Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan: May 2015; Revision July 2016 2. Date of General Procurement Notice: April 15, 2015 3. Period covered by this procurement plan: The procurement period of project covered from year Dec 2016-Jun 2017 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) US$ 2 million All 2. NCB (Goods) US$ 2 million All 3. ICB (Works) US$ 10 million All 4. NCB (Works) US$ 10 million All 5. (Non-Consultant Services) US$ 2 million All 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Reference to (if any) Project Operational/Procurement Manual: Procurement Manual is being updated in Aug 2017.PCMU will finalize by Aug 15, 2017. 4. Any Other Special Procurement Arrangements: Not Applicable 5. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) The main contract; two works and one consultancy have already been awarded. 1 2 3 4 5 6 7 Description Packages Review Aug 8, 2017 Ref. Estima Dome by Bank Comme No. ted stic (Prior / nts Cost Prefe Post) US$ rence million (yes/ no) Gate 140 ICB No Prior Replaceme nt and Divide Wall Constructio 50 ICB No Prior n of Training Wall III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 1 m 2. Single Source (Firms) Above US $ 1 m Justification alongwith identification of SSS in procurement plan 3. Individual Above US$ 300, 000 In addition the selection of procurement staff 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_500,000_equivalent per contract, may comprise entirely of national consultants in accordance with the OPCS guidance. 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimat Package Review Comment of ed s by Bank s Aug 8, 2017 Assignmen Cost (Prior / t US$ Post) million Constructio 1 Prior Continuat n ion of Supervision signed contract Monitoring 2.6 m 1 Prior and evaluation Services Aug 8, 2017 PROCUREMENT Pakistan : PK-Sindh Barrages Improvement Project PLAN General Information Country: Pakistan 2019-02-15 Bank’s Approval Date of the Original Procurement Plan: 2022-07-27 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P131324 GPN Date: Project Name: PK-Sindh Barrages Improvement Project Loan / Credit No: IDA / 62420 AF of SBIP Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned PK-AFOF SBIP -99622-CW-DI R / Repair of caisson gate an Component A: Rehabilitation 3,745,189.5 2020-04-1 d replacement of the 6 numb IDA / 62420 Post Direct Selection Direct 5,000,000.00 Signed 2019-02-19 2019-02-27 2019-03-01 2019-03-01 2019-04-15 2019-06-25 of the Guddu Barrage 6 3 er gates of the Sukkur Barrag e on emergency basis PK-AFOF SBIP -99629-CW-RF Component B: Improved Bar Request for Quota Single Stage - One E 2019-11-2 Q / Up-gradation of Barrage IDA / 62420 Post Open - National 30,000.00 0.00 Canceled 2019-03-30 2019-05-25 rage Operation tions nvelope 1 Monitoring Unit at Guddu, Su kkur and Kotri PK-AFOF SBIP -98651-CW-RF Component A: Rehabilitation Open - Internationa Single Stage - One E 67,000,000.0 2022-09-0 B / Contract No. SBIP/S1 Rest IDA / 62420 Prior Request for Bids 0.00 Canceled 2019-02-07 2019-09-18 2019-04-25 2019-04-25 2019-02-12 2019-10-04 2019-07-04 2019-08-03 2019-09-07 of the Guddu Barrage l nvelope 0 3 oration and Upgradation of S ukkur Barrage PK-AFOF SBIP -185187-CW-R Component A: Rehabilitation Open - Internationa Single Stage - One E 105,000,000. Under Imple 2025-03-0 FB / Contract