Liberia Liberia Forest Sector Project Procurement Plan (P154114) I. General 1. Bank’s approval Date of the procurement Plan: revised version on November 22, 2017. 2. Date of General Procurement Notice: January 31, 2017 3. Period covered by this procurement plan: October 2017 – September 2018 II. Goods and Works and non-consulting services 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Prior Review Threshold, Procurement Type ‘000US$ Works 10,000 Goods, IT & Non-Consulting Services 2,000 2. Summary of the Procurement Packages planned: Estimated Expected Bid Activity Reference No. Review Method Amount Opening Date / Description: Type (US$) (YYYY/MM/DD) LR-FDA-37151-GO-RFQ / Procurement of Furniture Request for & Office and Field Post 36,325 2017/12/26 Quotations Equipment for Liberia Land Authority LR-FDA-37144-NC-RFQ / Printing and Installation of Billboards (x6) and Request for Post 27,000 2017/12/19 Signposts (x10) for Lake Quotations Piso Multiple-Use Reserve LR-FDA-36679-GO-RFQ / Procurement of GPS (x5), Request for Plotter (x1), and a set of Post 15,000 2017/12/23 Quotations GIS Softwares for the Liberia Institute of November 22, 2017 Statistics and Geo- Information Services (LISGIS) LR-FDA-36664-GO-RFQ / Supply and Installation of Server (inclusive of hosting, and Request for subscription), Laptop Post 25,500 2017/12/29 Quotations Computers (x4), Desktop Computers (x5), and 3- in-1 Printer (x1) for LISGIS LR-FDA-36677-CW-RFB / Construction of FDA regional offices in Bomi, Request for Post 330,000 2018/04/01 Grand Bassa and Lofa Bids and Zwedru office renovation LR-FDA-37146-CW-RFB / Construction of Park Headquarters, Staff Request for Accommodation, and Post 1,020,000 2018/09/18 Bids Ranger Outposts for Gola and Wonegizi Forest National Parks III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold 1. Competitive Methods (Firms) Above US$1,000,000 2. Single Source (Firms) All 3. Individual Above US$ 300,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $300,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Consultancy Assignments with Selection Methods and Time Schedule November 22, 2017 Expected Activity proposals Estimated Reference Review Selection submission Amount No. / Type Method date (US$) Description: (YYYY/MM/DD) LR-FDA-37153- CS-UN / Design and Implementation of an MRV System and Development 692,000.00 Prior UN Agencies 2017/11/28 of FREL/FRL for REDD+ in Liberia (Part 2: FRELs/FRLs and institutional strengthening) LR-FDA-37149- CS-LCS / External Financial Audit Post LCS 2018/03/09 50,000 of the LFSP for fiscal years 2017/2018 & 2018/2019 LR-FDA-36689- CS-CQS / Technical Assistance for Post CQS 2017/10/17 295,000 Liberia Forest Concessions Review LR-FDA-36668- CS-CQS / Protected Area Feasibility Post CQS 2017/12/30 115,000 Study for Cestos SenkWehn LR-FDA-37141- CS-CQS / Protected Area Post CQS 2018/01/20 115,000 Feasibility Study for Grand Kru November 22, 2017 LR-FDA-36684- CS-CQS / Prepare and Implement Sustainable Livelihood Post CQS 2018/01/14 170,000 Support Activities for Communities around Sapo National Park LR-FDA-36671- CS-INDV / Technical Assistance x 1 (International) Individual for Community Post 2017/12/11 70,000 Consultant Forest Management Plan (CFMP) guidelines preparation LR-FDA-36690- CS-INDV / Civil Works Design Individual Post 2017/09/13 80,000 and Consultant Supervision Consultant LR-FDA-36666- CS-INDV / Management Individual Post 2017/12/08 25,000 Plans for Consultant Wonegizi Nature Reserve LR-FDA-37148- CS-INDV / Individual Management Post 2017/12/19 15,000 Consultant Plan Summary for Gola LR-FDA-37147- CS-INDV / Individual Livelihood Post 2017/12/19 14,000 Consultant Restoration Plan for Gola LR-FDA-37142- CS-INDV / Update of Individual Post 2018/01/03 10,000 Management Consultant Plan for Lake Piso November 22, 2017 LR-FDA-36672- CS-INDV / Community Forestry Individual Post 2018/06/06 20,000 Management Consultant Plan x 2 Communities in Sinoe County LR-FDA-37152- CS-INDV / Individual Junior Prior Consultant n/a 48,000 Procurement (Limited) Specialist (FDA- RIU) LR-FDA-37140- CS-INDV / Individual REDD+ Policy Post 2018/01/05 56,000 Consultant Coordinator (FDA) November 22, 2017 PROCUREMENT Liberia : Liberia Forest Sector Project PLAN General Information Country: Liberia Bank’s Approval Date of the Original Procurement Plan: 2017-11-27 2021-11-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P154114 GPN Date: Project Name: Liberia Forest Sector Project Loan / Credit No: TF / A2427 Forestry Development Authority Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned LR-FDA-36677-CW-RFB / Strengthened Regulatory and Under Construction of FDA regional Single Stage - One 2019-11- TF / A2427 Institutional Arrangements Post Request for Bids Open - National 598,335.75 0.00 Implementat 2018-10-31 2018-11-05 2018-11-05 2018-12-17 2018-12-18 2019-01-16 2019-02-20 offices in Bomi and Grand Envelope 17 for Implementation of REDD+ ion Bassa Counties LR-FDA-37146-CW-RFB / Construction of Park Headquarters, Staff Strengthened Capacity for Pending Single Stage - One 2019-10- Accommodation, and Ranger TF / A2427 Management of Targeted Post Request for Bids Open - National 1,020,000.00 0.00 Implementat 2018-11-15 2018-11-20 2019-01-01 2019-01-31 2019-03-07 Envelope 03 Outposts for Gola and Forest Landscapes ion Wonegizi Forest National Parks LR-FDA-81995-CW-RFQ / Strengthened Capacity for Construction of mini dock for Request for Single Stage - One 2019-04- TF / A2427 Management of Targeted Post Limited 20,031.27 0.00 Canceled 2018-11-19 2019-01-17 Lake Piso Multiple Use Reserve Quotations Envelope 17 Forest Landscapes to host two small boats LR-FDA-113328-CW-RFB / Strengthened Capacity for Under Single Stage - One 2020-05- Construction of Gola Forest TF / A2427 Management of Targeted Post Request for Bids Open - National 1,077,947.00 0.00 Implementat 2019-05-13 2019-08-09 2019-05-20 2019-08-09 2019-07-01 2019-09-20 2019-07-31 2019-08-24 Envelope 20 National Park Forest Landscapes ion LR-FDA-124505-CW-RFQ / Strengthened Regulatory and Under Rennovation of Eight Request for Single Stage - One 2020-03- TF / A2427 Institutional Arrangements Post Limited 219,000.00 0.00 Implementat 2019-08-17 2019-08-27 2019-10-05 Infrastructures at Forestry Quotations Envelope 03 for Implementation of REDD+ ion Training Institute