Annex 4 PROCUREMENT PLAN General 1. Project Information: Nigeria: Transforming Irrigation Management in Nigeria 2. Bank’s approval Date of the Procurement Plan: May 2014 3. Period covered by this procurement plan: 18 months II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement Method Prior Threshold Review Procurement Method US$ Threshold ICB (Goods and Non- Equal to and above 1. consulting services) 5,000,000 All Equal to or NCB (Goods and Non- above US$ 2. Consulting Services) Below 5,000,000 1,000,000 Equal to or above 3 ICB (Works) 20,000,000 All Equal to or above 4. NCB (Works) Below 20,000,000 10,000,000 Below US$ Shopping (Goods) 100,000 None Shopping (Vehicles) - Below US$ From 1st line distributors 500,000 None Below US$ 5. Shopping (Works) 200,000 None 2. Summary of the Procurement Packages planned during the first 18 months after project effectiveness 3. Procurement Packages with Methods 1 2 3 4 5 6 7 Re Description Estimat Procure Domes Revie Comme f. ed ment tic w nts No Cost Method Prefer by . US$ ence Bank million (yes/n (Prior o) / Post) 01 Rehabilitation 115 ICB No Prior of Bakalori Dam and Rehabilitation/I mprovement of Bakalori Irrigation Scheme 02 Rehabilitation 85 ICB No Prior and Improvement of Kano Irrigation Scheme 03 Rehabilitation 60 ICB No Prior and Extension of Hadejia Valley Irrigation Scheme 04 Rehabilitation 40 ICB No Prior of 6 No. Dams 05 Supply and 0.6 NCB No Post Installation of Hydrometric Equipment for Sokoto Rima Basin 06 Flood Plain 1.35 NCB No Prior Mapping for EPP (BIP & MRVIP) 07 Bathymetric 0.20 NCB No Post Survey of Goronyo, Zobe and Bakolori Dams 08 Procurement of 0.3 Shopping No Post Field and Operational Vehicles 09 Procurement of 0.1 Shopping No Post Computers 10 Procurement of 0.1 Shopping No Post Office Equipment III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Method Prior Review Threshold (USD) Threshold (USD) 1. Competitive Methods Equal to or above All (Firms); QCBS, QBS, LCS, 300,000 FCS 2. Consultant Qualification Below 300,000 None 3. Single Source Selection N/A All (Firms & Individuals) 4. Individuals N/A Above 100,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than US$300,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Consultancy Assignments with Selection Methods 1 2 3 4 5 6 Ref. Description of Estimat Selecti Review Comments No. Assignment ed on by Bank Cost Metho (Prior / US$ d Post) Million 01 Engineering 2.7 QCBS Prior Supervision of the Rehabilitation of Bakalori Dam and Irrigation Scheme 02 Technical Assistance 2.0 QCBS Prior for Dam Safety Assurance & Training for Dam & Reservoir Dept. and RBDA Staff 03 Dam Safety Panel of 1.0 IC Prior Series of Experts individual consultant contracts on specific aspects of dam 04 Technical Feasibility 2.0 QCBS Prior and detailed Design of Dadin Kowa Irrigation Scheme 05 Engineering 1.5 QCBS Prior Supervision of Rehabilitation and Extension of Kano Rima Irrigation Scheme 06 Engineering 0.65 QCBS Prior Supervision of Rehabilitation and Extension of Hadejia Valley Irrigation Scheme 07 Elaboration of 1.0 QCBS Prior Resettlement Action Plan for Kano River and Hadejia Valley Irrigation Schemes 08 Technical Assistance 1.5 QCBS Prior for WUA in Bakalori and Middle Rima Valley Irrigation Schemes 09 Technical Assistance 1.0 QCBS Prior for WUA in Kano River and Hadejia Valley Irrigation Schemes. 10 Technical Assistance 4.0 QCBS Prior on Farmers-Market Linkages and for the Establishment of FMCs 11 Support to RBDAs; 1.5 QCBS Prior Assessment, capacity Building and Strategic Planning 12 Development of 1.0 QCBS Prior Information Database and information System 13 Development of an 1.0 QCBS Prior Electronic and Document Management System 14 ESIA for Kano River 0.6 QCBS Prior and Hadejia Valley Irrigation Schemes 15 ESIA for Dadin Kowa 0.5 QCBS Prior Irrigation Scheme 16 ESIA for Middle Rima 0.1 IC Prior Valley Irrigation Scheme 17 Development of M&E 0.06 IC Post Manual 18 Development of 0.06 IC Post Financial Management Manual 19 Applied Research 2.3 N/A Prior Grantees Grant on Irrigated will be Agriculture selected competitivel y on the bases of Call for Research Proposals PROCUREMENT Nigeria : Transforming Irrigation Management in Nigeria PLAN General Information Country: Nigeria 2017-04-05 Bank’s Approval Date of the Original Procurement Plan: 2022-06-27 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P123112 GPN Date: Project Name: Transforming Irrigation Management in Nigeria Loan / Credit No: IDA / 55060 Transforming Irrigation Management In Nigeria Federal Coordinating Office Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned NG-TRIMING NCO-12728-CW Component 1: Water Resour -RFB / River Training Works i Single Stage - One E 4,538,527.0 2020-06-2 IDA / 55060 ces Management and Dam Prior Request for Bids Open - National 5,100,000.00 Signed 2017-02-09 2017-06-05 2017-02-09 2017-05-04 2017-05-04 2017-06-19 2017-10-23 2017-07-31 2018-05-24 n the Hadejia-Jama’are River nvelope 7 9 Operation Improvement. Basin Located in Jigawa State , Nigeria NG-TRIMING NCO-12726-CW Component 1: Water Resour -RFB / Works for Rehabilitatio Open - Internationa Single Stage - One E 125,000,000. 2021-09-0 IDA / 55060 ces Management and Dam Prior Request for Bids 0.00 Canceled 2017-03-23 2017-06-06 2017-03-23 2017-05-18 2017-06-29 2017-07-17 2017-09-13 n and Expansion of Irrigation l nvelope 00 6 Operation Improvement. Scheme in KRIS and HVIS NG-TRIMING NCO-14084-CW Component 2: Irrigation De Open - Internationa Single Stage - One E 79,920,874.0 110,425,88 2021-03-0 -RFB / Works for Rehabilitatio IDA / 55060 velopment and Management Prior Request for Bids Signed 2016-02-01 2016-02-23 2016-05-03 2016-05-03 2016-08-06 2017-05-10 2017-03-29 2017-03-29 l nvelope 0 3.81 8 n and Conversion of Bakolori . Irrigation Scheme NG-TRIMING NCO-19039-CW Component 4: Institutional -RFB / Rehabilitation of 4Nos Single Stage - One E 2016-07-1 IDA / 55060 Development and Project Ma Post Request for Bids Open - National 239,862.00 177,675.51 Signed 2015-11-11 2015-11-11 2015-11-11 2015-12-15 2015-12-09 2016-01-08 2016-02-02 2016-01-18 2017-01-18 Houses for TRIMING field offi nvelope 6 nagement. cers at Bunkure under KRIP i n Kano State FMWR/TRIMING/2018/ICB/W/ Component 1: Water Resour 01 / Dam Safety improvemen Open - Internationa Single Stage - One E 96,000,000.0 2022-02-2 IDA / 55060 ces Management and Dam Prior Request for Bids 0.00 Canceled 2018-06-29 2018-07-27 2018-10-05 2018-11-02 2019-01-25 t works of Bakolori, Zobe and l nvelope 0 5 Operation Improvement. Goronyo dams in two lots FMWR/TRIMING/2018/SH/W/ 01 / Rehabilitation of addition al 3 Nos House for Housing of Component 2: Irrigation De community radio at Hadejia Request for Quota Single Stage - One E 2018-10-1 IDA / 55060 velopment and Management Post Open - National 200,000.00 145,713.04 Completed 2018-03-31 2018-05-04 2018-06-12 Valley Irrigation Scheme, Da tions nvelope 5 . dinkkowa and Goronyo Irrigat ion Schemes and Remodeling of Studio rooms at Bakolori a nd Kano Scheme FMWR/TRIMING/2018/SH/W/ 02 / Upgrading and Securing Component 3: Enhancing Ag of 4nos Agricultural Develop Request for Quota Single Stage - One E 2018-09-1 IDA / 55060 ricultural Productivity and Su Post Open - National 70,000.00 52,052.92 Completed 2018-04-25 2018-05-28 2018-05-16 ment Projects offices allocate tions nvelope 2 pport to Value Chains. d for TRIMING project Farmer s Field and Business School a ctivities FMWR/TRIMING/2018/NCB/W /02 / Construction of Tomato Collection Centers in Kano Ri Component 3: Enhancing Ag Single Stage - One E 2018-11-1 ver Irrigation Scheme to sup IDA / 55060 ricultural Productivity and Su Post Request for Bids Open - National 700,000.00 0.00 Canceled 2018-03-21 2018-03-26 2018-05-02 2018-05-23 2018-07-20 nvelope 7 port tomato farmers in their pport to Value Chains. productive alliances with Dan gote tomato processing com pany and other offtakers in N igeria FMWR/TRIMING/2018/SH/W/ 04 / Additional works at Kano River Irrigation Scheme, Had Component 2: Irrigation De Request for Quota Single Stage - One E 2018-09-2 ejia Valley Irrigation Scheme IDA / 55060 velopment and Management Post Open - National 200,000.00 144,594.80 Completed 2018-03-24 2018-05-03 2018-05-17 tions nvelope 4 and Bakolori Irrigation Schem . e including one block, fence, gate houses, landscaping an d BTC security wire FMWR/TRIMING/2016/ICB/W/ 002 / Rehabilitation & Expans Component 1: Water Resour ion of Kano River Irrigation S Open - Internationa Single Stage - One E 125,000,000. 98,110,626. 2022-04-2 IDA / 55060 ces Management and Dam Prior Request for Bids Signed 2017-03-17 2017-03-23 2017-06-29 2017-06-29 2017-12-18 2018-04-18 2018-05-16 2018-07-06 cheme (KRIS) and Hadejia Va l nvelope 00 64 9 Operation Improvement. lley Irigation Scheme (HVIS) and Dam Safety Remedial W orks in Kano and Hadejia NG-TRIMING NCO-76567-CW -RFQ / Rehabilitation of Adjou rning Structures, Fencing and Component 2: Irrigation De Request for Quota Single Stage - One E 2018-12-1 Landscapping of Farmers Me IDA / 55060 velopment and Management Post Open - National 95,000.00 78,119.81 Completed 2018-09-13 2018-10-17 2018-12-24 tions nvelope 6 eting Hall, and Provisions of . 8 Nos 1,000litres Water Tank s and Distribution to Residen tial Apartments at BIS NG-TRIMING NCO-76571-CW Component 1: Water Resour -RFQ / Emergency repairs of Request for Quota Single Stage - One E 2018-12-1 IDA / 55060 ces Management and Dam Post Open - National 200,000.00 142,581.60 Completed 2018-09-07 2018-10-15 2019-02-14 Goronyo dam Spillway Radial tions nvelope 4 Operation Improvement. Gate and Gantry Cranes (as advised by DPoEs) NG-TRIMING NCO-76533-CW Component 1: Water Resour -RFQ / Emergency repairs of Request for Quota Single Stage - One E 2018-12-1 IDA / 55060 ces Management and Dam Post Open - National 150,000.00 122,802.17 Completed 2018-09-20 2018-10-19 2019-02-14 Goronyo dam Toe Drain Pum tions nvelope 8 Operation Improvement. p House and Pumps (as stron gly advised by DPoE) NG-TRIMING NCO-76528-CW -RFQ / Emergency Rehabilitat Component 2: Irrigation De Request for Quota Single Stage - One E Pending Imp 2018-12-1 ion of 3No. 3-Bedroom Hous IDA / 55060 velopment and Management Post Open - National 200,000.00 0.00 2018-09-07 2018-10-11 tions nvelope lementation 0 es and Construction of Secur . ing Fencing at Service Cente r No. 1 for the Army NG-TRIMING NCO-76583-CW -RFQ / Emergency Rehabilitat Component 2: Irrigation De ion of 3No. Junior Officers qu Request for Quota Single Stage - One E 2018-12-1 IDA / 55060 velopment and Management Post Open - National 150,000.00 109,721.89 Completed 2018-09-25 2018-11-04 2019-02-14 arters at Yarkofoji and Constr tions nvelope 9 . uction of Securing Fencing a t Service Center No. 1 for sec urity personnel. Page 1 FMWR/TRIMING/2019/ICB/W/ Component 2: Irrigation De 01 / Rehabilitation and expan Single Stage - One E 50,000,000.0 29,235,668. 