PROCUREMENT PLAN (Textual Part) Project information: Country: Afghanistan Project name: Cities Investment Program (CIP) Project ID: P160619 Project Implementation agency: Deputy Ministry for Municipalities (DMM) IDLG Date of the Procurement Plan: 28 October 2019 Period covered by this Procurement Plan: The Procurement plan covers the period of 6 Months Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the Model Procurement Documents agreed by the bank shall be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Procurement Law of the Islamic Republic of Afghanistan dated 27/06/13965 (September 17, 2016) published in the Official Gazette No.1223, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following NPP Conditions for Afghanistan: 1. The eligibility of bidders shall be as defined under Section III of the World Bank Procurement Regulations for IPF Borrowers (Procurement Regulations). Accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations (PR). 2. Only the model bidding documents acceptable to the World Bank shall be used for all national open competitive procurement. 3. The bidding documents shall require that bidders/proposers submitting bids/proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. 4. There shall be no negotiations of contract price at post contract stage or termination of the contract - on grounds of operation of Price Adjustment stipulated in a signed contract exceeding a specified percentage. 5. No preference of any kind shall be given to national bidders in the bidding process. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: [is not applicable/ is applicable for those contracts identified in the Procurement Plan tables]; NA Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; NA Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. “Not Applicable” Other Relevant Procurement Information. Also Project beyond the threshold of the First Grade Award Authorities will be facilitated by National Procurement Authority( NPA). PROCUREMENT Afghanistan : Cities Investment Program PLAN General Information Country: Afghanistan Bank’s Approval Date of the Original Procurement Plan: 2019-11-04 2020-07-26 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P160619 GPN Date: 2019-07-08 Project Name: Cities Investment Program Loan / Credit No: IDA / D4140 Executing Agency(ies): Independent Directorate of local governance-CIP WORKS Bid Evaluation Activity Reference No. / Procurement Estimated Actual Draft Bidding Loan / Credit Market Procurement Prequalification High SEA/SH Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Contract Description Component Review Type Method Document Amount Amount Document / Signed Contract No. Approach Process (Y/N) Risk Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Completion Type (US$) (US$) Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned AF-IDLG-CIP-139982-CW- RFB / HRT-PP 08- Component 1: Rehabilitate Single Stage - One IDA / D4140 Post Request for Bids Open - National 433,776.00 323,064.82 Signed 2020-04-15 2020-02-23 2020-04-20 2020-06-01 2020-03-23 2020-07-01 2020-06-01 2020-08-05 2020-06-28 2021-07-01 Construction of Salakhi ha Municipal Infrastructure Envelope Asphalt Road in District 3 AF-IDLG-CIP-139983-CW- RFB / (HRT-PP-20) CONSTRUCTION OF SAYED AKHTAR AGHA ROAD PROJECT in Component 1: Rehabilitate Single Stage - One IDA / D4140 Post Request for Bids Open - National 861,602.00 586,905.03 Signed 2020-04-20 2020-02-10 2020-04-25 2020-06-06 2020-02-10 2020-07-06 2020-05-06 2020-08-10 2020-06-01 2021-05-07 District 11 (HRT-PP-02) Municipal Infrastructure Envelope CONSTRUCTION OF ZAINUL ABBEDIN ROAD PROJECT in District 6 ( 