PROCUREMENT PLAN (Mandatory Requirements) Emergency Multi-Sector Rohingya Crisis Response Project (EMRCRP) Project Implementation Agencies: Ministry of Disaster Management and Relief (MoDMR) Department of Public Health Engineering (DPHE) Local Government Engineering Department (LGED) Period covered by this Procurement Plan: Entire Project Period Preamble In accordance with paragraph 5.9 of the World Bank Procurement Regulations for IPF Borrowers, July 2016 revised November 2017 (“Procurement Regulations”), the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to record all procurement actions for the Project, including preparing, updating and clearing its Procurement Plan, and seeking and receiving the Bank’s review and No-objection to procurement actions as required. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: The Bank’s Standard Procurement Documents (SPDs) shall be used for goods, works and non- consulting services where international competition is required and for all consulting services, including their respective forms of contract. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Public Procurement Act 2006 and the Public Procurement Rules 2008, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: 1) Lottery in award of contracts shall not be allowed; 2) Bidders’ qualification[s]/experience requirement[s] shall be mandatory; 3) Bids shall not be rejected based on percentage above or below the estimated cost; 4) Model Bidding Documents agreed with the Bank shall be used for all national open competitive procurement; 5) The eligibility of bidders shall be as defined under Section III of the Procurement Regulations. Accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations; 6) The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance (in the form attached) at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. 7) Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts When the Borrower uses other national procurement arrangements (other than national open competitive procurement), such as limited/restricted competitive bidding, request for quotations/shopping, direct contracting), such arrangements shall be consistent with the above requirements. As per paragraph 5.4 of the Procurement Regulations, the “Letter of Acceptance of the World Bank’s Anticorruption Guidelines and Sanctions Framework” as attached to this document shall form part of the Model Bidding Documents. Leased Assets: Not Applicable. Procurement of Second Hand Goods: Not Applicable. Domestic preference: as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works) as follows: Goods: Applicable; Works: Not applicable. Hands-on Expanded Implementation Support (HEIS): Not Applicable. Bank’s Procurement Prior Review Thresholds: contracts at or above the thresholds set out in table 1 below are subject to the Bank’s procurement prior review. Table 1: Procurement Prior Review Thresholds (US$ millions) Type of High risk Substantial Moderate Low risk procurement risk risk Works (including 5 10 15 20 turnkey, supply & installation of plant and equipment, and PPP) Goods, information 1.5 2 4 6 technology and non-consulting services Consulting 0.5 1 2 4 services: firms Consulting 0.2 0.3 0.4 0.5 services: Individual Notes: 1. These thresholds apply to all procurement activities regardless of their procurement/selection methods. There is no automatic requirement to undertake prior review for direct selection for value less than these thresholds. Consultant services covers a range of services that are of an advisory or professional nature. 2. In addition to the provisions of Table 1 above, and irrespective of the contract value, the following procurement activities are subject to the Bank’s procurement prior review: (a) procurement processes involving contract negotiations, as described in Section VI, paragraphs 6.34-36, of the Procurement Regulations; (b) competitive dialogue; (c) sustainable procurement; (d) selection of probity assurance providers, as described in Section III, paragraph 3.3 of the Procurement Regulations; and (e) best and final offer. 3. The determination of whether a contract meets the procurement prior review threshold is based on the estimated value of the contract or the package -when the selection document contains more than one lot/slice- , including all taxes and duties payable under the contract. Bid/ Proposal Evaluation Committee: formation and alteration of the bid/proposal evaluation committee shall be subject to Bank’s no objection. Fraud and Corruption (F&C) Checklist: Fraud and Corruption (F&C) checklist, as developed and provided by the Bank, shall be properly filled in during the evaluation and be attached with the evaluation report in case of contracts following national competitive procurement and request for quotations. Attachment 1 Letter of Acceptance of the World Bank’s Anticorruption Guidelines and Sanctions Framework1 Date: 1[Drafting note: This document shall be signed by bidders/proposers/consultants and submitted as part of their bids/proposals. In addition, this document shall be signed by the winning bidder/consultant and incorporated as part of the contract.] Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines2 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-Corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;3 (ii) to be a 2Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. 3 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification or initial selection), expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. nominated4 sub-contractor, sub-consultant, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank- financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect5 all accounts, records, and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. 4A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the bidding document) is one which has been: (i) included by the bidder in its pre-qualification or initial selection application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 5Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Proposer/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Proposer/ Consultant: Title of the person signing the Letter: PROCUREMENT Bangladesh : Emergency Multi-Sector Rohingya Crisis Response Project PLAN General Information Country: Bangladesh Bank’s Approval Date of the Original Procurement Plan: 2018-12-11 2021-11-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P167762 GPN Date: Project Name: Emergency Multi-Sector Rohingya Crisis Response Project Loan / Credit No: / , IDA / D4190, IDA / D5900 Department of Public Health Engineering Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Component 1: Strengthening EMRCRP/WD-02 / Delivery of Basic Services, Construction of Mini Piped Resilient Infrastructure, Single Stage - One 2,174,388.9 2020-04- IDA / D4190 Post Request for Bids Open - National 2,392,344.00 Signed 2019-01-01 2019-05-14 2019-01-06 2019-02-17 2019-06-16 2019-03-19 2019-06-27 2019-04-23 2019-06-30 Water Supply Schemes Emergency Response, and Envelope 5 22 including O&M Gender-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, EMCRP/WD-6 / Construction Resilient Infrastructure, Single Stage - One 1,650,984.6 2020-06- of community latrine / Post Request for Bids Open - National 1,674,641.00 Signed 2019-03-01 2019-05-06 2019-03-06 2019-04-17 2019-06-10 2019-05-17 2019-07-25 2019-06-21 2019-08-25 Emergency Response, and Envelope 7 20 including O & M Gender-Based Viol ence Prevention Component 1: Strengthening EMCRP/WD-03 / Delivery of Basic Services, Construction of Mini piped Resilient Infrastructure, Single Stage - One 2,360,284.2 2020-06- IDA / D4190 Post Request for Bids Open - National 2,392,344.00 Signed 2019-03-03 2019-04-02 2019-03-08 2019-04-19 2019-05-06 2019-05-19 2019-05-30 2019-06-23 2019-06-16 water supply schemes Emergency Response, and Envelope 5 22 including O&M Gender-Based Viol ence Prevention Component 1: Strengthening EMCRP/WD-04 / Delivery of Basic Services, Construction of Mini piped Resilient Infrastructure, Single Stage - One 1,748,868.5 2020-01- / Post Request for Bids Open - National 1,913,876.00 Signed 2019-03-17 2019-04-04 2019-03-22 2019-05-03 2019-05-06 2019-06-02 2019-06-11 2019-07-07 2019-06-23 water supply schemes Emergency Response, and Envelope 7 03 including O&M Gender-Based Viol ence Prevention Component 1: Strengthening EMCRP/WD-12 / Delivery of Basic Services, Construction of Camp office, Resilient Infrastructure, Single Stage - One 2020-02- IDA / D4190 Post Request for Bids Open - National 382,775.00 356,522.57 Signed 2019-04-21 2019-04-21 2019-04-26 2019-06-07 2019-05-21 2019-07-07 2019-06-30 2019-08-11 2019-07-16 renovation and extension of Emergency Response, and Envelope 07 RPO and truck shade Gender-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, EMCRP/WD-13 / Renovation Resilient Infrastructure, Single Stage - One 2020-03- IDA / D4190 Post Request for Bids Open - National 62,201.00 51,161.73 Signed 2019-06-13 2019-03-20 2019-06-18 2019-07-30 2019-04-07 2019-08-29 2019-05-09 2019-10-03 2019-05-20 of PMU Emergency Response, and Envelope 31 Gender-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, EMCRP/WD-10 / Installation Resilient Infrastructure, Single Stage - One 2,122,345.9 2020-06- of Household toilet including IDA / D4190 Post Request for Bids Open - National 2,150,537.63 Signed 2019-09-22 2019-05-05 2019-09-29 2019-10-24 2019-06-10 2019-11-08 2019-08-19 2019-12-13 2019-09-11 Emergency Response, and Envelope 9 10 renovation of existing toilets Gender-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, EMCRP/WD-11 / Installation Resilient Infrastructure, Single Stage - One 2020-04- IDA / D4190 Post Request for Bids Open - National 430,107.52 381,954.65 Signed 2019-10-03 2020-02-02 2019-10-10 2019-11-04 2020-02-18 2019-11-19 2020-04-14 2019-12-24 2020-05-11 of Household Bio-fill toilet Emergency Response, and Envelope 22 Gender-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, EMCRP/WD-07A / Installation Resilient Infrastructure, Single Stage - One 2020-04- IDA / D4190 Post Request for Bids Open - National 358,422.94 330,500.24 Signed 2019-09-25 2019-09-11 2019-10-02 2019-10-27 2019-10-03 2019-11-11 2019-11-03 2019-12-16 2019-11-26 of water options (DTW) Emergency Response, and Envelope 14 