Sample Procurement Plan I. General 2. Bank’s approval Date of the procurement Plan Original: March, 2014 : Revision: March, 2017 3. Date of General Procurement Notice: April, 2014 4. Period covered by this procurement plan: The procurement period of project covered from year May 1, 2015 to July 31, 2019 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Comments Threshold US$ 1 NCB (Goods) ; IT and Non- Equivalent and Below Above USD 2 mil. consulting services US$ 1,000,000 2 NCB (Works) Equivalent and Below Above USD 10 mil. US$ 10 million 3 Shopping (Goods) Equivalent and Below None US$ 100,000 4 Shopping (Works) Equivalent and Below None US$ 200,000 2. Prequalification. Bidders for Not applicable 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Not Applicable 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project P133828 is developed by MoA (for Parts A and C1) and the Guidelines for implementation of activities under parts B and C2 are developed by NAPR 5. Any Other Special Procurement Arrangements: None 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness 1 2 3 4 5 6 7 Ref. Description Packa Dome Revie Comments No. ges stic w Esti Prefer by mate ence Bank d (yes/n (Prior Cost o) / US$ Post) milli on Summary of the ICB 22.4 2 No Prior The first one has been already (Works) signed Summary of the NCB 1.15 1 No Post (Works) Summary of the NCB 0.75 3 No Post (Goods) Summary of the ICB (Non- 0.8 2 No Post Consultant Services) Summary of the Shopping 0.4 13 No Post (Goods) Summary of the Shopping 0.074 1 No Post (Non-Consultant Services) Summary of the Direct 0.2 2 Contracting III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comment Threshold 1. Competitive Methods Above US$ (Firms) 1,000,000 2. CQS Applicable for assignments with estimation below USD 300K 3. Individual Above US$ 300,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: None 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimate Packa Review Comments of d ges by Bank Assignment Cost (Prior / US$ Post) million Summary of number of 3.5 3 Prior contracts that will be let under QCBS Summary of number of 0.51 7 Post LCS, FB, CQS contracts that will be let under other methods Summary of number of 1.01 35 Prior/Post 4 signed contracts were contracts that will be let subject to the Prior under IC reviewer Summary of number of 0.33 11 Prior/Post 9 signed contracts were contracts that will be let subject to the Prior under SSS reviewer PROCUREMENT Georgia : Irrigation and Land Market Development Project PLAN General Information Country: Georgia Bank’s Approval Date of the Original Procurement Plan: 2016-09-15 2020-11-27 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P133828 GPN Date: Project Name: Irrigation and Land Market Development Project Loan / Credit No: IDA / 54560, IBRD / 90430 Ministry of Agriculture of Georgia Executing Agency(ies): WORKS Procureme Activity Reference No. / Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH nt Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) Justification for Award Type Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IDIC/CW/ICB/01 / Rehabilitation of Irrigation Scheme Main Canals and Component 1 Irrigation and Single Stage - One 14,623,975. 2018- IDA / 54560 Prior Request for Bids Open - International Signed 2016-02-23 2016-03-17 Electrical and Mechanical Drainage Improvement Envelope 02 08-10 parts of main canal and headwork IDIC/CW/NCB/01 / Sioni and Component 1 Irrigation and Single Stage - One 2018-09- IDA / 54560 Post Request for Bids Open - National 0.00 Canceled 2017-12-01 2017-12-15 2018-01-14 2018-02-13 2018-03-13 Algeti Dams Safety Works Drainage Improvement Envelope 09 IDIC/CW/ICB/02 / Rehabilitation of secondary Component 1 Irrigation and Single Stage - One 2019-07- networks for Zeda Ru, Tbisi- IDA / 54560 Prior Request for Bids Open - International 0.00 Canceled 