PROCUREMENT PLAN Project information: Bosnia and Herzegovina – Energy Efficiency Project – P143580 Project Implementation agency: Federal Ministry of Physical Planning Date of the Procurement Plan: 4/30/2020 Period covered by this Procurement Plan: 2020-2024 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. If the Borrower and the Bank agreed to use the Borrower’s national open competitive procurement arrangements, it will be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable; Works: is not applicable. Other Relevant Procurement Information. None. PROCUREMENT Bosnia and Herzegovina : Energy Efficiency Project PLAN General Information Country: Bosnia and Herzegovina Bank’s Approval Date of the Original Procurement Plan: 2020-10-19 2022-02-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P143580 GPN Date: 2020-03-19 Project Name: Energy Efficiency Project Loan / Credit No: IBRD / 89060 Project Implementing Unit Executing Agency(ies): WORKS Procureme Activity Reference No. / Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH nt Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) Justification for Award Type Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual P143580-BA-BEEP-8906BA- Pending Energy Efficiency Investments Single Stage - One 2021-07- RFB-W-20-1-RS / Retrofitting IBRD / 89060 Post Request for Bids Open - National 0.00 Implementat 2020-10-12 2020-10-17 2020-11-28 2020-12-28 2021-02-01 in Public Facilities Envelope 31 of public buildings ion P143580-BA-BEEP-8906BA- Pending Energy Efficiency Investments Single Stage - One 2021-07- RFB-W-20-2-RS / Retrofitting IBRD / 89060 Post Request for Bids Open - National 0.00 Implementat 2020-10-12 2020-10-17 2020-11-28 2020-12-28 2021-02-01 in Public Facilities Envelope 31 of public buildings ion P143580-BA-BEEP-8906BA- Under Energy Efficiency Investments Single Stage - One 2021-07- RFB-W-20-7-RS / Retrofitting IBRD / 89060 Post Request for Bids Open - National 0.00 Implementat 2020-10-12 2020-06-12 2020-10-17 2020-11-28 2020-07-03 2020-12-28 2021-02-01 in Public Facilities Envelope 31 of public buildings ion P143580-BA-BEEP-8906BA- Pending Energy Efficiency Investments Single Stage - One 2021-07- RFB-W-20-9-RS / Retrofitting IBRD / 89060 Post Request for Bids Open - National 0.00 Implementat 2020-10-12 2020-10-17 2020-11-28 2020-12-28 2021-02-01 in Public Facilities Envelope 31 of public buildings ion P143580-BA-BEEP-8906BA- Under RFB-W-20-10-RS / Energy Efficiency Investments Single Stage - One 2021-07- IBRD / 89060 Post Request for Bids Open - National 0.00 Implementat 2020-10-12 2020-07-15 2020-10-17 2020-11-28 2020-12-28 2021-02-01 Retrofitting of public in Public Facilities Envelope 31 ion buildings P143580-BA-BEEP-8906BA- RFB-W-20-12-RS / Energy Efficiency Investments Single Stage - One 2021-07- 2021- IBRD / 89060 Post Request for Bids Open - National 311,607.89 Completed 2020-10-12 2021-06-09 2020-10-17 2021-06-09 2020-11-28 2021-06-09 2020-12-28 2020-08-28 2021-02-01 2020-11-26 Retrofitting of public in Public Facilities Envelope 31 05-28 buildings P143580-BA-BEEP-8906BA- Pending RFB-W-20-13-RS / Energy Efficiency Investments Single Stage - One 2021-07- IBRD / 89060 Post Request for Bids Open - National 0.00 Implementat 2020-10-12 2020-10-17 2020-11-28 2020-12-28 2021-02-01 Retrofitting of public in Public Facilities Envelope 31 ion buildings P143580-BA-BEEP-8906BA- Pending RFB-W-20-14-RS / Energy Efficiency Investments Single Stage - One 2021-07- IBRD / 89060 Post Request for Bids Open - National 0.00 Implementat 2020-10-12 2020-10-17 2020-11-28 2020-12-28 2021-02-01 Retrofitting of public in Public Facilities Envelope 31 ion buildings P143580-BA-BEEP-8906BA- Pending RFB-W-20-15-RS / Energy Efficiency Investments Single Stage - One 2021-07- IBRD / 89060 Post Request for Bids Open - National 0.00 Implementat 2020-10-12 2020-10-17 2020-11-28 2020-12-28 2021-02-01 Retrofitting of public in Public Facilities Envelope 31 ion buildings P143580-BA-BEEP-8906BA- Pending RFB-W-20-16-RS / Energy Efficiency Investments Single Stage - One 2021-07- IBRD / 89060 Post Request for Bids Open - National 0.00 Implementat 2020-10-12 2020-10-17 2020-11-28 2020-12-28 2021-02-01 Retrofitting of public in Public