PROCUREMENT PLAN (Textual Part) Project information: Burundi - North East Region Refugee and Host Community Support Project - Turikumwe - P169315 Project Implementation agency: Prodema - Ministry in charge of Interior Date of the Procurement Plan: October 9, 2019 Period covered by this Procurement Plan: October 2019 – February 2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, , Revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the country procurement handbook, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. - The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. - Rights for the Bank to review procurement documentation and activities. - An effective complaints mechanism. - Maintenance of records of the Procurement Process When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables: Not Applicable Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable Works: is not applicable PROCUREMENT Burundi : Burundi Integrated Community Development Project PLAN General Information Country: Burundi 2019-10-18 Bank’s Approval Date of the Original Procurement Plan: 2022-06-20 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P169315 GPN Date: Project Name: Burundi Integrated Community Development Project Loan / Credit No: IDA / V2860, IDA / D5620 Ministry of the Interior, Community Development and Public Security Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned BI-PRODECI-048-2021-NC-RF Project Management, Monito Request for Quota Q / Aménagements, déména Single Stage - One E 2021-10-2 IDA / D5620 ring & Evaluation and Capaci A posteriori Demande de prix Limited tions (Non Bank-S 10,000.00 0.00 Annulé 2021-08-18 2021-09-25 gement et Réhabilitation des nvelope 5 ty-Building PD) bureaux - Niveau national et régional BI-TURIKUMWE-GITERANYI-0 01-2022-CW-RFB / Exécutiion National Procure des travaux d'extension es é Project Management, Monito ment Document - Single Stage - One E En cours d'e 2022-09-3 coles fondamentales de RUB IDA / D5620 ring & Evaluation and Capaci A posteriori Appel d'offres Open - National 1 Envelope proce 1,151,789.00 0.00 2022-02-10 2022-03-01 2022-02-13 2022-03-01 2022-03-15 2022-03-29 2022-05-03 nvelope xécution 0 ENGA, GITERANYI I, RUMAND ty-Building ss (Non Bank-SPD ARI et TURA dans la Commun ) e GITERANYI en Province de MUYINGA BI-TURIKUMWE-GASHOHO-0 National Procure 02-2022-CW-RFB / Travaux d' Project Management, Monito ment Document - Single Stage - One E En cours d'e 2022-09-1 extension de l'Ecole Fondam IDA / D5620 ring & Evaluation and Capaci A posteriori Appel d'offres Open - National 1 Envelope proce 285,318.00 0.00 2022-02-14 2022-03-04 2022-02-17 2022-03-04 2022-03-19 2022-04-02 2022-04-18 nvelope xécution 5 antale de GISABAZUBA de la ty-Building ss (Non Bank-SPD commune GASHOHO en Provi ) nce de MUYINGA BI-TURIKUMWE-BUTIHINDA-0 National Procure 03-2022-CW-RFB / Travaux d Project Management, Monito ment Document - Single Stage - One E En cours d'e 2022-09-1 e construction des hangars d IDA / D5620 ring & Evaluation and Capaci A posteriori Appel d'offres Open - National 1 Envelope proce 144,567.00 0.00 2022-02-14 2022-03-10 2022-02-17 2022-03-11 2022-03-19 2022-04-02 2022-04-17 nvelope xécution 4 e stockage dans la commune ty-Building ss (Non Bank-SPD de BUTIHINDA, (BUTIHINDA, ) CAGIZO et NYAMIHONDI BI-TURIKUMWE PIU-284570- CW-RFB / Extension de l'ECO National Procure FO MUSUMBA en Commune K Project Management, Monito ment Document - inyinya, Province RUYIGI (Lot Single Stage - One E En cours d'e 2022-09-2 IDA / D5620 ring & Evaluation and Capaci A posteriori Appel d'offres Open - National 1 Envelope proce 759,300.00 0.00 2022-03-18 2022-04-01 2022-03-21 2022-04-02 2022-04-20 2022-05-04 2022-05-28 1), ECOFO NZOZI de la Com nvelope xécution 5 ty-Building ss (Non Bank-SPD mune BWERU en Province RU ) YIGI (Lot 2) et ECOFO Murehe de la Commune et Province C ANKUZO (Lot 3) BI-TURIKUMWE PIU-289381- CW-RFB / Travaux d'extensio n de l'ECOFO RUKURAZO (Lot National Procure 1) et MURAMA (Lot 2), du Ly Project Management, Monito ment Document - Single Stage - One E En cours d'e 2022-09-1 cée Communal KARUNGURA IDA / D5620 ring & Evaluation and Capaci A posteriori Appel d'offres Open - National 1 Envelope proce 1,128,849.00 0.00 2022-04-12 2022-04-21 2022-04-13 2022-04-26 2022-05-13 2022-05-27 2022-06-13 nvelope xécution 1 (Lot3), des Centres de Santé ty-Building ss (Non Bank-SPD et leurs clôtures de Kagozi (l ) ot 4) et Gitwa (lot 5) tous situ és dans la Commune MWUM BA, Province Ngozi BI-TURIKUMWE