No. SBIP/S1: Re IDA / 62420 Prior Request for Bids 0.00 2020-08-06 2020-10-14 2020-10-22 2021-09-23 2020-10-22 2022-02-18 2020-08-11 2020-11-01 2020-12-31 2022-06-07 2021-01-30 2022-07-25 2021-03-06 of the Guddu Barrage l nvelope 00 mentation 1 storation and Up gradation of Sukkur Barrage. PK-AFOF SBIP -98657-CW-RF B / Contract package SBIP/S2 Dredging from pocket and ap Component A: Rehabilitation Open - Internationa Single Stage - One E 16,500,000.0 Pending Imp 2023-01-1 IDA / 62420 Prior Request for Bids 0.00 2020-09-22 2020-09-27 2020-11-08 2020-12-08 2021-01-12 proach and tail channels & E of the Guddu Barrage l nvelope 0 lementation 0 xcavation from pocket and a pproach and tail channels of Sukkur Barrage PK-AFOF SBIP -98666-CW-RF Component A: Rehabilitation Open - Internationa Single Stage - One E 13,000,000.0 Pending Imp 2023-02-0 B / Contract No. SBIP/S4 IDA / 62420 Prior Request for Bids 0.00 2020-10-15 2020-10-20 2020-12-01 2020-12-31 2021-02-04 of the Guddu Barrage l nvelope 0 lementation 2 Canal Desiliting PK-AFOF SBIP -146691-CW-R Component D: River basin w Single Stage - One E Pending Imp 2022-12-3 FB / Restoration of Fish Hatch IDA / 62420 ater resources and riverine Post Request for Bids Open - National 645,000.00 0.00 2021-01-15 2021-01-30 2021-03-13 2021-04-12 2021-05-17 nvelope lementation 0 ery at Sukkur management Request for Quota PK-AFOF SBIP -278232-CW-R Component E: Project mana Request for Quota Single Stage - One E Pending Imp 2022-06-1 IDA / 62420 Post Limited tions (Non Bank-S 15,000.00 0.00 2022-03-06 2022-05-01 FQ / Renovation of PCMU offi gement, Monitoring and Eval tions nvelope lementation 5 PD) ce uation PK-AFOF SBIP -298176-CW-R Request for Quota Component B: Improved Bar Request for Quota Single Stage - One E Pending Imp 2023-01-2 FQ / Construction of Model of IDA / 62420 Post Limited tions (Non Bank-S 20,000.00 0.00 2022-06-07 2022-07-24 rage Operation tions nvelope lementation 0 Long Crest Weir PD) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-AFOF SBIP -112061-GO-R FQ / 03 numbers trucks inclu Component B: Improved Bar Request for Quota Single Stage - One E IDA / 62420 Post Limited 70,000.00 57,021.67 Signed 2019-05-18 2020-01-03 2019-07-13 2020-01-27 2019-09-11 ding boat trailer (Optional) f rage Operation tions nvelope or Barrage monitoring Unit to transport of Boats PK-AFOF SBIP -112071-GO-R Component E: Project mana FQ / IT equipment (Computer Request for Quota Single Stage - One E IDA / 62420 gement, Monitoring and Eval Post Limited 40,000.00 33,302.43 Signed 2019-05-15 2019-05-31 2019-07-10 2019-11-04 2019-08-09 /Laptop, software, printers wi tions nvelope uation th accessories, Photocopier a nd Cameras etc. PK-AFOF SBIP -112059-GO-R Component B: Improved Bar Request for Quota Single Stage - One E FQ / 03 Numbers Boats to me IDA / 62420 Post Limited 90,000.00 22,159.40 Signed 2019-06-29 2019-09-20 2019-08-24 2019-12-17 2019-11-22 rage Operation tions nvelope asure discharge in canals PK-AFOF SBIP -98663-GO-RF B / Contract No. SBIP/S3 Component A: Rehabilitation Open - Internationa Single Stage - One E Pending Impl IDA / 62420 Post Request for Bids 1,050,000.00 0.00 2020-09-15 2020-09-20 2020-11-01 2020-12-01 2021-01-05 2021-07-04 Procurement of Dredger and of the Guddu Barrage l nvelope ementation performance demonstration PK-AFOF SBIP -112062-GO-R