PROCUREMENT PLAN Project information: Colombia Multipurpose Cadaster Project Region Project P162594 Project Implementation agency: 1. “DNP" means Departamento Nacional de Planeacion , the Borrower's National Planning Department created by Law 19 of 1958 and regulated by Decree 2996 of 1968. 2. "ANT" means Agencia Nacional de Tierras, the Borrower's National Land Agency, created by Law Decree 2363 of 2015 3. "SNR" means Superintendencia de Notariado y Registro, the Borrower's Superintendent of Notaries and Registries, created by Law Decree 3346 of 1959 and regulated by Decree 1298 of 1962. 4. "IGAC" means lnstituto Geografico Agustin Codazzi, the Geographic Institute Agustin Codazzi created by Law 14 of 1983 and regulated by Decree 283 8 of 1991. Date of the Procurement Plan: 02/07/2019 Period covered by this Procurement Plan: 02/07/2019 – 08/06/2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, revised November 2017) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the documents previously approved with the Bank will be used. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Is not applicable; Works: Is not applicable PROCUREMENT Colombia : Multipurpose Cadaster Project PLAN General Information Country: Colombia Bank’s Approval Date of the Original Procurement Plan: 2021-09-16 2022-01-18 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P162594 GPN Date: 2019-09-10 Project Name: Multipurpose Cadaster Project Loan / Credit No: TF / B4816 Action Fund Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual FA-ANT-206-GO-RFQ / Multipurpose Cadaster in Compra de Equipos de Environmental and Protected Solicitud de Single Stage - One Ejecución Computador para desarrollo TF / B4816 Posterior Open - National 12,916.67 0.00 2022-05-21 2022-07-29 2022-08-28 Areas to Strengthened cotizaciones Envelope pendiente de procesos del componente Sustainable Management ANT. FA-PNN-201-GO-RFB / Comprar equipos e insumos Multipurpose Cadaster in para la generacion de Environmental and Protected Solicitud de Single Stage - One Ejecución información, seguimiento y TF / B4816 Posterior Open - National 115,611.31 0.00 2022-01-11 2022-01-16 2022-02-27 2022-03-14 2022-04-03 2025-04-17 Areas to Strengthened ofertas Envelope pendiente monitoreo de los acuerdos a Sustainable Management implementar dentro de las áreas protegidas PNN. FA-PNN-204-GO-RFQ / Realizar señalización de los Multipurpose Cadaster in límites de los sectores Environmental and Protected Solicitud de Single Stage - One Ejecución TF / B4816 Posterior Open - National 24,774.27 0.00 2022-07-06 2022-08-21 2024-07-11 focalizados de las áreas Areas to Strengthened cotizaciones Envelope pendiente protegidas de Parques Sustainable Management Nacionales Naturales. FA-SNR-205-GO-RFQ / Multipurpose Cadaster in Equipos de cómputo, Environmental and Protected Solicitud de Single Stage - One Ejecución TF / B4816 Posterior Open - National 25,000.00 0.00 2023-02-06 2023-04-03 2023-06-02 impresoras y punto lógico Areas to Strengthened cotizaciones Envelope pendiente SNR Sustainable Management NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AF-SNR-253009-NC-RFQ / Multipurpose Cadaster in Intervención archivística de Environmental and Protected Solicitud de Single Stage - One TF / B4816 Posterior Open - National 70,050.20 77,656.29 Firmado 2021-09-17 2021-10-10 2021-11-04 2021-12-09 Antecedentes Registrales de la Areas to Strengthened cotizaciones Envelope ORIP San José del Guaviare. Sustainable Management AF-SNR-253236-NC-RFQ / Intervención archivística de Multipurpose Cadaster in Libros de Antiguo Sistema Environmental and Protected Solicitud de Single Stage - One TF / B4816 Posterior Open - National 84,650.67 96,262.30 Firmado 2021-09-17 2021-10-10 2021-11-08 2021-12-09 (LAS) y de Antecedentes Areas to Strengthened cotizaciones Envelope Registrales de la ORIP San Sustainable Management Vicente del Caguán. AF-IGAC-253679-NC-RFB / Establecer y poner en operación la red geodésica de Multipurpose Cadaster in municipios definidos para la Environmental and Protected Solicitud de Single Stage - One actualización de información TF / B4816 Previa Open - International 2,428,825.34 0.00 En ejecución 2021-10-01 2021-11-05 2021-10-06 2021-11-09 2021-11-20 2021-12-20 2022-01-13 2022-09-10 Areas to Strengthened ofertas Envelope geográfica oficial e Sustainable Management implementación del catastro multipropósito con áreas ambientalmente protegidas. AF-IGAC-253682-NC-RFB / Adquirir modelos digitales de terreno de la República de Multipurpose Cadaster in Colombia, como insumo para Environmental and Protected Solicitud de Single Stage - One la actualización de la TF / B4816 Posterior Open - National 1,720,515.00 0.00 En ejecución 2021-10-01 2021-11-05 2021-10-06 2021-12-03 2021-11-17 2021-12-17 2022-01-21 2022-05-21 Areas to Strengthened ofertas Envelope información geográfica oficial Sustainable Management e implementación del catastro multipropósito con áreas ambientalmente protegidas. AF-IGAC-258248-NC-RFB / Generar productos cartográficos de los Multipurpose Cadaster in municipios definidos para la Environmental and Protected Solicitud de Single Stage - One actualización de la TF / B4816 Previa Open - International 4,986,809.00 0.00 En ejecución 2021-11-05 2021-12-15 2021-11-10 2021-12-17 2021-12-22 2022-01-21 2022-02-25 2022-12-25 Areas to Strengthened ofertas Envelope información geográfica oficial Sustainable Management e implementación del catastro multipropósito con áreas ambientalmente protegidas. FA-IGAC-260245-NC-RFB / Adquisición de ortoimágenes de la República de Colombia, Multipurpose Cadaster in como insumo para la Environmental and Protected Solicitud de Single Stage - One actualización de la TF / B4816 Previa Open - International 4,569,852.68 0.00 En ejecución 2021-11-05 2022-01-12 2021-11-10 2022-01-14 2021-12-22 2022-01-21 2022-02-25 2022-06-24 Areas to Strengthened ofertas Envelope información geográfica oficial Sustainable Management e implementación del catastro multipropósito con áreas ambientalmente protegidas. Page 1 FA-PNN-202-NC-RFQ / Compra de fotografías aéreas Multipurpose Cadaster in e imágenes satelitales Environmental and Protected Solicitud de Single Stage - One Ejecución multiespectrales ópticas de TF / B4816 Posterior Open - National 79,513.05 0.00 2022-03-20 2022-05-02 2024-12-17 Areas to Strengthened cotizaciones Envelope pendiente resolución submétrica para el Sustainable Management monitoreo de acuerdos de conservación en PNN. FA-PNN-203-NC-RFQ / Realizar el levantamiento Multipurpose Cadaster in topográfico de los límites de Environmental and Protected Solicitud de Single Stage - One Ejecución TF / B4816 Posterior Open - National 24,774.27 0.00 2022-12-16 2023-02-20 2024-08-13 los sectores focalizados de las Areas to Strengthened cotizaciones Envelope pendiente áreas protegidas de Parques Sustainable Management Nacionales Naturales. FA-PNN-207-NC-RFQ / Realizar amojonamiento de Multipurpose Cadaster in los límites de los sectores Environmental and Protected Solicitud de Single Stage - One Ejecución TF / B4816 Posterior Open - National 49,548.55 0.00 2022-07-11 2022-09-15 2024-08-05 focalizados de las áreas Areas to Strengthened cotizaciones Envelope pendiente protegidas de Parques Sustainable Management Nacionales Naturales. FA-SNR-31-NC-RFB / Multipurpose Cadaster in Intervención archivística de Environmental and Protected Solicitud de Single Stage - One Ejecución TF / B4816 Posterior Open - National 1,631,463.24 0.00 2021-12-15 2021-12-20 2022-01-31 2022-03-02 2022-04-06 2022-10-06 antecedentes y libros de Areas to Strengthened ofertas Envelope pendiente antiguo sistema Sustainable Management FA-SNR-267-NC-RFB / Multipurpose Cadaster in Almacenamiento físico para la Environmental and Protected Solicitud de Single Stage - One Ejecución Intervención archivística de TF / B4816 Posterior Open - National 125,000.00 0.00 2021-12-15 2021-12-20 2022-01-31 2022-02-20 2022-03-27 2022-08-24 Areas to Strengthened ofertas Envelope pendiente antecedentes y libros de Sustainable Management antiguo sistema. - Bodega CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual FA-MADS-9-CS-QCBS / Diseñar e implementar una estrategia para fortalecer Multipurpose Cadaster in capacidades de las entidades Environmental and Protected Selección basada Ejecución del sector ambiente que TF / B4816 Posterior Open - National 277,777.78 0.00 2022-02-14 2022-03-07 2022-04-20 2022-05-18 2022-06-17 2022-07-22 2022-08-26 2024-08-26 Areas to Strengthened en calidad y costo pendiente garantice la calidad de los Sustainable Management datos geoespaciales y la integración del catastro multipropósito. FA-MADS-10-CS-QCBS / Diseñar e implementar una estrategia de comunicación y divulgación asociada a la Multipurpose Cadaster in gestión de la información Environmental and Protected Selección basada Ejecución TF / B4816 Posterior Open - National 208,333.33 0.00 2022-01-25 2022-02-15 2022-03-31 2022-04-28 2022-05-18 2022-06-15 2022-07-20 2024-07-22 catastral del sector ambiente