2 Lots) AF-IDLG-CIP-139987-CW- RFB / MZR-PP 26- Construction of Kart -e-Sulh 3 Asphalt Road and MZR- Component 1: Rehabilitate Single Stage - One IDA / D4140 Post Request for Bids Open - National 515,674.00 572,955.16 Signed 2020-02-29 2020-02-17 2020-03-05 2020-03-19 2020-04-16 2020-03-17 2020-05-16 2020-06-08 2020-06-20 2020-06-28 2021-02-15 PP 27- Construction of Municipal Infrastructure Envelope North of Amani Project's Asphalt Road in District 7 ( 2 Lots) AF-IDLG-CIP-139989-CW- RFB / KND-PP 19- Construction of Yaklang Road in District 7 and Under Component 1: Rehabilitate Single Stage - One KND-PP 20- Construction of IDA / D4140 Post Request for Bids Open - National 1,353,891.00 1,286,214.24 Implementat 2020-03-15 2020-02-22 2020-03-20 2020-05-01 2020-03-22 2020-05-31 2020-06-16 2020-07-05 2021-01-31 Municipal Infrastructure Envelope Mer Bazaar Road start from ion Mirwais Main Road to Mer Bazaar High School ( 2 Lots) AF-IDLG-CIP-140098-CW- RFB / KST-PP-10- Construction of C-reserve Pending area Asphalt Road in Component 1: Rehabilitate Single Stage - One IDA / D4140 Post Request for Bids Open - National 1,183,254.00 0.00 Implementat 2020-01-25 2020-01-30 2020-03-12 2020-04-11 2020-05-16 2020-12-12 District 4 and KST-PP-09- Municipal Infrastructure Envelope ion Construction of Asphalt Roads in District 2 and 3 (2 Lots) AF-IDLG-CIP-140111-CW- RFB / JBD-PP 14- Construction of Asphalt Pending Component 1: Rehabilitate Single Stage - One Roads in District 2 and JBD- IDA / D4140 Post Request for Bids Open - National 1,033,209.00 0.00 Implementat 2020-03-25 2020-03-30 2020-05-11 2020-06-10 2020-07-15 2021-04-11 Municipal Infrastructure Envelope PP 17- Construction of ion Asphalt Roads in District 4 ( 2 Lots) Page 1 AF-IDLG-CIP-141482-CW- Under RFB / KND-PP 15- Component 1: Rehabilitate Single Stage - One IDA / D4140 Post Request for Bids Open - National 722,951.00 0.00 Implementat 2020-03-10 2020-04-22 2020-03-15 2020-04-26 2020-05-21 2020-05-26 2020-07-21 2020-06-30 2021-01-26 Construction of Bypass road, Municipal Infrastructure Envelope ion side ditches in district 3 AF-IDLG-CIP-143184-CW- RFQ / Rehabilitation /repairing of existing Component 4: Project Request for Single Stage - One facilities ( warehouse , IDA / D4140 Post Limited 30,000.00 0.00 Canceled 2019-12-05 2020-01-30 2020-03-15 Implementation Management Quotations Envelope driver rooms and toilets for guards , Drivers and costumers) AF-IDLG-CIP-162457-CW- RFB / CONSTRUCTION OF Under Component 1: Rehabilitate Single Stage - One 1200 FAMILY PHASE-A IDA / D4140 Post Request for Bids Open - National 396,465.00 0.00 Implementat 2020-04-15 2020-04-03 2020-04-20 2020-06-01 2020-06-02 2020-07-01 2020-08-05 2021-02-01 Municipal Infrastructure Envelope ROADS (KHST-PP-02) in ion Khost Province AF-IDLG-CIP-140096-CW- RFB / KST-PP-08- Component 1: Rehabilitate Single Stage - One IDA / D4140 Post Request for Bids Open - National 845,350.00 734,763.25 Signed 2020-01-15 2020-02-11 2020-01-20 2020-03-02 2020-03-12 2020-04-01 2020-04-06 2020-05-06 2020-06-07 2021-01-31 Construction of Madikhel Municipal Infrastructure Envelope Asphalt Road in District 1 AF-IDLG-CIP-139985-CW- RFB / MZR-PP 23- Construction of Baba Yadgar Tertiary Road in District 4 Component 1: Rehabilitate Single Stage - One and MZR-PP 08- IDA / D4140 Post Request for Bids Open - National 812,746.00 0.00 Canceled 2020-02-25 2019-12-16 2020-03-01 2020-04-12 2020-02-05 2020-05-12 2020-04-14 2020-06-16 2021-03-13 Municipal Infrastructure Envelope Construction of Ota Qul & Ghulam Sakhi Khan Bagh Asphalt Streets in District 3 ( 2 Lots) AF-IDLG-CIP-169362-CW- RFB / MZR-PP 23- Construction of Baba