Republic Of Yemen Water Sector Support Program WSSP Procurement Plan of WSSP Compiled 2009 - 2012 I. General 1. Project Information Project Name: Water Setor Support Program Country: Republic of Yemen Project ID: P 107037 Loan/Credit Numbers: IDA Grant No. H449 RY 2. Bank's approval date of Procurement Plan Original: Revision 1: 17/4/2012 Add new revisions 11/12/2013 3. Date of General Procurement Notice September 16, 2009 UN Development Business issue # 758 II. Goods, Work and Non-Consulting Services Thresholds 1. Prior Review Threshold. Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Unlike the case in IDA credit agreemens,the tresholds of contract amounts were indicted only in proc plan for 2009 as attachment 3 of agrred minutes of the IDA grant agreement and some information was incomplete as shown in the comments. Prior Review Threshold 1a. Procurement Category (USD) Comments Goods 500,000 Plus first two contracts Works 5,000,000 Plus first two contracts Non-Consultant Services N/A Include all categories authorized by the loan agreement Procurement Method 1b. Procurement Method Threshold (USD) Comments ICB (Goods) > = 500000 NCB (Goods) >500,000 Shopping (Goods) <= 50000 ICB (Works) >5,000,000 NCB (Works) <= 5000000 Shopping works < 200000 ICB (Non-Consultant Services) N/A Include all methods authorized by the loan agreement 2. Prequalification. Bidders for US$ 10,000,000 shall be prequlified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. NA 3. Proposed Procedures for CDD Components (as per paragraph 3.17 of the Guidelines): NA 4. Reference to (if any) Project Operational/Procurement Manual: ??????? 5. Any Other Special Procurement Arrangements: [ncluding advance procurement and retroactive financing, if applicable 6. Procurement Packages with Methods and Time Schedule: See attached "Goods and Works" sheet III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Prior Review Threshold 1a. Procurement Category (USD) Comments Consulting Firms (Competitive) 200,000 Consulting Firms (Sole Source) All Individual Consultants (Competitive) 50,000 As mentioned in attachment 3 Individual Consultants (Sole Source) All SS contracts As mentioned in attachment 3 Include all categories authorized by the loan agreement Procurement Method 1b. Procurement Method Threshold (USD) Comments QCBS 300000 and more QCB less than 300000 FCS less than 300000 LCS less than 300000 CQS less than 300000 Consulting Firms (Competitive) 100,000 Consulting Firms (Sole Source) All Individual Consultants (Competitive) 50,000 As mentioned in attachment 3 Individual Consultants (Sole Source) All ICB (Non-Consultant Services) NA Include all methods authorized by the loan agreement 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $ 300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. Note: OPCPR list of ceilings can be found here:http://go.worldbank.org/MKXO98RY40 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable] NA 4. Consultancy Assignments with Selection Methods and Time Schedule: See attached "Consulting Services" sheet IV. Implementing Agency Capacity Building Activities with Time Schedule: See attached "Capacity Building" sheet P107037 Updated Republic of Yemen Water Sector Support Program (WSSP) Procurement Plan for Goods & Works for Part C - WSSP for Year 2009 - 2012 Canceled activities Red raws ** Applicable in case of Bank's prior review Prequalification No Objection No Objection Bank’s No Bank’s No Name, City, Review from Bank for from Bank for Contract Objection to Bid and Country Goods/ Domestic Preparation of Objection to Expenditure by Bank Method of Prequalifica Draft Evaluation of Bid Invitation Bid Closing Bid Opening Award Evaulation Contract Contract Contract of Completion of Package/ Reference No. Description of Goods Works/ Preference Bid Document Bidding Contract Value Currency No. Contractor Contract (Date) incurred to (Prior/ Selection tion (yes/no) Prequalification Prequalification (Date) (Date) (Date) Decision Report and Signed (Date) Date NCS (yes/no) (Date) Document (incl. Zip Post) documents Application (Date) Contract Award (Date)** Code if US) (Date)** (Date)** (Date)** Planned 08/G/RWSS/WSSP/09 Procurement of pipes and Goods Prior NCB No No NA NA 1-Feb-09 15-Feb-09 21-Feb-09 22-Mar-09 3-May-09 17-May-09 1-Jun-09 30-Oct-09 Revised fittings in Mahaweet 15-Dec-09 2-Jan-10 G.Irr.Coop 14-Apr-10 Actual 14-Jun-09 15-Jun-09 14-Jul-09 8-Aug-09 13-Aug-09 20-Dec-09 1-Feb-10 23-Mar-10 285,763.00 US $ erative 21-Jun-10 ‫مورد‬ Planned 05/G/RWSS/WSSP/09 Procurement of pipes and Goods Prior NCB No No NA NA 1-Feb-09 15-Feb-09 21-Feb-09 22-Mar-09 3-May-09 17-May-09 1-Jun-09 30-Oct-09 Revised fittings in saada 15-Dec-09 2-Jan-10 14-Apr-10 Actual 14-Jun-09 15-Jun-09 14-Jul-09 10-Aug-09 15-Aug-09 15-Dec-09 1-Feb-10 20-Mar-10 278,522.00 US $ Heskan Co. 18-Jun-10 ‫مورد‬ Planned 16/G/RWSS/WSSP/09 Procurement of pipes and Goods Post NCB No No NA NA 1-Feb-09 15-Feb-09 21-Feb-09 22-Mar-09 3-May-09 17-May-09 1-Jun-09 30-Oct-09 Revised fittings in lahj 15-Dec-09 2-Jan-10 G.Irr.Coop 14-Apr-10 Actual 14-Jun-09 15-Jun-09 10-Sep-09 25-Sep-09 30-Sep-09 4-Oct-09 1-Feb-10 24-Mar-10 136,998.68 US $ erative 22-Jun-10 ‫مورد‬ Planned 03/G/RWSS/WSSP/09 Procurement of pipes and Goods Post NCB No No NA NA 1-Feb-09 15-Feb-09 21-Feb-09 22-Mar-09 3-May-09 17-May-09 1-Jun-09 30-Oct-09 Revised fittings in Haja 15-Dec-09 2-Jan-10 G.Irr.Coop 14-Apr-10 Actual 14-Jun-09 15-Jun-09 3-Jul-09 26-Jul-09 1-Aug-09 15-Feb-10 1-Feb-10 26-Mar-10 371,021.73 US $ erative 24-Jun-10 ‫مورد‬ Planned 05/G/RWSS/WSSP/09 Procurement of pipes and Goods Post NCB No No NA NA 1-Feb-09 15-Feb-09 21-Feb-09 22-Mar-09 3-May-09 17-May-09 1-Jun-09 30-Oct-09 Revised fittings in Sanaa 15-Dec-09 2-Jan-10 G.Irr.Coop 14-Apr-10 Actual 14-Jun-09 15-Jun-09 6-Jul-09 30-Jul-09 5-Aug-09 15-Aug-09 1-Feb-10 24-Mar-10 137,093.39 US $ erative 22-Jun-10 ‫مورد‬ Planned 01/G/RWSS/WSSP/09 Procurement of pipes and Goods Post NCB No No NA NA 1-Feb-09 15-Feb-09 21-Feb-09 22-Mar-09 3-May-09 17-May-09 1-Jun-09 30-Oct-09 Revised fittings in Mareb 15-Dec-09 2-Jan-10 National 14-Apr-10 Actual 14-Jun-09 15-Jun-09 28-Jun-09 24-Jul-09 29-Jul-09 8-Oct-09 1-Feb-10 10-Jan-10 76,920.00 US $ Co. 10-Apr-10 ‫مورد‬ Planned 01/G/RWSS/WSSP/09 Procurement of pipes and Goods Post NCB No No NA NA 1-Feb-09 15-Feb-09 21-Feb-09 22-Mar-09 3-May-09 17-May-09 1-Jun-09 30-Oct-09 Revised fittings in Shabwa 15-Dec-09 2-Jan-10 G.Irr.Coop 14-Apr-10 Actual 14-Jun-09 15-Jun-09 4-Jul-09 30-Jul-09 5-Aug-09 23-Aug-09 1-Feb-10 23-Mar-10 336,631.75 US $ erative 21-Jun-10 ‫مورد‬ Planned 04/G/RWSS/WSSP/09 Procurement of pipes and Goods Post NCB No No NA NA 1-Feb-09 15-Feb-09 21-Feb-09 22-Mar-09 3-May-09 17-May-09 1-Jun-09 G.Irr.C & 30-Oct-09 Revised fittings in Hudaida 15-Dec-09 2-Jan-10 Green 14-Apr-10 Actual 14-Jun-09 15-Jun-09 15-Jul-09 10-Aug-09 15-Aug-09 19-Aug-09 1-Feb-10 20-Mar-10 303,265.00 US $ Land 18-Jun-10 ‫مورد‬ Planned 05/G/RWSS/WSSP/09 Procurement of pumps and Goods Prior NCB No No NA NA 15-Feb-09 28-Feb-09 2-Mar-09 5-Apr-09 22-Apr-09 6-May-09 20-May-09 Al-Abrag 30-Sep-09 Revised accessories in Hudaida 15-Dec-09 2-Jan-10 & Abu 14-Apr-10 Actual 14-Jun-09 15-Jun-09 15-Jul-09 10-Aug-09 10-Aug-09 1-Oct-09 1-Feb-10 25-Mar-10 90,232.00 US $ Alregal Co 23-Jun-10 ‫مورد‬ Planned 06/G/RWSS/WSSP/09 Procurement of pumps and Goods Prior NCB No No NA NA 15-Feb-09 28-Feb-09 2-Mar-09 5-Apr-09 22-Apr-09 6-May-09 20-May-09 30-Sep-09 Revised accessories in saada 9-Jan-10 23-Jan-10 6-Feb-10 27-Feb-10 31/0531-5-2010/2010 Actual 14-Jun-09 15-Jun-09 15-Dec-09 10-Jan-10 15-Jan-10 1-Feb-10 1-Feb-10 9-Mar-10 155,958.00 US $ Al-Sunidar 7-Jun-10 ‫مورد‬ Planned 17/G/RWSS/WSSP/09 Procurement of pumps and Goods Post NCB No No NA NA 15-Feb-09 28-Feb-09 2-Mar-09 5-Apr-09 22-Apr-09 6-May-09 20-May-09 14-Apr-10 Revised accessories in lahj Actual 14-Jun-09 15-Jun-09 29-Jun-09 22-Jul-09 27-Jul-09 10-Aug-09 1-Feb-10 10-Jan-10 24,772.44 US $ Abu Alrgal 10-Apr-10 ‫مورد‬ Planned 04/G/RWSS/WSSP/09 Procurement of pumps and Goods Post NCB No No NA NA 15-Feb-09 28-Feb-09 2-Mar-09 5-Apr-09 22-Apr-09 6-May-09 20-May-09 14-Apr-10 Revised accessories in Haja Actual 14-Jun-09 15-Jun-09 3-Jul-09 25-Jul-09 1-Aug-09 8-Aug-09 1-Feb-10 27-Feb-10 62,086.00 US $ Abu Alrgal 28-May-10 ‫مورد‬ Planned 04/G/RWSS/WSSP/09 Procurement of pumps and Goods Post NCB No No NA NA 15-Feb-09 28-Feb-09 2-Mar-09 5-Apr-09 22-Apr-09 6-May-09 20-May-09 Al-Abrag 14-Apr-10 Revised accessories in Sanaa & Abu Actual 14-Jun-09 15-Jun-09 6-Jul-09 30-Jul-09 5-Aug-09 15-Aug-09 15-Sep-09 23-Dec-09 172,941.00 US $ Alregal Co 23-Mar-10 ‫مورد‬ Planned 02/G/RWSS/WSSP/09 Procurement of pumps and Goods Post NCB No No NA NA 15-Feb-09 28-Feb-09 2-Mar-09 5-Apr-09 22-Apr-09 6-May-09 20-May-09 14-Apr-10 Revised accessories in Mareb Actual 14-Jun-09 15-Jun-09 28-Jun-09 24-Jul-09 29-Jul-09 8-Aug-09 1-Feb-10 10-Jan-10 104,045.00 US $ Al-Sunidar 10-Apr-10 ‫مورد‬ Planned 02/G/RWSS/WSSP/09 Procurement of pumps and Goods Post NCB No No NA NA 15-Feb-09 28-Feb-09 2-Mar-09 5-Apr-09 22-Apr-09 6-May-09 20-May-09 Al-Abrag 14-Apr-10 Revised accessories in Shabwa & Abu Actual 14-Jun-09 15-Jun-09 4-Jul-09 30-Jul-09 5-Aug-09 20-Aug-09 20-Feb-10 131,956.00 US $ Alregal Co 21-May-10 ‫مورد‬ above packages / contracts nos. 1-15 were already approvrd by IDA during 2009 - 2010 Rashad ALhaj 4/36 ** Applicable in case of Bank's prior review Prequalification No Objection No Objection Bank’s No Bank’s No Name, City, Review from Bank for from Bank for Contract Objection to Bid and Country Goods/ Domestic Preparation of Objection to Expenditure by Bank Method of Prequalifica Draft Evaluation of Bid Invitation Bid Closing Bid Opening Award Evaulation Contract Contract Contract of Completion of Package/ Reference No. Description of Goods Works/ Preference Bid Document Bidding Contract Value Currency No. Contractor Contract (Date) incurred to (Prior/ Selection tion (yes/no) Prequalification Prequalification (Date) (Date) (Date) Decision Report and Signed (Date) Date NCS (yes/no) (Date) Document (incl. Zip Post) documents Application (Date) Contract Award (Date)** Code if US) (Date)** (Date)** (Date)** Planned 07- Various Water & Sanitation Civil Works Post NCB No No NA NA 10-Jun-10 24-Jun-10 29-Jun-10 29-Jul-10 12-Aug-10 26-Aug-10 1-Sep-10 30-Dec-10 Revised 3/CW/RWSS/WSSP/0 Works alradyah in Hudaida Prior NCB No No 10-Oct-10 16-Oct-10 15-Nov-10 15-Nov-10 29-Nov-10 8-Jan-11 24-Jan-11 25-Mar-11 Actual 9 1-Aug-10 31-Oct-10 10-Nov-10 11-Dec-10 11-Dec-10 25-Dec-10 7-Feb-11 9-Feb-11 44,094.40 US $ Planned 01- Various Water & Sanitation Civil Works Prior NCB No No NA NA 10-Jun-10 24-Jun-10 29-Jun-10 29-Jul-10 12-Aug-10 26-Aug-10 1-Sep-10 30-Dec-10 Revised 2/CW/RWSS/WSSP/0 Works al alqar in Ma'reb Prior NS No No 17-May-10 5-Oct-10 9-Oct-10 23-Oct-10 23-Oct-10 30-Oct-10 4-Jan-11 20-Jan-11 15-May-11 Actual 9 1-Oct-10 25-Oct-10 25-Oct-10 9-Nov-10 9-Nov-10 20-Dec-10 5-Jan-11 15-Jan-11 4,031.67 US $ 11-May-11 Planned 01- Various Water & Sanitation Civil Works Prior NCB No No NA NA 10-Jun-10 24-Jun-10 29-Jun-10 29-Jul-10 12-Aug-10 1-Sep-10 30-Dec-10 Revised 1/CW/RWSS/WSSP/0 Works qasha albared in Ma'reb Post NS No No 17-May-10 N/A 9-Oct-10 23-Oct-10 23-Oct-10 30-Oct-10 15-Nov-10 15-Mar-11 Actual 9 1-Oct-10 26-Oct-10 9-Nov-10 9-Nov-10 1-Dec-10 28-Dec-10 15,318.67 US $ 16-May-11 Planned 01- Various Water & Sanitation Civil Works Prior NCB No No NA NA 10-Jun-10 24-Jun-10 29-Jun-10 29-Jul-10 12-Aug-10 1-Sep-10 30-Dec-10 Revised 3/CW/RWSS/WSSP/0 Works alaeer wahshan in Ma'reb Post NS No No 17-May-10 N/A 9-Oct-10 23-Oct-10 23-Oct-10 30-Oct-10 15-Nov-10 14-Jan-11 Actual 9 1-Oct-10 26-Oct-10 9-Nov-10 9-Nov-10 1-Dec-10 28-Dec-10 4,823.76 US $ 2-Feb-11 Planned 01- Various Water & Sanitation Civil Works Prior NCB No No NA NA 10-Jun-10 24-Jun-10 29-Jun-10 29-Jul-10 12-Aug-10 1-Sep-10 30-Dec-10 Revised 4/CW/RWSS/WSSP/0 Works algafynah in Ma'reb Post NS No No 17-May-10 N/A 9-Oct-10 23-Oct-10 23-Oct-10 30-Oct-10 15-Nov-10 15-Mar-11 Actual 9 1-Oct-10 26-Oct-10 9-Nov-10 9-Nov-10 1-Dec-10 28-Dec-10 22,741.82 US $ Planned 01- Various Water & Sanitation Civil Works Prior NCB No No NA NA 10-Jun-10 24-Jun-10 29-Jun-10 29-Jul-10 12-Aug-10 1-Sep-10 30-Dec-10 Revised 5/CW/RWSS/WSSP/0 Works goa alaber in Ma'reb Post NS No No 17-May-10 N/A 9-Oct-10 23-Oct-10 23-Oct-10 30-Oct-10 15-Nov-10 26-Feb-11 Actual 9 1-Oct-10 26-Oct-10 9-Nov-10 9-Nov-10 1-Dec-10 28-Dec-10 9,923.81 US $ 30-Jan-11 Planned 02/CW/RWSS/WSSP/ Various Water & Sanitation Civil Works Post NCB No No NA NA 10-Jun-10 24-Jun-10 29-Jun-10 29-Jul-10 12-Aug-10 1-Sep-10 30-Dec-10 Revised 09 Works in Mahaweet Post NCB No No 1-Jan-11 N/A 5-Feb-11 7-Mar-11 7-Mar-11 15-Mar-11 31-Mar-11 29-Jun-11 Actual 20-Jan-11 6-Feb-11 8-Mar-11 8-Mar-11 22-Mar-11 30-Mar-11 73,873.00 US $ Planned 04/CW/RWSS/WSSP/ Various Water & Sanitation Civil Works Post NCB No No NA NA 10-Jun-10 24-Jun-10 29-Jun-10 29-Jul-10 12-Aug-10 1-Sep-10 