PROCUREMENT PLAN - Textual Part Project information: Uzbekistan Medium-Size Cities Integrated Urban Development Project (P162929) Project Implementation agency: “State Investment Committee” or “SIC” means the Borrower’s governmental body established pursuant to the Borrower’s Presidential Decree No. УП-4996 “On the Formation of the State Committee of the Republic of Uzbekistan for Investments” dated March 31, 2017 Date of the Procurement Plan: November 7, 2018 Period covered by this Procurement Plan: From November 2018 to November 2019 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Law of Republic of Uzbekistan “On Public Procurement” dated January 25, 2018 such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: 1. The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. The Bank’s Anti-Corruption Guidelines and Sanctions Framework shall be incorporated into the national bidding documents by adding a page entitled “Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework”. 2. Contracts with an appropriate allocation of responsibilities, risks, and liabilities between the Borrower and the contractors/suppliers/consultants. 3. Rights for the Bank to review procurement documentation and activities. In accordance with the Procurement Regulations, each bidding document and contract shall include provisions stating the Bank's policy to sanction firms or individuals, found to have engaged in fraud and/or corruption as defined in the Procurement Regulations. In accordance with the Procurement Regulations, each bidding document and contract financed out of the proceeds of the Financing Agreement shall provide that bidders, suppliers, contractors and their subcontractors, agents, personnel, consultants, service providers, or suppliers shall permit the Bank to inspect all accounts, records and other documents relating to the bid submission and performance of the contract and to have said accounts and records audited by auditors appointed by the Bank. Acts intended to materially impede the exercise of the Bank's inspection and audit rights provided for in the Procurement Regulations constitute an obstructive practice as defined in the Regulations. 4. No bids shall be rejected solely because they fall below or exceed the estimated cost. All bids (including in the case when less than two bids are received) shall not be rejected, the procurement process shall not be cancelled, and new bids shall not be solicited without the Bank's prior written concurrence. The Bidding Documents template to be used under “national open competitive procurement arrangements” are subject to prior written concurrence by the Bank. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: applicable for those contracts identified in the Procurement Plan tables; Works: is applicable for those contracts identified in the Procurement Plan tables. PROCUREMENT Uzbekistan : Medium-Size Cities Integrated Urban Development Project PLAN General Information Country: Uzbekistan Bank’s Approval Date of the Original Procurement Plan: 2019-01-15 2022-02-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P162929 GPN Date: Project Name: Medium-Size Cities Integrated Urban Development Project Loan / Credit No: TF / A7556, IBRD / 89140 State Investment Committee of the Republic of Uzbekistan Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned MSC/UZB-C/W/1.6 / Restoration/strengthening and adaptive reuse in Component 1: Improvement accordance to modern energy of Urban Services and Single Stage - One 2020-11- IBRD / 89140 Post Request for Bids Open - National 500,553.00 0.00 Canceled 2020-02-12 2020-02-12 2020-02-17 2020-02-15 2020-03-30 2020-05-14 2020-04-29 2020-09-09 2020-06-03 efficiency norms of the former Enhancement of Public Urban Envelope 30 Kindergarten #17 and Spaces Administrative building at the Chartak city