Procurement Plan Guangxi Rural Poverty Alleviation Pilot Project I. General 1. Bank’s approval Date of the procurement Plan [Original: November 4, 2016]: Revision 1 of Updated Procurement Plan, June 1, 2017, Revision 2: July 24, 2018] 2. Date of General Procurement Notice: Jan. 13, 2017 3. Period covered by this procurement plan: 2017-2022 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ 2,000,000 2. NCB (Goods) Above US$ 2,000,000 3. ICB (Works) Above US$ 10 million 4. NCB (Works) Above US$ 10 million 5. (Non-Consultant Services) Below US$ 2,000,000 [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: [Refer to the relevant CDD project implementation Manual approved by the Bank] 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project issued by Guangxi Regional PMO 5. Any Other Special Procurement Arrangements: N/A 6. Summary of the Procurement Packages ( including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Ref. Descripti Estimat Packages Dome Review Comme No. on ed stic by Bank nts Cost Prefe (Prior / US$ rence Post) million (yes/ no) Summary of the ICB (Works) Summary of the ICB (Goods) Summary of the NCB (Works) Summary of the NCB (Goods) Summary of the ICB (Non- Consultant Services) Summary 0.0386 1 No Post of Shopping (Goods) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 1,000,000 2. Single Source (Firms) Above US$ 1,000,000 3. Individual Above US$ 300,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_500,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimat Package Review Comment of ed s by Bank s Assignmen Cost (Prior / t US$ Post) million Summary of number of contracts that will be let under QCBS Summary 0.5662 3 Post CQS of number of contracts that will be let under other methods PROCUREMENT China : Guangxi Rural Poverty Alleviation Pilot Project PLAN General Information Country: China 2017-06-11 Bank’s Approval Date of the Original Procurement Plan: 2022-06-21 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P153892 GPN Date: 2017-01-13 Project Name: Guangxi Rural Poverty Alleviation Pilot Project Loan / Credit No: IBRD / 86700 Guangxi Foreign Capital Poverty Reduction PM Center Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GXTD-GC-2021-01 / Guangxi Tiandong County Xingliang M Request for Quota Enhancing Investments in Po Request for Quota Single Stage - One E Under Imple 2022-07-1 ango Planting farmers cooper IBRD / 86700 Post Open - National tions (Non Bank-S 304,500.00 0.00 2021-11-22 2022-01-17 or Areas tions nvelope mentation 6 ative piggery and supporting PD) facilities and equipment cons truction project GXTD-GC-2021-21 / Guangxi Tiandong County, Zihe Planti Request for Quota ng and Raising Farmers' Prof Enhancing Investments in Po Request for Quota Single Stage - One E Pending Imp 2022-07-1 IBRD / 86700 Post Open - National tions (Non Bank-S 321,507.00 0.00 2021-11-22 2022-01-17 essional cooperative piggery or Areas tions nvelope lementation 6 PD) and supporting facilities and equipment construction proje ct GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CN-GXFCPRPMC-24076-GO-R FQ / ð 5 4ð ° , 5 9ð S p : Project Management, Monito Request for Quota Single Stage - One E 5ð S p p S : 1ð • q ê 1ð p IBRD / 86700 Post Limited 38,600.00 35,794.95 Completed 2018-07-31 2018-08-01 2018-09-24 2018-09-10 2019-03-23 2018-10-12 ring and Evaluation tions nvelope ø : 4ð p D Ï : 1ð U ó 3/ û ¨ l Ø 5* Ž ¸ : 8ð GXFS-HW-07-2020 / Fengsha n County to purchase office e Enhancing Investments in Po Request for Quota Single Stage - One E IBRD / 86700 Post Open - National 