PROCUREMENT PLAN (Textual Part) Project information: [Mali] [Reinsertion of Ex-Combatants Project] [P157233] Project Implementation agency: [Project Implementation Unit (PIU) of the National Disarmament, Demobilization, and Reinsertion Commission (NDDRC)] Date of the Procurement Plan: [01/28/2018] Period covered by this Procurement Plan: [02/15/2018 to 07/28/2019] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the [Decree No. 2015-3721 /MEF-SG dated October 22, 2015], such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: [is not applicable]; Works: [is not applicable] Other Relevant Procurement Information. PROCUREMENT Mali : Mali Reinsertion of Ex-combatants Project PLAN General Information Country: Mali Bank’s Approval Date of the Original Procurement Plan: 2018-01-30 2021-08-30 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P157233 GPN Date: Project Name: Mali Reinsertion of Ex-combatants Project Loan / Credit No: IDA / D1680 ML Reinsertion of Ex-combatants Project Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned CW-KID-03 / Tv. réalisation et équip. de 2 forages avec Single Stage - One 2020-03- IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 68,970.00 68,226.31 Signé 2019-11-27 2020-03-11 2020-01-16 2020-06-16 système solaire à Tintiska et à Envelope 01 Tinta ghène région de Kidal CW-KID-14 / Travaux de surcreusement de puits Single Stage - One 2020-12- pastoral à IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 43,103.00 44,118.22 Signé 2020-07-18 2020-10-15 2020-09-06 2020-12-24 Envelope 05 Anoumalène/aguelhoc dans la région de Kidal CW-TOM-07 / Tv réhabilitation du château du CSREF de Tombouctou ; Tv de Single Stage - One 2020-03- IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 71,154.00 55,631.38 Signé 2019-12-04 2020-05-26 2020-01-23 2020-07-22 réalisation d’une ADS à Envelope 08 Alkama bangou à Nboura région de Tombouctou CW-KID-07 / Tv. réalisation et équip 1 puit à Single Stage - One 2020-05- IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 20,688.00 22,193.82 Signé 2020-02-22 2020-05-11 2020-03-26 2020-07-02 Anhar/Tinzawatène commune Envelope 10 de Abeibara région de Kidal CW-KID-06 / Tv. réhab. du Single Stage - One 2019-12- radier de amassine dans la IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 31,923.00 32,022.95 Signé 2019-10-23 2020-05-13 2019-11-25 2020-07-02 Envelope 25 région de Kidal CW-MEN-05 / Travaux de réhabilitation trois adductions d'eau sommaire (AES) à Inzougaz, Assew et Single Stage - One 2020-12- IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 85,801.00 98,592.49 Signé 2020-07-29 2021-02-25 2020-09-17 2021-05-05 Tinazabène et de réalisation Envelope 16 d’une adduction d’eau à Wortakna dans la région de Ménaka CW-TOM-12 / Travaux de construction d'un forage Single Stage - One 2020-12- équipé d'un château et pompe IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 41,500.00 46,633.87 Signé 2020-08-08 2020-11-02 2020-09-27 2021-01-05 Envelope 26 solaire à Faytawane dans la région de Tombouctou CW-TOM-13 / Travaux de réhabilitation du canal principale et équipement d'un Single Stage - One 2020-11- IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 13,534.00 15,215.91 Signé 2020-08-08 2021-03-17 2020-09-27 2021-04-24 périmètre pour la culture du Envelope 26 riz à Mamadoukoyra dans la région de Tombouctou CW-GAO-14 / Travaux de surcreusement de 2 marres à Moudett et Intillit Nord à Moudett et Intillit, de construction d'une digue avec Single Stage - One 2020-12- IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 37,931.00 40,092.36 Signé 2020-08-26 2021-02-08 2020-10-15 2021-03-25 ouvrage à submersion Envelope 29 controlée à Abba Koyra et de construction d'un parc de vaccination à Haoussa dans la région de Gao CW-MEN-03 / Travaux de réalisation et équipement Single Stage - One En attente 2020-01- d’un forage à Adalwag IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 35,512.00 0.00 2019-10-26 2019-11-28 Envelope d'exécution 12 commune de Tidermène dans la région de Ménaka CW-KID-01 / Tv. Const. 