PROCUREMENT PLAN (Textual Part) Project information: Sao Tome and Principe - WACA Resilience Investment Project - P162337 Project Implementation agency: Ministry of Public Works and Natural Resources, Directorate General of Environment Date of the Procurement Plan: July 2017 Period covered by this Procurement Plan: July 1st 2017 to June 30th, 2018 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Regulamento de Licitação e Contratações Publicas such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable for those contracts identified in the Procurement Plan tables Other Relevant Procurement Information.: Not Applicable PROCUREMENT Western and Central Africa : West Africa Coasta Areas Resilience Investment Project PLAN General Information Country: Western and Central Africa 2019-02-12 Bank’s Approval Date of the Original Procurement Plan: 2022-06-27 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P162337 GPN Date: 2017-12-29 Project Name: West Africa Coasta Areas Resilience Investment Project Loan / Credit No: IDA / D2890, TF / A7132, TF / B4205 Project Fiduciary and Administrative Agency Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 20/STP/COMP2/W/WACA/201 Component 2: Strengthening Request for Quota Single Stage - One E 2019-11-0 IDA / D2890 Post Limited 21,815.20 Signed 2019-03-16 2019-05-14 2019-05-11 2019-07-22 9 / Réparation et entretien d the Policy and Institutional F tions nvelope 7 es phares. ramework 01/STP/COMP3/W/WACA/201 9 / Construction des routes d' Component 3: Strengthening Single Stage - One E 2020-10-3 accès,d'égouts et d'autres inf IDA / D2890 National Physical and Social Post Request for Bids Open - National 0.00 Canceled 2020-01-13 2020-01-18 2020-02-29 2020-03-30 2020-05-04 nvelope 1 rastructures dans les zones d Investments 'expansion sécurisées. 02/STP/COMP3/W/WACA720 Component 3: Strengthening Single Stage - One E 2021-01-1 19 / Infrastructures sociales IDA / D2890 National Physical and Social Post Request for Bids Open - National 0.00 Canceled 2020-04-01 2020-04-06 2020-05-18 2020-06-17 2020-07-22 nvelope 8 pour Malanza, Santa catarina Investments et Praia Burra. 03/STP/COMP3/W/WACA/201 Component 3: Strengthening 9 / Construtions de maisons Request for Quota Single Stage - One E 2021-01-2 IDA / D2890 National Physical and Social Post Limited 0.00 Canceled 2020-06-06 2020-08-01 pour les plus vulnérables au tions nvelope 8 Investments Malanza, Santa Catarina et P raia Burra. 26/STP/COMP3/W/WACA/201 Component 3: Strengthening 9 / Reabilitação dos dispositi 2020-07-1 IDA / D2890 National Physical and Social Post Direct Selection Direct 33,182.29 Signed 2019-12-09 2019-12-13 2019-12-14 2019-12-12 2020-01-18 2019-12-26 vos de protecção do Rio de R 6 Investments ibeira Afonso contra inundaç ões 32/STP/COMP3/W/WACA/202 Component 3: Strengthening 0 / Obras de murro de proteç Single Stage - One E 2021-01-0 IDA / D2890 National Physical and Social Post Request for Bids Open - National 506,252.93 Signed 2020-03-17 2020-03-31 2020-03-22 2020-04-06 2020-05-03 2020-06-25 2020-06-02 2020-06-26 2020-07-07 2020-08-17 ão e ordenamento urbanístic nvelope 3 Investments o de Santa Catarina 33/STP/COMP3/W/WACA/202 Component 3: Strengthening Single Stage - One E 1,073,025.3 2021-01-0 0 / Obras de ordenamento ur IDA / D2890 National Physical and Social Post Request for Bids Open - National Signed 2020-03-17 2020-03-31 2020-03-22 2020-04-06 2020-05-03 2020-08-14 2020-06-02 2020-10-01 2020-07-07 2020-10-07 nvelope 6 3 