MSC/UZB-C/W/1.6.1 / Restoration/strengthening and adaptive reuse in Component 1: Improvement accordance to modern energy of Urban Services and Single Stage - One 2021-06- IBRD / 89140 Post Request for Bids Open - National 500,553.00 0.00 Canceled 2020-09-09 2020-09-11 2020-09-14 2020-09-11 2020-10-26 2020-08-05 2020-11-18 2020-09-11 2020-12-23 efficiency norms of the former Enhancement of Public Urban Envelope 21 Kindergarten #17 and Spaces Administrative building at the Chartak city MSC/UZB-C/W/1.6.2 / Restoration/strengthening and adaptive reuse in Component 1: Improvement accordance to modern energy of Urban Services and Single Stage - One 2021-06- IBRD / 89140 Post Request for Bids Open - National 500,553.00 459,525.50 Signed 2020-09-11 2020-07-04 2020-09-16 2020-10-28 2020-08-05 2020-11-27 2020-08-28 2021-01-01 2020-10-05 efficiency norms of the former Enhancement of Public Urban Envelope 30 Kindergarten #17 and Spaces Administrative building at the Chartak city. MSC-CKY/W/2.1 / Component 2: Institutional Construction / Repair of Single Stage - One 2021-08- IBRD / 89140 Strengthening and Capacity Post Request for Bids Open - National 340,000.00 0.00 Canceled 2020-10-23 2020-11-24 2020-11-02 2020-11-24 2020-12-14 2020-12-24 2021-01-13 2021-01-21 2021-02-17 Garage Premises for Municipal Envelope 16 Building Equipment in the Chartak city MSC-CKY/W/2.2 / Component 2: Institutional Construction / Repair of Single Stage - One 2021-08- IBRD / 89140 Strengthening and Capacity Post Request for Bids Open - National 300,000.00 0.00 Canceled 2020-10-23 2020-11-24 2020-10-28 2020-11-24 2020-12-09 2020-12-24 2021-01-08 2021-01-21 2021-02-12 Garage Premises for Municipal Envelope 11 Building Equipment in the Kagan city MSC-CKY/W/2.3 / Component 2: Institutional Construction / Repair of Single Stage - One 2021-08- IBRD / 89140 Strengthening and Capacity Post Request for Bids Open - National 330,000.00 0.00 Canceled 2020-10-23 2020-11-24 2020-10-28 2020-11-24 2020-12-09 2020-12-24 2021-01-08 2021-01-21 2021-02-12 Garage Premises for Municipal Envelope 11 Building Equipment in the Yangiyul city MSC-СKY/W/2.1.1 / Construction of garages for Component 2: Institutional Single Stage - One 2021-12- parking and maintenance of IBRD / 89140 Strengthening and Capacity Post Request for Bids Open - National 340,000.00 332,777.08 Signed 2021-02-11 2021-02-15 2021-02-21 2021-02-16 2021-04-04 2021-03-19 2021-05-04 2021-05-07 2021-06-08 2021-06-09 Envelope 05 special equipment in Chartak, Building Namangan region. MSC-СKY/W/2.2.1 / Construction of garages for Component 2: Institutional Single Stage - One 2021-12- parking and maintenance of IBRD / 89140 Strengthening and Capacity Post Request for Bids Open - National 300,000.00 300,299.26 Signed 2021-02-11 2021-02-15 2021-02-21 2021-02-16 2021-04-04 2021-03-19 2021-05-04 2021-05-07 2021-06-08 2021-06-14 Envelope 05 special equipment in Kagan, Building Bukhara region. MSC-СKY/W/2.3.1 / Construction of garages for Component 2: Institutional Single Stage - One 2021-12- parking and maintenance of IBRD / 89140 Strengthening and Capacity Post Request for Bids Open - National 330,000.00 0.00 Canceled 2021-02-11 2021-02-15 2021-02-21 2021-02-16 2021-04-04 2021-03-19 2021-05-04 2021-05-07 2021-06-08 Envelope 05 special equipment in Yangiyul, Building Tashkent region. MSC-C/W/1.4 / Component 1: Improvement Request for Bids - Reconstruction of the existing of Urban Services and Single Stage - One Small Works SPD 2022-09- building of the "Old Bazaar" IBRD / 89140 Post Request for Bids Open - National 746,158.55 646,384.20 Signed 2021-05-24 2021-05-27 2021-06-01 2021-05-31 2021-07-15 2021-06-30 2021-08-16 2021-07-22 2021-09-27 2021-08-17 Enhancement of Public Urban Envelope (1 envelope 30 located in Chartak city, Spaces process) Namangan region MSC-СKY/W/2.3.1.1 / Request