Yadgar Tertiary Road in District 4 Under Component 1: Rehabilitate Single Stage - One and MZR-PP 08- IDA / D4140 Post Request for Bids Open - National 812,746.00 0.00 Implementat 2020-05-23 2020-05-06 2020-05-28 2020-07-09 2020-06-04 2020-08-08 2020-07-18 2020-09-12 2021-03-11 Municipal Infrastructure Envelope Construction of Ota Qul & ion Ghulam Sakhi Khan Bagh Asphalt Streets in District 3 ( 2 Lots) AF-IDLG-CIP-180516-CW- RFB / Rebid of Construction Under of Asphalt Roads in District Component 1: Rehabilitate Single Stage - One IDA / D4140 Post Request for Bids Open - National 1,035,217.43 0.00 Implementat 2020-08-17 2020-07-19 2020-08-22 2020-07-20 2020-10-03 2020-11-02 2020-12-07 2021-06-05 2 JBD-PP 14 and JBD-PP Municipal Infrastructure Envelope ion 17- Construction of Asphalt Roads in District 4 (2 Lots). AF-IDLG-CIP-180530-CW- RFB / Rebid of Construction of Asphalt Roads in District Under 2 KST-PP-09 and Component 1: Rehabilitate Single Stage - One IDA / D4140 Post Request for Bids Open - National 1,183,253.78 0.00 Implementat 2020-08-16 2020-07-22 2020-08-21 2020-07-25 2020-10-02 2020-11-01 2020-12-06 2021-06-04 Construction of C-reserve Municipal Infrastructure Envelope ion area Asphalt Road in District 4 KST-PP-10 in Khost Province. AF-IDLG-CIP-179178-CW- RFQ / Median and sidewalk Pending construction, Ahmadshahi Component 1: Rehabilitate Request for Single Stage - One IDA / D4140 Post Open - National 95,548.00 0.00 Implementat 2020-07-30 2020-09-24 2021-03-23 Jada in district 14 Ahmad Municipal Infrastructure Quotations Envelope ion Shahi Jada- Kandahar Porvince Page 2 AF-EZ-KAR_IDLG-CIP PIU- 147071-CW-RFB-15 / Pending Construction of Haji Aziz Component 1: Rehabilitate IDA / D4140 Post Direct Selection Direct 439,976.60 0.00 Implementat 2020-06-10 2020-06-15 2020-07-20 2021-01-16 Road (KND-PP-21) District-5 Municipal Infrastructure ion Kandahar City, Kandahar Province AF-IDLG-CIP-179193-CW- Pending RFQ / Canal Cleaning Component 1: Rehabilitate Request for Single Stage - One IDA / D4140 Post Open - National 79,200.00 0.00 Implementat 2020-08-01 2020-09-26 2021-03-25 (Pathaw canal) in district 2 Municipal Infrastructure Quotations Envelope ion and 3 -Kandahar Porvince AF-IDLG-CIP-179210-CW- RFQ / Qyamudin road Pending Component 1: Rehabilitate Request for Single Stage - One graveling (6km) in district IDA / D4140 Post Open - National 98,831.00 0.00 Implementat 2020-08-05 2020-09-30 2021-03-29 Municipal Infrastructure Quotations Envelope 8 Bara Baad Jalal Abad ion Province AF-IDLG-CIP-179243-CW- RFQ / Road graveling Pending Component 1: Rehabilitate Request for Single Stage - One Matun Mina (4000m) in IDA / D4140 Post Open - National 67,200.00 0.00 Implementat 2020-08-02 2020-09-27 2021-03-26 Municipal Infrastructure Quotations Envelope Distrct 5 Matun Mina Khost ion Province AF-IDLG-CIP-179258-CW- RFQ / Municipality Main Building Repairing (PVC Pending Component 1: Rehabilitate Request for Single Stage - One doors+ Windows+ painting IDA / D4140 Post Open - National 31,840.00 0.00 Implementat 2020-08-02 2020-09-27 2021-03-26 Municipal Infrastructure Quotations Envelope etc) in Distrct 2 ion Municipality Main Building Khost Province AF-IDLG-CIP-179265-CW- Pending RFQ / Road graveling, Component 1: Rehabilitate Request for Single Stage - One IDA / D4140 Post Open - National 12,452.00 0.00 Implementat 2020-08-05 2020-09-30 2021-03-29 Manni Kalai (1742m) in Municipal Infrastructure Quotations Envelope ion Distrct 9 Khost Province AF-IDLG-CIP-179269-CW- Pending RFQ / Canal Cleaning of Component 1: Rehabilitate Request for Single Stage - One IDA / D4140 Post Open - National 48,000.00 0.00 Implementat 