PROCUREMENT PLAN (Textual Part) Project information: Mauritania Youth Employability Project Preparation Advance [P162916] Project Implementation agency: Ministry of Employment, Youth and Sports & Department of Education and Training Projects Date of the Procurement Plan: February 2, 2021 Period covered by this Procurement Plan: February 2- December 30, 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Le décret N° 2020-122 du 06 octobre 2020, modifiant et complétant certaines dispositions du décret N° 2017-126 du 02 novembre 2017, abrogeant et replaçant les dispositions des décrets d’applications de la loi N° 2010-044 du 22 juillet 2010, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: [is not applicable]; Works: [is not applicable] Other Relevant Procurement Information. PROCUREMENT Mauritania : Mauritania Youth Employability Project PLAN General Information Country: Mauritania Bank’s Approval Date of the Original Procurement Plan: 2021-02-25 2021-02-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P162916 GPN Date: Project Name: Mauritania Youth Employability Project Loan / Credit No: IDA / V3030 Mauritania Youth Employability Project Executing Agency(ies): WORKS Procureme Activity Reference No. / Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH nt Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) Justification for Award Type Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 22/2021/PEJ-RIM / Project management, Single Stage - One En attente IDA / V3030 A posteriori Demande de prix Open - National 0.00 2021-02-20 2021-04-17 2021-10-14 Acquisition équipement monitoring, and evaluation Envelope d'exécution 23/2021/PEJ-RIM / Achat de Project management, Single Stage - One En attente IDA / V3030 A posteriori Demande de prix Open - National 0.00 2021-02-20 2021-04-08 2021-10-05 matériel informatique monitoring, and evaluation Envelope d'exécution 24/2021/PEJ-RIM / Achat et Project management, Single Stage - One En attente installation d'une salle de IDA / V3030 A posteriori Demande de prix Open - National 0.00 2021-02-20 2021-04-17 2021-10-14 monitoring, and evaluation Envelope d'exécution vidéo conférence NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 02/2021/PEJ-RIM / Sélection fondée Développement de contenu et Contingency emergency sur les En attente formation des conseillers IDA / V3030 A posteriori Open - International 0.00 2021-02-15 2021-03-08 2021-04-21 2021-05-21 2021-06-25 2021-12-22 response qualifications des d'exécution d'accueil, d'orientation et consultants d'accompagnement (coaching) 03/2021/PEJ-RIM / Sélection fondée Contingency emergency En attente Formation en compétences de IDA / V3030 A posteriori sur la qualité et le Open - International 0.00 2021-02-15 2021-03-08 2021-04-21 2021-05-19 2021-06-18 2021-07-23 2021-08-27 2022-08-27 response d'exécution vie coût 04/2021/PEJ-RIM / Sélection fondée Contractualisation d'une Orientation, job counseling, sur les En attente IDA / V3030 A posteriori Open - International 0.00 2021-02-15 2021-03-08 2021-04-21 2021-05-21 2021-06-25 2021-12-22 structure pour la formation en and life skills training qualifications des d'exécution gestion consultants Sélection fondée 05/2021/PEJ-RIM / Project management, sur les En attente Développement du système IDA / V3030 A posteriori Open - National 0.00 2021-02-17 2021-03-10 2021-04-23 2021-05-23 2021-06-27 2021-12-24 monitoring, and evaluation qualifications des d'exécution de gestion de l'information consultants 06/2021/PEJ-RIM / Appui Sélection fondée des entreprises structurées et Project management, sur les En attente du secteur informel dans IDA / V3030 A posteriori Open - National 0.00 2021-03-18 2021-04-08 2021-05-22 2021-06-21 2021-07-26 2022-01-22 monitoring, and evaluation qualifications des d'exécution l'identification des besoins en consultants main d'œuvre ; Sélection fondée 07/2021/PEJ-RIM / Project management, sur les En attente Spécialiste en gestion du IDA / V3030 A posteriori Open - National 0.00 2021-02-17 2021-03-10 2021-04-23 2021-05-23 2021-06-27 2021-12-24 monitoring, and