PROCUREMENT PLAN (Textual Part) Project information: Mongolia Strengthening Fiscal and Financial Stability Project (P161048) Project Implementation agency: Project Implementation Unit (PIU) under Ministry of Finance (MOF) of Mongolia Date of the Procurement Plan: November 11, 2017 Period covered by this Procurement Plan: January 2018 – December 2019 1. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. 2. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. 3. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. 3.1 National Open Competitive Procurement When the Borrower uses its own national open competitive procurement arrangements as set forth in Chapter Two of the Public Procurement Law of Mongolia enacted on December 1, 2005, as amended several times with the latest amendment on February 9, 2017, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. (a) Participation in Bidding and Preferences (i) Government-owned enterprises in Mongolia shall be eligible to participate in bidding only if they can establish that they are legally and financially autonomous, operate under commercial law, and are not a dependent of the agency contracting them. (ii) A bidder declared ineligible by the World Bank, based on a determination by the World Bank that the bidder has engaged in corrupt, fraudulent, collusive, coercive or obstructive practices in competing for or in executing a World Bank-financed contract, shall be ineligible to participate andbe awarded a World Bank- financed contract during the period determined by the World Bank. (iii) A firm which has been engaged by the Borrower to provide consulting services for the preparation or implementation of a project, and any of its affiliates, shall be disqualified from subsequently providing goods or works resulting from or directly related to the firm’s consulting services for such preparation or implementation. This provision does not apply to the various firms which together are performing the contractor’s obligations under a turnkey or design and build contract. (iv) Interested foreign bidders from eligible countries shall be allowed to participate without being required to associate or form joint ventures with local bidders. Foreign bidders shall be eligible to participate in bidding under the same conditions as local bidders. Mongolian bidders and goods of Mongolian origin shall be given no preference over foreign bidders, either in the bidding process or in the evaluation of bids. (v) Prior registration shall not be a requirement for any bidder to participate in bidding. (b) Request for Bids / Request for Proposals Documents (i) The request for bids/request for proposals documents shall be acceptable to the World Bank (ii) The request for bids / request for proposals documents and the signed contract shall include the clauses related to World Bank’s Policy in regard to corrupt and fraudulent practices. (iii) In the case of contracts of more than eighteen (18) months’ duration, the bidding documents and the resultant contract shall provide for price adjustment, based on a formula acceptable to the World Bank, which shall be disclosed to the bidders in the bidding documents. (v) There shall be no post-bidding negotiations with the lowest evaluated bidder or any other bidder. No bidder shall be required, as a condition for the award of contract, to change his bid price or otherwise materially alter his bid after it has been submitted. (c) Assessment of Bidder’s Qualification Qualification criteria shall be clearly specified in the bidding documents, and only criteria so specified, shall be used to determine whether a bidder is qualified. The evaluation of the bidder’s qualifications shall be conducted separately from the technical and commercial evaluation of the bid. When post qualification is applied, the assessment of bidder’s qualifications shall be carried out only after the preliminary and detailed evaluation of bids has been completed by the Recipient and, in doing so, the qualifications of the bidder who has submitted the lowest evaluated substantially responsive bid or most advantageous bid shall be assessed first. The evaluation of a bidder’s qualifications shall only take into account the bidder’s capacity and resources to perform the contract, specifically its experience and past performance on similar contracts, capabilities with respect to personnel, equipment and construction or manufacturing facilities and financial capacity. In carrying out the post-qualification assessment, the Recipient shall exercise reasonable judgment in requesting, in writing, from a bidder only missing factual or historical supporting information related to the bidder’s qualifications and shall provide a reasonable time period (that is, a minimum of seven days) to the bidder to provide his response. No bidders shall be disqualified on the ground that the bidder has tax debt. 3.2 Other National Procurement Arrangements When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. The request for bids / request for proposals / request for quotations documents should be acceptable to the Bank and jointly with the signed contract shall include the clauses related to World Bank’s Policy in regard to corrupt and fraudulent practices. The request for bids / request for proposals / request for quotations documents and the signed contract shall also include the clauses allowing the World Bank to inspect the site and/or all accounts and records relating to the performance of the contract and the submission of the bid or proposal, and to have such accounts and records audited. The standard text is attached hereafter. 4. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not applicable. 5. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not applicable. 6. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works): Not applicable. 7. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations: Not applicable. 8. Other Relevant Procurement Information: Not applicable.Standard Text for Fraud & Corruption and Inspection & Audit Fraud and The Bank requires compliance with the Bank’s Anti- Corruption Corruption Guidelines and its prevailing sanctions policies and procedures as set forth in the WBG’s Sanctions Framework, as set forth in Appendix to the GC. The Employer / Purchaser / Client requires the Contractor / Supplier / the Consultant to disclose any commissions or fees that may have been paid or are to be paid to agents or any other party with respect to the bidding /selection process or execution of the Contract. The information disclosed must include at least the name and address of the agent or other party, the amount and currency, and the purpose of the commission, gratuity or fee. Failure to disclose such commissions, gratuities or fees may result in termination of the Contract and/or sanctions by the Bank. Inspections The Contractor / Supplier / Consultant shall keep, and and Audit shall make all reasonable efforts to cause its by the Subcontractors and Sub-consultants to keep, accurate Bank and systematic accounts and records in respect of the Works / Goods / Services in such form and details as will clearly identify relevant time changes and costs. Pursuant to paragraph 2.2 e. of Appendix to the General Conditions the Contractor / Supplier / Consultant shall permit and shall cause its subcontractors and sub-consultants to permit, the Bank and/or persons appointed by the Bank to inspect the Site and/or the accounts and records relating to the performance of the Contract and the submission of the bid / proposal, and to have such accounts and records audited by auditors appointed by the Bank if requested by the Bank. The Contractor’s / Supplier’s / Consultant’s and its Subcontractors’ and sub- consultants’ acts intended to materially impede the exercise of the Bank’s inspection and audit rights constitute a prohibited practice subject to contract termination (as well as to a determination of ineligibility pursuant to the Bank’s prevailing sanctions procedures). APPENDIX TO GENERAL CONDITIONS Fraud and Corruption (Text in this Appendix shall not be modified) 1. Purpose 1.1 The Bank’s Anti-Corruption Guidelines and this annex apply with respect to procurement under Bank Investment Project Financing operations. 2. Requirements 2.1 The Bank requires that Borrowers (including beneficiaries of Bank financing); bidders, consultants, contractors and suppliers; any sub- contractors, sub-consultants, service providers or suppliers; any agents (whether declared or not); and any of their personnel, observe the highest standard of ethics during the procurement process, selection and contract execution of Bank-financed contracts, and refrain from Fraud and Corruption. 2.2 To this end, the Bank: a. Defines, for the purposes of this provision, the terms set forth below as follows: i. “corrupt practice” is the offering, giving, receiving, or soliciting, directly or indirectly, of anything of value to influence improperly the actions of another party; ii. “fraudulent practice” is any act or omission, including misrepresentation, that knowingly or recklessly misleads, or attempts to mislead, a party to obtain financial or other benefit or to avoid an obligation; iii. “collusive practice” is an arrangement between two or more parties designed to achieve an improper purpose, including to influence improperly the actions of another party; iv. “coercive practice” is impairing or harming, or threatening to impair or harm, directly or indirectly, any party or the property of the party to influence improperly the actions of a party; v. “obstructive practice” is: (a) deliberately destroying, falsifying, altering, or concealing of evidence material to the investigation or making false statements to investigators in order to materially impede a Bank investigation into allegations of a corrupt, fraudulent, coercive, or collusive practice; and/or threatening, harassing, or intimidating any party to prevent it from disclosing its knowledge of matters relevant to the investigation or from pursuing the investigation; or (b) acts intended to materially impede the exercise of the Bank’s inspection and audit rights provided for under paragraph 2.2 e. below. b. Rejects a proposal for award if the Bank determines that the firm or individual recommended for award, any of its personnel, or its agents, or its sub-consultants, sub-contractors, service providers, suppliers and/ or their employees, has, directly or indirectly, engaged in corrupt, fraudulent, collusive, coercive, or obstructive practices in competing for the contract in question; c. In addition to the legal remedies set out in the relevant Legal Agreement, may take other appropriate actions, including declaring mis-procurement, if the Bank determines at any time that representatives of the Borrower or of a recipient of any part of the proceeds of the loan engaged in corrupt, fraudulent, collusive, coercive, or obstructive practices during the procurement process, selection and/or execution of the contract in question, without the Borrower having taken timely and appropriate action satisfactory to the Bank to address such practices when they occur, including by failing to inform the Bank in a timely manner at the time they knew of the practices; d. Pursuant to the Bank’s Anti- Corruption Guidelines and in accordance with the Bank’s prevailing sanctions policies and procedures, may sanction a firm or individual, either indefinitely or for a stated period of time, including by publicly declaring such firm or individual ineligible (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;1 (ii) to be a nominated2 sub-contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank-financed project; 1 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 2 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. e. Requires that a clause be included in bidding/request for proposals documents and in contracts financed by a Bank loan, requiring (i) bidders, consultants, contractors, and suppliers, and their sub- contractors, sub-consultants, service providers, suppliers, agents personnel, permit the Bank to inspect3 all accounts, records and other documents relating to the submission of bids and contract performance, and to have them audited by auditors appointed by the Bank. 3 Inspections in this context usually are investigative (i.e., forensic) in nature. They involve fact- finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to: accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third party verification of information. PROCUREMENT Mongolia : Strengthening Fiscal and Financial Stability Project PLAN General Information Country: Mongolia 2018-03-1 Bank’s Approval Date of the Original Procurement Plan: 2022-06-2 3 if none) Revised Plan Date(s): (comma delineated, leave blank Project ID: P161048 GPN Date: 2017-10-1 0 Project Name: Strengthening Fiscal and Financial Stability Project 8 Loan / Credit No: IDA / 60850, IDA / 60840 Ministry of Finance Executing Agency(ies): WORKS Activity Reference No Procuremen Estimate Actual Draft Bidding Doc Specific Procureme Proposal Submissio Bid Evaluation Rep Loan / Credit Market Appro Procurement Prequalificati High SEA/S Process Draft Pre-qualificati Prequalification Ev Bidding Documents Contract Comp . / Description Component Review Type Method t Document d Amou Amount ument / Justificatio nt Notice / Invitatio n / Opening / Minut ort and Recommen Signed Contract No. ach Process on (Y/N) H Risk Status on Documents aluation Report as Issued letion Type nt (US$) (US$) n n es dation for Award Planne Actual Planne Actual Planne Actual Planne Actual Planne Actual Planne Actual Planne Actual Planne Actual Planne d d d d d d d d d GOODS Activity Reference No Estimated A Draft Bidding Doc Specific Procureme Proposal Submissio Bid Evaluation Rep Loan / Credit Market Appro Procurement Prequalificati Actual Amou Process Draft Pre-qualificati Prequalification Ev Bidding Documents Contract Completio . / Description Component Review Type Method mount (US$ ument / Justificatio nt Notice / Invitatio n / Opening / Minut ort and Recommen Signed Contract No. ach Process on (Y/N) nt (US$) Status on Documents aluation Report as Issued n ) n n es dation for Award Planne Actual Planne Actual Planne Actual Planne Actual Planne Actual Planne Actual Planne Actual Planne Actual Planne Actual d d d d d d d d d A1/GO/001 / Purchase offic Component A: Strengtheni Request for Quo Single Stage - On 2018-05- 2018-07- 2018-05- 2018-08- 2018-06- e IT goods (five laptops for IDA / 60850 ng Macroeconomic and Fis Post Open - National 7,000.00 6,131.70 Completed tations e Envelope 26 21 31 20 26 office use) cal Management A31/GO/001 / Purchase on e computer with desktop fo r Bloomberg terminal which Component A: Strengtheni Request for Quo Single Stage - On 2018-06- 2018-07- 2018-06- 2018-08- 2018-07- is recommended requireme IDA / 60850 ng Macroeconomic and Fis Post Open - National 10,000.00 7,241.72 Completed tations e Envelope 05 31 06 30 09 nts for user of Bloomberg s cal Management ervice two for the DMFAS a dmins and IT consultant, th ree laptops for newly hired consultants B4/GO/001 / Purchase of of Component B: Improving t Request for Quo Single Stage - On 2018-06- 2018-07- 2018-05- 2019-01- fice IT equipments includin IDA / 60850 he efficiency of Public Fina Post Open - National 6,500.00 5,755.34 Signed tations e Envelope 05 31 31 27 g PC, laptop, projector ncial Management C11/GO/001 / Publications of strategic documents, gui Component C: Enhancing Request for Quo Single Stage - On 2019-01- 2019-03- 2019-04- IDA / 60850 Post Open - National 7,000.00 0.00 Canceled delines, manuals, pamphlet Financial Sector Stability tations e Envelope 05 02 01 s or brochures produced un der Comp C1-C3 C5/GO/001 / Purchase of of fice IT goods Component C: Enhancing Request for Quo Single Stage - On 2018-09- 2018-10- 2018-11- 1. Storage IDA / 60850 Post Open - National 10,000.00 0.00 Canceled Financial Sector Stability tations e Envelope 05 31 30 2. Server 3. Optical switch. D1/GO/001 / Purchase of G oods (printing of training a Component D: Strengtheni nd public advocacy materia Request for Quo Single Stage - On 2018-07- 2018-08- 2018-12- 2019-02- 2018-12- IDA / 60850 ng of the Social Protection Post Open - National 27,200.00 1,128.62 Completed ls, guidance, handouts, co tations e Envelope 05 30 17 26 24 System mputers and printers etc.) related to Strengthening So cial Welfare Programs desi gn and operations D2/GO/001 / Purchase of G oods (printing of training a nd public advocacy materia Component D: Strengtheni ls, guidance, handouts, and Request for Quo Single Stage - On 2018-06- 2018-08- 2019-02- 2019-02- 2019-03- IDA / 60850 ng of the Social Protection Post Open - National 12,000.00 7,584.20 Completed computers,printers for cap tations e Envelope 28 23 15 19 15 System acity building etc.) related t o activity Strengthening so cial insurance design, gove rnance and financial mana gement A32/GO/001 / Purchase of office IT goods and service Component A: Strengtheni Request for Quo Single Stage - On 2018-07- 2018-08- 2018-11- 2019-02- 2018-12- s (Hardware): IDA / 60850 ng Macroeconomic and Fis Post Open - National 18,000.00 15,945.03 Completed tations e Envelope 04 29 05 25 20 Server: 1 pc cal Management Desktops: 5 pcs Networking and other equi pment E/GO/001 / Purchasing Acc Under Impl Component E: Project Man Request for Quo Single Stage - On 2018-03- 2018-05- 2018-08- ounting software, including IDA / 60850 Post Open - National 5,000.00 0.00 ementatio agement and Monitoring tations e Envelope 24 19 17 maintenance fee n E/GO/003 / Purchase of IT Component E: Project Man Request for Quo Single Stage - On 2018-09- 2018-10- 2018-11- IDA / 60850 Post Open - National 3,500.00 0.00 Canceled goods for the purpose of in agement and Monitoring tations e Envelope 01 27 26 ternal usage E/GO/004 / Office furniture Component E: Project Man Request for Quo Single Stage - On 2018-12- 2019-02- 2018-10- 2019-03- 2018-11- IDA / 60850 Post Open - National 3,500.00 1,319.35 Completed for internal usage agement and Monitoring tations e Envelope 15 09 17 11 05 E/GO/002 / Purchase of IT Component E: Project Man Request for Quo Single Stage - On 2018-12- 2019-01- 2018-11- 2019-02- 2018-12- IDA / 60850 Post Open - National 7,000.00 3,524.17 Completed goods for internal usage agement and Monitoring tations e Envelope 01 26 23 25 04 A2/GO/001 / Purchase of IT Goods (business desktops Component A: Strengtheni Request for Quo Single Stage - On 2018-10- 2018-11- 2018-10- 2019-05- 2018-10- with high speed suitable fo IDA / 60850 ng Macroeconomic and Fis Post Open - National 18,000.00 7,876.57 Completed tations e Envelope 03 28 01 27 14 r large amount of data anal cal Management ysis and professional tablet s "2 in 1") Component A: Strengtheni A31/GO/003 / IT goods for Request for Quo Single Stage - On 2019-03- 2019-04- 2019-08- 2019-10- 2019-08- IDA / 60850 ng Macroeconomic and Fis Post Open - National 15,000.00 13,875.71 Completed office use tations e Envelope 02 27 02 24 16 cal Management Component B: Improving t B11/GO/001 / Purchase of I Request for Quo Single Stage - On 2019-04- 2019-06- 2019-08- 2019-11- 2019-09- IDA / 60850 he efficiency of Public Fina Post Open - National 15,000.00 27,828.26 Completed T goods for office use tations e Envelope 06 01 14 28 13 ncial Management Component B: Improving t B12/GO/001 / Purchase of I Request for Quo Single Stage - On 2019-04- 2019-06- 2019-08- 2019-11- 2019-09- IDA / 60850 he efficiency of Public Fina Post Open - National 15,000.00 789.99 Completed T goods for office use tations e Envelope 06 01 14 28 13 ncial Management B13/GO/001 / Publishing: Quality assurance and Inter Component B: Improving t nal audit manuals, Internati Request for Quo Single Stage - On 2019-08- 2019-10- 2020-02- 2020-04- 2020-04- IDA / 60850 he efficiency of Public Fina Post Open - National 45,000.00 21,437.51 Completed onal standards for the prof tations e Envelope 30 25 03 22 20 ncial Management essional practice of Internal auditing (IPPF Standards) a nd other related policy doc uments Component B: Improving t B13/GO/002 / Purchase of I Request for Quo Single Stage - On 2019-04- 2019-06- 2019-09- 2019-12- 2019-10- IDA / 60850 he efficiency of Public Fina Post Open - National 20,000.00 12,069.05 Completed T goods tations e Envelope 13 08 06 05 04 ncial Management B31/GO/001 / Purchase of goods (Hardware): Video wall display /PD55N6 /:4 Component B: Improving t Request for Quo Single Stage - On 2019-03- 2019-05- 2019-05- 2019-10- 2019-05- Rack mount server /Dell Po IDA / 60850 he efficiency of Public Fina Post Open - National 40,000.00 28,735.59 Completed tations e Envelope 06 01 01 28 31 wer edge R730/:2 ncial Management Desktop /Dell Optiplex 706 0/:5 Tablet PC/Microsoft Surface Pro/:2 Firewall /Kerio control hard B32/GO/001 ware / Purchasing e appliance/:1 Component B: Improving t Request for Quo Single Stage - On 2019-03- 2019-05- 2019-12- 2019-10- 2020-02- quipments necessary for ca IDA / 60850 he efficiency of Public Fina Post Open - National 10,000.00 9,817.26 Completed tations e Envelope 06 01 19 28 11 pacity building of the PAMD ncial Management B4/GO/003 / Goods (publis Component B: Improving t Request for Quo Single Stage - On 2019-04- 2019-06- 2019-04- 2019-11- 2019-06- hing, computers, and other IDA / 60850 he efficiency of Public Fina Post Open - National 30,000.00 9,190.47 Completed tations e Envelope 06 01 24 28 13 equipments) ncial Management C11/GO/002 / Purchasing p Component C: Enhancing Request for Quo Single Stage - On 2019-04- 2019-05- 2019-07- 2019-11- 2019-08- IDA / 60850 Post Open - National 10,000.00 6,741.37 Completed ersonal desktop computers Financial Sector Stability tations e Envelope 05 31 19 27 16 and laptops. C5/GO/002 / Purchase of s Component C: Enhancing 2019-03- 2019-03- 2019-03- 2019-03- 2019-04- 2019-03- 2019-10- 2019-03- IDA / 60850 Post Direct Selection Direct 19,500.00 17,740.00 Completed oftware such as MATLAB Financial Sector Stability 01 07 06 07 10 25 07 25 D1/GO/002 / Printing of tra Component D: Strengtheni ining and public advocacy Request for Quo Single Stage - On 2019-03- 2019-05- 2019-11- IDA / 60850 ng of the Social Protection Post Open - National 1,100.00 0.00 Canceled materials, guidance, hando tations e Envelope 17 12 08 System uts, etc., related to Social Welfare law amendments D1/GO/003 / Printing of pu Component D: Strengtheni Request for Quo Single Stage - On 2019-03- 2019-05- 2019-11- 2019-11- 2019-12- blic advocacy materials, gu IDA / 60850 ng of the Social Protection Post Open - National 1,100.00 977.31 Completed tations e Envelope 17 12 19 08 05 idance, handouts, and book System D2/GO/004 / IT goods: gad get supplies computers, pri Component D: Strengtheni nters for capacity building Request for Quo Single Stage - On 2019-03- 2019-05- 2020-02- 2019-11- 2020-09- IDA / 60850 ng of the Social Protection Post Open - National 10,000.00 9,105.56 Completed etc.) related to activity D2. tations e Envelope 17 12 03 08 15 System Strengthening social insura nce design, governance, an d financial management E/GO/005 / Purchase of PC, Component E: Project Man Request for Quo Single Stage - On 2019-06- 2019-08- 2020-01- IDA / 60850 Post Open - National 9,000.00 0.00 Canceled office table and chairs agement and Monitoring tations e Envelope 06 01 28 B31/GO/002 / Purchase of goods (Software): Network monitor software / Component B: Improving t SolarWinds Network Perfor Request for Quo Single Stage - On 2019-03- 2019-05- 2019-11- 2019-10- 2019-11- IDA / 60850 he efficiency of Public Fina Post Open - National 18,000.00 16,678.92 Completed mance Monitor (NPM)/: SL5 tations e Envelope 06 01 04 28 15 ncial Management 00 (up to 500 elements) Lic ense with 1st-year Mainten ance System monitor software /S olarWinds Server & Applica A1/GO/003 tion / Purchase of g Monitor.. oods Component A: Strengtheni 2019-02- 2019-11- 2019-03- 2019-04- 2019-10- (Software): IDA / 60850 ng Macroeconomic and Fis Post Direct Selection Direct 3,000.00 0.00 Canceled 25 18 02 06 03 -Software application for vi cal Management sualizing, communicating a nd simplifying economic po licies A1/GO/004 / Purchase of g oods and services (Hardwa Component A: Strengtheni re): Request for Quo Single Stage - On 2019-03- 2019-05- 2020-01- 2019-10- 2020-04- IDA / 60850 ng Macroeconomic and Fis Post Open - National 15,000.00 10,719.35 Completed - Multifunction and color pri tations e Envelope 06 01 23 28 03 cal Management nter, B22/GO/001 - / Personal and Component B: Improving t laptop computers for imple Request for Quo Single Stage - On 2019-03- 2019-05- 2019-05- 2019-10- 2019-05- IDA / 60850 he efficiency of Public Fina Post Open - National 15,000.00 14,532.66 Completed menting commitment contr tations e Envelope 09 04 02 31 16 ncial Management ol system through GFMIS F Bv7 D1/GO/006 / Purchase of IT Goods (computers and prin Component D: Strengtheni Request for Quo Single Stage - On 2018-12- 2019-01- 2019-02- 2019-07- 2019-03- ters etc.for one stop servic IDA / 60850 ng of the Social Protection Post Open - National 21,600.00 18,499.12 Completed tations e Envelope 05 30 15 29 15 e center) related to Strengt System hening Social Welfare Progr ams design and operations C5/GO/01 / Purchase of ser Component C: Enhancing Request for Quo Single Stage - On 2019-06- 2019-07- 2019-09- 2020-01- 2019-10- IDA / 60850 Post Open - National 12,000.00 7,534.42 Completed ver Financial Sector Stability tations e Envelope 03 29 18 25 16 B22/GO/003 / Server and h Component B: Improving t Request for Bid Single Stage - On 2019-11- 2020-01- 2019-12- 2020-01- 2020-02- 2020-02- 2020-03- 2020-03- 2020-03- 2020-09- 2020-06- ardware equipment for IPS IDA / 60850 he efficiency of Public Fina Prior Open - National 310,000.00 237,273.69 Completed s e Envelope 28 28 03 14 17 13 10 19 18 15 01 implementation-LOT1 ncial Management B21/GO/003 / Publishing n Component B: Improving t Request for Quo Single Stage - On 2020-04- 2020-06- 2020-10- 2020-11- 2020-12- ewly translated IPSAS /2 vo IDA / 60850 he efficiency of Public Fina Post Open - National 22,000.00 7,339.41 Completed tations e Envelope 06 01 01 28 23 lumes each 1000 pieces/ ncial Management D2/GO/005 / IT goods: gad get supplies computers, pri nters for capacity building Component D: Strengtheni Request for Quo Single Stage - On 2020-01- 2020-03- 2020-03- 2020-08- 2020-06- etc.) related to activity D2. IDA / 60850 ng of the Social Protection Post Open - National 10,000.00 8,158.21 Completed tations e Envelope 06 02 24 29 10 Strengthening social insura System nce design, governance, an d financial management / Z avkhan province One stop shop SI center D1/GO/004 / IT goods: gad Component D: Strengtheni get supplies computers, an Request for Quo Single Stage - On 2020-01- 2020-03- 2020-03- 2020-08- 2020-06- IDA / 60850 ng of the Social Protection Post Open - National 12,500.00 8,057.66 Completed d printers etc.related to Za tations e Envelope 06 02 24 29 10 System vkhan province One stop s hop SI center D1/GO/005 / Other goods: Component D: Strengtheni Request for Quo Single Stage - On 2020-01- 2020-03- 2020-08- related to D1. Zavkhan pro IDA / 60850 ng of the Social Protection Post Open - National 12,500.00 0.00 Canceled tations e Envelope 06 02 29 vince One stop shop SI cen System ter D2/GO/003 / Purchase of G oods (printing of training a nd public advocacy materia Component D: Strengtheni ls, guidance, handouts, and Request for Quo Single Stage - On 2020-01- 2020-03- 2020-02- 2020-08- 2020-06- IDA / 60850 ng of the Social Protection Post Open - National 10,000.00 15,448.37 Completed computers,printers for cap tations e Envelope 06 02 03 29 29 System acity building etc.) related t o activity Strengthening so cial insurance design, gove rnance and financial mana gement/Zavkhan province D2/GO/002 / Printing of tra Component D: Strengtheni ining and public advocacy Request for Quo Single Stage - On 2020-01- 2020-03- 2020-08- IDA / 60850 ng of the Social Protection Post Open - National 1,500.00 0.00 Canceled materials, guidance, hando tations e Envelope 06 02 29 System uts, etc etc.) related to law amendment C4/GO/002 / Publication m Component C: Enhancing Request for Quo Single Stage - On 2019-12- 2020-02- 2020-03- 2020-08- 2020-06- anuals/guides, computers a IDA / 60850 Post Open - National 10,000.00 10,244.64 Completed Financial Sector Stability tations e Envelope 20 14 25 12 18 nd printers for consultants related to activity C4 A1/GO/03 / Purchase of go ods and services (Accessio Component A: Strengtheni n to economic intelligence 2019-11- 2019-11- 2019-11- 2020-05- 2019-12- 2020-08- 2020-06- 2021-06- IDA / 60850 ng Macroeconomic and Fis Post Direct Selection Direct 3,438.00 3,000.00 Completed database): 15 20 20 21 25 17 22 22 cal Management This includes The Economis t Intelligence Unit, Capital Economics and Statista Component B: Improving t B13/GO/003 / Purchase of 2019-08- 2019-08- 2019-08- 2019-08- 2019-09- 2019-08- 2020-03- 2019-08- IDA / 60850 he efficiency of Public Fina Post Direct Selection Direct 1,000.00 1,024.94 Completed books for office use 01 15 06 28 10 28 08 28 ncial Management B31/GO/003 / Purchase of I Component B: Improving t 2019-07- 2019-07- 2019-08- 2019-07- 2019-09- 2019-07- 2020-03- 2019-07- T goods for office use (lapt IDA / 60850 he efficiency of Public Fina Post Direct Selection Direct 3,600.00 3,490.94 Completed 29 26 03 26 07 30 05 30 op computer) ncial Management Component B: Improving t B4/GO/006 / Goods (office 2019-11- 2019-12- 2019-11- 2019-12- 2019-12- 2019-12- 2020-06- 2019-12- IDA / 60850 he efficiency of Public Fina Post Direct Selection Direct 2,600.00 2,019.98 Completed cabinets) 01 12 06 16 11 16 08 20 ncial Management Component B: Improving t B4/GO/004 / Purchase of IT 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-05- 2019-12- 2019-06- IDA / 60850 he efficiency of Public Fina Post Direct Selection Direct 2,000.00 1,804.74 Completed Goods - accessories 20 14 25 10 29 16 26 13 ncial Management Component B: Improving t B4/GO/005 / Purchase of IT Request for Quo Single Stage - On 2019-05- 2019-07- 2019-04- 2020-01- 2019-05- IDA / 60850 he efficiency of Public Fina Post Open - National 1,500.00 1,317.62 Completed Goods - USB tations e Envelope 25 20 25 16 07 ncial Management D2/GO/04 / IT good for offi Component D: Strengtheni 2019-07- 2019-08- 2019-08- 2019-08- 2019-09- 2019-08- 2020-03- 2019-08- IDA / 60850 Post Direct Selection Direct 1,500.00 1,371.89 Completed ce use (laptop and voice re ng of the Social Protection 29 01 03 01 07 01 05 02 corder) System B22/GO/004 / Server and h Component B: Improving t Request for Quo Single Stage - On 2019-11- 2020-01- 2020-04- 2020-07- 2020-05- ardware equipment for IPS IDA / 60850 he efficiency of Public Fina Post Open - National 60,000.00 74,986.87 Completed tations e Envelope 09 04 24 02 07 implementation-LOT2 (Soft ncial Management ware licences) B22/GO/005 / Server and h Component B: Improving t Request for Quo Single Stage - On 2019-11- 2020-01- 2020-01- 2020-07- 2020-01- ardware equipment for IPS IDA / 60850 he efficiency of Public Fina Post Open - National 16,000.00 9,925.12 Completed tations e Envelope 09 04 03 02 31 implementation-LOT4 (IT G ncial Management OODS) B22/GO/006 / Server and h Component B: Improving t Request for Quo Single Stage - On 2019-11- 2020-01- 2020-01- 2020-07- 2020-02- ardware equipment for IPS IDA / 60850 he efficiency of Public Fina Post Open - National 12,000.00 10,703.83 Completed tations e Envelope 09 04 03 02 19 implementation-LOT3 (Mee ncial Management ting room) A32/GO/004 / Purchase of I Component A: Strengtheni Request for Quo Single Stage - On 2019-10- 2019-12- 2020-10- 2020-05- 2021-02- T goods for office use and s IDA / 60850 ng Macroeconomic and Fis Post Open - National 20,000.00 19,604.25 Completed tations e Envelope 06 01 07 29 08 erver for newly developed cal Management software systems. A1/GO/007 / Purchase of IT Component A: Strengtheni Request for Quo Single Stage - On 2020-05- 2020-07- 2020-12- Goods (Smartboard 1pc, La IDA / 60850 ng Macroeconomic and Fis Post Open - National 10,200.00 0.00 Canceled tations e Envelope 06 01 28 ptop 4pcs, adjustable desk cal Management 1pc) A2/GO/003 / IT Goods for o Component A: Strengtheni Request for Quo Single Stage - On 2018-10- 2018-12- 2018-10- 2019-05- ffice use for LOT2 (desktop IDA / 60850 ng Macroeconomic and Fis Post Open 8,900.00 7,720.77 Signed tations e Envelope 06 01 15 30 PCs & Displays) cal Management Component A: Strengtheni A2/GO/004 / IT Goods for o Request for Quo Single Stage - On 2018-10- 2018-12- 2018-10- 2019-05- IDA / 60850 ng Macroeconomic and Fis Post Open - National 120.00 101.83 Signed ffice use for LOT3 tations e Envelope 06 01 15 30 cal Management B13/GO/005 / Purchase of goods: Component B: Improving t - The IIA's CIA Learning sys 2020-04- 2020-05- 2020-04- 2020-05- 2020-05- 2020-06- 2020-11- 2020-07- IDA / 60850 he efficiency of Public Fina Post Direct Selection Direct 5,000.00 2,451.60 Completed tem version 6.0 (Part 1-3 O 01 20 06 21 11 16 07 03 ncial Management nline + Print) - GLEIM premium CIA revie w system B22/GO/010 / IT goods for Component B: Improving t Request for Quo Single Stage - On 2020-05- 2020-07- 2020-09- 2020-12- 2020-10- office use (Personal compu IDA / 60850 he efficiency of Public Fina Post Open - National 17,000.00 17,939.61 Completed tations e Envelope 06 01 09 28 29 ters) ncial Management C4/GO/003 / Goods: Purch ase of necessary computer Component C: Enhancing Request for Quo Single Stage - On 2020-05- 2020-07- 2020-09- 2020-12- 2021-01- s and office equipment for t IDA / 60850 Post Open - National 30,000.00 14,549.31 Completed Financial Sector Stability tations e Envelope 06 01 24 28 29 he FRC office extension an d establishment of new divi sion and units. C4/GO/004 / Goods: Public Component C: Enhancing Request for Quo Single Stage - On 2020-06- 2020-08- 2021-01- 2021-01- 2021-04- IDA / 60850 Post Open - National 10,000.00 8,029.71 Completed ation of manual/guideline Financial Sector Stability tations e Envelope 06 01 28 28 08 C5/GO/003 / Procurement of hardware (optical switch Component C: Enhancing Request for Quo Single Stage - On 2020-05- 2020-07- 2020-06- 2020-12- 2020-08- IDA / 60850 Post Open - National 39,600.00 43,193.94 Completed and storage) to improve th Financial Sector Stability tations e Envelope 06 01 04 28 11 e Public credit registry's te chnical capacity. D1/GO/011 / Goods (printi ng of training and public ad Component D: Strengtheni vocacy materials, guidance Request for Quo Single Stage - On 2020-07- 2020-09- 2020-07- 2021-03- 2021-01- IDA / 60850 ng of the Social Protection Post Open - National 8,000.00 5,183.88 Completed , handouts, computers, an tations e Envelope 20 14 27 13 26 System d printers etc.) related to D 1. Strengthening Social Wel fare Programs design and o perations D2/GO/008 / Goods (printi ng of training and public ad Component D: Strengtheni Request for Quo Single Stage - On 2020-05- 2020-07- 2020-07- 2021-01- 2021-01- vocacy materials, guidance IDA / 60850 ng of the Social Protection Post Open - National 20,000.00 9,611.35 Completed tations e Envelope 15 10 27 06 26 , handouts, and computers, System printers for capacity buildin g etc.) D2/GO/006 / To publish ha Component D: Strengtheni ndouts and brochures to im Request for Quo Single Stage - On 2020-05- 2020-07- 2020-12- IDA / 60850 ng of the Social Protection Post Open - National 2,000.00 0.00 Canceled prove public awareness of tations e Envelope 06 01 28 System social insurance reform an d service. Page 1 D2/GO/007 / To publish a b rochures in braille on social Component D: Strengtheni Request for Quo Single Stage - On 2020-08- 2020-10- 2021-02- 2021-04- 2021-03- welfare service allowances IDA / 60850 ng of the Social Protection Post Open - National 4,000.00 3,922.91 Completed tations e Envelope 20 15 10 13 31 for the visually impaired pe System ople, and in kazakh langua ge for Kazakh people. E/GO/006 / Purchase of IT Component E: Project Man Request for Quo Single Stage - On 2020-03- 2020-05- 2020-04- 2020-10- 2020-04- IDA / 60850 Post Open - National 23,140.00 18,565.57 Completed goods. agement and Monitoring tations e Envelope 06 01 01 28 24 E/GO/007 / Purchase of fur Component E: Project Man Request for Quo Single Stage - On 2020-03- 2020-05- 2020-04- 2020-10- 2020-04- IDA / 60850 Post Open - National 4,400.00 2,337.18 Completed niture for office use. agement and Monitoring tations e Envelope 06 01 14 28 24 B31/GO/005 / Purchase of Component B: Improving t Request for Quo Single Stage - On 2020-07- 2020-08- 2020-11- 2021-02- 2020-12- software (Windows Server, IDA / 60850 he efficiency of Public Fina Post Open - National 44,000.00 38,209.35 Completed tations e Envelope 06 31 03 27 31 Solarwinds, Vitual host and ncial Management search engine) B31/GO/006 / Purchase of Component B: Improving t Request for Quo Single Stage - On 2020-04- 2020-06- 2020-04- 2020-11- 2020-05- 2pcs of laptop for mobile d IDA / 60850 he efficiency of Public Fina Post Open - National 7,000.00 6,599.93 Completed tations e Envelope 06 01 10 28 13 evelopment ncial Management Component B: Improving t B32/GO/002 / Purchase ha Request for Quo Single Stage - On 2020-05- 2020-07- 2020-05- 2020-12- 2020-07- IDA / 60850 he efficiency of Public Fina Post Open - National 20,500.00 20,332.54 Completed rdware for eArchive tations e Envelope 06 01 26 28 07 ncial Management B4/GO/007 / Goods (public Component B: Improving t Request for Quo Single Stage - On 2020-05- 2020-07- 2019-05- 2020-12- 2019-07- ation, computers, and othe IDA / 60850 he efficiency of Public Fina Post Open - National 10,000.00 1,277.83 Completed tations e Envelope 06 01 27 28 26 r equipment) ncial Management B13/GO/006 / Editing and printing brochure for FCRM Component B: Improving t 2020-05- 2020-08- 2020-05- 2020-08- 2020-06- 2020-08- 2020-12- 2020-12- D - 5000MNT*600pcs, Inter IDA / 60850 he efficiency of Public Fina Post Direct Selection Direct 3,237.41 3,092.29 Completed 01 04 06 17 10 17 07 01 national news & update - 5 ncial Management 000MNT*600pcs, laws and regulations - 5000MNT*600 pcs. B21/GO/001 / Payment of membership fee for interna Component B: Improving t 2019-04- 2019-04- 2019-05- 2019-11- tional research institutional IDA / 60850 he efficiency of Public Fina Post Direct Selection Direct 1,000.00 0.00 Canceled 01 06 11 07 database access regarding ncial Management public finance, and account ing B21/GO/002 / Publishing E Component B: Improving t nglish-Mongolia and Mongo Request for Quo Single Stage - On 2019-12- 2020-01- 2020-07- IDA / 60850 he efficiency of Public Fina Post Open - National 5,000.00 0.00 Canceled lian-English accounting glo tations e Envelope 06 31 29 ncial Management ssary /1 volume, 500 piece s/ D1/GO/012 / IT goods for o Component D: Strengtheni Request for Quo Single Stage - On 2020-08- 2020-09- 2020-09- 2021-03- 2020-12- IDA / 60850 Post Open - National 2,729.00 2,383.78 Completed ffice (Laptop computer) ng of the Social Protection tations e Envelope 05 30 03 29 17 System B21/GO/004 / Permission f Component B: Improving t 2020-08- 2020-08- 2020-08- 2020-09- 2020-09- 2020-09- 2021-03- 2021-06- ee to translate, reproduce, IDA / 60850 he efficiency of Public Fina Post Direct Selection Direct 1,250.00 1,250.00 Completed 12 04 17 30 21 29 20 09 publish, and distribute IPSA ncial Management S 2018 from IFAC A1/GO/002 / Purchase of p ublishing and cost-estimati Component A: Strengtheni 2018-12- 2019-11- 2018-12- 2019-01- 2019-07- on software for visualizing, IDA / 60850 ng Macroeconomic and Fis Post Direct Selection Direct 2,000.00 0.00 Canceled 10 18 15 19 18 communicating, simplifying cal Management and costing economic polici es Component B: Improving t B22/GO/012 / JIRA service 2020-05- 2020-05- 2020-06- 2020-12- IDA / 60850 he efficiency of Public Fina Post Direct Selection Direct 20,400.00 0.00 Canceled desk software lincense 01 06 10 07 ncial Management A1/GO/005 / Publication of Component A: Strengtheni Request for Quo Single Stage - On 2020-06- 2020-08- 2021-01- media contents for Econom IDA / 60850 ng Macroeconomic and Fis Post Open - National 10,000.00 0.00 Canceled tations e Envelope 06 01 28 ic and Social Development cal Management Guidelines for 2021 A2/GO/002 / IT Goods to su Component A: Strengtheni Request for Quo Single Stage - On 2020-11- 2021-01- 2021-02- 2021-07- 2021-05- pport tax and customs refo IDA / 60850 ng Macroeconomic and Fis Post Open - National 9,000.00 8,953.92 Completed tations e Envelope 14 09 24 08 10 rm activities cal Management A31/GO/002 / Purchase of I Component A: Strengtheni Request for Quo Single Stage - On 2020-11- 2021-01- 2021-02- 2021-07- 2021-07- T goods and accessories fo IDA / 60850 ng Macroeconomic and Fis Post Open - National 16,000.00 9,984.93 Completed tations e Envelope 13 08 09 07 23 r DMD cal Management B22/GO/007 / Printing guid Component B: Improving t Request for Quo Single Stage - On 2020-05- 2020-07- 2020-12- elines and regulations for b IDA / 60850 he efficiency of Public Fina Post Open - National 18,500.00 0.00 Canceled tations e Envelope 06 01 28 udget accountants and trea ncial Management sury officials Component B: Improving t B22/GO/008 / Printing IPS Request for Quo Single Stage - On 2020-09- 2020-11- 2021-04- IDA / 60850 he efficiency of Public Fina Post Open - National 15,000.00 0.00 Canceled user manual (5000 pc) tations e Envelope 06 01 30 ncial Management B22/GO/011 / Printing trea Component B: Improving t Request for Quo Single Stage - On 2020-06- 2020-08- 2021-01- sury accounitng policy instr IDA / 60850 he efficiency of Public Fina Post Open - National 3,800.00 0.00 Canceled tations e Envelope 06 01 28 uction for treasury officials ncial Management C4/GO/001 / Publication: p rint out manuals and guidel ines for inspection officers. Component C: Enhancing Request for Quo Single Stage - On 2018-08- 2018-09- 2019-03- The manuals and guideline IDA / 60850 Post Open - National 10,000.00 0.00 Canceled Financial Sector Stability tations e Envelope 05 30 29 s will be in the following ar eas: i) Risk based supervisi on, ii) Laws and regulations , iii) financial management and analysis, iv) manuals C11/GO/003 / Publishing th Component C: Enhancing Request for Quo Single Stage - On 2020-07- 2020-08- 2021-02- e bulletin to improve activit IDA / 60850 Post Open - National 5,000.00 0.00 Canceled Financial Sector Stability tations e Envelope 05 30 26 y of investor relations. A2/GO/005 / Purchase of IT Component A: Strengtheni Request for Quo Single Stage - On 2021-11- 2022-01- 2022-06- goods to support tax refor IDA / 60850 ng Macroeconomic and Fis Post Open - National 9,000.00 0.00 Canceled tations e Envelope 06 01 30 m cal Management A32/GO/002 / Publication: Prepare and publish annual Component A: Strengtheni official development assist Request for Quo Single Stage - On 2018-11- 2018-12- 2019-01- IDA / 60850 ng Macroeconomic and Fis Post Open - National 10,000.00 0.00 Canceled ance portfolio report which tations e Envelope 05 31 30 cal Management includes current statistics, t rends and main performan ces of sectors. B11/GO/002 / Purchase of I Component B: Improving t Request for Quo Single Stage - On 2021-11- 2022-01- 2021-02- 2022-06- 