30-Dec-10 Revised 09 Works in Sana'a Post NCB No No 1-Mar-10 N/A 25-Mar-10 25-Apr-10 15-May-10 15-Jun-10 25-Feb-11 Actual 3-Mar-10 2-Apr-10 2-May-10 2-May-10 1-Jun-10 4-Sep-10 46,929.38 US $ Planned 07- Various Water & Sanitation Civil Works Post NCB No No NA NA 10-Jun-10 24-Jun-10 29-Jun-10 29-Jul-10 12-Aug-10 1-Sep-10 30-Dec-10 Revised 1/CW/RWSS/WSSP/0 Works almdman in Hudaida Post NCB No No 17-May-10 N/A 11-Oct-10 10-Nov-10 10-Nov-10 18-Nov-10 10-Jan-11 12-Mar-11 Actual 9 1-Nov-10 10-Nov-10 11-Dec-10 11-Dec-10 25-Dec-10 11-Jan-11 63,037.12 US $ Planned 07- Various Water & Sanitation Civil Works Post NCB No No NA NA 10-Jun-10 24-Jun-10 29-Jun-10 29-Jul-10 12-Aug-10 1-Sep-10 30-Dec-10 Revised 2/CW/RWSS/WSSP/0 Works deer ali in Hudaida Post NCB No No 17-May-10 N/A 9-Oct-10 10-Nov-10 10-Nov-10 18-Nov-10 10-Jan-11 12-Mar-11 Actual 9 1-Nov-10 10-Nov-10 11-Dec-10 11-Dec-10 25-Dec-10 11-Jan-11 41,228.84 US $ Planned 07- Various Water & Sanitation Civil Works Post NCB No No NA NA 10-Jun-10 24-Jun-10 29-Jun-10 29-Jul-10 12-Aug-10 1-Sep-10 30-Dec-10 Revised 4/CW/RWSS/WSSP/0 Works alfash in Hudaida Post NS No No 17-May-10 N/A 9-Oct-10 23-Oct-10 23-Oct-10 30-Oct-10 15-Nov-10 20-Feb-11 Actual 9 10-Oct-10 11-Nov-10 25-Nov-10 25-Nov-10 10-Dec-10 22-Dec-10 27,621.00 US $ Planned 07- Various Water & Sanitation Civil Works Post NCB No No NA NA 10-Jun-09 24-Jun-09 29-Jun-09 29-Jul-09 12-Aug-09 1-Sep-10 30-Dec-10 Revised 5/CW/RWSS/WSSP/0 Works alzaher in Hudaida Post NS No No 17-May-10 N/A 9-Oct-10 23-Oct-10 23-Oct-10 30-Oct-10 1-Jan-11 5-Mar-11 Actual 9 10-Oct-10 11-Nov-10 25-Nov-10 25-Nov-10 16-Dec-10 4-Jan-11 30,611.70 US $ Planned 07- Various Water & Sanitation Civil Works Post NCB No No NA NA 10-Jun-10 24-Jun-10 29-Jun-10 29-Jul-10 12-Aug-10 1-Sep-10 30-Dec-10 Revised 6/CW/RWSS/WSSP/0 Works alhomra in Hudaida Post NS No No 17-May-10 N/A 9-Oct-10 23-Oct-10 23-Oct-10 30-Oct-10 1-Jan-11 5-Mar-11 Actual 9 1-Nov-10 11-Nov-10 25-Nov-10 25-Nov-10 16-Dec-10 4-Jan-11 17,746.40 US $ Planned 08- Various Water & Sanitation Civil Works Post NCB No No NA NA 10-Jun-09 24-Jun-09 29-Jun-09 29-Jul-09 12-Aug-09 1-Sep-10 30-Dec-10 Revised 1/CW/RWSS/WSSP/0 Works alsameesn in Lahj Post NS No No 17-May-10 N/A 9-Oct-10 23-Oct-10 23-Oct-10 30-Oct-10 15-Nov-10 4-Feb-11 Actual 9 25-Oct-10 27-Oct-10 13-Nov-10 13-Nov-10 23-Nov-10 6-Dec-10 20,337.00 US $ Planned 08- Various Water & Sanitation Civil Works Post NCB No No NA NA 10-Jun-10 24-Jun-10 29-Jun-10 29-Jul-10 12-Aug-10 1-Sep-10 30-Dec-10 Revised 2/CW/RWSS/WSSP/0 Works daqm in Lahj Post NS No No 17-May-10 N/A 9-Oct-10 23-Oct-10 23-Oct-10 30-Oct-10 15-Nov-10 13-Feb-11 Actual 9 25-Oct-10 13-Nov-10 29-Nov-10 29-Nov-10 9-Dec-10 15-Dec-10 36,071.00 US $ Rashad ALhaj 5/36 ** Applicable in case of Bank's prior review Prequalification No Objection No Objection Bank’s No Bank’s No Name, City, Review from Bank for from Bank for Contract Objection to Bid and Country Goods/ Domestic Preparation of Objection to Expenditure by Bank Method of Prequalifica Draft Evaluation of Bid Invitation Bid Closing Bid Opening Award Evaulation Contract Contract Contract of Completion of Package/ Reference No. Description of Goods Works/ Preference Bid Document Bidding Contract Value Currency No. Contractor Contract (Date) incurred to (Prior/ Selection tion (yes/no) Prequalification Prequalification (Date) (Date) (Date) Decision Report and Signed (Date) Date NCS (yes/no) (Date) Document (incl. Zip Post) documents Application (Date) Contract Award (Date)** Code if US) (Date)** (Date)** (Date)** Planned ‫مقترح‬ 1/ MAH Procurement of pipes and Goods Post NCB No No NA NA 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 Heskan Revised ‫متوقع‬ /G/RWSS/WSSP/10 fittings in Mahaweet Post NCB No No 1-Sep-10 1-Oct-10 1-Oct-10 20-Oct-10 15-Nov-10 22-Dec-10 Co. Actual ‫Ù?علي‬ 1-Feb-10 28-Mar-10 28-Mar-10 29-Aug-10 22-Sep-10 306,876.09 21-Dec-10 Planned ‫مقترح‬ 1/ SAD Procurement of pipes and Goods Post NCB No No NA NA 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 fittings in saada Post NCB No No 7-May-10 7-Jun-10 7-Jun-10 25-Jun-10 2-Oct-10 15-Jan-11 Actual ‫Ù?علي‬ 1-Feb-10 7-Jun-10 7-Jul-10 7-Jul-10 19-Jul-10 28-Jul-10 153,257.30 US $ Heskan Co. 26-Oct-10 Planned ‫مقترح‬ 1/ LAH Procurement of pipes and Goods post NCB No No NA NA 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 fittings in lahj G.Irr.Coop 20-Sep-10 Actual ‫Ù?علي‬ 1-Feb-10 18-Feb-10 17-Mar-10 22-Mar-10 1-Apr-10 16-Jun-10 527,180.63 US $ erative 14-Sep-10 Planned ‫مقترح‬ 1/ SAN Procurement of pipes and Goods Post NCB No No NA NA 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 fittings in Sanaa Post NCB No No 23-Jun-10 23-Jul-10 23-Jul-10 15-Aug-10 17-Oct-10 G.Irr.Coop 25-Dec-10 Actual ‫Ù?علي‬ 1-Feb-10 20-Mar-10 14-Apr-10 19-Apr-10 2-Oct-10 30-Oct-10 477,229.70 US $ erative 28-Jan-11 Planned ‫مقترح‬ 1/ MAR /G/RWSS/ Procurement of pipes and Goods Post NCB No No NA NA 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 Revised ‫متوقع‬ WSSP/10 fittings in Mareb Post NCB No No 1-May-10 1-Jun-10 1-Jun-10 5-Oct-10 15-Oct-10 H.Al- 30-Dec-10 Actual ‫Ù?علي‬ 1-Feb-10 12-May-10 7-Jun-10 12-Jun-10 15-Jul-10 2-Aug-10 82,831.00 US $ ALHbabi Almeen + Planned ‫مقترح‬ 1/ SHB Procurement of pipes and Goods Post NCB No No NA NA 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 National 29-Sep-10 Company for Revised ‫متوقع‬ /G/RWSS/WSSP/10 fittings in Shabwa Post NCB No No 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 Sponge & 25-Sep-10 Actual ‫Ù?علي‬ 1-Feb-10 28-Feb-10 29-Mar-10 4-Apr-10 19-Jun-10 23-Jun-10 397,148.00 US $ Plastic 21-Sep-10 Planned ‫مقترح‬ Post NCB No No NA NA 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 G.Irr.Coop 29-Sep-10 1/ HUD Procurement of pipes and Goods erative + Revised ‫متوقع‬ /G/RWSS/WSSP/10 fittings for two contracts in 25-Dec-10 alshahab Actual ‫Ù?علي‬ Hudaida 1-Feb-10 7-Mar-10 2-Apr-10 7-Apr-10 24-Jul-10 25-Aug-10 612,856.99 US $ co. 23-Nov-10 Planned ‫مقترح‬ 1/ TAZ Procurement of pipes and Goods Post NCB No No NA NA 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 fittings in taiz org. abo 30-Nov-10 Actual ‫Ù?علي‬ 1-Feb-10 7-Mar-10 5-Apr-10 10-Apr-10 24-Jul-10 31-Aug-10 597,515.23 US $ fras 29-Nov-10 Planned ‫مقترح‬ 1/ ABN Procurement of pipes and Goods Post NCB No No NA NA 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 fittings in Abyan Post NCB No No 15-Apr-10 15-May-10 15-May-10 15-Jun-10 7-Jul-10 Miss 29-Sep-10 Actual ‫Ù?علي‬ 1-Feb-10 28-Apr-10 20-May-10 25-May-10 20-Jun-10 21-Aug-10 384,000.00 Trading 19-Nov-10 Planned ‫مقترح‬ 1/ HAD Procurement of pipes and Goods Post NCB No No NA NA 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 fittings in moklla Post NCB No No 15-Apr-10 15-May-10 15-May-10 15-Jun-10 7-Jul-10 20-Nov-10 Actual ‫Ù?علي‬ 1-Feb-10 20-Apr-10 19-May-10 24-May-10 14-Aug-10 4-Sep-10 H.Al- 3-Dec-10 Planned ‫مقترح‬ Post NCB No 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 509,074.83 29-Sep-10 1/ HAD Procurement of pipes and Goods No NA NA Hbabi Revised ‫متوقع‬ /G/RWSS/WSSP/10 fittings in saioon Post NCB No No 15-Apr-10 15-May-10 15-May-10 15-Jun-10 7-Jul-10 20-Nov-10 Actual ‫Ù?علي‬ 1-Feb-10 20-Apr-10 19-May-10 24-May-10 14-Aug-10 4-Sep-10 3-Dec-10 Planned ‫مقترح‬ 1/ JWF Procurement of pipes and Goods Post NCB No No NA NA 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 National 29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 fittings in al-jowf Post NCB No No 25-May-10 20-Jun-10 25-Jun-10 15-Jul-10 15-Oct-10 Company 15-Dec-10 Actual ‫Ù?علي‬ 1-Feb-10 1-Jun-10 30-Jun-10 30-Jul-10 24-Jul-10 30-Aug-10 7,614.00 US $ for 28-Nov-10 Planned ‫مقترح‬ 1/ BYD Procurement of pipes and Goods Post NCB No No NA NA 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 fittings in al-bedhaa H.Al- 1-Sep-10 Actual ‫Ù?علي‬ 1-Feb-10 11-Mar-10 5-Apr-10 10-Apr-10 3-May-10 29-May-10 542,716.00 US $ Hbabi 27-Aug-10 Planned ‫مقترح‬ 1/ DHL /G/RWSS/ Procurement of pipes and Goods Post NCB No No NA NA 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 Revised ‫متوقع‬ WSSP/10 fittings in aldhale Miss 1-Sep-10 Actual ‫Ù?علي‬ 1-Feb-10 21-Feb-10 16-Mar-10 21-Mar-10 3-May-10 30-May-10 238,600.00 US $ Trading 28-Aug-10 Planned ‫مقترح‬ 1/ AMR Procurement of pipes and Goods Post NCB No No NA NA 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 H.Al- Revised ‫متوقع‬ /G/RWSS/WSSP/10 fittings in amran Post NCB No No 20-May-10 15-Jun-10 20-Jun-10 10-Jul-10 30-Jul-10 15-Nov-10 Hbabi Actual ‫Ù?علي‬ 1-Feb-10 28-May-10 21-Jun-10 27-Jun-10 24-Jul-10 15-Aug-10 476,475.50 US $ 20-Nov-10 Planned ‫مقترح‬ 1/ RYM Procurement of pipes and Goods Post NCB No No NA NA 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 fittings in ryimah H.Al- Actual ‫Ù?علي‬ 1-Feb-10 11-Mar-10 5-Apr-10 10-Apr-10 3-May-10 31-May-10 421,630.28 US $ Hbabi 29-Sep-10 Planned ‫مقترح‬ 1/ MAH Procurement of pipes and Goods Post NCB No No NA NA 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 National 29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 fittings in al-mahra 15-Oct-10 30-Oct-10 Company 30-Jan-11 Actual ‫Ù?علي‬ 1-Feb-10 9-May-10 1-Jun-10 6-Jun-10 18-Jun-10 17-Jul-10 85,418.00 for Planned ‫مقترح‬ 1/ DHM Procurement of pipes and Goods Post NCB No No NA NA 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 fittings in thamar Post NCB No No 5-Mar-10 1-Apr-10 5-Apr-10 5-May-10 7-Jun-10 H.Al- 29-Sep-10 Actual ‫Ù?علي‬ 1-Feb-10 1-Mar-10 25-Mar-10 31-Mar-10 3-May-10 1-Jun-10 492,896.73 US $ Hbabi 29-Sep-10 1|)-The above five contracts with red colour were forwarded to IDA for revision and approval . 2)- The revised cost estimates for some works packages were split into small packages with NS procurements Rashad ALhaj 6/36 ** Applicable in case of Bank's prior review Prequalification No Objection No Objection Bank’s No Bank’s No Name, City, Review from Bank for from Bank for Contract Objection to Bid and Country Goods/ Domestic Preparation of Objection to Expenditure by Bank Method of Prequalifica Draft Evaluation of Bid Invitation Bid Closing Bid Opening Award Evaulation Contract Contract Contract of Completion of Package/ Reference No. Description of Goods Works/ Preference Bid Document Bidding Contract Value Currency No. Contractor Contract (Date) incurred to (Prior/ Selection tion (yes/no) Prequalification Prequalification (Date) (Date) (Date) Decision Report and Signed (Date) Date NCS (yes/no) (Date) Document (incl. Zip Post) documents Application (Date) Contract Award (Date)** Code if US) (Date)** (Date)** (Date)** Planned ‫مقترح‬ 2/ MAH Procurement of pumps and Goods Post NCB No No NA NA 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 accessories in Mahaweet Post NCB No No 1-Jul-10 25-Jul-10 30-Jul-10 15-Aug-10 1-Sep-10 10-Nov-10 Actual ‫Ù?علي‬ 1-Feb-10 3-Aug-10 2-Sep-10 2-Sep-10 1-Oct-10 30-Oct-10 124,055.00 US $ 29-Sep-10 Planned ‫مقترح‬ * 2/ SAD Procurement of pumps and Goods Post NCB No No NA NA 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 accessories in saada Post NCB No No 1-Apr-10 25-Apr-10 30-Apr-10 1-Jun-10 10-Aug-10 10-Oct-10 Asonidar Revised ‫متوقع‬ Post NCB No No 1-Jun-10 25-Jun-10 30-Jun-10 20-Jul-10 10-Aug-10 10-Oct-10 Actual ‫Ù?علي‬ 1-Feb-10 3-Apr-10 1-May-01 5-May-01 23-May-10 17-Jul-10 129,000.00 US $ 29-Sep-10 Planned ‫مقترح‬ 2/ LAH Procurement of pumps and Goods Post NCB No No NA NA 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 Abu Revised ‫متوقع‬ /G/RWSS/WSSP/10 accessories in lahj Post NCB No No 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 7-Jun-10 15-Aug-10 Alregal Actual ‫Ù?علي‬ 1-Feb-10 18-Feb-10 15-Mar-10 20-Mar-10 2-Apr-10 25-Apr-10 120,886.00 US $ 29-Sep-10 Planned ‫مقترح‬ 2/ HAJ Procurement of pumps and Goods Post NCB No No NA NA 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 Alabrag 29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 accessories in Haja Post NCB No No 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 7-Jun-10 &Abureg 15-Aug-10 Actual ‫Ù?علي‬ 1-Feb-10 22-Feb-10 17-Mar-10 23-Mar-10 1-Apr-10 16-May-10 179,035.00 US $ al&alwat 29-Sep-10 Planned ‫مقترح‬ ** 2/ SAN Procurement of pumps and Goods Post NCB No No NA NA 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 accessories for (18)contracts Post NCB No No 23-Jun-10 23-Jul-10 23-Jul-10 10-Aug-10 30-Aug-10 30-Oct-10 Actual ‫Ù?علي‬ in Sanaa 1-Feb-10 7-Mar-10 1-Apr-10 5-Apr-10 19-Jun-10 19-Jul-10 788,401.22 US $ 16-Nov-10 Planned ‫مقترح‬ 2/ MAR /G/RWSS/ Procurement of pumps and Goods Post NCB No No NA NA 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 Alabrag 29-Sep-10 Revised ‫متوقع‬ WSSP/10 accessories for (15)contracts &alwatar 20-Aug-10 Actual ‫Ù?علي‬ in Mareb 1-Feb-10 3-Mar-10 28-Mar-10 3-Apr-10 3-May-10 5-Jun-10 338,888.00 US $ y&Asoni 3-Sep-10 Planned ‫مقترح‬ 2/ SHB Procurement of pumps and Goods Post NCB No No NA NA 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 Alabrag 29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 accessories in Shabwa Post NCB No No 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 7-Jun-10 &Abureg 25-Aug-10 Actual ‫Ù?