PROCUREMENT PLAN Project information: India; SECOND DAM REHABILITATION AND IMPROVEMENT PROJECT (P170873) Project Implementation agency: Central Water Commission, Govt. of India and various States/Agencies Date of the Procurement Plan: March 9, 2020 Period covered by this Procurement Plan: 18 months [as updated regularly on STEP] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: National competition for the procurement of goods, works and non-consulting services according to the established thresholds will be conducted in accordance with paragraphs 5.3 – 5.6 of Section V of the Regulations and the following provisions: i. Only the model bidding documents for National Competitive Procurement (NCP) agreed with the GOI Task Force (and as amended for time to time), shall be used for bidding. ii. Invitations to bid shall be advertised on a widely used website or electronic portal with free open access at least 30 days prior to the deadline for the submission of bids, unless otherwise agreed in the approved procurement plan. iii. No special preference will be accorded to any bidder either for price or for other terms and conditions when competing with foreign bidders, state-owned enterprises, small-scale enterprises or enterprises from any given State. iv. Except with the prior concurrence of the Bank, there shall be no negotiation of price with the bidders, even with the lowest evaluated bidder. v. Government e-Marketplace (GeM)* set-up by Ministry of Commerce, Government of India will be acceptable for procurement under Request for Quotations (RFQ) method. vi. At the Borrower’s request, the Bank may agree to the Borrower’s use, in whole or in part, of its electronic procurement system, provided that the Bank is satisfied with the adequacy of such system. vii. Procurement will be open to eligible firms from any country. This eligibility shall be as defined under Section III of the Procurement Regulations. Accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. viii. The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals include a signed acceptance in the bid, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti- Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. ix. The Borrower shall use an effective complaints mechanism for handling procurement related complaints in a timely manner. x. Procurement Documents will include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety risks and impacts. *Use of GeM will be allowed in lieu of RFQ/Shopping as per following details: i. up to INR 50,000 in catalog mode (viz. any available item could be selected by IA without further competition), provided selected Item/Supplier meeting the requisite quality, specification and delivery period. ii. up to INR 3 Million from the Supplier having lowest price amongst at least three Suppliers meeting the requisite quality, specification and delivery period. The tools for online bidding and online reverse auction available on GeM may be used by the Purchaser. iii. up to INR equivalent of US$ 100,000 from the Supplier having lowest price and meeting the requisite quality, specification and delivery period after mandatorily obtaining bids from at least three Suppliers, using online bidding or reverse auction tool provided on GeM. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets Not Applicable Procurement of Second Hand Goods: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations. Goods: is applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable Other Relevant Procurement Information. All contracts not covered under prior review by the Bank will be subject to post review during implementation support missions and/or special post review missions, including missions by consultants hired by the Bank. To avoid doubts, the Bank may conduct, at any time, Independent Procurement Reviews of all the contracts financed under the loan. Even for