Sample Procurement Plan I. General 1. Project Information : Disaster Risk Management and Urban Development Project (P145268) /Gouvernement de la République du Niger 2. Bank’s approval Date of the procurement Plan 19-oct.-15 3. Date of General Procurement Notice: March 17, 2015 4. Period covered by this procurement plan: Juillet 2017- Décembre 2018 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ 1,000,000 All 2. NCB (Goods) NA 3. ICB (Works) Above US$ 10 million All 4. NCB (Works) NA 5. (Non-Consultant Services) Above US$ 1,000,000 All [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: [Refer to the relevant CDD project implementation document approved by the Bank or delete if not applicable] 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project XYZ 04/01/2010 issued by 5. Any Other Special Procurement Arrangements: [including advance procurement and retroactive financing, if applicable] 5 ICB works packages will be financed under retroactive financing July 9, 2010 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Ref. Descripti Estimat Packages Domesti Review Comments No. on ed c by Bank Cost Prefere (Prior / US$ nce Post) million (yes/no) Summary 16.734 1 N/A Prior of the ICB (Work) Summary 0 0 N/A Post of the ICB (Goods) Summary 26.993 24 N/A Post of the NCB (Works) Summary 0.449 2 N/A Post of the NCB (Goods) Summary 0 0 N/A Post of the ICB (Non Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold (en US$ 1. Competitive Methods (Firms) Above US$ 500,000 2. Single Source (Firms) Above US$ 100,000 3. Individual (Comparison of CVs) Above US$ 100,000 Individual (Single source) Above US$ 200,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_200,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] July 9, 2010 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimat Package Review Comment of ed s by Bank s Assignmen Cost (Prior / t US$ Post) million Summary 3.124 11 Prior of number of contracts that will be let under QCBS Summary 1.886 18 Post CQS, of number CDS, I C of contracts that will be let under other methods July 9, 2010 PROCUREMENT Niger : Niger Disaster Risk Management and Urban Development Project PLAN General Information Country: Niger Bank’s Approval Date of the Original Procurement Plan: 2017-10-19 2021-07-28 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P145268 GPN Date: Project Name: Niger Disaster Risk Management and Urban Development Project Loan / Credit No: IDA / 53400, IDA / Q8620, IDA / 64130 Projet de Gestion des Risques de Catastrophes et de DéveloppementUrbain (PGRC-DU) Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned NE-PGRC-DU-21866-CW- RFB / TRAVAUX DE Comp. 1: Flood Risk Single Stage - One 1,926,017.1 2018-05- IDA / 53400 A posteriori Appel d'offres Open - National 1,666,666.00 Achevé 2017-07-25 2018-01-01 2017-07-30 2017-09-10 2017-08-14 2017-10-10 2017-12-25 2017-11-14 2018-01-31 REALISATION DE LA DIGUE Management Investments Envelope 3 13 ROUTE DE DOSSO NE-PGRC-DU-21896-CW- RFB / Réhabilitation et construction d'infrastructures Comp. 1: Flood Risk Single Stage - One 2018-05- IDA / 53400 A posteriori Appel d'offres Open - National 320,667.00 0.00 Annulé 2017-07-25 2017-07-30 2017-09-10 2017-10-10 2017-11-14 scolaires dans les zones Management Investments Envelope 13 touchées par les inondations à Diffa NE-PGRC-DU-22531-CW- RFB / REHABILITATION Comp. 1: Flood Risk Single Stage - One 2018-07- D'INFRASTRUCTURES IDA / 53400 A posteriori Appel d'offres Open - National 100,000.00 0.00 Annulé 2017-10-10 2017-10-15 2017-11-26 2017-12-26 2018-01-30 Management Investments Envelope 29 SCOLAIRES DANS LES REGIONS DE DOSSO ET TILLABERY NE-PGRC-DU-22568-CW- RFB / Construction Comp. 1: Flood Risk Single Stage - One 2018-07- IDA / 53400 A posteriori Appel d'offres Open - National 280,000.00 0.00 Annulé 2017-10-02 2017-10-07 2017-11-18 2017-12-18 2018-01-22 d'infrastructure scolaires et de Management Investments Envelope 21 sante à SENO NE-PGRC-DU-22586-CW- Comp. 1: Flood Risk Single Stage - One 2018-09- RFB / Travaux d'Extension du IDA / 53400 A posteriori Appel d'offres Open - National 430,000.00 0.00 Annulé 2017-12-04 2017-12-09 2018-01-20 2018-02-19 2018-03-26 Management Investments Envelope 22 réseau AEP à SENO NE-PGRC-DU-22598-CW- RFB / Réhabilitation des Comp. 1: Flood Risk Single Stage - One 2018-09- infrastructures scolaires dans IDA / 53400 A posteriori Appel d'offres Open - National 83,333.00 0.00 Annulé 2017-12-11 2017-12-16 2018-01-27 2018-02-26 2018-04-02 Management Investments Envelope 29 les Régions de Dosso et Tillabery NE-PGRC-DU-22601-CW- RFB / Travaux de construction Comp. 1: Flood Risk Single Stage - One 2018-07- du mur de clôture de l'Hôpital IDA / 53400 A posteriori Appel d'offres Open - National 141,667.00 0.00 Annulé 2017-10-02 2017-10-07 2017-11-18 2017-12-18 2018-01-22 Management Investments Envelope 21 de district de Kollo Région de Tillabéry NE-PGRC-DU-22611-CW- RFB / Travaux de construction Comp. 1: Flood Risk Single Stage - One 2018-08- de 10 blocs de 3 classes en IDA / 53400 A posteriori Appel d'offres Open - National 700,000.00 0.00 Annulé 2017-10-16 2017-10-21 2017-12-02 2018-01-01 2018-02-05 Management Investments Envelope 04 matériaux définitifs dans la Région de Diffa NE-PGRC-DU-22626-CW- Comp. 1: Flood Risk Single Stage - One 2019-01- RFB / Electrification de 23 IDA / 53400 A posteriori Appel d'offres Open - National 800,000.00 0.00 Annulé 2018-04-02 2018-04-07 2018-05-19 2018-06-18 2018-07-23 Management Investments Envelope 19 carrefours NE-PGRC-DU-22649-CW- RFB / Travaux de Comp. 1: Flood Risk Single Stage - One 2018-05- IDA / 53400 A priori Appel d'offres Open - National 6,000,000.00 0.00 Annulé 2017-07-28 2018-07-27 2017-08-02 2017-09-13 2017-10-13 2017-11-17 réhabilitation des AHA de Management Investments Envelope 16 DOSSO NE-PGRC-DU-22674-CW- RFB / Construction de Treize Comp. 1: Flood Risk Single Stage - One 2,028,538.5 2018-05- (13) Casernes de Sapeurs IDA / 53400 A posteriori Appel d'offres Open - National 3,453,443.00 Achevé 2017-07-28 2016-08-15 2017-08-02 2017-09-13 2016-09-02 2017-10-13 2016-10-26 2017-11-17 2017-03-01 Management Investments Envelope 5 16 Pompiers reparties sur les 4 Régions du Niger en 13 lots NE-PGRC-DU-22681-CW- RFB / Comp. 1: Flood Risk Single Stage - One 2018-05- Construction/renforcement 3 IDA / 53400 A posteriori Appel d'offres Open - National 2,795,280.00 0.00 Annulé 2017-07-28 2017-08-02 2017-09-13 2017-10-13 2017-11-17 Management Investments Envelope 16 Digues de protection a Niamey NE-PGRC-DU-22592-CW- RFB / Travaux de Comp. 1: Flood Risk Single Stage - One 2018-08- IDA / 53400 A posteriori Appel d'offres Open - National 1,666,667.00 0.00 Annulé 2017-11-06 2017-11-11 2017-12-23 2018-01-22 2018-02-26 réhabilitation des AHA de Management Investments Envelope 25 Diffa NE-PGRC-DU-34098-CW- RFB / Réalisation des travaux Comp. 1: Flood Risk Single Stage - One 2018-09- de Traitement des Koris de IDA / 53400 A posteriori Appel d'offres Open - National 2,000,000.00 0.00 Annulé 2017-12-01 2017-12-06 2018-01-17 2018-02-16 2018-03-23 Management Investments Envelope 19 Karma, Youri et Gourou Kaina en 3 lots, Region de Tillabery NE-PGRC-DU-48784-CW- RFB / Construction de CSI Type II à Kanya, d'une Comp. 1: Flood Risk Single Stage - One 2019-02- IDA / 53400 A posteriori Appel d'offres Open - National 1,000,000.00 0.00 Annulé 2018-04-30 2018-05-05 2018-06-16 2018-07-16 2018-08-20 maternité à Goubey et d'un Management Investments Envelope 16 mur de cloture à l'hôpital de district de Kollo NE-PGRC-DU-22620-CW- Comp. 1: Flood Risk Single Stage - One 2018-07- RFB / Construction de la route IDA / 53400 A posteriori Appel d'offres Open - National 4,000,000.00 0.00 Annulé 2017-09-25 2017-09-30 2017-11-11 2017-12-11 2018-01-15 Management Investments Envelope 14 Maine soroa-Gaidam Page 1 NE-PGRC-DU-22528-CW- RFB / Rehabilitation et construction d'INFRASTRUCTURES Comp. 1: Flood Risk Single Stage - One 2018-05- IDA / 53400 A posteriori Appel d'offres Open - National 997,917.00 0.00 Annulé 2017-07-28 2017-08-02 2017-09-13 2017-10-13 2017-11-17 SCOLAIRES ET SANITAIRES Management Investments Envelope 16 dans les zones touchées par les inondationsdans la region de Tillabéri NE-PGRC-DU-34095-CW- Comp. 1: Flood Risk Single Stage - One 2019-03- RFB / Travaux de réalisation IDA / 53400 A posteriori Appel d'offres Open - International 4,000,000.00 0.00 Annulé 2018-06-03 2018-06-08 2018-07-20 2018-08-19 2018-09-23 Management Investments Envelope 22 de la Route Mainé-Gaidam NE-PGRC-DU-22535-CW- Comp. 1: Flood Risk Single Stage - One 2018-11- RFB / Réalisation caniveaux de IDA / 53400 A posteriori Appel d'offres Open - National 1,833,333.00 0.00 Annulé 2018-02-05 2018-02-10 2018-03-24 2018-04-23 2018-05-28 Management Investments Envelope 24 Dosso NE-PGRC-DU-22512-CW- RFB / Viabilisation site de recasement SENO: blocs sanitaires LOT1, Construction et Equipement de classes (2 Comp. 1: Flood Risk Single Stage - One 2018-05- blocs de of six classes, bloc IDA / 53400 A posteriori Appel d'offres Open - National 1,558,333.00 0.00 Annulé 2017-07-28 2017-08-02 2017-09-13 2017-10-13 2017-11-17 Management Investments Envelope 16 administratif, case gardien, latrines et clôture) LO2, Construction de Centre de santé intégré de type II (avec maternité) NE-PGRC-DU-22554-CW- RFB / Travaux de réalisation Comp. 1: Flood Risk Single Stage - One 2018-09- IDA / 53400 A posteriori Appel d'offres Open - National 2,416,667.00 0.00 Annulé 2017-12-11 2017-12-16 2018-01-27 2018-02-26 2018-04-02 de forages, puits et caniveaux Management Investments Envelope 29 à Tillabery NE-PGRC-DU-57981-CW- RFQ / Fixation des dunes (clayonnage, plantations, Comp. 1: Flood Risk Single Stage - One 2018-12- ensemencement et IDA / Q8620 A posteriori Demande de prix Open - National 50,000.00 62,377.47 Achevé 2018-04-20 2018-06-15 2018-08-17 Management Investments Envelope 12 gardiennage) dans la Région de Diffa commune de Chetimari Zone N°1 NE-PGRC-DU-58098-CW- RFQ / Réalisation des regarnis sur les sites de récuperation Comp. 1: Flood Risk Single Stage - One 2018-12- IDA / Q8620 A posteriori Demande de prix Open - National 28,744.00 26,280.83 Achevé 2018-04-20 2018-07-17 2018-06-15 2018-08-02 de terres de 2015 et 2016 Management Investments Envelope 12 dans les départements de Loga et Tibiri (7 sites) NE-PGRC-DU-58096-CW- RFQ / Réalisation des regarnis sur les sites de récuperation Comp. 1: Flood Risk Single Stage - One 2018-12- IDA / Q8620 A posteriori Demande de prix Open - National 111,145.00 64,222.67 Achevé 2018-04-20 2018-07-17 2018-06-15 