01 PD-003-2019-AF / Admin O lementation Support ultant Selection mentation 0 0 5 1 fficer II PRDP-IS-NLU-R001-006-IB Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 -001-2019-AF / Rural Infras IBRD / 88160 Post Open 4,075.47 0.00 2019-04-01 lementation Support ultant Selection mentation 0 0 5 1 tructure Specialist- Road & Bridges PRDP-IS-NLU-R001-007-IB Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 -002-2019-AF / Rural Infras IBRD / 88160 Post Direct 9,169.81 0.00 2019-01-03 lementation Support ultant Selection mentation 3 3 0 6 tructure Engineer PRDP-IS-NLU-R001-008-IB Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 -003-2019-AF / Rural Infras IBRD / 88160 Post Direct 1,811.32 0.00 2019-01-03 lementation Support ultant Selection mentation 3 3 0 6 tructure Engineer PRDP-IS-NLU-R001-009-IB Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 -004-2019-AF / Rural Infras IBRD / 88160 Post Direct 1,811.32 0.00 2019-01-03 lementation Support ultant Selection mentation 3 3 0 6 tructure Engineer PRDP-IS-NLU-R001-010-IB Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 -005-2019-AF / Rural Infras IBRD / 88160 Post Direct 1,811.32 0.00 2019-01-03 lementation Support ultant Selection mentation 3 3 0 6 tructure Engineer PRDP-IS-NLU-R001-011-IB Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 -006-2019-AF / Rural Infras IBRD / 88160 Post Direct 1,811.32 0.00 2019-01-03 lementation Support ultant Selection mentation 3 3 0 6 tructure Engineer PRDP-IS-NLU-R001-012-IB Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 -007-2019-AF / Rural Infras IBRD / 88160 Post Open 1,811.32 0.00 2019-04-01 lementation Support ultant Selection mentation 0 0 5 1 tructure Engineer PRDP-IS-NLU-R001-013-IB Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 -008-2019-AF / Rural Infras IBRD / 88160 Post Open 7,698.11 0.00 2019-04-01 lementation Support ultant Selection mentation 0 0 5 1 tructure Engineer PRDP-IS-NLU-R001-014-IB Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 -009-2019-AF / Rural Infras IBRD / 88160 Post Open 7,698.11 0.00 2019-04-01 lementation Support ultant Selection mentation 0 0 5 1 tructure Engineer PRDP-IS-NLU-R001-015-IB Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 -010-2019-AF / Rural Infras IBRD / 88160 Post Open 7,698.11 0.00 2019-04-01 lementation Support ultant Selection mentation 0 0 5 1 tructure Engineer PRDP-IS-NLU-R001-016-IB Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 -011-2019-AF / Project Dev IBRD / 88160 Post Direct 7,698.11 0.00 2019-01-03 lementation Support ultant Selection mentation 3 3 0 6 elopment Associate PRDP-IS-NLU-R001-017-IB Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 -012-2019-AF / Project Dev IBRD / 88160 Post Open 566.04 0.00 2019-04-01 lementation Support ultant Selection mentation 0 0 5 1 elopment Associate PRDP-IS-NLU-R001-022-G Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 IBRD / 88160 Post Open 1,811.32 0.00 2019-04-01 GU-002-2019-AF / GIS Offi lementation Support ultant Selection mentation 0 0 5 1 cer PRDP-IS-NLU-R001-023-G Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 IBRD / 88160 Post Direct 8,150.94 0.00 2019-01-03 GU-003-2019-AF / GIS Offi lementation Support ultant Selection mentation 3 3 0 6 cer PRDP-IS-NLU-R001-024-G Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 GU 004-2019-AF / Project IBRD / 88160 Post Direct 1,132.08 0.00 2019-01-03 lementation Support ultant Selection mentation 3 3 0 6 Development Associate PRDP-IS-NLU-R001-025-PR Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 IBRD / 88160 Post Open 1,811.32 0.00 2019-04-01 O-001-2019-AF / Procurem lementation Support ultant Selection mentation 0 0 5 1 ent Officer PRDP-IS-NLU-R001-026-PR Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 O-002-2019-AF / Project D IBRD / 88160 Post Direct 8,150.94 0.00 2019-01-03 lementation Support ultant Selection mentation 3 3 0 6 evelopment Associate PRDP-IS-NLU-R001-027-PR Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 O-003-2019-AF / Project D IBRD / 88160 Post Direct 1,132.08 0.00 2019-01-03 lementation Support ultant Selection mentation 3 3 0 6 evelopment Associate PRDP-IS-NLU-R001-028-PR Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 O-004-2019-AF / Project D IBRD / 88160 Post Direct 1,132.08 0.00 2019-01-03 lementation Support ultant Selection mentation 3 3 0 6 evelopment Associate PRDP-IS-NLU-R001-029-PR Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 O-005-2019-AF / Project D IBRD / 88160 Post Open 1,132.08 0.00 2019-04-01 lementation Support ultant Selection mentation 0 0 5 1 evelopment Associate PRDP-IS-NLU-R001-030-PR Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 O-006-2019-AF / Associate IBRD / 88160 Post Direct 7,132.08 0.00 2019-01-03 lementation Support ultant Selection mentation 3 3 0 6 Procurement Officer PRDP-IS-NLU-R001-031-M Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 IBRD / 88160 Post Open 1,811.32 0.00 2019-04-01 NE-001-2019-AF / M&E Offi lementation Support ultant Selection mentation 0 0 5 1 cer PRDP-IS-NLU-R001-032-M Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 IBRD / 88160 Post Open 8,150.94 0.00 2019-04-01 NE-002-2019-AF / M&E Offi lementation Support ultant Selection mentation 0 0 5 1 cer PRDP-IS-NLU-R001-032-M Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 IBRD / 88160 Post Open 1,132.08 0.00 2019-04-01 NE-003-2019-AF / PDA - M lementation Support ultant Selection mentation 0 0 5 1 &E PRDP-IS-NLU-R001-033-M Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 IBRD / 88160 Post Open 7,132.08 0.00 2019-04-01 NE-004-2019-AF / Associat lementation Support ultant Selection mentation 0 0 5 1 e M&E Officer PRDP-IS-NLU-R001-034-SE Component 4: Project Imp Individual Cons Pending Imple 2018-01-1 2018-02-0 2018-03-0 2018-09-0 S-001-2019-AF / Environm IBRD / 88160 Post Direct 2,037.74 0.00 2018-01-01 lementation Support ultant Selection mentation 1 1 8 4 ental Safeguards Specialis t PRDP-IS-NLU-R001-035-SE Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 IBRD / 88160 Post Open 8,150.94 0.00 2019-04-01 S-002-2019-AF / SES Office lementation Support ultant Selection mentation 0 0 5 1 r PRDP-IS-NLU-R001-036-SE Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 IBRD / 88160 Post Open 7,132.08 0.00 2019-04-01 S-003-2019-AF / Associate lementation Support ultant Selection mentation 0 0 5 1 SES Officer PRDP-IS-NLU-R001-037-SE Component 4: Project Imp Individual Cons Pending Imple 2018-01-1 2018-02-0 2018-03-0 2018-09-0 S-004-2019-AF / Project De IBRD / 88160 Post Direct 1,132.08 0.00 2018-01-01 lementation Support ultant Selection mentation 1 1 8 4 velopment Associate PRDP-IS-NLU-R001-038-SE Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 S-005-2019-AF / Project De IBRD / 88160 Post Direct 1,132.08 0.00 2019-01-03 lementation Support ultant Selection mentation 3 3 0 6 velopment Associate PRDP-IS-NLU-R001-039-A Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 IBRD / 88160 Post Direct 1,584.91 0.00 2019-01-03 CE-001-2019-AF / Writer lementation Support ultant Selection mentation 3 3 0 6 PRDP-IS-NLU-R001-040-A Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 IBRD / 88160 Post Open 7,132.08 0.00 2019-04-01 CE-002-2019-AF / Writer lementation Support ultant Selection mentation 0 0 5 1 PRDP-IS-NLU-R001-042-FI Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 IBRD / 88160 Post Open 1,584.91 0.00 2019-04-01 N-001-2019-AF / Finance A lementation Support ultant Selection mentation 0 0 5 1 nalyst I PRDP-IS-NLU-R001-043-A Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 IBRD / 88160 Post Open 7,132.08 0.00 2019-04-01 CT-001-2019-AF / Finance lementation Support ultant Selection mentation 0 0 5 1 Analyst I PRDP-IS-NLU-R001-044-A Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 CT-002-2019-AF / Project IBRD / 88160 Post Open 1,132.08 0.00 2019-04-01 lementation Support ultant Selection mentation 0 0 5 1 Development Associate PRDP-IS-NLU-R002-003-D Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 IBRD / 88160 Post Direct 3,056.60 0.00 2019-01-03 PD-003-2019-AF / Complia lementation Support ultant Selection mentation 3 3 0 6 nce Officer PRDP-IS-NLU-R002-004-D Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 IBRD / 88160 Post Open 5,094.34 0.00 2019-04-01 PD-004-2019-AF / Administ lementation Support ultant Selection mentation 0 0 5 1 rative Officer II PRDP-IS-NLU-R002-005-D Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 IBRD / 88160 Post Direct 1,698.11 0.00 2019-01-03 PD-005-2019-AF / Administ lementation Support ultant Selection mentation 3 3 0 6 rative Officer I PRDP-IS-NLU-R002-006-D Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 IBRD / 88160 Post Open 8,150.94 0.00 2019-04-01 PD-006-2019-AF / Economi lementation Support ultant Selection mentation 0 0 5 1 st PRDP-IS-NLU-R002-007-IB Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 -001-2019-AF / Road and B IBRD / 88160 Post Open 9,169.81 0.00 2019-04-01 lementation Support ultant Selection mentation 0 0 5 1 ridges Specialist PRDP-IS-NLU-R002-008-IB Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 -002-2019-AF / Rural Infras IBRD / 88160 Post Direct 2,716.98 0.00 2019-01-03 lementation Support ultant Selection mentation 3 3 0 6 tructure Engineer PRDP-IS-NLU-R002-009-IB Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 -003-2019-AF / Rural Infras IBRD / 88160 Post Direct 2,716.98 0.00 2019-01-03 lementation Support ultant Selection mentation 3 3 0 6 tructure Engineer PRDP-IS-NLU-R002-010-IB Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 -004-2019-AF / Rural Infras IBRD / 88160 Post Direct 2,716.98 0.00 2019-01-03 lementation Support ultant Selection mentation 3 3 0 6 tructure Engineer PRDP-IS-NLU-R002-011-IB Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 -005-2019-AF / Rural Infras IBRD / 88160 Post Direct 2,716.98 0.00 2019-01-03 lementation Support ultant Selection mentation 3 3 0 6 tructure Engineer PRDP-IS-NLU-R002-012-IB Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 -006-2019-AF / Rural Infras IBRD / 88160 Post Direct 2,716.98 0.00 2019-01-03 lementation Support ultant Selection mentation 3 3 0 6 tructure Engineer PRDP-IS-NLU-R002-013-IB Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 -007-2019-AF / Rural Infras IBRD / 88160 Post Direct 2,716.98 0.00 2019-01-03 lementation Support ultant Selection mentation 3 3 0 6 tructure Engineer PRDP-IS-NLU-R002-014-IB Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 -008-2019-AF / Rural Infras IBRD / 88160 Post Open 8,150.94 0.00 2019-04-01 lementation Support ultant Selection mentation 0 0 5 1 tructure Engineer PRDP-IS-NLU-R002-015-IB Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 -009-2019-AF / Rural Infras IBRD / 88160 Post Open 8,150.94 0.00 2019-04-01 lementation Support ultant Selection mentation 0 0 5 1 tructure Engineer PRDP-IS-NLU-R002-016-IB Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 -010-2019-AF / Project Dev IBRD / 88160 Post Direct 1,698.11 0.00 2019-01-03 lementation Support ultant Selection mentation 3 3 0 6 elopment Associate PRDP-IS-NLU-R002-017-IB Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 -011-2019-AF / Project Dev IBRD / 88160 Post Open 5,094.34 0.00 2019-04-01 lementation Support ultant Selection mentation 0 0 5 1 elopment Associate PRDP-IS-NLU-R002-019-G Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 IBRD / 88160 Post Direct 3,056.60 0.00 2019-01-03 GU-001-2019-AF / GIS Spe lementation Support ultant Selection mentation 3 3 0 6 cialist PRDP-IS-NLU-R002-020-G Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 IBRD / 88160 Post Direct 2,716.98 0.00 2019-01-03 GU-002-2019-AF / GIS Offi lementation Support ultant Selection mentation 3 3 0 6 cer PRDP-IS-NLU-R002-021-G Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 IBRD / 88160 Post Open 8,150.94 0.00 2019-04-01 GU-003-2019-AF / GIS Offi lementation Support ultant Selection mentation 0 0 5 1 cer PRDP-IS-NLU-R002-022-G Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 GU-004-2019-AF / Project IBRD / 88160 Post Direct 1,698.11 0.00 2019-01-03 lementation Support ultant Selection mentation 3 3 0 6 Development Associate PRDP-IS-NLU-R002-023-G Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 IBRD / 88160 Post Direct 2,716.98 0.00 2019-01-03 GU-005-2019-AF / Procure lementation Support ultant Selection mentation 3 3 0 6 ment Officer PRDP-IS-NLU-R002-024-PR Component 4: Project Imp Individual Cons Pending Imple 2019-02-2 2019-03-1 2019-04-1 2019-10-1 IBRD / 88160 Post Open 8,150.94 0.00 2019-01-03 O-001-2019-AF / Procurem lementation Support ultant Selection mentation 1 4 8 5 ent Officer Page 6 PRDP-IS-NLU-R002-025-PR Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 O-006-2019-AF / Associate IBRD / 88160 Post Open 7,132.08 0.00 2019-04-01 lementation Support ultant Selection mentation 0 0 5 1 Procurement Officer PRDP-IS-NLU-R002-026-PR Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 O-007-2019-AF / Project D IBRD / 88160 Post Direct 1,698.11 0.00 2019-01-03 lementation Support ultant Selection mentation 3 3 0 6 evelopment Associate PRDP-IS-NLU-R002-027-M Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 NE-001-2019-AF / Monitori IBRD / 88160 Post Direct 2,716.98 0.00 2019-01-03 lementation Support ultant Selection mentation 3 3 0 6 ng & Evaluation Officer PRDP-IS-NLU-R002-028-M Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 NE-002-2019-AF / Monitori IBRD / 88160 Post Open 8,150.94 0.00 2019-04-01 lementation Support ultant Selection mentation 0 0 5 1 ng & Evaluation Officer PRDP-IS-NLU-R002-029-M Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 IBRD / 88160 Post Open 7,132.08 0.00 2019-04-01 NE-003-2019-AF / Associat lementation Support ultant Selection mentation 0 0 5 1 e M & E Officer PRDP-IS-NLU-R002-030-M Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 NE-004-2019-AF / Project IBRD / 88160 Post Direct 1,698.11 0.00 2019-01-03 lementation Support ultant Selection mentation 3 3 0 6 Development Associate PRDP-IS-NLU-R002-031-SE Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 S-001-2019-AF / Social Saf IBRD / 88160 Post Direct 3,056.60 0.00 2019-01-03 lementation Support ultant Selection mentation 3 3 0 6 eguard Specialist PRDP-IS-NLU-R002-032-SE Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 S-002-2019-AF / Social and IBRD / 88160 Post Direct 2,716.98 0.00 2019-01-03 lementation Support ultant Selection mentation 3 3 0 6 Environment Safeguards O fficer PRDP-IS-NLU-R002-033-SE Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 S-003-2019-AF / Social and IBRD / 88160 Post Open 8,150.94 0.00 2019-04-01 lementation Support ultant Selection mentation 0 0 5 1 Environment Safeguards O fficer PRDP-IS-NLU-R002-034-SE Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 IBRD / 88160 Post Open 7,132.08 0.00 2019-04-01 S-004-2019-AF / Associate lementation Support ultant Selection mentation 0 0 5 1 SES Officer PRDP-IS-NLU-R002-035-SE Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 S-005-2019-AF / Project De IBRD / 88160 Post Direct 1,698.11 0.00 2019-01-03 lementation Support ultant Selection mentation 3 3 0 6 velopment Associate PRDP-IS-NLU-R002-036-A Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 CE-001-2019-AF / Informat IBRD / 88160 Post Direct 3,056.60 0.00 2019-01-03 lementation Support ultant Selection mentation 3 3 0 6 ion & Advocacy Specialist PRDP-IS-NLU-R002-038-A Component 4: Project Imp Individual Cons Pending Imple 2019-02-2 2019-03-1 2019-04-1 2019-10-1 IBRD / 88160 Post Open 7,132.08 0.00 2019-01-03 CE-003-2019-AF / Writer