2021-05- T goods to support tax refo IDA / 60850 he efficiency of Public Fina Post Open - National 9,000.00 6,364.64 Completed tations e Envelope 06 01 24 30 10 rm ncial Management Component B: Improving t B12/GO/002 / Purchase of I Request for Quo Single Stage - On 2021-11- 2022-01- 2021-02- 2022-01- 2021-05- IDA / 60850 he efficiency of Public Fina Post Open - National 15,000.00 11,907.39 Completed T Goods for tax reform tations e Envelope 06 01 24 31 10 ncial Management B13/GO/004 / Publication s ervice: To publish an updat Component B: Improving t ed International standards f Request for Quo Single Stage - On 2021-06- 2021-08- 2022-01- IDA / 60850 he efficiency of Public Fina Post Open - National 30,000.00 0.00 Canceled or the professional practice tations e Envelope 06 01 28 ncial Management of Internal auditing (IPPF St andards) with official autho rization from The IIA C11/GO/004 / Goods: Purc Component C: Enhancing Request for Quo Single Stage - On 2021-05- 2021-07- 2021-05- 2021-12- 2021-07- hasing personal computers IDA / 60850 Post Open - National 12,000.00 10,543.24 Completed Financial Sector Stability tations e Envelope 07 02 20 29 19 (4) with desktops and 2 lap tops. B22/GO/013 / Host securit y module 2 pcss for Gatew ay to receive revenue pay ments made using a non-c Component B: Improving t Request for Quo Single Stage - On 2020-11- 2021-01- 2020-11- 2021-07- 2021-02- ash payment instrument su IDA / 60850 he efficiency of Public Fina Post Open - National 34,000.00 29,439.38 Completed tations e Envelope 13 08 03 07 08 ch as a payment card and ncial Management other similar equivalents pr ogressive instruments base d on payment cards using t he POS system, ATM QR co de, E-Commerce B4/GO/002 / Publication of Component B: Improving t Request for Quo Single Stage - On 2021-06- 2021-08- 2022-02- 2022-01- 2022-03- handouts and training mat IDA / 60850 he efficiency of Public Fina Post Open - National 10,000.00 4,785.14 Completed tations e Envelope 06 01 09 28 08 erials ncial Management D1/GO/008 / To increase t he access of social workers Component D: Strengtheni Request for Quo Single Stage - On 2020-11- 2021-01- 2021-02- 2021-07- 2021-03- to counselling (detached co IDA / 60850 ng of the Social Protection Post Open - National 30,000.00 24,523.32 Completed tations e Envelope 21 16 25 15 31 unseling table set with) an System d to buy furniture of a coun selling room in LSWA (Goo ds) D1/GO/009 / Publishing of Component D: Strengtheni handouts and brochures of Request for Quo Single Stage - On 2021-03- 2021-05- 2021-10- IDA / 60850 ng of the Social Protection Post Open - National 4,000.00 0.00 Canceled improving public understan tations e Envelope 06 01 28 System ding of social welfare refor m, programs, consolidation D1/GO/010 / Publishing br ochures in braille on social Component D: Strengtheni Request for Quo Single Stage - On 2020-09- 2020-11- 2021-05- welfare service allowances IDA / 60850 ng of the Social Protection Post Open - National 3,000.00 0.00 Canceled tations e Envelope 20 15 14 for the visually impaired pe System ople and in kazakh langua ge for Kazakh people A32/GO/005 / Purchase: IT Component A: Strengtheni Request for Quo Single Stage - On 2021-04- 2021-06- 2022-01- 2021-11- 2022-05- goods (video conferencing IDA / 60840 ng Macroeconomic and Fis Post Open - National 15,000.00 13,066.01 Completed tations e Envelope 06 01 07 28 02 equipment, including smart cal Management projector) B21/GO/006 / Annual copy Component B: Improving t 2021-06- 2021-03- 2021-06- 2021-03- 2021-08- 2021-06- 2022-01- 2021-06- right fee for publishing IPS IDA / 60840 he efficiency of Public Fina Post Direct Selection Direct 1,250.00 1,250.00 Completed 23 10 28 15 02 09 29 09 AS 2018 translated into Mo ncial Management ngolian due to IFAC. A1/GO/006 / Extension for Component A: Strengtheni 2021-11- 2021-08- 2021-11- 2021-08- 2021-12- 2021-11- 2022-01- data access to electronic s IDA / 60840 ng Macroeconomic and Fis Post Direct Selection Direct 3,000.00 5,000.00 Signed 01 27 06 27 11 15 31 ources cal Management B13/GO/04 / Publication se rvice: To publish an update Component B: Improving t Pending I d International standards fo Request for Quo Single Stage - On 2021-07- 2021-08- 2022-02- IDA / 60840 he efficiency of Public Fina Post Open - National 25,000.00 0.00 mplement r the professional practice tations e Envelope 06 31 27 ncial Management ation of Internal auditing (IPPF St andards) with official autho rization from The IIA C11/GO/005 / Subscribing f or some Internationally rec Component C: Enhancing 2020-09- 2020-09- 2020-10- 2021-04- IDA / 60850 Post Direct Selection Direct 450.00 0.00 Canceled ognized online journals (rel Financial Sector Stability 07 12 17 15 ated to finance and econo mics). B22/GO/09 / Host secirity module 2 pieces for Gatew ay to receive revenue pay Component B: Improving t Request for Quo Single Stage - On 2020-12- 2021-02- 2021-06- 2021-08- 2021-08- ments made using a non-c IDA / 60840 he efficiency of Public Fina Post Open - National 34,000.00 53,045.70 Completed tations e Envelope 28 22 02 21 02 ash payment instrument su ncial Management ch as a payment card and other similar equivalents pr ogressive instruments… Component B: Improving t B33/GO/001 / IT goods for Request for Quo Single Stage - On 2021-01- 2021-03- 2021-09- IDA / 60840 he efficiency of Public Fina Post Open - National 10,000.00 0.00 Canceled officials tations e Envelope 25 22 18 ncial Management C31/GO/001 / Process Gen Component C: Enhancing Request for Quo Single Stage - On Pending I 2021-01- 2021-03- 2021-09- IDA / 60840 Post Open - National 1,440.00 0.00 e GRC Software suite Financial Sector Stability tations e Envelope mplement 30 27 23 ation C4/GO/005 / Purchase of n ecessary IT goods for the F Component C: Enhancing Request for Quo Single Stage - On 2020-09- 2020-11- 2020-09- 2021-05- 2020-12- IDA / 60840 Post Open - National 15,330.00 15,326.11 Completed RC office extension and est Financial Sector Stability tations e Envelope 12 07 24 06 31 ablishment of new division and units C5/GO/004 / Procurement Component C: Enhancing 2021-04- 2021-01- 2021-04- 2021-01- 2021-05- 2021-02- 2021-11- 2022-03- IDA / 60840 Post Direct Selection Direct 43,480.00 43,480.00 Completed of MATLAB software license Financial Sector Stability 01 22 06 20 11 12 07 25 D1/GO/013 / Printing of pu blic advocacy materials, gu Component D: Strengtheni Request for Quo Single Stage - On 2021-02- 2021-04- 2022-01- 2021-09- idance, handouts, and book IDA / 60840 ng of the Social Protection Post Open - National 10,000.00 8,898.99 Signed tations e Envelope 05 02 18 29 related to Strengthening So System cial Welfare Programs desi gn and operations (1) D1/GO/014 / Printing of pu blic advocacy materials, gu Component D: Strengtheni Request for Quo Single Stage - On 2021-03- 2021-05- 2021-11- idance, handouts, and book IDA / 60840 ng of the Social Protection Post Open - National 5,000.00 0.00 Canceled tations e Envelope 25 20 16 related to Strengthening So System cial Welfare Programs desi gn and operations (2) D1/GO/016 / Purchase of IT Component D: Strengtheni Goods for supporting the di Request for Quo Single Stage - On 2021-02- 2021-04- 2021-05- 2021-09- 2021-05- IDA / 60840 ng of the Social Protection Post Open - National 5,000.00 4,772.18 Completed gitalization of social welfar tations e Envelope 06 03 13 30 17 System e administration, (5 compu ters) D1/GO/017 / Purchase of IT Goods for supporting the di Component D: Strengtheni gitalization of social welfar Request for Quo Single Stage - On 2021-02- 2021-04- 2021-06- 2021-09- 2021-08- IDA / 60840 ng of the Social Protection Post Open - National 22,500.00 25,208.68 Completed e administration, improving tations e Envelope 06 03 02 30 12 System efficiency of service deliver y, administrative reporting, monitoring and evaluation D2/GO/009 / Printing of pu blic advocacy materials, gu Component D: Strengtheni Request for Quo Single Stage - On 2021-02- 2021-04- 2021-12- 2021-09- idance, handouts, and book IDA / 60840 ng of the Social Protection Post Open - National 5,000.00 3,982.87 Signed tations e Envelope 06 03 23 30 related to strengthening so System cial insurance Reforms and operations (1) D2/GO/011 / Printing of pu blic advocacy materials, gu Component D: Strengtheni Request for Quo Single Stage - On 2021-06- 2021-08- 2022-01- 2022-02- idance, handouts, and book IDA / 60840 ng of the Social Protection Post Open - National 10,000.00 8,674.12 Signed tations e Envelope 25 20 24 16 related to strengthening so System cial insurance Reforms and operations (3) D2/GO/012 / Purchase of IT Goods for supporting the di Component D: Strengtheni gitalization for the social in Request for Quo Single Stage - On 2021-02- 2021-04- 2021-06- 2021-09- 2021-08- IDA / 60840 ng of the Social Protection Post Open - National 22,500.00 25,208.68 Completed surance administration, im tations e Envelope 06 03 02 30 12 System proving administrative repo rting and monitoring and st rengthening social insuranc e service delivery D2/GO/013 / Purchase of IT Component D: Strengtheni Request for Quo Single Stage - On 2021-04- 2021-05- 2021-06- 2021-11- Goods for training facility a IDA / 60840 ng of the Social Protection Post Open - National 15,500.00 13,840.46 Signed tations e Envelope 04 30 03 26 nd online meetings (SIGO's System training hall) B22/GO/009 / SAS SSD's fo Component B: Improving t Request for Quo Single Stage - On 2020-06- 2020-08- 2021-01- r increasing the storage ca IDA / 60850 he efficiency of Public Fina Post Open - National 60,000.00 0.00 Canceled tations e Envelope 06 01 28 pacity of interbank transact ncial Management ion servers D1/GO/0010 / Publishing b Component D: Strengtheni rochures in braille on social 2020-11- 2020-12- 2021-01- 2021-07- IDA / 60850 ng of the Social Protection Post Direct Selection Direct 3,000.00 0.00 Canceled welfare service allowances 30 05 09 08 System for the visually impaired pe ople D1/GO/019 / Publishing br Component D: Strengtheni ochures in braille on social Request for Quo Single Stage - On 2021-09- 2021-11- 2021-09- 2022-01- 2021-10- IDA / 60840 ng of the Social Protection Post Open - National 3,019.00 2,833.68 Completed welfare service allowances tations e Envelope 10 05 09 31 08 System for the visually impaired pe ople B22/GO/014 / IT goods for Component B: Improving t Request for Quo Single Stage - On 2021-09- 2021-11- 2021-10- 2022-01- 2021-12- UB and 21 aimags' local tre IDA / 60840 he efficiency of Public Fina Post Open - National 32,648.00 29,045.60 Completed tations e Envelope 26 21 28 31 31 asury officials (laptop comp ncial Management uters) B13/GO/007 / Editing and Component B: Improving t Pending I 2021-12- 2021-12- 2022-01- 2022-07- printing “Public Sector Inter IDA / 60840 he efficiency of Public Fina Post Direct Selection Direct 800.00 0.00 mplement 02 07 11 10 nal Auditor” magazine for F ncial Management ation CRMD B21/GO/005 / Copyright fe e due to IFAC for permissio Component B: Improving t 2022-04- 2022-04- 2022-04- 2022-03- 2022-05- 2022-05- 2022-08- n to translate and publish n IDA / 60840 he efficiency of Public Fina Post Direct Selection Direct 1,250.00 1,250.00 Signed 01 18 06 22 11 10 01 ew standards and amendm ncial Management ents to IPSAS 2018 and IPS AS 2019. B22/GO/016 / Printing: Tre Component B: Improving t Pending I Request for Quo Single Stage - On 2022-04- 2022-06- 2022-11- asury accounting manual 5 IDA / 60840 he efficiency of Public Fina Post Open - National 15,000.00 0.00 mplement tations e Envelope 06 01 28 00pc for local treasury and ncial Management ation ebook B31/GO/004 / Purchase ha Component B: Improving t Request for Quo Single Stage - On 2022-03- 2022-05- 2022-05- 2022-10- rdware to equip the interba IDA / 60850 he efficiency of Public Fina Post Open - National 80,000.00 47,643.08 Signed tations e Envelope 06 01 02 28 nk system ncial Management C4/GO/006 / Publication m Pending I Component C: Enhancing Request for Quo Single Stage - On 2022-06- 2022-08- 2023-01- anuals/guides for new mark IDA / 60840 Post Open - National 10,000.00 0.00 mplement Financial Sector Stability tations e Envelope 06 01 28 ets (REAs and DPMS ) and l ation egislation D1/GO/015 / Printing of pu blic advocacy materials, gu Component D: Strengtheni Request for Quo Single Stage - On 2022-06- 2022-08- 2022-01- 2023-01- idance, handouts, and book IDA / 60840 ng of the Social Protection Post Open - National 10,000.00 9,601.39 Signed tations e Envelope 06 01 21 31 related to Strengthening So System cial Welfare Programs desi gn and operations A32/GO/003 / Procurement Component A: Strengtheni Pending I Request for Quo Single Stage - On 2022-06- 2022-08- 2022-09- : IT goods (multifunction pri IDA / 60840 ng Macroeconomic and Fis Post Open - National 8,500.00 0.00 mplement tations e Envelope 20 15 14 nter and other necessary e cal Management ation quipment) B22/GO/015 / iSpring lifeti Component B: Improving t 2022-01- 2022-01- 2022-03- 2022-08- me license to use develop t IDA / 60840 he efficiency of Public Fina Post Direct Selection Direct 1,200.00 0.00 Canceled 23 28 04 31 raining content for LMS onli ncial Management ne training platform B4/GO/02 / Publication of Component B: Improving t manuals and materials expl Request for Quo Single Stage - On 2022-09- 2022-11- 2023-01- IDA / 60840 he efficiency of Public Fina Post Open - National 3,000.00 0.00 Canceled aining the public investmen tations e Envelope 06 01 31 ncial Management t management and method ology (300 pcs) B4/GO/008 / Publication of Component B: Improving t 2022-03- 2022-03- 2022-04- 2022-10- PPP law materials (200 pcs IDA / 60840 he efficiency of Public Fina Post Direct Selection Direct 7,000.00 0.00 Canceled 01 06 10 07 ) ncial Management D1/GO/007 / Printing of pu blic advocacy materials, gu Component D: Strengtheni Request for Quo Single Stage - On 2022-07- 2022-09- 2023-01- idance, handouts, and book IDA / 60840 ng of the Social Protection Post Open - National 10,000.00 0.00 Canceled tations e Envelope 25 19 31 related to strengthening th System e social welfare program d esign and operations E/GO/008 / Video conferen Component E: Project Man Request for Quo Single Stage - On 2021-06- 2021-08- 2022-01- IDA / 60840 Post Open - National 7,000.00 0.00 Canceled ce equipment agement and Monitoring tations e Envelope 06 01 28 D2/GO/014 / Printing of pu blic advocacy materials, gu Component D: Strengtheni Request for Quo Single Stage - On 2022-07- 2022-09- 2023-01- idance, handouts, and book IDA / 60840 ng of the Social Protection Post Open - National 15,000.00 0.00 Canceled tations e Envelope 25 19 31 related to Strengthening So System cial Welfare Programs desi gn and operations D2/GO/010 / Purchase tabl ets to be used for soum an Component D: Strengtheni Pending I Request for Quo Single Stage - On 2022-07- 2022-08- 2023-02- d khoroo social work surve IDA / 60840 ng of the Social Protection Post Open - National 60,000.00 0.00 mplement tations e Envelope 05 30 26 ys, as a new household livi System ation ng standard survey method ology has been approved. Component B: Improving t Pending I B4/GO/009 / Procurement Request for Quo Single Stage - On 2022-06- 2022-08- 2023-02- IDA / 60840 he efficiency of Public Fina Post Open - National 4,000.00 0.00 mplement of IT goods tations e Envelope 20 15 11 ncial Management ation Page 2 NON CONSULTING SERVICES Activity Reference No Estimated A Draft Bidding Doc Specific Procureme Proposal Submissio Bid Evaluation Rep Loan / Credit Market Appro Procurement Prequalificati Actual Amou Process Draft Pre-qualificati Prequalification Ev Bidding Documents Contract Completio . / Description Component Review Type Method mount (US$ ument / Justificatio nt Notice / Invitatio n / Opening / Minut ort and Recommen Signed Contract No. ach Process on (Y/N) nt (US$) Status on Documents aluation Report as Issued n ) n n es dation for Award Planne Actual Planne Actual Planne Actual Planne Actual Planne Actual Planne Actual Planne Actual Planne Actual Planne Actual d d d d d d d d d B13/NC/001 / Public aware Component B: Improving t ness activities of Internal A Request for Quo Single Stage - On 2018-11- 2018-12- 2019-06- IDA / 60850 he efficiency of Public Fina Post Open - National 12,000.00 0.00 Canceled udit Law, promote internal tations e Envelope 05 31 29 ncial Management audit issues among public C11/NC/002 / Public aware Component C: Enhancing Request for Quo Single Stage - On 2018-12- 2019-02- 2019-08- ness activities, including Pu IDA / 60850 Post Open - National 2,000.00 0.00 Canceled Financial Sector Stability tations e Envelope 29 23 22 blication of articles, newsp apers and magazines C11/NC/001 / Public aware Component C: Enhancing Request for Quo Single Stage - On 2019-01- 2019-03- 2019-08- ness activities, including br IDA / 60850 Post Open - National 3,000.00 0.00 Canceled Financial Sector Stability tations e Envelope 05 02 29 oadcasting of short-TV prog rams and interviews. B11/NC/001 / Non consulti ng service to develop 2018 Component B: Improving t 2018-07- 2018-07- 2018-07- 2018-07- 2018-08- 2018-07- 2019-02- 2018-08- Citizen's budget video clips IDA / 60850 he efficiency of Public Fina Post Direct Selection Direct 15,000.00 10,036.40 Completed 02 17 07 23 11 23 07 23 to improve budget transpar ncial Management ency and predictability for better service delivery D2/NC/001 / Public awaren ess for gradually building s Component D: Strengtheni 2020-04- 2020-06- 2020-04- 2020-06- 2020-05- 2020-06- 2020-11- 2021-10- ocial consensus on the pen IDA / 60850 ng of the Social Protection Post Direct Selection Direct 20,000.00 2,313.16 Completed 20 04 25 16 30 16 26 01 sion reform needs and prin System cipals (non-consulting servi ce and training). B13/NC/002 / Video makin g studio service /all service Component B: Improving t 2020-05- 2020-07- 2020-05- 2020-07- 2020-06- 2020-07- 2020-12- 2020-12- s for 45 min 4 types of vide IDA / 60850 he efficiency of Public Fina Post Direct Selection Direct 7,194.24 6,344.82 Completed 01 20 06 20 10 21 07 16 o lessons: IA, risk, quality a ncial Management ssurance, and international best practices/. A1/NC/001 / Public awaren ess activities and to create Component A: Strengtheni Request for Quo Single Stage - On 2020-06- 2020-08- 2021-01- short video of media conte IDA / 60850 ng Macroeconomic and Fis Post Open - National 10,000.00 0.00 Canceled tations e Envelope 06 01 28 nts for Economic and Social cal Management Development Guidelines fo r 2021 A2/NC/001 / Public awaren Component A: Strengtheni ess activities including med Request for Quo Single Stage - On 2020-06- 2020-08- 2021-02- IDA / 60850 ng Macroeconomic and Fis Post Open - National 12,000.00 0.00 Canceled ia coverage on the tax poli tations e Envelope 25 20 16 cal Management cy reform including public discussions on tax reforms B21/NC/001 / Training vide Component B: Improving t 2020-12- 2020-12- 2020-12- 2020-12- 2021-01- 2021-02- 2021-07- 2021-04- o lessons of IPSAS to accou IDA / 60850 he efficiency of Public Fina Post Direct Selection Direct 2,800.00 2,385.98 Completed 01 28 06 28 10 24 09 05 ntants of budget entities ncial Management D1/NC/001 / Non-consultin g service for formulating an Component D: Strengtheni d executing an internal and 2020-11- 2020-11- 2020-12- 2021-06- IDA / 60850 ng of the Social Protection Post Direct Selection Direct 10,000.00 0.00 Canceled external public awareness 09 14 19 17 System campaign to improve publi c understanding of social w elfare reform, programs, co nsolidation C31/NC/001 / Video tutoria ls, content, and manuals on Pending I deposit insurance system a Component C: Enhancing Request for Quo Single Stage - On 2021-02- 2021-04- 2021-09- IDA / 60840 Post Open - National 20,000.00 0.00 mplement nd operations, reimbursem Financial Sector Stability tations e Envelope 06 03 30 ation ent process /to enhance th e public awareness rate an d financial education/ D1/NC/002 / National cons ulting firm or NGO to collec Component D: Strengtheni t data for pilot testing of th Request for Quo Single Stage - On 2021-04- 2021-06- 2022-02- 2021-12- IDA / 60840 ng of the Social Protection Post Open - National 15,000.00 13,876.71 Signed e Modified Household Livin tations e Envelope 25 20 15 17 System g Standards Assessment q uestionnaire for developing a Hybrid PMT Model D1/NC/003 / Non-consultin g firm or NGO for formulati Component D: Strengtheni Request for Quo Single Stage - On 2021-02- 2021-04- 2021-11- 2021-10- ng and executing public aw IDA / 60840 ng of the Social Protection Post Open - National 9,000.00 8,717.78 Signed tations e Envelope 25 22 22 19 areness campaign to impro System ve public understanding of social welfare reforms and programs D1/NC/004 / Non-consultin g firm or NGO for formulati Component D: Strengtheni ng and executing public aw Request for Quo Single Stage - On 2021-03- 2021-05- 2021-11- 2021-11- 2022-01- IDA / 60840 ng of the Social Protection Post Open - National 7,000.00 6,975.52 Completed areness campaign to impro tations e Envelope 25 20 03 16 31 System ve public understanding of social welfare reforms and programs (1) D1/NC/006 / Non-consultin g firm or NGO for formulati Component D: Strengtheni ng and executing public aw Request for Quo Single Stage - On 2021-04- 2021-06- 2021-12- IDA / 60840 ng of the Social Protection Post Open - National 7,000.00 0.00 Canceled areness campaign to impro tations e Envelope 25 20 17 System ve public understanding of social welfare reforms and programs (3) D2/NC/003 / Non-consultin g firm or NGO for formulati Component D: Strengtheni ng and executing public aw Request for Quo Single Stage - On 2021-02- 2021-04- 2021-08- 2021-10- IDA / 60840 ng of the Social Protection Post Open - National 10,000.00 9,017.67 Signed areness campaign to impro tations e Envelope 25 22 20 19 System ve public understanding of social insurance reforms an d programs (2) D2/NC/004 / Non-consultin g firm or NGO for formulati Component D: Strengtheni ng and executing public aw Request for Quo Single Stage - On 2021-05- 2021-07- 2021-09- 2022-01- 2022-01- IDA / 60840 ng of the Social Protection Post Open - National 10,000.00 8,633.23 Completed areness campaign to impro tations e Envelope 25 20 01 16 31 System ve public understanding of social insurance reforms an d programs (3) D2/NC/002 / Non-consultin g firm or NGO for formulati Component D: Strengtheni ng and executing public aw Request for Quo Single Stage - On 2021-02- 2021-04- 2021-10- IDA / 60840 ng of the Social Protection Post Open - National 10,000.00 0.00 Canceled areness campaign to impro tations e Envelope 25 22 19 System ve public understanding of social insurance reforms an d programs (1) D2/NC/005 / Non-consultin g firm or NGO for formulati Component D: Strengtheni ng and executing public aw Request for Quo Single Stage - On 2021-08- 2021-09- 2021-09- 2022-01- 2022-01- IDA / 60840 ng of the Social Protection Post Open - National 5,000.00 4,464.09 Completed areness campaign to impro tations e Envelope 04 29 06 31 31 System ve public understanding of social insurance reforms an d programs D2/NC/006 / Non-consultin g firm or NGO for formulati Component D: Strengtheni ng and executing public aw Request for Quo Single Stage - On 2021-09- 2021-11- 2021-08- 2022-01- 2022-01- IDA / 60840 ng of the Social Protection Post Open - National 5,000.00 4,464.09 Completed areness campaign to impro tations e Envelope 06 01 30 31 31 System ve public understanding of social insurance reforms an d programs B31/NC/004 / Video conten Component B: Improving t Pending I 2021-12- 2021-12- 2022-01- 2022-07- t making for the “Leader M IDA / 60840 he efficiency of Public Fina Post Direct Selection Direct 6,500.00 0.00 mplement 02 07 11 10 onitoring-3 System User Ma ncial Management ation nual” B13/NC/003 / Editing and p Component B: Improving t Pending I osting the “Public Sector In 2022-02- 2022-02- 2022-03- 2022-09- IDA / 60840 he efficiency of Public Fina Post Direct Selection Direct 5,000.00 0.00 mplement ternal Auditor” magazine t 01 06 13 09 ncial Management ation o a digital platform, World Plus Application B13/NC/004 / Video conten Component B: Improving t 2022-04- 2022-04- 2022-05- 2022-11- t making for the "Leader M IDA / 60840 he efficiency of Public Fina Post Direct Selection Direct 6,500.00 0.00 Canceled 01 06 11 07 onitoring-3 System User Ma ncial Management nual" B13/NC/005 / Video conten Component B: Improving t Pending I 2022-02- 2022-02- 2022-03- 2022-09- t making for internal audit t IDA / 60840 he efficiency of Public Fina Post Direct Selection Direct 7,500.00 0.00 mplement 01 06 13 09 raining materials ncial Management ation D1/NC/005 / Consulting fir m/or NGO for broadcasting Component D: Strengtheni Request for Quo Single Stage - On 2022-03- 2022-05- 2023-01- public awareness products IDA / 60840 ng of the Social Protection Post Open - National 8,000.00 0.00 Canceled tations e Envelope 27 22 31 to improve public understa System nding of social welfare refo rms and programs D2/NC/008 / Consulting fir m/or NGO for broadcasting Component D: Strengtheni Request for Quo Single Stage - On 2022-04- 2022-06- 2023-01- public awareness products IDA / 60840 ng of the Social Protection Post Open - National 8,000.00 0.00 Canceled tations e Envelope 06 01 31 to improve public understa System nding of social insurance re forms and, programs D2/NC/007 / Non-consultin g firm- Digitalization of pap er-based personal file archi Component D: Strengtheni ves of social insurance pen Request for Quo Single Stage - On 2022-03- 2022-05- 2023-01- IDA / 60840 ng of the Social Protection Post Open - National 81,000.00 0.00 Canceled sions and transfer to smart tations e Envelope 06 01 31 System archive system (more than 56.0 thousand before 1995 , about 400.0 thousand for 26 years since 1995, total 456.0 thousand for person CONSULTING FIRMS Activity Reference No Short List and Draft Opening of Technic Combined Evaluati Loan / Credit Market Appro Contract Type Estimated A Actual Amo Process Stat Expression of Inter Request for Propos Evaluation of Tech Contract Completio . / Description Component Review Type Method Terms of Reference Request for Propos al Proposals / Minut on Report and Draf Signed Contract No. ach mount (US$) unt (US$) us est Notice als as Issued nical Proposal n als es t Negotiated Contr Planned Actual Planne Actual Planne Actual Planne Actual Planne Actual Planne Actual Planne act Actual Planne Actual Planne Actual d d d d d d d d A32/CS/002 / Consulting fir m (Software development) to improve automation of t Component A: Strengtheni Consultant Qual 2018-08-2 2018-09- 2018-10- 2018-11- 2019-01- 2019-07- ax exemption process and IDA / 60850 ng Macroeconomic and Fis Post ification Selecti Open - National 42,000.00 0.00 Canceled 7 17 31 30 04 03 recording to approve, revie cal Management on w, monitor and record gove rnment taxes and duties ex emption of externally fund ed development projects B13/CS/009 / Consulting fir m to develop risk manage ment system and strengthe Component B: Improving t Consultant Qual n risk management capacit 2018-11-3 2018-12- 2019-02- 2019-03- 2019-04- 2020-04- IDA / 60850 he efficiency of Public Fina Post ification Selecti Open - National 50,000.00 0.00 Canceled y including i.update and ev 0 21 03 05 09 08 ncial Management on aluate performance risk of the MoF, ii. update and eva luate risks in public budget planning and other related tasks B32/CS/001 / Consulting fir m to process analysis in th Component B: Improving t Consultant Qual 2018-11-3 2018-10- 2018-12- 2019-02- 2018-11- 2019-03- 2019-01- 2019-04- 2019-01- 2019-10- 2019-11- e implementation and man IDA / 60850 he efficiency of Public Fina Post ification Selecti Open - National 50,000.00 47,976.00 Completed 0 10 21 03 29 05 02 09 03 06 07 agement of the general an ncial Management on d specific functions of the Ministry of Finance E/CS/007 / Consultancy ser Component E: Project Man Consultant Qual 2018-12-1 2018-12- 2019-02- 2019-03- 2019-04- 2019-05- IDA / 60850 Prior Open - National 7,500.00 0.00 Canceled vices audit company agement and Monitoring ification Selecti 0 31 13 15 19 09 on B11/CS/007 / Consulting fir m to establish a sustainabl e training system at the na Component B: Improving t Consultant Qual 2018-07-3 2018-08- 2018-10- 2018-11- 2018-12- 2019-06- tionwide to strengthen the IDA / 60850 he efficiency of Public Fina Post ification Selecti Open - National 40,000.00 0.00 Canceled 1 21 04 03 08 06 capacity of budget officers ncial Management on to all level of budget entitie s with the help of universiti es, NGOs and private entiti es C11/CS/02 / Develop a lon g-term planning for capital Consultant Qual Component C: Enhancing 2018-08-3 2018-09- 2018-11- 2018-12- 2019-01- 2019-07- market IT system (impleme IDA / 60850 Post ification Selecti Open - National 29,600.00 0.00 Canceled Financial Sector Stability 1 21 04 04 08 07 ntation step X1.2-1), upgra on de existing system or add modules or replace system C4/CS/008 / Consultancy s Consultant Qual Component C: Enhancing 2018-08-3 2018-09- 2018-11- 2018-12- 2019-01- 2019-07- ervice (firm) to draft Over-t IDA / 60850 Post ification Selecti Open - National 32,000.00 0.00 Canceled Financial Sector Stability 1 21 04 04 08 07 he-counter (OTC) market re on gulations D2/CS/011 / National cons Component D: Strengtheni Consultant Qual ulting firm to draft legislati 2018-05-3 2018-06- 2018-08- 2018-09- 2018-10- 2019-04- IDA / 60850 ng of the Social Protection Post ification Selecti Open - National 54,000.00 0.00 Canceled on on specific types of pen 1 21 04 03 08 06 System on sion paid from Social insura nce fund A1/CS/009 / Consulting Fir Component A: Strengtheni Consultant Qual 2019-01-1 2019-02- 2019-03- 2019-04- 2019-05- 2019-11- m to estimate Purchasing IDA / 60850 ng Macroeconomic and Fis Post ification Selecti Open - National 30,000.00 0.00 Canceled 5 05 21 20 25 21 Manager's Index cal Management on B13/CS/007 / Consulting fir m: - To develop and have a pproved technical assignm Component B: Improving t Consultant Qual 2019-04-1 2019-06- 2019-05- 2019-06- 2019-08- 2019-07- 2019-09- 2019-08- 2019-09- 2020-02- 2020-05- ent, design/blueprint of the IDA / 60850 he efficiency of Public Fina Post ification Selecti Open - National 95,000.00 90,210.00 Completed 5 10 06 19 16 19 09 23 09 19 28 Internal Audit-Financial Con ncial Management on trol Management Informati on System, To provide fram ework and preparatory acti vities for the system B22/CS/006 / Consulting fir m on development of modu Component B: Improving t Consultant Qual le on reporting and reconcil 2019-04-0 2019-08- 2019-04- 2019-06- 2019-07- 2019-08- 2020-02- IDA / 60850 he efficiency of Public Fina Post ification Selecti Open - National 12,000.00 0.00 Canceled iation of accounts of budge 1 28 22 05 05 09 05 ncial Management on t entity's at commercials b anks and its interface with Bank of Mongolia A1/CS/017 / Consulting fir m to conduct a policy resea Component A: Strengtheni Consultant Qual rch on the realization of opt 2019-06-0 2019-11- 2019-06- 2019-08- 2019-09- 2019-10- 2020-04- IDA / 60850 ng Macroeconomic and Fis Post ification Selecti Open - National 15,000.00 0.00 Canceled imal mineral prices determi 1 19 22 05 04 09 06 cal Management on nation and government par ticipation in strategically i mportant mines A31/CS/008 / Consulting fir Component A: Strengtheni Consultant Qual m on legal framework, its p 2019-02-2 2019-11- 2019-03- 2019-05- 2020-03- 2019-05- 2020-08- 2019-07- 2020-09- 2020-01- 2021-04- IDA / 60850 ng Macroeconomic and Fis Post ification Selecti Open - National 24,000.00 39,928.00 Completed rinciples and monitoring an 5 15 18 01 19 31 21 05 03 01 03 cal Management on d evaluation on debt law e nforcement A31/CS/010 / Consulting fir Component A: Strengtheni Consultant Qual m on determining debt regi 2019-04-1 2019-05- 2019-06- 2019-07- 2019-08- 2020-02- IDA / 60850 ng Macroeconomic and Fis Post ification Selecti Open - National 20,000.00 0.00 Canceled stration and monitoring pro 0 01 14 14 18 14 cal Management on cess and developing regula tion draft A31/CS/011 / Consulting fir Component A: Strengtheni Consultant Qual 2019-03-1 2019-11- 2019-04- 2019-05- 2020-03- 2019-06- 2020-09- 2019-07- 2020-09- 2020-01- 2021-03- m on developing a professi IDA / 60850 ng Macroeconomic and Fis Post ification Selecti Open - National 15,000.00 38,625.80 Completed 3 15 03 17 20 16 30 21 30 17 01 onal training program for D cal Management on MO staff A31/CS/014 / Consulting fir Component A: Strengtheni Consultant Qual 2019-06-0 2019-06- 2019-08- 2019-09- 2019-10- 2020-04- m to develop debt manage IDA / 60850 ng Macroeconomic and Fis Post ification Selecti Open - National 25,000.00 0.00 Canceled 3 24 07 06 11 08 ment procedure manual an cal Management on d job descriptions B31/CS/008 / Consulting fir m to build the proper struct ure and organization of app Component B: Improving t Consultant Qual ropriate system databases, 2019-03-0 2019-04- 2019-03- 2019-05- 2019-05- 2019-06- 2019-05- 2019-07- 2019-05- 2020-01- 2022-01- IDA / 60850 he efficiency of Public Fina Post ification Selecti Open - National 24,000.00 59,985.00 Completed to maintain a database of i 1 05 22 05 15 04 29 09 29 05 26 ncial Management on ntegrated management an d control and develop a co mprehensive document for building the overall environ ment… B4/CS/011 / Consulting fir m to develop professional a nd methodological guidanc Component B: Improving t Consultant Qual e for preparation and super 2019-04-0 2019-04- 2019-06- 2019-07- 2019-08- 2020-02- IDA / 60850 he efficiency of Public Fina Post ification Selecti Open - National 36,000.00 0.00 Canceled vision of drawings and cost 1 22 05 05 09 05 ncial Management on estimation, implementation and monitoring of construc tion works, and improving l egal issues related to respo nsible of parties C4/CS/020 / Research Insti tution to conduct studies o n development of tech-bas Consultant Qual Component C: Enhancing 2019-04-0 2019-05- 2019-04- 2019-06- 2019-09- 2019-07- 2019-09- 2019-08- 2019-09- 2020-02- 2020-03- ed new product and service IDA / 60850 Post ification Selecti Open - National 12,500.00 11,873.00 Completed Financial Sector Stability 1 14 22 05 20 05 30 09 30 05 06 in financial markets except on commercial banks (capital, insurance, non-bank financi al institutions, savings and credit cooperatives) C5/CS/012 / Consulting fir Component C: Enhancing Consultant Qual Open - Internatio 2019-03-0 2019-03- 2019-05- 2019-06- 2019-07- 2020-01- IDA / 60850 Prior 200,000.00 0.00 Canceled m to facilitate implementat Financial Sector Stability ification Selecti nal 1 22 05 04 09 05 ion of IFRS-9 on A32/CS/03 / Consulting fir m (Software upgrade): Upgrading the Official Deve lopment Assistance Monitor Component A: Strengtheni Consultant Qual ing Information System (O 2019-04-0 2019-09- 2019-04- 2019-06- 2019-12- 2019-07- 2020-01- 2019-08- 2020-01- 2020-02- 2021-08- IDA / 60850 ng Macroeconomic and Fis Post ification Selecti Open - National 42,000.00 41,971.60 Completed DAMIS). 8 11 29 12 18 12 21 16 23 12 26 cal Management on - Completing historic infor mantion database of ODA. - Optimizing the structure o f the database of the projec t and activities... C5/CS/11 / International co Consultant Qual nsulting firm for Developin Component C: Enhancing Open - Internatio 2019-11-1 2019-12- 2019-12- 2020-01- 2020-01- 2020-03- 2020-02- 2020-07- 2020-03- 2020-07- 2020-09- 2021-12- IDA / 60850 Post ification Selecti 100,000.00 93,108.00 Completed g DSGE Model with Financi Financial Sector Stability nal 2 11 03 06 16 20 15 08 21 08 17 20 on al Sector and Element of M acroprudential Policy B22/CS/007 / Consulting fir m on development and enh ancement of customized re Component B: Improving t Consultant Qual 2020-06-3 2020-07- 2020-09- 2020-10- 2020-11- 2021-05- porting system /Integrating IDA / 60850 he efficiency of Public Fina Post ification Selecti Open - National 30,000.00 0.00 Canceled 0 21 03 03 07 06 GFMIS and E-reporting in li ncial Management on ne with standard/ rules GFS 2014 and reporting based on required coding blocks o f MOF C31/CS/002 / Consulting fir Consultant Qual m to develop risk manage Component C: Enhancing 2020-06-3 2020-07- 2020-09- 2020-10- 2020-11- 2021-05- IDA / 60850 Prior ification Selecti Open - National 150,000.00 0.00 Canceled ment and insurance reimbu Financial Sector Stability 0 21 03 03 07 06 on rsement software for DICO M. B22/CS/026 / Consulting fir m service to develop Gate Component B: Improving t Consultant Qual way on Bank interface syst 2019-12-0 2019-12- 2020-02- 2020-03- 2020-04- 2020-10- IDA / 60850 he efficiency of Public Fina Post ification Selecti Open - National 90,000.00 0.00 Canceled em to connect with varies 1 22 04 05 09 06 ncial Management on payment methods such as POS system, QR, Mobile, Ki osk system B32/CS/011 / Pilot English Component B: Improving t Consultant Qual 2020-09-0 2020-10- 2020-09- 2020-11- 2021-03- 2020-12- 2021-04- 2021-01- 2021-04- 2021-07- 2022-04- Language Training for MOF IDA / 60850 he efficiency of Public Fina Post ification Selecti Open - National 20,000.00 19,463.18 Completed 1 26 22 05 26 05 28 09 28 08 27 staffs ncial Management on B31/CS/02 / Consulting ser vice to develop a compreh ensive documentation of in Component B: Improving t Consultant Qual formation technology envir 2020-06-0 2020-10- 2020-06- 2020-08- 2020-11- 2020-09- 2020-12- 2020-10- 2020-12- 2021-04- 2021-12- IDA / 60850 he efficiency of Public Fina Post ification Selecti Open - National 54,000.00 42,031.20 Completed onments to improve the ne 1 06 22 05 25 04 23 09 23 07 22 ncial Management on twork infrastructure and se curity equipment, infrastru cture of the IT network, to i mprove the network capaci ty of systems and security B12/CS/01 / Consulting fir m to develop a revision of Component B: Improving t Consultant Qual FSL in relation to strengthe 2020-08-2 2020-09- 2020-10- 2020-11- 2020-12- 2021-12- IDA / 60850 he efficiency of Public Fina Post ification Selecti Open - National 30,000.00 0.00 Canceled ning credibility of MTFF and 0 10 24 23 28 23 ncial Management on to redefine principles of sta bility fund and re-determini ng special requirements Page 3 B12/CS/02 / Consulting fir m to develop amendments to the IBL: Component B: Improving t Consultant Qual (i) to expand the budget co 2020-08-2 2020-09- 2020-10- 2020-11- 2020-12- 2021-06- IDA / 60850 he efficiency of Public Fina Post ification Selecti Open - National 30,000.00 0.00 Canceled verage, i.e. to include ... 