Procurement Plan for Liaoning Safe and Sustainable Urban Water Supply Project Loan No. : 88370 I. General 1. Project information: The project will finance investments in the construction, repair/ rehabilitation and upgrading of water supply infrastructure facilities and technical assistance to improve operational and management capacities of participating five water supply companies, namely Anshan, Fushun, Fuxin, Gaizhou and Shenyang Water Companies. The project development objectives are to improve water quality and operational efficiency of selected water supply utilities in the project areas. Procurement for the proposed project will be carried out in accordance with the World Bank’s "Guidelines: Procurement of Goods, Works, and Non-Consulting Services under IBRD Loans and IDA Credits and Grants by World Bank Borrowers" dated January 2011, revised July 2014, and "Guidelines: Selection and Employment of Consultants under IBRD Loans and IDA Credits and Grants by World Bank Borrowers" dated January 2011, revised July 2014, and the provisions stipulated in the legal agreements. “Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by IBRD Loans and IDA Credits and Grants dated October 2006 and revised Jan 2011” shall apply to the project.“Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by IBRD Loans and IDA Credits and Grants, dated October 2006 and revised Jan 2011” shall apply to the project. The project procurement plan dated January 17, 2018 for the whole period of project implementation, prepared by Liaoning PPMO, has been submitted and reviewed by the World Bank. It will also be available in the project’s database, on the World Bank’s external website and at PPMO’s office. The procurement plan will be updated in agreement with the World Bank annually or as required to reflect actual project implementation needs and improvement in institutional capacity. Further details on procurement are provided in the project procurement plan. All procurement of project will be carried out by Liaoning PPMO( Liaoning Urban Construction and Renewal Project Management Company Limited ) and each city’s PIU. Detail project implementation agencies of each city are as following table: No. Project City Implementation agency 1 Shenyang Shenyang Water Supply Group 2 Anshan Anshan Water Supply Co. 3 Fushun Fushun Water Supply Co. 4 Fuxin Fuxin Water Supply Co. 5 Gaizhou Gaizhou Water Supply Co. 1 2. Bank’s approval Date of the procurement Plan: Original: March 2018 3. Date of General Procurement Notice: March 9, 2018 4. Period covered by this procurement plan: The procurement period of project covered from year May 2018 to August 2021 II. Goods and Works and Non-consulting Services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for procurement: Thresholds for applicable procurement methods of the Project have been determined as following table: Thresholds for Procurement Methods and Prior Review Expenditure Contract Value Procurement Prior Review Threshold Category Threshold (US$) Method (US$) ≥40,000,000 ICB 1. Civil works <40,000,000 NCB ≥US$15 million <500,000 Shopping ≥10,000,000 ICB 2. Goods <10,000,000 NCB ≥US$4 million <500,000 Shopping Notes: ICB: International Competitive Bidding NCB: National Competitive Bidding DC: Direct Contracting 2. Prequalification: Not applicable. 3. Reference to Project Operational/Procurement Manual: Management manual for World Bank Loan Project in Liaoning Province issued by Liaoning Financial Bureau. 4. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: No applicable. 5. Any Other Special Procurement Arrangements: Not applicable. 2 6. Procurement Packages with Methods and Time Schedule 1 2 3 4 5 6 7 Comment s Expected (Expecte Tender Estimated Procurem Review by d Ref. Contract Name Advertiseme Cost (USD ent Bank Duration No. Description nt x 106) Method (Prior/Post) of Publication Contract: Date Months) Anshan Water Supply       1. Civil Works Water distribution pipe network Non Bank AS-C01 5.28 7/2018 18 reconstruction project (A) Finance Water distribution pipe network AS-C02 4.38 NCB Post 8/2018 18 reconstruction project (B) Building pipeline reconstruction project AS-C03 7.26 NCB Post 10/2018 18 in Tiedong, Tiexi District Building pipeline reconstruction project AS-C04 in development zone, Qianshan, Lishan 5.36 NCB Post 3/2019 18 District 2. Goods and Non-consulting Services   Supply and installation of equipment, AS-E01 8.48 ICB(Goods) Prior 6/2018 18 materials for water source pumping station and water plant Supply and installation of equipment AS-E02 and water-meter for secondary boosting 6.23 ICB(Goods) Prior 5/2019 18 pumping stations (A) Supply and installation of equipment AS-E03 5.08 ICB(Goods) Prior 5/2019 16 and water-meter for secondary boosting 3 1 2 3 4 5 6 7 Comment s Expected (Expecte Tender Estimated Procurem Review by d Ref. Contract Name Advertiseme Cost (USD ent Bank Duration No. Description nt x 106) Method (Prior/Post) of Publication Contract: Date Months) pumping stations (B) Supply and installation of equipments of AS-E04 4.60 ICB(Goods) Prior 5/2019 18 SMART water Valve, pipe network maintenance AS-E05 equipment, engineering vehicles 2.53 ICB(Goods) Post 10/2018 16 procurement AS-E06 Office equipment 0.10 Shopping Post 5/2018 12 Institutional strengthening, training and AS-E07 0.13 Shopping Post 5/2018 60 investigation 3. Subtotal     Fuxin Water Supply     1. Civil Works     Water supply facilities reconstruction FX-C01 4.25 NCB Post 6/2018 18 project in old residential district (A) FX-C02 Water supply pipe network (A) 5.77 NCB Post 6/2019 16 Water supply facilities reconstruction FX-C03 3.40 NCB Post 3/2019 18 project in old residential district (B) Reconstruction of Naodehai water plant FX-C04 and construction of secondary boosting 1.23 NCB Post 4/2019 18 pumping stations FX-C05 Water supply pipe network (B) 3.26 NCB Post 11/2019 10 Water supply pipe network Non Bank FX-C06 2.89   6/2020 