Areas to Strengthened en calidad y costo pendiente a diferentes actores Sustainable Management directamente relacionadas con las áreas SINAP y público en general. FA-MADS-11-CS-QCBS / Generar capacidades, destrezas, habilidades y competencias del talento Multipurpose Cadaster in humano de las autoridades Environmental and Protected Selección basada Ejecución TF / B4816 Posterior Open - National 263,888.89 0.00 2022-01-25 2022-02-08 2022-02-23 2022-03-23 2022-04-07 2022-04-13 2022-05-07 2024-05-07 ambientales con competencia Areas to Strengthened en calidad y costo pendiente en los municipios priorizados Sustainable Management entorno a las tematicas relacionadas con la Política de Catastro Multipropósito. FA-MADS-12-CS-QCBS / Implementar la o las estrategia(s) seleccionada(s) Multipurpose Cadaster in por el sector ambiente, de Environmental and Protected Selección basada Ejecución TF / B4816 Posterior Open - International 470,555.56 0.00 2022-01-25 2022-02-08 2022-02-28 2022-03-28 2022-04-07 2022-04-27 2022-05-12 2024-12-31 acuerdo a los recursos Areas to Strengthened en calidad y costo pendiente disponibles para la Sustainable Management implementación de la Política de Catastro Multipróposito. FA-MADS-305-CS-QCBS / Multipurpose Cadaster in Definir el estado, requisitos, Environmental and Protected Selección basada Ejecución TF / B4816 Posterior Open - National 133,333.33 0.00 2022-03-01 2022-03-22 2022-05-05 2022-06-02 2022-07-02 2022-08-06 2022-09-10 2022-12-09 necesidades y arquitectura Areas to Strengthened en calidad y costo pendiente TIC de SIAC. Sustainable Management FA-MADS-25-CS-QCBS / Diseñar e implementar la estrategia para la actualización del SIAC, acorde Multipurpose Cadaster in con los requerimientos del Environmental and Protected Selección basada Ejecución sector ambiente, para la TF / B4816 Posterior Open - International 500,000.00 0.00 2022-05-01 2022-05-22 2022-07-05 2022-08-02 2022-09-01 2022-10-06 2022-11-10 2024-07-10 Areas to Strengthened en calidad y costo pendiente transformación digital, que Sustainable Management permita la integración de la información catastral y ambiental estratégica en el SIAC. FA-MADS-26-CS-QCBS / Diseñar e implementar la estrategia para la Multipurpose Cadaster in infraestructura en la nube del Environmental and Protected Selección basada Ejecución TF / B4816 Posterior Open - National 194,444.44 0.00 2022-05-01 2022-05-22 2022-07-05 2022-08-02 2022-09-01 2022-10-06 2022-11-10 2023-11-10 SIAC, como soporte a las Areas to Strengthened en calidad y costo pendiente solución tecnológica de Sustainable Management integración de información propuesta. FA-MADS-307-CS-QCBS / Desarrollo de la arquitectura de seguimiento, monitoreo y Multipurpose Cadaster in agregación de información del Environmental and Protected Selección basada Ejecución SIAC, como soporte a las TF / B4816 Posterior Open - National 194,444.44 0.00 2022-02-21 2022-03-14 2022-04-27 2022-05-25 2022-06-24 2022-07-29 2022-09-02 2023-09-02 Areas to Strengthened en calidad y costo pendiente solución tecnológica de Sustainable Management integración de información propuesta y fase inicial del certificador del SIAC. Page 2 FA-MADS-308-CS-QCBS / Multipurpose Cadaster in Desarrollo e implementación Environmental and Protected Selección basada Ejecución disposición de información TF / B4816 Posterior Open - National 111,111.11 0.00 2022-02-01 2022-02-22 2022-03-28 2022-04-25 2022-05-25 2022-06-29 2022-08-11 2022-12-12 Areas to Strengthened en calidad y costo pendiente digital a través de Sustainable Management ImageServer + Apollo. FA-MADS-28-CS-QCBS / Contribuir y generar capacidad técnica a las Multipurpose Cadaster in Autoridades Ambientales Environmental and Protected Selección basada Ejecución TF / B4816 Posterior Open - National 333,333.33 0.00 2022-03-31 2022-04-21 2022-06-04 2022-07-02 2022-08-01 2022-09-05 2022-10-05 2024-09-24 Regionales que presentan Areas to Strengthened en calidad y costo pendiente rezagos en cuanto a su Sustainable Management manejo de información ambiental estratégica, predial y de catastro multipropósito. FA-MADS-30-CS-QCBS / Fortalecer gobiernos subnacionales y otras ambientales en el uso y Multipurpose Cadaster in apropiación de la arquitectura Environmental and Protected Selección basada Ejecución empresarial sectorial para la TF / B4816 Posterior Open - National 333,333.33 0.00 2022-01-25 2022-02-15 2022-03-07 2022-04-04 2022-04-19 2022-05-18 2022-06-11 2024-06-11 Areas to Strengthened en calidad y costo pendiente gestión de información Sustainable Management catastral y ambiental relacionada con la actualización catastral y la administración de tierras. FA-MADS-29-CS-QCBS / Diseñar e implementar soluciones tecnológicas Multipurpose Cadaster in interoperables para la gestión, Environmental and Protected Selección basada Ejecución disposición e integración de TF / B4816 Posterior Open - International 777,777.78 0.00 2022-05-02 2022-05-23 2022-07-06 2022-08-03 2022-09-02 2022-10-07 2022-11-11 2024-10-31 Areas to Strengthened en calidad y costo pendiente información estratégica Sustainable Management ambiental de gobiernos subnacionales u otras entidades ambientales. FA-PNN-149-CS-QCBS / Implementador de los Multipurpose Cadaster in acuerdos de conservación con Environmental and Protected Selección basada Ejecución TF / B4816 Posterior Open - International 777,777.78 0.00 2022-02-01 2022-02-22 2022-03-18 2022-04-15 2022-04-30 2022-05-16 2022-06-20 2024-09-07 las comunidades campesinas Areas to Strengthened en calidad y costo pendiente vulnerables que habiten en los Sustainable Management parques nacionales naturales. INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AF-SNR-253239-CS-INDV / Apoyar al Fondo Acción y a la SNR en la supervisión de los Multipurpose Cadaster in contratos de intervención Environmental and Protected archivística de LAS y TF / B4816 Posterior Individual Open 3,605.83 3,272.90 Firmado 2021-09-15 2021-09-02 2021-09-30 2021-09-09 2021-10-03 2021-11-04 2021-10-11 2021-11-04 2022-01-09 Areas to Strengthened Antecedentes Registrales en Sustainable Management las ORIP de San Vicente del Caguán y San José del Guaviare. (Rol Archivista) AF-SNR-253240-CS-INDV / Apoyar al Fondo Acción y a la SNR en la supervisión del Multipurpose Cadaster in contrato de intervención de Environmental and Protected TF / B4816 Posterior Individual Open 3,605.83 3,300.94 Firmado 2021-09-15 2021-09-02 2021-09-30 2021-09-09 2021-10-03 2021-11-04 2021-10-11 2021-11-04 2022-01-09 LAS y Antecedentes Areas to Strengthened Registrales en las ORIP de San Sustainable Management Vicente del Caguán y San José del Guaviare. (Rol Ingeniero) AF-SNR-253237-CS-INDV / Apoyar al Fondo Acción y a la SNR en la supervisión de los contratos de intervención Multipurpose Cadaster in archivística de LAS y Environmental and Protected TF / B4816 Posterior Individual Open 2,403.89 2,200.63 Firmado 2021-09-15 2021-09-02 2021-09-30 2021-09-09 2021-10-03 2021-11-04 2021-10-11 2021-11-04 2021-12-10 Antecedentes Registrales en Areas to Strengthened las ORIP de registro de San Sustainable Management Vicente del Caguán y San José del Guaviare.(Rol Bacteriólogo y/o Microbiólogo) AF-SNR-253238-CS-INDV / Apoyar al Fondo Acción (FA) y a la SNR en la supervisión de los contratos para la Multipurpose Cadaster in intervención archivística de Environmental and Protected LAS y Antecedentes TF / B4816 Posterior Individual Open 8,353.33 7,647.00 Firmado 2021-09-15 2021-09-02 2021-09-30 2021-09-09 2021-10-03 2021-11-16 2021-10-11 2021-11-16 2022-01-09 Areas to Strengthened Registrales en las ORIP de Sustainable Management registro de San Vicente del Caguán y San José del Guaviare. (Rol Técnicos - 4 Contratos) AF-IGAC-253242-CS-INDV / Apoyar al IGAC, en el análisis, elaboración y consolidación de la caracterización territorial Multipurpose Cadaster in para los municipios Environmental and Protected TF / B4816 Posterior Individual Open 97,603.00 66,829.20 Firmado 2021-09-20 2021-09-07 2021-10-15 2021-09-10 2021-10-20 2021-11-05 2021-10-30 2021-11-08 2022-06-27 priorizados en el marco de la Areas to Strengthened implementación del catastro Sustainable Management multipropósito con áreas ambientalmente protegidas. (5 Consultores) AF-IGAC-253249-CS-CDS / Prestar los servicios de consultoría al IGAC para implementar la ruta de Multipurpose Cadaster in consulta previa para la Environmental and Protected Selección directa TF / B4816 Posterior Direct 342,967.78 0.00 En ejecución 2021-09-24 2021-09-29 2021-10-25 2021-11-23 2022-07-23 expedición de decretos y/o Areas to Strengthened de consultores instrumentos normativos Sustainable Management especiales sobre Catastro Multipropósito para pueblos indígenas. - Wayuu Page 3 AF-IGAC-253248-CS-CDS / Prestar los servicios de consultoría al IGAC para implementar la ruta de Multipurpose Cadaster in consulta previa para la Environmental and Protected Selección directa TF / B4816 Posterior Direct 230,337.06 0.00 En ejecución 2021-09-24 2021-09-29 2021-10-25 2021-09-30 2021-11-23 2022-07-23 