PROCUREMENT PLAN (Textual Part) Project information: Dominican Republic DISTRIBUTION GRID MODERNIZATION AND LOSS REDUCTION PROJECT P147277 Project Implementation agency: CDEEE Date of the Procurement Plan: 27-8-18 Period covered by this Procurement Plan:12 months Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: is applicable for those contracts identified in the Procurement Plan tables; Works: is applicable for those contracts identified in the Procurement Plan tables PROCUREMENT Dominican Republic : Distribution Grid Modernization and Loss Reduction Project PLAN General Information Country: Dominican Republic Bank’s Approval Date of the Original Procurement Plan: 2018-08-27 2020-05-19 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P147277 GPN Date: Project Name: Distribution Grid Modernization and Loss Reduction Project Loan / Credit No: IBRD / 85630 Executing Agency(ies): Dominican Corporation of State Power Companies WORKS Bid Evaluation Activity Reference No. / Procurement Estimated Actual Draft Bidding Loan / Credit Market Procurement Prequalification High SEA/SH Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Contract Description Component Review Type Method Document Amount Amount Document / Signed Contract No. Approach Process (Y/N) Risk Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Completion Type (US$) (US$) Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Rehabilitation of Selected BO-1-1 / bo.1.1 Proyecto de Distribution Circuits and Rehabilitacion de Circuitos Upgrading of Metering Solicitud de Open - Single Stage - One 101,208,000.0 94,636,401.9 de media y baja tension IBRD / 85630 Previa Firmado 2017-08-09 2017-08-09 2017-11-09 2017-11-09 2018-05-04 2018-09-10 2018-07-18 2018-08-02 2019-09-21 Systems - Implementation of ofertas International Envelope 0 1 (EDESUR-EDENORTE- Environmental Manag ement EDEESTE) System Rehabilitation of Selected BO-1-3 / bo.1.3 Adecuacion Distribution Circuits and de un sitio actual de acopio Upgrading of Metering Solicitud de Single Stage - One Ejecución Residuos (EDESUR- IBRD / 85630 Posterior Limited 150,000.00 0.00 2018-11-09 2018-12-10 2019-02-08 Systems - Implementation of cotizaciones Envelope pendiente EDENORTE-EDEESTE) - Environmental Manag ement PMAA System BO-3-1 / bo.3.1 Adecuacion Commercial Management Oficinas Comerciales Tipo A and Project Management, en la Zona de Influencia de Monitoring and Evaluation los Circuitos de Edesur) Solicitud de Single Stage - One Ejecución IBRD / 85630 of the Distribution Grid Posterior Limited 308,672.00 0.00 2017-11-20 2018-02-03 2018-04-04 (Contempla mobiliario, cotizaciones Envelope pendiente Modernization and Electri sistema de vigilancia, cal Losses Reduction deteccion de incendio) - Program Comercial Rehabilitation of Selected BO-1-2 / bo.1.2.Construccion Distribution Circuits and de tres puntos verdes Upgrading of Metering Solicitud de Single Stage - One IBRD / 85630 Previa Open - National 442,100.00 465,645.18 Firmado 2019-08-22 2019-09-17 2019-08-27 2019-09-19 2019-09-26 2019-10-31 2019-10-26 2020-01-16 2019-11-15 2020-02-14 2020-01-14 (EDESUR-EDENORTE- Systems - Implementation of ofertas Envelope EDEESTE) - PMAA Environmental Manag ement System Commercial Management and Project Management, BO-3-2 / Adecuación de Monitoring and Evaluation Ocho (8) Oficinas Solicitud de Single Stage - One IBRD / 85630 of the Distribution Grid Posterior Open - National 1,056,619.00 359,481.60 Firmado 2019-05-15 2019-07-25 2019-05-20 2019-07-01 2019-08-29 2019-07-16 2019-10-15 2019-08-14 2019-12-18 2019-12-12 Comerciales (Edesur (3) y ofertas Envelope Modernization and Electri Edenorte (5)) cal Losses Reduction Program Commercial Management BO-3-2-A / Adecuaciones de and Project Management, oficinas comerciales de Monitoring and Evaluation Solicitud de Single Stage - One Ejecución Edesur (San Cristóbal 1er y IBRD / 85630 of the Distribution Grid Posterior Limited 341,012.00 0.00 2019-12-26 2020-02-14 2020-04-14 cotizaciones Envelope pendiente 3er Piso, Patio Colombia y Modernization and Electri San Cristóbal Norte) cal Losses Reduction Program BO.2.1 / Adecuación Terrero para ubicación de furgón Citizen Engagement and Solicitud de Single Stage - One Ejecución IBRD / 85630 Posterior Limited 4,500.00 0.00 2020-04-16 2020-05-14 2020-05-29 para almacenamiento Community Participation cotizaciones Envelope pendiente temporal de la UEP/CDEEE. Page 1 GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual B-1-1 / b.1.1 Adquisición de Rehabilitation of Selected Kit para Analisis Cualitativo Distribution Circuits and - Subprograma de manejo y Upgrading of Metering Solicitud de Single Stage - One IBRD / 85630 Posterior Limited 24,000.00 0.00 Cancelado 2018-11-03 2018-11-26 2018-12-26 disposición de aceite con Systems - Implementation of cotizaciones Envelope PCB - Calidad Ambiental - Environmental Manag ement PMAA System Rehabilitation of Selected Distribution Circuits and B-1-2 / b.1.2 Equipo de Upgrading of Metering Solicitud de Single Stage - One campo, tabletas, seguridad y IBRD / 85630 Posterior Limited 35,000.00 8,601.49 Firmado 2018-08-17 2019-01-29 2018-09-04 2019-02-28 2018-10-04 2019-05-29 Systems - Implementation of cotizaciones Envelope manejo ambiental - PMAA Environmental Manag ement System Rehabilitation of Selected B-1-3 / b.1.3 Adq. Vehículos Distribution Circuits and utilitarios para las Unidades Upgrading of Metering Solicitud de Single Stage - One Ejecución IBRD / 85630 Previa Open - National 115,000.00 