Component B: Improved Bar Request for Quota Single Stage - One E Pending Impl FQ / Flow measurement/Surv IDA / 62420 Post Limited 20,000.00 0.00 2020-09-27 2020-11-22 2021-01-21 rage Operation tions nvelope ementation ey equipment for Barrage M onitoring Unit PK-AFOF SBIP -224427-GO-R Component E: Project mana FQ / Procurement of IT Equip Request for Quota Single Stage - One E IDA / 62420 gement, Monitoring and Eval Post Limited 10,000.00 9,088.99 Signed 2021-04-04 2021-07-20 2021-05-30 2021-09-14 2021-11-26 ment for Project Coordination tions nvelope uation & Monitoring Unit SBIP PK-AFOF SBIP -278229-GO-R Component E: Project mana Request for Quota Single Stage - One E Pending Impl FQ / Procurement of Electroni IDA / 62420 gement, Monitoring and Eval Post Limited 30,000.00 0.00 2022-03-06 2022-04-05 2022-04-25 tions nvelope ementation c Goods for PMO & PCMU offi uation ce. PK-AFOF SBIP -296323-GO-R Component B: Improved Bar Request for Quota Single Stage - One E Pending Impl FQ / Supply of 150 KVA Diese IDA / 62420 Post Limited 30,000.00 0.00 2022-06-02 2022-06-28 2022-08-12 rage Operation tions nvelope ementation l Generator and 15 hp Pump with Motor PK-AFOF SBIP -297917-GO-R Component B: Improved Bar Request for Quota Single Stage - One E Pending Impl FQ / Supply of Acoustic Doppl IDA / 62420 Post Limited 50,000.00 0.00 2022-06-17 2022-08-12 2023-02-08 rage Operation tions nvelope ementation er Current Profiler (ADCP) NON CONSULTING SERVICES Page 1 Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-AFOF SBIP -99625-CS-QC BS / Construction Supervision Component A: Rehabilitation Quality And Cost- Open - Internationa IDA / 62420 Prior 4,000,000.00 5,741,138.12 Signed 2019-03-04 2019-03-21 2019-03-25 2019-10-04 2019-05-08 2020-04-13 2019-06-05 2020-08-11 2019-07-05 2021-04-15 2019-08-09 2021-07-13 2019-09-13 2021-09-02 2022-03-11 consultants for Rehabilitation of the Guddu Barrage Based Selection l and Modernization of Sukkur Barrage Works. PK-AFOF SBIP -145949-CS-C Component C: Project Mana QS / Consultancy Services for Quality Based Sel Open - Internationa Under Implement IDA / 62420 gement, Monitoring, and Eva Prior 1,250,000.00 0.00 2019-12-20 2020-02-06 2020-01-10 2020-07-21 2020-02-23 2020-03-22 2020-04-21 2020-05-21 2020-06-25 2020-12-22 Physical Hydraulic and hydrol ection l ation luation ogical model of Sukkur Barra ge for Furture Studies' PK-AFOF SBIP -145958-CS-C QS / Third Party Consultant Fi Component A: Rehabilitation Consultant Qualifi Under Implement rm to Prepare Site Specific E IDA / 62420 Post Open - National 155,000.00 0.00 2019-12-20 2020-01-06 2020-01-10 2020-01-21 2020-02-23 2020-03-24 2020-04-28 2022-04-26 of the Guddu Barrage cation Selection ation nvironmental and Social Man agement Plan (ESMP) Right B ank Canals of Sukkur Barrage PK-AFOF SBIP -185186-CS-Q Component A: Rehabilitation Quality And Cost- Open - Internationa Pending Impleme CBS / Consultancy Services f IDA / 62420 Prior 2,500,000.00 0.00 2020-10-07 2020-10-28 2020-12-11 2021-01-08 2021-02-07 2021-03-14 2021-04-18 2023-04-16 of the Guddu Barrage Based Selection l ntation or Feasibility Study of Kotri B arrage PK-AFOF SBIP -278299-CS-C Component E: Project mana Consultant Qualifi Pending Impleme QS / Procurement of Internal IDA / 62420 gement, Monitoring and Eval Post Open - National 30,000.00 0.00 2022-02-21 2022-03-14 