expedición de decretos y/o Areas to Strengthened de consultores instrumentos normativos Sustainable Management especiales sobre Catastro Multipropósito para pueblos indígenas. - AICO AF-IGAC-253246-CS-CDS / Prestar los servicios de consultoría al IGAC para implementar la ruta de Multipurpose Cadaster in consulta previa para la Environmental and Protected Selección directa TF / B4816 Posterior Direct 91,900.46 0.00 En ejecución 2021-09-24 2021-09-29 2021-10-25 2021-11-23 2022-07-23 expedición de decretos y/o Areas to Strengthened de consultores instrumentos normativos Sustainable Management especiales sobre Catastro Multipropósito para pueblos indígenas. - CRIC AF-IGAC-253243-CS-CDS / Prestar los servicios de consultoría al IGAC para implementar la ruta de Multipurpose Cadaster in consulta previa para la Environmental and Protected Selección directa TF / B4816 Posterior Direct 382,897.97 0.00 En ejecución 2021-09-24 2021-09-29 2021-10-25 2021-11-23 2022-07-23 expedición de decretos y/o Areas to Strengthened de consultores instrumentos normativos Sustainable Management especiales sobre Catastro Multipropósito para pueblos indígenas. - Gobierno Mayor AF-IGAC-253247-CS-CDS / Prestar los servicios de consultoría al IGAC para implementar la ruta de Multipurpose Cadaster in consulta previa para la Environmental and Protected Selección directa TF / B4816 Posterior Direct 387,795.91 0.00 En ejecución 2021-09-24 2021-09-29 2021-10-25 2021-11-23 2022-07-23 expedición de decretos y/o Areas to Strengthened de consultores instrumentos normativos Sustainable Management especiales sobre Catastro Multipropósito para pueblos indígenas. - OPIAC AF-IGAC-253250-CS-CDS / Prestar los servicios de consultoría al IGAC para implementar la ruta de Multipurpose Cadaster in consulta previa para la Environmental and Protected Selección directa TF / B4816 Posterior Direct 117,263.44 0.00 En ejecución 2021-09-24 2021-09-29 2021-11-01 2021-11-23 2022-07-23 expedición de decretos y/o Areas to Strengthened de consultores instrumentos normativos Sustainable Management especiales sobre Catastro Multipropósito para pueblos indígenas. - Yukpa AF-IGAC-253244-CS-CDS / Prestar los servicios de consultoría al IGAC para implementar la ruta de Multipurpose Cadaster in consulta previa para la Environmental and Protected Selección directa TF / B4816 Posterior Direct 128,989.79 0.00 En ejecución 2021-09-30 2021-09-29 2021-10-25 2021-11-23 2022-07-23 expedición de decretos y/o Areas to Strengthened de consultores instrumentos normativos Sustainable Management especiales sobre Catastro Multipropósito para pueblos indígenas. - CIT AF-IGAC-253913-CS-CDS / Prestar los servicios de consultoría al IGAC para implementar la ruta de Multipurpose Cadaster in consulta previa para la Environmental and Protected Selección directa TF / B4816 Previa Direct 1,046,986.64 0.00 En ejecución 2021-09-30 2021-09-29 2021-10-25 2021-10-01 2021-11-23 2022-07-23 expedición de decretos y/o Areas to Strengthened de consultores instrumentos normativos Sustainable Management especiales sobre Catastro Multipropósito para pueblos indígenas. - ONIC FA-230451-CS-INDV / Multipurpose Cadaster in Gerente. Coordinar la unidad Environmental and Protected de Unidad de Gestión de TF / B4816 Posterior Individual Limited 204,832.00 47,081.69 Firmado 2021-04-21 2021-04-29 2021-04-26 2021-05-03 2021-05-03 2021-06-08 2021-05-31 2021-06-08 2022-05-31 Areas to Strengthened Fondo Acción para el Sustainable Management componente 5 FA-230455-CS-INDV / Especialista Financiero de la Multipurpose Cadaster in Unidad de Gestión de Fondo Environmental and Protected Acción para el componente 5. TF / B4816 Posterior Individual Limited 173,464.00 39,871.77 Firmado 2021-04-21 2021-04-29 2021-04-26 2021-05-04 2021-05-03 2021-07-14 2021-05-31 2021-07-14 2022-05-31 Areas to Strengthened Liderar los procesos Sustainable Management administrativos, financieros y contables del proyecto. FA-230457-CS-INDV / Especialista Planeación, Monitoreo y Seguimiento de la Multipurpose Cadaster in Unidad de Gestión de Fondo Environmental and Protected TF / B4816 Posterior Individual Limited 167,342.00 38,464.53 Firmado 2021-04-21 2021-04-29 2021-04-26 2021-05-03 2021-05-03 2021-07-01 2021-05-31 2021-07-01 2022-05-31 Acción del componente 5. Areas to Strengthened Liderar el proceso de Sustainable Management planeación, monitoreo y seguimiento del proyecto. FA-230430-CS-INDV / Especialista Adquisiciones del Fondo Acción Liderar las adquisiciones del componente Multipurpose Cadaster in 5 del proyecto por medio del Environmental and Protected TF / B4816 Posterior Individual Direct 204,832.00 41,571.94 Firmado 2021-04-29 2021-05-03 2021-05-04 2021-05-04 2021-05-08 2021-05-05 2021-05-19 2021-05-05 2022-05-19 cual se financia parcialmente Areas to Strengthened el Programa para la Adopción Sustainable Management e Implementación de un Catastro Multipropósito Rural- Urbano FA-PNN-244818-CS-INDV / Prestar Servicios profesionales para realizar la Multipurpose Cadaster in conceptualización y desarrollo Environmental and Protected TF / B4816 Posterior Individual Limited 8,240.00 7,351.63 Firmado 2021-07-30 2021-08-03 2021-08-09 2021-08-05 2021-08-19 2021-09-20 2021-08-29 2021-09-20 2022-02-25 de la estrategia de Areas to Strengthened información, educación y Sustainable Management comunicación de acuerdos de PNN. Page 4 FA-MADS-246851-CS-INDV / Liderar el diagnóstico, planeación, ejecución, seguimiento y evaluación Multipurpose Cadaster in técnica de todas las Environmental and Protected actividades del Componente 5 TF / B4816 Posterior Individual Limited 33,333.00 30,037.20 Firmado 2021-08-18 2021-08-17 2021-08-28 2021-08-31 2021-09-07 2021-11-04 2021-09-22 2021-11-04 2022-09-22 Areas to Strengthened del Proyecto, conforme a los Sustainable Management lineamientos y políticas establecidas por el Sector Ambiente y Desarrollo Sostenible. FA-MADS-246850-CS-INDV / Realizar el monitoreo, seguimiento y gestión administrativa de la matriz de Multipurpose Cadaster in resultados del Componente 5 Environmental and Protected TF / B4816 Posterior Individual Limited 20,000.00 18,022.32 Firmado 2021-08-18 2021-08-17 2021-08-28 2021-08-27 2021-09-07 2021-11-04 2021-09-22 2021-11-04 2022-09-22 y de la estrategia integral para Areas to Strengthened el fortalecimiento del Sector Sustainable Management Ambiente a ser implementada en el marco de la Política de Catastro Multipropósito. FA-MADS-246852-CS-INDV / Realizar el diagnóstico, la planificación, seguimiento y evaluación financiera de las Multipurpose Cadaster in actividades de la estrategia Environmental and Protected TF / B4816 Posterior Individual Limited 26,667.00 24,202.56 Firmado 2021-08-18 2021-08-17 2021-08-28 2021-08-27 2021-09-07 2021-11-04 2021-09-22 2021-11-04 2022-09-22 integral para fortalecer el Areas to Strengthened Sector Ambiente y Desarrollo Sustainable Management Sostenible y liderar el monitoreo y seguimiento y monitoreo a la ejecución. FA-MADS-246853-CS-INDV / Liderar el equipo técnico del Ministerio de Ambiente y Desarrollo Sostenible y Multipurpose Cadaster in realizar la coordinación, Environmental and Protected planeación, ejecución, TF / B4816 Posterior Individual Limited 40,000.00 36,576.00 Firmado 2021-08-18 2021-08-17 2021-08-28 2021-08-31 2021-09-07 2021-11-04 2021-09-22 2021-11-04 2022-09-22 Areas to Strengthened seguimiento y evaluación Sustainable Management técnica, financiera y operativa de todas las metas y actividades del Componente 5. FA-MADS-246854-CS-INDV / Liderar el diagnóstico, planeación, ejecución, seguimiento y evaluación Multipurpose Cadaster in técnica de todas las Environmental and Protected TF / B4816 Posterior Individual Limited 33,333.00 30,480.00 Firmado 2021-08-18 2021-08-17 2021-08-28 2021-08-27 2021-09-07 2021-11-05 2021-09-22 2021-11-05 2022-09-22 actividades del Componente 5 Areas to Strengthened relacionadas con la gestión y Sustainable Management uso de los datos, servicios y recursos de la información catastral. FA-MADS-246855-CS-INDV / Liderar el diagnóstico, planeación, ejecución, seguimiento y evaluación Multipurpose Cadaster in técnica de todas las Environmental and Protected actividades del Componente 5 TF / B4816 Posterior Individual Limited 33,333.00 30,480.00 Firmado 2021-08-18 2021-08-17 2021-08-28 2021-08-27 2021-09-07 2021-11-04 2021-09-22 2021-11-04 2022-09-22 Areas to Strengthened para el fortalecimiento Sustainable Management institucional del Sector Ambiente y Desarrollo Sostenible, en lo referente al desarrollo de TIC. FA-PNN-244814-CS-INDV / Multipurpose Cadaster in Prestar Servicios Profesionales Environmental and Protected para liderar el equipo técnico TF / B4816 Posterior Individual Limited 15,450.00 13,784.30 Firmado 2021-07-30 2021-08-03 2021-08-09 2021-08-05 2021-08-19 2021-09-16 2021-08-29 2021-09-16 2022-02-25 Areas to Strengthened de Subcomponente 5.3 del Sustainable Management Proyecto a cargo de PNN. FA-PNN-244820-CS-INDV / Prestar Servicios Profesionales Multipurpose Cadaster in para orientar desde el ámbito