PIU-289409- CW-RFB / Travaux d'Extensio National Procure n du Centre de Santé et une Project Management, Monito ment Document - Single Stage - One E En cours d'e 2022-09-1 Ecole du Camp des Réfugiés IDA / D5620 ring & Evaluation and Capaci A posteriori Appel d'offres Open - National 1 Envelope proce 498,170.00 0.00 2022-04-12 2022-04-21 2022-04-13 2022-04-22 2022-05-13 2022-05-27 2022-06-13 nvelope xécution 1 Congolais de MUSASA (Lot 1) ty-Building ss (Non Bank-SPD et de l'ECOFO RUTOBO (Lot 2 ) ) en Commune de Kiremba Pr ovince NGOZI. BI-TURIKUMWE PIU-289412- National Procure CW-RFB / Travaux d'extensio Project Management, Monito ment Document - n de l'ECOFO Gasekanya (Lot Single Stage - One E En cours d'e 2022-09-1 IDA / D5620 ring & Evaluation and Capaci A posteriori Appel d'offres Open - National 1 Envelope proce 354,623.00 0.00 2022-04-18 2022-04-21 2022-04-19 2022-04-22 2022-05-19 2022-06-02 2022-06-19 1) et Clôture de l'Hôpital de nvelope xécution 7 ty-Building ss (Non Bank-SPD MUSENYI (Lot 2) de la Comm ) une TANGARA, Province NGO ZI National Procure BI-TURIKUMWE PIU-289415- Project Management, Monito ment Document - CW-RFB / Extension du Centr Single Stage - One E En attente d 2022-11-2 IDA / D5620 ring & Evaluation and Capaci A posteriori Appel d'offres Open - National 1 Envelope proce 1,010,265.00 0.00 2022-04-22 2022-04-23 2022-05-23 2022-06-06 2022-06-23 e de Santé de GATUNGURWE nvelope 'exécution 0 ty-Building ss (Non Bank-SPD de la Commune Province Can ) kuzo National Procure BI-TURIKUMWE PIU-289419- Project Management, Monito ment Document - CW-RFB / Extension du Centr Single Stage - One E En attente d 2022-11-2 IDA / D5620 ring & Evaluation and Capaci A posteriori Appel d'offres Open - National 1 Envelope proce 858,920.00 0.00 2022-04-25 2022-04-26 2022-05-26 2022-06-09 2022-06-26 e de Sante de GASORWE (qui nvelope 'exécution 3 ty-Building ss (Non Bank-SPD évolue en Hôpital) en Provinc ) e MUYINGA GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PPA/001/G/RFQ/2019 / Fourn iture des équipements de bur Commune Socio-economic D Single Stage - One E IDA / V2860 A posteriori Demande de prix Limited 30,000.00 23,183.00 Signé 2019-10-21 2019-12-23 2019-11-05 2020-10-16 2019-11-20 eau (dix ordinateurs portable evelopment Grants nvelope s, scanner, 4 GPS, Caméra , a ppareil-photo, etc.) BI-PRODECI-049-2021-GO-RF Project Management, Monito Single Stage - One E En cours d'ex B / Fourniture des véhicules IDA / D5620 ring & Evaluation and Capaci A posteriori Appel d'offres Open - National 520,000.00 0.00 2021-08-13 2021-11-05 2021-08-15 2021-11-10 2021-09-14 2021-09-28 2021-10-25 2022-01-08 nvelope écution du PRODECI-TURIKUMWE ty-Building BI-PRODECI-051-2021-GO-RF Project Management, Monito Q / Mobilier et Equipements Single Stage - One E En cours d'ex IDA / D5620 ring & Evaluation and Capaci A posteriori Demande de prix Limited 77,000.00 0.00 2021-08-21 2021-10-01 2021-10-02 2021-11-01 de bureaux (bureaux, chaise nvelope écution ty-Building s,…) pour UGP et le BRUGP BI-PRODECI-053-2021-GO-DI Project Management, Monito R / Acquisition Logiciel TOMP Passation de marc En cours d'ex IDA / D5620 ring & Evaluation and Capaci A posteriori Direct 52,574.00 0.00 2021-08-20 2021-08-20 2021-08-25 2021-08-31 2026-02-28 RO et abonnement mensuel hé de gré à gré écution ty-Building au service d’assistance techn ique sur ce logiciel Page 1 BI-PRODECI-054-2021-GO-RF Project Management, Monito Single Stage - One E En attente d' Q / Equipements de terrain p IDA / D5620 ring & Evaluation and Capaci A posteriori Demande de prix Limited 10,000.00 0.00 2022-03-13 2022-04-24 2022-05-24 nvelope exécution our les experts de l’UGP et d ty-Building u BRUGP BI-PRODECI-056-2021-GO-RF Project Management, Monito Single Stage - One E Q / Achat des appareils télép IDA / D5620 ring & Evaluation and Capaci A posteriori Demande de prix Limited 50,000.00 0.00 Annulé 2021-08-28 2021-10-05 2021-11-04 nvelope honiques ty-Building BI-PRODECI-057-2021-GO-RF Q / Fourniture et pose des rid Project Management, Monito Single Stage - One E En cours d'ex eaux, port-rideaux et autres IDA / D5620 ring & Evaluation and Capaci A posteriori Demande de prix Limited 20,000.00 0.00 2021-08-23 2022-01-21 2021-09-26 2021-10-11 nvelope écution accessoires pour les bureau ty-Building x et la salle de réunion BI-PRODECI-047-2021-GO-DI Livelihood, Food Security an Passation de marc En cours d'ex R / Acquisition de la poudre IDA / D5620 A posteriori Direct 119,000.00 0.00 2022-02-01 2022-01-11 2022-02-06 