2020-07-26 2020-09-20 2021-03-19 Matun Tapa in District 4 Municipal Infrastructure Quotations Envelope ion Khost Province AF-IDLG-CIP-179278-CW- Pending RFQ / Road graveling Component 1: Rehabilitate Request for Single Stage - One IDA / D4140 Post Open - National 51,780.00 0.00 Implementat 2020-08-24 2020-10-19 2021-04-17 (3000m) Sarankot city in Municipal Infrastructure Quotations Envelope ion District 5 Khost Province AF-IDLG-CIP-179280-CW- RFQ / Stone Masonry wall Pending Component 1: Rehabilitate Request for Single Stage - One repair and grill installation IDA / D4140 Post Open - National 8,250.00 0.00 Implementat 2020-08-22 2020-10-17 2021-04-15 Municipal Infrastructure Quotations Envelope for recreation park (2750) ion in District 4 Khost Province AF-IDLG-CIP-179284-CW- RFQ / Boundary wall Pending Component 1: Rehabilitate Request for Single Stage - One construction of Park-1 in C IDA / D4140 Post Open - National 25,580.00 0.00 Implementat 2020-08-21 2020-10-16 2021-04-14 Municipal Infrastructure Quotations Envelope Families (136m) in District ion 4 Khost Province AF-IDLG-CIP-179286-CW- RFQ / Boundary wall Pending Component 1: Rehabilitate Request for Single Stage - One construction of Park-3 in C IDA / D4140 Post Open - National 32,128.00 0.00 Implementat 2020-08-15 2020-10-10 2021-04-08 Municipal Infrastructure Quotations Envelope Families (126m) in District ion 4 Khost Province Page 3 AF-IDLG-CIP-179238-CW- RFQ / Construction of Parks ( Gul Hussain and Pending Component 1: Rehabilitate Request for Single Stage - One Mohammad Saeed) in IDA / D4140 Post Open - National 38,555.00 0.00 Implementat 2020-08-03 2020-09-28 2021-03-27 Municipal Infrastructure Quotations Envelope district 1 Gul Hussain and ion Mohammad Saeed Jalal Abad Province AF-IDLG-CIP-179251-CW- RFQ / District 1 Pending Component 1: Rehabilitate Request for Single Stage - One Municipality building IDA / D4140 Post Open - National 23,940.00 0.00 Implementat 2020-08-03 2020-09-28 2021-03-27 Municipal Infrastructure Quotations Envelope Rehabilitation District 1, ion Municipality Khost Province AF-IDLG-CIP-179165-CW- RFQ / Median Construction Pending of Kandahar and Herat Component 1: Rehabilitate Request for Single Stage - One IDA / D4140 Post Open - National 92,337.00 0.00 Implementat 2020-07-30 2020-09-24 2021-03-23 main road in district 8 Municipal Infrastructure Quotations Envelope ion Kandahar Herat main road Kandahar Porvince AF-IDLG-CIP-179227-CW- RFQ / Road graveling, Pending Component 1: Rehabilitate Request for Single Stage - One Najmul Jihad Town (6Km) IDA / D4140 Post Open - National 98,831.00 0.00 Implementat 2020-08-03 2020-09-28 2021-03-27 Municipal Infrastructure Quotations Envelope in district 6 Najmul Jihad ion Town Jalal Abad Province AF-IDLG-CIP-179229-CW- RFQ / Side walk Pending Component 1: Rehabilitate Request for Single Stage - One construction (Mosaic), Serajul IDA / D4140 Post Open - National 90,428.00 0.00 Implementat 2020-07-25 2020-09-19 2021-03-18 Municipal Infrastructure Quotations Envelope Emara in district 1 Serajul ion Emara Jalal Abad Province AF-IDLG-CIP-179231-CW- RFQ / Canal Cleaning Angor Pending Component 1: Rehabilitate Request for Single Stage - One Bagh to Airport in district IDA / D4140 Post Open - National 44,545.00 0.00 Implementat 2020-07-27 2020-09-21 2021-03-20 Municipal Infrastructure Quotations Envelope 4 Angor Bagh to airport ion Jalal Abad Province AF-IDLG-CIP-179236-CW- RFQ / Construction of Parks Pending Component 1: Rehabilitate Request for Single Stage - One (Dawlat Sha and Kochai) in IDA / D4140 Post Open - National 38,555.00 0.00 Implementat 2020-08-05 2020-09-30 2021-03-29 