0 10 24 23 28 26 ncial Management on (ii) strengthen the IBL in rel ation to budget reporting, medium term planning and risk control and to regulate other issues.. B22/CS/028 / Consulting fir m to develop web portal for Component B: Improving t Consultant Qual 2020-11-1 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- treasury to enroll budget e IDA / 60850 he efficiency of Public Fina Post ification Selecti Open - National 120,000.00 0.00 Canceled 5 06 19 18 25 21 ntities accountant on GFMI ncial Management on S expense voucher and rep orting B11/CS/016 / Consulting s ervice to make an assessm Component B: Improving t Consultant Qual ent for implementing of var 2021-01-0 2021-01- 2021-03- 2021-04- 2021-05- 2021-11- IDA / 60850 he efficiency of Public Fina Post ification Selecti Open - National 43,200.00 0.00 Canceled iable cost allocation mecha 1 22 07 06 11 07 ncial Management on nism for pre-primary and s econdary education, and r evise the allocation metho dology. B13/CS/013 / Consulting fir Component B: Improving t Consultant Qual m to perform readiness ass 2021-06-0 2021-06- 2021-08- 2021-09- 2021-10- 2022-01- IDA / 60850 he efficiency of Public Fina Post ification Selecti Open - National 60,000.00 0.00 Canceled essment for Internal audit 1 22 05 04 09 31 ncial Management on Management Information S ystem (IAMIS) development B22/CS/029 / Consulting fir m to develop Gateway on B Component B: Improving t Consultant Qual 2020-04-0 2020-04- 2020-06- 2020-07- 2020-08- 2021-02- ank interface system to co IDA / 60850 he efficiency of Public Fina Post ification Selecti Open - National 30,000.00 0.00 Canceled 1 22 05 05 09 05 nnect with varies payment ncial Management on methods such as POS syst em, QR, Mobile, Kiosk syste m B22/CS/06 / Consulting fir m on development of modu Component B: Improving t Consultant Qual le on reporting and reconcil 2020-11-1 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- IDA / 60850 he efficiency of Public Fina Post ification Selecti Open - National 20,000.00 0.00 Canceled iation of accounts of budge 5 06 19 18 25 21 ncial Management on t entity’s at commercials b anks and its interface with Bank of Mongolia C11/CS/027 / National con sulting firm to conduct a su Consultant Qual Component C: Enhancing 2021-05-0 2021-05- 2021-07- 2021-08- 2021-09- 2022-01- rvey of public knowledge a IDA / 60850 Post ification Selecti Open - National 17,500.00 0.00 Canceled Financial Sector Stability 2 23 06 05 09 31 nd awareness of insurance on market and determine nee d for potential new insuran ce products. C4/CS/0029 / National con sulting firm to assist to revi Consultant Qual se “Accounting manual of Component C: Enhancing 2020-12-3 2021-01- 2021-03- 2021-04- 2021-05- 2021-11- IDA / 60850 Post ification Selecti Open - National 28,000.00 0.00 Canceled Non-bank financial instituti Financial Sector Stability 1 21 06 05 10 06 on ons” approved by Financial Regulatory Commission an d to compliance with intern ational standards D2/CS/00025 / Consulting f irm (1) to support the devel Component D: Strengtheni Consultant Qual 2020-07-0 2020-07- 2020-09- 2020-10- 2020-11- 2021-05- opment of content for publi IDA / 60850 ng of the Social Protection Post ification Selecti Open - National 20,000.00 0.00 Canceled 9 30 12 12 16 15 c awareness material in so System on cial welfare (newspaper, jo urnal , stork and others) D2/CS/25 / Consulting firm Component D: Strengtheni Consultant Qual (1) to support the develop 2020-06-2 2020-07- 2020-08- 2020-09- 2020-10- 2021-04- IDA / 60850 ng of the Social Protection Post ification Selecti Open - National 10,000.00 0.00 Canceled ment of content for public 2 13 26 25 30 28 System on awareness material (newsp aper, journal , stork and ot hers) D1/CS/039 / Develop meth odology on providing traini ng and testing services for Component D: Strengtheni Consultant Qual safety-net services such as 2020-04-2 2020-05- 2020-06- 2020-07- 2020-09- 2021-03- IDA / 60850 ng of the Social Protection Post ification Selecti Open - National 64,000.00 0.00 Canceled support training and social 5 16 29 29 02 01 System on work, psychological and he alth services and positive male role models for memb ers of poor households livi ng in the ger area D1/CS/038 / Develop meth odology on providing traini ng and testing services for Component D: Strengtheni Consultant Qual safety-net services such as 2020-11-2 2020-12- 2020-12- 2021-01- 2021-03- 2021-02- 2021-03- 2021-03- 2021-03- 2021-09- 2021-08- IDA / 60850 ng of the Social Protection Post ification Selecti Open - National 72,000.00 12,017.96 Completed support training and social 0 25 11 24 10 23 30 30 31 26 31 System on work, psychological and he alth services and positive male role models for memb ers of poor households livi ng in the ger area D1/CS/041 / National conc ultant company or NGO to Component D: Strengtheni Consultant Qual support the development o 2020-05-0 2020-05- 2020-07- 2020-08- 2020-09- 2021-03- IDA / 60850 ng of the Social Protection Post ification Selecti Open - National 28,000.00 0.00 Canceled f content for public awaren 1 22 05 04 08 07 System on ess material (newspaper, j ournal, short video, other p rograms, handouts, and br ochure) D1/CS/047 / English trainin Component D: Strengtheni Consultant Qual 2020-12-1 2020-12- 2020-12- 2021-02- 2021-03- 2021-03- 2021-02- 2021-04- 2021-04- 2021-10- 2021-11- IDA / 60850 Post Open - National 4,630.00 4,621.87 Completed g course for social welfare ng of the Social Protection ification Selecti 0 22 31 13 17 15 23 19 26 16 09 policy makers System on B13/CS/015 / Consulting fir Component B: Improving t Consultant Qual m to develop and impleme Under Impleme 2021-04-0 2021-04- 2021-06- 2021-07- 2021-08- 2022-02- IDA / 60840 he efficiency of Public Fina Post ification Selecti Open - National 124,100.00 0.00 nt an Internal audit Manag ntation 1 22 05 05 09 05 ncial Management on ement Information System (IAMIS) B22/CS/032 / National con sulting firm to develop a co mpiling guideline annual fi Component B: Improving t Consultant Qual 2021-02-0 2021-04- 2021-02- 2021-04- 2021-05- 2021-05- 2021-05- 2021-06- 2021-06- 2021-12- 2022-01- nance statistics compliance IDA / 60840 he efficiency of Public Fina Post ification Selecti Open - National 42,000.00 41,295.65 Completed 1 12 22 07 25 07 24 11 02 08 31 with GFSM 2014 and IPSAS ncial Management on and to provide support to p repare 2020 FY annual GF S through E-tailan and GFM IS v7 B22/CS/033 / Consulting fir m to develop E-learning to ols (knowlegde base syste Component B: Improving t Consultant Qual 2021-03-0 2021-04- 2021-03- 2021-05- 2021-06- 2021-06- 2021-07- 2021-07- 2021-07- 2022-01- 2021-11- m) for treasury officials and IDA / 60840 he efficiency of Public Fina Post ification Selecti Open - National 35,000.00 34,370.80 Completed 1 14 22 05 17 04 05 09 05 05 04 budget entities accountant ncial Management on s for better treasury servic es including payroll, financi al reporting and fiscal repo rting B4/CS/024 / Consulting fir m to conduct a historical a Component B: Improving t Consultant Qual 2021-02-1 2021-07- 2021-03- 2021-04- 2021-10- 2021-05- 2021-10- 2021-06- 2021-10- 2021-12- 2022-01- nalysis on public investmen IDA / 60840 he efficiency of Public Fina Post ification Selecti Open - National 40,000.00 27,381.58 Completed 5 09 08 21 08 21 08 25 08 22 10 t in Mongolia, create inform ncial Management on ation data base, produce re port on main findings D1/CS/41 / National consul ting company or NGO to su Component D: Strengtheni Consultant Qual pport the development of c 2021-03-0 2021-01- 2021-03- 2021-05- 2021-05- 2021-06- 2021-05- 2021-07- 2021-05- 2022-01- 2021-10- IDA / 60840 ng of the Social Protection Post ification Selecti Open - National 10,000.00 8,938.01 Completed ontent for public awarenes 1 25 22 05 13 04 14 09 14 05 20 System on s material (newspaper, jour nal, short video, other prog rams, handouts, and broch ure) D1/CS/049 / National cons ulting service firm or NGO t o developing an online lear Component D: Strengtheni Consultant Qual 2021-03-0 2021-03- 2021-05- 2021-06- 2021-07- 2022-01- ning content for social welf IDA / 60840 ng of the Social Protection Post ification Selecti Open - National 22,400.00 0.00 Canceled 1 22 05 04 09 05 are sector's human resourc System on es and its curriculum, video s, and handouts that enabl e social welfare organizatio ns and officials... D1/CS/050 / National cons ulting company or NGO to i ntroduce a Web-based syst Component D: Strengtheni Consultant Qual em for service process rep 2021-02-1 2021-10- 2021-03- 2021-04- 2022-02- 2021-05- 2022-03- 2021-06- 2022-03- 2021-12- IDA / 60840 ng of the Social Protection Post ification Selecti Open - National 50,000.00 44,147.21 Signed orting, internal monitoring, 0 26 03 16 25 16 10 20 10 17 System on and evaluation, establish a customer satisfaction surve y system for social welfare, labor, and social insurance organizations. D1/CS/051 / National Cons ulting firm or NGO to build Component D: Strengtheni Consultant Qual 2021-03-0 2021-07- 2021-03- 2021-05- 2021-08- 2021-06- 2021-09- 2021-07- 2021-09- 2022-01- 2022-01- capacity of selected aimag/ IDA / 60840 ng of the Social Protection Post ification Selecti Open - National 27,500.00 27,405.71 Completed 1 27 22 05 31 04 24 09 27 05 31 district’s Labor and Welfare System on Service Offices to apply qu ality management (ISO 900 1:2015) D1/CS/054 / National cons Component D: Strengtheni Consultant Qual ulting firm or NGO to devel 2021-04-0 2021-04- 2021-06- 2021-07- 2021-08- 2022-02- IDA / 60840 ng of the Social Protection Post ification Selecti Open - National 16,000.00 0.00 Canceled op the content of public aw 1 22 05 05 09 05 System on areness materials on soci al welfare reforms (2) C5/CS/019 / International c onsultancy firm to conduct analysis on current cash op Consultant Qual erating system and prepar Component C: Enhancing Open - Internatio 2021-04-0 2021-03- 2021-04- 2021-03- 2021-06- 2021-05- 2021-07- 2021-08- 2021-08- 2021-07- 2022-02- 2022-04- IDA / 60840 Post ification Selecti 120,000.00 109,956.95 Completed e technical and financial pr Financial Sector Stability nal 1 30 22 30 05 13 05 01 09 06 05 30 on oposals for optimizing effec tive cash management infr astructure, including IT sol utions and risk manageme nt. D2/CS/250 / National Cons ulting Service on supportin Component D: Strengtheni Consultant Qual 2020-06-0 2020-07- 2020-06- 2020-08- 2020-11- 2020-09- 2020-11- 2020-10- 2020-12- 2021-04- 2021-02- g the development of conte IDA / 60840 ng of the Social Protection Post ification Selecti Open - National 4,550.00 4,550.00 Completed 1 01 22 05 11 04 18 09 07 07 06 nt for public awareness ma System on terial (newspaper, journal, stork and others) D2/CS/045 / National cons ulting firm or NGO to devel op public awareness mate Component D: Strengtheni Consultant Qual rials for gradually building 2021-05-0 2021-05- 2021-07- 2021-08- 2021-09- 2022-03- IDA / 60840 ng of the Social Protection Post ification Selecti Open - National 16,000.00 0.00 Canceled social consensus on the pe 1 22 05 04 08 07 System on nsion reform needs and pri ncipals (newspaper, journa l, short video, other progra ms, handouts, and brochur e) (2) D2/CS/048 / National Cons ulting firm or NGO to devel Component D: Strengtheni Consultant Qual op and deliver training on 2021-04-2 2021-07- 2021-05- 2021-06- 2021-09- 2021-07- 2021-09- 2021-08- 2021-09- 2022-02- 2022-01- IDA / 60840 ng of the Social Protection Post ification Selecti Open - National 25,000.00 24,741.96 Completed quality management (ISO 9 0 27 11 24 06 24 30 28 30 24 31 System on 001:2015) for selected aim ag/district’s Social Insuranc e Departments C31/CS/001 / Consulting fir Consultant Qual Component C: Enhancing 2018-10-3 2021-07- 2018-11- 2019-01- 2021-12- 2019-02- 2022-01- 2019-03- 2022-01- 2019-09- m to develop the compens IDA / 60840 Post ification Selecti Open - National 245,600.00 123,459.82 Signed Financial Sector Stability 1 27 21 04 07 03 26 10 26 06 ation management softwar on e D1/CS/056 / National cons Component D: Strengtheni Consultant Qual ulting firm or NGO to devel 2021-08-0 2021-08- 2021-10- 2021-11- 2021-12- 2022-01- IDA / 60840 ng of the Social Protection Post ification Selecti Open - National 5,500.00 0.00 Canceled op the content of public aw 1 22 05 04 09 31 System on areness materials on social welfare reforms D1/CS/057 / National cons Component D: Strengtheni Consultant Qual ulting firm or NGO to devel 2021-09-0 2021-09- 2021-11- 2021-12- 2022-01- 2022-01- IDA / 60840 ng of the Social Protection Post ification Selecti Open - National 5,500.00 0.00 Canceled op the content of public aw 1 22 05 05 09 31 System on areness materials on soci al welfare reforms D1/CS/058 / National cons Component D: Strengtheni Consultant Qual ulting firm or NGO to devel 2021-09-1 2021-10- 2021-11- 2021-12- 2022-01- 2022-01- IDA / 60840 ng of the Social Protection Post ification Selecti Open - National 5,000.00 0.00 Canceled op the content of public aw 0 01 14 14 18 31 System on areness materials on soci al welfare reforms D1/CS/053 / National cons Component D: Strengtheni Consultant Qual ulting firm or NGO to devel 2021-03-2 2021-04- 2021-05- 2021-06- 2021-07- 2022-01- IDA / 60840 ng of the Social Protection Post ification Selecti Open - National 16,000.00 0.00 Canceled op the content of public aw 0 10 24 23 28 24 System on areness materials on soci al welfare reforms (1) D2/CS/050 / National cons ulting firm/NGO to develop Component D: Strengtheni Consultant Qual public awareness material 2021-07-2 2021-08- 2021-09- 2021-10- 2021-11- 2022-01- IDA / 60840 ng of the Social Protection Post ification Selecti Open - National 5,500.00 0.00 Canceled s for gradually building soci 0 10 23 23 27 31 System on al consensus on the pensio n reform needs and princip als (newspaper, short vide o etc) D2/CS/051 / National cons ulting firm/NGO to develop Component D: Strengtheni Consultant Qual public awareness materials 2021-08-0 2021-08- 2021-10- 2021-11- 2021-12- 2022-01- IDA / 60840 ng of the Social Protection Post ification Selecti Open - National 5,500.00 0.00 Canceled for gradually building social 1 22 05 04 09 31 System on consensus on the pension r eform needs and principals (newspaper, short video et c) D2/CS/052 / National cons ulting firm/NGO to develop Component D: Strengtheni Consultant Qual public awareness materials 2021-09-2 2021-10- 2021-11- 2021-12- 2022-01- 2022-01- IDA / 60840 ng of the Social Protection Post ification Selecti Open - National 5,000.00 0.00 Canceled for gradually building social 0 11 24 24 28 31 System on consensus on the pension r eform needs and principals (newspaper, short video et c) D2/CS/044 / National cons ulting firm or NGO to devel op public awareness mate Component D: Strengtheni Consultant Qual rials for gradually building 2021-03-2 2021-04- 2021-05- 2021-06- 2021-07- 2022-01- IDA / 60840 ng of the Social Protection Post ification Selecti Open - National 16,000.00 0.00 Canceled social consensus on the pe 0 10 24 23 28 24 System on nsion reform needs and pri ncipals (newspaper, journa l, short video, other progra ms, handouts, and brochur e) (1) D1/CS/052 / National cons ulting firm or NGO to devel Component D: Strengtheni Consultant Qual op online learning modules Pending Imple 2022-03-1 2022-03- 2022-05- 2022-06- 2022-07- 2023-01- IDA / 60840 ng of the Social Protection Post ification Selecti Open - National 40,000.00 0.00 for systematic and continu mentation 0 31 14 13 18 31 System on ous training of MLSP’s hum an resources in the social welfare sector D2/CS/042 / National cons ulting service firm or NGO t Component D: Strengtheni Consultant Qual o develop online learning Pending Imple 2022-03-1 2022-03- 2022-05- 2022-06- 2022-07- 2023-01- IDA / 60840 ng of the Social Protection Post ification Selecti Open - National 40,000.00 0.00 modules for systematic and mentation 0 31 14 13 18 14 System on continuous training of MLS P’s human resources in the social insurance sector B13/CS/014 / Consulting fir Component B: Improving t Consultant Qual 2021-01-0 2021-01- 2021-03- 2021-04- 2021-05- 2021-11- m to develop "Public sector IDA / 60850 he efficiency of Public Fina Post ification Selecti Open - National 50,000.00 0.00 Canceled 1 22 07 06 11 07 Internal audit midterm dev ncial Management on elopment strategy" B13/CS/14 / National cons Component B: Improving t Consultant Qual Pending Imple 2022-06-3 2022-07- 2022-09- 2022-10- 2022-11- 2023-05- ulting firm to develop draft IDA / 60840 he efficiency of Public Fina Post ification Selecti Open - National 50,000.00 0.00 mentation 0 21 03 03 07 06 law of internal audit ncial Management on D1/CS/60 / National consul ting firm or NGO to i) devel op a dynamic model (softw Component D: Strengtheni Consultant Qual are) for projecting mid and Pending Imple 2022-06-3 2022-07- 2022-09- 2022-10- 2022-11- 2023-05- IDA / 60840 ng of the Social Protection Post ification Selecti Open - National 15,000.00 0.00 long-term effects of social mentation 0 21 03 03 07 06 System on welfare and social insuranc e policies, and ii) organize capacity building training o f sector employees on this assessment model INDIVIDUAL CONSULTANTS Activity Reference No Invitation to Identif Loan / Credit Market Appro Contract Type Estimated A Actual Amo Process Stat Draft Negotiated C Contract Completio . / Description Component Review Type Method Terms of Reference ied/Selected Consu Signed Contract No. ach mount (US$) unt (US$) us ontract n ltant Planned Actual Planne Actual Planne Actual Planne Actual Planne Actual d d d d A1/CS/001 / National cons Component A: Strengtheni Individual Cons 2018-04-3 2018-05- 2018-06- 2018-06- 2018-07- 2018-06- 2018-08- 2018-06- 2019-08- 2019-10- ultant to build and update IDA / 60850 ng Macroeconomic and Fis Post Open 9,600.00 9,600.00 Completed ultant Selection 0 22 18 11 09 11 13 11 13 17 macroeconomic database cal Management A32/CS/007 / National con sultant on software/databa Component A: Strengtheni Individual Cons 2018-05-3 2018-05- 2018-07- 2018-07- 2018-08- 2018-07- 2018-09- 2018-07- 2019-05- se development updating a IDA / 60850 ng Macroeconomic and Fis Post Open 8,000.00 8,000.00 Terminated ultant Selection 1 22 19 25 09 25 13 25 11 nd maintaining Tax exempt cal Management ion recording system datab ase A32/CS/006 / National con Component A: Strengtheni sultant on software/databa Individual Cons 2018-05-3 2018-04- 2018-07- 2018-05- 2018-08- 2018-05- 2018-09- 2018-05- 2019-09- 2020-05- IDA / 60850 ng Macroeconomic and Fis Post Open 12,000.00 26,400.00 Completed se development to update ultant Selection 1 11 19 10 09 10 13 10 13 09 cal Management and maintain ODAMIS data base with new features A32/CS/005 / National con Component A: Strengtheni sultant on externally funde Individual Cons 2018-04-3 2018-04- 2018-06- 2018-05- 2018-07- 2018-05- 2018-08- 2018-05- 2019-08- 2019-05- IDA / 60850 ng Macroeconomic and Fis Post Open 24,000.00 24,000.00 Completed d projects medium-term fis ultant Selection 0 11 18 10 09 10 13 10 13 09 cal Management cal planning and policy dev elopment A32/CS/004 / Component Component A: Strengtheni Individual Cons 2018-03-3 2017-10- 2018-05- 2018-03- 2018-06- 2018-03- 2018-07- 2018-03- 2019-07- 2022-01- A3.2 coordinating consulta IDA / 60850 ng Macroeconomic and Fis Post Open 18,000.00 70,500.00 Completed ultant Selection 0 17 18 02 08 02 13 02 13 31 nt cal Management A1/CS/002 / National cons ultant to develop Dynamic Component A: Strengtheni stochastic general equilibri Individual Cons 2018-04-3 2018-05- 2018-06- 2018-07- 2018-08- 2019-08- IDA / 60850 ng Macroeconomic and Fis Post Open 9,000.00 0.00 Canceled um model (DSGE), which m ultant Selection 0 22 18 09 13 13 cal Management eet the needs of MoF and e valuate macroeconomic pol icies consistency A32/CS/003 / Consulting fir Component A: Strengtheni m (Software upgrade) to up 2018-06-2 2018-07- 2018-09- 2019-03- IDA / 60850 ng Macroeconomic and Fis Post Direct Selection Direct 25,000.00 0.00 Canceled grade the Official Develop 9 09 12 11 cal Management ment Assistance Monitoring Information System (ODAM IS). B31/CS/003 / National con sultant to research the syst ems used in the Ministry of Component B: Improving t Finance, to explore opportu Individual Cons 2018-04-3 2018-06- 2018-07- 2018-08- 2019-08- IDA / 60850 he efficiency of Public Fina Post Open 12,000.00 0.00 Canceled nities for identifying, integr ultant Selection 0 18 09 13 13 ncial Management ating and improving the int errelationships and relation ships of the overall environ ment, research the opportu nities C11/CS/007 / National con sultant to review and impro Component C: Enhancing Individual Cons 2018-06-3 2018-05- 2018-08- 2018-06- 2018-09- 2018-06- 2018-10- 2018-06- 2019-04- 2018-12- IDA / 60850 Post Open 7,200.00 7,200.00 Completed ve legal framework and infr Financial Sector Stability ultant Selection 0 09 18 19 08 19 13 19 11 28 astructure of capital marke t Component B: Improving t B22/CS/009 / Component Individual Cons 2018-03-3 2019-04- 2018-05- 2018-06- 2018-07- 2018-02- 2019-07- 2022-02- IDA / 60850 he efficiency of Public Fina Post Open 18,000.00 106,000.00 Completed B2 coordinating consultant ultant Selection 1 03 19 09 14 05 14 04 ncial Management B31/CS/001 / National con sultant to develop a compr ehensive documentation of Component B: Improving t information technology env Individual Cons 2018-04-3 2018-07- 2018-06- 2018-09- 2018-07- 2018-09- 2018-08- 2018-09- 2019-08- 2020-06- IDA / 60850 he efficiency of Public Fina Post Open 12,000.00 30,000.00 Completed ironments to improve the n ultant Selection 0 19 18 26 09 26 13 26 13 14 ncial Management etwork infrastructure and s ecurity equipment, infrastr ucture of the IT network, to improve the network capac ity of systems and security B22/CS/001 / National con Component B: Improving t sultant on managing the tr Individual Cons 2018-07-3 2018-10- 2018-09- 2018-10- 2018-10- 2018-10- 2018-11- 2018-10- 2019-11- 2019-09- IDA / 60850 he efficiency of Public Fina Post Open 18,000.00 18,000.00 Completed ansition to IPSAS and GFS c ultant Selection 1 10 18 29 09 29 13 29 13 30 ncial Management ompliance, integrating GFS with BPIS C11/CS/006 / National con sultant to review and impro Component C: Enhancing Individual Cons 2018-05-3 2018-04- 2018-07- 2018-06- 2018-08- 2018-06- 2018-09- 2018-06- 2019-03- 2018-12- ve legal framework of insur IDA / 60850 Post Open 9,000.00 9,000.00 Completed Financial Sector Stability ultant Selection 1 20 19 19 09 18 13 18 12 21 ance industry and make a mendments to relevant law s and insurance industry re gulations Page 4 B21/CS/004 / International Component B: Improving t Individual Cons 2018-10-3 2018-12- 2019-01- 2019-02- 2019-03- consultant to carry out the IDA / 60850 he efficiency of Public Fina Post Open 8,800.00 0.00 Canceled ultant Selection 1 19 09 13 15 quality control on audit ncial Management C11/CS/011 / Component Component C: Enhancing Individual Cons 2018-03-3 2017-10- 2018-05- 2018-02- 2018-06- 2018-02- 2018-07- 2018-02- 2019-07- IDA / 60850 Post Open 18,000.00 70,900.00 Terminated C1-C3 Coordinating consult Financial Sector Stability ultant Selection 1 16 19 23 09 23 14 23 14 ant B4/CS/003 / International c Component B: Improving t Individual Cons 2018-07-3 2018-06- 2018-09- 2018-08- 2018-10- 2018-08- 2018-11- 2018-08- 2019-01- 2019-03- onsultant to develop metho IDA / 60850 he efficiency of Public Fina Post Open 50,200.00 50,000.00 Completed ultant Selection 1 04 18 30 09 30 13 30 12 11 dology of project evaluatio ncial Management n C4/CS/003 / International c onsultant to draft the existi Component C: Enhancing Individual Cons 2018-05-3 2018-07- 2018-07- 2018-08- 2018-08- 2018-08- 2018-09- 2018-08- 2018-10- 2018-10- IDA / 60850 Post Open 25,100.00 19,700.00 Completed ng Law on Legal Status of F Financial Sector Stability ultant Selection 1 25 19 27 09 29 13 29 13 30 inancial Regulatory Commi ssion C5/CS/007 / International c onsultant to develop rules Component C: Enhancing Individual Cons 2018-05-3 2018-07- 2018-08- 2018-09- 2019-03- IDA / 60850 Post Open 57,500.00 0.00 Canceled and standards specified in t Financial Sector Stability ultant Selection 1 19 09 13 12 he Credit information law C5/CS/003 / National cons ultant to work with/assist t he international consultant Component C: Enhancing Individual Cons 2018-05-3 2018-04- 2018-07- 2018-05- 2018-08- 2018-05- 2018-09- 2018-12- 2019-03- 2019-01- IDA / 60850 Post Open 16,600.00 14,000.00 Completed to establish web based ma Financial Sector Stability ultant Selection 1 05 19 03 09 15 13 19 12 16 cro-micro-financial databas e system and capacity buil ding among FSC staff C5/CS/001 / International c onsultant to establish web Component C: Enhancing Individual Cons 2018-05-3 2018-04- 2018-07- 2018-11- 2018-08- 2018-11- 2018-09- 2018-11- 2019-03- 2019-08- based macro-micro-financi IDA / 60850 Post Open 45,000.00 44,400.00 Completed Financial Sector Stability ultant Selection 1 05 19 10 09 16 13 09 12 02 al database system and ca pacity building among FSC staff C4/CS/001 / International c onsultant to conduct a nee Component C: Enhancing Individual Cons 2018-04-3 2018-04- 2018-06- 2018-07- 2018-07- 2018-08- 2018-08- 2018-08- 2018-09- 2018-10- IDA / 60850 Post Open 25,100.00 20,950.00 Completed ds assessment of the existi Financial Sector Stability ultant Selection 0 20 18 25 09 13 13 13 12 20 ng law on Legal Status of F RC C5/CS/005 / International c Component C: Enhancing Individual Cons 2018-07-3 2018-04- 2018-09- 2018-05- 2018-10- 2018-05- 2018-11- 2018-05- 2018-12- 2018-12- onsultant for microeconomi IDA / 60850 Post Open 46,000.00 42,800.00 Completed Financial Sector Stability ultant Selection 1 05 18 23 09 23 13 23 13 24 cs research purpose C4/CS/002 / National cons ultant to work with/assist t Component C: Enhancing Individual Cons 2018-05-3 2018-07- 2018-08- 2018-09- 2018-10- he international consultant IDA / 60850 Post Open 2,000.00 0.00 Canceled Financial Sector Stability ultant Selection 1 19 09 13 13 to conduct a needs assess ment of the existing law on Legal Status of FRC C5/CS/008 / Component C Component C: Enhancing Individual Cons 2018-03-3 2017-10- 2018-05- 2018-06- 2018-07- 2019-07- IDA / 60850 Post Open 18,000.00 0.00 Canceled 5 Coordinating Consultant Financial Sector Stability ultant Selection 1 16 19 09 14 14 C5/CS/006 / International c onsultant on designing anal ytical and operational fram Component C: Enhancing Individual Cons 2018-07-3 2018-04- 2018-09- 2018-11- 2018-10- 2018-11- 2018-11- 2018-11- 2018-12- 2019-12- ework for macro prudential IDA / 60850 Post Open 42,000.00 39,800.00 Completed Financial Sector Stability ultant Selection 1 20 18 06 09 23 13 19 13 09 policy and learn from inter national best practices of macro prudential policy im plementation to define ope rational framework D2/CS/009 / International c onsultant on establishing t Component D: Strengtheni he ground rules for occupat Individual Cons 2018-07-3 2018-09- 2018-10- 2018-11- 2019-02- IDA / 60850 ng of the Social Protection Post Open 38,000.00 0.00 Canceled ional and individual pensio ultant Selection 1 18 09 13 11 System n savings arrangements, in cluding oversight, tax treat ment, and institutional arra ngements through D1/CS/002 / National cons ultant to work with/assist t Component D: Strengtheni he international consultant Individual Cons 2018-05-3 2018-07- 2018-07- 2018-08- 2018-09- 2019-01- IDA / 60850 ng of the Social Protection Post Open 16,000.00 0.00 Canceled on legal framework enablin ultant Selection 1 17 19 09 13 11 System g consolidation of the soci al welfare pensions, benefit s, allowances and services D1/CS/010 / National cons Component D: Strengtheni Individual Cons 2018-04-3 2018-06- 2018-07- 2018-08- 2018-12- ultant/s on assessment of s IDA / 60850 ng of the Social Protection Post Open 6,000.00 0.00 Canceled ultant Selection 0 18 09 13 11 elect social welfare benefit System s D2/CS/003 / International c Component D: Strengtheni Individual Cons 2018-05-3 2018-07- 2018-08- 2018-09- 2018-12- onsultant on long term act IDA / 60850 ng of the Social Protection Post Open 58,000.00 0.00 Canceled ultant Selection 1 19 09 13 12 uarial projections on propo System sed design options D2/CS/010 / National cons ultant to work with/assist t he international consultant Component D: Strengtheni on establishing the ground Individual Cons 2018-06-3 2018-08- 2018-09- 2018-10- 2019-04- IDA / 60850 ng of the Social Protection Post Open 8,000.00 0.00 Canceled rules for occupational and i ultant Selection 0 18 08 13 11 System ndividual pension savings a rrangements, including ove rsight, tax treatment, and i nstitutional arrangements t hrough E/CS/002 / Employment of Component E: Project Man 2018-05-3 2018-06- 2018-08- 2019-08- IDA / 60850 Prior Direct Selection Direct 6,480.00 0.00 Canceled PIU core staff: Procurement agement and Monitoring 1 10 14 14 specialist E/CS/001 / Employment of Component E: Project Man 2018-05-3 2020-04- 2018-06- 2018-08- 2019-08- IDA / 60850 Prior Direct Selection Direct 9,000.00 0.00 Canceled PIU core staff: Project Coor agement and Monitoring 1 30 10 14 14 dinator E/CS/003 / Employment of Component E: Project Man Individual Cons 2018-03-3 2018-08- 2018-05- 2018-11- 2018-06- 2019-12- 2018-07- 2018-11- 2019-07- PIU core staff: Financial Ma IDA / 60850 Prior Open 21,600.00 21,600.00 Signed agement and Monitoring ultant Selection 1 13 19 01 09 10 14 01 14 nagement Specialist E/CS/004 / Employment of Component E: Project Man 2018-05-3 2020-04- 2018-06- 2018-08- 2019-08- PIU core staff: Monitoring a IDA / 60850 Prior Direct Selection Direct 6,480.00 0.00 Canceled agement and Monitoring 1 30 10 14 14 nd Evaluation specialist E/CS/005 / Employment of Component E: Project Man 2018-05-3 2018-06- 2018-08- 2019-08- IDA / 60850 Prior Direct Selection Direct 5,400.00 0.00 Canceled PIU core staff: Procurement agement and Monitoring 1 10 14 14 Assistant A1/CS/003 / National cons Component A: Strengtheni ultant to develop Computa Individual Cons 2018-05-3 2018-05- 2018-07- 2018-06- 2018-08- 2018-06- 2018-09- 2018-06- 2019-09- 2019-06- IDA / 60850 ng Macroeconomic and Fis Post Open 18,000.00 18,000.00 Completed ble general equilibrium (CG ultant Selection 1 22 19 06 09 06 13 06 13 05 cal Management E) model and forecasting m acroeconomic indicators A1/CS/004 / National cons Component A: Strengtheni ultant to develop Financial Individual Cons 2018-05-3 2018-05- 2018-07- 2018-09- 2018-08- 2018-09- 2018-09- 2018-09- 2019-09- 2019-09- IDA / 60850 ng Macroeconomic and Fis Post Open 9,000.00 9,000.00 Completed programming macroecono ultant Selection 1 22 19 25 09 25 13 25 13 13 cal Management mic framework and forecas ting macroeconomic indica tors A1/CS/007 / National cons ultant to undertake evaluat Component A: Strengtheni Individual Cons 2018-05-3 2018-07- 2018-08- 2018-09- 2019-09- ions of linkage between ec IDA / 60850 ng Macroeconomic and Fis Post Open 9,000.00 0.00 Canceled ultant Selection 1 19 09 13 13 onomic growth, employme cal Management nt and poverty rate and ma ke policy A2/CS/002 / National cons ultant to develop and form Component A: Strengtheni Individual Cons 2018-05-3 2018-05- 2018-06- 2018-05- 2018-06- 2018-05- 2018-08- 2018-05- 2019-08- 2018-10- ulate revisions of the tax p IDA / 60850 ng Macroeconomic and Fis Post Direct 24,000.00 22,800.00 Completed ultant Selection 0 24 09 25 30 25 04 25 04 25 ackage laws: Personal inco cal Management me tax law in accordance with the Law on Legislation Acts A2/CS/001 / National cons ultant to develop and form Component A: Strengtheni Individual Cons 2018-05-3 2018-05- 2018-06- 2018-05- 2018-07- 2018-05- 2018-08- 2018-05- 2019-08- 2018-10- ulate revisions of the tax p IDA / 60850 ng Macroeconomic and Fis Post Direct 24,000.00 18,000.00 Completed ultant Selection 1 24 10 25 01 25 05 25 05 24 ackage laws: General Taxat cal Management ion Law in accordance with the Law on Legislation Acts A2/CS/003 / National cons ultant to develop and form Component A: Strengtheni Individual Cons 2018-05-2 2018-05- 2018-06- 2018-05- 2018-06- 2018-05- 2018-08- 2018-05- 2019-08- 2018-10- ulate revisions of the tax p IDA / 60850 ng Macroeconomic and Fis Post Direct 24,000.00 21,000.00 Completed ultant Selection 9 24 08 25 29 25 03 25 03 24 ackage laws: Corporate Inc cal Management ome Tax Law in accordanc e with the Law on Legislati on Acts A2/CS/012 / National junior consultant to make an asse Component A: Strengtheni Individual Cons 2018-06-3 2018-08- 2018-09- 2018-10- 2019-10- ssment and to develop a pr IDA / 60850 ng Macroeconomic and Fis Post Open 6,000.00 0.00 Canceled ultant Selection 0 18 08 13 13 oposal to introduce integra cal Management ted tax file number (used f or receiving public services ) A2/CS/011 / National cons ultant to make an assessm Component A: Strengtheni Individual Cons 2018-06-2 2018-08- 2018-09- 2018-10- 2019-10- ent and to develop a propo IDA / 60850 ng Macroeconomic and Fis Post Open 30,000.00 0.00 Canceled ultant Selection 9 17 07 12 12 sal to introduce integrated cal Management tax file number (used for re ceiving public services) A2/CS/010 / National cons ultant to make an assessm Component A: Strengtheni ent on existing structure an Individual Cons 2018-05-3 2018-07- 2018-08- 2018-09- 2019-09- IDA / 60850 ng Macroeconomic and Fis Post Open 27,000.00 0.00 Canceled d to develop financial mod ultant Selection 1 19 09 13 13 cal Management eling for mega projects incl uding budget data analysis and collection. A31/CS/007 / Component c Component A: Strengtheni oordinating consultant: co Individual Cons 2018-04-0 2018-05- 2018-06- 2018-07- 2019-07- IDA / 60850 ng Macroeconomic and Fis Post Open 18,000.00 0.00 Canceled mponent # A3 (Debt Mana ultant Selection 9 28 18 23 23 cal Management gement Division, Financial Policy Department) B11/CS/010 / National tech nical consultant to support BPIS sustainability at the lo Component B: Improving t Individual Cons 2018-04-3 2018-05- 2018-05- 2018-05- 2018-05- 2018-05- 2018-07- 2018-05- 2019-07- 2019-05- cal government level, oper IDA / 60850 he efficiency of Public Fina Post Direct 24,000.00 24,000.00 Completed ultant Selection 0 23 10 23 31 23 05 23 05 22 ation at central governmen ncial Management t level including end-users' training and to make an as sessment of BPIS further te chnical needs. B11/CS/011 / National juni or functional consultant to support BPIS sustainability Component B: Improving t Individual Cons 2018-04-3 2018-05- 2018-05- 2018-05- 2018-05- 2018-05- 2018-07- 2018-05- 2019-07- 2019-05- at the local government lev IDA / 60850 he efficiency of Public Fina Post Direct 9,600.00 9,600.00 Completed ultant Selection 0 23 10 23 31 23 05 23 05 22 el, operation at central gov ncial Management ernment level including en d-users' training and to ma ke an assessment of BPIS f urther functional needs. B21/CS/002 / National con sultant on 1. In cooperation with the international cons Component B: Improving t ultant to finalize the guideli Individual Cons 2018-04-3 2018-04- 2018-06- 2018-05- 2018-07- 2018-05- 2018-08- 2018-05- 2019-08- 2019-06- IDA / 60850 he efficiency of Public Fina Post Open 24,000.00 24,000.00 Completed ne, 2. Produce the accounti ultant Selection 0 26 18 29 09 29 13 29 13 24 ncial Management ng methodology for public sector consolidated financi al reporting, 3. produce mi d-term plan, 4. review acco unting glossary B21/CS/003 / National con sultant on 1.Assisting the i nternational and national c Component B: Improving t Individual Cons 2018-04-3 2018-04- 2018-06- 2018-05- 2018-07- 2018-05- 2018-08- 2018-05- 2019-08- 2019-06- onsultants to the guideline IDA / 60850 he efficiency of Public Fina Post Open 12,000.00 12,000.00 Completed ultant Selection 0 26 18 29 09 29 13 29 13 17 and regulations, 2. assist to ncial Management produce mid-term plan, 3. producing the accounting g lossary in English and Mon golian. B21/CS/006 / National con sultant to review translatio Component B: Improving t ns of IPSAS from English int Individual Cons 2018-12-2 2019-01- 2019-01- 2019-02- 2019-08- IDA / 60850 he efficiency of Public Fina Post Direct 4,200.00 0.00 Canceled o Mongolian as 2017 IPSAS ultant Selection 4 03 24 28 27 ncial Management 32-40 from English into Mo ngolian and revised the tra nslation of IPSAS 1-31 as at 2011 B22/CS/003 / National con sultant for Integration of ex Component B: Improving t isting systems /GFMIS, BPIS Individual Cons 2018-07-3 2018-04- 2018-09- 2018-04- 2018-10- 2018-04- 2018-11- 2018-04- 2019-11- 2019-09- IDA / 60850 he efficiency of Public Fina Post Open 18,000.00 9,000.00 Completed , E-Balance/ and prepare te ultant Selection 1 11 18 30 09 30 13 30 13 14 ncial Management chnical requirements for de velopment of reporting syst em in line with GFS 2014 B22/CS/002 / National con sultant on gap analysis to i Component B: Improving t Individual Cons 2018-07-3 2018-06- 2018-09- 2018-08- 2018-10- 2018-08- 2018-11- 2018-08- 2019-11- dentify the implementation IDA / 60850 he efficiency of Public Fina Post Open 18,000.00 18,000.00 Terminated ultant Selection 1 22 18 03 09 03 13 03 13 status of GFS 2014 and int ncial Management egration plan for budget ex ecution reports B31/CS/005 / National con sultant to monitor and man age receiving calls from ev Component B: Improving t ery Treasury department e Individual Cons 2018-05-3 2018-07- 2018-07- 2018-10- 2018-08- 2018-10- 2018-09- 2018-10- 2019-09- 2019-10- IDA / 60850 he efficiency of Public Fina Post Open 7,000.00 7,000.00 Completed mployees that are located ultant Selection 1 20 19 17 09 17 13 17 13 16 ncial Management around the country to perfo rm maintenance and stabili ty check on network enviro nment for Glass Account an d other systems. B31/CS/004 / National con sultant to optimize and ma nage receiving calls from e Component B: Improving t very Treasury department Individual Cons 2018-05-3 2018-07- 2018-07- 2018-09- 2018-08- 2018-09- 2018-09- 2018-09- 2019-09- 2021-03- IDA / 60850 he efficiency of Public Fina Post Open 7,000.00 17,500.00 Completed employees that are located ultant Selection 1 19 19 18 09 18 13 18 13 20 ncial Management around the country to perfo rm maintenance and invest igation into raised issues, a pplications that are respon sible for Glass Account etc. C11/CS/001 / National con sultant to improve the legal Component C: Enhancing Individual Cons 2018-05-3 2018-05- 2018-06- 2018-05- 2018-07- 2018-05- 2018-08- 2018-05- 2019-02- 2018-10- framework of banking sect IDA / 60850 Post Direct 9,000.00 9,000.00 Completed Financial Sector Stability ultant Selection 1 13 10 14 01 14 05 14 01 18 or and draft the bank recap italization law and NPL stra tegy. C11/CS/003 / National con sultant Senior Expert to rev Component C: Enhancing Individual Cons 2018-04-3 2018-05- 2018-05- 2018-07- 2019-01- IDA / 60850 Post Direct 12,000.00 0.00 Canceled iew and amend the Currenc Financial Sector Stability ultant Selection 0 10 31 05 01 y Settlement law and Forei gn Exchange Coordinating Act A2/CS/004 / National cons ultant on public awareness Component A: Strengtheni Individual Cons 2018-04-3 2018-06- 2018-07- 2018-08- 2019-08- activities including media c IDA / 60850 ng Macroeconomic and Fis Post Open 12,000.00 0.00 Canceled ultant Selection 0 18 09 13 13 overage on the tax policy r cal Management eform including public disc ussions on tax reforms A2/CS/005 / National cons ultant to translate the BEPS Component A: Strengtheni (Base Erosion and Profit Shi Individual Cons 2018-05-3 2018-07- 2018-08- 2018-09- 2019-09- IDA / 60850 ng Macroeconomic and Fis Post Open 18,000.00 0.00 Canceled fting) related tax policy legi ultant Selection 1 19 09 13 13 cal Management slation, policy documents a nd to organize local trainin g to advocate the approved tax package law A2/CS/006 / National cons ultant to translate the Glob Component A: Strengtheni al Forum related tax policy Individual Cons 2018-05-3 2018-07- 2018-08- 2018-09- 2019-09- IDA / 60850 ng Macroeconomic and Fis Post Open 18,000.00 0.00 Canceled legislation, policy documen ultant Selection 1 19 09 13 13 cal Management ts and to organize local trai ning to advocate the appro ved tax package law A2/CS/07 / National consul Component A: Strengtheni tant on broadening the tax Individual Cons 2018-06-2 2018-07- 2018-07- 2018-09- 2019-03- IDA / 60850 ng Macroeconomic and Fis Post Direct 18,000.00 0.00 Canceled base and reducing the sha ultant Selection 9 09 30 03 02 cal Management dow economy through the t ax systems A2/CS/007 / National consil Component A: Strengtheni tant on broadening the tax Individual Cons 2018-04-3 2018-06- 2018-07- 2018-08- 2019-08- IDA / 60850 ng Macroeconomic and Fis Post Open 18,000.00 0.00 Canceled base and reducing the sha ultant Selection 0 18 09 13 13 cal Management dow economy through the t ax systems A2/CS/008 / National junior Component A: Strengtheni consultant on broadening t Individual Cons 2018-04-3 2018-06- 2018-07- 2018-08- 2019-08- IDA / 60850 ng Macroeconomic and Fis Post Open 6,000.00 0.00 Canceled he tax base and reducing t ultant Selection 0 18 09 13 13 cal Management he shadow economy throu gh the tax systems A31/CS/001 / National con sultant to improve and upd ate the debt management l Component A: Strengtheni aw and designing annual re Individual Cons 2018-06-2 2018-08- 2018-09- 2018-10- 2019-10- IDA / 60850 ng Macroeconomic and Fis Post Open 18,000.00 0.00 Canceled port (or section of a wider r ultant Selection 9 17 07 12 12 cal Management eport) contains an assessm ent of how the government activities have complied wi th the government's docu mented and approved MTD A31/CS/002 / National con S. sultant on improving the pr eparation of the Medium Te Component A: Strengtheni Individual Cons 2018-06-2 2018-08- 2018-09- 2018-10- 2019-10- rm Debt Management Strat IDA / 60850 ng Macroeconomic and Fis Post Open 12,000.00 0.00 Canceled ultant Selection 9 17 07 12 12 egy for proper monitoring a cal Management nd control of risks. The con sultant will develop compre hensive analysis of costs a nd risks. A31/CS/003 / National con sultant on improving the pr eparation of the Medium Te Component A: Strengtheni rm Debt Management Strat Individual Cons 2018-06-2 2018-08- 2018-09- 2018-10- 2019-10- IDA / 60850 ng Macroeconomic and Fis Post Open 12,000.00 0.00 Canceled egy. The consultant will foc ultant Selection 9 17 07 12 12 cal Management us on the external and dom estic market analysis and d evelop risk analysis for the on-lending loan, governme nt guarantees. A31/CS/004 / National con sultant on improving the pr eparation of the Medium Te Component A: Strengtheni Individual Cons 2018-06-2 2018-07- 2018-07- 2018-09- 2019-03- rm Debt Management Strat IDA / 60850 ng Macroeconomic and Fis Post Direct 4,000.00 0.00 Canceled ultant Selection 9 09 30 03 02 egy. The consultant will reg cal Management ister the government debt data in the system and mai ntain the system. A31/CS/005 / National con sultant to validate DMFAS d atabase and introduce new Component A: Strengtheni debt statistics standard co Individual Cons 2018-06-2 2018-08- 2018-09- 2018-10- 2019-10- IDA / 60850 ng Macroeconomic and Fis Post Open 18,000.00 0.00 Canceled mpatible with Balance of p ultant Selection 9 17 07 12 12 cal Management ayment 6 and Government Finance statistics 2011 fro m IMF and the DMFAS proc edures manual. The consult ant will be admin for DMFA A31/CS/006 / National con S. sultant to validate DMFAS d atabase and introduce new Component A: Strengtheni debt statistics standard co Individual Cons 2018-06-2 2018-07- 2018-08- 2018-08- 2018-09- 2018-08- 2018-10- 2018-08- 2019-10- 2020-02- IDA / 60850 ng Macroeconomic and Fis Post Open 8,000.00 23,400.00 Completed mpatible with Balance of p ultant Selection 9 23 17 02 07 02 12 02 12 01 cal Management ayment 6 and Government Finance Statistics 2011 fro m IMF and the DMFAS proc edures manual. The consult ant will focus on IT perspec A32/CS/01 / National cons tive. ultant (Software developm ent): -Develop project portf Component A: Strengtheni olio management software Individual Cons 2018-10-3 2018-11- 2018-11- 2018-12- 2019-01- 2019-07- IDA / 60850 ng Macroeconomic and Fis Post Direct 25,000.00 0.00 Canceled to enable project disburse ultant Selection 1 21 10 01 05 04 cal Management ment projection and trackin g, improve reviewing proce dure and recording of loan disbursement to consolidat e in budget expenditure Page 5 A32/CS/001 / National con sultant (Software developm ent): -Develop project portfolio Component A: Strengtheni Individual Cons 2018-06-3 2018-08- 2018-09- 2018-10- 2019-04- management software to e IDA / 60850 ng Macroeconomic and Fis Post Open 25,000.00 0.00 Canceled ultant Selection 0 18 08 13 11 nable project disbursement cal Management projection and tracking, im prove reviewing procedure and recording of loan disbu rsement to consolidate in b udget expenditure B11/CS/003 / National seni or consultant to make an a ssessment on shifting to m Component B: Improving t echanism to finance some Individual Cons 2018-06-2 2018-08- 2018-09- 2018-10- 2019-10- IDA / 60850 he efficiency of Public Fina Post Open 18,000.00 0.00 Canceled of the operating and resear ultant Selection 9 17 07 12 12 ncial Management ch expenditures from reven ues earned by research ins titutions, vocational educat ion institutions and cultural institutions B11/CS/005 / National juni or consultant to assess the existing documents on syst Component B: Improving t Individual Cons 2018-05-3 2018-07- 2018-08- 2018-09- 2019-09- em of staffing and wages/s IDA / 60850 he efficiency of Public Fina Post Open 6,000.00 0.00 Canceled ultant Selection 1 19 09 13 13 alaries to define the resour ncial Management ces and to develop a propo sal on improvement of appr opriate mechanism for plan ning B11/CS/008 / National con sultant (leader) to support BPIS sustainability at the lo Component B: Improving t cal government level, oper Individual Cons 2018-06-2 2018-07- 2018-07- 2018-09- 2019-09- IDA / 60850 he efficiency of Public Fina Post Direct 15,600.00 0.00 Canceled ation at central governmen ultant Selection 9 09 30 03 03 ncial Management t level including end-users' training and to make an as sessment of BPIS further fu nctional and technical need s. B12/CS/002 / National con sultant to develop amendm ents to the IBL: i. to expand Component B: Improving t the budget coverage, i.e. t Individual Cons 2018-10-3 2018-12- 2019-01- 2019-02- 2020-02- IDA / 60850 he efficiency of Public Fina Post Open 30,000.00 0.00 Canceled o include un-reported budg ultant Selection 1 19 09 13 13 ncial Management et relations such as PPP, off -budget spending, governm ent liabilities and future pe nsion fund and ii. strengthe n the IBL etc, B12/CS/003 / National con sultant to continue instituti Component B: Improving t Individual Cons 2018-05-3 2018-07- 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- 2018-07- 2019-08- onalization of Financial Pro IDA / 60850 he efficiency of Public Fina Post Direct 24,000.00 21,600.00 Terminated ultant Selection 1 20 10 23 01 23 05 23 05 gramming and Policy (FPP) ncial Management method focused on moneta ry and fiscal sectors B12/CS/006 / National juni or consultant to make an a Component B: Improving t ssessment of current statis Individual Cons 2018-08-3 2018-09- 2018-10- 2018-11- 2019-05- IDA / 60850 he efficiency of Public Fina Post Direct 3,000.00 0.00 Canceled tical reporting system of M ultant Selection 1 10 01 05 04 ncial Management ongolia in the context of bu dget planning, identificatio n of further needs for intro ducing GFS 2014 B13/CS/001 / National con sultant to finalize the Inter Component B: Improving t nal Audit Law draft for appr Individual Cons 2018-08-3 2018-10- 2018-11- 2018-12- 2019-12- IDA / 60850 he efficiency of Public Fina Post Open 24,000.00 0.00 Canceled oval by the parliament and ultant Selection 1 19 09 14 14 ncial Management prepare and update rules a nd regulations from the leg al perspective related to th e Internal Audit Law B13/CS/002 / National con sultant to finalize the Inter nal Audit Law draft for appr Component B: Improving t oval by the parliament and Individual Cons 2018-08-3 2018-10- 2018-11- 2018-12- 2019-12- IDA / 60850 he efficiency of Public Fina Post Open 18,000.00 0.00 Canceled prepare and update rules a ultant Selection 1 19 09 14 14 ncial Management nd regulations from the eco nomic perspective and con duct nessesary researches related with the legal draft s. B13/CS/04 / National cons ultant to introduce a compr Component B: Improving t ehensive Internal Audit Sof Individual Cons 2018-07-3 2018-08- 2018-08- 2018-10- 2019-04- IDA / 60850 he efficiency of Public Fina Post Direct 12,000.00 0.00 Canceled tware with an Integrated R ultant Selection 1 10 31 05 03 ncial Management eporting System and a Dat abase: - Develop product st ory - Audit process analysis B13/CS/004 / National con sultant to introduce a comp rehensive Internal Audit So Component B: Improving t Individual Cons 2018-07-3 2018-09- 2018-10- 2018-11- 2019-11- ftware with an Integrated R IDA / 60850 he efficiency of Public Fina Post Open 12,000.00 0.00 Canceled ultant Selection 1 18 09 13 13 eporting System and a Dat ncial Management abase: - Develop product story - Audit process analysis B13/CS/05 / National cons ultant to introduce a compr Component B: Improving t ehensive Internal Audit Sof Individual Cons 2018-09-2 2018-10- 2018-10- 2018-12- 2019-06- IDA / 60850 he efficiency of Public Fina Post Direct 12,000.00 0.00 Canceled tware with an Integrated R ultant Selection 8 08 29 03 01 ncial Management eporting System and a Dat abase: - Develop design/bl ueprint of the Internal audit software B13/CS/005 / National con sultant to introduce a comp rehensive Internal Audit So Component B: Improving t Individual Cons 2018-07-3 2018-09- 2018-10- 2018-11- 2019-11- ftware with an Integrated R IDA / 60850 he efficiency of Public Fina Post Open 12,000.00 0.00 Canceled ultant Selection 1 18 09 13 13 eporting System and a Dat ncial Management abase: - Develop design/blueprint of the Internal audit softwa re B13/CS/06 / National cons ultant to introduce a compr ehensive Internal Audit Sof Component B: Improving t Individual Cons 2018-09-2 2018-10- 2018-10- 2018-10- 2018-12- 2019-06- tware with an Integrated R IDA / 60850 he efficiency of Public Fina Post Direct 12,000.00 0.00 Canceled ultant Selection 8 01 08 29 03 01 eporting System and a Dat ncial Management abase: - Develop system sp ecifications according to th e product story and audit p rocess analysis B13/CS/006 / National con sultant to introduce a comp rehensive Internal Audit So Component B: Improving t ftware with an Integrated R Individual Cons 2018-07-3 2018-09- 2018-10- 2018-11- 2019-11- IDA / 60850 he efficiency of Public Fina Post Open 12,000.00 0.00 Canceled eporting System and a Dat ultant Selection 1 18 09 13 13 ncial Management abase: - Develop system specificat ions according to the produ ct story and audit process analysis B13/CS/10 / National cons ultant responsible for contr Component B: Improving t Individual Cons 2018-10-3 2019-06- 2018-11- 2019-06- 2018-12- 2019-06- 2019-01- 2019-06- 2019-07- 2019-12- act management, coordina IDA / 60850 he efficiency of Public Fina Post Direct 12,000.00 12,000.00 Completed ultant Selection 1 27 10 27 01 27 05 27 04 31 tion of the consulting firm ( ncial Management risk management system d evelopment) B13/CS/010 / National con sultant responsible for cont Component B: Improving t Individual Cons 2018-11-3 2019-01- 2019-02- 2019-03- 2020-03- ract management, coordin IDA / 60850 he efficiency of Public Fina Post Open 12,000.00 0.00 Canceled ultant Selection 0 18 08 15 14 ation of the consulting firm ncial Management (risk management system development) B13/CS/08 / National cons ultant to work with the con sulting firm on: -Developm Component B: Improving t Individual Cons 2018-11-3 2018-12- 2018-12- 2019-02- 2019-08- ent and implementation of IDA / 60850 he efficiency of Public Fina Post Direct 9,000.00 0.00 Canceled ultant Selection 0 10 31 04 03 the internal audit planning, ncial Management performance and reporting software -Develop consolid ated data system of intern al audit and test the syste mB13/CS/008 / National con sultant to work with the co nsulting firm on: Component B: Improving t -Development and implem Individual Cons 2018-08-3 2018-10- 2018-11- 2018-12- 2019-06- IDA / 60850 he efficiency of Public Fina Post Open 9,000.00 0.00 Canceled entation of the internal aud ultant Selection 1 19 09 14 12 ncial Management it planning, performance a nd reporting software -Develop consolidated data system of internal audit an d test the system B21/CS/001 / National con Component B: Improving t sultant on revising the regu Individual Cons 2018-06-3 2018-08- 2018-09- 2018-10- 2018-12- IDA / 60850 he efficiency of Public Fina Post Open 6,200.00 0.00 Canceled lation of audit quality contr ultant Selection 0 18 08 13 12 ncial Management ol based on early findings o f the pilot B22/CS/010 / National con sultant on developing enha ncement of multi-currency Component B: Improving t Individual Cons 2018-05-3 2018-05- 2018-07- 2018-08- 2018-08- 2018-08- 2018-09- 2018-08- 2019-09- 2019-08- and real time gross settlem IDA / 60850 he efficiency of Public Fina Post Open 9,000.00 9,000.00 Completed ultant Selection 1 22 19 03 09 03 13 03 13 12 ent systems integrating wit ncial Management h GFMIS/FB V7, and providi ng technical support imple mentation of the web-base d GFMIS B32/CS/002 / National con Component B: Improving t Individual Cons 2018-05-3 2018-05- 2018-07- 2018-06- 2018-08- 2018-06- 2018-09- 2018-06- 2018-10- 2018-08- sultant to conduct market r IDA / 60850 he efficiency of Public Fina Post Open 2,000.00 2,000.00 Completed ultant Selection 1 23 19 22 09 22 13 22 13 15 esearch and draft the TOR f ncial Management or consulting firm B33/CS/001 / National con Component B: Improving t sultant to conduct research Individual Cons 2018-06-2 2018-08- 2018-09- 2018-10- 2019-04- IDA / 60850 he efficiency of Public Fina Post Open 7,800.00 0.00 Canceled on international organizatio ultant Selection 9 17 07 12 10 ncial Management n's procurement policy and prepare recommendations B33/CS/002 / National con sultant to develop the ame Component B: Improving t Individual Cons 2018-10-3 2018-12- 2019-01- 2019-02- 2020-02- ndment of the relevant pro IDA / 60850 he efficiency of Public Fina Post Open 14,400.00 0.00 Canceled ultant Selection 1 19 09 13 13 curement documents base ncial Management d on the findings and reco mmendations B33/CS/003 / National juni or consultant to assist the s enior consultant to conduct Component B: Improving t Individual Cons 2018-06-2 2018-08- 2018-09- 2018-10- 2019-10- research on international o IDA / 60850 he efficiency of Public Fina Post Open 7,800.00 0.00 Canceled ultant Selection 9 17 07 12 12 rganization's procurement ncial Management policy and to develop the a mendment to the relevant procurement documents B33/CS/05 / National cons ultant to conduct research Component B: Improving t on implementation of the P Individual Cons 2018-05-3 2018-06- 2018-07- 2018-08- 2019-02- IDA / 60850 he efficiency of Public Fina Post Direct 9,000.00 0.00 Canceled ublic Procurement Law of M ultant Selection 1 10 01 05 01 ncial Management ongolia and develop amen dment law draft based on t he recommendation B33/CS/005 / National con sultant to conduct research Component B: Improving t on implementation of the P Individual Cons 2018-05-3 2018-07- 2018-08- 2018-09- 2019-03- IDA / 60850 he efficiency of Public Fina Post Open 9,000.00 0.00 Canceled ublic Procurement Law of M ultant Selection 1 19 09 13 12 ncial Management ongolia and develop amen dment law draft based on t he recommendation B33/CS/06 / National cons ultant to conduct research Component B: Improving t Individual Cons 2018-06-2 2018-07- 2018-07- 2018-09- 2019-03- on international organizatio IDA / 60850 he efficiency of Public Fina Post Direct 7,800.00 0.00 Canceled ultant Selection 9 09 30 03 02 n's standard bidding docu ncial Management ments and prepare recom mendations B33/CS/006 / National con sultant to conduct research Component B: Improving t Individual Cons 2018-05-2 2018-07- 2018-08- 2018-09- 2019-09- on international organizatio IDA / 60850 he efficiency of Public Fina Post Open 12,000.00 0.00 Canceled ultant Selection 8 16 06 10 10 n's standard bidding docu ncial Management ments and prepare recom mendations B33/CS/008 / National juni or consultant to assist the s enior consultant to conduct Component B: Improving t Individual Cons 2018-06-2 2018-08- 2018-09- 2018-10- 2019-10- research on international o IDA / 60850 he efficiency of Public Fina Post Open 7,800.00 0.00 Canceled ultant Selection 9 17 07 12 12 rganization's standard bidd ncial Management ing documents and to deve lop amendment of the rele vant bidding documents B33/CS/007 / National con Component B: Improving t sultant to develop amendm Individual Cons 2018-06-2 2018-08- 2018-09- 2018-10- 2019-10- IDA / 60850 he efficiency of Public Fina Post Open 14,400.00 0.00 Canceled ent of the relevant bidding ultant Selection 9 17 07 12 12 ncial Management documents based on the fi ndings and recommendatio ns B4/CS/01 / National consul Component B: Improving t Individual Cons 2018-07-3 2018-06- 2018-08- 2018-06- 2018-08- 2018-06- 2018-10- 2018-06- 2019-04- 2019-03- tant to develop methodolo IDA / 60850 he efficiency of Public Fina Post Direct 10,000.00 9,000.00 Completed ultant Selection 1 04 10 05 31 05 05 05 03 04 gy for impact assessment o ncial Management n recurrent budget B4/CS/001 / National cons Component B: Improving t Individual Cons 2018-07-3 2018-09- 2018-10- 2018-11- 2019-11- ultant to develop methodol IDA / 60850 he efficiency of Public Fina Post Open 18,000.00 0.00 Canceled ultant Selection 1 18 09 13 13 ogy for impact assessment ncial Management on recurrent budget B4/CS/02 / National consul Component B: Improving t tant to develop guideline fo Individual Cons 2018-07-3 2018-06- 2018-08- 2018-06- 2018-08- 2018-06- 2018-10- 2018-06- 2019-04- 2019-03- IDA / 60850 he efficiency of Public Fina Post Direct 10,000.00 9,000.00 Completed r public investment project ultant Selection 1 04 10 05 31 05 05 05 03 04 ncial Management evaluation and its selection B4/CS/002 / National cons Component B: Improving t ultant to develop guideline Individual Cons 2018-07-3 2018-09- 2018-10- 2018-11- 2019-11- IDA / 60850 he efficiency of Public Fina Post Open 18,000.00 0.00 Canceled for public investment proje ultant Selection 1 18 09 13 13 ncial Management ct evaluation and its selecti on B4/CS/004 / National cons Component B: Improving t ultant to Improve planning Individual Cons 2018-07-3 2018-09- 2018-10- 2018-11- 2019-11- IDA / 60850 he efficiency of Public Fina Post Open 18,000.00 0.00 Canceled of medium term investmen ultant Selection 1 18 09 13 13 ncial Management t expenditure in the MTFF (l ocal) B4/CS/005 / National cons Component B: Improving t ultant to improve planning Individual Cons 2018-07-3 2018-09- 2018-10- 2018-11- 2019-08- IDA / 60850 he efficiency of Public Fina Post Open 13,500.00 0.00 Canceled of budget liabilities of PPP ultant Selection 1 18 09 13 10 ncial Management projects in the medium ter m fiscal framework B4/CS/06 / National consul tant to improve legal and Component B: Improving t Individual Cons 2018-07-3 2018-08- 2018-08- 2018-10- 2019-04- management systems of o IDA / 60850 he efficiency of Public Fina Post Direct 12,000.00 0.00 Canceled ultant Selection 1 10 31 05 03 ngoing investment projects ncial Management , improve contract impleme ntation and payable monito ring B4/CS/006 / National cons ultant to improve legal and Component B: Improving t Individual Cons 2018-06-3 2018-08- 2018-09- 2018-10- 2019-10- management systems of o IDA / 60850 he efficiency of Public Fina Post Open 12,000.00 0.00 Canceled ultant Selection 0 18 08 13 13 ngoing investment projects ncial Management , improve contract impleme ntation and payable monito ring C11/CS/004 / National con Component C: Enhancing Individual Cons 2018-11-3 2018-07- 2019-01- 2018-07- 2019-02- 2018-07- 2019-03- 2018-07- 2019-09- 2018-12- sultant to review and make IDA / 60850 Post Open 4,800.00 7,250.00 Completed Financial Sector Stability ultant Selection 0 18 18 30 08 30 15 30 11 31 amendments the law of Inv estment fund C11/CS/002 / National con sultant to draft the asset m Component C: Enhancing Individual Cons 2018-05-3 2018-07- 2018-08- 2018-09- 2019-05- IDA / 60850 Post Open 7,400.00 0.00 Canceled anagement company law a Financial Sector Stability ultant Selection 1 19 09 13 11 nd related regulations. C11/CS/005 / National con sultant to assist Financial P olicy Department of MOF fo Component C: Enhancing Individual Cons 2018-05-3 2018-06- 2018-07- 2018-06- 2018-08- 2018-06- 2018-09- 2018-06- 2019-07- 2019-01- r formulating New Govern IDA / 60850 Post Open 6,000.00 7,200.00 Completed Financial Sector Stability ultant Selection 1 11 19 26 09 26 13 26 10 02 ment subsidized mortgage financing schemes to supp ort housing and reduce air pollution in the urban areas C11/CS/008 / National con Component C: Enhancing Individual Cons 2018-08-3 2018-10- 2018-11- 2018-12- 2019-06- sultant on privatization of s IDA / 60850 Post Open 7,200.00 0.00 Canceled Financial Sector Stability ultant Selection 1 19 09 14 12 tate owned companies inlc uding MSE C11/CS/009 / National con Component C: Enhancing Individual Cons 2018-11-3 2019-01- 2019-01- 2019-02- 2019-03- 2019-11- sultant to prepare the priva IDA / 60850 Post Open 11,900.00 0.00 Canceled Financial Sector Stability ultant Selection 0 14 18 08 15 10 tization plan of the State b ank C11/CS/010 / National con Component C: Enhancing Individual Cons 2018-10-3 2018-05- 2018-12- 2018-06- 2019-01- 2018-06- 2019-02- 2018-06- 2019-10- 2018-09- sultant on development of IDA / 60850 Post Open 7,200.00 7,200.00 Completed Financial Sector Stability ultant Selection 1 16 19 19 09 19 13 19 11 11 Government external bond regulation C4/CS/004 / National cons ultant to work with/assist t Component C: Enhancing Individual Cons 2018-06-2 2018-08- 2018-09- 2018-10- 2018-11- he international consultant IDA / 60850 Post Open 2,500.00 0.00 Canceled Financial Sector Stability ultant Selection 9 17 07 12 11 to draft the existing Law on Legal Status of Financial Re gulatory Commission C4/CS/006 / National cons Component C: Enhancing Individual Cons 2018-06-3 2018-08- 2018-09- 2018-10- 2018-11- ultant to lead draft amend IDA / 60850 Post Open 3,500.00 0.00 Canceled Financial Sector Stability ultant Selection 0 18 08 13 12 ments to articles of other r elevant laws C4/CS/009 / National team Component C: Enhancing Individual Cons 2018-06-3 2018-08- 2018-09- 2018-10- 2019-01- of consultants to draft Over IDA / 60850 Post Open 32,000.00 0.00 Canceled Financial Sector Stability ultant Selection 0 18 08 13 11 -the-counter (OTC) market regulations C4/CS/09 / International co nsultant to conduct a need Component C: Enhancing Individual Cons 2018-08-3 2018-10- 2018-10- 2019-04- 2018-11- 2019-04- 2018-12- 2019-04- 2019-01- 2019-07- s assessment related to ca IDA / 60850 Post Open 18,150.00 20,200.00 Completed Financial Sector Stability ultant Selection 1 31 19 09 09 22 14 22 13 01 pacity building based on FR C's development strategy. Draft a training curriculum C4/CS/015 / International c onsultant to conduct a nee Component C: Enhancing Individual Cons 2018-06-3 2018-08- 2018-09- 2018-10- 2018-11- ds assessment related to c IDA / 60850 Post Open 18,150.00 0.00 Canceled Financial Sector Stability ultant Selection 0 18 08 13 12 apacity building based on F RC's development strategy. Draft a training curriculum C4/CS/010 / International c Component C: Enhancing Individual Cons 2018-05-3 2018-08- 2018-07- 2018-09- 2018-08- 2018-09- 2018-09- 2018-09- 2019-03- 2020-06- onsultant on terminologies/ IDA / 60850 Post Open 36,000.00 72,000.00 Completed Financial Sector Stability ultant Selection 1 13 19 05 09 10 13 10 12 16 technical terms of financial market for FRC staff C4/CS/016 / International c onsultant on academic writi Component C: Enhancing Individual Cons 2018-05-2 2018-07- 2018-08- 2018-09- 2019-03- IDA / 60850 Post Open 36,000.00 0.00 Canceled ng skills and terminologies/ Financial Sector Stability ultant Selection 4 12 02 06 05 technical terms of financial market for FRC staff C4/CS/011 / National cons Component C: Enhancing Individual Cons 2018-07-3 2018-11- 2018-09- 2019-01- 2018-10- 2019-01- 2018-11- 2019-01- 2019-05- 2019-03- ultant to translate risk base IDA / 60850 Post Open 5,000.00 6,451.20 Completed Financial Sector Stability ultant Selection 1 29 18 03 09 03 13 03 12 14 d supervision guideline/ma nual C4/CS/017 / National cons Component C: Enhancing Individual Cons 2018-08-3 2018-10- 2018-11- 2018-12- 2019-06- ultant to translate risk base IDA / 60850 Post Open 5,000.00 0.00 Canceled Financial Sector Stability ultant Selection 1 19 09 14 12 d supervision guideline/ma nual C5/CS/002 / International Consultant to provide traini Component C: Enhancing Individual Cons 2018-07-3 2018-07- 2018-09- 2018-12- 2018-10- 2018-12- 2018-11- 2018-12- 2019-05- 2019-03- IDA / 60850 Post Open 9,850.00 9,550.00 Completed ng for the FSC staff on fina Financial Sector Stability ultant Selection 1 25 18 06 09 10 13 12 12 19 ncial stability analysis and assessment C5/CS/004 / International Consultant to provide traini Component C: Enhancing Individual Cons 2018-10-3 2018-12- 2019-01- 2019-02- 2019-08- IDA / 60850 Post Open 9,850.00 0.00 Canceled ng for the FSC staff on Mod Financial Sector Stability ultant Selection 1 19 09 13 12 eling interactions between macroeconomic policies Page 6 C5/CS/009 / National Cons ultant to provide training fo r the FSC staff on financial Component C: Enhancing Individual Cons 2018-08-3 2018-10- 2018-11- 2018-12- 2019-06- programming, macro-prude IDA / 60850 Post Open 5,250.00 0.00 Canceled Financial Sector Stability ultant Selection 1 19 09 14 12 ntial stress test, balance sh eet analysis, crisis manage ment framework, and syste mic risk modeling D1/CS/003 / National cons ultant on policy analysis for Component D: Strengtheni employment promotion of t Individual Cons 2018-09-2 2018-10- 2018-10- 2018-12- 2019-06- IDA / 60850 ng of the Social Protection Post Direct 6,700.00 0.00 Canceled he poor, case management ultant Selection 8 08 29 03 01 System support on household deve lopment plan and impleme ntation D1/CS/004 / National cons ultant on policy analysis for Component D: Strengtheni employment promotion of t Individual Cons 2018-08-3 2018-10- 2018-11- 2018-12- 2019-04- IDA / 60850 ng of the Social Protection Post Open 6,700.00 0.00 Canceled he poor, case management ultant Selection 1 19 09 14 13 System support on household deve lopment plan and impleme ntation D1/CS/11 / Lead call cente Component D: Strengtheni Individual Cons 2018-12-2 2019-01- 2019-01- 2019-02- 2020-02- IDA / 60850 Post Direct 7,200.00 0.00 Canceled r operator ng of the Social Protection ultant Selection 4 03 24 28 28 System D1/CS/011 / National cons Component D: Strengtheni ultants on translation and i Individual Cons 2018-05-3 2018-07- 2018-08- 2018-09- 2019-09- IDA / 60850 ng of the Social Protection Post Open 30,000.00 0.00 Canceled nterpretation services, call ultant Selection 1 19 09 13 13 System center operators (multiple contracts) D1/CS/012 / Junior call cen Component D: Strengtheni Individual Cons 2018-12-3 2019-01- 2019-01- 2019-03- 2020-03- IDA / 60850 Post Direct 6,000.00 0.00 Canceled ter operator ng of the Social Protection ultant Selection 1 10 31 07 06 System D1/CS/013 / National cons ultant on translation and in terpretation services releva Component D: Strengtheni Individual Cons 2018-12-3 2019-01- 2019-01- 2019-03- 2019-09- nt to the selected Internati IDA / 60850 ng of the Social Protection Post Direct 2,800.00 0.00 Canceled ultant Selection 1 10 31 07 03 onal consultant services on System Legal framework enabling c onsolidation of the social w elfare pensions, benefits, al lowances and services D1/CS/014 / National cons ultant on translation and in terpretation services releva Component D: Strengtheni Individual Cons 2018-12-3 2019-01- 2019-01- 2019-03- 2019-09- nt to the selected Internati IDA / 60850 ng of the Social Protection Post Direct 2,800.00 0.00 Canceled ultant Selection 1 10 31 07 03 onal consultant services on System design pension parametric reforms in line with the Sta te Policy on Pension Refor m D1/CS/015 / National cons ultant on translation and in Component D: Strengtheni terpretation services releva Individual Cons 2018-12-3 2019-01- 2019-01- 2019-03- 2019-09- IDA / 60850 ng of the Social Protection Post Direct 2,800.00 0.00 Canceled nt to the selected Internati ultant Selection 1 10 31 07 03 System onal consultant services on long-term actuarial projecti ons on proposed design opt ions D1/CS/016 / National cons ultant on translation and in terpretation services releva Component D: Strengtheni Individual Cons 2018-12-3 2019-01- 2019-01- 2019-03- 2019-09- nt to the selected Internati IDA / 60850 ng of the Social Protection Post Direct 2,800.00 0.00 Canceled ultant Selection 1 10 31 07 03 onal consultant services on System overall governance framew ork for pension and for soci al insurance fund manage ment D1/CS/017 / National cons ultant on translation and in terpretation services releva Component D: Strengtheni Individual Cons 2018-12-3 2019-01- 2019-01- 2019-03- 2019-09- nt to the selected Internati IDA / 60850 ng of the Social Protection Post Direct 2,800.00 0.00 Canceled ultant Selection 1 10 31 07 03 onal consultant services on System diagnostic assessment of p olicy and institutional refor m options for broadening t he coverage D1/CS/018 / National cons ultant on translation and in terpretation services releva Component D: Strengtheni nt to the selected Internati Individual Cons 2018-12-3 2019-01- 2019-01- 2019-03- 2020-03- IDA / 60850 ng of the Social Protection Post Direct 2,800.00 0.00 Canceled onal consultant services on ultant Selection 1 10 31 07 06 System establishing the ground rul es for occupational and indi vidual pension savings arra ngements, including oversi ght, tax treatment, a D2/CS/002 / National cons ultant to work with/assist t Component D: Strengtheni Individual Cons 2018-05-3 2018-07- 2018-08- 2018-09- 2018-12- he international consultant IDA / 60850 ng of the Social Protection Post Open 8,000.00 0.00 Canceled ultant Selection 1 19 09 13 12 to design pension parametr System ic reforms in line with the S tate Policy on Pension Refo rm D2/CS/04 / National consul tant to work with/assist the Component D: Strengtheni Individual Cons 2018-07-3 2018-08- 2018-08- 2018-10- 2019-04- international consultant on IDA / 60850 ng of the Social Protection Post Direct 8,000.00 0.00 Canceled ultant Selection 1 10 31 05 03 long term Actuarial projecti System ons on proposed design opt ions D2/CS/004 / National cons ultant to work with/assist t Component D: Strengtheni Individual Cons 2018-05-3 2018-07- 2018-08- 2018-09- 2018-12- he international consultant IDA / 60850 ng of the Social Protection Post Open 8,000.00 0.00 Canceled ultant Selection 1 19 09 13 12 on long term Actuarial proj System ections on proposed design options D2/CS/008 / National cons ultant to work with/assist t Component D: Strengtheni he international consultant Individual Cons 2018-11-3 2019-01- 2019-02- 2019-03- 2019-09- IDA / 60850 ng of the Social Protection Post Open 8,000.00 0.00 Canceled on diagnostic assessment o ultant Selection 0 18 08 15 11 System f policy and institutional ref orm options for broadening the coverage D2/CS/11 / National consul Component D: Strengtheni tant (Lead) to draft legislati Individual Cons 2018-06-2 2018-05- 2018-07- 2018-05- 2018-07- 2018-05- 2018-09- 2018-05- 2019-03- 2019-05- IDA / 60850 ng of the Social Protection Post Direct 10,000.00 14,400.00 Completed ons on specific types of pe ultant Selection 9 11 09 23 30 23 03 23 02 31 System nsion paid from Social insur ance fund D2/CS/012 / National cons Component D: Strengtheni Individual Cons 2018-06-2 2018-07- 2018-07- 2018-08- 2019-02- IDA / 60850 Post Direct 8,000.00 0.00 Canceled ultant to draft Law on Socia ng of the Social Protection ultant Selection 5 05 26 30 26 l Insurance System D2/CS/013 / National cons ultant to draft Law on Pensi ons and Benefits Provided Component D: Strengtheni by the Social Insurance Fun Individual Cons 2018-06-2 2018-05- 2018-07- 2018-05- 2018-07- 2018-05- 2018-08- 2018-05- 2019-02- 2018-12- IDA / 60850 ng of the Social Protection Post Direct 8,000.00 6,000.00 Completed d and Legal regulations reg ultant Selection 5 22 05 23 26 23 30 23 26 31 System arding pension insurance a nd benefits for herders, self -employers and informal w orkers ( that need to be sp ecifically legislated eith D2/CS/014 / National cons ultant to draft Law on bene fits from unemployment an Component D: Strengtheni Individual Cons 2018-06-2 2018-05- 2018-07- 2018-05- 2018-07- 2018-05- 2018-08- 2018-05- 2019-02- d benefits insurance fund a IDA / 60850 ng of the Social Protection Post Direct 8,000.00 6,000.00 Terminated ultant Selection 5 22 05 23 26 23 30 23 26 nd Law on pensions, benefi System ts, and allowances from an industrial accident and occ upational disease insuranc e fund D1/CS/008 / Coordinating c Component D: Strengtheni Individual Cons 2018-04-3 2017-10- 2018-06- 2017-10- 2018-07- 2017-10- 2018-08- 2017-10- 2019-08- IDA / 60850 Post Open 18,000.00 18,000.00 Terminated onsultant of Component D ng of the Social Protection ultant Selection 0 16 18 31 09 31 13 31 13 System C4/CS/012 / FRC compone Component C: Enhancing Individual Cons 2018-04-2 2017-10- 2018-06- 2017-10- 2018-07- 2017-10- 2018-08- 2017-10- 2019-08- IDA / 60850 Post Open 18,000.00 102,843.08 Signed nt coordinating consultant Financial Sector Stability ultant Selection 7 16 15 31 06 31 10 31 10 B11/CS/012 / Component Component B: Improving t Individual Cons 2018-03-3 2017-10- 2018-05- 2018-01- 2018-06- 2018-01- 2018-07- 2018-01- 2019-07- 2019-11- A2&B1-FPPD coordinating c IDA / 60850 he efficiency of Public Fina Post Open 30,000.00 36,000.00 Completed ultant Selection 1 17 19 03 09 03 14 03 14 07 onsultant ncial Management A2/CS/009 / National cons ultant to make an assessm Component A: Strengtheni ent on existing revenue mo Individual Cons 2018-05-3 2018-07- 2018-08- 2018-09- 2019-09- IDA / 60850 ng Macroeconomic and Fis Post Open 26,400.00 0.00 Canceled dels and to develop fiscal r ultant Selection 1 19 09 13 13 cal Management evenue forecasting modelli ng including budget data a nalysis and collection A31/CS/01 / National cons ultant to improve and upda te the debt management la Component A: Strengtheni w and designing annual rep Individual Cons 2018-06-2 2018-07- 2018-07- 2018-08- 2019-02- IDA / 60850 ng Macroeconomic and Fis Post Direct 18,000.00 0.00 Canceled ort (or section of a wider re ultant Selection 5 05 26 30 26 cal Management port) contains an assessme nt of how the government activities have complied wi th the government's docu mented and approved MTD E/CS/006 / Employment of S. Component E: Project Man 2018-06-1 2018-06- 2018-08- 2019-08- PIU core staff: Monitoring a IDA / 60850 Prior Direct Selection Direct 10,200.00 0.00 Canceled agement and Monitoring 1 21 25 25 nd Evaluation Assistant B21/CS/01 / National cons Component B: Improving t ultant on revising the regul Individual Cons 2018-06-2 2018-06- 2018-07- 2018-07- 2018-07- 2018-07- 2018-09- 2018-07- 2019-03- 2018-12- IDA / 60850 he efficiency of Public Fina Post Direct 6,200.00 6,000.00 Completed ation of audit quality contr ultant Selection 9 19 09 02 30 02 03 02 02 31 ncial Management ol based on early findings o f the pilot A2/CS/09 / National consul tant to make an assessmen Component A: Strengtheni t on existing revenue mode Individual Cons 2018-06-0 2018-06- 2018-06- 2018-06- 2018-07- 2018-06- 2018-08- 2018-06- 2019-02- 2018-12- IDA / 60850 ng Macroeconomic and Fis Post Direct 26,400.00 18,000.00 Completed ls and to develop fiscal rev ultant Selection 4 04 14 04 05 04 09 04 05 04 cal Management enue forecasting modelling including budget data anal ysis and collection B11/CS/009 / National seni or functional consultant to support BPIS sustainability Component B: Improving t at the local government lev Individual Cons 2018-04-3 2018-06- 2018-05- 2018-06- 2018-05- 2018-06- 2018-07- 2018-06- 2019-07- 2019-06- IDA / 60850 he efficiency of Public Fina Post Direct 18,000.00 18,000.00 Completed el, operation at central gov ultant Selection 0 04 10 05 31 05 05 05 05 04 ncial Management ernment level including en d-users' training and to ma ke an assessment of BPIS f urther technical functional needs. A31/CS/03 / National cons ultant on improving the pre paration of the Medium Ter Component A: Strengtheni m Debt Management Strat Individual Cons 2018-06-1 2018-06- 2018-07- 2018-08- 2019-02- IDA / 60850 ng Macroeconomic and Fis Post Direct 12,000.00 0.00 Canceled egy. The consultant will foc ultant Selection 1 21 12 16 12 cal Management us on the external and dom estic market analysis and d evelop risk analysis for the on-lending loan, governme nt guarantees. A31/CS/05 / National cons ultant to validate DMFAS d atabase and introduce new Component A: Strengtheni debt statistics standard co Individual Cons 2018-07-3 2018-06- 2018-08- 2018-06- 2018-08- 2018-06- 2018-10- 2018-06- 2019-04- 2018-12- IDA / 60850 ng Macroeconomic and Fis Post Direct 18,000.00 52,500.00 Completed mpatible with Balance of p ultant Selection 0 04 09 04 30 04 04 04 02 03 cal Management ayment 6 and Government Finance statistics 2011 fro m IMF and the DMFAS proc edures manual. The consult ant will be admin for DMFA B4/CS/04 / National junior S. Component B: Improving t consultant to Improve plan Individual Cons 2018-07-3 2018-06- 2018-08- 2018-06- 2018-08- 2018-06- 2018-10- 2018-06- 2019-04- 2019-02- IDA / 60850 he efficiency of Public Fina Post Direct 6,000.00 6,000.00 Completed ning of medium term inves ultant Selection 1 11 10 12 31 12 05 12 03 12 ncial Management tment expenditure in the M TFF E/CS/06 / Employment of P Component E: Project Man Individual Cons 2018-06-1 2018-06- 2018-08- 2018-08- 2018-08- 2019-12- 2018-10- 2018-08- 2019-10- 2019-08- IU core staff: Monitoring an IDA / 60850 Prior Open 10,200.00 7,943.90 Completed agement and Monitoring ultant Selection 8 20 06 30 27 02 01 30 01 29 d Evaluation Assistant B21/CS/04 / International c Component B: Improving t Individual Cons 2018-10-3 2018-08- 2018-11- 2018-09- 2018-12- 2018-09- 2019-01- 2018-08- 2019-07- 2018-09- onsultant to carry out the q IDA / 60850 he efficiency of Public Fina Post Direct 8,800.00 6,100.00 Completed ultant Selection 1 28 10 05 01 06 05 29 04 28 uality control on audit ncial Management C4/CS/02 / National consul tant (Team leader) to work with/assist the internationa Component C: Enhancing Individual Cons 2018-07-3 2018-08- 2018-09- 2018-08- 2018-10- 2018-08- 2018-11- 2018-08- 2019-02- 2019-06- IDA / 60850 Post Open 6,000.00 18,000.00 Completed l consultant to review and Financial Sector Stability ultant Selection 1 06 18 22 09 22 13 22 11 03 draft the Law on Legal Stat us of FRC and prepare draft amendments to articles of r elevant laws. C4/CS/04 / National consul tant (team member) to wor k with/assist the internatio Component C: Enhancing Individual Cons 2018-07-3 2018-08- 2018-09- 2018-08- 2018-10- 2018-08- 2018-11- 2018-08- 2019-02- 2019-06- IDA / 60850 Post Open 5,400.00 5,400.00 Completed nal consultant to review an Financial Sector Stability ultant Selection 1 06 18 22 09 22 13 22 11 03 d draft the Law on Legal St atus of FRC and prepare dr aft amendments to articles of relevant laws. B21/CS/008 / National con sultant on updating the tra Component B: Improving t nslation of IPSAS from Engli Individual Cons 2018-12-2 2018-12- 2019-01- 2018-12- 2019-01- 2018-12- 2019-02- 2018-12- 2019-08- 2019-05- IDA / 60850 he efficiency of Public Fina Post Direct 3,800.00 4,600.00 Completed sh into Mongolian as of 201 ultant Selection 4 05 03 24 24 24 28 24 27 26 ncial Management 7, including Front Matters, Framework, Preface, IPSAS 32, 33 and 39. B21/CS/009 / National con sultant on updating the tra Component B: Improving t nslation of IPSAS from Engli Individual Cons 2018-12-2 2018-12- 2019-01- 2018-12- 2019-01- 2018-12- 2019-02- 2018-12- 2019-08- 2019-05- IDA / 60850 he efficiency of Public Fina Post Direct 4,500.00 5,350.00 Completed sh into Mongolian as of 201 ultant Selection 4 05 03 24 24 24 28 24 27 26 ncial Management 7, including the full translat ion of IPSAS 34-38 and 40 f rom English into Mongolian B21/CS/010 / National con sultant to review the transl ation of IPSAS from English Component B: Improving t Individual Cons 2018-12-2 2018-12- 2019-01- 2018-12- 2019-01- 2018-12- 2019-02- 2018-12- 2019-08- 2019-05- to Mongolian as of 2017, in IDA / 60850 he efficiency of Public Fina Post Direct 3,400.00 5,350.00 Completed ultant Selection 4 05 03 24 24 24 28 24 27 26 cluding Introduction to IPSA ncial Management S, IPSAS under cash basis, I ntroduction to guidelines, R PG1-3, Glossary, Accrual IP SAS. B21/CS/006 / National con sultant to edit and proofrea Component B: Improving t Individual Cons 2018-10-1 2018-12- 2018-10- 2018-12- 2018-11- 2018-12- 2018-12- 2018-12- 2019-06- 2019-08- d translations of IPSAS fro IDA / 60850 he efficiency of Public Fina Post Direct 13,000.00 13,000.00 Completed ultant Selection 5 05 25 24 15 24 20 24 18 26 m English into Mongolian a ncial Management s 2017 IPSAS 1-40 and tran slation of revised pages in I PSAS 1-31 B22/CS/011 / National seni or consultant to make a res earch and analysis to devel Component B: Improving t op commitment control sys Individual Cons 2018-09-2 2018-11- 2018-11- 2018-12- 2018-12- 2018-12- 2019-01- 2018-12- 2020-01- IDA / 60850 he efficiency of Public Fina Post Open 18,000.00 73,846.42 Signed tem through GFMIS FBv7, a ultant Selection 4 21 12 24 03 24 07 24 07 ncial Management nd develop related guidelin e to implement and provid e functional support to dem onstrate commitment contr ol function and pilot obligat B22/CS/012 / National con ion sultant to provide functiona l support to implement com Component B: Improving t Individual Cons 2018-09-1 2018-11- 2018-10- 2018-12- 2018-11- 2018-12- 2018-12- 2018-12- 2019-12- mitment control system thr IDA / 60850 he efficiency of Public Fina Post Open 8,400.00 33,917.78 Signed ultant Selection 0 21 29 24 19 24 24 24 24 ough GFMIS FBv7 and tech ncial Management nical support to demonstra te commitment control pilo t obligation in 3 aimags an d 3 line ministries E/CS/008 / Project Assistan Component E: Project Man Individual Cons 2018-09-2 2019-04- 2018-11- 2018-10- 2018-12- 2020-08- 2019-01- 2018-10- 2020-01- IDA / 60850 Prior Open 12,000.00 19,877.71 Terminated t at PIU agement and Monitoring ultant Selection 4 05 12 15 03 13 07 15 07 A1/CS/005 / National cons Component A: Strengtheni ultant on establishing Fore Individual Cons 2018-05-3 2018-08- 2018-07- 2018-09- 2018-08- 2018-09- 2018-09- 2018-09- 2019-09- 2019-09- IDA / 60850 ng Macroeconomic and Fis Post Open 24,000.00 24,000.00 Completed casting and Policy Analysis ultant Selection 1 30 19 25 09 25 13 25 13 30 cal Management System in Ministry of Finan ce. A1/CS/006 / National cons Component A: Strengtheni Individual Cons 2018-05-3 2018-08- 2018-07- 2018-09- 2018-08- 2018-09- 2018-09- 2018-09- 2019-09- 2019-09- ultant to cost-benefit analy IDA / 60850 ng Macroeconomic and Fis Post Open 24,000.00 24,000.00 Completed ultant Selection 1 31 19 25 09 25 13 25 13 25 sis of public programs cal Management D2/CS/13 / National consul Component D: Strengtheni tant to draft legal amendm Individual Cons 2018-11-0 2018-11- 2018-11- 2018-11- 2018-12- 2018-11- 2019-01- 2018-11- 2019-07- 2019-04- IDA / 60850 ng of the Social Protection Post Direct 4,800.00 4,800.00 Completed ents to the Law on Pension ultant Selection 9 15 19 28 10 28 14 28 13 28 System s and Benefits Provided by the Social Insurance Fund D2/CS/14 / National consul tant to draft legal amendm ents to the Law on Pension Component D: Strengtheni s, benefits, and allowances Individual Cons 2018-11-0 2018-11- 2018-11- 2018-12- 2019-01- 2019-07- IDA / 60850 ng of the Social Protection Post Direct 4,800.00 0.00 Canceled from an industrial accident ultant Selection 9 15 19 10 14 13 System and occupational disease p rovided by the Social Insur ance Fund and Law on Ben efits from unemployment p rovided by the Social Insur D2/CS/140 / National cons anc ultant to draft legal amend Component D: Strengtheni ments to the Law on Pensio 2018-11-0 2018-11- 2018-11- 2018-11- 2019-01- 2019-07- IDA / 60850 ng of the Social Protection Prior Direct Selection Direct 4,800.00 0.00 Canceled ns, benefits, and allowance 9 25 19 28 23 22 System s from an industrial accide nt and occupational diseas e provided by the Social Ins urance Fund… D2/CS/130 / National cons Component D: Strengtheni ultant to draft legal amend 2018-11-0 2018-11- 2018-11- 2019-01- 2019-07- IDA / 60850 ng of the Social Protection Prior Direct Selection Direct 4,800.00 0.00 Canceled ments to the Law on Pensio 9 25 19 23 22 System ns and Benefits Provided b y the Social Insurance Fund B4/CS/0005 / National con Component B: Improving t sultant to improve planning Individual Cons 2018-11-1 2018-12- 2019-01- 2019-01- 2019-01- 2019-02- 2019-01- 2019-08- IDA / 60850 he efficiency of Public Fina Post Open 13,500.00 12,000.00 Terminated of budget liabilities of PPP ultant Selection 5 19 03 24 25 28 25 27 ncial Management projects in the medium ter m fiscal framework A32/CS/008 / National con sultant on software/databa Component A: Strengtheni Individual Cons 2018-09-0 2019-01- 2018-10- 2019-01- 2018-11- 2019-01- 2018-12- 2019-01- 2019-06- 2022-01- se development updating a IDA / 60850 ng Macroeconomic and Fis Post Open 8,000.00 43,186.53 Completed ultant Selection 1 24 20 25 10 25 15 25 13 25 nd maintaining Tax exempt cal Management ion recording system datab ase B4/CS/05 / National consul Component B: Improving t tant to improve planning of Individual Cons 2018-07-3 2018-11- 2018-08- 2018-08- 2018-10- 2019-04- IDA / 60850 he efficiency of Public Fina Post Direct 13,500.00 0.00 Canceled budget liabilities of PPP pro ultant Selection 1 29 10 31 05 03 ncial Management jects in the medium term fi scal framework B13/CS/003 / National con sultant to update and publi sh existing draft of the qual Component B: Improving t ity assurance manual and i Individual Cons 2018-10-3 2018-12- 2019-01- 2019-02- 2019-08- IDA / 60850 he efficiency of Public Fina Post Open 10,000.00 0.00 Canceled nternal audit handbook. Th ultant Selection 1 19 09 13 12 ncial Management e update shall be inline wit h sector specific practical i mprovements and customi ze to fit the needs of differ ent organizations. B13/CS/03 / National cons ultant to update and publis h existing draft of the quali Component B: Improving t ty assurance manual and in 2018-11-2 2019-02- 2018-12- 2019-02- 2019-02- 2019-02- 2019-08- IDA / 60850 he efficiency of Public Fina Post Direct Selection Direct 10,000.00 10,000.00 Terminated ternal audit handbook. The 1 01 01 11 04 13 03 ncial Management update shall be inline with sector specific practical im provements and customize to fit the needs of different organizations. B4/CS/007 / National cons Component B: Improving t ultant to develop the manu 2019-01-3 2019-02- 2019-02- 2019-02- 2019-04- 2019-02- 2019-10- IDA / 60850 he efficiency of Public Fina Post Direct Selection Direct 12,000.00 12,000.00 Terminated al for public investment pro 0 01 09 13 15 13 12 ncial Management ject appraisal and selection Page 7 B4/CS/008 / National cons ultant to develop a manual Component B: Improving t 2019-01-3 2019-02- 2019-02- 2019-02- 2019-04- 2019-02- 2019-10- for estimating the economi IDA / 60850 he efficiency of Public Fina Post Direct Selection Direct 12,000.00 12,000.00 Terminated 0 01 09 13 15 13 12 c benefits and social signifi ncial Management cance of public investment projects B4/CS/009 / National cons Component B: Improving t 2019-01-3 2019-02- 2019-02- 2019-02- 2019-04- 2019-02- 2019-10- ultant to review the Public I IDA / 60850 he efficiency of Public Fina Post Direct Selection Direct 17,600.00 17,600.00 Terminated 0 01 09 13 15 13 12 nvestment Management Le ncial Management gislation C11/CS/09 / National cons Component C: Enhancing 2019-01-3 2019-02- 2019-02- 2019-02- 2019-04- 2019-02- 2019-10- ultant to draft a privatizatio IDA / 60850 Post Direct Selection Direct 11,900.00 9,000.00 Terminated Financial Sector Stability 0 01 09 11 15 11 12 n plan and its related docu ments/regulations A2/CS/04 / National consul tant on public awareness a Component A: Strengtheni Individual Cons 2019-07-0 2019-07- 2019-08- 2019-09- 2020-03- ctivities including media co IDA / 60850 ng Macroeconomic and Fis Post Direct 12,000.00 0.00 Canceled ultant Selection 1 11 01 05 03 verage on the tax policy ref cal Management orm including public discus sions on tax reforms A2/CS/05 / National consul Component A: Strengtheni Individual Cons 2019-04-0 2019-04- 2019-05- 2019-06- 2019-12- tant to translate the tax pol IDA / 60850 ng Macroeconomic and Fis Post Direct 9,000.00 0.00 Canceled ultant Selection 1 11 02 06 03 icy legislation and other pol cal Management icy documents A2/CS/06 / National consul Component A: Strengtheni tant to translate the BEPS ( Individual Cons 2019-05-0 2019-05- 2019-06- 2019-07- 2020-01- IDA / 60850 ng Macroeconomic and Fis Post Direct 9,000.00 0.00 Canceled Base Erosion and Profit Shif ultant Selection 1 11 01 06 02 cal Management ting) and Global Forum rela ted tax policy legislation B11/CS/004 / National seni or consultant and policy ad visor to provide functional Component B: Improving t support to the system of st Individual Cons 2019-02-2 2019-09- 2019-03- 2019-09- 2019-03- 2019-09- 2019-05- 2019-09- 2020-05- IDA / 60850 he efficiency of Public Fina Post Direct 36,200.00 56,000.00 Terminated affing and salaries on impr ultant Selection 5 20 07 20 28 20 02 20 01 ncial Management ovement of appropriate me chanism for planning (inclu ding other planned activitie s under Sub-Component B1 .1, SFFSP) B12/CS/001 / National con sultant to develop a revisio Component B: Improving t n of FSL in relation to stren Individual Cons 2019-03-0 2019-04- 2019-05- 2019-06- 2020-06- IDA / 60850 he efficiency of Public Fina Post Open 30,000.00 0.00 Canceled gthening credibility of MTF ultant Selection 1 19 10 14 13 ncial Management F and to redefine principles of stability fund and re-det ermining special requireme nts B12/CS/005 / National con sultant to make an assess Component B: Improving t ment of current statistical r Individual Cons 2019-03-0 2019-04- 2019-05- 2019-06- 2020-06- IDA / 60850 he efficiency of Public Fina Post Open 24,000.00 0.00 Canceled eporting system of Mongoli ultant Selection 1 19 10 14 13 ncial Management a in the context of budget planning, identification of f urther needs for introducin g GFS 2014 B12/CS/008 / National seni or consultant to make an a ssessment of current statu Component B: Improving t Individual Cons 2019-04-0 2019-05- 2019-06- 2019-07- 2020-07- s on compliance of special f IDA / 60850 he efficiency of Public Fina Post Open 18,000.00 0.00 Canceled ultant Selection 1 20 10 15 14 iscal requirements of the F ncial Management SL for local budget and pre