2022-03-31 2022-03-13 2022-06-11 d Nutrition hé de gré à gré écution micro nutritive et en acide fol ique par l'UNICEF BI-PRODECI-050-2021-GO-RF Q / Equipements et consomm Project Management, Monito ables informatiques et de rep Single Stage - One E En cours d'ex IDA / D5620 ring & Evaluation and Capaci A posteriori Appel d'offres Open - National 149,400.00 0.00 2021-08-20 2021-11-22 2021-08-25 2021-12-20 2021-09-24 2021-10-08 2021-10-29 2021-12-28 rographie , Equipements pou nvelope écution ty-Building r le Service Communication p our l’UGP et le BRUGP, Fourni tures informatiques. BI-PRODECI-066-2021 / Four Project Management, Monito Single Stage - One E En cours d'ex niture et installation des Clim IDA / D5620 ring & Evaluation and Capaci A posteriori Demande de prix Limited 35,000.00 0.00 2021-10-06 2021-10-15 2021-11-15 2021-12-15 nvelope écution atiseurs ty-Building BI-PRODECI-052-2021-GO-RF Project Management, Monito Single Stage - One E En attente d' Q / Acquisition d'un groupe él IDA / D5620 ring & Evaluation and Capaci A posteriori Demande de prix Limited 15,000.00 0.00 2022-04-23 2022-06-02 2022-07-02 nvelope exécution ectrogènes pour le BRUGP ty-Building NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BI-TURIKUMWE PIU-289476- NC-RFQ / Impression et diffus Livelihood, Food Security an Single Stage - One E En attente d' IDA / D5620 A posteriori Demande de prix Limited 13,013.00 0.00 2022-04-25 2022-06-04 2022-06-19 ion d'un guide de formation d d Nutrition nvelope exécution es parents lumières CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PPA/003/QC/2019 / Elaborati Project Management, Monito Sélection fondée s on des manuels de mise en o IDA / V2860 ring & Evaluation and Capaci A posteriori ur les qualification Limited 100,000.00 0.00 Annulé 2019-11-13 2020-03-19 2019-12-07 2019-12-15 2020-01-14 euvre du Projet ty-Building s des consultants PPA/003-BIS/QC/2019 / Elab Project Management, Monito Sélection fondée s oration des manuels de mise IDA / V2860 ring & Evaluation and Capaci A posteriori ur les qualification Open - National 100,000.00 80,400.00 Signé 2020-03-19 2020-04-16 2020-05-12 2020-05-14 2020-06-02 2020-06-09 2020-06-04 2020-06-19 2020-06-08 2020-06-23 2020-07-02 en oeuvre du Projet PRODECI ty-Building s des consultants -TURIKUMWE BI-PRODECI-062-2021-CS-LC Project Management, Monito Sélection au moin Open - Internationa En cours d'exécut S / Audit comptable et financi IDA / D5620 ring & Evaluation and Capaci A posteriori 20,000.00 0.00 2022-05-01 2022-05-16 2022-05-06 2022-06-01 2022-06-06 2022-07-06 2022-08-05 2022-08-29 2022-09-22 2022-10-22 dre coût l ion er de la PPA et des exercice ty-Building s 2021 et 2022 BI-PRODECI-058-2021-CS-QC Project Management, Monito Sélection fondée s Open - Internationa En cours d'exécut BS / Recrutement du facilitat IDA / D5620 ring & Evaluation and Capaci A priori ur la qualité et le 5,500,000.00 0.00 2021-10-06 2021-10-21 2021-10-11 2021-12-21 2021-11-15 2021-12-27 2022-01-17 2022-02-21 2022-03-14 2026-02-27 l ion eur pour les sous-composant ty-Building coût es A1 et A2 BI-PRODECI-059-2021-CS-QC Project Management, Monito Sélection fondée s Open - Internationa En cours d'exécut BS / Recrutement du facilitat IDA / D5620 ring & Evaluation and Capaci A priori ur la qualité et le 4,000,000.00 0.00 2021-10-06 2021-10-21 2021-10-11 2021-12-20 2021-11-15 2021-12-27 2022-01-17 2022-02-21 2022-03-14 2026-02-27 l ion eur pour les sous-composant ty-Building coût es B1 et B2 BI-PRODECI-067-2021-CS-LC Project Management, Monito Sélection au moin En cours d'exécut S / Sélection d'un cabinet d'A IDA / D5620 ring & Evaluation and Capaci A posteriori Open - National 37,800.00 0.00 2021-12-29 2022-04-19 2022-01-19 2022-04-26 2022-03-04 2022-03-07 2022-04-06 2022-05-11 2022-06-15 2023-06-15 dre coût ion udit interne pour un audit tri ty-Building mestriel BI-MINAGRIE-061-2021-CS-C QS / Recrutement d’un cabin Project Management, Monito Sélection fondée s et pour la collecte de donnée IDA / D5620 ring & Evaluation and Capaci A posteriori ur les qualification Open - National 60,000.00 0.00 Annulé 2021-09-30 2021-09-29 2021-10-05 2021-10-26 2021-11-14 2021-12-14 2022-01-07 2022-03-08 s de l’Enquête de base et éta ty-Building s des consultants blissement de la situation de référence BI-PRODECI-066-2021-CS-CQ S-2 / Recrutement d’une ON Sélection fondée s G chargée de la mise en œuv Commune Socio-economic D IDA / D5620 A posteriori ur les qualification Open - National 289,000.00 0.00 Annulé 2022-01-25 