0.00 2017-04-03 2017-04-18 2017-05-18 2017-05-28 2017-06-17 2017-08-01 ambientales Systems - Implementation of ofertas Envelope pendiente UEP/CDEEE/EDES - PMAA Environmental Manag ement System B-2-1 / b.2.1 Adquisicion de Carpetas para los Comites Citizen Engagement and Solicitud de Single Stage - One Ejecución de Seguimiento de las Obras IBRD / 85630 Posterior Limited 23,445.00 0.00 2018-07-04 2018-07-28 2018-08-27 Community Participation cotizaciones Envelope pendiente (COSE) (EDESUR- EDENORTE-EDEESTE) B-2-2 / b.2.2. Edesur: Gastos de Gestion Social, tales como: Actividades de Solidaridad Social en Citizen Engagement and Solicitud de Single Stage - One Ejecución Comunidades Intervenidas IBRD / 85630 Posterior Limited 24,161.00 0.00 2019-04-04 2019-04-28 2019-05-28 Community Participation cotizaciones Envelope pendiente (Entrega de articulos deportivos, uniformes, equipamiento para centros comunitarios, etc.) B-2-3 / b.2.3. Edenorte: Gastos de Gestion Social, tales como: Actividades de Solidaridad Social en Citizen Engagement and Solicitud de Single Stage - One Ejecución Comunidades Intervenidas IBRD / 85630 Posterior Limited 25,679.00 0.00 2019-04-04 2019-04-28 2019-05-28 Community Participation cotizaciones Envelope pendiente (Entrega de articulos deportivos, uniformes, equipamiento para centros comunitarios, etc.) B-2-4 / b.2.4. Edeeste: Gastos de Gestion Social, tales como: Actividades de Solidaridad Social en Citizen Engagement and Solicitud de Single Stage - One Ejecución Comunidades Intervenidas IBRD / 85630 Posterior Limited 15,285.00 0.00 2019-04-04 2019-04-28 2019-05-28 Community Participation cotizaciones Envelope pendiente (Entrega de articulos deportivos, uniformes, equipamiento para centros comunitarios, etc.) B-2-5 / b.2.5 Adquisicion Vehiculos para uso de la Citizen Engagement and Solicitud de Single Stage - One Ejecución Gestion Social de las IBRD / 85630 Previa Open - National 425,000.00 0.00 2017-05-12 2017-05-22 2017-07-03 2017-08-11 2017-09-05 2017-09-30 Community Participation ofertas Envelope pendiente distribuidoras (EDESUR- EDENORTE-EDEESTE) Page 2 B-2-6 / b.2.6 Adquisicion de bombillas de bajo consumo Citizen Engagement and Solicitud de Single Stage - One para las distribuidoras IBRD / 85630 Posterior Open - National 207,600.00 153,447.20 Firmado 2018-08-06 2019-10-02 2018-08-08 2019-10-09 2018-09-07 2019-11-14 2018-09-17 2019-12-20 2018-09-29 2020-02-25 2018-12-18 Community Participation ofertas Envelope (EDESUR-EDENORTE- EDEESTE) B-2-7 / b.2.7 Adqusicion de materiales Impresos (Publicitarios, didacticos y Citizen Engagement and Solicitud de Single Stage - One Ejecución IBRD / 85630 Posterior Limited 112,307.00 0.00 2018-08-07 2018-09-01 2018-10-16 brochures) para las Community Participation cotizaciones Envelope pendiente distribuidoras (EDESUR- EDENORTE- EDEESTE) Commercial Management and Project Management, B-3-1 / b.3.1. Equipamiento Monitoring and Evaluation Solicitud de Open - Single Stage - One Ejecución e Implementacion IBRD / 85630 of the Distribution Grid Previa 3,500,000.00 0.00 2019-01-15 2019-01-25 2019-03-08 2019-03-28 2019-04-27 2019-06-26 ofertas International Envelope pendiente DataCenter Modernization and Electri cal Losses Reduction Program Commercial Management B-3-2 / b.3.2. Adquisicion and Project Management, de vehiculos para realizar Monitoring and Evaluation Solicitud de Single Stage - One Ejecución visitas de supervision tecnica IBRD / 85630 of the Distribution Grid Previa Open - National 304,000.00 0.00 2017-09-05 2017-09-10 2017-10-22 2017-11-21 2017-12-26 2018-06-24 ofertas Envelope pendiente a las zonas de las obras Modernization and Electri (UEP-EDE) cal Losses Reduction Program B-3-5-2 / b.3.5.2 Equipos Commercial Management Informaticos para la and Project Management, Adecuacion de oficina Monitoring and Evaluation comercial tipo A, en la zona Solicitud de Single Stage - One Ejecución IBRD / 85630 of the Distribution Grid Posterior Limited 56,758.00 0.00 2018-02-06 2018-03-01 2018-03-22 de influencia de los circuitos cotizaciones Envelope pendiente Modernization and Electri de Edesur (Contempla la cal Losses Reduction adquisicion de mobiliario) - Program Comercial B-2-8 / Adq. Cámaras para Premiación Concurso Citizen Engagement and Solicitud de Single Stage - One Ejecución Fotografía Uso Racional de IBRD / 85630 Posterior Limited 4,000.00 0.00 2019-01-24 2019-02-18 2019-03-20 Community Participation cotizaciones Envelope pendiente Energía en Circuitos en el Ámbito del Proyecto. B-2-10 / Adq. Placas de Reconocimiento para líderes Citizen Engagement and Solicitud de Single Stage - One Ejecución Comunitarios de los Comités IBRD / 85630 Posterior Limited 3,500.00 0.00 2019-09-04 2019-09-23 2019-10-23 Community Participation cotizaciones Envelope pendiente de Seguimiento de los Circuitos Intervenidos. B-2-9 / Adq. de artículos publicitarios para la Citizen Engagement and Solicitud de Single Stage - One IBRD / 85630 Posterior Limited 30,000.00 12,144.18 Firmado 2018-10-24 2018-10-31 2018-11-12 2018-11-16 2018-12-12 campaña del subcomponente Community Participation cotizaciones Envelope de gestión ambiental Commercial Management B-3-9 / Adq de 3 Camiones and Project Management, Tipo Carga, sin carga - 4 Monitoring and Evaluation Solicitud de Single Stage - One Furgonetas - 2 Minibuses de IBRD / 85630 of the Distribution Grid Posterior Open - National 429,300.00 406,877.98 Firmado 2019-04-30 2019-05-10 2019-05-05 2019-05-14 2019-06-04 2019-06-18 2019-06-19 2019-07-19 