2018-11-05 2018-11-19 2018-12-31 2019-01-30 2019-02-27 Drainage Improvement Envelope 27 Kumisi and Zemo Samgori Irrigation Schemes IDIC/CW/NCB/02 / Kvemo Component 1 Irrigation and Single Stage - One 2021-05- Samgori On-Farm Network IDA / 54560 Post Request for Bids Open - National 0.00 Canceled 2020-02-14 2020-02-19 2020-04-01 2020-05-01 2020-06-05 Drainage Improvement Envelope 16 Rehabilitation, Section G33 IDIC/CW/ICB/03 / Kvemo Samgori On-Farm Network Component 1 Irrigation and Single Stage - One 8,699,977.7 2021-10- IDA / 54560 Post Request for Bids Open - International Signed 2020-01-31 2020-02-06 2020-02-05 2020-02-06 2020-03-18 2020-05-01 2020-04-17 2020-06-04 2020-05-22 2020-06-04 Rehabilitation, section G1- Drainage Improvement Envelope 2 01 G32 IDIC/CW/NCB/01-1 / Sioni Component 1 Irrigation and Single Stage - One 2020-11- IDA / 54560 Post Request for Bids Open - National 0.00 Canceled 2020-03-27 2020-03-31 2020-04-03 2020-05-03 2020-04-30 2020-05-18 2020-05-21 2020-06-02 and Algeti Dams Safety Works Drainage Improvement Envelope 29 IDIC/CW/ICB/04 / Zeda Ru Component 1 Irrigation and Single Stage - One 6,930,148.5 2021-12- On-Farm Network IDA / 54560 Post Request for Bids Open - International Signed 2020-03-30 2020-04-03 2020-04-04 2020-04-03 2020-05-16 2020-07-10 2020-06-05 2020-09-03 2020-06-22 2020-09-30 Drainage Improvement Envelope 7 22 Rehabilitation IDIC/AF/W/RFB/01 / Pending Component 1 Irrigation and Single Stage - One 2022-08- Rehabilitation works on Tbisi- IBRD / 90430 Post Request for Bids Open - International 0.00 Implementat 2020-05-04 2020-05-09 2020-06-20 2020-07-10 2020-07-27 Drainage Improvement Envelope 26 Kumisi Secondary Network ion IDIC/CW/NCB/01-2 / Sioni Component 1 Irrigation and Single Stage - One 1,521,764.1 2021-07- IDA / 54560 Post Request for Bids Open - National Signed 2020-05-25 2020-05-25 2020-05-26 2020-06-25 2020-06-25 2020-07-10 2020-07-10 2020-07-31 2020-08-06 and Algeti Dams Safety Works Drainage Improvement Envelope 2 31 IDIC/CW/ICB/05 / Kvemo Under Samgori On-Farm Network Component 1 Irrigation and Single Stage - One 2022-03- IDA / 54560 Prior Request for Bids Open - International 0.00 Implementat 2020-06-15 2020-08-05 2020-06-17 2020-08-19 2020-08-05 2020-10-26 2020-09-04 2020-10-04 Rehabilitation, section G33. Drainage Improvement Envelope 28 ion G33-1 GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IDIC/G/SH/07 / PPMD office Component 3 Project Request for Single Stage - One IDA / 54560 Post Open - National 0.00 Canceled 2018-01-17 2018-02-14 2018-04-15 Furniture Management Quotations Envelope IDIC/G/SH/08 / Component 3 Project Request for Single Stage - One Environmental Monitoring IDA / 54560 Post Open - National 0.00 Canceled 2018-01-17 2018-02-14 2018-04-15 Management Quotations Envelope Field Equipment IDIC/G/SH/09 / Component 3 Project Request for Single Stage - One Environmental Monitoring IDA / 54560 Post Open - National 0.00 Canceled 2018-01-17 2018-02-14 2018-04-15 Management Quotations Envelope Program IDIC/G/DC/01 / Procurement Component 1 Irrigation and of Agricultural software - IDA / 54560 Post Direct Selection Direct 0.00 Canceled 2017-02-17 2017-02-27 2017-03-11 2017-05-10 Drainage Improvement Sic^2 IDIC/G/SH/10 / Supply of Component 1 Irrigation and Request for Single Stage - One Tachometer for Georgian IDA / 54560 Post Open - National 0.00 Canceled 2017-07-06 2017-08-08 2017-10-07 Drainage Improvement Quotations Envelope Amelioration IDIC/G/SH/13 / Supply of 5 units of off-road small size Component 1 Irrigation and Request for Single Stage - One IDA / 54560 Post Open - National 0.00 Canceled 2017-10-05 2017-10-28 2017-12-27 trucks to the Georgian Drainage Improvement Quotations Envelope Amelioration (GA) IDIC/G/NCB/02 / Supply of Component 1 Irrigation and Single Stage - One Machinery and Equipment to IDA / 54560 Post Request for Bids