LR-FDA-249789-CW-RFB / Request for Bids - Construction of FDA Regional Strengthened Regulatory and Pending Single Stage - One Small Works SPD 2022-11- Office in Voinjama, Lofa TF / A2427 Institutional Arrangements Post Request for Bids Open - National 330,000.00 0.00 Implementat 2021-09-03 2021-09-08 2021-10-13 2021-10-27 2021-11-10 Envelope (1 envelope 10 County under the Liberia for Implementation of REDD+ ion process) Forest Sector Project LR-FDA-249795-CW-RFB / Request for Bids - Construction of FDA Regional Strengthened Regulatory and Under Single Stage - One Small Works SPD 2022-11- Office in Zwedru, Grand TF / A2427 Institutional Arrangements Post Request for Bids Open - National 338,491.00 0.00 Implementat 2021-09-08 2021-10-08 2021-09-13 2021-10-18 2021-11-01 2021-11-15 Envelope (1 envelope 15 Gedeh County under the for Implementation of REDD+ ion process) Liberian Forest Sector Project GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LR-FDA-37151-GO-RFQ / Strengthened Regulatory and Pending Procurement of Furniture & Request for Single Stage - One TF / A2427 Institutional Arrangements Post Limited 36,325.00 0.00 Implementati 2017-12-05 2018-01-30 2018-03-01 Office and Field Equipment for Quotations Envelope for Implementation of REDD+ on Liberia Land Authority LR-FDA-36680-GO-RFQ / Strengthened Regulatory and Under Procurement of Double Cabin Request for Single Stage - One TF / A2427 Institutional Arrangements Post Limited 89,000.00 0.00 Implementati 2017-12-12 2017-12-08 2018-02-09 2018-04-10 Pickup (x1) and Motorbike Quotations Envelope for Implementation of REDD+ on (x12) for LISGIS and LLA LR-FDA-39445-GO-RFB / Strengthened Capacity for Single Stage - One Procurement of Transport TF / A2427 Management of Targeted Prior Request for Bids Open - International 1,080,000.00 0.00 Canceled 2017-03-14 2017-03-17 2017-05-11 2017-07-05 2017-08-19 2018-01-06 Envelope Equipment Forest Landscapes LR-FDA-39457-GO-RFQ / Procurement of 7no. 4WD Forest Monitoring Request for Single Stage - One TF / A2427 Post Limited 378,000.00 427,000.00 Signed 2017-11-21 2017-11-21 2017-12-22 2018-01-09 2018-01-21 Vehicles and 7no. Motorbike Information System Quotations Envelope for FAO TA LR-FDA-47284-GO-RFB / Strengthened Capacity for Single Stage - One Procurement of Transport TF / A2427 Management of Targeted Post Request for Bids Open - International 1,080,000.00 849,450.00 Signed 2017-03-14 2017-03-15 2017-03-17 2017-05-11 2017-05-11 2017-07-05 2017-07-03 2017-08-19 2017-08-21 2018-02-28 Envelope Equipment Forest Landscapes LR-FDA-55212-GO-RFQ / Procurement of Office Strengthened Regulatory and Pending Request for Single Stage - One Furniture and Equipment for TF / A2427 Institutional Arrangements Post Limited 10,000.00 0.00 Implementati 2018-04-09 2018-06-07 2018-12-04 Quotations Envelope the Community Forestry for Implementation of REDD+ on Department LR-FDA-36664-GO-RFQ / Supply and Installation of Server (inclusive of hosting, and subscription), Laptop Pending Forest Monitoring Request for Single Stage - One Computers (x4), Desktop TF / A2427 Post Limited 40,500.00 0.00 Implementati 2018-04-16 2018-06-14 2018-07-29 Information System Quotations Envelope Computers (x5), and 3-in-1 on Printer (x1) GPS (x5), Plotter (x1), and a set of GIS Softwares for LISGIS LR-FDA-36679-GO-RFQ / Procurement of GPS (x5), Plotter (x1), and a set of GIS Forest Monitoring Request for Single Stage - One TF / A2427 Post Limited 15,000.00 0.00 Canceled 2017-12-02 2018-01-27 2018-04-27 Softwares for the Liberia Information System Quotations Envelope Institute of Statistics and Geo- Information Services (LISGIS) Page 1 LR-FDA-82003-GO-RFQ / Procurement of Ranger Uniforms for Five Protected Areas (Sapo National Park x Strengthened Capacity for 72 rangers, East Nimba Request for Single Stage - One TF / A2427 Management of Targeted Post Limited 62,000.00 65,940.00 Completed 2018-11-12 2019-04-19 2018-12-20 2019-05-21 2019-02-18 2019-07-02 Nature Reserve x 24 rangers, Quotations Envelope Forest Landscapes Lake Piso Multiple Use Reserve x 11 rangers, Gola Forest National Park x 30, and Wonegizi Nature Reserve x 20) LR-FDA-82497-GO-RFQ / Strengthened Regulatory and Procurement of four Request for Single Stage - One TF / A2427 Institutional Arrangements Post Limited 15,000.00 15,400.00 Completed 2018-11-04 2019-03-08 2018-12-09 2019-04-22 2019-02-07 2019-07-04 motorbikes for Foya Quotations Envelope for Implementation of REDD+ Afforestation Project LR-FDA-82499-GO-RFQ / Procurement of Office Strengthened Regulatory and Request for Single Stage - One Equipment for Union of TF / A2427 Institutional Arrangements Post Limited 5,500.00 0.00 Canceled 2018-11-20 2018-12-21 2019-01-20 Quotations Envelope Community Forestry for Implementation of REDD+ Management Bodies LR-FDA-56537-GO-RFQ / Pending Procure internet router x 2 Forest Monitoring Request for Single Stage - One TF / A2427 Post Limited 1,850.00 0.00 Implementati 2018-11-20 2019-01-15 2020-06-08 with internet subscription for Information System Quotations Envelope on 18 months LR-FDA-81210-GO-DIR / Strengthened Capacity for Procurement of Beekeeping TF / A2427 Management of Targeted Post Direct Selection Direct 103,225.00 103,020.00 Signed 2018-10-29 2019-01-30 2018-11-03 2019-01-31 2018-11-24 2019-04-09 2019-02-07 Equipment Forest Landscapes LR-FDA-55292-GO-RFQ / Strengthened Capacity for Procurement of Camping Request for Single Stage - One TF / A2427 Management of Targeted Post Limited 90,000.00 163,362.00 Completed 2018-11-06 2019-10-30 2019-01-04 2020-02-05 2019-07-03 2020-03-04 Equipment and field Quotations Envelope Forest Landscapes equipment x5 Protected Areas LR-FDA-82552-GO-RFQ / Procurement of Office Strengthened Capacity for Request for Single Stage - One Equipment for the TF / A2427 Management of Targeted Post Limited 28,050.00 24,188.00 Signed 2018-11-03 2019-03-14 2018-12-08 2019-05-13 2019-02-06 Quotations Envelope Conservation Department Forest Landscapes office and field staff LR-FDA-82550-GO-RFQ / Strengthened Capacity for Pending Procurement of Equipment Request for Single Stage - One TF / A2427 Management of Targeted Post Limited 12,000.00 0.00 Implementati 2019-01-15 2019-02-19 2019-04-20 and Supplies for Auxiliaries Quotations Envelope Forest Landscapes on and Watch Teams LR-FDA-81997-GO-RFQ / Procurement Office