lementation Support ultant Selection mentation 1 4 8 5 PRDP-IS-NLU-R002-039-A Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 CE-004-2019-AF / Photogr IBRD / 88160 Post Direct 2,037.74 0.00 2019-01-03 lementation Support ultant Selection mentation 3 3 0 6 apher/Videographer PRDP-IS-NLU-R002-040-A Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 CE-005-2019-AF / Project IBRD / 88160 Post Direct 1,698.11 0.00 2019-01-03 lementation Support ultant Selection mentation 3 3 0 6 Development Associate PRDP-IS-NLU-R002-041-FI Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 IBRD / 88160 Post Open 2,377.36 0.00 2019-04-01 N-001-2019-AF / Finance A lementation Support ultant Selection mentation 0 0 5 1 nalyst I PRDP-IS-NLU-R002-042-FI Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 IBRD / 88160 Post Open 2,377.36 0.00 2019-04-01 N-002-2019-AF / Finance A lementation Support ultant Selection mentation 0 0 5 1 nalyst I PRDP-IS-NLU-R002-043-FI Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 IBRD / 88160 Post Open 7,132.08 0.00 2019-04-01 N-003-2019-AF / Finance A lementation Support ultant Selection mentation 0 0 5 1 nalyst I PRDP-IS-NLU-R002-044-FI Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 N-004-2019-AF / Project D IBRD / 88160 Post Direct 1,698.11 0.00 2019-01-03 lementation Support ultant Selection mentation 3 3 0 6 evelopment Associate PRDP-IS-NLU-R002-045-FI Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 N-005-2019-AF / Project D IBRD / 88160 Post Direct 1,698.11 0.00 2019-01-03 lementation Support ultant Selection mentation 3 3 0 6 evelopment Associate PRDP-IS-NLU-R002-046-A Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 IBRD / 88160 Post Open 7,132.08 0.00 2019-04-01 CT-001-2019-AF / Finance lementation Support ultant Selection mentation 0 0 5 1 Analyst 1 PRDP-IS-NLU-R002-047-B Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 IBRD / 88160 Post Open 7,132.08 0.00 2019-04-01 UD-001-2019-AF / Budget lementation Support ultant Selection mentation 0 0 5 1 Analyst 1 PRDP-IS-NLU-R003-001-A Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 IBRD / 88160 Post Open 5,094.34 0.00 2019-04-01 DM-006-2019-AF / Adminis lementation Support ultant Selection mentation 0 0 5 1 trative Officer II PRDP-IS-NLU-R003-005-A Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 IBRD / 88160 Post Open 8,150.94 0.00 2019-04-01 DM-010-2019-AF / Econom lementation Support ultant Selection mentation 0 0 5 1 ist PRDP-IS-NLU-R003-012-IS Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 P-001-2019-AF / Project De IBRD / 88160 Post Direct 1,698.11 0.00 2019-01-03 lementation Support ultant Selection mentation 3 3 0 6 velopment Associate PRDP-IS-NLU-R003-013-IS Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 P-002-2019-AF / Project De IBRD / 88160 Post Direct 1,698.11 0.00 2019-01-03 lementation Support ultant Selection mentation 3 3 0 6 velopment Associate PRDP-IS-NLU-R003-014-IS Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 P-003-2019-AF / Project De IBRD / 88160 Post Direct 1,698.11 0.00 2019-01-03 lementation Support ultant Selection mentation 3 3 0 6 velopment Associate PRDP-IS-NLU-R003-015-A Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 IBRD / 88160 Post Open 7,132.08 0.00 2019-04-01 CE-001-2019-AF / Writer lementation Support ultant Selection mentation 0 0 5 1 PRDP-IS-NLU-R003-016-A Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 IBRD / 88160 Post Direct 1,698.11 0.00 2019-01-03 CE-002-2019-AF / PDA -Inf lementation Support ultant Selection mentation 3 3 0 6 oACE PRDP-IS-NLU-R003-017-FI Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 IBRD / 88160 Post Direct 9,509.43 0.00 2019-01-03 N-001-2019-AF / Finance A lementation Support ultant Selection mentation 3 3 0 6 nalyst 1 PRDP-IS-NLU-R003-018-A Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 IBRD / 88160 Post Open 3,566.04 0.00 2019-04-01 CT-001-2019-AF / Finance lementation Support ultant Selection mentation 0 0 5 1 Analyst 1 PRDP-IS-NLU-R003-019-A Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 IBRD / 88160 Post Open 3,566.04 0.00 2019-04-01 CT-002-2019-AF / Finance lementation Support ultant Selection mentation 0 0 5 1 Analyst 1 PRDP-IS-NLU-R003-020-B Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 IBRD / 88160 Post Open 7,132.08 0.00 2019-04-01 UD-001-2019-AF / Budget lementation Support ultant Selection mentation 0 0 5 1 Analyst PRDP-IS-NLU-R003-021-PR Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 IBRD / 88160 Post Direct 10,867.92 0.00 2019-01-03 O-001-2019-AF / Procurem lementation Support ultant Selection mentation 3 3 0 6 ent Officer PRDP-IS-NLU-R003-022-PR Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 O-002-2019-AF / Associate IBRD / 88160 Post Open 7,132.08 0.00 2019-04-01 lementation Support ultant Selection mentation 0 0 5 1 Procurement Officer PRDP-IS-NLU-R003-023-PR Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 O-003-2019-AF / Project D IBRD / 88160 Post Direct 1,698.11 0.00 2019-01-03 lementation Support ultant Selection mentation 3 3 0 6 evelopment Associate PRDP-IS-NLU-R003-024-PR Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 O-004-2019-AF / Project D IBRD / 88160 Post Direct 1,698.11 0.00 2019-01-03 lementation Support ultant Selection mentation 3 3 0 6 evelopment Associate PRDP-IS-NLU-R003-025-M Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 IBRD / 88160 Post Open 8,150.94 0.00 2019-04-01 NE-001-2019-AF / M&E Offi lementation Support ultant Selection mentation 0 0 5 1 cer PRDP-IS-NLU-R003-026-M Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 IBRD / 88160 Post Open 7,132.08 0.00 2019-04-01 NE-002-2019-AF / Associat lementation Support ultant Selection mentation 0 0 5 1 e M&E Officer PRDP-IS-NLU-R003-027-M Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 NE-003-2019-AF / Project IBRD / 88160 Post Direct 1,698.11 0.00 2019-01-03 lementation Support ultant Selection mentation 3 3 0 6 Development Associate PRDP-IS-NLU-R003-028-M Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 NE-004-2019-AF / Project IBRD / 88160 Post Direct 1,698.11 0.00 2019-01-03 lementation Support ultant Selection mentation 3 3 0 6 Development Associate PRDP-IS-NLU-R003-029-SE Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 IBRD / 88160 Post Direct 2,716.98 0.00 2019-01-03 S-001-2019-AF / Social Saf lementation Support ultant Selection mentation 3 3 0 6 eguard Officer PRDP-IS-NLU-R003-030-SE Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 S-002-2019-AF / Social and IBRD / 88160 Post Open 8,150.94 0.00 2019-04-01 lementation Support ultant Selection mentation 0 0 5 1 Environmental Safeguard Officer PRDP-IS-NLU-R003-031-SE Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 IBRD / 88160 Post Open 7,132.08 0.00 2019-04-01 S-003-2019-AF / Associate lementation Support ultant Selection mentation 0 0 5 1 SES Officer PRDP-IS-NLU-R003-032-SE Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 S-004-2019-AF / Project De IBRD / 88160 Post Direct 1,698.11 0.00 2019-01-03 lementation Support ultant Selection mentation 3 3 0 6 velopment Associate PRDP-IS-NLU-R003-033-SE Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 S-005-2019-AF / Project De IBRD / 88160 Post Direct 1,698.11 0.00 2019-01-03 lementation Support ultant Selection mentation 3 3 0 6 velopment Associate PRDP-IS-NLU-R003-034-G Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 IBRD / 88160 Post Direct 10,867.92 0.00 2019-01-03 GU-001-2019-AF / GIS Offi lementation Support ultant Selection mentation 3 3 0 6 cer PRDP-IS-NLU-R003-035-G Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 GU-002-2019-AF / Project IBRD / 88160 Post Direct 1,698.11 0.00 2019-01-03 lementation Support ultant Selection mentation 3 3 0 6 Development Associate PRDP-IS-NLU-R003-036-IB Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 -001-2019-AF / Project Dev IBRD / 88160 Post Direct 1,698.11 0.00 2019-01-03 lementation Support ultant Selection mentation 3 3 0 6 elopment Associate PRDP-IS-NLU-R003-037-IB Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 -002-2019-AF / Rural Infras IBRD / 88160 Post Direct 2,716.98 0.00 2019-01-03 lementation Support ultant Selection mentation 3 3 0 6 tructure Engineer PRDP-IS-NLU-R003-038-IB Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 -003-2019-AF / Rural Infras IBRD / 88160 Post Direct 2,716.98 0.00 2019-01-03 lementation Support ultant Selection mentation 3 3 0 6 tructure Engineer PRDP-IS-NLU-R003-039-IB Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 -004-2019-AF / Rural Infras IBRD / 88160 Post Direct 2,716.98 0.00 2019-01-03 lementation Support ultant Selection mentation 3 3 0 6 tructure Engineer PRDP-IS-NLU-R003-040-IB Component 4: Project Imp Individual Cons Pending Imple 2019-02-2 2019-03-1 2019-04-1 2019-10-1 -005-2019-AF / Rural Infras IBRD / 88160 Post Open 9,962.26 0.00 2019-01-03 lementation Support ultant Selection mentation 1 4 8 5 tructure Engineer PRDP-IS-NLU-R003-041-IB Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 -006-2019-AF / Rural Infras IBRD / 88160 Post Open 9,962.26 0.00 2019-04-01 lementation Support ultant Selection mentation 0 0 5 1 tructure Engineer PRDP-IS-NLU-R003-042-IB Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 -007-2019-AF / Rural Infras IBRD / 88160 Post Open 9,962.26 0.00 2019-04-01 lementation Support ultant Selection mentation 0 0 5 1 tructure Engineer PRDP-IS-NLU-R003-043-IB Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 -008-2019-AF / Rural Infras IBRD / 88160 Post Direct 8,150.94 0.00 2019-01-03 lementation Support ultant Selection mentation 3 3 0 6 tructure Engineer PRDP-IS-NLU-R003-044-IB Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 -009-2019-AF / Rural Infras IBRD / 88160 Post Direct 8,150.94 0.00 2019-01-03 lementation Support ultant Selection mentation 3 3 0 6 tructure Engineer PRDP-IS-NLU-R003-045-IB Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 -010-2019-AF / Project Dev IBRD / 88160 Post Direct 6,792.45 0.00 2019-01-03 lementation Support ultant Selection mentation 3 3 0 6 elopment Associate PRDP-IS-NLU-RCAR-002-D Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 IBRD / 88160 Post Open 8,150.94 0.00 2019-04-01 PD-002-2019-AF / Economi lementation Support ultant Selection mentation 0 0 5 1 st Page 7 PRDP-IS-NLU-RCAR-003-IB Component 4: Project Imp Individual Cons Pending Imple 2019-02-2 2019-03-1 2019-04-1 2019-10-1 -001-2019-AF / Roads & Br IBRD / 88160 Post Open 9,169.81 0.00 2019-01-03 lementation Support ultant Selection mentation 1 4 8 5 idges Specialist PRDP-IS-NLU-RCAR-004-IB Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 -002-2019-AF / Rural Infras IBRD / 88160 Post Direct 8,150.94 0.00 2019-01-03 lementation Support ultant Selection mentation 3 3 0 6 tructure Engineer PRDP-IS-NLU-RCAR-005-IB Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 -003-2019-AF / Rural Infras IBRD / 88160 Post Open 8,150.94 0.00 2019-04-01 lementation Support ultant Selection mentation 0 0 5 1 tructure Engineer PRDP-IS-NLU-RCAR-006-IB Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 -004-2019-AF / Rural Infras IBRD / 88160 Post Open 8,150.94 0.00 2019-04-01 lementation Support ultant Selection mentation 0 0 5 1 tructure Engineer PRDP-IS-NLU-RCAR-007-IB Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 -005-2019-AF / Rural Infras IBRD / 88160 Post Open 8,150.94 0.00 2019-04-01 lementation Support ultant Selection mentation 0 0 5 1 tructure Engineer PRDP-IS-NLU-RCAR-008-IB Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 -006-2019-AF / Rural Infras IBRD / 88160 Post Open 8,150.94 0.00 2019-04-01 lementation Support ultant Selection mentation 0 0 5 1 tructure Engineer PRDP-IS-NLU-RCAR-009-IB Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 -007-2019-AF / Project Dev IBRD / 88160 Post Open 5,094.34 0.00 2019-04-01 lementation Support ultant Selection mentation 0 0 5 1 elopment Associate PRDP-IS-NLU-RCAR-011-G Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 IBRD / 88160 Post Open 8,150.94 0.00 2019-04-01 GU-001-2019-AF / GIS Offi lementation Support ultant Selection mentation 0 0 5 1 cer PRDP-IS-NLU-RCAR-013-P Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 IBRD / 88160 Post Open 8,150.94 0.00 2019-04-01 RO-001-2019-AF / Procure lementation Support ultant Selection mentation 0 0 5 1 ment Officer PRDP-IS-NLU-RCAR-014-P Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 RO-002-2019-AF / Associat IBRD / 88160 Post Open 7,132.08 0.00 2019-04-01 lementation Support ultant Selection mentation 0 0 5 1 e Procurement Officer PRDP-IS-NLU-RCAR-015-P Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 RO-003-2019-AF / Associat IBRD / 88160 Post Open 7,132.08 0.00 2019-04-01 lementation Support ultant Selection mentation 0 0 5 1 e Procurement Officer PRDP-IS-NLU-RCAR-016-M Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 NE-001-2019-AF / Monitori IBRD / 88160 Post Open 8,150.94 0.00 2019-04-01 lementation Support ultant Selection mentation 0 0 5 1 ng & Evaluation Officer PRDP-IS-NLU-RCAR-017-M Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 IBRD / 88160 Post Open 7,132.08 0.00 2019-04-01 NE-002-2019-AF / Associat lementation Support ultant Selection mentation 0 0 5 1 e M & E Officer PRDP-IS-NLU-RCAR-018-S Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 ES-001-2019-AF / Social an IBRD / 88160 Post Open 8,150.94 0.00 2019-04-01 lementation Support ultant Selection mentation 0 0 5 1 d Environment Safeguards Officer PRDP-IS-NLU-RCAR-019-S Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 IBRD / 88160 Post Open 7,132.08 0.00 2019-04-01 ES-002-2019-AF / Associat lementation Support ultant Selection mentation 0 0 5 1 e SES Officer PRDP-IS-NLU-RCAR-021-A Component 4: Project Imp Individual Cons Pending Imple 2019-05-2 2019-06-1 2019-07-1 2020-01-1 IBRD / 88160 Post Open 7,132.08 0.00 2019-04-01 CE-001-2019-AF / Writer lementation Support ultant Selection mentation 0 0 5 1 PRDP-IS-NLU-RCAR-023-FI Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 IBRD / 88160 Post Direct 7,132.08 0.00 2019-01-03 N-001-2019-AF / Finance A lementation Support ultant Selection mentation 3 3 0 6 nalyst PRDP-IS-NLU-RCAR-024-A Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 IBRD / 88160 Post Direct 7,132.08 0.00 2019-01-03 CT-001-2019-AF / Finance lementation Support ultant Selection mentation 3 3 0 6 Analyst PRDP-IS-NLU-R002-037-A Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 IBRD / 88160 Post Direct 2,037.74 0.00 2019-01-03 CE-002-2019-AF / Layout A lementation Support ultant Selection mentation 3 3 0 6 rtist PRDP-IS-NLU-R001-041-A Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 CE-003-2019-AF / Videogra IBRD / 88160 Post Direct 1,358.49 0.00 2019-01-03 lementation Support ultant Selection mentation 3 3 0 6 pher/Photographer PRDP-IS-NLU-R002-002-D Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 IBRD / 88160 Post Direct 2,037.74 0.00 2019-01-03 PD-002-2019-AF / Executiv lementation Support ultant Selection mentation 3 3 0 6 e Assistant PRDP-IS-NLU-008-ACE-00 Component 4: Project Imp Individual Cons Pending Imple 2019-01-1 2019-02-0 2019-03-1 2019-09-0 IBRD / 88160 Post Direct 2,377.36 0.00 2019-01-03 2-2019-AF / Graphics/Lay- lementation Support ultant Selection mentation 3 3 0 6 out Artist PRDP-IS-NLU-001-DPD-00 Component 4: Project Imp Individual Cons Pending Imple 2020-01-1 2020-02-0 2020-03-0 2020-09-0 IBRD / 88160 Post Direct 12,705.88 0.00 2020-01-03 1-2020-AF / Economist lementation Support ultant Selection mentation 3 3 9 5 PRDP-IS-NLU-002-DPD-00 Component 4: Project Imp Individual Cons Pending Imple 2020-03-1 2020-04-0 2020-05-0 2020-11-0 IBRD / 88160 Post Direct 14,117.65 0.00 2020-03-01 2-2020-AF / Compliance Of lementation Support ultant Selection mentation 1 1 6 2 ficer PRDP-IS-NLU-003-ACE-00 Component 4: Project Imp Individual Cons Pending Imple 2020-03-1 2020-04-0 2020-05-0 2020-11-0 IBRD / 88160 Post Direct 11,294.12 0.00 2020-03-01 1-2020-AF / Writer lementation Support ultant Selection mentation 1 1 6 2 PRDP-IS-NLU-004-ACE-00 Component 4: Project Imp Individual Cons Pending Imple 2020-03-1 2020-04-0 2020-05-0 2020-11-0 IBRD / 88160 Post Direct 9,882.35 0.00 2020-03-01 2-2019-AF / Media Producti lementation Support ultant Selection mentation 1 1 6 2 on Officer PRDP-IS-NLU-005-PRO-00 Component 4: Project Imp Individual Cons Pending Imple 2020-02-2 2020-03-1 2020-04-1 2020-10-1 IBRD / 88160 Post Open 18,352.94 0.00 2020-01-03 1-2020-AF / Procurement lementation Support ultant Selection mentation 1 3 7 4 Unit Head PRDP-IS-NLU-006-PRO-00 Component 4: Project Imp Individual Cons Pending Imple 2020-01-1 2020-02-0 2020-03-0 2020-09-0 IBRD / 88160 Post Direct 12,705.88 0.00 2020-01-03 2-2020-AF / Procurement lementation Support ultant Selection mentation 3 3 9 5 Officer PRDP-IS-NLU-007-PRO-00 Component 4: Project Imp Individual Cons Pending Imple 2020-01-1 2020-02-0 2020-03-0 2020-09-0 IBRD / 88160 Post Direct 12,705.88 0.00 2020-01-03 3-2020-AF / Procurement lementation Support ultant Selection mentation 3 3 9 5 Officer PRDP-IS-NLU-008-PRO-00 Component 4: Project Imp Individual Cons Pending Imple 2020-03-1 2020-04-0 2020-05-0 2020-11-0 IBRD / 88160 Post Direct 11,294.12 0.00 2020-03-01 4-2020-AF / Associate Proc lementation Support ultant Selection mentation 1 1 6 2 urement Officer PRDP-IS-NLU-009-MNE-00 Component 4: Project Imp Individual Cons Pending Imple 2020-03-1 2020-04-0 2020-05-0 2020-11-0 IBRD / 88160 Post Direct 14,117.65 0.00 2020-03-01 1-2020-AF / M&E Specialist lementation Support ultant Selection mentation 1 1 6 2 PRDP-IS-NLU-010-MNE-00 Component 4: Project Imp Individual Cons Pending Imple 2020-01-1 2020-02-0 2020-03-0 2020-09-0 IBRD / 88160 Post Direct 12,705.88 0.00 2020-01-03 1-2020-AF / M&E Officer lementation Support ultant Selection mentation 3 3 9 5 PRDP-IS-NLU-011-FIN-001- Component 4: Project Imp Individual Cons Pending Imple 2020-03-1 2020-04-0 2020-05-0 2020-11-0 IBRD / 88160 Post Direct 14,117.65 0.00 2020-03-01 2020-AF / Financial Analys lementation Support ultant Selection mentation 1 1 6 2 t III PRDP-IS-NLU-012-FIN-001- Component 4: Project Imp Individual Cons Pending Imple 2020-01-1 2020-02-0 2020-03-0 2020-09-0 IBRD / 88160 Post Direct 12,705.88 0.00 2020-01-03 2020-AF / Financial Analys lementation Support ultant Selection mentation 3 3 9 5 t II PRDP-IS-NLU-013-FIN-001- Component 4: Project Imp Individual Cons Pending Imple 2020-01-1 2020-02-0 2020-03-0 2020-09-0 IBRD / 88160 Post Direct 12,705.88 0.00 2020-01-03 2020-AF / Financial Analys lementation Support ultant Selection mentation 3 3 9 5 t II PRDP-IS-NLU-014-FIN-001- Component 4: Project Imp Individual Cons Pending Imple 2020-03-1 2020-04-0 2020-05-0 2020-11-0 2020-AF / Financial Analys IBRD / 88160 Post Direct 12,705.88 0.00 2020-03-01 lementation Support ultant Selection mentation 1 1 6 2 t II (Accountant) PRDP-IS-NLU-015-FIN-001- Component 4: Project Imp Individual Cons Pending Imple 2020-03-1 2020-04-0 2020-05-0 2020-11-0 IBRD / 88160 Post Direct 11,294.12 0.00 2020-03-01 2020-AF / Financial Analys lementation Support ultant Selection mentation 1 1 6 2 tI PRDP-IS-NLU-016-BUD-00 Component 4: Project Imp Individual Cons Pending Imple 2020-01-1 2020-02-0 2020-03-0 2020-09-0 IBRD / 88160 Post Direct 11,294.12 0.00 2020-01-03 1-2020-AF / Budget Analys lementation Support ultant Selection mentation 3 3 9 5 t PRDP-IS-NLU-017-GGU-00 Component 4: Project Imp Individual Cons Pending Imple 2020-03-1 2020-04-0 2020-05-0 2020-11-0 IBRD / 88160 Post Direct 12,705.88 0.00 2020-03-01 1-2020-AF / GIS Data Offic lementation Support ultant Selection mentation 1 1 6 2 er PRDP-IS-NLU-018-GGU-00 Component 4: Project Imp Individual Cons Pending Imple 2020-03-1 2020-04-0 2020-05-0 2020-11-0 IBRD / 88160 Post Direct 12,705.88 0.00 2020-03-01 2-2020-AF / GIS Data Offic lementation Support ultant Selection mentation 1 1 6 2 er PRDP-IS-NLU-019-SES-001 Component 4: Project Imp Individual Cons Pending Imple 2020-03-1 2020-04-0 2020-05-0 2020-11-0 IBRD / 88160 Post Direct 18,352.94 0.00 2020-03-01 -2020-AF / SES Unit Head lementation Support ultant Selection mentation 1 1 6 2 PRDP-IS-NLU-020-SES-002 Component 4: Project Imp Individual Cons Pending Imple 2020-03-1 2020-04-0 2020-05-0 2020-11-0 -2020-AF / Social and Envir IBRD / 88160 Post Direct 14,117.65 0.00 2020-03-01 lementation Support ultant Selection mentation 1 1 6 2 onmental Safeguard Speci alist PRDP-IS-NLU-021-SES-003 Component 4: Project Imp Individual Cons Pending Imple 2020-01-1 2020-02-0 2020-03-0 2020-09-0 -2020-AF / Social and Envir IBRD / 88160 Post Direct 12,705.88 0.00 2020-01-03 lementation Support ultant Selection mentation 3 3 9 5 onmental Safeguards Offic er PRDP-IS-NLU-022-SES-004 Component 4: Project Imp Individual Cons Pending Imple 2020-03-1 2020-04-0 2020-05-0 2020-11-0 IBRD / 88160 Post Direct 11,294.12 0.00 2020-03-01 -2020-AF / Associate SES lementation Support ultant Selection mentation 1 1 6 2 Officer PRDP-IS-NLU-023-SES-005 Component 4: Project Imp Individual Cons Pending Imple 2020-01-1 2020-02-0 2020-03-0 2020-09-0 IBRD / 88160 Post Direct 9,882.35 0.00 2020-01-03 -2020-AF / Administrative lementation Support ultant Selection mentation 3 3 9 5 Officer III PRDP-IS-NLU-024-ADM-00 Component 4: Project Imp Individual Cons Pending Imple 2020-01-1 2020-02-0 2020-03-0 2020-09-0 IBRD / 88160 Post Direct 8,470.59 0.00 2020-01-03 1-2020-AF / Administrative lementation Support ultant Selection mentation 3 3 9 5 Officer II PRDP-IS-NLU-025-ADM-00 Component 4: Project Imp Individual Cons Pending Imple 2020-01-1 2020-02-0 2020-03-0 2020-09-0 IBRD / 88160 Post Direct 8,470.59 0.00 2020-01-03 2-2020-AF / Administrative lementation Support ultant Selection mentation 3 3 9 5 Officer II PRDP-IS-NLU-026-IB-001-2 Component 2: Infrastructu Individual Cons Pending Imple 2020-01-1 2020-02-0 2020-03-0 2020-09-0 IBRD / 88160 Post Direct 19,764.71 0.00 2020-01-03 020-AF / IBUILD Componen re Development ultant Selection mentation 3 3 9 5 t Head PRDP-IS-NLU-027-IB-002-2 Component 2: Infrastructu Individual Cons Pending Imple 2020-01-1 2020-02-0 2020-03-0 2020-09-0 020-AF / Rural Infrastractu IBRD / 88160 Post Direct 14,117.65 0.00 2020-01-03 re Development ultant Selection mentation 3 3 9 5 re Specialist -Roads and Br idges PRDP-IS-NLU-028-IB-003-2 Component 2: Infrastructu Individual Cons Pending Imple 2020-03-1 2020-04-0 2020-05-0 2020-11-0 IBRD / 88160 Post Direct 12,705.88 0.00 2020-03-01 020-AF / Rural Infrastructu re Development ultant Selection mentation 1 1 6 2 re Engineer (RIE) PRDP-IS-NLU-029-IB-004-2 Component 2: Infrastructu Individual Cons Pending Imple 2020-01-1 2020-02-0 2020-03-0 2020-09-0 IBRD / 88160 Post Direct 12,705.88 0.00 2020-01-03 020-AF / Rural Infrastructu re Development ultant Selection mentation 3 3 9 5 re Engineer (RIE) PRDP-IS-NLU-030-IB-005-2 Component 2: Infrastructu Individual Cons Pending Imple 2020-01-1 2020-02-0 2020-03-0 2020-09-0 IBRD / 88160 Post Direct 12,705.88 0.00 2020-01-03 020-AF / Rural Infrastructu re Development ultant Selection mentation 3 3 9 5 re Engineer (RIE) PRDP-IS-NLU-031-IB-006-2 Component 2: Infrastructu Individual Cons Pending Imple 2020-01-1 2020-02-0 2020-03-0 2020-09-0 020-AF / Project Developm IBRD / 88160 Post Direct 8,470.59 0.00 2020-01-03 re Development ultant Selection mentation 3 3 9 5 ent Associate (PDA) PRDP-IS-NLU-RCAR-001-D Component 4: Project Imp Individual Cons Pending Imple 2020-01-1 2020-02-0 2020-03-0 2020-09-0 IBRD / 88160 Post Direct 10,867.92 0.00 2020-01-03 PD-001-2020-AF / Economi lementation Support ultant Selection mentation 3 3 9 5 st PRDP-IS-NLU-RCAR-002-IB Component 2: Infrastructu Individual Cons Pending Imple 2020-03-1 2020-04-0 2020-05-0 2020-11-0 -001-2020-AF / Roads & Br IBRD / 88160 Post Direct 8,150.94 0.00 2020-03-01 re Development ultant Selection mentation 1 1 6 2 idges Specialist PRDP-IS-NLU-RCAR-003-IB Component 2: Infrastructu Individual Cons Pending Imple 2020-03-1 2020-04-0 2020-05-0 2020-11-0 -002-2020-AF / Rural Infras IBRD / 88160 Post Direct 9,169.81 0.00 2020-03-01 re Development ultant Selection mentation 1 1 6 2 tructure Engineer PRDP-IS-NLU-RCAR-004-IB Component 2: Infrastructu Individual Cons Pending Imple 2020-01-1 2020-02-0 2020-03-0 2020-09-0 -003-2020-AF / Rural Infras IBRD / 88160 Post Direct 11,294.12 0.00 2020-01-03 re Development ultant Selection mentation 3 3 9 5 tructure Engineer PRDP-IS-NLU-RCAR-005-IB Component 2: Infrastructu Individual Cons Pending Imple 2020-03-1 2020-04-0 2020-05-0 2020-11-0 -004-2020-AF / Rural Infras IBRD / 88160 Post Direct 12,705.88 0.00 2020-03-01 re Development ultant Selection mentation 1 1 6 2 tructure Engineer PRDP-IS-NLU-RCAR-006-IB Component 2: Infrastructu Individual Cons Pending Imple 2020-03-1 2020-04-0 2020-05-0 2020-11-0 -005-2020-AF / Project Dev IBRD / 88160 Post Direct 11,294.12 0.00 2020-03-01 re Development ultant Selection mentation 1 1 6 2 elopment Associate PRDP-IS-NLU-RCAR-007-G Component 4: Project Imp Individual Cons Pending Imple 2020-03-1 2020-04-0 2020-05-0 2020-11-0 IBRD / 88160 Post Direct 11,294.12 0.00 2020-03-01 GU-001-2020-AF / GIS Offi lementation Support ultant Selection mentation 1 1 6 2 cer PRDP-IS-NLU-RCAR-008-P Component 4: Project Imp Individual Cons Pending Imple 2020-03-1 2020-04-0 2020-05-0 2020-11-0 IBRD / 88160 Post Direct 11,294.12 0.00 2020-03-01 RO-001-2020-AF / Procure lementation Support ultant Selection mentation 1 1 6 2 ment Officer PRDP-IS-NLU-RCAR-009-P Component 4: Project Imp Individual Cons Pending Imple 2020-03-1 2020-04-0 2020-05-0 2020-11-0 RO-002-2020-AF / Associat IBRD / 88160 Post Direct 7,058.82 0.00 2020-03-01 lementation Support ultant Selection mentation 1 1 6 2 e Procurement Officer PRDP-IS-NLU-RCAR-010-P Component 4: Project Imp Individual Cons Pending Imple 2020-03-1 2020-04-0 2020-05-0 2020-11-0 RO-003-2020-AF / Associat IBRD / 88160 Post Direct 11,294.12 0.00 2020-03-01 lementation Support ultant Selection mentation 1 1 6 2 e Procurement Officer Page 8 PRDP-IS-NLU-RCAR-011-M Component 4: Project Imp Individual Cons Pending Imple 2020-03-1 2020-04-0 2020-05-0 2020-11-0 NE-001-2020-AF / Monitori IBRD / 88160 Post Direct 11,294.12 0.00 2020-03-01 lementation Support ultant Selection mentation 1 1 6 2 ng & Evaluation Officer PRDP-IS-NLU-RCAR-012-M Component 4: Project Imp Individual Cons Pending Imple 2020-03-1 2020-04-0 2020-05-0 2020-11-0 IBRD / 88160 Post Direct 9,882.35 0.00 2020-03-01 NE-001-2020-AF / Associat lementation Support ultant Selection mentation 1 1 6 2 e M & E Officer PRDP-IS-NLU-RCAR-013-S Component 4: Project Imp Individual Cons Pending Imple 2020-03-1 2020-04-0 2020-05-0 2020-11-0 ES-001-2020-AF / Social an IBRD / 88160 Post Direct 9,882.35 0.00 2020-03-01 lementation Support ultant Selection mentation 1 1 6 2 d Environment Safeguards Officer PRDP-IS-NLU-RCAR-014-S Component 4: Project Imp Individual Cons Pending Imple 2020-03-1 2020-04-0 2020-05-0 2020-11-0 IBRD / 88160 Post Direct 11,294.12 0.00 2020-03-01 ES-002-2020-AF / Associat lementation Support ultant Selection mentation 1 1 6 2 e SES Officer PRDP-IS-NLU-RCAR-015-M Component 4: Project Imp Individual Cons Pending Imple 2020-03-1 2020-04-0 2020-05-0 2020-11-0 IBRD / 88160 Post Direct 9,882.35 0.00 2020-03-01 NE-002-2019-AF / Writer lementation Support ultant Selection mentation 1 1 6 2 PRDP-IS-NLU-RCAR-016-FI Component 4: Project Imp Individual Cons Pending Imple 2020-03-1 2020-04-0 2020-05-0 2020-11-0 IBRD / 88160 Post Direct 11,294.12 0.00 2020-03-01 N-001-2020-AF / Finance A lementation Support ultant Selection mentation 1 1 6 2 nalyst PRDP-IS-NLU-RCAR-017-A Component 4: Project Imp Individual Cons Pending Imple 2020-03-1 2020-04-0 2020-05-0 2020-11-0 IBRD / 88160 Post Direct 9,882.35 0.00 2020-03-01 CT-001-2020-AF / Finance lementation Support ultant Selection mentation 1 1 6 2 Analyst PRDP-IS-NLU-R001-001DP Component 4: Project Imp Individual Cons Pending Imple 2020-01-1 2020-02-0 2020-03-0 2020-09-0 IBRD / 88160 Post Direct 7,058.82 0.00 2020-01-03 D-001-2020-AF / Administr lementation Support ultant Selection mentation 3 3 9 5 ative Officer II PRDP-IS-NLU-R001-002-IB Component 2: Infrastructu Individual Cons Pending Imple 2020-03-1 2020-04-0 2020-05-0 2020-11-0 -001-2020-AF / Rural Infras IBRD / 88160 Post Direct 12,705.88 0.00 2020-03-01 re Development ultant Selection mentation 1 1 6 2 tructure Specialist- Road & Bridges PRDP-IS-NLU-R001-003-IB Component 2: Infrastructu Individual Cons Pending Imple 2020-03-1 2020-04-0 2020-05-0 2020-11-0 -002-2020-AF / Rural Infras IBRD / 88160 Post Direct 11,294.12 0.00 2020-03-01 re Development ultant Selection mentation 1 1 6 2 tructure Engineer PRDP-IS-NLU-R001-004-IB Component 2: Infrastructu Individual Cons Pending Imple 2020-03-1 2020-04-0 2020-05-0 2020-11-0 -003-2020-AF / Rural Infras IBRD / 88160 Post Direct 11,294.12 0.00 2020-03-01 re Development ultant Selection mentation 1 1 6 2 tructure Engineer PRDP-IS-NLU-R001-005-IB Component 2: Infrastructu Individual Cons Pending Imple 2020-03-1 2020-04-0 2020-05-0 2020-11-0 -004-2020-AF / Project Dev IBRD / 88160 Post Direct 7,058.82 0.00 2020-03-01 re Development ultant Selection mentation 1 1 6 2 elopment Associate PRDP-IS-NLU-R001-006-G Component 4: Project Imp Individual Cons Pending Imple 2020-03-1 2020-04-0 2020-05-0 2020-11-0 IBRD / 88160 Post Direct 11,294.12 0.00 2020-03-01 GU-001-2020-AF / GIS Offi lementation Support ultant Selection mentation 1 1 6 2 cer PRDP-IS-NLU-R001-007-PR Component 4: Project Imp Individual Cons Pending Imple 2020-01-1 2020-02-0 2020-03-0 2020-09-0 IBRD / 88160 Post Direct 11,294.12 0.00 2020-01-03 O-001-2020-AF / Procurem lementation Support ultant Selection mentation 3 3 9 5 ent Officer PRDP-IS-NLU-R001-008-PR Component 4: Project Imp Individual Cons Pending Imple 2020-01-1 2020-02-0 2020-03-0 2020-09-0 O-002-2020-AF / Associate IBRD / 88160 Post Direct 9,882.35 0.00 2020-01-03 lementation Support ultant Selection mentation 3 3 9 5 Procurement Officer PRDP-IS-NLU-R001-009-M Component 4: Project Imp Individual Cons Pending Imple 2020-01-1 2020-02-0 2020-03-0 2020-09-0 IBRD / 88160 Post Direct 11,294.12 0.00 2020-01-03 NE-001-2020-AF / M&E Offi lementation Support ultant Selection mentation 3 3 9 5 cer PRDP-IS-NLU-R001-010-M Component 4: Project Imp Individual Cons Pending Imple 2020-01-1 2020-02-0 2020-03-0 2020-09-0 IBRD / 88160 Post Direct 9,882.35 0.00 2020-01-03 NE-002-2020-AF / Associat lementation Support ultant Selection mentation 3 3 9 5 e M&E Officer PRDP-IS-NLU-R001-011-SE Component 4: Project Imp Individual Cons Pending Imple 2020-01-1 2020-02-0 2020-03-0 2020-09-0 IBRD / 88160 Post Direct 11,294.12 0.00 2020-01-03 S-001-2020-AF / SES Office lementation Support ultant Selection mentation 3 3 9 5 r PRDP-IS-NLU-R001-012-SE Component 4: Project Imp Individual Cons Pending Imple 2020-03-1 2020-04-0 2020-05-0 2020-11-0 IBRD / 88160 Post Direct 9,882.35 0.00 2020-03-01 S-001-2020-AF / Associate lementation Support ultant Selection mentation 1 1 6 2 SES Officer PRDP-IS-NLU-R001-013-A Component 4: Project Imp Individual Cons Pending Imple 2020-03-1 2020-04-0 2020-05-0 2020-11-0 IBRD / 88160 Post Direct 9,882.35 0.00 