banístico de Malanza e Praia Investments Burra 37/STP/COMP3/W/WACA/202 Component 3: Strengthening 0 / Obras de construção de in Single Stage - One E 2021-05-2 IDA / D2890 National Physical and Social Post Request for Bids Open - National 0.00 Canceled 2020-08-03 2020-08-08 2020-09-19 2020-10-19 2020-11-23 fraestruturas sociais em Mala nvelope 2 Investments nza, Praia Burra e Santa Cata rina 46/STP/COMP3/W/WACA/202 0 / Appui à la construction de Component 3: Strengthening s maisons (Coût de l'appui, d Open - Internationa Single Stage - One E 2021-05-2 IDA / D2890 National Physical and Social Post Request for Bids 0.00 Canceled 2020-08-10 2020-08-15 2020-09-26 2020-10-26 2020-11-30 u materiel et de l'accompagn l nvelope 9 Investments ement technique) à Malanza, à Praia Burra et à Santa Cata rina. 47/STP/COMP3/W/WACA/202 Component 3: Strengthening 0 / Preparation zone expansi Request for Quota Single Stage - One E 2021-09-2 IDA / D2890 National Physical and Social Post Limited 0.00 Canceled 2021-02-03 2021-03-31 on: urbanisation et infraestru tions nvelope 7 Investments tures sociales à Praia Abade. 53/STP/COMP3/W/WACA/202 Component 3: Strengthening 0 / Constructions de maisons Open - Internationa Single Stage - One E 2021-07-1 IDA / D2890 National Physical and Social Post Request for Bids 0.00 Canceled 2020-09-22 2020-10-16 2020-09-27 2020-10-21 2020-11-08 2020-12-08 2021-01-12 et infraestructures sociales e l nvelope 1 Investments n Santa Catarina, Malanza et Praia Burra Request for 65/STP/COMP3/W/WACA/202 Component 3: Strengthening Request for Quota Single Stage - One E Quotations ( 2022-02-2 1 / Construction de infrastruc IDA / D2890 National Physical and Social Post Limited 264,961.83 Signed 2021-07-07 2021-07-05 2021-09-01 2021-08-23 tions nvelope Non Bank-SP 8 tures sociales à Santa Catari Investments D) na et à Malanza. 56/STP/COMP3/W/WACA/202 1 / Drainage des eaux pluvial Request for B es et mur de protection contr Component 3: Strengthening ids - Small W Single Stage - One E 2,688,495.9 2022-06-1 e l'inondation marine à IÔ Gr IDA / D2890 National Physical and Social Post Request for Bids Open - National orks SPD (1 e Signed 2021-08-25 2021-09-30 2021-08-30 2021-10-05 2021-10-11 2021-11-30 2021-11-10 2022-05-24 2021-12-15 2022-05-20 nvelope 9 3 ande, Micoló et Praia Abade Investments nvelope proc et Préparation de zone d'exp ess) ansion sécurité à IÔ Grande, Micoló et Praia Abade Request for B 60/STP/COMP3/W/WACA/202 Component 3: Strengthening ids - Small W 1 / Construção de casas soci Single Stage - One E 2022-06-2 IDA / D2890 National Physical and Social Post Request for Bids Open - National orks SPD (1 e 960,282.18 Signed 2021-09-06 2021-12-09 2021-09-11 2022-01-12 2021-10-23 2022-03-03 2021-11-22 2022-03-30 2021-12-27 2022-04-29 ais em Santa Catarina, Micol nvelope 5 Investments nvelope proc ó, Malanza, Iô Grande, Praia ess) Burra e Praia Abade Request for B 73/STP/COMP3/W/WACA/202 Component 3: Strengthening ids - Small W 2 / Construção de infraestrut Single Stage - One E Pending Imp 2023-04-2 IDA / D2890 National Physical and Social Post Request for Bids Open - National orks SPD (1 e 0.00 2022-07-04 2022-07-09 2022-08-20 2022-09-19 2022-10-24 uras sociais em Praia Burra, nvelope lementation 2 Investments nvelope proc Micoló, Iô Grande e Praia Aba ess) de Request for 82/STP/COMP3/W/WACA/202 Component 3: Strengthening Quotations - 2 / Construção da ponte que l Request for Quota Single Stage - One E Pending Imp 2023-03-1 TF / B4205 