2020-11-0 IDA / 55060 velopment and Management Prior Request for Bids Open - National Terminated 2019-04-25 2019-03-21 2019-04-30 2019-04-01 2019-06-11 2019-06-11 2019-07-11 2019-10-31 2019-08-22 2020-01-07 sion of Dadinkowa Irrigation nvelope 0 09 5 . Scheme (Quick Wins of 2000 ha) in Gombe State FMWR/TRIMING/2019/ICB/W/ Component 2: Irrigation De 02 / Additional construction Open - Internationa Single Stage - One E 20,000,000.0 2021-09-2 IDA / 55060 velopment and Management Prior Request for Bids 0.00 Canceled 2019-05-23 2019-06-06 2019-07-18 2019-08-17 2019-09-28 works of 1000ha at Bakolori I l nvelope 0 7 . rrigation Scheme(BIS) and 40 0ha at Jakaranwa FMWR/TRIMING/2019/RFQ/W Component 4: Institutional /01 / Fencing, lanscaping and Request for Quota Single Stage - One E Under Imple 2018-07-0 IDA / 55060 Development and Project Ma Post Open - National 150,000.00 0.00 2018-02-25 2018-04-04 securing of schemes radio ho tions nvelope mentation 3 nagement. uses and equipment at MRVI S, DKIS, KRIS and HVIS FMWR/TRIMING/2019/ICB/W/ Component 1: Water Resour Open - Internationa Single Stage - One E 45,000,000.0 2024-05-3 03 / Rehabilitation and Impro IDA / 55060 ces Management and Dam Prior Request for Bids 0.00 Canceled 2019-03-20 2019-04-03 2019-05-15 2019-06-14 2019-07-22 l nvelope 0 0 vement works for Bakolori an Operation Improvement. d Zobe dams FMWR/TRIMING/2019/ICB/W/ Component 1: Water Resour 04 / Rehabilitation and Impro Open - Internationa Single Stage - One E 35,000,000.0 2024-06-2 IDA / 55060 ces Management and Dam Prior Request for Bids 0.00 Canceled 2019-03-20 2019-04-03 2019-05-15 2019-06-14 2019-07-26 vement works for Goronyo a l nvelope 0 0 Operation Improvement. nd River Training at MRVIS FMWR/TRIMING/2019/NCB/W /01 / Removal of Typa grasse Component 1: Water Resour s and acquatic weeds for rest Open - Internationa Single Stage - One E 2022-08-0 IDA / 55060 ces Management and Dam Prior Request for Bids 3,000,000.00 0.00 Canceled 2019-04-20 2019-05-04 2019-06-15 2019-07-06 2019-08-13 oration of Ruwan Kanyan Res l nvelope 9 Operation Improvement. ervoir and the Hadejia Barrag e for optima performance un der Dam Safety Improvemen t FMWR/TRIMING/2019/RFQ/W Component 2: Irrigation De /02 / Rehabilitation of 6 nos. Request for Quota Single Stage - One E 2019-09-0 IDA / 55060 velopment and Management Post Limited 120,000.00 97,659.56 Completed 2019-04-15 2019-04-15 2019-05-20 2019-07-17 Project Managers Offices of T tions nvelope 9 . RIMING intervention Scheme s NG-TRIMING NCO-133311-C W-RFQ / Additional rehabilitat Component 2: Irrigation De ion and reconstruction of offi Request for Quota Single Stage - One E 2019-12-1 IDA / 55060 velopment and Management Post Limited 100,000.00 83,426.25 Completed 2019-09-30 2019-09-16 2019-11-04 2019-10-15 ce/residential block, fencing tions nvelope 6 . and landscaping at DKIS Colo ny and other works at Bakolo ri Community radio FMWR/TRIMING/2019/NCB/W /02/01 / Rehabilitation and I Component 1: Water Resour Single Stage - One E 17,000,000.0 12,686,633. 2022-03-1 mprovement Works for Bakol IDA / 55060 ces Management and Dam Prior Request for Bids Open - National Signed 2019-10-31 2020-03-30 2019-11-07 2020-06-09 2019-12-19 2020-07-22 2020-01-30 2021-06-09 2020-03-12 2021-09-09 nvelope 0 39 2 ori and Zobe Dams in Zamfar Operation Improvement. a and Katsina States, Nigeria FMWR/TRIMING/2019/NCB/W Component 1: Water Resour /03/01 / Rehabilitation and I Single Stage - One E 15,000,000.0 25,824,410. 2022-03-1 IDA / 55060 ces Management and Dam Prior Request for Bids Open - National Signed 2019-10-31 2020-09-08 2019-11-07 2020-09-16 2019-12-19 2020-11-02 2020-01-30 2021-05-21 2020-03-19 2021-08-05 mprovement works for Goron nvelope 0 42 9 Operation Improvement. yo and River Training at MRV IS FMWR/TRIMING/2020/NCB/W /03 / Procurement of Works f Component 2: Irrigation De Single Stage - One E 3,543,240.8 2022-02-2 or Construction and Rehabilit IDA / 55060 velopment and Management Prior Request for Bids Open - National 6,000,000.00 Signed 2020-04-30 2020-07-06 2020-05-14 2020-07-27 2020-06-25 2020-08-25 2020-07-25 2021-03-18 2020-09-05 2021-05-07 nvelope 6 7 ation of Roads in Hadejia Vall . ey Irrigation Scheme (HVIS) FMWR/TRIMING/2020/RFQ/W /010 / Upgrading and Demarc Component 4: Institutional Request for Quota Single Stage - One E 2020-10-2 ation of Officers Cubicles in T IDA / 55060 Development and Project Ma Post Limited 100,000.00 85,491.90 Signed 2020-06-04 2020-11-02 2020-07-23 2020-11-27 tions nvelope 1 RIMING Kano offices and prov nagement. ision of AC'S for TRIMING Abu ja and Kano offices. FMWR/TRIMING/2020/RFQ/W /04 / Furnishing for Additional Security Personnel Residence Component 2: Irrigation De s at Service Centre 1, Recons Request for Quota Single Stage - One E 2021-01-1 IDA / 55060 velopment and Management Post Limited 200,000.00 174,317.09 Completed 2020-06-04 2020-06-15 2020-07-16 2020-07-29 truction and Wire Fencing of tions nvelope 2 . Site Project Manager with tw o other Assistant Managers R esidences in Bakolori Irrigati on Scheme, Zamfara State. FMWR/TRIMING/2020/RFQ/W /05 / Provision of Borehole / r Component 2: Irrigation De eticulation and Solar System Request for Quota Single Stage - One E 2020-11-2 IDA / 55060 velopment and Management Post Limited 150,000.00 129,989.86 Completed 2020-06-20 2020-06-15 2020-08-01 2020-07-29 for remaining Security Perso tions nvelope 9 . nnel Residences at Bakolori I rrigation Scheme, Zamfara St ate. FMWR/TRIMING/2020/RFQ/W /011 / Rehabilitation and furn ishing of Scheme Level Staff Component 2: Irrigation De Request for Quota Single Stage - One E 2021-03-0 Offices, WUA Meeting Hall in IDA / 55060 velopment and Management Post Limited 200,000.00 174,655.33 Completed 2020-07-25 2020-06-15 2020-09-05 2020-07-29 tions nvelope 4 Kano River Irrigation Scheme . and Connection of Site office to National Grid at Kura in Ka no State FMWR/TRIMING/2020/RFQ/W /03 / Rehabilitation and furnis Component 2: Irrigation De Request for Quota Single Stage - One E 2021-01-1 hing of Water Users Associati IDA / 55060 velopment and Management Post Limited 100,000.00 90,937.57 Completed 2020-06-04 2020-05-04 2020-07-16 2020-06-29 tions nvelope 2 on meeting Hall and offices i . n Hadejia Valley Irrigation Sc heme (HVIS) in Jigawa State. FMWR/TRIMING/2020/NCB/W /01 / Procurement of Works f or Construction of Farmers M Component 3: Enhancing Ag Single Stage - One E 5,912,453.7 2021-10-3 anagement Center in Bakolor IDA / 55060 ricultural Productivity and Su Prior Request for Bids Open - National 6,400,000.00 Signed 2020-09-20 2020-10-26 2020-09-27 2020-10-26 2020-10-25 2020-11-25 2020-12-06 2021-06-07 2021-02-02 2021-08-13 nvelope 1 0 i, Kano, Hadejia Valley and M pport to Value Chains. iddle Rima Valley Irrigation S chemes in Zamfara, Kano, Jig awa and Sokoto States, Niger ia FMWR/TRIMING/2020/RFQ/C W/07 / Protection of 36Nos In Component 1: Water Resour Request for Quota Single Stage - One E 2021-02-2 stalled hydrolaugical stations IDA / 55060 ces Management and Dam Post Limited 200,000.00 86,718.69 Completed 2020-12-08 2020-11-02 2020-12-29 2020-11-30 tions nvelope 7 equipments at SRRBDA and P Operation Improvement. rovision of dedicated internet Page 2 FMWR/TRIMING/2021/RFQ/W /01 / Rehabilitation and upgr Component 2: Irrigation De Request for Quota ading of Project Manager and Request for Quota Single Stage - One E 2022-01-2 IDA / 55060 velopment and Management Post Open - National tions (Non Bank-S 200,000.00 0.00 Canceled 2021-09-25 2021-10-30 4 other APMS Residences at tions nvelope 8 . PD) Hadejia Valley Irrigation Sche me (HVIS), Hadejia, Jigawa St ate FMWR/TRIMING/2021/RFQ/W /02 / Rehabilitation and upgr Component 2: Irrigation De Request for Quota Request for Quota Single Stage - One E 2022-01-0 ading of 2 Project Managers IDA / 55060 velopment and Management Post Open - National tions (Non Bank-S 200,000.00 0.00 Canceled 2021-09-05 2021-10-10 tions nvelope 8 Residences at KRIS West and . PD) East with 4 other APMS, Kano State FMWR/TRIMING/2021/RFQ/W /03 / Rehabilitation of MIS offi Component 2: Irrigation De Request for Quota Request for Quota Single Stage - One E 2021-12-2 ce and provision of additional IDA / 55060 velopment and Management Post Open - National tions (Non Bank-S 100,000.00 0.00 Canceled 2021-09-19 2021-10-24 tions nvelope 3 ICT Equipment at Upper Ben . PD) ue River Basin Development Authority (UBRBDA) Yola FMWR/TRIMING/2021/RFQ/W /04 / Protection of Groundwat Component 1: Water Resour Request for Quota Request for Quota Single Stage - One E 2022-01-0 er Monitoring and Hydrologic IDA / 55060 ces Management and Dam Post Open - National tions (Non Bank-S 100,000.00 0.00 Canceled 2021-09-27 2021-11-08 tions nvelope 7 al Observation Stations in th Operation Improvement. PD) e intervention River Basins. FMWR/TRIMING/2021/RFQ/W /05 / Rehabilitation, Upgradin Component 1: Water Resour Request for Quota Request for Quota Single Stage - One E 2022-01-2 g and Securing of Hydromet r IDA / 55060 ces Management and Dam Post Open - National tions (Non Bank-S 200,000.00 0.00 Canceled 2021-09-25 2021-10-30 tions nvelope 8 eceiver stations in Hadejia Ja Operation Improvement. PD) ma'are, Sokoto Rima River B asins and UBRBDA FMWR/TRIMING/2021/RFQ/W /06 / Rehabilitation and furnis Component 2: Irrigation De Request for Quota hing of WUA Meeting Hall wit Request for Quota Single Stage - One E 2022-01-3 IDA / 55060 velopment and Management Post Open - National tions (Non Bank-S 200,000.00 0.00 Canceled 2021-09-28 2021-11-02 h Adjoining offices / area ma tions nvelope 1 . PD) nager and 2 other project ma nager residencies in DKIS, Go mbe State FMWR/TRIMING/2021/RFQ/W /07 / Emergency Constructio n of Watch Towers and Provis Component 2: Irrigation De Request for Quota Request for Quota Single Stage - One E 2021-11-1 ion of Equipment for Improve IDA / 55060 velopment and Management Post Open - National tions (Non Bank-S 100,000.00 0.00 Canceled 2021-09-04 2021-10-05 tions nvelope 9 ment of Security at the Middl . PD) e Rima Valley Irrigation Sche me (MRVIS), Goronyo, Sokoto State FMWR/TRIMING/2021/RFQ/W /08 / Emergency Constructio n of Watch Towers and Provis Component 2: Irrigation De Request for Quota Request for Quota Single Stage - One E 2021-11-2 ion of Equipment for Improve IDA / 55060 velopment and Management Post Limited tions (Non Bank-S 200,000.00 184,425.90 Signed 2021-09-15 2021-08-17 2021-10-14 2021-09-27 tions nvelope 8 ment of Security at the Bakol . PD) ori Irrigation Scheme (BIS), T alata-Marafa, Zamfara, Sokot o State FMWR/TRIMING/2021/NCB/W 01 / Procurement of works fo r Construction of 200Hectare Request for Bids - s of Surface Irrigation System Component 2: Irrigation De Open - Internationa Single Stage - One E Works (without pr 29,000,000.0 Pending Imp 2024-01-2 , Eight (8Nos) Buildings for A IDA / 55060 velopment and Management Prior Request for Bids 0.00 2021-09-20 2021-10-04 2021-11-15 2021-12-15 2022-01-26 l nvelope equalification) SP 0 lementation 6 gric Business Centers (ABC) . D and fisheries Production and Processing Facilities as livelih ood support options for Janka rawa community in Zamfara FMWR/TRIMING/2021/RFQ/W /01/01 / Rehabilitation and u Component 2: Irrigation De Request for Quota pgrading of Project Manager Request for Quota Single Stage - One E 2022-01-2 IDA / 55060 velopment and Management Post Limited tions (Non Bank-S 200,000.00 183,905.70 Signed 2021-09-25 2021-08-16 2021-10-24 2021-09-27 and 4 other APMS Residence tions nvelope 2 . PD) s at Hadejia Valley Irrigation Scheme (HVIS), Hadejia, Jiga wa State FMWR/TRIMING/2021/RFQ/W /02/01 / Rehabilitation and u Component 2: Irrigation De Request for Quota Request for Quota Single Stage - One E 2022-01-2 pgrading of 2 Project Manage IDA / 55060 velopment and Management Post Limited tions (Non Bank-S 200,000.00 184,417.52 Signed 2021-09-22 2021-08-16 2021-10-23 2021-09-27 tions nvelope 1 rs Residences at KRIS West a . PD) nd East with 4 other APMS, K ano State FMWR/TRIMING/2021/RFQ/W /03/01 / Rehabilitation of MIS Component 2: Irrigation De Request for Quota Request for Quota Single Stage - One E Pending Imp 2021-12-2 office and provision of additi IDA / 55060 velopment and Management Post Limited tions (Non Bank-S 100,000.00 0.00 2021-09-22 2021-10-21 tions nvelope lementation 0 onal ICT Equipment at Upper . PD) Benue River Basin Developm ent Authority (UBRBDA) Yola FMWR/TRIMING/2021/RFQ/W /04/01 / Protection of Ground Component 1: Water Resour Request for Quota Request for Quota Single Stage - One E Pending Imp 2021-12-2 water Monitoring and Hydrol IDA / 55060 ces Management and Dam Post Limited tions (Non Bank-S 100,000.00 0.00 2021-10-01 2021-10-30 tions nvelope lementation 9 ogical Observation Stations i Operation Improvement. PD) n the intervention River Basi ns. FMWR/TRIMING/2021/RFQ/W /05/01 / Rehabilitation, Upgra Component 1: Water Resour Request for Quota Request for Quota Single Stage - One E 2022-01-1 ding and Securing of Hydrom IDA / 55060 ces Management and Dam Post Limited tions (Non Bank-S 200,000.00 183,248.87 Signed 2021-09-20 2021-08-16 2021-10-19 2021-09-27 tions nvelope 7 et receiver stations in Hadeji Operation Improvement. PD) a Jama'are, Sokoto Rima Rive r Basins and UBRBDA FMWR/TRIMING/2021/RFQ/W /06/01 / Rehabilitation and fu Component 2: Irrigation De Request for Quota rnishing of WUA Meeting Hall Request for Quota Single Stage - One E Pending Imp 2022-02-0 IDA / 55060 velopment and Management Post Limited tions (Non Bank-S 200,000.00 0.00 2021-10-03 2021-11-03 with Adjoining offices / area tions nvelope lementation 1 . PD) manager and 2 other project manager residencies in