Women Entrepreneurship Development Project Summarized Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan: Original Nov.16,2013: Final Revision Updated Procurement Plan, August 15,2013 2. Date of General Procurement Notice: April 10,2013 2. Period covered by this procurement plan: The current procurement Plan period of project covered from year January 2018 to December 2018. II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ 1,500,000 All 2. NCB (Goods) Above US$ 100,000 All and Less than US$ 1.5 million 3. ICB (Works) Above US$ 5 million All 4. NCB (Works) Above US$ All 200,000.00 and less than US 5 million 5. ICB (Non-consultant Services) Above US$ 1.5 All million 6 NCB (Non-consultant Services Above US$ 100,000 and below All US$ 1.5 million 2. Prequalification. Bidders for _______ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. _Not applicable 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Not Applicable 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Women Entrepreneurship Development Project April 2013 issued by Women Entrepreneurship Development Project, WEDP Procurement Manual April 2013 issued by Women Entrepreneurship Development Project July 9, 2010 5. Any Other Special Procurement Arrangements: Not Applicable July 9, 2010 6. Summary of the Current Procurement Packages planned 1 2 3 4 5 6 7 Ref. No. Description Estimate Packag Domesti Review Commen d es c by Bank ts Cost Prefere (Prior / US$ nce Post) million (yes/no) 1 Summary of the 16,500.0 4 No Post Shopping (Goods) 0 2 Summary of the 10,500.0 3 No Post Shopping (Non 0 Consultancy Service) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 500,000 2. Single Source (Firms) All Below USD 100,000 shall be cleared by the TTL 3. Individual Above US$ 200,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than US$ 200,000_equivalent per contract and US$ 300,000 for engineering services, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements; N/A 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description of Estimated Packag Review Comme Assignment Cost US$ es by Bank nts million (Prior/Po st) 1. Summary of number of 7,000.00 1 Post contracts that will be let under QCBS July 9, 2010 2. Summary of number of 35,000.00 8 Post contracts that will be let under other methods July 9, 2010 PROCUREMENT Ethiopia : Ethiopia Women Entrepreneurship Development Project PLAN General Information Country: Ethiopia 2021-03-22 Bank’s Approval Date of the Original Procurement Plan: 2022-07-30 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P122764 GPN Date: Project Name: Ethiopia Women Entrepreneurship Development Project Loan / Credit No: IDA / 51120, IDA / 68140 Federal Urban Job Creation and Food Security Agency Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 3: Project Mana ET-FUJCFSA-223155-GO-DIR gement, Advocacy and Outr Pending Impl / Procurement of Team Viewe IDA / 51120 Post Direct Selection Direct 1,500.00 0.00 2021-03-10 2021-03-15 2021-04-19 2021-10-16 each, Monitoring Evaluation ementation r (Remote support software) and Impact Evaluation. ET-FUJCFSA-223239-GO-RFQ / Internet Infrastructure devic Component 3: Project Mana es gement, Advocacy and Outr Request for Quota Single Stage - One E Pending Impl IDA / 51120 Post Limited 9,000.00 0.00 2021-03-15 2021-05-10 2021-11-06 4 G LTEA modem Qty =14,3 each, Monitoring Evaluation tions nvelope ementation G WiFi Routers =16, ADSL M and Impact Evaluation. odem = 79, Cisco Router for PMU = 1, Cisco Manageable s witches for PMU =1 ET-FUJCFSA-223163-GO-RFQ Component 3: Project Mana / 'Procurement of IT Equipme gement, Advocacy and Outr Single Stage - One E Pending Impl IDA / 51120 Post Request for Bids Open - National 275,000.00 0.00 2021-12-23 2021-12-28 2022-02-08 2022-03-10 