Environmental and Protected jurídico el proceso de la TF / B4816 Posterior Individual Limited 12,017.00 10,721.13 Firmado 2021-07-30 2021-08-03 2021-08-09 2021-08-05 2021-08-19 2021-09-20 2021-08-29 2021-09-20 2022-02-25 Areas to Strengthened suscripción, implementación y Sustainable Management seguimiento de acuerdos de PNN. FA-PNN-244823-CS-INDV / Prestar Servicios Profesionales Multipurpose Cadaster in en SIG para realizar la Environmental and Protected revisión, estructuración y TF / B4816 Posterior Individual Limited 10,300.00 9,281.49 Firmado 2021-07-30 2021-08-03 2021-08-09 2021-08-05 2021-08-19 2021-09-20 2021-08-29 2021-09-20 2022-02-25 Areas to Strengthened análisis espaciales de Sustainable Management información contenida en las bases de datos geográficas de PNN. FA-PNN-244826-CS-INDV / Prestar Servicios Profesionales para administrar la Multipurpose Cadaster in información geográfica y Environmental and Protected alfanumérica producida en el TF / B4816 Posterior Individual Limited 10,300.00 10,828.41 Firmado 2021-07-30 2021-08-03 2021-08-09 2021-08-05 2021-08-19 2021-09-29 2021-08-29 2021-09-29 2022-02-25 Areas to Strengthened marco de las actividades Sustainable Management relacionadas con la suscripción y seguimiento de acuerdos de PNN. FA-PNN-244827-CS-INDV / Prestar Servicios Profesionales para orientar el proceso de la suscripción, implementación y Multipurpose Cadaster in seguimiento de acuerdos, con Environmental and Protected TF / B4816 Posterior Individual Limited 12,017.00 10,828.41 Firmado 2021-07-30 2021-08-03 2021-08-09 2021-09-15 2021-08-19 2021-11-08 2021-08-29 2021-11-08 2022-02-25 énfasis en la aplicación de los Areas to Strengthened criterios socioeconómicos y Sustainable Management de diálogo social y en concordancia con los lineamientos de PNN. FA-ANT-128-CS-INDV / Coordinador de Componente 5 ANT: Realizar la Multipurpose Cadaster in coordinación de las Environmental and Protected Ejecución actividades derivadas del TF / B4816 Posterior Individual Open 24,220.00 0.00 2022-02-15 2022-03-31 2022-04-12 2022-05-04 2022-11-30 Areas to Strengthened pendiente proceso de asignación de Sustainable Management derechos de uso, a cargo de la Subdirección de Administración de Tierras de la Nación. Page 5 FA-ANT-129-CS-INDV / Líder Técnico ANT para el Componente 5: Realizar la coordinación de las Multipurpose Cadaster in actividades técnicas derivadas Environmental and Protected Ejecución TF / B4816 Posterior Individual Open 19,375.83 0.00 2022-02-15 2022-03-31 2022-04-12 2022-05-04 2022-11-30 del proceso de asignación de Areas to Strengthened pendiente derechos de uso, a cargo de la Sustainable Management Subdirección de Administración de Tierras de la Nación. FA-ANT-130-CS-INDV / Profesional Administrativo para el Componente 5: Apoyar el desarrollo de las Multipurpose Cadaster in actividades administrativas Environmental and Protected Ejecución derivadas del proceso de TF / B4816 Posterior Individual Open 11,100.83 0.00 2022-02-15 2022-03-31 2022-04-12 2022-05-04 2022-11-30 Areas to Strengthened pendiente asignación de derechos de Sustainable Management uso, a cargo de la Subdirección de Administración de Tierras de la Nación. FA-ANT-131-CS-INDV / Profesional Jurídico 1 ANT Componente 5: Apoyar las Multipurpose Cadaster in actividades jurídicas derivadas Environmental and Protected Ejecución del proceso de asignación de TF / B4816 Posterior Individual Open 8,333.33 0.00 2022-02-08 2022-03-24 2022-04-14 2022-05-19 2022-10-16 Areas to Strengthened pendiente derechos de uso, a cargo de la Sustainable Management Subdirección de Administración de Tierras de la Nación. FA-ANT-132-CS-INDV / Profesional Jurídico 2 ANT Componente 5: Apoyar las Multipurpose Cadaster in actividades jurídicas derivadas Environmental and Protected Ejecución del proceso de asignación de TF / B4816 Posterior Individual Open 8,333.33 0.00 2022-02-08 2022-03-24 2022-04-14 2022-05-19 2022-10-16 Areas to Strengthened pendiente derechos de uso, a cargo de la Sustainable Management Subdirección de Administración de Tierras de la Nación. FA-ANT-133-CS-INDV / Profesional Jurídico 3 ANT Componente 5: Apoyar las Multipurpose Cadaster in actividades jurídicas derivadas Environmental and Protected Ejecución del proceso de asignación de TF / B4816 Posterior Individual Open 8,333.33 0.00 2022-02-08 2022-03-24 2022-04-14 2022-05-19 2022-10-16 Areas to Strengthened pendiente derechos de uso, a cargo de la Sustainable Management Subdirección de Administración de Tierras de la Nación. FA-ANT-134-CS-INDV / Profesional Jurídico 4 ANT Componente 5: Apoyar las actividades jurídicas derivadas Multipurpose Cadaster in del proceso de asignación de Environmental and Protected Ejecución TF / B4816 Posterior Individual Open 8,333.33 0.00 2022-02-08 2022-03-24 2022-04-14 2022-05-19 2022-10-16 derechos de uso, a cargo de la Areas to Strengthened pendiente Subdirección de Sustainable Management Administración de Tierras de la Nación, para la ejecución del Componente 5. FA-ANT-135-CS-INDV / Profesional Jurídico 5 ANT Componente 5: Apoyar las Multipurpose Cadaster in actividades jurídicas derivadas Environmental and Protected Ejecución del proceso de asignación de TF / B4816 Posterior Individual Open 8,333.33 0.00 2022-02-08 2022-03-24 2022-04-14 2022-05-19 2022-10-16 Areas to Strengthened pendiente derechos de uso, a cargo de la Sustainable Management Subdirección de Administración de Tierras de la Nación. FA-ANT-136-CS-INDV / Profesional Jurídico 6 ANT Componente 5: Apoyar las Multipurpose Cadaster in actividades jurídicas derivadas Environmental and Protected Ejecución del proceso de asignación de TF / B4816 Posterior Individual Open 8,333.33 0.00 2022-02-08 2022-03-24 2022-04-14 2022-05-19 2022-10-16 Areas to Strengthened pendiente derechos de uso, a cargo de la Sustainable Management Subdirección de Administración de Tierras de la Nación. FA-ANT-137-CS-INDV / Profesional Jurídico 7 ANT Componente 5: Apoyar las Multipurpose Cadaster in actividades jurídicas derivadas Environmental and Protected Ejecución del proceso de asignación de TF / B4816 Posterior Individual Open 8,333.33 0.00 2022-02-08 2022-03-24 2022-04-14 2022-05-19 2022-10-16 Areas to Strengthened pendiente derechos de uso, a cargo de la Sustainable Management Subdirección de Administración de Tierras de la Nación. FA-ANT-138-CS-INDV / Profesional Jurídico 8 ANT Componente 5: Apoyar las Multipurpose Cadaster in actividades jurídicas derivadas Environmental and Protected Ejecución del proceso de asignación de TF / B4816 Posterior Individual Open 8,333.33 0.00 2022-02-08 2022-03-24 2022-04-14 2022-05-19 2022-10-16 Areas to Strengthened pendiente derechos de uso, a cargo de la Sustainable Management Subdirección de Administración de Tierras de la Nación. FA-ANT-139-CS-INDV / Profesional Jurídico 9 ANT Componente 5: Apoyar las Multipurpose Cadaster in actividades jurídicas derivadas Environmental and Protected Ejecución del proceso de asignación de TF / B4816 Posterior Individual Open 8,333.33 0.00 2022-02-08 2022-03-24 2022-04-14 2022-05-19 2022-10-16 Areas to Strengthened pendiente derechos de uso, a cargo de la Sustainable Management Subdirección de Administración de Tierras de la Nación. Page 6 FA-ANT-140-CS-INDV / Profesional de las Ciencias Agrarias 1 ANT para el Componente 5: Apoyar los Multipurpose Cadaster in procesos de caracterización Environmental and Protected Ejecución del uso que se deriven del TF / B4816 Posterior Individual Open 8,333.33 0.00 2022-02-08 2022-03-24 2022-04-14 2022-05-19 2022-10-16 Areas to Strengthened pendiente proceso de asignación de Sustainable Management derechos de uso, a cargo de la Subdirección de Administración de Tierras de la Nación. FA-ANT-141-CS-INDV / Profesional de las Ciencias Agrarias 2 ANT para el Componente 5: Apoyar los Multipurpose Cadaster in procesos de caracterización Environmental and Protected Ejecución del uso que se deriven del TF / B4816 Posterior Individual Open 8,333.33 0.00 2022-02-08 2022-03-24 2022-04-14 2022-05-19 2022-10-16 Areas to Strengthened pendiente proceso de asignación de Sustainable Management derechos de uso, a cargo de la Subdirección de Administración de Tierras de la Nación. FA-ANT-142-CS-INDV / Profesional de las Ciencias Agrarias 3 ANT para el Componente 5: Apoyar los Multipurpose Cadaster in procesos de caracterización Environmental and Protected Ejecución del uso que se deriven del TF / B4816 Posterior Individual Open 8,333.33 0.00 2022-02-08 2022-03-24 2022-04-14 2022-05-19 2022-10-16 Areas to Strengthened pendiente proceso de asignación de Sustainable Management derechos de uso, a cargo de la Subdirección de Administración de Tierras de la Nación. FA-ANT-143-CS-INDV / Profesional de las Ciencias Agrarias 4 ANT para el Componente 5: Apoyar los Multipurpose Cadaster in procesos de caracterización Environmental and Protected Ejecución del uso que se deriven del TF / B4816 Posterior Individual Open 8,333.33 0.00 2022-02-08 2022-03-24 2022-04-14 2022-05-19 2022-10-16 Areas to Strengthened pendiente proceso