علي‬ 1-Feb-10 28-Feb-10 28-Mar-10 4-Apr-10 20-Apr-10 12-Jun-10 269,159.00 US $ al&Alwa 29-Sep-10 Planned ‫مقترح‬ 2/ HUD Procurement of pumps and Goods Post NCB No No NA NA 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 Alabrag 29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 accessories in Hudaida Post NCB No No 1-Mar-10 25-Mar-10 31-Mar-10 4-May-10 7-Jun-10 &Abureg 15-Aug-10 Actual ‫Ù?علي‬ 1-Feb-10 7-Mar-10 1-Apr-10 7-Apr-10 3-May-10 5-Jun-10 249,066.00 US $ al&alwat 3-Sep-10 Planned ‫مقترح‬ *** 2/ TAZ Procurement of pumps and Goods Post NCB No No NA NA 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 Alabrag 29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 accessories for (20)contracts Post NCB No No 1-Mar-10 25-Mar-10 31-Mar-10 4-May-10 7-Jun-10 &Alsoni 29-Sep-10 revised ‫متوقع‬ in taez 9-Jun-10 9-Jul-10 9-Jul-10 1-Aug-10 20-Aug-10 dar& Ali 30-Jan-11 Actual ‫Ù?علي‬ 1-Feb-10 7-Mar-10 5-Apr-10 10-Apr-00 15-May-10 4-Oct-10 595,059.94 US $ Alsonida Planned ‫مقترح‬ 2/ IBB Procurement of pumps and Goods Post NCB No No NA NA 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 Alabrag 29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 accessories for (22)contracts Post NCB No No &alwatar 15-Sep-10 Actual ‫Ù?علي‬ in Ibb 1-Feb-10 3-Mar-10 30-Mar-10 3-Apr-10 8-May-10 29-May-10 685,000.00 US $ y&Asoni 27-Aug-10 Planned ‫مقترح‬ 2/ ABN Procurement of pumps and Goods Post NCB No No NA NA 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 Alabrag Revised ‫متوقع‬ /G/RWSS/WSSP/10 accessories in Abyan Post NCB No No 1-Mar-10 25-Mar-10 31-Mar-10 4-May-10 7-Jun-10 Company Actual ‫Ù?علي‬ 1-Feb-10 5-Mar-10 30-Mar-10 5-Apr-10 18-Apr-10 15-May-10 200,400.00 US $ 13-Aug-10 Planned ‫مقترح‬ 2/ HAD Procurement of pumps and Goods Post NCB No No NA NA 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 Alabrag 29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 accessories in moklla Post NCB No No 1-Mar-10 25-Mar-10 31-Mar-10 4-May-10 7-Jun-10 &Asonid Actual ‫Ù?علي‬ 1-Feb-10 7-Mar-10 1-Apr-10 7-Apr-10 21-Apr-10 5-Jun-10 137,888.00 US $ ar 3-Sep-10 Planned ‫مقترح‬ 2/ HAD Procurement of pumps and Goods Post NCB No No NA NA 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 Alabrag 29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 accessories in saioon Post NCB No No 1-Mar-10 25-Mar-10 31-Mar-10 4-May-10 7-Jun-10 &Asonid Actual ‫Ù?علي‬ 1-Feb-10 7-Mar-10 1-Apr-10 7-Apr-10 21-Apr-10 5-Jun-10 123,956.00 US $ ar 3-Sep-10 Planned ‫مقترح‬ 2/ BYD Procurement of pumps and Goods Post NCB No No NA NA 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 accessories in al-bedhaa Post NCB No No 1-Mar-10 25-Mar-10 31-Mar-10 4-May-10 7-Jun-10 Alabrag 1-Jul-10 ‫مورد‬ Actual ‫Ù?علي‬ 1-Feb-10 11-Mar-10 5-Apr-10 10-Apr-10 20-Apr-10 9-May-10 120,500.00 US $ 7-Aug-10 Planned ‫مقترح‬ 2/ DHL /G/RWSS/ Procurement of pumps and Goods Post NCB No No NA NA 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 Alabrag 29-Sep-10 Revised ‫متوقع‬ WSSP/10 accessories in aldhale Post NCB No No 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 7-Jun-10 &Asonid Actual ‫Ù?علي‬ 1-Feb-10 21-Feb-10 16-Mar-10 21-Mar-10 4-Apr-10 23-Apr-10 149,149.00 US $ ar 22-Jul-10 Planned ‫مقترح‬ 2/ AMR Procurement of pumps and Goods Post NCB No No NA NA 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 Alabrag 29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 accessories for (9) contracts Post NCB No No 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 7-Jun-10 &Asonid Actual ‫Ù?علي‬ in amran 1-Feb-10 23-Feb-10 18-Mar-10 23-Mar-10 10-Apr-10 18-Apr-10 316,075.00 US $ ar 17-Jul-10 Planned ‫مقترح‬ 2/ RYM Procurement of pumps and Goods Post NCB No No NA NA 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 Alabrag 29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 accessories for (9) contracts Post NCB No No 1-Mar-10 25-Mar-10 31-Mar-10 4-May-10 7-Jun-10 &Asonid Actual ‫Ù?علي‬ in ryimah 1-Feb-10 11-Mar-10 5-Apr-10 10-Apr-10 3-May-10 29-May-10 362,056.00 US $ ar 27-Aug-10 Planned ‫مقترح‬ 2/ MAH Procurement of pumps and Goods Post NCB No No NA NA 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 accessories in al-mahra Alabrag Actual ‫Ù?علي‬ 24-Mar-10 19-Apr-10 24-Apr-10 1-Feb-10 10-May-10 29-May-10 99,993.00 US $ &M.alshr 27-Aug-10 Planned ‫مقترح‬ 2/ DHM Procurement of pumps and Goods Post NCB No No NA NA 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 Alabrag 29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 accessories for (28)contracts Post NCB No No 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 7-Jun-10 &Abureg in thamar a Actual ‫Ù?علي‬ 1-Feb-10 3-Mar-10 25-Mar-10 31-Mar-10 15-May-10 16-Jun-10 872,056.00 US $ 14-Sep-10 General Remark:- advertisement is published once for the package of procurement of many pumps indicated that each pump will be signed seperately * under package refrence 2/ SAD /G/RWSS/WSSP/10, comprising of procurement of pumps , contracts of three were signed , whereas two were techinically non responsive and were re- ** under package refrence 2/ SAN /G/RWSS/WSSP/10, comprising of procurement of pumps advertised , contracts of sixsteen were signed , whereas two were techinically non responsive and were re- *** under package refrence 2/ TAZ /G/RWSS/WSSP/10, comprising of procurement of pumps advertised , contracts of nine were signed , whereas eleven were techinically non responsive and were re- advertised Rashad ALhaj 7/36 ** Applicable in case of Bank's prior review Prequalification No Objection No Objection Bank’s No Bank’s No Name, City, Review from Bank for from Bank for Contract Objection to Bid and Country Goods/ Domestic Preparation of Objection to Expenditure by Bank Method of Prequalifica Draft Evaluation of Bid Invitation Bid Closing Bid Opening Award Evaulation Contract Contract Contract of Completion of Package/ Reference No. Description of Goods Works/ Preference Bid Document Bidding Contract Value Currency No. Contractor Contract (Date) incurred to (Prior/ Selection tion (yes/no) Prequalification Prequalification (Date) (Date) (Date) Decision Report and Signed (Date) Date NCS (yes/no) (Date) Document (incl. Zip Post) documents Application (Date) Contract Award (Date)** Code if US) (Date)** (Date)** (Date)** Planned ‫مقترح‬ 4-1/MAH Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works bani zeed in Mahaweet Post NS 1-Jan-11 5-Feb-11 19-Feb-11 19-Feb-11 1-Mar-11 17-Mar-11 16-May-11 Actual ‫Ù?علي‬ 20-Jan-11 31-Jan-11 1-Mar-11 1-Mar-11 13-Mar-11 26-Mar-11 48,101.00 US $ 06/24/2012 Planned ‫مقترح‬ 4-2/MAH Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works almarm in Mahaweet Post NS 1-Jan-11 5-Feb-11 19-Feb-11 19-Feb-11 1-Mar-11 17-Mar-11 16-May-11 Actual ‫Ù?علي‬ 20-Jan-11 31-Jan-11 1-Mar-11 1-Mar-11 13-Mar-11 26-Mar-11 6,581.50 US $ 2-May-11 Planned ‫مقترح‬ 4-3/MAH Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works almrmeeda in Mahaweet Post NS 1-Jan-11 5-Feb-11 19-Feb-11 19-Feb-11 1-Mar-11 17-Mar-11 16-May-11 Actual ‫Ù?علي‬ 20-Jan-11 31-Jan-11 1-Mar-11 1-Mar-11 13-Mar-11 26-Mar-11 1,738.00 US $ 24-Apr-11 Planned ‫مقترح‬ 4-4/MAH Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works anbar in Mahaweet Post NS 1-Jan-11 5-Feb-11 19-Feb-11 19-Feb-11 1-Mar-11 17-Mar-11 16-May-11 Actual ‫Ù?علي‬ 20-Jan-11 31-Jan-11 1-Mar-11 1-Mar-11 13-Mar-11 26-Mar-11 15,701.00 US $ 06/24/2012 Planned ‫مقترح‬ 4-5/MAH Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works bani alashal in Mahaweet Post NS 1-Jan-11 5-Feb-11 19-Feb-11 19-Feb-11 1-Mar-11 17-Mar-11 16-May-11 Actual ‫Ù?علي‬ 20-Jan-11 31-Jan-11 1-Mar-11 1-Mar-11 13-Mar-11 26-Mar-11 11,544.00 US $ 06/24/2012 Planned ‫مقترح‬ 4-1/ LAH Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works alhagr in lahj Post NS 9-Oct-10 23-Oct-10 23-Oct-10 30-Oct-10 15-Nov-10 14-Apr-11 Actual ‫Ù?علي‬ 25-Oct-10 13-Nov-10 29-Nov-10 29-Nov-10 1-Dec-10 15-Dec-10 43,837.00 US $ 07/04/2012 Planned ‫مقترح‬ 4-2/ LAH Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works boran in lahj Post NS 9-Oct-10 23-Oct-10 23-Oct-10 30-Oct-10 15-Nov-10 5-Apr-11 Actual ‫Ù?علي‬ 25-Oct-10 27-Oct-10 13-Nov-10 13-Nov-10 20-Nov-10 6-Dec-10 50,272.00 US $ 07/04/2012 Planned ‫مقترح‬ 4-3/ LAH Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works alsameen2 in lahj Post NCB 11-Oct-10 10-Nov-10 10-Nov-10 25-Nov-10 5-Dec-10 11-Apr-11 Actual ‫Ù?علي‬ 25-Oct-10 1-Nov-10 1-Dec-10 1-Dec-10 3-Dec-10 12-Dec-10 57,216.00 US $ 07/04/2012 Planned ‫مقترح‬ 4-4/ LAH Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works ama'een in lahj Post NS 9-Oct-10 23-Oct-10 23-Oct-10 30-Oct-10 15-Nov-10 14-Apr-11 Actual ‫Ù?علي‬ 25-Oct-10 13-Nov-10 29-Nov-10 29-Nov-10 1-Dec-10 15-Dec-10 37,428.00 US $ 07/04/2012 Planned ‫مقترح‬ 4-5/ LAH Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works aljamrk in lahj Post NS 9-Oct-10 23-Oct-10 23-Oct-10 30-Oct-10 15-Nov-10 14-Apr-11 Actual ‫Ù?علي‬ 25-Oct-10 13-Nov-10 29-Nov-10 29-Nov-10 1-Dec-10 15-Dec-10 52,989.00 US $ 07/04/2012 Planned ‫مقترح‬ 4-2/SAN Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works khadar in Sanaa Post NS 1-Feb-11 5-Feb-11 19-Feb-11 19-Feb-11 27-Feb-11 15-Mar-11 24-Jun-11 Actual ‫Ù?علي‬ 27-Feb-11 7-Mar-11 21-Mar-11 21-Mar-11 2-Apr-11 25-Apr-11 9,388.60 US $ 09/19/2011 Planned ‫مقترح‬ 4-3/SAN Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works algadeer in Sanaa Post NS 1-Feb-11 5-Feb-11 19-Feb-11 19-Feb-11 27-Feb-11 15-Mar-11 12-Jul-11 Actual ‫Ù?علي‬ 27-Feb-11 7-Mar-11 21-Mar-11 21-Mar-11 2-Apr-11 13-Apr-11 25,509.72 US $ 27-Jun-11 Planned ‫مقترح‬ 4-5/SAN Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works algeerf in Sanaa Post NS 1-Feb-11 5-Feb-11 19-Feb-11 19-Feb-11 27-Feb-11 15-Mar-11 14-May-11 Actual ‫Ù?علي‬ 27-Feb-11 7-Mar-11 21-Mar-11 21-Mar-11 2-Apr-11 23-May-11 7,702.14 US $ 12/12/2012 Planned ‫مقترح‬ 4-12/ SAN Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works alsahman in Sanaa Post NS 1-Feb-11 5-Feb-11 19-Feb-11 19-Feb-11 27-Feb-11 15-Mar-11 16-Jun-11 Actual ‫Ù?علي‬ 27-Feb-11 7-Mar-11 21-Mar-11 21-Mar-11 2-Apr-11 17-Apr-11 16,720.65 US $ 09/19/2011 Planned ‫مقترح‬ 4-13/ SAN Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works bashar in Sanaa Post NS 1-Feb-11 5-Feb-11 19-Feb-11 19-Feb-11 27-Feb-11 15-Mar-11 16-Jun-11 Actual ‫Ù?علي‬ 27-Feb-11 7-Mar-11 21-Mar-11 21-Mar-11 2-Apr-11 17-Apr-11 8,095.79 US $ Planned ‫مقترح‬ 4-14/ SAN Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works alhagar in Sanaa Post NS 1-Feb-11 5-Feb-11 19-Feb-11 19-Feb-11 27-Feb-11 15-Mar-11 24-Jun-11 Actual ‫Ù?علي‬ 27-Feb-11 7-Mar-11 21-Mar-11 21-Mar-11 2-Apr-11 25-Apr-11 8,090.75 US $ Rashad ALhaj 8/36 ** Applicable in case of Bank's prior review Prequalification No Objection No Objection Bank’s No Bank’s No Name, City, Review from Bank for from Bank for Contract Objection to Bid and Country Goods/ Domestic Preparation of Objection to Expenditure by Bank Method of Prequalifica Draft Evaluation of Bid Invitation Bid Closing Bid Opening Award Evaulation Contract Contract Contract of Completion of Package/ Reference No. Description of Goods Works/ Preference Bid Document Bidding Contract Value Currency No. Contractor Contract (Date) incurred to (Prior/ Selection tion (yes/no) Prequalification Prequalification (Date) (Date) (Date) Decision Report and Signed (Date) Date NCS (yes/no) (Date) Document (incl. Zip Post) documents Application (Date) Contract Award (Date)** Code if US) (Date)** (Date)** (Date)** Planned ‫مقترح‬ 4-3/ MAR /G/RWSS/ Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ WSSP/10 Works rahb al haglan in Mareb Post NS 1-Jan-11 5-Jan-11 19-Jan-11 19-Jan-11 29-Jan-11 14-Feb-11 15-Apr-11 Actual ‫Ù?علي‬ 20-Jan-11 5-Jan-11 18-Jan-11 18-Jan-11 25-Jan-11 5-Feb-11 18,197.00 US $ 07/01/2011 Planned ‫مقترح‬ 4-2/ TAZ Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works al'ameer in taez Post NS 1-Jan-11 5-Jan-11 30-Jan-11 30-Jan-11 7-Feb-11 23-Feb-11 24-Apr-11 Actual ‫Ù?علي‬ 15-Jan-11 18-Jan-11 7-Feb-11 7-Feb-11 15-Feb-11 16-Apr-11 3,155.79 US $ Planned ‫مقترح‬ 4-3/ TAZ Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works alkadsh in taez Post NS 1-Jan-11 5-Jan-11 30-Jan-11 30-Jan-11 7-Feb-11 23-Feb-11 24-Apr-11 Revised1 2-Apr-12 16-Apr-12 16-Apr-12 24-Apr-12 10-May-12 9-Jul-12 Actual ‫Ù?علي‬ 15-Jan-11 18-Jan-11 7-Feb-11 7-Feb-11 15-Feb-11 2-May-11 14,431.33 US $ 07/04/2012 Planned ‫مقترح‬ 4-4/ TAZ Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works bani abeedan in taez Post NS 1-Jan-11 5-Jan-11 30-Jan-11 30-Jan-11 7-Feb-11 23-Feb-11 24-Apr-11 Actual ‫Ù?علي‬ 15-Jan-11 18-Jan-11 7-Feb-11 7-Feb-11 15-Feb-11 4-May-11 7,704.60 US $ 06/17/2012 Planned ‫مقترح‬ 4-5/ TAZ Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works aldol &alkhansr in taez Post NS 1-Jan-11 5-Jan-11 30-Jan-11 30-Jan-11 7-Feb-11 23-Feb-11 24-Apr-11 Actual ‫Ù?