Facilities Envelope 31 ion buildings P143580-BA-BEEP-8906BA- Pending RFB-W-20-17-RS / Energy Efficiency Investments Single Stage - One 2021-07- IBRD / 89060 Post Request for Bids Open - National 0.00 Implementat 2020-10-12 2020-10-17 2020-11-28 2020-12-28 2021-02-01 Retrofitting of public in Public Facilities Envelope 31 ion buildings P143580-BA-BEEP-8906BA- Pending RFB-W-20-19-RS / Energy Efficiency Investments Single Stage - One 2021-07- IBRD / 89060 Post Request for Bids Open - National 0.00 Implementat 2020-10-12 2020-10-17 2020-11-28 2020-12-28 2021-02-01 Retrofitting of public in Public Facilities Envelope 31 ion buildings P143580-BA-BEEP-8906BA- Pending Energy Efficiency Investments Single Stage - One 2021-07- RFB-W-20-20-RS / IBRD / 89060 Post Request for Bids Open - National 0.00 Implementat 2020-10-12 2020-10-17 2020-11-28 2020-12-28 2021-02-01 in Public Facilities Envelope 31 Retrofitting of public building ion P143580-BA-BEEP-8906BA- Pending RFB-W-20-21-RS / Energy Efficiency Investments Single Stage - One 2021-07- IBRD / 89060 Post Request for Bids Open - National 0.00 Implementat 2020-10-12 2020-10-17 2020-11-28 2020-12-28 2021-02-01 Retrofitting of public in Public Facilities Envelope 31 ion buildings P143580-BA-BEEP-8906BA- Pending RFB-W-20-22-RS / Energy Efficiency Investments Single Stage - One 2021-07- IBRD / 89060 Post Request for Bids Open - National 0.00 Implementat 2020-10-12 2020-10-17 2020-11-28 2020-12-28 2021-02-01 Retrofitting of public in Public Facilities Envelope 31 ion buildings P143580-BA-BEEP-8906BA- RFB-W-20-69-RS / Energy Efficiency Investments Single Stage - One 2021-11- IBRD / 89060 Post Request for Bids Open - National 0.00 Canceled 2021-01-17 2021-01-22 2021-03-05 2021-04-04 2021-05-09 Retrofitting of public in Public Facilities Envelope 05 buildings-mechanical phase P143580-BA-BEEP-8906BA- Pending RFB-W-20-25-RS / Energy Efficiency Investments Single Stage - One 2021-08- IBRD / 89060 Post Request for Bids Open - National 0.00 Implementat 2020-10-13 2020-10-18 2020-11-29 2020-12-29 2021-02-02 Retrofitting of public in Public Facilities Envelope 01 ion buildings P143580-BA-BEEP-8906BA- RFB-W-20-83-RS / Pending Retrofitting of public Energy Efficiency Investments Single Stage - One 2022-01- IBRD / 89060 Post Request for Bids Open - National 0.00 Implementat 2021-04-05 2021-04-10 2021-05-22 2021-06-21 2021-07-26 buildings-mechanical phase in Public Facilities Envelope 22 ion Elementary school "Sveti Sava", Gacko Page 1 P143580-BA-BEEP-8906BA- RFB-W-20-84-RS / Retrofitting of public Under Energy Efficiency Investments Single Stage - One 2022-01- buildings-reconstruction of IBRD / 89060 Post Request for Bids Open - National 0.00 Implementat 2021-03-19 2021-03-31 2021-03-24 2021-05-05 2021-04-28 2021-06-04 2021-07-09 in Public Facilities Envelope 05 toilets of Elementary school ion "Zmaj Jova Jovanovic" Banja Luka P143580-BA-BEEP-8906BA- RFB-W-21-85-RS / Under Energy Efficiency Investments Single Stage - One 2022-01- Retrofitting of public IBRD / 89060 Post Request for Bids Open - National 0.00 Implementat 2021-03-19 2021-03-31 2021-03-24 2021-06-09 2021-05-05 2021-04-28 2021-06-04 2021-05-05 2021-07-09 in Public Facilities Envelope 05 buildings-University of ion Medicine-dentistry P143580-BA-BEEP-8906BA- RFB-W-21-86-RS / Energy Efficiency Investments Single Stage - One 2022-01- retrofitting of public buildings- IBRD / 89060 Post Request for Bids Open - National 224,162.87 Signed 2021-03-19 2021-03-31 2021-03-24 2021-10-15 2021-05-05 2021-04-28 2021-06-04 2021-06-01 2021-07-09 2021-07-23 in Public Facilities Envelope 05 Secondary school of Economics Banja Luka P143580-BA-BEEP-8906BA- RFB-W-21-87-RS / Under Energy Efficiency Investments Single Stage - One 2022-01- Retrofitting of public IBRD / 89060 Post Request for Bids Open - National 0.00 Implementat 2021-03-19 2021-03-31 2021-03-24 2021-05-05 2021-06-04 2021-07-09 in Public Facilities Envelope 05 buildings- Secondary school ion of polytechnics Banja Luka P143580-BA-BEEP-8906BA- Pending RFB-W-20-63-RS / Energy Efficiency Investments Single Stage - One 2021-11- IBRD / 89060 Post Request for Bids Open - National 0.00 Implementat 2021-01-17 2021-01-22 2021-03-05 2021-04-04 2021-05-09 