2018-08-06 de terres de 2015 et 2016 Management Investments Envelope 12 dans la région de Diffa (9 sites) NE-PGRC-DU-58076-CW- RFQ / Réalisation des regarnis sur les sites de récuperation Comp. 1: Flood Risk Single Stage - One 2018-12- IDA / Q8620 A posteriori Demande de prix Open - National 15,617.00 23,729.21 Achevé 2018-04-20 2018-06-15 2018-08-02 de terres de 2015 et 2016 Management Investments Envelope 12 dans les départements de Doutchi et Dosso (11 sites) NE-PGRC-DU-58100-CW- RFQ / Réalisation des regarnis sur les sites de récuperation Comp. 1: Flood Risk Single Stage - One 2018-12- IDA / Q8620 A posteriori Demande de prix Open - National 64,000.00 45,814.12 Achevé 2018-04-20 2018-06-15 2018-07-16 de terres de 2015 et 2016 Management Investments Envelope 12 dans le département de Mainé- Soroa (7 sites) NE-PGRC-DU-58101-CW- RFQ / Réalisation des regarnis sur les sites de récuperation Comp. 1: Flood Risk Single Stage - One 2018-12- IDA / Q8620 A posteriori Demande de prix Open - National 37,138.00 12,208.12 Achevé 2018-04-20 2018-06-15 2018-08-02 de terres de 2015 et 2016 Management Investments Envelope 12 dans les départements de Kollo et Niamey V (6 sites) NE-PGRC-DU-58106-CW- RFQ / Réalisation des regarnis sur les sites de récuperation Comp. 1: Flood Risk Single Stage - One 2018-12- IDA / Q8620 A posteriori Demande de prix Open - National 30,234.00 26,399.61 Achevé 2018-04-20 2018-07-17 2018-06-15 2018-08-02 de terres de 2015 et 2016 Management Investments Envelope 12 dans le département de Filingue (12 sites) NE-PGRC-DU-58103-CW- RFQ / Réalisation des regarnis sur les sites de récuperation Comp. 1: Flood Risk Single Stage - One 2018-12- IDA / Q8620 A posteriori Demande de prix Open - National 15,409.00 41,956.95 Achevé 2018-04-20 2018-06-15 2018-08-13 de terres de 2015 et 2016 Management Investments Envelope 12 dans les départements de Ouallam (9 sites) NE-PGRC-DU-58104-CW- RFQ / Réalisation des regarnis sur les sites de récuperation Comp. 1: Flood Risk Single Stage - One 2018-12- IDA / Q8620 A posteriori Demande de prix Open - National 16,398.00 42,224.84 Achevé 2018-04-20 2018-06-15 2018-08-02 de terres de 2015 et 2016 Management Investments Envelope 12 dans le département de Tillabery (8 sites) NE-PGRC-DU-58109-CW- RFQ / Réalisation des regarnis sur les sites de récuperation Comp. 1: Flood Risk Single Stage - One 2018-12- de terres de 2015 et 2016 IDA / Q8620 A posteriori Demande de prix Open - National 40,258.00 55,126.08 Achevé 2018-04-20 2018-07-17 2018-06-15 2018-08-10 Management Investments Envelope 12 dans les départements de Tera, Torodi et Bankilaré (9 sites) NE-PGRC-DU-57987-CW- RFQ / Fixation des dunes (clayonnage, plantations, Comp. 1: Flood Risk Single Stage - One 2018-12- ensemencement et IDA / Q8620 A posteriori Demande de prix Open - National 80,000.00 124,847.48 Achevé 2018-04-20 2018-06-15 2018-08-27 Management Investments Envelope 12 gardiennage) dans la Région de Diffa Commune de Chetimari Zone N°2 Page 2 NE-PGRC-DU-58051-CW- RFQ / Fixation des dunes (clayonnage, plantations, Comp. 1: Flood Risk Single Stage - One 2018-12- ensemencement et IDA / Q8620 A posteriori Demande de prix Open - National 60,000.00 124,831.28 Signé 2018-04-20 2018-06-15 2018-08-16 Management Investments Envelope 12 gardiennage) dans la Région de Diffa commune de Chetimari Zone 5 NE-PGRC-DU-58057-CW- RFQ / Fixation des dunes (clayonnage, plantations, Comp. 1: Flood Risk Single Stage - One 2018-12- ensemencement et IDA / Q8620 A posteriori Demande de prix Open - National 30,000.00 62,750.54 Achevé 2018-04-20 2018-06-15 2018-08-16 Management Investments Envelope 12 gardiennage) dans la Région de Diffa commune de Chetimari Zone 7 NE-PGRC-DU-58111-CW- RFQ / Réalisation de 75 km de Comp. 1: Flood Risk Single Stage - One En cours 2018-12- cordons de pierres sèches sur IDA / Q8620 A posteriori Demande de prix Open - National 37,500.00 0.00 2018-04-20 2018-06-15 Management Investments Envelope d'exécution 12 les versants des plateaux dans la Région de Tillabéry NE-PGRC-DU-58112-CW- RFQ / Réalisation de 75 km de Comp. 1: Flood Risk Single Stage - One En cours 2018-12- cordons de pierres sèches sur IDA / Q8620 A posteriori Demande de prix Open - National 37,500.00 0.00 2018-04-20 2018-06-15 Management Investments Envelope d'exécution 12 les versants des plateaux dans la Région de Dosso NE-PGRC-DU-58073-CW- RFQ / Réalisation des regarnis sur les sites de récuperation Comp. 1: Flood Risk Single Stage - One 2018-12- IDA / Q8620 A posteriori Demande de prix Open - National 41,652.00 29,706.83 Achevé 2018-04-20 2018-07-17 2018-06-15 2018-08-02 de terres de 2015 et 2016 Management Investments Envelope 12 dans les départements de Boboye et Dioudou (10 sites) NE-PGRC-DU-57993-CW- RFQ / Fixation des dunes (clayonnage, plantations, Comp. 1: Flood Risk Single Stage - One 2018-12- ensemencement et IDA / Q8620 A posteriori Demande de prix Open - National 80,000.00 62,768.43 Achevé 2018-04-20 2018-06-15 2018-08-16 Management Investments Envelope 12 gardiennage) dans la Région de Diffa commune de Chetimari Zone 3 NE-PGRC-DU-58041-CW- RFQ / Fixation des dunes (clayonnage, plantations, Comp. 1: Flood Risk Single Stage - One 2018-12- ensemencement et IDA / Q8620 A posteriori Demande de prix Open - National 120,000.00 62,124.13 Achevé 2018-04-20 2018-06-15 2018-08-16 Management Investments Envelope 12 gardiennage) dans la Région de Diffa commune de Chetimari Zone 3 NE-PGRC-DU-58060-CW- RFQ / Fixation des dunes (clayonnage, plantations, Comp. 1: Flood Risk Single Stage - One 2018-12- ensemencement et IDA / Q8620 A posteriori Demande de prix Open - National 80,000.00 62,246.44 Achevé 2018-04-20 2018-06-15 2018-08-16 Management Investments Envelope 12 gardiennage) dans la Région de Diffa commune de Chetimari Zone 6 NE-PGRC-DU-59864-CW- RFB / TRAVAUX DE REHABILITATION DES AMENAGEMENTS HYDRO- Comp. 1: Flood Risk Single Stage - One 16,734,385.0 16,657,746. 2017-11- IDA / 53400 A priori Appel d'offres Open - International Signé 2017-02-06 2017-02-11 2017-03-25 2017-04-24 2018-05-02 2017-05-29 2018-01-05 AGRICOLE Management Investments Envelope 0 32 25 DANS LES REGIONS DE TILLABERY ET NIAMEY EN 6 (SIX) LOTS NE-PGRC-DU-39244-CW- RFB / Travaux de réhabilitation des Comp. 1: Flood Risk Single Stage - One 16,734,385.0 2018-09- IDA / 53400 A priori Appel d'offres Open - International 0.00 Annulé 2017-12-04 2018-04-17 2017-12-09 2018-01-20 2018-02-19 2018-03-26 Aménagement Hydro Management Investments Envelope 0 22 Agricoles dans les Régions de Niamey et Tillabéry NE-PGRC-DU-22589-CW- RFB / TRAVAUX DE PROTECTION MECANIQUE DES Comp. 1: Flood Risk Single Stage - One 2018-12- IDA / 53400 A posteriori Appel d'offres Open - National 333,333.00 0.00 Annulé 2018-03-05 2018-04-30 2018-03-10 2018-04-21 2018-05-21 2018-06-25 BERGES DE KORIS (9 KORIS A Management Investments Envelope 22 NIAMEY, DO et TY + TAGABATTI ET YOURI NE-PGRC-DU-22561-CW- Comp. 1: Flood Risk Single Stage - One 2018-10- IDA / 53400 A posteriori Appel d'offres Open - National 500,000.00 0.00 Annulé 2017-12-18 2017-12-23 2018-02-03 2018-03-05 2018-04-09 RFB / Réalisation Piste SENO Management Investments Envelope 06 NE-PGRC-DU-103840-CW- RFB / Construction des Comp. 1: Flood Risk Single Stage - One 2020-01- IDA / 53400 A posteriori Appel d'offres Open - National 781,250.00 582,292.03 Achevé 2019-04-01 2019-06-12 2019-04-06 2019-06-12 2019-05-18 2019-07-10 2019-06-17 2019-07-30 2019-07-22 2019-09-10 caniveaux dans la région de Management Investments Envelope 18 Tillabéri NE-PGRC-DU-103785-CW- RFB / Installer des feux Comp. 2: Capacity Building Single Stage - One 2019-12- tricolores et passages cloutés IDA / 53400 for Urban Development and A posteriori Appel d'offres Open - National 572,916.67 494,525.02 Signé 2019-03-04 2019-03-07 2019-03-09 2019-04-20 2019-04-02 2019-05-20 2019-04-16 2019-06-24 2019-05-06 Envelope 21 au niveau de 23 carrefours de Disaster Risk Management la ville de Niamey NE-PGRC-DU-103831-CW- RFB / Travaux de Construire Comp. 1: Flood Risk Single Stage - One 2020-01- IDA / 53400 A posteriori Appel d'offres Open - National 684,027.78 783,695.23 Signé 2019-03-20 2019-06-17 2019-03-25 2019-06-19 2019-05-06 2019-07-17 2019-06-05 2019-07-30 2019-07-10 2019-09-23 des forages et puits villageois Management Investments Envelope 06 dans la région de Tillabéri NE-PGRC-DU-103819-CW- RFB / Réhabiliter les stations Comp. 1: Flood Risk Single Stage - One 2020-02- de pompage et de drainage de IDA / 53400 A posteriori Appel d'offres Open - National 868,055.56 948,715.39 Signé 2019-04-20 2020-01-23 2019-04-25 2020-04-10 2019-06-06 2020-05-14 2019-07-06 2020-06-09 2019-08-10 2020-09-17 Management Investments Envelope 06 l'AHA de Saga dans la région de Niamey NE-PGRC-DU-103833-CW- RFB / Construction de salles Comp. 1: Flood Risk Single Stage - One 2020-02- de classes en matériaux IDA / 53400 A posteriori Appel d'offres Open - National 260,416.67 260,873.12 Signé 2019-04-20 2019-05-20 2019-04-25 2019-05-21 2019-06-06 2019-06-24 2019-07-06 2019-07-10 2019-08-10 2019-09-03 Management Investments Envelope 06 définitifs dans la region de Diffa Page 3 NE-PGRC-DU-103795-CW- Comp. 1: Flood Risk Single Stage - One 2020-01- RFQ / Construction mur de IDA / 53400 A posteriori Demande de prix Limited 17,361.11 16,637.89 Achevé 2019-05-20 2019-08-30 2019-07-15 2019-09-27 Management Investments Envelope 11 clôture de l'école de Bandabari NE-PGRC-DU-103787-CW- RFQ / Construire le mur de Comp. 1: Flood Risk Single Stage - One 2020-01- IDA / 53400 A posteriori Demande de prix Limited 104,166.67 83,009.84 Achevé 2019-05-20 2019-08-22 2019-07-15 2019-09-26 clôture du l'Hopital de district Management Investments Envelope 11 de Kollo NE-PGRC-DU-103844-CW- Comp. 1: Flood Risk Single Stage - One 2020-01- RFQ / Construire une IDA / 53400 A posteriori Demande de prix Limited 104,166.67 84,073.65 Achevé 2019-05-20 2019-08-25 2019-07-15 2019-09-23 Management Investments Envelope 11 maternité à Goubey NE-PGRC-DU-103829-CW- RFQ / Réhabilitation de la Comp. 1: Flood Risk Single Stage - One 2020-01- IDA / 53400 A posteriori Demande de prix Limited 86,805.56 83,382.04 Achevé 2019-05-20 2019-08-19 2019-07-15 2019-11-12 case de santé de Ajé Muraba Management Investments Envelope 11 en CSI (Gaya) NE-PGRC-DU-103799-CW- Comp. 1: Flood Risk Single Stage - One 2020-01- RFQ / Construire le mur de IDA / 53400 A posteriori Demande de prix Limited 43,402.78 57,759.16 Achevé 2019-05-20 2019-08-22 2019-07-15 2019-09-26 Management Investments Envelope 11 cloture du CSI de Moussa Dey NE-PGRC-DU-103828-CW- RFQ / Réhabiliter