DKIS, Gombe State FMWR/TRIMING/2021/RFQ/W /07/01 / Emergency Construc tion of Watch Towers and Pro Component 2: Irrigation De Request for Quota Request for Quota Single Stage - One E Pending Imp 2021-11-0 vision of Equipment for Impr IDA / 55060 velopment and Management Post Limited tions (Non Bank-S 100,000.00 0.00 2021-09-17 2021-10-08 tions nvelope lementation 7 ovement of Security at the M . PD) iddle Rima Valley Irrigation S cheme (MRVIS), Goronyo, So koto State FMWR/TRIMING/2021/NCB/W /04 / Provision of social interv Request for Bids - ention facilities (Livestock Cr Component 2: Irrigation De Single Stage - One E Small Works SPD Under Imple 2023-02-0 ossings, watering points and IDA / 55060 velopment and Management Post Request for Bids Open - National 800,000.00 0.00 2021-12-23 2022-02-10 2022-01-18 2022-02-11 2022-02-15 2022-03-29 2022-05-10 nvelope (1 envelope proce mentation 4 Hand pump Boreholes at Kan . ss) o River Irrigation Scheme (KR IS) and Hadejia Valley Irrigati on Schemes (HVIS) Page 3 FMWR/TRIMING/2022/LIB/W/ Request for Bids - Component 2: Irrigation De 01 / Rehabilitation and Expan Single Stage - One E Works (without pr 30,000,000.0 Under Revie 2024-01-0 IDA / 55060 velopment and Management Prior Request for Bids Limited 0.00 2022-05-30 2022-06-06 2022-07-04 2022-07-25 2022-09-12 sion of Dadin-Kowa Irrigation nvelope equalification) SP 0 w 5 . Scheme (Quick Wins of 2000 D ha) in Gombe State FMWR/TRIMING/2022/NCB/W Request for Bids - Component 1: Water Resour /01 / Procurement of Works f Single Stage - One E Small Works SPD Pending Imp 2023-10-1 IDA / 55060 ces Management and Dam Post Request for Bids Open - National 7,000,000.00 0.00 2022-07-05 2022-07-12 2022-08-09 2022-09-08 2022-10-20 or Rehabilitation and Improv nvelope (1 envelope proce lementation 5 Operation Improvement. ement of Dadin-Kowa Dam in ss) Gombe State, Nigeria FMWR/TRIMING/2022/RFQ/W /01 / Procurement of Works f or the Mandatory Upgrade of Security Measures including Component 2: Irrigation De Request for Quota Request for Quota Single Stage - One E Pending Imp 2022-11-2 provision of Security Lighting IDA / 55060 velopment and Management Post Limited tions (Non Bank-S 200,000.00 0.00 2022-06-27 2022-07-26 tions nvelope lementation 3 , Access Control Barriers and . PD) other Security Equipment at TRIMING Colonies and Contra ctors’/Consultants’ Camps in Bakolori and Middle Rima Val ley. FMWR/TRIMING/2022/RFQ/W /03 / Procurement of Works f or the Mandatory Upgrade of Security Measures including Component 2: Irrigation De Request for Quota Request for Quota Single Stage - One E Pending Imp 2022-11-2 provision of Security Lighting IDA / 55060 velopment and Management Post Limited tions (Non Bank-S 200,000.00 0.00 2022-07-01 2022-07-28 tions nvelope lementation 5 , Access Control Barriers and . PD) other Security Equipment at TRIMING Colonies & Contract ors’/Consultants’ Camps in K ano and Hadejia Valley Irriga tion GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-TRIMING NCO-11056-GO- RFB / PROCUREMENT OF SEC Component 3: Enhancing Ag Single Stage - One E OND PHASE 25,000 UNITS TO IDA / 55060 ricultural Productivity and Su Post Request for Bids Open - National 240,000.00 199,416.41 Completed 2017-03-27 2017-05-04 2017-04-01 2017-05-01 2017-06-01 2017-05-31 2017-09-05 2017-07-05 2017-09-19 2018-01-01 2017-11-16 nvelope MATO PLASTIC CRATES TO A pport to Value Chains. NOTHER 500 TARGETTED FA RMERS OF KRIP NG-TRIMING NCO-19047-GO- RFB / Procurement of custom Component 1: Water Resour Open - Internationa Single Stage - One E Pending Impl ised boats and associated eq IDA / 55060 ces Management and Dam Post Request for Bids 830,079.00 0.00 2016-03-08 2016-03-17 2016-04-16 2016-08-16 2016-12-07 2017-12-02 l nvelope ementation uipment for bathymetric sur Operation Improvement. vey of Nigeria dams & reserv oirs NG-TRIMING NCO-19040-GO- RFB / Procurement of various Component 4: Institutional Single Stage - One E Under Imple office equipment and furnitur IDA / 55060 Development and Project Ma Post Request for Bids Open - National 315,000.00 0.00 2017-07-20 2017-10-05 2017-07-25 2017-09-05 2017-11-02 2017-09-19 2018-04-12 2017-10-10 2018-01-08 nvelope mentation e for office and residential ap nagement. partments for 12nos houses i n BIS, Zamfara State. NG-TRIMING NCO-18975-GO- RFQ / Procurement of person Component 2: Irrigation De al protective equipment for t Request for Quota Single Stage - One E IDA / 55060 velopment and Management Post Open - National 40,000.00 28,415.69 Completed 2017-08-01 2017-08-18 2017-11-09 2017-09-11 2017-12-04 he Project site and safe use o tions nvelope . f chemicals e.g (Nose mask, Safety boots, glooves e.t.c) Phase 3 NG-TRIMING NCO-18966-GO- Component 3: Enhancing Ag RFB / Procurement of agricul Single Stage - One E IDA / 55060 ricultural Productivity and Su Post Request for Bids Open - National 400,000.00 0.00 Canceled 2017-03-03 2017-03-07 2017-04-04 2017-05-15 2017-07-14 2017-10-12 tural equipment to support fa nvelope pport to Value Chains. rmers organisation on techno logy transfer NG-TRIMING NCO-18964-GO- RFQ / Procurement of additio nal 6nos Field and Operation Component 4: Institutional Request for Quota Single Stage - One E al Vehicles for Project Manag IDA / 55060 Development and Project Ma Post Open - National 400,000.00 330,351.26 Completed 2017-10-25 2017-11-29 2017-09-18 2017-12-27 2017-09-20 tions nvelope ement logistics (1nos -18 sea nagement. ters bus, 2nos Salon cars and 3nos 4WD for Project Manag ers). NG-TRIMING NCO-19034-GO- RFB / Procurement of various office equipment and furnitur Component 4: Institutional e for office and residential ap Single Stage - One E Pending Impl IDA / 55060 Development and Project Ma Post Request for Bids Open - National 600,000.00 0.00 2017-08-31 2017-09-05 2017-11-02 2017-11-16 2017-12-15 2018-03-15 artments for BIS, DIS, HVIS a nvelope ementation nagement. nd and Goronyo in Zamfara, Gombe, Jigawa and Sokoto St ate respectively under the TR IMING project (in lots) NG-TRIMING NCO-14025-GO- RFB / Procurement and Instal Component 4: Institutional Open - Internationa Single Stage - One E lation of Electronic Records & IDA / 55060 Development and Project Ma Prior Request for Bids 2,000,000.00 0.00 Canceled 2018-01-30 2018-03-07 2018-02-20 2018-04-09 2018-04-03 2018-05-03 2018-06-19 2019-04-23 l nvelope Documents Management Sys nagement. tem (ERDMS) Equipment and Associated Services FMWR/TRIMING/2018/NCB/G/ 03 / Procurement of 20T Low Component 1: Water Resour Single Stage - One E Bed trailer with Crane and 3, IDA / 55060 ces Management and Dam Post Request for Bids Open - National 480,000.00 461,094.27 Signed 2018-04-02 2018-11-30 2018-04-07 2018-04-30 2018-12-28 2018-05-14 2019-04-30 2018-06-18 2020-01-31 2018-12-15 nvelope 000litres Mobil fuel dump for Operation Improvement. use by National Water Resou rces Institute FMWR/TRIMING/2018/SH/G/0 1 / Procurement of personal Component 2: Irrigation De Request for Quota Single Stage - One E protective equipment and int IDA / 55060 velopment and Management Post Open - National 50,000.00 40,943.47 Completed 2018-03-05 2018-04-03 2018-05-11 2018-05-03 2018-06-08 tions nvelope egrated pest management a . nd safe use of chemical com modities Phase 4 FMWR/TRIMING/2018/NCB/G/ 02 / Procurement of 65,000n os Additional Plastic Crates t Component 3: Enhancing Ag o Kano mRiver Irrigation Sch Single Stage - One E IDA / 55060 ricultural Productivity and Su Post Request for Bids Open - National 950,000.00 0.00 Canceled 2018-04-16 2018-04-21 2018-05-19 2018-06-09 2018-07-21 2019-01-17 eme Tomato Farmers Associa nvelope pport to Value Chains. tion and other Beneficiaries a long Tomato Value Chains an d Productive Alliance in all TR IMING project Schemes Page 4 FMWR/TRIMING/2018/NCB/G/ 01 / Additional Procurement of Agricultural Technology La Component 3: Enhancing Ag Single Stage - One E nd Leveling and other Agricul IDA / 55060 ricultural Productivity and Su Post Request for Bids Open - National 750,000.00 0.00 Canceled 2018-03-19 2018-03-19 2018-04-16 2018-04-23 2018-05-28 2018-10-16 nvelope tural Equipment for Introduct pport to Value Chains. ion to Farmers and others Be neficiaries towards establish ment of Farmers Managemen t Centers FMWR/TRIMING/2018/SH/G/0 3 / Procurement of Protective Component 3: Enhancing Ag Riding Gears and High way C Request for Quota Single Stage - One E IDA / 55060 ricultural Productivity and Su Post Open - National 90,000.00 0.00 Canceled 2018-02-05 2018-04-02 2018-09-29 ode for Motorcycle/Vehicles f tions nvelope pport to Value Chains. or Extension officers and sign post for TRIMING Farmers Fie ld and Business School FMWR/TRIMING/2018/SH/G/0 4 / Procurement and Installati Component 4: Institutional on of Solar Panels and Invert Request for Quota Single Stage - One E IDA / 55060 Development and Project Ma Post Open - National 95,000.00 80,156.92 Completed 2018-03-07 2018-04-09 2018-04-13 2018-05-09 2018-05-11 ers for TRIMING project Offic tions nvelope nagement. e/Residencies in Kano and th ree (3nos) field offices at Auy o, Dadin Kowa and Goronyo FMWR/TRIMING/2018/SH/G/0 Component 4: Institutional 5 / Procurement of Laptops, Request for Quota Single Stage - One E IDA / 55060 Development and Project Ma Post Open - National 90,000.00 74,197.20 Completed 2018-04-07 2018-05-08 2018-06-15 2018-06-07 2018-08-02 Deskstops, Scanners and pri tions nvelope nagement. nters for PMU Kano and Abuj a Offices FMWR/TRIMING/2018/SH/G/0 Component 4: Institutional 6 / Support to FMWR (Irrigati Request for Quota Single Stage - One E Pending Impl IDA / 55060 Development and Project Ma Post Open - National 50,000.00 0.00 2018-04-07 2018-05-04 2018-06-04 on & Drainage Department) t tions nvelope ementation nagement. hrough procurement of requi red ICT Equipment. FMWR/TRIMING/2018/SH/G/0 7 / Procurement of various of Component 2: Irrigation De fice equipment and furniture Request for Quota Single Stage - One E Pending Impl IDA / 55060 velopment and Management Post Open - National 100,000.00 0.00 2018-02-17 2018-04-07 2018-05-07 for office and residential apar tions nvelope ementation . tments for Bunkure, Kano Riv er Irrigation Scheme in Kano State FMWR/TRIMING/2018/SH/G/0 Component 3: Enhancing Ag 8 / Procurement of 350nos si Request for Quota Single Stage - One E IDA / 55060 ricultural Productivity and Su Post Open - National 50,000.00 32,975.94 Completed 2018-02-12 2018-03-16 2018-03-28 2018-04-30 2018-05-17 gnpost for Farmers Field and tions nvelope pport to Value Chains. Business School Training sch ool FMWR/TRIMING/2018/NCB/G/ 04 / Procurement of services Component 3: Enhancing Ag Single Stage - One E provider for provision of Fam IDA / 55060 ricultural Productivity and Su Post Request for Bids Open - National 400,000.00 299,619.48 Completed 2018-02-26 2018-04-27 2018-03-03 2018-03-17 2018-05-25 2018-03-24 2018-07-02 2018-04-05 2018-07-31 2018-10-02 2018-12-14 nvelope ers Field Business School tra pport to Value Chains. ining materials and agricultur al inputs for running of FFS FMWR/TRIMING/2018/SH/G/1 Component 3: Enhancing Ag 1 / Furnishing of four (4) no. Request for Quota Single Stage - One E IDA / 55060 ricultural Productivity and Su Post Open - National 100,000.00 71,032.84 Completed 2018-04-28 2018-05-29 2018-11-19 2018-06-28 2018-12-06 Agricultural Development Pro tions nvelope pport to Value Chains. ject offices allocated for TRIM ING Project activities NG-TRIMING NCO-54492-GO- RFB / Procurement and Instal Component 1: Water Resour lation of Hydrometric Equipm Open - Internationa Single Stage - One E IDA / 55060 ces Management and Dam Prior Request for Bids 4,500,000.00 4,785,928.19 Signed 2018-03-19 2018-03-19 2018-03-19 2017-11-30 2018-04-06 2018-03-27 2018-05-11 2018-05-31 2021-04-25 ent and Related Services for l nvelope Operation Improvement. Sokoto Rima and Hadejia Jam a'are Basin for Hydrometric I mprovement FMWR/TRIMING/2016/ICB/G/ 001 / Procurement and Install Component 1: Water Resour ation of Hydromet Equipment Open - Internationa Single Stage - One E IDA / 55060 ces Management and Dam Prior Request for Bids 4,500,000.00 0.00 Canceled 2017-10-12 2017-10-12 2017-11-30 2018-02-28 2018-04-20 2021-04-04 and Provision of Related Serv l nvelope Operation Improvement. ices at Sokoto Rima and Had ejia Jama’are River Basins for Hydrometric Improvement FMWR/TRIMING/2018/SS/G/0 1 / Bathymetric Survey of Tig Component 1: Water Resour Under Imple a, Ruwankayan, Hadejia, Gor IDA / 55060 ces Management and Dam Post Direct Selection Direct 2,000,000.00 0.00 2018-06-11 2018-06-16 2018-07-21 2019-01-17 mentation onyo, Zobe, Dadin-0Kowa, Ch Operation Improvement. allawa Dams/Reservoirs NG-TRIMING NCO-76576-GO- RFQ / Support to FMWR (Dep Component 4: Institutional Request for Quota Single Stage - One E artment of Dams & Reservoir IDA / 55060 Development and Project Ma Post Open - National 50,000.00 41,125.17 Completed 2018-09-15 2018-10-27 2018-11-15 2018-11-26 2018-12-12 tions nvelope Operations) through procure nagement. ment of required ICT Equipm ent. NG-TRIMING NCO-76525-GO- RFQ / Purchase of 4 No Gene Component 1: Water Resour Request for Quota Single Stage - One E rators for TRIMING Project Sit IDA / 55060 ces Management and Dam Post Open - National 100,000.00 82,495.88 Signed 2018-09-15 2018-10-19 2018-09-18 2018-11-18 tions nvelope es at the Four Schems (BIS- 1 Operation Improvement. 