Gender-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, EMCRP/WD-7B / Installation Resilient Infrastructure, Single Stage - One 2020-04- IDA / D4190 Post Request for Bids Open - National 358,422.94 319,623.58 Signed 2019-09-30 2019-09-01 2019-10-07 2019-11-01 2019-10-06 2019-11-16 2019-10-28 2019-12-21 2019-11-26 of water options (DTW) Emergency Response, and Envelope 19 Gender-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, EMCRP/WD-13.1 / Resilient Infrastructure, Single Stage - One 2020-09- Renovation & extension of IDA / D4190 Post Request for Bids Open - National 57,347.67 44,561.14 Signed 2019-11-26 2019-10-31 2019-11-27 2020-01-08 2019-11-24 2020-02-07 2020-01-29 2020-03-13 2020-02-27 Emergency Response, and Envelope 09 RPO Gender-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, EMRCRP/WD-01 / Test Tube- Resilient Infrastructure, Single Stage - One 2019-09- / Post Request for Bids Open - National 66,986.00 0.00 Canceled 2019-01-30 2019-02-04 2019-03-18 2019-04-17 2019-05-22 well Emergency Response, and Envelope 19 Gender-Based Viol ence Prevention Component 1: Strengthening EMCRP/DPHE/WD-14 / Delivery of Basic Services, Supply and Installation with Resilient Infrastructure, Single Stage - One 2020-11- IDA / D4190 Post Request for Bids Open - National 358,250.00 323,682.68 Signed 2020-06-10 2020-08-25 2020-06-13 2021-02-16 2020-06-27 2020-09-06 2020-07-12 2020-10-20 2020-08-09 2020-11-04 OM of Hand Washing Basin for Emergency Response, and Envelope 07 COVID-19 Gender-Based Viol ence Prevention Component 1: Strengthening EMCRP/DPHE/WD-5 / Delivery of Basic Services, Construction of latrine with Resilient Infrastructure, Single Stage - One 2021-06- IDA / D4190 Post Request for Bids Open - National 835,000.00 777,561.30 Signed 2020-06-07 2020-06-04 2020-06-10 2020-07-01 2020-07-05 2020-07-31 2020-07-05 2020-09-04 2020-09-03 composting bio-gas plant Emergency Response, and Envelope 01 including O & M Gender-Based Viol ence Prevention Page 1 Component 1: Strengthening EMCRP/WD-08 / Supply, Delivery of Basic Services, Under Installation and Construction Resilient Infrastructure, Single Stage - One 2023-02- IDA / D4190 Post Request for Bids Open - National 1,438,240.00 0.00 Implementat 2020-11-10 2021-01-25 2020-11-13 2020-12-04 2021-02-23 2021-01-03 2021-02-07 with O & M of solid waste Emergency Response, and Envelope 07 ion management system. Gender-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/WD-24 / Delivery of Basic Services, Installation of Water Options Under Resilient Infrastructure, Single Stage - One 2023-01- including O & M for Host IDA / D5900 Post Request for Bids Open - National 2,151,105.00 0.00 Implementat 2021-03-30 2021-05-23 2021-04-02 2021-05-02 2021-06-13 2021-06-01 2021-07-06 Emergency Response, and Envelope 07 Community (4"-2" dia with ion Gender-Based Viol ence submersible pump) Prevention Component 1: Strengthening EMCRP/AF/WD-26 / Delivery of Basic Services, Installation of Water Options Under Resilient Infrastructure, Single Stage - One 2023-01- including O & M for Host IDA / D5900 Post Request for Bids Open - National 1,473,360.00 0.00 Implementat 2021-03-30 2021-03-14 2021-04-02 2021-05-02 2021-04-11 2021-06-01 2021-07-06 Emergency Response, and Envelope 07 Community (4"-2" dia with ion Gender-Based Viol ence submersible pump) Prevention Component 1: Strengthening EMCRP/AF/WD-30 / Delivery of Basic Services, Installation of Household Pending Resilient Infrastructure, Single Stage - One 2022-12- toilet for Host Community ( IDA / D5900 Post Request for Bids Open - National 1,555,870.00 0.00 Implementat 2021-03-15 2021-03-18 2021-04-08 2021-05-08 2021-06-12 Emergency Response, and Envelope 14 Chakoria Upazila, Cox's Bazar ion Gender-Based Viol ence ) Prevention Component 1: Strengthening EMCRP/AF/WD-31 / Delivery of Basic Services, Installation of Household Under Resilient Infrastructure, Single Stage - One 2022-12- Toilet for Host Community ( IDA / D5900 Post Request for Bids Open - National 1,763,320.00 0.00 Implementat 2021-03-14 2021-04-01 2021-03-17 2021-04-16 2021-05-19 2021-05-16 2021-06-20 Emergency Response, and Envelope 22 Cox's Bazar Sadar and ion Gender-Based Viol ence Moheshkhali upazila ) Prevention Component 1: Strengthening EMCRP/AF/WD-33 / Delivery of Basic Services, Installation of Household Under Resilient Infrastructure, Single Stage - One 2023-01- Toilet for Host Community IDA / D5900 Post Request for Bids Open - National 1,201,745.00 0.00 Implementat 2021-03-30 2021-04-01 2021-04-02 2021-05-02 2021-05-19 2021-06-01 2021-07-06 Emergency Response, and Envelope 07 (Kutubdia and Pekua upazila, ion Gender-Based Viol ence Cox's Bazar ) Prevention Component 1: Strengthening EMCRP/AF/WD-32 / Delivery of Basic Services, Installation of Household Pending Resilient Infrastructure, Single Stage - One 2023-01- Toilet for Host Community IDA / D5900 Post Request for Bids Open - National 1,694,012.00 0.00 Implementat 2021-03-30 2021-04-02 2021-05-02 2021-06-01 2021-07-06 Emergency Response, and Envelope 07 (Ramu, Ukhia and Teknaf ion Gender-Based Viol ence upazila) Prevention Component 1: Strengthening EMCRP/AF/WD-19 / Delivery of