2022-04-14 2022-10-11 nt. Including Laptops, Desk t each, Monitoring Evaluation nvelope ementation ops, printers, ups, heavy dut and Impact Evaluation. y Photocopy, Component 3: Project Mana ET-FUJCFSA-270940-GO-RFQ gement, Advocacy and Outr Request for Quota Single Stage - One E Pending Impl / Office Annual cleaning supp IDA / 51120 Post Open - National 1,100.00 0.00 2022-02-20 2022-04-17 2022-10-14 each, Monitoring Evaluation tions nvelope ementation lies and Impact Evaluation. Component 3: Project Mana ET-FUJCFSA-270942-GO-RFQ gement, Advocacy and Outr Request for Quota Single Stage - One E Pending Impl IDA / 51120 Post Open - National 800.00 0.00 2022-03-06 2022-05-01 2022-10-28 / Office refreshment Items each, Monitoring Evaluation tions nvelope ementation and Impact Evaluation. Component 3: Project Mana ET-FUJCFSA-270938-GO-RFQ gement, Advocacy and Outr Request for Quota Single Stage - One E Pending Impl IDA / 51120 Post Limited 7,000.00 0.00 2022-01-31 2022-03-28 2022-09-24 / Office Stationary items each, Monitoring Evaluation tions nvelope ementation and Impact Evaluation. Component 3: Project Mana ET-FUJCFSA-222903-GO-RFQ gement, Advocacy and Outr Request for Quota Single Stage - One E Pending Impl / Procurement of Office Furni IDA / 51120 Post Limited 23,000.00 0.00 2022-05-07 2022-07-02 2022-12-29 each, Monitoring Evaluation tions nvelope ementation ture: and Impact Evaluation. ET-FUJCFSA-271173-GO-RFQ Component 3: Project Mana / Procurement of One Pick u gement, Advocacy and Outr Single Stage - One E Pending Impl IDA / 51120 Post Request for Bids Open - National 200,000.00 0.00 2022-05-18 2022-05-23 2022-07-04 2022-08-03 2022-09-07 2023-03-06 p Double canine and One Ca each, Monitoring Evaluation nvelope ementation r ( or Automobile Car) for Cit and Impact Evaluation. y purpose by PC. ET-FUJCFSA-299504-GO-RFQ Component 2: Entrepreneur / 8 laptops for new specialist Request for Quota Single Stage - One E Pending Impl IDA / 51120 ial skills, Technology and Clu Post Limited 19,000.00 0.00 2022-06-20 2022-07-25 2023-01-21 s and replacement to nonfun tions nvelope ementation ster Development. ctional old laptops NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 3: Project Mana ET-FUJCFSA-266461-GO-RFQ gement, Advocacy and Outr Request for Quota Single Stage - One E Pending Impl / Printing Of Communication IDA / 68140 Post Limited 20,000.00 0.00 2022-05-07 2022-07-02 2022-12-29 each, Monitoring Evaluation tions nvelope ementation Materials and Impact Evaluation. ET-FUJCFSA-266444-NC-DIR Component 3: Project Mana / Procurement of Radio and T gement, Advocacy and Outr Request for Quota Single Stage - One E Pending Impl IDA / 51120 Post Limited 12,000.00 0.00 2022-05-21 2022-07-16 2023-01-12 elevision Broadcasting Servic each, Monitoring Evaluation tions nvelope ementation es and Impact Evaluation. Component 3: Project Mana ET-FUJCFSA-223090-NC-RFP gement, Advocacy and Outr Request for Quota Single Stage - One E Pending Impl / Radio and Television advert IDA / 51120 Post Limited 5,500.00 0.00 2022-05-07 2022-07-02 2022-12-29 each, Monitoring Evaluation tions nvelope ementation ising production service. and Impact Evaluation. ET-FUJCFSA-223243-GO-RFQ Component 3: Project Mana / Procurement of data protec gement, Advocacy and Outr Request for Quota Single Stage - One E Pending Impl IDA / 51120 Post Limited 300.00 0.00 2022-04-30 2022-06-25 2022-12-22 tion and security service (TLS each, Monitoring Evaluation tions nvelope ementation /SSL) for WEDP MIS. and Impact Evaluation. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-FUJCFSA-227369-CS-LCS Component 3: Project Mana / Procurement of Consulting gement, Advocacy and Outr Least Cost Selecti Pending Impleme IDA / 51120 Post Open - National 22,000.00 0.00 2021-03-31 2021-04-21 2021-06-04 2021-07-02 2021-08-01 2021-09-05 2021-10-10 2022-04-08 Services to up grade WEDP M each, Monitoring Evaluation on ntation IS System. and Impact Evaluation. Page 1 ET-FUJCFSA-265974-CS-LCS Component 3: Project Mana / 2020/2021 fiscal year Annu gement, Advocacy and Outr Least Cost Selecti Pending Impleme IDA / 51120 Post Open - National 3,000.00 0.00 2021-11-30 2021-12-21 2022-02-03 2022-03-03 2022-04-02 2022-05-07 2022-06-11 2022-12-08 al Financial Statements Audi each, Monitoring Evaluation on ntation t of the WEDP Project Accoun and Impact Evaluation. ts. Component 3: Project Mana ET-FUJCFSA-270920-NC-RFP gement, Advocacy and Outr Consultant Qualifi Pending Impleme / To hire a Consulting Firm fo IDA / 51120 Post Open - National 15,000.00 0.00 2022-05-18 2022-06-08 2022-07-22 2022-08-21 2022-09-25 2023-03-24 each, Monitoring Evaluation cation Selection ntation r e-learning's development and Impact Evaluation. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-FUJCFSA-222696-CS-CDS Component 3: Project Mana / Recruitment of Addis Ababa gement, Advocacy and Outr Pending Impleme IDA / 51120 Post Direct Selection Direct 16,666.67 0.00 2020-11-25 2020-12-05 2021-02-08 2022-02-07 City Coordinator No 1 for one each, Monitoring Evaluation ntation year contract starting Februa and Impact Evaluation. ry 08/2021 ET-FUJCFSA-222690-CS-CDS Component 3: Project Mana / Recruitment of Addis Ababa gement, Advocacy and Outr Pending Impleme IDA / 51120 Post Direct Selection Direct 16,666.67 0.00 2020-11-25 2020-12-05 2021-02-08 2022-02-07 City Coordinator No 3 for one each, Monitoring Evaluation ntation year contract starting Februa and Impact Evaluation. ry 08/2021 ET-FUJCFSA-222694-CS-CDS Component 3: Project Mana / Recruitment of Addis Ababa gement, Advocacy and Outr Pending Impleme IDA / 51120 Post Direct Selection Direct 16,666.67 0.00 2020-11-25 2020-12-05 2021-02-08 2022-02-07 City Coordinator No 4 for one each, Monitoring Evaluation ntation year contract starting Februa and Impact Evaluation. ry 08/2021 ET-FUJCFSA-222716-CS-CDS Component 3: Project Mana / Recruitment of Gonder City gement, Advocacy and Outr Pending Impleme IDA / 51120 Post Direct Selection Direct 16,666.67 0.00 2020-11-25 2020-12-05 2021-02-08 2022-02-07 Coordinator for one year cont each, Monitoring Evaluation ntation ract starting February 08/202 and Impact Evaluation. 1 ET-FUJCFSA-222719-CS-CDS Component 3: Project Mana / Recruitment of Aksum City gement, Advocacy and Outr Pending Impleme IDA / 51120 Post Direct Selection Direct 16,666.67 0.00 2020-11-25 2020-12-05 2021-02-08 2022-02-07 Coordinator for one year cont each, Monitoring Evaluation ntation ract starting February 08/202 and Impact Evaluation. 1 ET-FUJCFSA-222715-CS-CDS Component 3: Project Mana / Recruitment of Mekele City gement, Advocacy and Outr Pending Impleme IDA / 51120 Post Direct Selection Direct 16,666.67 0.00 2020-11-25 2020-12-05 2021-02-08 2022-02-07 Coordinator for one year cont each, Monitoring Evaluation ntation ract starting February 08/202 and Impact Evaluation. 1 ET-FUJCFSA-222709-CS-CDS Component 3: Project Mana / Recruitment of Bahir Dar Cit gement, Advocacy and Outr Pending Impleme IDA / 51120 Post Direct Selection Direct 16,666.67 0.00 2020-11-25 2020-12-05 2021-02-08 2022-02-07 y Coordinator for one year co each, Monitoring Evaluation ntation ntract starting February 08/2 and Impact Evaluation. 021 ET-FUJCFSA-222707-CS-CDS Component 3: Project Mana / Recruitment of Adama City gement, Advocacy and Outr Pending Impleme IDA / 51120 Post Direct Selection Direct 16,666.67 0.00 2020-11-25 2020-12-05 2021-02-08 2022-02-07 Coordinator for one year cont each, Monitoring Evaluation ntation ract starting February 08/202 and Impact Evaluation. 