de asignación de Sustainable Management derechos de uso, a cargo de la Subdirección de Administración de Tierras de la Nación. FA-ANT-144-CS-INDV / Ingeniero Catastral 1 ANT Componente 5. Apoyar el análisis de la información Multipurpose Cadaster in catastral y topográfica Environmental and Protected Ejecución requerida en el marco del TF / B4816 Posterior Individual Open 8,333.33 0.00 2022-02-14 2022-03-30 2022-04-20 2022-05-25 2022-10-22 Areas to Strengthened pendiente proceso de asignación de Sustainable Management derechos de uso, a cargo de la Subdirección de Administración de Tierras de la Nación. FA-ANT-145-CS-INDV / Ingeniero Catastral 2 ANT Componente 5. Apoyar el análisis de la información Multipurpose Cadaster in catastral y topográfica Environmental and Protected Ejecución requerida en el marco del TF / B4816 Posterior Individual Open 8,333.33 0.00 2022-02-14 2022-03-30 2022-04-20 2022-05-25 2022-10-22 Areas to Strengthened pendiente proceso de asignación de Sustainable Management derechos de uso, a cargo de la Subdirección de Administración de Tierras de la Nación. FA-ANT-146-CS-INDV / Ingeniero Catastral 3 ANT Componente 5. Apoyar el análisis de la información Multipurpose Cadaster in catastral y topográfica Environmental and Protected Ejecución requerida en el marco del TF / B4816 Posterior Individual Open 8,333.33 0.00 2022-02-14 2022-03-30 2022-04-20 2022-05-25 2022-10-22 Areas to Strengthened pendiente proceso de asignación de Sustainable Management derechos de uso, a cargo de la Subdirección de Administración de Tierras de la Nación. FA-ANT-147-CS-INDV / Gestor Documental 1 ANT Comp. 5: Apoyar la creación de expedientes de cada Multipurpose Cadaster in proceso y archivar la Environmental and Protected Ejecución información física y digital TF / B4816 Posterior Individual Open 5,045.83 0.00 2022-02-14 2022-03-30 2022-04-20 2022-05-25 2022-10-22 Areas to Strengthened pendiente que se genere del proceso de Sustainable Management asignación de derechos de uso, a cargo de la Subd. de Administración de Tierras de la Nación. FA-ANT-148-CS-INDV / Gestor Documental 2 ANT Componente 5: Apoyar la creación de expedientes de Multipurpose Cadaster in cada proceso y archivar la Environmental and Protected Ejecución TF / B4816 Posterior Individual Open 5,045.83 0.00 2022-02-14 2022-03-30 2022-04-20 2022-05-25 2022-10-22 información física y digital del Areas to Strengthened pendiente proceso de asignación de Sustainable Management derechos de uso, a cargo de la Subd. de Administración de Tierras de la Nación. FA-IGAC-94-CS-INDV / Realizar los procesos de aseguramiento de la calidad en campo, requeridos en la Multipurpose Cadaster in revisión de los productos Environmental and Protected Ejecución TF / B4816 Posterior Individual Open 69,189.48 0.00 2022-02-20 2022-04-05 2022-04-26 2022-05-31 2022-12-27 generados por los operadores Areas to Strengthened pendiente catastrales contratados para Sustainable Management la implementación del CM con áreas ambientalmente protegidas. SAC1 Page 7 FA-IGAC-106-CS-INDV / Apoyar desde el componente jurídicos la supervisión de los contratos suscritos por el Multipurpose Cadaster in IGAC, con los operadores Environmental and Protected Ejecución TF / B4816 Posterior Individual Open 19,441.96 0.00 2022-01-20 2022-03-05 2022-03-26 2022-04-30 2023-01-25 catastrales para la Areas to Strengthened pendiente implementación del catastro Sustainable Management multipropósito con áreas ambientalmente protegidas. JUR FA-IGAC-107-CS-INDV / Apoyar desde el componente financiero la supervisión de los contratos suscritos por el Multipurpose Cadaster in IGAC, con los operadores Environmental and Protected Ejecución TF / B4816 Posterior Individual Open 19,441.96 0.00 2022-01-20 2022-03-05 2022-03-26 2022-04-30 2023-01-25 catastrales para la Areas to Strengthened pendiente implementación del catastro Sustainable Management multipropósito con áreas ambientalmente protegidas. FIN FA-IGAC-108-CS-INDV / Coordinar el componente de aseguramiento de la calidad en la revisión de los Multipurpose Cadaster in productos generados por los Environmental and Protected Ejecución TF / B4816 Posterior Individual Open 50,806.21 0.00 2022-02-20 2022-04-05 2022-04-26 2022-05-31 2023-02-25 operadores catastrales para la Areas to Strengthened pendiente implementación del catastro Sustainable Management multipropósito con áreas ambientalmente protegidas. CAC1 FA-IGAC-112-CS-INDV / Realizar los procesos de aseguramiento de la calidad del componente económico Multipurpose Cadaster in de los productos generados Environmental and Protected Ejecución por los operadores catastrales TF / B4816 Posterior Individual Open 30,243.05 0.00 2022-02-20 2022-04-05 2022-04-26 2022-05-31 2022-12-27 Areas to Strengthened pendiente contratados para la Sustainable Management implementación del catastro multipropósito con áreas ambientalmente protegidas. ECON1 FA-IGAC-115-CS-INDV / Realizar los procesos de aseguramiento de la calidad del componente social y Multipurpose Cadaster in documental de los productos Environmental and Protected Ejecución generados por los operadores TF / B4816 Posterior Individual Open 38,442.88 0.00 2022-01-20 2022-03-05 2022-03-26 2022-04-30 2023-01-25 Areas to Strengthened pendiente catastrales para la Sustainable Management implementación del catastro multipropósito con áreas ambientalmente protegidas. SOC1 FA-IGAC-118-CS-INDV / Realizar los procesos de aseguramiento de la calidad requeridos en la revisión de Multipurpose Cadaster in los productos generados por Environmental and Protected Ejecución los operadores catastrales TF / B4816 Posterior Individual Open 34,594.74 0.00 2022-02-20 2022-04-05 2022-04-26 2022-05-31 2022-12-27 Areas to Strengthened pendiente contratados para la Sustainable Management implementación del catastro multipropósito con áreas ambientalmente protegidas. ACO1 FA-IGAC-124-CS-INDV / Prestación de servicios profesionales para el seguimiento a la ejecución de Multipurpose Cadaster in los procesos de actualización Environmental and Protected Ejecución catastral de los municipios TF / B4816 Posterior Individual Open 94,089.73 0.00 2022-01-20 2022-03-05 2022-03-26 2022-04-30 2023-01-25 Areas to Strengthened pendiente priorizados para la Sustainable Management implementación del catastro multipropósito con áreas ambientalmente protegidas. SEJ1 FA-IGAC-252-CS-INDV / Prestación de servicios profesionales para apoyar el Multipurpose Cadaster in componente jurídico de los Environmental and Protected procesos precontractuales y TF / B4816 Posterior Individual Open 9,884.21 0.00 En ejecución 2021-12-15 2021-12-10 2022-01-13 2022-01-19 2022-02-01 2022-07-31 Areas to Strengthened contractuales en ejecución del Sustainable Management proyecto de catastro multipropósito en áreas ambientalmente protegidas. FA-IGAC-253-CS-INDV / Prestación de servicios profesionales para apoyar el Multipurpose Cadaster in componente financiero de los Environmental and Protected procesos precontractuales y TF / B4816 Posterior Individual Open 9,884.21 0.00 En ejecución 2021-12-15 2021-12-10 2022-01-13 2022-01-19 2022-02-01 2022-07-31 Areas to Strengthened contractuales en ejecución del Sustainable Management proyecto de catastro multipropósito en áreas ambientalmente protegidas. FA-IGAC-254-CS-INDV / Prestación de servicios profesionales para apoyar el componente técnico catastral Multipurpose Cadaster in de los procesos Environmental and Protected TF / B4816 Posterior Individual Open 9,884.21 0.00 En ejecución 2021-12-15 2021-12-10 2022-01-13 2022-01-19 2022-02-01 2022-07-31 precontractuales y Areas to Strengthened contractuales en ejecución del Sustainable Management proyecto de catastro multipropósito en áreas ambientalmente protegidas. FA-IGAC-255-CS-INDV / Prestación de servicios profesionales para apoyar el Multipurpose Cadaster in componente administrativo de Environmental and Protected los procesos precontractuales TF / B4816 Posterior Individual Open 16,092.37 0.00 En ejecución 2021-12-15 2021-12-10 2022-01-13 2022-01-19 2022-02-01 2022-07-31 Areas to Strengthened y contractuales en ejecución Sustainable Management del proyecto de catastro multipropósito en áreas ambientalmente protegidas. Page 8 FA-MADS-5-CS-INDV / Líder Social. Diagnosticar la estructura organizacional en el componente social, diseñar Multipurpose Cadaster in estrategias y definir el alcance Environmental and Protected Ejecución TF / B4816 Posterior Individual Open 95,871.58 0.00 2021-12-22 2022-01-19 2022-01-29 2022-03-01 2024-12-31 de la gestión de la Areas to Strengthened pendiente información ambiental y Sustainable Management catastral en zonas ambientales siguiendo lineamientos ICDE. FA-MADS-7-CS-INDV / Líder Jurídico. Diagnosticar la estructura organizacional en el componente jurídico, Multipurpose Cadaster in diseñar estrategias y definir el Environmental and Protected Ejecución TF / B4816 Posterior Individual Open 95,871.59 0.00 2021-12-22 2022-01-20 2022-02-04 2022-03-01 2024-12-31 alcance de la gestión de la Areas to