Sample Procurement Plan (Text in italic font is meant for instruction to staff and should be deleted in the final version of the PP) (This is only a sample with the minimum content that is required to be included in the PAD. The detailed procurement plan is still mandatory for disclosure on the Bank’s website in accordance with the guidelines. The initial procurement plan will cover the first 18 months of the project and then updated annually or earlier as necessary). I. General 1. Bank’s approval Date of the procurement Plan: Updated Procurement Plan, M 2. Date of General Procurement Notice: Dec 24, 2006 3. Period covered by this procurement plan: The procurement period of project covered from year June 2010 to December 2012 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ 500,000 All 2. NCB (Goods) Above US$ 100,000 First contract 3. ICB (Works) Above US$ 15 million All 4. NCB (Works) Above US$ 5 million All 5. (Non-Consultant Services) Below US$ 100,000 First contract [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: [Refer to the relevant CDD project July 9, 2010 implementation document approved by the Bank or delete if not applicable] 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project XYZ 04/01/2010 issued by 5. Any Other Special Procurement Arrangements: [including advance procurement and retroactive financing, if applicable] 5 ICB works packages will be financed under retroactive financing 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) [List the Packages which require Bank’s prior review first and then the other packages] 1 2 3 4 5 6 7 Ref. Descripti Estimat Packages Dome Review Comme No. on ed stic by Bank nts Cost Prefe (Prior / US$ rence Post) million (yes/ no) Summary 82 5 No Prior of the ICB (Works) Summary 43.77 15 No Prior of the ICB (Goods) Summary 64.53 18 No Post 1st of the NCB contrac (Works) t for Prior Review Summary 1.86 4 No Post 1st of the NCB contrac (Goods) t for Prior Review Summary 0.45 1 No Prior of the ICB (Non- Consultant Services) III. Selection of Consultants July 9, 2010 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 100,000 2. Single Source (Firms) All 3. Individual Above US$ 50,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimat Package Review Comment of ed s by Bank s Assignmen Cost (Prior / t US$ Post) million Summary 4.17 7 Prior of number of contracts that will be let under QCBS Summary 0.83 1 Prior CQS of number of contracts that will be let under other methods July 9, 2010 July 9, 2010 PROCUREMENT Ethiopia : Second Agricultural Growth Project PLAN General Information Country: Ethiopia 2017-03-27 Bank’s Approval Date of the Original Procurement Plan: 2022-07-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P148591 GPN Date: Project Name: Second Agricultural Growth Project Loan / Credit No: IDA / 56050 Ministry of Agriculutre and Natural Resources Development Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Project Management, Capaci DC/UNOPS / 102 Vechicles a UN Agencies (Dire IDA / 56050 ty Building and Monitoring a Prior Direct 3,000,000.00 4,759,844.78 Completed 2016-07-14 2017-02-22 2017-04-10 2017-04-12 2017-07-13 2018-01-09 nd 688 Motor Cycles ct) nd Evaluation ICB/FAGP/CU-003 / Row plan Agricultural Public Support S Open - Internationa Single Stage - One E IDA / 56050 Post Request for Bids 500,000.00 0.00 Canceled 2017-03-31 2017-04-06 2017-04-05 2017-04-24 2017-05-17 2017-07-17 2017-06-09 2017-07-14 2018-01-10 ter ervices l nvelope Project Management, Capaci NCB/FAGP/CU-007 / Equiping Single Stage - One E IDA / 56050 ty Building and Monitoring a Post Request for Bids Open - National 535,600.00 359,643.68 Completed 2017-04-05 2017-04-03 2017-04-10 2017-05-10 2017-05-01 2017-06-09 2017-05-05 2017-07-14 2018-11-30 2018-01-10 2019-01-02 Data Center for MoANR nvelope nd Evaluation Project Management, Capaci NCB/FAGP/CU-002 / Standby Single Stage - One E IDA / 56050 ty Building and Monitoring a Post Request for Bids Open - National 450,000.00 166,469.90 Completed 2017-04-05 2017-01-05 2017-04-07 2017-05-06 2017-02-08 2017-06-04 2017-05-08 2017-07-03 2017-08-28 2017-12-30 2019-01-30 Diesel Generator nvelope nd Evaluation Project Management, Capaci NCB/FAGP/CU-008 / Comput Single Stage - One E IDA / 56050 ty Building and Monitoring a Post Request for Bids Open - National 360,000.00 66,576.46 Completed 2017-04-05 2017-04-10 2017-04-06 2017-04-12 2017-05-15 2017-05-15 2017-06-01 2017-07-18 2017-07-06 2017-09-04 2018-01-02 2017-10-25 er and IT equipments nvelope nd Evaluation Project Management, Capaci NCB/FAGP/CU-009 / Office e Single Stage - One E IDA / 56050 ty Building and Monitoring a Post Request for Bids Open - National 765,000.00 49,271.82 Completed 2017-04-05 2017-04-07 2017-04-06 2017-04-12 2017-05-05 2017-05-09 2017-05-22 2017-07-28 2017-06-26 2017-09-05 2017-12-23 2017-10-24 quipment nvelope nd Evaluation ICB/AGP/CU-005 / Provision o Agriculture Marketing and V Open - Internationa Single Stage - One E f new parent stock for poultr IDA / 56050 Post Request for Bids 200,000.00 0.00 Canceled 2017-04-17 2017-04-22 2017-05-19 2017-06-06 2017-07-06 2017-08-10 2018-02-06 alue Chains l nvelope y multiplication centers ICB/FAGP/CU-004 / Nitrogen Agriculture Marketing and V Open - Internationa Single Stage - One E IDA / 56050 Post Request for Bids 1,100,000.00 0.00 Canceled 2017-04-24 2017-05-09 2017-05-09 2017-06-23 2017-07-23 2017-11-01 2017-08-27 2018-02-23 plant and spare parts alue Chains l nvelope ICB/AGP/CU-002 / Seed quali Agricultural Public Support S Open - Internationa Single Stage - One E IDA / 56050 Prior Request for Bids 1,600,000.00 0.00 Canceled 2017-06-01 2017-06-06 2017-07-21 2017-08-17 2017-09-21 2018-03-20 ty control Laboratory equipm ervices l nvelope ents NCB/AGP/CU-07/09 / Ear Tag Agriculture Marketing and V Single Stage - One E IDA / 56050 Post Request for Bids Open - National 100,000.00 0.00 Canceled 2017-05-26 2017-05-31 2017-07-12 2017-08-11 2017-09-15 2018-03-14 (printed and black) for cows alue Chains nvelope Project Management, Capaci SH/FAGP/CU-001/17 / Station Request for Quota Single Stage - One E IDA / 56050 ty Building and Monitoring a Post Limited 30,000.00 1,925.16 Completed 2017-05-20 2019-02-28 2017-06-11 2019-02-28 2017-07-26 2019-03-28 ery items tions nvelope nd Evaluation Project Management, Capaci MOANR/AGPII/UNOPS1 / 620 UN Agencies (Dire IDA / 56050 ty Building and Monitoring a Prior Direct 2,155,000.00 2,085,429.87 Completed 2016-07-14 2017-02-22 2017-05-16 2017-05-16 2017-08-16 2018-01-16 motor cycles ct) nd Evaluation Project Management, Capaci SH/FAGP/CU/001 / four statio Request for Quota Single Stage - One E Under Imple IDA / 56050 ty Building and Monitoring a Post Limited 17,500.00 0.00 2017-09-24 2017-11-12 2018-05-11 n furniture tions nvelope mentation nd Evaluation NCB/AGP/CU-10/2010 / Antiv Project Management, Capaci Single Stage - One E irus soft ware including instal IDA / 56050 ty Building and Monitoring a Post Request for Bids Open - National 110,000.00 34,598.12 Completed 2017-09-15 2017-09-04 2017-09-18 2017-10-18 2017-09-29 2017-11-17 2017-11-01 2017-12-22 2018-02-20 2018-06-20 2018-04-03 nvelope ation nd Evaluation SH/FAGP/CU-001/10 / Audiov Project Management, Capaci Request for