2019-07-11 2019-08-27 2019-08-25 ofertas Envelope 15 Pasajeros - y 4 Modernization and Electri Camionetas - para Edeeste. cal Losses Reduction Program B-3-4 / b.3.4. Adquisicion de 4 oficinas comerciales Commercial Management moviles (1 Edesur - 2 and Project Management, Edenorte - 1 Edeeste) Monitoring and Evaluation Solicitud de Single Stage - One (Incluye: Adquisicion de IBRD / 85630 of the Distribution Grid Posterior Open - National 119,118.00 0.00 En ejecución 2018-09-19 2019-06-13 2018-09-24 2018-11-05 2018-12-05 2019-01-09 2019-03-10 ofertas Envelope camion, mobiliario, equipos Modernization and Electri de informaticos, equipo de cal Losses Reduction sonido, senalizacion) - Program Comercial Page 3 Commercial Management and Project Management, Monitoring and Evaluation B-3-10 / Adq de 6 Quioscos Solicitud de Single Stage - One IBRD / 85630 of the Distribution Grid Posterior Limited 49,800.00 24,003.56 En ejecución 2019-05-23 2019-06-12 2019-06-16 2019-07-09 2019-07-31 2019-07-16 de Autopago para Edeeste cotizaciones Envelope Modernization and Electri cal Losses Reduction Program Commercial Management and Project Management, B-3-3-A / Adq. de Licencias Monitoring and Evaluation Adobe Acrobat Professional y Solicitud de Single Stage - One IBRD / 85630 of the Distribution Grid Posterior Limited 7,558.00 3,496.06 Finalizado 2019-05-01 2019-04-26 2019-05-12 2019-05-08 2019-05-27 2019-05-16 Adobe Creative Cloud for cotizaciones Envelope Modernization and Electri Teams para la UEP. cal Losses Reduction Program Commercial Management and Project Management, Monitoring and Evaluation B-3-3-B / Adquisición de Solicitud de Single Stage - One IBRD / 85630 of the Distribution Grid Posterior Limited 1,000.00 0.00 En ejecución 2019-05-01 2019-04-25 2019-05-17 2019-06-01 Trituradora para la UEP. cotizaciones Envelope Modernization and Electri cal Losses Reduction Program Commercial Management and Project Management, B-3-3 / b.3.3. Adquisicion Monitoring and Evaluation Solicitud de Single Stage - One Ejecución de Equipos Informaticos para IBRD / 85630 of the Distribution Grid Posterior Limited 36,442.00 0.00 2018-02-10 2018-04-07 2018-06-06 cotizaciones Envelope pendiente la UEP Modernization and Electri cal Losses Reduction Program B-3-5-1 / b.3.5.1 Adecuacion Commercial Management de oficinas comerciales tipo and Project Management, B, en la zona de influencia Monitoring and Evaluation Solicitud de Single Stage - One de los circuitos de Edenorte IBRD / 85630 of the Distribution Grid Posterior Open - National 339,650.00 0.00 Cancelado 2018-10-29 2018-11-03 2018-12-03 2018-12-18 2019-01-07 2019-03-08 ofertas Envelope y Edesur (Contempla la Modernization and Electri adquisicion de mobiliario) - cal Losses Reduction Comercial Program Commercial Management B-3-7 / b.3.7. and Project Management, Implementacion Sistema de Monitoring and Evaluation Administracion de Turnos Solicitud de Single Stage - One IBRD / 85630 of the Distribution Grid Posterior Limited 12,000.00 0.00 Cancelado 2018-08-13 2018-09-27 2018-10-27 (Computadoras, Software, cotizaciones Envelope Modernization and Electri Impresoras Pantalla de TV, cal Losses Reduction Audio) - Comercial Program Commercial Management B-3-6-A / b.3.6. Adquisicion and Project Management, de materiales para suplir Monitoring and Evaluation Demanda Comercial y Solicitud de Open - Single Stage - One IBRD / 85630 of the Distribution Grid Previa 1,551,261.00 968,330.52 En ejecución 2019-04-22 2019-09-12 2019-04-27 2019-09-23 2019-06-08 2019-11-15 2019-06-23 2020-02-05 2019-07-22 2019-11-19 Mantenimiento (Medidores, ofertas International Envelope Modernization and Electri acometidas, cajas, etc) - cal Losses Reduction Comercial Program Rehabilitation of Selected B-1-2-A / Adq. 5 laptops Distribution Circuits and para los técnicos y Upgrading of Metering Solicitud de Single Stage - One IBRD / 85630 Posterior Limited 6,750.00 7,526.12 Finalizado 2019-08-28 2019-08-29 2019-09-14 2019-09-30 2019-10-14 2019-11-05 coordinadores ambientales de Systems - Implementation of cotizaciones Envelope las EDE. Environmental Manag ement System B-2-11 / Adq. 18 parantes alusivos al Programa de Citizen Engagement and Solicitud de Single Stage - One Ejecución IBRD / 85630 Posterior Limited 2,250.00 0.00 2019-09-15 2019-10-02 2019-10-17 Rehabilitación de Redes Community Participation cotizaciones Envelope pendiente Eléctricas B-2-12 / B-2-12 Adq. 651 Collarines alusivos al Citizen Engagement and Solicitud de Single Stage - One Ejecución IBRD / 85630 Posterior Limited 1,623.00 0.00 2019-09-15 2019-10-14 2019-10-29 Programa de Rehabilitación Community Participation cotizaciones Envelope pendiente de Redes Eléctricas Page 4 B-2-13 / B-2-13 Adq. 47,250 cajitas de crayones para Citizen Engagement and Solicitud de Single Stage - One Ejecución completivo de los libros de IBRD / 85630 Posterior Limited 16,029.00 0.00 2019-09-15 2019-10-16 2019-10-31 Community Participation cotizaciones Envelope pendiente colorear sobre uso eficiente y seguro de energía. Rehabilitation of Selected B-1-2-B / B-1-2-B Máscaras Distribution Circuits and y filtros para el personal Upgrading of Metering Solicitud de Single Stage - One Ejecución IBRD / 85630 Posterior Limited 1,800.00 0.00 2019-11-23 2019-12-10 2020-01-09 Gestión Ambiental de las Systems - Implementation of cotizaciones Envelope pendiente EDE. Environmental Manag ement System Rehabilitation of Selected Distribution Circuits and B-2-15 / B-2-15 Luminarias Upgrading of Metering