Equipment (Paper shredder x 1, air Project Management, Under Request for Single Stage - One conditioner x 2, projector and TF / A2427 Monitoring and Post Limited 4,350.00 2,745.00 Implementati 2018-11-11 2018-11-19 2018-12-16 2019-01-15 Quotations Envelope screen x 2, mini refrigerator x Communication on 1) for REDD+ Implementation Unit LR-FDA-97899-GO-RFQ / Procurement of 1no. High Strengthened Regulatory and Request for Single Stage - One Performance Computer TF / A2427 Institutional Arrangements Post Limited 2,500.00 1,590.00 Signed 2019-02-20 2019-03-20 2019-04-17 2019-04-22 2019-05-17 Quotations Envelope (Laptop) for Liberia Land for Implementation of REDD+ Authority LR-FDA-106599-GO-RFQ / Supply and Installation of Project Management, Request for Single Stage - One Office Furniture and TF / A2427 Monitoring and Post Limited 3,195.00 3,120.00 Signed 2019-03-26 2019-03-20 2019-04-23 2019-05-06 2019-05-23 Quotations Envelope Equipment for the REDD+ Communication Implementation Unit LR-FDA-124463-GO-RFQ / Strengthened Regulatory and Supply and Delivery of Safety Request for Single Stage - One TF / A2427 Institutional Arrangements Post Limited 5,500.00 5,630.00 Completed 2019-07-29 2019-07-17 2019-09-23 2019-08-08 2020-03-21 2019-09-13 Tools for Forestry Training Quotations Envelope for Implementation of REDD+ Institute LR-FDA-124323-GO-RFQ / Strengthened Regulatory and Supply and Installation of Request for Single Stage - One TF / A2427 Institutional Arrangements Post Limited 6,000.00 7,987.00 Completed 2019-08-02 2019-09-27 2019-08-23 2019-12-02 2019-09-06 2019-12-13 Office Equipment for Support Quotations Envelope for Implementation of REDD+ to NUCFMB LR-FDA-155114-GO-RFQ / Strengthened Capacity for Supply of Office and Field Request for Single Stage - One TF / A2427 Management of Targeted Post Limited 10,000.00 0.00 Canceled 2020-02-06 2020-03-10 2020-02-26 2020-03-12 Equipment to support LLA Quotations Envelope Forest Landscapes activities in the Landscape LR-FDA-155076-GO-RFQ / Strengthened Capacity for Suppl of 1no. 4x4 SUV to Request for Single Stage - One TF / A2427 Management of Targeted Post Limited 55,000.00 48,425.00 Signed 2020-02-05 2020-02-18 2020-02-23 2020-03-20 2020-03-26 support LLA activities in the Quotations Envelope Forest Landscapes Landscape. LR-FDA-187671-GO-RFQ / Strengthened Capacity for Supply of Office Equipment to Request for Single Stage - One TF / A2427 Management of Targeted Post Open - National 10,000.00 26,562.00 Signed 2020-03-14 2020-05-09 2020-06-03 2020-11-05 Support LLA Activities in the Quotations Envelope Forest Landscapes Landscape LR-FDA-209852-GO-RFQ / Supply and Installation of Strengthened Regulatory and Under Office Furniture's and Request for Single Stage - One TF / A2427 Institutional Arrangements Post Limited 85,000.00 0.00 Implementati 2020-12-28 2021-02-19 2021-01-19 2021-02-18 Equipment's for Two FDA Quotations Envelope for Implementation of REDD+ on Regional Offices in Tubmanburg & Buchanan LR-FDA-209980-GO-RFB / Supply & Delivery of Three (3) Hightop Pickups for Supervision & Monitoring in Strengthened Regulatory and Single Stage - One the Cluster Landscapes (North TF / A2427 Institutional Arrangements Post Request for Bids Open - National 146,000.00 129,850.00 Signed 2021-01-04 2021-03-03 2021-01-08 2021-07-09 2021-02-05 2021-05-31 2021-02-12 2021-06-11 2021-02-22 2021-08-24 2021-03-29 Envelope West & South East) for for Implementation of REDD+ REDD+ Implementation Unit under the Liberia Forest Sector Project LR-FDA-225736-GO-RFQ / Strengthened Capacity for Pending Supply and Delivery of Office Request for Single Stage - One TF / A2427 Management of Targeted Post Open - National 6,000.00 0.00 Implementati 2021-05-03 2021-06-02 2021-06-30 Equipment and Materials to Quotations Envelope Forest Landscapes on Support LLA County Offices Page 2 LR-FDA-223457-GO-RFQ / Supply and Installation of Solar Electrification for Two Strengthened Capacity for Under Request for Single Stage - One FDA Regional Offices in TF / A2427 Management of Targeted Post Open - National 80,000.00 0.00 Implementati 2021-04-03 2021-05-29 2021-11-25 Quotations Envelope Buchanan, Grand Bassa Forest Landscapes on County and Tubmanburg, Bomi County. LR-FDA-228678-GO-RFQ / Supply and Delivery of Building Materials for Strengthened Regulatory and Pending Request for Single Stage - One Construction of a Mini Boat TF / A2427 Institutional Arrangements Post Limited 34,360.00 0.00 Implementati 2021-04-30 2021-05-22 2021-06-21 Quotations Envelope Dock in Lake Piso, Grand Cape for Implementation of REDD+ on Mount under the Liberia Forest Sector Project LR-FDA-229079-GO-RFQ / Supply of Data Collection Equipment for National Forest Under Forest Monitoring Request for Single Stage - One Monitoring System (NFMS) TF / A2427 Post Limited 17,000.00 0.00 Implementati 2021-04-29 2021-05-14 2021-06-04 Information System Quotations Envelope MRV Field Monitoring under on the Liberia Forest Sector Project LR-FDA-243477-GO-RFQ / Project Management, Under Supply and Delivery of Office Request for Single Stage - One TF / A2427 Monitoring and Post Limited 12,000.00 0.00 Implementati 2021-07-21 2021-08-20 2021-08-14 2021-08-28 Furniture and Monitors for Quotations Envelope Communication on REDD+ Implementation Unit LR-FDA-245448-GO-RFQ / Supply of Office Equipments Strengthened Regulatory and Pending Request for Single Stage - One for Ministry of Mines & Energy TF / A2427 Institutional Arrangements Post Limited 15,600.00 0.00 Implementati 2021-08-21 2021-09-16 2021-10-14 Quotations Envelope Under the Liberia Forest for Implementation of REDD+ on Sector Project LR-FDA-245449-GO-RFQ / Supply and Installation of One Strengthened Regulatory and Spectrophotometer and Two Request for Single Stage - One TF / A2427 Institutional Arrangements Post Limited 19,000.00 0.00 Canceled 2021-08-30 2021-09-03 2021-09-23 2021-10-28 Drones for the Ministry of Quotations Envelope for Implementation of REDD+ Mines & Energy Under the Liberia Forest Sector Project. LR-FDA-245451-GO-RFQ / Supply and Delivery of Strengthened Regulatory and Pending Request for Single Stage - One Reagents for Ministry of Mines TF / A2427 Institutional Arrangements Post Limited 3,000.00 0.00 Implementati 2021-08-28 2021-09-21 2021-10-26 Quotations Envelope & Energy Under the Liberia for Implementation