Retrofitting of public in Public Facilities Envelope 05 ion buildings-mechanical phase. P143580-BA-BEEP-8906BA- Pending RFB-W-20-64-RS / Energy Efficiency Investments Single Stage - One 2021-11- IBRD / 89060 Post Request for Bids Open - National 0.00 Implementat 2021-01-17 2021-01-22 2021-03-05 2021-04-04 2021-05-09 Retrofitting of public in Public Facilities Envelope 05 ion buildings-mechanical phase P143580-BA-BEEP-8906BA- Pending RFB-W-20-65-RS / Energy Efficiency Investments Single Stage - One 2021-11- IBRD / 89060 Post Request for Bids Open - National 0.00 Implementat 2021-01-17 2021-01-22 2021-03-05 2021-04-04 2021-05-09 Retrofitting of public in Public Facilities Envelope 05 ion buildings-mechanical phase P143580-BA-BEEP-8906BA- Pending RFB-W-20-66-RS / Energy Efficiency Investments Single Stage - One 2021-11- IBRD / 89060 Post Request for Bids Open - National 0.00 Implementat 2021-01-17 2021-01-22 2021-03-05 2021-04-04 2021-05-09 Retrofitting of public in Public Facilities Envelope 05 ion buildings-mechanical phase P143580-BA-BEEP-8906BA- Pending RFB-W-20-68-RS / Energy Efficiency Investments Single Stage - One 2021-11- IBRD / 89060 Post Request for Bids Open - National 0.00 Implementat 2021-01-17 2021-01-22 2021-03-05 2021-04-04 2021-05-09 Retrofitting of public in Public Facilities Envelope 05 ion buildings-mechanical phase P143580-BA-BEEP-8906BA- Pending RFB-W-20-70-RS / Energy Efficiency Investments Single Stage - One 2021-11- IBRD / 89060 Post Request for Bids Open - National 0.00 Implementat 2021-01-17 2021-01-22 2021-03-05 2021-04-04 2021-05-09 Retrofitting of public in Public Facilities Envelope 05 ion buildings-mechanical phase P143580-BA-BEEP-8906BA- Pending RFB-W-20-71-RS / Energy Efficiency Investments Single Stage - One 2021-11- IBRD / 89060 Post Request for Bids Open - National 0.00 Implementat 2021-01-17 2021-01-22 2021-03-05 2021-04-04 2021-05-09 Retrofitting of public in Public Facilities Envelope 05 ion buildings-mechanical phase P143580-BA-BEEP-8906BA- Pending RFB-W-20-72-RS / Energy Efficiency Investments Single Stage - One 2021-11- IBRD / 89060 Post Request for Bids Open - National 0.00 Implementat 2021-01-17 2021-01-22 2021-03-05 2021-04-04 2021-05-09 retrofitting of public buildings- in Public Facilities Envelope 05 ion mechanical phase P143580-BA-BEEP-8906BA- RFB-W-20-67-RS / Energy Efficiency Investments Single Stage - One 2021-11- IBRD / 89060 Post Request for Bids Open - National 0.00 Canceled 2021-01-17 2021-01-22 2021-03-05 2021-04-04 2021-05-09 Retrofitting of public in Public Facilities Envelope 05 buildings-mechanical phase P143580-BA-BEEP-8906BA- RFB-W-20-18-RS / Energy Efficiency Investments Single Stage - One 2021-07- IBRD / 89060 Post Request for Bids Open - National 0.00 Canceled 2020-10-12 2020-10-17 2020-11-28 2020-12-28 2021-02-01 Retrofitting of public in Public Facilities Envelope 31 buildings P143580-BA-BEEP-8906BA- Request for RFB-W-21-90-RS / Bids - Small Pending Energy Efficiency Investments Single Stage - One 2022-03- Retrofitting of public IBRD / 89060 Post Request for Bids Open - National Works SPD (1 0.00 Implementat 2021-06-10 2021-06-15 2021-07-27 2021-08-26 2021-09-30 in Public Facilities Envelope 29 buildings- Rectory envelope ion building,Banja Luka process) Request for P143580-BA-BEEP-8906BA- Bids - Works Pending Energy Efficiency Investments Single Stage - One 2021-07- RFB-W-20-11-RS / IBRD / 89060 Post Request for Bids Open - National (without 0.00 Implementat 2020-10-12 2020-10-17 2020-11-28 2020-12-28 2021-02-01 in Public Facilities Envelope 31 Retrofitting of public building prequalificati ion on) SPD P143580-BA-BEEP-8906BA- Request for RFB-W-21-96-RS / Rectory Bids - Small Pending Energy Efficiency Investments Single Stage - One 2022-11- building, Banja Luka, IBRD / 89060 Post Request for Bids Open - National Works SPD (1 0.00 Implementat 2022-02-10 2022-02-15 2022-03-29 2022-04-28 2022-06-02 in Public Facilities Envelope 29 University of Banja Luka, envelope ion Mechanical phase process) National P143580-BA-BEEP-8906BA- Procurement Pending RFB-W-21-97-RS / Faculty of Energy Efficiency Investments Single Stage - One Document - 1 2022-11- IBRD / 89060 Post Request for Bids Open - National 0.00 