Quota Single Stage - One E isual equipment s for public r IDA / 56050 ty Building and Monitoring a Post Limited 160,000.00 0.00 Canceled 2017-10-11 2017-12-06 2018-06-04 tions nvelope elation/communication of pro nd Evaluation ject SH/FAGP/CU-002/10 / Self pr Agricultural Public Support S Request for Quota Single Stage - One E opelled reaper binder harves IDA / 56050 Post Limited 100,000.00 47,027.02 Completed 2017-10-23 2017-05-26 2017-12-06 2017-06-15 2018-06-04 2020-11-03 ervices tions nvelope ting machine FAGP/CU/DC/003/10 / Hass V Agricultural Public Support S IDA / 56050 Prior Direct Selection Direct 540,000.00 0.00 Canceled 2017-12-14 2017-12-19 2018-01-23 2018-07-22 ariety Avocado Scion ervices NCB/FAGP/CU-001/10 / Agric Agricultural Public Support S Single Stage - One E ultural Mechanization Machin IDA / 56050 Post Request for Bids Open - National 350,000.00 299,913.20 Signed 2017-12-07 2017-11-19 2017-12-12 2018-01-23 2017-12-26 2018-02-22 2018-03-06 2018-03-29 2018-03-30 2018-09-25 ervices nvelope es for Demonstration NCB/FAGP/CU/002/10 / Com Agricultural Public Support S Single Stage - One E IDA / 56050 Post Request for Bids Open - National 280,000.00 0.00 Canceled 2018-01-01 2018-01-06 2018-02-17 2018-03-19 2018-04-23 2018-10-20 puter and Servers for NAIC ervices nvelope Project Management, Capaci NCB/FAGP/CU-013/2017 / Au Single Stage - One E IDA / 56050 ty Building and Monitoring a Post Request for Bids Open - National 200,000.00 80,949.31 Signed 2018-01-05 2018-01-08 2018-01-10 2018-02-09 2018-02-08 2018-02-24 2018-03-26 2018-03-25 2018-04-16 2018-06-23 2019-07-31 dio Visual equipments nvelope nd Evaluation Project Management, Capaci NCB/FAGP/CU-002/10 / vehic Request for Quota Single Stage - One E IDA / 56050 ty Building and Monitoring a Post Limited 500,000.00 169,147.50 Completed 2018-01-19 2018-05-14 2018-03-03 2018-05-23 2018-06-01 2018-08-23 les tions nvelope nd Evaluation ET-MOANRD-47309-GO-RFB Agricultural Public Support S Open - Internationa Single Stage - One E IDA / 56050 Post Request for Bids 540,000.00 0.00 Canceled 2018-02-05 2018-02-10 2018-03-24 2018-04-23 2018-05-28 2018-11-24 / Aocado Scion Hass Variety ervices l nvelope SH/AGP-CU/05/2018 / plant c Agricultural Public Support S Request for Quota Single Stage - One E IDA / 56050 Post Limited 50,000.00 45,669.83 Completed 2018-08-18 2019-02-20 2018-10-13 2019-03-15 2019-04-11 2019-04-02 linic facility materials ervices tions nvelope Page 1 DC/MOALR/-AGP2/LAB/O2/17 Project Management, Capaci UN Agencies (Dire Pending Impl / Procurement of Trucks with IDA / 56050 ty Building and Monitoring a Post Direct 1,028,015.75 0.00 2016-10-05 2016-10-06 2018-08-24 2019-05-24 ct) ementation liquid Nitrogen Storage tank nd Evaluation and crane SH/AGP-CU/06/2018 / Desk t Project Management, Capaci Request for Quota Single Stage - One E op computer and photocopy IDA / 56050 ty Building and Monitoring a Post Limited 40,000.00 0.00 Canceled 2018-11-18 2019-01-13 2019-07-12 tions nvelope machine nd Evaluation Project Management, Capaci SH/AGP-CU/08/2018 / Statio Request for Quota Single Stage - One E IDA / 56050 ty Building and Monitoring a Post Limited 17,000.00 8,304.92 Completed 2018-12-03 2019-02-04 2019-01-28 2019-03-28 2019-07-27 2019-07-31 nary items tions nvelope nd Evaluation SH/AGP-CU/09/2018 / water l Request for Quota Single Stage - One E IDA / 56050 Small Scale Irrigation Post Limited 65,000.00 0.00 Canceled 2018-12-26 2019-02-20 2019-08-19 ifting and saving equipment tions nvelope ET-MOANRD-82712-GO-RFB Agricultural Public Support S Single Stage - One E / Equipping central veterinar IDA / 56050 