23,077.00 20,612.05 Completed 2020-06-23 2020-10-28 2020-07-21 2020-07-15 2020-08-30 2020-08-13 quipment, air conditioners an or Areas tions nvelope d office furniture for business incubation center GXSH-TLHW-04 / Tianlin busi Improvement of Pro-Poor Val Request for Quota Single Stage - One E ness incubation center plans IBRD / 86700 Post Open - National 30,305.00 30,605.02 Completed 2021-02-01 2021-03-09 2020-07-09 2021-04-09 2020-07-16 ue Chains tions nvelope to buy office equipment and f urniture. GXDL-HW-2020-01 / As Don glan PMO purchased a batch of office equipment with sho pping, it plans to buy one co Project Management, Monito IBRD / 86700 Post Direct Selection Direct 1,323.00 1,322.18 Completed 2021-01-27 2020-06-25 2021-02-01 2020-07-15 2021-02-03 2020-07-15 2021-02-04 2020-07-15 mputer and one printer whic ring and Evaluation h cost less than 2000USD, s o it will purchase directly fro m the originally selected sup plier with the original contrac t price. GXBMWZB-HW-2020-01 / As Bama Project management o ffice purchased a batch of off ice equipment with shopping, Project Management, Monito IBRD / 86700 Post Direct Selection Direct 1,970.00 1,988.60 Completed 2021-01-27 2020-07-01 2021-02-01 2020-07-24 2021-02-05 2020-07-24 2021-02-05 2020-08-07 it plans to buy two laptops w ring and Evaluation hich cost less than 2000USD , so it will purchase from the originally selected suppler dir ectly with the original contra ct price. GXDL-HW-HS-2021-02 / Don Project Management, Monito Request for Quota Single Stage - One E glan Huashen Silk Company's IBRD / 86700 Post Open - National 461,538.46 340,462.41 Completed 2021-03-31 2021-08-05 2021-05-26 2021-08-06 2021-11-22 2021-08-06 ring and Evaluation tions nvelope purchase of silk reeling equip ment . GXBMSYFH-HW-2021-01 / Pr Project Management, Monito Request for Quota Single Stage - One E ocurement of office equipme IBRD / 86700 Post Open - National 2,461.00 2,575.53 Completed 2021-04-11 2021-06-06 2021-06-08 2021-12-03 2021-07-28 ring and Evaluation tions nvelope nt by Bama County BIC GXYZ-HW-JL001 / Guangxi Ji Improvement of Pro-Poor Val alian Silk Co., Ltd. Rapier Loo IBRD / 86700 Post Direct Selection Direct 498,000.00 485,621.09 Completed 2021-11-18 2021-11-15 2021-11-23 2022-01-12 2021-12-28 2022-01-25 2022-06-26 2022-04-18 ue Chains m Procurement GXTL-ZK-XFY-HW-2021-01 / Guangxi Tianlin Xin Fuyuan C Improvement of Pro-Poor Val Request for Quota Single Stage - One E Pending Impl IBRD / 86700 Post Open - National 43,076.92 0.00 2021-11-23 2022-01-18 2022-07-17 amellia Oil Development Co., ue Chains tions nvelope ementation LTD. Logistics distribution ve hicle procurement. GXTL-ZK-XFY-HW-2021-02 / Guangxi Tianlin Xinfuyuan Ca Improvement of Pro-Poor Val Request for Quota Single Stage - One E Pending Impl mellia Oil Development Co., IBRD / 86700 Post Open - National 58,461.54 0.00 2021-11-23 2022-01-18 2022-07-17 ue Chains tions nvelope ementation LTD. Light freight vehicles, c old chain transport vehicles p rocurement GXLY-HW-HD-01 / Procurem ent of beef quality testing eq Improvement of Pro-Poor Val Request for Quota Single Stage - One E Pending Impl IBRD / 86700 Post Open - National 123,100.00 0.00 2021-12-14 2022-02-08 2022-08-07 uipment of Guangxi Leye Hu ue Chains tions nvelope ementation adong Investment Co., Ltd GXLY-HW-HD-02 / Procurem ent of fresh meat processing Improvement of Pro-Poor Val Request for Quota Single Stage - One E Pending Impl IBRD / 86700 Post Open - National 123,100.00 0.00 2021-12-14 2022-02-08 2022-08-07 equipment of Guangxi Leye