Implementat 2022-02-10 2022-02-15 2022-03-29 2022-04-28 2022-06-02 Medicine, Foca, Mechanical in Public Facilities Envelope Envelope 29 ion phase process (Non Bank-SPD) P143580-BA-BEEP-8906BA- National RFB-W-22-106-RS / Procurement Secondary School of Pending Energy Efficiency Investments Single Stage - One Document - 1 2022-12- Economics Banja Luka and IBRD / 89060 Post Request for Bids Open - National 0.00 Implementat 2022-02-27 2022-03-04 2022-04-15 2022-05-15 2022-06-19 in Public Facilities Envelope Envelope 16 Secondary School of ion process (Non Polytechnics, Banja Luka, Bank-SPD) Mechanical phase P143580-BA-BEEP-8906BA- National RFB-W-22-107-RS / Procurement Pending Retrofitting of public Energy Efficiency Investments Single Stage - One Document - 1 2022-12- IBRD / 89060 Post Request for Bids Open - National 0.00 Implementat 2022-02-27 2022-03-04 2022-04-15 2022-05-15 2022-06-19 buildings- University of Banja in Public Facilities Envelope Envelope 16 ion Luka, Rectory building, Banja process (Non Luka Bank-SPD) Page 2 National P143580-BA-BEEP-8906BA- Procurement RFB-W-22-108-RS / Pending Energy Efficiency Investments Single Stage - One Document - 1 2022-12- University of Banja Luka, IBRD / 89060 Post Request for Bids Open - National 0.00 Implementat 2022-02-27 2022-03-04 2022-04-15 2022-05-15 2022-06-19 in Public Facilities Envelope Envelope 16 Faculty of Humanities and ion process (Non Social Sciences, Banja Luka Bank-SPD) National P143580-BA-BEEP-8906BA- Procurement RFB-W-22-109-RS / Health Pending Energy Efficiency Investments Single Stage - One Document - 1 2022-12- Center “Dr Milenko IBRD / 89060 Post Request for Bids Open - National 0.00 Implementat 2022-02-27 2022-03-04 2022-04-15 2022-05-15 2022-06-19 in Public Facilities Envelope Envelope 16 Muratovic", Berkovici, ion process (Non Mechanical phase Bank-SPD) National P143580-BA-BEEP-8906BA- Procurement RFB-W-22-110-RS / Pending Energy Efficiency Investments Single Stage - One Document - 1 2022-12- Elementary school "Sveti Sava" IBRD / 89060 Post Request for Bids Open - National 0.00 Implementat 2022-02-27 2022-03-04 2022-04-15 2022-05-15 2022-06-19 in Public Facilities Envelope Envelope 16 Kakmuz/Petrovo, Mechanical ion process (Non phase Bank-SPD) National P143580-BA-BEEP-8906BA- Procurement Pending RFB-W-22-111-RS / High Energy Efficiency Investments Single Stage - One Document - 1 2022-12- IBRD / 89060 Post Request for Bids Open - National 0.00 Implementat 2022-02-27 2022-03-04 2022-04-15 2022-05-15 2022-06-19 School Centre “Jovan Cvijić” in Public Facilities Envelope Envelope 16 ion Modriča, Mechanical phase process (Non Bank-SPD) National P143580-BA-BEEP-8906BA- Procurement RFB-W-22-112-RS / Pending Energy Efficiency Investments Single Stage - One Document - 1 2022-12- Elementary school "Sveti IBRD / 89060 Post Request for Bids Open - National 0.00 Implementat 2022-02-27 2022-03-04 2022-04-15 2022-05-15 2022-06-19 in Public Facilities Envelope Envelope 16 Vasilije Ostroški” Trebinje, ion process (Non Mechanical phase Bank-SPD) National P143580-BA-BEEP-8906BA- Procurement Pending RFB-W-20-67-RS. / University Energy Efficiency Investments Single Stage - One Document - 1 2022-12- IBRD / 89060 Post Request for Bids Open - National 0.00 Implementat 2022-02-21 2022-02-26 2022-04-09 2022-05-09 2022-06-13 of Medicine-dentistry Banja in Public Facilities Envelope Envelope 10 ion Luka, Mechanical phase process (Non Bank-SPD) GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual P143580-BA-BEEP-8906BA- Pending Energy Efficiency Investments Request for Single Stage - One RFQ-G-20-26- RS / Metering IBRD / 89060 Post Open - National 0.00 Implementati 2020-12-06 2021-01-31 2021-07-30 in Public Facilities Quotations Envelope equipment on P143580-BA-BEEP-8906BA- Pending RFQ-G-20-27- RS / Energy Efficiency Investments Request for Single Stage - One IBRD / 89060 Post Open - National 0.00 Implementati 2020-12-06 2021-01-31 2021-07-30 Equipment for supervision - in Public Facilities Quotations Envelope on vehicle P143580-BA-BEEP-8906BA- Energy Efficiency Investments Request for Single Stage - One RFQ-G-20-28- RS / Video IBRD / 89060 Post Open - National 0.00 Canceled 2020-12-06 2021-01-31 2021-07-30 in Public