Post Review cases, the inputs of Bank on Technical Specifications / TORs will be obtained by project. PROCUREMENT India : Second Dam Rehabilitation and Improvement Project PLAN General Information Country: India 2020-05-20 Bank’s Approval Date of the Original Procurement Plan: 2022-08-03 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P170873 GPN Date: 2020-04-30 Project Name: Second Dam Rehabilitation and Improvement Project Loan / Credit No: / , IBRD / 91810 Rajasthan SPMU Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned IN-RAJASTHAN SPMU-174058 Component 1: Rehabilitation -CW-RFB / Rehabilitation, Imp and Management Planning f Single Stage - Two E Under Imple 2023-04-0 rovement and Basic Facility o / Post Request for Bids Open - National 2,073,333.33 0.00 2020-05-25 2020-05-22 2020-05-26 2020-07-10 2020-09-23 2020-10-18 or Dams and Associated App nvelope mentation 6 f Chhapi Dam in Jhalawar Dis urtenances trict of Rajasthan under DRIP -II IN-RAJASTHAN SPMU-174059 Component 1: Rehabilitation -CW-RFB / Rehabilitation, Imp and Management Planning f Single Stage - Two E Under Imple 2023-04-0 rovement and Basic Facility o / Post Request for Bids Open - National 2,854,666.67 0.00 2020-05-26 2020-05-22 2020-05-27 2020-07-11 2020-09-24 2020-10-19 or Dams and Associated App nvelope mentation 7 f Sukli Selwada Dam in Sirohi urtenances District of Rajasthan under D RIP-II IN-RAJASTHAN SPMU-174060 Component 1: Rehabilitation -CW-RFB / Rehabilitation, Imp and Management Planning f Single Stage - Two E Under Imple 2023-10-1 rovement and Basic Facility / Post Request for Bids Open - National 3,244,000.00 0.00 2020-05-26 2020-05-26 2020-05-27 2020-07-11 2020-09-24 2020-10-19 or Dams and Associated App nvelope mentation 9 of Jawai Dam in Pali District o urtenances f Rajasthan under DRIP-II IN-RAJASTHAN SPMU-174061 Component 1: Rehabilitation -CW-RFB / Rehabilitation, Imp and Management Planning f Single Stage - Two E Under Imple 2023-10-2 rovement and Basic Facility o / Post Request for Bids Open - National 3,496,000.00 0.00 2020-05-29 2020-06-01 2020-05-30 2020-07-14 2020-12-04 2020-09-27 2020-10-22 or Dams and Associated App nvelope mentation 2 f Mahi Dam in Banswara Dist urtenances rict of Rajasthan under DRIP-I I IN-RAJASTHAN SPMU-174062 Component 1: Rehabilitation -CW-RFB / Rehabilitation, Imp and Management Planning f Single Stage - Two E Under Imple 2022-10-2 rovement and Basic Facility o / Post Request for Bids Open - National 1,536,000.00 0.00 2020-05-29 2020-03-30 2020-05-30 2020-07-14 2020-12-04 2020-09-27 2020-10-22 or Dams and Associated App nvelope mentation 2 f Matrikundia Dam in Bhilwar urtenances a District of Rajasthan under DRIP-II IN-RAJASTHAN SPMU-174063 Component 1: Rehabilitation -CW-RFB / Rehabilitation, Imp and Management Planning f Single Stage - Two E Pending Imp 2022-10-2 rovement and Basic Facility o / Post Request for Bids Open - National 2,578,666.67 0.00 2020-05-29 2020-05-30 2020-07-14 2020-09-27 2020-10-22 or Dams and Associated App nvelope lementation 2 f Gambhiri Dam in Chittorgar urtenances h District of Rajasthan under DRIP-II IN-RAJASTHAN SPMU-174064 Component 1: Rehabilitation -CW-RFB / Rehabilitation, Imp and Management Planning f Single Stage - Two E Pending Imp 2023-04-1 rovement and Basic Facilit / Post Request for Bids Open - National 1,528,000.00 0.00 2020-06-02 2020-06-03 2020-07-18 2020-10-01 2020-10-26 or Dams and Associated App nvelope lementation 4 y of Som Kamla Amba Dam i urtenances n Dungarpur District of Rajas than under DRIP-II IN-RAJASTHAN-SPMU-17405 National Procure Component 1: Rehabilitation 7-CW-RFB / Rehabilitation, Im ment Document - and Management Planning f Single Stage - Two E Pending Imp 2021-01-1 provement and Basic Facility IBRD / 91810 Post Request for Bids Open - National 2 Envelope proce 4,734,666.67 0.00 2020-08-07 2020-08-12 2020-09-09 2020-10-05 2020-11-02 or Dams and