10 reconstruction project (A) Finance 4 1 2 3 4 5 6 7 Comment s Expected (Expecte Tender Estimated Procurem Review by d Ref. Contract Name Advertiseme Cost (USD ent Bank Duration No. Description nt x 106) Method (Prior/Post) of Publication Contract: Date Months) Water supply pipe network Non Bank FX-C07 3.37   11/2020 18 reconstruction project (B) Finance Water supply pipe network FX-C08 0.95 NCB Post 8/2021 8 reconstruction project (C) 2. Goods and Non-consulting Services 0.00   Procurement of equipment materials for FX-E01 0.89 NCB(goods) Post 6/2018 18 Water supply facilities in old residential district FX-E02 Procurement of GPS system 1.42 ICB(IT) Prior 7/2018 18 Procurement of water quality testing FX-E03 1.62 ICB(Goods) Prior 9/2018 6 equipment Supply and installation of equipments of FX-E04 3.33 ICB(goods) Prior 10/2018 10 SMART water Supply and installation of equipment for FX-E05 Naodehai water plant and secondary 1.68 ICB(Goods) Prior 4/2019 10 boosting pumping stations FX-E06 Office equipment 0.10 Shopping Post 5/2018 12 Institutional strengthening, training and FX-E07 0.13 Shopping Post 5/2018 60 investigation 3. Subtotal Fushun Water Supply 1. Civil Works 5 1 2 3 4 5 6 7 Comment s Expected (Expecte Tender Estimated Procurem Review by d Ref. Contract Name Advertiseme Cost (USD ent Bank Duration No. Description nt x 106) Method (Prior/Post) of Publication Contract: Date Months) Water distribution pipe network FS-C01 3.67 NCB Post 7/2018 16 reconstruction project (A) Water distribution pipe network FS-C02 2.80 NCB Post 4/2019 16 reconstruction project (B) Water distribution pipe network FS-C03 2.86 NCB Post 4/2020 16 reconstruction project (C) Water distribution pipe network FS-C04 2.91 NCB Post 4/2021 16 reconstruction project (D) Building pipeline reconstruction project FS- in Dongzhou,Hetai and Henan District 6.99 NCB Post 7/2018 18 C05-1 (A) FS- Building pipeline reconstruction project 6.61 NCB Post C05-2 in Hebei and Fengzhe District (B) FS- Building pipeline reconstruction project 5.61 NCB Post 4/2019 18 C06-1 in Hebei and Fengzhe District (A) Building pipeline reconstruction project FS- in Dongzhou,Hetai and Henan District 7.16 NCB Post C06-2 (C) Building pipeline reconstruction project FS-  Non Bank in Dongzhou,Hetai and Henan District 7.95   4/2020 18 C07-1 Finance (B) FS- Building pipeline reconstruction project 5.85 NCB Post 4/2020 18 C07-2 in Hebei and Fengzhe District (C) FS- Building pipeline reconstruction project  Non Bank 6.60   4/2021 18 C08-1 in Dongzhou,Hetai and Henan District Finance 6 1 2 3 4 5 6 7 Comment s Expected (Expecte Tender Estimated Procurem Review by d Ref. Contract Name Advertiseme Cost (USD ent Bank Duration No. Description nt x 106) Method (Prior/Post) of Publication Contract: Date Months) (D) FS- Building pipeline reconstruction project 5.51 NCB Post 4/2021 18 C08-2 in Hebei and Fengzhe District (D) 2. Goods and Non-consulting Services Supply and installation of equipment for FS-E01 secondary boosting pumping stations 2.78 ICB(Goods) Post 7/2018 18 (A) Supply and installation of equipment for Non Bank FS-E02 secondary boosting pumping stations 3.02   4/2020 18 Finance  (B) Pipe network emergency repair FS-E03 2.13 ICB(Goods) Post 7/2018 8 equipment Supply and installation of equipments of FS-E04 1.27 NCB(goods) Post 10/2018 18 SMART water (A) Supply and installation of equipments of FS-E05 5.53 ICB(Goods) Prior 10/2018 18 SMART water (B) Supply and installation of equipments of FS-E06 1.16 NCB(goods) Post 10/2018 12 SMART water (C) FS-E07 Office equipment 0.10 Shopping Post 10/2018 12 Institutional strengthening, training and FS-E08 0.13 Shopping Post 5/2018 60 investigation 3. Subtotal Gaizhou Water Supply 1. Civil Works 7 1 2 3 4 5 6 7 Comment s Expected (Expecte Tender Estimated Procurem Review by d Ref. Contract Name Advertiseme Cost (USD ent Bank Duration No. Description nt x 106) Method (Prior/Post) of Publication Contract: Date Months) Pipeline and water meter works (zone A GZ-C01 7.34 NCB Post 7/2018 18 ) Pipeline and water meter works (zone B GZ-C02 5.11 NCB Post 9/2018 18 ) Pipeline and water meter works (zone C GZ-C03 5.30 NCB Post 1/2019 18 ) Construction of main water supply  Non Bank GZ-C04 6.62   5/2020 18 pipeline Finance GZ-C05 Reconstruction of water plant 1.01 NCB Post 11/2020 18 2. Goods and Non-consulting Services Supply and installation of equipments of GZ-E01 3.15 ICB(Goods) Post 7/2018 18 SMART water GZ-E02 Operation and maintenance equipment 1.31 NCB(goods) Post 7/2018 18 GZ-E03 Office equipment 0.10 Shopping Post 7/2018 12 Institutional strengthening, training and GZ-E04 0.13 Shopping Post 7/2018 60 investigation 3. Subtotal Shenyang Water Supply 1. Civil Works Reconstruction of building pipeline  Non Bank SY-C01 reconstruction and secondary boosting 15.48   7/2018 16 Finance pumping stations SY-C02 Reconstruction and construction of 2.98 NCB Post 7/2018 18 8 1 2 3 4 5 6 7 Comment s Expected (Expecte Tender Estimated Procurem Review by d Ref. Contract Name Advertiseme Cost (USD ent Bank Duration No. Description nt x 106) Method (Prior/Post) of Publication Contract: Date Months) water distribution pipe network in Heping and Yuhong districts Reconstruction and construction of SY-C03 water distribution pipe network in 6.90 NCB Post 7/2018 15 Sujiatun and Shenhe districts Construction of water distribution pipe SY-C04 6.25 NCB Post 12/2018 12 network in Huanggu district Reconstruction and construction of SY-C05 water distribution pipe network in 12.54 NCB Post 2/2019 18 Huanggu and Tiexi districts Reconstruction and construction of SY-C06 water distribution pipe network in 12.31 NCB Post 12/2018 18 huanggu districts Reconstruction of water distribution SY-C07 12.39 NCB Post 9/2018 18 pipe network in huanggu districts Reconstruction of water distribution SY-C08 pipe network in Dadong,Shenhe, 4.23 NCB Post 9/2019 18 Huanggu and Heping districts Reconstruction and construction of