1 ET-FUJCFSA-222714-CS-CDS Component 3: Project Mana / Recruitment of Asela City C gement, Advocacy and Outr Pending Impleme IDA / 51120 Post Direct Selection Direct 16,666.67 0.00 2020-11-25 2020-12-05 2021-02-08 2022-02-07 oordinator for one year contr each, Monitoring Evaluation ntation act starting February 08/202 and Impact Evaluation. 1 ET-FUJCFSA-222718-CS-CDS Component 3: Project Mana / Recruitment of Dire Dawa C gement, Advocacy and Outr Pending Impleme IDA / 51120 Post Direct Selection Direct 16,666.67 0.00 2020-11-25 2020-12-05 2021-02-08 2022-02-07 ity Coordinator for one year c each, Monitoring Evaluation ntation ontract starting February 08/ and Impact Evaluation. 2021 ET-FUJCFSA-222711-CS-CDS Component 3: Project Mana / Recruitment of Hawasa City gement, Advocacy and Outr Pending Impleme IDA / 51120 Post Direct Selection Direct 16,666.67 0.00 2020-11-25 2020-12-05 2021-02-08 2022-02-07 Coordinator for one year cont each, Monitoring Evaluation ntation ract starting February 08/202 and Impact Evaluation. 1 ET-FUJCFSA-222713-CS-CDS Component 3: Project Mana / Recruitment of Dila City Co gement, Advocacy and Outr Pending Impleme IDA / 51120 Post Direct Selection Direct 16,666.67 0.00 2020-11-25 2020-12-05 2021-02-08 2022-02-07 ordinator for one year contra each, Monitoring Evaluation ntation ct starting February 08/2021 and Impact Evaluation. ET-FUJCFSA-222770-CS-CDS Component 3: Project Mana / Recruitment of WEDP Projec gement, Advocacy and Outr Pending Impleme IDA / 51120 Post Direct Selection Direct 56,000.00 0.00 2020-11-25 2020-12-05 2021-02-08 2022-02-07 t Coordinator for one year co each, Monitoring Evaluation ntation ntract starting February 08/2 and Impact Evaluation. 021 Component 3: Project Mana ET-FUJCFSA-223028-CS-INDV gement, Advocacy and Outr Individual Consult Pending Impleme / Recruitment of Shire City C IDA / 51120 Post Open 16,666.67 0.00 2021-03-10 2021-04-28 2021-05-19 2021-06-23 2022-06-22 each, Monitoring Evaluation ant Selection ntation oordinator and Impact Evaluation. Component 3: Project Mana ET-FUJCFSA-222954-CS-INDV gement, Advocacy and Outr Individual Consult Pending Impleme / Recruitment of D/Markos Cit IDA / 51120 Post Open 16,666.67 0.00 2021-03-10 2021-04-28 2021-05-19 2021-06-23 2022-06-22 each, Monitoring Evaluation ant Selection ntation y Coordinator and Impact Evaluation. Component 3: Project Mana ET-FUJCFSA-223039-CS-INDV gement, Advocacy and Outr Individual Consult Pending Impleme / Recruitment of Dessie City IDA / 51120 Post Open 16,666.67 0.00 2021-03-10 2021-04-28 2021-05-19 2021-06-23 2022-06-22 each, Monitoring Evaluation ant Selection ntation Coordinator and Impact Evaluation. Component 3: Project Mana ET-FUJCFSA-223036-CS-INDV gement, Advocacy and Outr Individual Consult Pending Impleme / Recruitment of Nekempte C IDA / 51120 Post Open 16,666.67 0.00 2021-03-10 2021-04-28 2021-05-19 2021-06-23 2022-06-22 each, Monitoring Evaluation ant Selection ntation ity Coordinator and Impact Evaluation. Component 3: Project Mana ET-FUJCFSA-222957-CS-INDV gement, Advocacy and Outr Individual Consult Pending Impleme / Recruitment of Jima City Co IDA / 51120 Post Open 16,666.67 0.00 2021-03-10 2021-04-28 2021-05-19 2021-06-23 2022-06-22 each, Monitoring Evaluation ant Selection ntation ordinator and Impact Evaluation. Component 3: Project Mana ET-FUJCFSA-223035-CS-INDV gement, Advocacy and Outr Individual Consult Pending Impleme / Recruitment of Shashaman IDA / 51120 Post Open 16,666.67 0.00 2021-03-10 2021-04-28 2021-05-19 2021-06-23 2022-06-22 each, Monitoring Evaluation ant Selection ntation e City Coordinator and Impact Evaluation. Page 2 Component 3: Project Mana ET-FUJCFSA-223061-CS-INDV gement, Advocacy and Outr Individual Consult Pending Impleme / Recruitment