2022-04-27 2022-05-09 2022-05-30 2022-11-26 cation Selection ntation Auditor Firm for Guddu Barra uation ge Project INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-AFOF SBIP -101733-CS-C DS / Consulting Services for Component A: Rehabilitation Design and Construction Sup IDA / 62420 Post Direct Selection Direct 450,000.00 718,498.15 Signed 2019-02-22 2019-01-28 2019-03-04 2019-01-28 2019-05-08 2019-04-01 2020-05-06 of the Guddu Barrage ervision for Emergency repla cement of Sukkur Barrage Ga tes PK-AFOF SBIP -104268-CS-IN Component C: Project Mana Individual Consult DV / Kotri Barrage Safety Ass IDA / 62420 gement, Monitoring, and Eva Post Limited 10,000.00 8,519.70 Signed 2019-03-08 2019-03-13 2019-03-14 2019-04-03 2019-03-29 2019-05-08 2019-04-01 2019-07-07 ant Selection essment Consultants (Civil) T luation eam Leader PK-AFOF SBIP -104270-CS-IN Component C: Project Mana Individual Consult DV / Kotri Barrage Safety Ass IDA / 62420 gement, Monitoring, and Eva Post Limited 10,000.00 8,519.70 Signed 2019-03-08 2019-03-12 2019-03-13 2019-03-14 2019-04-03 2019-03-29 2019-05-08 2019-04-01 2019-07-07 ant Selection essment Consultants (Mecha luation nical) PK-AFOF SBIP -129060-CS-IN DV / Procurement of Individu Component E: Project mana al Consultant (LEGAL ADVISO Individual Consult IDA / 62420 gement, Monitoring and Eval Post Limited 41,500.00 34,866.83 Signed 2019-08-26 2019-08-27 2019-08-27 2019-08-28 2019-09-09 2019-12-17 2019-09-16 2019-12-24 2020-08-31 2020-12-31 R) ant Selection uation (Project Management Office- PMO, Sindh Barrages Improv ement Project-SBIP) PK-AFOF SBIP -145939-CS-IN Component A: Rehabilitation Individual Consult IDA / 62420 Post Limited 80,000.00 20,410.30 Terminated 2019-11-25 2019-12-13 2019-12-15 2019-12-13 2020-01-05 2019-12-20 2020-02-09 2019-12-24 2022-02-06 DV / Contract Management S of the Guddu Barrage ant Selection pecialist PK-AFOF SBIP -145940-CS-IN Component A: Rehabilitation Individual Consult Under Implement DV / Senior Environmental an IDA / 62420 Post Limited 10,000.00 0.00 2019-11-29 2020-01-06 2019-12-19 2020-01-07 2020-01-09 2020-02-13 2021-02-11 of the Guddu Barrage ant Selection ation d Ecological Advisor PK-AFOF SBIP -145942-CS-C DS / Independent Consultant for Engineering Panel of Expe Component A: Rehabilitation rt as per World Bank (OP 4.3 IDA / 62420 Post Direct Selection Direct 70,000.00 55,500.00 Signed 2020-01-01 2020-02-25 2020-02-10 2020-02-28 2020-04-15 2020-03-15 2022-04-13 of the Guddu Barrage 7 Safety of Dams) for Rehabi litation of Sukkur Barrage Pro ject Mechanical Engineer/Team L eader PK-AFOF SBIP -150856-CS-IN Component E: Project mana DV / Procurement of consulti Individual Consult IDA / 62420 gement, Monitoring and Eval Post Limited 18,000.00 14,054.56 Signed 2019-12-22 2020-01-06 2019-12-27 2021-05-27 2020-01-17 2021-06-24 2020-02-21 2021-07-16 2020-08-19 ng services (Individual Consu ant Selection uation ltant) Social Safeguard Speci alist PMO-SBIP PK-AFOF SBIP -152688-CS-IN Component E: Project mana Individual Consult IDA / 62420 Post Limited 10,000.00 23,630.68 Signed 2020-01-06 2020-01-09 2020-01-08 2020-01-13 2020-01-29 2020-01-23 2020-01-31 2020-01-28 2021-01-30 DV / Media Communication S gement, Monitoring and Eval ant Selection pecialist uation PK-AFOF SBIP -169021-CS-IN DV / Independent Consultant for Engineering Panel