du service Comp. 1: Flood Risk Single Stage - One 2020-01- IDA / 53400 A posteriori Demande de prix Limited 104,166.67 86,616.49 Achevé 2019-05-20 2019-08-19 2019-07-15 2019-10-02 des urgences de l'Hôpital de Management Investments Envelope 11 District de Mainé Soroa NE-PGRC-DU-103812-CW- RFB / Réaliser les travaux de Comp. 1: Flood Risk Single Stage - One 2020-02- IDA / 53400 A posteriori Appel d'offres Open - National 225,694.44 282,887.18 Signé 2019-04-20 2020-06-08 2019-04-25 2020-06-12 2019-06-06 2020-07-10 2019-07-06 2020-08-14 2019-08-10 2020-09-30 protection des berges des Management Investments Envelope 06 koris dans la région de Dosso NE-PGRC-DU-103813-CW- RFB / Réaliser les travaux de Comp. 1: Flood Risk Single Stage - One En attente 2020-02- protection des berges du kori IDA / 53400 A posteriori Appel d'offres Open - National 138,888.89 0.00 2019-04-20 2019-04-25 2019-06-06 2019-07-06 2019-08-10 Management Investments Envelope d'exécution 06 de Bangou Koira Zéno et Saga Fondo , région de Tillabéri NE-PGRC-DU-103794-CW- RFB / Travaux de realisation Comp. 1: Flood Risk Single Stage - One 2020-02- IDA / 53400 A posteriori Appel d'offres Open - National 319,444.44 459,054.58 Signé 2019-04-20 2020-01-24 2019-04-25 2020-01-29 2019-06-06 2020-02-27 2019-07-06 2020-03-24 2019-08-10 2020-04-21 de l'Ouvrage de Management Investments Envelope 06 franchissement de Sirfi Koira NE-PGRC-DU-103826-CW- RFB / Travaux de realisation Comp. 1: Flood Risk Single Stage - One 2020-04- des Ouvrages de protection IDA / 53400 A posteriori Appel d'offres Open - National 781,250.00 985,222.89 Achevé 2019-07-03 2019-04-16 2019-07-08 2019-05-15 2019-08-19 2019-05-15 2019-09-18 2019-06-07 2019-10-23 2019-07-07 Management Investments Envelope 20 dans les régions d'Agadez et Tahoua NE-PGRC-DU-103832-CW- RFQ / Selection des ONGs pour la realisation des Comp. 1: Flood Risk Single Stage - One 2019-12- IDA / 53400 A posteriori Demande de prix Limited 170,000.00 235,466.15 Signé 2019-04-25 2019-06-11 2019-06-20 2019-08-27 activités de renforcement des Management Investments Envelope 17 fixations des dunes sur 300 HA en 3 Lot à Diffa NE-PGRC-DU-103825-CW- Comp. 1: Flood Risk Single Stage - One 2020-02- RFB / Travaux de Construction IDA / 53400 A posteriori Demande de prix Open - National 187,500.00 0.00 Annulé 2019-06-30 2019-08-25 Management Investments Envelope 21 puits villageois Dosso NE-PGRC-DU-103791-CW- RFQ / Selection des ONGs Comp. 1: Flood Risk Single Stage - One En attente 2019-12- pour Assurer le regarnis des IDA / Q8620 A posteriori Demande de prix Limited 138,888.89 0.00 2019-04-25 2019-06-20 Management Investments Envelope d'exécution 17 sites de restauration des terres de 2015,2016 et 2017 NE-PGRC-DU-34154-CW- RFB / travaux Passation de supplémentaires de Comp. 1: Flood Risk 2018-08- IDA / 53400 A posteriori marché de gré à Direct 44,560.00 0.00 Annulé 2018-01-08 2018-01-13 2018-02-17 rehabilitation des routes en Management Investments 16 gré terres Région de Dosso Lot 2: SIA-ADIGA-KAWRAN DEBE (31 km) NE-PGRC-DU-22521-CW- RFB / Rehabilitation ou construction de latrines dans Comp. 1: Flood Risk Single Stage - One 2018-05- IDA / 53400 A posteriori Appel d'offres Open - National 333,333.00 0.00 Annulé 2017-07-28 2017-08-02 2017-09-13 2017-10-13 2017-11-17 les zones touchées par les Management Investments Envelope 16 inondations dans la Région de Tillabéri NE-PGRC-DU-22624-CW- Comp. 1: Flood Risk Single Stage - One 2018-11- RFB / Travaux de construction IDA / 53400 A posteriori Appel d'offres Open - National 1,000,000.00 0.00 Annulé 2018-02-05 2018-02-10 2018-03-24 2018-04-23 2018-05-28 Management Investments Envelope 24 de la Digue de DIFFA NE-PGRC-DU-22547-CW- RFB / Travaux de réalisation Comp. 1: Flood Risk Single Stage - One 2018-08- IDA / 53400 A posteriori Appel d'offres Open - National 450,000.00 0.00 Annulé 2017-11-06 2017-11-11 2017-12-23 2018-01-22 2018-02-26 de de Puits et Mini AEP dans la Management Investments Envelope 25 Région de Diffa NE-PGRC-DU-103839-CW- RFQ / Construire le mur de Comp. 1: Flood Risk Single Stage - One 2020-01- IDA / 53400 A posteriori Demande de prix Limited 86,805.56 0.00 Annulé 2019-05-20 2019-07-15 clôture du l'Hopital de district Management Investments Envelope 11 de Kollo NE-PGRC-DU-138616-CW- RFQ / Construction d'un mur Comp. 2: Capacity Building Single Stage - One 2020-06- de clôture de la Caserne de IDA / Q8620 for Urban Development and A posteriori Demande de prix Limited 60,000.00 55,142.76 Signé 2019-10-20 2019-12-05 2019-12-15 2020-01-08 Envelope 12 Sapeurs Pompiers de la ville Disaster Risk Management de Diffa NE-PGRC-DU-103842-CW- RFB / Réalisation des Collecteurs Prioritaires du Comp. 1: Flood Risk Single Stage - One 2,432,852.9 2020-09- IDA / 53400 A posteriori Appel d'offres Open - National 2,400,000.00 Signé 2019-11-17 2019-12-09 2019-11-22 2019-12-10 2020-01-03 2020-01-17 2020-02-02 2020-02-13 2020-03-08 2020-03-12 Bassin versant S3 dans Management Investments Envelope 6 04 l’Arrondissement Communal n°1 de Niamey NE-PGRC-DU-145434-CW- RFB / Travaux de construction Comp. 1: Flood Risk Single Stage - One 2020-09- IDA / 53400 A posteriori Appel d'offres Open - National 220,000.00 191,818.82 Signé 2019-11-14 2019-09-23 2019-11-19 2020-01-09 2019-12-31 2019-11-18 2020-01-30 2019-12-19 2020-03-05 2020-02-13 de 10 puits cimentés dans la Management Investments Envelope 01 Région de Dosso Page 4 NE-PGRC-DU-151386-CW- RFB / Travaux de pose de Pierres sèches et gabions Comp. 1: Flood Risk Single Stage - One 2020-11- 4350 m/l sur les sites de IDA / 53400 A posteriori Appel d'offres Open - National 945,455.00 364,234.40 Signé 2020-01-20 2021-04-09 2020-01-25 2021-04-09 2020-03-07 2021-05-13 2020-04-06 2021-05-25 2020-05-11 2021-07-07 Management Investments Envelope 07 TAGAZAR, BOGHOL, ELIWALANE à Tirozerine Region d'Agadez NE-PGRC-DU-151515-CW- RFQ / Ouvrage d’épandage Comp. 1: Flood Risk Single Stage - One En attente 2020-10- sur des terres pastorales  à IDA / 64130 A posteriori Demande de prix Limited 181,818.00 0.00 2020-02-20 2020-04-16 Management Investments Envelope d'exécution 13 Agarégaré (INGALL) Region d'Agadez : NE-PGRC-DU-151414-CW- RFB / Travaux de réalisation Comp. 1: Flood Risk Single Stage - One En attente 2020-12- IDA / 64130 A posteriori Appel d'offres Open - National 263,636.00 0.00 2020-02-15 2020-02-20 2020-04-02 2020-05-02 2020-06-06 de 800 ml de canivaux dans la Management Investments Envelope d'exécution 03 Ville de Tahoua NE-PGRC-DU-151421-CW- RFB / Travaux de pavage de Comp. 1: Flood Risk Single Stage - One En attente 2020-12- rue (9km)/ chaussées IDA / 64130 A posteriori Appel d'offres Open - National 589,091.00 0.00 2020-02-15 2020-02-20 2020-04-02 2020-05-02 2020-06-06 Management Investments Envelope d'exécution 03 drainantes dans la Ville de Tahoua NE-PGRC-DU-151419-CW- RFQ / Travaux de Comp. 1: Flood Risk Single Stage - One En attente 2020-11- rehabilitation de 20 puits IDA / 64130 A posteriori Demande de prix Limited 63,636.00 0.00 2020-03-20 2020-05-15 Management Investments Envelope d'exécution 11 maraichers (complement) à Iferouna Région d'Agadez NE-PGRC-DU-151415-CW- RFB / Travaux d'Aménagements mare de Comp. 1: Flood Risk Single Stage - One En attente 2020-12- Babaye (Endiguement IDA / 64130 A posteriori Appel d'offres Open - National 530,000.00 0.00 2020-02-15 2020-02-20 2020-04-02 2020-05-02 2020-06-06 Management Investments Envelope d'exécution 03 &plantation) et travaux de traitement de Koris de Maboya Amaré (Region de Tahoua) NE-PGRC-DU-151361-CW- RFB / Travaux de Construction Comp. 1: Flood Risk Single Stage - One En attente 2020-12- de 2250 ml de chaussées IDA / 64130 A posteriori Appel d'offres Open - National 586,364.00 0.00 2020-03-10 2020-03-15 2020-04-26 2020-05-26 2020-06-30 Management Investments Envelope d'exécution 27 drainantes dans la Ville de Konni Region de Tahoua NE-PGRC-DU-151416-CW- Comp. 2: Capacity Building RFQ / Rehabilitation des salles Single Stage - One En attente 2020-11- IDA / 64130 for Urban Development and A posteriori Demande de prix Limited 36,000.00 0.00 2020-03-15 2020-05-10 de classes à Loubé Envelope d'exécution 06 Disaster Risk Management (Deoulé/Bouza) NE-PGRC-DU-151387-GO- RFB / Traitement mécanique et biologique le plateau et les Comp. 1: Flood Risk Single Stage - One En attente 2020-12- berges du Koris à Loubé IDA / 53400 A posteriori Appel d'offres Open - National 345,455.00 0.00 2020-03-10 2020-03-15 2020-04-26 2020-05-26 2020-06-30 Management Investments Envelope d'exécution 27 /Bouza commune rurale de Déoulé et à Bado dans la commune d’Illéla NE-PGRC-DU-151364-CW- RFQ / Travaux de Comp. 1: Flood Risk Single Stage - One En attente 2020-11- IDA / 64130 A posteriori Demande de prix Limited 127,273.00 0.00 2020-03-15 2020-05-10 construction d’un seuil radier Management Investments Envelope d'exécution 06 à Toumboul commune d’Illéla NE-PGRC-DU-151359-CW- Comp. 1: Flood Risk Single Stage - One 2020-12- RFQ / Activité de fixation des IDA / Q8620 A posteriori Demande de prix Limited 181,000.00 132,369.56 Signé 2020-04-15 2020-08-17 2020-06-10 2020-09-30 Management Investments Envelope 07 dunes dans la Région de Diffa NE-PGRC-DU-151516-CW- RFQ / Travaux de Comp. 1: Flood Risk Single Stage - One 2020-11- IDA / 53400 A posteriori Demande de prix Limited 109,000.00 90,865.66 Signé 2020-03-15 2020-02-25 2020-05-10 2020-04-09 construction d’un seuil radier Management Investments Envelope 06 à Kourki et Safar Banqui (Tera) NE-PGRC-DU-151411-CW- RFQ / Travaux de Comp. 1: Flood Risk Single Stage - One En attente 2020-11- réhabilitation de 750 ml de IDA / 64130 A posteriori Demande de prix Limited 68,182.00 0.00 2020-03-15 2020-05-10 Management Investments Envelope d'exécution 06 caniveaux dans la ville de Konni NE-PGRC-DU-153648-CW- RFQ / Appui à l'amélioration et construction des latrines Comp. 1: Flood Risk Single Stage - One En cours 2020-09- IDA / 64130 A posteriori Demande de prix Limited 181,818.00 123,036.14 2020-01-22 2020-04-09 2020-03-18 familiales (500 latrines) au Management Investments Envelope d'exécution 14 profit des menages sur les sites de déplacés NE-PGRC-DU-151409-CW- RFB / Travaux de construction Comp. 1: Flood Risk Single Stage - One 2021-03- IDA / 64130 A posteriori Appel d'offres Open - National 498,545.00 378,475.52 Signé 2020-05-18 2020-08-27 2020-05-23 2020-09-11 2020-07-04 2021-01-28 2020-08-03 2021-02-23 2020-09-07 2021-03-26 de la cité de l'Innovation sur le Management Investments Envelope 06 site de Sadoré (ANSI) NE-PGRC-DU-151423-CW- RFB / Comp. 1: Flood Risk