Solicitud de Single Stage - One Ejecución para los Ciruelitos IBRD / 85630 Posterior Limited 700.00 0.00 2019-11-25 2019-12-19 2020-01-18 Systems - Implementation of cotizaciones Envelope pendiente (Comunidad Edenorte) Environmental Manag ement System B-2-14 / Adq. 800 agendas 2020 del Programa de Citizen Engagement and Solicitud de Single Stage - One Ejecución IBRD / 85630 Posterior Limited 10,717.00 0.00 2019-12-13 2020-01-01 2020-01-31 Rehabilitación de Redes Community Participation cotizaciones Envelope pendiente Eléctricas. Commercial Management B-3-11 / Adq. Equipos and Project Management, técnologicos para oficinas de Monitoring and Evaluation Solicitud de Single Stage - One Edesur (San Cristóbal 1er y IBRD / 85630 of the Distribution Grid Posterior Open - National 116,127.00 0.00 En ejecución 2019-12-27 2020-02-03 2020-01-03 2020-02-04 2020-02-02 2020-02-17 2020-03-03 2020-04-17 ofertas Envelope 3er Piso, Patio Colombia, Modernization and Electri San Cristóbal Norte) cal Losses Reduction Program Commercial Management and Project Management, B-3-12 / Adq. Kiosco para Monitoring and Evaluation Solicitud de Single Stage - One Ejecución oficina Patio Colombia, IBRD / 85630 of the Distribution Grid Posterior Limited 4,730.00 0.00 2020-03-08 2020-04-02 2020-04-17 cotizaciones Envelope pendiente Edesur Modernization and Electri cal Losses Reduction Program Commercial Management B-3-13 / Adq. de and Project Management, Señalizaciones de Mercadeo Monitoring and Evaluation para Oficinas de Edesur Solicitud de Single Stage - One Ejecución IBRD / 85630 of the Distribution Grid Posterior Limited 25,198.00 0.00 2020-03-08 2020-03-30 2020-04-29 (San Cristóbal 1er y 3er cotizaciones Envelope pendiente Modernization and Electri piso, Patio Colombia y San cal Losses Reduction Cristóbal Norte) Program Commercial Management B-3-14 / Adq. equipos de and Project Management, comunicaciones oficinas de Monitoring and Evaluation Adquisición Ejecución Edesur (San Cristóbal 1er y IBRD / 85630 of the Distribution Grid Posterior Direct 9,985.00 0.00 2020-03-06 2020-03-11 2020-03-23 2020-05-07 directa pendiente 3er piso, Patio Colombia y Modernization and Electri San Cristóbal Norte) cal Losses Reduction Program Commercial Management B-3-15 / Adq. de Licencias and Project Management, de Software de Turnos Eflow Monitoring and Evaluation para las oficinas de Edesur Adquisición Ejecución IBRD / 85630 of the Distribution Grid Posterior Direct 8,510.00 0.00 2020-03-06 2020-03-11 2020-03-23 2020-04-22 (San Cristóbal 1er y 3er directa pendiente Modernization and Electri piso, Patio Colombia y San cal Losses Reduction Cristóbal Norte) Program Commercial Management B-3-16 / Adq. Equipos para and Project Management, seguridad y vigilancia de las Monitoring and Evaluation oficinas de Edesur (San Solicitud de Single Stage - One Ejecución IBRD / 85630 of the Distribution Grid Posterior Limited 31,982.00 0.00 2020-03-11 2020-04-08 2020-05-23 Cristóbal 1er y 3er, Patio cotizaciones Envelope pendiente Modernization and Electri Colombia y San Cristóbal cal Losses Reduction Norte) Program Page 5 Commercial Management and Project Management, Monitoring and Evaluation B-3-8 / b.3.8 Armarios para Solicitud de Single Stage - One IBRD / 85630 of the Distribution Grid Posterior Limited 37,400.00 0.00 Cancelado 2018-11-03 2018-12-25 2019-01-09 area de Archivo - UEP cotizaciones Envelope Modernization and Electri cal Losses Reduction Program Commercial Management and Project Management, B-3-8-A / Fabricación e Monitoring and Evaluation Adquisición Ejecución Instalacion de Archivos para IBRD / 85630 of the Distribution Grid Posterior Direct 29,628.00 0.00 2019-12-27 2019-12-30 2020-01-11 2020-02-10 directa pendiente UEP Modernization and Electri cal Losses Reduction Program Rehabilitation of Selected B-1-1-A / Adq. de Kit para Distribution Circuits and Análisis Cualitativo - Upgrading of Metering Adquisición Subprograma de manejo y IBRD / 85630 Posterior Direct 20,000.00 0.00 En ejecución 2019-12-26 2019-12-05 2019-12-31 2020-01-09 2020-02-08 Systems - Implementation of directa disposición de aceite con Environmental Manag ement PCB . System B-2-16 / Adq. de Furgón para almacenamiento Citizen Engagement and Solicitud de Single Stage - One Ejecución IBRD / 85630 Posterior Limited 5,200.00 0.00 2020-03-27 2020-04-17 2020-06-16 temporal de bienes o Community Participation cotizaciones Envelope pendiente materiales UEP/CDEEE B-2-17 / Adquisición de Citizen Engagement and Solicitud de Single Stage - One Ejecución Uniformes para personal de IBRD / 85630 Posterior Limited 31,293.00 0.00 2020-03-27 2020-04-22 2020-06-21 Community Participation cotizaciones Envelope pendiente gestión social de las EDE. B-3-17 / Adquisición de mobiliario para el salón de Citizen Engagement and Solicitud de Single Stage - One Ejecución IBRD / 85630 Posterior Limited 9,260.00 0.00 2020-03-27 2020-04-20 2020-05-20 reuniones (mesas, sillones y Community Participation cotizaciones Envelope pendiente credenza) B-2-18 / Adq. Materiales para prácticas del programa de formación de electricistas Citizen Engagement and Solicitud de Single Stage - One Ejecución IBRD / 85630 Posterior Limited 11,879.34 0.00 2020-03-27 2020-04-23 2020-05-23 comunitarios (incluye Community Participation cotizaciones Envelope pendiente materiales eléctricos, tubos, plywood para panales) B-2-19 / Adquisición de Kits de herramientas para Citizen Engagement and Solicitud de Single Stage - One Ejecución los participantes del