of Expe Component A: Rehabilitation Individual Consult Under Implement rt as per World Bank (OP 4.3 IDA / 62420 Post Direct 50,000.00 0.00 2020-04-20 2020-07-21 2020-04-30 2020-12-28 2020-05-21 2021-02-08 2020-06-25 2021-06-24 of the Guddu Barrage ant Selection ation 7 Safety of Dams) for Rehabil itation of Sukkur Barrage Proj ect, Hydrologist/Sediment S pecialist (member PoE) PK-AFOF SBIP -145943-CS-C DS / Independent Consultant for Engineering Panel of Expe rt (PoE) as per World Bank ( Component A: Rehabilitation Pending Impleme IDA / 62420 Post Direct Selection Direct 20,000.00 0.00 2021-01-01 2021-02-10 2021-04-16 2023-04-14 OP 4.37 Safety of Dams) for of the Guddu Barrage ntation Rehabilitation of Sukkur Barr age Project Hydraulic Design Specialist/T eam Member PK-AFOF SBIP -188965-CS-C Component E: Project mana Individual Consult Pending Impleme IDA / 62420 Post Limited 30,000.00 0.00 2020-09-23 2020-09-24 2020-09-25 2020-09-28 2022-08-30 DS / Environmental Safeguar gement, Monitoring and Eval ant Selection ntation d Specialist uation PK-AFOF SBIP -191103-CS-IN Component E: Project mana Individual Consult Pending Impleme IDA / 62420 Post Open 100,000.00 0.00 2020-09-07 2020-10-26 2020-11-16 2020-12-21 2024-12-30 DV / Manager Finance Specia gement, Monitoring and Eval ant Selection ntation list uation Page 2 PK-AFOF SBIP -224419-CS-IN DV / Procurement of consulti Component D: River basin w ng services (Individual Consu Individual Consult IDA / 62420 ater resources and riverine Post Limited 40,000.00 36,000.00 Signed 2021-03-12 2021-03-18 2021-03-17 2021-03-22 2021-03-18 2021-04-19 2021-03-25 2021-04-01 2021-12-30 ltant) Environmental Safegua ant Selection management rd Specialist for preparation of ES Safegua rds instruments for SWAT pre paration PK-AFOF SBIP -224422-CS-IN DV / Procurement of consulti ng services (Individual Consu ltant) Social Safeguard Speci Component D: River basin w Individual Consult alist I for preparation of Rese IDA / 62420 ater resources and riverine Post Limited 20,000.00 17,198.06 Signed 2021-03-12 2021-03-18 2021-03-17 2021-03-22 2021-03-19 2021-04-26 2021-03-24 2021-04-01 2021-12-30 ant Selection ttlement Policy Framework & management Gender Action Plan for SWAT & review and update of reset tlement action plan RAP of A kram Wah Canal. PK-AFOF SBIP -224423-CS-IN DV / Procurement of consulti Component D: River basin w ng services (Individual Consu Individual Consult IDA / 62420 ater resources and riverine Post Limited 20,000.00 13,526.56 Signed 2021-03-12 2021-03-18 2021-03-15 2021-03-22 2021-03-17 2021-04-19 2021-03-26 2021-04-20 2021-12-30 ltant) Social Specialist II to pr ant Selection management epare an Environmental and Social Management Framewo rk (ESMF) and RAP for SWAT. PK-AFOF SBIP -224424-CS-IN Component E: Project mana DV / Procurement of consulti Individual Consult Under Implement IDA / 62420 gement, Monitoring and Eval Post Open 20,000.00 0.00 2021-03-25 2021-06-18 2021-05-13 2021-06-03 2021-06-18 2022-05-30 ng services (Individual Consu ant Selection ation uation ltant) M&E Specialist for PMO SBIP PK-AFOF SBIP -224672-CS-IN Component E: Project mana Individual Consult Under Implement DV / Individual consultant to IDA / 62420 gement, Monitoring and Eval Post Limited 10,000.00 0.00 2021-03-25 2021-07-29 2021-04-04 2021-04-25 2021-05-30 2022-05-29 ant Selection