Associated App nvelope lementation 6 of Bisalpur Dam in Tonk Distr ss (Non Bank-SPD urtenances ict of Rajasthan under DRIP-II ) IN-RAJASTHAN SPMU-174057 Component 1: Rehabilitation -CW-RFB / Rehabilitation, Imp and Management Planning f Single Stage - Two E 2023-10-1 rovement and Basic Facility / Post Request for Bids Open - National 4,734,666.67 0.00 Canceled 2020-05-25 2020-04-24 2020-05-26 2020-06-16 2020-07-10 2020-05-27 2020-09-23 2020-10-18 or Dams and Associated App nvelope 8 of Bisalpur Dam in Tonk Distr urtenances ict of Rajasthan under DRIP-II National Procure IN-RAJASTHAN SPMU-303680 Component 1: Rehabilitation ment Document - -CW-RFB / Rehabilitation and and Management Planning f Single Stage - Two E Pending Imp 2025-03-0 IBRD / 91810 Post Request for Bids Open - National 2 Envelope proce 2,246,666.00 0.00 2022-10-15 2022-10-20 2022-12-01 2023-02-13 2023-03-20 improvement work of RPS da or Dams and Associated App nvelope lementation 9 ss (Non Bank-SPD m(Civil Works) under DRIP ph urtenances ) ase-II National Procure IN-RAJASTHAN SPMU-303682 Component 1: Rehabilitation ment Document - -CW-RFB / Rehabilitation and and Management Planning f Single Stage - Two E Pending Imp 2025-03-0 IBRD / 91810 Post Request for Bids Open - National 2 Envelope proce 5,189,333.00 0.00 2022-10-15 2022-10-20 2022-12-01 2023-02-13 2023-03-20 improvement work of Jawaha or Dams and Associated App nvelope lementation 9 ss (Non Bank-SPD r Sagar dam(Civil Works) und urtenances ) er DRIP phase-II National Procure IN-RAJASTHAN SPMU-303683 Component 1: Rehabilitation ment Document - -CW-RFB / Rehabilitation and and Management Planning f Single Stage - Two E Pending Imp 2025-03-0 IBRD / 91810 Post Request for Bids Open - National 2 Envelope proce 1,097,333.00 0.00 2022-10-15 2022-10-20 2022-12-01 2023-02-13 2023-03-20 improvement work of Kota B or Dams and Associated App nvelope lementation 9 ss (Non Bank-SPD arrage dam (Civil Works) und urtenances ) er DRIP phase-II National Procure IN-RAJASTHAN SPMU-303684 Component 1: Rehabilitation ment Document - -CW-RFB / Rehabilitation , im and Management Planning f Single Stage - Two E Pending Imp 2025-02-0 IBRD / 91810 Post Request for Bids Open - National 2 Envelope proce 2,237,333.00 0.00 2022-09-15 2022-09-20 2022-11-01 2023-01-14 2023-02-18 provement and Basic Facility or Dams and Associated App nvelope lementation 7 ss (Non Bank-SPD work of Panchna dam under urtenances ) DRIP phase-II National Procure IN-RAJASTHAN SPMU-303688 Component 1: Rehabilitation ment Document - -CW-RFB / Rehabilitation ,imp and Management Planning f Single Stage - Two E Pending Imp 2025-03-2 IBRD / 91810 Post Request for Bids Open - National 2 Envelope proce 1,569,333.00 0.00 2022-10-01 2022-10-06 2022-11-17 2023-01-30 2023-03-06 rovement and Basic Facility or Dams and Associated App nvelope lementation 5 ss (Non Bank-SPD work of Parbati dam under D urtenances ) RIP phase-II National Procure IN-RAJASTHAN SPMU-303689 Component 1: Rehabilitation ment Document - -CW-RFB / Rehabilitation, Imp and Management Planning f Single Stage - Two E Pending Imp 2025-02-0 IBRD / 91810 Post Request for Bids Open - National 2 Envelope proce 893,333.00 0.00 2022-09-15 2022-09-20 2022-11-01 2023-01-14 2023-02-18 rovement and Basic Facility or Dams and Associated App nvelope lementation 7 ss (Non Bank-SPD work of Raipur luni dam unde urtenances ) r DRIP phase-II National Procure IN-RAJASTHAN SPMU-303690 Component 1: Rehabilitation ment Document - -CW-RFB / Rehabilitation, Imp and Management Planning f Single Stage - Two E Pending Imp 2025-03-0 IBRD / 91810 Post Request for Bids Open - National 2 Envelope proce 2,925,333.00 0.00 2022-10-15 2022-10-20 2022-12-01 2023-02-13 2023-03-20 rovement and Basic Facility or Dams and Associated App nvelope lementation 9 ss (Non Bank-SPD work of Chhaparwara dam un urtenances ) der DRIP phase-II National Procure IN-RAJASTHAN