Basic Services, Construction of Mini piped Pending Resilient Infrastructure, Single Stage - One 2022-08- water supply schemes IDA / D4190 Post Request for Bids Open - National 2,310,230.00 0.00 Implementat 2021-05-25 2021-05-28 2021-06-18 2021-07-18 2021-08-22 Emergency Response, and Envelope 22 including O & M for Host ion Gender-Based Viol ence Community. Prevention Component 1: Strengthening Delivery of Basic Services, EMCRP/AF/WD-23 / Pending Resilient Infrastructure, Single Stage - One 2023-06- Installation of Water Options IDA / D5900 Post Request for Bids Open - National 530,410.00 0.00 Implementat 2021-03-30 2021-04-02 2021-04-23 2021-05-23 2021-06-27 Emergency Response, and Envelope 27 Including O & M for DRP ion Gender-Based Viol ence Prevention Component 1: Strengthening EMCRP/WD/19 / National Delivery of Basic Services, Construction of Mini Piped Procurement Resilient Infrastructure, Single Stage - One 2022-11- Water Supply Schemes IDA / D5900 Post Request for Bids Open - National Document - 1 2,310,230.00 0.00 Canceled 2021-07-01 2021-07-06 2021-08-05 2021-10-04 2021-11-15 Emergency Response, and Envelope 15 including O&M for Host Envelope process Gender-Based Viol ence Community (Non Bank-SPD) Prevention Component 1: Strengthening National EMCRP/WD-23 / Installation Delivery of Basic Services, Procurement of Water Options including Resilient Infrastructure, Single Stage - One 2022-11- IDA / D5900 Post Request for Bids Open - National Document - 1 530,410.00 0.00 Canceled 2021-07-05 2021-07-10 2021-08-09 2021-10-08 2021-11-19 O&M for DRP ( 3"-1.5" dia Emergency Response, and Envelope 19 Envelope process with deep set pump) Gender-Based Viol ence (Non Bank-SPD) Prevention Component 1: Strengthening National EMCRP/WD-25 / Installation Delivery of Basic Services, Procurement Pending of Water Options Including Resilient Infrastructure, Single Stage - One 2022-11- IDA / D5900 Post Request for Bids Open - National Document - 1 1,826,970.00 0.00 Implementat 2021-07-11 2021-07-16 2021-08-15 2021-10-14 2021-11-25 O&M for Host Community ( 4"- Emergency Response, and Envelope 25 Envelope process ion 2" dia with submersible pump) Gender-Based Viol ence (Non Bank-SPD) Prevention Component 1: Strengthening National EMCRP/WD-25A / Installation Delivery of Basic Services, Procurement Pending of Water Options including Resilient Infrastructure, Single Stage - One 2022-12- IDA / D5900 Post Request for Bids Open - National Document - 1 1,090,285.00 0.00 Implementat 2021-07-25 2021-07-30 2021-08-29 2021-10-28 2021-12-09 O&M for host community ( 4"- Emergency Response, and Envelope 09 Envelope process ion 2" dia with submersible pump) Gender-Based Viol ence (Non Bank-SPD) Prevention Component 1: Strengthening National Delivery of Basic Services, EMCRP/WD-35 / Installation Procurement Pending Resilient Infrastructure, Single Stage - One 2022-11- of Household Biofill Toilet IDA / D5900 Post Request for Bids Open - National Document - 1 766,150.00 0.00 Implementat 2021-06-24 2021-06-29 2021-07-29 2021-09-27 2021-11-08 Emergency Response, and Envelope 08 including O&M ( Host ) Envelope process ion Gender-Based Viol ence (Non Bank-SPD) Prevention Component 1: Strengthening National EMCRP/WD-09 / Supply, Delivery of Basic Services, Procurement Pending Installation and Construction Resilient Infrastructure, Single Stage - One 2022-12- IDA / D4190 Post Request for Bids Open - National Document - 1 2,129,600.00 0.00 Implementat 2021-09-12 2021-09-15 2021-10-06 2021-10-31 2021-12-05 with O&M of fecal sludge Emergency Response, and Envelope 05 Envelope process ion management system Gender-Based Viol ence (Non Bank-SPD) Prevention Component 1: Strengthening EMCRP/AF/WD-20 / National Delivery of Basic Services, Construction of Mini piped Procurement Pending Resilient Infrastructure, Single Stage - One 2023-06- water supply schemes IDA / D4190 Post Request for Bids Open - National Document - 1 2,310,230.00 0.00 Implementat 2021-09-20 2021-09-23 2021-10-14 2021-11-13 2021-12-18 Emergency Response, and Envelope 16 including O&M for Host Envelope process ion Gender-Based Viol ence Community (Non Bank-SPD) Prevention Page 2 Component 1: Strengthening EMCRP/AF/WD-21 / National Delivery of Basic Services, Construction of Mini piped Procurement Pending Resilient Infrastructure, Single Stage - One 2023-06- water supply schemes IDA / D4190 Post Request for Bids Open - National Document - 1 2,310,230.00 0.00 Implementat 2021-09-23 2021-09-26 2021-10-17 2021-11-16 2021-12-21 Emergency Response, and Envelope 19 including O&M for Host Envelope process ion Gender-Based Viol ence Community (Non Bank-SPD) Prevention Component 1: Strengthening EMCRP/AF/WD-22 / National Delivery of Basic Services, Construction of Mini piped Procurement Pending Resilient Infrastructure, Single Stage - One 2023-06- water supply schemes IDA / D5900 Post Request for Bids Open - National Document - 1 2,021,452.14 0.00 Implementat 2021-09-26 2021-09-29 2021-10-20 2021-11-19 2021-12-24 Emergency Response, and Envelope 22 including O&M for Host Envelope process ion Gender-Based Viol ence Community (Non Bank-SPD) Prevention EMCRP/AF/WD-16 / Reconstruction