Facilities Quotations Envelope Surveillance P143580-BA-BEEP-8906BA- Pending Energy Efficiency Investments Request for Single Stage - One RFQ-G-20-29- RS / Supply of IBRD / 89060 Post Open - National 0.00 Implementati 2020-12-06 2021-01-31 2021-07-30 in Public Facilities Quotations Envelope solar panels on NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual P143580-BA-BEEP-5538BA- Consultant Energy Efficiency Investments Pending CQ-CS-19-82-RS / Technical IBRD / 89060 Post Qualification Open - National 0.00 2020-10-12 2020-11-02 2020-12-16 2021-01-15 2021-02-19 2021-08-18 in Public Facilities Implementation design audit Selection P143580-BA-BEEP-8906BA- Consultant Energy Efficiency Investments Pending RFP-CQ-20-3-RS / IBRD / 89060 Post Qualification Open - National 0.00 2020-10-12 2020-11-02 2020-12-16 2021-01-15 2021-02-19 2021-08-18 in Public Facilities Implementation Supervision of works Selection P143580-BA-BEEP-8906BA- Consultant Energy Efficiency Investments Pending RFP-CQ-20-23-RS / IBRD / 89060 Post Qualification Open - National 0.00 2020-10-12 2020-11-02 2020-12-16 2021-01-15 2021-02-19 2021-08-18 in Public Facilities Implementation Supervision of works Selection P143580-BA-BEEP-5393BA- QBS-CS-14-23-RS / EE Energy Efficiency Investments Quality Based Information system IBRD / 89060 Post Open - National 282,728.17 Signed 2020-10-12 2021-03-13 2020-11-02 2021-03-17 2020-12-16 2021-03-29 2021-01-13 2021-03-31 2021-02-12 2021-04-13 2021-03-14 2021-04-16 2021-04-18 2020-08-10 2022-04-18 in Public Facilities Selection development (Phase 1 and Phase 2) P143580-BA-BEEP-8906BA- Consultant Energy Efficiency Investments Under RFP-CQ-20-75-RS / Detailed IBRD / 89060 Post Qualification Open - National 0.00 2020-11-25 2020-11-23 2020-12-16 2021-01-29 2021-02-28 2021-04-04 2021-10-01 in Public Facilities Implementation Energy Audit Selection P143580-BA-BEEP-8906BA- RFP-QBS-20-30- R / Project Energy Efficiency Investments Quality Based IBRD / 89060 Post Open - National 0.00 Canceled 2020-10-12 2020-11-02 2020-12-16 2021-01-13 2021-02-12 2021-03-14 2021-04-18 2022-04-18 implementation and in Public Facilities Selection monitoring assistance P143580-BA-BEEP-8906BA- Consultant RFP-CQ-20-40-RS / Energy Efficiency Investments IBRD / 89060 Post Qualification Open - National 0.00 Under Review 2020-12-24 2021-11-25 2021-01-14 2021-02-27 2021-03-29 2021-05-03 2021-10-30 Trainings and event in Public Facilities Selection management Page 3 P143580-BA-BEEP-8906BA- Consultant Energy Efficiency Investments Pending RFP-CQ-21-88-RS / Energy IBRD / 89060 Post Qualification Open - National 0.00 2021-05-31 2021-06-21 2021-08-04 2021-09-03 2021-10-08 2022-04-06 in Public Facilities Implementation certificates Selection P143580-BA-BEEP-8906BA- Consultant Energy Efficiency Investments Pending RFP-CQ-CS-21-92-R / IBRD / 89060 Post Qualification Open - National 0.00 2021-06-10 2021-07-01 2021-08-14 2021-09-13 2021-10-18 2022-04-16 in Public Facilities Implementation Supervision of works Selection P143580-BA-BEEP-8906BA- Consultant Energy Efficiency Investments Pending RFP-CQ-CS-21-93-R / IBRD / 89060 Post Qualification Open - National 0.00 2021-06-10 2021-07-01 2021-08-14 2021-09-13 2021-10-18 2022-04-16 in Public Facilities Implementation Technical design Selection P143580-BA-BEEP-8906BA- Consultant Energy Efficiency Investments Pending RFP-CQ-CS-21-94-R / IBRD / 89060 Post Qualification Open - National 0.00 2021-06-18 2021-07-09 2021-08-22 2021-09-21 2021-10-26 2022-04-24 in Public Facilities Implementation Technical design audit Selection Support for the Development P143580-BA-BEEP-8906BA- Consultant of Scalable Financing RFP-CQ-21-98-RS / FIDIC IBRD / 89060 Post Qualification Open - National 0.00 Canceled 2021-07-09 2021-07-30 2021-09-12 2021-10-12 2021-11-16 2022-05-15 Mechanisms and Capacity training for PIU BEEP staff Selection Building P143580-BA-BEEP-8906BA- Consultant Energy Efficiency Investments RFP-CQ-21-99-RS / Project IBRD / 89060 Post Qualification Open - National 0.00 Under Review 2021-10-15 2021-11-14 2021-11-05 2021-12-19 2022-01-18 2022-02-22 2022-08-21 in Public Facilities monitoring assistance Selection P143580-BA-BEEP-8906BA- Energy Efficiency Investments Quality Based