National Physical and Social Post Open - National Small Works 0.00 2022-07-20 2022-09-14 iga Morro Peixe à Praia Gueg tions nvelope lementation 3 Investments (Emergency) ue SPD -Compet itive 71/STP/COMP3/W/WACA/202 Request for B 2 / Berma rochosa e rampa e Component 3: Strengthening ids - Small W m Pantufo; Berma rochosa e Single Stage - One E Under Imple 2023-02-2 IDA / D2890 National Physical and Social Post Request for Bids Open - National orks SPD (1 e 0.00 2022-05-12 2022-06-14 2022-05-17 2022-06-14 2022-06-28 2022-07-28 2022-09-01 parte da rede de drenagem e nvelope mentation 8 Investments nvelope proc m Praia Melão; Parte do queb ess) ra-mar e aterro em praias Lo chinga, Gamboa e Cruz GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 02/STP/COMP2/G/WACA/201 Component 2: Strengthening Open - Internationa Single Stage - One E 9 / Kit d'equipements de séc IDA / D2890 the Policy and Institutional F Post Request for Bids 267,258.69 Signed 2019-06-24 2019-09-17 2019-06-29 2019-09-20 2019-08-10 2019-10-21 2019-09-09 2019-10-21 2019-10-14 2020-10-22 2020-04-11 l nvelope urite en mer pour les pêcheu ramework rs. 03/STP/COMP2/G/WACA/201 9 / Acquisition de matériel inf Component 2: Strengthening Request for Quota Single Stage - One E ormatique et de logiciels dan TF / A7132 the Policy and Institutional F Post Open - National 57,751.70 Completed 2019-03-30 2019-05-25 2019-07-16 2019-11-21 2019-09-23 tions nvelope s le domaine de la surveillan ramework ce pour l'observatoire de l'en vironnement 04/STP/COMP4/G/WACA/201 9 / Acquisition de biens et de Component 4: National Coor Request for Quota Single Stage - One E IDA / D2890 Post Open - National 0.00 Canceled 2019-04-06 2019-06-01 2019-11-28 matériaux aux propriétaires dination tions nvelope pour la cession de terres. 21/STP/COMP4/G/WACA/201 Component 4: National Coor 9 / Acquisition de biens aux p IDA / D2890 Post Direct Selection Direct 4,700.00 Completed 2019-05-23 2019-05-27 2019-05-28 2019-06-05 2019-07-02 2019-06-11 2019-12-29 2019-06-12 dination roprietaires pour la cession d es terres. 27/STP/COMP4/G/WACA/201 9 / Aquisição de bens para os Component 4: National Coor Request for Quota Single Stage - One E IDA / D2890 Post Limited 6,969.30 Signed 2019-11-20 2019-12-23 2020-01-15 2020-02-18 2020-07-13 2020-02-26 proprietários pela concepção dination tions nvelope de terras em Praia Abade 29/STP/COMP4/G/WACA/201 Component 4: National Coor Under Imple 9 / Aquisição e instalação de IDA / D2890 Post Direct Selection Direct 0.00 2019-12-09 2019-12-16 2019-12-14 2019-12-23 2020-01-18 2020-07-16 dination mentation sistema de contabilidade e g estão financeira 38/STP/COMP4/G/WACA/202 Component 4: National Coor Request for Quota Single Stage - One E IDA / D2890 Post Limited 14,343.87 Signed 2020-03-28 2020-04-06 2020-05-23 2020-06-08 2020-11-19 0 / Equipamentos para a UGP dination tions nvelope 39/STP/COMP4/G/WACA/202 Component 4: National Coor 0 / Aquisição de software de IDA / D2890 Post Direct Selection Direct 8,880.00 Signed 2020-04-08 2020-04-10 2020-04-13 2020-04-15 2020-05-18 2020-04-30 2020-11-14 dination monitoria e avaliação RUCHE 52/STP/COMP3/G/WACA/202 Component 3: Strengthening 0 / Aquisição de uma moto c IDA / D2890 National Physical and Social Post Direct Selection Direct 3,018.79 Completed 2020-06-15 2020-06-22 2020-06-20 2020-07-07 2020-07-25 2020-07-01 2021-01-21 2020-07-02 arrinha Investments 54/STP/COMP4/G/WACA/202 Component 4: National Coor Request for Quota Single Stage - One E IDA / D2890 Post Limited 40,400.50 Signed 2022-01-18 2022-01-27 2022-03-15 2022-04-08 2022-09-11 2 / Aquisição de uma Pick up dination tions nvelope 63/STP/COMP4/G/WACA/202 2 / Aquisição de equipament Component 4: National Coor Request for Quota Single Stage - One E Under Imple TF / A7132 Post Limited 0.00 2022-04-10 2022-03-29 2022-06-05 2022-12-02 o suplementar para drone: b dination tions nvelope mentation ateria e telefone portátil 85/STP/COMP3/G/WACA/202 Component 3: Strengthening Request for Quota Single Stage - One E Pending Impl 2 / Aquisição de três portátei TF / A7132 National Physical and Social Post Open - National 0.00 2022-07-03 2022-08-28 2023-02-24 tions nvelope ementation s e uma fotocopiadora para U Investments GP 86/STP/COMP3/G/WACA/202 Component 3: Strengthening 2 / Apetrechamento das esco Request for Quota Single Stage - One E Pending Impl IDA / D2890 National Physical and Social Post Limited 0.00 2022-07-03 2022-08-28 2023-02-24 las de Santa Catarina e Mala tions nvelope ementation Investments nza com mobiliário NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 01/STP/COMP2/S/WACA/201 Component 2: Strengthening Request for Quota Single Stage - One E 9 / Aquisition peinture pour IDA / D2890 the Policy and Institutional F Post Open - National 0.00 Canceled 2019-05-20 2019-07-15 2020-01-11 tions nvelope Marquage des pirogues. ramework CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 02/STP/COMP3/C/WACA/201 Component 3: Strengthening 9 / Dessins techniques pour l Consultant Qualifi IDA / D2890 National Physical and Social Post Open - National 65,815.47 Signed 2019-02-08 2019-04-24 2019-03-01 2019-06-12 2019-04-14 2019-10-10 2019-05-14 2019-10-17 2019-06-18 2019-10-17 2019-12-15 a planification spatiale de zo cation Selection Investments nes d'expansion sûres 34/STP/COMP3/C/WACA/202 0 / Fiscalização das obras de Component 3: Strengthening Consultant Qualifi ordenamento urbanístico em IDA / D2890 National Physical and Social Post Open - National 133,492.96 Signed 2020-03-17 2020-03-31 2020-04-07 2020-04-27 2020-05-21 2020-07-08 2020-06-20 2020-09-28 2020-07-25 2020-08-24 2021-01-21 cation Selection S.Tomé e Príncipe (Santa Cat Investments arina, Malanza e Praia Burra) 45/STP/COMP3/C/WACA/202 Component 3: Strengthening 0 / Supervision des travaux c Consultant Qualifi IDA / D2890 National Physical and Social Post Open - National 0.00 Canceled 2020-05-11 2020-04-08 2020-06-01 2020-07-15 2020-08-14 2020-09-18 2021-03-17 onstruction des oeuvres soci cation Selection Investments aux à S.Tomé et à RAP. 44/STP/COMP3/C/WACA/202 Component 3: Strengthening 0 / Design d'oeuvres pour les Consultant Qualifi IDA / D2890 National Physical and Social Post Open - National 196,330.00 Signed 2020-04-23 2020-04-25 2020-05-14 2020-07-12 2020-06-27 2020-09-22 2020-07-27 2020-12-18 2020-08-31 2020-12-18 2021-02-27 travaux des communités (Pa cation Selection Investments ntufo,Praia Melão, Praia Gam boa-Lochinga-Cruz) 48/STP/COMP3/C/WACA/202 Component 3: Strengthening 0 / Etude d'impact environne Consultant Qualifi Open - Internationa IDA / D2890 National Physical and Social Post 88,393.37 Signed 2020-05-15 2020-12-16 2020-06-05 2021-01-07 2020-07-19 2021-04-06 2020-08-18 2021-05-05 2020-09-22 2021-04-19 2021-03-21 mentale et sociale au Pantuf cation Selection l Investments o, Praia Melão et Praia Gamb oa-Lochinga-Cruz 57/STP/COMP3/C/WACA/202 1 / Supervision des travaux d Component 3: Strengthening 'aménagement des zones d'e