SY-C09 water distribution pipe network in 3.57 NCB Post 2/2020 18 Heping and Tiexi districts 2. Goods and Non-consulting Services Water quality testing equipment and SY-E01 1.40 ICB Goods) Post 7/2018 12 leak detection equipment SY-E02 Water supply network repair machinery 1.58 ICB Goods) Post 7/2018 10 9 1 2 3 4 5 6 7 Comment s Expected (Expecte Tender Estimated Procurem Review by d Ref. Contract Name Advertiseme Cost (USD ent Bank Duration No. Description nt x 106) Method (Prior/Post) of Publication Contract: Date Months) and equipment Online monitoring system (DCS) of SY-E03 Water plan tand water source pump 4.86 ICB Goods) Prior 7/2018 18 station Online monitoring system of secondary SY-E04 6.87 ICB Goods) Prior 7/2018 18 boosting pump stations Equipments of online monitoring SY-E05 system of secondary boosting pump 8.41 ICB Goods) Prior 12/2019 18 stations and water-meter Pipe network geographic information SY-E06 2.88 ICB(IT) Post 7/2018 18 system SY-E07 Platform of SMART water supply 1.59 ICB(IT) Post 7/2018 18 SY-E08 Water supply network analysis platform 1.57 ICB(IT) Post 12/2018 18 SY-E09 Office equipment 0.10 Shopping Post 7/2018 12 Institutional strengthening, training and SY-E10 0.13 Shopping Post 7/2018 60 investigation 3. Subtotal Total for Works, Goods and Non-consulting       services . 10 III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Expenditur Contract Value Procurement Bank Prior Review e Category (US$) Method ≥300,000 QCBS/QBS/LCS/FBS Consultant ≥US$2 million <300,000 CQS s Individual Consultant ≥US$400,000 Notes: QCBS: Quality- and Cost- SSS: Single Source Selection Based Selection IC: Individual Consultant selection QBS: Quality-Based Selection procedure CQS: Selection Based on the FBS: Fix Budget Selection Consultants’ Qualifications LCS: Least Cost Selection 2. Short list comprising entirely of national consultants: Short lists of consultants (firms) for services estimated to cost less than US$500,000 equivalent per contract may be composed entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 7 Comment Expecte s Estimate Selecti Review d (Expecte d Description of on by Bank REOI d Ref. No. Cost Assignment Metho (Prior / Publicat Duration (US$ d Post) ion of million) Date Contract: Months) Technical assistance Construction FX- drawings (detailed) Post Prio 0.32 QCBS 5/2018 48 ZX01 design for Fuxin r TOR  Project Engineering FX- supervision for Civil Post Prio 0.25 QCBS 5/2018 60 ZX02 Works for Fuxin r TOR  Project Construction GZ- drawings (detailed) Post Prio 1.08 QCBS 5/2018 48 ZX01 design for Gaizhou r TOR  Project GZ- Engineering 0.50 FBS Post Prio 7/2018 60 11 ZX02 supervision for Civil r TOR  Works for Gaizhou Project Engineering SY- Post Prio supervision for Civil 1.80 FBS 7/2018 60 ZX01 r TOR  Works Project management LN- consultants service 3.60 QCBS Prior 5/2018 60 ZX01 and IT contracts supervision Researchr on NRW, energy saving, KPI, Institutional LN- Post Prio strengthening and 0.40 QCBS 5/2018 60 ZX02 r TOR  benchmarking for Water Supply Companies Provincial institutional LN- strengthening, 0.35 QCBS Post 5/2018 60 ZX03 training and investigation LN- Study on PPP Policy 0.20 CQS Post 5/2018 18 ZX04 of Water Industry Subtotal of TA 12 PROCUREMENT China : China: Liaoning Safe and Sustainable Urban Water Supply Project PLAN General Information Country: China 2018-03-28 Bank’s Approval Date of the Original Procurement Plan: 2022-08-03 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P158713 GPN Date: 2018-03-09 Project Name: China: Liaoning Safe and Sustainable Urban Water Supply Project Loan / Credit No: IBRD / 88370, / Liaoning Urban Construction and Renewal Project Office Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GZ-C01 / Gaizhou City Pipeli Component 1: Water supply Single Stage - One E 4,974,657.1 2020-12-2 IBRD / 88370 Post Request for Bids Open - National Signed 2019-05-15 2019-05-15 2019-05-17 2019-05-27 2019-06-16 2019-06-27 2019-06-23 2019-10-28 2019-07-07 2019-11-15 ne and water meter works (z service infrastructure impro nvelope 9 8 one A ) vement GZ-C05 / Rehabilitation of ex Component 1: Water supply Single Stage - One E 2021-02-1 IBRD / 88370 Post Request for Bids Open - National 963,781.26 Signed 2019-06-10 2019-06-12 2019-06-21 2019-06-13 2019-07-21 2019-07-15 2019-08-04 2019-07-18 2019-08-23 2019-08-12 isting water plants service infrastructure impro nvelope 3 vement FS-C01 / Rehabilitation of m unicipal water distribution pi pelines(A) Component 1: Water supply Single Stage - One E 6,346,170.9 2021-03-2 2019 upgrading plan: Haixin IBRD / 88370 service infrastructure impro Post Request for Bids Open - National Signed 2019-07-26 2019-07-23 2019-07-31 2019-07-25 2019-08-30 2019-09-09 2019-09-13 2019-09-23 2019-10-04 2019-10-15 nvelope 2 7 River to Shanshang Lianluom vement en, Tawan pump station to M eikuang Dianjichang, Taian S treet, Liuhe Street and other sections (30 roads in total) FS-C05-1 / Rehabilitation of water distribution pipelines o f residential quarters in Don Component 1: Water supply Single Stage - One E 4,946,415.6 2021-03-2 gzhou,Hetai and Henan Distri IBRD / 88370 service infrastructure impro Post Request for Bids Open - National Signed 2019-07-26 2019-07-25 2019-07-31 2019-07-25 2019-08-30 2019-09-09 2019-09-13 2019-09-23 2019-09-27 2019-10-15 nvelope 1 0 ct (A) vement Gaoshan Road Laomo reside ntial department and other di stricts (30 districts in total); FS-C05-2 / Rehabilitation of water distribution pipelines o Component 1: Water supply f residential quarters in Hebe Single Stage - One E 4,158,852.3 2021-03-2 IBRD / 88370 service infrastructure impro Post Request for Bids Open - National Signed 2019-07-26 2019-07-23 2019-07-31 2019-07-25 2019-08-30 2019-09-09 2019-09-13 2019-09-23 2019-09-27 2019-10-15 i and Fengzhe District (A) nvelope 6 0 vement Xifeng District, Taian District, and other districts (46 distric ts in total) FS-C06-1 / Rehabilitation