Post Request for Bids Open - National 215,000.00 173,991.45 Completed 2018-12-28 2018-12-14 2019-01-02 2018-12-17 2019-02-13 2019-01-16 2019-03-15 2019-04-15 2019-04-19 2019-05-13 2019-10-16 2021-01-18 ervices nvelope y drug and feed quality contr ol laboratory ET-MOANRD-94168-GO-RFB Agricultural Public Support S Open - Internationa Single Stage - One E IDA / 56050 Post Request for Bids 750,000.00 1,163,376.82 Signed 2019-01-24 2019-02-06 2019-01-29 2019-02-12 2019-03-12 2019-03-28 2019-04-11 2019-06-21 2019-05-16 2019-08-22 2019-11-12 2020-08-11 / Agricultural machinery ervices l nvelope ICB/FAGP/CU/G-004/09 / Liqu Agricultural Public Support S Open - Internationa Single Stage - One E IDA / 56050 Prior Request for Bids 3,100,000.00 0.00 Canceled 2018-01-16 2018-01-21 2018-03-04 2018-04-03 2018-05-23 2018-05-08 2018-11-04 id Nitrogen Plant and Spare p ervices l nvelope arts Project Management, Capaci DC/FAGP/CU-12/2017 / Docu IDA / 56050 ty Building and Monitoring a Prior Direct Selection Direct 600,000.00 0.00 Canceled 2017-11-28 2017-12-03 2018-01-07 2018-07-06 ment Management System nd Evaluation ET-MOANRD-95997-GO-RFB Agricultural Public Support S Open - Internationa Single Stage - One E / Liquid nitrogen plant(15 lit/ IDA / 56050 Prior Request for Bids 3,500,000.00 2,049,608.87 Signed 2019-03-18 2019-10-25 2019-03-23 2019-11-21 2019-05-07 2020-01-02 2019-06-06 2020-03-07 2019-07-11 2020-12-01 2020-01-07 ervices l nvelope h 7 pcs and 20 lit/h 3 pcs ) a nd spare part ET-MOANRD-118287-GO-RF Agricultural Public Support S Single Stage - One E Under Imple IDA / 56050 Post Request for Bids Open - National 300,000.00 0.00 2019-06-13 2019-10-29 2019-06-18 2019-10-29 2019-07-30 2019-08-29 2019-10-03 2020-03-31 B / Computer and IT Equipme ervices nvelope mentation nt ET-MOANRD-111906-GO-RF Agricultural Public Support S Open - Internationa Single Stage - One E IDA / 56050 Post Request for Bids 900,000.00 109,463.96 Completed 2019-07-31 2019-10-10 2019-08-05 2019-10-14 2019-09-16 2019-11-28 2019-10-16 2020-02-05 2019-11-20 2020-03-04 2020-05-18 2020-08-20 B / Printed ear tag for animal ervices l nvelope s ET-MOANRD-124213-GO-RF Agricultural Public Support S Open - Internationa Single Stage - One E Under Imple B / Procurement of 4170 unit IDA / 56050 Prior Request for Bids 2,156,896.00 0.00 2019-09-16 2020-02-07 2019-09-23 2020-02-28 2019-11-08 2020-04-21 2019-12-08 2020-01-12 2020-07-10 ervices l nvelope mentation s of tablet for AGP II impleme nter. ICB/FAGP/CU/G-001/10 / Plan Agricultural Public Support S Open - Internationa Single Stage - One E t protection laboratory equip IDA / 56050 Prior Request for Bids 1,700,000.00 0.00 Canceled 2017-10-09 2017-10-14 2017-11-25 2017-12-25 2018-01-29 2018-07-28 ervices l nvelope ment for regions ET-MOANRD-136461-GO-RF Agricultural Public Support S Single Stage - One E Under Imple B / plant protection & Seed la IDA / 56050 Post Request for Bids Open - National 990,000.00 0.00 2019-11-28 2019-10-30 2019-12-03 2019-11-06 2020-01-14 2020-02-13 2020-03-19 2020-09-15 ervices nvelope mentation boratory equipment. Project Management, Capaci ET-MOANRD-143196-GO-RF Request for Quota Single Stage - One E Under Imple IDA / 56050 ty Building and Monitoring a Post Limited 32,000.00 0.00 2019-12-05 2020-01-30 2020-01-30 2020-07-28 Q / Car Tyre tions nvelope mentation nd Evaluation ET-MOANRD-177303-GO-RF Project Management, Capaci Request for Quota Single Stage - One E Q / Sanitation materials for c IDA / 56050 ty Building and Monitoring a Post Limited 100,000.00 70,275.07 Completed 2020-06-13 2020-08-03 2020-08-08 2020-07-28 2021-02-04 2020-08-03 tions