Consultant Qualifi IDA / D2890 National Physical and Social Post Limited 0.00 Canceled 2021-08-27 2021-09-10 2021-10-10 2021-11-14 2022-05-13 xpansion à Iô Grande et Mico cation Selection Investments ló et des travaux de drainage et mur de protection à Iô Gra nde et Micoló Page 2 58/STP/COMP3/C/WACA/202 1 / Supervisão de trabalhos d e ordenamento das zonas de Component 3: Strengthening expansão em Iô Grande, Mic Consultant Qualifi IDA / D2890 National Physical and Social Post Limited 100,000.00 Signed 2021-09-08 2021-09-14 2021-09-22 2021-12-27 2021-10-22 2022-06-08 2021-11-26 2022-06-08 2022-05-25 oló e em Praia Abade e de tr cation Selection Investments abalhos de drenagem, proteç ão costeira e muro de proteç ão em Iô Grande, Micoló e e m Praia Abade 59/STP/COMP3/C/WACA/202 1 / Supervision des travaux c Component 3: Strengthening Consultant Qualifi onstruction des maisons soci IDA / D2890 National Physical and Social Post Limited 60,000.00 Signed 2021-09-15 2022-03-21 2021-09-29 2022-04-08 2021-10-29 2022-06-09 2021-12-03 2022-06-10 2022-06-01 cation Selection aux à Santa Catarina, Micoló, Investments Iô Grande Malanza, à Praia Burra et Praia Abade 79/STP/COMP2/C/WACA/202 Component 2: Strengthening 2 / Assistência técnica intern Consultant Qualifi Open - Internationa Under Implement TF / B4205 the Policy and Institutional F Post 0.00 2022-03-17 2022-03-17 2022-04-07 2022-03-17 2022-05-21 2022-06-20 2022-07-25 2023-01-21 acional para elaboração do pl cation Selection l ation ramework ano de ordenamento costeiro e marítimo 74/STP/COMP3/C/WACA/202 Component 3: Strengthening Consultant Qualifi Pending Impleme 2 / Fiscalização das infraestr IDA / D2890 National Physical and Social Post Open - National 0.00 2022-11-01 2022-11-22 2023-01-05 2023-02-04 2023-03-11 2023-09-07 cation Selection ntation uturas sociais em S. Tomé e Investments na RAP 83/STP/COMP3/C/WACA/202 Component 3: Strengthening 2 / Fiscalização da obras de c Consultant Qualifi Under Implement TF / A7132 National Physical and Social Post Open - National 0.00 2022-05-06 2022-05-05 2022-05-27 2022-05-06 2022-07-10 2022-08-09 2022-09-13 2023-03-12 onstrução da ponte que liga cation Selection ation Investments Morro Peixe à Praia guegue 72/STP/COMP3/C/WACA/202 2 / Supervision des travaux d Component 3: Strengthening Consultant Qualifi Pending Impleme 'adaptation dans des commu TF / B4205 National Physical and Social Post Open - National 0.00 2022-05-20 2022-06-10 2022-07-24 2022-08-23 2022-09-27 2023-03-26 cation Selection ntation nautés de Praia Melão, Pantu Investments fo, Lochinga, Gamboa e Cruz INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 01/STP/COMP2/C/WACA/201 Component 2: Strengthening 9 / Diagnostic de la situation Individual Consult TF / A7132 the Policy and Institutional F Post Open 48,973.00 Completed 2019-02-08 2019-04-18 2019-03-29 2019-09-05 2019-04-19 2019-09-05 2019-05-24 2019-08-28 2019-11-20 2019-12-30 de la météorologie maritime ant Selection ramework pour la création d'un centre de prévision maritime 04/STP/COMP2/C/WACA/201 Component 2: Strengthening 9 / Assistance technique à l'I Individual Consult TF / A7132 the Policy and Institutional F Post Open 0.00 Canceled 2019-05-27 2019-05-12 2019-07-15 2019-08-05 2019-09-09 2020-03-07 NM pour la préparation et la t ant Selection ramework ransmission d'informations m étéorologiques sur TVS 05/STP/COMP2/C/WACA/201 Component 2: Strengthening 9 / Conseil en techniques de Individual Consult TF / A7132 the Policy and