ue Chains tions nvelope ementation Huadong Investment Co., Ltd . GXLY-HW-HD-03 / Procurem ent of beef ball processing e Improvement of Pro-Poor Val Request for Quota Single Stage - One E Pending Impl IBRD / 86700 Post Open - National 138,500.00 0.00 2021-12-14 2022-02-08 2022-08-07 quipment of Guangxi Leye H ue Chains tions nvelope ementation uadong Investment Co., Ltd Page 1 GXTL-ZK-XFY-HW-2021-03 / Procurement of 3T type Cam ellia oleifera fruit complete tr eatment and production equi Improvement of Pro-Poor Val Request for Quota Single Stage - One E IBRD / 86700 Post Open - National 476,923.00 465,444.51 Completed 2021-12-30 2022-06-06 2022-02-24 2022-01-06 2022-08-23 2022-03-26 pment (shelling and sorting, ue Chains tions nvelope drying, specific gravity sortin g and packaging section) of Guangxi Tianlin Xinfuyuan Ca mellia Oil Development Co., Ltd GXTL-ZK-XFY-HW-2021-04 / Procurement of 3T type Cam ellia oleifera fruit complete tr Improvement of Pro-Poor Val Request for Quota Single Stage - One E Pending Impl eatment production equipme IBRD / 86700 Post Open - National 76,923.08 0.00 2022-01-04 2022-03-01 2022-08-28 ue Chains tions nvelope ementation nt (small Camellia oleifera fru it treatment system) of Guan gxi Tianlin Xinfuyuan Camelli a Oil Development Co., Ltd GXDL-HW-HS-03 / Guangxi D onglan Huashen Silk Co., LTD Improvement of Pro-Poor Val Request for Quota Single Stage - One E Pending Impl IBRD / 86700 Post Open - National 169,230.00 0.00 2022-01-04 2022-03-01 2022-08-28 . Second batch of automatic ue Chains tions nvelope ementation silk reeling machine procure ment GXFS-HW-JH--02 / Guangxi F engshan Jiahong Seed And S Improvement of Pro-Poor Val Request for Quota Single Stage - One E Pending Impl eedling Co., LTD. Type 85 wh IBRD / 86700 Post Open - National 36,923.08 0.00 2022-01-04 2022-03-01 2022-08-28 ue Chains tions nvelope ementation eel wood grabper (loading an d unloading, feeding) equipm ent purchase. GXFS-HW-JH--03 / Guangxi F engshan Jiahong Seed And S Improvement of Pro-Poor Val Request for Quota Single Stage - One E Pending Impl IBRD / 86700 Post Open - National 30,769.23 0.00 2022-01-04 2022-03-01 2022-08-28 eedling Co., LTD. Credit wood ue Chains tions nvelope ementation tea drying equipment purcha se. GXFS-HW-JH-2021-06 / Guan Improvement of Pro-Poor Val Request for Quota Single Stage - One E Pending Impl gxi Fengshan Jiahong Seed C IBRD / 86700 Post Open - National 69,230.77 0.00 2022-01-04 2022-03-01 2022-08-28 ue Chains tions nvelope ementation o., LTD. Transport vehicle pro curement GXFS-HW-JH-2021-07 / Guan gxi Fengshan Jiahong Seed C Improvement of Pro-Poor Val Request for Quota Single Stage - One E Pending Impl IBRD / 86700 Post Open - National 131,261.54 0.00 2022-01-04 2022-03-01 2022-08-28 o., LTD. Walnut processing pr ue Chains tions nvelope ementation oduction line procurement GXFS-HW-JH-2021-08 / Guan gxi Fengshan Jiahong Seed C Improvement of Pro-Poor Val Request for Quota Single Stage - One E Pending Impl IBRD / 86700 Post Open - National 200,000.00 0.00 2022-01-04 2022-03-01 2022-08-28 o., LTD. Medicinal drying equi ue Chains tions nvelope ementation pment procurement GXFS-HW-JH-2021-09 / Guan gxi Fengshan Jiahong Seed C Improvement of Pro-Poor Val Request for Quota Single Stage - One E Pending Impl IBRD / 86700 Post Open - National 52,769.23 0.00 2022-01-04 2022-03-01 2022-08-28 o., LTD. Medicinal processing ue Chains tions nvelope ementation production line equipment pr ocurement. GXBM-HW-XGJ-2021-01 / Gu angxi Bama Xiaogu Chicken Improvement of Pro-Poor Val Request