Open - National 80,241.94 Signed 2017-12-04 2017-11-13 2017-12-18 2018-01-17 2017-12-15 2018-02-16 2018-01-30 2018-03-09 2018-02-12 2018-06-07 Drainage Improvement Envelope Georgian Amelioration IDIC/G/NCB/03 / PPMD Component 3 Project Single Stage - One IDA / 54560 Post Request for Bids Open - National 0.00 Canceled 2018-01-10 2018-01-24 2018-02-23 2018-03-25 2018-04-22 2018-06-21 Equipment - Vehicles Management Envelope IDIC/G/NCB/01 / Supply of IT Component 1 Irrigation and Single Stage - One equipment to Georgian IDA / 54560 Post Request for Bids Open - National 0.00 Canceled 2017-04-25 2017-10-23 2017-05-09 2017-06-08 2017-12-05 2017-07-08 2017-12-15 2017-07-29 2017-09-27 Drainage Improvement Envelope Amelioration Page 1 IDIC/G/SH/06 / Supply of IT Office Equipment for DPMMU Component 3 Project Request for Single Stage - One and Amelioration and Land IDA / 54560 Post Open - National 0.00 Canceled 2018-01-17 2018-02-14 2018-04-15 Management Quotations Envelope Management Department of MoA IDIC/G/SH/11 / Supply Echo- sounder and 10 units of Component 1 Irrigation and Request for Single Stage - One IDA / 54560 Post Open - National 0.00 Canceled 2017-03-02 2017-01-26 2017-04-02 2017-06-01 Leveling Instrument to Drainage Improvement Quotations Envelope Georgian Amelioration IDIC/G/NCB/02-1 / Supply of Component 1 Irrigation and Single Stage - One Machinery and Equipment to IDA / 54560 Post Request for Bids Open - National 0.00 Canceled 2018-02-27 2018-02-27 2018-03-29 2018-04-28 2018-06-12 2018-05-19 2018-07-18 Drainage Improvement Envelope Georgian Amelioration IDIC/G/SH/14 / Supply of 2 units of Off-Road 4X4 Component 1 Irrigation and Request for Single Stage - One IDA / 54560 Post Open - National 44,019.87 Signed 2018-03-28 2018-04-30 2018-05-25 2018-07-02 vehicles for Georgian Drainage Improvement Quotations Envelope Amelioration IDIC/G/SH/06-1 / Re- announcement of Supply of IT Office Equipment for DPMMU Component 3 Project Request for Single Stage - One IDA / 54560 Post Open - National 0.00 Canceled 2018-04-27 2018-05-18 2018-06-17 and Amelioration and Land Management Quotations Envelope Management Department of MEPA IDIC/G/SH/15 / Supply of Component 1 Irrigation and Request for Single Stage - One IDA / 54560 Post Open - National 17,920.02 Completed 2018-11-07 2018-12-28 2020-01-06 2019-06-26 2020-07-22 GPS Navigators for GA Drainage Improvement Quotations Envelope IDIC/G/SH/16 / Supply of Component 1 Irrigation and Request for Single Stage - One Printing and Scanning IDA / 54560 Post Open - National 1,705.17 Signed 2018-11-05 2018-12-28 2019-05-13 2019-06-26 Drainage Improvement Quotations Envelope Instruments for GA IDIC/G/SH/17 / Supply of Component 1 Irrigation and Request for Single Stage - One IDA / 54560 Post Open - National 2,367.80 Signed 2018-11-05 2018-12-28 2018-12-28 2019-06-26 Network Equipment fro GA Drainage Improvement Quotations Envelope IDIC/G/SH/18 / Supply of Component 1 Irrigation and Request for Single Stage - One IDA / 54560 Post Open - National 6,087.28 Signed 2018-11-07 2018-12-28 2019-05-15 2019-06-26 Photography Tools for GA Drainage Improvement Quotations Envelope IDIC/G/SH/19 / Supply of Component 1 Irrigation and Request for Single Stage - One IDA / 54560 Post Open - National 12,834.62 Signed 2018-11-07 2018-12-28 2019-01-21 2019-06-26 Automotive Equipment for GA Drainage Improvement Quotations Envelope IDIC/G/ICB/01 / Supply of IT Component 1 Irrigation and Single Stage - One equipment for Georgian IDA / 54560 Post Request for Bids Open - International 56,110.00 Completed 2018-11-02 2018-12-14 2018-11-07 2019-02-15 2018-12-19 2019-02-25 2019-01-18 2019-05-06 2019-02-16 2019-05-07 2019-08-15 2019-07-05 Drainage Improvement Envelope Amelioration IDIC/G/NCB/04 / Supply of Component 1 Irrigation and Single Stage - One SUV vehicles for Georgian IDA / 54560 Post Request for Bids Open - National 359,300.60 Signed 2018-11-20 2019-01-25 2018-11-20 2018-12-20 2019-02-25 2019-01-10 2019-03-18 2019-02-01 2019-03-21 2019-04-02 Drainage Improvement Envelope Amelioration IDIC/G/SH/21 / Unionalls Component 1 Irrigation and Request for Single Stage - One IDA / 54560 Post Open - National 14,668.13 Signed 2019-02-13 2019-03-27 2019-04-18 2019-07-25 (Uniforms) for GA Drainage Improvement Quotations Envelope IDIC/G/SH/22 / Supply of Component 1 Irrigation and Request for Single Stage - One Printing Equipment to the IDA / 54560 Post Open - National 10,927.76 Signed 2019-03-27 2019-05-07 2019-05-15 2019-08-05 Drainage Improvement Quotations Envelope Georgian Amelioration IDIC/G/NCB/01-1 / Supply of Component 1 Irrigation and Single Stage - One IT equipment to Georgian IDA / 54560 Post Request for Bids Open - National 0.00 Canceled 2018-01-29 2018-02-03 2018-03-05 2018-04-04 2018-04-25 2018-07-24 Drainage Improvement Envelope Amelioration IDIC/G/SH/22-1 / Supply of Under Component 1 Irrigation and Request for Single Stage - One Printing Equipment for IDA / 54560 Post Open - National 0.00 Implementati 2019-06-25 2019-08-05 2019-10-04 Drainage Improvement Quotations Envelope Georgian Amelioration on IDIC/G/SH/12 / Supply of 3 units of Automatic Flow Measuring Devices and 15 Component 1 Irrigation and Request for Single Stage - One IDA / 54560 Post Open - National 0.00 Canceled 2018-02-08 2018-03-11 2018-05-10 units of water flow velocity Drainage Improvement Quotations Envelope measurement equipment for Georgian Amelioration (GA) IDIC/G/NCB/05 / Computer Component 1 Irrigation and Single Stage - One hardware for Georgian IDA / 54560 Post Request for Bids Open - National 96,969.16 Completed 2019-07-09 2019-07-10 2019-07-12 2019-08-11 2019-08-09 2019-08-26 2019-09-25 2019-09-17 2019-10-04 2019-12-16 2019-12-23 Drainage Improvement Envelope Amelioration IDIC/G/SH/20 / Automotive Component 1 Irrigation and Request for Single Stage - One and Network Equipment for IDA / 54560 Post Open - National 29,498.04 Completed 2019-11-04 2019-12-12 2020-01-06 2020-03-11 2020-07-22 Drainage Improvement Quotations Envelope GA IDIC/AF/G/RFB/01 / Supply Pending Component 1 Irrigation and Single Stage - One of Computer hardware for IBRD / 90430 Post Request for Bids Open - International 0.00 Implementati 2020-05-29 2020-06-03 2020-07-15 2020-08-14 2020-09-12 2020-12-22 Drainage Improvement Envelope NSLMLUMA on IDIC/AF/G/RFQ/01 / Supply Pending of Drones for remote Component 1 Irrigation and Request for Single Stage - One IBRD / 90430 Post Open - National 0.00 Implementati 2020-06-06 2020-07-17 2020-09-15 monitoring and inventory for Drainage Improvement Quotations Envelope on NSLMLUMA IDIC/AF/G/RFB/02 / Supply Pending Component 1 Irrigation and Single Stage - One of SUV Vehicles for IBRD / 90430 Post Request for Bids Open - National 0.00 Implementati 2020-05-25 2020-05-25 2020-06-24 2020-07-15 2020-08-06 2020-11-04 Drainage Improvement Envelope NSLMLUMA on NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IDIC/NCS/NCB/02 / Component 1 Irrigation and Single Stage - One Bathymetric survey for Algeti, IDA / 54560 Post Request for Bids Open - National 0.00 Canceled 2018-02-12 2018-02-17 2018-03-19 2018-04-18 2018-05-09 2018-11-05 Drainage Improvement Envelope Sioni and Tbilisi Reservoirs Page 2 IDIC/NCS/NCB/01 / Topographic Survey for Tbisi Component 1 Irrigation and Single Stage - One IDA / 54560 Post Request for Bids Open - National 0.00 Canceled 2017-02-27 2017-03-10 2017-03-06 2017-03-10 2017-03-27 2017-04-18 2017-04-10 2017-04-17 2017-08-15 Kumisi, Kvemo Samgori and Drainage Improvement Envelope Zeda Ru Irrigation Schemes IDIC/G/SH/23 / Bathymetric Pending Component 1 Irrigation and Request for Single Stage - One Survey for Algeti and Tbilisi IDA / 54560 Post Open - National 0.00 Implementati 2019-04-22 2019-06-17 2019-12-14 Drainage