Single Stage - One 2021-02- Construction/Equipement de IDA / 64130 A posteriori Appel d'offres Open - National 400,000.00 352,740.85 Signé 2020-04-29 2020-10-21 2020-05-04 2020-11-02 2020-06-15 2020-12-02 2020-07-15 2021-02-22 2020-08-19 2021-04-14 Management Investments Envelope 15 20 salles de classes dans la Région d'Agadez NE-PGRC-DU-151418-CW- RFB / Amenagement de la mare de Maboya Amare et Comp. 1: Flood Risk Single Stage - One En attente 2021-01- IDA / 64130 A posteriori Appel d'offres Open - National 267,273.00 0.00 2020-03-16 2020-03-21 2020-05-02 2020-06-01 2020-07-06 Traitement biologique du Management Investments Envelope d'exécution 02 plateau de Koloma et Koureya Commune Urbaine de Tahoua NE-PGRC-DU-171206-CW- RFQ / Travaux de Comp. 1: Flood Risk Single Stage - One 2021-01- construction d'un mur de IDA / 53400 A posteriori Demande de prix Limited 30,000.00 32,361.98 Signé 2020-05-15 2020-06-02 2020-07-10 2020-08-06 Management Investments Envelope 06 clôture de la caserne de sapeurs pompiers de la ville de Gaya Page 5 NE-PGRC-DU-171649-CW- RFQ / Travaux de Nettoyage Comp. 1: Flood Risk Single Stage - One 2021-01- du lit mineur du Kori en vue IDA / 64130 A posteriori Demande de prix Limited 52,000.00 53,715.39 Signé 2020-05-16 2020-04-21 2020-07-11 2020-06-29 Management Investments Envelope 07 de la protection de la digue d'Iférouane NE-PGRC-DU-185456-CW- RFQ / Travaux d’aménagement de passage Comp. 1: Flood Risk Single Stage - One En attente 2021-04- IDA / 53400 A posteriori Demande de prix Limited 28,000.00 0.00 2020-08-09 2020-10-04 cloutés autour des feux Management Investments Envelope d'exécution 02 optiques solaires réalisés par le PGRC DU NE-PGRC-DU-185463-CW- RFQ / Travaux de réalisation d'un ouvrage hydraulique (Puit Comp. 1: Flood Risk Single Stage - One 2021-04- IDA / 53400 A posteriori Demande de prix Limited 55,000.00 64,648.82 Signé 2020-09-02 2020-12-15 2020-10-28 2021-02-03 pastoral) à dans le Management Investments Envelope 26 Département de NGOURTI (Diffa) NE-PGRC-DU-185476-CW- RFQ / Travaux de realisation Comp. 1: Flood Risk Single Stage - One 2021-04- IDA / 64130 A posteriori Demande de prix Limited 90,000.00 95,584.96 Signé 2020-08-16 2020-09-04 2020-10-11 2020-11-25 du CSI de Kehel Departement Management Investments Envelope 09 de Gaya NE-PGRC-DU-185627-CW- RFQ / Travaux d'amenagement des terrains de cultures dans le cadre de la Comp. 1: Flood Risk Single Stage - One En attente 2021-06- IDA / 64130 A posteriori Demande de prix Limited 30,000.00 0.00 2020-10-11 2020-12-06 mise en oeuvre des mesures Management Investments Envelope d'exécution 04 sociales autour de l'Amenagement Hydro Agricole de DAIKAINA Region de Tillabery NE-PGRC-DU-103792-CW- RFQ / Traitement mécanique Comp. 1: Flood Risk Single Stage - One 2019-12- IDA / Q8620 A posteriori Demande de prix Limited 52,083.33 0.00 Annulé 2019-04-25 2019-06-20 et biologique du plateau et du Management Investments Envelope 17 bassin versant de Youri NE-PGRC-DU-185475-CW- RFQ / Travaux de Comp. 1: Flood Risk Single Stage - One En attente 2021-07- IDA / 64130 A posteriori Demande de prix Limited 50,000.00 0.00 2020-11-22 2021-01-17 Rehaussement de la Digue de Management Investments Envelope d'exécution 16 NDOUNGA GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NE-PGRC-DU-22700-GO- RFB / Fournitures pour l'Assainissement Piloté par les Comp. 1: Flood Risk Single Stage - One IDA / 53400 A posteriori Appel d'offres Open - National 360,000.00 0.00 Annulé 2017-08-25 2017-08-30 2017-10-11 2017-11-10 2017-12-15 2018-06-13 Communautés (ATPC) dans les Management Investments Envelope régions de Diffa, Tillabéri, Dosso NE-PGRC-DU-34106-GO- RFB / Fourniture et installation de panneaux de signalisation et rehabilitation Comp. 1: Flood Risk Single Stage - One IDA / 53400 A posteriori Appel d'offres Open - International 800,000.00 968,388.84 Signé 2017-12-04 2018-01-02 2017-12-09 2018-01-20 2019-04-02 2018-02-19 2019-04-19 2018-03-26 2019-05-02 2018-09-22 de 42 feux tricolores avec Management Investments Envelope amenagement des passages cloutés à proximité des feux dans la ville de Niamey NE-PGRC-DU-34111-GO- RFB / Acquisition de divers Comp. 1: Flood Risk Single Stage - One materiels informatiques et IDA / 53400 A posteriori Appel d'offres Open - National 200,000.00 0.00 Annulé 2017-11-15 2017-11-20 2018-01-01 2018-01-31 2018-03-07 2018-09-03 Management Investments Envelope mobiliers au profit des partennaires du PGRC-DU NE-PGRC-DU-34117-GO- RFQ / Acquisition de Comp. 1: Flood Risk Single Stage - One mobiliers pour equiper 9 IDA / 53400 A posteriori Demande de prix Limited 27,000.00 19,517.66 Achevé 2017-11-20 2018-01-15 2018-01-24 2018-07-14 2018-08-07 Management Investments Envelope salles de classe dans la Région de Diffa NE-PGRC-DU-34142-GO- RFQ / Acquisition de Comp. 1: Flood Risk Single Stage - One mobiliers pour equiper 6 IDA / 53400 A posteriori Demande de prix Limited 10,000.00 27,708.96 Achevé 2017-11-20 2018-08-14 2018-01-15 2018-02-06 2018-07-14 2018-04-12 Management Investments Envelope salles de classe dans la Région de Tillabery NE-PGRC-DU-34091-GO-DIR / Travaux de fourniture et Passation de Comp. 1: Flood Risk pose de 80 panneaux de IDA / 53400 A posteriori marché de gré à Direct 40,000.00 0.00 Annulé 2017-11-15 2017-11-20 2017-12-25 2018-06-23 Management Investments signalisation pour les 40 mini gré AEP solaire de Diffa NE-PGRC-DU-48782-GO- RFB / Acquisition des Comp. 1: Flood Risk Single Stage - One équipements de recyclage des IDA / 53400 A posteriori Appel d'offres Open - International 200,000.00 160,045.69 Achevé 2018-05-15 2018-10-09 2018-05-20 2018-10-15 2018-07-01 2018-10-23 2018-07-31 2018-12-06 2018-09-04 2019-01-21 2019-03-03 2019-12-10 Management Investments Envelope déchets plastiques dans les communes urbaines NE-PGRC-DU-32968-GO- RFB / Fourniture de 1072 pompes solaires installation Comp. 4: Contingency Single Stage - One et formation des utilisateurs IDA / 53400 A priori Appel d'offres Open - International 5,788,800.00 4,347,188.22 Signé 2018-02-27 2018-04-18 2018-03-04 2018-04-27 2018-04-15 2018-06-18 2018-05-15 2018-10-16 2018-06-19 2018-12-26 2018-12-16 Component Envelope dans les Régions de Tahoua et Agadez dans le cadre du MRI- 2017 NE-PGRC-DU-50933-GO- Comp. 1: Flood Risk Single Stage - One RFQ / Acquisition des gadgets IDA / 53400 A posteriori Demande de prix Limited 26,000.00 25,924.94 Achevé 2018-03-03 2018-02-27 2018-04-28 2018-03-20 2018-10-25 2018-05-17 Management Investments Envelope publicitaires 2018 Page 6 NE-PGRC-DU-49754-GO-DIR / Acquisition de 3 cameras Passation de d'évaluation de catastrophes Comp. 1: Flood Risk IDA / 53400 A posteriori marché de gré à Direct 69,900.00 59,954.94 Achevé 2018-02-28 2018-04-17 2018-03-05 2018-04-09 2018-04-09 2018-04-26 2018-10-06 2018-07-12 et formation des agents de la Management Investments gré protection civile sur leur utilisation NE-PGRC-DU-54042-GO- RFQ / Acquisition des Comp. 1: Flood Risk Single Stage - One semences et l'ensemencement IDA / Q8620 A posteriori Demande de prix Limited 100,000.00 73,458.42 Achevé 2018-04-14 2018-07-18 2018-06-09 2018-08-07 2018-12-06 2018-08-15 Management Investments Envelope des sites de récupération des terres de 2015, 2016 et 2017 NE-PGRC-DU-54044-GO- RFQ / Acquisition des Pneu Comp. 1: Flood Risk Single Stage - One IDA / 53400 A posteriori Demande de prix Limited 6,500.00 6,100.68 Achevé 2018-03-24 2018-04-26 2018-05-19 2018-04-25 2018-11-15 2018-06-21 pour le Parc des UEP ( Management Investments Envelope Tillabéry et Dosso) NE-PGRC-DU-80731-GO- RFQ / Acquisition d'Equipement et de matériel Comp. 1: Flood Risk Single Stage - One informatique pour IDA / 53400 A posteriori Demande de prix Limited 60,000.00 60,996.79 Achevé 2018-10-25 2018-12-19 2018-12-20 2019-01-07 2019-06-18 2019-02-14 Management Investments Envelope l'opérationnalisation SAP- DNPGCA et des dispositifs locaux d'alerte précoce. NE-PGRC-DU-80656-GO- RFQ / Acquisition et installation des lampes Comp. 1: Flood Risk Single Stage - One IDA / 53400 A posteriori Demande de prix Limited 56,000.00 51,884.03 Achevé 2018-10-25 2018-11-22 2018-12-20 2018-12-06 2019-06-18 2019-06-26 solaires dans la ville de Management Investments Envelope Niamey en appui au programme Niamey Nyalla NE-PGRC-DU-80707-GO- Comp. 1: Flood Risk Single Stage - One RFQ / Acquisition de Gabgets IDA / 53400 A posteriori Demande de prix Limited 18,200.00 16,858.11 Achevé 2018-11-04 2018-12-05 2018-12-30 2018-12-26 2019-06-28 2019-03-04 Management Investments Envelope publicitaires 2019 NE-PGRC-DU-103808-GO- RFB / Acquisition des materiaux pour l'appui à Comp. 1: Flood Risk Single Stage - One IDA / 53400 A posteriori Appel d'offres Open - National 120,000.00 140,874.28 Achevé 2019-04-15 2020-03-26 2019-04-20 2020-03-26 2019-06-01 2020-04-27 2019-07-01 2020-06-29 2019-08-05 2020-08-07 2020-02-01 2020-10-06 l'amélioration des latrines Management Investments Envelope familiales dans les régions de Diffa, Dosso et Tillabéri NE-PGRC-DU-103836-GO- RFQ / Assurer l'acquisition des semences et Comp. 1: Flood Risk Single Stage - One En cours IDA / Q8620 A posteriori Demande de prix Limited 34,722.22 0.00 2019-04-27 2019-08-02 2019-06-22 2019-12-19 l'ensemencement des sites de Management Investments Envelope d'exécution récupération des terres de 2015, 2016; et 2017 NE-PGRC-DU-103834-GO- RFQ / Acquisition de mobilier Comp. 1: Flood Risk Single Stage - One IDA / 53400 A posteriori Demande de prix Limited 5,208.33 0.00 Annulé 2019-05-20 2019-07-15 2020-01-11 de bureau pour les UEP de Management Investments Envelope Tahoua et Agadez NE-PGRC-DU-103843-GO- RFQ / Acquisition de serveurs Comp. 1: Flood Risk Single Stage - One et les equipements IDA / 53400 A posteriori Demande de prix Limited 26,041.67 27,879.73 Achevé 2019-04-25 2019-05-20 2019-06-20 2019-05-26 2019-12-17 2019-08-08 Management Investments Envelope accessoires pour la base des données PGRC-DU NE-PGRC-DU-103796-GO- RFQ / Acquisition des Comp. 2: Capacity Building Single Stage - One equipements informatique IDA / 53400 for Urban Development and A posteriori Demande de prix Open - National 475,694.00 553,813.84 Signé 2019-07-13 2019-12-30 2019-09-07 2020-04-16 2020-03-05 Envelope pour les partennaires dans le Disaster Risk Management cadre de la composante NTIC NE-PGRC-DU-103827-GO- RFQ / Acquisition des Autres Comp. 1: Flood Risk Single Stage - One En attente équipements techniques IDA / 53400 A posteriori Demande de prix Open - National 63,574.00 0.00 2019-07-06 2019-08-31 2020-02-27 Management Investments Envelope