of the mini Component 1: Strengthening National pipe water supply system, Delivery of Basic Services, Procurement Pending water option and toilets Resilient Infrastructure, Single Stage - One 2022-08- IDA / D5900 Post Request for Bids Open - National Document - 1 193,300.00 0.00 Implementat 2021-11-17 2021-11-22 2021-12-13 2022-01-27 2022-02-24 damaged by fire and Emergency Response, and Envelope 23 Envelope process ion landslides under the budget Gender-Based Viol ence (Non Bank-SPD) of Miscellaneous for Prevention Immediate Support. Component 1: Strengthening National Delivery of Basic Services, EMCRP/AF/WD-44 / Procurement Pending Resilient Infrastructure, Single Stage - One 2024-03- Construction of WASH training IDA / D5900 Post Request for Bids Open - National Document - 1 2,003,770.00 0.00 Implementat 2021-12-01 2021-12-06 2022-01-17 2022-03-03 2022-03-31 Emergency Response, and Envelope 30 facility center at Cox's bazar Envelope process ion Gender-Based Viol ence (Non Bank-SPD) Prevention Component 1: Strengthening National EMCRP/AF/WD-40 / Delivery of Basic Services, Procurement Pending Extension and improvement Resilient Infrastructure, Single Stage - One 2023-04- IDA / D5900 Post Request for Bids Open - National Document - 1 538,660.00 0.00 Implementat 2021-12-20 2021-12-26 2022-01-30 2022-03-01 2022-04-05 of truck shed, camp office and Emergency Response, and Envelope 05 Envelope process ion DPHE field level offices Gender-Based Viol ence (Non Bank-SPD) Prevention GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Strengthening Delivery of Basic Services, EMRCRP/GD-07 / Supply of Resilient Infrastructure, Single Stage - One Computer with printer and IDA / D4190 Post Request for Bids Open - National 29,904.31 28,936.62 Signed 2019-01-15 2019-04-03 2019-01-20 2019-03-03 2019-04-18 2019-04-02 2019-05-23 2019-05-07 2019-06-06 2019-07-06 Emergency Response, and Envelope scanner including laptop Gender-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, EMRCRP/GD-08 / Supply of Resilient Infrastructure, Single Stage - One Furniture and Fixtures for IDA / D4190 Post Request for Bids Open - National 23,923.44 15,107.97 Signed 2019-02-01 2019-04-18 2019-02-06 2019-03-20 2019-05-16 2019-04-19 2019-06-03 2019-05-24 2019-06-19 2019-06-23 Emergency Response, and Envelope PMU & RPO Gender-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, EMRCRP/GD-10 / Supply of Resilient Infrastructure, Single Stage - One Air Conditioner for PMU and IDA / D4190 Post Request for Bids Open - National 23,923.44 18,243.68 Signed 2019-02-15 2019-04-09 2019-02-20 2019-04-03 2019-04-25 2019-05-03 2019-06-29 2019-06-07 2019-07-10 2019-07-07 Emergency Response, and Envelope RPO Gender-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, EMRCRP/GD-11 / Equipment Resilient Infrastructure, Single Stage - One for Cox's Bazar Zonal / Post Request for Bids Open - National 598,086.12 0.00 Canceled 2019-07-01 2019-07-06 2019-08-17 2019-09-16 2019-10-21 2020-02-18 Emergency Response, and Envelope Laboratory Gender-Based Viol ence Prevention EMCRP/GD-11 A / Supply of Component 1: Strengthening Equipment for Cox's Bazar Delivery of Basic Services, Zonal Laboratory, DPHE Resilient Infrastructure, Single Stage - One IDA / D4190 Post Request for Bids Open - National 478,469.00 350,917.81 Completed 2019-03-20 2019-03-13 2019-03-25 2019-05-06 2019-04-04 2019-06-05 2019-05-09 2019-07-10 2019-06-11 2020-01-06 2019-08-31 (Atomic Absorption Emergency Response, and Envelope Spectrometer - AAS and AAS Gender-Based Viol ence with Graphite Furnace) Prevention Component 1: Strengthening EMCRP/GD-11 B / Supply of Delivery of Basic Services, Different Types of Laboratory Resilient Infrastructure, Single Stage - One IDA / D4190 Post Request for Bids Open - National 119,617.00 76,275.53 Signed 2019-04-04 2019-03-12 2019-04-09 2019-05-21 2019-03-28 2019-06-20 2019-05-09 2019-07-25 2019-06-11 2020-01-21 Equipment for Water Quality Emergency Response, and Envelope Test Gender-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, EMCRP/GD-01 / Supply and Resilient Infrastructure, Single Stage - One Installation of Truck based IDA / D4190 Post Request for Bids Open - National 1,194,743.13 1,141,911.52 Signed 2019-09-29 2019-12-08 2019-10-04 2019-10-29 2020-01-07 2019-11-14 2020-03-03 2019-12-19 2020-03-24 2020-02-13 Emergency Response, and Envelope mobile water treatment plant Gender-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, EMCRP/GD-02 / Supply of Resilient Infrastructure, Single Stage - One IDA / D4190 Post Request for Bids Open - National 507,765.83 353,685.08 Signed 2019-09-30 2020-03-08 2019-10-07 2019-11-01 2020-05-11 2019-11-17 2020-07-10 2019-12-22 2020-08-18 2020-02-16 Truck mounted water carrier Emergency Response, and Envelope Gender-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, EMCRP/GD-11.C / Supply of Resilient Infrastructure, Single Stage - One Laboratory Equipment for IDA / D4190 Post Request for Bids Open - National 166,069.30 105,009.10 Signed 2019-11-27 2019-12-04 2019-12-02 2020-01-13 2019-12-29 2020-02-12 2020-01-30 2020-03-18 2020-02-17 2020-09-14 Emergency Response, and Envelope Water