nvelope orona (Covid-19) pre protecti nd Evaluation ve ET-MOANRD-188503-GO-RF Project Management, Capaci Request for Quota Single Stage - One E Q / Indoor digital signage for IDA / 56050 ty Building and Monitoring a Post Limited 100,000.00 82,908.26 Completed 2020-08-26 2020-08-19 2020-10-21 2020-09-17 2021-04-19 2020-09-18 tions nvelope MoA infrastructure upgrade nd Evaluation Project Management, Capaci SH/AGP-CU/07/2018 / Office Request for Quota Single Stage - One E IDA / 56050 ty Building and Monitoring a Post Limited 45,000.00 0.00 Canceled 2018-12-05 2019-01-30 2019-07-29 Furniture tions nvelope nd Evaluation ET-MOANRD-210969-GO-RF Agriculture Marketing and V Open - Internationa Single Stage - One E Pending Impl B / Artificial Insemination Equ IDA / 56050 Post Request for Bids 999,999.00 0.00 2021-01-10 2021-01-15 2021-03-01 2021-04-30 2021-06-04 2021-12-01 alue Chains l nvelope ementation ipment Procurement ET-MOANRD-210757-GO-UN UN Agencies (Dire Pending Impl / Procurement of 15- Four Wh IDA / 56050 Small Scale Irrigation Post Direct 720,000.00 0.00 2021-01-10 2021-01-15 2021-02-23 2021-06-23 ct) ementation eel Drive Vehicles LNB/FAGP/CU/008/10 / Lime Agricultural Public Support S Single Stage - One E IDA / 56050 Post Request for Bids Limited 358,000.00 0.00 Canceled 2018-05-04 2018-05-09 2018-06-20 2018-07-20 2018-08-24 2019-02-20 for the treatment of soil acidi ervices nvelope ty ET-MOANRD-223244-GO-RF Agriculture Marketing and V Open - Internationa Single Stage - One E IDA / 56050 Post Request for Bids 1,000,000.00 856,521.45 Signed 2021-03-28 2021-05-20 2021-04-04 2021-08-06 2021-05-19 2021-08-12 2021-06-18 2021-11-04 2021-07-22 2022-01-28 2021-12-19 B / liquid Nitrogen spare part alue Chains l nvelope ET-MOANRD-231199-GO-RF Q / Procurement of one lapto Project Management, Capaci Request for Quota Single Stage - One E p computer, one printer ,two IDA / 56050 ty Building and Monitoring a Post Limited 3,500.00 1,723.95 Completed 2021-05-17 2021-05-14 2021-05-29 2021-06-01 2021-06-28 2021-07-07 tions nvelope power point pointers, one De nd Evaluation sktop computer with accesso ries ET-MOANRD-233938-GO-RF Project Management, Capaci Q / All-In-One 4K Conference Request for Quota Single Stage - One E Pending Impl IDA / 56050 ty Building and Monitoring a Post Limited 4,500.00 0.00 2021-08-16 2021-09-20 2021-10-04 Cam with auto-detect mic an tions nvelope ementation nd Evaluation d audio for virtual meeting ET-MOANRD-246484-GO-RF Q / Procurement of laborator Request for Quota Single Stage - One E Under Imple IDA / 56050 Agricultural Research Post Limited 5,000.00 3,848.92 2021-08-28 2021-08-25 2021-09-27 2021-10-12 y Falcon tubes , Silica Gel, Po tions nvelope mentation ly-bag, 3 Labeler, Mortar and pestle Project Management, Capaci ET-MOANRD-260731-GO-RF Request for Quota Single Stage - One E IDA / 56050 ty Building and Monitoring a Post Limited 490,000.00 497.96 Completed 2021-11-22 2021-11-12 2022-01-03 2021-11-23 2022-01-17 2021-11-25 Q / Procurement of Vehicles tions nvelope nd Evaluation ET-MOANRD-294764-GO-RF Project Management, Capaci Request for Quota Single Stage - One E Pending Impl Q / Procurement of two mini IDA / 56050 ty Building and Monitoring a Post Limited 3,000.00 0.00 2022-05-27 2022-07-01 2022-07-08 tions nvelope ementation LCD projector with Speaker nd Evaluation ET-MOANRD-294766-GO-RF Project Management, Capaci Request for Quota Single Stage - One E Pending Impl Q / Procurement of Tyre and i IDA / 56050 ty Building and Monitoring a Post Limited 36,000.00 0.00 2022-06-05 2022-07-10 2022-07-24 tions nvelope ementation nner tubes nd Evaluation