Improvement Quotations Envelope Reservoirs on CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ILMDP/C/QCBS/01-2015 / Consulting Services for Supervision of Civil Works to be implemented under Component 1 Irrigation and Quality And Cost- Irrigation and Land Market IDA / 54560 Prior Open - International 2,506,926.80 Signed 2016-02-03 2016-02-29 Drainage Improvement Based Selection Development Project - Irrigation And Drainage Improvement Component (ILMDP) IDIC/CS/LCS/02 / GILMDP Component 1 Irrigation and Least Cost Project Financial Audit for IDA / 54560 Post Open - International 36,167.00 Signed 2016-11-07 2016-11-10 2016-11-17 2016-11-10 2016-12-22 2017-01-11 2017-01-12 2017-02-01 2017-02-11 2017-02-27 2017-03-11 2017-03-13 2017-03-18 2017-03-15 2019-07-31 Drainage Improvement Selection 2015-2019 fiscal years IDIC/CS/CQS/01 / Strengthening of Designing Consultant Component 1 Irrigation and Capacity and Technical IDA / 54560 Post Qualification Open - National 0.00 Canceled 2017-12-11 2017-12-25 2018-01-15 2018-02-05 2018-02-12 2019-02-12 Drainage Improvement maintenance of Georgian Selection Amelioration IDIC/CS/QCBS/03 / Component 1 Irrigation and Quality And Cost- Institutional Strengthening of IDA / 54560 Prior Open - International 0.00 Canceled 2017-11-01 2017-11-15 2017-12-13 2018-01-10 2018-02-09 2018-03-02 2018-03-16 2019-09-07 Drainage Improvement Based Selection Georgian Amelioration Consultant IDIC/CS/CQS/05 / National Component 3 Project IDA / 54560 Post Qualification Open - National 0.00 Canceled 2018-03-01 2018-03-15 2018-04-19 2018-05-03 2018-05-10 2018-11-06 Technical Assistance Management Selection IDIC/CS/CQS/03 / Independent Dam Safety Consultant Assessment and Design and Component 1 Irrigation and IDA / 54560 Post Qualification Open - International 257,415.49 Signed 2017-07-31 2017-10-11 2017-08-14 2017-10-12 2017-09-18 2018-06-19 2017-10-09 2018-10-17 2017-10-23 2018-10-18 2019-02-15 Supervision of Dam Safety Drainage Improvement Selection Activities for Algeti and Sioni Dams IDIC/CS/CQS/07 / Design Consultant Component 1 Irrigation and Engineering Consultancy IDA / 54560 Post Qualification Open - National 0.00 Canceled 2017-02-27 2017-01-25 2017-03-13 2017-01-25 2017-04-24 2017-03-16 2017-05-08 2017-05-15 2018-02-09 Drainage Improvement Services Selection IDIC/CS/QCBS/02 / Preparation of Detailed Engineering Design and Construction Supervision Component 1 Irrigation and Quality And Cost- IDA / 54560 Prior Open - International 3,126,284.12 Signed 2017-09-25 2017-10-09 2017-10-09 2017-11-13 2018-08-21 2017-12-11 2018-10-19 2018-01-10 2018-12-27 2018-01-31 2019-01-29 2018-02-21 2019-01-31 2019-08-15 services for Kvemo Samgori, Drainage Improvement Based Selection Tbisi-Kumisi and Zeda Ru irrigation system's secondary, tertiary and on-farm network IDIC/CS/CQS/08 / Consultant Preparation of Training Component 1 Irrigation and Under IDA / 54560 Post Qualification Open - International 0.00 2018-10-01 2018-10-26 2018-10-15 2018-10-29 2018-11-14 2018-11-25 2019-12-31 Modules and Conduction of Drainage Improvement Implementation Selection Training Courses IDIC/CS/LCS/03 / ILMDP Component 1 Irrigation and Least Cost Project Financial Audit for IDA / 54560 Post Open - International 21,420.00 Signed 2020-01-22 2020-01-22 2020-02-01 2020-01-27 2020-03-01 2020-02-07 2020-03-16 2020-02-21 2020-03-31 2020-03-02 2020-04-28 2020-03-09 2020-05-18 2020-03-12 2021-07-31 Drainage Improvement Selection 2019-2021 fiscal years IDIC/AF/CS/QCBS/01 / Component 1 Irrigation and Quality And Cost- Under Feasibility Study for 20 IBRD / 90430 Prior Open - International 0.00 2020-04-10 2020-06-09 2020-04-24 2020-06-30 2020-05-22 2020-11-25 2020-06-19 2020-07-04 2020-07-18 2020-07-25 2021-10-28 Drainage Improvement Based Selection Implementation Reservoirs IDIC/AF/CS/CQS/01 / Consultant Consultancy Services for Component 1 Irrigation