IBRD / 85630 Posterior Limited 30,125.00 0.00 2020-03-27 2020-04-18 2020-05-03 Community Participation cotizaciones Envelope pendiente programa de formación de electricistas comunitarios B-2-20 / Reproducción de Citizen Engagement and Solicitud de Single Stage - One Ejecución letreros prepago para las IBRD / 85630 Posterior Limited 3,150.00 0.00 2020-03-27 2020-04-15 2020-05-15 Community Participation cotizaciones Envelope pendiente EDE Commercial Management and Project Management, B-3-18 / Adquisición de Monitoring and Evaluation artículos de protección contra Solicitud de Single Stage - One Ejecución IBRD / 85630 of the Distribution Grid Posterior Limited 98,000.00 0.00 2020-06-06 2020-07-02 2020-08-01 el COVID-19 para personal cotizaciones Envelope pendiente Modernization and Electri de la CDEEE y las EDE. cal Losses Reduction Program Commercial Management and Project Management, B-3-3-C / Adquisición de Monitoring and Evaluation Solicitud de Single Stage - One Ejecución una laptop para la IBRD / 85630 of the Distribution Grid Posterior Limited 1,600.00 0.00 2020-05-16 2020-06-06 2020-06-21 cotizaciones Envelope pendiente coordinación de la UEP Modernization and Electri cal Losses Reduction Program Page 6 NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual S-1-1 / S.1.1 Transporte Rehabilitation of Selected para el Movimiento de Distribution Circuits and Transformadores con PCB - Upgrading of Metering Solicitud de Open - Single Stage - One Ejecución Tratamiento final Equipo IBRD / 85630 Posterior 110,000.00 0.00 2018-12-11 2018-12-16 2019-01-27 2019-02-26 2019-04-02 2019-06-01 Systems - Implementation of ofertas International Envelope pendiente Contaminado - PMAA Environmental Manag ement (EDESUR - EDENORTE - System EDEESTE) S-2-1 / S.2.1 Edesur: Gastos de Gestión Social, tales como: Actividades de Solidaridad Social en Citizen Engagement and Solicitud de Single Stage - One Ejecución IBRD / 85630 Posterior Limited 6,040.00 0.00 2019-04-06 2019-05-07 2019-11-03 Comunidades Intervenidas Community Participation cotizaciones Envelope pendiente (Refrigerios, Transporte, Alquileres de Carpas, sillas y mesas, etc.) S-2-2 / S.2.2 Edenorte: Gastos de Gestión Social, tales como: Actividades de Solidaridad Social en Citizen Engagement and Solicitud de Single Stage - One Ejecución IBRD / 85630 Posterior Limited 6,420.00 0.00 2019-04-06 2019-05-07 2019-11-03 Comunidades Intervenidas Community Participation cotizaciones Envelope pendiente (Refrigerios, Transporte, Alquileres de Carpas, sillas y mesas, etc.) S-2-3 / S.2.3 Edeeste: Gastos de Gestión Social, tales como: Actividades de Solidaridad Social en Citizen Engagement and Solicitud de Single Stage - One Ejecución IBRD / 85630 Posterior Limited 3,821.00 0.00 2019-05-21 2019-06-21 2019-12-18 Comunidades Intervenidas Community Participation cotizaciones Envelope pendiente (Refrigerios, Transporte, Alquileres de Carpas, sillas y mesas, etc.) S-2-5 / S.2.5. Campaña Digitales en Redes Sociales Citizen Engagement and Solicitud de Single Stage - One Ejecución del Programa de IBRD / 85630 Posterior Limited 60,000.00 0.00 2019-05-30 2019-06-21 2019-10-19 Community Participation cotizaciones Envelope pendiente Rehabilitación de Redes Eléctricas. S-2-6 / Logística para Ceremonia de Premiación Concurso Fotográfico Uso Racional de Energía en Citizen Engagement and Solicitud de Single Stage - One Ejecución IBRD / 85630 Posterior Limited 7,000.00 0.00 2019-02-06 2019-02-28 2019-03-05 Circuitos en el Ámbito del Community Participation cotizaciones Envelope pendiente Proyecto - EDE (Refrigerios, Luces de ambientación, Truss, Bajantes, etc). S-2-7 / Contratación de servicios para Ruta de Aprendizaje CIclo de Energá Citizen Engagement and Solicitud de Single Stage - One Ejecución IBRD / 85630 Posterior Limited 8,000.00 0.00 2019-06-07 2019-07-07 2019-08-06 para Lideres Comutarios de Community Participation cotizaciones Envelope pendiente Edesur - Edenorte - Edeeste (Transporte y Refrigerios) S-2-4 / S.2.4 Implementación del Plan de Citizen Engagement and Solicitud de Single Stage - One Ejecución IBRD / 85630 Posterior Limited 205,974.00 0.00 2019-01-12 2019-02-12 2019-05-13 Comunicación del PRRE Community Participation cotizaciones Envelope pendiente (Publicidad Externa) Page 7 Commercial Management S-3-1 / S.3.1. Contratación and Project Management, Servicios de Empresas (15 Monitoring and Evaluation Brigadas) para Gestión Solicitud de Single Stage - One IBRD / 85630 of the Distribution Grid Posterior Open - National 216,333.00 0.00 Cancelado 2019-03-28 2019-04-02 2019-05-14 2019-06-13 2019-07-08 2020-07-07 Técnico - Comercial y ofertas Envelope Modernization and Electri Disciplinario (EDENORTE), cal Losses Reduction por - Comercial Program Commercial Management S-3-2 / S.3.2. Contratación and Project Management, Servicios de Empresas (10 Monitoring and Evaluation Solicitud de Single Stage - One Brigadas) para Corte y IBRD / 85630 of the Distribution Grid Posterior Open - National 420,000.00 0.00 Cancelado 2019-03-28 2019-04-02 2019-05-14 2019-06-13 2019-07-18 2020-07-17 ofertas Envelope Reconexión (EDESUR) - Modernization and Electri Comercial cal Losses Reduction Program Commercial Management S-3-3 / S.3.3. Contratación and Project Management, Servicios de Empresas (18 Monitoring and Evaluation Brigadas) para Gestión Solicitud de Single Stage - One IBRD / 85630 of the Distribution Grid Previa Open - National 932,200.00 0.00 Cancelado 2018-12-03 2018-12-08 2019-01-19 2019-02-18 2019-03-25 