Page 2 ET-MOANRD-294772-GO-RF Project Management, Capaci Request for Quota Single Stage - One E Pending Impl Q / Stationer and other consu IDA / 56050 ty Building and Monitoring a Post Limited 9,000.00 0.00 2022-06-07 2022-07-05 2023-01-01 tions nvelope ementation mable items nd Evaluation ET-MOANRD-294774-GO-RF Project Management, Capaci Request for Quota Single Stage - One E Pending Impl Q / Smart-board 86 Inch 2 an IDA / 56050 ty Building and Monitoring a Post Limited 50,000.00 0.00 2022-06-03 2022-07-08 2022-07-29 tions nvelope ementation d 75 inch 1 nd Evaluation Project Management, Capaci ET-MOANRD-294779-GO-RF Request for Quota Single Stage - One E Pending Impl IDA / 56050 ty Building and Monitoring a Post Limited 2,000.00 0.00 2022-06-06 2022-07-04 2022-07-18 Q / Multi-factional Printer tions nvelope ementation nd Evaluation ET-MOANRD-302852-GO-DIR Pending Impl / Procurement of 97 Double C IDA / 56050 Small Scale Irrigation Prior Direct Selection Direct 4,000,000.00 0.00 2022-07-27 2022-08-03 2022-09-14 2023-03-13 ementation abin Vehicles ET-MOANRD-302853-GO-DIR Pending Impl IDA / 56050 Small Scale Irrigation Post Direct Selection Direct 1,050,000.00 0.00 2022-07-27 2022-08-03 2022-09-14 2023-03-13 / Procurement of 350 Motorc ementation ycle ET-MOANRD-302858-GO-RF Open - Internationa Single Stage - One E Pending Impl B / Procurement of 15,000 Irr IDA / 56050 Small Scale Irrigation Prior Request for Bids 18,000,000.00 0.00 2022-08-02 2022-08-09 2022-09-20 2022-10-20 2022-11-24 2023-05-23 l nvelope ementation igation Pump for Wheat Deve lopment NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SH/FAGP/CU/NCS-007/10 / V Agricultural Public Support S Request for Quota Single Stage - One E IDA / 56050 Post Limited 35,000.00 0.00 Canceled 2018-05-05 2018-06-30 2018-12-27 enues for exhibition at hawas ervices tions nvelope sa DS/FAGP/CU/NCS-001/10 / A Project Management, Capaci dvertising &Broadcasting on IDA / 56050 ty Building and Monitoring a Post Direct Selection Direct 20,000.00 17,947.52 Signed 2018-10-12 2018-10-10 2018-10-17 2018-10-15 2018-11-21 2018-10-24 2019-05-20 TV and Radio using governm nd Evaluation ent owned Media ET-MOANRD-87884-NC-DIR / Single Stage - One E Training on small scale irrigat IDA / 56050 Small Scale Irrigation Post Direct Selection Direct - National 125,000.00 106,246.22 Completed 2018-11-30 2018-11-19 2018-12-07 2019-05-24 2019-01-17 2019-06-25 2019-03-19 2019-08-30 nvelope ion (SSI) guidelines ET-MOANRD-91874-NC-DIR / Agricultural Public Support S Pending Impl IDA / 56050 Post Direct Selection Direct 35,000.00 0.00 2018-12-17 2018-12-22 2019-01-26 2019-07-25 Training of Development Age ervices ementation nts (DA) AGP/CU/CONS-012/10 / Direc Agricultural Public Support S t contract of government ow IDA / 56050 Post Direct Selection Direct 25,000.00 0.00 Canceled 2017-05-15 2017-05-20 2017-06-29 2017-12-26 ervices ned Alage ATVET to roviding training Project Management, Capaci DC/FAGP/CU-12/2019 / Docu Under Imple IDA / 56050 ty Building and Monitoring a Prior Direct Selection Direct 1,500,000.00 0.00 2019-06-12 2020-04-01 2019-06-17 2020-04-01 2019-07-22 2020-01-18 ment management system mentation nd Evaluation ET-MOANRD-126769-NC-RFB / Ministry of Agriculture IT(inf Agricultural Public Support S Single Stage - One E IDA / 56050 Post Request for Bids Open - National 795,000.00 0.00 Canceled 2019-09-16 2019-09-21 2019-11-02 2019-12-02 2020-01-06 2020-07-04 ormation technology) infrast ervices nvelope ructure up grade . CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual FAGP/CU/CON-003/09 / Progr Project Management, Capaci