Municipal Infrastructure Quotations Envelope district 2 Dawlat Sha and ion Kochai Jalal Abad Province AF-IDLG-CIP-179306-CW- Pending RFQ / Drainage Cleaning Component 1: Rehabilitate Request for Single Stage - One IDA / D4140 Post Open - National 12,250.00 0.00 Implementat 2020-08-28 2020-10-23 2021-04-21 (7000m) in district 4 Mazar Municipal Infrastructure Quotations Envelope ion Province AF-IDLG-CIP-179234-CW- RFQ / Trash Bins Pending Component 1: Rehabilitate Request for Single Stage - One installation in District- IDA / D4140 Post Open - National 60,389.00 0.00 Implementat 2020-08-04 2020-09-29 2021-03-28 Municipal Infrastructure Quotations Envelope 1,2,3,4,5 & 7 Jalal Abad ion Province AF-EZ-KAR_IDLG-CIP PIU- 147077-CW-RFB-13 / Pending CONSTRUCTION OF Component 1: Rehabilitate IDA / D4140 Post Direct Selection Direct 363,679.00 0.00 Implementat 2020-06-10 2020-06-15 2020-07-20 2021-01-16 CONCRETE STREETS AT Municipal Infrastructure ion JALALABAD PROVINCE IN SINGLE LOT AF-IDLG-CIP-179254-CW- RFQ / Sidewalk construction Pending Component 1: Rehabilitate Request for Single Stage - One (Mosaic) (2230m) in Distrct IDA / D4140 Post Open - National 98,343.00 0.00 Implementat 2020-08-02 2020-09-27 2021-03-26 Municipal Infrastructure Quotations Envelope 4 in 1200 Families, Phase A ion Khost Province Page 4 AF-IDLG-CIP-179266-CW- RFQ / City drain cleaning Pending Component 1: Rehabilitate Request for Single Stage - One and Repairing of damaged IDA / D4140 Post Open - National 25,300.00 0.00 Implementat 2020-07-31 2020-09-25 2021-03-24 Municipal Infrastructure Quotations Envelope concrete (1400m) in District ion 1 and 2 and 3 Khost city AF-IDLG-CIP-179293-CW- RFQ / Boundary wall Pending Component 1: Rehabilitate Request for Single Stage - One construction of Matun Mina IDA / D4140 Post Open - National 25,041.00 0.00 Implementat 2020-08-20 2020-10-15 2021-04-13 Municipal Infrastructure Quotations Envelope Park(86m) in District 5 ion Khost Province AF-IDLG-CIP-179301-CW- Pending RFQ / Canal Cleaning Component 1: Rehabilitate Request for Single Stage - One IDA / D4140 Post Open - National 25,300.00 0.00 Implementat 2020-09-02 2020-10-28 2021-04-26 (600mx20mx1m) in District 2 Municipal Infrastructure Quotations Envelope ion and 10 Herat City AF-IDLG-CIP-179310-CW- RFQ / Canal Cleaning from Angor Bagh to Chaparhar Pending Component 1: Rehabilitate Request for Single Stage - One old Hada in district 4 IDA / D4140 Post Open - National 4,493.00 0.00 Implementat 2020-08-29 2020-10-24 2021-04-22 Municipal Infrastructure Quotations Envelope Angor Bagh to Chaparhar ion old Hada Jalal Abad Province AF-IDLG-CIP-179221-CW- RFQ / Road graveling, Pending Component 1: Rehabilitate Request for Single Stage - One Samarkhil Graveyard in IDA / D4140 Post Open - National 98,831.00 0.00 Implementat 2020-07-31 2020-09-25 2021-03-24 Municipal Infrastructure Quotations Envelope district 9 Samarkhil Jalal ion Abad Province AF-IDLG-CIP-179296-CW- RFQ / Side walk Pending Component 1: Rehabilitate Request for Single Stage - One construction in District 1, IDA / D4140 Post Open - National 96,750.00 0.00 Implementat 2020-08-28 2020-10-23 2021-04-21 Municipal Infrastructure Quotations Envelope 2,3, 4,5,6,7, 8, 9, 11& 15 ion Herat City AF-IDLG-CIP-179304-CW- Pending RFQ / Drainage Cleaning Component 1: Rehabilitate Request for Single Stage - One IDA / D4140 Post Open - National 6,650.00 0.00 Implementat 2020-09-02 2020-10-28 2021-04-26 (3800m) in district 1 Mazar Municipal Infrastructure Quotations Envelope ion Province AF-IDLG-CIP-179205-CW- RFQ / Construction of Pending boundary wall for new Component 1: Rehabilitate Request for Single Stage - One