00KVA, HVIS - 60KVS, DKIS - 30KVA, & MRVIS - 50KVA) NG-TRIMING NCO-76524-GO- Component 2: Irrigation De RFQ / Purchase of 3 No 4WD Request for Quota Single Stage - One E IDA / 55060 velopment and Management Post Open - National 250,000.00 207,574.26 Completed 2018-09-30 2018-11-03 2018-09-21 2018-12-03 2018-10-15 Utility vehicle for Consultant tions nvelope . Field Operation for Bakolori Ir rigation Civil Works NG-TRIMING NCO-76529-GO- RFQ / Modest furnishing and Component 2: Irrigation De Request for Quota Single Stage - One E provision of Solar Pannels an IDA / 55060 velopment and Management Post Open - National 100,000.00 73,465.63 Completed 2018-09-04 2018-10-30 2018-12-24 2018-11-29 2019-12-18 tions nvelope d Inverters for the newly ren . ovated Houses for Security A gencies covering BIS NG-TRIMING NCO-76530-GO- RFQ / Procurement of micros Component 4: Institutional oft office applications and ot Request for Quota Single Stage - One E Pending Impl IDA / 55060 Development and Project Ma Post Open - National 65,000.00 0.00 2018-10-05 2018-11-08 2018-12-08 her relevant software for PM tions nvelope ementation nagement. U, TRIMING project MIS Cente rs at FMWR, RBDAs and TRIM ING Schemes NG-TRIMING NCO-76522-GO- Component 4: Institutional Request for Quota Single Stage - One E RFQ / Support to FPFMD thro IDA / 55060 Development and Project Ma Post Open - National 50,000.00 36,398.75 Completed 2018-09-15 2018-10-10 2018-09-21 2018-10-24 2018-09-25 tions nvelope ugh procurement of required nagement. ICT Equipment. NG-TRIMING NCO-91445-GO- RFQ / Procurement and instal Component 2: Irrigation De lation of communication Gad Request for Quota Single Stage - One E IDA / 55060 velopment and Management Post Limited 100,000.00 72,848.69 Completed 2018-12-19 2018-12-04 2019-01-16 2018-12-28 2019-01-30 2019-04-30 gets on vehicles and for field tions nvelope . works in TRIMING interventio n sites as securities measure s (BIS) Page 5 FMWR/TRIMING/2019/NCB/G/ 02 / Procurement of Agricultu Component 3: Enhancing Ag ral Technology Equipment for Single Stage - One E IDA / 55060 ricultural Productivity and Su Post Request for Bids Open - National 950,000.00 0.00 Canceled 2019-04-24 2019-05-01 2019-05-29 2019-06-19 2019-07-31 2020-01-27 the Establishment and Devel nvelope pport to Value Chains. opment of Mechanization in t he FMCs at BIS, HVIS, KRIS a nd MRVIS. - LOT 1 FMWR/TRIMING/2019/NCB/G/ 04 / Procurement and Installa Component 1: Water Resour tion of Solar Panels, Inverters Single Stage - One E IDA / 55060 ces Management and Dam Post Request for Bids Open - National 195,000.00 137,226.88 Signed 2019-03-11 2019-09-19 2019-03-16 2019-09-19 2019-04-13 2019-10-24 2019-04-27 2020-02-20 2019-06-04 2020-08-10 2019-10-02 , Hybrid Batteries with solar i nvelope Operation Improvement. nverters for TRIMING Project Office/Residences and Hydro metry observation stations FMWR/TRIMING/2019/NCB/0 5 / Procurement of Services P rovider for provision of Fame Component 3: Enhancing Ag Single Stage - One E rs Field Business School (FFS IDA / 55060 ricultural Productivity and Su Post Request for Bids Open - National 750,000.00 736,090.58 Completed 2019-02-20 2019-03-20 2019-02-27 2019-03-27 2019-04-14 2019-04-17 2019-05-13 2019-05-22 2019-06-11 2021-05-21 2020-12-23 nvelope BS) Training Materials for Ru pport to Value Chains. nning of FFBS in Wet and Dry Season for 2019/2020 and 2 020/2021 FMWR/TRIMING/2019/NCB/G/ 06 / Procurement and Installa Component 1: Water Resour tion, commissioning and Trai Single Stage - One E IDA / 55060 ces Management and Dam Post Request for Bids Open - National 500,000.00 300,109.36 Signed 2019-03-10 2019-10-10 2019-03-17 2019-10-10 2019-04-14 2019-11-07 2019-05-05 2020-02-05 2019-06-16 2020-07-15 2019-10-14 ning of flow measurment dev nvelope Operation Improvement. ices in the irrigation supply c anal of TRIMING dams and re servoirs FMWR/TRIMING/2019/ICB/G/ Component 1: Water Resour 01 / Procurement and Installa Open - Internationa Single Stage - One E IDA / 55060 ces Management and Dam Prior Request for Bids 2,800,000.00 0.00 Canceled 2019-06-27 2019-07-11 2019-08-22 2019-09-21 2019-11-02 2021-11-01 tion of Hydrometric Equipme l nvelope Operation Improvement. nt and Related services for U pper Benue River Basin FMWR/TRIMING/2019/RFQ/G/ 07 / Procurement of 6Nos. Op Component 4: Institutional erational field vehicles for us Request for Quota Single Stage - One E IDA / 55060 Development and Project Ma Post Limited 450,000.00 379,267.45 Completed 2019-04-04 2019-04-19 2019-05-09 2019-05-27 2019-06-08 2019-06-11 e by TRIMING Project Manage tions nvelope nagement. rs, Basin Level Coordinators and for FMCs takeoff operatio n at BIS,HVIS,KRIS and MRVIS FMWR/TRIMING/2019/NCB/G/ 08 / Procurement and Installa tions of ICT equipment & rela Component 4: Institutional ted services as Additional Su Single Stage - One E IDA / 55060 Development and Project Ma Post Request for Bids Open - National 300,000.00 0.00 Canceled 2019-05-30 2019-10-10 2019-06-06 2019-10-10 2019-07-04 2019-07-25 2019-09-05 2019-12-04 pport to Irrigation & Drainage nvelope nagement. Department, Dam & Reservoi rs Operations Dept., Honoura ble Minister Office and the Pr oject Change Management C ommittee FMWR/TRIMING/2019/RFQ/G/ 02 / Procurement and installt Component 2: Irrigation De ion of communication Gadget Request for Quota Single Stage - One E IDA / 55060 velopment and Management Post Limited 100,000.00 73,575.79 Completed 2019-02-20 2019-09-02 2019-03-27 2019-10-02 2019-04-26 2019-11-18 s on vechiles and for field wo tions nvelope . rks in TRIMING intervention si tes as securities measures ( KRIS & HVIS) FMWR/TRIMING/2019/NCB/G/ 09 / Supply and Installations i Component 4: Institutional Single Stage - One E ncluding provision of base pl IDA / 55060 Development and Project Ma Post Request for Bids Open - National 140,000.00 90,205.56 Completed 2019-05-09 2019-09-19 2019-05-14 2019-09-19 2019-06-11 2019-10-17 2019-06-25 2020-01-30 2019-07-30 2020-03-24 2019-10-28 2020-05-27 nvelope atform for the 5Nos Generato nagement. rs (60KVA) in 5Nos Radio Hou ses FMWR/TRIMING/2019/NCB/G/ 10 / Procurement of Large M ultipurpose Printers and GIS f Component 4: Institutional or use by the PMU and for th Single Stage - One E IDA / 55060 Development and Project Ma Post Request for Bids Open - National 190,000.00 70,846.38 Completed 2019-05-20 2019-10-10 2019-05-27 2019-10-10 2019-06-24 2019-11-07 2019-07-15 2020-01-15 2019-08-26 2020-03-18 2019-12-24 2020-06-09 e establishment of GIS Units nvelope nagement. in I & D-FMWR, TRIMING hea d offices in Abuja & Kano, TRI MING RBDA headquarters, an d TRIMING scheme offices FMWR/TRIMING/2019/RFQ/G/ 03 / Purchase of personal pro tective equipment and integr Component 3: Enhancing Ag Request for Quota Single Stage - One E ated pest management and s IDA / 55060 ricultural Productivity and Su Post Limited 60,000.00 49,899.05 Completed 2019-09-25 2019-08-21 2019-10-30 2019-09-16 2019-11-29 2019-10-09 tions nvelope afe use of chemical commodi pport to Value Chains. ty and Waste Seperation and Segregation Containers for T RIMING use FMWR/TRIMING/2019/RFQ/G/ 04 / Furnishing of 6nos Projec Component 4: Institutional Request for Quota Single Stage - One E t Managers offices at all TRIM IDA / 55060 Development and Project Ma Post Limited 100,000.00 82,190.46 Completed 2019-10-07 2019-07-26 2019-11-11 2019-08-29 2019-12-11 2019-11-08 tions nvelope ING Project Schemes and TR nagement. IMING Library office in Kano FMWR/TRIMING/2019/NCB/G/ Component 3: Enhancing Ag 01 / Provision of Office Furnit Single Stage - One E IDA / 55060 ricultural Productivity and Su Post Request for Bids Open - National 250,000.00 0.00 Canceled 2019-03-18 2019-03-25 2019-04-22 2019-05-13 2019-06-24 2019-09-22 ure and Equipment for the F nvelope pport to Value Chains. MCs at BIS, KRIS and MRVIS. FMWR/TRIMING/2020/RFQ/G/ Component 4: Institutional 07 / Procurement of 6Nos fiel Request for Quota Single Stage - One E IDA / 55060 Development and Project Ma Post Limited 485,000.00 8,790,905.26 Completed 2020-04-25 2020-05-04 2020-05-26 2020-06-01 2020-06-25 2020-06-25 d operational vehicles for mo tions nvelope nagement. nitoring and supervision of c onstruction activities FMWR/TRIMING/2020/RFQ/G/ 04 / Procurement and furnish Component 2: Irrigation De Request for Quota Single Stage - One E ing of Water Users Associatio IDA / 55060 velopment and Management Post Limited 100,000.00 80,885.33 Completed 2020-04-25 2020-03-02 2020-06-06 2020-06-03 2020-07-18 2020-08-03 tions nvelope ns meeting halls at Bakolori . and Middle Rima Valley Irriga tion Schemes FMWR/TRIMING/2020/G/RFQ/ Component 3: Enhancing Ag 01 / Procurement of Protectiv Request for Quota Single Stage - One E IDA / 55060 ricultural Productivity and Su Post Limited 100,000.00 73,233.21 Completed 2020-04-25 2020-03-02 2020-05-30 2020-06-03 2020-06-29 2020-06-16 e riding gears, 25Nos motor tions nvelope pport to Value Chains. cycles and generators for ext ension services delivery FMWR/TRIMING/2020/RFQ/G/ 02 / Purchase of personal pro Component 3: Enhancing Ag Request for Quota Single Stage - One E tective equipment (commodi IDA / 55060 ricultural Productivity and Su Post Limited 70,000.00 61,040.73 Completed 2020-04-25 2020-06-03 2020-05-30 2020-06-25 2020-06-29 2020-07-23 tions nvelope ty) to support the integrated pport to Value Chains. pest management and safe u se of chemical approach Page 6 FMWR/TRIMING/2020/NCB/G/ 07 / Procurement and Installa Component 1: Water Resour Single Stage - One E tion of Hydrometric Equipme IDA / 55060 ces Management and Dam Prior Request for Bids Open - National 2,800,000.00 0.00 Canceled 2020-06-30 2020-07-14 2020-08-12 2020-09-11 2020-10-23 2022-04-16 nvelope nt and Related Activities for Operation Improvement. Upper Benue River Basin FMWR/TRIMING/2020/NCB/G/ 03 / Procurement and Installa Component 4: Institutional Single Stage - One E tion of FM Radio Equipment a IDA / 55060 Development and Project Ma Post Request for Bids Open - National 800,000.00 0.00 Canceled 2020-09-30 2020-10-07 2020-11-04 2020-12-04 2021-01-15 2021-05-15 nvelope nd Associated furnishing for nagement. TRIMING project schemes FMWR/TRIMING/2019/NCB/G/ 03 / Procurement and Installa Component 3: Enhancing Ag Single Stage - One E tion of (FM Radio) Equipment IDA / 55060 ricultural Productivity and Su Post Request for Bids Open - National 400,000.00 0.00 Canceled 2019-05-01 2019-05-08 2019-06-05 2019-06-26 2019-08-07 2019-11-05 nvelope and associated furnishing for pport to Value Chains. TRIMING Project FM stations at BIS, HVIS, KRIS and MRVIS. FMWR/TRIMING/2020/RFQ/G/ 05 / Procurement Improveme Component 4: Institutional nt/Expansion of Communicati Request for Quota Single Stage - One E IDA / 55060 Development and Project Ma Post Limited 100,000.00 85,608.97 Completed 2020-05-05 2020-07-06 2020-06-03 2020-08-17 2020-08-02 2020-09-30 on Coverage with Gadgets wi tions nvelope nagement. thin Kano River and Hadejia Valley Irrigation Schemes (Ph ase II) FMWR/TRIMING/2020/RFQ/G/ 06 / Provision of Communicat Component 4: Institutional Request for Quota Single Stage - One E ion Gadgets (including masts IDA / 55060 Development and Project Ma Post