paration of a proposal on e nhancement of fiscal discip line at local government B12/CS/009 / National con sultant to make an assess ment of current status on c Component B: Improving t Individual Cons 2019-03-0 2019-05- 2019-03- 2019-04- 2019-05- 2019-11- ompliance of special fiscal r IDA / 60850 he efficiency of Public Fina Post Direct 6,000.00 0.00 Canceled ultant Selection 1 23 11 01 06 02 equirements of the FSL for ncial Management local budget and preparatio n of a proposal on enhance ment of fiscal discipline at l ocal government C21/CS/001 / National con sultant on implementation Component C: Enhancing Individual Cons 2019-06-3 2019-08- 2019-09- 2019-10- 2019-11- IDA / 60850 Post Open 13,300.00 0.00 Canceled of anti-bribery managemen Financial Sector Stability ultant Selection 0 18 08 13 12 t systems - ISO 37001:201 6 C21/CS/003 / International consultant to review and re Component C: Enhancing Individual Cons 2019-06-3 2019-08- 2019-09- 2019-10- 2019-11- IDA / 60850 Post Open 22,100.00 0.00 Canceled new the investment policy Financial Sector Stability ultant Selection 0 18 08 13 12 and regulation and its impl ementation C21/CS/002 / International Component C: Enhancing Individual Cons 2019-04-3 2019-06- 2019-07- 2019-08- 2019-09- consultant on Institutions' c IDA / 60850 Post Open 22,000.00 0.00 Canceled Financial Sector Stability ultant Selection 0 18 09 13 12 orporate structure D1/CS/001 / International c onsultant on Legal framew ork and effective model en Component D: Strengtheni Individual Cons 2019-05-0 2019-06- 2019-07- 2019-08- 2019-12- abling consolidation of the IDA / 60850 ng of the Social Protection Post Open 46,000.00 0.00 Canceled ultant Selection 1 19 10 14 12 social welfare pensions, be System nefits, allowances and servi ces including institutional c are development strategy proposal D2/CS/02 / National consul tant on the design of Pensi on Parametric reforms in li Component D: Strengtheni ne with the State Policy on Individual Cons 2019-06-0 2019-06- 2019-07- 2019-08- 2020-02- IDA / 60850 ng of the Social Protection Post Direct 6,000.00 0.00 Canceled Pension Reform and long-te ultant Selection 1 11 02 06 02 System rm Actuarial projections on proposed design options (u pdates to the current para metric projections includin g individual based mode A1/CS/016 / National cons ultant to develop a policy r Component A: Strengtheni ecommendation on populat Individual Cons 2019-04-0 2020-07- 2019-05- 2020-03- 2019-06- 2020-06- 2019-07- 2020-06- 2020-01- 2020-12- IDA / 60850 ng Macroeconomic and Fis Post Open 18,000.00 9,000.00 Completed ion livelihoods and poverty ultant Selection 1 03 20 26 10 26 15 29 11 28 cal Management reduction, and develop a m odel and methodology for e stimating poverty indicator s A2/CS/013 / National senio r consultant to develop and formulate regulations and t Component A: Strengtheni o organize capacity-buildin 2019-03-1 2019-03- 2019-05- 2019-11- IDA / 60850 ng Macroeconomic and Fis Post Direct Selection Direct 26,000.00 0.00 Canceled g training to ensure imple 1 21 25 21 cal Management mentation of the newly revi sed tax package laws: Gen eral Taxation Law, Personal Income Tax Law and Corpo rate Income Tax Law A2/CS/014 / National cons ultant to develop and form Component A: Strengtheni ulate regulations and to or 2019-03-1 2019-03- 2019-05- 2019-11- IDA / 60850 ng Macroeconomic and Fis Post Direct Selection Direct 20,000.00 0.00 Canceled ganize capacity-building tr 1 21 25 21 cal Management aining to ensure implement ation of the newly revised General Taxation Law A2/CS/015 / National cons ultant to develop and form Component A: Strengtheni ulate regulations and to or 2019-03-1 2019-03- 2019-05- 2019-11- IDA / 60850 ng Macroeconomic and Fis Post Direct Selection Direct 20,000.00 0.00 Canceled ganize capacity-building tr 1 21 25 21 cal Management aining to ensure implement ation of the newly revised Corporate Income Tax Law A2/CS/016 / National senio r consultant to provide tech Component A: Strengtheni nical support to reduce sha Individual Cons 2019-04-0 2019-05- 2019-06- 2019-07- 2020-01- IDA / 60850 ng Macroeconomic and Fis Post Open 20,000.00 0.00 Canceled dow economy through the ultant Selection 1 20 10 15 11 cal Management expansion of tax base and the Tax Administration and Information System (TAIS) A2/CS/019 / National senio r consultant to ensure impl Component A: Strengtheni 2019-03-1 2019-03- 2019-05- 2019-11- ementation and further imp IDA / 60850 ng Macroeconomic and Fis Post Direct Selection Direct 24,000.00 0.00 Canceled 1 21 25 21 rovements of the revenue f cal Management orecasting models and dat abase A2/CS/020 / National cons Component A: Strengtheni ultant to ensure implement Individual Cons 2019-04-0 2019-05- 2019-06- 2019-07- 2020-01- IDA / 60850 ng Macroeconomic and Fis Post Open 12,000.00 0.00 Canceled ation and further improvem ultant Selection 1 20 10 15 11 cal Management ents of the revenue forecas ting models and database A31/CS/012 / National con Component A: Strengtheni sultant on updating onlendi Individual Cons 2019-03-2 2019-06- 2019-05- 2019-07- 2019-06- 2019-08- 2019-07- 2019-08- 2020-01- 2020-09- IDA / 60850 ng Macroeconomic and Fis Post Open 12,000.00 12,000.00 Completed ng database and assisting ultant Selection 5 17 13 26 03 02 08 05 04 04 cal Management DMO to resovle non-perfor ming and overdue loans A31/CS/013 / National con sultant on improving onlen Component A: Strengtheni ding loan processing, devel Individual Cons 2019-03-2 2019-06- 2019-05- 2019-08- 2019-06- 2019-08- 2019-07- 2019-08- 2020-01- 2020-09- IDA / 60850 ng Macroeconomic and Fis Post Open 12,000.00 12,000.00 Completed oping leverages for timely r ultant Selection 5 17 13 02 03 05 08 05 04 01 cal Management epayment and reflect them on updated onlending loan regulation A32/CS/009 / National con sultant on designing the str ucture and determining fun Component A: Strengtheni ctional requirements of the Individual Cons 2019-05-1 2019-06- 2019-07- 2019-08- 2020-02- IDA / 60850 ng Macroeconomic and Fis Post Open 14,400.00 0.00 Canceled ODA Management informat ultant Selection 0 28 19 23 19 cal Management ion system (ODAMIS) and D evelop Economic cooperati on information manageme nt system (ECIMS) - collecting and updating … A32/CS/012 / National con sultant to prepare official d Component A: Strengtheni 2019-03-1 2019-11- 2019-03- 2019-11- 2019-05- 2019-11- 2019-11- 2020-06- evelopment assistance port IDA / 60850 ng Macroeconomic and Fis Post Direct Selection Direct 6,000.00 10,500.00 Completed 1 12 21 13 25 13 21 13 folio report which includes cal Management current statistics, trends an d main performance of sect ors. B11/CS/015 / National con sultant to provide technical Component B: Improving t 2019-02-2 2019-09- 2019-03- 2019-09- 2019-05- 2019-09- 2019-11- support to the system of st IDA / 60850 he efficiency of Public Fina Post Direct Selection Direct 19,800.00 56,000.00 Terminated 5 11 07 20 11 30 07 affing and salaries on impr ncial Management ovement of appropriate me chanism for planning B11/CS/013 / National seni or consultant to assess and Component B: Improving t Individual Cons 2019-03-0 2019-04- 2019-05- 2019-06- 2019-12- analyze budget expenditur IDA / 60850 he efficiency of Public Fina Post Open 24,000.00 0.00 Canceled ultant Selection 1 19 10 14 11 e norm and normative cove ncial Management ring all sectors and revise t hem for approval B11/CS/014 / National con sultant to assess and analy Component B: Improving t Individual Cons 2019-03-0 2019-04- 2019-05- 2019-06- 2019-12- se budget expenditure nor IDA / 60850 he efficiency of Public Fina Post Open 18,000.00 0.00 Canceled ultant Selection 1 19 10 14 11 m and normatives covering ncial Management all sectors and revise them for approval B21/CS/012 / National con Component B: Improving t sultant to provide support t Individual Cons 2019-03-0 2019-03- 2019-04- 2019-04- 2019-05- 2019-04- 2019-06- 2019-04- 2019-12- 2020-02- IDA / 60850 he efficiency of Public Fina Post Open 9,600.00 9,450.00 Completed o deliver IPSAS training for ultant Selection 1 13 19 09 10 10 14 10 11 28 ncial Management trainers other accounting r elated trainings B22/CS/014 / National con sultant to carry out an in-d epth evaluation with intern Component B: Improving t Individual Cons 2019-04-0 2019-09- 2019-05- 2019-10- 2019-06- 2019-10- 2019-07- 2019-10- 2020-01- ational consultant to identif IDA / 60850 he efficiency of Public Fina Post Open 27,000.00 27,000.00 Signed ultant Selection 1 17 20 15 10 15 15 15 11 y gaps between existing TD ncial Management business procedures and th e new functionalities availa ble in the new version of G FMIS B22/CS/017 / National con Component B: Improving t Individual Cons 2019-03-1 2019-05- 2019-05- 2019-06- 2019-12- sultant to lead to implemen IDA / 60850 he efficiency of Public Fina Post Open 10,000.00 0.00 Canceled ultant Selection 5 03 24 28 25 t integrated Payroll systen ncial Management nationwide B22/CS/018 / National con Component B: Improving t sultant /IT specialist/ to pro Individual Cons 2019-03-1 2019-04- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-05- 2019-12- 2021-03- IDA / 60850 he efficiency of Public Fina Post Open 15,000.00 33,000.00 Completed vide technical support to i ultant Selection 5 03 03 02 24 02 28 02 25 04 ncial Management mplement Integrated Payro ll system B22/CS/019 / National con Component B: Improving t Individual Cons 2019-03-1 2019-04- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-05- 2019-12- 2021-06- sultant to provide functiona IDA / 60850 he efficiency of Public Fina Post Open 12,000.00 31,602.82 Completed ultant Selection 5 03 03 02 24 02 28 02 25 30 l support to implement Inte ncial Management grated Payroll system B22/CS/020 / National con sultant to provide functiona Component B: Improving t Individual Cons 2019-03-1 2019-04- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-05- 2019-12- 2021-12- l support to implement Inte IDA / 60850 he efficiency of Public Fina Post Open 8,000.00 26,615.91 Completed ultant Selection 5 03 03 02 24 02 28 02 25 31 grated Payroll system (help ncial Management desk #1 central budget ent ities and UB ) B22/CS/021 / National con sultant to provide functiona Component B: Improving t Individual Cons 2019-03-1 2019-04- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-05- 2019-12- l support to implement Inte IDA / 60850 he efficiency of Public Fina Post Open 7,000.00 35,305.50 Signed ultant Selection 5 03 03 02 24 02 28 02 25 grated Payroll system (help ncial Management desk #2 local budget-west ern aimags) B22/CS/022 / National con sultant to provide functiona Component B: Improving t Individual Cons 2019-03-1 2019-04- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-05- 2019-12- l support to implement Inte IDA / 60850 he efficiency of Public Fina Post Open 7,000.00 34,116.37 Signed ultant Selection 5 03 03 02 24 02 28 02 25 grated Payroll system (help ncial Management desk #3 local budget entiti es central aimags) B22/CS/023 / National con sultant to provide functiona Component B: Improving t Individual Cons 2019-03-1 2019-04- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-05- 2019-12- 2022-02- l support to implement Inte IDA / 60850 he efficiency of Public Fina Post Open 7,000.00 15,400.00 Completed ultant Selection 5 03 03 02 24 02 28 02 25 28 grated Payroll system (help ncial Management desk #4 local budget-easte rn aimags) B31/CS/006 / National con Component B: Improving t sultant to develop special p Individual Cons 2019-03-0 2019-05- 2019-04- 2019-06- 2019-05- 2019-07- 2019-06- 2019-07- 2019-12- 2021-06- IDA / 60850 he efficiency of Public Fina Post Open 18,000.00 36,000.00 Completed urposed software such as e ultant Selection 1 31 19 25 10 01 14 01 11 29 ncial Management -huulga /e-statement of acc ount/ B31/CS/007 / National con sultant to analyze and desi Component B: Improving t gn all systems that used by Individual Cons 2019-03-0 2019-04- 2019-05- 2019-06- 2019-12- IDA / 60850 he efficiency of Public Fina Post Open 24,000.00 0.00 Canceled MOF and prepare documen ultant Selection 1 19 10 14 11 ncial Management ts for integration of that sy stems (GFMIS, Fiscal, BPIS, PMMIS, DMFAS and ODAMI S) B31/CS/009 / National con Component B: Improving t Individual Cons 2019-02-2 2019-03- 2019-04- 2019-04- 2019-05- 2019-04- 2019-06- 2019-04- 2019-12- 2022-01- sultant to design and confi IDA / 60850 he efficiency of Public Fina Post Open 24,000.00 54,000.00 Completed ultant Selection 5 15 15 05 06 05 10 05 07 31 gure MOF’s datacenter. ncial Management B33/CS/009 / National Con sultant to analyse 2017, 2 018 complaints which sub Component B: Improving t mited to not only Ministry o Individual Cons 2019-02-2 2019-04- 2019-05- 2019-06- 2019-12- IDA / 60850 he efficiency of Public Fina Post Open 34,500.00 0.00 Canceled f Finance but also, courts' d ultant Selection 5 15 06 10 07 ncial Management atabase. To develop the a mendment of the relevant procurement documents b ased on the findings and re commendations… B33/CS/010 / National Con sultant to conduct research on 13 standard bidding doc Component B: Improving t uments, bid evaluation pro Individual Cons 2019-02-2 2019-04- 2019-05- 2019-06- 2019-12- IDA / 60850 he efficiency of Public Fina Post Open 34,500.00 0.00 Canceled cedure for consultant servi ultant Selection 5 15 06 10 07 ncial Management ces and develop amendme nt of the relevant bidding d ocuments based on the fin dings and recommendation s. B4/CS/010 / National cons Component B: Improving t ultant for improving policy, Individual Cons 2019-03-1 2019-04- 2019-05- 2019-04- 2019-05- 2019-04- 2019-06- 2019-04- 2019-12- IDA / 60850 he efficiency of Public Fina Post Open 24,000.00 83,678.78 Signed consistency of activities of i ultant Selection 5 02 03 26 24 26 28 26 25 ncial Management nvestment projects finance d from different sources B4/CS/012 / National cons ultant to design investment Component B: Improving t development model for pro Individual Cons 2019-04-1 2019-06- 2019-06- 2019-07- 2020-01- IDA / 60850 he efficiency of Public Fina Post Open 15,000.00 0.00 Canceled vinces as Arkhangai, Dorno ultant Selection 5 03 24 29 25 ncial Management d, Dundgovi, Uvs, Khovd ai mags and Songinokhairkha n district B4/CS/013 / National cons Component B: Improving t ultant to provide translatio 2019-03-1 2019-03- 2019-05- 2019-11- IDA / 60850 he efficiency of Public Fina Post Direct Selection Direct 4,000.00 0.00 Canceled n service of reports, propos 5 25 29 25 ncial Management al, paper, procedure and tr aining materials C11/CS/012 / National con Component C: Enhancing Individual Cons 2019-09-3 2019-10- 2019-11- 2019-12- 2019-12- 2019-12- 2020-01- 2019-12- 2020-07- 2020-08- sultant to review and make IDA / 60850 Post Open 10,800.00 10,800.00 Completed Financial Sector Stability ultant Selection 0 14 18 27 09 27 13 27 11 31 amendments to the securiti es laws of Mongolia. C11/CS/014 / National con sultant to conduct research on international good prati Component C: Enhancing Individual Cons 2019-03-3 2019-03- 2019-05- 2019-04- 2019-06- 2019-04- 2019-07- 2019-04- 2020-01- 2019-10- ce of supporting and encou IDA / 60850 Post Open 10,800.00 10,800.00 Completed Financial Sector Stability ultant Selection 1 18 19 09 09 09 14 10 10 10 raging stock market throug h tax incentives and prepar e recommendation on Mon golian legal environment. C11/CS/015 / National con sultant to review and make Component C: Enhancing Individual Cons 2019-06-3 2019-03- 2019-08- 2019-04- 2019-09- 2019-05- 2019-10- 2019-05- 2020-04- 2019-10- amendments to the Propert IDA / 60850 Post Open 12,600.00 9,000.00 Completed Financial Sector Stability ultant Selection 0 18 18 22 08 15 13 15 10 14 y appraisal law and its relat ed regulations and organiz e workshops and discussio n C11/CS/016 / National con sultant to develop model/m Component C: Enhancing Individual Cons 2019-07-3 2019-06- 2019-09- 2019-08- 2019-10- 2019-10- 2019-11- 2019-10- 2020-05- 2020-07- ethodology for business/fin IDA / 60850 Post Open 23,400.00 20,400.00 Completed Financial Sector Stability ultant Selection 0 26 17 30 08 02 12 02 10 31 ancial valuation of property appraisal industry and wor kshops and discussions C11/CS/017 / National con sultant to conduct research Component C: Enhancing Individual Cons 2019-05-3 2019-05- 2019-07- 2019-06- 2019-08- 2019-06- 2019-09- 2019-06- 2020-03- 2020-03- IDA / 60850 Post Open 16,650.00 16,650.00 Completed on "General law of compuls Financial Sector Stability ultant Selection 1 07 19 21 09 21 13 21 11 20 ory insurance products law s." C11/CS/018 / National con Component C: Enhancing Individual Cons 2019-03-3 2019-04- 2019-05- 2019-06- 2019-06- 2019-06- 2019-07- 2019-06- 2020-01- 2019-09- sultant to prepare the bulle IDA / 60850 Post Open 3,000.00 3,000.00 Completed Financial Sector Stability ultant Selection 1 10 19 10 09 10 14 10 10 09 tin to improve activity of in vestor relations. C11/CS/020 / National con sultant to review and make Component C: Enhancing Individual Cons 2019-05-3 2019-05- 2019-07- 2019-06- 2019-08- 2019-06- 2019-09- 2019-06- 2020-03- 2020-08- amendments in the law of IDA / 60850 Post Open 10,800.00 21,600.00 Completed Financial Sector Stability ultant Selection 1 01 19 24 09 24 13 24 11 11 Asset backed securities, an d prepare recommendation on cost reducing of securiti sation. C11/CS/021 / National con sultant to review and impro Component C: Enhancing Individual Cons 2019-05-3 2019-07- 2019-08- 2019-09- 2020-03- IDA / 60850 Post Open 10,800.00 0.00 Canceled ve the Mortgage financing Financial Sector Stability ultant Selection 1 19 09 13 11 system and conduct resear ch on related laws. C4/CS/019 / International consultant to conduct rese Component C: Enhancing Individual Cons 2019-04-0 2019-04- 2019-05- 2019-06- 2019-06- 2019-08- 2019-07- 2019-08- 2020-01- 2019-11- arch on 'Reinsurance' mark IDA / 60850 Post Open 28,500.00 24,000.00 Completed Financial Sector Stability ultant Selection 1 23 20 21 10 16 15 23 11 05 et in order to improve curr ent legislation and capacity building C4/CS/021 / International c onsultant to conduct resear ch on introducing internati Component C: Enhancing Individual Cons 2019-05-0 2019-04- 2019-06- 2019-06- 2019-07- 2019-08- 2019-08- 2019-08- 2020-02- 2019-10- IDA / 60850 Post Open 28,500.00 24,150.00 Completed onal practice of own risk so Financial Sector Stability ultant Selection 1 23 19 21 10 16 14 15 10 07 lvency assessment (ORSA) and Risk based capital (RB C), To provide training to F RC staff Page 8 C5/CS/010 / International c onsultant to provide trainin Component C: Enhancing Individual Cons 2019-09-0 2019-06- 2019-10- 2019-11- 2019-12- 2020-06- IDA / 60850 Post Open 45,000.00 0.00 Canceled g on methods to conduct s Financial Sector Stability ultant Selection 1 18 20 10 15 12 ystemic risk analysis and a ssessment C5/CS/011 / International c onsultant in developing DS Component C: Enhancing Individual Cons 2019-12-0 2020-01- 2020-02- 2020-03- 2020-09- IDA / 60850 Post Open 60,000.00 0.00 Canceled GE model with an element Financial Sector Stability ultant Selection 1 19 09 15 11 of macroprudential policy C5/CS/014 / Internatinal C Component C: Enhancing Individual Cons 2019-04-0 2019-03- 2019-05- 2019-05- 2019-06- 2019-06- 2019-07- 2019-05- 2020-01- 2021-01- onsultant to develop risk-b IDA / 60850 Post Open 40,000.00 33,800.00 Completed Financial Sector Stability ultant Selection 1 07 20 28 10 04 15 31 11 27 ased audit methodology an d guidelines D1/CS/028 / National cons ultant on the legal framewo Component D: Strengtheni Individual Cons 2019-04-0 2019-05- 2019-06- 2019-07- 2020-01- rk and effective model ena IDA / 60850 ng of the Social Protection Post Open 6,000.00 0.00 Canceled ultant Selection 1 20 10 15 11 bling consolidation of the s System ocial welfare pensions, ben efits, allowances and servic es D1/CS/019 / National cons Component D: Strengtheni ultant to develop institution Individual Cons 2019-05-0 2019-06- 2019-07- 2019-08- 2020-02- IDA / 60850 ng of the Social Protection Post Open 8,000.00 0.00 Canceled al care strategy and/or to a ultant Selection 1 19 10 14 10 System ssist with international con sultant D1/CS/020 / National cons ultant to conduct an assess Component D: Strengtheni Individual Cons 2019-04-0 2019-04- 2019-05- 2019-06- 2019-07- 2020-01- ment for social welfare insti IDA / 60850 ng of the Social Protection Post Open 7,000.00 0.00 Canceled ultant Selection 1 08 20 10 15 11 tutional service, and develo System p a recommendation for po licy and quality standards D1/CS/021 / National cons ultant to fully utilize WAIS, Component D: Strengtheni Individual Cons 2019-06-0 2019-07- 2019-08- 2019-09- 2020-03- PMT-HEB,E-Office to analyz IDA / 60850 ng of the Social Protection Post Open 5,000.00 0.00 Canceled ultant Selection 1 20 10 14 12 e administrative data, / Re System porting and Financing Mod ule Assessment D1/CS/023 / National cons ultant to provide translatio n service on the legal fram Component D: Strengtheni ework and effective model 2019-03-1 2019-03- 2019-05- 2019-11- IDA / 60850 ng of the Social Protection Post Direct Selection Direct 1,600.00 0.00 Canceled enabling consolidation of th 2 22 26 22 System e social welfare pensions, b enefits, allowances and ser vices including institutional care development strategy proposal D1/CS/025 / National cons ultant to provide translatio n service on the developm Component D: Strengtheni 2019-03-1 2019-03- 2019-05- 2019-11- ent of institutional care str IDA / 60850 ng of the Social Protection Post Direct Selection Direct 1,600.00 0.00 Canceled 2 22 26 22 ategy and an assessment f System or social welfare institution al service, and recommend ation for policy and quality standards D1/CS/026 / National cons ultant to provide translatio n service on new types of s Component D: Strengtheni ervices on poverty target p 2019-04-0 2019-04- 2019-06- 2019-12- IDA / 60850 ng of the Social Protection Post Direct Selection Direct 1,600.00 0.00 Canceled rograms that will be covere 1 11 15 12 System d employment, health, edu cation and compensation o f electricity etc., new types of services on poverty targ et program, and others.. D2/CS/018 / International c onsultant on the design of Pension Parametric reforms Component D: Strengtheni 2019-06-0 2019-05- 2019-06- 2019-05- 2019-08- 2019-05- 2020-02- in line with the State Polic IDA / 60850 ng of the Social Protection Prior Direct Selection Direct 47,000.00 40,500.00 Signed 1 28 11 29 15 29 11 y on Pension Reform and lo System ng-term Actuarial projectio ns on proposed design opti ons (proposed parametric c hanges projection), D2/CS/019 / National cons ultant on the design of Pen sion Parametric reforms in l Component D: Strengtheni Individual Cons 2019-06-0 2019-07- 2019-07- 2019-08- 2019-09- 2020-03- ine with the State Policy o IDA / 60850 ng of the Social Protection Post Open 6,000.00 0.00 Canceled ultant Selection 1 22 20 10 14 12 n Pension Reform and long- System term Actuarial projections on proposed design option s (proposed parametric cha nges projection), D2/CS/015 / National cons ultant to review the rationa le, fiscal costs, institutional Component D: Strengtheni 2019-04-0 2019-04- 2019-06- 2019-12- requirements and potential IDA / 60850 ng of the Social Protection Post Direct Selection Direct 8,000.00 0.00 Canceled 1 11 15 12 benefits of a matching cont System ribution scheme, defining w ays to determine non-cash contribution scheme/pilot s tudy E/CS/009 / Project coordin Component E: Project Man 2019-03-0 2019-06- 2019-03- 2019-06- 2019-05- 2019-06- 2019-11- IDA / 60850 Prior Direct Selection Direct 30,000.00 22,542.92 Terminated ator - PIU core staff agement and Monitoring 1 13 11 07 15 10 11 E/CS/010 / Financial Mana Component E: Project Man 2019-03-0 2019-08- 2019-03- 2019-06- 2019-05- 2019-09- 2019-11- IDA / 60850 Prior Direct Selection Direct 21,600.00 21,615.90 Terminated gement Specialist - PIU cor agement and Monitoring 1 26 11 30 15 30 11 e staff E/CS/011 / Procurement Sp Component E: Project Man 2019-03-0 2019-06- 2019-03- 2019-05- 2019-11- IDA / 60850 Prior Direct Selection Direct 21,600.00 0.00 Canceled ecialist - PIU core staff agement and Monitoring 1 24 11 15 11 E/CS/012 / Monitoring-Eval Component E: Project Man 2019-03-0 2019-06- 2019-03- 2019-05- 2019-11- IDA / 60850 Prior Direct Selection Direct 21,600.00 0.00 Canceled uation Specialist - PIU core agement and Monitoring 1 24 11 15 11 staff E/CS/013 / Audit fee for 20 Component E: Project Man 2019-03-0 2019-03- 2019-05- 2019-11- IDA / 60850 Prior Direct Selection Direct 3,000.00 0.00 Canceled 19 agement and Monitoring 1 11 15 11 C5/CS/013 / National Cons ultant to review the existin g legal framework for finan Component C: Enhancing Individual Cons 2019-07-0 2019-09- 2019-08- 2019-10- 2019-09- 2019-10- 2019-10- 2019-10- 2020-04- 2020-09- cial derivatives and other h IDA / 60850 Post Open 15,000.00 14,000.00 Completed Financial Sector Stability ultant Selection 1 02 19 16 09 16 14 16 11 17 edging instrument and thei r application in Mongolia, a nd identification legal and practical issues concerning enforcement of collateral… A32/CS/1 / National consul tant (Software developmen t): Develop Economic coopera Component A: Strengtheni Individual Cons 2019-03-2 2019-06- 2019-05- 2019-08- 2019-06- 2019-08- 2019-07- 2019-08- 2020-01- 2021-02- tion information managem IDA / 60850 ng Macroeconomic and Fis Post Open 25,000.00 12,000.00 Completed ultant Selection 5 06 13 02 03 02 08 02 04 04 ent system (ECIMS) to man cal Management age and record all the infor mation related to the econ omic and development coo peration between Mongolia and its partner countries a A32/CS/02 nd ... / National cons ultant (Software developm ent): Develop ODA project portfo Component A: Strengtheni Individual Cons 2019-04-0 2019-06- 2019-05- 2019-08- 2019-06- 2019-08- 2019-07- 2019-08- 2020-01- 2021-04- lio management software ( IDA / 60850 ng Macroeconomic and Fis Post Open 25,000.00 28,000.00 Completed ultant Selection 1 06 20 01 10 02 15 02 11 01 ODAFIN) to improve the aut cal Management omation of approving and r eviewing procedure of proj ect financing and tax exem ption of ODA projects. - System will be available .. .B21/CS/016 / International consultant /PUM expert/ to Component B: Improving t 2019-06-1 2019-03- 2019-06- 2019-03- 2019-08- 2019-04- 2020-02- lead carrying out the qualit IDA / 60850 he efficiency of Public Fina Post Direct Selection Direct 10,000.00 6,650.00 Terminated 0 14 20 25 24 01 20 y control review team on a ncial Management udit firms according to the revised regulation B22/CS/016 / Consulting fir m: on development Integra ted of Payroll System (Goo Component B: Improving t ksoft LLC) 2019-04-0 2019-04- 2019-06- 2019-12- IDA / 60850 he efficiency of Public Fina Post Direct Selection Direct 40,000.00 0.00 Canceled - (i) organize the system pil 1 11 15 12 ncial Management oting for selected budget s upervisors, (ii) deliver the t echnical end-users' training to the MOF, (iii) deliver end -users around 6000 particip A1/CS/010 / National cons ants ultant on compiling model and methodology of project Component A: Strengtheni Individual Cons 2019-03-2 2019-09- 2019-05- 2019-11- 2019-06- 2019-11- 2019-07- 2019-11- 2020-01- 2021-11- ion, statistical data prepara IDA / 60850 ng Macroeconomic and Fis Post Open 18,000.00 36,000.00 Completed ultant Selection 5 24 13 13 03 13 08 13 04 12 tion for Balance of Paymen cal Management t, introducing them to MOF, presenting results to Mana gement and staffs of MOF A1/CS/011 / National cons ultant on introducing Forec asting and Policy Analysis S Component A: Strengtheni ystem (FPAS) to Ministry of Individual Cons 2019-08-0 2019-09- 2019-10- 2019-11- 2020-05- IDA / 60850 ng Macroeconomic and Fis Post Open 24,000.00 0.00 Canceled Finance, compiling regulati ultant Selection 1 19 10 14 12 cal Management on draft of introducing FPA S, presenting economic gro wth projection to Managem ent and staffs of Ministry of Finance. A1/CS/012 / National cons ultant on analyzing consist ency of fiscal policy and m Component A: Strengtheni Individual Cons 2019-08-0 2019-05- 2019-09- 2019-11- 2019-10- 2019-11- 2019-11- 2019-11- 2020-05- 2021-11- onetary policy, making rec IDA / 60850 ng Macroeconomic and Fis Post Open 24,000.00 48,000.00 Completed ultant Selection 1 15 19 13 10 13 14 13 12 12 ommendation on enhancin cal Management g coherence of the policy, drafting regulation and met hodology, and introducing t hem into MOF A1/CS/013 / National cons ultant on developing propo Component A: Strengtheni sals for improving the finan Individual Cons 2019-04-0 2019-05- 2019-05- 2019-11- 2019-06- 2019-11- 2019-07- 2019-11- 2020-01- 2021-11- IDA / 60850 ng Macroeconomic and Fis Post Open 18,000.00 36,000.00 Completed cing system of export deve ultant Selection 1 15 20 13 10 13 15 13 11 12 cal Management lopment and providing sup port to the development of a relevant legal environme nt A1/CS/015 / National cons ultant to study infrastructur e requirements and prepar Component A: Strengtheni e proposals to develop an i Individual Cons 2019-02-2 2019-02- 2019-04- 2019-05- 2019-05- 2019-05- 2019-06- 2019-05- 2019-12- 2019-12- IDA / 60850 ng Macroeconomic and Fis Post Open 18,000.00 18,000.00 Completed ntegrated database and th ultant Selection 5 27 15 02 06 02 10 02 07 02 cal Management e design of an application t hat administers the databa se in order to align the targ ets and the measures of th e government action progr B21/CS/011 / International am consultant to conduct the I Component B: Improving t Individual Cons 2019-10-0 2019-06- 2019-11- 2019-12- 2020-01- 2020-07- PSAS training for trainers a IDA / 60850 he efficiency of Public Fina Post Open 24,000.00 0.00 Canceled ultant Selection 1 17 19 10 14 12 nd to provide a support to ncial Management establish sustainable traini ng system on IPSAS at the nationwide A1/CS/008 / National cons ultant on making policy rec ommendation on economic Component A: Strengtheni structural changes and enh Individual Cons 2019-02-2 2019-03- 2019-04- 2019-04- 2019-05- 2019-05- 2019-06- 2019-05- 2019-12- IDA / 60850 ng Macroeconomic and Fis Prior Open 26,400.00 63,455.37 Signed ancing inclusive growth an ultant Selection 5 06 15 29 06 03 10 01 07 cal Management d providing support to the development of a relevant l egal environment, and a co ordinating consultant to th e sub-component A1 A1/CS/014 / National cons ultant on making recomme Component A: Strengtheni Individual Cons 2019-04-0 2019-11- 2019-05- 2020-01- 2019-06- 2020-01- 2019-07- 2020-01- 2020-01- ndation on introducing GFS IDA / 60850 ng Macroeconomic and Fis Post Open 18,000.00 49,164.52 Signed ultant Selection 1 19 20 09 10 09 15 09 11 2014 into macroeconomic s cal Management tatistical data and creating required database. A31/CS/009 / National con sultant on providing evalua tion and assessment on de bt management performan Component A: Strengtheni 2019-02-2 2019-05- 2019-03- 2019-05- 2019-05- 2019-05- 2019-11- ce in accordance with inter IDA / 60850 ng Macroeconomic and Fis Post Direct Selection Direct 24,000.00 22,500.00 Terminated 0 01 02 07 06 02 02 national methodology and cal Management make suggestions on areas of improvement and monit or implementation on regul ar basis and Coordinating c onsultant A31 B4/CS/014 / National cons ultant to create a detailed video on the approved proc Component B: Improving t edure and methodology on Individual Cons 2019-05-2 2019-06- 2019-06- 2019-06- 2019-06- 2019-06- 2019-08- 2019-06- 2020-01- 2019-11- IDA / 60850 he efficiency of Public Fina Post Direct 2,300.00 2,152.08 Completed appraisal and selection, pro ultant Selection 9 18 08 19 29 18 03 18 30 16 ncial Management ject analysis, and on-going project rationalization, vide o training on Public Invest ment Management Integrat ed System. D2/CS/007 / International c Component D: Strengtheni onsultant to support deter Individual Cons 2020-02-0 2020-03- 2020-04- 2020-05- 2020-08- IDA / 60850 ng of the Social Protection Post Open 30,000.00 0.00 Canceled mining ways to expand cov ultant Selection 2 22 12 17 15 System erage and reduce contribut ion debts B22/CS/005 / Consulting fir m on development of additi onal modules and functions Component B: Improving t of GFMIS system and also p 2018-10-3 2018-11- 2019-01- 2019-07- IDA / 60850 he efficiency of Public Fina Post Direct Selection Direct 98,000.00 0.00 Canceled urchase of hardware. - Con 1 10 14 13 ncial Management figuration of real time gros s settlement, - Multicurrenc y function configuration, - GFMIS 7 user license upgra de B22/CS/008 / National con sultant on improving execu tion for better delivery i. re Component B: Improving t view and assess current sit Individual Cons 2019-12-3 2020-03- 2020-02- 2020-06- 2020-03- 2020-06- 2020-04- 2020-06- 2021-04- 2021-03- IDA / 60850 he efficiency of Public Fina Post Open 18,000.00 18,000.00 Completed uation of internal control of ultant Selection 1 10 18 04 10 04 14 04 14 31 ncial Management treasury through GFMIS an d produce the report for be tter delivery, ii. prepare the guideline on practice intern al control B22/CS/013 / National con sultant to provide technical Component B: Improving t Individual Cons 2019-12-3 2020-02- 2020-03- 2020-04- 2020-10- support to TD on configurat IDA / 60850 he efficiency of Public Fina Post Open 24,000.00 0.00 Canceled ultant Selection 1 18 10 14 11 ion of Real time gross settl ncial Management ement and Multicurrency fu nction configuration B22/CS/015 / Consulting fir m: on improvement E-taila Component B: Improving t 2019-12-1 2020-02- 2019-12- 2020-04- 2020-02- 2020-04- 2020-08- 2021-01- n system comply with IPSA IDA / 60850 he efficiency of Public Fina Post Direct Selection Direct 20,000.00 15,878.70 Completed 5 20 25 23 28 23 26 31 S, its related renewed regul ncial Management ations and guidance (Inter active BI LLC) D1/CS/007 / National cons ultant on refinement of SP i Component D: Strengtheni nput for poverty reduction Individual Cons 2018-11-3 2019-04- 2019-01- 2019-02- 2019-03- 2019-09- IDA / 60850 ng of the Social Protection Post Open 8,000.00 0.00 Canceled strategy and Government n ultant Selection 0 03 18 08 15 11 System ational programs (specializ ed institutional care reform program for elders) D1/CS/009 / National cons Component D: Strengtheni ultant to analyze administr Individual Cons 2018-04-3 2018-06- 2018-07- 2018-08- 2018-12- IDA / 60850 ng of the Social Protection Post Open 8,200.00 0.00 Canceled ative data and to support t ultant Selection 0 18 09 13 11 System he improvement of Social welfare programs D1/CS/022 / National cons ultant to improve services on poverty target programs Component D: Strengtheni Individual Cons 2019-12-0 2020-01- 2020-02- 2020-03- 2020-09- linked to the conditions rel IDA / 60850 ng of the Social Protection Post Open 5,000.00 0.00 Canceled ultant Selection 1 19 09 15 11 ated to employment, educa System tion and health etc.., within the framework of amendin g Social Welfare Law D2/CS/005 / International c Component D: Strengtheni onsultant on overall govern Individual Cons 2020-03-0 2020-04- 2020-05- 2020-06- 2020-09- IDA / 60850 ng of the Social Protection Post Open 34,000.00 0.00 Canceled ance framework for pensio ultant Selection 1 19 10 14 12 System n and for social insurance f und management D2/CS/006 / National cons Component D: Strengtheni ultant for overall governan Individual Cons 2020-03-0 2019-12- 2020-04- 2020-01- 2020-05- 2020-01- 2020-06- 2020-01- 2020-09- 2020-06- IDA / 60850 ng of the Social Protection Post Open 8,000.00 8,000.00 Completed ce framework for pension a ultant Selection 1 19 19 14 10 14 14 14 12 30 System nd for social insurance fund management D2/CS/016 / National Cons Component D: Strengtheni Individual Cons 2019-09-0 2019-10- 2019-11- 2019-12- 2020-06- ultant to design and condu IDA / 60850 ng of the Social Protection Post Open 6,000.00 0.00 Canceled ultant Selection 1 20 10 15 12 ct public awareness campai System gn D1/CS/024 / National cons Component D: Strengtheni 2020-01-0 2020-01- 2020-03- 2020-09- IDA / 60850 Post Direct Selection Direct 4,800.00 0.00 Canceled ultant to provide translatio ng of the Social Protection 1 11 16 12 n services System D1/CS/04 / National consul Component D: Strengtheni Individual Cons 2020-01-0 2020-02- 2020-03- 2020-04- 2020-10- IDA / 60850 Post Open 8,000.00 0.00 Canceled tant on improvement of PM ng of the Social Protection ultant Selection 1 19 11 15 12 T utilization System C4/CS/018 / International consultant to conduct rese Component C: Enhancing Individual Cons 2020-01-1 2020-03- 2020-03- 2020-04- 2020-10- arch on 'Regulatory Sandbo IDA / 60850 Post Open 28,500.00 0.00 Canceled Financial Sector Stability ultant Selection 2 01 22 26 23 x' in securities and insuran ce market and provide trai ning to FRC staff C21/CS/004 / International Component C: Enhancing Individual Cons 2020-02-1 2020-03- 2020-04- 2020-05- 2020-07- consultant on project appra IDA / 60850 Post Open 28,000.00 0.00 Canceled Financial Sector Stability ultant Selection 0 30 20 25 24 isal, project development a nd risk management B31/CS/002 / Consulting s ervice to develop a compre hensive documentation of i Component B: Improving t nformation technology envi Individual Cons 2019-12-0 2020-01- 2020-02- 2020-03- 2021-03- IDA / 60850 he efficiency of Public Fina Post Open 54,000.00 0.00 Canceled ronments to improve the n ultant Selection 2 20 10 16 16 ncial Management etwork infrastructure and s ecurity equipment, infrastr ucture of the IT network, to improve the network capac ity of systems and security B13/CS/012 / Consulting fir m: Component B: Improving t - To provide translation ser 2019-12-2 2020-03- 2020-01- 2020-04- 2020-03- 2020-06- 2020-09- IDA / 60850 he efficiency of Public Fina Post Direct Selection Direct 15,000.00 12,817.00 Signed vice for the updated IPPF (I 7 11 06 22 11 09 07 ncial Management nternational Professional Pr actice Framework-2017) fro m ENGLISH to MONGOLIAN with official authorization fr The IIA / International B21/CS/05 om Component B: Improving t Consultant for providing su Individual Cons 2019-03-0 2019-04- 2019-05- 2019-06- 2019-12- IDA / 60850 he efficiency of Public Fina Post Open 31,500.00 0.00 Canceled pport on implementing the ultant Selection 1 19 10 14 11 ncial Management International Public Sector Accounting Standards B21/CS/11 / International c onsultant to conduct the IP Component B: Improving t Individual Cons 2019-03-3 2019-03- 2019-04- 2019-06- 2019-04- 2019-06- 2019-06- 2019-06- 2019-12- 2019-09- SAS training for trainers an IDA / 60850 he efficiency of Public Fina Post Direct 25,000.00 25,000.00 Completed ultant Selection 0 14 09 20 30 19 04 19 01 13 d to provide a support to es ncial Management tablish sustainable training system on IPSAS at the nati onwide B22/CS/024 / National con Component B: Improving t sultant to provide policy re Individual Cons 2019-10-0 2019-10- 2019-10- 2018-10- 2019-11- 2018-10- 2019-12- 2018-10- 2020-06- 2021-01- IDA / 60850 he efficiency of Public Fina Post Direct 28,800.00 21,600.00 Completed search and advice on mana ultant Selection 1 04 11 29 01 29 06 29 03 03 ncial Management ging the transition to IPSAS and GFS compliance B22/CS/025 / Consultancy firm service to built Applica Component B: Improving t 2019-12-0 2020-03- 2019-12- 2020-03- 2020-02- 2020-05- 2020-08- 2021-01- tion program interfaces for IDA / 60850 he efficiency of Public Fina Post Direct Selection Direct 250,000.00 220,000.00 Completed 1 30 11 30 14 19 12 31 Freebalance to link with Pa ncial Management yroll system, glass account law and other systems. B31/CS/010 / National con sultant to optimize and ma Component B: Improving t Individual Cons 2019-09-2 2019-10- 2019-11- 2019-11- 2019-12- 2019-11- 2020-01- 2019-11- 2020-07- 2021-05- nage application-related ca IDA / 60850 he efficiency of Public Fina Post Open 10,500.00 10,500.00 Completed ultant Selection 7 09 15 01 06 01 10 01 08 30 lls from Treasury departme ncial Management nt specialists and budgetar y organizations - long term contract Page 9 B31/CS/0007 / National co nsultant to analyze and des Component B: Improving t ign all systems that used b Individual Cons 2019-03-0 2019-05- 2019-03- 2019-06- 2019-04- 2019-06- 2019-05- 2019-06- 2019-11- 2020-06- IDA / 60850 he efficiency of Public Fina Post Direct 24,000.00 24,000.00 Completed y MOF and prepare docume ultant Selection 1 23 11 05 01 05 06 05 02 04 ncial Management nts for integration of that s ystems (GFMIS, Fiscal, BPIS , PMMIS, DMFAS and ODAM IS) B32/CS/003 / National con Component B: Improving t Individual Cons 2019-08-0 2019-07- 2019-09- 2019-08- 2019-10- 2019-08- 2019-11- 2019-09- 2020-05- sultant for Training Coordin IDA / 60850 he efficiency of Public Fina Post Open 40,500.00 66,000.00 Signed ultant Selection 1 30 19 19 10 19 14 09 12 ation ncial Management B33/CS/09 / National cons Component B: Improving t ultant to revise procedures Individual Cons 2019-02-2 2019-03- 2019-03- 2019-04- 2019-03- 2019-04- 2019-05- 2019-04- 2019-10- 2020-12- IDA / 60850 he efficiency of Public Fina Post Direct 34,500.00 34,200.00 Completed and guidelines used for pu ultant Selection 5 14 07 11 28 23 02 23 29 07 ncial Management blic procurement in Mongol ia B33/CS/10 / National cons Component B: Improving t ultant to revise standard bi Individual Cons 2019-02-2 2019-03- 2019-03- 2019-04- 2019-03- 2019-04- 2019-05- 2019-04- 2019-10- 2020-12- IDA / 60850 he efficiency of Public Fina Post Direct 34,500.00 34,200.00 Completed dding documents used for ultant Selection 5 14 07 11 28 11 02 11 29 11 ncial Management public procurement in Mon golia B4/CS/015 / National cons ultant (junior IT/technical c onsultant) to develop a Pub Component B: Improving t lic Investment Managemen Individual Cons 2019-07-2 2019-08- 2019-08- 2019-08- 2019-08- 2019-08- 2019-10- 2019-08- 2020-03- 2019-12- IDA / 60850 he efficiency of Public Fina Post Direct 8,500.00 8,500.00 Completed t System and a mobile appl ultant Selection 9 05 08 05 29 06 03 06 31 26 ncial Management ication to support impleme ntation of the new method ologies and enhance transp arency and accountability i n the relevant processes B4/CS/016 / National cons ultant (senior IT/technical c onsultant) to develop a Pub Component B: Improving t lic Investment Managemen Individual Cons 2019-07-2 2019-06- 2019-08- 2019-08- 2019-08- 2019-08- 2019-10- 2019-08- 2020-03- 2019-12- IDA / 60850 he efficiency of Public Fina Post Direct 9,500.00 9,500.00 Completed t System and a mobile appl ultant Selection 9 27 08 06 29 06 03 09 31 26 ncial Management ication to support impleme ntation of the new method ologies and enhance transp arency and accountability i n the relevant processes B4/CS/017 / National cons ultant (team leader) to dev elop a Public Investment M Component B: Improving t anagement System and a Individual Cons 2019-07-2 2019-06- 2019-08- 2019-08- 2019-08- 2019-08- 2019-10- 2019-08- 2020-03- 2019-12- IDA / 60850 he efficiency of Public Fina Post Direct 10,000.00 10,000.00 Completed mobile application to suppo ultant Selection 9 27 08 06 29 06 03 09 31 26 ncial Management rt implementation of the ne w methodologies and enha nce transparency and acco untability in the relevant pr ocesses B4/CS/019 / National cons ultant to implement and ref