IDA / D4140 Post Open - National 97,709.00 0.00 Implementat 2020-07-31 2020-09-25 2021-03-24 Municipality building in Municipal Infrastructure Quotations Envelope ion district 11 Aino Mina - Kandahar Province AF-IDLG-CIP-179237-CW- RFQ / Construction of Parks Pending (Sabawon and Haji Zahir) in Component 1: Rehabilitate Request for Single Stage - One IDA / D4140 Post Open - National 38,555.00 0.00 Implementat 2020-08-04 2020-09-29 2021-03-28 district 2 Sabawon and Municipal Infrastructure Quotations Envelope ion Haji Zahir Jalal Abad Province AF-IDLG-CIP-179257-CW- Pending RFQ / Road graveling (1250) Component 1: Rehabilitate Request for Single Stage - One IDA / D4140 Post Open - National 12,945.00 0.00 Implementat 2020-08-04 2020-09-29 2021-03-28 Matun in Distrct 3 Matun Municipal Infrastructure Quotations Envelope ion Khost Province AF-IDLG-CIP-179261-CW- Pending RFQ / Road graveling Component 1: Rehabilitate Request for Single Stage - One IDA / D4140 Post Open - National 11,317.00 0.00 Implementat 2020-07-27 2020-09-21 2021-03-20 Khalise Kalai (1451m) in Municipal Infrastructure Quotations Envelope ion District 2 Khost Province AF-IDLG-CIP-179270-CW- Pending RFQ / Canal Cleaning of Component 1: Rehabilitate Request for Single Stage - One IDA / D4140 Post Open - National 1,750.00 0.00 Implementat 2020-07-26 2020-09-20 2021-03-19 Rogha Kalai (700) in Municipal Infrastructure Quotations Envelope ion Distrct 4 Khost Province Page 5 AF-IDLG-CIP-179272-CW- RFQ / Construction of RCC Pending Component 1: Rehabilitate Request for Single Stage - One Trash or Garbage Bins in IDA / D4140 Post Open - National 43,842.00 0.00 Implementat 2020-07-26 2020-09-20 2021-03-19 Municipal Infrastructure Quotations Envelope District 1,2,3,4,5,6, &7 Khost ion Province AF-IDLG-CIP-179276-CW- RFQ / Sidewalk construction Pending Component 1: Rehabilitate Request for Single Stage - One (Mosaic) (1600m) in District IDA / D4140 Post Open - National 35,280.00 0.00 Implementat 2020-08-01 2020-09-26 2021-03-25 Municipal Infrastructure Quotations Envelope Four 1200 Families, Phase ion A Khost Province AF-IDLG-CIP-179290-CW- RFQ / Boundary wall Pending Component 1: Rehabilitate Request for Single Stage - One construction of Park-2 in C IDA / D4140 Post Open - National 36,360.00 0.00 Implementat 2020-08-16 2020-10-11 2021-04-09 Municipal Infrastructure Quotations Envelope Families (196m) in ion District 4 Khost Province AF-IDLG-CIP-179312-CW- RFQ / Construction of Parks Pending Component 1: Rehabilitate Request for Single Stage - One (2) Near Momand Hospital IDA / D4140 Post Open - National 3,855.00 0.00 Implementat 2020-08-27 2020-10-22 2021-04-20 Municipal Infrastructure Quotations Envelope in district 2 Near Momand ion Hospital Jalal Abad Province AF-IDLG-CIP-179174-CW- RFQ / Median Construction Pending on Kandahar and Herat Component 1: Rehabilitate Request for Single Stage - One IDA / D4140 Post Open - National 93,270.00 0.00 Implementat 2020-07-27 2020-09-21 2021-03-20 main road in district 8 Municipal Infrastructure Quotations Envelope ion Kandahar Herat main road- Kandahar Porvince AF-IDLG-CIP-179190-CW- Pending RFQ / Canal Cleaning Component 1: Rehabilitate Request for Single Stage - One IDA / D4140 Post Open - National 87,120.00 0.00 Implementat 2020-07-30 2020-09-24 2021-03-23 (Pathaw canal) in District 1- Municipal Infrastructure Quotations Envelope ion Kandahar Porvince AF-IDLG-CIP-180116-CW- Pending RFQ / Canal Cleaning Component 1: Rehabilitate Request for Single Stage - One IDA / D4140 Post Open - National 96,750.00 0.00 Implementat 2020-07-27 2020-09-21 2021-03-20 (600mx20mx1m) in District 8 Municipal Infrastructure