and Pending IBRD / 90430 Post Qualification Open - International 0.00 2020-04-30 2020-05-14 2020-06-18 2020-07-09 2020-07-23 2021-07-23 Institutional strengthening of Drainage Improvement Implementation Selection NSLMLUMA IDIC/CS/CQS/09 / Development, implementation and monitoring of Communication, Social Consultant Component 1 Irrigation and Mobilization and Media IDA / 54560 Post Qualification Open - National 0.00 Canceled 2020-07-19 2020-07-20 2020-07-26 2020-08-30 2020-09-13 2020-10-11 2022-06-03 Drainage Improvement Strategy to support the Selection Activities of Water Users Organization’s Development in the ILMD Project areas IDIC/CS/CQS/09-1 / Strategic planning for Consultant facilitation of establishment of Component 1 Irrigation and Pending IDA / 54560 Post Qualification Open - National 0.00 2020-11-30 2020-12-14 2020-12-28 2021-01-04 2021-01-16 2022-09-08 the Water User Organizations Drainage Improvement Implementation Selection (WUO) in the ILMDP Project areas INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Individual CS/IC/10 / Procurement Component 1 Irrigation and IDA / 54560 Prior Consultant Open 225,515.89 Signed 2015-02-25 2015-02-25 Consultant Drainage Improvement Selection Page 3 IDIC/CS/IC/03 / Water Individual Resource and Climate Advisor Component 1 Irrigation and IDA / 54560 Prior Consultant Open 42,611.12 Signed 2015-04-24 2015-04-24 for Institutional Strengthening Drainage Improvement Selection of UASCG Individual IDIC/CS/IC/04 / Agricultural Component 1 Irrigation and IDA / 54560 Prior Consultant Open 43,266.65 Signed 2015-04-23 2015-04-23 Economist Drainage Improvement Selection Individual IDIC/CS/IC/05 / Water Component 1 Irrigation and IDA / 54560 Prior Consultant Open 34,272.44 Signed 2015-05-22 2015-06-15 Resource Legal Advisor Drainage Improvement Selection IDIC/CS/IC/01 / Management Individual Component 1 Irrigation and Operation and Maintenance IDA / 54560 Prior Consultant Open 55,932.00 Signed 2015-04-24 2015-06-27 Drainage Improvement (MOM) Advisor Selection IDIC/CS/SSS/01 / Local-level Component 1 Irrigation and Water Management IDA / 54560 Prior Direct Selection Direct 114,971.33 Completed 2015-07-07 2018-08-01 Drainage Improvement Institutions Advisor IDIC/CS/SSS/04 / Component Component 1 Irrigation and IDA / 54560 Prior Direct Selection Direct 108,323.87 Signed 2015-07-01 Director Drainage Improvement IDIC/CS/SSS/05 / Financial Component 1 Irrigation and IDA / 54560 Prior Direct Selection Direct 105,143.96 Signed 2015-07-01 Manager Drainage Improvement IDIC/CS/SSS/06 / Accountant Component 1 Irrigation and IDA / 54560 Prior Direct Selection Direct 82,667.50 Signed 2015-07-01 and Disbursement Specialist Drainage Improvement IDIC/CS/SSS/02 / Irrigation Component 1 Irrigation and Policy Specialist and Strategy IDA / 54560 Prior Direct Selection Direct 37,366.67 Signed 2015-07-15 Drainage Improvement Team Leader Individual IDIC/CS/IC/14 / Component Component 1 Irrigation and IDA / 54560 Prior Consultant Open 188,934.76 Signed 2015-07-08 2015-07-09 Coordinator Drainage Improvement Selection IDIC/CS/SSS/03 / Accounting Component 1 Irrigation and Software Maintenance IDA / 54560 Prior Direct Selection Direct 29,588.38 Signed 2015-11-15 Drainage Improvement Specialist IDIC/CS/SSS/08 / Water Component 1 Irrigation and IDA / 54560 Prior Direct Selection Direct 23,862.23 Signed 2016-02-17 Resource and Climate Advisor Drainage Improvement IDIC/CS/SSS/09 / Agricultural Component 1 Irrigation and IDA / 54560 Prior Direct Selection Direct 55,263.33 Signed 2016-02-17 Economist Drainage Improvement IDIC/CS/SSS/10 / Water Resource Legal advisory Component 1 Irrigation and Under IDA / 54560 Prior Direct Selection Direct 67,587.78 2016-03-30 services for Institutional Drainage Improvement Implementation Strengthening of GA IDIC/CS/IC/29 / Designing advisory services for Individual