of water distribution pipelines o Component 1: Water supply f residential quarters in Dong Single Stage - One E 3,144,872.1 2021-03-2 IBRD / 88370 service infrastructure impro Post Request for Bids Open - National Signed 2019-07-26 2019-07-23 2019-07-31 2019-07-25 2019-08-30 2019-09-09 2019-09-13 2019-09-27 2019-10-15 zhou, Hetai and Henan Distri nvelope 7 0 vement ct (B) Donggang Districts and other districts (23 districts in total) FS-C06-2 / Rehabilitation of water distribution pipelines o Component 1: Water supply Single Stage - One E 2,951,477.7 2021-03-2 f residential quarters in Hebe IBRD / 88370 service infrastructure impro Post Request for Bids Open - National Signed 2019-07-26 2019-07-23 2019-07-31 2019-07-25 2019-08-30 2019-09-09 2019-09-13 2019-09-23 2019-09-27 2019-10-15 nvelope 9 0 i and Fengzhe (B) vement Yixi District and other district s (24 districts in total) AS-C02 / Water distribution Component 1: Water supply Single Stage - One E Pending Imp 2022-05-1 pipe network rehabilitation p IBRD / 88370 service infrastructure impro Post Request for Bids Open - National 0.00 2020-09-15 2020-09-20 2020-10-20 2020-11-03 2020-11-24 nvelope lementation 8 roject in old pipe network (B) vement AS-C04 / Building pipeline re Component 1: Water supply Single Stage - One E 5,728,328.8 2021-12-1 habilitation project in Lishan IBRD / 88370 service infrastructure impro Post Request for Bids Open - National Signed 2020-04-14 2020-06-29 2020-04-19 2020-06-29 2020-05-19 2020-07-30 2020-06-02 2020-08-25 2020-06-23 2020-09-28 nvelope 6 5 and Tiexi District vement FS-C03 / Rehabilitation of m Component 1: Water supply Single Stage - One E 1,070,619.5 2021-11-2 IBRD / 88370 Post Request for Bids Open - National Signed 2020-03-20 2021-05-28 2020-03-25 2021-05-27 2020-04-24 2021-06-30 2020-05-08 2021-08-27 2020-05-29 2021-09-23 unicipal water distribution pi service infrastructure impro nvelope 4 0 pelines(C) vement FS-C04 / Rehabilitation of m Component 1: Water supply Single Stage - One E 2022-12-1 IBRD / 88370 Post Request for Bids Open - National 850,343.24 Signed 2021-04-10 2021-05-28 2021-04-15 2021-05-27 2021-05-15 2021-06-29 2021-05-29 2021-08-27 2021-06-19 2021-09-23 unicipal water distribution pi service infrastructure impro nvelope 1 pelines (D) vement FS-C07-1 / Rehabilitation of Component 1: Water supply water distribution pipelines o Single Stage - One E 3,950,219.5 2021-11-1 IBRD / 88370 service infrastructure impro Post Request for Bids Open - National Signed 2020-03-20 2021-05-28 2020-03-25 2021-05-27 2020-04-24 2021-06-29 2020-05-08 2021-08-27 2020-05-22 2021-09-23 f residential quarters in Dong nvelope 4 3 vement zhou,Hetai and Henan Distric t (C) FS-C07-2 / Rehabilitation of Component 1: Water supply water distribution pipelines o Single Stage - One E 4,425,579.5 2021-11-1 IBRD / 88370 service infrastructure impro Post Request for Bids Open - National Signed 2020-03-20 2021-05-28 2020-03-25 2021-05-27 2020-04-24 2021-06-29 2020-05-08 2021-08-27 2020-05-22 2021-09-23 f residential quarters in Hebe nvelope 6 3 vement i and Fengzhe District (C) GZ-C02 / Water pipelines an Component 1: Water supply Single Stage - One E 5,622,442.6 2021-08-0 IBRD / 88370 Post Request for Bids Open - National Signed 2019-12-15 2020-01-14 2019-12-20 2020-01-14 2020-01-19 2020-03-05 2020-01-26 2020-03-10 2020-02-09 2020-03-27 d water meters in Area B service infrastructure impro nvelope 9 2 vement GZ-C03 / Water pipelines an Component 1: Water supply Single Stage - One E 2,372,031.2 2021-11-1 IBRD / 88370 Post Request for Bids Open - National Signed 2020-04-01 2021-10-19 2020-04-06 2021-10-19 2020-05-06 2021-11-18 2020-05-13 2021-12-28 2020-05-27 2021-12-28 d water meters in Area C service infrastructure impro nvelope 9 8 vement GZ-C04 / Purified water tran Component 1: Water supply Single Stage - One E Pending Imp 2022-10-2 IBRD / 88370 Post Request for Bids Open - National 0.00 2021-02-26 2021-03-05 2021-04-04 2021-04-18 2021-05-07 smission pipelines service infrastructure impro nvelope lementation 9 vement SY-C02 / Area-based rehabili Component 1: Water supply tation and construction of wa Single Stage - One E 2022-01-2 IBRD / 88370 service infrastructure impro Post Request for Bids Open - National 0.00 Canceled 2020-05-31 2020-06-07 2020-07-07 2020-07-21 2020-08-04 ter distribution pipe network nvelope 6 vement in Heping and Yuhong Distric ts SY-C03 / Area-based rehabili Component 1: Water supply tation and construction of wa Single Stage - One E 2022-01-2 IBRD / 88370 service infrastructure impro Post Request for Bids Open - National 0.00 Canceled 2020-05-31 2020-06-07 2020-07-07 2020-07-21 2020-08-04 ter distribution pipe network nvelope 6 vement in Sujiatun and Shenhe Distri cts SY-C04 / Construction of wat Component 1: Water supply Single Stage - One E Pending Imp 2022-09-2 er distribution pipe network o IBRD / 88370 service infrastructure impro Post Request for Bids Open - National 0.00 2021-01-30 2021-02-06 2021-03-08 2021-03-22 2021-04-05 nvelope lementation 7 n Wenda Road in Huanggu Di vement strict SY-C05 / Area-based rehabili Component 1: Water supply tation and construction of wa Single Stage - One E Pending Imp 2022-09-2 IBRD / 88370 service infrastructure impro Post Request for Bids Open - National 0.00 2021-01-30 2021-02-06 2021-03-08 2021-03-22 2021-04-05 ter distribution pipe network nvelope lementation 7 vement in Huanggu and Tiexi District s Page 1 SY-C07 / Rehabilitation of wa Component 1: Water supply Single Stage - One E Pending Imp 2022-09-2 ter distribution pipe network IBRD / 88370 service infrastructure impro Post Request for Bids Open - National 0.00 2021-01-30 2021-02-06 2021-03-08 2021-03-22 2021-04-05 nvelope lementation 7 on Hushitai Da Street in Hua vement nggu District SY-C08 / Area-based rehabili Component 1: Water supply tation of water distribution pi Single Stage - One E 2022-09-2 IBRD / 88370 service infrastructure impro