for Quota Single Stage - One E Pending Impl IBRD / 86700 Post Open - National 70,769.23 0.00 2022-01-04 2022-03-01 2022-08-28 Breeding Co., LTD. Refrigerat ue Chains tions nvelope ementation ed vehicle procurement GXBM-HW-XGJ-2021-02 / Gu angxi Bama Xiaogu Chicken Improvement of Pro-Poor Val Request for Quota Single Stage - One E Pending Impl IBRD / 86700 Post Open - National 92,307.69 0.00 2022-01-04 2022-03-01 2022-08-28 Breeding Co., LTD. Cold stora ue Chains tions nvelope ementation ge equipment procurement. GXBM-HW-XGJ-2021-03 / Gu angxi Bama Xiaogu Chicken Improvement of Pro-Poor Val Request for Quota Single Stage - One E Pending Impl IBRD / 86700 Post Open - National 53,846.15 0.00 2022-01-04 2022-03-01 2022-08-28 Breeding Co., LTD. Slaughter ue Chains tions nvelope ementation equipment procurement. GXBM-HW-XGJ-2021-07 / Gu angxi Bama Xiaogu Chicken Improvement of Pro-Poor Val Request for Quota Single Stage - One E Pending Impl IBRD / 86700 Post Open - National 405,538.46 0.00 2022-01-04 2022-03-01 2022-08-28 Breeding Co., LTD. Productio ue Chains tions nvelope ementation n line machinery equipment procurement. GXDA-GHQ-HW-2021-01 / G uangxi Guihequan Ecological Improvement of Pro-Poor Val Request for Quota Single Stage - One E Under Imple IBRD / 86700 Post Open - National 270,769.00 0.00 2021-12-31 2022-02-25 2022-08-24 Agriculture Co.,ltd.Oganic fer ue Chains tions nvelope mentation tilizer processing equipment procurement. GXDH-ZK-HW-GT2021-01 / G uangxi Dahua Guitong Agricu lture and Forestry Developm Improvement of Pro-Poor Val Request for Quota Single Stage - One E Under Imple IBRD / 86700 Post Open - National 498,000.00 0.00 2022-01-22 2022-03-19 2022-09-15 ent Co., LTD. Chicken coops ue Chains tions nvelope mentation and thermal insulation autom atic feeding equipment procu rement GXDL-HW-HS-001 / Cocoon b Enhancing Investments in Po Request for Quota Single Stage - One E Under Imple askets procurement by Dongl IBRD / 86700 Post Open - National 307,692.00 0.00 2022-01-22 2022-03-19 2022-09-15 or Areas tions nvelope mentation an Huashen Silk company GXDL-ZK-GL-01 / Guangxi D onglan Guilong Ecological Ag Improvement of Pro-Poor Val Request for Quota Single Stage - One E Under Imple riculture Science and Technol IBRD / 86700 Post Open - National 461,538.50 0.00 2022-01-22 2022-03-19 2022-09-15 ue Chains tions nvelope mentation ogy Co., LTD., the first batch of fresh air circulation syste m. GXBMWZB-HW-2022-01 / Ba ma Yao Autonomous County I Public Infrastructure and Ser Single Stage - One E Pending Impl IBRD / 86700 Post Request for Bids Open - National 760,000.00 0.00 2022-07-01 2022-07-06 2022-08-17 2022-09-16 2022-10-21 2023-04-19 ndustrial Chain Risk - Food T vices nvelope ementation esting Equipment Procureme nt NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GXLY-FZX-10 / LeYe busines s incubation center plans to purchase financial software s Improvement of Pro-Poor Val IBRD / 86700 Post Direct Selection Direct 1,425.00 1,493.68 Signed 2021-01-27 2020-09-07 2021-02-01 2020-09-08 2021-02-05 2020-09-26 2021-08-12 ervice, with budget around 1 ue Chains 500USD, as there is no suppli er in the Leye county, it mak e enquiries online . Page 2 GXPG-FZX-2021-03 / Pinggu Project Management, Monito Request for Quota Single Stage - One E o PMO purchases project ma IBRD / 86700 Post Open - National 12,300.00 4,557.81 Signed 2021-05-25 2021-08-04 2021-07-20 2021-08-05 2022-07-20 ring and Evaluation tions nvelope nagement service for civil wo rks. GXPG-FZX-2021-06 / Pinggu Improvement of Pro-Poor Val