3 salles de classe équipées 3 Single Stage - One 2019-12- IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 46,552.00 48,580.83 Signé 2019-10-23 2020-04-01 2019-11-25 2020-05-21 latrines et bureau mag. à Envelope 25 Efereur région de Kidal CW-GAO-10 / Travaux de réalisation et équipement de 3 forages en pompe solaire à Single Stage - One 2020-01- IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 171,914.00 168,511.94 Signé 2019-11-05 2020-03-09 2019-12-08 2020-04-24 Tabankorte à Almoustarat et Envelope 07 Nbeykoul lajoulla région de Gao CW-KID-10 / Travaux de construction d'une digue de Single Stage - One 2020-12- IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 75,862.00 83,304.91 Signé 2020-07-21 2020-12-07 2020-09-09 2021-02-03 protection à Kidal aviation, Envelope 08 région de Kidal CW-TOM-14 / Travaux de construction de 2 salles de Single Stage - One 2020-12- IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 39,326.00 40,628.28 Signé 2020-08-08 2020-10-09 2020-09-27 2021-01-15 classe à Milala dans la région Envelope 11 de Tombouctou CW-GAO-13 / Travaux de réalisation d’un périmètre maraicher pour la coopérative des femmes à Taboye et d’un Single Stage - One 2021-01- IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 19,224.00 22,192.41 Signé 2020-08-22 2021-02-08 2020-10-11 2021-03-25 périmètre 3 hectares pour Envelope 09 l’association des groupements ruraux villageois à Gounga dans la région de Gao Page 1 CW-GAO-03 / Tv const. 2 magasins dans le marché Taboye Commune Taboye cercle Bourem , Tv Const. 6 Single Stage - One 2020-01- IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 31,035.00 31,988.62 Signé 2019-11-02 2020-04-07 2019-12-05 2020-05-21 hangars dans le marché Envelope 04 TEMERA Commune de Temera cercle Bourem dans la région de Gao CW-GAO-04 / Travaux d’aménagement de la plaine Single Stage - One 2020-01- de Moudakhane Commune de IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 77,204.00 75,723.89 Signé 2019-11-02 2020-04-30 2019-12-05 2020-06-24 Envelope 04 Taboye cercle Bourem dans la région de Gao CW-GAO-01 / Construction de 3 salles de classes, Bureau Single Stage - One 2019-12- magasin et de 2 blocs de 3 IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 73,686.00 71,853.22 Signé 2019-11-03 2020-03-30 2019-12-06 2020-05-11 Envelope 12 latrines à Tindjirindjitane Tessit dans la région de Gao CW-GAO-11 / Travaux de réalisation et équipement Single Stage - One 2020-07- d’un forage en PMH à IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 43,103.00 43,521.01 Signé 2020-03-29 2020-05-20 2020-05-18 2020-06-26 Envelope 17 Tinassamede cercle de Bourem dans la région de Gao CW-TOM-11 / Travaux de réhabilitation d'une dune Single Stage - One 2020-01- ecole Oguenatt Ag ALWEYNA IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 25,862.00 26,781.47 Signé 2019-11-02 2020-04-06 2019-12-05 2020-05-22 Envelope 04 Ebanguimalane à GOSSI Gourma rharous CW-TOM-15 / Travaux d’équipement d'un forage en Single Stage - One 2020-12- mini adduction d'eau à IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 39,326.00 41,422.17 Signé 2020-08-08 2020-11-02 2020-09-27 2020-12-24 Envelope 26 Amachachare à Imbodiki dans la région de Tombouctou CW-KID-02 / Tv. réalisation et équip. 2 forage avec Single Stage - One 2020-03- IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 85,960.00 86,067.14 Signé 2019-11-27 2020-04-17 2020-01-16 2020-06-22 système solaire à Djanchassé Envelope 01 et à Takalout région de Kidal CW-TOM-04 / Travaux de fonçage d’un puit pastoral à Single Stage - One 2020-03- IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 27,557.00 15,184.40 Signé 2019-11-27 2020-06-03 2020-01-16 2020-07-22 Sakarouratan à BER dans la Envelope 01 région de Tombouctou CW-TAO-03 / Travaux de Single Stage - One 2020-01- construction d'un poste de IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 60,259.00 52,761.89 Signé 2019-10-30 2020-04-23 2019-12-02 2020-07-27 Envelope 31 santé avancé Taoudénit CW-TAO-02 / Tv const. 