Post Request for Bids Open - National 0.00 Canceled 2021-01-30 2021-02-06 2021-03-08 2021-03-22 2021-04-05 pe network in Dadong, Shenh nvelope 7 vement e, Huanggu and Heping Distri cts SY-C09 / Area-based rehabili Component 1: Water supply tation and construction of wa Single Stage - One E 2022-09-2 IBRD / 88370 service infrastructure impro Post Request for Bids Open - National 0.00 Canceled 2021-01-30 2021-02-06 2021-03-08 2021-03-22 2021-04-05 ter distribution pipe network nvelope 7 vement in Huanggu and Heping Distri cts FX-C01 / Rehabilitation of wa Component 1: Water supply Single Stage - One E 7,218,542.7 2021-08-0 ter supply facilities in Fuxin o IBRD / 88370 service infrastructure impro Post Request for Bids Open - National Signed 2019-12-10 2020-06-30 2019-12-15 2020-07-06 2020-01-14 2020-07-31 2020-01-28 2020-08-25 2020-02-11 2020-09-01 nvelope 6 4 ld residential district (A) vement FX-C02 / Construction of Fux Component 1: Water supply Single Stage - One E 2022-09-1 IBRD / 88370 Post Request for Bids Open - National 0.00 Canceled 2021-01-22 2021-01-27 2021-02-26 2021-03-12 2021-03-26 in new water supply pipeline service infrastructure impro nvelope 7 s (A) vement FX-C05 / Construction of Fux Component 1: Water supply Single Stage - One E Pending Imp 2022-08-1 IBRD / 88370 Post Request for Bids Open - National 0.00 2020-12-17 2020-12-22 2021-01-21 2021-02-04 2021-02-18 in new water supply pipeline service infrastructure impro nvelope lementation 2 s (B) vement FX-C06 / Fuxin Rehabilitation of Fuxin water supply pipelin Component 1: Water supply Single Stage - One E Under Imple 2021-09-1 es (A), civil works and equip IBRD / 88370 service infrastructure impro Post Request for Bids Open - National 0.00 2020-01-22 2021-05-10 2020-01-27 2021-05-09 2020-02-26 2020-03-11 2020-03-25 nvelope mentation 6 ment supply of booster pum vement p stations in Development Zo ne FX-C07 / Rehabilitation of Fu Component 1: Water supply Single Stage - One E Pending Imp 2022-08-1 IBRD / 88370 Post Request for Bids Open - National 0.00 2020-12-17 2020-12-22 2021-01-21 2021-02-04 2021-02-18 xin water supply pipelines (B service infrastructure impro nvelope lementation 2 ) vement FX-C08 / Construction of Fux Component 1: Water supply Single Stage - One E Pending Imp 2022-09-2 IBRD / 88370 Post Request for Bids Open - National 0.00 2021-02-02 2021-02-07 2021-03-09 2021-03-23 2021-04-06 in new water supply pipeline service infrastructure impro nvelope lementation 8 s (C) vement AS-E01 / Equipments supply and installation of Wangjiay Component 1: Water supply Open - Internationa Single Stage - One E Under Imple 2022-03-1 u water plant and Tanghe wa IBRD / 88370 service infrastructure impro Post Request for Bids 0.00 2020-07-10 2021-05-10 2020-07-15 2021-05-09 2020-08-26 2020-09-02 2020-09-23 l nvelope mentation 7 ter source pumping station r vement ehibilitation for high standar d SY-C01 / Rehabilitation of pi Component 1: Water supply pelines of residential quarter Single Stage - One E 2021-11-1 IBRD / 88370 service infrastructure impro Post Request for Bids Open - National 0.00 Canceled 2020-03-22 2020-03-29 2020-04-28 2020-05-12 2020-05-26 s; Rehabilitation of secondar nvelope 7 vement y boosting pumping stations AS-E02-1 / Supply and install Component 1: Water supply ation of equipment and wate Open - Internationa Single Stage - One E 6,819,411.0 2022-05-0 IBRD / 88370 service infrastructure impro Post Request for Bids Signed 2020-08-25 2021-05-06 2020-08-30 2021-05-06 2020-10-11 2021-06-17 2020-10-18 2021-07-09 2020-11-08 2021-08-16 r-meter for secondary boosti l nvelope 5 2 vement ng pumping stations FS-E04-1 / SMART water syst Component 1: Water supply Open - Internationa Single Stage - One E 4,540,003.3 2021-12-1 IBRD / 88370 Post Request for Bids Signed 2020-04-05 2021-08-04 2020-04-10 2021-08-04 2020-05-22 2021-09-15 2020-05-29 2021-09-26 2020-06-19 2021-11-15 em (A) service infrastructure impro l nvelope 1 1 vement SY-C01-1 / Rehabilitation of Component 1: Water supply Single Stage - One E 5,649,288.2 2021-11-1 water supply pipelines in resi IBRD / 88370 service infrastructure impro Post Request for Bids Open - National Signed 2020-03-20 2020-11-17 2020-03-27 2020-11-18 2020-04-26 2020-12-18 2020-05-10 2021-03-24 2020-05-24 2021-04-28 nvelope 5 5 dential areas vement SY-E11 / Supply and installat Component 1: Water supply Open - Internationa Single Stage - One E Under Imple 2021-11-2 ion of equipment for seconda IBRD / 88370 service infrastructure impro Post Request for Bids 0.00 2020-03-20 2021-06-01 2020-03-25 2021-05-31 2020-05-06 2020-05-13 2020-06-03 l nvelope mentation 5 ry boosting pumping stations vement AS-C03 / Building pipeline re Component 1: Water supply Single Stage - One E 5,802,084.7 2022-03-0 habilitation project in Tiedon IBRD / 88370 service infrastructure impro Post Request for Bids Open - National Signed 2020-06-29 2020-06-29 2020-06-30 2020-06-29 2020-07-30 2020-07-30 2020-08-13 2020-08-25 2020-09-11 2020-09-28 nvelope 1 5 g, Development Zone and Qi vement anshan District Request for B SY-C02-1 / rehabilitation and Component 1: Water supply ids - Works ( Single Stage - One E Pending Imp 2023-03-1 construction of street-based IBRD / 88370 service infrastructure impro Post Request for Bids Open - National without preq 0.00 2021-07-08 2021-07-13 2021-08-12 2021-08-19 2021-09-16 nvelope lementation 0 water distribution pipelines A vement ualification) SPD Request for B SY-C03-1 / rehabilitation and Component 1: Water supply ids - Works ( Single Stage - One E Pending Imp 2023-03-1 construction of street-based IBRD / 88370 service infrastructure impro Post Request for Bids Open - National without preq 0.00 2021-07-16 2021-07-21 2021-08-20 2021-08-27 2021-09-24 nvelope lementation 8 water distribution pipelines B vement ualification) SPD Request for B SY-C08-1 / rehabilitation and Component 1: Water supply ids - Works ( Single Stage - One E