of REDD+ on Forest Sector Project. LR-FDA-245452-GO-RFQ / Printing of Forestry Books Strengthened Regulatory and Pending Title " Forest Conservation Request for Single Stage - One TF / A2427 Institutional Arrangements Post Limited 15,000.00 0.00 Implementati 2021-10-04 2021-10-30 2021-12-29 and Preservation in Liberia" Quotations Envelope for Implementation of REDD+ on Volume 1 & 2 under the Liberia Forest Sector Project LR-FDA-262173-GO-RFQ / Strengthened Capacity for Pending Request for Single Stage - One Supply and Delivery of TF / A2427 Management of Targeted Post Limited 130,000.00 0.00 Implementati 2021-11-20 2021-12-16 2022-02-14 Quotations Envelope Uniforms for FDA Rangers Forest Landscapes on LR-FDA-264664-GO-RFQ / Supply of One (1) Strengthened Regulatory and Pending Spectrophotometer and Two Request for Single Stage - One TF / A2427 Institutional Arrangements Post Limited 19,000.00 0.00 Implementati 2021-12-01 2021-12-25 2022-01-24 (2) Drones to the Ministry of Quotations Envelope for Implementation of REDD+ on Mines & Energy under the Liberia Forest Sector Project NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LR-FDA-37144-NC-RFQ / Printing and Installation of Strengthened Capacity for Under Request for Single Stage - One Billboards (x6) and Signposts TF / A2427 Management of Targeted Post Limited 27,000.00 0.00 Implementati 2017-11-28 2017-12-15 2018-01-23 2018-04-23 Quotations Envelope (x10) for Lake Piso Multiple- Forest Landscapes on Use Reserve LR-FDA-109981-NC-RFQ / Printing and Erection of 7 no. Strengthened Capacity for Request for Single Stage - One Billboards and 11 no. TF / A2427 Management of Targeted Post Limited 32,720.00 26,766.00 Signed 2019-04-27 2019-06-04 2019-06-18 2019-07-30 2019-08-17 Quotations Envelope Signposts for Gola Forest Forest Landscapes National Park CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LR-FDA-36689-CS-CQS / Strengthened Regulatory and Consultant Technical Assistance for Under TF / A2427 Institutional Arrangements Post Qualification Open - International 295,000.00 0.00 2017-05-28 2017-06-05 2017-09-07 2017-10-31 2017-12-27 2018-01-31 2018-07-30 Liberia Forest Concessions Implementation for Implementation of REDD+ Selection Review LR-FDA-36684-CS-CQS / Prepare and Implement Strengthened Capacity for Consultant Sustainable Livelihood TF / A2427 Management of Targeted Post Qualification Open - National 170,000.00 171,802.37 Signed 2017-11-24 2018-01-02 2017-12-15 2018-01-05 2018-01-28 2018-04-09 2018-03-09 2019-04-26 2018-04-13 2019-04-11 2019-01-08 Support Activities for Forest Landscapes Selection Communities around Sapo National Park LR-FDA-37153-CS-UN / Design and Implementation of an MRV System and Forest Monitoring UN Agencies Development of FREL/FRL for TF / A2427 Prior Direct 692,000.00 1,130,214.00 Signed 2018-01-02 2017-12-18 2019-12-23 Information System (Direct) REDD+ in Liberia (Part 2: FRELs/FRLs and institutional strengthening) Page 3 LR-FDA-39453-CS-CQS / Strengthened Capacity for Consultant Study on Tourism and TF / A2427 Management of Targeted Post Qualification Open - National 100,000.00 261,187.50 Signed 2017-07-29 2017-08-01 2017-09-05 2017-09-27 2017-10-27 2017-12-21 2018-07-16 2018-01-25 2018-08-13 2018-07-24 Ecotourism Potential in the Forest Landscapes Selection Targeted Landscapes LR-FDA-55302-CS-CQS / Baseline assessments and mapping on land uses and Strengthened Regulatory and Consultant Pending development in growth TF / A2427 Institutional Arrangements Post Qualification Open - National 89,000.00 0.00 2018-04-10 2018-05-01 2018-06-14 2018-07-29 2018-09-02 2019-03-01 Implementation corridors, and three for Implementation of REDD+ Selection communities in the Southeast (LLA) LR-FDA-55211-CS-CQS / Strengthened Capacity for Consultant Pilot the development of land TF / A2427 Management of Targeted Post Qualification Open - National 60,000.00 0.00 Canceled 2018-04-13 2018-05-04 2018-06-17 2018-07-17 2018-08-21 2019-02-17 use plans in target Forest Landscapes Selection communities (LLA) LR-FDA-36668-CS-CQS / Strengthened Capacity for Consultant Under Protected Area Feasibility TF / A2427 Management of Targeted Post Qualification Open - National 115,000.00 0.00 2018-04-03 2018-08-22 2018-04-24 2018-05-23 2019-03-22 2018-07-22 2018-08-26 2019-02-22 Implementation Study for Cestos SenkWehn Forest Landscapes Selection LR-FDA-37149-CS-LCS / Project Management, External Financial Audit of the Least Cost TF / A2427 Monitoring and Post Open - National 50,000.00 0.00 Canceled 2018-04-05 2018-06-20 2018-04-26 2018-07-06 2018-06-09 2018-07-07 2018-08-06 2018-09-10 2018-10-15 2018-12-14 LFSP for fiscal years Selection Communication 2017/2018 & 2018/2019 LR-FDA-37141-CS-CQS / Strengthened Capacity for Consultant Protected Area Feasibility TF / A2427 Management of Targeted Post Qualification Open - National 115,000.00 176,725.00 Signed 2018-04-18 2018-08-22 2018-05-09 2018-06-22 2019-03-22 2018-07-22 2019-06-17 2018-08-26 2019-08-20 2019-02-22 Study for Grand Kru Forest Landscapes Selection LR-FDA-55631-CS-CQS / Strengthened Capacity for Consultant Protected Area Feasibility TF / A2427 Management of Targeted Post Qualification Open - National 115,000.00 169,525.00 Completed 2018-04-05 2018-08-22 2018-04-26 2018-06-09 2019-03-22 2018-07-24 2019-06-03 2018-08-28 2019-07-17 2019-02-24 2020-05-29 Study for Kpo Forest Landscapes Selection LR-FDA-56541-CS-CQS / Strengthened Capacity for Consultant Training on agroforestry to TF / A2427 Management of Targeted Post Qualification Open - National 100,000.00 0.00 Canceled 2018-04-12 2018-05-03 2018-06-16 2018-07-31 2018-09-04 2019-03-03 400 forest users from 20 Forest Landscapes Selection communities LR-FDA-55328-CS-CQS / Strengthened Capacity for Consultant Development of a National TF / A2427 Management of Targeted Post Qualification Open - National 131,000.00 0.00 Canceled 2018-04-30 2018-05-21 2018-07-04 2018-08-18 2018-09-22 2019-03-21 Land Use Policy (LLA) Forest Landscapes Selection LR-FDA-55209-CS-CQS / Strengthened Capacity for Consultant Prepare data packs on CFMA TF / A2427 Management of Targeted Post Qualification Open - National 50,000.00 0.00 Canceled 2018-09-25 2018-10-09 2018-11-22 2019-01-06 2019-02-10 2019-08-09 communities Forest Landscapes Selection LR-FDA-82490-CS-CQS / Liberia Conservation Trust Strengthened Capacity