ine appraisal methodology Component B: Improving t Individual Cons 2019-09-2 2019-09- 2019-10- 2019-09- 2019-10- 2019-09- 2019-12- 2019-09- 2020-05- 2020-10- for estimating the economi IDA / 60850 he efficiency of Public Fina Post Direct 24,000.00 24,000.00 Completed ultant Selection 6 27 06 27 27 27 01 27 29 06 c benefits and social signifi ncial Management cance of public investment projects by producing and updating appraisal templat es and manual B4/CS/12 / National consul tant to improve preparatio Component B: Improving t Individual Cons 2019-11-0 2019-11- 2019-11- 2019-11- 2019-12- 2019-11- 2020-01- 2019-11- 2020-07- 2020-09- n and review of design, dr IDA / 60850 he efficiency of Public Fina Post Direct 12,000.00 12,000.00 Completed ultant Selection 1 15 11 18 02 18 06 15 04 18 awings and cost estimation ncial Management , implementation and moni toring of construction work s B4/CS/018 / National cons ultant to develop a proposa Component B: Improving t Individual Cons 2019-09-2 2019-11- 2019-12- 2020-01- 2020-07- l to improve planning of bu IDA / 60850 he efficiency of Public Fina Post Open 12,000.00 0.00 Canceled ultant Selection 6 14 05 09 07 dget liabilities of PPP projec ncial Management ts in the medium- term fisc al framework C4/CS/022 / National cons ultant (Team Leader) to pro vide further legal assistanc e in implementation of the Component C: Enhancing Individual Cons 2019-09-1 2019-08- 2019-09- 2019-09- 2019-10- 2019-09- 2019-11- 2019-09- 2020-05- 2020-03- IDA / 60850 Post Direct 12,000.00 12,000.00 Completed General Directive to Improv Financial Sector Stability ultant Selection 8 19 28 18 19 18 23 18 21 17 e Legislation of Mongolia u ntil 2020 and prepare a Co mprehensive Legal Handbo ok for State Inspectors of t he FRC C4/CS/023 / National cons ultant (Team Member) to p rovide further legal assista nce in implementation of th Component C: Enhancing Individual Cons 2019-09-1 2019-08- 2019-09- 2019-09- 2019-10- 2019-09- 2019-11- 2019-09- 2020-05- 2020-03- IDA / 60850 Post Direct 10,800.00 10,800.00 Completed e General Directive to Impr Financial Sector Stability ultant Selection 8 27 28 18 19 18 23 18 21 17 ove Legislation of Mongolia until 2020 and prepare a C omprehensive Legal Handb ook for State Inspectors of the FRC C5/CS/01 / Consultant on d Component C: Enhancing Individual Cons 2019-11-2 2020-01- 2020-01- 2020-03- 2020-02- 2020-03- 2020-03- 2020-03- 2020-09- 2020-12- eveloping systemic risk ass IDA / 60850 Post Open 45,000.00 30,000.00 Completed Financial Sector Stability ultant Selection 5 06 13 02 03 02 09 02 05 17 essment model and financi al stability index D1/CS/029 / National Cons ultant to support process a Component D: Strengtheni nalysis of the social welfare Individual Cons 2019-12-0 2019-12- 2020-01- 2020-02- 2020-08- IDA / 60850 ng of the Social Protection Post Direct 8,000.00 0.00 Canceled delivery system and to dev ultant Selection 1 11 01 05 03 System elop a strategic plan for ML SP in regards to the consoli dation of the social welfare programs D1/CS/0020 / National con sultant to conduct an asses sment for social welfare ins Component D: Strengtheni titutional service, and deve Individual Cons 2019-06-0 2019-06- 2019-07- 2019-08- 2020-02- IDA / 60850 ng of the Social Protection Post Direct 7,000.00 0.00 Canceled lop recommendation, polici ultant Selection 1 11 02 06 02 System es and draft National progr am (Specialized Institution al Care Reform Program) a nd develop quality standar ds D1/CS/09 / National consul Component D: Strengtheni tant to analyze administrati Individual Cons 2020-01-0 2020-01- 2020-02- 2020-03- 2020-09- IDA / 60850 ng of the Social Protection Post Direct 8,200.00 0.00 Canceled ve data and to support the ultant Selection 1 11 01 07 03 System improvement of Social welf are programs D1/CS/21 / National consul tant to fully utilize WAIS, P Component D: Strengtheni Individual Cons 2020-03-0 2020-04- 2020-05- 2020-06- 2020-12- MT-HEB,E-Office to analyze IDA / 60850 ng of the Social Protection Post Open 8,200.00 0.00 Canceled ultant Selection 1 19 10 14 11 administrative data and to System support the improvement o f Social welfare programs D2/CS/0001 / International consultant to design Pensio Component D: Strengtheni n Parametric reforms in lin Individual Cons 2019-06-0 2019-05- 2019-06- 2019-05- 2019-07- 2019-05- 2019-08- 2019-05- 2020-02- 2020-07- IDA / 60850 ng of the Social Protection Post Direct 53,000.00 40,500.00 Completed e with the State Policy on ultant Selection 1 22 11 29 02 29 06 29 02 21 System Pension Reform and long-te rm Actuarial projections on proposed design options; / DB model/ D2/CS/16 / National Consul Component D: Strengtheni Individual Cons 2020-01-0 2020-01- 2020-02- 2020-03- 2020-09- tant to design and conduct IDA / 60850 ng of the Social Protection Post Direct 6,000.00 0.00 Canceled ultant Selection 1 11 01 07 03 public awareness campaig System n E/CS/014 / Monitoring-Eval Component E: Project Man Individual Cons 2019-08-0 2019-12- 2019-09- 2019-08- 2019-10- 2020-08- 2019-11- 2019-08- 2020-05- 2020-08- IDA / 60850 Prior Open 21,600.00 1,728.80 Completed uation Specialist - PIU core agement and Monitoring ultant Selection 1 20 19 29 10 17 14 30 12 31 staff A2/CS/13 / National senior consultant to develop and f ormulate regulations and t Component A: Strengtheni Individual Cons 2019-11-1 2019-12- 2019-11- 2019-12- 2019-11- 2019-12- 2019-12- 2019-12- 2020-12- o organize capacity-buildin IDA / 60850 ng Macroeconomic and Fis Post Direct 39,600.00 118,800.00 Signed ultant Selection 9 11 29 11 29 11 20 12 14 g training to ensure imple cal Management mentation of the newly revi sed tax package laws: Gen eral Taxation Law and Pers onal Income Tax Law A2/CS/15 / National consul tant to develop and formul Component A: Strengtheni ate regulations and to orga Individual Cons 2019-11-1 2019-12- 2019-11- 2019-12- 2019-12- 2019-12- 2020-01- 2019-12- 2021-01- 2020-12- IDA / 60850 ng Macroeconomic and Fis Post Direct 33,600.00 33,600.00 Completed nize capacity-building traini ultant Selection 9 11 29 11 20 12 24 12 18 12 cal Management ng to ensure implementati on of the newly revised Cor porate Income Tax Law and BEPS standards A2/CS/0005 / National con Component A: Strengtheni Individual Cons 2019-11-1 2019-12- 2020-01- 2020-01- 2020-01- 2020-01- 2020-03- 2020-01- 2020-08- 2020-05- sultant to translate the tax IDA / 60850 ng Macroeconomic and Fis Post Open 9,600.00 9,600.00 Completed ultant Selection 9 11 07 10 28 10 03 10 30 08 policy legislation and other cal Management policy documents A2/CS/19 / National consul Component A: Strengtheni tant to ensure implementat Individual Cons 2019-11-1 2019-12- 2020-01- 2020-01- 2020-01- 2020-01- 2020-03- 2020-01- 2021-02- IDA / 60850 ng Macroeconomic and Fis Post Open 33,600.00 103,600.00 Terminated ion and further improveme ultant Selection 9 11 07 10 28 10 03 10 26 cal Management nts of the revenue forecasti ng models and database B11/CS/0004 / National se nior consultant and policy a Component B: Improving t Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- 2019-12- 2019-12- 2019-12- 2022-01- dvisor IDA / 60850 he efficiency of Public Fina Post Direct 91,000.00 126,962.16 Signed ultant Selection 2 11 02 13 02 13 02 13 20 to provide functional suppo ncial Management rt to implementation of bud get expenditure reforms B11/CS/017 / National seni Component B: Improving t or functional consultant to f Individual Cons 2019-11-2 2020-02- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- 2020-02- 2021-01- 2020-12- IDA / 60850 he efficiency of Public Fina Post Direct 12,000.00 5,400.00 Completed inalize BPIS and hand over ultant Selection 2 08 02 17 23 17 27 17 21 24 ncial Management to the Ministry of Finance B12/CS/05 / National cons ultant to make an assessm Component B: Improving t ent of current statistical re Individual Cons 2019-11-1 2019-12- 2019-11- 2019-12- 2019-12- 2019-12- 2020-01- 2019-12- 2022-01- 2021-02- IDA / 60850 he efficiency of Public Fina Post Direct 34,000.00 34,000.00 Completed porting system of Mongolia ultant Selection 9 11 29 11 20 11 24 11 13 10 ncial Management in the context of budget pl anning, identification of fur ther needs for introducing GFS 2014 B12/CS/09 / National cons ultant to make an assessm ent of current status on co Component B: Improving t Individual Cons 2019-05-2 2019-05- 2019-07- 2019-08- 2019-08- 2019-08- 2019-09- 2019-08- 2020-08- 2021-03- mpliance of special fiscal re IDA / 60850 he efficiency of Public Fina Post Open 15,000.00 15,000.00 Completed ultant Selection 3 29 11 01 01 01 05 01 30 30 quirements of the FSL for l ncial Management ocal budget and preparatio n of a proposal on enhance ment of fiscal discipline at l ocal government D1/CS/030 / Coordinating c Component D: Strengtheni Individual Cons 2018-09-0 2017-10- 2018-10- 2018-09- 2018-11- 2018-09- 2018-12- 2018-09- 2019-06- 2019-12- IDA / 60850 Post Open 18,000.00 22,500.00 Completed onsultant of Component D ( ng of the Social Protection ultant Selection 1 17 20 25 10 25 15 25 13 05 2nd) System C5/CS/08 / Component C5 Component C: Enhancing Individual Cons 2018-01-0 2017-10- 2018-01- 2018-03- 2018-02- 2018-03- 2018-03- 2018-02- 2018-09- IDA / 60850 Post Direct 55,500.00 79,250.00 Terminated Coordinating Consultant Financial Sector Stability ultant Selection 1 16 11 27 01 27 08 27 04 D2/CS/1300 / National con Component D: Strengtheni sultant to draft legal amen Individual Cons 2018-05-1 2018-05- 2018-05- 2018-05- 2018-06- 2018-05- 2018-07- 2018-05- 2019-01- IDA / 60850 ng of the Social Protection Post Direct 6,000.00 6,000.00 Terminated dments to the Law on Pensi ultant Selection 1 23 21 23 11 23 16 23 12 System ons and benefits Provided by the Social Insurance Fun d D1/CS/02 / National consul tant on the preparation of t Component D: Strengtheni Individual Cons 2018-07-0 2018-07- 2018-07- 2018-07- 2018-08- 2018-07- 2018-09- 2018-07- 2019-03- 2019-03- he revises to the Law on So IDA / 60850 ng of the Social Protection Post Direct 6,000.00 6,000.00 Completed ultant Selection 9 25 19 26 09 26 13 26 12 01 cial Welfare and legal ame System ndments to the other legisl ation in relevance with the revised E/CS/01 / Financial Manag Component E: Project Man Individual Cons 2017-12-0 2017-12- 2018-01- 2017-11- 2018-02- 2017-12- 2018-03- 2017-12- 2018-09- IDA / 60850 Post Open 21,600.00 1,465.21 Terminated ement Specialist - PIU core agement and Monitoring ultant Selection 7 08 25 28 15 07 22 07 18 staff E/CS/0010 / Financial Man Component E: Project Man Individual Cons 2019-08-0 2019-08- 2019-08- 2019-09- 2019-09- 2019-09- 2019-10- 2019-09- 2020-04- IDA / 60850 Post Direct 21,600.00 75,538.65 Signed agement Specialist - PIU co agement and Monitoring ultant Selection 1 26 11 27 01 30 06 30 03 re staff E/CS/11 / Procurement Spe Component E: Project Man Individual Cons 2019-08-0 2019-06- 2019-08- 2019-08- 2019-09- 2019-08- 2019-10- 2019-08- 2020-04- 2020-10- IDA / 60850 Post Direct 21,600.00 1,680.20 Completed cialist - PIU core staff agement and Monitoring ultant Selection 1 21 11 28 01 30 06 30 03 28 E/CS/05 / Procurement Ass Component E: Project Man Individual Cons 2018-08-0 2018-09- 2018-10- 2018-11- 2019-05- IDA / 60850 Post Open 5,400.00 0.00 Canceled istant - PIU core staff agement and Monitoring ultant Selection 1 19 10 14 13 D1/CS/031 / Coordinating Component D: Strengtheni Consultant of consulting se Individual Cons 2019-10-1 2019-09- 2019-12- 2019-11- 2019-12- 2019-10- 2020-01- 2019-11- 2020-07- IDA / 60850 ng of the Social Protection Post Open 43,200.00 69,575.47 Signed rvices and goods for D1 an ultant Selection 4 27 02 14 23 17 27 14 25 System d D2 component (3rd) A31/CS/015 / Consultancy service on uploading and u Component A: Strengtheni pdating exchange and inter Individual Cons 2020-03-0 2020-02- 2020-03- 2020-04- 2020-04- 2020-04- 2020-05- 2020-04- 2020-11- IDA / 60850 ng Macroeconomic and Fis Post Direct 42,000.00 65,417.97 Signed est rates onto DMFAS, conn ultant Selection 1 20 11 14 01 14 06 14 02 cal Management ect DMFAS to Office 365 for automized debt repayment reminder to corresponding personnel... B13/CS/016 / National con sultant to update and impr Component B: Improving t ove an existing "Leader mo Individual Cons 2020-04-0 2020-04- 2020-04- 2020-05- 2020-06- 2020-12- IDA / 60850 he efficiency of Public Fina Post Direct 10,000.00 0.00 Canceled nitoring" system of MoF in ultant Selection 1 15 11 02 06 03 ncial Management consistent with an updated Government regulations No . 36, 37, 38 in 2019 B13/CS/6 / National consul tant to introduce a compre hensive Internal Audit Soft Component B: Improving t Individual Cons 2018-10-0 2018-09- 2018-11- 2018-10- 2018-12- 2018-10- 2019-01- 2018-10- 2019-07- 2020-11- ware with an Integrated Re IDA / 60850 he efficiency of Public Fina Post Open 58,900.00 36,000.00 Completed ultant Selection 1 21 19 19 10 19 14 19 13 09 porting System and a Data ncial Management base: - Develop system spe cifications according to the product story and audit pro cess analysis Component B: Improving t B21/CS/018 / Coordinating Individual Cons 2020-03-0 2020-03- 2020-04- 2020-04- 2020-05- 2020-04- 2020-06- 2020-04- 2020-12- IDA / 60850 he efficiency of Public Fina Post Open 33,000.00 52,345.85 Signed consultant for B21 ultant Selection 1 19 19 27 10 27 14 28 11 ncial Management B22/CS/17 / National cons ultant make a research and Component B: Improving t analysis to implement onlin Individual Cons 2020-05-0 2020-09- 2020-06- 2020-10- 2020-07- 2020-10- 2020-08- 2020-11- 2021-02- 2021-11- IDA / 60850 he efficiency of Public Fina Post Open 24,000.00 19,200.00 Completed e settlement with digital si ultant Selection 1 23 19 30 10 30 14 30 10 01 ncial Management gnature and provide techni cal support on the impleme ntation of the web-based G FMIS B31/CS/011 / Consulting s ervice to make relations of Component B: Improving t all systems used by MOF a Individual Cons 2020-06-0 2020-06- 2020-06- 2020-06- 2020-07- 2020-06- 2020-08- 2020-06- 2021-02- 2022-01- IDA / 60850 he efficiency of Public Fina Post Direct 24,000.00 37,994.71 Completed nd hand out all works for in ultant Selection 1 12 11 12 02 12 06 12 02 11 ncial Management tegration of that systems ( GFMIS, Fiscal, BPIS, PIMIS, DMFAS and ODAMIS) C11/CS/023 / National con sultant to conduct a thorou Component C: Enhancing Individual Cons 2020-05-2 2020-08- 2020-07- 2020-07- 2020-09- 2021-03- gh analysis for developing l IDA / 60850 Post Open 13,200.00 0.00 Canceled Financial Sector Stability ultant Selection 0 26 08 29 02 01 ife insurance in Mongolia a nd formulate its developme nt policy. C11/CS/026 / National con sultant to develop research and recommendations to id Component C: Enhancing Individual Cons 2020-09-1 2020-08- 2020-11- 2020-10- 2020-11- 2020-10- 2020-12- 2020-10- 2021-06- 2021-04- entifying challenges and ob IDA / 60850 Post Open 11,100.00 11,100.00 Completed Financial Sector Stability ultant Selection 4 05 02 28 23 28 28 28 26 27 stacles for foreign investors to invest in the Mongolian c apital markets and offer sol utions to the issues. C11/CS/028 / National Leg al Expert for providing cons Component C: Enhancing Individual Cons 2020-05-1 2020-05- 2020-07- 2020-07- 2020-07- 2020-07- 2020-08- 2021-02- IDA / 60850 Post Open 27,000.00 0.00 Canceled ultancy on financial market Financial Sector Stability ultant Selection 5 19 03 06 24 06 28 24 s and insurance related law s. C21/CS/005 / International Individual Consultant on de Component C: Enhancing Individual Cons 2020-06-0 2020-07- 2020-08- 2020-09- 2021-03- IDA / 60850 Post Open 45,000.00 0.00 Canceled veloping approaches and in Financial Sector Stability ultant Selection 1 20 10 14 13 struments for SDG financin g. C21/CS/006 / International Component C: Enhancing Individual Cons 2020-06-0 2020-07- 2020-08- 2020-09- 2021-03- Individual Consultant on op IDA / 60850 Post Open 45,000.00 0.00 Canceled Financial Sector Stability ultant Selection 1 20 10 14 13 timization of asset portfolio and its management. C21/CS/010 / International Individual Consultant to pre Component C: Enhancing Individual Cons 2020-06-0 2020-07- 2020-08- 2020-09- 2021-03- IDA / 60850 Post Open 55,000.00 0.00 Canceled pare action plan for implem Financial Sector Stability ultant Selection 1 20 10 14 13 enting the financial diagno stics recommendations. C4/CS/027 / National cons ultant for designing softwar Component C: Enhancing Individual Cons 2020-04-1 2020-05- 2020-04- 2020-06- 2020-05- 2020-06- 2020-06- 2020-06- 2020-12- 2020-12- e and registration platform IDA / 60850 Post Direct 10,200.00 10,200.00 Completed Financial Sector Stability ultant Selection 5 07 25 23 16 23 20 23 17 28 to create real estate and as sess money laundering risk of real estate agents. C4/CS/028 / National cons ultant to develop recomme Component C: Enhancing Individual Cons 2020-04-1 2020-05- 2020-04- 2020-06- 2020-05- 2020-06- 2020-06- 2020-06- 2020-12- IDA / 60850 Post Direct 10,200.00 10,200.00 Terminated ndation and guidance for fi Financial Sector Stability ultant Selection 5 08 25 22 16 22 20 22 17 nancial conglomerates’ sup ervision. C4/CS/033 / National cons ultant (Team Leader) to pro Component C: Enhancing Individual Cons 2020-04-1 2020-06- 2020-04- 2020-06- 2020-05- 2020-06- 2020-06- 2020-06- 2020-12- 2020-12- vide further legal assistanc IDA / 60850 Post Direct 6,000.00 6,000.00 Completed Financial Sector Stability ultant Selection 5 03 25 29 16 29 20 22 17 28 e in the implementation of General Directive to Improv e Legislation of Mongolia u ntil 2020. C4/CS/034 / National cons ultant (Team member) to p rovide further legal assista Component C: Enhancing Individual Cons 2020-04-1 2020-06- 2020-04- 2020-06- 2020-05- 2020-06- 2020-06- 2020-06- 2020-12- 2020-09- IDA / 60850 Post Direct 5,400.00 5,400.00 Completed nce in implementation of th Financial Sector Stability ultant Selection 5 03 25 29 16 29 20 29 17 28 e General Directive to Impr ove Legislation of Mongolia until 2020. C5/CS/015 / International Consultancy service to draf Component C: Enhancing Individual Cons 2020-07-0 2020-04- 2020-08- 2020-06- 2020-09- 2020-06- 2020-10- 2020-06- 2021-04- 2021-05- t laws and regulations to g IDA / 60850 Post Open 45,000.00 38,000.00 Completed Financial Sector Stability ultant Selection 1 08 19 25 09 25 14 25 12 03 overn virtual assets/crypto currency and provide the n ecessary training to the BO M staff. C5/CS/016 / International Consultancy service to furt her develop audit methodol Component C: Enhancing Individual Cons 2020-09-0 2020-11- 2020-09- 2020-12- 2020-10- 2020-12- 2020-11- 2020-12- 2021-05- IDA / 60850 Post Direct 60,000.00 66,530.00 Signed ogy and guidelines for the I Financial Sector Stability ultant Selection 1 12 11 24 02 24 06 24 05 nternal Audit Department s pecially on IT auditing and cyber security auditing. D1/CS/034 / IT concultant on supporting further refin ements of the welfare admi Component D: Strengtheni nistration information syste Individual Cons 2020-07-0 2020-09- 2020-08- 2020-10- 2020-09- 2020-10- 2020-10- 2020-10- 2021-04- 2022-06- IDA / 60850 ng of the Social Protection Post Open 28,000.00 27,600.00 Completed m and maximizing the prac ultant Selection 1 09 19 02 09 02 14 02 12 01 System tical application of the spec ific modules for administrat ive reporting and monitorin g and evaluation purposes D1.5 D1/CS/037 / National conc ultant to develop recomme ndations for developing car Component D: Strengtheni Individual Cons 2020-04-0 2020-08- 2020-05- 2020-09- 2020-06- 2020-09- 2020-07- 2020-09- 2021-01- 2021-01- e service options and supp IDA / 60850 ng of the Social Protection Post Open 8,000.00 6,400.00 Completed ultant Selection 1 04 20 09 10 09 15 09 11 08 ort for private partnerships System and to develop proposals f or updating nursing home r egulations and donation pr ocedures D1/CS/040 / National cons Component D: Strengtheni ultant to monitor identifyin Individual Cons 2020-04-0 2020-06- 2020-04- 2020-07- 2020-05- 2020-07- 2020-06- 2020-07- 2020-12- 2020-12- IDA / 60850 ng of the Social Protection Post Direct 8,000.00 8,000.00 Completed g processes who are takin ultant Selection 1 21 11 02 02 02 06 02 03 23 System g caregivers allowance, an d improve regulations, guid elines Page 10 D2/CS/020 / Develop prop osals for new amendments of social insurance package Component D: Strengtheni law based on the actuarial Individual Cons 2020-04-1 2020-05- 2020-05- 2020-06- 2020-06- 2020-06- 2020-07- 2020-06- 2021-01- 2020-11- IDA / 60850 ng of the Social Protection Post Open 10,000.00 9,750.00 Completed projections report, and red ultant Selection 0 21 29 29 19 29 24 29 20 28 System esign drafts the attached fil es for Social Insurance pac kage laws such as researc hes, and calculations (Natio nal consultant 1) D2/CS/021 / Develop regul ations, implementation gui Component D: Strengtheni Individual Cons 2020-07-0 2020-08- 2020-09- 2020-10- 2021-04- delines and methodologies IDA / 60850 ng of the Social Protection Post Open 10,000.00 0.00 Canceled ultant Selection 1 19 09 14 12 of the new Social Social In System surance Package Laws draf t (National consultant 2) D2/CS/05 / Consultancy se rvice to evaluate the curre nt situation of Social Insura Component D: Strengtheni Individual Cons 2020-05-1 2020-07- 2020-07- 2020-09- 2020-07- 2020-09- 2020-08- 2020-09- 2021-02- 2021-03- nce funds management an IDA / 60850 ng of the Social Protection Post Open 45,000.00 32,400.00 Completed ultant Selection 5 31 03 15 24 15 28 15 24 31 d develop recommendation System s for improvement, and go vernance and legal framew ork for social insurance fun d management. D2/CS/06 / National consul tant to evaluate the curren t situation of Social Insuran Component D: Strengtheni Individual Cons 2020-05-0 2020-08- 2020-06- 2020-10- 2020-07- 2020-10- 2020-08- 2020-10- 2021-02- 2021-03- ce Funds management and IDA / 60850 ng of the Social Protection Post Open 10,000.00 7,500.00 Completed ultant Selection 1 18 19 23 10 27 14 27 10 31 develop recommendations System for improvement, and supp ort the improvement of the legal framework. D2/CS/07 / International co Component D: Strengtheni nsultant to develop implem Individual Cons 2020-09-1 2020-07- 2020-11- 2020-09- 2020-11- 2020-09- 2020-12- 2020-09- 2021-06- 2021-06- IDA / 60850 ng of the Social Protection Post Open 20,000.00 19,200.00 Completed entation guideline and met ultant Selection 5 28 03 15 24 15 29 15 27 21 System hodology to reduce contrib ution debts. D2/CS/022 / National cons Component D: Strengtheni ultant to develop implemen Individual Cons 2020-09-0 2020-09- 2020-10- 2020-10- 2020-11- 2020-10- 2020-12- 2020-10- 2021-06- 2021-05- IDA / 60850 ng of the Social Protection Post Open 5,000.00 7,500.00 Completed tation guideline and metho ultant Selection 1 02 20 23 10 23 15 28 13 07 System dology for reducing contrib ution debts D2/CS/023 / National cons ultant (1) to elaborate prop osals and recommendation Component D: Strengtheni s on amendments and impr Individual Cons 2020-05-1 2020-05- 2020-07- 2020-06- 2020-07- 2020-06- 2020-08- 2020-06- 2021-02- 2020-09- IDA / 60850 ng of the Social Protection Post Open 8,000.00 6,900.00 Completed ovements to the Occupatio ultant Selection 5 21 03 29 24 29 28 29 24 29 System nal Safety and Health Law and other relevant laws rel ated to the update of the p ension and allowance law … D2/CS/024 / National cons ultant (2) to elaborate prop osals and recommendation Component D: Strengtheni s on amendments and impr Individual Cons 2020-05-1 2020-05- 2020-07- 2020-06- 2020-07- 2020-06- 2020-08- 2020-06- 2021-02- 2020-10- IDA / 60850 ng of the Social Protection Post Open 8,000.00 6,750.00 Completed ovements to the Occupatio ultant Selection 5 21 03 29 24 29 28 29 24 23 System nal Safety and Health Law and other relevant laws rel ated to the update of the p ension and allowance law … D2/CS/029 / Coordinating Component D: Strengtheni Individual Cons 2020-04-0 2020-04- 2020-05- 2020-06- 2020-06- 2020-06- 2020-07- 2020-06- 2021-01- Consultant of overseas and IDA / 60850 ng of the Social Protection Post Open 21,600.00 64,141,958.33 Signed ultant Selection 5 30 24 03 14 04 19 04 15 local training for D1 and D2 System component D2/CS/030 / Consultancy s Component D: Strengtheni Individual Cons 2020-05-0 2020-07- 2020-05- 2020-08- 2020-06- 2020-09- 2020-07- 2020-09- 2021-01- 2022-01- ervice for translation and o IDA / 60850 ng of the Social Protection Post Direct 3,000.00 3,000.00 Completed ultant Selection 1 23 11 11 01 09 06 10 02 31 ther consultancy services, System multiple contracts. D2/CS/031 / Consultancy s Component D: Strengtheni Individual Cons 2020-05-0 2020-07- 2020-05- 2020-07- 2020-06- 2020-07- 2020-07- 2020-07- 2021-01- ervice for translations and IDA / 60850 ng of the Social Protection Post Direct 3,000.00 3,000.00 Signed ultant Selection 1 01 11 09 01 10 06 10 02 other consultancy services, System multiple contracts. D2/CS/032 / Consultancy s Component D: Strengtheni Individual Cons 2020-05-0 2020-07- 2020-05- 2020-07- 2020-06- 2020-07- 2020-07- 2020-07- 2021-01- ervice for translations and IDA / 60850 ng of the Social Protection Post Direct 4,000.00 4,000.00 Signed ultant Selection 1 02 11 23 01 23 06 23 02 other consultancy services, System multiple contracts. E/CS/015 / National consul Component E: Project Man Individual Cons 2020-03-0 2020-08- 2020-04- 2020-08- 2020-05- 2020-08- 2020-06- 2020-08- 2020-12- 2021-02- IDA / 60850 Post Open 5,400.00 5,400.00 Completed tant to assist in procureme agement and Monitoring ultant Selection 1 13 19 17 10 17 14 17 11 26 nt activities. B21/CS/019 / National con sulting firm to conduct a st udy on “Outcome based ed Component B: Improving t 2020-04-2 2020-07- 2020-05- 2020-07- 2020-07- 2020-08- 2021-01- 2020-12- ucation policy” that will incl IDA / 60850 he efficiency of Public Fina Post Direct Selection Direct 25,000.00 25,000.00 Completed 4 24 04 30 08 03 04 18 ude a situation analysis on ncial Management the current accounting deg ree programmes and a poli cy document with a recom mendation B21/CS/020 / National con sulting firm to develop: 1) s tandard test to assess a pr Component B: Improving t ogress in students’ knowle 2020-04-2 2020-07- 2020-05- 2020-07- 2020-07- 2020-08- 2021-01- 2020-12- IDA / 60850 he efficiency of Public Fina Post Direct Selection Direct 8,000.00 8,000.00 Completed dge in 15 professional subj 4 27 04 30 08 03 04 20 ncial Management ects that are included in un iversities’ academic plan a nd 2) a test to assess profe ssional accountants’ knowl edge of IPSASs B32/CS/004 / National con sultant to carry out consult Component B: Improving t ations, market research an Individual Cons 2020-05-0 2020-05- 2020-06- 2020-08- 2020-07- 2020-08- 2020-08- 2020-08- 2021-02- 2021-04- IDA / 60850 he efficiency of Public Fina Post Open 18,000.00 18,000.00 Completed d preparatory work for impl ultant Selection 1 11 19 25 10 25 14 25 10 15 ncial Management ementation to processing Human Resource Develop ment program's sub-progra ms … B33/CS/013 / National Con sultant to develope online Component B: Improving t Individual Cons 2020-03-0 2020-03- 2020-04- 2020-04- 2020-05- 2020-04- 2020-06- 2020-04- 2020-12- procurement application on IDA / 60850 he efficiency of Public Fina Post Open 32,400.00 32,400.00 Signed ultant Selection 1 21 19 18 10 28 14 28 11 mobile devices, and suppor ncial Management t online public procurement system B4/CS/020 / Consulting Ser vice for cleaning/quality en hancements of the data en Component B: Improving t Individual Cons 2020-04-0 2020-04- 2020-04- 2020-04- 2020-05- 2020-04- 2020-06- 2020-04- 2020-12- 2022-01- tries in the PIMS for consist IDA / 60850 he efficiency of Public Fina Post Direct 12,000.00 12,000.00 Completed ultant Selection 1 13 11 13 02 13 06 13 03 16 ency check and potential in ncial Management tegration for information/d ata of investment projects f inanced from other sources A1/CS/018 / Consulting ser Component A: Strengtheni Individual Cons 2020-01-0 2020-03- 2020-02- 2020-07- 2020-03- 2020-06- 2020-04- 2020-06- 2020-10- 2021-06- vices to design Integrated IDA / 60850 ng Macroeconomic and Fis Post Open 24,000.00 24,000.00 Completed ultant Selection 1 26 19 21 11 08 15 08 12 10 Results-Based Managemen cal Management t System (IRBM) B11/CS/018 / National IT c onsultant to finalize hando Component B: Improving t Individual Cons 2019-11-2 2020-01- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- 2020-02- 2021-01- 2022-02- ver of the BPIS to the Minis IDA / 60850 he efficiency of Public Fina Post Direct 60,000.00 60,000.00 Completed ultant Selection 2 23 02 17 23 17 27 17 21 16 try of Finance and to upgra ncial Management de the current Fiscal syste m to enable web-based dat a transfer A31/CS/09 / National cons ultant on providing evaluati on and assessment on debt Component A: Strengtheni management performance Individual Cons 2019-05-0 2019-04- 2019-05- 2019-05- 2019-06- 2019-05- 2019-07- 2019-05- 2020-01- 2021-02- IDA / 60850 ng Macroeconomic and Fis Post Direct 24,000.00 52,500.00 Completed in accordance with internat ultant Selection 1 16 11 23 01 02 06 02 02 01 cal Management ional methodology and ma ke suggestions on areas of improvement and monitor i mplementation on regular basis… B13/CS/3 / National consul tant to update and publish existing draft of the quality Component B: Improving t assurance manual and inte Individual Cons 2019-02-0 2018-11- 2019-02- 2019-01- 2019-03- 2019-01- 2019-04- 2019-01- 2019-10- 2019-02- IDA / 60850 he efficiency of Public Fina Post Direct 10,000.00 10,000.00 Completed rnal audit handbook. The u ultant Selection 1 22 11 28 04 28 08 28 05 11 ncial Management pdate shall be inline with s ector specific practical impr ovements and customize to fit the needs of different or ganizations. B21/CS/16 / International c onsultant /PUM expert/ to l Component B: Improving t Individual Cons 2019-03-1 2019-03- 2019-03- 2019-03- 2019-04- 2019-03- 2019-05- 2019-03- 2019-11- 2019-06- ead carrying out the qualit IDA / 60850 he efficiency of Public Fina Post Direct 10,000.00 6,650.00 Completed ultant Selection 4 13 24 26 14 25 19 25 15 21 y control review team on a ncial Management udit firms according to the revised regulation B4/CS/07 / National consul Component B: Improving t tant to develop the manual Individual Cons 2019-02-0 2019-02- 2019-02- 2019-02- 2019-03- 2019-02- 2019-04- 2019-02- 2019-10- 2019-10- IDA / 60850 he efficiency of Public Fina Post Direct 12,000.00 12,000.00 Completed for public investment proje ultant Selection 1 01 11 13 04 13 08 13 05 14 ncial Management ct appraisal and selection B4/CS/08 / National consul tant to develop a manual fo Component B: Improving t Individual Cons 2019-02-0 2019-02- 2019-02- 2019-02- 2019-03- 2019-02- 2019-04- 2019-02- 2019-10- 2019-08- r estimating the economic IDA / 60850 he efficiency of Public Fina Post Direct 12,000.00 12,000.00 Completed ultant Selection 1 01 11 19 04 13 08 13 05 14 benefits and social significa ncial Management nce of public investment pr ojects. B4/CS/09 / National consul Component B: Improving t Individual Cons 2019-02-0 2019-02- 2019-02- 2019-02- 2019-03- 2019-02- 2019-04- 2019-02- 2019-10- 2020-01- tant to review the Public In IDA / 60850 he efficiency of Public Fina Post Direct 17,600.00 17,600.00 Completed ultant Selection 1 01 11 13 04 13 08 13 05 09 vestment Management Leg ncial Management islation C11/CS/9 / National consul Component C: Enhancing Individual Cons 2019-02-0 2019-02- 2019-02- 2019-02- 2019-03- 2019-02- 2019-04- 2019-02- 2019-10- 2019-05- tant to draft a privatization IDA / 60850 Post Direct 11,900.00 9,000.00 Completed Financial Sector Stability ultant Selection 1 01 11 11 04 11 08 11 05 24 plan and its related docum ents/regulations. D2/CS/18 / International co nsultant on the design of P ension Parametric reforms i Component D: Strengtheni Individual Cons 2019-05-2 2020-09- 2019-06- 2019-05- 2019-06- 2021-02- 2019-08- 2019-05- 2020-01- 2019-10- n line with the State Policy IDA / 60850 ng of the Social Protection Prior Direct 47,000.00 40,500.00 Completed ultant Selection 8 29 07 29 28 09 02 29 29 26 on Pension Reform and lon System g-term Actuarial projection s on proposed design optio ns (proposed parametric ch anges projection). D2/CS/4 / National consult ant to work with/assist the i Component D: Strengtheni Individual Cons 2018-06-1 2019-07- 2018-06- 2019-09- 2018-07- 2019-09- 2018-08- 2019-01- 2019-02- 2020-12- nternational consultant on l IDA / 60850 ng of the Social Protection Post Direct 6,000.00 2,400.00 Completed ultant Selection 1 30 21 19 12 19 16 13 12 31 ong term Actuarial projecti System ons on proposed design opt ions B11/CS/15 / National cons ultant to provide technical Component B: Improving t Individual Cons 2019-09-1 2019-09- 2019-09- 2019-09- 2019-10- 2019-09- 2019-11- 2019-09- 2020-05- 2021-12- support to the system of st IDA / 60850 he efficiency of Public Fina Post Direct 56,000.00 62,000.00 Completed ultant Selection 1 20 21 20 12 20 16 21 14 18 affing and salaries on impr ncial Management ovement of appropriate me chanism for planning D2/CS/0014 / National con sultant to draft legal amen Component D: Strengtheni dments to the Law on Pensi Individual Cons 2018-11-2 2020-08- 2018-12- 2018-11- 2018-12- 2020-09- 2019-01- 2018-11- 2019-07- 2019-05- IDA / 60850 ng of the Social Protection Prior Direct 4,800.00 4,800.00 Completed ons, benefits, and allowanc ultant Selection 5 14 05 28 26 29 30 28 29 02 System es from an industrial accide nt and occupational diseas e provided by the Social Ins urance Fund… D2/CS/33 / National consul Component D: Strengtheni tant consultant to carry out Individual Cons 2018-06-1 2018-06- 2018-06- 2018-06- 2018-07- 2018-06- 2018-08- 2018-06- 2019-02- 2018-11- IDA / 60850 ng of the Social Protection Post Direct 6,000.00 6,000.00 Completed actuarial projections on var ultant Selection 5 18 25 19 16 19 20 19 16 14 System ious parametric changes in to the pension system. E/CS/9 / Project coordinato Component E: Project Man Individual Cons 2019-06-1 2020-08- 2019-06- 2019-06- 2019-07- 2020-09- 2019-08- 2019-06- 2020-02- IDA / 60850 Prior Direct 30,000.00 106,213.58 Signed r - PIU core staff agement and Monitoring ultant Selection 3 03 23 10 14 25 18 10 14 D2/CS/0025 / Consulting fir m (2) to support the develo Component D: Strengtheni 2020-04-2 2020-05- 2020-07- 2021-01- pment of content for publi IDA / 60850 ng of the Social Protection Post Direct Selection Direct 10,000.00 0.00 Canceled 7 07 11 07 c awareness material (new System spaper, journal , stork and others) D2/CS/034 / Consulting fir Component D: Strengtheni m for preparing online train 2020-04-2 2020-06- 2020-05- 2020-07- 2021-01- IDA / 60850 ng of the Social Protection Post Direct Selection Direct 10,000.00 0.00 Canceled ing video content for impro 7 30 07 11 07 System ving Social Insurance deliv ery and capacity building B21/CS/005 / International consultant to provide supp ort to develop the accounti Component B: Improving t ng methodology on public s Individual Cons 2019-04-0 2019-09- 2019-05- 2019-06- 2019-07- 2019-09- IDA / 60850 he efficiency of Public Fina Post Open 31,500.00 0.00 Canceled ector consolidated financial ultant Selection 1 17 20 10 15 13 ncial Management reporting for consolidating business entities that are a pplied IFRS and state-owne d enterprises and enterpris es with less than 90 .. B21/CS/015 / National IT c onsultant to analyze the sy Component B: Improving t stems/interconnectivity iss Individual Cons 2019-07-0 2019-08- 2019-09- 2019-10- 2020-04- IDA / 60850 he efficiency of Public Fina Post Open 9,600.00 0.00 Canceled ues for public sector accou ultant Selection 1 19 09 14 11 ncial Management nting and reporting in close collaboration with the Trea sury Department C11/CS/013 / National con Component C: Enhancing Individual Cons 2019-09-3 2019-11- 2019-12- 2020-01- 2020-07- sultant to prepare compreh IDA / 60850 Post Open 10,800.00 0.00 Canceled Financial Sector Stability ultant Selection 0 18 09 13 11 ensive guide for Mongolian Bond Market. A2/CS/0008 / National juni Component A: Strengtheni or consultant on broadenin Individual Cons 2018-06-1 2018-06- 2018-07- 2018-06- 2018-08- 2018-06- 2018-09- 2018-06- 2019-03- 2019-06- IDA / 60850 ng Macroeconomic and Fis Post Open 6,000.00 6,000.00 Completed g the tax base and reducin ultant Selection 2 13 31 27 21 27 25 27 24 27 cal Management g the shadow economy thr ough the tax systems D2/CS/035 / International c Component D: Strengtheni onsultant for review and re Individual Cons 2020-05-0 2020-06- 2020-05- 2020-06- 2020-06- 2020-06- 2020-07- 2020-06- 2021-01- 2020-10- IDA / 60850 ng of the Social Protection Post Direct 8,000.00 8,000.00 Completed draft the existing draft legi ultant Selection 1 04 11 12 01 08 06 08 02 14 System slation on Private Supplem entary Pensions C4/CS/036 / International c onsultant to assist/work wit Component C: Enhancing Individual Cons 2020-06-0 2020-07- 2020-06- 2020-08- 2020-07- 2020-08- 2020-08- 2020-08- 2021-02- 2020-10- h International Cooperation IDA / 60850 Post Direct 10,200.00 10,200.00 Completed Financial Sector Stability ultant Selection 1 31 11 03 02 03 06 03 02 30 Department and provide ca pacity building training to F RC personnel D1/CS/43 / Translation ser Component D: Strengtheni Individual Cons 2020-07-0 2020-08- 2020-07- 2020-08- 2020-08- 2020-08- 2020-09- 2020-08- 2021-03- 2020-08- vices - Russian to Mongolia IDA / 60850 ng of the Social Protection Post Direct 450.00 450.00 Completed ultant Selection 1 11 11 12 01 11 05 11 04 26 n for one-day virtual meeti System ng D1/CS/0043 / Translation s Component D: Strengtheni Individual Cons 2020-07-0 2020-09- 2020-07- 2020-09- 2020-08- 2020-09- 2020-09- 2020-09- 2021-03- 2022-01- IDA / 60850 Post Direct 4,500.00 4,500.00 Completed ervices - English to Mongoli ng of the Social Protection ultant Selection 1 09 11 09 01 09 05 09 04 30 an System D2/CS/001 / International c onsultant to design pension parametric reforms in line Component D: Strengtheni with the State Policy on Pe Individual Cons 2019-06-0 2019-05- 2019-07- 2019-08- 2019-09- 2019-12- IDA / 60850 ng of the Social Protection Post Open 47,000.00 0.00 Canceled nsion Reform and long ter ultant Selection 3 22 22 12 16 15 System m Actuarial projections on proposed design options (u pdates to the current para metric projections includin g individual-based model) D2/CS/0004 / National con sultant to work with/assist t Component D: Strengtheni 2018-06-1 2018-06- 2018-06- 2018-08- 2019-02- he international consultant IDA / 60850 ng of the Social Protection Post Direct Selection Direct 6,000.00 0.00 Canceled 5 11 25 29 25 on long term Actuarial proj System ections on proposed design options D1/CS/043 / Translations s Component D: Strengtheni Individual Cons 2020-10-0 2020-10- 2020-11- 2020-12- 2021-06- IDA / 60850 Post Direct 5,000.00 0.00 Canceled ervices ng of the Social Protection ultant Selection 1 11 01 06 04 System B22/CS/004 / International consultant on road map (fin ancial statement and the b Component B: Improving t udget execution based on I Individual Cons 2019-12-3 2020-02- 2020-03- 2020-04- 2020-06- IDA / 60850 he efficiency of Public Fina Post Open 65,200.00 0.00 Canceled PSAS implementation, GFM ultant Selection 1 18 10 14 13 ncial Management IS v7) carry out an in-depth evaluation to identify gaps between existing TD busine ss procedures and the new functionalities available A2/CS/08 / National junior Component A: Strengtheni consultant on broadening t Individual Cons 2018-06-2 2018-06- 2018-07- 2018-07- 2018-09- 2019-03- IDA / 60850 ng Macroeconomic and Fis Post Direct 6,000.00 0.00 Canceled he tax base and reducing t ultant Selection 9 12 09 30 03 02 cal Management he shadow economy throu gh the tax systems A32/CS/010 / National con sultant on improving the m Component A: Strengtheni Individual Cons 2020-01-0 2020-02- 2020-03- 2020-04- 2020-10- onitoring and evaluation, a IDA / 60850 ng Macroeconomic and Fis Post Open 24,000.00 0.00 Canceled ultant Selection 1 19 11 15 12 nd reporting process of ext cal Management ernarlly funded developme nt projects. D1/CS/027 / National cons Component D: Strengtheni ultant to provide translatio 2019-03-1 2020-01- 2019-03- 2019-05- 2019-11- IDA / 60850 ng of the Social Protection Post Direct Selection Direct 1,600.00 0.00 Canceled n service of reviewing Mon 2 31 22 26 22 System golian translation prior to p rinting books D1/CS/0027 / National con Component D: Strengtheni sultant to provide translati Individual Cons 2020-02-0 2020-02- 2020-02- 2020-02- 2020-03- 2020-02- 2020-04- 2020-02- 2020-10- 2020-09- IDA / 60850 ng of the Social Protection Post Direct 1,600.00 899.99 Completed on service of reviewing Mo ultant Selection 1 11 11 12 03 12 07 12 04 07 System ngolian translation prior to printing books B32/CS/005 / Consulting s Component B: Improving t Individual Cons 2020-05-0 2020-06- 2020-07- 2020-08- 2021-02- ervice to create digital arch IDA / 60850 he efficiency of Public Fina Post Open 2,000.00 0.00 Canceled ultant Selection 1 19 10 14 10 ive -1 ncial Management B32/CS/006 / Consulting s Component B: Improving t Individual Cons 2020-05-0 2020-06- 2020-07- 2020-08- 2021-02- ervice to create digital arch IDA / 60850 he efficiency of Public Fina Post Open 2,000.00 0.00 Canceled ultant Selection 1 19 10 14 10 ive -2 ncial Management B32/CS/007 / Consulting s Component B: Improving t Individual Cons 2020-05-0 2020-06- 2020-07- 2020-08- 2021-02- ervice to create digital arch IDA / 60850 he efficiency of Public Fina Post Open 2,000.00 0.00 Canceled ultant Selection 1 19 10 14 10 ive -3 ncial Management B32/CS/008 / Consulting s Component B: Improving t Individual Cons 2020-05-0 2020-06- 2020-07- 2020-08- 2021-02- ervice to create digital arch IDA / 60850 he efficiency of Public Fina Post Open 2,000.00 0.00 Canceled ultant Selection 1 19 10 14 10 ive -4 ncial Management B32/CS/009 / Consulting s Component B: Improving t Individual Cons 2020-05-0 2020-06- 2020-07- 2020-08- 2021-02- ervice to create digital arch IDA / 60850 he efficiency of Public Fina Post Open 2,000.00 0.00 Canceled ultant Selection 1 19 10 14 10 ive -5 ncial Management B32/CS/010 / Consulting s Component B: Improving t Individual Cons 2020-05-0 2020-06- 2020-07- 2020-08- 2021-02- ervice to create digital arch IDA / 60850 he efficiency of Public Fina Post Open 2,000.00 0.00 Canceled ultant Selection 1 19 10 14 10 ive -6 ncial Management A32/CS/013 / National con sultant for assisting on the update of the ODA Manage Component A: Strengtheni Individual Cons 2020-06-1 2020-06- 2020-06- 2020-06- 2020-06- 2020-06- 2020-06- 2020-06- 2022-01- ment information system ( IDA / 60850 ng Macroeconomic and Fis Post Direct 25,200.00 37,306.57 Signed ultant Selection 1 12 12 15 12 15 19 15 31 ODAMIS) and the developm cal Management ent of Economic cooperatio n information management system (ECIMS) E/CS/017 / Employment of Component E: Project Man Individual Cons 2020-09-1 2020-10- 2020-09- 2020-12- 2020-10- 2020-12- 2020-11- 2020-12- 2022-01- PIU core staff: Monitoring a IDA / 60850 Prior Direct 33,000.00 48,032.36 Signed agement and Monitoring ultant Selection 7 13 27 02 18 21 22 02 31 nd Evaluation specialist B32/CS/05 / Consultancy t Component B: Improving t o Create Digital Archives fo Individual Cons 2020-08-1 