2020-03-24 Técnico - Comercial y ofertas Envelope Modernization and Electri Disciplinario (EDEESTE) - cal Losses Reduction Comercial Program Rehabilitation of Selected S-1-2 / Disposición Final de Distribution Circuits and Residuos Peligrosos del Upgrading of Metering Solicitud de Single Stage - One Ejecución IBRD / 85630 Posterior Limited 45,000.00 0.00 2020-02-01 2020-03-03 2020-05-02 Programa de Rehabilitación Systems - Implementation of cotizaciones Envelope pendiente de Redes Eléctricas Environmental Manag ement System CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Selección basada C-2-9-B / c.2.9.b Realizacion Citizen Engagement and Ejecución IBRD / 85630 Posterior en calificaciones Open - National 40,000.00 0.00 2018-11-12 2018-12-03 2018-12-25 2019-01-01 2019-01-16 2019-04-16 Documental Proyecto BM Community Participation pendiente de consultores Commercial Management and Project Management, Monitoring and Evaluation C-3-1 / c.3.1 Auditoria Selección basada IBRD / 85630 of the Distribution Grid Posterior Open - National 150,000.00 0.00 Cancelado 2018-08-20 2018-09-10 2018-10-02 2018-10-30 2018-11-14 2018-12-01 2018-12-21 2019-12-21 Financiera del Proyecto en calidad y costo Modernization and Electri cal Losses Reduction Program Commercial Management and Project Management, C-3-2 / c.3.2 Firma Monitoring and Evaluation verificadora de la Calidad Selección basada Open - IBRD / 85630 of the Distribution Grid Previa 1,920,000.00 1,271,935.00 Firmado 2018-05-29 2018-06-26 2018-07-24 2018-10-04 2018-08-28 2018-11-22 2018-09-27 2019-01-14 2018-10-25 2019-04-25 2018-11-29 2019-04-25 2020-05-22 Tecnica de las Obras de en calidad y costo International Modernization and Electri Rehabilitacion de Redes cal Losses Reduction Program Commercial Management and Project Management, C-3-3 / c.3.3. Monitoring and Evaluation Selección basada Open - Ejecución Fortalecimiento Institucional IBRD / 85630 of the Distribution Grid Previa 500,000.00 0.00 2018-09-10 2018-10-01 2018-10-23 2018-11-20 2018-12-20 2019-01-24 2019-02-28 2020-02-28 en calidad y costo International pendiente de las EDE Modernization and Electri cal Losses Reduction Program Page 8 Commercial Management and Project Management, Monitoring and Evaluation C-3-1-A / Auditoria Selección basada IBRD / 85630 of the Distribution Grid Previa Open - National 150,000.00 0.00 Cancelado 2018-10-02 2018-10-25 2018-10-16 2018-11-07 2018-12-05 2018-12-20 2019-01-06 2019-02-03 2020-02-03 Financiera del Proyecto. en calidad y costo Modernization and Electri cal Losses Reduction Program Rehabilitation of Selected C-1-8 / c.1.8 Sistema de Distribution Circuits and Gestion Integral para la Upgrading of Metering Selección basada Ejecución Estandarizacion y Manejo IBRD / 85630 Posterior Open - National 400,000.00 0.00 2018-12-12 2019-01-02 2019-01-24 2019-02-28 2019-03-30 2019-04-20 2019-05-10 2019-11-06 Systems - Implementation of en calidad y costo pendiente Ambiental del Proyecto - Environmental Manag ement PMAA System C-2-9-A / c.2.9.a Produccion de Videos sobre el antes y Selección basada Citizen Engagement and después de las obras y IBRD / 85630 Posterior en calificaciones Open - National 21,100.00 0.00 En ejecución 2018-11-04 2018-12-13 2018-11-25 2019-02-07 2019-01-08 2019-03-28 2019-01-23 2019-02-27 2019-04-28 Community Participation testimonios de los de consultores beneficiarios. C-1-9 / c.1.9 Diagnostico y Rehabilitation of Selected monitoreo del estado actual Distribution Circuits and Selección basada del agua, suelo y aire en los Upgrading of Metering Ejecución IBRD / 85630 Posterior en calificaciones Open - National 55,000.00 0.00 2018-11-05 2018-11-26 2018-12-25 2019-01-24 2019-02-17 2019-05-18 sitios actuales de acopio, Systems - Implementation of pendiente de consultores almacen y sitios a remediar Environmental Manag ement - PMAA System INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Rehabilitation of Selected Distribution Circuits and C-1-1 / c.1.1 Coordinador Upgrading of Metering Selección directa Ejecución Ambiental para la UEP- IBRD / 85630 Previa Direct 144,000.00 0.00 2018-07-01 2018-07-11 2018-07-31 2019-07-26 Systems - Implementation of de consultores pendiente PMAA Environmental Manag ement System Rehabilitation of Selected C-1-5 / c.1.5 Dos Distribution Circuits and Inspectores Medioambientales Upgrading of Metering Selección directa Ejecución IBRD / 85630 Previa Direct 135,000.00 0.00 2018-06-04 2018-06-11 2018-06-29 2019-06-29 y de Seguridad Industrial Systems - Implementation of de consultores pendiente (EDESUR) - PMAA Environmental Manag ement System Rehabilitation of Selected C-1-6 / c.1.6 Dos Distribution Circuits and Inspectores Medioambientales Upgrading of Metering Selección directa Ejecución IBRD / 85630 Previa Direct 135,000.00 0.00 2018-06-04 2018-06-11 2018-07-01 2019-07-01 y de Seguridad Industrial Systems - Implementation of de consultores pendiente (EDENORTE) - PMAA Environmental Manag ement System Rehabilitation of Selected C-1-7 / c.1.7 Dos Distribution Circuits and Inspectores Medioambientales Upgrading of Metering Selección directa Ejecución IBRD / 85630 Previa Direct 135,000.00 0.00 2018-06-04 2018-06-11 2018-07-01 2019-07-01 y de Seguridad Industrial Systems - Implementation of de consultores pendiente (EDEESTE) - PMAA Environmental Manag ement System Rehabilitation of Selected Distribution Circuits and C-1-10 / c.1.10 Auditorias Upgrading of Metering Ejecución de apoyo a la supervision y IBRD / 85630 Posterior Individual