d'exécution (Ondulaire, projecteur vidéo, panneau solaire) NTIC NE-PGRC-DU-103807-GO- Comp. 1: Flood Risk Single Stage - One RFB / Acquisition de drones IDA / 53400 A posteriori Appel d'offres Open - International 118,924.00 159,342.71 Signé 2019-07-01 2020-06-25 2019-07-06 2020-06-26 2019-08-17 2020-08-07 2019-09-16 2021-02-16 2019-10-21 2021-03-29 2020-04-18 Management Investments Envelope pour les partenaires NTIC NE-PGRC-DU-103823-GO- RFB / Acquisition du matériel Comp. 1: Flood Risk Single Stage - One d’assainissement pour les IDA / 53400 A posteriori Appel d'offres Open - International 781,250.00 793,664.65 Signé 2019-07-08 2020-06-09 2019-07-13 2020-06-12 2019-08-24 2020-07-13 2019-09-23 2020-08-14 2019-10-28 2020-09-30 2020-04-25 Management Investments Envelope communes urbaines d’Agadez et de Tahoua NE-PGRC-DU-103810-GO- Comp. 1: Flood Risk Single Stage - One En attente RFB / Acquisition de materiel IDA / 53400 A posteriori Demande de prix Open - National 88,585.00 0.00 2019-07-20 2019-09-14 2020-03-12 Management Investments Envelope d'exécution de cartographie NTIC NE-PGRC-DU-54058-GO- RFQ / Acquisition fourniture Comp. 1: Flood Risk Single Stage - One IDA / 53400 A posteriori Demande de prix Limited 5,500.00 0.00 Annulé 2018-03-31 2018-05-26 2018-11-22 de bureau UCP et UEP (Diffa, Management Investments Envelope Dosso et Tillabéry) NE-PGRC-DU-138597-GO- RFQ / Acquisition des intrants (semences de riz, semences potagères et engrais) pour Comp. 1: Flood Risk Single Stage - One appuyer les producteurs IDA / Q8620 A posteriori Demande de prix Limited 35,000.00 38,504.41 Achevé 2019-10-08 2019-06-17 2019-12-03 2019-08-15 2020-05-31 2019-08-19 Management Investments Envelope opérant autour des Aménagements Hydro Agricoles de la Région de Tillabery. NE-PGRC-DU-138610-GO- RFQ / acquisition des plants Comp. 1: Flood Risk Single Stage - One En attente IDA / Q8620 A posteriori Demande de prix Limited 73,000.00 0.00 2019-10-20 2019-12-15 2020-06-12 pour les activités de regarnis Management Investments Envelope d'exécution 2019 NE-PGRC-DU-34100-GO- RFB / Fourniture et Comp. 1: Flood Risk Single Stage - One installation de deux (02) IDA / 53400 A posteriori Appel d'offres Open - National 140,000.00 0.00 Annulé 2017-11-07 2018-07-01 2017-11-12 2017-12-24 2018-05-31 2018-01-23 2018-07-06 2018-02-27 2018-08-26 Management Investments Envelope groupes électrogénes au profit du MAH/GC et l'UEP de Diffa Page 7 NE-PGRC-DU-145419-GO- Comp. 3: Project Single Stage - One RFQ / Acquisition des gadgets IDA / 64130 A posteriori Demande de prix Limited 20,000.00 0.00 Annulé 2019-11-26 2020-01-21 2020-07-19 Management Envelope publicitaires 2020 NE-PGRC-DU-151417-GO- Comp. 2: Capacity Building RFQ / Acquisition des Autres Single Stage - One En cours IDA / 64130 for Urban Development and A posteriori Demande de prix Limited 65,455.00 0.00 2020-03-15 2021-01-14 2020-05-10 2020-11-06 équipements techniques Envelope d'exécution Disaster Risk Management (panneaux solaires) NTIC NE-PGRC-DU-151396-GO- RFB / Acquisition de matériels Comp. 1: Flood Risk Single Stage - One informatiques et mobiliers de IDA / 64130 A posteriori Appel d'offres Open - National 360,000.00 287,360.47 Signé 2020-04-20 2020-08-11 2020-04-25 2020-08-14 2020-06-06 2020-09-18 2020-07-06 2020-12-02 2020-08-10 2021-02-09 2021-02-06 Management Investments Envelope bureau pour équiper le coding academy de l'ANSI NE-PGRC-DU-151413-GO- RFQ / Acquisition des equipements Comp. 2: Capacity Building Single Stage - One complementaires IDA / 53400 for Urban Development and A posteriori Demande de prix Limited 27,000.00 30,893.59 Achevé 2020-01-15 2020-04-23 2020-03-11 2020-05-27 2020-09-07 2020-07-28 Envelope (ordinateurs, imprimantes, Disaster Risk Management panneaux solaires) pour l'operationalisation SAP à travers les OSV/SCAP/RU NE-PGRC-DU-153645-GO- RFQ / Acquisition de 10 Kits Comp. 1: Flood Risk Single Stage - One IDA / 64130 A posteriori Demande de prix Limited 27,000.00 46,577.03 Achevé 2020-01-22 2020-03-12 2020-03-18 2020-03-29 2020-09-14 2020-11-04 sanitaires pour la région de Management Investments Envelope Diffa NE-PGRC-DU-151512-GO- RFQ / Acquisition de Comp. 2: Capacity Building Single Stage - One En attente consomables informatiques IDA / 64130 for Urban Development and A posteriori Appel d'offres Open - National 130,000.00 0.00 2020-03-15 2020-03-20 2020-05-01 2020-05-31 2020-07-05 2021-01-01 Envelope d'exécution pour les partennaires dans le Disaster Risk Management cadre de la composante NTIC NE-PGRC-DU-153650-GO- RFQ / Acquisitions de 334 motopompes dans le cadre des Travaux d'amenagement Comp. 4: Contingency Single Stage - One de 5ha de sites maraichers IDA / Q8620 A posteriori Demande de prix Limited 182,000.00 157,928.35 Achevé 2020-01-22 2020-02-07 2020-03-18 2020-02-18 2020-09-14 2020-08-10 Component Envelope féminins et la réhabilitation de 152 ha d’aménagement hydro agricole le long de la Komadougou NE-PGRC-DU-160891-GO- RFB / Appui à l'amélioration des latrines familiales au Comp. 2: Capacity Building Single Stage - One profit des ménages sur les IDA / 64130 for Urban Development and A posteriori Appel d'offres Open - National 120,000.00 0.00 Annulé 2020-02-24 2020-02-26 2020-04-08 2020-05-08 2020-06-12 2020-12-09 Envelope sites de déplacés (acquisition Disaster Risk Management de matériels et matériaux de construction) NE-PGRC-DU-151513-GO- RFQ / Acquisition de Drones Comp. 1: Flood Risk Single Stage - One pour la Direction de la IDA / 64130 A posteriori Demande de prix Limited 54,545.00 0.00 Annulé 2020-03-15 2020-05-10 2020-11-06 Management Investments Envelope Protection Civile dans le cadre de la composante NTIC NE-PGRC-DU-185477-GO- RFQ / Acquisition et installation d'un groupe Comp. 2: Capacity Building électrogène au Profit du Single Stage - One IDA / 53400 for Urban Development and A posteriori Demande de prix Limited 50,000.00 64,316.56 Achevé 2020-08-16 2020-09-29 2020-10-11 2020-10-14 2021-04-09 2020-10-27 Ministère de l'Action Envelope Disaster Risk Management Humanitaire et de la Gestion de Catastrophe dans le cadre de la composante NTIC NE-PGRC-DU-185478-GO- RFQ / Acquisition de matériel Comp. 1: Flood Risk Single Stage - One IDA / 64130 A posteriori Demande de prix Open - International 136,000.00 94,187.70 Achevé 2020-08-09 2020-10-28 2020-10-04 2020-12-30 2021-04-02 2021-03-31 de cartographie dans le cadre Management Investments Envelope de la composante NTIC NE-PGRC-DU-185474-GO- RFQ / Appui à la réalisation de Comp. 4: Contingency Single Stage - One 400 latrines familiales dans IDA / 64130 A posteriori Demande de prix Limited 128,000.00 133,830.19 Achevé 2020-07-28 2020-04-09 2020-09-22 2020-06-19 2021-03-21 2020-09-30 Component Envelope plusieurs villages dans le cadre de l'Urgence Diffa NE-PGRC-DU-151517-GO- RFQ / Acquisition de matériel Comp. 1: Flood Risk Single Stage - One IDA / 64130 A posteriori Demande de prix Limited 88,585.00 0.00 Annulé 2020-01-25 2020-03-21 2020-09-17 de cartographie dans le cadre Management Investments Envelope de la composante NTIC NE-PGRC-DU-203837-GO- RFQ / Acquisition des petits et gros ruminants au profit du Comp. 2: Capacity Building Single Stage - One En attente groupement des femmes dans IDA / 64130 for Urban Development and A posteriori Appel d'offres Limited 130,000.00 0.00 2020-12-16 2020-12-21 2021-02-01 2021-03-03 2021-04-07 2021-10-04 Envelope d'exécution le cadre des activités AGR Disaster Risk Management autour des Aménagements Hydro Agricole de Tillabery NE-PGRC-DU-103800-GO- RFQ / Acquisition de matériel d'etuvage et autres activités Comp. 1: Flood Risk Single Stage - One En attente dans le cadre de l'AGR IDA / 53400 A posteriori Demande de prix Limited 45,000.00 0.00 2020-12-20 2021-02-14 2021-08-13 Management Investments Envelope d'exécution Tillabery (site de NDOUNGA, DAIKAINA, YELWANI 1 et 2, et SAGA) NE-PGRC-DU-209128-GO- RFQ / Acquisition de 6 Comp. 1: Flood Risk Single Stage - One tronçonneuses au Profit de la IDA / 64130 A posteriori Demande de prix Limited 15,000.00 5,687.02 Signé 2020-12-21 2021-02-09 2021-02-15 2021-02-23 2021-08-14 Management Investments Envelope Direction Générale de l'Environnement NE-PGRC-DU-209238-GO- RFQ / Acquisition de 380 sacs de Riz PADY au profit des Comp. 2: Capacity Building Single Stage - One En cours producteurs intervenants sur IDA / 64130 for Urban Development and A posteriori Demande de prix Limited 19,700.00 0.00 2020-12-22 2021-01-14 2021-02-16 2021-08-15 Envelope d'exécution les Aménagements Hydro Disaster Risk Management Agricole de la Région de Tillabery NON CONSULTING SERVICES Page 8 Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NE-PGRC-DU-53790-NC- RFQ / Réalisation de Spot publicitaire sur la Comp. 1: Flood Risk Single Stage - One IDA / 53400 A posteriori Demande de prix Limited 23,000.00 26,576.63 Achevé 2018-03-24 2018-04-24 2018-05-19 2018-06-20 2018-11-15 2018-07-05 sensibilisation à l'utilisation Management Investments Envelope civique des lignes d'appel d'urgence 18 NE-PGRC-DU-68111-NC- RFQ / Appui pour l'Acquisition Comp. 1: Flood Risk Single Stage - One et installation d'un logiciel de IDA / 53400 A posteriori Demande de prix Limited 10,000.00 0.00 Annulé 2018-07-28 2018-09-22 2019-03-21 Management Investments Envelope gestion du parc auto pour le compte de la primature NE-PGRC-DU-139716-GO- RFQ / Confection des plaques de visibilité pour les infrastructures réalisées dans Comp. 3: Project Single Stage - One le cadre du PGRC-DU dans IDA / 53400 A posteriori Demande de prix Limited 45,000.00 33,817.69 Achevé 2019-10-20 2020-01-24 2019-12-15 2020-02-17 2020-06-12 2020-06-26 Management Envelope différentes zones d'intervention du Projet (Diffa, Dosso, Tillabery, Niamey, Tahoua et Agadez) NE-PGRC-DU-151683-NC- RFQ / Confection de Gadgets Comp. 3: Project Single Stage - One publicitaires 2020 pour l'UCP IDA / 64130 A posteriori Demande de prix Limited 20,000.00 15,344.17 Achevé 2019-12-30 2019-12-26 2020-02-24 2020-01-11 2020-08-22 2020-01-31 Management Envelope et les differents UEP du PGRC- DU NE-PGRC-DU-160922-NC- RFB / Acquisition et Comp. 2: Capacity Building Single Stage - One installation d'un VSAT et IDA / 64130 for Urban Development and A posteriori Appel d'offres Open - International 360,000.00 352,704.49 Signé 2020-04-06 2020-12-24 2020-04-11 2020-12-24 2020-05-23 2021-01-28 2020-06-22 2021-05-18 2020-07-27 2021-07-08 2021-01-23 Envelope accessoires au profit de Disaster Risk Management l'ANSI NE-PGRC-DU-172387-NC- RFQ / Acquisition Comp. 2: Capacity Building d’équipements et logiciels Single