SPMU-303691 Component 1: Rehabilitation ment Document - -CW-RFB / Rehabilitation, Imp and Management Planning f Single Stage - Two E Pending Imp 2025-03-0 IBRD / 91810 Post Request for Bids Open - National 2 Envelope proce 1,130,667.00 0.00 2022-10-15 2022-10-20 2022-12-01 2023-02-13 2023-03-20 rovement and Basic Facility or Dams and Associated App nvelope lementation 9 ss (Non Bank-SPD work of Som Kagdar dam un urtenances ) der DRIP phase-II Page 1 National Procure IN-RAJASTHAN SPMU-303692 Component 1: Rehabilitation ment Document - -CW-RFB / Rehabilitation, Imp and Management Planning f Single Stage - Two E Pending Imp 2025-05-0 IBRD / 91810 Post Request for Bids Open - National 2 Envelope proce 1,581,333.00 0.00 2022-11-15 2022-11-20 2023-01-01 2023-03-16 2023-04-20 rovement and Basic Facility or Dams and Associated App nvelope lementation 9 ss (Non Bank-SPD work of Jakham dam under D urtenances ) RIP phase-II National Procure IN-RAJASTHAN SPMU-303695 Component 1: Rehabilitation ment Document - -CW-RFB / Rehabilitation, Imp and Management Planning f Single Stage - Two E Pending Imp 2025-07-0 IBRD / 91810 Post Request for Bids Open - National 2 Envelope proce 4,000,000.00 0.00 2022-12-15 2022-12-20 2023-01-31 2023-04-15 2023-05-20 rovement and Basic Facility or Dams and Associated App nvelope lementation 3 ss (Non Bank-SPD works of Ora Dam under DRI urtenances ) P-II National Procure IN-RAJASTHAN SPMU-303703 Component 1: Rehabilitation ment Document - -CW-RFB / Rehabilitation and and Management Planning f Single Stage - Two E Pending Imp 2025-03-0 IBRD / 91810 Post Request for Bids Open - National 2 Envelope proce 9,890,000.00 0.00 2022-10-15 2022-10-20 2022-12-01 2023-02-13 2023-03-20 improvement of RPS(HM wor or Dams and Associated App nvelope lementation 9 ss (Non Bank-SPD k) under DRIP Phase-II989 urtenances ) National Procure IN-RAJASTHAN SPMU-303707 Component 1: Rehabilitation ment Document - -CW-RFB / Rehabilitation and and Management Planning f Single Stage - Two E Pending Imp 2025-03-0 IBRD / 91810 Post Request for Bids Open - National 2 Envelope proce 7,800,000.00 0.00 2022-10-15 2022-10-20 2022-12-01 2023-02-13 2023-03-20 improvement of JS(HM work) or Dams and Associated App nvelope lementation 9 ss (Non Bank-SPD under DRIP Phase-II urtenances ) National Procure IN-RAJASTHAN SPMU-303708 Component 1: Rehabilitation ment Document - -CW-RFB / Rehabilitation and and Management Planning f Single Stage - Two E 10,682,670.0 Pending Imp 2025-03-0 IBRD / 91810 Prior Request for Bids Open - National 2 Envelope proce 0.00 2022-10-15 2022-10-20 2022-12-01 2023-02-13 2023-03-20 improvement of Kota barrage or Dams and Associated App nvelope 0 lementation 9 ss (Non Bank-SPD (HM work) under DRIP Phase- urtenances ) II GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-RAJASTHAN SPMU-174066 -GO-RFQ / Procurement of Pri Component 4: Project Manag Request for Quota Single Stage - One E Pending Impl / Post Open - National 16,000.00 0.00 2020-07-20 2020-10-03 2022-03-27 nters/scanners for SPMU/DS ement tions nvelope ementation O/ Field Division Offices. IN-RAJASTHAN SPMU-174067 Component 4: Project Manag Request for Quota Single Stage - One E Pending Impl -GO-RFQ / Procurement of fu / Post Open - National 24,000.00 0.00 2020-07-20 2020-10-03 2022-03-27 ement tions nvelope ementation rniture for SPMU/DS0/ Field D ivision Offices. IN-RAJASTHAN SPMU-174068 Component 4: Project Manag Request for Quota Single Stage - One E Pending Impl -GO-RFQ / Procurement of La / Post Open - National 20,000.00 0.00 2021-01-06 2021-03-22 2022-09-13 ement tions nvelope ementation ptops for SPMU/DS0 IN-RAJASTHAN SPMU-174065 -GO-RFQ / Procurement of de Component 4: Project Manag Request for Quota Single Stage - One E Pending Impl / Post Open - National 26,666.67 0.00 2020-07-20 2020-10-03 2022-03-27 sktop computers for SPMU/D ement tions nvelope ementation SO/ Field Division Offices. IN-RAJASTHAN SPMU-303719 Component 4: Project Manag Request for Quota Single Stage - One E Pending Impl IBRD / 91810 Post Open - National 26,666.00 0.00 2022-09-20 2022-11-15 2023-05-14 -GO-RFQ / Procurement of Fu ement tions nvelope ementation rniture NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-RAJASTHAN SPMU-174069 Component 4: Project Manag Request for Quota Single Stage - One E Pending Impl -NCS-RFQ / Procurement of H / Post Open - National 46,666.67 0.00 2020-07-20 2020-10-03 2022-03-27 ement tions nvelope ementation iring of vehicle for SPMU /DS O IN-RAJASTHAN SPMU-303738 Component 1: Rehabilitation Single Stage - Two E Pending Impl -NC-RFB / Sedimentation Stu IBRD / 91810 and Management Planning f Post Request for Bids Open - National 666,666.00 0.00 2022-12-10 2022-12-15 2023-01-26 2023-04-10 2023-05-15 2026-04-29 nvelope ementation dies for Bisalpur and Mahi Ba or Dams and Associated App jaj Sagar Dam urtenances IN-RAJASTHAN SPMU-303905 Component 4: Project Manag Request for Quota Single Stage - One E Pending Impl IBRD / 91810 Post Open - National 21,333.00 0.00 2022-08-15 2022-10-10 2024-09-09 -NC-RFQ / Hiring of vehicle fo ement tions nvelope ementation r SPMU CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-RAJASTHAN SPMU-303742 -CS-LCS / Consultancy regard Component 2: Dam Safety In Least Cost Selecti Pending Impleme IBRD / 91810 Prior Open - National 4,666,666.00 0.00 2022-12-10 2022-12-31 2023-02-13 2023-03-13 2023-04-12 2023-05-17 2023-06-21 2026-06-05 ing Rajashan State Dam Safe stitutional Strengthening on ntation ty and River Basin planning INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-RAJASTHAN SPMU-303721 Component 4: Project Manag Individual Consult Pending Impleme -CS-INDV / Hiring of Hydro m IBRD / 91810 Post Open - National 10,400.00 0.00 2022-08-16 2022-10-04 2022-10-25 2022-11-29 2023-05-28 ement ant Selection ntation echanical expert for SPMU Ra jasthan IN-RAJASTHAN SPMU-303723 Component 4: Project Manag Individual Consult Pending Impleme -CS-INDV / Hiring of Environ IBRD / 91810 Post Open - National 41,600.00 0.00 2022-08-16 2022-10-04 2022-10-25 2022-11-29 2023-05-28 ement ant Selection ntation mental and Social Experts IN-RAJASTHAN SPMU-303726 Component 4: Project Manag Individual Consult Pending Impleme -CS-INDV / Hiring of Instrume IBRD / 91810 Post Open - National 10,400.00 0.00 2022-08-16 2022-10-04 2022-10-25 2022-11-29 2023-05-28 ement ant Selection ntation ntation Experts IN-RAJASTHAN SPMU-303728 Component 4: Project Manag Individual Consult Pending Impleme -CS-INDV / Hiring of procure IBRD / 91810 Post Open - National 10,400.00 0.00 2022-08-16 2022-10-04 2022-10-25 2022-11-29 2023-05-28 ement ant Selection ntation ment Expert by SPMU Page 2 IN-RAJASTHAN SPMU-303729 Component 4: Project Manag Individual Consult Pending Impleme -CS-INDV / Hiring of Quality a IBRD / 91810 Post Open - National 20,800.00 0.00 2022-08-16 2022-10-04 2022-10-25 2022-11-29 2023-05-28 ement ant Selection ntation ssurance expert by SPMU IN-RAJASTHAN SPMU-303731 Component 4: Project Manag Individual Consult Pending Impleme -CS-INDV / Hiring of GIS expe IBRD / 91810 Post Open - National 10,400.00 0.00 2022-08-16 2022-10-04 2022-10-25 2022-11-29 2023-05-28 ement ant Selection ntation rt by SPMU IN-RAJASTHAN SPMU-303734 Component 4: Project Manag Individual Consult Pending Impleme -CS-INDV / Hiring of Data Ent IBRD / 91810 Post Open - National 2,670.00 0.00 2022-08-16 2022-10-04 2022-10-25 2022-11-29 2023-05-28 ement ant Selection ntation ry Operator by SPMU IN-RAJASTHAN SPMU-303901 -CS-INDV / Hiring of IT/Softwa Component 4: Project Manag Individual Consult Pending Impleme IBRD / 91810 Post Open - National 266,666.00 0.00 2022-12-01 2023-01-19 2023-02-09 2023-03-16 2025-03-05 re expert for development of ement ant Selection ntation Project management Applicat ion under DRIP-II Page 3