Request for Quota Single Stage - One E o PMO purchses soil detectio IBRD / 86700 Post Open - National 23,000.00 23,086.45 Completed 2021-03-06 2021-08-06 2021-05-01 2021-03-30 2021-06-30 2021-07-01 ue Chains tions nvelope n service and forage detectio n service. GXTD-FZX-2021-01 / World Project Management, Monito Request for Quota Single Stage - One E Pending Impl Bank project engineering des IBRD / 86700 Post Open - National 33,846.15 0.00 2021-11-22 2022-01-17 2022-07-16 ring and Evaluation tions nvelope ementation ign service procurement in Ti andong County. GXTD-FZX-2021-02 / World Bank project engineering sup Project Management, Monito Request for Quota Single Stage - One E Pending Impl IBRD / 86700 Post Open - National 38,461.54 0.00 2021-11-22 2022-01-17 2022-07-16 ervision service procuremen ring and Evaluation tions nvelope ementation t in Tiandong County GXTD-FZX-2021-03 / Tiando ng County project cooperativ Public Infrastructure and Ser Request for Quota Single Stage - One E Pending Impl IBRD / 86700 Post Open - National 20,000.00 0.00 2021-11-22 2022-01-17 2022-07-16 es agricultural products certif vices tions nvelope ementation ication service procurement GXTD-FZX-2021-04 / Design and Registration of Agricultur Public Infrastructure and Ser Request for Quota Single Stage - One E Pending Impl IBRD / 86700 Post Open - National 18,461.00 0.00 2021-11-22 2022-01-17 2022-07-16 al Product Trademarks of Proj vices tions nvelope ementation ect Cooperatives in Tiandong County GXTD-FZX-2021-05 / Tiando Improvement of Pro-Poor Val Request for Quota Single Stage - One E Pending Impl ng County Project Cooperativ IBRD / 86700 Post Open - National 77,307.00 0.00 2021-11-22 2022-01-17 2022-07-16 ue Chains tions nvelope ementation es Asset Assessment CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CN-GXFCPRPMC-16732-CS-C Project Management, Monito Consultant Qualifi QS / Ç - MISy î ¡ û ß Œ M W „ û ß IBRD / 86700 Post Open - National 73,800.00 71,447.71 Signed 2017-10-10 2018-07-16 2017-10-31 2018-07-16 2017-12-14 2018-08-08 2018-01-13 2018-08-28 2018-02-17 2018-10-09 2022-12-30 ring and Evaluation cation Selection ô ¤ / ‘ ¡ CN-GXFCPRPMC-24081-CS-C Enhancing Investments in Po Consultant Qualifi IBRD / 86700 Post Open - National 246,200.00 238,159.02 Completed 2018-07-24 2018-07-27 2018-08-14 2018-12-25 2018-09-27 2018-08-21 2018-10-27 2018-09-06 2018-12-01 2018-10-09 2019-05-30 2019-10-08 QS / § þ Î i Ä 0 Œ Ä or Areas cation Selection CN-GXFCPRPMC-24083-CS-C Project Management, Monito Consultant Qualifi IBRD / 86700 Post Open - National 246,200.00 238,159.02 Completed 2018-07-24 2018-08-20 2018-08-14 2018-12-25 2018-09-27 2018-09-14 2018-10-27 2018-10-09 2018-12-01 2018-11-01 2019-05-30 2019-10-31 QS / \ > • D ¡ f € / ¨ â ¡ ring and Evaluation cation Selection CN-GXFCPRPMC-69880-CS-C Project Management, Monito Consultant Qualifi IBRD / 86700 Post Open - National 73,800.00 71,447.71 Completed 2018-07-24 2018-07-27 2018-08-14 2018-12-25 2018-09-27 2018-09-03 2018-10-27 2018-09-28 2018-12-01 2018-11-01 2019-05-30 2019-10-31 QS / \ > ù - Œ ý › ú ¾ ring and Evaluation cation Selection GXSJ-ZX-05 / Project Manage ment- provide project manag Project Management, Monito Quality And Cost- Open - Internationa ement consulting services for IBRD / 86700 Post 984,600.00 723,554.08 Signed 2019-01-23 2019-01-25 2019-02-13 2019-03-12 2019-03-29 2019-04-30 2019-04-26 2019-06-17 2019-05-26 2019-06-17 2019-06-30 2019-07-04 2019-08-04 2019-08-30 2020-08-03 ring and Evaluation Based Selection l project manangement office s in autonomous