Institutional F Post Limited 20,000.00 Completed 2019-05-24 2019-08-21 2019-05-29 2019-10-03 2019-06-19 2019-10-17 2019-07-24 2019-10-18 2020-01-20 2019-11-15 suivi et de traitement de don ant Selection ramework nées pour les indicateurs de projet 07/STP/COMP2/C/WACA/201 Component 2: Strengthening Individual Consult 9 / Appui à la loi de gestion d TF / A7132 the Policy and Institutional F Prior Open 0.00 Canceled 2019-04-24 2019-06-24 2019-06-12 2019-07-03 2019-08-07 2020-02-03 ant Selection es risques et catastrophes ramework 09/STP/COMP2/C/WACA/201 Component 2: Strengthening Individual Consult TF / A7132 Prior Open 0.00 Canceled 2019-04-25 2019-06-13 2019-07-04 2019-08-08 2020-02-04 9 / Appui au cadre juridique p the Policy and Institutional F ant Selection our le littoral ramework 10/STP/COMP4/C/WACA/STA Component 4: National Coor Individual Consult FF/2019 / Spécialiste en suivi TF / A7132 Post Open 18,000.00 Signed 2019-01-31 2019-02-13 2019-03-21 2019-04-16 2019-04-11 2019-04-17 2019-05-16 2019-04-05 2019-11-12 dination ant Selection et évaluation 11/STP/COMP4/C/WACA/STA Component 4: National Coor Individual Consult FF/2019 / Spécialiste en com IDA / D2890 Post Limited 10,411.00 Signed 2019-01-31 2019-02-21 2019-02-05 2019-05-27 2019-02-26 2019-06-14 2019-04-02 2019-06-11 2019-09-29 dination ant Selection munication à temps partiel 12/STP/COMP4/C/WACA/STA Component 4: National Coor Individual Consult IDA / D2890 Post Open 21,600.00 Signed 2019-01-31 2019-02-13 2019-03-21 2019-04-16 2019-04-11 2019-04-17 2019-05-16 2019-04-05 2019-11-12 FF/2019 / Hiring a civil engin dination ant Selection eer 06/STP/COMP2/C/WACA/201 Component 2: Strengthening Individual Consult 9 / Amélioration de la diffusio TF / A7132 the Policy and Institutional F Post Open 11,327.50 Signed 2019-03-20 2019-04-18 2019-05-08 2019-07-10 2019-05-29 2019-07-22 2019-07-03 2019-06-28 2019-12-30 ant Selection n de messages. ramework 03/STP/COMP2/C/WACA/201 9 / Réalisation du diagnostic Component 2: Strengthening Individual Consult de la situation du studio de t TF / A7132 the Policy and Institutional F Post Open 0.00 Canceled 2019-04-01 2019-09-26 2019-05-20 2019-06-10 2019-07-15 2020-01-11 ant Selection élévision pour la diffusion d'i ramework nformations météorologiques 22/C/AFAP/STAFF/2019 / Spé Component 4: National Coor cialiste en sauvegardes envir IDA / D2890 Post Direct Selection Direct 32,181.60 Signed 2019-08-09 2019-08-08 2019-08-19 2019-08-20 2019-10-23 2019-01-01 2020-04-20 dination onnemental et sociales 23/C/AFAP/STAFF/2019 / Assi Component 4: National Coor IDA / D2890 Post Direct Selection Direct 32,181.60 Signed 2019-08-09 2019-08-08 2019-08-19 2019-08-20 2019-10-23 2019-01-01 2020-04-20 stente de operações dination 24/C/AFAP/STAFF/2019 / Spé Component 4: National Coor IDA / D2890 Prior Direct Selection Direct 33,000.00 Signed 2019-08-09 2019-09-19 2019-08-19 2019-09-25 2019-10-23 2019-01-01 2020-04-20 cialiste en passation de marc dination hés 25/C/AFAP/STAFF/2019 / Ges Component 4: National Coor IDA / D2890 Post Direct Selection Direct 33,000.00 Signed 2019-08-09 2019-08-08 2019-08-19 2019-08-20 2019-10-23 2019-01-01 2020-04-20 tor financeiro adjunto dination 08/STP/COMP3/C/WACA/201 Component 3: Strengthening Individual Consult 9 / Soutien à la mise en œuvr TF / A7132 National Physical and Social Post Open 0.00 Canceled 2020-02-10 2020-03-30 2020-04-20 2020-05-25 2020-11-21 ant Selection e de solutions végétatives Investments 28/STP/COMP4/C/WACA/201 Component 4: National Coor Under Implement 9 / Auditoria as contas do an IDA / D2890 Post Direct Selection Direct 0.00 2019-12-20 2019-12-19 2019-12-30 2019-12-23 2020-03-04 2020-08-31 dination ation o de 2018 do Projecto WACA . 