2020-08- 2020-08- 2020-08- 2020-09- 2020-08- 2020-10- 2020-08- 2021-04- 2021-02- IDA / 60850 he efficiency of Public Fina Post Direct 2,000.00 2,000.00 Completed r permanent storage docu ultant Selection 1 20 21 20 11 20 16 20 14 28 ncial Management ments from 2014-2018 A4 documents of MOF Page 11 B32/CS/06 / Consultancy t Component B: Improving t Individual Cons 2020-08-1 2020-08- 2020-08- 2020-08- 2020-09- 2020-08- 2020-10- 2020-08- 2021-04- 2021-02- o Create Digital Archives fo IDA / 60850 he efficiency of Public Fina Post Direct 2,000.00 2,000.00 Completed ultant Selection 1 20 21 20 11 20 16 20 14 28 r 1942-1953 A3 documents ncial Management of MOF B32/CS/07 / Consultancy t Component B: Improving t o Create Digital Archives fo Individual Cons 2020-08-1 2020-08- 2020-08- 2020-08- 2020-09- 2020-08- 2020-10- 2020-08- 2021-04- IDA / 60850 he efficiency of Public Fina Post Direct 2,000.00 2,000.00 Terminated r permanent storage docu ultant Selection 1 20 21 20 11 20 16 20 14 ncial Management ments from 2004-2008 A4 documents of MOF B32/CS/08 / Consultancy t o Create Digital Archives fo r the orders of the Minister Component B: Improving t Individual Cons 2020-08-1 2020-08- 2020-08- 2020-08- 2020-09- 2020-08- 2020-10- 2020-08- 2021-04- 2021-02- of Finance and the State Se IDA / 60850 he efficiency of Public Fina Post Direct 2,000.00 2,000.00 Completed ultant Selection 1 20 21 20 11 20 16 20 14 28 cretary, and the official cor ncial Management respondence documents se nt by the MOF to other org anizations during 2003-201 8 A4 documents of MOF B32/CS/09 / Consultancy t Component B: Improving t o Create Digital Archives fo Individual Cons 2020-08-1 2020-08- 2020-08- 2020-08- 2020-09- 2020-08- 2020-10- 2020-08- 2021-04- 2021-02- IDA / 60850 he efficiency of Public Fina Post Direct 2,000.00 2,000.00 Completed r permanent storage docu ultant Selection 1 20 21 20 11 20 16 20 14 28 ncial Management ments from 2009-2013 A4 documents of MOF B32/CS/10 / Consultancy t Component B: Improving t Individual Cons 2020-08-1 2020-08- 2020-08- 2020-08- 2020-09- 2020-08- 2020-10- 2020-08- 2021-04- 2021-02- o Create Digital Archives fo IDA / 60850 he efficiency of Public Fina Post Direct 2,000.00 2,000.00 Completed ultant Selection 1 20 21 20 11 20 16 20 14 28 r 1927-1941 A3 documents ncial Management of MOF E/CS/016 / Employment of Component E: Project Man Individual Cons 2020-09-1 2020-10- 2020-11- 2020-11- 2020-11- 2021-02- 2020-12- 2020-11- 2022-01- IDA / 60850 Prior Open 33,000.00 37,039.69 Terminated PIU core staff: Procurement agement and Monitoring ultant Selection 7 13 05 04 26 01 31 17 31 specialist B11/CS/019 / Coordinating Consultant for the Subcom Component B: Improving t Individual Cons 2020-09-2 2020-09- 2020-11- 2020-10- 2020-12- 2020-10- 2021-01- 2020-10- 2022-01- ponents A2 and B1 of the S IDA / 60850 he efficiency of Public Fina Post Open 43,200.00 53,835.43 Signed ultant Selection 2 30 10 27 01 27 05 27 31 FFS Project and Subcompo ncial Management nents 1.3, 2.1. and 2.2 of t he SGM Project A1/CS/019 / Consulting fir Component A: Strengtheni m service to develop media 2020-06-0 2020-06- 2020-08- 2021-02- IDA / 60850 ng Macroeconomic and Fis Post Direct Selection Direct 10,000.00 0.00 Canceled content for Economic and S 1 11 15 11 cal Management ocial Development Guidelin es for 2021 B21/CS/0005 / Internationa l policy consutlant to revie Component B: Improving t Individual Cons 2020-05-0 2020-05- 2020-06- 2020-07- 2021-01- w and advise on the IPSAS/ IDA / 60850 he efficiency of Public Fina Post Direct 40,000.00 0.00 Canceled ultant Selection 1 11 01 06 02 GFS and systems on public ncial Management sector accounting and repo rting B33/CS/014 / National Con Component B: Improving t sultant to conduct survey o Individual Cons 2020-04-1 2020-06- 2020-06- 2020-07- 2021-01- IDA / 60850 he efficiency of Public Fina Post Open 20,000.00 0.00 Canceled n last 15 years annual total ultant Selection 5 03 24 29 25 ncial Management procurement based on Wor ld Bank methodology B4/CS/021 / National cons Component B: Improving t ultant to improve medium t Individual Cons 2020-09-0 2020-09- 2020-10- 2020-11- 2021-05- IDA / 60850 he efficiency of Public Fina Post Direct 12,000.00 0.00 Canceled erm planning of public inve ultant Selection 1 11 02 06 05 ncial Management stment in the medium term fiscal framework B4/CS/023 / Translation se Component B: Improving t Individual Cons 2020-07-0 2020-08- 2020-09- 2020-10- 2021-04- rvice of the project docume IDA / 60850 he efficiency of Public Fina Post Open 5,000.00 0.00 Canceled ultant Selection 1 19 09 14 12 nts ncial Management C11/CS/025 / National con sultant to develop the priva Component C: Enhancing Individual Cons 2020-08-2 2020-10- 2020-10- 2020-12- 2021-06- IDA / 60850 Post Open 12,600.00 0.00 Canceled tization plan for Mongolian Financial Sector Stability ultant Selection 0 08 29 03 01 Stock Exchange based on i nternational best practices. C4/CS/026 / International c onsultant to support the A ML/CFT unit under the Sup Component C: Enhancing Individual Cons 2020-09-0 2020-10- 2020-11- 2020-12- 2021-06- ervision Department to con IDA / 60850 Post Open 54,800.00 0.00 Canceled Financial Sector Stability ultant Selection 1 20 10 15 13 duct a sectorial and individ ual risk assessment of terro rism financing and prolifera tion financing and improve risk based supervision. C4/CS/030 / International c onsultant to provide capaci Component C: Enhancing Individual Cons 2020-05-0 2020-06- 2020-07- 2020-08- 2021-02- ty building training on Pens IDA / 60850 Post Open 15,000.00 0.00 Canceled Financial Sector Stability ultant Selection 1 19 10 14 10 ion fund (theory, principles, application in local market etc). C4/CS/031 / International c onsultant/trainer to conduc Component C: Enhancing Individual Cons 2020-07-2 2020-09- 2020-09- 2020-11- 2021-05- t training on strengthening IDA / 60850 Post Open 15,000.00 0.00 Canceled Financial Sector Stability ultant Selection 0 07 28 02 01 risk management and risk based supervision skills of t he FRC personnel. C4/CS/035 / National cons ultant to assist/work with In Component C: Enhancing Individual Cons 2020-05-0 2020-06- 2020-07- 2020-08- 2021-02- ternational consultants and IDA / 60850 Post Open 9,000.00 0.00 Canceled Financial Sector Stability ultant Selection 1 19 10 14 10 provide translation and inte rpretation support during t heir assignments. C4/CS/029 / National cons ulting firm to assist to revis e “Accounting manual of N Component C: Enhancing Individual Cons 2020-06-0 2020-07- 2020-08- 2020-09- 2021-03- IDA / 60850 Post Open 28,000.00 0.00 Canceled on-bank financial institutio Financial Sector Stability ultant Selection 1 20 10 14 13 ns” approved by FRC and t o compliance with internati onal standards D1/CS/07 / National consul tant on refinement of SP in Component D: Strengtheni put for poverty reduction st Individual Cons 2019-04-0 2019-04- 2019-05- 2019-06- 2019-12- IDA / 60850 ng of the Social Protection Post Direct 3,600.00 0.00 Canceled rategy and Government na ultant Selection 3 13 04 08 05 System tional programs (specialize d institutional care reform program for elders) D2/CS/025 / Consulting fir m (1) to support the develo Component D: Strengtheni 2020-04-2 2020-04- 2020-07- 2020-12- pment of content for publi IDA / 60850 ng of the Social Protection Post Direct Selection Direct 10,000.00 0.00 Canceled 0 30 04 31 c awareness material (new System spaper, journal , stork and others) B22/CS/027 / Consulting fir Component B: Improving t 2020-08-0 2020-08- 2020-10- 2021-04- m on configuration of multi IDA / 60850 he efficiency of Public Fina Post Direct Selection Direct 128,000.00 0.00 Canceled 1 11 15 13 -currency function of GFMIS ncial Management system (Freebalance) A2/CS/0006 / National con Component A: Strengtheni sultant to translate the BEP Individual Cons 2020-02-0 2020-03- 2020-04- 2020-05- 2020-11- IDA / 60850 ng Macroeconomic and Fis Post Open 8,400.00 0.00 Canceled S (Base Erosion and Profit S ultant Selection 1 21 11 16 12 cal Management hifting) and Global Forum r elated tax policy legislation A2/CS/017 / National cons ultant to provide technical Component A: Strengtheni support to reduce shadow Individual Cons 2019-04-0 2019-05- 2019-06- 2019-07- 2020-01- IDA / 60850 ng Macroeconomic and Fis Post Open 18,000.00 0.00 Canceled economy through the expa ultant Selection 1 20 10 15 11 cal Management nsion of tax base and the T ax Administration and Infor mation System (TAIS) A2/CS/018 / National cons ultant to provide functional Component A: Strengtheni support to reduce shadow Individual Cons 2019-04-0 2019-05- 2019-06- 2019-07- 2020-01- IDA / 60850 ng Macroeconomic and Fis Post Open 18,000.00 0.00 Canceled economy through the expa ultant Selection 1 20 10 15 11 cal Management nsion of tax base and the T ax Administration and Infor mation System (TAIS) A2/CS/021 / National cons ultant for reducing shadow Component A: Strengtheni Individual Cons 2019-11-1 2020-01- 2020-01- 2020-03- 2021-02- economy and expanding ta IDA / 60850 ng Macroeconomic and Fis Post Open 21,000.00 0.00 Canceled ultant Selection 9 07 28 03 26 x base through the tax syst cal Management ems and improve tax trans parency A31/CS/016 / Consultancy service on developing a for mal process for borrowings Component A: Strengtheni Individual Cons 2020-08-0 2020-09- 2020-10- 2020-11- 2021-05- cost-risk analysis, debt ser IDA / 60850 ng Macroeconomic and Fis Post Open 24,000.00 0.00 Canceled ultant Selection 1 19 10 14 13 vice sensitivity assumption cal Management on interest rate and exchan ge rate and propose a met hodology in accordance wit h best practices A32/CS/10 / National cons ultant on improving the mo Component A: Strengtheni Individual Cons 2021-01-1 2021-03- 2021-01- 2021-03- 2021-02- 2021-03- 2021-03- 2021-03- 2021-09- 2022-01- nitoring and evaluation; an IDA / 60850 ng Macroeconomic and Fis Post Direct 30,000.00 25,548.24 Completed ultant Selection 5 23 25 24 15 24 22 24 18 31 d reporting process of exte cal Management rnally funded development project B11/CS/001 / National seni or consultant to make an a ssessment for implementin Component B: Improving t g output based financing m Individual Cons 2020-02-2 2020-04- 2020-04- 2020-06- 2021-06- IDA / 60850 he efficiency of Public Fina Post Open 24,000.00 0.00 Canceled echanism for secondary an ultant Selection 0 09 30 04 04 ncial Management d tertiary hospitals to oper ate independently and orga nize public discussion to int roduce the assessment res ults B11/CS/002 / National con sultant to make an assess ment for implementing out Component B: Improving t put based financing mecha Individual Cons 2020-02-2 2020-04- 2020-04- 2020-06- 2021-06- IDA / 60850 he efficiency of Public Fina Post Open 18,000.00 0.00 Canceled nism for secondary and tert ultant Selection 0 09 30 04 04 ncial Management iary hospitals to operate in dependently and organize public discussion to introdu ce the assessment results B12/CS/004 / National con sultant to continue instituti Component B: Improving t Individual Cons 2018-05-3 2018-07- 2018-08- 2018-09- 2019-09- onalization of Financial Pro IDA / 60850 he efficiency of Public Fina Post Open 24,000.00 0.00 Canceled ultant Selection 1 19 09 13 13 gramming and Policy (FPP) ncial Management method focused on real an d external sectors B12/CS/007 / National con sultant to make an assess ment of current transfer m Component B: Improving t echanism (financial support Individual Cons 2021-04-0 2021-05- 2021-05- 2021-06- 2021-06- IDA / 60850 he efficiency of Public Fina Post Open 24,000.00 0.00 Canceled , special purpose transfers ultant Selection 1 04 09 04 30 ncial Management and revenue transfers) and to develop an appropriate t ransfer mechanism for stre ngthening fiscal decentralis ation B13/CS/011 / National Con Component B: Improving t sultant to develop and impl 2021-06-0 2021-06- 2021-08- 2022-01- IDA / 60850 he efficiency of Public Fina Post Direct Selection Direct 25,000.00 0.00 Canceled ement an Internal audit reg 1 11 15 31 ncial Management ular training program and r egulation B21/CS/013 / National con sultant to develop an accou Component B: Improving t nting manual for public sec Individual Cons 2021-01-1 2021-03- 2021-03- 2021-04- 2021-10- IDA / 60850 he efficiency of Public Fina Post Open 24,000.00 0.00 Canceled tor and renew related form ultant Selection 5 05 26 30 27 ncial Management s and templates for better i mplementation of IPSAS an d improve data quality B21/CS/014 / National con sultant /functional/ to make assessment on existing in Component B: Improving t house developed accountin Individual Cons 2021-03-1 2021-05- 2021-05- 2021-06- 2021-12- IDA / 60850 he efficiency of Public Fina Post Open 9,600.00 0.00 Canceled g IT systems could comply I ultant Selection 5 03 24 28 25 ncial Management PSAS, and Finance Minister s approved regulations, gui dance of budget entities an d state-owned enterprises . .. B21/CS/017 / National IPSA S policy consultant to work iwth the other GFS consulta Component B: Improving t nts from the Treasury and Individual Cons 2021-01-1 2021-03- 2021-03- 2021-04- 2021-10- IDA / 60850 he efficiency of Public Fina Post Open 42,000.00 0.00 Canceled Budget Departments on th ultant Selection 5 05 26 30 27 ncial Management e chart of accounts bringin g in the IPSAS perspective and advise on the policy iss ues/roadmap for reforming public sector accounting an dB22/CS/0029 / Consulting f irm to develop Gateway on Component B: Improving t 2020-11-1 2020-12- 2020-11- 2020-12- 2021-01- 2021-02- 2021-07- 2021-06- Bank interface system to c IDA / 60850 he efficiency of Public Fina Post Direct Selection Direct 30,000.00 29,921.22 Completed 5 24 25 25 29 24 28 23 onnect with varies paymen ncial Management t methods such as POS sys tem, QR, Mobile, Kiosk syst em C11/CS/019 / National con sultant conduct to research related to possible effect of Component C: Enhancing Individual Cons 2020-11-0 2020-12- 2021-01- 2021-02- 2021-08- the blockchain technology i IDA / 60850 Post Open 12,600.00 0.00 Canceled Financial Sector Stability ultant Selection 9 28 18 22 21 n financial sector of Mongol ia, especially in stock mark et and insurance and prepa re recommendation C11/CS/022 / National con sultant to carry out compre Component C: Enhancing Individual Cons 2021-05-0 2021-05- 2021-06- 2021-07- 2022-01- hensive operational and fin IDA / 60850 Post Direct 6,600.00 0.00 Canceled Financial Sector Stability ultant Selection 2 12 02 07 03 ancial analysis for the key Capital markets institutions of Mongolia B22/CS/030 / National con sultant to provide functiona l support on implementing Component B: Improving t an electronic Transaction V Individual Cons 2020-11-1 2020-12- 2021-01- 2021-02- 2021-08- IDA / 60850 he efficiency of Public Fina Post Open 18,000.00 0.00 Canceled erification Directory, a mult ultant Selection 0 29 19 23 22 ncial Management icurrency system, and a Mi nistry of Finance’s portal, w hich is to bring Treasury se rvices to a new level throu gh improved automation B22/CS/031 / National con sultant to provide functiona l support on implementing Component B: Improving t an electronic Transaction V Individual Cons 2020-11-1 2020-12- 2021-01- 2021-02- 2021-08- IDA / 60850 he efficiency of Public Fina Post Open 9,600.00 0.00 Canceled erification Directory, a mult ultant Selection 0 29 19 23 22 ncial Management icurrency system, and a Mi nistry of Finance’s portal, w hich is to bring Treasury se rvices to a new level throu gh improved automation C11/CS/032 / National Indi vidual Legal Expert for Mort Component C: Enhancing Individual Cons 2021-05-0 2020-11- 2021-06- 2021-07- 2021-08- 2022-01- IDA / 60850 Post Open 25,200.00 0.00 Canceled gage Subsidized Loan/Gove Financial Sector Stability ultant Selection 2 11 20 11 15 31 rnment Mortgage Program related legal issues. C11/CS/033 / International individual consultant to car Component C: Enhancing Individual Cons 2021-06-0 2021-07- 2021-08- 2021-09- 2022-01- ry out comprehensive mid t IDA / 60850 Post Open 55,000.00 0.00 Canceled Financial Sector Stability ultant Selection 1 20 10 14 31 o long term capital markets development plan in Mong olia. C11/CS/0022 / National co nsultant to carry out compr Component C: Enhancing Individual Cons 2021-05-0 2021-06- 2021-07- 2021-08- 2022-01- ehensive operational and fi IDA / 60850 Post Open 6,600.00 0.00 Canceled Financial Sector Stability ultant Selection 2 20 11 15 31 nancial analysis for the key Capital markets institutions of Mongolia B33/CS/011 / National Con sultant to support Public pr ocurement inspectors' deci Component B: Improving t sion based on legal profess Individual Cons 2020-10-0 2020-11- 2020-12- 2021-01- 2021-07- IDA / 60850 he efficiency of Public Fina Post Open 25,200.00 0.00 Canceled ioncy, cooperate with inspe ultant Selection 1 19 10 14 13 ncial Management ctors to represent MoF's at the Administrative Court an d to consult with the inspec tors decisions related to re gister blacklist B33/CS/0011 / National co nsultant to draft an internal legal guidance for the Minis Component B: Improving t Individual Cons 2020-11-0 2020-11- 2020-11- 2020-11- 2020-12- 2020-11- 2021-01- 2020-11- 2021-07- try of Finance in resolving IDA / 60850 he efficiency of Public Fina Post Direct 29,250.00 57,200.00 Signed ultant Selection 8 20 18 20 09 20 13 20 12 public procurement-related ncial Management complaints and to provide backstopping support to st ate inspectors in public pro curement B33/CS/012 / National Con Component B: Improving t sultant to provide trainings Individual Cons 2020-10-0 2020-11- 2020-12- 2021-01- 2021-07- IDA / 60850 he efficiency of Public Fina Post Open 25,200.00 0.00 Canceled and support operationalizin ultant Selection 1 19 10 14 13 ncial Management g the newly developed SBD s and its procedures B33/CS/0012 / National co nsultant to conduct trainin Component B: Improving t Individual Cons 2020-11-0 2020-11- 2020-11- 2020-11- 2020-12- 2020-11- 2021-01- 2020-11- 2021-07- g and support operationaliz IDA / 60850 he efficiency of Public Fina Post Direct 29,250.00 57,200.00 Signed ultant Selection 9 19 19 20 10 20 14 20 13 ation of the newly develop ncial Management ed Standard Bidding Docu ments and the relevant pro cedures C4/CS/037 / Coordinating c Component C: Enhancing Individual Cons 2020-10-1 2020-12- 2020-12- 2021-02- 2021-07- IDA / 60850 Post Open 27,000.00 0.00 Canceled onsultant (2nd) Financial Sector Stability ultant Selection 9 07 28 01 31 B4/CS/022 / National cons ultant to refine appraisal m ethodology for estimating t Component B: Improving t he economic benefits and s Individual Cons 2020-11-0 2020-11- 2020-11- 2020-11- 2020-12- 2020-11- 2021-01- 2020-11- 2021-07- IDA / 60850 he efficiency of Public Fina Post Direct 32,000.00 52,782.72 Signed ocial significance of public i ultant Selection 9 19 19 24 10 20 14 20 13 ncial Management nvestment projects, to und ertake ex post monitoring f or finished capital projects and produce report and rec ommendation on capital D1/CS/005 / International c onsultant to assist on impr ovement of PMT methodolo gy's formula, indicators an Component D: Strengtheni Individual Cons 2020-12-0 2020-12- 2021-01- 2021-03- 2021-02- 2021-03- 2021-03- 2021-03- 2021-09- 2022-03- d to develop recommendati IDA / 60850 ng of the Social Protection Post Open 64,000.00 36,870.00 Completed ultant Selection 1 15 19 01 09 01 16 24 12 31 ons for reduce errors and t System o develop guidelines and p olicy reccommendations on the improvement of the im plementation and monitori ng... D2/CS/017 / National cons ultant to conduct an assess Component D: Strengtheni Individual Cons 2020-03-0 2020-04- 2020-05- 2020-06- 2020-12- ment for under-reported co IDA / 60850 ng of the Social Protection Post Open 14,500.00 0.00 Canceled ultant Selection 1 19 10 14 11 ntributory income and deliv System er proposals for realistic co ntributions D1/CS/006 / National cons ultant to assist on improve Component D: Strengtheni Individual Cons 2020-12-0 2020-12- 2021-01- 2021-02- 2021-02- 2021-02- 2021-03- 2021-02- 2021-09- 2022-02- ment of PMT methodology' IDA / 60850 ng of the Social Protection Post Open 8,000.00 7,999.11 Completed ultant Selection 1 22 19 05 09 05 16 10 12 28 s formula, indicators and to System develop recommendations for reduce errors D1.2 D2/CS/027 / To develop an Component D: Strengtheni d implementation design of Individual Cons 2020-09-0 2020-10- 2020-11- 2020-12- 2021-06- IDA / 60850 ng of the Social Protection Post Open 6,000.00 0.00 Canceled electronic contract module ultant Selection 1 20 10 15 13 System with Mongolians abroad (n ational consultant) D2/CS/028 / National cons ultant to develop new digit Component D: Strengtheni Individual Cons 2020-09-0 2020-09- 2020-09- 2020-09- 2020-09- al tool/platforms for social i IDA / 60850 ng of the Social Protection Post 6,000.00 0.00 Canceled ultant Selection 1 01 01 01 01 nsurance collection contrib System utions in coordination with banking services D1/CS/032 / National cons ultant to develop guideline s and policy reccommendat Component D: Strengtheni Individual Cons 2021-04-0 2021-05- 2021-06- 2021-07- 2022-01- ions on the improvement of IDA / 60850 ng of the Social Protection Post Open 10,000.00 0.00 Canceled ultant Selection 1 20 10 15 11 the implementation and m System onitoring process and supp orting improvements to ver ification and validation me asures of the PMT D1.1 Page 12 D2/CS/036 / To develop co Component D: Strengtheni Individual Cons 2020-11-2 2020-11- 2020-12- 2021-01- 2021-07- ntent of social insurance-N IDA / 60850 ng of the Social Protection Post Direct 10,000.00 0.00 Canceled ultant Selection 0 30 21 25 24 ational consultant System D1/CS/033 / National cons Component D: Strengtheni Individual Cons 2021-06-0 2021-07- 2021-08- 2021-09- 2022-01- IDA / 60850 Post Open 18,000.00 0.00 Canceled ultant (IT) to develop PMT s ng of the Social Protection ultant Selection 1 20 10 14 31 oftware System D1/CS/035 / International c onsultant to define and de velop proposals for improv Component D: Strengtheni ing the structure of social Individual Cons 2021-04-0 2021-05- 2021-06- 2021-07- 2022-01- IDA / 60850 ng of the Social Protection Post Open 36,000.00 0.00 Canceled welfare services delivery, a ultant Selection 1 20 10 15 11 System nd improving organizationa l structure in all level such as LSWA, aimag, district di visions and soum, khoroo l evel D1/CS/036 / National cons ultant to define and develo p proposals for improving t Component D: Strengtheni he structure of social welfa Individual Cons 2020-12-1 2021-01- 2021-02- 2021-03- 2021-09- IDA / 60850 ng of the Social Protection Post Open 10,000.00 0.00 Canceled re services delivery, and im ultant Selection 0 28 18 25 21 System prove organizational struct ure in all level such as LS WA, aimag and district divi sions and soum, khoroo lev el D2/CS/037 / The training c ontent video including cha nges in the objectives and Component D: Strengtheni 2020-11-0 2020-11- 2020-11- 2021-01- 2021-01- 2021-01- 2021-07- 2021-03- main principles of the refor IDA / 60850 ng of the Social Protection Post Direct Selection Direct 3,000.00 2,486.85 Completed 9 02 19 07 23 05 22 05 m of the Law on Occupatio System nal Injuries and Occupation al Diseases, including, first of all, prevention, rehabilita tion, and pensions. D1/CS/045 / Consulting fir Component D: Strengtheni m for preparing online train 2021-04-0 2021-04- 2021-06- 2021-12- IDA / 60850 ng of the Social Protection Post Direct Selection Direct 8,000.00 0.00 Canceled ing video content for impro 1 11 15 12 System ving Social Welfare deliver y and business process D2/CS/0041 / National con sulting firm or NGO to supp Component D: Strengtheni ort the development of con 2020-11-2 2020-11- 2021-02- 2021-08- IDA / 60850 ng of the Social Protection Post Direct Selection Direct 10,000.00 0.00 Canceled tent for public awareness 0 30 03 02 System material (newspaper, journ al, short video, other progr ams, handouts, and brochu re) B32/CS/7 / Consultancy to Create Digital Archives for t he orders of the Minister of Component B: Improving t Individual Cons 2020-11-0 2020-12- 2020-11- 2020-12- 2020-12- 2020-12- 2021-01- 2020-12- 2021-07- 2021-04- Finance and the State Secr IDA / 60850 he efficiency of Public Fina Post Direct 1,400.00 1,400.00 Completed ultant Selection 9 02 19 03 10 03 14 03 13 02 etary, and the official corre ncial Management spondence documents sent by the MOF to other organi zations during 2004-2008 A 4 documents of MOF C11/CS/0028 / National Le gal Expert for providing co Component C: Enhancing Individual Cons 2020-11-0 2020-12- 2021-01- 2021-02- 2021-08- IDA / 60850 Post Open 11,000.00 0.00 Canceled nsultancy on financial mark Financial Sector Stability ultant Selection 9 28 18 22 21 ets and insurance related l aws D1/CS/0041 / National con sulting company or NGO to Component D: Strengtheni support the development o 2020-11-2 2020-11- 2021-02- 2021-08- IDA / 60850 ng of the Social Protection Post Direct Selection Direct 10,000.00 0.00 Canceled f content for public awaren 0 30 03 02 System ess material (newspaper, j ournal, short video, other p rograms, handouts, and br ochure) A31/CS/018 / Consultancy service on developing plan Component A: Strengtheni for domestic secondary ma Individual Cons 2021-03-0 2021-09- 2021-04- 2021-11- 2021-05- 2021-11- 2021-06- 2021-11- 2021-12- 2022-05- IDA / 60840 ng Macroeconomic and Fis Post Open 20,000.00 10,159.01 Completed rket; review the clearing & ultant Selection 1 22 19 16 10 16 14 16 11 16 cal Management settlement structure with t he aim of identifying a set- up that handles all govern ment securities A31/CS/019 / Consultancy service on developing a for Component A: Strengtheni mal process manual for bor Individual Cons 2021-02-0 2021-03- 2021-04- 2021-05- 2021-11- IDA / 60840 ng Macroeconomic and Fis Post Open 12,000.00 0.00 Canceled rowings cost-risk analysis, ultant Selection 1 22 12 17 13 cal Management debt sustainability analysis reflecting DeMPA methodol ogy and best practices. B11/CS/020 / Consulting s Component B: Improving t Individual Cons 2021-02-0 2021-05- 2021-03- 2021-10- 2021-04- 2021-10- 2021-05- 2021-10- 2021-11- 2022-03- ervice to support Education IDA / 60840 he efficiency of Public Fina Post Open 24,000.00 13,451.22 Completed ultant Selection 1 11 22 22 12 25 17 25 13 30 sector financing reform ncial Management B12/CS/010 / Based on the previously conducted repor ts and assessment of the fu Component B: Improving t Individual Cons 2021-02-0 2021-03- 2021-03- 2021-04- 2021-04- 2021-04- 2021-05- 2021-04- 2021-11- 2022-01- ture needs of the GFS 2014 IDA / 60840 he efficiency of Public Fina Post Open 18,000.00 13,582.06 Completed ultant Selection 1 01 22 16 12 19 17 19 13 31 , identify and support imple ncial Management mentation of the key priorit y actions including develop ing and implementing the l egal … B21/CS/021 / National con sultant (team leader) to rev ise the regulations and inst Component B: Improving t Individual Cons 2021-02-1 2021-04- 2021-04- 2021-05- 2022-01- ructions including the chart IDA / 60840 he efficiency of Public Fina Post Open 26,000.00 0.00 Canceled ultant Selection 5 05 26 31 31 of accounts and guidelines ncial Management for the accounts followed in public sector accounting in accordance with the most r ecent IPSAS and IFRS ... B21/CS/022 / National con sultant (team member) to r evise the regulations and i Component B: Improving t nstructions including the ch Individual Cons 2021-02-1 2021-04- 2021-04- 2021-05- 2021-11- IDA / 60840 he efficiency of Public Fina Post Open 9,000.00 0.00 Canceled art of accounts and guideli ultant Selection 5 05 26 31 27 ncial Management nes for the accounts follow ed in public sector accounti ng in accordance with the most recent IPSAS and IFRS … B21/CS/026 / National con sultant to conduct translati Component B: Improving t Individual Cons 2021-04-0 2021-03- 2021-04- 2021-03- 2021-05- 2021-03- 2021-06- 2021-03- 2021-08- 2021-09- on and edits of the translati IDA / 60840 he efficiency of Public Fina Post Direct 8,765.26 8,750.56 Completed ultant Selection 1 23 11 26 02 24 06 24 06 30 on of new standards and a ncial Management mendments to IPSAS 2018 and IPSAS 2019. B21/CS/027 / Consultancy service for layout and readi Component B: Improving t ng before publishing the tr 2021-07-0 2021-07- 2021-09- 2022-03- IDA / 60840 he efficiency of Public Fina Post Direct Selection Direct 175.44 0.00 Canceled anslation of new standards 1 11 14 13 ncial Management and amendments to IPSAS 2018 and IPSAS 2019 in sof t version as PDF format via MOF webpage. A32/CS/011 / National con Component A: Strengtheni Individual Cons 2019-05-1 2019-06- 2019-07- 2019-08- 2020-02- sultant on improving the le IDA / 60840 ng Macroeconomic and Fis Post Open 30,000.00 0.00 Canceled ultant Selection 0 28 19 23 19 gal framework of the Devel cal Management opment finance A31/CS/017 / Consultancy service on improving dome stic primary market by revi Component A: Strengtheni ewing domestic primary m Individual Cons 2021-02-0 2021-09- 2021-03- 2021-11- 2021-04- 2021-11- 2021-05- 2021-11- 2021-11- 2022-03- IDA / 60840 ng Macroeconomic and Fis Post Open 22,000.00 3,982.81 Completed arket, testing alternative g ultant Selection 1 23 22 16 12 16 17 16 13 16 cal Management overnment sercurities and i ssuance mechanisms, setti ng limits on individual purc hases and other mechanis ms A2/CS/10 / National consul tant to carry out comprehe Component A: Strengtheni nsive financial analysis on t Individual Cons 2021-02-0 2021-06- 2021-03- 2021-08- 2021-04- 2021-08- 2021-05- 2021-08- 2021-11- IDA / 60840 ng Macroeconomic and Fis Post Open 32,500.00 37,971.62 Terminated he activities of state owned ultant Selection 1 15 22 16 12 17 17 17 13 cal Management enterprises (including meg a projects) and other reven ue mobilization measures C21/CS/008 / International Individual Consultant to de Component C: Enhancing Individual Cons 2021-01-2 2021-07- 2021-03- 2021-09- 2021-03- 2021-09- 2021-05- 2021-09- 2021-11- velop methodology for proj IDA / 60840 Post Open 56,000.00 50,400.00 Signed Financial Sector Stability ultant Selection 0 09 10 23 31 24 05 24 01 ect development, credit ap praisal and its risk manage ment. B22/CS/034 / National con sultants to provide support to implement E-learning to Component B: Improving t ols (knowlegde base syste Individual Cons 2021-03-0 2021-05- 2021-04- 2021-06- 2021-05- 2021-06- 2021-06- 2021-06- 2021-12- 2022-01- IDA / 60840 he efficiency of Public Fina Post Open 18,000.00 12,777.35 Completed m) for treasury officials and ultant Selection 1 03 19 02 10 02 14 02 11 31 ncial Management budget entities accountant s for better treasury servic es including payroll, financi al reporting and fiscal repo rting B33/CS/015 / National con Component B: Improving t sultant to revise procureme Individual Cons 2021-03-1 2021-03- 2021-04- 2021-04- 2021-05- 2021-04- 2021-06- 2021-04- 2021-12- 2022-01- IDA / 60840 he efficiency of Public Fina Post Open 19,800.00 19,778.85 Completed nt planning and report regu ultant Selection 0 04 28 06 19 06 23 06 20 05 ncial Management lation based on current legi slation C11/CS/034 / National indi vidual consultancy service: Formulate recommendatio n to establish derivative fin Component C: Enhancing Individual Cons 2021-01-2 2021-05- 2021-03- 2021-07- 2021-03- 2021-07- 2021-05- 2021-07- 2021-11- IDA / 60840 Post Open 28,200.00 12,896.44 Signed ancial instruments based o Financial Sector Stability ultant Selection 0 20 10 02 31 02 05 02 01 n government securities an d improve the legal environ ment for the application of international standards and agreements C11/CS/037 / National indi vidual consultancy service: Component C: Enhancing Individual Cons 2021-03-0 2021-06- 2021-04- 2021-07- 2021-05- 2021-07- 2021-06- 2021-07- 2021-12- 2022-01- Carry out research and pro IDA / 60840 Post Open 25,650.00 12,945.74 Completed Financial Sector Stability ultant Selection 1 02 19 02 10 02 14 02 11 31 vide recommendations for developing mutual fund ma rket and services C11/CS/038 / National indi vidual consultancy service: Component C: Enhancing Individual Cons 2021-03-0 2021-08- 2021-04- 2021-10- 2021-05- 2021-10- 2021-06- 2021-10- 2021-12- 2022-01- IDA / 60840 Post Open 25,800.00 7,165.14 Completed Prepare draft amendments Financial Sector Stability ultant Selection 1 05 19 15 10 15 14 15 11 31 to the Financial leasing law C21/CS/009 / International Individual Consultant to de Component C: Enhancing Individual Cons 2021-04-0 2021-07- 2021-05- 2021-09- 2021-06- 2021-09- 2021-07- 2021-09- 2022-01- 2022-05- IDA / 60840 Post Open 45,000.00 45,000.00 Completed velop corporate governanc Financial Sector Stability ultant Selection 1 09 20 03 10 20 15 20 11 01 e framework and complian ce risk management C4/CS/32 / International co nsultant to assist/work with International Cooperation D Component C: Enhancing Individual Cons 2021-02-0 2020-12- 2021-02- 2020-12- 2021-03- 2020-12- 2021-04- 2020-12- 2021-10- 2021-04- IDA / 60840 Post Direct 10,000.00 8,400.00 Completed epartment to join the Enha Financial Sector Stability ultant Selection 1 18 11 18 04 28 08 28 05 09 nced Multilateral Memoran dum of Understanding with IOSCO and IAIS C4/CS/038 / International Consultant to assist the FR C's Insurance Market Depar Component C: Enhancing Individual Cons 2021-06-0 2021-07- 2021-08- 2021-09- 2022-03- IDA / 60840 Post Open 25,000.00 0.00 Canceled tment in developing guidan Financial Sector Stability ultant Selection 1 20 10 14 13 ce and embedding practice s in Insurtech/Regtech of th e insurance industry C4/CS/039 / National Cons ultant to assist the FRC's C Component C: Enhancing Individual Cons 2021-04-0 2021-06- 2021-05- 2021-09- 2021-06- 2021-09- 2021-07- 2021-09- 2022-01- 2022-01- GCD to improve/develop th IDA / 60840 Post Open 6,600.00 6,597.97 Completed Financial Sector Stability ultant Selection 1 15 20 07 10 10 15 10 11 09 e Mongolian Corporate Gov ernance Code in line with i nternational standard C4/CS/040 / International c onsultant to assist the FRC in drafting a Law on Regula Component C: Enhancing Individual Cons 2021-06-0 2021-05- 2021-07- 2021-06- 2021-08- 2021-06- 2021-09- 2021-07- 2022-03- 2021-12- IDA / 60840 Post Open 26,000.00 26,000.00 Completed tion for Dealers of Precious Financial Sector Stability ultant Selection 1 17 20 25 10 25 14 01 13 31 Metals and Stones (DPMS); a new market under the FR C regulation; C4/CS/041 / National cons ultant to assist the FRC in d Component C: Enhancing Individual Cons 2021-02-0 2021-05- 2021-03- 2021-07- 2021-04- 2021-08- 2021-05- 2021-08- 2021-11- 2021-11- IDA / 60840 Post Open 7,000.00 6,987.12 Completed rafting a Law on Regulation Financial Sector Stability ultant Selection 1 17 22 28 12 02 17 02 13 01 for Real Estate Agents (REA s) C5/CS/017 / Consultancy s ervice for developing AML/ CFT legal and regulatory fr Component C: Enhancing Individual Cons 2021-04-0 2021-06- 2021-05- 2021-07- 2021-06- 2021-07- 2021-07- 2021-07- 2022-01- IDA / 60840 Post Open 75,000.00 55,000.00 Signed amework focusing on the p Financial Sector Stability ultant Selection 1 10 20 22 10 26 15 28 11 reparation of Mongolia's 5t h year follow-up assessmen t by the Financial Action Ta sk Force (FATF)… C5/CS/018 / Local consulta ncy service: Banking and fi nancial sector legislation g ap and overlap analysis, re Component C: Enhancing Individual Cons 2021-02-0 2021-02- 2021-03- 2021-05- 2021-04- 2021-05- 2021-05- 2021-05- 2021-11- 2021-10- IDA / 60840 Post Open 10,000.00 9,988.31 Completed search project Financial Sector Stability ultant Selection 1 15 22 20 12 20 17 31 13 30 Conduct a research on all b anking sector related legisl ations and draft a analysis on possible gaps and overl aps. E/CS/018 / National consul Component E: Project Man Individual Cons 2021-03-0 2021-02- 2021-03- 2021-02- 2021-04- 2021-02- 2021-05- 2021-03- 2021-11- IDA / 60840 Post Direct 12,000.00 15,956.56 Signed tant for contract managem agement and Monitoring ultant Selection 1 26 11 26 01 26 06 01 02 ent C31/CS/004 / International consultant for introducing Risk-based premium syste Component C: Enhancing Individual Cons 2020-10-0 2020-11- 2020-12- 2021-01- 2021-07- IDA / 60850 Post Open 28,000.00 0.00 Canceled ms and developing Risk as Financial Sector Stability ultant Selection 2 20 11 15 14 sessment methodology for differentiating deposit insur ance premiums. C31/CS/005 / International consultant to develop conti Component C: Enhancing Individual Cons 2020-08-0 2020-09- 2020-10- 2020-11- 2021-05- IDA / 60850 Post Open 45,000.00 0.00 Canceled ngency plan and crisis man Financial Sector Stability ultant Selection 7 25 16 20 19 agement framework amon g safety-nets. C4/CS/025 / National cons ulting firm to provide techn ical assistance in implemen tation of immediate outco Component C: Enhancing 2020-05-0 2020-05- 2020-07- 2021-01- IDA / 60850 Post Direct Selection Direct 27,400.00 0.00 Canceled mes set by FATF regional b Financial Sector Stability 1 11 15 11 ody (APG) and support in A ction plan agreed with FAT F relevant immediate outco mes to FRC; to assist with F RC's regulated and reportin C4/CS/032 / International c g.. onsultant to assist/work wit h International Cooperation Component C: Enhancing Individual Cons 2020-04-2 2020-05- 2020-06- 2020-07- 2020-08- 2021-02- IDA / 60850 Post Open 10,000.00 0.00 Canceled Department to join the Enh Financial Sector Stability ultant Selection 3 08 11 02 06 02 anced Multilateral Memora ndum of Understanding wit h IOSCO and IAIS. D1/CS/048 / National cons ultant to finalize the draft L aw on Social Welfare and r Component D: Strengtheni Individual Cons 2021-02-1 2021-04- 2021-03- 2021-05- 2021-04- 2021-05- 2021-05- 2021-05- 2021-11- 2022-01- elated implementation guid IDA / 60840 ng of the Social Protection Post Open 20,900.00 15,959.97 Completed ultant Selection 0 19 31 18 21 18 26 18 22 18 elines, and to develop guid System elines on improving the exi sting delivery mechanism o f the social welfare progra ms... D2/CS/040 / National cons ultant to develop a draft so cial insurance package law, Component D: Strengtheni Individual Cons 2021-02-2 2021-05- 2021-04- 2021-06- 2021-05- 2021-06- 2021-06- 2021-06- 2021-12- 2022-01- accompanying procedures, IDA / 60840 ng of the Social Protection Post Open 17,600.00 13,984.07 Completed ultant Selection 0 18 10 15 01 15 05 15 02 15 rules and methodologies to System increase public awareness and support the developme nt of online training materi als and content (1) D2/CS/041 / National cons ultant to develop a draft so cial insurance package law, Component D: Strengtheni Individual Cons 2021-02-2 2021-05- 2021-04- 2021-06- 2021-05- 2021-06- 2021-06- 2021-06- 2021-12- 2022-01- accompanying procedures, IDA / 60840 ng of the Social Protection Post Open 17,600.00 13,984.07 Completed ultant Selection 0 17 10 15 01 15 05 15 02 15 rules and methodologies to System increase public awareness and support the developme nt of online training materi als and content (2) D2/CS/046 / National cons ultant to provide translatio n service of online training Component D: Strengtheni Individual Cons 2021-03-0 2021-12- 2021-04- 2022-02- 2021-05- 2022-03- 2021-06- 2022-03- 2021-12- on Safety Net and Social In IDA / 60840 ng of the Social Protection Post Open 14,000.00 7,859.20 Signed ultant Selection 1 22 19 28 10 01 14 01 11 surance Policy and Internat System ional experience on Social Welfare Policy and to prepa re handouts in English and Mongolian D2/CS/047 / National cons Component D: Strengtheni Individual Cons 2021-03-2 2021-05- 2021-05- 2021-07- 2021-12- ultant to assist to publish a IDA / 60840 ng of the Social Protection Post Open 8,000.00 0.00 Canceled ultant Selection 0 08 29 03 30 nd edit documents System E/CS/019 / Project Assistan Component E: Project Man Individual Cons 2021-02-2 2021-02- 2021-03- 2021-03- 2021-03- 2021-03- 2021-03- 2021-05- 2021-09- 2021-12- IDA / 60840 Post Direct 12,100.00 7,704.54 Completed t at the PIU agement and Monitoring ultant Selection 5 26 03 15 06 15 14 11 10 31 A1/CS/020 / National cons ultant to develop a policy r Component A: Strengtheni ecommendation on populat Individual Cons 2021-04-0 2021-04- 2021-04- 2021-04- 2021-05- 2021-04- 2021-06- 2021-04- 2021-12- IDA / 60840 ng Macroeconomic and Fis Post Direct 16,500.00 28,289.79 Signed ion livelihoods and poverty ultant Selection 5 06 15 06 06 06 10 06 07 cal Management reduction, and develop a m odel and methodology for e stimating poverty indicator s B12/CS/011 / National con sultant to support the MOF to refine current procedure Component B: Improving t for local budget planning, i Individual Cons 2021-04-0 2021-04- 2021-04- 2021-04- 2021-05- 2021-04- 2021-06- 2021-04- 2022-01- 2022-01- IDA / 60840 he efficiency of Public Fina Post Direct 12,000.00 11,226.20 Completed mprove current regulatory ultant Selection 9 20 19 22 10 21 14 21 31 31 ncial Management mechanism for LDF transfe rs, and align the Budget La w with the Law on Administ rative and Territorial Units of Mongolia and Their Gove rD2/CS/34 / Professional en tity to training on impleme Component D: Strengtheni ntation of a quality manage 2021-04-0 2020-07- 2021-04- 2021-01- 2021-06- 2021-01- 2021-12- 2021-03- IDA / 60840 ng of the Social Protection Post Direct Selection Direct 2,500.00 2,427.87 Completed ment system according to I 4 01 14 07 18 07 15 07 System SO 9001:2015 Social Insura nce Department of Bayanz urkh district C11/CS/040 / Coordinating Component C: Enhancing Individual Cons 2021-06-0 2021-06- 2021-07- 2021-07- 2021-08- 2021-07- 2021-09- 2021-07- 2022-01- 2022-01- Consultant for Sub-Compon IDA / 60840 Post Open 12,000.00 10,495.66 Completed Financial Sector Stability ultant Selection 9 09 28 05 18 05 22 02 31 31 ent C1-C3 for the SFFS Proj ect B13/CS/017 / National con sultant to provide functiona Component B: Improving t Individual Cons 2021-06-0 2021-06- 2021-07- 2021-08- 2021-09- 2022-01- l and technical support for IDA / 60840 he efficiency of Public Fina Post Open 9,600.00 0.00 Canceled ultant Selection 7 08 26 16 20 31 development and customiz ncial Management ation of the Leader Monitori ng system B21/CS/023 / National con sultant (Team leader) to or ganize and manage conduc Component B: Improving t ting independent assessme Individual Cons 2021-08-0 2021-06- 2021-09- 2021-09- 2021-10- 2021-09- 2021-11- 2021-09- 2022-05- 2021-12- IDA / 60840 he efficiency of Public Fina Post Open 5,280.00 5,274.58 Completed nt of students’ knowledge ultant Selection 1 08 19 07 10 13 14 13 15 31 ncial Management and skills in accounting and other relevant subjects as well as public sector accou ntants’ knowledge of IPSAS s in order to assess... B21/CS/024 / National con sultant to organize and ma nage conducting independ Component B: Improving t ent assessment of students Individual Cons 2021-08-0 2021-06- 2021-09- 2021-09- 2021-10- 2021-09- 2021-11- 2021-09- 2022-05- IDA / 60840 he efficiency of Public Fina Post Open 7,280.00 7,272.53 Terminated ’ knowledge and skills in ac ultant Selection 1 08 19 07 10 13 14 13 13 ncial Management counting and other relevan t subjects as well as public sector accountants’ knowle dge of IPSASs … Team me mber (1) Page 13 B21/CS/025 / National con sultant to organize and