Quality And Cost- am Implemntation Pefrorman IDA / 56050 ty Building and Monitoring a Prior Open - National 245,000.00 246,075.00 Completed 2016-04-08 2016-04-27 2016-07-11 2016-08-12 2016-10-14 2017-03-23 2017-05-26 2017-04-18 2017-03-27 2017-09-18 2018-03-08 Based Selection ce Review nd Evaluation AGP/CU/CONS-002/09 / Inde Project Management, Capaci Quality And Cost- Open - Internationa pendent procurement Audit o IDA / 56050 ty Building and Monitoring a Prior 150,000.00 65,170.00 Completed 2017-05-19 2017-06-09 2017-07-23 2018-07-09 2017-08-20 2018-11-02 2017-09-19 2018-12-04 2017-10-24 2019-01-22 2017-11-28 2019-02-28 2018-11-28 2020-11-02 Based Selection l f AGP nd Evaluation FAGP/CU/CON-006/09 / Train Quality And Cost- IDA / 56050 Small Scale Irrigation Post Open - National 250,000.00 58,447.06 Completed 2017-05-12 2017-05-16 2017-06-02 2017-07-16 2017-06-19 2017-08-13 2017-07-19 2017-09-12 2017-09-21 2017-10-17 2017-10-12 2017-11-21 2017-12-04 2018-11-21 2018-02-28 ing on SSI Feasibility Study a Based Selection nd Design FAGP/CU/CONS-22/2018 / De Agricultural Public Support S Quality And Cost- Under Implement sign and supervision for com IDA / 56050 Post Open - National 295,000.00 0.00 2018-08-09 2018-10-01 2018-08-13 2018-09-07 2018-10-10 2018-10-25 2018-11-05 2018-12-05 2019-06-03 ervices Based Selection ation prehensive laboratory constr uction ET-MOANRD-82633-CS-QCBS Project Management, Capaci Quality And Cost- Open - Internationa Pending Impleme / Independent procurement a IDA / 56050 ty Building and Monitoring a Post 100,000.00 0.00 2018-11-27 2018-12-18 2019-01-31 2019-02-28 2019-03-30 2019-05-04 2019-06-08 2020-06-07 Based Selection l ntation udit for 2011 E.C nd Evaluation ET-MOANRD-82646-CS-CQS / Consultant Qualifi Open - Internationa Training on Advanced GIS an IDA / 56050 Small Scale Irrigation Post 70,000.00 0.00 Canceled 2018-12-20 2019-01-10 2019-02-23 2019-03-25 2019-04-29 2019-10-26 cation Selection l d Hydrology ET-MOANRD-82723-CS-CQS / Agricultural Public Support S Consultant Qualifi Open - Internationa Under Implement Design and supervision for m IDA / 56050 Post 55,000.00 0.00 2018-12-19 2019-05-17 2019-01-09 2019-09-09 2019-02-22 2019-03-24 2019-04-28 2019-10-25 ervices cation Selection l ation olecular laboratory ET-MOANRD-133724-CS-LCS Project Management, Capaci Least Cost Selecti Under Implement / External financial audit for IDA / 56050 ty Building and Monitoring a Post Open - National 55,000.00 0.00 2019-10-31 2019-09-18 2019-11-21 2020-01-04 2019-09-20 2020-02-01 2020-03-02 2020-04-06 2020-05-11 2020-11-07 on ation 2012 FY nd Evaluation Project Management, Capaci ET-MOANRD-187316-CS-LCS Least Cost Selecti IDA / 56050 ty Building and Monitoring a Post Open - National 55,000.00 0.00 Under Review 2020-08-12 2020-08-07 2020-08-19 2020-09-12 2020-10-10 2020-11-09 2020-12-14 2021-01-18 2021-07-17 / Financial audit for 2013 EFY on nd Evaluation ET-MOANRD-260732-CS-LCS Project Management, Capaci Least Cost Selecti Under Implement / External Financial Audit for IDA / 56050 ty Building and Monitoring a Post Open - National 45,000.00 0.00 2021-11-12 2021-11-14 2021-12-03 2021-12-24 2022-01-21 2022-01-28 2022-02-18 2022-03-11 2022-04-15 on ation 2013/2014EFY nd Evaluation ET-MOANRD-276241-CS-QCB S / Recruitment of consultant Project Management, Capaci Quality And Cost- Pending Impleme for the preparation of Compr IDA / 56050 ty Building and Monitoring a Post Open - National 250,000.00 0.00 2022-02-17 2022-03-03 2022-03-31 2022-04-28 2022-05-28 2022-07-02 2022-08-06 2022-12-04 Based Selection ntation ehensive Implementation Per nd Evaluation formance