for Bids - Construction of garages for Component 2: Institutional Single Stage - One Small Works SPD 2022-03- parking and maintenance of IBRD / 89140 Strengthening and Capacity Post Request for Bids Open - National 330,000.00 0.00 Canceled 2021-05-31 2021-05-31 2021-06-05 2021-05-31 2021-07-17 2021-06-30 2021-08-16 2021-09-20 Envelope (1 envelope 19 special equipment in Yangiyul, Building process) Tashkent region. MSC-СKY/W/2.3.1.1.1 / National Construction of garages for Component 2: Institutional Procurement Single Stage - One 2022-05- parking and maintenance of IBRD / 89140 Strengthening and Capacity Post Request for Bids Open - National Document - 1 330,000.00 293,069.96 Signed 2021-07-28 2021-07-29 2021-07-28 2021-07-29 2021-08-31 2021-08-31 2021-09-30 2021-09-22 2021-11-04 2021-10-26 Envelope 03 special equipment in Yangiyul, Building Envelope process Tashkent region. (Non Bank-SPD) MSC-Y/W/1.1 / Component 1: Improvement Request for Bids - Under Reconstruction of Nyozbash of Urban Services and Single Stage - One Small Works SPD 2022-09- IBRD / 89140 Prior Request for Bids Open - International 6,215,354.36 0.00 Implementat 2021-12-01 2021-12-05 2021-12-06 2021-12-13 2022-01-17 2022-01-27 2022-02-16 2022-03-23 WI and Water Main of the Enhancement of Public Urban Envelope (1 envelope 19 ion Yangiyul city Spaces process) Component 1: Improvement Request for Bids - MSC-K/W/1.1 / Under of Urban Services and Single Stage - One Small Works SPD 2022-09- Reconstruction of sewerage IBRD / 89140 Prior Request for Bids Open - International 7,612,634.43 0.00 Implementat 2021-12-01 2021-12-20 2021-12-06 2021-12-21 2022-01-17 2022-02-08 2022-02-16 2022-03-23 Enhancement of Public Urban Envelope (1 envelope 19 system of the Kagan city ion Spaces process) MSC-C/W/1.2.1 / Component 1: Improvement Request for Bids - Construction of bridges for Under of Urban Services and Single Stage - One Small Works SPD 2022-12- the construction of the Eco- IBRD / 89140 Post Request for Bids Open - National 441,338.53 0.00 Implementat 2022-02-01 2022-02-03 2022-02-16 2022-02-04 2022-04-02 2022-05-02 2022-06-16 Enhancement of Public Urban Envelope (1 envelope 13 trail in the city of Chartak, ion Spaces process) Namangan region Page 1 GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MSC/UZB-G-RFQ/2.1 / Strengthening the material Component 2: Institutional Request for Single Stage - One and technical base of the IBRD / 89140 Strengthening and Capacity Post Open - National 115,000.00 98,087.01 Completed 2020-02-12 2020-02-26 2020-02-27 2020-02-24 2020-04-30 2020-05-14 Quotations Envelope State Committee Tourism Building Development MSC/UZB-G/2.1 / Procurement of Special Component 2: Institutional Single Stage - One equipment for khokimiyats of IBRD / 89140 Strengthening and Capacity Prior Request for Bids Open - International 2,600,000.00 0.00 Canceled 2020-02-28 2020-02-27 2020-02-29 2020-03-05 2020-03-31 2020-05-14 2020-04-30 2020-09-15 2020-06-04 2020-12-01 Envelope Chartak, Kagan and Yangiyul Building cities MSC/UZB-G/2.1.1 / Procurement of Special Component 2: Institutional Single Stage - One equipment for khokimiyats of IBRD / 89140 Strengthening and Capacity Prior Request for Bids Open - International 3,330,000.00 3,087,093.00 Signed 2020-09-14 2020-09-16 2020-09-19 2020-09-17 2020-10-31 2020-01-03 2020-11-30 2021-03-04 2021-01-04 2021-03-31 2021-07-03 Envelope Chartak, Kagan and Yangiyul Building cities NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MSCIUDP-CS/QCBS-03-02 / Development of feasibility study,detailed designs and construction supervision, for Component 1: Improvement the upgrading and of Urban Services and Quality And Cost- improvements of three cities TF / A7556 Prior Open - International 1,235,000.00 1,028,000.00 Signed 2018-10-04 2018-10-08 2018-11-21 2019-03-28 2018-12-19 