Pending Imp 2023-03-2 construction of street-based IBRD / 88370 service infrastructure impro Post Request for Bids Open - National without preq 0.00 2021-07-22 2021-07-27 2021-08-26 2021-09-02 2021-09-30 nvelope lementation 4 water distribution pipelines F vement ualification) SPD Request for B SY-C09-1 / rehabilitation and Component 1: Water supply ids - Works ( Single Stage - One E Pending Imp 2023-03-2 construction of street-based IBRD / 88370 service infrastructure impro Post Request for Bids Open - National without preq 0.00 2021-07-23 2021-07-28 2021-08-27 2021-09-03 2021-10-01 nvelope lementation 5 water distribution pipelines G vement ualification) SPD GZ-C06 / Water Supply Pipeli Request for B ne and Water Meter Construc Component 1: Water supply ids - Works ( Single Stage - One E Pending Imp 2024-05-0 tion in Areas D and E, and W IBRD / 88370 service infrastructure impro Prior Request for Bids Open - National without preq 0.00 2022-08-09 2022-08-16 2022-09-15 2022-09-29 2022-11-09 nvelope lementation 2 ater Transmission Pipeline Co vement ualification) nstruction in Yangjiadian WT SPD P GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual FX-E06 / Fuxin PMO office eq Component 1: Water supply Request for Quota Single Stage - One E IBRD / 88370 Post Limited 86,460.93 Signed 2019-06-24 2019-09-24 2019-07-27 2019-10-25 2020-07-21 uipments service infrastructure impro tions nvelope vement GZ-E02 / Opertion and meint Component 1: Water supply Open - Internationa Single Stage - One E IBRD / 88370 Post Request for Bids 2,385,986.05 Signed 2019-06-18 2019-06-20 2019-06-21 2019-06-20 2019-08-02 2019-08-02 2019-08-07 2019-08-09 2019-08-22 2019-09-05 2021-02-12 enance equipment service infrastructure impro l nvelope vement FS-E09 / SMART water syste Component 1: Water supply m (D) Request for Quota Single Stage - One E IBRD / 88370 service infrastructure impro Post Limited 172,061.69 Signed 2019-08-02 2019-07-30 2019-09-20 2019-09-03 2020-09-14 1900 pieces of wireless remo tions nvelope vement te transmission water meters and relevant software procu rement Page 2 GZ-E03 / Gazhou PMO office Component 2: Water supply Request for Quota Single Stage - One E IBRD / 88370 Post Limited 112,517.44 Signed 2019-07-31 2019-07-31 2019-09-04 2019-09-05 2020-08-29 equipments service management improv tions nvelope ement GZ-E05 / 5 emergency repar Component 2: Water supply Request for Quota Single Stage - One E IBRD / 88370 Post Limited 102,918.26 Signed 2019-07-31 2019-08-30 2019-09-04 2019-10-10 2021-02-25 ie vehicles service management improv tions nvelope ement AS-E02 / Supply and installat Component 1: Water supply ion of equipment and water- Open - Internationa Single Stage - One E IBRD / 88370 service infrastructure impro Prior Request for Bids 0.00 Canceled 2020-08-23 2020-08-30 2020-10-11 2020-10-16 2020-10-31 2022-04-24 meter for secondary boosting l nvelope vement pumping stations AS-E03 / Supply and installat ion of equipment for central control room, power automat Component 1: Water supply Open - Internationa Single Stage - One E ic control equipment, and aut IBRD / 88370 service infrastructure impro Post Request for Bids 3,682,905.24 Signed 2020-08-23 2021-01-15 2020-08-30 2021-01-14 2020-10-11 2021-03-09 2020-10-16 2021-04-25 2020-10-31 2021-05-28 2022-04-24 l nvelope omatic control lifiting equime vement nt of secondary boosting pu mping stations; and procure ment and installation of wate r meters AS-E04 / Supply and installat Component 2: Water supply Open - Internationa Single Stage - One E ion of main equipment of sta IBRD / 88370 service management improv Post Request for Bids 0.00 Canceled 2020-05-23 2020-05-30 2020-07-11 2020-07-16 2020-07-31 2022-01-22 l nvelope rt water management syste ement m AS-E05 / Supply of maintena Component 1: Water supply nce equipment, emergence r Open - Internationa Single Stage - One E IBRD / 88370 service infrastructure impro Post Request for Bids 2,947,761.17 Signed 2020-06-23 2020-06-28 2020-06-30 2020-06-28 2020-08-11 2020-08-11 2020-08-16 2020-08-14 2020-08-31 2020-09-17 2022-02-22 epair equipment, network eq l nvelope vement uipment and water quality m onitoring equipment AS-E08 / Supply and installat Component 1: Water supply Open - Internationa Single Stage - One E IBRD / 88370 Post Request for Bids 4,746,592.34 Signed 2020-02-21 2020-03-09 2020-02-28 2020-03-12 2020-04-10 2020-04-24 2020-04-15 2020-10-15 2020-04-30 2020-06-05 2021-10-22 ion of water meters service infrastructure impro l nvelope vement FS-E03 / Pipeline emergency Component 2: Water supply Open - Internationa Single Stage - One E IBRD / 88370 Post Request for Bids 1,925,373.12 Signed 2019-11-13 2020-06-02 2019-11-20 2020-06-03 2020-01-01 2020-07-16 2020-01-06 2020-07-27 2020-01-21 2020-09-10 2021-07-14 repair equipment service management improv l nvelope ement FS-E04 / SMART water syste Component 2: Water supply Open - Internationa Single Stage - One E IBRD / 88370 Post Request for Bids 0.00 Canceled 2020-04-03 2020-04-10 2020-05-22 2020-05-27 2020-06-11 2021-12-03 m (A) service management improv l nvelope ement FS-E05 / SMART water syste Component 2: Water supply Open - Internationa Single Stage - One E IBRD / 88370 Post Request for Bids 4,431,853.41 Signed 2020-04-03 2021-01-14 2020-04-10 2021-01-14 2020-05-22 2021-03-11 2020-05-27 2021-03-19 2020-06-11 2021-04-20 2021-12-03 m (B) service management improv l nvelope ement FS-E06 / SMART water syste Component 2: Water supply Single Stage - One E IBRD / 88370 Post Request for Bids Open - National 0.00 Canceled 2020-03-29 2019-09-24 2020-04-05 2020-05-17 2019-10-12 2020-05-22 2020-06-06 2021-11-28 m (C) service management improv nvelope ement FS-E07 / Fushun PMO Office Component 2: Water supply Request for Quota Single Stage - One E IBRD / 88370 Post Limited 102,723.28 Signed 2019-12-20 2020-06-02 2020-01-22 2020-07-09 2021-01-16 equipments service management improv tions nvelope ement