Limited 100,000.00 87,384.32 Completed 2020-05-05 2020-05-18 2020-06-05 2020-06-27 2020-08-04 2020-08-07 tions nvelope and independent power supp nagement. ly in Dadin Kowa Irrigation Sc heme, Gombe State FMWR/TRIMING/2020/NCB/G/ 04 / Procurement of addition Component 3: Enhancing Ag al service provider for the pr Single Stage - One E IDA / 55060 ricultural Productivity and Su Post Request for Bids Open - National 350,000.00 267,803.63 Signed 2020-04-30 2020-06-10 2020-05-14 2020-06-11 2020-06-11 2020-07-08 2020-07-23 2020-08-18 2020-09-03 2020-10-15 2021-12-31 ovision of agricultural inputs, nvelope pport to Value Chains. training materials and furnitu re for use by relevant Agricur etural Development Program mes FMWR/TRIMING/2020/RFQ/G/ 08 / Provision and Installation Component 4: Institutional s of solar power Including Bat Request for Quota Single Stage - One E IDA / 55060 Development and Project Ma Post Limited 100,000.00 77,970.40 Completed 2020-05-20 2020-02-24 2020-07-01 2020-06-03 2020-08-30 2020-08-03 teries and Inverters systems tions nvelope nagement. for Residences and offices at Dadinkowa Irrigation Scheme (DKIS) FMWR/TRIMING/2020/NCB/G/ 01 / Procurement and Installa Component 4: Institutional Single Stage - One E tion of Electronic Records an IDA / 55060 Development and Project Ma Prior Request for Bids Open - National 1,650,000.00 1,467,421.98 Signed 2020-07-30 2020-07-28 2020-08-13 2020-08-04 2020-09-24 2020-09-02 2020-10-24 2021-03-31 2020-11-21 2021-06-22 2021-06-19 nvelope d Documents Management S nagement. ystem (ERDMS) Equipment a nd Associated Services FMWR/TRIMING/2020/RFQ/G O/010 / Purchase of ICT equi Component 2: Irrigation De pment for use by APEX and S Request for Quota Single Stage - One E IDA / 55060 velopment and Management Post Limited 100,000.00 87,243.38 Completed 2020-12-08 2020-11-16 2020-12-29 2020-12-09 2021-01-28 2020-12-22 ectors WUA Offices, Basin Le tions nvelope . vels Coordinator (BLCs), Site Contract Coordinators SCCs, at HJRBDA including New PM U FMWR/TRIMING/2021/RFQ/G/ 01 / Purchase and Installatio Component 1: Water Resour n of GeoHECRAS software’s f Request for Quota Single Stage - One E IDA / 55060 ces Management and Dam Post Open - National 100,000.00 0.00 Canceled 2021-09-05 2021-10-09 2021-11-08 or FMWR/PMU/RBDAs for effe tions nvelope Operation Improvement. ctive dam and reservoir oper ation monitoring and provisio n of online / physical training FMWR/TRIMING/2021/RFQ/G/ 03 / Procurement and Installa Component 2: Irrigation De Request for Quota Single Stage - One E tion of furniture for 7Nos. Sec IDA / 55060 velopment and Management Post Open - National 100,000.00 0.00 Canceled 2021-09-11 2021-10-10 2021-12-09 tions nvelope tor WUA offices at BIS, 14Nos . at KRIS and 6Nos at HVIS FMWR/TRIMING/2021/RFQ/G/ 04 / Procurement of solar inst Component 1: Water Resour allation as alternative source Request for Quota Single Stage - One E IDA / 55060 ces Management and Dam Post Open - National 100,000.00 0.00 Canceled 2021-09-13 2021-10-12 2021-12-11 of energy in Workshop office tions nvelope Operation Improvement. s for Dam operators at Bakol ori, Tiga, Challawa and Dadin kowa FMWR/TRIMING/2021/RFQ/G/ Component 2: Irrigation De 06 / Procurement of Plotters, Request for Quota Single Stage - One E IDA / 55060 velopment and Management Post Open - National 100,000.00 0.00 Canceled 2021-09-25 2021-11-09 2022-01-08 Scanner and other related GI tions nvelope . S Facilities for TRIMING Proje ct GIS Centers FMWR/TRIMING/2021/RFQ/G/ 07 / Procurement of compute Component 2: Irrigation De Request for Quota Single Stage - One E rs and related ICT facilities fo IDA / 55060 velopment and Management Post Open - National 100,000.00 0.00 Canceled 2021-09-19 2021-10-20 2021-12-19 tions nvelope r WUA offices at BIS MRVIS a . nd New PMU Members and Si tes offices FMWR/TRIMING/2021/NCB/G/ 02 / Procurement of Services Provider for provision of Fam Component 3: Enhancing Ag Single Stage - One E Under Imple ers Field Business School (FF IDA / 55060 ricultural Productivity and Su Post Request for Bids Open - National 950,000.00 0.00 2021-09-13 2022-01-28 2021-09-20 2022-01-28 2021-10-18 2021-11-01 2021-11-29 2024-01-18 nvelope mentation BS) Training Materials for Ru pport to Value Chains. nning of FFBS in 2021 Dry Se ason, 2022 wet and dry seas ons and 2023 wet and dry se asons FMWR/TRIMING/2021/RFQ/G/ 05 / Procurement of 6Nos (4 Component 4: Institutional WD) field operational vehicle Request for Quota Single Stage - One E Pending Impl IDA / 55060 Development and Project Ma Post Limited 495,000.00 0.00 2021-10-05 2021-11-09 2021-12-24 s for monitoring and supervis tions nvelope ementation nagement. ion of construction activities to replace 7 years old poorly serviceable vehicles FMWR/TRIMING/2021/NCB/G/ 01 / Procurement and Installa tion of Agric processing equi Component 2: Irrigation De pment for eight (8Nos) Agric Open - Internationa Single Stage - One E Pending Impl IDA / 55060 velopment and Management Prior Request for Bids 10,200,000.00 0.00 2021-09-30 2021-10-14 2021-11-25 2021-12-25 2022-02-05 2024-02-05 Business Centers (ABC) plus l nvelope ementation . two (2) years inputs for fisher ies production facilities in Jan karawa community, Zamfara State, Nigeria Page 7 FMWR/TRIMING/2021/RFQ/G/ 001 / Purchase and Installati Component 1: Water Resour on of GeoHECRAS software’s Request for Quota Single Stage - One E IDA / 55060 ces Management and Dam Post Limited 100,000.00 92,159.67 Signed 2021-09-25 2021-09-24 2021-10-24 2021-11-18 2021-11-23 for FMWR/PMU/RBDAs for eff tions nvelope Operation Improvement. ective dam and reservoir ope ration monitoring and provisi on of online / physical trainin g FMWR/TRIMING/2021/RFQ/G/ 02 / Procurement and Installa Component 4: Institutional Request for Quota Single Stage - One E Pending Impl tion of Communication gadge IDA / 55060 Development and Project Ma Post Open - National 100,000.00 0.00 2021-09-07 2021-10-06 2021-12-05 tions nvelope ementation ts with Masts, inverters and S nagement. olar panels at MRVIS Gorony o, Sokoto State FMWR/TRIMING/2021/RFQ/G/ 02/01 / Procurement and Inst Component 4: Institutional Request for Quota Single Stage - One E Pending Impl allation of Communication ga IDA / 55060 Development and Project Ma Post Limited 100,000.00 0.00 2021-10-03 2021-11-01 2021-12-31 tions nvelope ementation dgets with Masts, inverters a nagement. nd Solar panels at MRVIS Gor onyo, Sokoto State FMWR/TRIMING/2021/RFQ/G/ 03/01 / Procurement and Inst Component 2: Irrigation De Request for Quota Single Stage - One E Pending Impl allation of furniture for 7Nos. IDA / 55060 velopment and Management Post Limited 100,000.00 0.00 2021-10-02 2021-10-31 2021-12-30 tions nvelope ementation Sector WUA offices at BIS, 14 . Nos at KRIS and 6Nos at HVIS FMWR/TRIMING/2021/RFQ/G/ 04/01 / Procurement of solar Component 1: Water Resour installation as alternative sou Request for Quota Single Stage - One E Pending Impl IDA / 55060 ces Management and Dam Post Limited 100,000.00 0.00 2021-09-30 2021-10-31 2021-12-30 rce of energy in Workshop off tions nvelope ementation Operation Improvement. ices for Dam operators at Ba kolori, Tiga, Challawa and Da dinkowa FMWR/TRIMING/2021/RFQ/G/ Component 2: Irrigation De 06/01 / Procurement of Plotte Request for Quota Single Stage - One E Pending Impl IDA / 55060 velopment and Management Post Limited 100,000.00 0.00 2021-10-23 2021-11-23 2022-01-22 rs, Scanner and other related tions nvelope ementation . GIS Facilities for TRIMING Pro ject GIS Centers FMWR/TRIMING/2021/RFQ/G/ 07/01 / Procurement of comp Component 2: Irrigation De Request for Quota Single Stage - One E uters and related ICT facilitie IDA / 55060 velopment and Management Post Limited 100,000.00 91,924.27 Signed 2021-10-13 2021-10-12 2021-11-11 2021-11-02 2021-12-26 tions nvelope s for WUA offices at BIS MRVI . S and New PMU Members an d Sites offices FMWR/TRIMING/2021/NCB/G/ Component 3: Enhancing Ag 07 / Procurement and supply Single Stage - One E Pending Impl IDA / 55060 ricultural Productivity and Su Post Request for Bids Open - National 350,000.00 0.00 2021-12-24 2021-12-29 2022-02-09 2022-03-11 2022-04-22 2022-08-20 of 20,000 Tomato plastic crat nvelope ementation pport to Value Chains. es for 4Nos FMC (BIS, HVIS, MRVIS and KRIS) FMWR/TRIMING/2021/NCB/G/ 5 / Procurement of Agricultur al Technology Equipment for Component 3: Enhancing Ag the Establishment and Devel Single Stage - One E Pending Impl IDA / 55060 ricultural Productivity and Su Post Request for Bids Open - National 950,000.00 0.00 2021-12-24 2022-01-10 2022-02-21 2022-03-23 2022-05-04 2022-09-01 opment of Mechanization in t nvelope ementation pport to Value Chains. he Farmers Management Cen ters (FMCs) at Bakolori, Hade jia Valley, Kano River and Mi ddle Rima Valley Irrigation Sc hemes FMWR/TRIMING/2021/NCB/G/ 6 / Provision of Office Furnitu Component 3: Enhancing Ag re and Equipment for the Far Single Stage - One E Pending Impl IDA / 55060 ricultural Productivity and Su Post Request for Bids Open - National 800,000.00 0.00 2021-12-23 2022-01-11 2022-02-22 2022-03-24 2022-05-05 2022-09-02 mers Management Centers a nvelope ementation pport to Value Chains. t Bakolori, Kano River, Hadeji a Valley and Middle Rima Vall ey Irrigation Schemes FMWR/TRIMING/2021/NCB/G/ 03 / Procurement and Installa tion of (FM Radio) Equipment Component 3: Enhancing Ag Single Stage - One E Pending Impl and associated furnishing for IDA / 55060 ricultural Productivity and Su Post Request for Bids Open - National 950,000.00 0.00 2021-12-23 2022-01-20 2022-03-03 2022-04-14 2022-05-26 2022-11-22 nvelope ementation TRIMING Project FM stations pport to Value Chains. at Bakolori, Hadejia Valley, K ano River, Middle Rima Valle y and Dadinkowa Irrigation S chemes FMWR/TRIMING/2021/NCB/G/ 06 / Procurement of Agricultu Component 3: Enhancing Ag ral input as investment to th Single Stage - One E Pending Impl IDA / 55060 ricultural Productivity and Su Post Request for Bids Open - National 600,000.00 0.00 2021-12-24 2022-01-17 2022-02-28 2022-03-30 2022-05-11 2022-09-08 e Farmers Management Cent nvelope ementation pport to Value Chains. ers at Bakolori, Hadejia Valle y, Kano River and Middle Ri ma Valley Irrigation Schemes FMWR/TRIMING/2022/NCB/G/ 01 / Procurement and Deploy Component 2: Irrigation De Single Stage - One E Pending Impl ment of Security Equipment IDA / 55060 velopment and Management Post Request for Bids Open - National 350,000.00 0.00 2022-07-10 2022-07-15 2022-08-12 2022-08-26 2022-09-30 2022-12-29 nvelope ementation and Communication Systems . in all TRIMING intervention sc hemes FMWR/TRIMING/2022/RFQ/G/ Component 1: Water Resour 01 / Provision of solar back-u Request for Quota Single Stage - One E Pending Impl IDA / 55060 ces Management and Dam Post Limited 65,000.00 0.00 2022-07-03 2022-07-30 2022-09-28 p power for the 4th receiver tions nvelope ementation Operation Improvement. station in NIMET H/Q office in Abuja FMWR/TRIMING/2022/RFQ/G/ 04 / Provision and installation of inverters, batteries and sol Component 2: Irrigation De Request for Quota Single Stage - One E Pending Impl ar panels at WUA Meeting Ha IDA / 55060 velopment and Management Post Limited 95,000.00 0.00 2022-08-17 2022-09-15 2022-11-14 tions nvelope ementation ll and automatic solar power . on poles at zonal head office s at Dadin - Kowa, Irrigation Scheme (DKIS), Gombe State FMWR/TRIMING/2022/NCB/G/ 02 / Provision and installation of inverters, batteries, solar panels and Automatic Solar P Component 2: Irrigation De Single Stage - One E Pending Impl owered Lights on poles and o IDA / 55060 velopment and Management Post Request for Bids Open - National 300,000.00 0.00 2022-06-30 2022-07-05 2022-08-02 2022-08-23 2022-09-27 2022-12-26 nvelope ementation ther light fittings in and arou . nd 20Nos Water User Associa tion Sector Offices & 2Nos M eeting Hall at Kano River and Hadejia River Irrigation FMWR/TRIMING/2022/RFQ/G/ 03 / Provision and installation of inverters, batteries, solar Component 2: Irrigation De panels, and Automatic Solar Request for Quota Single Stage - One E Pending Impl IDA / 55060 velopment and Management Post Limited 100,000.00 0.00 2022-08-03 2022-09-01 2022-10-31 Powered Lights on poles at W tions nvelope ementation . UA Meeting