Strengthened pendiente información ambiental y Sustainable Management catastral en zonas ambientales siguiendo lineamientos ICDE. FA-MADS-303-CS-INDV / Multipurpose Cadaster in Consultor. Planear y liderar el Environmental and Protected Ejecución TF / B4816 Posterior Individual Open 13,888.89 0.00 2022-01-11 2022-02-08 2022-02-18 2022-03-10 2022-08-10 esquema de gestión de Areas to Strengthened pendiente información del SIAC. Sustainable Management FA-MADS-304-CS-INDV / Multipurpose Cadaster in Consultor. Planear y liderar el Environmental and Protected Ejecución TF / B4816 Posterior Individual Open 19,444.44 0.00 2022-01-11 2022-02-09 2022-02-19 2022-03-02 2022-10-03 mapa de información del Areas to Strengthened pendiente sector. Sustainable Management FA-MADS-315-CS-INDV / Construir la infraestructura de datos espaciales (ICE) del Multipurpose Cadaster in sector ambiente para la Environmental and Protected Ejecución TF / B4816 Posterior Individual Open 166,666.67 0.00 2022-06-01 2022-07-20 2022-08-10 2022-09-14 2022-12-14 gestión de los datos, servicios Areas to Strengthened pendiente y recursos de información Sustainable Management catastral de las zonas ambientales estratégicas. FA-MADS-309-CS-INDV / Multipurpose Cadaster in Desarrollador 1. Apoyar en el Environmental and Protected Ejecución desarrollo del modelo de TF / B4816 Posterior Individual Open 30,000.00 0.00 2022-02-08 2022-03-29 2022-04-19 2022-05-24 2023-05-24 Areas to Strengthened pendiente trámites para Catastro Sustainable Management Multiproposito. FA-MADS-310-CS-INDV / Multipurpose Cadaster in Desarrollador 2. Apoyar en el Environmental and Protected Ejecución desarrollo del modelo de TF / B4816 Posterior Individual Open 30,000.00 0.00 2022-02-08 2022-03-29 2022-04-19 2022-05-24 2023-05-24 Areas to Strengthened pendiente trámites para Catastro Sustainable Management Multiproposito. FA-MADS-311-CS-INDV / Multipurpose Cadaster in Desarrollador 3. Apoyar en el Environmental and Protected Ejecución desarrollo del modelo de TF / B4816 Posterior Individual Open 30,000.00 0.00 2022-02-08 2022-03-29 2022-04-19 2022-05-24 2023-05-24 Areas to Strengthened pendiente trámites para Catastro Sustainable Management Multiproposito. FA-MADS-312-CS-INDV / Multipurpose Cadaster in Desarrollador 4. Apoyar en el Environmental and Protected Ejecución desarrollo del modelo de TF / B4816 Posterior Individual Open 30,000.00 0.00 2022-02-08 2022-03-29 2022-04-19 2022-05-24 2023-05-24 Areas to Strengthened pendiente trámites para Catastro Sustainable Management Multiproposito. FA-MADS-313-CS-INDV / Multipurpose Cadaster in Uso y apropiación y pruebas. Environmental and Protected Ejecución Apoyar en el desarrollo del TF / B4816 Posterior Individual Open 9,722.22 0.00 2022-02-08 2022-03-29 2022-04-19 2022-05-24 2023-05-24 Areas to Strengthened pendiente modelo de trámites para Sustainable Management Catastro Multiproposito. FA-PNN-154-CS-INDV / Consultor geográfico. Brindar el acompañamiento en el Multipurpose Cadaster in componente geográfico de la Environmental and Protected Ejecución temática de límites TF / B4816 Posterior Individual Open 52,851.14 0.00 2022-01-11 2022-02-10 2022-02-20 2022-03-12 2024-10-27 Areas to Strengthened pendiente señalización y amojonamiento Sustainable Management en áreas ambientales estratégicas ubicadas en zonas de alta deforestación. FA-PNN-156-CS-INDV / Consultor 10. Brindar el acompañamiento en el componente técnico Multipurpose Cadaster in relacionado con la producción Environmental and Protected Ejecución TF / B4816 Posterior Individual Open 9,909.59 0.00 2022-01-06 2022-01-26 2022-01-31 2022-02-15 2022-08-14 y disposición de información Areas to Strengthened pendiente con base en productos Sustainable Management cartográficos alternos para la suscripción de acuerdos en áreas ambientales. FA-PNN-157-CS-INDV / Consultor 11. Brindar el acompañamiento en el componente técnico Multipurpose Cadaster in relacionado con la producción Environmental and Protected Ejecución TF / B4816 Posterior Individual Open 9,909.59 0.00 2022-01-07 2022-01-27 2022-02-01 2022-02-15 2022-08-14 y disposición de información Areas to Strengthened pendiente con base en productos Sustainable Management cartográficos alternos para la suscripción de acuerdos en áreas ambientales. FA-PNN-299-CS-INDV / Profesional monitoreo y seguimiento. Brindar apoyo en el seguimiento, monitoreo y Multipurpose Cadaster in gestión administrativa Environmental and Protected Ejecución relacionada con la TF / B4816 Posterior Individual Open 56,154.33 0.00 2021-12-28 2022-01-17 2022-01-22 2022-02-01 2024-11-17 Areas to Strengthened pendiente producción, procesamiento y Sustainable Management disposición de información estandarizada para la suscripción de acuerdos en áreas ambientales. Page 9 FA-PNN-301-CS-INDV / Profesional control y aseguramiento calidad. Multipurpose Cadaster in Brindar apoyo en la evaluación Environmental and Protected Ejecución TF / B4816 Posterior Individual Open 16,904.32 0.00 2021-12-28 2022-01-17 2022-01-22 2022-02-01 2022-12-28 de la calidad de la Areas to Strengthened pendiente información generada en Sustainable Management áreas ambientales estratégicas ubicadas en zonas de alta deforestación. FA-PNN-158-CS-INDV / Líder Enlace Local 1. Coordinar y articular los componentes relacionados Multipurpose Cadaster in con la producción, Environmental and Protected Ejecución TF / B4816 Posterior Individual Open 64,088.89 0.00 2022-01-17 2022-02-16 2022-02-26 2022-03-16 2024-10-31 procesamiento y disposición Areas to Strengthened pendiente de información estandarizada Sustainable Management así como hacer el seguimiento a metas en el área protegida priorizada. FA-PNN-159-CS-INDV / Líder Enlace Local 2. Coordinar y articular los componentes relacionados Multipurpose Cadaster in con la producción, Environmental and Protected Ejecución TF / B4816 Posterior Individual Open 64,088.89 0.00 2022-01-17 2022-02-16 2022-02-26 2022-03-16 2024-10-31 procesamiento y disposición Areas to Strengthened pendiente de información estandarizada Sustainable Management así como hacer el seguimiento a metas en el área protegida priorizada. FA-PNN-160-CS-INDV / Líder Enlace Local 3. Coordinar y articular los componentes relacionados Multipurpose Cadaster in con la producción, Environmental and Protected Ejecución TF / B4816 Posterior Individual Open 64,088.89 0.00 2022-01-17 2022-02-10 2022-02-20 2022-03-16 2024-10-31 procesamiento y disposición Areas to Strengthened pendiente de información estandarizada Sustainable Management así como hacer el seguimiento a metas en el área protegida priorizada. FA-PNN-161-CS-INDV / Profesional UOT 1A. Realizar la caracterización socio Multipurpose Cadaster in económica y análisis de Environmental and Protected Ejecución conflictos así como la TF / B4816 Posterior Individual Open 31,146.82 0.00 2022-02-01 2022-03-03 2022-03-18 2022-04-14 2022-06-04 Areas to Strengthened pendiente propuesta del acuerdo con las Sustainable Management comunidades que habitan o hacen uso del área protegida priorizada. FA-PNN-162-CS-INDV / Profesional UOT 1B. Realizar la caracterización socio Multipurpose Cadaster in económica y análisis de Environmental and Protected Ejecución conflictos así como la TF / B4816 Posterior Individual Open 26,124.86 0.00 2022-02-01 2022-02-25 2022-03-07 2022-04-14 2023-09-06 Areas to Strengthened pendiente propuesta del acuerdo con las Sustainable Management comunidades que habitan o hacen uso del área protegida priorizada. FA-PNN-163-CS-INDV / Profesional UOT 2A. Realizar la caracterización socio Multipurpose Cadaster in económica y análisis de Environmental and Protected Ejecución conflictos así como la TF / B4816 Posterior Individual Open 31,146.82 0.00 2022-02-01 2022-03-03 2022-03-15 2022-04-14 2023-09-06 Areas to Strengthened pendiente propuesta del acuerdo con las Sustainable Management comunidades que habitan o hacen uso del área protegida priorizada. FA-PNN-164-CS-INDV / Profesional UOT 2B. Realizar la caracterización socio Multipurpose Cadaster in económica y análisis de Environmental and Protected Ejecución conflictos así como la TF / B4816 Posterior Individual Open 26,124.86 0.00 2022-02-01 2022-03-03 2022-03-18 2022-04-14 2023-09-06 Areas to Strengthened pendiente propuesta del acuerdo con las Sustainable Management comunidades que habitan o hacen uso del área protegida priorizada. FA-PNN-165-CS-INDV / Profesional UOT 3A. Realizar la caracterización socio Multipurpose Cadaster in económica y análisis de Environmental and Protected Ejecución conflictos así como la TF / B4816 Posterior Individual Open 31,146.82 0.00 2022-02-01 2022-02-25 2022-03-07 2022-04-14 2023-09-06 Areas to Strengthened pendiente propuesta del acuerdo con las Sustainable Management comunidades que habitan o hacen uso del área protegida priorizada. FA-PNN-166-CS-INDV / Profesional UOT 3B. Realizar la caracterización socio Multipurpose Cadaster in económica y análisis de Environmental and Protected Ejecución conflictos así como la TF / B4816 Posterior Individual