for Consultant Under Fund Strengthened in TF / A2427 Management of Targeted Post Qualification Open - National 100,000.00 0.00 2018-11-14 2019-02-19 2018-12-05 2019-04-08 2019-01-18 2019-02-17 2019-03-24 2019-09-20 Implementation Governance Structure and Forest Landscapes Selection Fund-raising Capability LR-FDA-80921-CS-CQS / Prepare and Implement Strengthened Capacity for Consultant Sustainable Livelihood TF / A2427 Management of Targeted Post Qualification Open - National 170,000.00 83,974.00 Signed 2018-10-29 2018-08-29 2018-11-03 2018-12-15 2018-12-10 2019-02-09 2019-02-26 2019-03-16 2019-05-09 2020-03-10 Support Activities for Forest Landscapes Selection communities around Gola National Forest Park LR-FDA-82495-CS-CDS / Strengthened Capacity for Preparation of Project Brief for Least Cost Pending TF / A2427 Management of Targeted Post Open - National 15,000.00 0.00 2018-10-23 2018-11-06 2018-12-04 2019-01-01 2019-01-31 2019-03-07 2019-04-11 2019-06-10 proposed Civil Works of the Selection Implementation Forest Landscapes Liberia Forest Sector Project LR-FDA-82491-CS-CQS / Coordination and Strengthened Capacity for Consultant Management of Livelihood TF / A2427 Management of Targeted Post Qualification Open - National 190,000.00 195,991.50 Completed 2018-10-24 2018-12-10 2018-11-14 2018-12-28 2019-04-10 2019-02-26 2019-07-12 2019-04-02 2019-09-13 2020-06-25 2021-02-28 Activity Support to Forest- Forest Landscapes Selection Dependent Communities LR-FDA-97892-CS-CQS / Strengthened Capacity for Consultant Development of National Land TF / A2427 Management of Targeted Post Qualification Open - International 130,000.00 228,490.00 Signed 2019-02-11 2019-04-10 2019-03-04 2019-08-01 2019-04-17 2019-11-23 2019-05-17 2020-02-28 2019-06-21 2020-03-06 2020-01-17 Use and Management Policy Forest Landscapes Selection for Liberia Land Authority LR-FDA-97895-CS-CQS / Assessment and Mapping of Strengthened Capacity for Consultant Pending Existing Land Uses in Three TF / A2427 Management of Targeted Post Qualification Open - National 45,000.00 0.00 2019-02-13 2019-03-06 2019-04-19 2019-05-19 2019-06-23 2019-12-20 Implementation Customary Communities for Forest Landscapes Selection Liberia Land Authority LR-FDA-97933-CS-LCS / Project Management, External Financial Audit of the Least Cost Pending TF / A2427 Monitoring and Post Open - National 15,000.00 0.00 2019-03-05 2019-03-26 2019-05-09 2019-06-06 2019-07-06 2019-08-10 2019-09-14 2019-12-13 Liberia Forest Sector Project Selection Implementation Communication for FY 2018/2019 LR-FDA-180276-CS-QCBS / Consultancy Services for Intensification and Acceleration of Impacts by Strengthened Capacity for Quality And Cost- Under Focusing Livelihood TF / A2427 Management of Targeted Prior Open - International 3,000,000.00 0.00 2020-06-18 2020-09-01 2020-07-02 2020-09-06 2020-07-25 2021-08-05 2020-09-06 2021-01-28 2020-09-20 2021-08-05 2020-10-16 2020-10-28 2022-04-28 Based Selection Implementation Development and Land Use Forest Landscapes Support in Clustered Communities in the North West Landscape LR-FDA-180397-CS-QCBS / Consultancy Services for Intensification and Acceleration of Impacts by Strengthened Capacity for Quality And Cost- Focusing Livelihood TF / A2427 Management of Targeted Prior Open - International 2,600,000.00 3,473,059.60 Signed 2020-06-18 2020-09-04 2020-07-02 2020-09-06 2020-07-27 2020-12-18 2020-09-09 2021-01-25 2020-09-23 2021-03-24 2020-10-17 2021-08-02 2020-10-31 2021-10-28 2022-05-01 Based Selection Development and Land Use Forest Landscapes Support in Clustered Communities in the South East Landscape Page 4 LR-FDA-225737-CS-UN / Consultancy Services for Provision Of Technical Assistance For The Design Strengthened Regulatory and And Implementation Of A MRV UN Agencies Under TF / A2427 Institutional Arrangements Post Direct 240,000.00 0.00 2021-05-29 2021-09-26 Framework And Development (Direct) Implementation for Implementation of REDD+ Of FREL/FRl For REDD+ In Liberia Part 2 (FRELS/FRLS And Institutional Strengthening)” (Continuation) LR-FDA-229675-CS-QCBS / Consultancy Services for Pre- Strengthened Capacity for Quality And Cost- Under gazzetment Activities for Foya TF / A2427 Management of Targeted Post Open - International 800,000.00 0.00 2021-04-25 2021-05-03 2021-05-09 2021-06-09 2021-06-06 2021-07-18 2021-08-01 2021-08-11 2021-09-01 2023-02-23 Based Selection Implementation and Kpo Proposed Protected Forest Landscapes Area LR-FDA-228904-CS-QCBS / Consultancy Services for Pre- Strengthened Capacity for gazzetment Activities for Gbi- Quality And Cost- Under TF / A2427 Management of Targeted Post Open - International 1,200,000.00 0.00 2021-04-28 2021-05-03 2021-05-12 2021-06-09 2021-06-09 2021-07-21 2021-08-04 2021-08-14 2021-09-04 2023-02-26 Krahn Bassa, Grand Kru- River Based Selection Implementation Forest Landscapes Gee and Cestos Senkwehn Proposed Protected Area LR-FDA-245447-CS-CQS / Consultancy Services for Strengthened Regulatory and Consultant Communication Awareness TF / A2427 Institutional Arrangements Post Qualification Open - International 300,000.00 0.00 Canceled 2021-08-24 2021-08-18 2021-09-07 2021-08-25 2021-10-19 2021-10-26 2021-11-09 2022-11-09 and Stakeholder Engagement for Implementation of REDD+ Selection Under the Liberia Forest Sector Project LR-FDA-253480-CS-CQS / Strengthened Regulatory and Consultant Consultancy Services for Under TF / A2427 Institutional Arrangements Post Qualification Open - International 294,545.00 0.00 2021-09-28 2021-10-10 2021-10-12 2021-10-22 2021-11-25 2021-12-09 2021-12-23 2022-06-21 Liberia's Forest Concession Implementation for Implementation of REDD+ Selection Review_ Phase II LR-FDA-257156-CS-CQS / Consultancy Services to Train Forestry Development Strengthened Capacity for Consultant Under Authority (FDA) Staff working TF / A2427 Management of Targeted Post Qualification Open - International 75,000.00 0.00 2021-10-18 2021-10-12 2021-11-01 2021-10-14 2021-12-25 2021-12-30 2022-01-09 2022-03-20 Implementation in Protected Areas on Forest Landscapes Selection Sustainable Protected Areas Management LR-FDA-258634-CS-CQS / Consulting Services for Review and harmonization of the Strengthened Regulatory and Consultant National Forestry Reform Law Under TF / A2427 Institutional Arrangements Post Qualification Open - International 45,000.00 0.00 