ation Work on Fish Migration uation PK-AFOF SBIP -224673-CS-IN Component E: Project mana Individual Consult Under Implement DV / Individual Consultant Ex IDA / 62420 gement, Monitoring and Eval Post Limited 10,000.00 0.00 2021-03-25 2021-07-29 2021-04-04 2021-04-25 2021-05-30 2022-05-29 ant Selection ation pert on Environmental Flow uation PK-AFOF SBIP -224674-CS-IN Component E: Project mana Individual Consult Pending Impleme DV / Individual Consultant Ex IDA / 62420 gement, Monitoring and Eval Post Limited 10,000.00 0.00 2021-03-25 2021-04-04 2021-04-25 2021-05-30 2022-05-29 ant Selection ntation pert on Capacity Building uation PK-AFOF SBIP -238446-CS-IN DV / Services of an Individua l Consultant Irrigation / Hydra Component C: Project Mana Individual Consult ulic Specialist PCMU is requir IDA / 62420 gement, Monitoring, and Eva Post Limited 12,500.00 12,500.00 Signed 2021-06-07 2021-06-03 2021-06-08 2021-06-23 2021-06-13 2021-06-25 2021-06-15 2021-07-01 2021-10-30 ant Selection ed, who will work as a two-m luation ember team for preparing an d finalizing the Planning Com mission Proforma - 1 (PC-I) fo r SWAT. PK-AFOF SBIP -238448-CS-IN Component C: Project Mana DV / Procurement of Individu Individual Consult IDA / 62420 gement, Monitoring, and Eva Post Limited 12,500.00 23,625.28 Signed 2021-06-08 2021-06-03 2021-06-14 2021-06-23 2021-06-15 2021-06-25 2021-06-18 2021-07-01 2021-10-30 al Consultant Agriculture Eco ant Selection luation nomist PCMU for preparation of PC-1 of SWAT. PK-AFOF SBIP -240789-CS-IN DV / Procurement of individu al consultant Capacity Devel opment Expert to help PMO i Component B: Improved Bar Individual Consult Pending Impleme IDA / 62420 Post Limited 18,000.00 0.00 2021-07-05 2021-08-23 2021-09-13 2021-10-18 2022-08-30 n management and develop rage Operation ant Selection ntation ment of organizational plan t o build capacity of the staff i n various fields for one year duration and extendable. PK-AFOF SBIP -278222-CS-IN Component E: Project mana DV / Procurement of Individu Individual Consult Under Implement IDA / 62420 gement, Monitoring and Eval Post Limited 15,000.00 15,000.00 2022-02-09 2022-02-10 2022-02-11 2022-02-22 2022-02-19 2022-02-24 2022-02-22 2022-12-13 al Consultant Services, Envir ant Selection ation uation onmental Specialist for PCMU PK-AFOF SBIP -278228-CS-IN Component E: Project mana DV / Procurement of Individu Individual Consult Pending Impleme IDA / 62420 gement, Monitoring and Eval Post Limited 75,000.00 0.00 2022-02-14 2022-02-19 2022-03-12 2022-04-16 2024-02-28 al Consultant Services, Contr ant Selection ntation uation act Management Specialist fo r PMO SBIP PK-AFOF SBIP -278308-CS-C DS / Hiring of UN-FAO team u nder SBIP as Project Manage Component E: Project mana Pending Impleme ment Consultants. IDA / 62420 gement, Monitoring and Eval Post Direct Selection Direct 140,000.00 0.00 2022-02-10 2022-02-14 2022-02-17 2022-03-31 ntation Justification of Amendment V uation & VI of PMC UN-FAO Contract is given in comments section . PK-AFOF SBIP -278314-CS-C DS / Contracting UN-FAO tea Component E: Project mana Pending Impleme m under a new 18 months co IDA / 62420 gement, Monitoring and Eval Prior Direct Selection Direct 1,200,000.00 0.00 2022-02-10 2022-02-20 2022-03-28 2023-09-30 ntation ntract as Project Managemen uation t Consultants for AF SBIP. Page 3