Stage - One IDA / 64130 for Urban Development and A posteriori Demande de prix Limited 27,000.00 28,058.42 Signé 2020-05-23 2020-12-15 2020-07-18 2021-01-04 2021-01-14 pour l'operationalisation du Envelope Disaster Risk Management Systeme d'Alerte Precose SAP/DNPGCA CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NE-PGRC-DU-22707-CS- QCBS / Etudes et base de Comp. 2: Capacity Building Sélection fondée données en ligne sur IDA / 53400 for Urban Development and A posteriori sur la qualité et le Open - International 438,000.00 0.00 Annulé 2017-08-15 2017-09-05 2017-10-19 2017-11-16 2017-12-16 2018-01-20 2018-02-24 2019-02-24 l'occupation des zones Disaster Risk Management coût inondables et pistes pour la réduction des risques NE-PGRC-DU-22713-CS- QCBS / Etude d'avant projet sommaire (APS), d'avant projet Sélection fondée détaillé (APD) et dossiers Comp. 1: Flood Risk En attente IDA / 53400 A posteriori sur la qualité et le Open - International 576,000.00 0.00 2017-11-20 2017-12-11 2018-01-24 2018-02-21 2018-03-23 2018-04-27 2018-06-01 2019-06-01 d'appel d'offres (DAO) et s uivi Management Investments d'exécution coût contrôle des travaux pour la construction de collecteurs S3, S4, S5, S8 et S10 NE-PGRC-DU-22716-CS- QCBS / Elaboration de plans urbains de référence de 13 Comp. 2: Capacity Building Sélection fondée Communes , de l'audit urbain IDA / 53400 for Urban Development and A posteriori sur la qualité et le Open - International 300,000.00 0.00 Annulé 2017-12-25 2018-01-15 2018-02-28 2018-03-28 2018-04-27 2018-06-01 2018-07-06 2019-07-06 des villes des 4 Régions Disaster Risk Management coût d'intervention du Projet et de l'audit organisationnel et financier des communes NE-PGRC-DU-22718-CS- Comp. 2: Capacity Building Sélection fondée En attente QCBS / Elaboration des PDCs IDA / 53400 for Urban Development and A posteriori sur la qualité et le Open - International 360,000.00 0.00 2017-07-28 2017-08-18 2017-10-01 2017-10-29 2017-11-28 2018-01-02 2018-02-06 2019-02-06 d'exécution de 24 communes Disaster Risk Management coût NE-PGRC-DU-22719-CS-QBS Comp. 2: Capacity Building / Réalisation de l'audit Sélection fondée IDA / 53400 for Urban Development and A posteriori Open - National 100,712.00 0.00 Annulé 2018-03-05 2018-03-26 2018-05-09 2018-06-06 2018-07-06 2018-08-05 2018-09-09 2019-09-09 organisationnel et financier sur la qualité Disaster Risk Management des communes NE-PGRC-DU-22720-CS-LCS / APS APS EIES DAOet suivi contrôle des travaux Comp. 1: Flood Risk Sélection au En cours IDA / 53400 A posteriori Open - National 100,000.00 0.00 2017-07-28 2019-03-12 2017-08-18 2017-10-01 2017-10-29 2017-11-28 2018-01-02 2018-02-06 2018-08-05 d'aménagement d'une Management Investments moindre coût d'exécution décharge pour la ville de Niamey NE-PGRC-DU-22724-CS- CQS / Etude d'avant projet Sélection fondée détaillé (APD) et dossiers Comp. 1: Flood Risk sur les IDA / 53400 A posteriori Open - National 100,000.00 0.00 Annulé 2017-07-28 2017-08-18 2017-10-01 2017-10-31 2017-12-05 2018-06-03 d'appel d'offres (DAO) et suivi Management Investments qualifications des contrôle des travaux pour la consultants digue route de Dosso NE-PGRC-DU-22726-CS- QCBS / APS APD EIES DAO Sélection fondée Comp. 1: Flood Risk pour la construction de IDA / 53400 A posteriori sur la qualité et le Open - International 300,000.00 0.00 Annulé 2017-09-04 2017-09-25 2017-11-08 2017-12-06 2018-01-05 2018-02-09 2018-03-16 2019-03-16 Management Investments canaux et reprofilage le long coût du Gounty Yena (9 km) NE-PGRC-DU-22727-CS- CQS / Etudes APD/EIES/DAO Sélection fondée et suivi contrôle pour les Comp. 1: Flood Risk sur les IDA / 53400 A posteriori Open - National 120,500.00 0.00 En cours d'examen 2017-07-28 2017-07-17 2017-08-18 2017-10-01 2017-10-31 2017-12-05 2018-06-03 travaux de construction de Management Investments qualifications des caniveaux puits et forages à consultants Tillabery Page 9 NE-PGRC-DU-22728-CS- CQS / ETUDES Sélection fondée COMPLEMENTAIRES ET SUIVI Comp. 1: Flood Risk sur les IDA / 53400 A posteriori Open - National 100,000.00 0.00 Annulé 2017-07-28 2017-08-18 2017-10-01 2017-10-31 2017-12-05 2018-06-03 CONTRÖLE DES TRAVAUX DE Management Investments qualifications des REALISATION DE LA DIGUE consultants ROUTE DE DOSSO NE-PGRC-DU-22733-CS- Sélection fondée CQS / ETUDES APS APD DAO Comp. 1: Flood Risk sur les REHABILITATION IDA / 53400 A posteriori Open - National 150,000.00 0.00 Annulé 2018-03-05 2018-03-26 2018-05-09 2018-06-08 2018-07-13 2019-01-09 Management Investments qualifications des CONSTRUCTION PUITS ET consultants CANIVEAU DOSSO NE-PGRC-DU-22734-CS- Sélection fondée QCBS / Actualisation études et Comp. 1: Flood Risk IDA / 53400 A posteriori sur la qualité et le Open - International 200,000.00 290,289.49 Achevé 2017-07-28 2018-01-08 2017-08-18 2017-10-01 2018-03-05 2017-10-29 2018-05-06 2017-11-28 2018-05-15 2018-01-02 2018-05-31 2018-02-06 2018-06-03 2019-02-06 2018-08-15 suivi contrôle Route Mainé- Management Investments coût Gaidam NE-PGRC-DU-22740-CS- CQS / RECRUTEMENT D'UNE Sélection fondée ONG POUR Comp. 1: Flood Risk sur les ACCOMPAGNEMENT DES IDA / 53400 A posteriori Open - National 244,152.00 0.00 Annulé 2017-07-28 2017-08-18 2017-10-01 2017-10-31 2017-12-05 2018-06-03 Management Investments qualifications des ACTIVITES AGR consultants AMENAGEMENT DOSSO (Sakongui, Tara et Kessa) NE-PGRC-DU-22741-CS- CQS / ACTUALISATION ETUDES ETSUIVI CONTRÔLE Sélection fondée DES TRAVAUX DE Comp. 1: Flood Risk sur les CONSTRUCTION DES 10 IDA / 53400 A posteriori Open - National 90,000.00 0.00 Annulé 2017-07-28 2017-08-18 2017-10-01 2017-10-31 2017-12-05 2018-06-03 Management Investments qualifications des BLOCS DE 3 CLASSES EN consultants PLAQUE ECOLOGIQUE DANS LE CADRE DE L'URGENCE REGION DE DIFFA NE-PGRC-DU-22742-CS- CQS / Elaboration de la Sélection fondée Comp. 2: Capacity Building politique nationale de l'action sur les IDA / 53400 for Urban Development and A posteriori Open - National 200,000.00 0.00 Annulé 2018-01-15 2018-02-05 2018-03-21 2018-04-20 2018-05-25 2018-11-21 humanitaire et de la gestion qualifications des Disaster Risk Management des catastrophes et de son consultants plan d'actions NE-PGRC-DU-70949-CS- INDV / CONCEPTION ET HEBERGEMENT D'UN SITE WEB POUR LE PROJET DE GESTION Comp. 3: Project Sélection fondée En cours IDA / 53400 A posteriori Open - National 10,181.00 0.00 2018-07-31 2018-09-25 2018-08-21 2019-01-15 2018-10-04 2018-10-17 2018-11-01 2018-12-01 2018-12-31 2019-02-04 2020-02-04 DES RISQUES DE Management sur la qualité d'exécution CATASTROPHES ET DU DÉVELOPPEMENT URBAIN (PGRC-DU) NE-PGRC-DU-80733-CS- QCBS / Recrutement d'un Sélection fondée auditeur Externe pour la Comp. 1: Flood Risk En cours IDA / 53400 A posteriori sur la qualité et le Open - National 50,000.00 0.00 2018-11-01 2018-11-09 2018-11-22 2018-11-19 2019-01-05 2019-02-02 2019-03-04 2019-04-08 2019-05-13 2020-05-12 réalisation d'audit des compte Management Investments d'exécution coût exercice 2018, 2019, 2020 et cloture NE-PGRC-DU-80700-CS- CQS / Recrutement d'un consultant chargé de la mise à Sélection fondée jour de 8 plans de Comp. 1: Flood Risk sur les IDA / 53400 A posteriori Open - National 120,000.00 147,948.08 Signé 2018-11-10 2019-03-20 2018-12-01 2019-05-09 2019-01-14 2019-06-25 2019-02-13 2019-08-25 2019-03-20 2019-08-29 2019-09-16 Developpement Communaux Management Investments qualifications des (PDC) en intégrant les consultants dimensions ''changements climatiques, paix et securité" NE-PGRC-DU-96507-CS- QCBS / Recrutement d'un Sélection fondée auditeur Externe pour la Comp. 3: Project IDA / 53400 A posteriori sur la qualité et le Open - International 50,000.00 37,490.67 Achevé 2018-12-31 2019-02-05 2019-01-21 2019-02-28 2019-03-06 2019-01-03 2019-04-03 2019-02-28 2019-05-03 2019-02-28 2019-06-07 2019-04-02 2019-07-12 2019-05-10 2020-07-11 2019-06-28 réalisation d'audit des compte Management coût exercice 2018, 2019, 2020 et cloture NE-PGRC-DU-96510-CS- QCBS / Recrutement d'un Sélection fondée Comp. 3: Project cabinet chargé de sélectionner IDA / 53400 A posteriori sur la qualité et le Open - International 15,000.00 13,208.92 Achevé 2018-12-31 2019-02-26 2019-01-21 2019-02-28 2019-03-06 2019-04-19 2019-04-03 2019-05-06 2019-05-03 2019-05-17 2019-06-07 2019-05-24 2019-07-12 2019-06-11 2020-07-11 2019-07-26 Management le coordonnateur National du coût PGRC-DU NE-PGRC-DU-103786-CS- Sélection fondée CQS / Appui à l'amélioration Comp. 2: Capacity Building sur les des latrines familiales dans les IDA / 53400 for Urban Development and A posteriori Open - National 50,000.00 0.00 Annulé 2019-04-15 2019-05-06 2019-06-19 2019-07-19 2019-08-23 2020-02-19 qualifications des régions de Diffa, Dosso et Disaster Risk Management consultants Tillabéri NE-PGRC-DU-103793-CS- Sélection fondée CQS / Suivi contrôle des Comp. 1: Flood Risk sur les IDA / 53400 A posteriori Open - National 27,777.78 0.00 Annulé 2019-03-15 2019-04-05 2019-05-19 2019-06-18 2019-07-23 2020-01-19 travaux de l'Ouvrage de Management Investments qualifications des franchissement de Sirfi Koira consultants NE-PGRC-DU-103841-CS- CQS / Recrutement d'un Sélection fondée cabinet pour realiser les Comp. 1: Flood Risk sur les Etudes techniques et IDA / 53400 A posteriori Open - National 130,208.33 89,390.56 Signé 2019-03-15 2020-01-30 2019-04-05 2019-05-19 2020-07-27 2019-06-18 2020-08-31 2019-07-23 2020-09-29 2020-01-19 Management Investments qualifications des environementales travaux consultants prévus dans le cadre du Fonds additioonnel NE-PGRC-DU-22722-CS- CQS / Etude d'avant projet Sélection fondée détaillé (APD) et dossiers Comp. 1: Flood Risk sur les IDA / 53400 A posteriori Open - National 110,000.00 0.00 Annulé 2017-09-04 2017-09-25 2017-11-08 2017-12-08 2018-01-12 2018-07-11 d'appel d'offres (DAO) pour Management Investments qualifications des les travaux de réalisation des consultants caniveaux de Dosso NE-PGRC-DU-22717-CS-QBS Comp. 2: Capacity Building Sélection fondée / Elaboration d'un guide sur IDA / 53400 for Urban Development and A posteriori Open - National 100,000.00 0.00 Annulé 2018-04-02 2018-04-23 2018-06-06 2018-07-04 2018-08-03 2018-09-02 2018-10-07 2019-10-07 sur la qualité l'intercollectivité Disaster Risk Management Page 10 NE-PGRC-DU-22709-CS- QCBS / Etude de faisabilité Sélection fondée pour la régulation des Comp. 1: Flood Risk IDA / 53400 A posteriori sur la qualité et le Open - International 250,000.00 0.00 Annulé 2017-10-02 2017-10-23 2017-12-06 2018-01-03 2018-02-02 2018-03-09 2018-04-13 2019-04-13 écoulements dans