Open 26,124.86 0.00 2022-02-01 2022-03-03 2022-03-16 2022-04-14 2023-09-06 Areas to Strengthened pendiente propuesta del acuerdo con las Sustainable Management comunidades que habitan o hacen uso del área protegida priorizada. FA-PNN-167-CS-INDV / Profesional Social 1A. Facilitar Multipurpose Cadaster in los procesos sociales en torno Environmental and Protected Ejecución a la suscripción de acuerdos TF / B4816 Posterior Individual Open 31,146.82 0.00 2022-02-01 2022-03-03 2022-03-18 2022-04-14 2023-09-06 Areas to Strengthened pendiente que promuevan el desarrollo Sustainable Management integral de las comunidades locales. FA-PNN-168-CS-INDV / Profesional Social 1B. Facilitar Multipurpose Cadaster in los procesos sociales en torno Environmental and Protected Ejecución a la suscripción de acuerdos TF / B4816 Posterior Individual Open 26,124.86 0.00 2022-02-01 2022-03-03 2022-03-15 2022-04-14 2023-09-06 Areas to Strengthened pendiente que promuevan el desarrollo Sustainable Management integral de las comunidades locales. Page 10 FA-PNN-169-CS-INDV / Profesional Social 2A. Facilitar Multipurpose Cadaster in los procesos sociales en torno Environmental and Protected Ejecución a la suscripción de acuerdos TF / B4816 Posterior Individual Open 31,146.82 0.00 2022-02-01 2022-03-03 2022-03-16 2022-04-14 2023-09-06 Areas to Strengthened pendiente que promuevan el desarrollo Sustainable Management integral de las comunidades locales. FA-PNN-170-CS-INDV / Profesional Social 2B. Facilitar Multipurpose Cadaster in los procesos sociales en torno Environmental and Protected Ejecución a la suscripción de acuerdos TF / B4816 Posterior Individual Open 26,124.86 0.00 2022-02-01 2022-03-03 2022-03-18 2022-04-14 2023-09-06 Areas to Strengthened pendiente que promuevan el desarrollo Sustainable Management integral de las comunidades locales. FA-PNN-171-CS-INDV / Profesional Social 3A. Facilitar Multipurpose Cadaster in los procesos sociales en torno Environmental and Protected Ejecución a la suscripción de acuerdos TF / B4816 Posterior Individual Open 31,146.82 0.00 2022-02-01 2022-03-02 2022-03-15 2022-04-14 2023-09-06 Areas to Strengthened pendiente que promuevan el desarrollo Sustainable Management integral de las comunidades locales. FA-PNN-172-CS-INDV / Profesional Social 3B. Facilitar Multipurpose Cadaster in los procesos sociales en torno Environmental and Protected Ejecución a la suscripción de acuerdos TF / B4816 Posterior Individual Open 26,124.86 0.00 2022-02-01 2022-03-03 2022-03-16 2022-04-14 2023-09-06 Areas to Strengthened pendiente que promuevan el desarrollo Sustainable Management integral de las comunidades locales. FA-PNN-174-CS-INDV / Ing forestal, agrónomo sistemas Multipurpose Cadaster in sostenibles. Garantizar que el Environmental and Protected Ejecución diseño e implementación de TF / B4816 Posterior Individual Open 22,030.56 0.00 2022-01-03 2022-01-23 2022-01-26 2022-02-01 2022-12-28 Areas to Strengthened pendiente los acuerdos de conservación Sustainable Management estén en el marco del desarrollo sostenible). FA-PNN-175-CS-INDV / Profesional restauración+Sistemas Sostenibles 1A. Realizar el Multipurpose Cadaster in acompañamiento para las Environmental and Protected Ejecución TF / B4816 Posterior Individual Open 53,132.81 0.00 2022-02-01 2022-03-02 2022-03-17 2022-04-14 2024-08-15 acciones de restauración y de Areas to Strengthened pendiente sistemas sostenibles en áreas Sustainable Management ambientales estratégicas ubicadas en zonas de alta deforestación. FA-PNN-176-CS-INDV / Profesional restauración+Sistemas Sostenibles 1B. Realizar el Multipurpose Cadaster in acompañamiento para las Environmental and Protected Ejecución TF / B4816 Posterior Individual Open 44,565.94 0.00 2022-02-01 2022-03-03 2022-03-19 2022-04-14 2024-08-31 acciones de restauración y de Areas to Strengthened pendiente sistemas sostenibles en áreas Sustainable Management ambientales estratégicas ubicadas en zonas de alta deforestación. FA-PNN-177-CS-INDV / Profesional restauración+Sistemas Sostenibles 2A. Realizar el Multipurpose Cadaster in acompañamiento para las Environmental and Protected Ejecución TF / B4816 Posterior Individual Open 53,132.81 0.00 2022-02-01 2022-03-03 2022-03-18 2022-04-14 2024-08-31 acciones de restauración y de Areas to Strengthened pendiente sistemas sostenibles en áreas Sustainable Management ambientales estratégicas ubicadas en zonas de alta deforestación. FA-PNN-178-CS-INDV / Profesional restauración+Sistemas Sostenibles 2B. Realizar el Multipurpose Cadaster in acompañamiento para las Environmental and Protected Ejecución TF / B4816 Posterior Individual Open 44,565.94 0.00 2022-02-01 2022-03-03 2022-03-14 2022-04-14 2024-08-31 acciones de restauración y de Areas to Strengthened pendiente sistemas sostenibles en áreas Sustainable Management ambientales estratégicas ubicadas en zonas de alta deforestación. FA-PNN-179-CS-INDV / Profesional restauración+Sistemas Sostenibles 3A. Realizar el Multipurpose Cadaster in acompañamiento para las Environmental and Protected Ejecución TF / B4816 Posterior Individual Open 53,132.81 0.00 2022-02-01 2022-03-03 2022-03-18 2022-04-14 2024-08-31 acciones de restauración y de Areas to Strengthened pendiente sistemas sostenibles en áreas Sustainable Management ambientales estratégicas ubicadas en zonas de alta deforestación. FA-PNN-180-CS-INDV / Profesional restauración+Sistemas Sostenibles 3B. Realizar el Multipurpose Cadaster in acompañamiento para las Environmental and Protected Ejecución TF / B4816 Posterior Individual Open 44,565.94 0.00 2022-02-01 2022-03-03 2022-03-18 2022-04-14 2024-08-31 acciones de restauración y de Areas to Strengthened pendiente sistemas sostenibles en áreas Sustainable Management ambientales estratégicas ubicadas en zonas de alta deforestación. FA-PNN-181-CS-INDV / SIG 1. Estructurar la información Multipurpose Cadaster in para la suscripción de Environmental and Protected Ejecución TF / B4816 Posterior Individual Open 44,565.94 0.00 2022-02-01 2022-03-03 2022-03-18 2022-04-14 2024-08-31 acuerdos en áreas Areas to Strengthened pendiente ambientales estratégicas Sustainable Management ubicadas en zonas de alta deforestación. FA-PNN-182-CS-INDV / SIG 2. Estructurar la información Multipurpose Cadaster in para la suscripción de Environmental and Protected Ejecución TF / B4816 Posterior Individual Open 44,565.94 0.00 2022-02-01 2022-03-03 2022-03-18 2022-04-14 2024-08-31 acuerdos en áreas Areas to Strengthened pendiente ambientales estratégicas Sustainable Management ubicadas en zonas de alta deforestación. Page 11 FA-PNN-183-CS-INDV / SIG 3. Estructurar la información Multipurpose Cadaster in para la suscripción de Environmental and Protected Ejecución TF / B4816 Posterior Individual Open 44,565.94 0.00 2022-02-01 2022-03-03 2022-03-18 2022-04-14 2024-08-31 acuerdos en áreas Areas to Strengthened pendiente ambientales estratégicas Sustainable Management ubicadas en zonas de alta deforestación. FA-PNN-184-CS-INDV / Técnico 1A. Apoyar Multipurpose Cadaster in técnicamente el levantamiento Environmental and Protected Ejecución TF / B4816 Posterior Individual Open 31,806.78 0.00 2022-02-01 2022-03-03 2022-03-18 2022-04-14 2024-08-31 de la información en campo Areas to Strengthened pendiente en el marco de los acuerdos Sustainable Management de conservación. FA-PNN-185-CS-INDV / Técnico 1B. Apoyar Multipurpose Cadaster in técnicamente el levantamiento Environmental and Protected Ejecución TF / B4816 Posterior Individual Open 31,806.78 0.00 2022-02-01 2022-03-03 2022-03-18 2022-04-14 2024-08-31 de la información en campo Areas to Strengthened pendiente en el marco de los acuerdos Sustainable Management de conservación. FA-PNN-186-CS-INDV / Técnico 2A. Apoyar Multipurpose Cadaster in técnicamente el levantamiento Environmental and Protected Ejecución TF / B4816 Posterior Individual Open 31,806.78 0.00 2022-02-01 2022-03-03 2022-03-18 2022-04-14 2024-08-31 de la información en campo Areas to Strengthened pendiente en el marco de los acuerdos Sustainable Management de conservación. FA-PNN-187-CS-INDV / Técnico 2B. Apoyar Multipurpose Cadaster in técnicamente el levantamiento Environmental and Protected Ejecución TF / B4816 Posterior Individual Open 31,806.78 0.00 2022-02-01 2022-03-02 2022-03-17 2022-04-14 2024-08-15 de la información en campo Areas to Strengthened pendiente en el marco de los acuerdos Sustainable Management de conservación. FA-PNN-188-CS-INDV / Técnico 3A. Apoyar Multipurpose Cadaster in técnicamente el levantamiento Environmental and Protected Ejecución TF / B4816 Posterior Individual Open 31,806.78 0.00 2022-02-01 2022-03-03 2022-03-18 2022-04-14 2024-08-31 de la información en campo Areas to Strengthened pendiente en el marco de los acuerdos Sustainable Management de conservación. FA-PNN-189-CS-INDV / Técnico 3B. Apoyar Multipurpose Cadaster in técnicamente el levantamiento Environmental and Protected Ejecución TF / B4816 Posterior Individual Open 31,806.78 0.00 2022-02-01 2022-03-03 2022-03-18 2022-04-14 2024-08-31 de la