2022-04-13 2022-05-13 2022-05-16 2022-06-01 2025-12-31 re des activités de préventio evelopment Grants s des consultants n et réponse à l’Exploitation, les Abus Sexuels (EAS) et le Harcèlement Sexuel (HS) BI-MINAGRIE-066-2021-CS-C QS / Recrutement d’une ONG Project Management, Monito Sélection fondée s chargée de la mise en œuvre IDA / D5620 ring & Evaluation and Capaci A posteriori ur les qualification Open - National 25,000.00 0.00 Annulé 2021-12-28 2021-12-21 2022-01-02 2022-02-14 2022-02-06 2022-02-21 2022-03-08 2023-03-03 des activités de prévention e ty-Building s des consultants t réponse à l’Exploitation, les Abus Sexuels (EAS) et le Har cèlement Sexuel (HS) BI-TURIKUMWE PIU-297459- CS-CQS / Surveillance et Con trôle des travaux d’Extension du DCS Gatungurwe et de l’E Sélection fondée s Commune Socio-economic D En attente d'exéc COFO Murehe en commune e IDA / D5620 A posteriori ur les qualification Limited 60,000.00 0.00 2022-06-15 2022-06-25 2022-06-30 2022-07-07 2022-11-04 evelopment Grants ution t Province CANKUZO (Lot1) e s des consultants t Extension de l’ECOFO Nzozi en commune Bweru et de l’E COFO Musumba en commun e Kinyinya tous de la Provinc e de RUYIGI (Lot 2) Page 2 BI-TURIKUMWE PIU-298596- CS-CQS / Surveillance et Con trôle des travaux d’Extension Sélection fondée s de l’ECOFO Gasekanya et de Commune Socio-economic D En attente d'exéc IDA / D5620 A posteriori ur les qualification Limited 50,000.00 0.00 2022-06-20 2022-06-30 2022-07-05 2022-07-09 2022-11-06 la Cloture de l’Hopitale de M evelopment Grants ution s des consultants usenyi en commune Tangara (Lot1) et Extension CDS Gitw a de la commune Mwumba (L ot2) tous de la Province NGO ZI BI-TURIKUMWE PIU-298582- CS-CQS / Surveillance et Con trôle des travaux d’Extension du CDS Rusimbuko en COMM Sélection fondée s Commune Socio-economic D En attente d'exéc UNE Gasorwe de la Pronvince IDA / D5620 A posteriori ur les qualification Limited 50,000.00 0.00 2022-06-15 2022-06-29 2022-07-04 2022-07-08 2022-11-05 evelopment Grants ution Muyinga (Lot1) et Extension s des consultants CDS et Réhabilitation de l'Ec ole du Camp Musasa, Extensi on de l'ECOFO-Rutobo en co mmune Kiremba de la provin ce NGOZI (Lot 2) BI-TURIKUMWE PIU-298592- CS-CQS / Surveillance et Con trôle des travaux d’Extension Sélection fondée s de l’ECOFO Murama et du ly Commune Socio-economic D En attente d'exéc IDA / D5620 A posteriori ur les qualification Limited 50,000.00 0.00 2022-06-16 2022-06-30 2022-07-30 2022-09-03 2023-03-02 cée Communal Karungura (L evelopment Grants ution s des consultants ot1), l’Extension de l’ECOFO Rukurazo et du CDS Kagozi ( lot2) en commune Mwumba de la province NGOZI INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PPA/004/CI/2019 / Elaboratio En cours d'exécut n d'un système intégré de g IDA / V2860 A posteriori Individuel Limited 23,750.00 35,989.04 2019-11-13 2019-11-07 2019-11-27 2019-11-21 2019-12-07 2019-11-25 2019-12-22 2020-01-21 ion estion du projet ainsi que la f ormation PPA/006/CI/2019 / Manuel d’ exécution du Projet et format IDA / V2860 A posteriori Individuel Limited 33,750.00 0.00 Annulé 2019-11-15 2019-11-20 2019-12-11 2020-01-15 2020-02-14 ion/sensibilisation sur le man uel PPA/007/CI/2019 / Appui à la IDA / V2860 A posteriori Individuel Limited 33,750.00 0.00 Annulé 2019-10-18 2019-11-01 2019-11-11 2019-11-17 2019-12-17 budgétisation détaillée (cost ing) PPA/008/CI/2019 / Elaboratio n d'un cadre de gestion envir Commune Socio-economic D IDA / V2860 A posteriori Individuel Limited 16,000.00 0.00 Annulé 2019-11-18 2019-10-07 2019-12-03 2019-12-13 2019-12-19 2020-01-18 onnemental et social et son evelopment Grants plan de gestion (y compris le genre) PPA/009/CI/2019 / Cadre de IDA / V2860 A posteriori Individuel Limited 12,000.00 0.00 Annulé 2019-11-22 2019-12-07 2019-12-17 2019-12-23 2020-01-22 réinstallation des populations PPA/010/CI/2019 / Plan de g IDA / V2860 A posteriori Individuel Limited 12,000.00 7,064.51 Signé 2019-11-25 2020-03-19 2019-12-10 2020-04-17 2019-12-20 2020-06-10 2019-12-26 2020-06-10 2020-01-25 estion intégrée des pesticide s PPA/012/CI/2019 / Plan de m obilisation des parties prenan IDA / V2860 A posteriori Individuel Limited 12,000.00 0.00 Annulé 2019-10-15 2019-10-22 2019-10-25 2019-10-31 2019-11-30 tes du projet PPA/017/CI/2019 / Formation sur la cartographie, digitalis IDA / V2860 A posteriori Individuel Limited 12,000.00 0.00 Annulé 2019-10-28 2019-10-31 2019-11-14 2019-11-18 2019-12-18 ation et positionnement des i nfrastructures