2019-01-18 2019-05-02 2019-02-22 2019-09-11 2019-03-29 2019-11-08 2020-03-28 Enhancement of Public Urban Based Selection of Uzbekistan. The first Lump- Spaces Sum contract to be financed by ECAPDEV Grant and Second and Third contracts by IBRD Loans. UDP-CS/CQS-5 / Consultant Component 1: Improvement Consultant Firm for Environmental and of Urban Services and TF / A7556 Post Qualification Open - International 25,000.00 0.00 Canceled 2019-01-23 2018-08-06 2019-02-13 2019-03-29 2019-04-28 2019-06-02 2019-11-29 Social Safeguards, including Enhancement of Public Urban Selection training and RPF Spaces Component 1: Improvement UDP-CS/CQS-6 / M&E Consultant of Urban Services and surveys (beneficiary TF / A7556 Post Qualification Open - International 19,000.00 0.00 Canceled 2019-01-23 2018-11-15 2019-02-13 2019-03-29 2019-04-28 2019-01-17 2019-06-02 2019-11-29 Enhancement of Public Urban satisfaction survey) Selection Spaces Component 1: Improvement Consultant UDP-CS/CQS-04 / Grant of Urban Services and TF / A7556 Post Qualification Open - International 6,000.00 0.00 Canceled 2019-01-30 2019-02-20 2019-04-05 2019-05-05 2019-06-09 2019-12-06 Audit Enhancement of Public Urban Selection Spaces UDP-CS/CQS-01 / Preparation of detailed Component 1: Improvement designs DDs and Bidding Consultant of Urban Services and Documents, and construction IBRD / 89140 Post Qualification Open - International 80,000.00 80,000.00 Signed 2019-03-06 2019-03-05 2019-03-08 2019-03-25 2019-03-20 2019-03-28 2019-04-05 2019-04-01 2019-04-09 2019-09-30 Enhancement of Public Urban supervision. For the Phase 1 - Selection Spaces US $ 30 000 Lump Sum, Phase 2 - US $ 50 000 Time Based. MSCIUDP-CS/QCBS-05-02 / Development of a National Component 2: Institutional Monitoring and Evaluation Quality And Cost- IBRD / 89140 Strengthening and Capacity Post Open - International 270,000.00 0.00 Canceled 2019-09-27 2019-10-18 2019-12-01 2019-12-29 2020-01-28 2020-03-03 2020-04-07 2021-04-07 (M&E) system for the Based Selection Building sustainable Tourism & Travel sector in Uzbekistan MSCIUDP-CS/QCBS-06-01 / Analysis and Assessment of Component 2: Institutional the Financing of Urban Quality And Cost- IBRD / 89140 Strengthening and Capacity Prior Open - International 1,000,000.00 0.00 Canceled 2019-09-27 2019-10-18 2019-12-01 2019-12-29 2020-01-28 2020-03-03 2020-04-07 2021-04-07 Development and Based Selection Building Intergovernmental Fiscal Relations in Uzbekistan MSCIUDP-CS/QCBS-05-01 / Development of new susainable tourism destinations, including Component 2: Institutional Quality And Cost- promotion, marketing & IBRD / 89140 Strengthening and Capacity Post Open - International 480,000.00 0.00 Canceled 2019-11-05 2019-11-26 2020-01-09 2020-02-06 2020-03-07 2020-04-11 2020-05-16 2021-05-16 Based Selection branding strategy and action Building plan, for (i) the Fergana Valley and (ii) Bukhara Region in Uzbekistan MSC-PA/3.1 / Consultant for Component 3: Least Cost IBRD / 89140 Post Open - International 70,000.00 29,500.00 Signed 2020-06-19 2020-06-24 2020-07-10 2020-07-29 2020-08-23 2020-12-21 2020-09-20 2021-01-22 2020-10-20 2021-04-14 2020-11-24 2021-05-05 2020-12-29 2021-05-10 2021-06-27 Audit Implementation Support Selection MSC-CKY/CS/1.1 / Preparation of Detailed Design Component 1: Improvement and Bidding Documents, and of Urban Services and Quality And Cost- IBRD / 89140 Prior Open - International 2,200,000.00 2,068,573.00 Signed 2020-06-26 2020-06-30 2020-07-17 2020-08-27 2020-08-30 2021-01-08 2020-09-27 2021-02-11 2020-10-27 2021-06-17 2020-12-01 2021-08-06 2021-01-05 2021-08-09 2022-01-05 Construction Supervision for Enhancement of Public Urban Based Selection integrated urban upgrading in Spaces the three pilot cities. MSC-MA/3.2 / Project Monitoring and Evaluation Component 3: Fixed Budget IBRD / 89140 Post Open - International 80,000.00 79,700.00 Signed 2020-06-29 2020-09-11 2020-07-20 2020-09-11 2020-09-02 2021-02-01 2020-09-30 2021-03-09 2020-10-30 2021-04-14 2020-12-04 2021-05-05 2021-01-08 2021-05-10 2022-01-08 Baseline Survey and Implementation Support Selection Beneficiary Satisfaction Page 2 MSC-CS/2.3 / Advisory Services to State Committee Component 2: Institutional Quality And Cost- on Tourism Development on IBRD / 89140 Strengthening and Capacity Prior Open - International 800,000.00 727,887.71 Signed 2020-06-29 2020-06-30 2020-07-20 2020-08-31 2020-09-02 2021-02-11 2020-09-30 2021-03-17 2020-10-30 2021-08-20 2020-12-04 2021-12-17 2021-01-08 2021-12-17 2022-01-08 Based Selection developing comprehensive Building strategy MSCIUDP-CS/QCBS-04-01 / Detailed Design, Bidding Documents, and Supervision Component 1: Improvement for Restoration and adaptive of Urban Services and Quality And Cost- reuse of (i) Emir's Palace; (ii) IBRD / 89140 Prior Open - International 1,300,000.00 1,128,000.00 Signed 2019-09-30 2020-08-17 2019-10-21 2020-08-31 2019-12-04 2021-05-27 2020-01-01 2021-08-08 2020-01-31 2021-08-30 2020-03-06 2021-12-17 2020-04-10 2021-12-17 2021-04-10 Enhancement of Public Urban Based Selection Italian Hotel; and (iii) Russian Spaces Consulate (Makhalla Committee Building) in Kagan (Bukhara region) MSC-CS/2.2 / Analysis and Assessment of the Financing Component 2: Institutional Quality And Cost- of Urban Development and IBRD / 89140 Strengthening and Capacity Prior Open - International 1,000,000.00 997,864.00 Signed 2020-12-01 2020-12-02 2020-12-01 2020-12-07 2021-01-19 2021-06-02 2021-02-16 2021-07-13 2021-03-18 2021-10-13 2021-04-22 2021-12-17 2021-05-27 2021-12-17 2022-05-27 Based Selection Intergovernmental Fiscal Building Relations in Uzbekistan MSC-CS/3.3.2 / Development of presentation materials Component 3: Least Cost Under (video 360 and augmented IBRD / 89140 Post Open - National 25,000.00 0.00 2021-10-08 2021-10-13 2021-11-15 2021-10-19 2021-12-29 2022-01-26 2022-02-25 2022-04-01 2022-05-06 2022-11-02 Implementation Support Selection Implementation reality) for Eco-trail and old bazaar in Chartak city MSC-CS/AF/1 / Consulting Component 1: Improvement Services for the Development of Urban Services and Quality And Cost- Pending IBRD / 89140 Post Open - International 485,150.00 0.00 2022-03-07 2022-03-28 2022-05-20 2022-06-17 2022-07-22 2022-09-04 2022-10-10 2023-10-10 of a Feasibility Study for an Enhancement of Public Urban Based Selection Implementation Additional Financing Project Spaces INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Improvement UDP-CS/SSS-01 / Feasibility of Urban Services and Studies and detailed designs TF / A7556 Prior Direct Selection Direct 30,000.00 0.00 Under Review 2019-01-23 2019-02-02 2019-04-08 2019-10-05 Enhancement of Public Urban for Year-1 Chartak Eco-trail Spaces MSCIUDP-CS/IND-02/1 / Individual Component 3: Project Implementation Unit TF / A7556 Prior Consultant Open 9,600.00 0.00 Canceled 2019-01-23 2019-03-13 2019-04-03 2019-05-08 2019-11-04 Implementation Support Manager Selection Individual MSCIUDP-CS/IND-02/4 / Component 3: TF / A7556 Post Consultant Open 5,600.00 0.00 Canceled 2019-01-23 2018-08-31 2019-03-13 2019-04-03 2019-05-08 2019-11-04 Sociologist Implementation Support Selection Individual MSCIUDP-CS/IND-02/5 / Component 3: TF / A7556 Post Consultant Open 5,200.00 0.00 Canceled 2019-01-23 2018-09-28 2019-03-13 2019-04-03 2019-05-08 2019-11-04 Ecologist Implementation Support Selection Individual MSCIUDP-CS/IND-02/6 / Component 3: TF / A7556 Post Consultant Open 5,200.00 0.00 Canceled 2019-01-23 2018-09-10 2019-03-13 2019-04-03 2019-05-08 2019-11-04 Engineer Implementation Support Selection MSCIUDP-CS/IND-02/3 / Individual Component 3: Financial management TF / A7556 Post Consultant Open 4,000.00 0.00 Canceled 