RFP-QBS-20-42-RS / IBRD / 89060 Post Open - National 0.00 Canceled 2020-12-30 2021-01-20 2021-03-05 2021-04-02 2021-05-02 2021-06-01 2021-07-06 2022-07-06 in Public Facilities Selection Trainings P143580-BA-BEEP-8906BA- RFP-CQ-20-42-RS / TRAINING The objective of the Support for the Development Consultant assignment is to organize of Scalable Financing Under IBRD / 89060 Post Qualification Open - National 0.00 2022-01-27 2021-11-17 2022-02-17 2022-04-02 2022-05-02 2022-06-06 2022-12-03 training for various project Mechanisms and Capacity Implementation Selection stakeholders to spread know- Building how, share lessons learned, and additionally improve knowledge of the PIU staff. Support for the Development P143580-BA-BEEP-8906BA- Consultant of Scalable Financing Pending RFP-CQ-21-100-RS / PIU IBRD / 89060 Post Qualification Open - National 0.00 2022-02-18 2022-03-11 2022-04-24 2022-05-24 2022-06-28 2022-12-25 Mechanisms and Capacity Implementation Technical Assistence Selection Building INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual P143580-BA-BEEP-8906BA- Individual Energy Efficiency Investments RFP-IC-20-39-RS / Review of IBRD / 89060 Post Consultant Open 0.00 Canceled 2020-12-25 2021-02-12 2021-03-05 2021-04-09 2021-10-06 in Public Facilities the Promotion Action Plan Selection P143580-BA-BEEP-8906BA- RFP-IC-20-46-RS / Study on Individual Energy Efficiency Investments macroeconomic effects of EE IBRD / 89060 Post Consultant Open 0.00 Canceled 2020-12-30 2021-02-17 2021-03-10 2021-04-14 2021-10-11 in Public Facilities measures (Economics Expert) Selection (Key Expert Coordinator) P143580-BA-BEEP-8906BA- Individual RFP-IC-20-24-RS / Social Energy Efficiency Investments Pending IBRD / 89060 Post Consultant Open 0.00 2020-10-12 2020-11-30 2020-12-21 2021-01-25 2021-07-24 Monitoring - Metodology and in Public Facilities Implementation Selection Baseline Survay P143580-BA-BEEP-8906BA- Individual RFP-IC-20-52-RS / Social Energy Efficiency Investments IBRD / 89060 Post Consultant Open 0.00 Canceled 2020-12-30 2021-02-17 2021-03-10 2021-04-14 2021-10-11 Monitoring - Metodology and in Public Facilities Selection Survay after investment P143580-BA-BEEP-8906BA- Individual RFP-IC-20-53-RS / Social Energy Efficiency Investments IBRD / 89060 Post Consultant Open 0.00 Canceled 2020-12-30 2021-02-17 2021-03-10 2021-04-14 2021-10-11 Monitoring - Data Analysis in Public Facilities Selection and Final Report P143580-BA-BEEP-8906BA- Energy Efficiency Investments RFP-IC-20-55-RS / IBRD / 89060 Prior Direct Selection Direct 20,334.62 Under Review 2020-11-01 2020-11-24 2020-11-11 2020-12-01 2021-01-15 2020-11-01 2021-07-14 in Public Facilities Procurement Manager P143580-BA-BEEP-8906BA- Energy Efficiency Investments RFP-IC-20-56-RS / IBRD / 89060 Prior Direct Selection Direct 31,923.68 Signed 2020-11-01 2020-11-24 2020-11-11 2020-11-02 2021-01-15 2020-11-01 2021-07-14 in Public Facilities Accountant P143580-BA-BEEP-8906BA- Energy Efficiency Investments RFP-IC-20-57-RS / IBRD / 89060 Prior Direct Selection Direct 34,090.70 Signed 2020-11-01 2020-11-24 2020-11-11 2020-11-02 2021-01-15 2020-11-01 2021-07-14 in Public Facilities Operations officer P143580-BA-BEEP-8906BA- Energy Efficiency Investments RFP-IC-20-58-RS / Technical IBRD / 89060 Prior Direct Selection Direct 25,619.59 Under Review 2020-11-01 2020-11-24 2020-11-11 2020-11-02 2021-01-15 2020-11-01 2021-07-14 in Public Facilities expert 1 P143580-BA-BEEP-8906BA- Energy Efficiency Investments RFP-IC-20-5-RS / Technical IBRD / 89060 Prior Direct Selection Direct 112,351.28 Signed 2020-10-13 2020-11-26 2020-10-23 2020-12-02 2020-12-27 2020-06-08 2021-06-25 in Public Facilities Expert 2 P143580-BA-BEEP-8906BA- Energy Efficiency Investments IBRD / 89060 Post Direct Selection Direct 0.00 Under Review 2020-11-01 2021-02-01 2020-11-11 2021-01-15 2021-07-14 RFP-IC-20-62-RS / Driver in Public Facilities P143580-BA-BEEP-8906BA- RFP-IC-20-73-RS / Preparation of Pre-study for Individual Energy Efficiency Investments Pending heating on biomass for IBRD / 89060 Post Consultant Open 0.00 2020-11-15 2021-01-03 2021-01-24 2021-02-28 2021-08-27 in Public Facilities Implementation Psychiatry Prijedor (analysis Selection for piloting of