علي‬ 15-Jan-11 18-Jan-11 7-Feb-11 7-Feb-11 15-Feb-11 7-Mar-11 29,468.69 US $ 08/09/2012 Planned ‫مقترح‬ 4-6/ TAZ Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works alaza'az in taez Post NS 1-Jan-11 5-Jan-11 30-Jan-11 30-Jan-11 7-Feb-11 23-Feb-11 24-Apr-11 Actual ‫Ù?علي‬ 15-Jan-11 18-Jan-11 7-Feb-11 7-Feb-11 15-Feb-11 2-May-11 5,910.67 US $ 05/06/2012 Planned ‫مقترح‬ 4-7/ TAZ Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works heeb alasabah in taez Post NS 1-Jan-11 5-Jan-11 30-Jan-11 30-Jan-11 7-Feb-11 23-Feb-11 24-Apr-11 Actual ‫Ù?علي‬ 15-Jan-11 18-Jan-11 7-Feb-11 7-Feb-11 15-Feb-11 16-Apr-11 5,985.80 US $ 08/10/2011 Planned ‫مقترح‬ 4-8/ TAZ Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works bani msan in taez Post NS 1-Jan-11 5-Jan-11 30-Jan-11 30-Jan-11 7-Feb-11 23-Feb-11 24-Apr-11 Revised1 2-Apr-12 16-Apr-12 16-Apr-12 24-Apr-12 10-May-12 9-Jul-12 Actual ‫Ù?علي‬ 15-Jan-11 18-Jan-11 7-Feb-11 7-Feb-11 15-Feb-11 23-Apr-11 5,232.93 US $ Planned ‫مقترح‬ 4-9/ TAZ Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works alkhabal in taez Post NS 1-Jan-11 5-Jan-11 30-Jan-11 30-Jan-11 7-Feb-11 23-Feb-11 24-Apr-11 Revised1 2-Apr-12 16-Apr-12 16-Apr-12 24-Apr-12 10-May-12 9-Jul-12 Actual ‫Ù?علي‬ 15-Jan-11 18-Jan-11 7-Feb-11 7-Feb-11 15-Feb-11 2-May-11 26,648.79 US $ Planned ‫مقترح‬ 4-10/ TAZ Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works mayala in taez Post NS 1-Jan-11 5-Jan-11 30-Jan-11 30-Jan-11 7-Feb-11 23-Feb-11 24-Apr-11 Actual ‫Ù?علي‬ 15-Jan-11 18-Jan-11 7-Feb-11 7-Feb-11 15-Feb-11 4-May-11 2,668.13 US $ Planned ‫مقترح‬ 4-11/ TAZ Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works alqreesha in taez Post NS 1-Jan-11 5-Jan-11 30-Jan-11 30-Jan-11 7-Feb-11 23-Feb-11 24-Apr-11 Actual ‫Ù?علي‬ 15-Jan-11 18-Jan-11 7-Feb-11 7-Feb-11 15-Feb-11 16-Apr-11 6,526.02 US $ 08/10/2011 Planned ‫مقترح‬ 4-12/ TAZ Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works alsha'aby in taez Post NS 1-Jan-11 5-Jan-11 30-Jan-11 30-Jan-11 7-Feb-11 23-Feb-11 24-Apr-11 Revised1 2-Apr-12 16-Apr-12 16-Apr-12 24-Apr-12 10-May-12 9-Jul-12 Actual ‫Ù?علي‬ 15-Jan-11 18-Jan-11 7-Feb-11 7-Feb-11 15-Feb-11 2-May-11 3,724.99 US $ 06/18/2012 Planned ‫مقترح‬ 4-13/ TAZ Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works alkadra qadas in taez Post NS 1-Jan-11 5-Jan-11 30-Jan-11 30-Jan-11 7-Feb-11 23-Feb-11 24-Apr-11 Actual ‫Ù?علي‬ 15-Jan-11 18-Jan-11 7-Feb-11 7-Feb-11 15-Feb-11 2-May-11 8,528.02 US $ Planned ‫مقترح‬ 4-14/ TAZ Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works alshareera in taez Post NS 1-Jan-11 5-Jan-11 30-Jan-11 30-Jan-11 7-Feb-11 23-Feb-11 24-Apr-11 Revised1 2-Apr-12 16-Apr-12 16-Apr-12 24-Apr-12 10-May-12 9-Jul-12 Actual ‫Ù?علي‬ 15-Jan-11 18-Jan-11 7-Feb-11 7-Feb-11 15-Feb-11 23-Apr-11 18,624.38 US $ Planned ‫مقترح‬ 4-1/ BYD Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works abiy in al-bedhaa Post NS 9-Oct-10 23-Oct-10 23-Oct-10 26-Dec-10 19-Jan-11 6-Mar-11 Actual ‫Ù?علي‬ 1-Dec-10 11-Dec-10 18-Dec-10 18-Dec-10 3-Jan-11 5-Jan-11 11,708.80 US $ 08/10/2012 Rashad ALhaj 9/36 ** Applicable in case of Bank's prior review Prequalification No Objection No Objection Bank’s No Bank’s No Name, City, Review from Bank for from Bank for Contract Objection to Bid and Country Goods/ Domestic Preparation of Objection to Expenditure by Bank Method of Prequalifica Draft Evaluation of Bid Invitation Bid Closing Bid Opening Award Evaulation Contract Contract Contract of Completion of Package/ Reference No. Description of Goods Works/ Preference Bid Document Bidding Contract Value Currency No. Contractor Contract (Date) incurred to (Prior/ Selection tion (yes/no) Prequalification Prequalification (Date) (Date) (Date) Decision Report and Signed (Date) Date NCS (yes/no) (Date) Document (incl. Zip Post) documents Application (Date) Contract Award (Date)** Code if US) (Date)** (Date)** (Date)** Planned ‫مقترح‬ 4-2/ BYD Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works alshraf in al-bedhaa Post NS 9-Oct-10 23-Oct-10 23-Oct-10 26-Dec-10 19-Jan-11 6-Mar-11 Actual ‫Ù?علي‬ 1-Dec-10 11-Dec-10 18-Dec-10 18-Dec-10 3-Jan-11 5-Jan-11 10,249.50 US $ 08/10/2012 Planned ‫مقترح‬ 4-3/ BYD Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works almagleen in al-bedhaa Post NS 9-Oct-10 23-Oct-10 23-Oct-10 26-Dec-10 19-Jan-11 6-Mar-11 Actual ‫Ù?علي‬ 1-Dec-10 11-Dec-10 18-Dec-10 18-Dec-10 3-Jan-11 5-Jan-11 6,498.50 US $ 08/10/2012 Planned ‫مقترح‬ 4-4/ BYD Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works al alsalal in al-bedhaa Post NS 9-Oct-10 23-Oct-10 23-Oct-10 26-Dec-10 19-Jan-11 6-Mar-11 Actual ‫Ù?علي‬ 1-Dec-10 11-Dec-10 18-Dec-10 18-Dec-10 3-Jan-11 5-Jan-11 19,878.60 US $ 08/10/2012 Planned ‫مقترح‬ 4-5/ BYD Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works almakla in al-bedhaa Post NS 9-Oct-10 23-Oct-10 23-Oct-10 26-Dec-10 19-Jan-11 6-Mar-11 Actual ‫Ù?علي‬ 1-Dec-10 11-Dec-10 18-Dec-10 18-Dec-10 3-Jan-11 5-Jan-11 26,546.90 US $ 08/10/2012 Planned ‫مقترح‬ 4-6/ BYD Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works alkhaf in al-bedhaa Post NS 9-Oct-10 23-Oct-10 23-Oct-10 26-Dec-10 19-Jan-11 6-Mar-11 Actual ‫Ù?علي‬ 1-Dec-10 11-Dec-10 18-Dec-10 18-Dec-10 3-Jan-11 5-Jan-11 19,430.60 US $ 08/10/2012 Planned ‫مقترح‬ 4-7/ BYD Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works almcehar in al-bedhaa Post NS 9-Oct-10 23-Oct-10 23-Oct-10 26-Dec-10 19-Jan-11 6-Mar-11 Actual ‫Ù?علي‬ 1-Dec-10 11-Dec-10 18-Dec-10 18-Dec-10 3-Jan-11 5-Jan-11 17,450.90 US $ 07/09/2012 Planned ‫مقترح‬ 4-8/ BYD Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 /G/RWSS/WSSP/10 Works mahaba in al-bedhaa Revised ‫متوقع‬ Post NCB 11-Oct-10 10-Nov-10 10-Nov-10 3-Jan-11 19-Jan-11 21-Mar-11 Actual ‫Ù?علي‬ 20-Nov-10 26-Nov-10 26-Dec-10 26-Dec-10 3-Jan-11 10-Jan-11 49,376.26 US $ 07/09/2012 Planned ‫مقترح‬ 4-1/ DHL /G/RWSS/ Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ WSSP/10 Works alkadam in aldhale Post NS 19-Dec-10 1-Jan-11 1-Jan-11 7-Jan-11 23-Jan-11 23-Mar-11 Actual ‫Ù?علي‬ 1-Dec-10 20-Dec-10 28-Dec-10 28-Dec-10 2-Jan-11 12-Jan-11 22,384.00 US $ 07/27/2011 Planned ‫مقترح‬ 4-2/ DHL /G/RWSS/ Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ WSSP/10 Works al-lakmah in aldhale Post NS 9-Oct-10 1-Jan-11 3-Jan-11 7-Jan-11 23-Jan-11 23-Mar-11 Actual ‫Ù?علي‬ 1-Dec-10 20-Dec-10 28-Dec-10 28-Dec-10 2-Jan-11 12-Jan-11 17,607.00 US $ 03/23/2012 Planned ‫مقترح‬ 4-3/ DHL /G/RWSS/ Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ WSSP/10 Works hagalan in aldhale Post NS 9-Oct-10 1-Jan-11 3-Jan-11 7-Jan-11 23-Jan-11 23-Mar-11 Actual ‫Ù?علي‬ 1-Dec-10 20-Dec-10 28-Dec-10 28-Dec-10 2-Jan-11 12-Jan-11 13,846.00 US $ 05/05/2012 Planned ‫مقترح‬ 4-4/ DHL /G/RWSS/ Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ WSSP/10 Works algaboba in aldhale Post NS 9-Oct-10 1-Jan-11 3-Jan-11 7-Jan-11 23-Jan-11 23-Mar-11 Actual ‫Ù?علي‬ 1-Dec-10 20-Dec-10 28-Dec-10 28-Dec-10 2-Jan-11 12-Jan-11 17,456.00 US $ 05/09/2012 Planned ‫مقترح‬ 4-5/ DHL /G/RWSS/ Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ WSSP/10 Works altreera in aldhale Post NS 9-Oct-10 1-Jan-11 3-Jan-11 7-Jan-11 23-Jan-11 23-Mar-11 Actual ‫Ù?علي‬ 1-Dec-10 20-Dec-10 28-Dec-10 28-Dec-10 2-Jan-11 12-Jan-11 17,707.00 US $ 06/02/2012 Planned ‫مقترح‬ 4-1/ AMR Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works algadm in amran Post NS 1-Jan-11 15-Jan-11 5-Feb-11 5-Feb-11 15-Feb-11 3-Mar-11 2-May-11 Actual ‫Ù?علي‬ 15-Jan-11 22-Jan-11 8-Feb-11 8-Feb-11 20-Feb-11 5-Mar-11 18,935.05 US $ 11/19/2011 Planned ‫مقترح‬ 4-2/ AMR Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works alaqeely in amran Post NS 1-Jan-11 15-Jan-11 5-Feb-11 5-Feb-11 15-Feb-11 3-Mar-11 2-May-11 Actual ‫Ù?علي‬ 15-Jan-11 22-Jan-11 8-Feb-11 8-Feb-11 20-Feb-11 5-Mar-11 14,059.81 US $ 11/19/2011 Planned ‫مقترح‬ 4-4/ AMR Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works alswadeen in amran Post NS 1-Jan-11 15-Jan-11 5-Feb-11 5-Feb-11 15-Feb-11 3-Mar-11 2-May-11 Actual ‫Ù?علي‬ 15-Jan-11 22-Jan-11 8-Feb-11 8-Feb-11 20-Feb-11 23-Mar-11 11,918.93 US $ 07/27/2011 Planned ‫مقترح‬ 4-5/ AMR Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works alafry in amran Post NS 1-Jan-11 15-Jan-11 5-Feb-11 5-Feb-11 15-Feb-11 3-Mar-11 2-May-11 Actual ‫Ù?علي‬ 15-Jan-11 22-Jan-11 8-Feb-11 8-Feb-11 20-Feb-11 5-Mar-11 9,266.82 US $ Planned ‫مقترح‬ 4-7/ AMR Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works beet alman in amran Post NS 1-Jan-11 15-Jan-11 5-Feb-11 5-Feb-11 15-Feb-11 3-Mar-11 2-May-11 Actual ‫Ù?علي‬ 15-Jan-11 22-Jan-11 8-Feb-11 8-Feb-11 20-Feb-11 5-Mar-11 5,332.94 US $ 11/06/2011 Planned ‫مقترح‬ 4-9/ AMR Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works bani abd in amran Post NS 1-Jan-11 15-Jan-11 5-Feb-11 5-Feb-11 15-Feb-11 3-Mar-11 2-May-11 Actual ‫Ù?علي‬ 15-Jan-11 22-Jan-11 8-Feb-11 8-Feb-11 20-Feb-11 5-Mar-11 16,228.27 Planned ‫مقترح‬ 4-1/ RYM Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works almahamal in ryimah Post NS 30-Jan-11 5-Feb-11 19-Feb-11 19-Feb-11 1-Mar-11 17-Mar-11 1-Jun-11 Actual ‫Ù?علي‬ 30-Jan-11 12-Feb-11 26-Feb-11 26-Feb-11 15-Mar-11 2-Apr-11 16,091.33 US $ 08/28/2012 Planned ‫مقترح‬ 4-2/ RYM Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works wadi seer in ryimah Post NS 30-Jan-11 5-Feb-11 19-Feb-11 19-Feb-11 1-Mar-11 17-Mar-11 1-Jun-11 Actual ‫Ù?علي‬ 30-Jan-11 12-Feb-11 26-Feb-11 26-Feb-11 15-Mar-11 2-Apr-11 15,217.61 US $ 03/17/2012 Planned ‫مقترح‬ 4-3/ RYM Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works bani asd&reem in ryimah Post NCB 30-Jan-11 12-Feb-11 14-Mar-11 14-Mar-11 22-Mar-11 7-Apr-11 28-Sep-11 Actual ‫Ù?علي‬ 30-Jan-11 27-Mar-11 26-Apr-11 26-Apr-11 15-May-11 31-May-11 193,467.72 US $ Planned ‫مقترح‬ 4-4/ RYM Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works asfal mzar in ryimah Post NS 30-Jan-11 5-Feb-11 19-Feb-11 19-Feb-11 27-Feb-11 15-Mar-11 1-Jun-11 Actual ‫Ù?علي‬ 30-Jan-11 12-Feb-11 26-Feb-11 26-Feb-11 15-Mar-11 2-Apr-11 17,855.24 US $ 03/19/2012 Planned ‫مقترح‬ 4-2/ DHM Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works alhmr in thamar Post NS 9-Oct-10 1-Jan-11 1-Jan-11 11-Jan-11 8-Feb-11 9-Apr-11 Actual ‫Ù?علي‬ 5-Dec-10 18-Dec-10 3-Jan-11 3-Jan-11 23-Jan-11 7-Feb-11 2,385.51 US $ 02/07/2011 Planned ‫مقترح‬ 4-3/ DHM Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works bani ahmed in thamar Post NS 9-Oct-10 1-Jan-11 1-Jan-11 11-Jan-11 8-Feb-11 9-Apr-11 Actual ‫Ù?علي‬ 5-Dec-10 18-Dec-10 3-Jan-11 3-Jan-11 23-Jan-11 7-Feb-11 4,637.02 US $ Planned ‫مقترح‬ 4-4/ DHM Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works yafah in thamar Post NS 9-Oct-10 1-Jan-11 1-Jan-11 11-Jan-11 8-Feb-11 9-Apr-11 Actual ‫Ù?علي‬ 5-Dec-10 18-Dec-10 3-Jan-11 3-Jan-11 23-Jan-11 7-Feb-11 5,691.68 US $ 07/04/2012 Planned ‫مقترح‬ 4-5/ DHM Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works wathan in thamar Post NS 9-Oct-10 1-Jan-11 1-Jan-11 11-Jan-11 8-Feb-11 9-Apr-11 Actual ‫Ù?علي‬ Rashad ALhaj 5-Dec-10 10/36 18-Dec-10 3-Jan-11 3-Jan-11 23-Jan-11 7-Feb-11 3,850.47 US $ 10/01/2011 ** Applicable in case of Bank's prior review Prequalification No Objection No Objection Bank’s No Bank’s No Name, City, Review from Bank for from Bank for Contract Objection to Bid and Country Goods/ Domestic Preparation of Objection to Expenditure by Bank Method of Prequalifica Draft Evaluation of Bid Invitation Bid Closing Bid Opening Award Evaulation Contract Contract Contract of Completion of Package/ Reference No. Description of Goods Works/ Preference Bid Document Bidding Contract Value Currency No. Contractor Contract (Date) incurred to (Prior/ Selection tion (yes/no) Prequalification Prequalification (Date) (Date) (Date) Decision Report and Signed (Date) Date NCS (yes/no) (Date) Document (incl. Zip Post) documents Application (Date) Contract Award (Date)** Code if US) (Date)** (Date)** (Date)** Planned ‫مقترح‬ 4-6/ DHM Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works rabat amran in thamar Post NS 9-Oct-10 1-Jan-11 1-Jan-11 11-Jan-11 8-Feb-11 9-Apr-11 Actual ‫Ù?علي‬ 5-Dec-10 18-Dec-10 3-Jan-11 3-Jan-11 23-Jan-11 7-Feb-11 1,729.00 US $ 10/01/2011 Planned ‫مقترح‬ 4-7/ DHM Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works ftayl in thamar Post NS 9-Oct-10 1-Jan-11 1-Jan-11 11-Jan-11 8-Feb-11 9-Apr-11 Actual ‫Ù?علي‬ 5-Dec-10 18-Dec-10 3-Jan-11 3-Jan-11 23-Jan-11 7-Feb-11 2,192.00 US $ 10/01/2011 Planned ‫مقترح‬ 4-8/ DHM Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works hagrah sabeel in thamar Post NS 9-Oct-10 1-Jan-11 1-Jan-11 11-Jan-11 8-Feb-11 9-Apr-11 Actual ‫Ù?علي‬ 5-Dec-10 18-Dec-10 3-Jan-11 3-Jan-11 23-Jan-11 7-Feb-11 4,635.89 US $ 03/28/2012 Planned ‫مقترح‬ 4-9/ DHM Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works altalha in thamar Post NS 9-Oct-10 1-Jan-11 1-Jan-11 11-Jan-11 8-Feb-11 9-Apr-11 Actual ‫Ù?علي‬ 5-Dec-10 18-Dec-10 3-Jan-11 3-Jan-11 23-Jan-11 7-Feb-11 2,810.75 US $ 06/25/2012 Planned ‫مقترح‬ 4-10/ DHM Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works alkmeem in thamar Post NS 9-Oct-10 1-Jan-11 1-Jan-11 11-Jan-11 8-Feb-11 9-Apr-11 Actual ‫Ù?