30/STP/COMP3/C/WACA/201 Component 3: Strengthening Individual Consult 9 / Levantamento topográfico IDA / D2890 National Physical and Social Post Limited 2,600.00 Signed 2019-12-30 2020-01-13 2020-01-04 2020-03-06 2020-01-25 2020-03-11 2020-02-29 2020-03-11 2020-08-27 ant Selection da zona de expansão segura Investments de Micoló Page 3 36/STP/COMP3/C/WACA/202 Component 3: Strengthening Individual Consult 0 / Desenhos técnicos das ca IDA / D2890 National Physical and Social Post Limited 13,200.00 Signed 2020-03-20 2020-04-06 2020-03-25 2020-05-04 2020-04-15 2020-06-26 2020-05-20 2020-06-29 2020-11-16 ant Selection sas e infraestruturas sociais Investments 35/STP/COMP3/C/WACA/202 Component 3: Strengthening 0 / Estudos técnicos de orden IDA / D2890 National Physical and Social Post Direct Selection Direct 137,960.00 Signed 2020-03-20 2020-04-06 2020-03-30 2020-04-13 2020-06-03 2020-04-23 2020-11-30 amento urbanístico em Iô Gr Investments ande, Micoló e Praia Abade 31/STP/COMP4/C/WACA/202 Component 4: National Coor IDA / D2890 Post Direct Selection Direct 18,000.00 Signed 2020-03-23 2019-12-30 2020-04-02 2020-01-02 2020-06-06 2020-01-03 2020-12-03 0 / Assistente de Direcção dination 40/STP/COMP2/C/WACA/202 Component 2: Strengthening 0 / Diagnostic des réglement Individual Consult IDA / D2890 the Policy and Institutional F Post Open 88,108.10 Signed 2020-04-16 2020-04-17 2020-06-04 2021-05-05 2020-06-25 2021-06-22 2020-07-30 2021-06-29 2021-01-26 ations et des cadres politique ant Selection ramework s côtières, et les textes d'app lication. 41/STP/COMP2/C/WACA/202 Component 2: Strengthening 0 / Appui aux réformes législ Individual Consult IDA / D2890 the Policy and Institutional F Prior Open 8,740.00 Signed 2020-04-20 2020-07-07 2020-06-08 2021-01-27 2020-06-29 2021-02-11 2020-08-03 2021-02-12 2021-01-30 atives visant à promouvoir la ant Selection ramework sécurité maritime (actualisati on du decret) 43/STP/COMP2/C/WACA/202 0 / Appui à la préparation des Component 2: Strengthening bulletins météorologiques et Individual Consult IDA / D2890 the Policy and Institutional F Post Open 0.00 Canceled 2020-09-08 2020-10-27 2020-11-17 2020-12-22 2021-06-20 formation des cadres techniq ant Selection ramework ues de INM dans la préparati on de prévisions météorologi ques. 42/STP/COMP2/C/WACA/202 0 / Assistance technique pour Component 2: Strengthening Individual Consult un système de partage d'info IDA / D2890 the Policy and Institutional F Post Open 0.00 Canceled 2020-09-01 2020-10-20 2020-11-10 2020-12-15 2021-06-13 ant Selection rmations climatolgiques (à co ramework mbiner avec le studio COROB OR) 49/STP/COMP2/C/WACA/202 0 / Recrutement du juriste na Component 2: Strengthening Individual Consult tional pour l’analyse du cadr TF / A7132 the Policy and Institutional F Post Limited 9,500.00 Signed 2021-05-14 2021-05-14 2021-05-19 2021-06-28 2021-06-09 2021-07-06 2021-07-14 2021-07-07 2022-01-10 ant Selection e legal et institutionnel pour l ramework a gestion des zones côtières 50/STP/COMP2/C/WACA/202 Component 2: Strengthening Individual Consult 0 / Elaboração da Lei de gest TF / A7132 the Policy and Institutional F Post Open 55,700.00 Signed 2021-05-17 2021-05-17 2021-07-05 2021-07-26 2021-07-26 2021-08-16 2021-08-30 2021-08-12 