Limited 44,000.00 0.00 2020-01-10 2020-01-15 2020-02-04 2020-03-10 2020-04-24 Systems - Implementation of pendiente capacitacion - PMAA Environmental Manag ement System Page 9 Rehabilitation of Selected Distribution Circuits and C-1-11 / c.1.11 Consultor Upgrading of Metering Ejecución para el Diseno de los IBRD / 85630 Posterior Individual Limited 7,900.00 0.00 2018-07-09 2018-07-16 2018-07-26 2018-08-09 2018-11-07 Systems - Implementation of pendiente Puntos Verdes - PMAA Environmental Manag ement System C-2-1 / c.2.1 Contratacion Citizen Engagement and Selección directa Coordinador de Gestion IBRD / 85630 Previa Direct 49,392.00 0.00 En ejecución 2018-06-01 2018-06-06 2018-07-01 2019-07-01 Community Participation de consultores Social C-2-2 / c.2.2 Contratacion Citizen Engagement and Selección directa IBRD / 85630 Previa Direct 33,516.00 0.00 Cancelado 2018-06-04 2018-06-10 2018-08-01 2019-08-01 Analista de Gestion Social Community Participation de consultores C-2-10 / c.2.10 Consultor para el Diseno de la Citizen Engagement and Muestra para el Calculo de IBRD / 85630 Posterior Individual Limited 25,000.00 0.00 En ejecución 2018-06-28 2018-10-01 2018-07-10 2018-10-04 2018-08-09 2018-08-31 2018-10-15 Community Participation Usuarios Servicio Electrico y Capacitacion Personal Commercial Management and Project Management, C-3-4 / c.3.4. Especialista Monitoring and Evaluation Ejecución Adm Legal Contratos Obras, IBRD / 85630 of the Distribution Grid Posterior Individual Limited 102,000.00 0.00 2018-05-22 2018-05-23 2018-06-06 2018-06-15 2019-06-15 pendiente Bienes y Consultorias Modernization and Electri cal Losses Reduction Program Commercial Management and Project Management, Monitoring and Evaluation C-3-5 / c.3.5 Especialista de Selección directa Ejecución IBRD / 85630 of the Distribution Grid Previa Direct 118,000.00 0.00 2019-03-18 2019-03-23 2019-04-10 2020-04-09 Proyectos UEP de consultores pendiente Modernization and Electri cal Losses Reduction Program Commercial Management and Project Management, Monitoring and Evaluation C-3-7 / c.3.7 Analista de Selección directa Ejecución IBRD / 85630 of the Distribution Grid Previa Direct 48,000.00 0.00 2018-06-04 2018-06-09 2018-07-01 2019-07-01 Adquisiciones - UEP de consultores pendiente Modernization and Electri cal Losses Reduction Program Commercial Management and Project Management, Monitoring and Evaluation C-3-8 / c.3.8 Ingeniero Selección directa Ejecución IBRD / 85630 of the Distribution Grid Previa Direct 64,000.00 0.00 2018-06-06 2018-06-11 2018-07-01 2019-07-01 Supervisor UEP de consultores pendiente Modernization and Electri cal Losses Reduction Program Commercial Management and Project Management, C-3-9 / c.3.9 Especialista Monitoring and Evaluation Selección directa Ejecución Monitoreo y Evaluacion del IBRD / 85630 of the Distribution Grid Previa Direct 96,000.00 0.00 2018-06-06 2018-06-11 2018-07-16 2019-07-16 de consultores pendiente Proyecto Modernization and Electri cal Losses Reduction Program C-2-11 / c.2.11 Consultor para el Diseno Grafico de Productos Comunicacionales Citizen Engagement and Ejecución IBRD / 85630 Posterior Individual Limited 38,900.00 0.00 2018-06-01 2018-06-12 2018-07-12 2018-08-01 2019-08-01 del Programa de Community Participation pendiente Rehabilitacion de Redes Electricas C-2-5-1 / C-2-5-1 Contratación Analistas de Citizen Engagement and IBRD / 85630 Posterior Individual Limited 63,520.00 0.00 En ejecución 2018-10-15 2018-10-27 2018-10-22 2018-10-29 2018-10-27 2018-10-31 2019-10-31 Datos para Edesur y Community Participation Edeeste. Page 10 Commercial Management and Project Management, Monitoring and Evaluation C-3-1-B / c.3.1 Auditoria Selección directa IBRD / 85630 of the Distribution Grid Previa Direct 112,000.00 30,746.08 Firmado 2018-10-30 2018-11-07 2018-11-07 2019-02-07 2019-03-08 2019-05-17 Financiera del Proyecto de consultores Modernization and Electri cal Losses Reduction Program C-2-3-A / C-2-3 Citizen Engagement and Contratación Encargada de IBRD / 85630 Posterior Individual Limited 55,219.00 0.00 En ejecución 2019-04-10 2019-04-10 2019-04-15 2019-04-30 2019-05-10 2020-05-09 Community Participation Comunicaciones de la UEP. C-2-3 / c.2.3 Encargada de Citizen Engagement and Selección directa IBRD / 85630 Previa Direct 55,219.00 0.00 Cancelado 2018-12-10 2018-12-15 2019-01-10 2020-01-10 Comunicaciones de la UEP Community Participation de consultores C-2-5 / c.2.5. Contratacion Citizen Engagement and Selección directa Ejecución Directa Analista de datos IBRD / 85630 Posterior Direct 36,735.00 0.00 2018-05-15 2018-05-25 2018-07-01 2019-07-01 Community Participation de consultores pendiente Edenorte C-2-7 / c.2.7 Contratacion de 12 Gestores Sociales de Citizen Engagement and Selección directa Ejecución Informacion para las EDE ( IBRD / 85630 Posterior Direct 244,754.00 0.00 2018-05-14 2018-05-20 2018-06-16 2019-06-16 Community Participation de consultores pendiente 4 EDESUR - 4 EDENORTE - 4 EDEESTE) C-2-8 / c.2.8 Contratacion de 95 personas para gestion social de las EDE (entre Citizen Engagement and Ejecución gestores y supervisores IBRD / 85630 Posterior Individual Limited 2,032,231.00 0.00 2017-06-06 2017-06-11 2017-07-11 2017-08-31 2018-08-31 Community Participation pendiente sociales (36 EDESUR - 37 EDENORTE y 22 EDEESTE) C-3-10 / Contratación Directa de 4 captores Commercial Management actuales, cuyos contratos and Project Management, vencen para aprovechar: la Monitoring and Evaluation Ejecución compentencia