les bassins Management Investments coût versants de la SIRBA et du GOROUBI NE-PGRC-DU-22710-CS- QCBS / Elaboration d'une politique nationale Sélection fondée Comp. 1: Flood Risk d'assainissement (eaux IDA / 53400 A posteriori sur la qualité et le Open - International 400,000.00 0.00 Annulé 2017-11-15 2017-12-06 2018-01-19 2018-02-16 2018-03-18 2018-04-22 2018-05-27 2019-05-27 Management Investments pluviales, eaux usées, coût assainissement de base, déchets solides) NE-PGRC-DU-34174-CS-QBS Sélection fondée / Etude-Suivi-contrôle des Comp. 1: Flood Risk sur les IDA / 53400 A posteriori Open - National 20,000.00 0.00 Annulé 2017-12-04 2017-12-25 2018-02-07 2018-03-09 2018-04-13 2018-10-10 travaux supplementaire sur la Management Investments qualifications des Route en Terre SIA-ADIGA consultants NE-PGRC-DU-22729-CS- CQS / ETUDES Sélection fondée COMPLEMENTAIRES ET SUIVI Comp. 1: Flood Risk sur les IDA / 53400 A posteriori Open - National 100,000.00 0.00 Annulé 2018-03-05 2018-03-26 2018-05-09 2018-06-08 2018-07-13 2019-01-09 CONTRÖLE DES TRAVAUX DE Management Investments qualifications des REALISATION DES CANIVEAUX consultants DE DOSSO Sélection fondée NE-PGRC-DU-22731-CS- Comp. 1: Flood Risk sur les CQS / ETUDES APS APD DAO IDA / 53400 A posteriori Open - National 100,000.00 0.00 Annulé 2018-02-05 2018-02-26 2018-04-11 2018-05-11 2018-06-15 2018-12-12 Management Investments qualifications des CONFORTATION AHA KARMA consultants Sélection fondée NE-PGRC-DU-22732-CS- Comp. 1: Flood Risk sur les CQS / ETUDES APS APD DAO IDA / 53400 A posteriori Open - National 100,000.00 0.00 Annulé 2018-02-05 2018-02-26 2018-04-11 2018-05-11 2018-06-15 2018-12-12 Management Investments qualifications des CONFORTATION AHA KARMA consultants NE-PGRC-DU-138614-CS- CQS / Recrutement d'une ONG pour faciliter les Activités Sélection fondée Comp. 2: Capacity Building Génératrices de revenus au sur les En cours IDA / Q8620 for Urban Development and A posteriori Open - National 60,000.00 0.00 2019-10-03 2019-07-08 2019-10-24 2019-12-07 2020-01-06 2020-02-10 2020-08-08 profit des groupements des qualifications des d'exécution Disaster Risk Management femmes autour des consultants Aménagements Hydro Agricoles de Tillabery NE-PGRC-DU-91457-CS- CQS / Recrutement d'un Sélection fondée Comp. 3: Project cabinet chargé de sélectionner IDA / 53400 A priori sur la qualité et le Open - International 15,000.00 0.00 Annulé 2018-12-19 2019-02-26 2019-01-09 2019-02-22 2019-03-22 2019-04-21 2019-05-26 2019-06-30 2020-06-29 Management le coordonnateur National du coût PGRC-DU NE-PGRC-DU-151514-CS- Sélection fondée CQS / Etudes techniques et Comp. 1: Flood Risk sur les IDA / 53400 A posteriori Open - National 36,000.00 0.00 Annulé 2020-02-15 2020-03-07 2020-04-20 2020-05-20 2020-06-24 2020-12-21 environnementale de la Digue Management Investments qualifications des de Kirkissoye Niamey consultants NE-PGRC-DU-151420-CS- CQS / Etudes et suivi contrôle Sélection fondée Comp. 2: Capacity Building des travaux de construction sur les IDA / 64130 for Urban Development and A posteriori Open - National 44,000.00 42,779.31 Signé 2020-01-20 2020-03-16 2020-02-10 2020-03-25 2020-03-27 2020-04-24 2020-04-07 2020-05-29 2020-05-18 2020-11-25 de la cité de l'innovation dans qualifications des Disaster Risk Management le cadre de la composante consultants NTIC NE-PGRC-DU-151510-CS- CQS / Recrutement d'une Sélection fondée firme pour l'etude sur le Comp. 2: Capacity Building sur les En attente transfert et le financement IDA / 53400 for Urban Development and A posteriori Open - National 85,000.00 0.00 2020-06-10 2020-07-01 2020-08-14 2020-09-13 2020-10-18 2021-04-16 qualifications des d'exécution des competences municipales Disaster Risk Management consultants dans les zones d'intervention du Projet NE-PGRC-DU-171196-CS- CQS / Élaboration e diffusion d'un spot de sensibilisation Sélection fondée Comp. 2: Capacity Building sur la conduite à tenir au sur les En attente IDA / 53400 for Urban Development and A posteriori Open - National 37,600.00 0.00 2020-04-30 2020-05-21 2020-07-04 2020-08-03 2020-09-07 2021-03-06 niveau des carrefours dotés qualifications des d'exécution Disaster Risk Management des feux tricolores solaires consultants financés dans le cadre du PGRC-DU NE-PGRC-DU-22735-CS- CQS / Actualisation des Sélection fondée études et suivi contrôle des Comp. 1: Flood Risk sur les travaux de construction IDA / 53400 A posteriori Open - National 90,000.00 0.00 Annulé 2017-07-28 2017-08-18 2017-10-01 2017-10-31 2017-12-05 2018-06-03 Management Investments qualifications des d'infrastructures scolaires et consultants sanitaires dans la régions de Dosso et Tillabery NE-PGRC-DU-209129-CS- CQS / Etudes de faisabilité Sélection fondée technique, environnementales Comp. 4: Contingency sur les En attente IDA / 64130 A posteriori Open - National 90,000.00 0.00 2020-12-22 2021-01-12 2021-02-25 2021-03-27 2021-05-01 2021-10-28 et sociales des Component qualifications des d'exécution aménagements et consultants assainissements urbains NE-PGRC-DU-209132-CS- Sélection fondée CQS / Etudes sommaires pour Comp. 4: Contingency sur les la réhabilitation des sites IDA / 64130 A posteriori Open - National 55,000.00 0.00 Annulé 2020-12-22 2021-01-12 2021-02-25 2021-03-27 2021-05-01 2021-10-28 Component qualifications des maraichers endommagés par consultants les inondations NE-PGRC-DU-209130-CS- CQS / Etudes de faisabilité technique, environnementale Sélection fondée et sociale pour la Réalisation Comp. 4: Contingency sur les des travaux de protection des IDA / 64130 A posteriori Open - National 85,000.00 0.00 Annulé 2020-12-22 2021-01-12 2021-02-25 2021-03-27 2021-05-01 2021-10-28 Component qualifications des Berges sur le Goulbi Maradi consultants (Duplex Maradi Kolia, Tibiri Korin Garin Daouré et Tibiri Korin Kawkaye) Page 11 NE-PGRC-DU-221036-CS- QBS / Recrutement d'un Sélection fondée consultant Acquisition Comp. 2: Capacity Building sur les En cours d’images à haute résolution IDA / 64130 for Urban Development and A posteriori Open - International 108,000.00 0.00 2021-03-15 2021-03-12 2021-04-05 2021-04-15 2021-05-19 2021-06-18 2021-07-23 2022-01-19 qualifications des d'exécution spatiale et production de Disaster Risk Management consultants produits d’information dans le cadre de la composante NTIC INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NE-PGRC-DU-22736-CS- INDV / consultant Pour conduire la collecte des Comp. 2: Capacity Building données sur les bâtiments et IDA / 53400 for Urban Development and A priori Individuel Direct 150,000.00 0.00 Annulé 2017-07-28 2017-08-07 2017-08-28 2017-10-02 2018-03-31 les terrains agricoles dans la Disaster Risk Management commune V, le quartier de Goudel et le quartier de Lossa- Goungou NE-PGRC-DU-22739-CS- Comp. 1: Flood Risk INDV / EIES DIGUE ROUTE IDA / 53400 A posteriori Individuel Limited 30,000.00 0.00 Annulé 2017-07-28 2017-08-02 2017-08-23 2017-09-27 2018-03-26 Management Investments DIFFA NE-PGRC-DU-48768-CS- INDV / Recrutement d'un consultant chargé de la mise à jour du cadre de Gestion Comp. 4: Contingency Environnementale et Sociales IDA / 53400 A posteriori Individuel Limited 13,090.00 9,531.15 Achevé 2018-02-13 2018-01-10 2018-02-18 2018-02-09 2018-03-11 2018-02-20 2018-04-15 2018-04-13 2018-10-12 2018-08-02 Component (CGES) du PGRC-DU pour couvrir les régions d'Agadez et de Tahoua dans le cadre de l'extension du projet NE-PGRC-DU-48770-CS- INDV / Recrutement d'un consultant chargé de la mise à jour du cadre de politique de Comp. 4: Contingency Réinstallation des Populations IDA / 53400 A posteriori Individuel Limited 9,430.00 7,975.05 Achevé 2018-02-13 2018-01-24 2018-02-18 2018-02-09 2018-03-11 2018-03-11 2018-04-15 2018-04-12 2018-10-12 2018-11-02 Component (CPRP) du PGRC-DU pour couvrir les régions d'Agadez et de Tahoua dans le cadre de l'extension du projet NE-PGRC-DU-48772-CS- INDV / Recrutement d'un consultant chargé de la mise à jour du plan anti-parasitaires Comp. 4: Contingency et Gestion des Pesticides (GPP) IDA / 53400 A posteriori Individuel Limited 8,430.00 9,505.78 Achevé 2018-02-13 2018-02-02 2018-02-18 2018-02-09 2018-03-11 2018-03-13 2018-04-15 2018-04-12 2018-10-12 2018-12-18 Component du PGRC-DU pour couvrir les régions d'Agadez et de Tahoua dans le cadre de l'extension du projet NE-PGRC-DU-48773-CS- INDV / Recrutement d'un Comp. 3: Project consultant pour la mise à jour IDA / 53400 A posteriori Individuel Limited 15,000.00 6,866.61 Achevé 2018-03-19 2018-05-07 2018-03-24 2018-05-03 2018-04-14 2018-06-06 2018-05-19 2018-06-11 2018-11-15 2018-08-06 Management du Manuel de procédure du PGRC-DU NE-PGRC-DU-58280-CS- INDV / Recrutement d'un Comp. 1: Flood Risk consultant pour la mise à jour IDA / 53400 A posteriori Individuel Limited 8,500.00 6,866.61 Achevé 2018-04-16 2018-05-01 2018-04-21 2018-06-08 2018-05-12 2018-06-25 2018-06-16 2018-07-08 2018-12-13 2018-09-10 Management Investments de la base de données "PGRC- DU" NE-PGRC-DU-50930-CS- Sélection de CDS / Recrutement consultant Comp. 1: Flood Risk IDA / 53400 A posteriori consultants par Direct 33,000.00 23,938.03 Achevé 2018-07-31 2018-09-26 2018-08-10 2018-09-26 2018-10-14 2018-10-08 2019-04-12 2018-12-05 en Infrastructure pour le suivi Management Investments entente directe des activités du PGRC-DU NE-PGRC-DU-92303-CS- INDV / Recrutement de consultant local pour la Comp. 3: Project poursuite de la mise en place IDA / 53400 A posteriori Individuel Limited 20,000.00 17,523.92 Signé 2018-12-26 2019-01-15 2018-12-31 2019-12-02 2019-01-21 2019-12-18 2019-02-25 2019-12-24 2019-08-24 Management d'une base de données suivi - évaluation au sein du PGRC- DU NE-PGRC-DU-103835-CS- INDV / Recrutement d'un Comp. 1: Flood Risk consultant pour l'Elaboration IDA / 53400 A posteriori Individuel Limited 17,361.00 0.00 Annulé 2019-04-20 2019-04-25 2019-05-16 2019-06-20 2019-12-17 Management Investments du cadre réglementaire et juridique des drones NE-PGRC-DU-108338-CS- INDV / Recrutement du Comp. 1: Flood Risk En cours IDA / 53400 A posteriori Individuel Open 85,750.00 0.00 2019-04-08 2019-04-09 2019-05-27 2019-06-17 2019-07-22 2020-01-18 Coordonnateur National du Management Investments d'exécution PGRC-DU NE-PGRC-DU-109638-CS- INDV / Recrutement d'un consultant pour réaliser les Etudes d'Impact Environnemental et Sociale Comp. 1: Flood Risk EIES dans le cadre de IDA / 53400 A posteriori Individuel Limited 17,800.00 16,668.79 Achevé 2019-04-15 2019-04-10 2019-04-20 2019-04-12 2019-05-11 2019-04-30 2019-06-15 2019-05-02 2019-12-12 2019-06-18 Management