public-private partnership) Page 4 P143580-BA-BEEP-8906BA- RFP-IC-20-60-RS / Energy Efficiency Investments IBRD / 89060 Prior Direct Selection Direct 33,336.43 Under Review 2020-11-01 2020-11-24 2020-11-11 2020-11-02 2021-01-15 2020-11-01 2021-07-14 Accountant and financial in Public Facilities specialist P143580-BA-BEEP-8906BA- RFP-IC-20-79-RS / Preparation of Pre-study for Individual Energy Efficiency Investments Pending heating on biomass for IBRD / 89060 Post Consultant Open 0.00 2021-03-31 2021-05-19 2021-06-09 2021-07-14 2022-01-10 in Public Facilities Implementation Faculty in Zvornik and Selection Modrica (analysis for piloting of public-private partnership) P143580-BA-BEEP-8906BA- RFP-IC-20-80-RS / Preparation of Pre-study for Individual Energy Efficiency Investments Pending heating on biomass for school IBRD / 89060 Post Consultant Open 0.00 2021-03-31 2021-05-19 2021-06-09 2021-07-14 2022-01-10 in Public Facilities Implementation in Modrica and Zvornik Selection (analysis for piloting of public- private partnership) P143580-BA-BEEP-8906BA- RFP-IC-20-31-RS / ESCO Individual Energy Efficiency Investments model RS - Energy Efficiency IBRD / 89060 Post Consultant Open 0.00 Canceled 2020-12-15 2021-02-02 2021-02-23 2021-03-30 2021-09-26 in Public Facilities Expert (Key Expert Selection Coordinator) P143580-BA-BEEP-8906BA- Individual RFP-IC-20-32-RS / ESCO Energy Efficiency Investments IBRD / 89060 Post Consultant Open 0.00 Canceled 2020-12-15 2021-02-02 2021-02-23 2021-03-30 2021-09-26 model RS - Financial Expert in Public Facilities Selection (Support Expert) P143580-BA-BEEP-8906BA- Individual RFP-IC-20-33-RS / ESCO Energy Efficiency Investments IBRD / 89060 Post Consultant Open 0.00 Canceled 2020-12-15 2021-02-02 2021-02-23 2021-03-30 2021-09-26 model RS - Tax Expert in Public Facilities Selection (Support Expert) P143580-BA-BEEP-8906BA- Individual RFP-IC-20-34-RS / ESCO Energy Efficiency Investments IBRD / 89060 Post Consultant Open 0.00 Canceled 2020-12-15 2021-02-02 2021-02-23 2021-03-30 2021-09-26 model RS - Banking Expert in Public Facilities Selection (Support Expert) P143580-BA-BEEP-8906BA- RFP-IC-20-38-RS / Pilot Individual Energy Efficiency Investments Pending model contracting and ESCO IBRD / 89060 Post Consultant Open 0.00 2020-12-20 2021-02-07 2021-02-28 2021-04-04 2021-10-01 in Public Facilities Implementation model (Finance Expert) Selection (Support Expert) P143580-BA-BEEP-8906BA- RFP-IC-20-36-RS / Pilot Individual model contracting and ESCO Energy Efficiency Investments Pending IBRD / 89060 Post Consultant Open 0.00 2020-12-20 2021-02-07 2021-02-28 2021-04-04 2021-10-01 model (Energy Efficiency in Public Facilities Implementation Selection Expert) (Key Expert Coordinator) P143580-BA-BEEP-8906BA- RFP-IC-20-37-RS / Pilot Individual Energy Efficiency Investments Pending model contracting and ESCO IBRD / 89060 Post Consultant Open 0.00 2020-12-20 2021-02-07 2021-02-28 2021-04-04 2021-10-01 in Public Facilities Implementation model (Technical Expert) Selection (Support Expert) P143580-BA-BEEP-8906BA- Individual RFP-IC-20-74-RS / Pilot Energy Efficiency Investments Pending IBRD / 89060 Post Consultant Open 0.00 2021-03-10 2021-04-28 2021-05-19 2021-06-23 2021-12-20 model contracting and ESCO in Public Facilities Implementation Selection model (Procurement Expert) P143580-BA-BEEP-8906BA- Individual Energy Efficiency Investments Pending RFP-IC-20-35-RS / Feasibility IBRD / 89060 Post Consultant Open 0.00 2020-12-15 2021-02-02 2021-02-23 2021-03-30 2021-09-26 in Public Facilities Implementation study for PPP Selection P143580-BA-BEEP-8906BA- Individual Energy Efficiency Investments Pending RFP-IC-20-41-RS / Online PR IBRD / 89060 Post Consultant Open 0.00 2020-12-01 2021-01-19 2021-02-09 2021-03-16 2021-09-12 in Public Facilities Implementation Campaign Selection P143580-BA-BEEP-8906BA- Individual RFP-IC-20-43-RS / Energy Efficiency Investments IBRD / 89060 Post Consultant Open 0.00 Canceled 2020-12-30 2021-02-17 2021-03-10 2021-04-14 2021-10-11 Development of energy RS in Public Facilities Selection management model P143580-BA-BEEP-8906BA- RFP-IC-20-44-RS / Individual Energy Efficiency Investments Development of training IBRD / 89060 Post Consultant