GZ-E01 / Pipeline smart man Component 2: Water supply Single Stage - One E IBRD / 88370 Post Request for Bids Open - National 3,089,845.44 Signed 2019-11-28 2020-07-03 2019-12-05 2020-07-05 2020-01-16 2020-08-06 2020-01-21 2020-08-19 2020-02-05 2020-09-30 2021-07-29 agement system service management improv nvelope ement SY-E01 / Water quality testin Component 2: Water supply Open - Internationa Single Stage - One E g equipment and leak detecti IBRD / 88370 service management improv Post Request for Bids 1,329,001.84 Signed 2019-12-07 2020-02-10 2019-12-14 2020-02-18 2020-01-25 2020-04-02 2020-01-30 2020-04-14 2020-02-14 2020-05-19 2021-08-07 l nvelope on equipment ement SY-E02 / Water supply netwo Component 1: Water supply Open - Internationa Single Stage - One E rk repair machinery and equi IBRD / 88370 service infrastructure impro Post Request for Bids 1,980,149.24 Signed 2019-12-07 2020-02-26 2019-12-14 2020-02-26 2020-01-25 2020-04-09 2020-01-30 2020-04-16 2020-02-14 2020-05-22 2021-02-08 l nvelope pment and flow meters vement SY-E03 / Online monitoring s Component 2: Water supply Open - Internationa Single Stage - One E Under Imple ystem (DCS) of water plant a IBRD / 88370 service management improv Post Request for Bids 0.00 2020-04-12 2021-06-29 2020-04-19 2021-06-28 2020-05-31 2020-06-05 2020-06-20 2021-12-12 l nvelope mentation nd water source pump statio ement n SY-E04 / Remote online mon Component 2: Water supply Open - Internationa Single Stage - One E itoring system of secondary IBRD / 88370 service management improv Prior Request for Bids 0.00 Canceled 2019-12-22 2021-01-17 2019-12-29 2021-07-19 2020-02-09 2020-02-14 2020-02-29 2021-08-22 l nvelope boosting pump stations A ement SY-E05 / Remote online mon Component 2: Water supply Open - Internationa Single Stage - One E Under Imple itoring system of secondary IBRD / 88370 service management improv Prior Request for Bids 0.00 2020-06-08 2020-12-18 2020-06-15 2021-01-15 2020-07-27 2021-04-15 2020-08-01 2021-05-07 2020-08-16 2022-02-07 l nvelope mentation boosting pump stations B ement SY-E06 / Pipe network geogr Component 2: Water supply Single Stage - One E aphic information system (GI IBRD / 88370 service management improv Prior Request for Bids Open - National 0.00 Canceled 2019-12-22 2020-04-21 2019-12-29 2020-05-06 2020-02-09 2020-06-05 2020-02-14 2020-10-11 2020-02-29 2021-08-22 nvelope S) and Platform of SMART wa ement ter supply SY-E09 / Shenyang PMO offic Component 2: Water supply Request for Quota Single Stage - One E IBRD / 88370 Post Limited 126,491.90 Signed 2019-12-29 2020-05-07 2020-02-02 2020-07-01 2021-01-27 e equipments service management improv tions nvelope ement FX-E01 / Procurement of equ Component 1: Water supply Open - Internationa Single Stage - One E ipment and materials for wat IBRD / 88370 service infrastructure impro Post Request for Bids 3,103,027.90 Signed 2019-11-23 2019-12-05 2019-11-30 2019-12-06 2020-01-11 2020-01-17 2020-01-16 2020-01-22 2020-01-31 2020-02-28 2021-07-24 l nvelope er supply facilities in old resi vement dential district FX-E03 / Procurement of wat Component 2: Water supply Open - Internationa Single Stage - One E IBRD / 88370 Post Request for Bids 1,450,973.47 Signed 2019-12-23 2020-09-29 2019-12-30 2020-10-11 2020-02-10 2020-11-24 2020-02-17 2020-12-10 2020-03-09 2021-01-12 2020-03-14 er quality testing equipmen service management improv l nvelope ement FX-E04 / Fuxin smart water i nfrastructure online monitori Component 1: Water supply Open - Internationa Single Stage - One E ng equipment procurement a IBRD / 88370 service infrastructure impro Post Request for Bids 2,625,960.11 Signed 2020-01-23 2021-01-14 2020-01-30 2021-01-14 2020-03-12 2021-03-10 2020-03-17 2021-03-19 2020-04-01 2021-04-20 2021-09-23 l nvelope nd emergency repair equipm vement ent and leakage detecting eq uipment SY-E06-1 / Rebid for SY-E06, Component 2: Water supply Pipe network geographic info Single Stage - One E Under Imple IBRD / 88370 service management improv Prior Request for Bids Open - National 0.00 2020-11-03 2020-11-26 2020-11-17 2020-12-01 2020-12-17 2021-02-24 2020-12-31 2021-03-31 2021-02-02 2022-07-27 rmation system (GIS) and Pla nvelope mentation ement tform of SMART water supply FS-E06-1 / SMART water syst Component 2: Water supply Single Stage - One E IBRD / 88370 Prior Request for Bids Open - National 5,553,136.56 Signed 2021-06-01 2021-06-28 2021-06-15 2021-06-29 2021-07-15 2021-08-03 2021-07-29 2021-10-28 2021-08-17 2021-11-30 2023-02-08 em (C) service management improv nvelope ement AS-E04-1 / Supply and install Component 2: Water supply Single Stage - One E ation of software and equipm IBRD / 88370 service management improv Prior Request for Bids Open - National 3,016,392.19 Signed 2021-06-01 2021-10-01 2021-06-15 2021-10-15 2021-07-15 2021-11-23 2021-07-29 2021-12-15 2021-08-17 2021-12-30 2023-02-08 nvelope ent of SMART water system ement SY-E08 / Area-based water s Component 2: Water supply Single Stage - One E Pending Impl IBRD / 88370 Post Request for Bids Open - National 0.00 2021-06-01 2021-06-15 2021-07-15 2021-07-29 2021-08-17 2023-02-08 upply network analysis platfo service management improv nvelope ementation rm ement FX-E02 / Procurement of GIS Component 2: Water supply system, ESB, water hydraulic Single Stage - One E IBRD / 88370 service management improv Prior Request for Bids Open - National 0.00 Canceled 2021-06-01 2021-07-15 2021-06-15 2021-07-31 2021-07-15 2021-07-29 2021-08-17 2023-02-08 model development, Second nvelope ement ary pressurized water supply dispatching system Page 3 FS-E02 / Supply and installat Component 1: Water supply Open - Internationa Single Stage - One E ion of equipment for seconda IBRD / 88370 service infrastructure impro Post Request for Bids 1,998,792.89 Signed 2021-05-28 2021-08-04 2021-06-04 2021-08-04 2021-07-16 2021-09-16 2021-07-21 2021-09-26 2021-08-05 2021-11-15 2023-01-27 l nvelope ry