Quotations Envelope ion & 15 Herat City GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AF-IDLG-CIP-139959-GO- RFQ / Office Furniture and Component 4: Project Request for Single Stage - One fixture for City Investment IDA / D4140 Post Open - National 16,633.00 8,126.72 Signed 2019-12-26 2020-02-20 2019-12-07 2020-04-05 Implementation Management Quotations Envelope Program (CIP) main office setup AF-IDLG-CIP-142171-GO- Component 4: Project Request for Single Stage - One RFQ / Safety Equipment for IDA / D4140 Post Limited 25,000.00 14,217.63 Signed 2020-03-26 2020-03-25 2020-05-21 2020-03-28 2020-06-20 Implementation Management Quotations Envelope CIP security enhancement AF-IDLG-CIP-139954-GO- Pending Component 4: Project Request for Single Stage - One RFQ / ICT Equipment for IDA / D4140 Post Open - National 48,539.00 0.00 Implementati 2019-12-20 2020-02-14 2020-04-14 Implementation Management Quotations Envelope CIP main office setup on AF-IDLG-CIP-139965-GO- Component 4: Project Request for Single Stage - One RFQ / Office Equipment for IDA / D4140 Post Open - National 11,626.00 2,583.94 Signed 2020-01-04 2020-02-29 2020-03-21 2020-03-30 Implementation Management Quotations Envelope CIP main office setup Page 6 AF-IDLG-CIP-181592-GO- Pending RFQ / ICT Equipment for Component 4: Project Request for Single Stage - One IDA / D4140 Post Open - National 47,968.00 0.00 Implementati 2020-09-27 2020-11-22 2021-05-21 CIP main office and 5 Implementation Management Quotations Envelope on Provincial offices AF-IDLG-CIP-181593-GO- RFQ / Furniture for CIP Pending Component 4: Project Request for Single Stage - One Main Office Meeting Room IDA / D4140 Post Open - National 18,838.00 0.00 Implementati 2020-09-18 2020-11-13 2021-05-12 Implementation Management Quotations Envelope and Furniture for 5 on Provincial Offices NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AF-IDLG-CIP-150668-NC- Component 3: Improve the Pending RFB / Design and Single Stage - One IDA / D4140 Municipal Management Post Request for Bids Open - National 4,500.00 0.00 Implementati 2020-02-08 2020-02-13 2020-03-26 2020-04-25 2020-05-30 2020-09-27 Establishment Online Envelope Framework on Dynamic Web Application CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AF-IDLG-CIP-162471-CS- INDV / "Preparing Own Component 2: Strengthen Quality And Cost- Open - Source Revenue IDA / D4140 the Municipal Finance Prior 329,259.00 0.00 Canceled 2020-05-24 2020-04-13 2020-06-14 2020-07-28 2020-08-25 2020-09-24 2020-10-29 2020-12-03 2021-12-03 Based Selection International Enhancement Strategies Framework (OSR) AF-IDLG-CIP-170106-CS- QCBS / Preparing Own Component 2: Strengthen Quality And Cost- Under Source Revenue IDA / D4140 the Municipal Finance Post Open 329,259.00 0.00 2020-05-27 2020-05-07 2020-06-17 2020-05-09 2020-07-31 2020-08-28 2020-09-27 2020-11-01 2020-12-06 2021-12-06 Based Selection Implementation Enhancement Strategies Framework (OSR) AF-IDLG-CIP-178824-CS- CQS / Baseline Assessment Component 2: Strengthen Consultant for Implementation of Under IDA / D4140 the Municipal Finance Post Qualification Limited 37,245.00 0.00 2020-08-30 2020-07-08 2020-09-13 2020-10-13 2020-11-17 2021-05-16 Municipal Finance Implementation Framework Selection Management Information System in Five Provincial Capital Cities. Component 3: Improve the Consultant AF-IDLG-CIP-183942-CS- Open - Pending IDA / D4140 Municipal Management Post Qualification 126,000.00 0.00 2020-09-14 2020-10-05 2020-11-18 2020-12-18 2021-01-22 2021-07-21 CQS / Verification Agent International Implementation Framework Selection INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 7