evaluation qualifications des d'exécution système d'information; consultants 08/2021/PEJ-RIM / Sélection fondée Conception et la mise en Project management, sur les En attente IDA / V3030 A posteriori Open - National 0.00 2021-02-18 2021-03-11 2021-04-24 2021-05-24 2021-06-28 2021-12-25 place d'un système de Suivi et monitoring, and evaluation qualifications des d'exécution évaluation projet PEJ consultants 01/2021/PEJ6RIM / Développement et mise en Sélection fondée œuvre d'un plan de Contingency emergency sur les En attente IDA / V3030 A posteriori Open - National 0.00 2021-02-19 2021-03-12 2021-04-25 2021-05-25 2021-06-29 2021-12-26 communication(stratégie response qualifications des d'exécution nationale et programme consultants d'inclusion économique) INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 09/2021/PEJ-RIM / Elaboration d'un manuel de Project management, En attente procédures administratives, IDA / V3030 A posteriori Individuel Open 0.00 2021-02-18 2021-04-08 2021-04-29 2021-06-03 2021-11-30 monitoring, and evaluation d'exécution financières et de passation des marchés du PEJ Page 1 10/2021/PEJ-RIM / Mission d'appui et d'accompagnement Project management, En attente pour la finalisation des IDA / V3030 A posteriori Individuel Direct 0.00 2021-02-04 2021-02-14 2021-03-07 2021-04-11 2021-10-08 monitoring, and evaluation d'exécution conditions de négociation du PEJ 11/2021/PEJ-RIM / Technical skills training and En attente Coordinateur technique du IDA / V3030 A posteriori Individuel Open 0.00 2021-02-18 2021-04-08 2021-04-29 2021-06-03 2021-11-30 internship d'exécution projet 12/2021/PEJ-RIM / Project management, En attente Spécialiste en passation de IDA / V3030 A posteriori Individuel Open 0.00 2021-02-18 2021-04-08 2021-04-29 2021-06-03 2021-11-30 monitoring, and evaluation d'exécution marchés du PEJ 13/2021/PEJ-RIM / Project management, En attente Responsable administratif et IDA / V3030 A posteriori Individuel Open 0.00 2021-02-04 2021-03-25 2021-04-15 2021-05-20 2021-11-16 monitoring, and evaluation d'exécution financier 14/2021/PEJ-RIM / Project management, En attente Spécialiste en suivi et IDA / V3030 A posteriori Individuel Open 0.00 2021-02-04 2021-03-25 2021-04-15 2021-05-20 2021-11-16 monitoring, and evaluation d'exécution évaluation 15/2021/PEJ-RIM / Spécialiste en formation Technical skills training and En attente IDA / V3030 A posteriori Individuel Open 0.00 2021-02-18 2021-04-08 2021-04-29 2021-06-03 2021-11-30 professionnelle et internship d'exécution entrepreneuriat 16/2021/PEJ-RIM / Consultant-e-s pour l’appui à la composante 3 micro- Orientation, job counseling, En attente entrepreneuriat pour les IDA / V3030 A posteriori Individuel Open 0.00 2021-02-04 2021-03-25 2021-04-15 2021-05-20 2021-11-16 and life skills training d'exécution activités génératrices de revenus, consultant individuel ; 17/2021/PEJ-RIM / Consultant-e-s pour l’appui à Fostering En attente la composante 2 (adaptation IDA / V3030 microentrepreneurship for A posteriori Individuel Open 0.00 2021-02-04 2021-03-25 2021-04-15 2021-05-20 2021-11-16 d'exécution et développement des outils income-generating activities de l'ingénierie de formation) ; 18/2021/PEJ-RIM / Project management, En attente IDA / V3030 A posteriori Individuel Open 0.00 2021-02-04 2021-03-25 2021-04-15 2021-05-20 2021-11-16 Spécialiste en communication monitoring, and evaluation d'exécution 19/2021/PEJ-RIM / Project management, En attente Spécialiste genre et IDA / V3030 A posteriori Individuel Open 0.00 2021-02-04 2021-03-25 2021-04-15 2021-05-20 2021-11-16 monitoring, and evaluation d'exécution sauvegardes sociales 20/2021/PEJ-RIM / Contingency emergency En attente Consultant-e pour l'extension IDA / V3030 A posteriori Individuel Open 0.00 2021-02-04 2021-03-25 2021-04-15 2021-05-20 2021-11-16 response d'exécution du SI de l'ANAPEJ 21/2021/PEJ-RIM / Project management, En attente IDA / V3030 A posteriori Individuel Open 0.00 2021-02-04 2021-03-25 2021-04-15 2021-05-20 2021-11-16 Comptable du PEJ monitoring, and evaluation d'exécution Page 2