Quality Test Gender-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, EMCRP/DPHE/GD-15-A / Resilient Infrastructure, Single Stage - One Supply of Office Equipment IDA / D4190 Post Request for Bids Open - National 16,200.00 0.00 Canceled 2020-03-15 2020-03-20 2020-04-10 2020-05-10 2020-06-07 2020-08-06 Emergency Response, and Envelope for PMU and RPO Gender-Based Viol ence Prevention Page 3 Component 1: Strengthening EMCRP/DPHE/GD-12 / Delivery of Basic Services, Supply of Video Conferencing Resilient Infrastructure, Single Stage - One IDA / D4190 Post Request for Bids Open - National 25,000.00 21,738.77 Signed 2020-03-25 2020-03-25 2020-03-26 2020-04-09 2020-04-08 2020-04-19 2020-04-16 2020-05-03 2020-05-13 2020-05-18 System and office Equipment Emergency Response, and Envelope for PMU and RPMU Gender-Based Viol ence Prevention Component 1: Strengthening EMCRP/DPHE/13-A / Delivery of Basic Services, Procurement of Soap Bar as Resilient Infrastructure, Request for Single Stage - One Hand Washing Agent - for IDA / D4190 Post Limited 79,500.00 70,159.61 Signed 2020-04-05 2020-04-06 2020-04-24 2020-05-03 2020-05-24 Emergency Response, and Quotations Envelope Emergency Support to prevent Gender-Based Viol ence COVID-19 virus Prevention Component 1: Strengthening EMCRP/DPHE/GD-13 / Delivery of Basic Services, Procurement of Hand Sanitizer Resilient Infrastructure, Request for Single Stage - One IDA / D4190 Post Limited 149,650.00 141,181.70 Completed 2020-04-06 2020-04-06 2020-04-25 2020-05-03 2020-04-28 2020-06-09 for Emergency Support to Emergency Response, and Quotations Envelope prevent COVID-19 virus . Gender-Based Viol ence Prevention Component 1: Strengthening EMCRP/DPHE/GD-14 / Delivery of Basic Services, Procurement of Water Resilient Infrastructure, Request for Single Stage - One IDA / D4190 Post Limited 53,770.00 52,220.07 Signed 2020-06-11 2020-06-07 2020-07-04 2020-06-22 2020-08-03 Purifying Tablets for Cyclone Emergency Response, and Quotations Envelope Amphan effected people. Gender-Based Viol ence Prevention Component 1: Strengthening EMCRP/GD-3.A / Supply of Delivery of Basic Services, Under Vacuum tag and Mini Covered Resilient Infrastructure, Single Stage - One IDA / D4190 Post Request for Bids Open - National 672,000.00 636,830.10 Implementati 2020-11-30 2020-01-07 2020-12-07 2021-01-06 2021-01-07 2021-02-05 2021-02-23 2021-03-12 2021-07-10 Van (Garbage Truck) with O & Emergency Response, and Envelope on M Gender-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, EMCRP/AF/GD-26 / Supply of Pending Resilient Infrastructure, Single Stage - One Air Conditioner for PMU and IDA / D5900 Post Request for Bids Open - National 17,185.00 0.00 Implementati 2021-01-27 2021-02-01 2021-02-22 2021-03-24 2021-04-28 2021-06-27 Emergency Response, and Envelope RPMU on Gender-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/GD-27 / Supply of Delivery of Basic Services, Pending Computer with Printer and Resilient Infrastructure, Single Stage - One IDA / D4190 Post Request for Bids Open - National 24,222.00 0.00 Implementati 2021-04-05 2021-04-07 2021-04-28 2021-05-28 2021-07-02 2021-09-30 Scanner including laptop and Emergency Response, and Envelope on Photocopier Gender-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, EMCRP/AF/GD-09 / Supply of Pending Resilient Infrastructure, Single Stage - One Furniture & Fixtures for PMU & IDA / D5900 Post Request for Bids Open - National 32,060.00 0.00 Implementati 2021-04-15 2021-04-17 2021-05-08 2021-06-07 2021-07-12 2021-10-10 Emergency Response, and Envelope RPMU on Gender-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, EMCRP/AF/GD-24 / Supply of Pending Resilient Infrastructure, Single Stage - One office stationery for PMU and IDA / D5900 Post Request for Bids Open - National 17,680.00 0.00 Implementati 2021-07-15 2021-07-17 2021-08-07 2021-09-06 2021-10-11 2021-12-10 Emergency Response, and Envelope field offices on Gender-Based Viol ence Prevention NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Strengthening Delivery of Basic Services, EMRCRP/NSD-01 / Support Under Resilient Infrastructure, Single Stage - One staff/Manpower for PMU and / Post Request for Bids Open - National 71,770.00 51,226.58 Implementati 2019-01-01 2019-03-04 2019-01-06 2019-02-17 2019-04-02 2019-03-19 2019-06-16 2019-04-23 2022-04-22 Emergency Response, and Envelope RPO (outsourcing) on Gender-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, EMCRP/NSD-03 / Vehicle Resilient Infrastructure, Single Stage - One IDA / D4190 Post Request for Bids Open - National 251,612.90 224,069.85 Signed 2019-10-13 2019-08-22 2019-10-20 2019-11-14 2019-09-16 2019-11-29 2019-10-24 2020-01-03 2020-01-02 2020-04-02 rental Emergency Response, and Envelope Gender-Based Viol ence Prevention CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Strengthening EMCRP/SD-16 / Training on Delivery of Basic Services, O&M for caretaker, Awareness Resilient Infrastructure, Quality And Cost- program on water and IDA / D4190 Post Open - International 717,703.00 496,450.34 Signed 2019-03-01 2019-02-11 2019-03-22 2019-02-20 2019-05-05 2019-06-13 2019-06-02 2019-07-24 2019-07-02 