2020-03-01 CE-001-2020-AF / Writer lementation Support ultant Selection mentation 1 1 6 2 PRDP-IS-NLU-R001-014-FI Component 4: Project Imp Individual Cons Pending Imple 2020-03-1 2020-04-0 2020-05-0 2020-11-0 IBRD / 88160 Post Direct 9,882.35 0.00 2020-03-01 N-001-2020-AF / Finance A lementation Support ultant Selection mentation 1 1 6 2 nalyst I PRDP-IS-NLU-R002-001-D Component 4: Project Imp Individual Cons Pending Imple 2020-03-1 2020-04-0 2020-05-0 2020-11-0 IBRD / 88160 Post Direct 9,882.35 0.00 2020-03-02 PD-001-2020-AF / Administ lementation Support ultant Selection mentation 2 2 7 3 rative Officer II PRDP-IS-NLU-R002-002-D Component 4: Project Imp Individual Cons Pending Imple 2020-01-1 2020-02-0 2020-03-0 2020-09-0 IBRD / 88160 Post Direct 10,867.92 0.00 2020-01-03 PD-002-2020-AF / Economi lementation Support ultant Selection mentation 3 3 9 5 st PRDP-IS-NLU-R002-003-IB Component 2: Infrastructu Individual Cons Pending Imple 2020-01-1 2020-02-0 2020-03-0 2020-09-0 -001-2020-AF / Road and B IBRD / 88160 Post Direct 12,226.42 0.00 2020-01-03 re Development ultant Selection mentation 3 3 9 5 ridges Specialist PRDP-IS-NLU-R002-004-IB Component 2: Infrastructu Individual Cons Pending Imple 2020-03-1 2020-04-0 2020-05-0 2020-11-0 -001-2020-AF / Rural Infras IBRD / 88160 Post Direct 10,867.92 0.00 2020-03-01 re Development ultant Selection mentation 1 1 6 2 tructure Engineer PRDP-IS-NLU-R002-005-IB Component 2: Infrastructu Individual Cons Pending Imple 2020-01-1 2020-02-0 2020-03-0 2020-09-0 -001-2020-AF / Rural Infras IBRD / 88160 Post Direct 10,867.92 0.00 2020-01-03 re Development ultant Selection mentation 3 3 9 5 tructure Engineer PRDP-IS-NLU-R002-005-IB Component 2: Infrastructu Individual Cons Pending Imple 2020-01-1 2020-02-0 2020-03-0 2020-09-0 -001A-2020F-AF / Rural Inf IBRD / 88160 Post Direct 10,867.92 0.00 2020-01-03 re Development ultant Selection mentation 3 3 9 5 rastructure Engineer PRDP-IS-NLU-R002-005-IB Component 2: Infrastructu Individual Cons Pending Imple 2020-01-1 2020-02-0 2020-03-0 2020-09-0 -001B-2020F-AF / Rural Inf IBRD / 88160 Post Direct 10,867.92 0.00 2020-01-03 re Development ultant Selection mentation 3 3 9 5 rastructure Engineer PRDP-IS-NLU-R002-006-IB Component 2: Infrastructu Individual Cons Pending Imple 2020-03-1 2020-04-0 2020-05-0 2020-11-0 -001-2020-AF / Project Dev IBRD / 88160 Post Direct 6,792.45 0.00 2020-03-01 re Development ultant Selection mentation 1 1 6 2 elopment Associate PRDP-IS-NLU-R002-007-G Component 4: Project Imp Individual Cons Pending Imple 2020-03-1 2020-04-0 2020-05-0 2020-11-0 IBRD / 88160 Post Direct 10,867.92 0.00 2020-03-01 GU-001-2020-AF / GIS Offi lementation Support ultant Selection mentation 1 1 6 2 cer PRDP-IS-NLU-R002-008-PR Component 4: Project Imp Individual Cons Pending Imple 2020-01-1 2020-02-0 2020-03-0 2020-09-0 IBRD / 88160 Post Direct 10,867.92 0.00 2020-01-03 O-001-2020-AF / Procurem lementation Support ultant Selection mentation 3 3 9 5 ent Officer PRDP-IS-NLU-R002-009-PR Component 4: Project Imp Individual Cons Pending Imple 2020-01-1 2020-02-0 2020-03-0 2020-09-0 O-001-2020-AF / Associate IBRD / 88160 Post Direct 9,509.43 0.00 2020-01-03 lementation Support ultant Selection mentation 3 3 9 5 Procurement Officer PRDP-IS-NLU-R002-010-M Component 4: Project Imp Individual Cons Pending Imple 2020-01-1 2020-02-0 2020-03-0 2020-09-0 NE-001-2020-AF / Monitori IBRD / 88160 Post Direct 10,867.92 0.00 2020-01-03 lementation Support ultant Selection mentation 3 3 9 5 ng & Evaluation Officer PRDP-IS-NLU-R002-011-M Component 4: Project Imp Individual Cons Pending Imple 2020-01-1 2020-02-0 2020-03-0 2020-09-0 IBRD / 88160 Post Direct 9,509.43 0.00 2020-01-03 NE-001-2020-AF / Associat lementation Support ultant Selection mentation 3 3 9 5 e M & E Officer PRDP-IS-NLU-R002-012-SE Component 4: Project Imp Individual Cons Pending Imple 2020-01-1 2020-02-0 2020-03-0 2020-09-0 S-001-2020-AF / Social Saf IBRD / 88160 Post Direct 10,867.92 0.00 2020-01-03 lementation Support ultant Selection mentation 3 3 9 5 eguard Specialist PRDP-IS-NLU-R002-013-SE Component 4: Project Imp Individual Cons Pending Imple 2020-01-1 2020-02-0 2020-03-0 2020-09-0 IBRD / 88160 Post Direct 9,509.43 0.00 2020-01-03 S-002-2020-AF / Associate lementation Support ultant Selection mentation 3 3 9 5 SES Officer PRDP-IS-NLU-R002-014-A Component 4: Project Imp Individual Cons Pending Imple 2020-03-1 2020-04-0 2020-05-0 2020-11-0 IBRD / 88160 Post Direct 9,509.43 0.00 2020-03-01 CE-001-2020-AF / Writer lementation Support ultant Selection mentation 1 1 6 2 PRDP-IS-NLU-R002-015-FI Component 4: Project Imp Individual Cons Pending Imple 2020-03-1 2020-04-0 2020-05-0 2020-11-0 IBRD / 88160 Post Direct 9,509.43 0.00 2020-03-01 N-001-2020-AF / Finance A lementation Support ultant Selection mentation 1 1 6 2 nalyst I PRDP-IS-NLU-R002-016-A Component 4: Project Imp Individual Cons Pending Imple 2020-01-1 2020-02-0 2020-03-0 2020-09-0 IBRD / 88160 Post Direct 9,509.43 0.00 2020-01-03 CT-001-2020-AF / Budget lementation Support ultant Selection mentation 3 3 9 5 Analyst PRDP-IS-NLU-R002-017-B Component 4: Project Imp Individual Cons Pending Imple 2020-03-1 2020-04-0 2020-05-0 2020-11-0 IBRD / 88160 Post Direct 9,509.43 0.00 2020-03-01 UD-001-2020-AF / Finance lementation Support ultant Selection mentation 1 1 6 2 Analyst I PRDP-IS-NLU-R003-001-D Component 4: Project Imp Individual Cons Pending Imple 2020-03-1 2020-04-0 2020-05-0 2020-11-0 IBRD / 88160 Post Direct 6,792.45 0.00 2020-03-01 PD-001-2020-AF / Administ lementation Support ultant Selection mentation 1 1 6 2 rative /Officer II PRDP-IS-NLU-R003-002-D Component 4: Project Imp Individual Cons Pending Imple 2020-03-1 2020-04-0 2020-05-0 2020-11-0 IBRD / 88160 Post Direct 10,867.92 0.00 2020-03-01 PD-002-2020-AF / Economi lementation Support ultant Selection mentation 1 1 6 2 st PRDP-IS-NLU-R003-003-G Component 4: Project Imp Individual Cons Pending Imple 2020-01-1 2020-02-0 2020-03-0 2020-09-0 IBRD / 88160 Post Direct 10,867.92 0.00 2020-01-03 GU-001-2020-AF / GIS Offi lementation Support ultant Selection mentation 3 3 9 5 cer PRDP-IS-NLU-R003-004-PR Component 4: Project Imp Individual Cons Pending Imple 2020-01-1 2020-02-0 2020-03-0 2020-09-0 IBRD / 88160 Post Direct 10,867.92 0.00 2020-01-03 O-001-2020-AF / Procurem lementation Support ultant Selection mentation 3 3 9 5 ent Officer PRDP-IS-NLU-R003-005-PR Component 4: Project Imp Individual Cons Pending Imple 2020-01-1 2020-02-0 2020-03-0 2020-09-0 O-002-2020-AF / Associate IBRD / 88160 Post Direct 10,867.92 0.00 2020-01-03 lementation Support ultant Selection mentation 3 3 9 5 Procurement Officer PRDP-IS-NLU-R003-006-SE Component 4: Project Imp Individual Cons Pending Imple 2020-03-1 2020-04-0 2020-05-0 2020-11-0 IBRD / 88160 Post Direct 10,867.92 0.00 2020-03-01 S-001-2020-AF / SES Office lementation Support ultant Selection mentation 1 1 6 2 r PRDP-IS-NLU-R003-007-SE Component 4: Project Imp Individual Cons Pending Imple 2020-01-1 2020-02-0 2020-03-0 2020-09-0 IBRD / 88160 Post Direct 9,509.43 0.00 2020-01-03 S-002-2020-AF / Associate lementation Support ultant Selection mentation 3 3 9 5 SES Officer PRDP-IS-NLU-R003-008-M Component 4: Project Imp Individual Cons Pending Imple 2020-01-1 2020-02-0 2020-03-0 2020-09-0 IBRD / 88160 Post Direct 9,509.43 0.00 2020-01-03 NE-001-2020-AF / M&E Offi lementation Support ultant Selection mentation 3 3 9 5 cer PRDP-IS-NLU-R003-009-M Component 4: Project Imp Individual Cons Pending Imple 2020-03-1 2020-04-0 2020-05-0 2020-11-0 IBRD / 88160 Post Direct 9,509.43 0.00 2020-03-01 NE-002-2020-AF / Associat lementation Support ultant Selection mentation 1 1 6 2 e M&E Officer PRDP-IS-NLU-R003-010-FI Component 4: Project Imp Individual Cons Pending Imple 2020-03-1 2020-04-0 2020-05-0 2020-11-0 IBRD / 88160 Post Direct 9,509.43 0.00 2020-03-01 N-001-2020-AF / Finance A lementation Support ultant Selection mentation 1 1 6 2 nalyst I PRDP-IS-NLU-R003-011-FI Component 4: Project Imp Individual Cons Pending Imple 2020-03-1 2020-04-0 2020-05-0 2020-11-0 IBRD / 88160 Post Direct 9,509.43 0.00 2020-03-01 N-002-2020-AF / Finance A lementation Support ultant Selection mentation 1 1 6 2 nalyst I PRDP-IS-NLU-R003-012-B Component 4: Project Imp Individual Cons Pending Imple 2020-01-1 2020-02-0 2020-03-0 2020-09-0 IBRD / 88160 Post Direct 9,509.43 0.00 2020-01-03 UD-001-2020-AF / Budget lementation Support ultant Selection mentation 3 3 9 5 Analyst PRDP-IS-NLU-R003-013-A Component 4: Project Imp Individual Cons Pending Imple 2020-03-1 2020-04-0 2020-05-0 2020-11-0 IBRD / 88160 Post Direct 9,509.43 0.00 2020-03-01 CE-001-2020-AF / Writer lementation Support ultant Selection mentation 1 1 6 2 PRDP-IS-NLU-R003-014-IB Component 2: Infrastructu Individual Cons Pending Imple 2020-01-1 2020-02-0 2020-03-0 2020-09-0 -001-2020-AF / Rural Infras IBRD / 88160 Post Direct 10,867.92 0.00 2020-01-03 re Development ultant Selection mentation 3 3 9 5 tructure Engineer PRDP-IS-NLU-R003-015-IB Component 2: Infrastructu Individual Cons Pending Imple 2020-01-1 2020-02-0 2020-03-0 2020-09-0 -002-2020-AF / Rural Infras IBRD / 88160 Post Direct 10,867.92 0.00 2020-01-03 re Development ultant Selection mentation 3 3 9 5 tructure Engineer PRDP-IS-NLU-R003-016-IB Component 2: Infrastructu Individual Cons Pending Imple 2020-03-1 2020-04-0 2020-05-0 2020-11-0 -003-2020-AF / Rural Infras IBRD / 88160 Post Direct 10,867.92 0.00 2020-03-01 re Development ultant Selection mentation 1 1 6 2 tructure Engineer PRDP-IS-NLU-R003-016-IB Component 2: Infrastructu Individual Cons Pending Imple 2020-03-1 2020-04-0 2020-05-0 2020-11-0 -003-2020F-AF / Rural Infr IBRD / 88160 Post Direct 10,867.92 0.00 2020-03-01 re Development ultant Selection mentation 1 1 6 2 astructure Engineer PRDP-IS-NLU-R003-017-IB Component 2: Infrastructu Individual Cons Pending Imple 2020-03-1 2020-04-0 2020-05-0 2020-11-0 -004-2020-AF / Project Dev IBRD / 88160 Post Direct 6,792.45 0.00 2020-03-01 re Development ultant Selection mentation 1 1 6 2 elopment Associate PRDP-IS-NLU-001-DPD-00 Component 4: Project Imp Individual Cons Pending Imple 2021-01-1 2021-02-0 2021-03-1 2021-09-0 IBRD / 88160 Post Direct 4,500.00 0.00 2021-01-03 1-2021-AF / Economist lementation Support ultant Selection mentation 3 3 0 6 PRDP-IS-NLU-002-DPD-00 Component 4: Project Imp Individual Cons Pending Imple 2021-03-1 2021-04-0 2021-05-0 2021-11-0 IBRD / 88160 Post Direct 5,000.00 0.00 2021-03-01 2-2021-AF / Compliance Of lementation Support ultant Selection mentation 1 1 6 2 ficer PRDP-IS-NLU-003-ACE-00 Component 4: Project Imp Individual Cons Pending Imple 2021-03-1 2021-04-0 2021-05-0 2021-11-0 IBRD / 88160 Post Direct 4,000.00 0.00 2021-03-01 1-2021-AF / Writer lementation Support ultant Selection mentation 1 1 6 2 PRDP-IS-NLU-004-ACE-00 Component 4: Project Imp Individual Cons Pending Imple 2021-03-1 2021-04-0 2021-05-0 2021-11-0 IBRD / 88160 Post Direct 3,500.00 0.00 2021-03-01 2-2021-AF / Media Producti lementation Support ultant Selection mentation 1 1 6 2 on Officer PRDP-IS-NLU-006-PRO-00 Component 4: Project Imp Individual Cons Pending Imple 2021-01-1 2021-02-0 2021-03-1 2021-09-0 IBRD / 88160 Post Direct 4,500.00 0.00 2021-01-03 2-2021-AF / Procurement lementation Support ultant Selection mentation 3 3 0 6 Officer Page 9 PRDP-IS-NLU-007-PRO-00 Component 4: Project Imp Individual Cons Pending Imple 2021-01-1 2021-02-0 2021-03-1 2021-09-0 IBRD / 88160 Post Direct 4,500.00 0.00 2021-01-03 3-2021-AF / Procurement lementation Support ultant Selection mentation 3 3 0 6 Officer PRDP-IS-NLU-008-PRO-00 Component 4: Project Imp Individual Cons Pending Imple 2021-03-1 2021-04-0 2021-05-0 2021-11-0 IBRD / 88160 Post Direct 4,000.00 0.00 2021-03-01 4-2021-AF / Associate Proc lementation Support ultant Selection mentation 1 1 6 2 urement Officer PRDP-IS-NLU-009-MNE-00 Component 4: Project Imp Individual Cons Pending Imple 2021-03-1 2021-04-0 2021-05-0 2021-11-0 IBRD / 88160 Post Direct 5,000.00 0.00 2021-03-01 1-2021-AF / M&E Specialist lementation Support ultant Selection mentation 1 1 6 2 PRDP-IS-NLU-010-MNE-00 Component 4: Project Imp Individual Cons Pending Imple 2021-01-1 2021-02-0 2021-03-1 2021-09-0 IBRD / 88160 Post Direct 4,500.00 0.00 2021-01-03 1-2021-AF / M&E Officer lementation Support ultant Selection mentation 3 3 0 6 PRDP-IS-NLU-011-FIN-001- Component 4: Project Imp Individual Cons Pending Imple 2021-03-1 2021-04-0 2021-05-0 2021-11-0 IBRD / 88160 Post Direct 3,750.00 0.00 2021-03-01 2021-AF / Financial Analys lementation Support ultant Selection mentation 1 1 6 2 t III PRDP-IS-NLU-012-FIN-001- Component 4: Project Imp Individual Cons Pending Imple 2021-01-1 2021-02-0 2021-03-1 2021-09-0 IBRD / 88160 Post Direct 3,375.00 0.00 2021-01-03 2021-AF / Financial Analys lementation Support ultant Selection mentation 3 3 0 6 t II PRDP-IS-NLU-013-FIN-001- Component 4: Project Imp Individual Cons Pending Imple 2021-01-1 2021-02-0 2021-03-1 2021-09-0 IBRD / 88160 Post Direct 3,375.00 0.00 2021-01-03 2021-AF / Financial Analys lementation Support ultant Selection mentation 3 3 0 6 t II PRDP-IS-NLU-014-FIN-001- Component 4: Project Imp Individual Cons Pending Imple 2021-03-1 2021-04-0 2021-05-0 2021-11-0 2021-AF / Financial Analys IBRD / 88160 Post Direct 3,375.00 0.00 2021-03-01 lementation Support ultant Selection mentation 1 1 6 2 t II (Accountant) PRDP-IS-NLU-015-FIN-001- Component 4: Project Imp Individual Cons Pending Imple 2021-03-1 2021-04-0 2021-05-0 2021-11-0 IBRD / 88160 Post Direct 3,000.00 0.00 2021-03-01 2021-AF / Financial Analys lementation Support ultant Selection mentation 1 1 6 2 tI PRDP-IS-NLU-016-BUD-00 Component 4: Project Imp Individual Cons Pending Imple 2021-01-1 2021-02-0 2021-03-1 2021-09-0 IBRD / 88160 Post Direct 3,000.00 0.00 2021-01-03 1-2021-AF / Budget Analys lementation Support ultant Selection mentation 3 3 0 6 t PRDP-IS-NLU-017-GGU-00 Component 4: Project Imp Individual Cons Pending Imple 2021-03-1 2021-04-0 2021-05-0 2021-11-0 IBRD / 88160 Post Direct 3,375.00 0.00 2021-03-01 1-2021-AF / GIS Data Offic lementation Support ultant Selection mentation 1 1 6 2 er PRDP-IS-NLU-018-GGU-00 Component 4: Project Imp Individual Cons Pending Imple 2021-03-1 2021-04-0 2021-05-0 2021-11-0 IBRD / 88160 Post Direct 3,375.00 0.00 2021-03-01 2-2021-AF / GIS Data Offic lementation Support ultant Selection mentation 1 1 6 2 er PRDP-IS-NLU-019-SES-001 Component 4: Project Imp Individual Cons Pending Imple 2021-03-1 2021-04-0 2021-05-0 2021-11-0 IBRD / 88160 Post Direct 4,875.00 0.00 2021-03-01 -2021-AF / SES Unit Head lementation Support ultant Selection mentation 1 1 6 2 PRDP-IS-NLU-020-SES-002 Component 4: Project Imp Individual Cons Pending Imple 2021-03-1 2021-04-0 2021-05-0 2021-11-0 -2021-AF / Social and Envir IBRD / 88160 Post Direct 3,750.00 0.00 2021-03-01 lementation Support ultant Selection mentation 1 1 6 2 onmental Safeguard Speci alist PRDP-IS-NLU-021-SES-003 Component 4: Project Imp Individual Cons Pending Imple 2021-01-1 2021-02-0 2021-03-1 2021-09-0 -2021-AF / Social and Envir IBRD / 88160 Post Direct 3,375.00 0.00 2021-01-03 lementation Support ultant Selection mentation 3 3 0 6 onmental Safeguards Offic er PRDP-IS-NLU-022-SES-004 Component 4: Project Imp Individual Cons Pending Imple 2021-03-1 2021-04-0 2021-05-0 2021-11-0 IBRD / 88160 Post Direct 3,000.00 0.00 2021-03-01 -2021-AF / Associate SES lementation Support ultant Selection mentation 1 1 6 2 Officer PRDP-IS-NLU-023-SES-005 Component 4: Project Imp Individual Cons Pending Imple 2021-01-1 2021-02-0 2021-03-1 2021-09-0 IBRD / 88160 Post Direct 2,625.00 0.00 2021-01-03 -2021-AF / Administrative lementation Support ultant Selection mentation 3 3 0 6 Officer III PRDP-IS-NLU-024-ADM-00 Component 4: Project Imp Individual Cons Pending Imple 2021-01-1 2021-02-0 2021-03-1 2021-09-0 IBRD / 88160 Post Direct 2,250.00 0.00 2021-01-03 1-2021-AF / Administrative lementation Support ultant Selection mentation 3 3 0 6 Officer II PRDP-IS-NLU-025-ADM-00 Component 4: Project Imp Individual Cons Pending Imple 2021-01-1 2021-02-0 2021-03-1 2021-09-0 IBRD / 88160 Post Direct 2,250.00 0.00 2021-01-03 2-2021-AF / Administrative lementation Support ultant Selection mentation 3 3 0 6 Officer II PRDP-IS-NLU-026-IB-001-2 Component 2: Infrastructu Individual Cons Pending Imple 2021-01-1 2021-02-0 2021-03-1 2021-09-0 IBRD / 88160 Post Direct 5,250.00 0.00 2021-01-03 021-AF / IBUILD Componen re Development ultant Selection mentation 3 3 0 6 t Head PRDP-IS-NLU-027-IB-002-2 Component 2: Infrastructu Individual Cons Pending Imple 2021-01-1 2021-02-0 2021-03-1 2021-09-0 021-AF / Rural Infrastractu IBRD / 88160 Post Direct 3,750.00 0.00 2021-01-03 re Development ultant Selection mentation 3 3 0 6 re Specialist -Roads and Br idges PRDP-IS-NLU-028-IB-003-2 Component 2: Infrastructu Individual Cons Pending Imple 2021-03-1 2021-04-0 2021-05-0 2021-11-0 IBRD / 88160 Post Direct 3,375.00 0.00 2021-03-01 021-AF / Rural Infrastructu re Development ultant Selection mentation 1 1 6 2 re Engineer (RIE) PRDP-IS-NLU-029-IB-004-2 Component 2: Infrastructu Individual Cons Pending Imple 2021-01-1 2021-02-0 2021-03-1 2021-09-0 IBRD / 88160 Post Direct 3,375.00 0.00 2021-01-03 021-AF / Rural Infrastructu re Development ultant Selection mentation 3 3 0 6 re Engineer (RIE) PRDP-IS-NLU-030-IB-005-2 Component 2: Infrastructu Individual Cons Pending Imple 2021-01-1 2021-02-0 2021-03-1 2021-09-0 IBRD / 88160 Post Direct 3,375.00 0.00 2021-01-03 021-AF / Rural Infrastructu re Development ultant Selection mentation 3 3 0 6 re Engineer (RIE) PRDP-IS-NLU-031-IB-006-2 Component 2: Infrastructu Individual Cons Pending Imple 2021-01-1 2021-02-0 2021-03-1 2021-09-0 021-AF / Project Developm IBRD / 88160 Post Direct 2,250.00 0.00 2021-01-03 re Development ultant Selection mentation 3 3 0 6 ent Associate (PDA) PRDP-IS-NLU-RCAR-001-D Component 4: Project Imp Individual Cons Pending Imple 2021-01-1 2021-02-0 2021-03-1 2021-09-0 IBRD / 88160 Post Direct 6,000.00 0.00 2021-01-03 PD-001-2021-AF / Economi lementation Support ultant Selection mentation 3 3 0 6 st PRDP-IS-NLU-RCAR-003-IB Component 2: Infrastructu Individual Cons Pending Imple 2021-03-1 2021-04-0 2021-05-0 2021-11-0 -002-2021-AF / Rural Infras IBRD / 88160 Post Direct 1,000.00 0.00 2021-03-01 re Development ultant Selection mentation 1 1 6 2 tructure Engineer PRDP-IS-NLU-RCAR-004-IB Component 2: Infrastructu Individual Cons Pending Imple 2021-01-1 2021-02-0 2021-03-1 2021-09-0 -003-2021-AF / Rural Infras IBRD / 88160 Post Direct 1,000.00 0.00 2021-01-03 re Development ultant Selection mentation 3 3 0 6 tructure Engineer PRDP-IS-NLU-RCAR-005-IB Component 2: Infrastructu Individual Cons Pending Imple 2021-03-1 2021-04-0 2021-05-0 2021-11-0 -004-2021-AF / Rural Infras IBRD / 88160 Post Direct 1,000.00 0.00 2021-03-01 re Development ultant Selection mentation 1 1 6 2 tructure Engineer PRDP-IS-NLU-RCAR-003A-I Component 2: Infrastructu Individual Cons Pending Imple 2021-03-1 2021-04-0 2021-05-0 2021-11-0 B-002-2021-AF / Rural Infr IBRD / 88160 Post Direct 1,000.00 0.00 2021-03-01 re Development ultant Selection mentation 1 1 6 2 astructure Engineer PRDP-IS-NLU-RCAR-004B-I Component 2: Infrastructu Individual Cons Pending Imple 2021-01-1 2021-02-0 2021-03-1 2021-09-0 B-003-2021-AF / Rural Infr IBRD / 88160 Post Direct 1,000.00 0.00 2021-01-03 re Development ultant Selection mentation 3 3 0 6 astructure Engineer PRDP-IS-NLU-RCAR-006-IB Component 2: Infrastructu Individual Cons Pending Imple 2021-03-1 2021-04-0 2021-05-0 2021-11-0 -005-2021-AF / Project Dev IBRD / 88160 Post Direct 3,750.00 0.00 2021-03-01 re Development ultant Selection mentation 1 1 6 2 elopment Associate PRDP-IS-NLU-RCAR-007-G Component 4: Project Imp Individual Cons Pending Imple 2021-03-1 2021-04-0 2021-05-0 2021-11-0 IBRD / 88160 Post Direct 6,000.00 0.00 2021-03-01 GU-001-2021-AF / GIS Offi lementation Support ultant Selection mentation 1 1 6 2 cer PRDP-IS-NLU-RCAR-008-P Component 4: Project Imp Individual Cons Pending Imple 2021-03-1 2021-04-0 2021-05-0 2021-11-0 IBRD / 88160 Post Direct 6,000.00 0.00 2021-03-01 RO-001-2021-AF / Procure lementation Support ultant Selection mentation 1 1 6 2 ment Officer PRDP-IS-NLU-RCAR-009-P Component 4: Project Imp Individual Cons Pending Imple 2021-03-1 2021-04-0 2021-05-0 2021-11-0 RO-002-2021-AF / Associat IBRD / 88160 Post Direct 5,250.00 0.00 2021-03-01 lementation Support ultant Selection mentation 1 1 6 2 e Procurement Officer PRDP-IS-NLU-RCAR-012-M Component 4: Project Imp Individual Cons Pending Imple 2021-03-1 2021-04-0 2021-05-0 2021-11-0 IBRD / 88160 Post Direct 5,250.00 0.00 2021-03-01 NE-001-2021-AF / Associat lementation Support ultant Selection mentation 1 1 6 2 e M & E Officer PRDP-IS-NLU-RCAR-013-S Component 4: Project Imp Individual Cons Pending Imple 2021-03-1 2021-04-0 2021-05-0 2021-11-0 ES-001-2021-AF / Social an IBRD / 88160 Post Direct 6,000.00 0.00 2021-03-01 lementation Support ultant Selection mentation 1 1 6 2 d Environment Safeguards Officer PRDP-IS-NLU-RCAR-014-S Component 4: Project Imp Individual Cons Pending Imple 2021-03-1 2021-04-0 2021-05-0 2021-11-0 IBRD / 88160 Post Direct 5,250.00 0.00 2021-03-01 ES-002-2021-AF / Associat lementation Support ultant Selection mentation 1 1 6 2 e SES Officer PRDP-IS-NLU-RCAR-015-M Component 4: Project Imp Individual Cons Pending Imple 2021-03-1 2021-04-0 2021-05-0 2021-11-0 IBRD / 88160 Post Direct 5,250.00 0.00 2021-03-01 NE-002-2021-AF / Writer lementation Support ultant Selection mentation 1 1 6 2 PRDP-IS-NLU-RCAR-016-FI Component 4: Project Imp Individual Cons Pending Imple 2021-03-1 2021-04-0 2021-05-0 2021-11-0 IBRD / 88160 Post Direct 5,250.00 0.00 2021-03-01 N-001-2021-AF / Finance A lementation Support ultant Selection mentation 1 1 6 2 nalyst PRDP-IS-NLU-RCAR-017-A Component 4: Project Imp Individual Cons Pending Imple 2021-03-1 2021-04-0 2021-05-0 2021-11-0 IBRD / 88160 Post Direct 5,250.00 0.00 2021-03-01 CT-001-2021-AF / Finance lementation Support ultant Selection mentation 1 1 6 2 Analyst PRDP-IS-NLU-R001-001DP Component 4: Project Imp Individual Cons Pending Imple 2021-01-1 2021-02-0 2021-03-1 2021-09-0 IBRD / 88160 Post Direct 2,770.83 0.00 2021-01-03 D-001-2021-AF / Administr lementation Support ultant Selection mentation 3 3 0 6 ative Officer II PRDP-IS-NLU-R001-002-IB Component 2: Infrastructu Individual Cons Pending Imple 2021-03-1 2021-04-0 2021-05-0 2021-11-0 -001-2021-AF / Rural Infras IBRD / 88160 Post Direct 5,625.00 0.00 2021-03-01 re Development ultant Selection mentation 1 1 6 2 tructure Specialist- Road & Bridges PRDP-IS-NLU-R001-003-IB Component 2: Infrastructu Individual Cons Pending Imple 2021-03-1 2021-04-0 2021-05-0 2021-11-0 -002-2021-AF / Rural Infras IBRD / 88160 Post Direct 5,000.00 0.00 2021-03-01 re Development ultant Selection mentation 1 1 6 2 tructure Engineer PRDP-IS-NLU-R001-003-IB Component 2: Infrastructu Individual Cons Pending Imple 2021-03-1 2021-04-0 2021-05-0 2021-11-0 -002A-2021-AF / Rural Infr IBRD / 88160 Post Direct 5,000.00 0.00 2021-03-01 re Development ultant Selection mentation 1 1 6 2 astructure Engineer PRDP-IS-NLU-R001-004-IB Component 2: Infrastructu Individual Cons Pending Imple 2021-03-1 2021-04-0 2021-05-0 2021-11-0 -003-2021-AF / Rural Infras IBRD / 88160 Post Direct 5,000.00 0.00 2021-03-01 re Development ultant Selection mentation 1 1 6 2 tructure Engineer PRDP-IS-NLU-R001-005-IB Component 2: Infrastructu Individual Cons Pending Imple 2021-03-1 2021-04-0 2021-05-0 2021-11-0 -004-2021-AF / Project Dev IBRD / 88160 Post Direct 2,500.00 0.00 2021-03-01 re Development ultant Selection mentation 1 1 6 2 elopment Associate PRDP-IS-NLU-R001-006-A Component 4: Project Imp Individual Cons Pending Imple 2021-03-1 2021-04-0 2021-05-0 2021-11-0 DMIN-001A-2021-AF / Adm IBRD / 88160 Post Direct 2,500.00 0.00 2021-03-01 lementation Support ultant Selection mentation 1 1 6 2 inistrative Officer II PRDP-IS-NLU-R001-006-A Component 4: Project Imp Individual Cons Pending Imple 2021-03-1 2021-04-0 2021-05-0 2021-11-0 DMIN-001B-2021-AF / Adm IBRD / 88160 Post Direct 2,500.00 0.00 2021-03-01 lementation Support ultant Selection mentation 1 1 6 2 inistrative Officer II PRDP-IS-NLU-R001-006-A Component 4: Project Imp Individual Cons Pending Imple 2021-03-1 2021-04-0 2021-05-0 2021-11-0 DMIN-001C-2021-AF / Adm IBRD / 88160 Post Direct 2,500.00 0.00 2021-03-01 lementation Support ultant Selection mentation 1 1 6 2 inistrative Officer II PRDP-IS-NLU-R001-006-G Component 4: Project Imp Individual Cons Pending Imple 2021-03-1 2021-04-0 2021-05-0 2021-11-0 IBRD / 88160 Post Direct 5,000.00 0.00 2021-03-01 GU-001-2021-AF / GIS Offi lementation Support ultant Selection mentation 1 1 6 2 cer PRDP-IS-NLU-R001-007-PR Component 4: Project Imp Individual Cons Pending Imple 2021-01-1 2021-02-0 2021-03-1 2021-09-0 IBRD / 88160 Post Direct 5,000.00 0.00 2021-01-03 O-001-2021-AF / Procurem lementation Support ultant Selection mentation 3 3 0 6 ent Officer PRDP-IS-NLU-R001-008-PR Component 4: Project Imp Individual Cons Pending Imple 2021-01-1 2021-02-0 2021-03-1 2021-09-0 O-002-2021-AF / Associate IBRD / 88160 Post Direct 4,375.00 0.00 2021-01-04 lementation Support ultant Selection mentation 4 4 1 7 Procurement Officer PRDP-IS-NLU-R001-009-M Component 4: Project Imp Individual Cons Pending Imple 2021-01-1 2021-02-0 2021-03-1 2021-09-0 IBRD / 88160 Post Direct 5,000.00 0.00 2021-01-04 NE-001-2021-AF / M&E Offi lementation Support ultant Selection mentation 4 4 1 7 cer PRDP-IS-NLU-R001-010-M Component 4: Project Imp Individual Cons Pending Imple 2021-01-1 2021-02-0 2021-03-1 2021-09-0 IBRD / 88160 Post Direct 4,375.00 0.00 2021-01-04 NE-002-2021-AF / Associat lementation Support ultant Selection mentation 4 4 1 7 e M&E Officer PRDP-IS-NLU-R001-011-SE Component 4: Project Imp Individual Cons Pending Imple 2021-01-1 2021-02-0 2021-03-1 2021-09-0 IBRD / 88160 Post Direct 5,000.00 0.00 2021-01-04 S-001-2021-AF / SES Office lementation Support ultant Selection mentation 4 4 1 7 r PRDP-IS-NLU-R001-012-SE Component 4: Project Imp Individual Cons Pending Imple 2021-01-1 2021-02-0 2021-03-1 2021-09-0 IBRD / 88160 Post Direct 4,375.00 0.00 2021-01-04 S-001-2021-AF / Associate lementation Support ultant Selection mentation 4 4 1 7 SES Officer PRDP-IS-NLU-R002-001-D Component 4: Project Imp Individual Cons Pending Imple 2021-01-1 2021-02-0 2021-03-1 2021-09-0 IBRD / 88160 Post Direct 3,750.00 0.00 2021-01-04 PD-001-2021-AF / Administ lementation Support ultant Selection mentation 4 4 1 7 rative Officer II PRDP-IS-NLU-R002-002-D Component 4: Project Imp Individual Cons Pending Imple 2021-02-2 2021-03-1 2021-04-1 2021-10-1 IBRD / 88160 Post Open 6,000.00 0.00 2021-01-04 PD-002-2021-AF / Economi lementation Support ultant Selection mentation 2 5 9 6 st PRDP-IS-NLU-R002-003-IB Component 2: Infrastructu Individual Cons Pending Imple 2021-01-1 2021-02-0 2021-03-1 2021-09-0 -001-2021-AF / Road and B IBRD / 88160 Post Direct 6,750.00 0.00 2021-01-04 re Development ultant Selection mentation 4 4 1 7 ridges Specialist PRDP-IS-NLU-R002-004-IB Component 2: Infrastructu Individual Cons Pending Imple 2021-01-1 2021-02-0 2021-03-1 2021-09-0 -001-2021-AF / Rural Infras IBRD / 88160 Post Direct 4,796.88 0.00 2021-01-04 re Development ultant Selection mentation 4 4 1 7 tructure Engineer PRDP-IS-NLU-R002-005-IB Component 2: Infrastructu Individual Cons Pending Imple 2021-01-1 2021-02-0 2021-03-1 2021-09-0 -001-2021-AF / Rural Infras IBRD / 88160 Post Direct 4,796.88 0.00 2021-01-04 re Development ultant Selection mentation 4 4 1 7 tructure Engineer Page 10 PRDP-IS-NLU-R002-005-IB Component 2: Infrastructu Individual Cons Pending Imple 2021-01-1 2021-02-0 2021-03-1 2021-09-0 -001A-2021F-AF / Rural Inf IBRD / 88160 Post Direct 4,796.88 0.00 2021-01-04 re Development ultant Selection mentation 4 4 1 7 rastructure Engineer PRDP-IS-NLU-R002-005-IB Component 2: Infrastructu Individual Cons Pending Imple 2021-01-1 2021-02-0 2021-03-1 2021-09-0 -001B-2021F-AF / Rural Inf IBRD / 88160 Post Direct 4,796.88 0.00 2021-01-04 re Development ultant Selection mentation 4 4 1 7 rastructure Engineer PRDP-IS-NLU-R002-006-IB Component 2: Infrastructu Individual Cons Pending Imple 2021-01-1 2021-02-0 2021-03-1 2021-09-0 -001-2021-AF / Project Dev IBRD / 88160 Post Direct 3,750.00 0.00 2021-01-04 re Development ultant Selection mentation 4 4 1 7 elopment Associate PRDP-IS-NLU-R002-007-G Component 4: Project Imp Individual Cons Pending Imple 2021-01-1 2021-02-0 2021-03-1 2021-09-0 IBRD / 88160 Post Direct 6,000.00 0.00 2021-01-04 GU-001-2021-AF / GIS Offi lementation Support ultant Selection mentation 4 4 1 7 cer PRDP-IS-NLU-R002-008-PR Component 4: Project Imp Individual Cons Pending Imple 2021-01-1 2021-02-0 2021-03-1 2021-09-0 IBRD / 88160 Post Direct 6,000.00 0.00 2021-01-04 O-001-2021-AF / Procurem lementation Support ultant Selection mentation 4 4 1 7 ent Officer PRDP-IS-NLU-R002-009-PR Component 4: Project Imp Individual Cons Pending Imple 2021-01-1 2021-02-0 2021-03-1 2021-09-0 O-001-2021-AF / Associate IBRD / 88160 Post Direct 5,250.00 0.00 2021-01-04 lementation Support ultant Selection mentation 4 4 1 7 Procurement Officer PRDP-IS-NLU-R002-010-M Component 4: Project Imp Individual Cons Pending Imple 2021-01-1 2021-02-0 2021-03-1 2021-09-0 NE-001-2021-AF / Monitori IBRD / 88160 Post Direct 6,000.00 0.00 2021-01-04 lementation Support ultant Selection mentation 4 4 1 7 ng & Evaluation Officer PRDP-IS-NLU-R002-011-M Component 4: Project Imp Individual Cons Pending Imple 2021-01-1 2021-02-0 2021-03-1 2021-09-0 IBRD / 88160 Post Direct 5,250.00 0.00 2021-01-04 NE-001-2021-AF / Associat lementation Support ultant Selection mentation 4 4 1 7 e M & E Officer PRDP-IS-NLU-R002-012-SE Component 4: Project Imp Individual Cons Pending Imple 2021-01-1 2021-02-0 2021-03-1 2021-09-0 S-001-2021-AF / Social Saf IBRD / 88160 Post Direct 6,000.00 0.00 2021-01-04 lementation Support ultant Selection mentation 4 4 1 7 eguard Specialist PRDP-IS-NLU-R002-013-SE Component 4: Project Imp Individual Cons Pending Imple 2021-01-1 2021-02-0 2021-03-1 2021-09-0 IBRD / 88160 Post Direct 5,250.00 0.00 2021-01-04 S-002-2021-AF / Associate lementation Support ultant Selection mentation 4 4 1 7 SES Officer PRDP-IS-NLU-R002-014-A Component 4: Project Imp Individual Cons Pending Imple 2021-01-1 2021-02-0 2021-03-1 2021-09-0 IBRD / 88160 Post Direct 5,250.00 0.00 2021-01-04 CE-001-2021-AF / Writer lementation Support ultant Selection mentation 4 4 1 7 PRDP-IS-NLU-R002-015-FI Component 4: Project Imp Individual Cons Pending Imple 2021-01-1 2021-02-0 2021-03-1 2021-09-0 IBRD / 88160 Post Direct 5,250.00 0.00 2021-01-04 N-001-2021-AF / Finance A lementation Support ultant Selection mentation 4 4 1 7 nalyst I PRDP-IS-NLU-R002-016-A Component 4: Project Imp Individual Cons Pending Imple 2021-01-1 2021-02-0 2021-03-1 2021-09-0 IBRD / 88160 Post Direct 5,250.00 0.00 2021-01-04 CT-001-2021-AF / Budget lementation Support ultant Selection mentation 4 4 1 7 Analyst PRDP-IS-NLU-R002-017-A Component 4: Project Imp Individual Cons Pending Imple 2021-01-1 2021-02-0 2021-03-1 2021-09-0 IBRD / 88160 Post Direct 5,250.00 0.00 2021-01-04 CT--002-2021-AF / Finance lementation