Hall, TRIMING Col ony and its environs at Middl e Rima Valley Irrigation Sche me (MRVIS) Goronyo, Sokoto State Page 8 NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-TRIMING NCO-14028-NC- Component 2: Irrigation De Open - Internationa Single Stage - One E Under Imple RFB / Detailed aerial topogra IDA / 55060 velopment and Management Post Request for Bids 1,173,600.00 0.00 2016-04-14 2016-04-14 2016-05-26 2016-05-26 2016-06-25 2017-06-06 2017-03-03 2017-10-29 l nvelope mentation hical survey of Dadin-Kowa a . nd Guyuk CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-TRIMING NCO-14068-CS- QCBS / Technical Assistance Component 3: Enhancing Ag Quality And Cost- Open - Internationa on Farmers -Market Linkages IDA / 55060 ricultural Productivity and Su Prior 5,179,190.00 4,732,203.54 Signed 2015-06-09 2015-06-09 2016-03-07 2016-04-25 2016-07-21 2017-04-28 2017-06-08 2017-05-19 2017-06-30 2021-04-28 Based Selection l ,value chain development an pport to Value Chains. d for the establishment of FM C in 4 irrigation schemes NG-TRIMING NCO-14090-CS- QCBS / Design and Constructi Component 2: Irrigation De Quality And Cost- Open - Internationa on Supervision of Dadin Kow IDA / 55060 velopment and Management Prior 4,029,884.00 3,964,523.32 Signed 2015-04-10 2015-04-17 2015-12-08 2016-09-09 2016-09-09 2016-10-09 2017-05-05 2017-06-19 2017-06-16 2017-07-10 2020-09-28 Based Selection l a Irrigation Scheme and feasi . bility studies of Guyuk Irrigati on Scheme NG-TRIMING NCO-14034-CS- QCBS / Consultancy Service f or Construction Supervision f Component 1: Water Resour or Rehabilitation and Expansi Quality And Cost- Open - Internationa IDA / 55060 ces Management and Dam Prior 5,000,000.00 5,275,353.25 Terminated 2016-08-03 2016-08-10 2017-05-25 2017-09-18 2017-07-06 2017-10-30 2017-08-05 2018-01-09 2017-09-09 2018-07-24 2017-10-14 2018-08-09 2022-09-18 on of Kano River Irrigation Sc Based Selection l Operation Improvement. heme (KRIS) And Hadejia Vall ey Irrigation Scheme (HVIS), Dam Safety / River Training Works in The Hadejia-Jama’ar e Basin. NG-TRIMING NCO-14022-CS- Component 2: Irrigation De QCBS / Engineering Supervisi Quality And Cost- Open - Internationa IDA / 55060 velopment and Management Prior 4,043,083.00 3,442,767.00 Signed 2015-04-17 2015-04-17 2016-07-15 2016-09-09 2016-05-13 2016-10-19 2017-04-28 2017-05-10 2017-06-02 2017-03-08 2020-09-30 on of the Rehabilitation/conv Based Selection l . ersion area of Bakolori Irrigat ion Scheme NG-TRIMING NCO-14031-CS- Component 1: Water Resour Quality And Cost- Open - Internationa QCBS / Technical Assistance IDA / 55060 ces Management and Dam Prior 2,500,000.00 5,219,268.89 Signed 2016-02-09 2016-03-01 2016-10-28 2016-12-23 2017-05-08 2017-07-30 2017-06-12 2018-11-12 2017-07-17 2018-01-11 2020-07-01 Based Selection l for WUA in KRIS and HVIS Operation Improvement. NG-TRIMING NCO-14076-CS- QCBS / Technical Assistance f Component 1: Water Resour Quality And Cost- Open - Internationa or Dam Safety Assurance & T IDA / 55060 ces Management and Dam Prior 1,421,626.00 1,398,283.30 Signed 2015-04-17 2015-04-17 2015-12-16 2016-02-10 2016-02-16 2016-05-06 2016-07-21 2017-06-06 2016-09-21 2016-09-21 2019-09-06 Based Selection l raining for Dam and Reservoi Operation Improvement. r Dept. and RBDA staff NG-TRIMING NCO-14092-CS- Component 1: Water Resour QCBS / Consulting services fo Quality And Cost- Open - Internationa IDA / 55060 ces Management and Dam Prior 1,500,000.00 0.00 Canceled 2016-10-04 2016-10-11 2017-06-08 2017-07-20 2017-08-19 2017-09-16 2017-10-21 2019-04-14 r dams safety, improved hydr Based Selection l Operation Improvement. ometry and IWRM Dadin Kow a Irrigation Scheme NG-TRIMING NCO-19048-CS- Component 2: Irrigation De CQS / Consultancy Services f Consultant Qualifi Pending Impleme IDA / 55060 velopment and Management Post Open - National 286,040.00 0.00 2014-09-23 2014-10-14 2014-11-27 2014-12-27 2015-01-31 2015-07-30 or preparation of ESIA for MR cation Selection ntation . VIS with Goronyo Dam in Sok oto State NG-TRIMING NCO-19044-CS- Component 2: Irrigation De CQS / Consultancy Services f Consultant Qualifi Pending Impleme IDA / 55060 velopment and Management Post Open - National 127,700.00 0.00 2016-03-18 2016-04-08 2016-05-22 2016-06-21 2016-07-26 2017-01-22 or Preparation of Environme cation Selection ntation . ntal and Social Assessment f or Zobe Dam NG-TRIMING NCO-18972-CS- Component 2: Irrigation De Consultant Qualifi Open - Internationa Under Implement IDA / 55060 Post 222,240.00 0.00 2016-02-01 2016-02-01 2016-02-09 2016-06-03 2016-06-21 2016-08-19 2017-01-20 CQS / Elaboration of RAP for velopment and Management cation Selection l ation KRIS . NG-TRIMING NCO-19043-CS- Component 2: Irrigation De Consultant Qualifi Under Implement IDA / 55060 Post Open - National 245,300.00 0.00 2016-02-09 2016-02-01 2016-03-01 2016-04-14 2016-06-17 2016-08-19 2017-02-15 CQS / Elaboration of RAP for velopment and Management cation Selection ation HVIS . NG-TRIMING NCO-18962-CS- Component 2: Irrigation De Consultant Qualifi Pending Impleme CQS / ESIA Dadin Kowa Irriga IDA / 55060 velopment and Management Post Open - National 271,899.00 0.00 2016-04-08 2016-10-07 2017-03-02 2017-04-27 2017-06-23 2018-03-12 cation Selection ntation tion Scheme . FWMR/TRIMING/2018/CQ/CS/ 01 / Elaboration and impleme Component 2: Irrigation De Consultant Qualifi ntation of resettlement actio IDA / 55060 velopment and Management Post Open - National 200,000.00 0.00 Canceled 2018-07-03 2018-07-24 2018-08-10 2018-08-14 2018-08-28 2019-02-24 cation Selection n plan (RAP) for Jankarawa Irr . igation and other Projects. FMWR/TRIMING/2018/QCBS/ Component 1: Water Resour CS/01 / Supervision of Dam s Quality And Cost- Open - Internationa IDA / 55060 ces Management and Dam Prior 7,000,000.00 6,056,557.61 Signed 2018-04-10 2019-09-10 2018-05-01 2019-09-13 2018-06-14 2020-07-20 2018-07-05 2020-08-18 2018-07-12 2021-05-18 2018-08-14 2021-10-04 2018-10-19 2021-11-11 2022-02-22 afety improvement works at Based Selection l Operation Improvement. Bakolori, Zobe and Goronyo dams FWMR/TRIMING/2018/CQ/CS/ 02 / TA for review of existing studies and identification of Component 2: Irrigation De development options for Zob Consultant Qualifi IDA / 55060 velopment and Management Post Open - National 295,000.00 0.00 Canceled 2018-04-05 2018-04-19 2018-06-02 2018-07-02 2018-08-06 2018-12-28 e Irrigation Scheme and pref cation Selection . easibility studies of Dutse an d Mairuwa Dams for the deve lopment of gravity irrigation potentials in Katsina State. FWMR/TRIMING/2018/CQ/CS/ 03 / Elaboration and Impleme Component 2: Irrigation De Consultant Qualifi Under Implement ntation of Resettlement Actio IDA / 55060 velopment and Management Post Open - National 200,000.00 0.00 2018-04-05 2019-03-10 2018-04-26 2018-06-09 2018-07-09 2018-08-13 2019-02-09 cation Selection ation n Plan (RAP) for the Middle Ri . ma Valley Irrigation Scheme, Sokoto State FMWR/TRIMING/2018/CS/CQ/ Component 2: Irrigation De 04 / Review and Upgrade of f Consultant Qualifi IDA / 55060 velopment and Management Post Open - National 295,000.00 0.00 Canceled 2018-02-13 2018-03-06 2018-04-19 2018-05-19 2018-06-23 2018-12-20 easibility studies on Hadejia cation Selection . Valley Irrigation Project, Phas e 1 stage 2 NG-TRIMING NCO-76564-CS- Component 4: Institutional CQS / Recruitment of Schem Consultant Qualifi IDA / 55060 Development and Project Ma Post Open - National 20,000.00 0.00 Canceled 2018-09-20 2018-09-10 2018-09-27 2018-10-11 2018-10-25 2018-11-08 2019-11-03 e Safeguards Officer in Bakol cation Selection nagement. ori irrigation Project (BIP) (So cial Safeguards) Page 9 FMWR/TRIMING/2019/QCBS/ CS/01 / Consultancy contract Component 2: Irrigation De Quality And Cost- for works supervision of addit IDA / 55060 velopment and Management Prior Open - National 1,000,000.00 0.00 Canceled 2019-03-18 2019-04-01 2019-04-29 2019-05-27 2019-06-17 2019-07-08 2019-08-12 2022-08-11 Based Selection ional works (1400ha) at Bako . lori Irrigation Scheme (BIS) in cluding Jankarawa FMWR/TRIMING/2019/CQS/C S/02 / Feasibility studies and Component 1: Water Resour technical specification for re Consultant Qualifi IDA / 55060 ces Management and Dam Post Open - National 295,000.00 0.00 Canceled 2019-03-18 2019-06-03 2019-04-01 2019-05-06 2019-05-20 2019-06-17 2019-12-14 moval of aquatic weeds from cation Selection Operation Improvement. TRIMING dams and Reservoir s in Ruwan Kanya and Hadeji a Barrage FMWR/TRIMING/2019/QCBS/ CS/02 / Consultancy Service f Component 1: Water Resour or the Review and Completio Quality And Cost- Open - Internationa IDA / 55060 ces Management and Dam Prior 900,000.00 0.00 Canceled 2019-03-18 2019-04-01 2019-05-06 2019-05-20 2019-06-03 2019-07-01 2019-07-29 2021-07-28 n of the Catchment Manage Based Selection l Operation Improvement. ment Area (CMA) in Hydrolog ical Area 1. (Sokoto Rima Bas in FMWR/TRIMING/2019/CQS/C S/03 / Consultancy Services f Component 1: Water Resour Consultant Qualifi or improved hydrometry and IDA / 55060 ces Management and Dam Post Open - National 290,000.00 0.00 Canceled 2019-03-30 2019-06-03 2019-04-13 2019-05-18 2019-06-01 2019-06-22 2019-12-19 cation Selection IWRM of the Gongola sub-Bas Operation Improvement. in in the Upper Benue Basin. FMWR/TRIMING/2019/CQS/C S/04 / Technical Assistance o n Integrated Pest Manageme Component 3: Enhancing Ag Consultant Qualifi nt and safe use of chemicals IDA / 55060 ricultural Productivity and Su Post Open - National 150,000.00 123,623.50 Completed 2019-02-28 2019-02-26 2019-03-14 2019-04-18 2019-04-10 2019-05-02 2019-06-03 2019-05-30 2019-06-03 2019-11-26 2019-12-06 cation Selection for the Farmers Field Busines pport to Value Chains. s School facilitators and step down trainings for farmer fac ilitators FMWR/TRIMING/2018/QCBS/ Component 4: Institutional Quality And Cost- Open - Internationa CS/02 / Periodic M & E data c IDA / 55060 Development and Project Ma Prior 350,000.00 0.00 Canceled 2018-02-20 2018-03-13 2018-04-26 2018-05-24 2018-06-23 2018-07-28 2018-09-01 2019-09-01 Based Selection l ollection and midterm Impact nagement. evaluation FMWR/TRIMING/2019/CQS/C S/01 / Gender Based Violence Component 2: Irrigation De Consultant Qualifi mapping of TRIMING Project IDA / 55060 velopment and Management Prior Open - National 120,000.00 0.00 Canceled 2019-03-28 2019-03-13 2019-04-11 2019-03-18 2019-05-16 2019-05-30 2019-06-16 2019-10-14 cation Selection participating schemes and de . velopment of a proactive pre vention response plan NG-TRIMING NCO-114549-C S-QCBS / Consultancy Servic Component 4: Institutional Quality And Cost- Open - Internationa es for Periodic M&E Data Coll IDA / 55060 Development and Project Ma Prior 900,000.00 883,208.30 Signed 2019-05-30 2019-07-18 2019-06-13 2019-07-30 2019-07-11 2020-02-29 2019-08-08 2020-04-14 2019-08-22 2020-07-15 2019-09-19 2020-08-25 2019-10-17 2020-09-11 2022-03-31 Based Selection l ection, Impact Evaluations an nagement. d Completion Report for the TRIMING Project NG-TRIMING NCO-19031-CS- QCBS / Technical Assistance Component 2: Irrigation De Quality And Cost- Open - Internationa for WUA in Bakolori Irrigation IDA / 55060 velopment and Management Prior 2,156,440.00 0.00 Canceled 2014-12-12 2015-01-30 2015-04-14 2015-05-12 2015-07-11 2016-02-02 2018-03-05 2016-03-08 2019-06-19 Based Selection l Schemes and Middle Rima va . lley Irrigation Scheme FMWR/TRIMING/2020/QCBS/ CS/01 / TA Emergency Prepar Component 1: Water Resour edness Plan and Action Plan Quality And Cost- Open - Internationa IDA / 55060 ces Management and Dam Prior 1,500,000.00 0.00 Canceled 2020-04-23 2020-05-07 2020-06-11 2020-07-09 2020-07-23 2020-08-20 2020-09-17 2021-11-11 Framework and detailed stud Based Selection l Operation Improvement. ies of the effect of Dam Brea k on Downstream settlement for TRIMING Project Dams FMWR/TRIMING/2020/CQS/C S/01 / Gender Based Violence Component 2: Irrigation De Consultant Qualifi mapping of TRIMING Project IDA / 55060 velopment and Management Post Open - National 290,000.00 258,070.09 Signed 2020-05-30 2020-05-06 2020-06-06 2020-06-17 2020-07-11 2020-10-06 2020-08-10 2020-11-12 2020-08-31 2020-12-04 2020-11-29 cation Selection participating schemes and de . velopment of a proactive pre vention response plan FMWR/TRIMING/QCBS/14/00 