boosting pumping stations vement (B) GZ-E06 / Procurement of Eq Component 1: Water supply uipment and Flowmeters for Single Stage - One E Pending Impl IBRD / 88370 service infrastructure impro Post Request for Bids Open - National 0.00 2022-08-17 2022-08-22 2022-10-10 2022-10-24 2022-12-21 2023-12-16 Secondary Booster Pumping nvelope ementation vement Stations for Water Supply NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 3: Project Imple AS-FZX01 / Anshan trainings Request for Quota Single Stage - One E Pending Impl IBRD / 88370 mentation support and instit Post Limited 0.00 2020-01-06 2020-02-17 2021-08-10 , study tours (A) tions nvelope ementation utional strengthening Component 3: Project Imple AS-FZX02 / Ansahn trainings Request for Quota Single Stage - One E IBRD / 88370 mentation support and instit Post Limited 108,953.81 Signed 2021-08-06 2021-08-10 2021-09-17 2021-09-22 2023-03-11 , study tours (B) tions nvelope utional strengthening Component 3: Project Imple FX-FZX01 / Fuxin training, st Request for Quota Single Stage - One E Pending Impl IBRD / 88370 mentation support and instit Post Limited 0.00 2020-01-06 2020-02-17 2021-08-10 udy tour (A) tions nvelope ementation utional strengthening Component 3: Project Imple FX-FZX02 / Fuxin training, st Request for Quota Single Stage - One E Pending Impl IBRD / 88370 mentation support and instit Post Limited 0.00 2021-08-06 2021-09-17 2023-03-11 udy tour (B) tions nvelope ementation utional strengthening Component 3: Project Imple FS-FZX01 / Fushun training, Request for Quota Single Stage - One E Pending Impl IBRD / 88370 mentation support and instit Post Limited 0.00 2020-01-06 2020-02-17 2021-08-10 study tour (A) tions nvelope ementation utional strengthening Component 3: Project Imple FS-FZX02 / Fushun training, Request for Quota Single Stage - One E Pending Impl IBRD / 88370 mentation support and instit Post Limited 0.00 2021-08-06 2021-09-17 2023-03-11 study tour (B) tions nvelope ementation utional strengthening Component 3: Project Imple GZ-FZX01 / Gaizhou training Request for Quota Single Stage - One E Pending Impl IBRD / 88370 mentation support and instit Post Limited 0.00 2020-01-06 2020-02-17 2021-08-10 , study tour (A) tions nvelope ementation utional strengthening Component 3: Project Imple GZ-FZX02 / Gazhou training, Request for Quota Single Stage - One E Pending Impl IBRD / 88370 mentation support and instit Post Limited 0.00 2021-08-06 2021-09-17 2023-03-11 study tour (B) tions nvelope ementation utional strengthening Component 3: Project Imple SY-FZX01 / Shenyang trainin Request for Quota Single Stage - One E Pending Impl IBRD / 88370 mentation support and instit Post Limited 0.00 2020-01-06 2020-02-17 2021-08-10 g, study tour (A) tions nvelope ementation utional strengthening Component 3: Project Imple SY-FZX02 / Shenyang trainin Request for Quota Single Stage - One E Pending Impl IBRD / 88370 mentation support and instit Post Limited 0.00 2021-08-06 2021-09-17 2023-03-11 g, study tour (B) tions nvelope ementation utional strengthening CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual FX-ZX01 / Construction draw Component 3: Project Imple Quality And Cost- ings (detailed) design for Fux IBRD / 88370 mentation support and instit Post Open - National 482,359.00 Signed 2018-03-29 2018-03-29 2018-04-08 2018-05-23 2018-05-13 2018-08-07 2018-06-10 2018-09-20 2018-06-25 2018-10-18 2018-07-30 2018-12-14 2018-08-27 2018-12-18 2020-08-26 Based Selection in City utional strengthening GZ-ZX01 / Construction dra Component 3: Project Imple Fixed Budget Sele wings (detailed) design for G / mentation support and instit Post Open - National 0.00 Canceled 2018-03-29 2018-04-08 2018-05-13 2018-06-10 2018-06-25 2018-07-30 2018-08-27 2020-08-26 ction aizhou City utional strengthening LN-ZX01 / Project managem Component 3: Project Imple Quality And Cost- Open - Internationa ent consultants service and I IBRD / 88370 mentation support and instit Prior 3,543,309.00 Signed 2018-03-29 2018-04-12 2018-04-08 2018-05-28 2018-05-13 2018-08-22 2018-06-10 2018-09-26 2018-06-25 2018-11-08 2018-07-30 2018-12-18 2018-08-27 2018-12-15 2023-08-26 Based Selection l T contracts supervision utional strengthening GZ-ZX01-2 / Construction dr Component 3: Project Imple Quality And Cost- awings (detailed) design for IBRD / 88370 mentation support and instit Post Open - National 812,289.52 Signed 2018-03-29 2018-04-08 2018-05-10 2018-05-13 2018-08-07 2018-06-10 2018-09-18 2018-06-25 2018-10-18 2018-07-30 2018-12-14 2018-08-27 2018-12-18 2020-08-26 Based Selection Gaizhou Project utional strengthening LN-ZX02 / Consulting Servic e of Non-revenue Water Red uction, Energy Conservation, Component 3: Project Imple Quality And Cost- Open - Internationa and Performance Manageme IBRD / 88370 mentation support and instit Post 881,666.00 Signed 2018-12-25 2019-01-17 2019-01-08 2019-02-21 2019-03-07 2019-03-21 2019-04-12 2019-04-05 2019-04-25 2019-04-19 2019-05-15 2019-05-10 2019-05-28 2023-05-09 Based Selection l nt for the Water Supply Com utional strengthening panies (WSCs) of Shenyang, Anshan, Fushun, Fuxin and G aizhou Cities GZ-ZX02 / Engineering supe Component 3: Project Imple Quality And Cost- Under Implement rvision for civil works in Gaiz IBRD / 88370 mentation support and instit Post Open - National 0.00 2019-04-10 2019-04-29 2019-04-17 2019-05-06 2019-05-15 2019-06-12 2019-06-12 2019-06-19 2019-07-03 2019-07-24 2022-02-23 Based Selection ation hou city utional strengthening Component 3: Project Imple SY-ZX01 / Engineering super Quality And Cost- IBRD / 88370 mentation support and instit Post Open - National 1,542,635.05 Signed 2019-12-23 2020-03-11 2019-12-30 2020-04-16 2020-01-27 2020-05-20 2020-02-24 2020-06-19 2020-03-02 2020-06-29 2020-03-16 2020-07-13 2020-04-06 2020-08-28 2023-04-06 vision for Civil Works Based Selection utional strengthening INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 4