of Wolayita So IDA / 51120 Post Open 16,666.67 0.00 2021-03-10 2021-04-28 2021-05-19 2021-06-23 2022-06-22 each, Monitoring Evaluation ant Selection ntation do City Coordinator and Impact Evaluation. Component 3: Project Mana ET-FUJCFSA-223034-CS-INDV gement, Advocacy and Outr Individual Consult Pending Impleme / Recruitment of Arba Minch IDA / 51120 Post Open 16,666.67 0.00 2021-03-10 2021-04-28 2021-05-19 2021-06-23 2022-06-22 each, Monitoring Evaluation ant Selection ntation City Coordinator and Impact Evaluation. ET-FUJCFSA-267645-CS-INDV Component 3: Project Mana / Recruitment of Environmen gement, Advocacy and Outr Individual Consult Under Implement IDA / 51120 Post Open 16,667.00 0.00 2021-12-23 2022-05-02 2022-02-10 2022-03-03 2022-04-07 2022-10-04 tal and Social Safeguards Sp each, Monitoring Evaluation ant Selection ation ecialist and Impact Evaluation. Component 3: Project Mana ET-FUJCFSA-267596-CS-INDV gement, Advocacy and Outr Individual Consult Pending Impleme / Recruitment of Business De IDA / 68140 Post Open 16,666.00 0.00 2022-04-21 2022-06-09 2022-06-30 2022-08-04 2023-08-04 each, Monitoring Evaluation ant Selection ntation velopment Specialist. and Impact Evaluation. Component 3: Project Mana ET-FUJCFSA-222735-CS-CDS gement, Advocacy and Outr Individual Consult Under Implement / Recruitment of Procuremen IDA / 51120 Post Open 9,000.00 0.00 2022-04-21 2022-05-20 2022-05-20 2022-06-03 2022-06-24 2023-06-24 each, Monitoring Evaluation ant Selection ation t Specialist and Impact Evaluation. ET-FUJCFSA-306219-CS-INDV Component 3: Project Mana / Recruitment of 2 Senior B gement, Advocacy and Outr Individual Consult Pending Impleme IDA / 51120 Post Open - National 24,000.00 0.00 2022-07-27 2022-09-14 2022-10-05 2022-11-09 2023-11-04 usiness Development Service each, Monitoring Evaluation ant Selection ntation Advisors at National PMU and Impact Evaluation. ET-FUJCFSA-306222-CS-INDV Component 3: Project Mana / Recruitment of Addis Ababa gement, Advocacy and Outr Individual Consult Pending Impleme IDA / 51120 Post Open - National 5,892.00 0.00 2022-07-27 2022-09-14 2022-10-05 2022-11-09 2023-11-04 City Business Development each, Monitoring Evaluation ant Selection ntation Service Expert (Junior Consul and Impact Evaluation. tant) ET-FUJCFSA-306226-CS-INDV Component 3: Project Mana / Recruitment of Adma City B gement, Advocacy and Outr Individual Consult Pending Impleme IDA / 51120 Post Open - National 5,892.00 0.00 2022-07-27 2022-09-14 2022-10-05 2022-11-09 2023-11-04 usiness Development Service each, Monitoring Evaluation ant Selection ntation Expert (Junior Consultant) and Impact Evaluation. ET-FUJCFSA-306229-CS-INDV Component 3: Project Mana / Recruitment of Arbaminch C gement, Advocacy and Outr Individual Consult Pending Impleme IDA / 51120 Post Open - National 5,892.00 0.00 2022-07-27 2022-09-14 2022-10-05 2022-11-09 2023-11-04 ity Business Development Se each, Monitoring Evaluation ant Selection ntation rvice Expert (Junior Consulta and Impact Evaluation. nt) ET-FUJCFSA-306231-CS-INDV Component 3: Project Mana / Recruitment of Assela City gement, Advocacy and Outr Individual Consult Pending Impleme IDA / 51120 Post Open - National 5,892.00 0.00 2022-07-27 2022-09-14 2022-10-05 2022-11-09 2023-11-04 Business Development Servic each, Monitoring Evaluation ant Selection ntation e Expert (Junior Consultant) and Impact Evaluation. ET-FUJCFSA-306246-CS-INDV Component 3: Project Mana / Recruitment of Debremarko gement, Advocacy and Outr Individual Consult Pending Impleme IDA / 51120 Post Open - National 5,892.00 0.00 2022-07-27 2022-09-14 2022-10-05 2022-11-09 2023-11-04 s City Business Development each, Monitoring Evaluation ant Selection ntation Service Expert (Junior Consul and Impact