2 / Regularization of Contract for Consultancy Services for Component 2: Irrigation De Technical Assistance for Wat Quality And Cost- Open - Internationa IDA / 55060 velopment and Management Prior 2,156,445.00 1,629,867.50 Signed 2017-05-30 2017-06-20 2017-08-03 2020-05-18 2017-08-31 2015-05-28 2017-09-30 2020-06-16 2017-10-28 2020-06-28 2017-12-02 2016-03-09 2020-02-02 er Users Associations and Sc Based Selection l . heme Management Develop ment at Bakolori (BIS) and Mi ddle Rima (MRVIS) Irrigation Schemes under TRIMING Proj ect FMWR/TRIMING/2020/CQS/C S/03 / Technical Assistance o Component 3: Enhancing Ag n Integrated Pest Manageme Consultant Qualifi Under Implement IDA / 55060 ricultural Productivity and Su Post Open - National 150,000.00 0.00 2020-04-30 2020-05-06 2020-05-21 2020-06-04 2020-07-02 2020-07-23 2020-08-20 2021-02-16 nt and safe use of chemicals cation Selection ation pport to Value Chains. on the use of scouting sheets , record keeping and data sto rage FMWR/TRIMING/QCBS/2015/ 01 / Regularization of subsisti Component 2: Irrigation De Quality And Cost- Open - Internationa ng Contract for Construction IDA / 55060 velopment and Management Prior 4,043,083.00 3,264,780.12 Signed 2015-01-04 2015-03-19 2016-03-09 2016-03-13 2016-09-12 2017-02-14 2020-09-10 2017-03-08 2017-03-08 2022-04-11 Based Selection l Supervision for Bakolori Irrig . ation Scheme Rehabilitation and Reconversion FMWR/TRIMING/2020/QCBS/ CS/02 / Consultancy Services Component 2: Irrigation De Quality And Cost- Open - Internationa for Engagement of Security IDA / 55060 velopment and Management Prior 1,800,000.00 1,645,986.11 Signed 2020-09-01 2020-08-28 2020-09-08 2020-09-01 2020-09-29 2021-01-08 2020-10-27 2021-02-10 2020-11-03 2021-07-31 2020-11-24 2021-09-21 2020-12-15 2021-09-30 2021-12-15 Based Selection l Management Firm at Bakolori . , Kano, Hadejia and Dadin-Ko wa Irrigation Schemes NG-TRIMING NCO-60760-CS- QCBS / Consultancy Services Component 1: Water Resour for Construction Supervision Quality And Cost- Open - Internationa IDA / 55060 ces Management and Dam Prior 5,000,000.00 0.00 Canceled 2016-08-10 2018-04-27 2016-08-10 2017-08-18 2018-05-01 2017-10-30 2017-10-30 2018-04-26 2018-05-17 2018-05-31 2022-05-31 of Kano River and Hadejia Va Based Selection l Operation Improvement. lley Irrigation Schemes, Dam s Safety and Rivers Training i n Hadejia-Jama’are River Basi ns FMWR/TRIMING/QCBS/2016/ 01 / TA for Construction Supe Component 1: Water Resour rvision of Kano River and Had Quality And Cost- Open - Internationa IDA / 55060 ces Management and Dam Prior 5,000,000.00 0.00 Canceled 2016-08-10 2016-08-10 2017-08-18 2017-10-30 2017-10-30 2018-04-13 2018-05-17 2018-06-07 2022-06-07 ejia Valley Irrigation Scheme Based Selection l Operation Improvement. s, Dams Safety and Rivers Tr aining in Hadejia-Jama’are Ri ver Basins Page 10 FMWR/TRIMING/2020/QCBS/ CS/03 / Consultancy Services for Feasibility Studies and De Component 1: Water Resour Quality And Cost- Open - Internationa Under Implement tailed Design of Benue River IDA / 55060 ces Management and Dam Prior 4,550,000.00 0.00 2020-11-30 2021-01-12 2020-12-07 2021-01-19 2021-02-08 2021-03-08 2021-04-07 2021-05-12 2021-06-09 2022-12-01 Based Selection l ation Basin Water Resources Devel Operation Improvement. opment and Management Pr ogram for Formulation of TRI MING Project II FMWR/TRIMING/2020/CQS/C S/03/01 / Consultancy Servic es for Preparation of an Envir Component 2: Irrigation De onmental and Social Manage Consultant Qualifi Under Implement IDA / 55060 velopment and Management Post Open - National 150,000.00 0.00 2020-12-05 2020-12-10 2020-12-10 2020-12-21 2021-01-07 2021-03-12 2021-01-21 2021-02-02 2021-05-03 ment Plan (ESMP) for Interve cation Selection ation . ntion to Support Livelihood O ptions for the Maradun Com munity Affected During the B akolori Dam Construction FWMR/TRIMING/2021/CQS/C S/01 / Consultancy Services f Component 2: Irrigation De or the Preparation of an Envir Consultant Qualifi Under Implement IDA / 55060 velopment and Management Post Open - National 200,000.00 0.00 2021-08-23 2021-08-12 2021-08-30 2021-08-24 2021-09-27 2021-10-11 2021-11-08 2022-02-06 onmental and Social Safegua cation Selection ation . rds Audit for the Transformin g Irrigation Management in N igeria (TRIMING) Project FWMR/TRIMING/2021/CQS/C S/02/01 / Consultancy Servic Component 2: Irrigation De Consultant Qualifi Under Implement es for Preparation and Imple IDA / 55060 velopment and Management Post Open - National 295,000.00 0.00 2021-08-16 2021-08-12 2021-08-23 2021-08-17 2021-09-20 2021-10-04 2021-10-18 2023-04-11 cation Selection ation mentation of a Resettlement . Action Plan for Jankarawa int erventions FMWR/TRIMING/2021/CQS/C S/03 / Technical Assistance t o implement the recommend Component 4: Institutional Consultant Qualifi Under Implement ation of the Gender Based Vi IDA / 55060 Development and Project Ma Post Open - National 295,000.00 0.00 2021-09-30 2021-10-25 2021-10-14 2021-11-05 2021-11-27 2022-02-16 2021-12-27 2022-01-24 2022-06-23 cation Selection ation olence (GBV) mapping exerci nagement. ses and establishment of ide ntified referral pathways alon g existing project structures FMWR/TRIMING/2021/QCBS/ CS/01 / Consultancy Services Component 2: Irrigation De for supervision of infrastructu Quality And Cost- Open - Internationa Under Implement IDA / 55060 velopment and Management Prior 4,200,000.00 0.00 2021-09-06 2022-06-19 2021-09-20 2021-11-01 2021-11-29 2021-12-29 2022-01-26 2022-03-02 2023-08-24 re and capacity building inclu Based Selection l ation . ding livelihood investment in Jankarawa community, Zamf ara State, Nigeria FMWR/TRIMING/2020/QCBS/ CS/03/01 / Consultancy Servi ces for Feasibility Studies an Component 1: Water Resour Quality And Cost- Open - Internationa d Detailed Design of Benue R IDA / 55060 ces Management and Dam Prior 4,550,000.00 0.00 Under Review 2021-09-12 2021-09-12 2021-09-26 2022-01-26 2021-11-07 2022-04-01 2021-12-07 2022-01-04 2022-02-08 2024-02-08 Based Selection l iver Basin Water Resources D Operation Improvement. evelopment and Managemen t Program for Formulation of TRIMING Project II FMWR/TRIMING/2021/CQS/C Component 3: Enhancing Ag S/04 / Technical Assistance f Consultant Qualifi Under Implement IDA / 55060 ricultural Productivity and Su Post Open - National 100,000.00 0.00 2021-12-23 2022-02-07 2022-01-10 2022-06-23 2022-02-14 2022-02-28 2022-03-28 2022-09-24 or Documentation and airing cation Selection ation pport to Value Chains. of success stories of TRIMING project activities FMWR/TRIMING/2021/CQS/C S/05 / TA to Support Sokoto Component 2: Irrigation De Rima River Basin Developme Consultant Qualifi Under Implement IDA / 55060 velopment and Management Post Open - National 200,000.00 0.00 2021-12-23 2022-05-24 2022-01-19 2022-02-23 2022-03-25 2022-04-22 2023-04-17 nt Authority (SRRBDA) in Cad cation Selection ation . astral Survey and re-allocatio n of farmlands to farmers in t he conversion area of BIS INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-TRIMING NCO-14061-CS- Component 3: Enhancing Ag CDS / Supervision of ADP on IDA / 55060 ricultural Productivity and Su Prior Direct Selection Direct 450,000.00 447,571.03 Completed 2016-11-11 2016-12-14 2016-09-23 2017-05-26 2017-10-10 2018-01-21 2019-03-21 Extension service delivery in pport to Value Chains. all TRIMING Project Schemes by IFDC NG-TRIMING NCO-19036-CS- CDS / Technical Assistance o Component 2: Irrigation De n Quality Assuarance and Qu IDA / 55060 velopment and Management Post Direct Selection Direct 90,000.00 75,000.00 Completed 2017-06-20 2017-02-12 2017-07-01 2017-06-02 2017-07-14 2017-06-20 2018-03-11 2019-07-10 ality Control of aerial(LiDar) s . urvey for Dadin-Kowa and Gu yuk proposed scheme (Gong ola Sub-Basin) NG-TRIMING NCO-19809-CS- CDS / Third phase of Technic al Assistance and Capacity B uilding on Integrated Pest Ma Component 3: Enhancing Ag nagement and Safe use of Ch IDA / 55060 ricultural Productivity and Su Post Direct Selection Direct 100,000.00 71,372.25 Completed 2017-09-29 2017-11-22 2017-10-09 2017-11-24 2017-12-13 2018-01-18 2018-06-11 2018-07-23 emicals targeted at the staffs pport to Value Chains. of the proposed consultancy on the Establishment of Farm ers Management Service Cen ters and retraining of the AD Ps FWMR/TRIMING/2018/IC/CS/ 01 / Preparation of site-specif Component 2: Irrigation De Individual Consult ic Environmental & Social Ma IDA / 55060 velopment and Management Post Open 100,000.00 0.00 Canceled 2018-07-03 2018-08-21 2018-09-11 2018-10-16 2019-04-14 ant Selection nagement Plan (ESMP) for Ja . nkarawa Irrigation and other Projects. FWMR/TRIMING/2018/SS/CS/ 01 / Consultancy services for Component 3: Enhancing Ag demonstration of small laser IDA / 55060 ricultural Productivity and Su Prior Direct Selection Direct 100,000.00 0.00 Canceled 2018-04-28 2018-05-08 2018-07-12 2018-09-18 leveling equipment/Techniqu pport to Value Chains. e for farm irrigation practices for TRIMING project sites. FWMR/TRIMING/2018/SS/CS/ 02 / 4th phase of TA and Cap acity Building on Integrated P Component 3: Enhancing Ag est Management and Safe us IDA / 55060 ricultural Productivity and Su Prior Direct Selection Direct 100,000.00 0.00 Canceled 2018-09-05 2018-09-15 2018-10-31 2019-04-29 e of Chemicals targeted at th pport to Value Chains. e staffs of the proposed cons ultancy on the Establishment of Farmers Management Ser vice Centers and retraining o f the ADPs Page 11 FWMR/TRIMING/2018/SS/CS/ Component 4: Institutional 03 / Consultancy Services for IDA / 55060 Development and Project Ma Post Direct Selection Direct 35,000.00 0.00 Canceled 2018-10-01 2018-10-11 2018-12-15 2019-06-13 computerized Accounting sof nagement. tware upgrade for TRIMING p roject stores FWMR/TRIMING/2018/IC/CS/ Component 4: Institutional 02 / Technical backstop servi Individual Consult IDA / 55060 Development and Project Ma Post Open 90,000.00 0.00 Canceled 2018-06-13 2018-07-18 2018-08-01 2018-08-29 2019-02-25 ces for the implementation of ant Selection nagement. TRIMING M&E system FWMR/TRIMING/2018/SS/CS/ Component 4: Institutional 04 / Consultancy Services for Pending Impleme IDA / 55060 Development and Project Ma Post Direct Selection Direct 95,000.00 0.00 2018-04-23 2018-05-07 2018-06-25 2018-08-24 Training of FMWR/PMU on FID ntation nagement. IC contract management FWMR/TRIMING/2018/IC/CS/ Component 4: Institutional Individual Consult 03 / Techanical Assistance _Ir IDA / 55060 Development and Project Ma Post Open 100,000.00 299,585.32 Signed 2018-03-12 2019-03-18 2018-04-30 2019-07-16 2018-05-21 2019-07-24 2018-06-25 2019-11-10 2018-12-22 ant Selection rigation Specialist nagement. FWMR/TRIMING/2018/IC/CS/ Component 4: Institutional Individual Consult 04 / Techanical Assistance_D IDA / 55060 Development and Project Ma Post Open 100,000.00 127,150.09 Signed 2018-03-12 2019-03-18 2018-04-09 2019-07-16 2018-04-13 2019-07-23 2018-04-27 2019-11-06 2019-04-27 ant Selection am Safety Specialist nagement. FWMR/TRIMING/2018/IC/CS/ Component 4: Institutional Individual Consult 05 / Techanical Assistance_C IDA / 55060 Development and Project Ma Post Open - National 100,000.00 126,962.63 Signed 2018-03-12 2019-03-18 2018-04-09 2019-07-16 2018-04-12 2019-10-15 2018-04-23 2019-11-01 2019-04-23 ant Selection ontract Management Speciali nagement. st FMWR/TRIMING/2018/IC/CS/ Component 4: Institutional 06 / Engagement of IT Consul Individual Consult IDA / 55060 Development and Project Ma Post Limited 100,000.00 79,641.06 Signed 2018-06-15 2020-08-10 2018-06-20 2020-08-14 2018-07-11 2020-09-14 2018-08-15 2020-12-21 2019-02-11 tant for the supervision of ER ant Selection nagement. DMS Implementation/Roll out NG-TRIMING NCO-75569-CS- CDS / Innovative Research an d Development on Participat Component 3: Enhancing Ag ory Soil Salinity/Sodicity Man IDA / 55060 ricultural Productivity and Su Prior Direct Selection Direct 400,000.00 327,263.92 Signed 2018-09-12 2018-12-12 2018-09-22 2018-02-06 2018-10-07 2019-03-07 2021-09-21 agement for Sustainable Cro pport to Value Chains. p Productivity under Irrigatio n and Improved Livelihood in Kano River Irrigation Scheme (KRIS) NG-TRIMING NCO-76575-CS- CDS / Addendun No. 1 to Sup Component 3: Enhancing Ag ervision of ADP on Extension IDA / 55060 ricultural Productivity and Su Prior Direct Selection Direct 495,000.00 1,363,377.36 Signed 2018-09-23 2018-10-14 2018-11-07 2018-11-18 2019-03-25 2019-11-13 service delivery in all TRIMIN pport to Value Chains. G Project Schemes by IFDC NG-TRIMING NCO-76531-CS- INDV / Recruitment of Sche Component 4: Institutional Individual Consult me Safeguards Officer in Had IDA / 55060 Development and Project Ma Post Open 20,000.00 0.00 Canceled 2018-09-20 2018-09-10 2018-10-11 2018-10-25 2018-11-08 2019-11-03 ant Selection ejia Jamare sub Basin with K nagement. RIS and HVIS (Social Safegua rds) NG-TRIMING NCO-76569-CS- INDV / Recruitment of Schem Component 4: Institutional Individual Consult e Safeguards Officer in Hadej IDA / 55060 Development and Project Ma Post Open 20,000.00 0.00 Canceled 2018-09-20 2018-09-10 2018-10-11 2018-10-25 2018-11-08 2019-11-03 ant Selection ia Valley irrigation Project (H nagement. VIP) (Social Safeguards) NG-TRIMING NCO-76582-CS- Component 4: Institutional INDV / Recruitment of Sche Individual Consult IDA / 55060 Development and Project Ma Post Open 20,000.00 0.00 Canceled 2018-09-20 2018-09-10 2018-10-11 2018-10-25 2018-11-08 2019-11-03 me Safeguards Officer in dad ant Selection nagement. inkowa Irrigation Scheme (So cial Safeguards) NG-TRIMING NCO-76584-CS- CDS / Addendum No. 1 - TA f or Dam Safety Assurance- E Component 1: Water Resour mergency Preparedness Plan IDA / 55060 ces Management and Dam Prior Direct Selection Direct 1,200,000.00 0.00 Canceled 2018-09-30 2018-10-21 2018-12-16 2020-12-05 and Action Plan Framework a Operation Improvement. nd detailed studies of the eff ect of Dam Break on Downstr eam settlement for TRIMING Project Dams (7. Nos) NG-TRIMING NCO-76532-CS- Component 1: Water Resour INDV / Technical Assistance f IDA / 55060 ces Management and Dam Prior Direct Selection Direct 100,000.00 0.00 Canceled 2018-09-25 2019-02-21 2018-10-14 2018-12-09 2020-11-28 or Implementation Support of Operation Improvement. WUA regulations NG-TRIMING NCO-75571-CS- CDS / Innovative Research an d Development for Identificat Component 3: Enhancing Ag ion and Implementation of La IDA / 55060 ricultural Productivity and Su Prior Direct Selection Direct 400,000.00 295,044.17 Signed 2018-09-12 2018-09-22 2018-02-08 2018-10-07 2019-03-07 2021-09-21 nd Administration and Consol pport to Value Chains. idation Approaches for Sustai nable Development of Dadin- Kowa Irrigation Project (DKIP) NG-TRIMING NCO-77750-CS- Component 2: Irrigation De CDS / Additional Studies and IDA / 55060 velopment and Management Prior Direct Selection Direct 300,000.00 240,321.94 Signed 2018-11-20 2018-11-06 2018-12-11 2018-03-22 2019-01-08 2019-02-18 2019-09-05 Design for the Jankarawa Inte . rvention as Part of the Bakol ori Irrigation Scheme NG-TRIMING NCO-83840-CS- Component 4: Institutional CDS / Consultancy Services f IDA / 55060 Development and Project Ma Prior Direct Selection Direct 250,000.00 0.00 Canceled 2018-10-31 2018-11-15 2018-11-28 2019-01-09 2019-04-17 or Periodic M & E data collect nagement. ion and Mid -Term Impact Ev aluation Review NG-TRIMING NCO-88280-CS- Component 4: Institutional INDV / Recruitment of TRIMIN Individual Consult IDA / 55060 Development and Project Ma Post Open 20,000.00 0.00 Canceled 2018-12-10 2018-11-27 2019-01-14 2019-01-21 2019-02-04 2020-02-04 G Project Secretary with parti ant Selection nagement. cular focus to the Project Coo rdinator’s Office NG-TRIMING NCO-88279-CS- Component 4: Institutional Individual Consult INDV / Recruitment of TRIMIN IDA / 55060 Development and Project Ma Post Open 20,000.00 0.00 Canceled 2018-12-10 2018-11-27 2019-01-21 2019-01-28 2019-02-11 2020-02-11 ant Selection G Project Front Desk Officer / nagement. Receptionist NG-TRIMING NCO-91462-CS- Component 2: Irrigation De Individual Consult INDV / TRIMING Security Coor IDA / 55060 velopment and Management Post Limited 100,000.00 0.00 Canceled 2018-12-14 2019-03-06 2018-12-19 2018-12-26 2019-01-09 2020-01-09 ant Selection dinator for BIS . FMWR/TRIMING/2019/INDV/C S/01 / Elaboration and imple Component 2: Irrigation De Individual Consult mentation of Resettlement A IDA / 55060 velopment and Management Post Limited 50,000.00 0.00 Canceled 2019-03-28 2019-04-11 2019-04-25 2019-05-16 2019-11-12 ant Selection ction Plan For additional work . s in Bakolori Irrigation Schem e Page 12 FMWR/TRIMING/2019/INV/CS Component 2: Irrigation De /02 / Engagement of TRIMING Individual Consult IDA / 55060 velopment and Management Post Limited 100,000.00 0.00 Canceled 2019-02-25 2019-03-02 2019-03-09 2019-04-06 2021-04-05 Security Coordinator for BIS f ant Selection . or initial period of two (2) ye ars FMWR/TRIMING/2019/INV/CS /03 / TA on Mentoring of SRB Component 1: Water Resour Individual Consult DA staff attached to Bakolori IDA / 55060 ces Management and Dam Post Limited 100,000.00 39,177.30 Signed 2019-02-25 2019-08-23 2019-03-11 2020-07-03 2019-03-25 2020-09-22 2019-04-29 2020-11-01 2021-04-28 ant Selection dam on dam safety operation Operation Improvement. s and instrumentation for tw o (2) years FMWR/TRIMING/2019/INV/CS /04 / TA on Mentoring of UBR Component 1: Water Resour Individual Consult DA staff attached to Dadin K IDA / 55060 ces Management and Dam Post Limited 100,000.00 39,177.30 Signed 2019-02-25 2019-08-23 2019-03-04 2020-07-03 2019-03-18 2020-09-22 2019-04-15 2020-11-01 2021-04-14 ant Selection owa dam on dam safety oper Operation Improvement. ations and instrumentation fo r two (2) years FMWR/TRIMING/2019/INDV/C Component 4: Institutional Individual Consult S/02 / Engagement of two (2 IDA / 55060 Development and Project Ma Post Limited 20,000.00 0.00 Canceled 2019-04-15 2019-04-29 2019-05-13 2019-06-10 2020-06-09 ant Selection Nos) Procurement Asssitant nagement. NG-TRIMING NCO-102152-C S-CDS / TA for Consultancy S Component 1: Water Resour ervices for Dam Safety of Da IDA / 55060 ces Management and Dam Prior Direct Selection Direct 350,000.00 311,431.74 Signed 2019-03-15 2019-07-22 2019-04-08 2019-08-05 2019-05-13 2020-05-20 2019-11-09 dinkowa Irrigation Scheme (D Operation Improvement. KIS) in upper Benue River Ba sin FMWR/TRIMING/2019/CDS/C S/01 / Consultancy Services f Component 2: Irrigation De or engagement of PSC-1 Sec IDA / 55060 velopment and Management Prior Direct Selection Direct 1,200,000.00 1,683,091.17 Terminated 2019-08-10 2019-07-24 2019-08-24 2019-07-25 2019-10-05 2019-11-01 2020-10-04 uirty firm for Provision of Pro . ject Risk Manager (PRM) and Security Coordinators at BIS, KRIS, HVIS and DKIS at TRIMI NG sites NG-TRIMING NCO-129623-C S-INDV / Upgrade of the Moni Component 4: Institutional Individual Consult toring and Evaluation (M&E) IDA / 55060 Development and Project Ma Post Limited 80,000.00 33,416.44 Signed 2019-09-25 2019-09-05 2019-10-02 2019-09-24 2019-10-16 2020-08-14 2019-11-13 2020-08-20 2020-05-11 ant Selection Application of the Transformi nagement. ng Irrigation Management in Nigeria (TRIMING) Project NG-TRIMING NCO-101098-C S-CDS / Engagement of Third Component 2: Irrigation De Party NGO through an MOU ( IDA / 55060 velopment and Management Prior Direct Selection Direct 50,000.00 0.00 Canceled 2019-03-18 2019-04-15 2019-05-13 2021-05-02 RAP Implementation) for Had . ejia Valley Irrigation Scheme (HVIS) NG-TRIMING NCO-101094-C S-CDS / Engagement of Third Component 2: Irrigation De Party NGO through an MOU ( IDA / 55060 velopment and Management Prior Direct Selection Direct 50,000.00 0.00 Canceled 2019-03-18 2019-04-15 2019-05-13 2022-04-27 RAP Implementation) for Bak . olori Irrigation Scheme (BIS) NG-TRIMING NCO-76523-CS- CDS / Engagement of Third P Component 2: Irrigation De arty NGO through an MOU ( IDA / 55060 velopment and Management Prior Direct Selection Direct 65,000.00 0.00 Canceled 2018-09-15 2018-09-25 2018-10-06 2021-09-20 RAP Implementation) for Kan . o River Irrigation Scheme (KR IS) NG-TRIMING NCO-76566-CS- CDS / Engagement of Third P Component 2: Irrigation De arty NGO through an MOU ( IDA / 55060 velopment and Management Post Direct Selection Direct 50,000.00 0.00 Canceled 2018-09-15 2018-10-25 2018-09-27 2018-10-14 2021-09-28 RAP Implementation) for Bak . olori Irrigation Scheme (BIS) NG-TRIMING NCO-76526-CS- CDS / Engagement of Third P Component 2: Irrigation De arty NGO through an MOU ( IDA / 55060 velopment and Management Post Direct Selection Direct 50,000.00 0.00 Canceled 2018-09-15 2018-10-25 2018-09-27 2018-10-14 2020-10-03 RAP Implementation) for Ha . dejia Valley Irrigation Schem e (HVIS) FMWR/TRIMING/2020/INDV/C S/01 / Technical Assistance f Component 3: Enhancing Ag Individual Consult or the training of farmer facili IDA / 55060 ricultural Productivity and Su Post Limited 25,000.00 21,912.10 Completed 2020-04-20 2020-03-12 2020-04-27 2020-03-16 2020-05-18 2020-07-01 2020-06-08 2020-09-11 2020-08-07 2020-12-29 ant Selection tators on farmer field and bu pport to Value Chains. siness school (FFBS) and on r ice production FMWR/TRIMING/2020/INDV/C S/02 / Technical Assistance f Component 4: Institutional Individual Consult Under Implement or GIS-Based Cataloguing an IDA / 55060 Development and Project Ma Post Limited 100,000.00 0.00 2020-06-30 2021-11-18 2020-07-14 2020-08-04 2020-09-01 2021-08-27 ant Selection ation d Indexing of Irrigation Infras nagement. tructure Assets of all the five (5) TRIMING Schemes FMWR/TRIMING/2020/CDS/C S/02/01 / TA for Construction Supervision of Kano River an Component 1: Water Resour d Hadejia Valley Irrigation Sc IDA / 55060 ces Management and Dam Prior Direct Selection Direct 2,793,651.00 2,710,686.36 Signed 2020-12-10 2021-01-25 2020-12-22 2021-02-01 2021-01-19 2021-08-03 2022-04-30 hemes, Dams Safety and Riv Operation Improvement. ers Training in Hadejia-Jama’ are River Basins works throu gh direct selection FWMR/TRIMING/2021/CDS/C S/01/01 / Consultancy Servic Component 3: Enhancing Ag es for Upscaling of Research Under Implement IDA / 55060 ricultural Productivity and Su Post Direct Selection Direct 200,000.00 0.00 2021-08-16 2021-11-17 2021-08-26 2021-11-22 2021-09-23 2023-03-17 on the Utilization of Tpypa fo ation pport to Value Chains. r Biogas and Animal Feed Pro duction in Hadejia Valley Irrig ation Scheme (HVIS) FWMR/TRIMING/2021/CDS/C S/02/01 / Consultancy Servic es for Upscaling of research Component 3: Enhancing Ag Under Implement on Applying Innovation Syste IDA / 55060 ricultural Productivity and Su Post Direct Selection Direct 200,000.00 0.00 2021-08-16 2021-11-17 2021-08-26 2021-11-22 2021-09-23 2023-03-17 ation m Approach in Rice Value Ch pport to Value Chains. ain Analysis and Developmen t for Competitive Market in B akolori Irrigation Scheme (BI S) FWMR/TRIMING/2021/CDS/C S/03/01 / Consultancy Servic es Upscaling of Research on Component 3: Enhancing Ag Testing and Promotion of Sys Under Implement IDA / 55060 ricultural Productivity and Su Post Direct Selection Direct 300,000.00 0.00 2021-08-16 2021-11-17 2021-08-26 2021-11-22 2021-09-23 2023-03-17 tem of Rice Intensification (S ation pport to Value Chains. RI) Practices for sustainable Rice Production in Middle Ri ma Valley Irrigation Scheme (MRVIS) and Dadinkowa Irrig ation Scheme (DKIS) Page 13 FMWR/TRIMING/2021/INDV/C S/01 / Preparation of an Envir Component 2: Irrigation De Individual Consult Under Implement onmental & Social Managem IDA / 55060 velopment and Management Post Open 100,000.00 0.00 2021-09-30 2021-12-07 2021-11-02 2021-11-16 2021-11-30 2022-01-29 ant Selection ation ent Plan (ESMP) for TRIMING . Project intervention at Dadin- Kowa Dam and reservoir FMWR/TRIMING/2021/INDV/C S/04 / TECHNICAL ASSISTANC Component 3: Enhancing Ag Individual Consult Under Implement E FOR IMPLEMENTATION OF F IDA / 55060 ricultural Productivity and Su Post Limited 100,000.00 0.00 2021-12-20 2022-02-04 2021-12-25 2022-01-08 2022-02-05 2022-09-03 ant Selection ation ARMERS MANAGEMENT AND pport to Value Chains. SERVICE DELIVERY CENTERS (FMC) FMWR/TRIMING/2021/INDV/C S/03 / TA on Follow Up Traini Component 2: Irrigation De ng Program for Water User A Individual Consult Under Implement IDA / 55060 velopment and Management Post Limited 100,000.00 0.00 2021-12-20 2022-01-31 2022-01-10 2022-01-31 2022-02-21 2023-08-15 ssociation and Scheme Mana ant Selection ation . gement Development in Bak olori and Middle Rima Valley Irrigation Schemes Page 14