ma nage conducting independ Component B: Improving t ent assessment of students Individual Cons 2021-08-0 2021-06- 2021-09- 2021-09- 2021-10- 2021-09- 2021-11- 2021-09- 2022-05- 2021-12- IDA / 60840 he efficiency of Public Fina Post Open 5,440.00 5,434.42 Completed ’ knowledge and skills in ac ultant Selection 1 08 19 07 10 13 14 13 13 31 ncial Management counting and other relevan t subjects as well as public sector accountants’ knowle dge of IPSASs … Team me mber (2) A1/CS/021 / Consultancy s ervice to develop a graphic al user interface which pro Component A: Strengtheni vides at-a-glance views of Individual Cons 2021-06-1 2021-08- 2021-06- 2021-08- 2021-07- 2021-08- 2021-07- 2021-08- 2022-01- IDA / 60840 ng Macroeconomic and Fis Post Direct 12,000.00 25,281.05 Signed key performance indicators ultant Selection 4 24 24 30 01 30 22 30 31 cal Management relevant to the Governmen t of Mongolia’s comprehens ive plan for health protecti on and economic recovery C4/CS/042 / National cons Component C: Enhancing Individual Cons 2021-06-2 2021-06- 2021-08- 2021-09- 2021-09- 2021-09- 2021-10- 2021-09- 2022-01- 2022-01- ultant (Team leader) to dra IDA / 60840 Post Open 8,000.00 7,997.87 Completed Financial Sector Stability ultant Selection 9 09 17 09 07 10 12 10 31 09 ft amendments/revision of i nsurance legislation C4/CS/043 / National cons Component C: Enhancing Individual Cons 2021-06-2 2021-07- 2021-08- 2021-09- 2021-09- 2021-09- 2021-10- 2021-09- 2022-01- 2022-01- ultant (Team member) to d IDA / 60840 Post Open 7,200.00 7,198.09 Completed Financial Sector Stability ultant Selection 9 09 17 02 07 10 12 10 31 09 raft amendments/revision o f insurance legislation D1/CS/055 / National cons Component D: Strengtheni Individual Cons 2021-07-1 2021-12- 2021-09- 2022-01- 2021-09- 2022-01- 2021-10- 2022-01- 2022-01- 2022-03- ultant to develop guideline IDA / 60840 ng of the Social Protection Post Open 4,500.00 4,483.05 Completed ultant Selection 8 22 05 21 26 21 31 24 31 23 s for implementing the PMT System methodology C5/CS/020 / Coordinating Component C: Enhancing Individual Cons 2021-09-1 2021-09- 2021-09- 2021-09- 2021-10- 2021-09- 2021-11- 2021-09- 2022-01- IDA / 60840 Post Direct 7,000.00 32,009.49 Signed Consultant for sub-compon Financial Sector Stability ultant Selection 0 17 20 20 11 20 15 20 31 ent C5 A32/CS/014 / Translation s Component A: Strengtheni ervice for revision of the G Individual Cons 2021-12-0 2021-11- 2021-12- 2021-11- 2022-01- 2021-11- 2022-02- 2021-11- 2022-08- 2021-12- IDA / 60840 ng Macroeconomic and Fis Post Direct 1,800.00 1,784.82 Completed overnment Regulation of fo ultant Selection 2 12 12 12 02 12 06 15 05 31 cal Management reign aid and related docu ments B21/CS/028 / National con sultant to organize and ma nage conducting independ Component B: Improving t ent assessment of students Individual Cons 2021-12-0 2021-07- 2022-01- 2021-10- 2022-02- 2021-10- 2022-03- 2021-10- 2022-09- 2021-12- IDA / 60840 he efficiency of Public Fina Post Open 7,280.00 7,219.42 Completed ’ knowledge and skills in ac ultant Selection 2 01 20 13 10 13 17 13 13 31 ncial Management counting and other relevan t subjects as well as public sector accountants’ knowle dge of IPSASs Team memb er 1 B22/CS/035 / National con Component B: Improving t sultant to provide senior fu Individual Cons 2021-12-1 2021-12- 2021-12- 2021-12- 2022-01- 2021-12- 2022-02- 2021-12- 2022-08- IDA / 60840 he efficiency of Public Fina Post Direct 21,000.00 20,717.29 Signed nctional support to further ultant Selection 9 28 29 28 19 28 23 28 22 ncial Management rollout of Integrated Payroll System for civil servants B32/CS/012 / Consulting s ervice to consolidate and u Component B: Improving t Individual Cons 2021-12-1 2021-12- 2021-12- 2021-12- 2022-01- 2021-12- 2022-02- 2022-01- 2022-08- pdate the strategic goals of IDA / 60840 he efficiency of Public Fina Post Direct 500.00 495.42 Signed ultant Selection 9 28 29 28 19 28 23 31 22 MOF 2021-2024, and provi ncial Management de quantitative indicators a nd determine the results to be achieved D2/CS/053 / National cons ultant to provide translatio n service of online training Component D: Strengtheni Individual Cons Under Impleme 2021-12-2 2021-12- 2022-01- 2022-02- 2022-08- on Safety Net and Social In IDA / 60840 ng of the Social Protection Post Direct 6,000.00 0.00 ultant Selection ntation 0 30 20 24 23 surance Policy and Internat System ional experience on Social Welfare Policy and to prepa re handouts in English and Mongolian A2/CS/022 / National cons Component A: Strengtheni ultant to develop and impr Individual Cons 2021-12-1 2022-04- 2022-02- 2022-05- 2022-02- 2022-05- 2022-04- 2022-05- 2022-09- IDA / 60840 ng Macroeconomic and Fis Post Open 24,000.00 18,992.86 Signed ove domestic legislations r ultant Selection 9 13 06 03 27 03 03 03 30 cal Management elated to Customs reform A1/CS/022 / National cons ultant to build a general m odel for forecasting revenu Component A: Strengtheni Individual Cons 2022-01-3 2022-02- 2022-02- 2022-02- 2022-03- 2022-02- 2022-04- 2022-02- 2023-01- e stream from mega projec IDA / 60840 ng Macroeconomic and Fis Post Direct 13,500.00 13,377.78 Signed ultant Selection 0 15 09 16 02 16 06 16 31 ts; and fiscal analysis of su cal Management ch projects: A Tool for Fisca l Modeling of Projects, Fisca l calculations tool, and reve nue forecasting tool A1/CS/023 / National cons ultant to build a general m odel for forecasting revenu Component A: Strengtheni Individual Cons 2022-01-3 2022-02- 2022-02- 2022-02- 2022-03- 2022-02- 2022-04- 2022-02- 2023-01- e stream from mega projec IDA / 60840 ng Macroeconomic and Fis Post Direct 13,500.00 11,986.46 Signed ultant Selection 0 06 09 07 02 07 06 07 31 ts; and fiscal analysis of su cal Management ch projects: Feasibility and options analysis tool, Temp late of an Appraisal Report, Financial analysis tool … A1/CS/024 / National cons ultant to build a general m odel for forecasting revenu Component A: Strengtheni e stream from mega projec Individual Cons 2022-01-3 2022-02- 2022-02- 2022-02- 2022-03- 2022-02- 2022-04- 2022-02- 2023-01- IDA / 60840 ng Macroeconomic and Fis Post Direct 7,500.00 7,432.10 Signed ts; and fiscal analysis of su ultant Selection 0 15 09 16 02 16 06 16 31 cal Management ch projects: Template shee t of information from feasib ility studies, Built dataset o f a selected megaproject a nd a handbook for data. A2/CS/023 / National cons Component A: Strengtheni ultant to improve the effect Individual Cons Under Impleme 2022-02-1 2022-04- 2022-04- 2022-05- 2023-01- IDA / 60840 ng Macroeconomic and Fis Post Open 23,400.00 0.00 iveness of data analysis ca ultant Selection ntation 5 05 26 31 31 cal Management pacity of tax administration A2/CS/024 / National cons Component A: Strengtheni ultant to support tax collect Individual Cons Under Impleme 2022-02-1 2022-04- 2022-04- 2022-05- 2023-01- IDA / 60840 ng Macroeconomic and Fis Post Open 19,500.00 0.00 ion management and to im ultant Selection ntation 5 05 26 31 31 cal Management prove effectiveness of tax debt management A31/CS/020 / Consultancy service on developing a for Component A: Strengtheni mal process manual for bor Individual Cons 2022-02-1 2022-04- 2022-02- 2022-04- 2022-03- 2022-04- 2022-04- 2022-04- 2023-01- IDA / 60840 ng Macroeconomic and Fis Post Direct 16,800.00 12,143.07 Signed rowings cost-risk analysis, ultant Selection 5 05 25 06 18 06 22 06 31 cal Management debt sustainability analysis reflecting DeMPA methodol ogy and best practices B21/CS/029 / Team leader: Revising consolidated chart of accounts of the entities Component B: Improving t which are consolidated into Individual Cons 2022-03-0 2022-03- 2022-04- 2022-04- 2022-05- 2022-04- 2022-06- 2022-04- 2023-01- IDA / 60840 he efficiency of Public Fina Post Open 33,000.00 31,079.49 Signed the government's financial ultant Selection 1 01 19 06 10 05 14 11 31 ncial Management statements, accounting gui delines and methodology o f budget entities, and provi ding policy recommendatio n and methodology B21/CS/030 / Team memb er: Revising consolidated c Component B: Improving t hart of accounts of the enti Individual Cons 2022-03-0 2022-03- 2022-04- 2022-04- 2022-05- 2022-04- 2022-06- 2022-04- 2023-01- IDA / 60840 he efficiency of Public Fina Post Open 22,000.00 20,719.66 Signed ties which are consolidated ultant Selection 1 01 19 04 10 05 14 11 31 ncial Management into the government's finan cial statements, accounting guidelines and methodolog y B22/CS/036 / National con sultant to provide functiona Component B: Improving t Individual Cons Pending Imple 2022-01-3 2022-03- 2022-04- 2022-05- 2023-01- l support to implement Inte IDA / 60840 he efficiency of Public Fina Post Open 10,800.00 0.00 ultant Selection mentation 1 21 11 16 31 grated Payroll system (help ncial Management desk #1 central budget ent ities and UB) B22/CS/037 / National con sultant 1 to provide suppor t to implement output-base Component B: Improving t Individual Cons Under Impleme 2022-01-3 2022-03- 2022-04- 2022-05- 2023-01- d budgeting and financial r IDA / 60840 he efficiency of Public Fina Post Open 18,000.00 0.00 ultant Selection ntation 0 20 10 15 31 eports with developing req ncial Management uired guideline compliance with GFSM 2014 and IPSAS through E-tailan and GFMIS v7 (Team member) B22/CS/038 / National con sultant 2 to provide suppor t to implement output-base Component B: Improving t Individual Cons Under Impleme 2022-01-3 2022-03- 2022-04- 2022-05- 2023-01- d budgeting and financial r IDA / 60840 he efficiency of Public Fina Post Open 30,000.00 0.00 ultant Selection ntation 0 20 10 15 31 eports with developing req ncial Management uired guideline compliance with GFSM 2014 and IPSAS through E-tailan and GFMIS v7 (Team leader) B31/CS/012 / Consulting s ervice to prepare network environment, topology and Component B: Improving t Individual Cons 2022-04-0 2022-04- 2022-05- 2022-05- 2022-06- 2022-05- 2022-07- 2022-05- 2023-01- cables of the server rooms IDA / 60840 he efficiency of Public Fina Post Open 24,000.00 21,844.99 Signed ultant Selection 1 13 20 16 10 18 15 18 31 transferring to the new Dat ncial Management a Center, and ensure the n ormal and reliable network operation of Treasury and MOF B32/CS/013 / Consulting s ervice to Government loan Component B: Improving t Individual Cons Under Impleme 2022-04-0 2022-05- 2022-06- 2022-07- 2023-01- and aid, Public investment IDA / 60840 he efficiency of Public Fina Post Open 12,000.00 0.00 ultant Selection ntation 1 20 10 15 31 budget policy related to th ncial Management e budget portfolio of the Mi nister of Finance B33/CS/016 / National Con sultant to support finalizati on and adoption of the draf Component B: Improving t Individual Cons 2022-01-3 2022-01- 2022-02- 2022-01- 2022-03- 2022-01- 2022-04- 2022-01- 2023-01- t revision of the Public Proc IDA / 60840 he efficiency of Public Fina Post Direct 28,600.00 28,385.19 Signed ultant Selection 0 25 09 27 02 26 06 26 31 urement Law and to prepar ncial Management e follow-up rules and regul ations to be adopted under the Public Procurement La w of Mongolia B33/CS/017 / National Con sultant to provide a final re Component B: Improving t Individual Cons 2022-01-3 2022-01- 2022-02- 2022-01- 2022-03- 2022-01- 2022-04- 2022-01- 2022-10- 2022-02- ading of the draft revision IDA / 60840 he efficiency of Public Fina Post Direct 1,500.00 1,488.59 Completed ultant Selection 0 26 09 27 02 26 06 26 03 25 of the Public Procurement L ncial Management aw before submitting it to t he Parliament of Mongolia B33/CS/018 / Information t Component B: Improving t echnology (IT) consultant t Individual Cons 2022-01-3 2022-01- 2022-02- 2022-01- 2022-03- 2022-01- 2022-04- 2022-01- 2023-01- IDA / 60840 he efficiency of Public Fina Post Direct 24,050.00 23,869.27 Signed o support improvements to ultant Selection 0 25 09 27 02 26 06 26 31 ncial Management the Mongolian e-procureme nt system B33/CS/019 / National Con sultant to prepare standard technical specifications tha Component B: Improving t Individual Cons 2022-01-3 2022-04- 2022-03- 2022-05- 2022-04- 2022-05- 2022-05- 2022-05- 2023-01- t will be useful for contracti IDA / 60840 he efficiency of Public Fina Post Open 23,400.00 14,540.99 Signed ultant Selection 0 13 20 12 10 12 15 12 31 ng authorities to procure v ncial Management arieties of goods, works, an d services in compliance wi th sustainable developmen t goals C11/CS/035 / National indi vidual consultancy service: Conduct comprehensive int Component C: Enhancing Individual Cons Under Impleme 2022-04-0 2022-05- 2022-06- 2022-07- 2023-01- IDA / 60840 Post Open 21,600.00 0.00 ernational comparative res Financial Sector Stability ultant Selection ntation 1 20 10 15 31 earch and develop recomm endations on the new prod ucts and services to the sto ck market... C11/CS/036 / National indi vidual consultancy service: Develop a strategy and pla Component C: Enhancing Individual Cons Pending Imple 2022-03-0 2022-04- 2022-05- 2022-06- 2023-01- n for the phased implemen IDA / 60840 Post Open 21,600.00 0.00 Financial Sector Stability ultant Selection mentation 1 19 10 14 31 tation of the privatization o f state-owned and partly st ate-owned companies thro ugh the Mongolian Stock E xchange C11/CS/039 / National con sultancy service: Conduct r Component C: Enhancing Individual Cons Under Impleme 2022-03-1 2022-05- 2022-05- 2022-06- 2023-01- esearch on improving the l IDA / 60840 Post Open 21,600.00 0.00 Financial Sector Stability ultant Selection ntation 5 03 24 28 31 egal framework governing f oreign banking in Mongolia and international experienc e C11/CS/041 / National indi vidual consultancy service: Component C: Enhancing Individual Cons 2022-04-1 2022-05- 2022-04- 2022-05- 2022-05- 2022-05- 2022-06- 2022-05- 2023-01- Comprehensive study rese IDA / 60840 Post Direct 22,500.00 16,357.59 Signed Financial Sector Stability ultant Selection 5 19 25 20 16 20 20 20 31 arch on specific insurance l aws, government policies, and domestic market resea rch C4/CS/024 / Consulting ser vice: National Consulting fir m to train FRC's personnel; Conduct professional Englis Component C: Enhancing Under Impleme 2022-04-0 2022-04- 2022-06- 2023-01- IDA / 60840 Post Direct Selection Direct 18,000.00 0.00 h training to improve Englis Financial Sector Stability ntation 1 11 15 31 h literacy of personnel for q ualification of international professional courses by IOS CO, IAIS, AFI, ACURN etc - II (216 hours... C4/CS/044 / International c onsulting service to provid e advice to increase the nu mber of asset-backed secu Component C: Enhancing Individual Cons Under Impleme 2022-08-1 2022-03- 2022-10- 2022-10- 2022-11- 2023-01- IDA / 60840 Post Open 26,000.00 0.00 rities and mutual investme Financial Sector Stability ultant Selection ntation 5 31 03 24 28 31 nt funds; to introduce exch ange-trade funds (ETFs) an d derivatives; and improve the regulatory environment on share mutual funds ... C4/CS/045 / Consulting ser vice: International consulti ng service to conduct a stu Component C: Enhancing Individual Cons Under Impleme 2022-05-1 2022-05- 2022-07- 2022-07- 2022-08- 2023-01- dy and develop policy reco IDA / 60840 Post Open 26,000.00 0.00 Financial Sector Stability ultant Selection ntation 5 20 03 24 28 31 mmendations for the devel opment of the green financ ial sector market within the framework of the Green Gr owth concept C4/CS/046 / International c onsulting service to suppor t the Anti-Money Launderin g Compliance Unit under th Component C: Enhancing Individual Cons 2022-02-1 2022-02- 2022-03- 2022-04- 2023-01- IDA / 60840 Post Direct 10,000.00 0.00 Canceled e Supervision Department t Financial Sector Stability ultant Selection 0 20 13 17 31 o review Follow-Up Reports (FURs) for assessment for u pcoming Mutual Evaluation of the implementation of a nti-money laundering and .. .C4/CS/047 / National Cons ultant to make a research a nd analyze the barriers to i ncrease professional/institu Component C: Enhancing Individual Cons Under Impleme 2022-05-0 2022-06- 2022-07- 2022-08- 2023-01- IDA / 60840 Post Open 7,200.00 0.00 tional investors’ base and d Financial Sector Stability ultant Selection ntation 1 19 10 14 31 evelop related policy and r egulatory recommendation on improving the participat ion of professional/instituti onal investors C4/CS/048 / National Cons ultant to develop a draft Di gital Transformation progra Component C: Enhancing Individual Cons 2022-04-0 2022-04- 2022-05- 2022-06- 2023-01- IDA / 60840 Post Direct 6,400.00 0.00 Canceled m for the FRC and a schem Financial Sector Stability ultant Selection 1 11 02 06 31 atic model within the frame work of the National Digital Transformation program (T eam Lead) C4/CS/049 / National Cons ultant to develop a draft Di gital Transformation progra Component C: Enhancing Individual Cons 2022-04-0 2022-04- 2022-05- 2022-06- 2023-01- IDA / 60840 Post Direct 5,600.00 0.00 Canceled m for the FRC and a schem Financial Sector Stability ultant Selection 1 11 02 06 31 atic model within the frame work of the National Digital Transformation program (T eam Member) C4/CS/051 / National Cons ultant to conduct study on f Component C: Enhancing Individual Cons 2022-05-0 2022-03- 2022-06- 2022-06- 2022-07- 2022-06- 2022-08- 2022-06- 2023-01- IDA / 60840 Post Open 3,600.00 3,271.24 Signed inancial group's supervisio Financial Sector Stability ultant Selection 1 31 19 08 10 09 14 09 31 n and regulation and provid e recommendations C4/CS/052 / National Cons ultant to assist in departme Component C: Enhancing Individual Cons Under Impleme 2022-02-2 2022-03- 2022-03- 2022-04- 2023-01- nts for translating laws, rul IDA / 60840 Post Direct 3,000.00 0.00 Financial Sector Stability ultant Selection ntation 0 02 23 27 31 es and regulations for inter national consultants' assig nments C5/CS/021 / National Cons Component C: Enhancing Individual Cons Pending Imple 2022-04-0 2022-05- 2022-06- 2022-07- 2023-01- ultant: Correspondent bank IDA / 60840 Post Open 3,000.00 0.00 Financial Sector Stability ultant Selection mentation 1 20 10 15 31 ing-related International co nsulting service C5/CS/022 / International c Component C: Enhancing Individual Cons Pending Imple 2022-06-0 2022-07- 2022-08- 2022-09- 2023-01- onsultant for establishing a IDA / 60840 Post Open 21,000.00 0.00 Financial Sector Stability ultant Selection mentation 1 20 10 14 30 credit rating system based on a credit database C5/CS/023 / National cons Component C: Enhancing Individual Cons Pending Imple 2022-06-0 2022-07- 2022-08- 2022-09- 2023-01- ultant for supporting the es IDA / 60840 Post Open 9,000.00 0.00 Financial Sector Stability ultant Selection mentation 1 20 10 14 31 tablishment of a credit rati ng system C5/CS/024 / International c onsulting services to introd uce Supervisory review and Component C: Enhancing Individual Cons Pending Imple 2022-05-0 2022-06- 2022-07- 2022-08- 2023-01- IDA / 60840 Post Open 21,000.00 0.00 evaluation process, ICAAP, Financial Sector Stability ultant Selection mentation 1 19 10 14 31 and Internal Liquidity Asses sment Methodology (ILAAP) in banking supervision proc edures; C5/CS/025 / National cons ulting services to support S upervisory review and eval Component C: Enhancing Individual Cons Pending Imple 2022-05-0 2022-06- 2022-07- 2022-08- 2023-01- IDA / 60840 Post Open 9,000.00 0.00 uation process, ICAAP, and Financial Sector Stability ultant Selection mentation 1 19 10 14 31 Internal Liquidity Assessme nt Methodology (ILAAP) in b anking supervision procedu res; C5/CS/026 / International c onsultant on international b Component C: Enhancing Individual Cons Pending Imple 2022-03-0 2022-04- 2022-05- 2022-06- 2023-01- est practices in establish di IDA / 60840 Post Open 41,000.00 0.00 Financial Sector Stability ultant Selection mentation 1 19 10 14 31 versified, market based sus tainable mortgage financin g scheme C5/CS/027 / National cons ultant on supporting establi Component C: Enhancing Individual Cons Under Impleme 2022-03-0 2022-04- 2022-05- 2022-06- 2023-01- IDA / 60840 Post Open 9,000.00 0.00 shment of diversified, mark Financial Sector Stability ultant Selection ntation 1 19 10 14 31 et based sustainable mortg age financing scheme. D1/CS/0007 / National con sultant to support the MLSP in i) Parliamentarian discus Component D: Strengtheni sion of the draft Law on So Individual Cons Pending Imple 2022-02-1 2022-03- 2022-04- 2022-05- 2023-01- IDA / 60840 ng of the Social Protection Post Open 20,000.00 0.00 cial Welfare; ii) further dev ultant Selection mentation 0 31 21 26 31 System eloping and finalizing relat ed implementation guidelin es, iii) finalizing guidelines i ncluding enhancing the mo nitoring and ... D1/CS/046 / National Cons Component D: Strengtheni Individual Cons 2022-02-1 2022-04- 2022-02- 2022-04- 2022-03- 2022-04- 2022-04- 2022-04- 2023-01- ultant for developing strate IDA / 60840 ng of the Social Protection Post Direct 5,000.00 4,670.02 Signed ultant Selection 0 13 20 14 13 14 17 14 31 gies in the field of labor an System d social protection D1/CS/062 / National cons ultant to analyze the needs and develop recommendati Component D: Strengtheni Individual Cons Pending Imple 2022-04-0 2022-05- 2022-06- 2022-07- 2023-01- ons and methodologies and IDA / 60840 ng of the Social Protection Post Open 8,000.00 0.00 ultant Selection mentation 1 20 10 15 31 draft government resolutio System ns for an emergency social protection response to hou seholds affected by shock ( zud-affected) D1/CS/063 / English langu age training institution to p rovide English language tra Component D: Strengtheni Under Impleme 2022-02-2 2022-03- 2022-05- 2023-01- ining to social insurance an IDA / 60840 ng of the Social Protection Post Direct Selection Direct 6,000.00 0.00 ntation 0 02 06 31 d welfare specialists (for in System creasing staff capacity to le arn from international expe rience in policy developme nt and implementation) Page 14 D1/CS/064 / Consultancy s Component D: Strengtheni Individual Cons Pending Imple 2022-02-2 2022-04- 2022-05- 2022-06- 2023-01- ervices for translation and i IDA / 60840 ng of the Social Protection Post Open 10,000.00 0.00 ultant Selection mentation 0 10 01 05 31 nterpretation services (1) System D2/CS/039 / National cons ultant to support the MLSP in i) to support Parliamenta Component D: Strengtheni rian discussions of the final Individual Cons Under Impleme 2022-02-1 2022-03- 2022-04- 2022-05- 2023-01- IDA / 60840 ng of the Social Protection Post Open 20,000.00 0.00 draft Law on Pensions Provi ultant Selection ntation 0 31 21 26 31 System ded from the Social Insuran ce Fund, and the final draft Law on Pensions, Benefits, and Payments for Industrial Accidents and ... D2/CS/054 / National cons ultant to support IC in prep aring and delivering knowle Component D: Strengtheni dge and information sessio Individual Cons Pending Imple 2022-04-0 2022-05- 2022-06- 2022-07- 2023-01- IDA / 60840 ng of the Social Protection Post Open 5,000.00 0.00 ns on FDC (design, legal an ultant Selection mentation 1 20 10 15 31 System d institutional requirement s and roles, international e xperiences), for relevant st akeholders such as employ ers associations, trade... D2/CS/055 / Research insti tute or NGO to provide trai Component D: Strengtheni ning for social insurance an Under Impleme 2022-02-2 2022-03- 2022-05- 2023-01- IDA / 60840 ng of the Social Protection Post Direct Selection Direct 5,000.00 0.00 d welfare workers to use SP ntation 0 02 06 31 System SS, STATA software progra ms in the field of social pro tection policy E/CS/020 / Procurement Sp Component E: Project Man Individual Cons 2022-02-0 2022-03- 2022-02- 2022-02- 2022-03- 2022-02- 2022-04- 2022-02- 2023-04- IDA / 60840 Post Direct 24,000.00 15,986.12 Signed ecialist at the PIU agement and Monitoring ultant Selection 1 01 11 01 04 01 08 01 30 A32/CS/016 / National con sultant on identifying issue s and challenges in project Component A: Strengtheni Individual Cons 2022-02-2 2022-05- 2022-03- 2022-05- 2022-03- 2022-05- 2022-04- 2022-05- 2022-10- launch and implementation IDA / 60840 ng Macroeconomic and Fis Post Direct 26,500.00 9,360.18 Signed ultant Selection 2 19 04 20 25 20 29 20 26 , overseeing timelines, and cal Management developing an operational manual and recommendati ons for implementing agen cies A32/CS/017 / National con sultant on software/databa Component A: Strengtheni Individual Cons 2022-03-0 2022-04- 2022-03- 2022-04- 2022-04- 2022-04- 2022-05- 2022-04- 2022-11- se development updating a IDA / 60840 ng Macroeconomic and Fis Post Direct 18,000.00 16,684.76 Signed ultant Selection 1 14 11 14 01 14 06 14 02 nd maintaining Tax exempt cal Management ion recording system datab ase B12/CS/012 / National con sultant to contribute to imp Component B: Improving t Individual Cons 2022-02-2 2022-02- 2022-03- 2022-02- 2022-03- 2022-02- 2022-05- 2022-02- 2022-11- roving Local Development IDA / 60840 he efficiency of Public Fina Post Direct 21,000.00 20,737.49 Signed ultant Selection 8 25 10 25 31 25 05 25 01 Fund planning and manage ncial Management ment as well as public fina ncial management at the lo cal level B4/CS/025 / National cons ultant to support the consol Component B: Improving t idation and fast retrieval of Individual Cons 2022-02-2 2022-03- 2022-03- 2022-03- 2022-03- 2022-03- 2022-05- 2022-03- 2022-11- IDA / 60840 he efficiency of Public Fina Post Direct 6,000.00 5,854.06 Signed archival records to prepare ultant Selection 8 04 10 07 31 07 05 07 01 ncial Management for electronic processing of financing for public invest ment projects A32/CS/018 / National con Component A: Strengtheni sultant to support develop Individual Cons 2022-04-1 2022-04- 2022-04- 2022-04- 2022-05- 2022-04- 2022-06- 2022-04- 2022-12- IDA / 60850 ng Macroeconomic and Fis Post Direct 30,000.00 27,548.11 Signed ment cooperation policies a ultant Selection 1 26 21 26 12 26 16 26 13 cal Management nd strategies of official assi stance B11/CS/021 / National con sultant to support the MOF in undertaking necessary st udies, analysis and estimat Component B: Improving t Individual Cons 2022-04-1 2022-04- 2022-04- 2022-04- 2022-05- 2022-04- 2022-06- 2022-04- 2022-12- ion for development and im IDA / 60850 he efficiency of Public Fina Post Direct 12,000.00 11,047.62 Signed ultant Selection 5 26 25 26 16 26 20 26 17 plementation of a reform p ncial Management rogram to improve the qual ity of and access to educati on through funding mecha nism of general education and TV C4/CS/46 / International co nsulting service to support the Anti-Money Laundering Compliance Unit under the Component C: Enhancing Individual Cons 2022-04-1 2022-04- 2022-06- 2022-06- 2022-06- 2022-06- 2022-07- 2022-06- 2023-01- IDA / 60850 Post Open 10,000.00 10,000.00 Signed Supervision Department to Financial Sector Stability ultant Selection 5 28 03 08 24 08 29 08 25 review Follow-Up Reports ( FURs) for assessment for u pcoming Mutual Evaluation of the implementation of a nti-money laundering and .. .C4/CS/48 / Consulting serv ice: National Consultant to develop a draft Digital Tran Component C: Enhancing Individual Cons 2022-04-1 2022-04- 2022-06- 2022-06- 2022-06- 2022-06- 2022-07- 2022-06- 2023-01- sformation program for the IDA / 60850 Post Open 6,400.00 5,815.54 Signed Financial Sector Stability ultant Selection 5 28 03 08 24 09 29 09 25 FRC and a schematic mode l within the framework of th e National Digital Transfor mation program (Team Lea d) C4/CS/49 / Consulting serv ice: National Consultant to develop a draft Digital Tran Component C: Enhancing Individual Cons Under Impleme 2022-04-1 2022-06- 2022-06- 2022-07- 2023-01- sformation program for the IDA / 60850 Post Open 5,600.00 0.00 Financial Sector Stability ultant Selection ntation 5 03 24 29 25 FRC and a schematic mode l within the framework of th e National Digital Transfor mation program (Team Me mber) A2/CS/11 / National consul Component A: Strengtheni tant to develop and improv Individual Cons 2021-02-0 2021-06- 2021-03- 2021-04- 2021-05- 2021-11- IDA / 60840 ng Macroeconomic and Fis Post Open 26,000.00 0.00 Canceled e domestic legislations rela ultant Selection 1 15 22 12 17 13 cal Management ted to Customs reform A32/CS/015 / National con sultant on identifieng issue s and challenges arise duri Component A: Strengtheni ng project implementation Individual Cons 2022-03-0 2022-04- 2022-05- 2022-06- 2023-02- IDA / 60840 ng Macroeconomic and Fis Post Open 14,000.00 0.00 Canceled process, overseeing the ov ultant Selection 1 19 10 14 28 cal Management erall flow of launching and i mplementing of project on time, and developing guide lines and recommendations for project implementing... B13/CS/16 / National cons ultant to provide functional Component B: Improving t Individual Cons 2022-03-0 2022-04- 2022-03- 2022-05- 2022-04- 2022-04- 2022-05- 2022-11- and technical support for d IDA / 60840 he efficiency of Public Fina Post Direct 6,000.00 0.00 Canceled ultant Selection 1 13 11 09 01 14 06 02 evelopment and customiza ncial Management tion of the Leader Monitori ng system C11/CS/024 / National con sultant to conduct research Component C: Enhancing Individual Cons 2020-07-2 2021-08- 2020-09- 2020-09- 2020-11- 2021-05- IDA / 60850 Post Open 19,350.00 0.00 Canceled on attracting investments i Financial Sector Stability ultant Selection 0 02 07 28 02 01 n insurance industry and d etermine its related policie s. C11/CS/029 / National Indi Component C: Enhancing Individual Cons 2020-09-2 2020-11- 2020-11- 2021-01- 2021-07- vidual Consultant to formul IDA / 60850 Post Open 9,200.00 0.00 Canceled Financial Sector Stability ultant Selection 0 08 29 03 02 ate appraisal methodology for financial reporting. C11/CS/030 / National Indi vidual Consultant to formul Component C: Enhancing Individual Cons 2021-05-0 2021-06- 2021-07- 2021-08- 2022-01- IDA / 60850 Post Open 8,200.00 0.00 Canceled ate appraisal methodology Financial Sector Stability ultant Selection 2 20 11 15 31 for movable property/perso nal property. C11/CS/031 / National Con Component C: Enhancing Individual Cons 2021-05-0 2021-06- 2021-07- 2021-08- 2022-01- sultant for developing auto IDA / 60850 Post Open 16,800.00 0.00 Canceled Financial Sector Stability ultant Selection 2 20 11 15 31 mated system for Professio nal Appraisal institutes. C21/CS/007 / International individual consultancy servi ce: In connection with the DBM becoming an export-i Component C: Enhancing Individual Cons 2022-03-0 2022-04- 2022-05- 2022-06- 2023-01- IDA / 60840 Post Open 40,000.00 0.00 Canceled mport bank, develop EXIM Financial Sector Stability ultant Selection 1 19 10 14 31 bank's policy draft docume ntation and recommendati on on the range of product s, trade financing, investm ent and international EXIM C31/CS/003 / International bank Component C: Enhancing Individual Cons 2020-06-0 2020-07- 2020-08- 2020-09- 2021-03- consultant for advising on IDA / 60850 Post Open 28,000.00 0.00 Canceled Financial Sector Stability ultant Selection 5 24 14 18 17 determining optimal deposi t insurance coverage. C4/CS/050 / National Cons ultant to identify relevant p Component C: Enhancing Individual Cons 2022-08-0 2022-08- 2022-09- 2022-10- 2023-01- olicies and approaches to IDA / 60840 Post Direct 5,400.00 0.00 Canceled Financial Sector Stability ultant Selection 1 11 01 06 31 develop and support the in surance market through th e stock market D1/CS/061 / International c onsultant to support the de Component D: Strengtheni velopment of a dynamic m Individual Cons Pending Imple 2022-06-3 2022-08- 2022-09- 2022-10- 2023-05- IDA / 60840 ng of the Social Protection Post Open 25,000.00 0.00 odel (software), especially i ultant Selection mentation 0 18 08 13 01 System n developing the software of social insurance actuaria l assessments of four SI su b-funds D1/CS/060 / National cons ulting firm or NGO to i) dev elop a dynamic model (soft Component D: Strengtheni ware) for projecting mid an 2022-02-2 2022-03- 2022-05- 2022-11- IDA / 60840 ng of the Social Protection Post Direct Selection Direct 15,000.00 0.00 Canceled d long-term effects of socia 0 02 06 02 System l welfare and social insuran ce policies, and ii) organize capacity building training o f sector employees on this assessment model D1/CS/042 / Translations s Component D: Strengtheni Individual Cons 2020-08-0 2020-07- 2020-08- 2020-09- 2020-10- 2021-04- IDA / 60850 Post Direct 5,000.00 0.00 Canceled ervices ng of the Social Protection ultant Selection 1 24 11 01 06 04 System D1/CS/059 / National cons Component D: Strengtheni ulting firm or NGO to devel 2022-04-2 2022-04- 2022-07- 2022-12- IDA / 60840 ng of the Social Protection Post Direct Selection Direct 5,000.00 0.00 Canceled op the content of public aw 0 30 04 31 System areness materials on soci al welfare reforms D2/CS/038 / National cons ulting firm or NGO to devel Component D: Strengtheni op public awareness materi 2022-03-1 2022-03- 2022-05- 2023-01- IDA / 60840 ng of the Social Protection Post Direct Selection Direct 5,000.00 0.00 Canceled als for gradually building so 0 20 24 31 System cial consensus on the pensi on reform needs and princi pals (newspaper, journal, . .. D2/CS/049 / National cons ultants to support the MLSP Component D: Strengtheni in drafting the regulations Individual Cons 2022-03-2 2022-03- 2022-04- 2022-05- 2022-11- IDA / 60840 ng of the Social Protection Post Direct 7,000.00 0.00 Canceled concerning legal and instit ultant Selection 0 30 20 25 10 System utional requirements of the FDC and SIF assets manag ement related regulations ( 2) D2/CS/026 / National cons ultants to support the MLSP Component D: Strengtheni in drafting the regulations Individual Cons 2022-03-2 2022-03- 2022-04- 2022-05- 2023-01- IDA / 60840 ng of the Social Protection Post Direct 7,000.00 0.00 Canceled concerning legal and instit ultant Selection 0 30 20 25 31 System utional requirements of the FDC and SIF assets manag ement related regulations ( 1) D2/CS/056 / National cons ultant to support the MLSP in i) to support Parliamenta Component D: Strengtheni rian discussions of the draft Individual Cons 2022-02-1 2022-02- 2022-03- 2022-04- 2023-01- IDA / 60840 ng of the Social Protection Post Direct 20,000.00 0.00 Canceled law on general social insur ultant Selection 0 20 13 17 31 System ance, and the draft law on benefits from the Social Ins urance Fund, ii) develop dr aft accompanying procedur es, rules, and method D2/CS/057 / International c onsultant to conduct an act uarial assessment of param Component D: Strengtheni Individual Cons 2022-03-3 2022-04- 2022-05- 2022-06- 2022-12- etric reforms to the Pensio IDA / 60850 ng of the Social Protection Post Direct 11,000.00 0.00 Canceled ultant Selection 1 10 01 05 02 n Insurance Scheme and th System e establishment of a Means -Tested Social Pension in li ne with the State Policy on Pension Reform 1 D2/CS/043 / International c onsultant to prepare and pr ovide knowledge and infor Component D: Strengtheni mation sessions on FDC (de Individual Cons Pending Imple 2022-06-3 2022-08- 2022-09- 2022-10- 2023-05- IDA / 60840 ng of the Social Protection Post Open 23,850.00 0.00 sign, legal and institutional ultant Selection mentation 0 18 08 13 01 System requirements and roles, int ernational experiences), for relevant stakeholders such as employers associations, trade unions... D2/CS/058 / International c onsultant to conduct an act uarial assessment of param Component D: Strengtheni Individual Cons 2022-03-3 2022-04- 2022-05- 2022-06- 2022-12- etric reforms to the Pensio IDA / 60850 ng of the Social Protection Post Direct 11,000.00 0.00 Canceled ultant Selection 1 10 01 05 02 n Insurance Scheme and th System e establishment of a Means -Tested Social Pension in li ne with the State Policy on Pension Reform 2 A2/CS/025 / National cons ultant to improve fiscal rev Component A: Strengtheni enue forecasting modelling Individual Cons Pending Imple 2022-06-1 2022-08- 2022-08- 2022-09- 2023-03- IDA / 60840 ng Macroeconomic and Fis Post Open 13,000.00 0.00 , revenue performance mo ultant Selection mentation 5 03 24 28 27 cal Management nitoring, revenue impact a nalysis of legal changes, an d measuring policy, compli ance gaps A2/CS/026 / National cons ultant to carry out compreh Component A: Strengtheni ensive financial analysis on Individual Cons Pending Imple 2022-06-1 2022-08- 2022-08- 2022-09- 2023-03- IDA / 60840 ng Macroeconomic and Fis Post Open 13,000.00 0.00 the activities of state owne ultant Selection mentation 5 03 24 28 27 cal Management d enterprises (including me ga projects) and other reve nue mobilization measures A2/CS/027 / National cons Component A: Strengtheni Individual Cons Pending Imple 2022-06-1 2022-08- 2022-08- 2022-09- 2023-03- ultant to provide support o IDA / 60840 ng Macroeconomic and Fis Post Open 17,000.00 0.00 ultant Selection mentation 5 03 24 28 27 n tax risk management cal Management A31/CS/021 / Consulting se rvices to develop a plan for Component A: Strengtheni the development of the sec Individual Cons Pending Imple 2022-09-0 2022-10- 2022-11- 2022-12- 2023-06- IDA / 60840 ng Macroeconomic and Fis Post Open 12,700.00 0.00 ondary market for domesti ultant Selection mentation 1 20 10 15 13 cal Management c securities and to determi ne the structure for the set tlement of government sec urities. A32/CS/019 / National con sultant on supporting the G Component A: Strengtheni overnment foreign loan an Individual Cons Pending Imple 2022-06-1 2022-08- 2022-08- 2022-09- 2023-03- IDA / 60840 ng Macroeconomic and Fis Post Open 6,400.00 0.00 d aid management informa ultant Selection mentation 5 03 24 28 27 cal Management tion system (ODAMIS) for t he development of a new p roject proposal module A32/CS/020 / IT developer Component A: Strengtheni Individual Cons Pending Imple 2022-06-1 2022-06- 2022-07- 2022-08- 2023-02- for the necssary improvem IDA / 60840 ng Macroeconomic and Fis Post Direct 12,000.00 0.00 ultant Selection mentation 5 25 16 20 16 ents and new modules for t cal Management he ODAMIS system A32/CS/021 / National con sultant on improving the m Component A: Strengtheni Individual Cons Pending Imple 2022-06-1 2022-08- 2022-08- 2022-09- 2023-03- onitoring and evaluation an IDA / 60840 ng Macroeconomic and Fis Post Open 6,400.00 0.00 ultant Selection mentation 5 03 24 28 27 d reporting process of exte cal Management rnally funded development projects A32/CS/022 / National con sultant to support the deve Component A: Strengtheni Individual Cons Pending Imple 2022-06-1 2022-06- 2022-07- 2022-08- 2023-02- lopment of methodology on IDA / 60840 ng Macroeconomic and Fis Post Direct 14,400.00 0.00 ultant Selection mentation 5 25 16 20 16 selection and prioritization cal Management of externally funded projec ts (MED) B13/CS/0016 / National co nsultant to provide function Component B: Improving t Individual Cons Pending Imple 2022-06-1 2022-06- 2022-07- 2022-08- 2023-02- al and technical support for IDA / 60840 he efficiency of Public Fina Post Direct 6,000.00 0.00 ultant Selection mentation 5 25 16 20 16 development and customiz ncial Management ation of the Leader Monitori ng system B21/CS/031 / National con Component B: Improving t sultant to develop methodo Individual Cons Pending Imple 2022-06-1 2022-08- 2022-08- 2022-09- 2023-03- IDA / 60840 he efficiency of Public Fina Post Open 4,500.00 0.00 logy for conducting financi ultant Selection mentation 5 03 24 28 27 ncial Management al analysis of budget entitie s, SOEs, and private entitie s. B21/CS/032 / National con sultant to develop a syste Component B: Improving t m, e-balance according to t Individual Cons Pending Imple 2022-06-2 2022-08- 2022-09- 2022-10- 2023-04- IDA / 60840 he efficiency of Public Fina Post Open 8,400.00 0.00 he methodology for conduc ultant Selection mentation 5 13 03 08 06 ncial Management ting financial analysis that i s to be developed by the ot her national consultant B21/CS/033 / National con Component B: Improving t sultancy service: National I Individual Cons Pending Imple 2022-07-2 2022-09- 2022-10- 2022-11- 2023-05- IDA / 60840 he efficiency of Public Fina Post Open 9,200.00 0.00 ndividual Consultant to for ultant Selection mentation 5 12 03 07 06 ncial Management mulate appraisal methodol ogy for financial reporting B21/CS/034 / National con sultancy service: National I Component B: Improving t Individual Cons Pending Imple 2022-07-2 2022-09- 2022-10- 2022-11- 2023-05- ndividual Consultant to for IDA / 60840 he efficiency of Public Fina Post Open 8,200.00 0.00 ultant Selection mentation 5 12 03 07 06 mulate appraisal methodol ncial Management ogy for movable property/p ersonal property B21/CS/035 / National con Component B: Improving t sultancy service: National Individual Cons Pending Imple 2022-07-2 2022-09- 2022-10- 2022-11- 2023-05- IDA / 60840 he efficiency of Public Fina Post Open 14,800.00 0.00 Consultant for developing a ultant Selection mentation 5 12 03 07 06 ncial Management utomated system for Profes sional Appraisal institutes B4/CS/026 / National cons ultant to identify measures Component B: Improving t to improve the public inves Individual Cons Pending Imple 2022-06-1 2022-08- 2022-08- 2022-09- 2023-03- IDA / 60840 he efficiency of Public Fina Post Open 10,000.00 0.00 tment management and s ultant Selection mentation 5 03 24 28 27 ncial Management upport the PID to get a for mal approval for the draft methodology for pre-scree ning B4/CS/027 / National cons ultant to help improve impl Component B: Improving t ementation and monitoring Individual Cons Pending Imple 2022-06-1 2022-08- 2022-08- 2022-09- 2023-03- IDA / 60840 he efficiency of Public Fina Post Open 10,000.00 0.00 of public investments proje ultant Selection mentation 5 03 24 28 27 ncial Management cts with regards to post-pro ject evaluation and public asset management C4/CS/50 / National Consul tant to identify relevant pol Component C: Enhancing Individual Cons Pending Imple 2022-06-1 2022-08- 2022-08- 2022-09- 2023-03- icies and approaches to de IDA / 60840 Post Open 5,400.00 0.00 Financial Sector Stability ultant Selection mentation 5 03 24 28 27 velop and support the insur ance market through the st ock market D2/CS/060 / International c onsultant for actuarial anal Component D: Strengtheni ysis of funds related to cha Individual Cons Pending Imple 2022-06-3 2022-08- 2022-09- 2022-10- 2023-04- IDA / 60840 ng of the Social Protection Post Open 50,000.00 0.00 nges in pension parameter ultant Selection mentation 0 18 08 13 11 System s and social insurance refor m during the transition to a multi-tiered pension syste m D2/CS/56 / "National consu ltant to support the MLSP i n i) to support Parliamentar Component D: Strengtheni ian discussions of the draft Individual Cons Pending Imple 2022-06-1 2022-08- 2022-08- 2022-09- 2023-03- IDA / 60840 ng of the Social Protection Post Open 20,000.00 0.00 law on general social insur ultant Selection mentation 5 03 24 28 27 System ance, and the draft law on benefits from the Social Ins urance Fund, ii) develop dr aft accompanying procedur es, rules, and methodo Page 15 E/CS/021 / Monitoring and Component E: Project Man Individual Cons Pending Imple 2022-06-1 2022-08- 2022-08- 2022-09- 2023-03- IDA / 60840 Post Open 16,200.00 0.00 evaluation consultant agement and Monitoring ultant Selection mentation 5 03 24 28 27 Page 16