Open 0.00 Canceled 2020-12-30 2021-02-17 2021-03-10 2021-04-14 2021-10-11 in Public Facilities programs for RS energy Selection management P143580-BA-BEEP-8906BA- Individual Energy Efficiency Investments RFP-IC-20-45-RS / IBRD / 89060 Post Consultant Open 0.00 Canceled 2020-12-30 2021-02-17 2021-03-10 2021-04-14 2021-10-11 in Public Facilities Preparation of TOR Selection P143580-BA-BEEP-8906BA- RFP-IC-20-47-RS / Study on Individual Energy Efficiency Investments macroeconomic effects of EE IBRD / 89060 Post Consultant Open 0.00 Canceled 2020-12-30 2021-02-17 2021-03-10 2021-04-14 2021-10-11 in Public Facilities measures (Energy Efficiency Selection Expert) P143580-BA-BEEP-8906BA- Individual RFP-IC-20-48-RS / Study on Energy Efficiency Investments IBRD / 89060 Post Consultant Open 0.00 Canceled 2020-12-30 2021-02-17 2021-03-10 2021-04-14 2021-10-11 macroeconomic effects of EE in Public Facilities Selection measures (Modeling Expert) P143580-BA-BEEP-8906BA- RFP-IC-20-49-RS / Study on Individual Energy Efficiency Investments macroeconomic effects of EE IBRD / 89060 Post Consultant Open 0.00 Canceled 2020-12-30 2021-02-17 2021-03-10 2021-04-14 2021-10-11 in Public Facilities measures (Public Finance Selection Expert) P143580-BA-BEEP-8906BA- Individual RFP-IC-20-50-RS / EE Energy Efficiency Investments Pending IBRD / 89060 Post Consultant Open 0.00 2021-01-11 2021-03-01 2021-03-22 2021-04-26 2021-10-23 Information system in Public Facilities Implementation Selection development Supervision Page 5 P143580-BA-BEEP-8906BA- Individual Energy Efficiency Investments Pending RFP-IC-20-54-RS / WBIF IBRD / 89060 Post Consultant Open 0.00 2020-12-30 2021-02-17 2021-03-10 2021-04-14 2021-10-11 in Public Facilities Implementation Project Aplication Preparation Selection P143580-BA-BEEP-8906BA- Energy Efficiency Investments RFP-IC-20-61-RS / IC IBRD / 89060 Prior Direct Selection Direct 0.00 Canceled 2020-11-01 2020-11-11 2021-01-15 2021-07-14 in Public Facilities communication officer P143580-BA-BEEP-8906BA- Individual Energy Efficiency Investments RFP-IC-21-89-RS / IC IBRD / 89060 Post Consultant Open 0.00 Under Review 2021-03-16 2021-03-23 2021-05-04 2021-05-25 2021-06-29 2021-12-26 in Public Facilities ommunication officer Selection P143580-BA-BEEP-8906BA- RFP-IC-21-91-RS / Position Individual of Procurement Manager at RS IBRD / 89060 Project Management Post Consultant Open 0.00 Under Review 2021-06-09 2021-05-24 2021-07-28 2021-08-18 2021-09-22 2022-03-21 Project Implementation Unit Selection BEEP P143580-BA-BEEP-8906BA- RFP-IC-21-95-RS / Position Individual of Procurement Officer at RS IBRD / 89060 Project Management Post Consultant Open 0.00 Under Review 2021-06-09 2021-05-25 2021-07-28 2021-08-18 2021-09-22 2022-03-21 Project Implementation Unit Selection BEEP P143580-BA-BEEP-8906BA- Individual RFP-IC-22-102-RS / Director Under IBRD / 89060 Project Management Post Consultant Limited 0.00 2022-01-26 2022-01-16 2022-01-31 2022-02-21 2022-03-28 2022-09-24 of the Project Implementation Implementation Selection Unit BEEP RS P143580-BA-BEEP-8906BA- RFP-IC-22-101-RS / Project Under Management Advisor - during IBRD / 89060 Project Management Post Direct Selection Direct 0.00 2022-01-27 2022-01-18 2022-02-06 2022-04-12 2022-10-09 Implementation the transition period, 6 month, direct contracting P143580-BA-BEEP-8906BA- Individual Under RFP-IC-22-104-RS / Building IBRD / 89060 Project Management Post Consultant Limited 0.00 2022-01-28 2022-01-18 2022-02-02 2022-02-23 2022-03-30 2022-09-26 Implementation Expert (PIU) Selection P143580-BA-BEEP-8906BA- RFP-IC-21-96-RS / Individual Energy Efficiency Investments Under Accountant and Financial IBRD / 89060 Post Consultant Open 0.00 2021-08-03 2021-07-01 2021-09-21 2021-10-12 2021-11-16 2022-05-15 in Public Facilities Implementation Specialist - full-time position Selection in PIU team P143580-BA-BEEP-8906BA- RFP-IC-22-105-RS / EE Support for the Development Individual Information system of Scalable Financing Pending IBRD / 89060 Post Consultant Limited 0.00 2022-02-10 2022-02-15 2022-03-08 2022-04-12 2022-10-09 development- Preparation and Mechanisms and Capacity Implementation Selection drafting of legal acts and Building regulations Page 6