de este IBRD / 85630 of the Distribution Grid Posterior Individual Direct 27,890.46 0.00 2019-06-10 2019-06-14 2019-06-19 2019-06-29 2020-06-28 pendiente personal, la inversión Modernization and Electri realizada en capacitación, cal Losses Reduction la sinergia del equipo de Program trabajo, etc. Commercial Management and Project Management, C-3-11 / Contratación de 4 Monitoring and Evaluation Ejecución captores comerciales para IBRD / 85630 of the Distribution Grid Posterior Individual Limited 27,980.46 0.00 2019-06-10 2019-06-15 2019-06-20 2019-06-27 2020-06-26 pendiente Edenorte. Modernization and Electri cal Losses Reduction Program Commercial Management and Project Management, C-3-12 / Contratación Monitoring and Evaluation Directa de 5 supervisores de Ejecución IBRD / 85630 of the Distribution Grid Posterior Individual Direct 47,065.15 0.00 2019-06-10 2019-06-14 2019-06-19 2019-06-29 2020-06-28 captores comerciales para pendiente Modernization and Electri Edenorte cal Losses Reduction Program C-2-4-B / c.2.4-B Contratación Encargada de Citizen Engagement and Ejecución IBRD / 85630 Posterior Individual Limited 18,900.00 0.00 2018-06-25 2019-04-10 2019-05-01 2019-06-10 2020-06-09 Comunicaciones de Edeeste, Community Participation pendiente por un año C-2-4 / c.2.4 Consultores de Citizen Engagement and Selección directa Ejecución Comunicacion y Publicidad IBRD / 85630 Posterior Direct 91,789.00 0.00 2019-06-07 2019-06-12 2019-07-03 2020-07-02 Community Participation de consultores pendiente de las EDE Page 11 Commercial Management and Project Management, Monitoring and Evaluation C-3-6 / c.3.6. Especialista Selección directa IBRD / 85630 of the Distribution Grid Previa Direct 118,000.00 0.00 Cancelado 2018-12-10 2018-12-15 2019-01-02 2020-01-02 en Adquisiciones UEP de consultores Modernization and Electri cal Losses Reduction Program C-1-9-A / Consultor para la evaluación ambiental y Rehabilitation of Selected propuesta de remediación de Distribution Circuits and sitios para ser utilizados Upgrading of Metering Ejecución IBRD / 85630 Posterior Individual Open 55,000.00 0.00 2019-05-13 2019-06-18 2019-07-09 2019-08-13 2019-11-11 como lugar de Systems - Implementation of pendiente almacenamiento de residuos Environmental Manag ement eléctricos generados por el System Proyecto Rehabilitation of Selected C-1-4 / c.1.4. Coordinador Distribution Circuits and Ambiental y Seguridad Upgrading of Metering IBRD / 85630 Posterior Individual Limited 93,600.00 0.00 Cancelado 2018-07-23 2018-07-28 2018-08-07 2018-09-01 2019-09-01 Industrial (EDEESTE) - Systems - Implementation of PMAA Environmental Manag ement System Rehabilitation of Selected C-1-4-A / Coordinador Distribution Circuits and Ambiental y Seguridad Upgrading of Metering Selección directa Ejecución IBRD / 85630 Posterior Direct 93,600.00 0.00 2019-06-25 2019-06-30 2019-07-04 2020-07-03 Industrial (EDEESTE) – Systems - Implementation of de consultores pendiente PMAA Environmental Manag ement System Rehabilitation of Selected C-1-2 / c.1.2. Coordinador Distribution Circuits and Ambiental y Seguridad Upgrading of Metering IBRD / 85630 Posterior Individual Limited 93,600.00 0.00 Cancelado 2018-08-09 2018-08-17 2018-08-22 2018-09-01 2019-08-27 Industrial (EDESUR) - Systems - Implementation of PMAA Environmental Manag ement System Rehabilitation of Selected C-1-3 / c.1.3. Coordinador Distribution Circuits and Ambiental y Seguridad Upgrading of Metering IBRD / 85630 Posterior Individual Limited 93,600.00 0.00 Cancelado 2018-07-23 2018-07-28 2018-08-07 2018-09-01 2019-09-01 Industrial (EDENORTE)- Systems - Implementation of PMAA Environmental Manag ement System Rehabilitation of Selected C-1-2-A / Coordinador Distribution Circuits and Ambiental y Seguridad Upgrading of Metering Selección directa Ejecución IBRD / 85630 Posterior Direct 93,600.00 0.00 2019-06-25 2019-08-26 2019-09-04 2020-09-03 Industrial (EDESUR) – Systems - Implementation of de consultores pendiente PMAA Environmental Manag ement System Rehabilitation of Selected C-1-3-A / Coordinador Distribution Circuits and Ambiental y Seguridad Upgrading of Metering Selección directa Ejecución IBRD / 85630 Posterior Direct 93,600.00 0.00 2019-06-25 2019-08-26 2019-09-04 2020-09-03 Industrial (EDENORTE) – Systems - Implementation of de consultores pendiente PMAA Environmental Manag ement System C-2-2-A / C-2-2-A Citizen Engagement and Ejecución Contratación Analista de IBRD / 85630 Posterior Individual Limited 22,000.00 0.00 2019-09-02 2019-09-07 2019-09-28 2019-11-02 2019-12-02 Community Participation pendiente Gestión Social para la UEP C-2-6 / c.2.6 Contratacion Consultores Asistentes Citizen Engagement and Selección directa Ejecución IBRD / 85630 Posterior Direct 72,554.00 0.00 2018-05-15 2018-05-23 2018-06-16 2019-06-16 Gestión Social de las EDE Community Participation de consultores pendiente (EDENORTE - EDEESTE) C-2-6-A / Contratación Citizen Engagement and Ejecución Asistente Gestión Social de IBRD / 85630 Posterior Individual Limited 13,500.00 0.00 2020-01-26 2020-02-02 2020-02-12 2020-02-27 2020-12-31 Community Participation pendiente Edesur Page 12 Commercial Management and Project Management, C-3-3-B / Segundo Contrato Monitoring and Evaluation Selección directa Ejecución Especialista de Proyectos IBRD / 85630 of the Distribution Grid Posterior Direct 88,034.00 0.00 2020-03-12 2020-03-15 2020-04-12 2021-04-12 de consultores pendiente UEP/CDEEE Modernization and Electri cal Losses Reduction Program Page 13