2021-10-28 2021-10-19 2021-11-11 2021-10-22 2021-12-02 2022-01-22 2022-02-05 2022-04-16 2006, Community Rights Law Implementation for Implementation of REDD+ Selection of 2009, the Community Rights Law Regulations, and the Land Rights Act LR-FDA-259530-CS-CQS / Consultancy Services for Strengthened Capacity for Consultant Under Communication and TF / A2427 Management of Targeted Post Qualification Open - International 300,000.00 0.00 2021-10-26 2021-10-21 2021-11-09 2021-10-26 2021-12-21 2021-12-30 2022-01-13 2023-01-13 Implementation Stakeholder Engagement Forest Landscapes Selection Strategy INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LR-FDA-36671-CS-INDV / Technical Assistance x 1 Strengthened Regulatory and Individual Under (International) for Community TF / A2427 Institutional Arrangements Post Consultant Open 70,000.00 0.00 2017-11-20 2017-12-15 2018-01-20 2018-02-10 2018-03-17 2018-09-13 Implementation Forest Management Plan for Implementation of REDD+ Selection (CFMP) guidelines preparation LR-FDA-36690-CS-INDV / Strengthened Regulatory and Individual Pending Civil Works Design and TF / A2427 Institutional Arrangements Post Consultant Open 80,000.00 0.00 2017-08-23 2017-11-17 2017-12-08 2018-01-12 2019-01-07 Implementation Supervision Consultant for Implementation of REDD+ Selection LR-FDA-36672-CS-INDV / Strengthened Capacity for Individual Community Forestry Pending TF / A2427 Management of Targeted Post Consultant Open 20,000.00 0.00 2018-05-16 2018-07-16 2018-08-06 2018-09-10 2019-03-09 Management Plan x 2 Implementation Forest Landscapes Selection Communities in Sinoe County LR-FDA-55332-CS-INDV / Project Management, Individual Junior Procurement Specialist TF / A2427 Monitoring and Prior Consultant Open 48,000.00 0.00 Canceled 2018-04-02 2018-05-18 2018-05-26 2018-06-16 2018-07-21 2019-07-16 (FDA-RIU) Communication Selection LR-FDA-37152-CS-INDV / Project Management, Individual Junior Procurement Specialist TF / A2427 Monitoring and Prior Consultant Limited 48,000.00 0.00 Canceled 2017-12-08 2017-12-07 2018-01-07 2018-01-28 2018-03-04 2019-02-27 (FDA-RIU) Communication Selection LR-FDA-37140-CS-INDV / Project Management, Individual Pending REDD+ Policy Coordinator TF / A2427 Monitoring and Post Consultant Open 56,000.00 0.00 2018-11-30 2019-01-25 2019-02-15 2019-03-22 2020-03-16 Implementation (FDA) Communication Selection LR-FDA-55633-CS-CDS / Strengthened Capacity for Under Sustainable Protected Area TF / A2427 Management of Targeted Post Direct Selection Direct 75,000.00 0.00 2018-04-25 2018-06-20 2018-05-05 2018-06-21 2018-07-24 2019-01-20 Implementation Management Training Forest Landscapes Project Management, LR-FDA-55641-CS-CDS / TF / A2427 Monitoring and Prior Direct Selection Direct 60,000.00 54,000.00 Signed 2018-10-17 2018-10-18 2018-10-27 2018-12-31 2019-02-08 2019-12-26 Procurement Specialist Communication Project Management, LR-FDA-55643-CS-CDS / TF / A2427 Monitoring and Prior Direct Selection Direct 30,000.00 95,400.00 Signed 2018-10-17 2018-10-18 2018-10-27 2018-12-31 2019-02-14 2019-12-26 Procurement Officer Communication Project Management, LR-FDA-55645-CS-CDS / TF / A2427 Monitoring and Post Direct Selection Direct 30,000.00 30,000.00 Signed 2018-10-17 2018-10-16 2018-10-27 2018-12-31 2018-10-31 2019-12-26 Project Accountant Communication Strengthened Regulatory and LR-FDA-55318-CS-CDS / TF / A2427 Institutional Arrangements Post Direct Selection Direct 26,343.00 28,037.94 Signed 2018-03-19 2018-03-19 2018-03-29 2018-04-03 2018-06-17 2018-11-07 2018-12-14 Civil Service Survey for Implementation of REDD+ Page 5 LR-FDA-55210-CS-CDS / Project Management, Liberia Forest Sector Project TF / A2427 Monitoring and Post Direct Selection Direct 30,000.00 22,000.00 Signed 2018-03-16 2018-04-02 2018-03-26 2018-04-02 2018-05-30 2018-04-04 2018-11-26 Stock-Taking Review Communication LR-FDA-55646-CS-CDS / Project Management, National REDD+ Project TF / A2427 Monitoring and Post Direct Selection Direct 93,600.00 269,694.00 Signed 2018-10-17 2018-10-16 2018-10-27 2018-10-23 2018-12-31 2018-10-30 2019-12-26 Coordinator Communication LR-FDA-55648-CS-CDS / Project Management, Communication and TF / A2427 Monitoring and Post Direct Selection Direct 36,000.00 33,600.00 Signed 2018-10-17 2018-10-16 2018-10-27 2018-12-31 2018-10-31 2019-12-26 Stakeholder Engagement Communication Specialist Project Management, LR-FDA-55653-CS-CDS / TF / A2427 Monitoring and Post Direct Selection Direct 18,000.00 70,134.00 Signed 2018-10-17 2018-10-16 2018-10-27 2018-12-31 2018-10-31 2019-12-26 Team Assistant Communication LR-FDA-56532-CS-INDV / Project Management, Individual Monitoring and Evaluation TF / A2427 Monitoring and Post Consultant Open 54,000.00 0.00 Canceled 2018-10-09 2018-10-20 2018-12-04 2018-12-18 2019-01-15 2020-01-10 Specialist Communication Selection LR-FDA-55670-CS-CDS / Strengthened Capacity for Scoping / feasibility study for TF / A2427 Management of Targeted Post Direct Selection Direct 75,000.00 50,878.20 Signed 2018-04-18 2018-04-11 2018-04-28 2018-04-18 2018-07-17 2018-08-13 2019-01-13 a Community Forestry Forest Landscapes Cooperative LR-FDA-37142-CS-INDV / Strengthened Capacity for Individual Pending Update of Management Plan TF / A2427 Management of Targeted Post Consultant Open 10,000.00 0.00 2018-05-17 2018-07-12 2018-08-02 2018-09-06 2019-03-05 Implementation for Lake Piso Forest Landscapes Selection LR-FDA-37143-CS-CDS / Strengthened Capacity for Facilitator for Conservation TF / A2427 Management of Targeted Prior Direct Selection Direct 100,000.00 0.00 Canceled 2017-12-18 2017-12-28 2018-03-18 2018-09-14 Trust Fund Design Forest Landscapes LR-FDA-68672-CS-CDS / Project Management, External Financial Audit of the Pending TF / A2427 Monitoring and Post Direct Selection Direct 15,000.00 0.00 2018-07-27 2018-08-06 2018-10-10 2018-12-09 Liberia Forest Sector Project Implementation Communication for fiscal year 2017/2018 Project Management, Individual LR-FDA-68674-CS-INDV / TF / A2427 Monitoring and Prior Consultant Open 48,000.00 92,250.00 Signed 2018-07-30 2018-08-30 2018-09-08 2018-12-27 2018-09-29 2019-01-16 2018-11-03 2019-01-30 2019-10-29 Procurement Officer Communication Selection LR-FDA-55640-CS-CDS / Strengthened Regulatory and Training for LICSADUN on TF / A2427 Institutional Arrangements Post Direct Selection Direct 