The World Bank Implementation Status & Results Report Turkey Organized Industrial Zones Project (P171645) Turkey Organized Industrial Zones Project (P171645) EUROPE AND CENTRAL ASIA | Turkey | Finance, Competitiveness and Innovation Global Practice | IBRD/IDA | Investment Project Financing | FY 2021 | Seq No: 2 | ARCHIVED on 25-Jan-2022 | ISR49227 | Implementing Agencies: Republic of Turkey, Ministry of Industry and Technology Key Dates Key Project Dates Bank Approval Date: 25-Jan-2021 Effectiveness Date: 20-Jul-2021 Planned Mid Term Review Date: 26-May-2023 Actual Mid-Term Review Date: Original Closing Date: 31-Dec-2026 Revised Closing Date: 31-Dec-2026 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) The PDO is to increase the efficiency, environmental sustainability and competitiveness of select Organized Industrial Zones (OIZs) in Turkey. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Components Table Name Supporting the infrastructure and the enabling environment for OIZ sustainability, competitiveness and efficiency:(Cost $290.00 M) Technical assistance, capacity building and project management:(Cost $10.00 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Satisfactory Overall Implementation Progress (IP) Satisfactory Satisfactory Overall Risk Rating Moderate Moderate Implementation Status and Key Decisions The project became effective on July 20, 2022. Since then the Bank and MoIT teams have been working toward establishing a Project Implementation Unit (PIU) in MoIT, finalizing various documents and engaging with OIZs and other stakeholders, such as OSBUK and regional development agencies. The first call for OIZ sub-project applications was launched on November 2, 2021 via the online MEYDIP platform. So far, 33 sub-project applications have been received and are currently being evaluated. The Bank team will conduct a supervision mission January 18-21 to assist with outstanding issues. 1/25/2022 Page 1 of 6 The World Bank Implementation Status & Results Report Turkey Organized Industrial Zones Project (P171645) Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance Moderate Moderate Moderate Macroeconomic Moderate Moderate Substantial Sector Strategies and Policies Moderate Moderate Moderate Technical Design of Project or Program Moderate Moderate Moderate Institutional Capacity for Implementation and Substantial Substantial Substantial Sustainability Fiduciary Moderate Moderate Substantial Environment and Social Substantial Substantial Substantial Stakeholders Low Low Low Other Moderate Moderate Moderate Overall Moderate Moderate Moderate Results PDO Indicators by Objectives / Outcomes Increase the efficiency, environmental sustainability and competitiveness of select OIZs in Turkey IN01092377 ►Water savings from OIZ green investments (Cubic meters/year, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 6,628,000.00 Date 25-Jan-2021 -- 10-Jan-2022 31-Dec-2026 IN01092381 ►Energy savings from OIZ both basic and green infrastructure investments (MWh/year, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 16,579.68 Date 25-Jan-2021 -- 10-Jan-2022 31-Dec-2026 IN01092323 ►Annual reduction in CO2 emissions due to supported investments (Metric tons/year, Custom) Baseline Actual (Previous) Actual (Current) End Target 1/25/2022 Page 2 of 6 The World Bank Implementation Status & Results Report Turkey Organized Industrial Zones Project (P171645) Value 0.00 -- 0.00 18,434.00 Date 25-Jan-2021 -- 10-Jan-2022 31-Dec-2026 IN01092324 ►Share of OIZs that attract new investments (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 30.00 Date 25-Jan-2021 -- 10-Jan-2022 31-Dec-2026 Intermediate Results Indicators by Components Supporting infrastructure and the enabling environment for OIZ sustainability, comp. and efficiency IN01092339 ►Number of firms that benefit from OIZ basic and/or green infrastructure investments (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 1,000.00 Date 25-Jan-2021 -- 10-Jan-2022 31-Dec-2026 IN01092325 ►Renewable energy generated due to OIZ green infrastructure investments (MWh/year, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 32,600.00 Date 25-Jan-2021 -- 10-Jan-2022 31-Dec-2026 IN01092378 ►Wastewater treated in new/upgraded facilities (Cubic meters/year, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 29,200,000.00 Date 25-Jan-2021 -- 10-Jan-2022 31-Dec-2026 IN01092379 ►Number of employees trained in the innovation centers and model factories (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 2,160.00 Date 25-Jan-2021 -- 10-Jan-2022 31-Dec-2026 IN01092340 1/25/2022 Page 3 of 6 The World Bank Implementation Status & Results Report Turkey Organized Industrial Zones Project (P171645) ►Proportion of private sector investments facilitated in OIZs as compared to disbursed loan for infrastructure development (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 3.00 Date 25-Jan-2021 -- 10-Jan-2022 31-Dec-2026 IN01092380 ►Number of collaborative projects supported between OIZ firms and academia/research establishments (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 10.00 Date 25-Jan-2021 -- 10-Jan-2022 31-Dec-2026 IN01092386 ►The establishment of a database/system to track, collect and disaggregate gender-related data (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No -- No Yes Date 25-Jan-2021 -- 10-Jan-2022 31-Dec-2026 Technical assistance and capacity building IN01092387 ►Number of laws/standards/regulations or amendments to current regulations enacted to support Green OIZ development (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 1.00 Date 25-Jan-2021 -- 10-Jan-2022 31-Dec-2026 IN01092391 ►Number of OIZs certified as Green OIZs (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 10.00 Date 25-Jan-2021 -- 10-Jan-2022 31-Dec-2026 IN01092392 ►Number of firms reporting that they benefit from improved OIZ basic, green and competitiveness infrastructure (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 1,000.00 Date 25-Jan-2021 -- 10-Jan-2022 31-Dec-2026 IN01092393 1/25/2022 Page 4 of 6 The World Bank Implementation Status & Results Report Turkey Organized Industrial Zones Project (P171645) ►Number of firms reporting that they understand the benefits of certified Green OIZs (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 700.00 Date 25-Jan-2021 -- 10-Jan-2022 31-Dec-2026 Performance-Based Conditions Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P171645 IBRD-92050 Effective USD 300.00 300.00 0.00 1.16 298.80 0.4% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P171645 IBRD-92050 Effective 25-Jan-2021 26-Feb-2021 20-Jul-2021 31-Dec-2026 31-Dec-2026 Cumulative Disbursements 1/25/2022 Page 5 of 6 The World Bank Implementation Status & Results Report Turkey Organized Industrial Zones Project (P171645) PBC Disbursement Achievement Disbursed amount in Disbursement % PBC ID PBC Type Description Coc PBC Amount Status Coc for PBC Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 1/25/2022 Page 6 of 6