2019-01-23 2019-03-13 2019-04-03 2019-05-08 2019-11-04 Implementation Support specialist Selection Individual MSCIUDP-CS/IND-02/2 / Component 3: TF / A7556 Post Consultant Open 8,800.00 0.00 Canceled 2019-03-06 2019-04-24 2019-05-15 2019-06-19 2019-12-16 Procurement specialist Implementation Support Selection MSC-C/CS/1.1 / Consulting services for the development Component 1: Improvement of detailed design, bidding of Urban Services and documents and construction IBRD / 89140 Post Direct Selection Direct 425,000.00 0.00 Canceled 2020-03-26 2020-02-03 2020-04-05 2020-02-28 2020-06-09 2021-04-01 Enhancement of Public Urban supervision of the Chartak Eco- Spaces Trail for non-motorized mobility in the city of Chartak MSC-CKY/CS/2.3.1.1 / Advisory Services to Ministry of Construction on Component 2: Institutional Individual modernization of Urban and IBRD / 89140 Strengthening and Capacity Post Consultant Open 132,000.00 0.00 Canceled 2020-06-29 2020-06-29 2020-08-17 2021-01-08 2020-09-07 2020-10-12 2021-04-10 Regional Planning Practices in Building Selection Uzbekistan (phase 1 - international) MSC-CKY/CS/2.3.1.2 / Advisory Services to Ministry Component 2: Institutional Individual of Construction on IBRD / 89140 Strengthening and Capacity Post Consultant Open 21,000.00 16,000.00 Signed 2020-06-29 2020-06-29 2020-08-17 2020-11-25 2020-09-07 2020-12-07 2020-10-12 2021-02-25 2021-04-10 modernization of Urban and Building Selection Regional Planning Practices in Uzbekistan (phase 1 - local) MSC-C/CS/1.1.1 / Consulting services for the development of detailed Component 1: Improvement design, bidding documents of Urban Services and IBRD / 89140 Post Direct Selection Direct 424,900.00 424,900.00 Signed 2020-08-05 2020-08-05 2020-08-05 2020-08-05 2020-08-05 2020-04-22 2021-10-05 and construction supervision Enhancement of Public Urban of the Chartak Eco-Trail for Spaces non-motorized mobility in the city of Chartak MSC-CKY/CS/2.1 / Consultant for Development of Detailed Designs and Bid documents, and Construction Component 2: Institutional Supervision for the IBRD / 89140 Strengthening and Capacity Post Direct Selection Direct 91,600.00 91,600.00 Signed 2020-03-26 2020-04-07 2020-04-05 2020-05-13 2020-06-09 2020-05-15 2020-12-06 Construction / Repair of Building Garage Premises in the cities of Chartak, Kagan and Yangiyul. Page 3 MSC-CKY/CS/2.3.1.1.1 / Advisory Services to Ministry of Construction on Component 2: Institutional Individual modernization of Urban and IBRD / 89140 Strengthening and Capacity Post Consultant Open 132,000.00 0.00 Canceled 2021-04-12 2021-04-14 2021-05-31 2021-06-21 2021-07-26 2022-01-22 Regional Planning Practices in Building Selection Uzbekistan (phase 1 - international) MSC-C/CS/1.2 / SERVICES ON COMPLETION OF DETAILED DESIGN, ESTIMATE, Component 1: Improvement BID DOCUMENTS AND of Urban Services and Pending IBRD / 89140 Post Direct Selection Direct 222,049.03 0.00 2021-09-25 2021-10-05 2021-12-09 2024-04-07 CONSTRUCTION SUPERVISON Enhancement of Public Urban Implementation FOR ECO-TRAIL Spaces CONSTRUCTION IN CHARTAK, NAMANGAN REGION MSC-CKY/CS/2.3.1.1.1.1 / Advisory Services to Ministry of Construction on Component 2: Institutional Individual modernization of Urban and IBRD / 89140 Strengthening and Capacity Post Consultant Open 132,000.00 0.00 Canceled 2021-09-24 2021-12-14 2021-11-12 2021-12-03 2022-01-07 2022-07-06 Regional Planning Practices in Building Selection Uzbekistan (phase 1 - international) MSC-CKY/CS/2.3.1.1.1.1.1 / Component 2: Institutional Individual Advisory Services to Ministry IBRD / 89140 Strengthening and Capacity Post Consultant Open 132,000.00 120,000.00 Signed 2021-12-21 2021-12-22 2021-12-22 2021-12-22 2021-12-22 2021-12-22 2021-12-22 2021-10-08 2022-08-19 of Construction, International Building Selection consultant (Phase 1) Page 4