علي‬ 5-Dec-10 18-Dec-10 3-Jan-11 3-Jan-11 23-Jan-11 7-Feb-11 1,840.61 06/17/2011 Planned ‫مقترح‬ 4-11/ DHM Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works almatahn in thamar Post NS 9-Oct-10 1-Jan-11 1-Jan-11 11-Jan-11 8-Feb-11 9-Apr-11 Actual ‫Ù?علي‬ 5-Dec-10 18-Dec-10 3-Jan-11 3-Jan-11 23-Jan-11 7-Feb-11 4,142.00 US $ 06/17/2011 Planned ‫مقترح‬ 4-12/ DHM Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works ahlal in thamar Post NS 9-Oct-10 1-Jan-11 1-Jan-11 11-Jan-11 8-Feb-11 9-Apr-11 Actual ‫Ù?علي‬ 5-Dec-10 18-Dec-10 3-Jan-11 3-Jan-11 23-Jan-11 7-Feb-11 1,792.64 US $ 06/11/2011 Planned ‫مقترح‬ 4-13/ DHM Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works alshmah in thamar Post NS 9-Oct-10 1-Jan-11 1-Jan-11 11-Jan-11 8-Feb-11 9-Apr-11 Actual ‫Ù?علي‬ 5-Dec-10 18-Dec-10 3-Jan-11 3-Jan-11 23-Jan-11 6-Feb-11 4,342.67 US $ 04/26/2011 Rashad ALhaj 11/36 ** Applicable in case of Bank's prior review Prequalification No Objection No Objection Bank’s No Bank’s No Name, City, Review from Bank for from Bank for Contract Objection to Bid and Country Goods/ Domestic Preparation of Objection to Expenditure by Bank Method of Prequalifica Draft Evaluation of Bid Invitation Bid Closing Bid Opening Award Evaulation Contract Contract Contract of Completion of Package/ Reference No. Description of Goods Works/ Preference Bid Document Bidding Contract Value Currency No. Contractor Contract (Date) incurred to (Prior/ Selection tion (yes/no) Prequalification Prequalification (Date) (Date) (Date) Decision Report and Signed (Date) Date NCS (yes/no) (Date) Document (incl. Zip Post) documents Application (Date) Contract Award (Date)** Code if US) (Date)** (Date)** (Date)** Planned ‫مقترح‬ 4-14/ DHM Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works alsanam in thamar Post NS 9-Oct-10 1-Jan-11 1-Jan-11 11-Jan-11 8-Feb-11 9-Apr-11 Actual ‫Ù?علي‬ 5-Dec-10 18-Dec-10 3-Jan-11 3-Jan-11 23-Jan-11 21-Mar-11 1,845.40 US $ 04/26/2011 Planned ‫مقترح‬ 4-15/ DHM Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works zaragah in thamar Post NS 9-Oct-10 1-Jan-11 1-Jan-11 11-Jan-11 8-Feb-11 9-Apr-11 Actual ‫Ù?علي‬ 5-Dec-10 18-Dec-10 3-Jan-11 3-Jan-11 23-Jan-11 7-Feb-11 4,039.89 US $ 05/17/2011 Planned ‫مقترح‬ 4-16/ DHM Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works kalba alaqar in thamar Post NS 9-Oct-10 1-Jan-11 1-Jan-11 11-Jan-11 8-Feb-11 9-Apr-11 Actual ‫Ù?علي‬ 5-Dec-10 18-Dec-10 3-Jan-11 3-Jan-11 23-Jan-11 7-Feb-11 5,058.04 US $ Planned ‫مقترح‬ 3/ SAD works of tank in saada Works Post NCB No No NA NA 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 ‫مطري‬ 29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 30-Aug-10 + ‫عيبان‬ 15-Feb-11 Actual ‫Ù?علي‬ 1-Feb-10 3-Apr-10 1-May-10 5-May-10 24-Jun-10 25-Jul-10 70,938.93 US $ ‫Ù?ارع‬ 06/28/2012 Planned ‫مقترح‬ 3/ MAR /G/RWSS/ works of tank in Mareb Works Post NCB No No NA NA 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 Revised ‫متوقع‬ WSSP/10 Post NCB No No 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 7-Jun-10 Actual ‫Ù?علي‬ 1-Feb-10 3-Mar-10 28-Mar-10 3-Apr-10 25-Apr-10 10-May-10 36,564.95 US $ ‫مانع عجالن‬ 07/24/2012 Planned ‫مقترح‬ 3/ SHB works of tank in Shabwa Works Post NCB No No NA NA 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 ‫مكتب‬ 29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Post NCB No No 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 7-Jun-10 ‫محمد‬ 1-Mar-11 Actual ‫Ù?علي‬ 1-Feb-10 28-Feb-10 28-Mar-10 4-Apr-10 27-Apr-00 5-Jun-10 77,454.67 US $ ‫الزعتري‬ Planned ‫مقترح‬ 3/ TAZ works of tank in taez Works Post NCB No No NA NA 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 ‫مبارك‬ 29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Post NCB No No ‫الزرقه‬ 1-Mar-11 Actual ‫Ù?علي‬ 1-Feb-10 8-Mar-10 5-Apr-10 10-Apr-10 10-May-10 29-May-10 64,376.17 US $ ‫وعبدالحق‬ 06/17/2012 Planned ‫مقترح‬ 3/ ABN works of tank in Abyan Works Post NCB No No NA NA 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Post NCB No No 1-Mar-10 25-Mar-10 30-Mar-10 3-May-10 7-Jun-10 1-Mar-11 Actual ‫Ù?علي‬ 1-Feb-10 25-Mar-10 19-Apr-10 24-Apr-10 20-Oct-10 26,779.67 US $ 14-Mar-11 Planned ‫مقترح‬ 3/ HAD works of tank in moklla Works Post NCB No No NA NA 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 ‫عوض‬ Revised ‫متوقع‬ /G/RWSS/WSSP/10 Post NCB No No 1-Mar-10 25-Mar-10 30-Mar-10 3-May-10 7-Jun-10 1-Mar-11 ‫السومحي‬ Actual ‫Ù?علي‬ 1-Feb-10 22-Mar-10 15-Apr-10 21-Apr-10 10-May-10 27-May-10 113,032.24 US $ Planned ‫مقترح‬ 3/ DHL /G/RWSS/ works of tank in aldhale Works Post NCB No No NA NA 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 ‫Ù?ضل محمد‬ Revised ‫متوقع‬ WSSP/10 Post NCB No No 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 7-Jun-10 ‫مساعد‬ Actual ‫Ù?علي‬ 1-Feb-10 21-Feb-10 16-Mar-10 21-Mar-10 4-Apr-10 27-Apr-10 68,405.19 US $ 1-Nov-10 Planned ‫مقترح‬ 3/ AMR works of tank in amran Works Post NCB No No NA NA 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Post NCB No No 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 7-Jun-10 1-Mar-11 Actual ‫Ù?علي‬ 1-Feb-10 1-Mar-10 26-Mar-10 31-Mar-10 10-May-10 29/05&1/8/2010 448,694.77 US $ 10/04/2011 Planned ‫مقترح‬ 3/ RYM works of tank in ryimah Works Post NCB No No NA NA 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 ‫قائد محمد‬ Revised ‫متوقع‬ /G/RWSS/WSSP/10 Post NCB No No 1-Mar-10 25-Mar-10 30-Mar-10 3-May-10 7-Jun-10 1-Mar-11 ‫علي المالكي‬ Actual ‫Ù?علي‬ 1-Feb-10 11-Mar-10 5-Apr-10 10-Apr-10 3-May-10 28-Jul-10 242,690.42 US $ 03/21/2012 Planned ‫مقترح‬ 3/ MAH works of tank in al-mahra Works Post NCB No No NA NA 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 ‫ صالح ابو‬29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 ‫زيد و‬ 1-Mar-11 Actual ‫Ù?علي‬ 1-Feb-10 18-Apr-10 18-May-10 18-May-10 25-May-10 9-Jun-10 18,852.00 US $ ‫ محمد بن‬03/21/2012 Planned ‫مقترح‬ 3/ HQ works ofBuildings in al-jowf Works Post NCB No No NA NA 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 /CW/RWSS/WSSP/10 ‫يوسÙ?‬ Revised ‫متوقع‬ 18-Jul-11 ‫الصنعاني‬ Actual ‫Ù?علي‬ 1-Feb-10 9-Apr-10 19-May-10 24-May-10 1-Jul-10 18-Jul-10 271,684.74 US $ Planned ‫مقترح‬ *4/ HQ works ofBuildings in al mahra Works Post NCB No No NA NA 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 /CW/RWSS/WSSP/10 ‫مؤسسة‬ Revised ‫متوقع‬ 18-Jul-11 ‫التميمي‬ Actual ‫Ù?علي‬ 1-Feb-10 9-Apr-10 19-May-10 24-May-10 1-Jul-10 31-Jul-10 368,792.55 US $ Planned ‫مقترح‬ **1/HQ /G/RWSS/ Goods of Tools and materials Goods Post NCB No No NA NA 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 Revised ‫متوقع‬ WSSP/10 laboratory in HQ 1-Sep-10 30-Sep-10 30-Sep-10 15-Oct-10 30-Oct-10 23-Jan-11 Actual ‫Ù?علي‬ 1-Feb-10 18-Aug-10 18-Sep-10 18-Sep-10 15-Oct-10 25-Oct-10 254,424.00 US $ 12-Jan-11 Planned ‫مقترح‬ 3/ IBB /G/RWSS/ works of tank in Ibb Works Post NCB No No NA NA 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 Revised ‫متوقع‬ WSSP/10 1-Mar-11 Actual ‫Ù?علي‬ 1-Feb-10 1-Mar-10 25-Mar-10 30-Mar-10 18-Apr-10 11-May-10 91,021.12 US $ 12/25/2011 Planned ‫مقترح‬ 3/HAJ /G/RWSS/ works of tank in Haja Works Post NCB No No NA NA 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 ‫القدمي‬ 29-Sep-10 Revised ‫متوقع‬ WSSP/10 ‫ للمقاوالت‬1-Mar-11 Actual ‫Ù?علي‬ 1-Feb-10 22-Feb-10 17-Mar-10 23-Mar-10 20-Apr-10 12-May-10 71,152.06 US $ ‫ Ùˆ احمد‬05/20/2012 Planned ‫مقترح‬ 3/DHM /G/RWSS/ works of tank in thamar Works Post NCB No No NA NA 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 Revised ‫متوقع‬ WSSP/10 ‫ عبدالخالق‬1-Mar-11 Actual ‫Ù?علي‬ 1-Feb-10 1-Jun-10 25-Jun-10 30-Jun-10 1-May-10 31-May-10 11,583.79 US $ ‫ المعانسي‬05/20/2012 Planned ‫مقترح‬ 3/LAH /G/RWSS/ works of tank in lahj Works Post NCB No No NA NA 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 ‫جلوي‬ 29-Sep-10 Revised ‫متوقع‬ WSSP/10 ‫عبداهلل‬ 1-Mar-11 Actual ‫Ù?علي‬ 1-Feb-10 18-Feb-10 15-Mar-10 20-Mar-10 2-Apr-10 25-Apr-10 54,335.28 US $ ‫ناصر‬ 03/06/2012 Planned ‫مقترح‬ 3/SAN /G/RWSS/ works of tank in sanaa Works Post NCB No No NA NA 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 Revised ‫متوقع‬ WSSP/10 1-Mar-11 Actual ‫Ù?علي‬ 5-Mar-10 1-Feb-10 20-Mar-10 14-Apr-10 19-Apr-10 24-May-10 13-Jul-10 71,726.62 US $ 01/01/2012 Planned ‫مقترح‬ 3/BYD /G/RWSS/ works of tank in al-bedhaa Works Post NCB No No NA NA 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 Revised ‫متوقع‬ WSSP/10 ‫ علي هادي‬1-Mar-11 Actual ‫Ù?علي‬ 1-Feb-10 11-Mar-10 5-Apr-10 10-Apr-10 20-Apr-10 26-Apr-10 62,560.75 US $ ‫ الزعكري‬15-Mar-12 Planned ‫مقترح‬ 5/ TAZ works of wells in taez Works Post NCB No No NA NA 6-Feb-10 21-Feb-10 1-May-10 26-May-10 1-Jun-10 1-Jul-10 19-Jul-10 10-Aug-10 ‫ مهدي راشد‬29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 ‫أبو علي و‬ Actual ‫Ù?علي‬ 5-Mar-10 8-Mar-10 5-Apr-10 10-Apr-10 19-May-10 9-Jun-10 200,849.37 US $ ‫ علي غالب‬15-Jan-11 Rashad ALhaj 12/36 ** Applicable in case of Bank's prior review Prequalification No Objection No Objection Bank’s No Bank’s No Name, City, Review from Bank for from Bank for Contract Objection to Bid and Country Goods/ Domestic Preparation of Objection to Expenditure by Bank Method of Prequalifica Draft Evaluation of Bid Invitation Bid Closing Bid Opening Award Evaulation Contract Contract Contract of Completion of Package/ Reference No. Description of Goods Works/ Preference Bid Document Bidding Contract Value Currency No. Contractor Contract (Date) incurred to (Prior/ Selection tion (yes/no) Prequalification Prequalification (Date) (Date) (Date) Decision Report and Signed (Date) Date NCS (yes/no) (Date) Document (incl. Zip Post) documents Application (Date) Contract Award (Date)** Code if US) (Date)** (Date)** (Date)** Planned ‫مقترح‬ * 5/SAN /G/RWSS/ works of wells in sanaa Works Post NCB No No NA NA 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 Revised ‫متوقع‬ WSSP/10 Post NCB No No 1-Mar-11 Actual ‫Ù?علي‬ 5-Apr-10 22-Apr-10 15-Apr-10 21-Apr-10 26-May-10 30-Jun-10 313,010.91 US $ 1-Apr-11 Planned ‫مقترح‬ 5/ AMR works of wells for (13) Works Post NCB No No NA NA 6-Feb-10 21-Feb-10 1-May-10 26-May-10 1-Jun-10 1-Jul-10 19-Jul-10 10-Aug-10 29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 contracts in amran 1-Mar-11 Actual ‫Ù?علي‬ 5-Mar-10 1-Mar-10 26-Mar-10 31-Mar-10 12-May-10 20/6&9/8/2010 639,105.58 US $ 14-Jan-11 Planned ‫مقترح‬ 5/ HAD works of wells in moklla Works Post NCB No No NA NA 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 15-Aug-10 9-Oct-10 2-Feb-11 Actual ‫Ù?علي‬ 5-Apr-10 28-Apr-10 18-May-10 23-May-10 28-Aug-10 3-Oct-10 85,763.89 US $ 1-Jan-11 Planned ‫مقترح‬ 5/ SAD works of wells in saada Works Post NCB No No NA NA 6-Feb-10 1-May-10 26-May-10 1-Jun-10 1-Jul-10 10-Aug-10 29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Post NCB No No 1-Jan-11 17-Jan-11 18-Mar-11 Actual ‫Ù?علي‬ 5-Aug-10 1-Sep-10 1-Oct-10 1-Oct-10 2-Jan-11 15-Jan-11 65,500.00 US $ 07/18/2012 Planned ‫مقترح‬ 5/ MAH works of wells in Mahaweet Works Post NCB No No NA NA 30-May-10 21-Feb-10 1-May-10 26-May-10 1-Jun-10 1-Jul-10 19-Jul-10 10-Aug-10 29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Post NS No No 9-Oct-10 18-Oct-10 18-Oct-10 5-Oct-10 15-Oct-10 1-Feb-11 Actual ‫Ù?علي‬ 5-Aug-10 1-Oct-10 11-Oct-10 11-Oct-10 19-Oct-10 3-Nov-10 43,256.31 US $ 07/13/2011 Planned ‫مقترح‬ 5/ MAH works of wells in al-mahra Works Post NCB No No NA NA 6-Feb-10 21-Feb-10 1-May-10 26-May-10 1-Jun-10 1-Jul-10 19-Jul-10 10-Aug-10 ‫باسعد‬ 29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 15-Aug-10 30-Aug-10 ‫للمقاوالت‬ 1-Mar-11 Actual ‫Ù?علي‬ 5-Apr-10 9-Jun-10 2-Jul-10 6-Jul-10 1-Aug-10 18-Aug-10 109,815.00 US $ 07/13/2011 Planned ‫مقترح‬ 5/ JWF works of wells in al-jowf Works Post NCB No No NA NA 6-Feb-10 21-Feb-10 1-May-10 26-May-10 1-Jun-10 1-Jul-10 19-Jul-10 10-Aug-10 ‫ علي هادي‬29-Sep-10 Revised ‫متوقع‬ /CW/RWSS/WSSP/10 NS 20-Aug-10 ‫العكص‬ 1-Mar-11 Actual ‫Ù?علي‬ 5-Apr-10 9-May-10 4-Jun-10 9-Jun-10 24-Jul-10 11-Aug-10 188,932.90 US $ 12/30/2012 Rashad ALhaj 13/36 ** Applicable in case of Bank's prior review Prequalification No Objection No Objection Bank’s No Bank’s No Name, City, Review from Bank for from Bank for Contract Objection to Bid and Country Goods/ Domestic Preparation of Objection to Expenditure by Bank Method of Prequalifica Draft Evaluation of Bid Invitation Bid Closing Bid Opening Award Evaulation Contract Contract Contract of Completion of Package/ Reference No. Description of Goods Works/ Preference Bid Document Bidding Contract Value Currency No. Contractor Contract (Date) incurred to (Prior/ Selection tion (yes/no) Prequalification Prequalification (Date) (Date) (Date) Decision Report and Signed (Date) Date NCS (yes/no) (Date) Document (incl. Zip Post) documents Application (Date) Contract Award (Date)** Code if US) (Date)** (Date)** (Date)** Planned ‫مقترح‬ 1/ DHL /G/RWSS/ Procurement of pipes and Goods Post NCB No No NA NA 25-Jan-11 5-Feb-11 7-Mar-11 7-Mar-11 22-Mar-11 9-Apr-11 9-Jul-11 Revised ‫متوقع‬ Actual ‫Ù?