80,000.00 0.00 Canceled 2018-04-10 2018-04-20 2018-06-24 2018-12-21 small-scale timber harvesting for Implementation of REDD+ LR-FDA-55639-CS-CDS / Strengthened Regulatory and Training for NACUL on TF / A2427 Institutional Arrangements Post Direct Selection Direct 80,000.00 0.00 Canceled 2018-05-02 2018-05-12 2018-07-31 2019-01-27 sustainable charcoal for Implementation of REDD+ production LR-FDA-55310-CS-CDS / Training on beekeeping and honey production to 400 Strengthened Capacity for Forest users from 20 TF / A2427 Management of Targeted Post Direct Selection Direct 200,000.00 0.00 Canceled 2018-03-19 2018-03-19 2018-03-29 2018-04-09 2018-06-17 2018-12-14 communities (20 person per Forest Landscapes community) in around Sapo and Gola LR-FDA-37147-CS-INDV / Strengthened Capacity for Individual Livelihood Restoraion Plan for TF / A2427 Management of Targeted Post Consultant Open 14,000.00 0.00 Canceled 2018-05-21 2018-07-16 2018-08-06 2018-09-10 2019-03-09 Gola Forest Landscapes Selection LR-FDA-56544-CS-INDV / Strengthened Capacity for Individual Training Facilitator for TF / A2427 Management of Targeted Post Consultant Limited 10,000.00 0.00 Canceled 2018-10-24 2018-10-29 2018-11-19 2018-12-24 2019-02-07 Workshop on Community Forest Landscapes Selection Forestry Nine-Step Process LR-FDA-81317-CS-CDS / Training on beekeeping and honey production to 400 Strengthened Capacity for forest users from 20 TF / A2427 Management of Targeted Post Direct Selection Direct 81,000.00 78,436.95 Signed 2018-03-19 2018-03-19 2018-03-29 2018-04-09 2018-06-17 2018-12-27 2019-12-09 communities (20 persons per Forest Landscapes community) around Sapo and Gola LR-FDA-82000-CS-INDV / Community Forestry Strengthened Capacity for Individual Management Plan (CFMP) TF / A2427 Management of Targeted Post Consultant Open 42,348.00 50,000.00 Signed 2019-01-15 2019-01-22 2019-03-05 2019-05-29 2019-03-26 2019-06-17 2019-04-16 2019-07-01 2019-10-13 Guidelines Piloted in three Forest Landscapes Selection communities LR-FDA-82502-CS-INDV / Community Forestry Strengthened Capacity for Individual Pending Management Plans (CFMPs) TF / A2427 Management of Targeted Post Consultant Direct 50,000.00 0.00 2018-11-30 2018-12-10 2018-12-31 2019-01-21 2019-07-20 Implementation prepared for remaining 30 Forest Landscapes Selection communities Strengthened Capacity for Individual LR-FDA-80948-CS-INDV / TF / A2427 Management of Targeted Post Consultant Open 28,000.00 27,000.00 Signed 2018-10-29 2018-11-24 2018-12-23 2019-03-05 2018-12-30 2019-03-23 2019-01-16 2019-04-15 2020-01-11 Community Forestry Specialist Forest Landscapes Selection LR-FDA-80944-CS-CDS / Strengthened Capacity for Awareness Raising and TF / A2427 Management of Targeted Post Direct Selection Direct 40,000.00 323,453.00 Signed 2018-10-15 2018-10-25 2018-10-25 2018-11-08 2019-01-03 2019-05-22 2020-06-26 Establishment of Community Forest Landscapes Forest Governance Entities LR-FDA-80905-CS-CDS / Strengthened Capacity for Capacity Building for Union of TF / A2427 Management of Targeted Post Direct Selection Direct 153,000.00 165,675.00 Signed 2018-10-15 2018-10-25 2018-10-25 2018-11-08 2019-01-03 2019-08-02 2020-06-26 Community Forest Forest Landscapes Management Bodies LR-FDA-36666-CS-INDV / Strengthened Capacity for Individual Pending Management Plans for TF / A2427 Management of Targeted Post Consultant Open 25,000.00 0.00 2018-11-06 2018-12-25 2019-01-15 2019-02-19 2019-05-20 Implementation Wonegizi Nature Reserve Forest Landscapes Selection Page 6 LR-FDA-82486-CS-INDV / Strengthened Capacity for Individual Preparation of Data Packs on Pending TF / A2427 Management of Targeted Post Consultant Direct 10,000.00 0.00 2018-12-06 2018-12-16 2019-01-06 2019-02-10 2019-08-09 Communities' post Implementation Forest Landscapes Selection demarcation LR-FDA-82002-CS-CDS / Monitoring, Reporting, and Forest Monitoring TF / A2427 Post Direct Selection Direct 36,000.00 30,000.00 Signed 2018-10-19 2018-10-23 2018-10-29 2019-01-02 2018-12-12 2019-12-28 Verification (MRV) Officer for Information System LISGIS LR-FDA-83007-CS-INDV / Strengthened Capacity for Individual Pending Management Plan Summary TF / A2427 Management of Targeted Post Consultant Direct 3,000.00 0.00 2018-11-19 2018-11-29 2018-12-20 2019-01-24 2019-03-25 Implementation for Sapo National Park Forest Landscapes Selection Project Management, Individual LR-FDA-88484-CS-INDV / TF / A2427 Monitoring and Post Consultant Open 20,000.00 43,710.00 Signed 2018-11-30 2018-11-28 2018-12-31 2019-01-27 2019-01-07 2019-02-14 2019-01-21 2019-02-19 2019-04-21 LFSP Mid-term Review Communication Selection LR-FDA-55637-CS-INDV / Strengthened Capacity for Individual Pending Gazzetment Package for Gbi TF / A2427 Management of Targeted Post Consultant Open 8,500.00 0.00 2019-03-19 2019-05-07 2019-05-28 2019-07-02 2019-12-29 Implementation (Krahn-Bassa) Forest Landscapes Selection Strengthened Capacity for Individual LR-FDA-55635-CS-INDV / Pending TF / A2427 Management of Targeted Post Consultant Open 8,500.00 0.00 2019-03-11 2019-04-29 2019-05-20 2019-06-24 2019-12-21 Gazzetment Package for Foya Implementation Forest Landscapes Selection LR-FDA-104706-CS-INDV / Project Management, Individual Monitoring and Evaluation TF / A2427 Monitoring and Post Consultant Direct 54,000.00 53,400.00 Signed 2019-03-08 2019-03-27 2019-03-13 2019-04-01 2019-03-16 2019-04-08 2019-03-20 2019-04-15 2020-03-14 Specialist Communication Selection LR-FDA-120294-CS-CDS / Project Management, Consultancy Services For Under TF / A2427 Monitoring and Post Direct Selection Direct 50,000.00 0.00 2019-06-24 2019-07-07 2019-07-04 2019-08-26 2019-11-25 Provision of External Financial Implementation Communication Audit_FY 2018 and 2019 LR-FDA-149493-CS-INDV / Strengthened Regulatory and Individual Consulting Servies for Pending TF / A2427 Institutional Arrangements Post Consultant Limited 20,000.00 0.00 2020-01-21 2020-01-24 2020-01-29 2020-02-04 2020-06-30 Provision of Supervision Implementation for Implementation of REDD+ Selection Engineer LR-FDA-155011-CS-CDS / Provision of Individual Project Management, Under Consultancy for Social TF / A2427 Monitoring and Post Direct Selection Direct 14,400.00 0.00 2020-01-30 2020-02-04 2020-02-09 2020-02-20 2020-06-30 Implementation Safeguard Coordinator under Communication the LFSP