Support ultant Selection mentation 4 4 1 7 Analyst I PRDP-IS-NLU-R003-001-D Component 4: Project Imp Individual Cons Pending Imple 2021-01-1 2021-02-0 2021-03-1 2021-09-0 IBRD / 88160 Post Direct 3,750.00 0.00 2021-01-04 PD-001-2021-AF / Administ lementation Support ultant Selection mentation 4 4 1 7 rative /Officer II PRDP-IS-NLU-R003-002-D Component 4: Project Imp Individual Cons Pending Imple 2021-01-1 2021-02-0 2021-03-1 2021-09-0 IBRD / 88160 Post Direct 6,000.00 0.00 2021-01-04 PD-002-2021-AF / Economi lementation Support ultant Selection mentation 4 4 1 7 st PRDP-IS-NLU-R003-013-A Component 4: Project Imp Individual Cons Pending Imple 2021-01-1 2021-02-0 2021-03-1 2021-09-0 IBRD / 88160 Post Direct 5,250.00 0.00 2021-01-04 CE-001-2021-AF / Writer lementation Support ultant Selection mentation 4 4 1 7 PRDP-IS-NLU-R003-010-FI Component 4: Project Imp Individual Cons Pending Imple 2021-01-1 2021-02-0 2021-03-1 2021-09-0 IBRD / 88160 Post Direct 5,250.00 0.00 2021-01-04 N-001-2021-AF / Finance A lementation Support ultant Selection mentation 4 4 1 7 nalyst I PRDP-IS-NLU-R003-011-A Component 4: Project Imp Individual Cons Pending Imple 2021-01-1 2021-02-0 2021-03-1 2021-09-0 IBRD / 88160 Post Direct 5,250.00 0.00 2021-01-04 CT-002-2021-AF / Finance lementation Support ultant Selection mentation 4 4 1 7 Analyst I PRDP-IS-NLU-R003-012-B Component 4: Project Imp Individual Cons Pending Imple 2021-01-1 2021-02-0 2021-03-1 2021-09-0 IBRD / 88160 Post Direct 5,250.00 0.00 2021-01-04 UD-001-2021-AF / Budget lementation Support ultant Selection mentation 4 4 1 7 Analyst PRDP-IS-NLU-R003-004-PR Component 4: Project Imp Individual Cons Pending Imple 2021-01-1 2021-02-0 2021-03-1 2021-09-0 IBRD / 88160 Post Direct 6,000.00 0.00 2021-01-04 O-001-2021-AF / Procurem lementation Support ultant Selection mentation 4 4 1 7 ent Officer PRDP-IS-NLU-R003-005-PR Component 4: Project Imp Individual Cons Pending Imple 2021-01-1 2021-02-0 2021-03-1 2021-09-0 O-002-2021-AF / Associate IBRD / 88160 Post Direct 5,250.00 0.00 2021-01-04 lementation Support ultant Selection mentation 4 4 1 7 Procurement Officer PRDP-IS-NLU-R003-008-M Component 4: Project Imp Individual Cons Pending Imple 2021-01-1 2021-02-0 2021-03-1 2021-09-0 IBRD / 88160 Post Direct 6,000.00 0.00 2021-01-04 NE-001-2021-AF / M&E Offi lementation Support ultant Selection mentation 4 4 1 7 cer PRDP-IS-NLU-R003-009-M Component 4: Project Imp Individual Cons Pending Imple 2021-01-1 2021-02-0 2021-03-1 2021-09-0 IBRD / 88160 Post Direct 5,250.00 0.00 2021-01-04 NE-002-2021-AF / Associat lementation Support ultant Selection mentation 4 4 1 7 e M&E Officer PRDP-IS-NLU-R003-006-SE Component 4: Project Imp Individual Cons Pending Imple 2021-01-1 2021-02-0 2021-03-1 2021-09-0 IBRD / 88160 Post Direct 6,000.00 0.00 2021-01-04 S-001-2021-AF / SES Office lementation Support ultant Selection mentation 4 4 1 7 r PRDP-IS-NLU-R003-007-SE Component 4: Project Imp Individual Cons Pending Imple 2021-01-1 2021-02-0 2021-03-1 2021-09-0 IBRD / 88160 Post Direct 5,250.00 0.00 2021-01-04 S-002-2021-AF / Associate lementation Support ultant Selection mentation 4 4 1 7 SES Officer PRDP-IS-NLU-R003-003-G Component 4: Project Imp Individual Cons Pending Imple 2021-01-1 2021-02-0 2021-03-1 2021-09-0 IBRD / 88160 Post Direct 6,000.00 0.00 2021-01-04 GU-001-2021-AF / GIS Offi lementation Support ultant Selection mentation 4 4 1 7 cer PRDP-IS-NLU-R003-014-IB Component 2: Infrastructu Individual Cons Pending Imple 2021-01-1 2021-02-0 2021-03-1 2021-09-0 -001-2021-AF / Rural Infras IBRD / 88160 Post Direct 6,000.00 0.00 2021-01-04 re Development ultant Selection mentation 4 4 1 7 tructure Engineer PRDP-IS-NLU-R003-015-IB Component 2: Infrastructu Individual Cons Pending Imple 2021-01-1 2021-02-0 2021-03-1 2021-09-0 -002-2021-AF / Rural Infras IBRD / 88160 Post Direct 6,000.00 0.00 2021-01-04 re Development ultant Selection mentation 4 4 1 7 tructure Engineer PRDP-IS-NLU-R003-016-IB Component 2: Infrastructu Individual Cons Pending Imple 2021-01-1 2021-02-0 2021-03-1 2021-09-0 -003-2021-AF / Rural Infras IBRD / 88160 Post Direct 6,000.00 0.00 2021-01-04 re Development ultant Selection mentation 4 4 1 7 tructure Engineer PRDP-IS-NLU-R003-016-IB Component 2: Infrastructu Individual Cons Pending Imple 2021-01-1 2021-02-0 2021-03-1 2021-09-0 -004-2021F-AF / Rural Infr IBRD / 88160 Post Direct 6,000.00 0.00 2021-01-04 re Development ultant Selection mentation 4 4 1 7 astructure Engineer PRDP-IS-NLU-R003-016-IB Component 2: Infrastructu Individual Cons Pending Imple 2021-01-1 2021-02-0 2021-03-1 2021-09-0 -005-2021F-AF / Rural Infr IBRD / 88160 Post Direct 6,000.00 0.00 2021-01-04 re Development ultant Selection mentation 4 4 1 7 astructure Engineer PRDP-IS-NLU-R003-017-IB Component 2: Infrastructu Individual Cons Pending Imple 2021-01-1 2021-02-0 2021-03-1 2021-09-0 -004-2021-AF / Project Dev IBRD / 88160 Post Direct 3,750.00 0.00 2021-01-04 re Development ultant Selection mentation 4 4 1 7 elopment Associate PRDP-IS-NLU-001-IPLAN-0 Component 1: Local and Individual Cons 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 20,160.00 0.00 Under Review 2022-01-01 01-2022-AF2 / I-PLAN Com National Level Planning ultant Selection 5 1 1 8 4 ponent Head PRDP-IS-NLU-002-IPLAN-0 Component 1: Local and Individual Cons Under Impleme 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 12,960.00 0.00 2022-01-01 01-2022-AF2 / Planning Off National Level Planning ultant Selection ntation 5 1 1 8 4 icer PRDP-IS-NLU-002-IPLAN-0 Component 1: Local and Individual Cons Under Impleme 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 12,960.00 0.00 2022-01-01 02-2022-AF2 / Planning Off National Level Planning ultant Selection ntation 5 1 1 8 4 icer PRDP-IS-NLU-003-IPLAN-0 Component 1: Local and Individual Cons Under Impleme 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 01-2022-AF2 / Project Dev IBRD / 92710 Post Direct 8,640.00 0.00 2022-01-01 National Level Planning ultant Selection ntation 5 1 1 8 4 elopment Associate PRDP-IS-NLU-001-IREAP-0 Component 3. Enterprise Individual Cons Under Impleme 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 20,160.00 0.00 2022-01-01 01-2022-AF2 / I-REAP Com Development ultant Selection ntation 5 1 1 8 4 ponent Head PRDP-IS-NLU-002-IREAP-0 Component 3. Enterprise Individual Cons Under Impleme 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 01-2022-AF2 / Enterprise IBRD / 92710 Post Direct 14,400.00 0.00 2022-01-01 Development ultant Selection ntation 5 1 1 8 4 Development & Marketing Specialist PRDP-IS-NLU-002-IREAP-0 Component 3. Enterprise Individual Cons Under Impleme 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 02-2022-AF2 / Enterprise IBRD / 92710 Post Direct 14,400.00 0.00 2022-01-01 Development ultant Selection ntation 5 1 1 8 4 Development & Marketing Specialist PRDP-IS-NLU-003-IREAP-0 Component 3. Enterprise Individual Cons Under Impleme 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 01-2022-AF2 / Business De IBRD / 92710 Post Direct 12,960.00 0.00 2022-01-01 Development ultant Selection ntation 5 1 1 8 4 velopment Officer PRDP-IS-NLU-003-IREAP-0 Component 3. Enterprise Individual Cons Under Impleme 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 02-2022-AF2 / Business De IBRD / 92710 Post Direct 12,960.00 0.00 2022-01-01 Development ultant Selection ntation 5 1 1 8 4 velopment Officer PRDP-IS-NLU-004-IREAP-0 Component 3. Enterprise Individual Cons Under Impleme 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 8,640.00 0.00 2022-01-01 01-2022-AF2 / Project Dev' Development ultant Selection ntation 5 1 1 8 4 t Associate PRDP-IS-NLU-001-IB-001-2 Component 2: Infrastructu Individual Cons Under Impleme 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 20,160.00 0.00 2022-01-01 022-AF2 / I-BUILD Compon re Development ultant Selection ntation 5 1 1 8 4 ent Head PRDP-IS-NLU-002-IB-002-2 Component 2: Infrastructu Individual Cons 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 14,400.00 0.00 Under Review 2022-01-01 022-AF2 / Roads and Bridg re Development ultant Selection 5 1 1 8 4 es Specialist PRDP-IS-NLU-003-IB-001-2 Component 2: Infrastructu Individual Cons Under Impleme 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 022-AF2 / Rural Infrastruct IBRD / 92710 Post Direct 12,960.00 0.00 2022-01-01 re Development ultant Selection ntation 5 1 1 8 4 ure Engineer (RIE) PRDP-IS-NLU-003-IB-002-2 Component 2: Infrastructu Individual Cons Under Impleme 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 022-AF2 / Rural Infrastruct IBRD / 92710 Post Direct 12,960.00 0.00 2022-01-01 re Development ultant Selection ntation 5 1 1 8 4 ure Engineer (RIE) PRDP-IS-NLU-003-IB-003-2 Component 2: Infrastructu Individual Cons Under Impleme 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 022-AF2 / Rural Infrastruct IBRD / 92710 Post Direct 12,960.00 0.00 2022-01-01 re Development ultant Selection ntation 5 1 1 8 4 ure Engineer (RIE) PRDP-IS-NLU-004-IB-004-2 Component 2: Infrastructu Individual Cons Under Impleme 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 022-AF2 / Project Develop IBRD / 92710 Post Direct 8,640.00 0.00 2022-01-01 re Development ultant Selection ntation 5 1 1 8 4 ment Associate (PDA) PRDP-IS-NLU-001-DPD-00 Component 4: Project Imp Individual Cons 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 12,960.00 0.00 Under Review 2022-01-01 1-2022-AF2 / Economist lementation Support ultant Selection 5 1 1 8 4 PRDP-IS-NLU-002-DPD-00 Component 4: Project Imp Individual Cons Under Impleme 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 14,400.00 0.00 2022-01-01 1-2022-AF2 / Compliance lementation Support ultant Selection ntation 5 1 1 8 4 Officer PRDP-IS-NLU-001-ACE-00 Component 4: Project Imp Individual Cons Under Impleme 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 11,520.00 0.00 2022-01-01 1-2022-AF2 / Writer lementation Support ultant Selection ntation 5 1 1 8 4 PRDP-IS-NLU-002-ACE-00 Component 4: Project Imp Individual Cons Under Impleme 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 12,960.00 0.00 2022-01-01 1-2022-AF2 / Media Produc lementation Support ultant Selection ntation 5 1 1 8 4 tion Officer PRDP-IS-NLU-001-PROC-0 Component 4: Project Imp Individual Cons Under Impleme 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 18,720.00 0.00 2022-01-01 01-2022-AF2 / Procuremen lementation Support ultant Selection ntation 5 1 1 8 4 t Unit Head PRDP-IS-NLU-002-PROC-0 Component 4: Project Imp Individual Cons 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 12,960.00 0.00 Under Review 2022-01-01 01-2022-AF2 / Procuremen lementation Support ultant Selection 5 1 1 8 4 t Officer PRDP-IS-NLU-002-PROC-0 Component 4: Project Imp Individual Cons Under Impleme 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 12,960.00 0.00 2022-01-01 02-2022-AF2 / Procuremen lementation Support ultant Selection ntation 5 1 1 8 4 t Officer PRDP-IS-NLU-003-PROC-0 Component 4: Project Imp Individual Cons 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 01-2022-AF2 / Associate Pr IBRD / 92710 Post Direct 11,520.00 0.00 Under Review 2022-01-01 lementation Support ultant Selection 5 1 1 8 4 ocurement Officer PRDP-IS-NLU-001-MNE-00 Component 4: Project Imp Individual Cons Under Impleme 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 14,400.00 0.00 2022-01-01 1-2022-AF2 / M&E Speciali lementation Support ultant Selection ntation 5 1 1 8 4 st PRDP-IS-NLU-002-MNE-00 Component 4: Project Imp Individual Cons Under Impleme 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 12,960.00 0.00 2022-01-01 1-2022-AF2 / M&E Officer lementation Support ultant Selection ntation 5 1 1 8 4 PRDP-IS-NLU-001-FIN-001- Component 4: Project Imp Individual Cons Under Impleme 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 14,400.00 0.00 2022-01-01 2022-AF2 / Financial Analy lementation Support ultant Selection ntation 5 1 1 8 4 st III PRDP-IS-NLU-002-FIN-001- Component 4: Project Imp Individual Cons Under Impleme 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 12,960.00 0.00 2022-01-01 2022-AF2 / Financial Analy lementation Support ultant Selection ntation 5 1 1 8 4 st II PRDP-IS-NLU-002-FIN-002- Component 4: Project Imp Individual Cons Under Impleme 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 12,960.00 0.00 2022-01-01 2022-AF2 / Financial Analy lementation Support ultant Selection ntation 5 1 1 8 4 st II PRDP-IS-NLU-003-FIN-001- Component 4: Project Imp Individual Cons Under Impleme 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 2022-AF2 / Financial Analy IBRD / 92710 Post Direct 12,960.00 0.00 2022-01-01 lementation Support ultant Selection ntation 5 1 1 8 4 st II (Accountant) Page 11 PRDP-IS-NLU-004-FIN-001- Component 4: Project Imp Individual Cons Under Impleme 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 11,520.00 0.00 2022-01-01 2022-AF2 / Financial Analy lementation Support ultant Selection ntation 5 1 1 8 4 st I PRDP-IS-NLU-005-FIN-001- Component 4: Project Imp Individual Cons Pending Imple 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 11,520.00 0.00 2022-01-01 2022-AF2 / Budget Analyst lementation Support ultant Selection mentation 1 1 8 4 PRDP-IS-NLU-001-GGU-00 Component 4: Project Imp Individual Cons Pending Imple 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 12,960.00 0.00 2022-01-01 1-2022-AF2 / GIS Data Offi lementation Support ultant Selection mentation 1 1 8 4 cer PRDP-IS-NLU-002-GGU-00 Component 4: Project Imp Individual Cons Pending Imple 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 12,960.00 0.00 2022-01-01 1-2022-AF2 / GIS Data Offi lementation Support ultant Selection mentation 1 1 8 4 cer PRDP-IS-NLU-001-SES-001 Component 4: Project Imp Individual Cons Under Impleme 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 18,720.00 0.00 2022-01-01 -2022-AF2 / SES Unit Head lementation Support ultant Selection ntation 5 1 1 8 4 PRDP-IS-NLU-002-SES-001 Component 4: Project Imp Individual Cons 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 -2022-AF2 / Social and Env IBRD / 92710 Post Direct 14,400.00 0.00 Under Review 2022-01-01 lementation Support ultant Selection 5 1 1 8 4 ironmental Safeguard Spe cialist PRDP-IS-NLU-003-SES-001 Component 4: Project Imp Individual Cons Under Impleme 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 -2022-AF2 / Social and Env IBRD / 92710 Post Direct 12,960.00 0.00 2022-01-01 lementation Support ultant Selection ntation 5 1 1 8 4 ironemental Safeguards Of ficer PRDP-IS-NLU-004-SES-001 Component 4: Project Imp Individual Cons 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 11,520.00 0.00 Under Review 2022-01-01 -2022-AF2 / Associate SES lementation Support ultant Selection 5 1 1 8 4 Officer PRDP-IS-NLU-001-ADM-00 Component 4: Project Imp Individual Cons Under Impleme 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 10,080.00 0.00 2022-01-01 1-2022-AF2 / Administrativ lementation Support ultant Selection ntation 5 1 1 8 4 e Officer III PRDP-IS-NLU-002-ADM-00 Component 4: Project Imp Individual Cons Under Impleme 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 8,640.00 0.00 2022-01-01 1-2022-AF2 / Administrativ lementation Support ultant Selection ntation 5 1 1 8 4 e Officer II PRDP-IS-NLU-002-ADM-00 Component 4: Project Imp Individual Cons Under Impleme 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 8,640.00 0.00 2022-01-01 2-2022-AF2 / Administrativ lementation Support ultant Selection ntation 5 1 1 8 4 e Officer II PRDP-IS-RCAR-001-IPLAN- Component 1: Local and Individual Cons