Assessment Report Page 3 ET-MOANRD-276244-CS-QCB Project Management, Capaci S / Recruitment of consultant Quality And Cost- Open - Internationa IDA / 56050 ty Building and Monitoring a Post 900,000.00 0.00 Canceled 2022-02-28 2022-03-21 2022-05-04 2022-06-01 2022-07-01 2022-08-05 2022-09-09 2023-02-06 for Baseline Survey of Food S Based Selection l nd Evaluation ystems Resilience Project INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DC/FAGP/CU/CON-28/10 / do cumentary film content prod Agricultural Public Support S IDA / 56050 Prior Direct Selection Direct 15,000.00 0.00 Canceled 2017-11-03 2017-11-13 2018-01-17 2018-07-16 uction and broadcasting by E ervices thiopian broad casting corpor ation DC/AGP/CU-003/10 / Recruit Project Management, Capaci Under Implement ment of consultant ot conduc IDA / 56050 ty Building and Monitoring a Prior Direct Selection Direct 500,000.00 455,679.88 2018-04-16 2018-05-21 2018-04-26 2018-07-06 2018-06-30 2018-12-27 ation t Midterm review nd Evaluation FAGP/CU/CON-013/09 / Exter Project Management, Capaci Under Implement nal financial Audit for AGP 1 IDA / 56050 ty Building and Monitoring a Post Direct Selection Direct 100,000.00 0.00 2017-04-24 2017-05-31 2017-05-04 2017-06-16 2017-12-13 ation closing and Agp 2 2009 EFY nd Evaluation FAGP/CU/CON-012/09 / Exter Project Management, Capaci nal Financial Audit for AGP 1 IDA / 56050 ty Building and Monitoring a Prior Direct Selection Direct 100,000.00 0.00 Canceled 2017-04-24 2017-08-09 2017-05-04 2017-06-10 2017-07-25 closing and AGp 2 2009 EFY nd Evaluation AGP/CU/CONS-012/09 / Direc Agriculture Marketing and V t contract of government ow IDA / 56050 Prior Direct Selection Direct 25,000.00 0.00 Canceled 2017-05-15 2017-05-25 2017-07-29 2018-01-25 alue Chains ned Alage ATVET to provide t raining ET-MOANRD-204421-CS-IND V / To Hire/recruit procureme Project Management, Capaci Individual Consult Under Implement nt specialist for the duration IDA / 56050 ty Building and Monitoring a Prior Open 24,000.00 0.00 2020-11-12 2020-12-02 2020-12-24 2021-01-06 2021-01-14 2021-03-12 2021-02-18 2022-02-18 ant Selection ation of the AGP- programme to w nd Evaluation ork in the procurement case Team in MoA. ET-MOANRD-220703-CS-IND Project Management, Capaci V / Development of Environm Individual Consult IDA / 56050 ty Building and Monitoring a Post Open 15,000.00 15,858.49 Signed 2021-03-18 2021-03-14 2021-05-06 2021-06-14 2021-05-27 2021-07-13 2021-07-01 2021-07-13 2021-08-25 ental and Social Managemen ant Selection nd Evaluation t for Integrated Agricultural D evelopment Program ET-MOANRD-220704-CS-IND Project Management, Capaci V / Development of Social As Individual Consult IDA / 56050 ty Building and Monitoring a Post Open 15,000.00 15,853.39 Signed 2021-03-17 2021-03-14 2021-05-05 2021-06-14 2021-05-26 2021-07-13 2021-06-30 2021-07-13 2021-08-24 sessment for Integrated Agri ant Selection nd Evaluation cultural Development Progra m ET-MOANRD-220706-CS-IND Project Management, Capaci V / Development of Resettle Individual Consult IDA / 56050 ty Building and Monitoring a Post Open 15,000.00 15,643.17 Signed 2021-03-22 2021-03-14 2021-05-10 2021-06-14 2021-05-31 2021-07-13 2021-07-05 2021-07-13 2021-08-29 ment Framework (RF) for Inte ant Selection nd Evaluation grated Agricultural Developm ent Program ET-MOANRD-275893-CS-CDS Project Management, Capaci Pending Impleme / Recruitment of consultant t IDA / 56050 ty Building and Monitoring a Post Direct Selection Direct 680,000.00 0.00 2022-07-19 2022-08-02 2022-09-11 2023-01-09 ntation o conduct end-line evaluatio nd Evaluation n of AGP II Page 4