Evaluation. tant) ET-FUJCFSA-306247-CS-INDV Component 3: Project Mana / Recruitment of Desse City B gement, Advocacy and Outr Individual Consult Pending Impleme IDA / 51120 Post Open - National 5,892.00 0.00 2022-07-27 2022-09-14 2022-10-05 2022-11-09 2023-11-04 usiness Development Service each, Monitoring Evaluation ant Selection ntation Expert (Junior Consultant) and Impact Evaluation. ET-FUJCFSA-306248-CS-INDV Component 3: Project Mana / Recruitment of Dilla City Bu gement, Advocacy and Outr Individual Consult Pending Impleme IDA / 51120 Post Open - National 5,892.00 0.00 2022-07-27 2022-09-14 2022-10-05 2022-11-09 2023-11-04 siness Development Service each, Monitoring Evaluation ant Selection ntation Expert (Junior Consultant) and Impact Evaluation. ET-FUJCFSA-306249-CS-INDV Component 3: Project Mana / Recruitment of Dire Dawa C gement, Advocacy and Outr Individual Consult Pending Impleme IDA / 51120 Post Open - National 5,892.00 0.00 2022-07-27 2022-09-14 2022-10-05 2022-11-09 2023-11-04 ity Business Development Se each, Monitoring Evaluation ant Selection ntation rvice Expert (Junior Consulta and Impact Evaluation. nt) ET-FUJCFSA-306251-CS-INDV Component 3: Project Mana / Recruitment of Gonder City gement, Advocacy and Outr Individual Consult Pending Impleme IDA / 51120 Post Open - National 5,892.00 0.00 2022-07-27 2022-09-14 2022-10-05 2022-11-09 2023-11-04 Business Development Servic each, Monitoring Evaluation ant Selection ntation e Expert (Junior Consultant) and Impact Evaluation. ET-FUJCFSA-306252-CS-INDV Component 3: Project Mana / Recruitment of Hawassa Cit gement, Advocacy and Outr Individual Consult Pending Impleme IDA / 51120 Post Open - National 5,892.00 0.00 2022-07-28 2022-09-15 2022-10-06 2022-11-10 2023-11-05 y Business Development Ser each, Monitoring Evaluation ant Selection ntation vice Expert (Junior Consultan and Impact Evaluation. t) ET-FUJCFSA-306253-CS-INDV Component 3: Project Mana / Recruitment of Jimma City B gement, Advocacy and Outr Individual Consult Pending Impleme IDA / 51120 Post Open - National 5,892.00 0.00 2022-07-28 2022-09-15 2022-10-06 2022-11-10 2023-11-05 usiness Development Service each, Monitoring Evaluation ant Selection ntation Expert (Junior Consultant) and Impact Evaluation. ET-FUJCFSA-306258-CS-INDV Component 3: Project Mana / Recruitment of Mekele City gement, Advocacy and Outr Individual Consult Pending Impleme IDA / 51120 Post Open - National 5,892.00 0.00 2022-07-28 2022-09-15 2022-10-06 2022-11-10 2023-11-05 Business Development Servic each, Monitoring Evaluation ant Selection ntation e Expert (Junior Consultant) and Impact Evaluation. ET-FUJCFSA-306259-CS-INDV Component 3: Project Mana / Recruitment of Nekemte Cit gement, Advocacy and Outr Individual Consult Pending Impleme IDA / 51120 Post Open - National 5,892.00 0.00 2022-07-28 2022-09-15 2022-10-06 2022-11-10 2023-11-05 y Business Development Ser each, Monitoring Evaluation ant Selection ntation vice Expert (Junior Consultan and Impact Evaluation. t) ET-FUJCFSA-306260-CS-INDV Component 3: Project Mana / Recruitment of Shashemen gement, Advocacy and Outr Individual Consult Pending Impleme IDA / 51120 Post Open - National 5,892.00 0.00 2022-07-28 2022-09-15 2022-10-06 2022-11-10 2023-11-05 e City Business Developmen each, Monitoring Evaluation ant Selection ntation t Service Expert (Junior Cons and Impact Evaluation. ultant) ET-FUJCFSA-306262-CS-INDV Component 3: Project Mana / Recruitment of Welayta Se gement, Advocacy and Outr Individual Consult Pending Impleme IDA / 51120 Post Open - National 5,892.00 0.00 2022-07-28 2022-09-15 2022-10-06 2022-11-10 2023-11-05 do City Business Developme each, Monitoring Evaluation ant Selection ntation nt Service Expert (Junior Con and Impact Evaluation. sultant) Page 3