LR-FDA-155829-CS-CDS / Provision of Individual Project Management, Consultancy for Part Time TF / A2427 Monitoring and Post Direct Selection Direct 22,500.00 0.00 Canceled 2020-02-03 2020-02-13 2020-02-20 2020-06-30 Monitoring and Evaluation Communication Speciaist under the LFSP LR-FDA-155092-CS-CDS / Consultancy Services for Strengthened Capacity for Scoping Study for Community TF / A2427 Management of Targeted Prior Direct Selection Direct 98,000.00 146,886.25 Signed 2020-02-02 2020-06-19 2020-02-12 2020-06-22 2020-03-25 2020-12-15 2020-06-30 Forestry Cooperative Phase II Forest Landscapes (Implementation) LR-FDA-160565-CS-CDS / Consultancy Services for Project Management, Under Provision of Individual Part- TF / A2427 Monitoring and Post Direct Selection Direct 60,000.00 0.00 2020-02-27 2020-03-06 2020-03-08 2020-03-16 2020-06-30 Implementation Time Monitoring and Communication Evaluation Consulant LR-FDA-155051-CS-CDS / Consultancy Services for Intensification and Acceleration of Impacts by Strengthened Capacity for Focusing Livelihood TF / A2427 Management of Targeted Prior Direct Selection Direct 3,000,000.00 0.00 Canceled 2020-02-10 2020-02-20 2020-04-25 2023-04-25 Development and Land Use Forest Landscapes Support in Clustered Communities in the North West and South East Landscapes LR-FDA-155813-CS-CDS / Consultancy Services for Implementation of Selected Strengthened Capacity for Activities of the LFSP in TF / A2427 Management of Targeted Prior Direct Selection Direct 2,600,000.00 0.00 Canceled 2020-02-15 2020-02-25 2020-04-30 2023-04-30 Clustered Communities in the Forest Landscapes Northwest Landscape (Gola and Foya) LR-FDA-167967-CS-CDS / Project Management, Consultancy Services for TF / A2427 Monitoring and Post Direct Selection Direct 5,500.00 2,620.00 Signed 2020-04-13 2020-05-04 2020-04-16 2020-05-04 2020-04-24 2020-05-11 2020-06-30 Provision Monitoring & Data Communication Reporting Assistant LR-FDA-187670-CS-INDV / Consultancy Services for Project Management, Individual Communication Stakeholder Under TF / A2427 Monitoring and Post Consultant Limited 63,270.00 0.00 2020-08-14 2020-09-03 2020-08-19 2020-09-09 2020-09-30 2022-03-31 Engagement Specialist under Implementation Communication Selection the Liberia Forest Sector Project LR-FDA-196693-CS-INDV / Consultancy Services for Civl Project Management, Individual Under Works Supervision TF / A2427 Monitoring and Post Consultant Direct 32,400.00 26,110.00 2020-10-07 2020-10-28 2020-10-15 2020-11-04 2020-10-20 2020-11-06 2020-10-28 2021-04-26 Implementation Infrastructures under the Communication Selection Liberia Forest Sector Project LR-FDA-82485-CS-INDV / Strengthened Capacity for Management Plan Summary Under TF / A2427 Management of Targeted Post Direct Selection Direct 3,000.00 0.00 2018-12-13 2021-02-16 2018-12-28 2019-03-03 2019-08-30 for Lake Piso Multiple Use Implementation Forest Landscapes Reserve LR-FDA-37148-CS-INDV / Strengthened Capacity for Individual Management Plan Summary TF / A2427 Management of Targeted Post Consultant Direct 3,000.00 6,000.00 Signed 2021-01-05 2021-02-16 2021-01-15 2021-03-01 2021-01-25 2021-03-16 2021-02-08 2021-03-19 2021-03-10 for Gola Forest Landscapes Selection Page 7 LR-FDA-225734-CS-INDV / Strengthened Regulatory and Individual Consultancy Services to Under TF / A2427 Institutional Arrangements Post Consultant Open 80,000.00 0.00 2021-04-12 2021-04-12 2021-05-22 2021-06-05 2021-06-19 2021-12-16 Revised /Update National Implementation for Implementation of REDD+ Selection REDD+ Stragegy LR-FDA-223552-CS-CDS / Strengthened Capacity for Consultancy Services for the TF / A2427 Management of Targeted Post Direct Selection Direct 15,000.00 0.00 Under Review 2021-04-01 2021-10-12 2021-04-13 2021-05-02 2021-07-31 Development of Ecotourism Forest Landscapes Enterprise Business Plan LR-FDA-225733-CS-CDS / Strengthened Regulatory and Consultancy Services for TF / A2427 Institutional Arrangements Post Direct Selection Direct 294,545.00 0.00 Canceled 2021-04-21 2021-07-12 2021-05-01 2021-06-07 2021-10-05 Liberia Forest Concession for Implementation of REDD+ Review Phase II LR-FDA-229648-CS-INDV / Consultancy Services to Review & Revised the National Forestry Reform Law ,Community Rights Law & to Strengthened Capacity for Individual Under Review and Harmonize 15 TF / A2427 Management of Targeted Post Consultant Open 45,000.00 0.00 2021-04-26 2021-04-22 2021-05-25 2021-06-01 2021-06-13 2021-11-10 Implementation years Community Forest Forest Landscapes Selection Management Agreement (CFMA) tenure & the 25 years felling circle of the Code of Timber Harvesting Practice LR-FDA-243472-CS-INDV / Project Management, Individual Provision of Individual Under TF / A2427 Monitoring and Post Consultant Open 77,700.00 0.00 2021-07-19 2021-07-25 2021-08-21 2021-08-26 2021-09-09 2022-09-09 Consultancy as Monitoring & Implementation Communication Selection Evaluation Specialist LR-FDA-245453-CS-INDV / Provision of Individual Strengthened Capacity for Individual Consultancy Services to Pending TF / A2427 Management of Targeted Post Consultant Limited 12,500.00 0.00 2021-09-01 2021-09-06 2021-09-27 2021-10-11 2022-01-09 Develop Training Materials in Implementation Forest Landscapes Selection Five (5) Modules for Forest Management. LR-FDA-245774-CS-INDV / Provision of Individual Strengthened Regulatory and Individual Consultancy to Create E-book Pending TF / A2427 Institutional Arrangements Post Consultant Limited 7,500.00 0.00 2021-09-20 2021-09-25 2021-10-16 2021-10-30 2022-02-27 Platform for Forest Implementation for Implementation of REDD+ Selection Management Book Volume 1 &2 LR-FDA-253499-CS-INDV / Consultancy Services for Strengthened Regulatory and Individual Pending Provision Individual TF / A2427 Institutional Arrangements Post Consultant Limited 12,750.00 0.00 2021-09-30 2021-10-07 2021-10-21 2021-11-06 2022-02-04 Implementation Consultant as Infographics for Implementation of REDD+ Selection and Layout Expert. LR-FDA-253534-CS-INDV / Consultancy Services for Copy Strengthened Regulatory and Individual Under Edit of Two Forestry Books TF / A2427 Institutional Arrangements Post Consultant Limited 14,875.00 0.00 2021-10-01 2021-09-15 2021-10-08 2021-10-09 2021-10-23 2021-12-22 Implementation Under the Liberia Forest for Implementation of REDD+ Selection Sector Project Page 8