2022-02-26 ant Selection ão de riscos e catástrofes ramework 64/STP/COMP2/C/WACA/202 Component 2: Strengthening 1 / Recrutement du juriste na Individual Consult TF / A7132 the Policy and Institutional F Post Limited 7,500.00 Signed 2021-05-26 2021-05-27 2021-05-31 2021-06-11 2021-06-21 2021-08-16 2021-07-26 2021-08-16 2022-01-22 tional pour l’appui a l' elabor ant Selection ramework ation de loi de gestion des ris ques et catastrophes 67/STP/COMP4/C/WACA/202 Component 4: National Coor Individual Consult IDA / D2890 Post Limited 29,750.00 Signed 2021-07-14 2021-07-15 2021-07-19 2021-10-14 2021-08-09 2021-11-03 2021-09-13 2021-11-15 2022-03-12 1 / Revisão a meio percurso dination ant Selection do projecto 66/STP/COMP3/C/WACA/202 Component 3: Strengthening 1 / Supervision des constructi Individual Consult IDA / D2890 National Physical and Social Post Limited 17,050.00 Signed 2021-08-09 2021-07-15 2021-08-14 2021-08-09 2021-09-04 2021-09-13 2021-10-09 2021-08-26 2022-04-07 on des infrastructures sociau ant Selection Investments x à Santa Catarina et Malanz a 68/STP/COMP4/C/WACA/202 Component 4: National Coor Individual Consult IDA / D2890 Post Limited 0.00 Canceled 2021-07-21 2021-07-26 2021-08-16 2021-09-20 2022-03-19 1 / Revisão a meio percurso dination ant Selection 69/STP/COMP2/C/WACA/202 Component 2: Strengthening 1 / Elaboração dos regulame Individual Consult IDA / D2890 the Policy and Institutional F Post Open 15,960.00 Signed 2021-08-30 2021-10-06 2021-10-18 2022-03-16 2021-11-08 2022-05-11 2021-12-13 2022-05-12 2022-06-11 ntos da lei de exploração e e ant Selection ramework xtração de inertes 55/STP/COMP2/C/WACA/202 1 / Recrutamento de um cons Component 2: Strengthening Individual Consult ultor para ministrar Formaçã TF / B4205 the Policy and Institutional F Post Open 11,835.60 Signed 2021-09-06 2021-09-14 2021-10-25 2021-12-28 2021-11-15 2021-12-29 2021-12-20 2021-12-29 2022-06-18 ant Selection o para Observatório ambient ramework al sobre plataforma DR clima 70/STP/COMP4/C/WACA/STA Component 4: National Coor Individual Consult FF/2021 / Contratação de en IDA / D2890 Post Open 18,000.00 Signed 2021-12-13 2021-12-13 2022-01-31 2022-01-31 2022-02-21 2022-02-21 2022-03-28 2022-02-21 2022-09-24 dination ant Selection genheiro civil 62/STP/COMP4/C/STAFF/WAC Component 4: National Coor Individual Consult IDA / D2890 Post Limited 6,000.00 Signed 2022-01-13 2022-01-18 2022-01-18 2022-01-20 2022-02-08 2022-03-07 2022-03-15 2022-03-07 2022-09-11 A/2022 / Condutor/Animador dination ant Selection para UGT 61/STP/COMP2/C/WACA/202 Component 2: Strengthening 1 / Recrutement d'un expert i Individual Consult TF / A7132 the Policy and Institutional F Post Open 0.00 Canceled 2021-05-19 2022-01-18 2021-07-07 2021-07-28 2021-09-01 2022-02-28 nternational pour l'élaboratio ant Selection ramework n du plan spatial maritime. 84/STP/C/WACA/2022 / Avali Component 3: Strengthening ação ambiental e social simpl Individual Consult Under Implement TF / A7132 National Physical and Social Post Limited 0.00 2022-05-26 2022-05-24 2022-05-31 2022-06-09 2022-06-21 2022-07-26 2023-01-22 ificada para as obras da Pont ant Selection ation Investments e pedonal de Morro Peixe à P raia Guegue 87/STP/COMP2/C/WACA/202 Component 2: Strengthening Individual Consult Pending Impleme 2 / Contratação de um inform TF / A7132 the Policy and Institutional F Post Limited 0.00 2022-06-30 2022-07-05 2022-07-26 2022-08-30 2023-02-26 ant Selection ntation ático a part time ramework Page 4