información en campo Areas to Strengthened pendiente en el marco de los acuerdos Sustainable Management de conservación. FA-PNN-190-CS-INDV / Experto Local 1A. Facilitar la comunicación en los procesos Multipurpose Cadaster in de concertación con las Environmental and Protected Ejecución TF / B4816 Posterior Individual Open 13,650.00 0.00 2022-02-01 2022-03-03 2022-03-18 2022-04-14 2024-08-31 comunidades locales que Areas to Strengthened pendiente habitan las áreas ambientales Sustainable Management estratégicas ubicadas en zonas de alta deforestación. FA-PNN-191-CS-INDV / Experto Local 1B. Facilitar la comunicación en los procesos Multipurpose Cadaster in de concertación con las Environmental and Protected Ejecución TF / B4816 Posterior Individual Open 13,650.00 0.00 2022-02-01 2022-03-03 2022-03-18 2022-04-14 2024-08-31 comunidades locales que Areas to Strengthened pendiente habitan las áreas ambientales Sustainable Management estratégicas ubicadas en zonas de alta deforestación. FA-PNN-192-CS-INDV / Experto Local 1C. Facilitar la comunicación en los procesos Multipurpose Cadaster in de concertación con las Environmental and Protected Ejecución TF / B4816 Posterior Individual Open 13,650.00 0.00 2022-02-01 2022-03-03 2022-03-18 2022-04-14 2024-08-31 comunidades locales que Areas to Strengthened pendiente habitan las áreas ambientales Sustainable Management estratégicas ubicadas en zonas de alta deforestación. FA-PNN-193-CS-INDV / Experto Local 2A. Facilitar la comunicación en los procesos Multipurpose Cadaster in de concertación con las Environmental and Protected Ejecución TF / B4816 Posterior Individual Open 13,650.00 0.00 2022-02-01 2022-03-03 2022-03-18 2022-04-14 2024-08-31 comunidades locales que Areas to Strengthened pendiente habitan las áreas ambientales Sustainable Management estratégicas ubicadas en zonas de alta deforestación. FA-PNN-194-CS-INDV / Experto Local 2B. Facilitar la comunicación en los procesos Multipurpose Cadaster in de concertación con las Environmental and Protected Ejecución TF / B4816 Posterior Individual Open 13,650.00 0.00 2022-02-01 2022-03-03 2022-03-18 2022-04-14 2024-08-31 comunidades locales que Areas to Strengthened pendiente habitan las áreas ambientales Sustainable Management estratégicas ubicadas en zonas de alta deforestación. FA-PNN-195-CS-INDV / Experto Local 2C. Facilitar la comunicación en los procesos Multipurpose Cadaster in de concertación con las Environmental and Protected Ejecución TF / B4816 Posterior Individual Open 13,650.00 0.00 2022-02-01 2022-03-03 2022-03-18 2022-04-14 2024-08-31 comunidades locales que Areas to Strengthened pendiente habitan las áreas ambientales Sustainable Management estratégicas ubicadas en zonas de alta deforestación. FA-PNN-196-CS-INDV / Experto Local 3A. Facilitar la comunicación en los procesos Multipurpose Cadaster in de concertación con las Environmental and Protected Ejecución TF / B4816 Posterior Individual Open 13,650.00 0.00 2022-02-01 2022-03-03 2022-03-18 2022-04-14 2024-08-31 comunidades locales que Areas to Strengthened pendiente habitan las áreas ambientales Sustainable Management estratégicas ubicadas en zonas de alta deforestación. Page 12 FA-PNN-197-CS-INDV / Experto Local 3B. Facilitar la comunicación en los procesos Multipurpose Cadaster in de concertación con las Environmental and Protected Ejecución TF / B4816 Posterior Individual Open 13,650.00 0.00 2022-02-01 2022-03-03 2022-03-18 2022-04-14 2024-08-31 comunidades locales que Areas to Strengthened pendiente habitan las áreas ambientales Sustainable Management estratégicas ubicadas en zonas de alta deforestación. FA-PNN-198-CS-INDV / Experto Local 3C. Facilitar la comunicación en los procesos Multipurpose Cadaster in de concertación con las Environmental and Protected Ejecución TF / B4816 Posterior Individual Open 13,650.00 0.00 2022-02-01 2022-03-03 2022-03-18 2022-04-14 2024-08-31 comunidades locales que Areas to Strengthened pendiente habitan las áreas ambientales Sustainable Management estratégicas ubicadas en zonas de alta deforestación. FA-PNN-272-CS-INDV / Consultor 12. Brindar el acompañamiento en el componente técnico Multipurpose Cadaster in relacionado con la producción Environmental and Protected Ejecución TF / B4816 Posterior Individual Open 9,909.59 0.00 2023-11-15 2023-12-15 2023-12-30 2024-01-26 2026-06-14 y disposición de información Areas to Strengthened pendiente con base en productos Sustainable Management cartográficos alternos para la suscripción de acuerdos en áreas ambientales. FA-PNN-316-CS-INDV / Consultor 13. Brindar el acompañamiento en el componente técnico Multipurpose Cadaster in relacionado con la producción Environmental and Protected Ejecución TF / B4816 Posterior Individual Open 9,909.59 0.00 2022-01-07 2022-01-30 2022-02-05 2022-02-15 2022-08-14 y disposición de información Areas to Strengthened pendiente con base en productos Sustainable Management cartográficos alternos para la suscripción de acuerdos en áreas ambientales. FA-SNR-32-CS-INDV / Multipurpose Cadaster in Profesional 1. Prestar Environmental and Protected Ejecución TF / B4816 Posterior Individual Open 12,000.00 0.00 2023-02-01 2023-03-22 2023-04-12 2023-05-17 2024-01-16 servicios de apoyo en el Areas to Strengthened pendiente proceso de calificación. Sustainable Management FA-SNR-33-CS-INDV / Multipurpose Cadaster in Profesional 2. Prestar Environmental and Protected Ejecución TF / B4816 Posterior Individual Open 12,000.00 0.00 2023-02-01 2023-03-22 2023-04-12 2023-05-17 2024-01-16 servicios de apoyo en el Areas to Strengthened pendiente proceso de calificación. Sustainable Management FA-SNR-34-CS-INDV / Multipurpose Cadaster in Profesional 3. Prestar Environmental and Protected Ejecución TF / B4816 Posterior Individual Open 12,000.00 0.00 2023-01-10 2023-02-28 2023-03-21 2023-04-25 2023-10-22 servicios de apoyo en el Areas to Strengthened pendiente proceso de calificación. Sustainable Management FA-SNR-35-CS-INDV / Multipurpose Cadaster in Profesional 4. Prestar Environmental and Protected Ejecución TF / B4816 Posterior Individual Open 12,000.00 0.00 2023-02-01 2023-03-22 2023-04-12 2023-05-17 2024-01-16 servicios de apoyo en el Areas to Strengthened pendiente proceso de calificación. Sustainable Management FA-SNR-36-CS-INDV / Multipurpose Cadaster in Profesional 5. Prestar Environmental and Protected Ejecución TF / B4816 Posterior Individual Open 12,000.00 0.00 2023-02-01 2023-03-22 2023-04-12 2023-05-17 2024-01-16 servicios de apoyo en el Areas to Strengthened pendiente proceso de calificación. Sustainable Management FA-SNR-37-CS-INDV / Multipurpose Cadaster in Profesional 6. Prestar Environmental and Protected Ejecución TF / B4816 Posterior Individual Open 12,000.00 0.00 2023-02-01 2023-03-22 2023-04-12 2023-05-17 2024-01-16 servicios de apoyo en el Areas to Strengthened pendiente proceso de calificación. Sustainable Management FA-SNR-38-CS-INDV / Multipurpose Cadaster in Profesional 7. Prestar Environmental and Protected Ejecución TF / B4816 Posterior Individual Open 12,000.00 0.00 2023-02-01 2023-03-22 2023-04-12 2023-05-17 2024-01-16 servicios de apoyo en el Areas to Strengthened pendiente proceso de calificación. Sustainable Management FA-SNR-39-CS-INDV / Multipurpose Cadaster in Profesional 8. Prestar Environmental and Protected Ejecución TF / B4816 Posterior Individual Open 12,000.00 0.00 2023-02-01 2023-03-22 2023-04-12 2023-05-17 2024-01-16 servicios de apoyo en el Areas to Strengthened pendiente proceso de calificación. Sustainable Management FA-SNR-256-CS-INDV / Supervisión a la Intervención Multipurpose Cadaster in archivística de antecedentes y Environmental and Protected Ejecución TF / B4816 Posterior Individual Open 8,413.61 0.00 2022-01-11 2022-02-09 2022-02-19 2022-03-11 2022-10-07 libros de antiguo sistema - Areas to Strengthened pendiente Perfil Restaurador, Cantidad Sustainable Management uno (1) FA-SNR-257-CS-INDV / Supervisión a la Intervención Multipurpose Cadaster in archivística de antecedentes y Environmental and Protected Ejecución TF / B4816 Posterior Individual Open 8,413.61 0.00 2022-01-11 2022-02-10 2022-02-20 2022-03-12 2022-10-08 libros de antiguo sistema - Areas to Strengthened pendiente Perfil Ingeniero de sistemas, Sustainable Management Cantidad uno (1) FA-SNR-258-CS-INDV / Supervisión a la Intervención Multipurpose Cadaster in archivística de antecedentes y Environmental and Protected Ejecución TF / B4816 Posterior Individual Open 7,228.33 0.00 2022-01-11 2022-02-10 2022-02-20 2022-03-12 2022-10-08 libros de antiguo sistema - Areas to Strengthened pendiente Perfil Archivista, Cantidad uno Sustainable Management (1) Perfil: Archivista FA-SNR-259-CS-INDV / Supervisión a la Intervención Multipurpose Cadaster in archivística de antecedentes y Environmental and Protected Ejecución TF / B4816 Posterior Individual Open 29,236.67 0.00 2022-01-11 2022-02-09 2022-02-19 2022-03-11 2022-10-07 libros de antiguo sistema - Areas to Strengthened pendiente Perfil Técnicos en archivo, Sustainable Management Cantidad seis (6) Page 13