علي‬ WSSP/11 fittings in aldhale 30-Jan-11 26-Jan-11 26-Feb-11 26-Feb-11 2-Mar-11 4-Apr-11 444,989.50 US $ 15-Dec-12 Planned ‫مقترح‬ 1/ RYM Procurement of pipes and Goods Post NCB No No NA NA 25-Jan-11 5-Feb-11 7-Mar-11 7-Mar-11 22-Mar-11 9-Apr-11 9-Jul-11 Revised ‫متوقع‬ /G/RWSS/WSSP/11 fittings in ryimah Actual ‫Ù?علي‬ 25-Jan-11 3-Feb-11 5-Mar-11 5-Mar-11 6-May-11 26-May-11 356,315.00 US $ 15-Dec-12 Planned ‫مقترح‬ 2/ MAH Procurement of pumps and Goods Post NCB No No NA NA 25-Jan-11 5-Feb-11 7-Mar-11 7-Mar-11 22-Mar-11 9-Apr-11 9-Jul-11 Revised ‫متوقع‬ /G/RWSS/WSSP/11 accessories in Mahaweet 24-Sep-11 Actual ‫Ù?علي‬ 30-Jan-11 5-Feb-11 7-Mar-11 7-Mar-11 19-Mar-11 27-Apr-11 202,303.18 us $ Planned ‫مقترح‬ 2/ DHL /G/RWSS/ Procurement of pumps and Goods Post NCB No No NA NA 25-Jan-11 5-Feb-11 7-Mar-11 7-Mar-11 22-Mar-11 9-Apr-11 9-Jul-11 Revised ‫متوقع‬ WSSP/11 accessories in aldhale Actual ‫Ù?علي‬ 30-Jan-11 26-Jan-11 26-Feb-11 26-Feb-11 2-Mar-11 20-Apr-11 161,356.52 US $ 07/12/2011 Planned ‫مقترح‬ 2/ MAH Procurement of pumps and Goods Post NCB No No NA NA 25-Jan-11 5-Feb-11 7-Mar-11 7-Mar-11 22-Mar-11 9-Apr-11 9-Jul-11 Revised ‫متوقع‬ /G/RWSS/WSSP/11 accessories in Al-mahra 21-Jun-12 21-Jul-12 21-Jul-12 15-Aug-12 30-Aug-12 28-Nov-12 Actual ‫Ù?علي‬ 30-Jan-11 2-Feb-11 5-Mar-11 5-Mar-11 16-Mar-11 9-May-12 147,800.00 07/05/2012 Rashad ALhaj 14/36 ** Applicable in case of Bank's prior review Prequalification No Objection No Objection Bank’s No Bank’s No Name, City, Review from Bank for from Bank for Contract Objection to Bid and Country Goods/ Domestic Preparation of Objection to Expenditure by Bank Method of Prequalifica Draft Evaluation of Bid Invitation Bid Closing Bid Opening Award Evaulation Contract Contract Contract of Completion of Package/ Reference No. Description of Goods Works/ Preference Bid Document Bidding Contract Value Currency No. Contractor Contract (Date) incurred to (Prior/ Selection tion (yes/no) Prequalification Prequalification (Date) (Date) (Date) Decision Report and Signed (Date) Date NCS (yes/no) (Date) Document (incl. Zip Post) documents Application (Date) Contract Award (Date)** Code if US) (Date)** (Date)** (Date)** Planned ‫مقترح‬ 3/ MAH Civil Works of tank of tank Works Post NCB No No NA NA 25-Jan-11 5-Feb-11 7-Mar-11 7-Mar-11 22-Mar-11 9-Apr-11 9-Jul-11 Revised ‫متوقع‬ /CW/RWSS/WSSP/11 in Mahaweet Actual ‫Ù?علي‬ 30-Jan-11 6-Feb-11 8-Mar-11 8-Mar-11 28-Mar-11 17-Apr-11 43,338.79 US $ Planned ‫مقترح‬ 3/ LAH Civil Works of tank in lahj Works Post NCB No No NA NA 25-Jan-11 5-Feb-11 7-Mar-11 7-Mar-11 22-Mar-11 9-Apr-11 9-Jul-11 Revised ‫متوقع‬ /CW/RWSS/WSSP/11 Actual ‫Ù?علي‬ 30-Jan-11 8-Feb-11 12-Mar-11 12-Mar-11 8-Apr-11 22-Apr-11 84,410.00 US $ Planned ‫مقترح‬ 3/ TAZ Civil Works of tank in taez Works Post NCB No No NA NA 25-Jan-11 5-Feb-11 7-Mar-11 7-Mar-11 22-Mar-11 9-Apr-11 9-Jul-11 Revised ‫متوقع‬ /CW/RWSS/WSSP/11 11-Aug-11 Actual ‫Ù?علي‬ 28-Jan-11 31-Jan-11 5-Mar-11 5-Mar-11 15-Apr-11 13-May-11 58,428.74 US $ 05/02/2012 Planned ‫مقترح‬ 3/ IBB Civil Works of tank in Ibb Works Post NCB No No NA NA 25-Jan-11 5-Feb-11 7-Mar-11 7-Mar-11 22-Mar-11 9-Apr-11 9-Jul-11 Revised ‫متوقع‬ /CW/RWSS/WSSP/11 Actual ‫Ù?علي‬ 30-Jan-11 3-Feb-11 5-Mar-11 5-Mar-11 28-Mar-11 11-Apr-11 28,221.00 US $ Planned ‫مقترح‬ 3/ DHL /CW/RWSS/ Civil Works of tank in Works Post NCB No No NA NA 25-Jan-11 5-Feb-11 7-Mar-11 7-Mar-11 22-Mar-11 9-Apr-11 9-Jul-11 Revised ‫متوقع‬ WSSP/11 aldhale Actual ‫Ù?علي‬ 30-Jan-11 26-Jan-11 26-Feb-11 26-Feb-11 2-Mar-11 3-Mar-11 118,988.79 US $ 04/10/2011 Planned ‫مقترح‬ 3/ AMR Civil Works of tank in amran Works Post NCB No No NA NA 25-Jan-11 5-Feb-11 7-Mar-11 7-Mar-11 22-Mar-11 9-Apr-11 9-Jul-11 Revised ‫متوقع‬ /CW/RWSS/WSSP/11 Actual ‫Ù?علي‬ 25-Jan-11 30-Jan-11 1-Mar-11 1-Mar-11 13-Mar-11 14-May-11 298,276.06 US $ Planned ‫مقترح‬ 3/ RYM Civil Works of tank in Works Post NCB No No NA NA 25-Jan-11 12-Feb-11 14-Mar-11 14-Mar-11 29-Mar-11 16-Apr-11 16-Jul-11 Revised ‫متوقع‬ /CW/RWSS/WSSP/11 ryimah Actual ‫Ù?علي‬ 30-Jan-11 3-Feb-11 5-Mar-11 5-Mar-11 20-Mar-11 9-Apr-11 86,280.37 US $ Rashad ALhaj 15/36 ** Applicable in case of Bank's prior review Prequalification No Objection No Objection Bank’s No Bank’s No Name, City, Review from Bank for from Bank for Contract Objection to Bid and Country Goods/ Domestic Preparation of Objection to Expenditure by Bank Method of Prequalifica Draft Evaluation of Bid Invitation Bid Closing Bid Opening Award Evaulation Contract Contract Contract of Completion of Package/ Reference No. Description of Goods Works/ Preference Bid Document Bidding Contract Value Currency No. Contractor Contract (Date) incurred to (Prior/ Selection tion (yes/no) Prequalification Prequalification (Date) (Date) (Date) Decision Report and Signed (Date) Date NCS (yes/no) (Date) Document (incl. Zip Post) documents Application (Date) Contract Award (Date)** Code if US) (Date)** (Date)** (Date)** Planned ‫مقترح‬ 4/ SAD Civil Works of Wells in saada Works Post NCB No No NA NA 30-Jan-11 5-Feb-11 7-Mar-11 7-Mar-11 22-Mar-11 9-Apr-11 8-Jul-11 Revised ‫متوقع‬ /CW/RWSS/WSSP/11 30-Mar-00 Actual ‫Ù?علي‬ 20-Feb-11 27-Feb-11 27-Mar-11 27-Mar-11 4-Apr-11 4-May-11 153,488.00 US $ 07/08/2011 Planned ‫مقترح‬ 4/ LAH Civil Works of Wells in lahj Works Post NCB No No NA NA 30-Jan-11 5-Feb-11 7-Mar-11 7-Mar-11 22-Mar-11 9-Apr-11 8-Jul-11 Revised ‫متوقع‬ /CW/RWSS/WSSP/11 Actual ‫Ù?علي‬ 30-Jan-11 8-Feb-11 12-Mar-11 12-Mar-11 22-Mar-11 25-May-11 184,092.00 US $ 08/30/2012 Planned ‫مقترح‬ 4/ HAD Civil Works of Wells in Works Post NCB No No NA NA 30-Jan-11 5-Feb-11 7-Mar-11 7-Mar-11 22-Mar-11 9-Apr-11 8-Jul-11 Revised ‫متوقع‬ /CW/RWSS/WSSP/11 Hadramout Actual ‫Ù?علي‬ 30-Jan-11 7-Feb-11 7-Mar-11 7-Mar-11 14-Mar-11 4-Apr-11 117,243.00 US $ 08/30/2012 Planned ‫مقترح‬ 4/ AMR Civil Works of Wells in Works Post NCB No No NA NA 30-Jan-11 5-Feb-11 7-Mar-11 7-Mar-11 22-Mar-11 9-Apr-11 8-Jul-11 Revised ‫متوقع‬ /CW/RWSS/WSSP/11 amran 30-Mar-00 Actual ‫Ù?علي‬ 25-Jan-11 28-Jan-11 26-Feb-11 26-Feb-11 15-Jun-11 15-Jul-11 142,970.00 US $ 10/01/2011 Planned ‫مقترح‬ 7/ AMR Civil Works of in amran Works Post NCB No No NA NA 30-Jan-11 5-Feb-11 7-Mar-11 7-Mar-11 22-Mar-11 9-Apr-11 8-Jul-11 Revised ‫متوقع‬ /G/RWSS/WSSP/11 19-Jan-12 Actual ‫Ù?علي‬ 24-Apr-11 23-May-11 23-May-11 20-Jun-11 23-Jul-11 128,000.00 US$ Rashad ALhaj 16/36 ** Applicable in case of Bank's prior review Prequalification No Objection No Objection Bank’s No Bank’s No Name, City, Review from Bank for from Bank for Contract Objection to Bid and Country Goods/ Domestic Preparation of Objection to Expenditure by Bank Method of Prequalifica Draft Evaluation of Bid Invitation Bid Closing Bid Opening Award Evaulation Contract Contract Contract of Completion of Package/ Reference No. Description of Goods Works/ Preference Bid Document Bidding Contract Value Currency No. Contractor Contract (Date) incurred to (Prior/ Selection tion (yes/no) Prequalification Prequalification (Date) (Date) (Date) Decision Report and Signed (Date) Date NCS (yes/no) (Date) Document (incl. Zip Post) documents Application (Date) Contract Award (Date)** Code if US) (Date)** (Date)** (Date)** Rashad ALhaj 17/36 ** Applicable in case of Bank's prior review Prequalification No Objection No Objection Bank’s No Bank’s No Name, City, Review from Bank for from Bank for Contract Objection to Bid and Country Goods/ Domestic Preparation of Objection to Expenditure by Bank Method of Prequalifica Draft Evaluation of Bid Invitation Bid Closing Bid Opening Award Evaulation Contract Contract Contract of Completion of Package/ Reference No. Description of Goods Works/ Preference Bid Document Bidding Contract Value Currency No. Contractor Contract (Date) incurred to (Prior/ Selection tion (yes/no) Prequalification Prequalification (Date) (Date) (Date) Decision Report and Signed (Date) Date NCS (yes/no) (Date) Document (incl. Zip Post) documents Application (Date) Contract Award (Date)** Code if US) (Date)** (Date)** (Date)** Rashad ALhaj 18/36 ** Applicable in case of Bank's prior review Prequalification No Objection No Objection Bank’s No Bank’s No Name, City, Review from Bank for from Bank for Contract Objection to Bid and Country Goods/ Domestic Preparation of Objection to Expenditure by Bank Method of Prequalifica Draft Evaluation of Bid Invitation Bid Closing Bid Opening Award Evaulation Contract Contract Contract of Completion of Package/ Reference No. Description of Goods Works/ Preference Bid Document Bidding Contract Value Currency No. Contractor Contract (Date) incurred to (Prior/ Selection tion (yes/no) Prequalification Prequalification (Date) (Date) (Date) Decision Report and Signed (Date) Date NCS (yes/no) (Date) Document (incl. Zip Post) documents Application (Date) Contract Award (Date)** Code if US) (Date)** (Date)** (Date)** Rashad ALhaj 19/36 ** Applicable in case of Bank's prior review Prequalification No Objection No Objection Bank’s No Bank’s No Name, City, Review from Bank for from Bank for Contract Objection to Bid and Country Goods/ Domestic Preparation of Objection to Expenditure by Bank Method of Prequalifica Draft Evaluation of Bid Invitation Bid Closing Bid Opening Award Evaulation Contract Contract Contract of Completion of Package/ Reference No. Description of Goods Works/ Preference Bid Document Bidding Contract Value Currency No. Contractor Contract (Date) incurred to (Prior/ Selection tion (yes/no) Prequalification Prequalification (Date) (Date) (Date) Decision Report and Signed (Date) Date NCS (yes/no) (Date) Document (incl. Zip Post) documents Application (Date) Contract Award (Date)** Code if US) (Date)** (Date)** (Date)** Rashad ALhaj 20/36 ** Applicable in case of Bank's prior review Prequalification No Objection No Objection Bank’s No Bank’s No Name, City, Review from Bank for from Bank for Contract Objection to Bid and Country Goods/ Domestic Preparation of Objection to Expenditure by Bank Method of Prequalifica Draft Evaluation of Bid Invitation Bid Closing Bid Opening Award Evaulation Contract Contract Contract of Completion of Package/ Reference No. Description of Goods Works/ Preference Bid Document Bidding Contract Value Currency No. Contractor Contract (Date) incurred to (Prior/ Selection tion (yes/no) Prequalification Prequalification (Date) (Date) (Date) Decision Report and Signed (Date) Date NCS (yes/no) (Date) Document (incl. Zip Post) documents Application (Date) Contract Award (Date)** Code if US) (Date)** (Date)** (Date)** Rashad ALhaj 21/36 ** Applicable in case of Bank's prior review Prequalification No Objection No Objection Bank’s No Bank’s No Name, City, Review from Bank for from Bank for Contract Objection to Bid and Country Goods/ Domestic Preparation of Objection to Expenditure by Bank Method of Prequalifica Draft Evaluation of Bid Invitation Bid Closing Bid Opening Award Evaulation Contract Contract Contract of Completion of Package/ Reference No. Description of Goods Works/ Preference Bid Document Bidding Contract Value Currency No. Contractor Contract (Date) incurred to (Prior/ Selection tion (yes/no) Prequalification Prequalification (Date) (Date) (Date) Decision Report and Signed (Date) Date NCS (yes/no) (Date) Document (incl. Zip Post) documents Application (Date) Contract Award (Date)** Code if US) (Date)** (Date)** (Date)** Rashad ALhaj 22/36 ** Applicable in case of Bank's prior review Prequalification No Objection No Objection Bank’s No Bank’s No Name, City, Review from Bank for from Bank for Contract Objection to Bid and Country Goods/ Domestic Preparation of Objection to Expenditure by Bank Method of Prequalifica Draft Evaluation of Bid Invitation Bid Closing Bid Opening Award Evaulation Contract Contract Contract of Completion of Package/ Reference No. Description of Goods Works/ Preference Bid Document Bidding Contract Value Currency No. Contractor Contract (Date) incurred to (Prior/ Selection tion (yes/no) Prequalification Prequalification (Date) (Date) (Date) Decision Report and Signed (Date) Date NCS (yes/no) (Date) Document (incl. Zip Post) documents Application (Date) Contract Award (Date)** Code if US) (Date)** (Date)** (Date)** Planned ‫مقترح‬ 1/ HAJ Procurement of pipes and Goods Post NCB No No NA NA 6-Feb-10 21-Feb-10 27-Feb-10 24-Mar-10 30-Mar-10 3-May-10 19-May-10 7-Jun-10 29-Sep-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 fittings in Haja Prior ICB No No 5-Oct-10 10-Oct-10 20-Oct-10 2-Dec-10 2-Dec-10 21-Jan-11 5-Feb-11 21-Feb-11 22-May-11 Revised2 Actual ‫Ù?علي‬ 5-Oct-10 17-Oct-10 14-Nov-10 27-Dec-10 27-Dec-10 1-Mar-11 29-Mar-11 18-Jun-12 1,344,345.97 under termination 2012-2013 schemes Planned ‫مقترح‬ 4-11/ SAN Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works , algaraa, bani shadad in Post NS 1-Feb-11 5-Feb-11 19-Feb-11 19-Feb-11 27-Feb-11 15-Mar-11 14-May-11 Sanaa 45,198.60 Revised2 21-Jun-12 5-Jul-12 5-Jul-12 15-Jul-12 31-Jul-12 29-Sep-12 Actual ‫Ù?