sur Carte PPA/014/CI/2019 / Elaboratio Project Management, Monito n du PPSD du Projet PACARN IDA / V2860 ring & Evaluation and Capaci A posteriori Individuel Direct 45,000.00 35,989.04 Signé 2019-10-22 2019-11-06 2019-11-05 2019-11-21 2019-11-08 2019-11-25 2019-11-16 2019-11-25 2019-12-07 E ty-Building PPA/002/CI/2019 / Appui à la Project Management, Monito Budgétisation étaillée, costin IDA / V2860 ring & Evaluation and Capaci A posteriori Individuel Direct 35,000.00 24,438.00 Signé 2019-10-10 2019-11-07 2019-11-14 2019-11-12 2019-11-21 2019-11-15 2019-11-25 2019-11-11 2019-11-28 g et analyse économique et f ty-Building inancière du projet PPA/011/CI/2019 / Elaboratio n de trois (03) documents de sauvegarde environnemental Project Management, Monito e et sociale: (i) Cadre de Ges IDA / V2860 ring & Evaluation and Capaci A posteriori Individuel Limited 35,000.00 0.00 Annulé 2019-11-14 2019-10-28 2019-11-29 2019-12-09 2019-12-15 2020-01-14 tion Environnemental et Soci ty-Building al, (ii) Cadre de Réinstallation Involontaire, et (iii) le Cadre de planification en faveur de s peuples autochtones PPA/008/CI/2019-2 / Elaborat Project Management, Monito ion d'un Cadre de Gestion En IDA / V2860 ring & Evaluation and Capaci A posteriori Individuel Limited 16,000.00 8,775.33 Signé 2019-11-04 2019-11-04 2019-11-06 2019-11-07 2019-11-16 2019-11-11 2019-11-18 2019-11-11 2019-12-18 vironnemental et social (CGE ty-Building S) PPA/009/CI/2019-2 / Cadre d Project Management, Monito e Réinstallation involontaire IDA / V2860 ring & Evaluation and Capaci A posteriori Individuel Limited 12,000.00 8,775.33 Signé 2019-11-04 2019-11-04 2019-11-06 2019-11-07 2019-11-16 2019-11-11 2019-11-18 2019-11-11 2019-12-18 des Population ty-Building PPA/018/CI/2019 / Cadre de Project Management, Monito Planification en faveur des Po IDA / V2860 ring & Evaluation and Capaci A posteriori Individuel Limited 12,000.00 8,386.79 Signé 2019-11-04 2019-11-04 2019-11-05 2019-11-07 2019-11-15 2019-11-11 2019-11-17 2019-11-11 2019-12-17 pulations Autochtones ty-Building PPA-019-CS-CDS-2020 / Rec onduction du contrat (06 moi Project Management, Monito Sélection de cons s) pour le Responsable Admi IDA / V2860 ring & Evaluation and Capaci A posteriori ultants par entent Direct 26,400.00 39,600.00 Signé 2019-02-01 2020-02-01 2019-02-01 2020-02-01 2019-02-01 2020-02-01 2019-07-31 nistratif et Financier (Madam ty-Building e directe e Oda SINDAYIZERUKA) pour la facilitation de la préparatio n du Projet PRODECI-TURIKU MWE PPA-020-CS-CDS-2020 / Rec onduction du contrat (06 moi Project Management, Monito Sélection de cons s) pour le Responsable en Pa IDA / V2860 ring & Evaluation and Capaci A posteriori ultants par entent Direct 20,790.00 31,185.00 Signé 2019-02-01 2020-02-01 2019-02-01 2020-02-01 2019-02-01 2020-02-01 2019-07-31 ssation de Marchés (Monsieu ty-Building e directe r Antoine NDAYAMBAJE) pour la facilitation de la préparatio n du Projet PRODECI-TURIKU MWE Page 3 PPA-021-CS-CDS-2020 / Rec onduction du contrat (06 moi Project Management, Monito Sélection de cons s) pour le Responsable des S IDA / V2860 ring & Evaluation and Capaci A posteriori ultants par entent Direct 20,790.00 31,185.00 Signé 2019-02-01 2020-02-01 2019-02-01 2020-02-01 2019-02-01 2020-02-01 2019-02-01 ous-Projets pour la facilitatio ty-Building e directe n de la préparation du Projet PRODECI-TURIKUMWE PPA-022-CS-CDS-2020 / Rec onduction du contrat (06 moi s) pour le Responsable du Re Project Management, Monito Sélection de cons nforcement des Capacités et IDA / V2860 ring & Evaluation and Capaci A posteriori ultants par entent Direct 18,324.00 18,324.00 Signé 2019-02-01 2020-02-01 2019-02-01 2020-02-01 2019-02-01 2020-02-01 2019-07-31 Appuis Institutionnels (Monsi ty-Building e directe eur Callixte MBONYINGINGO) pour la facilitation de la prép aration du Projet PRODECI-TU RIKUMWE. PPA-023-CS-CDS-2020 / Rec onduction du contrat (06 moi s) pour le Responsable Irrigat Project Management, Monito Sélection de cons ion et Infrastructures (Monsie IDA / V2860 ring & Evaluation and Capaci A posteriori ultants par entent Direct 18,324.00 27,000.00 Signé 2019-02-01 2020-02-01 2019-02-01 2020-02-01 2019-02-01 2020-02-01 2019-07-31 ur Jean Bosco NTASIGWA) po ty-Building e directe ur la facilitation de la prépara tion du Projet PRODECI-TURI KUMWE PPA-024-CS-CDS-2020 / Rec onduction du contrat (06 moi Project Management, Monito Sélection de cons s) pour le Responsable Suivi- IDA / V2860 ring & Evaluation and Capaci A posteriori ultants