Under Impleme 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 11,520.00 0.00 2022-01-01 001-2022-AF2 / Planning O National Level Planning ultant Selection ntation 5 1 1 8 4 fficer PRDP-IS-RCAR-001-IPLAN- Component 1: Local and Individual Cons Under Impleme 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 11,520.00 0.00 2022-01-01 002-2022-AF2 / Planning O National Level Planning ultant Selection ntation 5 1 1 8 4 fficer PRDP-IS-RCAR-001-IREAP- Component 3. Enterprise Individual Cons Under Impleme 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 001-2022-AF2 / Enterprise IBRD / 92710 Post Direct 12,960.00 0.00 2022-01-01 Development ultant Selection ntation 5 1 1 8 4 Development and Marketi ng Specialist PRDP-IS-RCAR-002-IREAP- Component 3. Enterprise Individual Cons Under Impleme 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 001-2022-AF2 / Business D IBRD / 92710 Post Direct 11,520.00 0.00 2022-01-01 Development ultant Selection ntation 5 1 1 8 4 evelopment Officer PRDP-IS-RCAR-002-IREAP- Component 3. Enterprise Individual Cons Under Impleme 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 002-2022-AF2 / Business D IBRD / 92710 Post Direct 11,520.00 0.00 2022-01-01 Development ultant Selection ntation 5 1 1 8 4 evelopment Officer PRDP-IS-RCAR-002-IREAP- Component 3. Enterprise Individual Cons Under Impleme 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 003-2022-AF2 / Business D IBRD / 92710 Post Direct 11,520.00 0.00 2022-01-01 Development ultant Selection ntation 5 1 1 8 4 evelopment Officer PRDP-IS-RCAR-002-IREAP- Component 3. Enterprise Individual Cons Under Impleme 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 004-2022-AF2 / Business D IBRD / 92710 Post Direct 11,520.00 0.00 2022-01-01 Development ultant Selection ntation 5 1 1 8 4 evelopment Officer PRDP-IS-RCAR-003-IREAP- Component 3. Enterprise Individual Cons Under Impleme 2021-12-2 2022-01-1 2022-02-0 2022-03-0 2022-09-0 001-2022-AF2 / Project De IBRD / 92710 Post Direct 7,200.00 0.00 2022-01-01 Development ultant Selection ntation 0 1 1 8 4 veloment Associate PRDP-IS-RCAR-001-IBUILD Component 2: Infrastructu Individual Cons Under Impleme 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 -001-2022-AF2 / Rural Infr IBRD / 92710 Post Direct 11,520.00 0.00 2022-01-01 re Development ultant Selection ntation 5 1 1 8 4 astructure Engineer ( RIE) PRDP-IS-RCAR-001-IBUILD Component 2: Infrastructu Individual Cons Under Impleme 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 -002-2022-AF2 / Rural Infr IBRD / 92710 Post Direct 11,520.00 0.00 2022-01-01 re Development ultant Selection ntation 5 1 1 8 4 astructure Engineer ( RIE) PRDP-IS-RCAR-001-IBUILD Component 2: Infrastructu Individual Cons Under Impleme 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 -003-2022-AF2 / Rural Infr IBRD / 92710 Post Direct 11,520.00 0.00 2022-01-01 re Development ultant Selection ntation 5 1 1 8 4 astructure Engineer ( RIE) PRDP-IS-RCAR-001-IBUILD Component 2: Infrastructu Individual Cons Under Impleme 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 -004-2022-AF2 / Rural Infr IBRD / 92710 Post Direct 11,520.00 0.00 2022-01-01 re Development ultant Selection ntation 5 1 1 8 4 astructure Engineer ( RIE) PRDP-IS-RCAR-001-IBUILD Component 2: Infrastructu Individual Cons Under Impleme 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 -005-2022-AF2 / Rural Infr IBRD / 92710 Post Direct 11,520.00 0.00 2022-01-01 re Development ultant Selection ntation 5 1 1 8 4 astructure Engineer ( RIE) PRDP-IS-RCAR-001-IBUILD Component 2: Infrastructu Individual Cons Under Impleme 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 -006-2022-AF2 / Rural Infr IBRD / 92710 Post Direct 11,520.00 0.00 2022-01-01 re Development ultant Selection ntation 5 1 1 8 4 astructure Engineer ( RIE) PRDP-IS-RCAR-002-IBUILD Component 2: Infrastructu Individual Cons Under Impleme 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 -001-2022-AF2 / Project De IBRD / 92710 Post Direct 7,200.00 0.00 2022-01-01 re Development ultant Selection ntation 5 1 1 8 4 velopment Associate (PDA ) PRDP-IS-RCAR-001-ECON- Component 4: Project Imp Individual Cons Under Impleme 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 11,520.00 0.00 2022-01-01 001-2022-AF2 / Economist lementation Support ultant Selection ntation 5 1 1 8 4 PRDP-IS-RCAR-001-GGU-0 Component 4: Project Imp Individual Cons 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 11,520.00 0.00 Under Review 2022-01-01 01-2022-AF2 / GIS Data Of lementation Support ultant Selection 5 1 1 8 4 ficer PRDP-IS-RCAR-001-PROC- Component 4: Project Imp Individual Cons Under Impleme 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 11,520.00 0.00 2022-01-01 001-2022-AF2 / Procureme lementation Support ultant Selection ntation 5 1 1 8 4 nt Officer PRDP-IS-RCAR-002-PROC- Component 4: Project Imp Individual Cons Under Impleme 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 001-2022-AF2 / Associate IBRD / 92710 Post Direct 10,080.00 0.00 2022-01-01 lementation Support ultant Selection ntation 5 1 1 8 4 Procurement Officer PRDP-IS-RCAR-001-MNE-0 Component 4: Project Imp Individual Cons Under Impleme 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 10,080.00 0.00 2022-01-01 01-2022-AF2 / Associate M lementation Support ultant Selection ntation 5 1 1 8 4 &E Officer PRDP-IS-RCAR-001-SES-00 Component 4: Project Imp Individual Cons Under Impleme 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 11,520.00 0.00 2022-01-01 1-2022-AF2 / SES Officer lementation Support ultant Selection ntation 5 1 1 8 4 PRDP-IS-RCAR-002-SES-00 Component 4: Project Imp Individual Cons Under Impleme 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 5,040.00 0.00 2022-01-01 1-2022-AF2 / Associate SE lementation Support ultant Selection ntation 5 1 1 8 4 S Officer PRDP-IS-RCAR-002-SES-00 Component 4: Project Imp Individual Cons Under Impleme 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 5,040.00 0.00 2022-01-01 2-2022-AF2 / Associate SE lementation Support ultant Selection ntation 5 1 1 8 4 S Officer PRDP-IS-RCAR-001-ACE-0 Component 4: Project Imp Individual Cons Under Impleme 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 10,080.00 0.00 2022-01-01 01-2022-AF2 / Writer lementation Support ultant Selection ntation 5 1 1 8 4 PRDP-IS-RCAR-001-FIN-00 Component 4: Project Imp Individual Cons Under Impleme 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 10,080.00 0.00 2022-01-01 1-2022-AF2 / Finance Anal lementation Support ultant Selection ntation 5 1 1 8 4 yst PRDP-IS-RCAR-001-FIN-00 Component 4: Project Imp Individual Cons Under Impleme 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 10,080.00 0.00 2022-01-01 2-2022-AF2 / Finance Anal lementation Support ultant Selection ntation 5 1 1 8 4 yst PRDP-IS-R1-001-IPLAN-00 Component 1: Local and Individual Cons 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 11,520.00 0.00 Under Review 2022-01-01 1-2022-AF2 / Planning Offi National Level Planning ultant Selection 5 1 1 8 4 cer PRDP-IS-R1-001-IPLAN-00 Component 1: Local and Individual Cons 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 11,520.00 0.00 Under Review 2022-01-01 2-2022-AF2 / Planning Offi National Level Planning ultant Selection 5 1 1 8 4 cer PRDP-IS-R1-001-IREAP-00 Component 3. Enterprise Individual Cons 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 1-2022-AF2 / Enterprise D IBRD / 92710 Post Direct 12,960.00 0.00 Under Review 2022-01-01 Development ultant Selection 5 1 1 8 4 evelopment and Marketing Specialist PRDP-IS-R1-002-IREAP-00 Component 3. Enterprise Individual Cons 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 1-2022-AF2 / Business Dev IBRD / 92710 Post Direct 11,520.00 0.00 Under Review 2022-01-01 Development ultant Selection 5 1 1 8 4 elopment Officer PRDP-IS-R1-002-IREAP-00 Component 3. Enterprise Individual Cons 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 3-2022-AF2 / Business Dev IBRD / 92710 Post Direct 11,520.00 0.00 Under Review 2022-01-01 Development ultant Selection 5 1 1 8 4 elopment Officer PRDP-IS-R1-002-IREAP-00 Component 3. Enterprise Individual Cons 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 4-2022-AF2 / Business Dev IBRD / 92710 Post Direct 11,520.00 0.00 Under Review 2022-01-01 Development ultant Selection 5 1 1 8 4 elopment Officer PRDP-IS-R1-003-IREAP-00 Component 3. Enterprise Individual Cons 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 1-2022-AF2 / Project Devel IBRD / 92710 Post Direct 7,200.00 0.00 Under Review 2022-01-01 Development ultant Selection 5 1 1 8 4 oment Associate PRDP-IS-R1-001-IBUILD-00 Component 2: Infrastructu Individual Cons 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 1-2022-AF2 / Rural Infrastr IBRD / 92710 Post Direct 12,960.00 0.00 Under Review 2022-01-01 re Development ultant Selection 5 1 1 8 4 ucture Specialist PRDP-IS-R1-002-IBUILD-00 Component 2: Infrastructu Individual Cons 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 1-2022-AF2 / Rural Infrastr IBRD / 92710 Post Direct 11,520.00 0.00 Under Review 2022-01-01 re Development ultant Selection 5 1 1 8 4 ucture Engineer ( RIE) PRDP-IS-R1-002-IBUILD-00 Component 2: Infrastructu Individual Cons 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 2-2022-AF2 / Rural Infrastr IBRD / 92710 Post Direct 11,520.00 0.00 Under Review 2022-01-01 re Development ultant Selection 5 1 1 8 4 ucture Engineer ( RIE) PRDP-IS-R1-002-IBUILD-00 Component 2: Infrastructu Individual Cons 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 3-2022-AF2 / Rural Infrastr IBRD / 92710 Post Direct 11,520.00 0.00 Under Review 2022-01-01 re Development ultant Selection 5 1 1 8 4 ucture Engineer ( RIE) PRDP-IS-R1-002-IBUILD-00 Component 2: Infrastructu Individual Cons 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 4-2022-AF2 / Rural Infrastr IBRD / 92710 Post Direct 11,520.00 0.00 Under Review 2022-01-01 re Development ultant Selection 5 1 1 8 4 ucture Engineer ( RIE) PRDP-IS-R1-003-IBUILD-00 Component 2: Infrastructu Individual Cons 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 1-2022-AF2 / Project Devel IBRD / 92710 Post Direct 7,200.00 0.00 Under Review 2022-01-01 re Development ultant Selection 5 1 1 8 4 opment Associate (PDA) PRDP-IS-R1-001-DPD-001- Component 4: Project Imp Individual Cons 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 7,200.00 0.00 Under Review 2022-01-01 2022-AF2 / Administrative lementation Support ultant Selection 5 1 1 8 4 Officer II PRDP-IS-R1-002-ADM-001- Component 4: Project Imp Individual Cons 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 7,200.00 0.00 Under Review 2022-01-01 2022-AF2 / Administrative lementation Support ultant Selection 5 1 1 8 4 Officer II PRDP-IS-R1-002-ADM-002- Component 4: Project Imp Individual Cons 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 7,200.00 0.00 Under Review 2022-01-01 2022-AF2 / Administrative lementation Support ultant Selection 5 1 1 8 4 Officer II PRDP-IS-R1-002-ADM-003- Component 4: Project Imp Individual Cons 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 7,200.00 0.00 Under Review 2022-01-01 2022-AF2 / Administrative lementation Support ultant Selection 5 1 1 8 4 Officer II PRDP-IS-R1-001-GGU-001- Component 4: Project Imp Individual Cons 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 11,520.00 0.00 Under Review 2022-01-01 2022-AF2 / GIS Officer lementation Support ultant Selection 5 1 1 8 4 PRDP-IS-R1-001-PROC-00 Component 4: Project Imp Individual Cons 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 11,520.00 0.00 Under Review 2022-01-01 1-2022-AF2 / Procurement lementation Support ultant Selection 5 1 1 8 4 Officer PRDP-IS-R1-002-PROC-00 Component 4: Project Imp Individual Cons 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 1-2022-AF2 / Associate Pro IBRD / 92710 Post Direct 10,080.00 0.00 Under Review 2022-01-01 lementation Support ultant Selection 5 1 1 8 4 curement Officer PRDP-IS-R1-001-MNE-001- Component 4: Project Imp Individual Cons 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 11,520.00 0.00 Under Review 2022-01-01 2022-AF2 / M&E Officer lementation Support ultant Selection 5 1 1 8 4 PRDP-IS-R1-002-MNE-001- Component 4: Project Imp Individual Cons 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 10,080.00 0.00 Under Review 2022-01-01 2022-AF2 / Associate M&E lementation Support ultant Selection 5 1 1 8 4 Officer PRDP-IS-R1-001-SES-001- Component 4: Project Imp Individual Cons 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 11,520.00 0.00 Under Review 2022-01-01 2022-AF2 / SES Officer lementation Support ultant Selection 5 1 1 8 4 PRDP-IS-R1-002-SES-001- Component 4: Project Imp Individual Cons 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 5,040.00 0.00 Under Review 2022-01-01 2022-AF2 / Associate SES lementation Support ultant Selection 5 1 1 8 4 Officer PRDP-IS-R1-002-SES-002- Component 4: Project Imp Individual Cons 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 5,040.00 0.00 Under Review 2022-01-01 2022-AF2 / Associate SES lementation Support ultant Selection 5 1 1 8 4 Officer Page 12 PRDP-IS-R2-001-IPLAN-00 Component 1: Local and Individual Cons 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 11,520.00 0.00 Under Review 2022-01-01 1-2022-AF2 / Planning Offi National Level Planning ultant Selection 5 1 1 8 4 cer PRDP-IS-R2-001-IPLAN-00 Component 1: Local and Individual Cons 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 11,520.00 0.00 Under Review 2022-01-01 2-2022-AF2 / Planning Offi National Level Planning ultant Selection 5 1 1 8 4 cer PRDP-IS-R2-001-IREAP-00 Component 3. Enterprise Individual Cons 2021-12-2 2022-01-1 2022-02-0 2022-03-0 2022-09-0 1-2022-AF2 / Enterprise D IBRD / 92710 Post Direct 12,960.00 0.00 Under Review 2022-01-01 Development ultant Selection 4 1 1 8 4 evelopment and Marketing Specialist PRDP-IS-R2-002-IREAP-00 Component 3. Enterprise Individual Cons 2021-12-2 2022-01-1 2022-02-0 2022-03-0 2022-09-0 1-2022-AF2 / Business Dev IBRD / 92710 Post Direct 11,520.00 0.00 Under Review 2022-01-01 Development ultant Selection 3 1 1 8 4 elopment Officer PRDP-IS-R2-002-IREAP-00 Component 3. Enterprise Individual Cons 2021-12-2 2022-01-1 2022-02-0 2022-03-0 2022-09-0 2-2022-AF2 / Business Dev IBRD / 92710 Post Direct 11,520.00 0.00 Under Review 2022-01-01 Development ultant Selection 3 1 1 8 4 elopment Officer PRDP-IS-R2-002-IREAP-00 Component 3. Enterprise Individual Cons 2021-12-2 2022-01-1 2022-02-0 2022-03-0 2022-09-0 3-2022-AF2 / Business Dev IBRD / 92710 Post Direct 11,520.00 0.00 Under Review 2022-01-01 Development ultant Selection 3 1 1 8 4 elopment Officer PRDP-IS-R2-002-IREAP-00 Component 3. Enterprise Individual Cons 2021-12-2 2022-01-1 2022-02-0 2022-03-0 2022-09-0 4-2022-AF2 / Business Dev IBRD / 92710 Post Direct 11,520.00 0.00 Under Review 2022-01-01 Development ultant Selection 3 1 1 8 4 elopment Officer PRDP-IS-R2-003-IREAP-00 Component 3. Enterprise Individual Cons 2021-12-2 2022-01-1 2022-02-0 2022-03-0 2022-09-0 1-2022-AF2 / Project Devel IBRD / 92710 Post Direct 7,200.00 0.00 Under Review 2022-01-01 Development ultant Selection 3 1 1 8 4 oment Associate PRDP-IS-R2-001-IBUILD-00 Component 2: Infrastructu Individual Cons 2021-12-2 2022-01-1 2022-02-0 2022-03-0 2022-09-0 1-2022-AF2 / Rural Infrastr IBRD / 92710 Post Direct 12,960.00 0.00 Under Review 2022-01-01 re Development ultant Selection 8 1 1 8 4 ucture Specialist PRDP-IS-R2-002-IBUILD-00 Component 2: Infrastructu Individual Cons 2021-12-2 2022-01-1 2022-02-0 