Institutional Strengthening of Component 1 Irrigation and IDA / 54560 Post Consultant Open 45,076.00 Terminated 2016-10-10 2016-09-20 2016-11-19 2016-10-26 2016-12-03 2016-10-28 2016-12-17 2016-11-01 2017-12-17 Georgian Amelioration Drainage Improvement Selection (Consultant with international experience) IDIC/CS/SSS/13 / Team Component 1 Irrigation and Leader for finalization of IDA / 54560 Post Direct Selection Direct 20,256.67 Signed 2016-10-24 2016-10-24 2016-11-03 2016-11-04 2016-11-24 2016-11-18 2017-05-23 Drainage Improvement Irrigation Strategy Individual IDIC/CS/IC/17 / PPMD Component 3 Project IDA / 54560 Post Consultant Open 22,675.43 Signed 2017-02-20 2017-02-06 2017-03-18 2017-02-13 2017-03-25 2017-02-13 2017-03-30 2017-02-13 2019-07-28 Engineer 2 Management Selection Individual IDIC/CS/IC/21 / Component 3 Project IDA / 54560 Post Consultant Open 0.00 Canceled 2018-01-11 2018-02-13 2018-02-27 2018-03-04 2019-03-04 Environmental Specialist Management Selection IDIC/CS/IC/30 / Agricultural Economics advisory services Individual for Institutional Strengthening Component 1 Irrigation and IDA / 54560 Post Consultant Open 45,217.60 Signed 2017-02-27 2017-02-22 2017-03-30 2017-03-22 2017-04-09 2017-03-31 2017-04-12 2017-03-31 2018-01-07 of Georgian Amelioration Drainage Improvement Selection (Consultant with international experience) IDIC/CS/IC/32 / Local Individual Consultant for Preparation of Component 1 Irrigation and IDA / 54560 Post Consultant Open 7,069.67 Signed 2017-04-17 2017-03-30 2017-05-16 2017-05-01 2017-05-23 2017-05-01 2017-05-24 2017-05-01 2017-08-22 Georgian National Drainage Drainage Improvement Selection Strategy IDIC/CS/IC/33 / Regional Advisor to the Georgian Individual Component 1 Irrigation and Amelioration (GA) for Water IDA / 54560 Post Consultant Open 71,213.00 Signed 2017-09-25 2017-09-13 2017-10-24 2017-11-08 2017-11-03 2017-11-10 2017-11-08 2017-11-10 2019-02-01 Drainage Improvement Users Organisations (WUO) Selection strategy development IDIC/CS/IC/34 / Consultant for supervision of implementation of civil works under Batch 1 for Zeda Ru, Individual Component 1 Irrigation and Kvemo Samgori and Tbisi- IDA / 54560 Post Consultant Open 13,136.62 Signed 2017-09-25 2017-09-28 2017-10-13 2017-10-05 2017-10-20 2017-10-05 2017-10-21 2017-10-06 2018-07-08 Drainage Improvement Kumisi Irrigation Schemes in Selection compliance with the ESMF and EMPs and consultations for Drainage Strategy IDIC/CS/IC/35 / Team Leader Individual Component 1 Irrigation and for Water Users Development IDA / 54560 Post Consultant Open 12,785.39 Signed 2018-01-22 2018-02-18 2018-02-23 2018-02-26 2018-06-12 2018-08-25 Drainage Improvement Support Unit Selection Individual IDIC/CS/IC/36 / Assistant Component 3 Project IDA / 54560 Post Consultant Open 29,117.65 Signed 2018-01-08 2018-01-05 2018-01-23 2018-01-26 2018-01-27 2018-01-15 2019-07-21 Procurement Consultant Management Selection Page 4 IDIC/CS/IC/37 / Senior Specialist for irrigation Individual Component 1 Irrigation and engineering, operation and IDA / 54560 Post Consultant Open 6,849.32 Signed 2018-01-22 2018-02-18 2018-02-23 2018-02-26 2018-06-15 2018-08-25 Drainage Improvement maintenance of Water Users Selection Development Support Unit IDIC/CS/IC/26 / Preparation Individual Component 1 Irrigation and of Environment Management IDA / 54560 Post Consultant Open 0.00 Canceled 2017-11-15 2017-12-18 2018-01-01 2018-01-06 2018-03-07 Drainage Improvement Plan for Batch 2 Selection IDIC/CS/IC/31 / Complete Individual legislative framework analysis Component 1 Irrigation and IDA / 54560 Post Consultant Open 0.00 Canceled 2017-04-03 2017-05-04 2017-05-02 2017-05-12 2017-05-15 2017-07-14 regarding agricultural land in Drainage Improvement Selection Georgia IDIC/CS/SSS/14 / Accountant Component 1 Irrigation and IDA / 54560 Post Direct Selection Direct 13,664.85 Signed 