علي‬ 27-Feb-11 3-Oct-12 9-Oct-12 9-Oct-12 30-Oct-12 Planned ‫مقترح‬ 4-12/ SAN Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /G/RWSS/WSSP/10 Works bani walid,in Sanaa Post NS 1-Feb-11 5-Feb-11 19-Feb-11 19-Feb-11 27-Feb-11 15-Mar-11 14-May-11 35,899.48 Revised2 21-Jun-12 5-Jul-12 5-Jul-12 15-Jul-12 31-Jul-12 29-Sep-12 Actual ‫Ù?علي‬ 27-Feb-11 3-Oct-12 9-Oct-12 9-Oct-12 26-Dec-12 Planned ‫مقترح‬ 2/ SAN Procurement of pumps and Goods Post NCB No No NA NA 25-Jan-11 5-Feb-11 7-Mar-11 7-Mar-11 22-Mar-11 9-Apr-11 9-Jul-11 Revised ‫متوقع‬ /G/RWSS/WSSP/11 accessories for (8)contracts in Sanaa 21-Jun-13 21-Jul-13 21-Jul-13 15-Aug-13 30-Aug-13 28-Nov-13 Actual ‫Ù?علي‬ 30-Jan-11 26-Jun-13 27-Jul-13 27-Jul-13 15-Sep-13 10-Oct-13 224,429.52 us Planned ‫مقترح‬ 2/ HUD Procurement of pumps and Goods Post NCB No No NA NA 25-Jan-11 5-Feb-11 7-Mar-11 7-Mar-11 22-Mar-11 9-Apr-11 9-Jul-11 Revised ‫متوقع‬ /G/RWSS/WSSP/11 accessories in Hudaida Post NCB 21-Jun-12 21-Jul-12 21-Jul-12 15-Aug-12 30-Aug-12 28-Nov-12 Actual ‫Ù?علي‬ 25-Jan-11 19-Dec-12 221,261.05 Planned ‫مقترح‬ 2/ HAD Procurement of pumps and Goods Post NCB No No NA NA 25-Jan-11 5-Feb-11 7-Mar-11 7-Mar-11 22-Mar-11 9-Apr-11 9-Jul-11 Revised ‫متوقع‬ /G/RWSS/WSSP/11 accessories in Hadramout 21-Jun-12 21-Jul-12 21-Jul-12 15-Aug-12 30-Aug-12 28-Nov-12 Actual ‫Ù?علي‬ 15-Feb-11 19-Jul-12 28-Aug-12 28-Aug-12 19-Sep-12 30-Sep-12 109,500.00 Planned ‫مقترح‬ 2/ RYM Procurement of pumps and Goods Post NCB No No NA NA 25-Jan-11 12-Feb-11 14-Mar-11 14-Mar-11 29-Mar-11 16-Apr-11 16-Jul-11 Revised ‫متوقع‬ /G/RWSS/WSSP/11 accessories in Ryimah 21-Jun-12 21-Jul-12 21-Jul-12 15-Aug-12 30-Aug-12 28-Nov-12 Actual ‫Ù?علي‬ 25-Jan-11 7-Jul-12 7-Aug-12 7-Aug-12 25-Aug-12 17-Nov-12 212,576.74 Planned ‫مقترح‬ 2/ AMR Procurement of pumps and Goods Post NCB No No NA NA 25-Jan-11 5-Feb-11 7-Mar-11 7-Mar-11 22-Mar-11 9-Apr-11 9-Jul-11 Revised ‫متوقع‬ /G/RWSS/WSSP/11 accessories in amran 21-Jan-12 20-Feb-12 20-Feb-12 16-Mar-12 21-Jun-12 19-Sep-12 Actual ‫Ù?علي‬ 25-Jan-11 9-Jul-12 11-Aug-12 11-Aug-12 9-Dec-12 64,000.00 Planned ‫مقترح‬ 5-1/ DHL /G/RWSS/ Various Water & Sanitation Civil Works Post NS No No NA NA 1-Aug-11 15-Aug-11 30-Aug-11 30-Aug-11 7-Sep-11 17-Sep-11 16-Nov-11 Revised ‫متوقع‬ WSSP/11 Works al kharbah shoki'a in Post NS 20-Jan-12 21-Jun-12 5-Jul-12 5-Jul-12 15-Jul-12 31-Jul-12 140,794.51 9-Oct-12 Actual ‫Ù?علي‬ Aldhale 7-Oct-12 Planned ‫مقترح‬ 5-1/ RYM Various Water & Sanitation Civil Works Post NCB No No NA NA 1-Aug-11 15-Aug-11 14-Sep-11 14-Sep-11 22-Sep-11 9-Oct-11 8-Dec-11 Revised ‫متوقع‬ /G/RWSS/WSSP/11 Works mahalat wadi alzanam in Post NCB 20-Jan-12 21-Jan-13 20-Feb-13 20-Feb-13 2-Mar-13 18-Mar-13 27-May-13 Ryimah Actual ‫Ù?علي‬ 17-Apr-13 18-May-13 18-May-13 1-Jun-13 1-Jun-13 86,840.00 Planned ‫مقترح‬ 5-2/ RYM Various Water & Sanitation Civil Works Post NCB No No NA NA 1-Aug-11 15-Aug-11 14-Sep-11 14-Sep-11 22-Sep-11 9-Oct-11 8-Dec-11 Revised ‫متوقع‬ /G/RWSS/WSSP/11 Works alkabah in Ryimah Post NCB 20-Jan-12 21-Jan-13 20-Feb-13 20-Feb-13 2-Mar-13 18-Mar-13 27-May-13 Actual ‫Ù?علي‬ 17-Apr-13 18-May-13 18-May-13 15-Jun-13 1-Jul-13 231,608.47 Planned ‫مقترح‬ 7/ Construction of turn key WS Works Post NCB No No NA NA 1-Jan-11 5-Feb-11 22-Mar-11 22-Mar-11 16-Apr-11 17-Jan-00 16-Apr-00 Revised ‫متوقع‬ HAJ/CW/RWSS/WSS system in (al danay) in Hajah 21-Jun-12 21-Jul-12 21-Jul-12 15-Aug-12 30-Aug-12 28-Nov-12 Actual ‫Ù?علي‬ P/11 15-Apr-11 18-Aug-12 16-Sep-12 16-Sep-12 12-Dec-12 336,825.35 Planned ‫مقترح‬ 8/ Construction of turn key WS Works Post NCB No No NA NA 1-Jan-11 5-Feb-11 22-Mar-11 22-Mar-11 16-Apr-11 17-Jan-00 16-Apr-00 Revised ‫متوقع‬ HAJ/CW/RWSS/WSS system in Alhadhan in Hajah 21-Jun-13 21-Jul-13 21-Jul-13 15-Aug-13 30-Aug-13 28-Nov-13 Actual ‫Ù?علي‬ P/11 15-Apr-11 18-Aug-12 16-Sep-12 16-Sep-12 12-Dec-12 253,572.10 Rashad ALhaj 23/36 ** Applicable in case of Bank's prior review Prequalification No Objection No Objection Bank’s No Bank’s No Name, City, Review from Bank for from Bank for Contract Objection to Bid and Country Goods/ Domestic Preparation of Objection to Expenditure by Bank Method of Prequalifica Draft Evaluation of Bid Invitation Bid Closing Bid Opening Award Evaulation Contract Contract Contract of Completion of Package/ Reference No. Description of Goods Works/ Preference Bid Document Bidding Contract Value Currency No. Contractor Contract (Date) incurred to (Prior/ Selection tion (yes/no) Prequalification Prequalification (Date) (Date) (Date) Decision Report and Signed (Date) Date NCS (yes/no) (Date) Document (incl. Zip Post) documents Application (Date) Contract Award (Date)** Code if US) (Date)** (Date)** (Date)** Planned ‫مقترح‬ 3/ HQ Procurement of Emergency Goods Post NCB No No NA NA 31-Mar-12 21-Jun-12 21-Jul-12 21-Jul-12 5-Aug-12 23-Aug-12 21-Nov-12 Revised ‫متوقع‬ 11-Jan-13 11-Jan-13 5-Feb-13 /G/RWSS/WSSP/12 Computers & accessories& Actual ‫Ù?علي‬ 12-Dec-12 20-Jan-13 20-Jan-13 294,413.69 copy machine ,…. in HQ Planned ‫مقترح‬ 3/ HQ Procurement of Emergency Goods Post NCB No No NA NA 31-Mar-12 1-Jan-13 31-Jan-13 31-Jan-13 15-Feb-13 5-Mar-13 3-Jun-13 Revised ‫متوقع‬ /G/RWSS/WSSP/13 copy machine ,…. in HQ Actual ‫Ù?علي‬ 17-Jan-13 20-Feb-13 20-Feb-13 20-May-13 27,144.00 Planned ‫مقترح‬ 6/ HQ Civil Works of Emergency Works Post NCB No No NA NA 31-Mar-12 21-Jun-12 21-Jul-12 21-Jul-12 5-Aug-12 23-Aug-12 21-Nov-12 Revised ‫متوقع‬ /CW/RWSS/WSSP/12 Rehabilitation of GARWSP 13-Apr-13 Actual ‫Ù?علي‬ HQ buildings in 8-May-12 10-Jun-12 10-Jun-12 15-Oct-12 291,731.00 Planned ‫مقترح‬ 2/ MAH Procurement of pumps and Goods Post NCB No No NA NA 25-Jan-13 5-Feb-13 7-Mar-13 7-Mar-13 22-Mar-13 9-Apr-13 9-Jul-13 Revised ‫متوقع‬ /G/RWSS/WSSP/13 accessories in Al-mahra Actual ‫Ù?علي‬ 30-Jan-13 10-May-13 8-Jun-13 8-Jun-13 26-Jun-13 38,800.00 Planned ‫مقترح‬ 6/ Civil Works & Sanitation Works Post NCB No No NA NA 1-Jan-11 5-Feb-11 22-Mar-11 22-Mar-11 16-Apr-11 17-Jan-00 16-Apr-00 Revised ‫متوقع‬ IBB/CW/RWSS/WSSP &Pumps-pipes (al maseel) in 20-May-13 19-Jun-13 19-Jun-13 14-Jul-13 29-Jul-13 27-Oct-13 Actual ‫Ù?علي‬ IBB 15-Apr-11 30-Jul-13 1-Sep-13 1-Sep-13 24-Nov-13 597,882.90 /11 Planned ‫مقترح‬ 7/ Civil Works & Sanitation Works Post NCB No No NA NA 1-Jan-11 5-Feb-11 22-Mar-11 22-Mar-11 16-Apr-11 17-Jan-00 16-Apr-00 Revised ‫متوقع‬ IBB/CW/RWSS/WSSP &Pumps-pipes (almoueh) in IBB 20-May-13 19-Jun-13 19-Jun-13 14-Jul-13 29-Jul-13 27-Oct-13 Actual ‫Ù?علي‬ /11 15-Apr-11 30-Jul-13 1-Sep-13 1-Sep-13 27-Oct-13 578,134.05 Planned ‫مقترح‬ 2/ MAR /G/RWSS/ Procurement of pumps and Goods Post NCB No No NA NA 25-Jan-11 5-Feb-11 7-Mar-11 7-Mar-11 22-Mar-11 9-Apr-11 9-Jul-11 Revised ‫متوقع‬ WSSP/11 accessories in Mareb 2-Jan-13 1-Feb-13 1-Feb-13 26-Feb-13 13-Mar-13 11-Jun-13 Actual ‫Ù?علي‬ 5-Feb-11 17-Apr-13 15-May-13 15-May-13 1-Jun-13 53,800.00 Planned ‫مقترح‬ 2/ Construction of (Al mesher) turn Works Post NCB No No NA NA 1-Jan-13 5-Feb-13 22-Mar-13 22-Mar-13 16-Apr-13 3-May-13 1-Aug-13 Revised ‫متوقع‬ IBB/CW/RWSS/WSSP key WS system in Ibb Actual ‫Ù?علي‬ /13 30-Mar-13 185,295.36 Planned ‫مقترح‬ 3/ Construction of (Al ‫ ) الوزيرة‬turn Works Post NCB No No NA NA 1-Jan-13 5-Feb-13 22-Mar-13 22-Mar-13 16-Apr-13 3-May-13 1-Aug-13 Revised ‫متوقع‬ IBB/CW/RWSS/WSSP key WS system in Ibb Actual ‫Ù?علي‬ /13 30-Mar-13 396,508.45 Planned ‫مقترح‬ 1/ Construction of (Al lasaan) turn Works Post NCB No No NA NA 1-Jan-13 5-Feb-13 22-Mar-13 22-Mar-13 16-Apr-13 3-May-13 1-Aug-13 Revised ‫متوقع‬ AMR/CW/RWSS/WSS key WS system in Amran Actual ‫Ù?علي‬ P/13 21-Jun-13 20-Jul-13 20-Jul-13 232,014.50 Planned ‫مقترح‬ 1/ Construction of (almashkib) turn Works Post NCB No No NA NA 1-Jan-13 5-Feb-13 22-Mar-13 22-Mar-13 16-Apr-13 3-May-13 1-Aug-13 Revised ‫متوقع‬ TAZ/CW/RWSS/WSS key WS system() - Taiz Actual ‫Ù?علي‬ P/13 21-Jul-13 21-Aug-13 21-Aug-13 8-Oct-13 204,725.00 Planned ‫مقترح‬ 2/ Construction of (Asleef) turn key Works Post NCB No No NA NA 1-Jan-13 5-Feb-13 22-Mar-13 22-Mar-13 16-Apr-13 3-May-13 1-Aug-13 Revised ‫متوقع‬ TAZ/CW/RWSS/WSS WS system - Taiz Actual ‫Ù?علي‬ P/13 21-Jul-13 21-Aug-13 21-Aug-13 8-Oct-13 157,961.00 Planned ‫مقترح‬ 3/ Construction of (Mahoal Alala'a) Works Post NCB No No NA NA 1-Jan-13 5-Feb-13 22-Mar-13 22-Mar-13 16-Apr-13 3-May-13 1-Aug-13 Revised ‫متوقع‬ TAZ/CW/RWSS/WSS turn key WS system - Taiz Actual ‫Ù?علي‬ P/13 21-Jul-13 21-Aug-13 21-Aug-13 8-Oct-13 166,966.00 Planned ‫مقترح‬ 4/ Supply of pumping unit for Good Post NCB No No NA NA 1-Jan-13 5-Feb-13 22-Mar-13 22-Mar-13 16-Apr-13 3-May-13 1-Aug-13 Revised ‫متوقع‬ TAZ/G/RWSS/WSSP/ (hajreen ) - Taiz Actual ‫Ù?علي‬ 13 21-Jul-13 21-Aug-13 21-Aug-13 46,500.00 Planned ‫مقترح‬ 4/ Supply of pumping unit for(Daba Good Post NCB No No NA NA 1-Jan-13 5-Feb-13 22-Mar-13 22-Mar-13 16-Apr-13 3-May-13 1-Aug-13 Revised ‫متوقع‬ TAZ/G/RWSS/WSSP/ ) - Taiz Actual ‫Ù?علي‬ 13 21-Jul-13 21-Aug-13 21-Aug-13 37,500.00 Planned ‫مقترح‬ 4/ Supply of pumping unit for Good Post NCB No No NA NA 1-Jan-13 5-Feb-13 22-Mar-13 22-Mar-13 16-Apr-13 3-May-13 1-Aug-13 Revised ‫متوقع‬ TAZ/G/RWSS/WSSP/ (Alsafeh ) - Taiz Actual ‫Ù?علي‬ 13 21-Jul-13 21-Aug-13 21-Aug-13 9-Oct-13 26,867.00 €1 Planned 03/CW/RWSS/WSSP/ Construction of Various Water & Works Post NCB No No NA NA 10-Jun-10 24-Jun-10 29-Jun-10 29-Jul-10 12-Aug-10 1-Sep-10 30-Dec-10 Revised 09 Sanitation Civil Works in Haja Post NS No No 1-Jan-11 N/A 8-Jan-11 7-Feb-11 15-Feb-11 3-Mar-11 1-Jun-11 Revised2 21-Dec-13 5-Jan-14 5-Jan-14 13-Jan-14 29-Jan-14 29-Apr-14 Actual 15-Jan-11 Planned 06- Various Water & Sanitation Civil Works Post NCB No No NA NA 10-Jun-10 24-Jun-10 29-Jun-10 29-Jul-10 12-Aug-10 1-Sep-10 30-Dec-10 Revised 1/CW/RWSS/WSSP/0 Works lahyah in Shabwa Post NS No No 30-Jan-11 N/A 5-Feb-11 19-Feb-11 19-Feb-11 27-Feb-11 15-Mar-11 14-May-11 Revised2 9 Post NS 30-Jan-12 21-Dec-13 4-Jan-14 4-Jan-14 12-Jan-14 28-Jan-14 29-Mar-14 Actual Planned ‫مقترح‬ 4-1/ HAJ Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /CW/RWSS/WSSP/10 Works bani gamal in Haja Post NCB 1-Apr-11 10-Apr-11 10-May-11 10-May-11 18-May-11 3-Jun-11 2-Aug-11 Revised2 1-Apr-12 21-Dec-13 20-Jan-14 20-Jan-14 28-Jan-14 13-Feb-14 14-Apr-14 Actual ‫Ù?علي‬ Planned ‫مقترح‬ 4-2/ HAJ Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /CW/RWSS/WSSP/10 Works altowr in Haja Post NCB 1-Apr-11 10-Apr-11 10-May-11 10-May-11 18-May-11 3-Jun-11 2-Aug-11 Revised2 1-Apr-12 21-Dec-13 20-Jan-14 20-Jan-14 28-Jan-14 13-Feb-14 14-Apr-14 Actual ‫Ù?علي‬ Planned ‫مقترح‬ 4-3/ HAJ Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /CW/RWSS/WSSP/10 Works bani Mshata'a in Haja Post NCB 1-Apr-11 10-Apr-11 10-May-11 10-May-11 18-May-11 3-Jun-11 2-Aug-11 Revised2 1-Apr-12 21-Dec-13 20-Jan-14 20-Jan-14 28-Jan-14 13-Feb-14 14-Apr-14 Actual ‫Ù?علي‬ Planned ‫مقترح‬ 4-4/ HAJ Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /CW/RWSS/WSSP/10 Works bani faeed in Haja Post NCB 1-Apr-11 10-Apr-11 10-May-11 10-May-11 18-May-11 3-Jun-11 2-Aug-11 Revised2 1-Apr-12 21-Dec-13 20-Jan-14 20-Jan-14 28-Jan-14 13-Feb-14 14-Apr-14 Actual ‫Ù?علي‬ Planned ‫مقترح‬ 4-5/ HAJ Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /CW/RWSS/WSSP/10 Works Shaleelh in Haja Post NCB 1-Apr-11 10-Apr-11 10-May-11 10-May-11 18-May-11 3-Jun-11 2-Aug-11 Revised2 1-Apr-12 21-Dec-13 20-Jan-14 20-Jan-14 28-Jan-14 13-Feb-14 14-Apr-14 Actual ‫Ù?علي‬ cancel Planned ‫مقترح‬ 4-11/ SAN Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /CW/RWSS/WSSP/10 Works hara ala'atzaz, alareen, Post NS 1-Feb-11 5-Feb-11 19-Feb-11 19-Feb-11 27-Feb-11 15-Mar-11 14-May-11 al-ladan,alhamra and alfars in 21-Dec-13 4-Jan-14 4-Jan-14 14-Jan-14 30-Jan-14 31-Mar-14 Rashad ALhajRevised2 24/36 Sanaa ** Applicable in case of Bank's prior review Prequalification No Objection No Objection Bank’s No Bank’s No Name, City, Review from Bank for from Bank for Contract Objection to Bid and Country Goods/ Domestic Preparation of Objection to Expenditure by Bank Method of Prequalifica Draft Evaluation of Bid Invitation Bid Closing Bid Opening Award Evaulation Contract Contract Contract of Completion of Package/ 4-11/ SAN No. Reference VariousDescription of Goods Civil Water & Sanitation Works/ Works Preference Bid Document Bidding Contract Value Currency No. Contractor Contract (Date) incurred to (Prior/ Selection tion (yes/no) Prequalification Prequalification (Date) (Date) (Date) Decision Report and Signed (Date) Date Works hara ala'atzaz, alareen, NCS (yes/no) (Date) Document (incl. Zip /CW/RWSS/WSSP/10 Post) documents Application (Date) Contract Award al-ladan,alhamra and alfars in (Date)** Code if US) (Date)** (Date)** (Date)** Sanaa Actual ‫Ù?علي‬ 27-Feb-11 Planned ‫مقترح‬ 4-1/ SHB Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /CW/RWSS/WSSP/10 Works alfara in Shabwa Post NS 30-Jan-11 5-Feb-11 19-Feb-11 19-Feb-11 27-Feb-11 15-Mar-11 14-May-11 Revised2 Post NCB 30-Jan-12 21-Dec-13 20-Jan-14 20-Jan-14 28-Jan-14 13-Feb-14 14-Apr-14 Actual ‫Ù?