par entent Direct 15,000.00 22,500.00 Signé 2019-02-01 2020-02-01 2019-02-01 2020-02-01 2019-02-01 2020-02-01 2019-07-31 Evaluation (Monsieur Dismas ty-Building e directe NSENGIYUMVA) pour la facilit ation de la préparation du Pr ojet PRODECI-TURIKUMWE PPA-025-CS-CDS-2020 / Rec onduction du contrat (06 moi Project Management, Monito Sélection de cons s) pour le Chef Comptable (M IDA / V2860 ring & Evaluation and Capaci A posteriori ultants par entent Direct 15,000.00 22,500.00 Signé 2019-02-01 2020-02-01 2019-02-01 2020-02-01 2019-02-01 2020-02-01 2019-07-31 onsieur Aimé NDIZEYE) pour l ty-Building e directe a facilitation de la préparatio n du Projet PRODECI-TURIKU MWE PPA-026-CS-CDS-2020 / Rec onduction du contrat (06 moi Project Management, Monito Sélection de cons s) pour un Chauffeur (Monsi IDA / V2860 ring & Evaluation and Capaci A posteriori ultants par entent Direct 2,910.00 0.00 Annulé 2019-02-01 2019-02-01 2019-02-01 2019-07-31 eur Edouard NGOYA) pour la ty-Building e directe facilitation de la préparation du Projet PRODECI-TURIKUM WE. PPA-027-CS-CDS-2020 / Rec onduction du contrat (06 moi Project Management, Monito Sélection de cons s) pour un Chauffeur (Monsie IDA / V2860 ring & Evaluation and Capaci A posteriori ultants par entent Direct 2,400.00 0.00 Annulé 2019-02-01 2019-02-01 2019-02-01 2019-07-31 ur Philippe NAHIMANA) pour l ty-Building e directe a facilitation de la préparatio n du Projet PRODECI-TURIKU MWE PPA-028-CS-CDS-2020 / App ui d'un consultant dans les tâ Project Management, Monito Sélection de cons ches relatives au nouveau ca IDA / V2860 ring & Evaluation and Capaci A posteriori ultants par entent Direct 6,000.00 8,597.29 Signé 2020-05-18 2020-05-18 2020-05-19 2020-05-28 2020-05-25 2020-06-05 2020-07-31 dre environnemental et socia ty-Building e directe l pour la facilitation de la pré paration du PRODECI-TURIKU MWE PRODECI/028/CI/2020 / Recr Project Management, Monito utement du Coordonnateur N IDA / D5620 ring & Evaluation and Capaci A posteriori Individuel Open 49,000.00 34,504.69 Signé 2020-08-25 2020-08-25 2020-10-03 2020-12-28 2020-10-08 2021-03-23 2020-10-15 2021-04-12 2021-10-15 ational du Projet ty-Building PRODECI/029/CI/2020 / Recr Project Management, Monito En cours d'exécut utement d'un Responsable A IDA / D5620 ring & Evaluation and Capaci A posteriori Individuel Open 39,900.00 0.00 2020-08-25 2020-08-25 2020-10-03 2020-10-08 2020-10-15 2021-10-15 ion dministratif et Financier du P ty-Building rojet PRODECI/030/CI/2020 / Recr Project Management, Monito utement d'un Expert en Pass IDA / D5620 ring & Evaluation and Capaci A posteriori Individuel Open 38,500.00 23,893.10 Signé 2020-08-25 2020-08-25 2020-10-03 2021-04-27 2020-10-08 2021-05-07 2020-10-15 2021-06-14 2021-10-15 ation de Marchés ty-Building PRODECI/031/CI/2020 / Recr Project Management, Monito En cours d'exécut utement d'un expert en Suivi IDA / D5620 ring & Evaluation and Capaci A posteriori Individuel Open 38,500.00 0.00 2020-08-25 2020-08-25 2020-10-03 2020-10-08 2020-10-15 2021-10-15 ion -Evaluation ty-Building PRODECI/032/CI/2020 / Recr Project Management, Monito En cours d'exécut utement d'un Spécialiste env IDA / D5620 ring & Evaluation and Capaci A posteriori Individuel Open 37,800.00 0.00 2020-08-25 2020-08-25 2020-10-03 2020-10-08 2020-10-15 2021-10-15 ion ironnemental et Social ty-Building PRODECI/033/CI/2020 / Recr Project Management, Monito En cours d'exécut utement d'un Spécialiste en I IDA / D5620 ring & Evaluation and Capaci A posteriori Individuel Open 37,800.00 0.00 2020-08-25 2020-08-25 2020-10-03 2020-10-08 2020-10-15 2021-10-15 ion nformatique et Gestion de la ty-Building Base de données Project Management, Monito PRODECI/035/CI/2020 / Séle IDA / D5620 ring & Evaluation and Capaci A posteriori Individuel Open 37,800.00 0.00 Annulé 2020-08-25 2020-08-25 2020-10-03 2020-10-08 2020-10-15 2021-10-15 ction d'un Auditeur interne ty-Building PRODECI/036/CI/2020 / Recr Project Management, Monito utement d'un Spécialiste en I IDA / D5620 ring & Evaluation and Capaci A posteriori Individuel Open 38,500.00 0.00 Annulé 2020-08-25 2020-08-25 2020-10-03 2020-10-08 2020-10-15 2021-10-15 nfrastructures et Équipement ty-Building s communaux PRODECI/37/CI/2020 / Recru Project Management, Monito En cours d'exécut tement d'un Chef Comptable IDA / D5620 ring & Evaluation and Capaci A posteriori Individuel Open 24,500.00 0.00 2020-08-25 2020-08-25 2020-10-03 2020-10-08 2020-10-15 2021-10-15 ion du Projet ty-Building Project Management, Monito