Investments réalisation des infrastructures Socio Economiques et les ouvrages de protection des terres et d'habitation dans la Région d'Agadez NE-PGRC-DU-110369-CS- INDV / Recrutement d'un consultant pour la Préparation d'un Plan d'Action de Réinstallation (PAR) des Comp. 1: Flood Risk IDA / 53400 A posteriori Individuel Limited 14,600.00 15,883.62 Achevé 2019-04-17 2019-04-19 2019-04-22 2019-04-26 2019-05-13 2019-05-22 2019-06-17 2019-06-05 2019-12-14 2019-07-15 Personnes Affectées par les Management Investments Travaux de construction des trois collecteurs dans l'Arrondissement Communal 1 de Niamey Page 12 NE-PGRC-DU-22743-CS- INDV / ETUDES ET SUIVI Comp. 1: Flood Risk IDA / 53400 A posteriori Individuel Limited 20,000.00 0.00 Annulé 2017-10-02 2017-10-07 2017-10-28 2017-12-02 2018-05-31 CONTRÔLE ROUTE EN TERRE Management Investments SIA ADIGUA NE-PGRC-DU-22737-CS- Comp. 2: Capacity Building INDV / Etude sur les IDA / 53400 for Urban Development and A posteriori Individuel Limited 20,000.00 0.00 Annulé 2018-01-08 2018-01-13 2018-02-03 2018-03-10 2018-09-06 procédures opérationnelles Disaster Risk Management pour l'alerte aux catastrophes NE-PGRC-DU-22738-CS- INDV / AUDIT Comp. 1: Flood Risk ENVIRONNEMENTAL ET IDA / 53400 A posteriori Individuel Limited 18,000.00 0.00 Annulé 2017-10-02 2017-10-07 2017-10-28 2017-12-02 2018-05-31 Management Investments SOCIAL REHABILITATION BASSINS VERSANTS NE-PGRC-DU-22744-CS- Comp. 2: Capacity Building Sélection de CDS / IEC SAMPLAT IDA / 53400 for Urban Development and A priori consultants par Direct 144,000.00 0.00 Annulé 2018-01-16 2018-01-26 2018-04-01 2018-09-28 (POURSUITE 3 MOIS) Disaster Risk Management entente directe NE-PGRC-DU-138600-CS- INDV / Recrutement d'un Comp. 3: Project En cours IDA / 53400 A posteriori Individuel Open 36,000.00 0.00 2019-10-03 2019-10-21 2019-11-21 2019-12-12 2020-01-16 2020-07-14 Assistant comptable pour Management d'exécution servir à l'UCP de Niamey NE-PGRC-DU-138604-CS- INDV / Recrutement d'un Comp. 3: Project En cours IDA / 53400 A posteriori Individuel Open 48,000.00 0.00 2019-10-03 2019-10-21 2019-11-21 2019-12-12 2020-01-16 2020-07-14 Coordonnateur Régional pour Management d'exécution l'UEP de Niamey NE-PGRC-DU-103830-CS- CDS / Recrutement d'une ONG Comp. 2: Capacity Building Sélection de pour faciliter les Activités IDA / 53400 for Urban Development and A posteriori consultants par Direct 60,763.89 0.00 Annulé 2019-04-22 2019-05-02 2019-07-06 2020-01-02 Génératrices de revenus au Disaster Risk Management entente directe profit des groupements des femmes NE-PGRC-DU-145431-CS- INDV / Recrutement d’un consultant international individuel pour l’Organisation Comp. 1: Flood Risk IDA / 64130 A posteriori Individuel Limited 17,000.00 17,774.86 Signé 2019-11-24 2020-01-23 2019-11-29 2020-02-11 2019-12-20 2020-08-12 2020-01-24 2020-08-13 2020-07-22 d’un Atelier d’Information sur Management Investments les Drones et l’appui à la finalisation de la législation des drones au Niger. NE-PGRC-DU-146425-CS- INDV / Recrutement d’un consultant charge de la Réalisation d’une étude Comp. 1: Flood Risk d’impact environnemental et IDA / 53400 A posteriori Individuel Limited 19,000.00 17,396.95 Achevé 2019-11-27 2020-01-21 2019-12-02 2020-02-07 2019-12-23 2020-02-18 2020-01-27 2020-02-24 2020-07-25 2020-03-18 Management Investments social du sous-projet des travaux de traitement et la protection des berges du Kori de Dosso NE-PGRC-DU-151365-CS- INDV / Recrutement d'un Comp. 4: Contingency IDA / 53400 A posteriori Individuel Limited 50,000.00 34,932.19 Signé 2020-04-10 2020-05-20 2020-04-15 2020-10-12 2020-05-06 2020-10-16 2020-06-10 2020-10-28 2020-12-07 consultant pour l'evaluation Component des activités du MRI NE-PGRC-DU-153657-CS- INDV / Mise à jour de l'Etude Comp. 1: Flood Risk EIES pour la réhabilitation de IDA / 64130 A posteriori Individuel Limited 9,000.00 9,708.37 Achevé 2020-01-17 2020-01-16 2020-01-22 2020-01-20 2020-02-12 2020-01-26 2020-03-18 2020-02-05 2020-09-14 2020-05-12 Management Investments l’Aménagement Hydro Agricole de SAGA NE-PGRC-DU-160921-CS- INDV / RECRUTEMENT D’UN CONSULTANT NTIC EXPERT EN Comp. 2: Capacity Building TRANSFORMATION En cours IDA / 64130 for Urban Development and A posteriori Individuel Open 35,000.00 0.00 2020-02-25 2020-02-21 2020-04-14 2020-05-05 2020-06-09 2020-12-06 NUMÉRIQUE DES TERRITOIRES d'exécution Disaster Risk Management AUPRÈS DE L’AGENCE NATIONALE POUR LA SOCIÉTÉ DE L’INFORMATION (ANSI). NE-PGRC-DU-171203-CS- INDV / Recrutement d’un consultant pour l'Evaluation thématique de la prise en compte de la question du Comp. 1: Flood Risk En cours genre et l’inclusion des IDA / 53400 A posteriori Individuel Limited 40,000.00 0.00 2020-05-04 2020-06-26 2020-05-09 2020-05-30 2020-07-04 2020-12-31 Management Investments d'exécution groupes vulnérables dans le cadre des interventions du Projet de Gestion des Risques de Catastrophes et de Développement Urbain NE-PGRC-DU-171212-CS- INDV / Elaboration de Plans de Gestion Environnementale et Sociale (PGES), en document séparés par site, Comp. 1: Flood Risk IDA / 53400 A posteriori Individuel Limited 20,000.00 0.00 En cours d'examen 2020-05-10 2020-06-26 2020-05-15 2020-06-05 2020-07-10 2021-01-06 des ouvrages de protection Management Investments des villages de Bado, Toumboul et de Loubé dans les départements d’Illéla et de Bouza et le traitement des bassins versants adja NE-PGRC-DU-171408-CS- INDV / Conception d'un message de sensibilisation des populations bénéficiaires Comp. 4: Contingency En attente IDA / 53400 A posteriori Individuel Limited 8,000.00 0.00 2020-05-10 2020-05-15 2020-06-05 2020-07-10 2021-01-06 sur l'utilisation et la Component d'exécution sauvegarde des infrastructures réalisées dans le cadre du PGRC DU NE-PGRC-DU-191050-CS- INDV / Recrutement d'un consultant pour l’élaboration Comp. 4: Contingency IDA / 64130 A posteriori Individuel Limited 6,000.00 7,378.12 Achevé 2020-08-31 2020-08-29 2020-09-05 2020-09-01 2020-09-26 2020-09-07 2020-10-31 2020-09-08 2021-04-29 2020-09-22 du Programme de mise en Component Oeuvre du MRI Niger au titre de l'année 2020 Page 13 NE-PGRC-DU-191055-CS- INDV / Recrutement d'un consultant pour l’élaboration Comp. 1: Flood Risk IDA / 64130 A posteriori Individuel Limited 25,000.00 0.00 En cours d'examen 2020-09-07 2020-09-15 2020-09-12 2020-10-03 2020-11-07 2021-05-06 d'un Plan de Gestion des Sites Management Investments restaurés dans le cadre du PGRC DU NE-PGRC-DU-191052-CS- INDV / Recrutement d'un consultant en vue de Comp. 4: Contingency IDA / 64130 A posteriori Individuel Limited 6,000.00 0.00 Annulé 2020-08-31 2020-08-30 2020-09-05 2020-09-26 2020-10-31 2021-04-29 l'actualisation du Manuel Component d'opération du Mécanisme de Riposte Immédiate MRI 2020 NE-PGRC-DU-196011-CS- INDV / Recrutement d'un Spécialiste en Sauvegarde Comp. 3: Project IDA / 64130 A posteriori Individuel Limited 21,000.00 35,358.34 Signé 2020-09-28 2020-09-17 2020-10-03 2021-01-11 2020-10-24 2021-02-23 2020-11-28 2021-03-01 2021-05-27 Environnementales et Sociales Management pour le compte de l'UCP du PGRC DU NE-PGRC-DU-209114-CS- INDV / Recrutement d’un Spécialiste en Sauvegardes environnementales en appui Comp. 3: Project au Projet de Gestion des IDA / 64130 A posteriori Individuel Limited 35,000.00 23,142.03 Signé 2020-12-16 2021-02-05 2020-12-21 2021-02-10 2021-01-11 2021-03-03 2021-02-15 2021-03-10 2021-08-14 Management Risques de Catastrophes et de Développement Urbain (PGRC- DU) pour la mise en œuvre du MRI2020 NE-PGRC-DU-209116-CS- INDV / Recrutement d’un Spécialiste en Sauvegarde sociale en appui au Projet de Comp. 3: Project Gestion des Risques de IDA / 64130 A posteriori Individuel Limited 35,000.00 21,169.70 Signé 2020-12-16 2021-02-05 2020-12-21 2021-02-09 2021-01-11 2021-02-15 2021-02-15 2021-03-10 2021-08-14 Management Catastrophes et de Développement Urbain (PGRC- DU) pour la mise en œuvre du MRI2020 NE-PGRC-DU-209118-CS- INDV / RECRUTEMENT D'UN CONSULTANT POUR Comp. 3: Project L'ÉVALUATION DES IDA / 64130 A posteriori Individuel Limited 5,500.00 0.00 Annulé 2020-12-15 2020-12-20 2021-01-10 2021-02-14 2021-08-13 Management DOMMAGES, PERTES ET BESOINS POST INONDATIONS AU NIGER EN 2020 NE-PGRC-DU-221031-CS- INDV / RECRUTEMENT D’UN CONSULTANT NTIC EXPERT EN TRANSFORMATION NUMÉRIQUE DES TERRITOIRES Comp. 3: Project IDA / 64130 A posteriori Individuel Limited 20,000.00 17,074.36 Signé 2021-02-26 2021-03-08 2021-03-03 2021-03-08 2021-03-24 2021-04-16 2021-04-28 2021-05-10 2021-10-25 AUPRÈS DE L’AGENCE Management NATIONALE POUR LA SOCIÉTÉ DE L’INFORMATION (ANSI) DANS LE CADRE DE LA COMPOSANTE NTIC NE-PGRC-DU-241469-CS- INDV / Recrutement d'un Comp. 3: Project En cours IDA / 64130 A posteriori Individuel Limited 35,000.00 0.00 2021-06-30 2021-07-19 2021-07-05 2021-07-26 2021-08-30 2022-02-26 Spécialiste en infrastructure Management d'exécution pour le compte de l'UCP NE-PGRC-DU-243797-CS- INDV / Recrutement d’un consultant charge de Comp. 1: Flood Risk En attente l’Elaboration du cadre de IDA / 64130 A posteriori Individuel Limited 15,000.00 0.00 2021-07-19 2021-07-24 2021-08-14 2021-09-18 2022-03-17 Management Investments d'exécution politique de Réinstallation des populations (CPRP) du PIDUREM NE-PGRC-DU-243801-CS- INDV / Recrutement d’un consultant chargé de Comp. 1: Flood Risk En attente IDA / 64130 A posteriori Individuel Limited 13,000.00 0.00 2021-07-19 2021-07-24 2021-08-14 2021-09-18 2022-03-17 l’Elaboration du Cadre de Management Investments d'exécution Gestion Environnementale et Sociale (CGES) du PIDUREM NE-PGRC-DU-243806-CS- INDV / Recrutement d’un consultant chargé de Comp. 1: Flood Risk En attente IDA / 64130 A posteriori Individuel Limited 15,000.00 0.00 2021-07-19 2021-07-24 2021-08-14 2021-09-18 2022-03-17 l’Elaboration du Plan de Management Investments d'exécution Gestion des Pestes et Pesticides (PGPP) du PIDUREM NE-PGRC-DU-243816-CS- INDV / Recrutement d’un consultant chargé de l’Elaboration du Plan de Comp. 1: Flood Risk En attente IDA / 64130 A posteriori Individuel Limited 20,000.00 0.00 2021-07-19 2021-07-24 2021-08-14 2021-09-18 2022-03-17 Gestion de la Main d’œuvre Management Investments d'exécution (PGMO) et d’un Plan de Mobilisation des Parties Prenantes (PMPP) du PIDUREM NE-PGRC-DU-243823-CS- INDV / Recrutement d’un consultant chargé de Comp. 1: Flood Risk En attente IDA / 64130 A posteriori Individuel Limited 12,000.00 0.00 2021-07-19 2021-07-24 2021-08-14 2021-09-18 2022-03-17 l’Elaboration du Plan de Management Investments d'exécution Gestion de la Sécurité (PGS) du PIDUREM Page 14