regions, citi es and counties GXSJ-ZX-06 / Monitoring ass essment from the thrid party Project Management, Monito Consultant Qualifi IBRD / 86700 Post Open - National 298,500.00 271,863.65 Signed 2019-01-25 2019-01-25 2019-02-15 2019-03-31 2019-03-25 2019-04-30 2019-07-27 2019-06-04 2019-08-30 2019-12-01 -provide external monitoring ring and Evaluation cation Selection and evaluation for the projec t from the thrid party GXSJ-ZX-07 / Project financia l guidance and inspection -To Project Management, Monito Consultant Qualifi provide financial guidance, in IBRD / 86700 Post Open - National 276,900.00 249,371.34 Signed 2019-03-31 2019-04-22 2019-04-21 2019-06-04 2019-05-09 2019-07-04 2019-05-28 2019-08-08 2019-06-14 2020-02-04 ring and Evaluation cation Selection spection and consulting servi ces for PMOs in autonomous regions, cities and counties GXSJ-ZX-08 / Purchase of co nsulting service for Business Enhancing Investments in Po Consultant Qualifi Incubation Center informatio IBRD / 86700 Post Open - National 184,615.38 165,728.49 Signed 2020-05-07 2020-05-11 2020-05-21 2020-06-11 2020-06-08 2020-07-11 2020-07-14 2020-08-15 2020-07-08 2021-02-11 or Areas cation Selection n platform (APP) developmen t, operation and maintenanc e GXDL-ZX-10 / Donglan count y purchased livestock and po Public Infrastructure and Ser Consultant Qualifi Under Implement IBRD / 86700 Post Open - National 252,307.00 0.00 2021-12-30 2021-04-01 2022-01-20 2022-03-05 2022-04-04 2022-05-09 2022-11-05 ultry disease prevention and vices cation Selection ation control risk mitigation servic es. GXPG-ZX-2022-04 / Pingguo city rural revitalization villag Project Management, Monito Consultant Qualifi Under Implement IBRD / 86700 Post Open - National 290,000.00 0.00 2022-06-01 2022-04-28 2022-06-22 2022-05-20 2022-08-05 2022-09-04 2022-10-09 2023-04-07 e planning services (one proj ring and Evaluation cation Selection ation ect village and one non-proje ct village) GXTD-ZX-2022-13 / Tiandon g county rural revitalization v Project Management, Monito Consultant Qualifi Under Implement IBRD / 86700 Post Open - National 290,000.00 0.00 2022-06-01 2022-04-28 2022-06-22 2022-05-20 2022-08-05 2022-09-04 2022-10-09 2023-04-07 illage planning services (one ring and Evaluation cation Selection ation project village and one non-p roject village) GXTL-ZX-2022-15 / Tianlin c ounty rural revitalization villa Project Management, Monito Consultant Qualifi Under Implement IBRD / 86700 Post Open - National 290,000.00 0.00 2022-06-01 2022-04-28 2022-06-22 2022-05-20 2022-08-05 2022-09-04 2022-10-09 2023-04-07 ge planning services (one pro ring and Evaluation cation Selection ation ject village and one non-proj ect village) GXLY-ZX-2022-05 / Leye cou nty rural revitalization village Project Management, Monito Consultant Qualifi Under Implement IBRD / 86700 Post Open - National 290,000.00 0.00 2022-06-01 2022-04-28 2022-06-22 2022-05-20 2022-08-05 2022-09-04 2022-10-09 2023-04-07 planning services (one projec ring and Evaluation cation Selection ation t village and one non-project village) GXBMWZB-ZX-2022-10 / Ba ma Yao Autonomous county r Project Management, Monito Consultant Qualifi Under Implement ural revitalization village plan IBRD / 86700 Post Open - National 290,000.00 0.00 2022-06-01 2022-04-28 2022-06-22 2022-05-20 2022-08-05 2022-09-04 2022-10-09 2023-04-07 ring and Evaluation cation Selection ation ning services (one project vill age and one non-project villa ge) GXFSXMB-ZX-2022-02 / Fen gshan county rural revitalizat Project Management, Monito Consultant Qualifi