PRODECI/039/CI/2020 / Recr En cours d'exécut IDA / D5620 ring & Evaluation and Capaci A posteriori Individuel Open 20,300.00 0.00 2020-08-25 2020-08-25 2020-09-24 2020-10-08 2020-10-15 2021-10-15 utement d'un Comptable ion ty-Building PRODECI/041/CI/2020 / Recr Project Management, Monito En cours d'exécut utement d'un Spécialiste Agr IDA / D5620 ring & Evaluation and Capaci A posteriori Individuel Open 37,800.00 0.00 2020-08-25 2020-08-25 2020-10-03 2020-10-08 2020-10-15 2021-10-15 ion onome/Développement rural ty-Building du Projet PRODECI/042/CI/2020 / Recr Project Management, Monito En cours d'exécut utement d'un Spécialiste en IDA / D5620 ring & Evaluation and Capaci A posteriori Individuel Open 38,500.00 0.00 2020-08-25 2020-09-22 2020-10-03 2020-10-08 2020-10-15 2021-10-15 ion Renforcement des Capacités ty-Building PRODECI/043/CI/2020 / Recr Project Management, Monito En cours d'exécut utement d'un Spécialiste en IDA / D5620 ring & Evaluation and Capaci A posteriori Individuel Open 38,500.00 0.00 2020-08-25 2020-08-25 2020-10-03 2020-10-08 2020-10-15 2020-11-20 ion Communication ty-Building PRODEC/044/CI/2020 / Recru Project Management, Monito En cours d'exécut tement d'un Coordonnateur r IDA / D5620 ring & Evaluation and Capaci A posteriori Individuel Open 35,000.00 0.00 2020-08-25 2020-08-25 2020-10-03 2020-10-08 2020-10-15 2021-10-15 ion égional du Projet ty-Building Page 4 PRODECI/045/CI/2020 / Recr Project Management, Monito En cours d'exécut utement d'un Spécialiste en IDA / D5620 ring & Evaluation and Capaci A posteriori Individuel Open 24,500.00 0.00 2020-08-25 2020-08-25 2020-10-03 2020-10-08 2020-10-15 2021-10-15 ion Suivi-Evaluation Junior ty-Building PRODECI/046/CI/2020 / Recr Project Management, Monito En cours d'exécut utement d'un Spécialiste en IDA / D5620 ring & Evaluation and Capaci A posteriori Individuel Open 24,500.00 0.00 2020-08-25 2020-09-21 2020-10-03 2020-10-08 2020-10-15 2021-10-15 ion Passation de marchés junion ty-Building BI-MIDCSP-01-CS-CDS / Reco nduction du Contrat du RAF p Project Management, Monito Sélection de cons En cours d'exécut our une période de trois (03) IDA / D5620 ring & Evaluation and Capaci A posteriori ultants par entent Direct 13,200.00 0.00 2020-11-27 2020-11-27 2020-11-30 2020-12-07 2020-12-01 2021-02-28 ion mois en vue de faciliter la tra ty-Building e directe nsition de la mise en oeuvre du PRODECI-TURIKUMWE BI-MIDCSP-02-CS-CDS / Reco nduction du contrat du SPM p Project Management, Monito Sélection de cons En cours d'exécut our une période de trois (03) IDA / D5620 ring & Evaluation and Capaci A posteriori ultants par entent Direct 10,395.00 0.00 2020-11-27 2020-11-27 2020-11-30 2020-12-07 2020-12-01 2021-02-28 ion mois en vue de faciliter la tra ty-Building e directe nsition de la mise en œuvre du PRODECI-TURIKUMWE BI-MIDCSP-03-CS-CDS / Reco nduction du contrat du Chef Project Management, Monito Sélection de cons Comptable pour une période En cours d'exécut IDA / D5620 ring & Evaluation and Capaci A posteriori ultants par entent Direct 7,500.00 0.00 2020-11-27 2020-11-27 2020-11-30 2020-12-07 2020-12-01 2021-02-28 de trois (03) mois en vue de f ion ty-Building e directe aciliter la transition de la mis e en œuvre du PRODECI-TURI KUMWE BI-MIDCSP-04-CS-CDS / Reco Project Management, Monito Sélection de cons nduction du contrat du RAF p En cours d'exécut IDA / D5620 ring & Evaluation and Capaci A posteriori ultants par entent Direct 6,600.00 6,570.65 2021-03-04 2021-03-05 2021-03-04 2021-03-05 2021-03-05 2021-06-04 our la période de transition a ion ty-Building e directe vant la mise en œuvre du PR ODECI-TURIKUMWE BI-MIDCSP-05-CS-CDS / Reco nduction du contrat du Chef Project Management, Monito Sélection de cons En cours d'exécut comptable pour la période tr IDA / D5620 ring & Evaluation and Capaci A posteriori ultants par entent Direct 5,100.00 5,395.95 2021-03-04 2021-03-05 2021-03-04 2021-03-05 2021-03-05 2021-06-04 ion ansitoire de 03 mois avant la ty-Building e directe mise en œuvre du PRODECI- TURIKUMWE BI-PRODECI-063-2021-CS-IN Project Management, Monito En cours d'exécut DV / Recrutement d'un spéci IDA / D5620 ring & Evaluation and Capaci A posteriori Individuel Open 24,175.00 0.00 2021-08-13 2021-08-12 2021-10-06 2021-10-11 2021-10-18 2022-10-18 ion aliste en Genre ty-Building BI-MINAGRIE-064-2021-CS-I Project Management, Monito En cours d'exécut NDV / Recrutement d'un spéc IDA / D5620 ring & Evaluation and Capaci A posteriori Individuel Open 24,175.00 0.00 2021-08-11 2021-08-12 