2018-03-20 2018-03-30 2018-05-06 2019-03-01 2018-11-02 and Disbursement Specialist Drainage Improvement IDIC/CS/SSS/15 / Component 1 Irrigation and International Lead-Consultant IDA / 54560 Post Direct Selection Direct 56,679.33 Signed 2018-03-29 2018-04-02 2018-04-09 2018-04-05 2018-10-06 Drainage Improvement Irrigation and Drainage IDIC/CS/IC/39 / Deputy Individual Component 1 Irrigation and Team leader for Water Users IDA / 54560 Post Consultant Open 7,777.78 Signed 2018-05-16 2018-06-13 2018-06-18 2018-10-17 2018-06-21 2018-10-01 2018-12-21 Drainage Improvement Development Support Unit Selection IDIC/CS/IC/40 / Water Individual management Specialist Water Component 1 Irrigation and IDA / 54560 Post Consultant Open 11,351.35 Signed 2018-05-18 2018-06-23 2018-06-28 2018-07-01 2018-11-16 2018-12-31 Users Development Support Drainage Improvement Selection Unit IDIC/CS/IC/41 / Regional Individual Team Leader for Water Users Component 1 Irrigation and IDA / 54560 Post Consultant Open 6,671.61 Signed 2018-05-18 2018-06-23 2018-06-28 2018-09-28 2018-07-01 2018-10-01 2018-12-31 Development Support Unit for Drainage Improvement Selection Tbisi-Kumisi IDIC/CS/IC/42 / Regional Individual Team Leader for Water Users Component 1 Irrigation and IDA / 54560 Post Consultant Open 6,671.61 Signed 2018-05-18 2018-06-23 2018-06-28 2018-09-28 2018-07-01 2018-10-01 2018-12-31 Development Support Unit for Drainage Improvement Selection Zeda Ru IDIC/CS/IC/43 / Regional Individual Team Leader for Water Users Component 1 Irrigation and IDA / 54560 Post Consultant Open 6,671.61 Signed 2018-05-18 2018-06-23 2018-06-28 2018-09-28 2018-07-01 2018-10-01 2018-12-31 Development Support Unit for Drainage Improvement Selection Zemo Samgori IDIC/CS/IC/44 / Regional Individual Team Leader for Water Users Component 1 Irrigation and Under IDA / 54560 Post Consultant Open 0.00 2018-05-18 2018-06-23 2018-06-28 2018-07-01 2018-12-31 Development Support Unit for Drainage Improvement Implementation Selection Kvemo Samgori IDIC/CS/SSS/-16 / Water Resource Legal advisory Component 1 Irrigation and IDA / 54560 Prior Direct Selection Direct 0.00 Canceled 2018-06-19 2018-06-19 2018-06-27 2019-06-27 services for Institutional Drainage Improvement Strengthening of GA IDIC/CS/SSS/-16/1 / Water Resource Legal advisory Component 1 Irrigation and IDA / 54560 Post Direct Selection Direct 46,741.10 Signed 2018-06-22 2018-06-22 2018-06-30 2018-07-02 2019-06-30 services for Institutional Drainage Improvement Strengthening of GA IDIC/CS/SSS/17 / Local-level Component 1 Irrigation and Water Management IDA / 54560 Post Direct Selection Direct 84,370.00 Signed 2018-09-28 2018-10-05 2018-11-01 2018-11-08 2020-01-11 Drainage Improvement Institutions Advisor IDIC/CS/SSS/18 / Training Component 1 Irrigation and IDA / 54560 Post Direct Selection Direct 3,915.38 Signed 2019-02-08 2019-02-20 2019-02-15 2019-03-22 2019-02-20 2019-07-20 Course for GA Drainage Improvement IDIC/CS/SSS/19 / Local Component 1 Irrigation and Environmental and Social IDA / 54560 Post Direct Selection Direct 10,344.83 Signed 2019-04-03 2019-06-18 2019-04-07 2019-04-18 2019-06-19 2019-12-30 Drainage Improvement Specialist Individual IDIC/CS/IC/38 / Financial Component 1 Irrigation and IDA / 54560 Post Consultant Open 0.00 Canceled 2018-03-25 2018-05-01 2018-05-22 2018-06-26 2018-12-23 Manager Drainage Improvement Selection IDIC/CS/SSS/20 / Mid-term Survey for Irrigation and Component 1 Irrigation and IDA / 54560 Post Direct Selection Direct 34,741.20 Signed 2019-11-04 2019-11-19 2019-11-10 2019-11-22 2019-12-12 2020-01-20 2020-06-09 Drainage Improvement Drainage Improvement Component I IDIC/CS/SSS/21 / Component 1 Irrigation and IDA / 54560 Post Direct Selection Direct 25,200.00 Signed 2020-06-02 2020-06-03 2020-06-02 2020-06-02 2020-06-05 2020-06-03 2020-09-03 Procurement Consultant Drainage Improvement Page 5