Under Implement IBRD / 86700 Post Open - National 290,000.00 0.00 2022-06-01 2022-04-28 2022-06-22 2022-05-20 2022-08-05 2022-09-04 2022-10-09 2023-04-07 ion village planning services ring and Evaluation cation Selection ation (one project village and one non-project village) Page 3 GXDH-ZX-2022-06 / Dahua Y ao Autonomous county rural Project Management, Monito Consultant Qualifi Under Implement revitalization village planning IBRD / 86700 Post Open - National 290,000.00 0.00 2022-06-01 2022-04-28 2022-06-22 2022-05-20 2022-08-05 2022-09-04 2022-10-09 2023-04-07 ring and Evaluation cation Selection ation services (one project village and one non-project village) GXDA-ZX-2022-01 / Du'an Y ao Autonomous county rural Project Management, Monito Consultant Qualifi Under Implement revitalization village planning IBRD / 86700 Post Open - National 280,000.00 0.00 2022-06-01 2022-04-28 2022-06-22 2022-05-20 2022-08-05 2022-09-04 2022-10-09 2023-04-07 ring and Evaluation cation Selection ation services (one project village and one non-project village) GXYZ-ZX-2022-01 / Yizhou D istrict rural revitalization villa Project Management, Monito Consultant Qualifi Under Implement IBRD / 86700 Post Open - National 290,000.00 0.00 2022-06-01 2022-04-28 2022-06-22 2022-05-20 2022-08-05 2022-09-04 2022-10-09 2023-04-07 ge planning services (one pro ring and Evaluation cation Selection ation ject village and one non-proj ect village) GXDLXMC-ZX-2022-04 / Don glan county rural revitalizatio Project Management, Monito Consultant Qualifi Under Implement IBRD / 86700 Post Open - National 290,000.00 0.00 2022-06-01 2022-05-12 2022-06-22 2022-05-20 2022-08-05 2022-09-04 2022-10-09 2023-04-07 n village planning services (o ring and Evaluation cation Selection ation ne project village and one no n-project village) GXSJ-ZX-2022-02 / BIC popul Project Management, Monito Consultant Qualifi Pending Impleme IBRD / 86700 Post Open - National 153,846.00 0.00 2022-07-01 2022-07-22 2022-09-04 2022-10-04 2022-11-08 2023-05-07 arize service ring and Evaluation cation Selection ntation GXSJ-ZX-2022-04 / Procurem Project Management, Monito Consultant Qualifi Pending Impleme IBRD / 86700 Post Open - National 153,846.00 0.00 2022-07-10 2022-07-31 2022-09-13 2022-10-13 2022-11-17 2023-05-16 ent of project publicity servic ring and Evaluation cation Selection ntation es GXSJ-ZX-2022-05 / Procurem Project Management, Monito Consultant Qualifi Pending Impleme ent of project publicity atlas IBRD / 86700 Post Open - National 46,000.00 0.00 2022-08-01 2022-08-22 2022-10-05 2022-11-04 2022-12-09 2023-06-07 ring and Evaluation cation Selection ntation preparation service GXSJ-ZX-2022-07 / A prospe Project Management, Monito Consultant Qualifi Pending Impleme IBRD / 86700 Post Open - National 106,150.00 0.00 2022-08-01 2022-08-22 2022-10-05 2022-11-04 2022-12-09 2023-06-07 ctive study on Rural Revitaliz ring and Evaluation cation Selection ntation ation INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GXPG-ZX-2021-01 / Pingguo Improvement of Pro-Poor Val Individual Consult BIC purchases legal consulta IBRD / 86700 Post Open 10,000.00 10,079.86 Signed 2021-03-01 2021-01-05 2021-04-19 2021-02-10 2021-05-10 2021-02-05 2021-06-14 2021-02-05 2022-05-11 ue Chains ant Selection ncy service. GXSJ-ZX-09 / Publicity servic Public Infrastructure and Ser e of Guangxi Poverty Alleviati IBRD / 86700 Post Direct Selection Direct 46,153.85 46,888.92 Completed 2021-05-20 2021-07-15 2021-05-30 2021-04-02 2021-08-03 2021-07-29 2022-01-30 2022-05-12 vices on Pilot Project Page 4