2021-10-04 2021-10-09 2021-10-16 2022-10-16 ion ialiste en nutrition ty-Building PRODECI/034/CI/2020 / Recr Project Management, Monito utement d'un Spécialiste en IDA / D5620 ring & Evaluation and Capaci A posteriori Individuel Open 38,500.00 0.00 Annulé 2020-08-25 2020-08-25 2020-10-03 2020-10-08 2020-10-15 2021-10-15 Nutrition et Genre ty-Building BI-PRODECI-065-2021-CS-IN Project Management, Monito DV / Elaboration de la stratég IDA / D5620 ring & Evaluation and Capaci A posteriori Individuel Open 20,000.00 0.00 Annulé 2021-08-23 2021-10-09 2021-10-14 2021-10-21 2021-11-20 ie de communication ty-Building PRODECI/036/CI/2020-2 / Re Project Management, Monito crutement d'un Spécialiste e En cours d'exécut IDA / D5620 ring & Evaluation and Capaci A posteriori Individuel Open 24,200.00 0.00 2021-12-23 2021-12-23 2022-01-11 2022-01-16 2022-01-18 2023-01-17 n Infrastructures et Equipem ion ty-Building ents communaux PRODECI/040/CI/2020 / Recr Project Management, Monito utement d'un Assistant en Pa IDA / D5620 ring & Evaluation and Capaci A posteriori Individuel Open 24,500.00 0.00 Annulé 2020-08-25 2020-08-25 2020-10-03 2020-10-08 2020-10-15 2021-10-15 ssation de Marchés ty-Building BI-PRODECI-067-2022-CS-CQ S / / Recrutement d'un Consu Project Management, Monito En cours d'exécut ltant individuel pour appuyer IDA / D5620 ring & Evaluation and Capaci A posteriori Individuel Limited 9,900.00 0.00 2022-02-07 2022-02-24 2022-02-10 2022-02-13 2022-02-18 2022-05-19 ion le Projet au niveau des dossi ty-Building ers d'infrastructures des com munes PRODECI/040/CI/2020-2 / Re Project Management, Monito crutement d'un Spécialiste e En cours d'exécut IDA / D5620 ring & Evaluation and Capaci A posteriori Individuel Open 12,000.00 0.00 2022-02-18 2022-05-12 2022-03-29 2022-04-03 2022-04-10 2023-04-10 n Passation de Marchés Junio ion ty-Building r basé à Muyinga BI-TURIKUMWE PIU-281132- CS-INDV / Recrutement de M Project Management, Monito En cours d'exécut onsieur MASUMBUKO Jean de IDA / D5620 ring & Evaluation and Capaci A posteriori Individuel Direct 40,000.00 0.00 2022-03-04 2022-03-10 2022-03-07 2022-03-12 2022-03-16 2023-03-15 ion Dieu, Coordonnateur Adjoint ty-Building du PRODECI-TURIKUMWE BI-TURIKUMWE PIU-289424- CS-INDV / Recrutement d’un consultant individuel chargé de mener une étude sur les o Livelihood, Food Security an En cours d'exécut IDA / D5620 A posteriori Individuel Open 25,000.00 0.00 2022-04-25 2022-04-19 2022-05-29 2022-06-03 2022-06-22 2022-08-01 pportunités économiques po d Nutrition ion ur les populations des cinq c amps des refugies congolais au Burundi et les populations hôtes des collines sous-jacen tes BI-TURIKUMWE PIU-289472- CS-INDV / Réalisation d’une é tude de faisabilité des jardins potagers et renforcement de Livelihood, Food Security an En cours d'exécut IDA / D5620 A posteriori Individuel Open 30,000.00 0.00 2022-04-15 2022-04-19 2022-05-17 2022-05-20 2022-05-30 2022-07-14 s capacités sur des modèles d Nutrition ion porteurs et innovants de jard ins potagers pour les populat ions des cinq camps des réfu giés (Consultant international ) BI-PRODECI-066-2021-CS-CD S / Recrutement de l'ONG SA VE THE CHILDREN pour la mi Sélection de cons Commune Socio-economic D En cours d'exécut se en œuvre des activités de IDA / D5620 A posteriori ultants par entent Direct 958,684.00 0.00 2021-12-21 2021-12-25 2022-04-24 2022-04-28 2022-05-16 2025-12-31 evelopment Grants ion prévention et réponse à l’Exp e directe loitation, les Abus Sexuels (E AS) et le Harcèlement Sexuel (HS) BI-TURIKUMWE PIU-291009- CS-CDS / Sélection du Cabine t EIFEL CONSULTING pour la surveillance et contrôle des t Sélection de cons Commune Socio-economic D En cours d'exécut ravaux de construction des i IDA / D5620 A posteriori ultants par entent Direct 120,000.00 0.00 2022-04-20 2022-05-20 2022-04-24 2022-05-25 2022-05-09 2022-09-06 evelopment Grants ion nfrastructures priorisées par e directe les communes (infrastucture s ne nécessitant pas d'étude s détaillées d'impact environ nemental et social) Page 5 BI-TURIKUMWE PIU-295677- CS-CDS / Recrutement du ca binet SETRAGEC pour la surv Sélection de cons eillance et Contôle des trava Commune Socio-economic D En cours d'exécut IDA / D5620 A posteriori ultants par entent Direct 50,000.00 0.00 2022-05-19 2022-05-18 2022-05-23 2022-05-25 2022-06-01 2022-09-29 ux d'extension de l'ECOFO T evelopment Grants ion e directe URA de la Commune GASHO HO et de Construction de tro is hangars de stockage dans la commune de BUTIHINDA Page 6