2022-03-0 2022-09-0 1-2022-AF2 / Rural Infrastr IBRD / 92710 Post Direct 11,520.00 0.00 Under Review 2022-01-01 re Development ultant Selection 3 1 1 8 4 ucture Engineer ( RIE) PRDP-IS-R2-002-IBUILD-00 Component 2: Infrastructu Individual Cons 2021-12-2 2022-01-1 2022-02-0 2022-03-0 2022-09-0 2-2022-AF2 / Rural Infrastr IBRD / 92710 Post Direct 11,520.00 0.00 Under Review 2022-01-01 re Development ultant Selection 3 1 1 8 4 ucture Engineer ( RIE) PRDP-IS-R2-002-IBUILD-00 Component 2: Infrastructu Individual Cons 2021-12-2 2022-01-1 2022-02-0 2022-03-0 2022-09-0 3-2022-AF2 / Rural Infrastr IBRD / 92710 Post Direct 11,520.00 0.00 Under Review 2022-01-01 re Development ultant Selection 3 1 1 8 4 ucture Engineer ( RIE) PRDP-IS-R2-002-IBUILD-00 Component 2: Infrastructu Individual Cons 2021-12-2 2022-01-1 2022-02-0 2022-03-0 2022-09-0 4-2022-AF2 / Rural Infrastr IBRD / 92710 Post Direct 11,520.00 0.00 Under Review 2022-01-01 re Development ultant Selection 3 1 1 8 4 ucture Engineer ( RIE) PRDP-IS-R2-002-IBUILD-00 Component 2: Infrastructu Individual Cons 2021-12-2 2022-01-1 2022-02-0 2022-03-0 2022-09-0 5-2022-AF2 / Rural Infrastr IBRD / 92710 Post Direct 11,520.00 0.00 Under Review 2022-01-01 re Development ultant Selection 3 1 1 8 4 ucture Engineer ( RIE) PRDP-IS-R2-002-IBUILD-00 Component 2: Infrastructu Individual Cons 2021-12-2 2022-01-1 2022-02-0 2022-03-0 2022-09-0 6-2022-AF2 / Rural Infrastr IBRD / 92710 Post Direct 11,520.00 0.00 Under Review 2022-01-01 re Development ultant Selection 3 1 1 8 4 ucture Engineer ( RIE) PRDP-IS-R2-003-IBUILD-00 Component 2: Infrastructu Individual Cons 2021-12-2 2022-01-1 2022-02-0 2022-03-0 2022-09-0 1-2022-AF2 / Project Devel IBRD / 92710 Post Direct 7,200.00 0.00 Under Review 2022-01-01 re Development ultant Selection 3 1 1 8 4 opment Associate (PDA) PRDP-IS-R2-001-DPD-001- Component 4: Project Imp Individual Cons 2021-12-2 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 7,200.00 0.00 Under Review 2022-01-01 2022-AF2 / Administrative lementation Support ultant Selection 3 1 1 8 4 Officer II PRDP-IS-R2-002-DPD-001- Component 4: Project Imp Individual Cons 2021-12-2 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 7,200.00 0.00 Under Review 2022-01-01 2022-AF2 / Economist lementation Support ultant Selection 3 1 1 8 4 PRDP-IS-R2-001-FIN-001-2 Component 4: Project Imp Individual Cons 2021-12-2 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 10,080.00 0.00 Under Review 2022-01-01 022-AF2 / Financial Analys lementation Support ultant Selection 3 1 1 8 4 tI PRDP-IS-R2-002-ACC-002- Component 4: Project Imp Individual Cons 2021-12-2 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 10,080.00 0.00 Under Review 2022-01-01 2022-AF2 / Financial Analy lementation Support ultant Selection 3 1 1 8 4 st I PRDP-IS-R2-001-BUD-001- Component 4: Project Imp Individual Cons 2021-12-2 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 10,080.00 0.00 Under Review 2022-01-01 2022-AF2 / Budget Analyst lementation Support ultant Selection 3 1 1 8 4 PRDP-IS-R2-001-PROC-00 Component 4: Project Imp Individual Cons 2021-12-2 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 11,520.00 0.00 Under Review 2022-01-01 1-2022-AF2 / Procurement lementation Support ultant Selection 3 1 1 8 4 Officer PRDP-IS-R2-002-PROC-00 Component 4: Project Imp Individual Cons 2021-12-2 2022-01-1 2022-02-0 2022-03-0 2022-09-0 1-2022-AF2 / Associate Pro IBRD / 92710 Post Direct 10,080.00 0.00 Under Review 2022-01-01 lementation Support ultant Selection 3 1 1 8 4 curement Officer PRDP-IS-R2-001-MNE-001- Component 4: Project Imp Individual Cons 2021-12-2 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 11,520.00 0.00 Under Review 2022-01-01 2022-AF2 / M&E Officer lementation Support ultant Selection 3 1 1 8 4 PRDP-IS-R2-002-MNE-001- Component 4: Project Imp Individual Cons 2021-12-2 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 10,080.00 0.00 Under Review 2022-01-01 2022-AF2 / Associate M&E lementation Support ultant Selection 3 1 1 8 4 Officer PRDP-IS-R2-001-SES-001- Component 4: Project Imp Individual Cons 2021-12-2 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 11,520.00 0.00 Under Review 2022-01-01 2022-AF2 / SES Officer lementation Support ultant Selection 3 1 1 8 4 PRDP-IS-R2-002-SES-001- Component 4: Project Imp Individual Cons 2021-12-2 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 10,080.00 0.00 Under Review 2022-01-01 2022-AF2 / Associate SES lementation Support ultant Selection 3 1 1 8 4 Officer PRDP-IS-R2-002-SES-002- Component 4: Project Imp Individual Cons 2021-12-2 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 10,080.00 0.00 Under Review 2022-01-01 2022-AF2 / Associate SES lementation Support ultant Selection 3 1 1 8 4 Officer PRDP-IS-R2-001-GGU-001- Component 4: Project Imp Individual Cons 2021-12-2 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 11,520.00 0.00 Under Review 2022-01-01 2022-AF2 / GIS Officer lementation Support ultant Selection 4 1 1 8 4 PRDP-IS-R2-001-INFO-001 Component 4: Project Imp Individual Cons 2021-12-2 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 10,080.00 0.00 Under Review 2022-01-01 -2022-AF2 / Writer lementation Support ultant Selection 4 1 1 8 4 PRDP-IS-R3-001-IPLAN-00 Component 1: Local and Individual Cons Under Impleme 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 11,520.00 0.00 2022-01-01 1-2022-AF2 / Planning Offi National Level Planning ultant Selection ntation 5 1 1 8 4 cer PRDP-IS-R3-0013-IPLAN-0 Component 1: Local and Individual Cons Under Impleme 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 11,520.00 0.00 2022-01-01 02-2022-AF2 / Planning Off National Level Planning ultant Selection ntation 5 1 1 8 4 icer PRDP-IS-R3-001-IREAP-00 Component 3. Enterprise Individual Cons Under Impleme 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 1-2022-AF2 / Enterprise D IBRD / 92710 Post Direct 12,960.00 0.00 2022-01-01 Development ultant Selection ntation 5 1 1 8 4 evelopment and Marketing Specialist PRDP-IS-R3-002-IREAP-00 Component 3. Enterprise Individual Cons Under Impleme 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 1-2022-AF2 / Business Dev IBRD / 92710 Post Direct 11,520.00 0.00 2022-01-01 Development ultant Selection ntation 5 1 1 8 4 elopment Officer PRDP-IS-R3-002-IREAP-00 Component 3. Enterprise Individual Cons Under Impleme 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 2-2022-AF2 / Business Dev IBRD / 92710 Post Direct 11,520.00 0.00 2022-01-01 Development ultant Selection ntation 5 1 1 8 4 elopment Officer PRDP-IS-R3-002-IREAP-00 Component 3. Enterprise Individual Cons Under Impleme 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 3-2022-AF2 / Business Dev IBRD / 92710 Post Direct 11,520.00 0.00 2022-01-01 Development ultant Selection ntation 5 1 1 8 4 elopment Officer PRDP-IS-R3-002-IREAP-00 Component 3. Enterprise Individual Cons Under Impleme 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 4-2022-AF2 / Business Dev IBRD / 92710 Post Direct 11,520.00 0.00 2022-01-01 Development ultant Selection ntation 5 1 1 8 4 elopment Officer PRDP-IS-R3-002-IREAP-00 Component 3. Enterprise Individual Cons Under Impleme 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 5-2022-AF2 / Business Dev IBRD / 92710 Post Direct 11,520.00 0.00 2022-01-01 Development ultant Selection ntation 5 1 1 8 4 elopment Officer PRDP-IS-R3-003-IREAP-00 Component 3. Enterprise Individual Cons Under Impleme 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 1-2022-AF2 / Project Devel IBRD / 92710 Post Direct 7,200.00 0.00 2022-01-01 Development ultant Selection ntation 5 1 1 8 4 oment Associate PRDP-IS-R3-001-IBUILD-00 Component 2: Infrastructu Individual Cons 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 1-2022-AF2 / Rural Infrastr IBRD / 92710 Post Direct 11,520.00 0.00 Under Review 2022-01-01 re Development ultant Selection 5 1 1 8 4 ucture Engineer ( RIE) PRDP-IS-R3-001-IBUILD-00 Component 2: Infrastructu Individual Cons 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 2-2022-AF2 / Rural Infrastr IBRD / 92710 Post Direct 11,520.00 0.00 Under Review 2022-01-01 re Development ultant Selection 5 1 1 8 4 ucture Engineer ( RIE) PRDP-IS-R3-001-IBUILD-00 Component 2: Infrastructu Individual Cons 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 3-2022-AF2 / Rural Infrastr IBRD / 92710 Post Direct 11,520.00 0.00 Under Review 2022-01-01 re Development ultant Selection 5 1 1 8 4 ucture Engineer ( RIE) PRDP-IS-R3-001-IBUILD-00 Component 2: Infrastructu Individual Cons 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 4-2022-AF2 / Rural Infrastr IBRD / 92710 Post Direct 11,520.00 0.00 Under Review 2022-01-01 re Development ultant Selection 5 1 1 8 4 ucture Engineer ( RIE) PRDP-IS-R3-001-IBUILD-00 Component 2: Infrastructu Individual Cons 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 5-2022-AF2 / Rural Infrastr IBRD / 92710 Post Direct 11,520.00 0.00 Under Review 2022-01-01 re Development ultant Selection 5 1 1 8 4 ucture Engineer ( RIE) PRDP-IS-R3-001-IBUILD-00 Component 2: Infrastructu Individual Cons 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 6-2022-AF2 / Rural Infrastr IBRD / 92710 Post Direct 11,520.00 0.00 Under Review 2022-01-01 re Development ultant Selection 5 1 1 8 4 ucture Engineer ( RIE) PRDP-IS-R3-001-IBUILD-00 Component 2: Infrastructu Individual Cons 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 7-2022-AF2 / Rural Infrastr IBRD / 92710 Post Direct 11,520.00 0.00 Under Review 2022-01-01 re Development ultant Selection 5 1 1 8 4 ucture Engineer ( RIE) PRDP-IS-R3-002-IBUILD-00 Component 2: Infrastructu Individual Cons 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 1-2022-AF2 / Project Devel IBRD / 92710 Post Direct 7,200.00 0.00 Under Review 2022-01-01 re Development ultant Selection 5 1 1 8 4 opment Associate (PDA) PRDP-IS-R3-001-ADM-001- Component 4: Project Imp Individual Cons 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 7,200.00 0.00 Under Review 2022-01-01 2022-AF2 / Administrative lementation Support ultant Selection 5 1 1 8 4 Officer II PRDP-IS-R3-002-DPD-001- Component 4: Project Imp Individual Cons 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 11,520.00 0.00 Under Review 2022-01-01 2022-AF2 / Economist lementation Support ultant Selection 5 1 1 8 4 PRDP-IS-R3-003-GGU-001- Component 4: Project Imp Individual Cons Under Impleme 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 11,520.00 0.00 2022-01-01 2022-AF2 / GIS Officer lementation Support ultant Selection ntation 5 1 1 8 4 PRDP-IS-R3-004-PROC-00 Component 4: Project Imp Individual Cons 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 11,520.00 0.00 Under Review 2022-01-01 1-2022-AF2 / Procurement lementation Support ultant Selection 5 1 1 8 4 Officer PRDP-IS-R3-005-SES-001- Component 4: Project Imp Individual Cons 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 11,520.00 0.00 Under Review 2022-01-01 2022-AF2 / SES Officer lementation Support ultant Selection 5 1 1 8 4 PRDP-IS-R3-006-MNE-001- Component 4: Project Imp Individual Cons 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 11,520.00 0.00 Under Review 2022-01-01 2022-AF2 / M&E Officer lementation Support ultant Selection 5 1 1 8 4 PRDP-IS-R3-007-MNE-001- Component 4: Project Imp Individual Cons 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 10,080.00 0.00 Under Review 2022-01-01 2022-AF2 / Associate M&E lementation Support ultant Selection 5 1 1 8 4 Officer PRDP-IS-R3-008-PROC-00 Component 4: Project Imp Individual Cons 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 1-2022-AF2 / Associate Pro IBRD / 92710 Post Direct 10,080.00 0.00 Under Review 2022-01-01 lementation Support ultant Selection 5 1 1 8 4 curement Officer PRDP-IS-R3-009-SES-001- Component 4: Project Imp Individual Cons 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 10,080.00 0.00 Under Review 2022-01-01 2022-AF2 / Associate SES lementation Support ultant Selection 5 1 1 8 4 Officer PRDP-IS-R3-010-FIN-001-2 Component 4: Project Imp Individual Cons 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 10,080.00 0.00 Under Review 2022-01-01 022-AF2 / Finance Analyst lementation Support ultant Selection 5 1 1 8 4 I PRDP-IS-R3-010-FIN-002-2 Component 4: Project Imp Individual Cons 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 10,080.00 0.00 Under Review 2022-01-01 022-AF2 / Finance Analyst lementation Support ultant Selection 5 1 1 8 4 I PRDP-IS-R3-011-BUD-001- Component 4: Project Imp Individual Cons 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 10,080.00 0.00 Under Review 2022-01-01 2022-AF2 / Budget Analyst lementation Support ultant Selection 5 1 1 8 4 PRDP-IS-R3-012-INFO-001 Component 4: Project Imp Individual Cons 2021-12-0 2022-01-1 2022-02-0 2022-03-0 2022-09-0 IBRD / 92710 Post Direct 10,080.00 0.00 Under Review 2022-01-01 -2022-AF2 / Writer lementation Support ultant Selection 5 1 1 8 4 PRDP-IS-NL-001-DPD-001- Component 4: Project Imp Individual Cons Pending Imple 2022-04-2 2022-05-1 2022-06-1 2022-12-1 IBRD / 92710 Post Open 7,200.00 0.00 2022-03-06 2022-AF2.ADD / Administr lementation Support ultant Selection mentation 4 5 9 6 ative Officer II Page 13 PRDP-IS-NLU-001-IREAP-0 Component 3. Enterprise Individual Cons Pending Imple 2022-02-1 2022-03-1 2022-04-1 2022-10-1 01-2022-AF2A / Organizati IBRD / 92710 Post Open 14,880.00 0.00 2022-01-01 Development ultant Selection mentation 9 2 6 3 onal Development Speciali st PRDP-IS-R1-001-IREAP-00 Component 3. Enterprise Individual Cons Pending Imple 2022-04-2 2022-05-1 2022-06-1 2022-12-1 1-2022-AF2A / Organizatio IBRD / 92710 Post Open 12,000.00 0.00 2022-03-06 Development ultant Selection mentation 4 5 9 6 nal Development Officer PRDP-IS-R1-001-PROC-00 Component 4: Project Imp Individual Cons Pending Imple 2022-04-2 2022-05-1 2022-06-1 2022-12-1 IBRD / 92710 Post Open 9,000.00 0.00 2022-03-06 1-2022-AF2A / Procuremen lementation Support ultant Selection mentation 4 5 9 6 t Officer PRDP-IS-R2-001-IREAP-00 Component 3. Enterprise Individual Cons Pending Imple 2022-02-1 2022-03-1 2022-04-1 2022-10-1 1-2022-AF2A / Organizatio IBRD / 92710 Post Open 12,000.00 0.00 2022-01-01 Development ultant Selection mentation 9 2 6 3 nal Development Officer PRDP-IS-RCAR-001-IREAP- Component 3. Enterprise Individual Cons Pending Imple 2022-04-2 2022-05-1 2022-06-1 2022-12-1 001-2022-AF2A / Organiza IBRD / 92710 Post Open 12,000.00 0.00 2022-03-06 Development ultant Selection mentation 4 5 9 6 tional Development Officer PRDP-IS-R3-001-IREAP-00 Component 3. Enterprise Individual Cons Pending Imple 2022-04-2 2022-05-1 2022-06-1 2022-12-1 1-2022-AF2A / Organizatio IBRD / 92710 Post Open 12,000.00 0.00 2022-03-06 Development ultant Selection mentation 4 5 9 6 nal Development Officer PRDP-IS-R3-001-PROC-00 Component 4: Project Imp Individual Cons Pending Imple 2022-04-2 2022-05-1 2022-06-1 2022-12-1 IBRD / 92710 Post Open 6,000.00 0.00 2022-03-06 1-2022-AF2A / Procuremen lementation Support ultant Selection mentation 4 5 9 6 t Officer PRDP-IS-NLU-001-PROC-0 Component 4: Project Imp Individual Cons Pending Imple 2022-04-2 2022-05-1 2022-06-1 2022-12-1 IBRD / 92710 Post Open 10,480.00 0.00 2022-03-06 01-2022-AF2A / Procureme lementation Support ultant Selection mentation 4 5 9 6 nt Officer PRDP-IS-R2-PROC-003-20 Component 4: Project Imp Individual Cons Pending Imple 2022-08-1 2022-09-0 2022-10-1 2023-04-1 IBRD / 92710 Post Open 6,000.00 0.00 2022-07-01 22-AF2A / Procurement Off lementation Support ultant Selection mentation 9 9 4 2 icer Page 14