2019-08-26 2019-08-06 2019-09-08 2019-09-10 2019-12-30 2021-09-07 Emergency Response, and Based Selection sanitation, hygine promotion Gender-Based Viol ence and BCC campaign Prevention EMCRP/SD-14 / Monitoring and supervision of water Component 1: Strengthening supply and sanitation Delivery of Basic Services, Consultant schemes including review, Resilient Infrastructure, IDA / D4190 Prior Qualification Open - National 2,200,957.00 2,138,191.37 Signed 2019-03-25 2019-04-10 2019-04-15 2019-04-10 2019-05-29 2019-05-22 2019-06-28 2019-07-11 2019-08-02 2019-09-26 2020-01-29 update of existing drawing, Emergency Response, and Selection design and Environmental and Gender-Based Viol ence Social Impact Assessment (EIA Prevention & SIA) Component 1: Strengthening EMCRP/AF/SD-22 / Selection Delivery of Basic Services, of Consultant for Community Resilient Infrastructure, Quality And Cost- Under IDA / D5900 Post Open - National 825,100.00 0.00 2021-04-15 2021-06-20 2021-05-15 2021-06-27 2021-07-29 2021-10-27 2021-08-28 2021-09-27 2021-11-01 2021-12-06 2024-05-24 mobilization and Capacity Emergency Response, and Based Selection Implementation Development Gender-Based Viol ence Prevention Page 4 Component 1: Strengthening EMCRP/AF/SD-25 / Delivery of Basic Services, Consultant Consulting firm for arranging Resilient Infrastructure, Pending IDA / D4190 Post Qualification Limited 146,157.00 0.00 2021-11-18 2022-01-17 2022-02-16 2022-03-23 2024-02-28 foreign Training, Workshop, Emergency Response, and Implementation Selection Exposure Visit etc Gender-Based Viol ence Prevention INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Strengthening Delivery of Basic Services, Individual EMRCRP/SD-01 / Financial Resilient Infrastructure, / Post Consultant Limited 150,717.70 4,144.71 Terminated 2019-01-01 2019-01-02 2019-01-06 2019-03-25 2019-01-27 2019-03-28 2019-03-03 2019-04-18 2022-03-02 Management Consultant Emergency Response, and Selection Gender-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, Individual EMRCRP/SD-02 / Resilient Infrastructure, / Post Consultant Limited 129,187.00 3,552.61 Terminated 2019-01-01 2019-01-02 2019-01-06 2019-03-25 2019-01-27 2019-03-28 2019-03-03 2019-05-14 2022-03-02 Procurement Consultant Emergency Response, and Selection Gender-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, Individual EMRCRP/SD-03 / Jr. Resilient Infrastructure, / Post Consultant Limited 64,593.00 0.00 Canceled 2019-02-01 2019-02-06 2019-02-27 2019-04-03 2022-04-02 Procurement Consultant Emergency Response, and Selection Gender-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, Individual EMRCRP/SD-04 / Water Resilient Infrastructure, / Post Consultant Limited 129,187.00 2,723.67 Signed 2019-02-01 2019-01-20 2019-02-06 2019-03-25 2019-02-27 2019-03-28 2019-04-03 2019-04-16 2022-04-02 Supply Consultant Emergency Response, and Selection Gender-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, EMRCRP/SD-06 / Individual Resilient Infrastructure, Environmental and / Post Consultant Limited 129,187.00 127,848.46 Signed 2019-02-01 2019-01-20 2019-02-06 2019-05-05 2019-02-27 2019-05-06 2019-04-03 2019-05-14 2022-04-02 Emergency Response, and Hydrogeologist Consultant Selection Gender-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, Individual EMRCRP/SD-07 / M&E Resilient Infrastructure, / Post Consultant Limited 107,656.00 106,540.38 Signed 2019-02-01 2019-01-20 2019-02-06 2019-05-05 2019-02-27 2019-05-06 2019-04-03 2019-05-14 2022-04-02 Consultant Emergency Response, and Selection Gender-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, EMRCRP/SD-09 / Social Individual Resilient Infrastructure, Development and Hygiene / Post Consultant Open 107,656.00 106,540.38 Signed 2019-03-03 2019-01-20 2019-04-21 2019-05-05 2019-05-12 2019-05-06 2019-06-16 2019-05-14 2022-06-15 Emergency Response, and Promotion Consultant Selection Gender-Based Viol ence Prevention EMRCRP/SD-14 / Monitoring and supervision of water Component 1: Strengthening supply and sanitation Delivery of Basic Services, schemes including review, Resilient Infrastructure, / Prior Direct Selection Direct 2,200,957.00 0.00 Canceled 2019-02-01 2019-01-22 2019-02-11 2019-04-17 2022-04-16 update of existing drawing, Emergency Response, and design and Environmental and Gender-Based Viol ence Social Impact Assessment (EIA Prevention & SIA) Component 1: Strengthening Delivery of Basic Services, EMRCRP/SD-05 / Sanitation Individual Resilient Infrastructure, and Waste Management / Post Consultant Open 129,187.00 0.00 Canceled 2019-03-03 2019-01-20 2019-04-21 2019-07-07 2019-05-12 2019-06-16 2022-06-15 Emergency Response, and Consultant Selection Gender-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, Individual EMCRP-SD-03 / Jr. Resilient Infrastructure, IDA / D4190 Post Consultant Open 64,593.00 1,776.30 Signed 2019-01-31 2019-01-20 2019-03-21 2019-05-13 2019-04-11 2019-03-28 2019-05-16 2019-06-18 2022-04-30 Procurement Consultant Emergency Response, and Selection Gender-Based Viol ence Prevention Component 1: Strengthening EMCRP/SD-15 / Design Delivery of Basic Services, (including feasibilty and site Resilient