علي‬ Rashad ALhaj 25/36 ** Applicable in case of Bank's prior review Prequalification No Objection No Objection Bank’s No Bank’s No Name, City, Review from Bank for from Bank for Contract Objection to Bid and Country Goods/ Domestic Preparation of Objection to Expenditure by Bank Method of Prequalifica Draft Evaluation of Bid Invitation Bid Closing Bid Opening Award Evaulation Contract Contract Contract of Completion of Package/ Reference No. Description of Goods Works/ Preference Bid Document Bidding Contract Value Currency No. Contractor Contract (Date) incurred to (Prior/ Selection tion (yes/no) Prequalification Prequalification (Date) (Date) (Date) Decision Report and Signed (Date) Date NCS (yes/no) (Date) Document (incl. Zip Post) documents Application (Date) Contract Award (Date)** Code if US) (Date)** (Date)** (Date)** Rashad ALhaj 26/36 ** Applicable in case of Bank's prior review Prequalification No Objection No Objection Bank’s No Bank’s No Name, City, Review from Bank for from Bank for Contract Objection to Bid and Country Goods/ Domestic Preparation of Objection to Expenditure by Bank Method of Prequalifica Draft Evaluation of Bid Invitation Bid Closing Bid Opening Award Evaulation Contract Contract Contract of Completion of Package/ Reference No. Description of Goods Works/ Preference Bid Document Bidding Contract Value Currency No. Contractor Contract (Date) incurred to (Prior/ Selection tion (yes/no) Prequalification Prequalification (Date) (Date) (Date) Decision Report and Signed (Date) Date NCS (yes/no) (Date) Document (incl. Zip Post) documents Application (Date) Contract Award (Date)** Code if US) (Date)** (Date)** (Date)** Planned ‫مقترح‬ 4-1/ ABN Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /CW/RWSS/WSSP/10 Works alrhaba in Abyan Post NS 1-Jan-11 5-Feb-11 19-Feb-11 19-Feb-11 1-Mar-11 17-Mar-11 16-May-11 Revised2 Post NS 21-Dec-13 4-Jan-14 4-Jan-14 14-Jan-14 30-Jan-14 31-Mar-14 Actual ‫Ù?علي‬ 20-Jan-11 Planned ‫مقترح‬ 4-1/ HAD Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /CW/RWSS/WSSP/10 Works that altareek in Moklla Post NS 1-Jan-11 5-Feb-11 19-Feb-11 19-Feb-11 1-Mar-11 17-Mar-11 16-May-11 Revised2 Post NS 21-Dec-13 4-Jan-14 4-Jan-14 14-Jan-14 30-Jan-14 31-Mar-14 Actual ‫Ù?علي‬ 20-Jan-11 Planned ‫مقترح‬ 4-2/ HAD Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /CW/RWSS/WSSP/10 Works moshah in Saioon Post NS 1-Jan-11 5-Feb-11 19-Feb-11 19-Feb-11 1-Mar-11 17-Mar-11 16-May-11 Revised2 Post NS 21-Dec-13 4-Jan-14 4-Jan-14 14-Jan-14 30-Jan-14 31-Mar-14 Actual ‫Ù?علي‬ 20-Jan-11 Planned ‫مقترح‬ 4-1/ JWF Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /CW/RWSS/WSSP/10 Works in Al kharba al-jowf Post NS 1-Jan-11 5-Feb-11 19-Feb-11 19-Feb-11 1-Mar-11 17-Mar-11 16-May-11 Revised2 21-Dec-13 4-Jan-14 4-Jan-14 14-Jan-14 30-Jan-14 31-Mar-14 Actual ‫Ù?علي‬ 20-Jan-11 Planned ‫مقترح‬ 4-3/ AMR Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /CW/RWSS/WSSP/10 Works in habor, dho mosalam, Post NS 1-Jan-11 15-Jan-11 14-Jan-00 14-Jan-00 24-Jan-00 9-Feb-00 9-Apr-00 Revised2 higara, alfara and algadom al 21-Dec-13 4-Jan-14 4-Jan-14 14-Jan-14 30-Jan-14 31-Mar-14 ala in Amran Actual ‫Ù?علي‬ 15-Jan-11 Planned ‫مقترح‬ 4-1/ MAH Various Water & Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /CW/RWSS/WSSP/10 Works atab in Al-mahra Post NS 1-Feb-11 5-Feb-11 19-Feb-11 19-Feb-11 27-Feb-11 15-Mar-11 14-May-11 Revised2 Post NS 1-Feb-12 21-Dec-13 4-Jan-14 4-Jan-14 12-Jan-14 28-Jan-14 29-Mar-14 Actual ‫Ù?علي‬ 12-Jun-12 Planned ‫مقترح‬ 4-1/ DHM Various Water& Sanitation Civil Works Post NCB No No NA NA 30-May-10 21-Jun-10 20-Jul-10 25-Jul-10 9-Aug-10 12-Sep-10 30-Dec-10 Revised ‫متوقع‬ /CW/RWSS/WSSP/10 Works thwamah&alhd in Thamar Post NS 9-Oct-10 14-Jan-00 14-Jan-00 8-Jan-00 16-Jan-00 16-Mar-00 Revised2 21-Dec-13 4-Jan-14 4-Jan-14 14-Jan-14 30-Jan-14 31-Mar-14 Actual ‫Ù?علي‬ 5-Dec-10 Planned ‫مقترح‬ 5-1/SAD Various Water & Sanitation Civil Works Post NS No No NA NA 1-Aug-11 15-Aug-11 30-Aug-11 30-Aug-11 7-Sep-11 17-Sep-11 16-Nov-11 Revised ‫متوقع‬ /CW/RWSS/WSSP/11 Works falla & alkhashab & alt Post NCB 15-May-12 21-Dec-13 4-Jan-14 4-Jan-14 14-Jan-14 30-Jan-14 10-Apr-14 Actual ‫Ù?علي‬ majz and wadi kona in Saada Planned ‫مقترح‬ 6/ Civil Works & Sanitation Works Post NCB No No NA NA 1-Jan-11 5-Feb-11 22-Mar-11 22-Mar-11 16-Apr-11 17-Jan-00 16-Apr-00 HAJ/CW/RWSS/WSS &Pumps-pipes(jabal al adbae) Revised ‫متوقع‬ in Hajah 21-Jun-13 21-Jul-13 21-Jul-13 15-Aug-13 30-Aug-13 28-Nov-13 Actual ‫Ù?علي‬ P/11 15-Apr-11 Planned ‫مقترح‬ 1/ HQ Procurement of Emergency Goods Post NCB No No NA NA 31-Mar-12 4-May-12 3-Jun-12 3-Jun-12 18-Jun-12 6-Jul-12 4-Oct-12 Revised ‫متوقع‬ 21-Dec-13 20-Jan-14 20-Jan-14 14-Feb-14 1-Mar-14 /G/RWSS/WSSP/12 lab equipments in HQ Actual ‫Ù?علي‬ Planned ‫مقترح‬ 2/ HQ Procurement of Emergency Goods Post NCB No No NA NA 31-Mar-12 21-Jun-12 21-Jul-12 21-Jul-12 5-Aug-12 23-Aug-12 21-Nov-12 Revised ‫متوقع‬ 21-Dec-13 20-Jan-14 20-Jan-14 14-Feb-14 1-Mar-14 /G/RWSS/WSSP/12 Survey equipments in HQ Actual ‫Ù?علي‬ Planned ‫مقترح‬ 4/ HQ Procurement of Emergency Goods Post NCB No No NA NA 31-Mar-12 21-Jun-12 21-Jul-12 21-Jul-12 5-Aug-12 23-Aug-12 21-Nov-12 Revised ‫متوقع‬ 21-Dec-13 20-Jan-14 20-Jan-14 14-Feb-14 1-Mar-14 /G/RWSS/WSSP/12 Office Furniture in HQ Actual ‫Ù?علي‬ Planned ‫مقترح‬ HQ/WSSP/G/NS/12/1 Procurement of FM system Goods post NS No No NA NA 15-Sep-12 21-Sep-12 5-Oct-12 5-Oct-12 15-Oct-12 2-Nov-12 Revised ‫متوقع‬ Actual ‫Ù?علي‬ 5-Sep-12 5-Oct-12 5-Oct-12 16-Oct-12 20,206.00 Planned ‫مقترح‬ 7/ HQ Civil Works of Emergency Works Post NCB No No NA NA 31-Mar-12 21-Jun-12 21-Jul-12 21-Jul-12 5-Aug-12 23-Aug-12 21-Nov-12 Revised ‫متوقع‬ 21-Dec-13 20-Jan-14 20-Jan-14 14-Feb-14 1-Mar-14 /CW/RWSS/WSSP/12 Sanaa branch’s buildings Actual ‫Ù?علي‬ 2014 Schemes Planned ‫مقترح‬ 1/ Supply and installation of Goods Post NCB No No NA NA 1-Jan-13 21-Dec-13 4-Feb-14 4-Feb-14 1-Mar-14 18-Mar-14 16-Jun-14 Revised ‫متوقع‬ LAH/G/RWSS/WSSP/ pumping unit for (Aldhaabob) in Actual ‫Ù?علي‬ Taiz 13 Planned ‫مقترح‬ 1/ Construction of (Algadowr) WS Works Post NCB No No NA NA 1-Jan-13 21-Dec-13 4-Feb-14 4-Feb-14 1-Mar-14 18-Mar-14 16-Jun-14 Revised ‫متوقع‬ LAH/CW/RWSS/WSS system in Lahjj Actual ‫Ù?علي‬ P/13 Planned ‫مقترح‬ 1/ Construction of (Algafar) WS Works Post NCB No No NA NA 1-Jan-13 21-Dec-13 4-Feb-14 4-Feb-14 1-Mar-14 18-Mar-14 16-Jun-14 Revised ‫متوقع‬ MAH/CW/RWSS/WS system in Mahaweet Actual ‫Ù?علي‬ SP/13 Planned ‫مقترح‬ 1/ Construction of (Alkabah) turn Works Post NCB No No NA NA 21-Jun-13 21-Dec-13 4-Feb-14 4-Feb-14 1-Mar-14 18-Mar-14 16-Jun-14 Revised ‫متوقع‬ TAZ/CW/RWSS/WSS key WS system - Haja Actual ‫Ù?علي‬ P/13 Planned ‫مقترح‬ 1/ Construction of (Alkharh bani Works Post NCB No No NA NA 21-Jun-13 21-Dec-13 4-Feb-14 4-Feb-14 1-Mar-14 18-Mar-14 16-Jun-14 Revised ‫متوقع‬ TAZ/CW/RWSS/WSS sowar) Turn key WS system - Actual ‫Ù?علي‬ Sana'a P/13 Planned ‫مقترح‬ 1/ Construction of (Beet Aladeeb) Works Post NCB No No NA NA 1-Jan-13 21-Dec-13 4-Feb-14 4-Feb-14 1-Mar-14 18-Mar-14 16-Jun-14 Revised ‫متوقع‬ IBB/CW/RWSS/WSSP turn key WS system in Ibb Actual ‫Ù?علي‬ /13 Rashad ALhaj 27/36 Republic of Yemen Water Sector Support Program (WSSP) Consultancy services 2010 - 2014 In some contracts, one or more of these approvals may be ** Applicable in case of Bank's prior review contained in one Bank communication. Name, City, No No Objection by No Objection by and Country RFP Final Review Type of TOR/Shortlis No Objection Objection Proposal the Bank to the the Bank of Expenses SL Method Advertising Draft to be No Objection Services SL Package/ Reference by Bank Consultant t to be from Bank for from Bank RFP Issued Submission Technical (Technical/ Contract Contract Contract Contract Contractor No. Description of Services of for Short forwarded from Bank for Completion No. No. (Prior/ (Firm/ Finalised Shortlist for Final (Date) Deadline Evaluation #Combined/ Draft Signed (Date) Value Currency No. (incl. Zip Incurred CS Selection listing (Date) to the Bank TOR (Date)** (Date) Post) Individual) (Date) (Date)** RFP (Date) Report Contract/ Final Code if US) to Date (Date) (Date)** (Date)** Contract) (Date)** 35 ‫استشاري لتقييم تجربة الهيئة‬ 01/G/RWSS/WSSP/10 ‫ومشروع المياه والصرÙ?‬ Prior Individual IC Planned 1-Aug-10 15-Aug-10 15-Sep-10 15-Sep-10 20-Sep-10 shoat term ‫الصحي الريÙ?ي‬ 2 17940.00 US$ consultant for Assessment 19-Feb-11 Revised GARWSP and RWSSP Actual Methods 24-Jul-10 25-Sep-10 20-Dec-10 21-Dec-10 28/36 Republic of Yemen Water Sector Support Program (WSSP) Plan of Capacity Building Activities (GARWSP) SL Estimated Completion No. Expected Outcome/ Activity Description Duration Start Date Date Comments Local training program 2012 AOP Training Subject Cost remain2011 paid as end December ampunt # of trainee cost 0 Preparation of different operational manuals 13636 13636 0 English language training courses 13636 13636 0 Accounting (intl. standard) 28000 28000 0 Project management 28000 28000 0 Monitoring and evaluation 23455 23455 Republic of Yemen Water Sector Support Program (WSSP) Plan of Capacity Building Activities (GARWSP) SL Estimated Completion Expected No. Different courses Activity Outcome/ technical Description (Evaluation and Duration Start Date Date Comments installation of electonic systems, GIS systems and 0 profesional management 44180 44180 Training on plans and budgets preparation 26 9000 - Use of the new financial and accounting systems 60 18000 - Procurement procedures 60 18000 40 - Design and Selection of pumping units 42418 - Technical Supervision of wells drilling . 25 9000 - Using new software’s in designs of water systems 27 14455 - Water quality monitoring 25 9728 50 - Wells testing and logging 22545 25 - Use of GIS in wells data base 9000 - Wells drilling techniques 25 9000 - Design of water harvesting systems 25 13545 - Artificial Well recharging 25 9000 - Operation and maintenance of pumping units 25 9000 - Computer and software courses 60 16800 - Environmental impact assessment 25 9000 Charactarastics of Ground water and movement of 25 underground water 9000 Cost of supervising and monitoring 13509 Total 150907 250000 Serail Number Number of tender of 1 1 2 9 3 13 suply of pipes 4 2 5 3 6 8 7 4 8 10 9 1 10 1 11 1 12 13 pipes installation 13 11 14 7 15 7 16 1 17 3 18 4 19 1 20 13 21 5 22 10 23 3 24 2 supply of Pumps 25 2 26 6 27 8 28 4 29 2 installion of pipes 30 1 31 1 32 1 33 1 34 1 35 36 37 38 39 40 160 total tenders total schemes for Rehabilatation and 145 completation 1 7-Mar-12 21-Apr-12 2 2-Jul-12 3-Sep-13 3 8-Jan-12 12-Mar-12 4 5-Mar-12 24-Apr-12 5 6-Jun-12 26-Jul-12 6 10-Jul-12 17-Sep-12 7 23-Oct-12 25-Dec-12 8 22-Jan-12 13-Mar-12 9 19-Mar-12 8-May-12 10 20-Jun-12 9-Aug-12 11 23-Apr-12 12-Jun-12 12 6-Nov-12 9-Oct-12 13 24-Sep-12 13-Nov-12 14 5-Feb-12 27-Mar-12 15 12-Mar-12 20-May-12 16 4-Jul-12 11-Sep-12 17 7-May-12 26-Jun-12 18 7-Aug-12 26-Sep-12 19 20-Nov-12 23-Oct-12 20 8-Oct-12 16-Dec-12 21 22-Oct-12 30-Dec-12 22 20-Feb-12 27-Dec-12 ‫اعداد الخطط والموازنات التقديرية واساليب متابعة‬ ‫تنÙ?يذها وتقييمها ÙˆÙ?قا الليات الهيئة‬ ‫النظام المحاسبي االلي الجديد‬ ‫اسس ومعايير اختيار وحدات الضخ واعمال الÙ?حص‬ ‫والتحليل الÙ?ني وحساب الجدوى االقتصادية‬ ‫دور واهمية االشراÙ? الÙ?ني Ù?ÙŠ ضبط جودة اههية جودة‬ ‫التركيب والتشغيل واالشراÙ? ورÙ?ع التقارير‬ ‫تشغيل وصيانة وحدات لضخ (اÙ?قية‪/‬عمودية‪ /‬غاطسة)‬ ‫ادارة االالت والمعدات الخاصة بورشة الصيانه‬ ‫دورة تدريبية Ù?ÙŠ قانون المناقصات الجديد والئحتة‬ ‫التنÙ?يذية‬ ‫دورة تدريبية عن جيولوجية اليمن والمنطقة المحيطة‬ ‫(الصخور‪ ،‬الوضع البنائي والتاريخ الجيولوجي)‪.‬‬ ‫دورة تدريبية عن هيدرولوجية اليمن (الظروÙ? المناخية‬ ‫وتواجد المياه السطحية واالحواض المائية)‪.‬‬ ‫دورة تدريبية Ù?ÙŠ المجال الهيدروجيولوجي لليمن‬ ‫المبادئ االساسية Ù?Ù‰ حركة المياه الجوÙ?ية والخواص‬ ‫الÙ?يزيائية للطبقات المائية‬ ‫االسلوب االمثل Ù?ÙŠ اعداد الدراسات االستكشاÙ?ية المائية‬ ‫وتقييم الجدوى االقتصادية Ù?Ù‰ اختيار البدائل المالئمة‬ ‫دورة تدريبية Ù?Ù‰ كيÙ?ية الدقة والتحري الختيار مواقع‬ ‫ابار المياه ووضع المواصÙ?ات والتصاميم المناسبة‬ ‫لالبار بحسب خصوصية المناطق للحد من الÙ?شل‬ ‫دورة تدريبية Ù?Ù‰ ابار المياه وتقنيات الحÙ?ر‬ ‫دورة تدريبية Ù?Ù‰ كيÙ?ية االشراÙ? على Ø­Ù?ر االبار ورÙ?ع‬ ‫التقارير‬ ‫دورة تدريبية Ù?Ù‰ طرق واساليب اعداد الدراسات و‬ ‫التصاميم الهندسية باستخدام االجهزة الحديثة‬ ‫دورة تدريبية الستخدام وتطبيق تقنيات حديثة (برنامج‬ ‫حاسوب)‪ ،‬Ù?ÙŠ معالجة وعرض وتÙ?سير وتقييم وخزن‬ ‫واسترجاع نتائج الضخ االختباري لآلبار العميقة وصوال‬ ‫لمعرÙ?Ø© خواص البئر وسمات الخزان الجوÙ?ي‪.‬‬ ‫الهيدرولوكية‬ ‫دورة تدريبية Ù?Ù‰ جودة المياه ومراقبتها‬ ‫التغذية االصطناعية للمياه الجوÙ?ية لزيادة مخزون‬ ‫الطبقات المائية‬ ‫عمل قاعدة معلوماتية لآلبار Ù?ÙŠ مركز الهيئة وباستخدام‬ ‫تقينات حديثة (تطبيق البرنامج ‪.) GIS‬‬ ‫دورة تدريبية Ù?ÙŠ كيÙ?ية اعداد دراسات حصاد مياه‬ ‫األمطار لتشيد حواجز أو سدود أو كرÙ?ان مائية وحسن‬ ‫االختيار للمواقع االنسب ووضع التصاميم الهندسية‬ ‫وجدول الكميات وتقدير الكلÙ?ة‪.‬‬ ‫دورة تدريبية Ù?ÙŠ طرق اعداد البحوث العلمية Ù?ÙŠ مجال‬ ‫المياه ووضع استراتجية (خطة) للبحث العلمي Ù?ÙŠ مجال‬ ‫المياه وتحديد االولويات البحثية العاجلة منها‪.‬‬ ‫الرخصة الدولية لقيادة الحاسوب(‪ )ICDL‬برامج‬ ‫تطبيقية‬