Infrastructure, selection) of fecal sludge and / Post Direct Selection Direct 315,958.00 343,006.30 Signed 2019-02-03 2019-02-13 2019-01-23 2019-04-19 2019-06-11 2020-04-13 Emergency Response, and solid waste management Gender-Based Viol ence system Prevention Component 1: Strengthening Delivery of Basic Services, Individual EMCRP/SD-8 / Training Resilient Infrastructure, IDA / D4190 Post Consultant Open 107,656.00 106,622.46 Signed 2019-06-13 2019-05-01 2019-08-01 2019-07-07 2019-08-22 2019-07-18 2019-09-26 2019-08-06 2020-03-24 Consultant Emergency Response, and Selection Gender-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, Individual EMCRP/SD-10 / Building Resilient Infrastructure, IDA / D4190 Post Consultant Limited 26,786.00 26,370.00 Signed 2019-12-22 2020-01-02 2019-12-27 2020-01-02 2020-01-17 2020-02-21 2020-03-24 2020-08-19 Design Consultant Emergency Response, and Selection Gender-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, EMCRP/SD-10(A) / Individual Resilient Infrastructure, Architectural Drawing IDA / D4190 Post Consultant Limited 18,184.00 17,893.93 Signed 2019-12-22 2020-01-02 2019-12-27 2020-01-02 2020-01-17 2020-02-26 2020-02-21 2020-03-24 2020-08-19 Emergency Response, and Consultant Selection Gender-Based Viol ence Prevention Page 5 Component 1: Strengthening Delivery of Basic Services, Individual EMCRP/SD-11 / ICT Resilient Infrastructure, IDA / D4190 Post Consultant Limited 35,842.00 35,347.25 Signed 2019-12-22 2019-12-26 2019-12-27 2019-12-26 2020-01-17 2020-01-26 2020-02-21 2020-02-03 2020-08-19 Consultant Emergency Response, and Selection Gender-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, Individual EMCRP/SD-2-A / Selection of Resilient Infrastructure, IDA / D4190 Post Consultant Open 86,000.00 84,910.68 Signed 2020-01-26 2019-11-17 2020-02-24 2019-12-18 2020-03-02 2019-12-22 2020-03-16 2019-12-23 2022-03-01 Procurement Specialist Emergency Response, and Selection Gender-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, EMCRP/SD-1-A / Selection of Individual Resilient Infrastructure, Financial Management IDA / D4190 Post Consultant Limited 105,000.00 96,232.10 Signed 2020-03-25 2019-11-20 2020-03-30 2019-12-01 2020-04-06 2019-12-22 2020-04-20 2019-12-29 2022-03-31 Emergency Response, and Consultant Selection Gender-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, Individual EMCRP/DPHE/SD-3-A / Jr. Resilient Infrastructure, IDA / D5900 Post Consultant Open 86,000.00 84,990.82 Signed 2020-07-30 2020-07-20 2020-09-24 2020-09-07 2020-10-15 2020-09-27 2020-11-19 2020-10-19 2023-11-04 Procurement Consultant Emergency Response, and Selection Gender-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, EMCRP/AF/SD-26 / Resilient Infrastructure, Pending Consulting firm for the IDA / D5900 Post Direct Selection Direct 117,865.00 0.00 2021-03-15 2021-04-19 2021-06-16 2021-11-13 Emergency Response, and Implementation preparation of EIA and SIA Gender-Based Viol ence Prevention EMCRP/AF/SD-21 / Monitoring & supervision of Component 1: Strengthening water supply and sanitation Delivery of Basic Services, schemes including review and Resilient Infrastructure, IDA / D5900 Prior Direct Selection Direct 2,121,640.00 0.00 Under Review 2021-01-27 2021-07-25 2021-03-03 2021-06-06 2023-11-23 update of existing drawing Emergency Response, and and design, EIA and SIA and Gender-Based Viol ence establishment of ICT Prevention Monitoring System Component 1: Strengthening Delivery of Basic Services, Individual EMCRP/AF/SD-12 / Hydraulic Resilient Infrastructure, Pending IDA / D5900 Post Consultant Limited 70,720.00 0.00 2021-07-15 2021-07-30 2021-09-28 2021-11-16 2023-11-16 Structure Consultant Emergency Response, and Implementation Selection Gender-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/SD-23 / Delivery of Basic Services, Consulting firm for Resilient Infrastructure, Under IDA / D5900 Post Direct Selection Direct 60,502.00 0.00 2021-03-21 2021-06-20 2021-04-05 2021-07-27 2021-06-16 2022-06-16 conducting Training on Emergency Response, and Implementation Procurement, GBV etc. Gender-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/SD-24 / Delivery of Basic Services, Consulting firm for Resilient Infrastructure, Under conducting Training on IDA / D5900 Post Direct Selection Direct 195,792.00 0.00 2021-03-21 2021-06-20 2021-04-05 2021-07-27 2021-06-16 2023-06-16 Emergency Response, and Implementation Sanitation,Waste Management, Gender-Based Viol ence etc Prevention Component 1: Strengthening EMCRP/AF/SD-19 / Fecal Delivery of Basic Services, Individual Sludge & Solid Waste Resilient Infrastructure, Pending IDA / D5900 Post Consultant Limited 48,505.00 0.00 2021-03-30 2021-04-06 2021-05-06 2021-06-10 2024-04-17 Management Consultant Emergency Response, and Implementation Selection (FS&SWM) Gender-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, Individual EMCRP/AF/SD-18 / Rain Resilient Infrastructure, Pending IDA / D5900 Post Consultant Limited 21,216.00 0.00 2021-05-10 2021-05-17 2021-06-16 2021-07-21 2024-05-28 Water Harvesting Consultant Emergency Response, and Implementation Selection Gender-Based Viol ence Prevention Page 6