3 salles classes bureau magasin et un bloc 3 latrines Foum Elba cercle de Foum Elba et Tv Single Stage - One 2020-01- IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 139,102.00 152,039.31 Signé 2019-10-30 2020-04-01 2019-12-02 2020-07-22 const. 3 salles classes bureau Envelope 16 magasin et un bloc 3 latrines Al ourch cercle de Al ourch région de Taoudénit CW-MOP-04 / Tv 1 radier 50m kanibonzo: Const. clôture école diandiori Single Stage - One 2019-12- Sokoura; Const. 1mag stoc. IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 103,917.00 111,420.67 Signé 2019-10-19 2020-06-04 2019-11-21 2020-07-28 Envelope 21 Ass. karanga Guiné;Const. salle d’obs. mag. au CSR de Bankass CW-KID-09 / Travaux de réalisation de trois (3) forages équipés de Système Solaire Single Stage - One 2020-09- IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 129,300.00 136,059.86 Signé 2020-07-21 2020-11-02 2020-09-09 2020-12-24 àTidjazal, Intilit et Envelope 18 Abatolnmanit dans la région de Kidal CW-KID-11 / Travaux de réalisation et d’équipement de trois (3) puits citernes, de Single Stage - One 2020-12- IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 85,344.00 87,581.96 Signé 2020-07-21 2020-12-07 2020-09-09 2021-02-01 château et système solaire à Envelope 08 Abuyou, Agazer et Ibadid dans la région de Kidal CW-KID-12 / Travaux de réalisation de deux forages Single Stage - One 2020-09- équipés de Système Solaire à IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 86,206.00 91,106.07 Signé 2020-07-21 2020-11-16 2020-09-09 2021-01-07 Envelope 18 Tacharaght et Imasrakaden dans la région de Kidal CW-MEN-06 / Travaux d’équipement en systéme d'adduction d'eau sommaire à Afaisawa, de forage à Inafere Single Stage - One 2020-12- IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 79,870.00 80,382.27 Signé 2020-07-29 2020-10-08 2020-09-17 2020-12-22 et Tabakort, de réhabilitation Envelope 16 d’une adduction d'eau sommaire (AES) à Elangue dans la région de Ménaka CW-MEN-07 / Construction d'un parc de vaccination à Single Stage - One 2020-12- IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 29,310.00 21,780.91 Signé 2020-07-29 2020-10-09 2020-09-17 2020-12-21 Andéraboukane dans la région Envelope 16 de Ménaka CW-MOP-07 / Travaux de Single Stage - One 2020-11- réalisation d'un puits moderne IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 45,534.00 49,770.26 Signé 2020-07-11 2020-10-15 2020-08-30 2021-01-07 Envelope 28 dans la région de Mopti Page 2 CW-TAO-04 / Travaux de Réalisation de deux (2) forges équipés de pompe solaire avec mini d'adduction d’eau Single Stage - One 2021-09- IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 121,264.00 99,770.07 Signé 2019-10-30 2020-04-23 2019-12-02 2020-08-27 sommaire de 3 bornes Envelope 07 fontaines à Tinaghalhaj et à M’Back Semna dans le Cercle d’Araoune reion Taoudenit CW-MOP-05 / Tv. réalisat. d’un jardin d’arbres fruitiers à Single Stage - One 2019-11- IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 35,873.00 40,955.29 Signé 2019-10-20 2020-06-09 2019-11-22 2020-08-18 Kanibonzo dans la région de Envelope 25 Mopti CW-GAO-12 / Travaux de réalisation d'un forage équipé de PMH à Tinassamede, d’un Single Stage - One 2021-01- puits d'un à grand diamètre à IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 55,173.00 58,753.16 Signé 2020-08-22 2021-01-07 2020-10-11 2021-02-18 Envelope 09 Inamakka et d'un mini forage californien équipé motopompe dans la région de Gao CW-TOM-06 / Tv construction d’un mur de Single Stage - One 2020-03- clôture du second cycle « IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 35,432.00 20,193.87 Signé 2019-12-04 2020-03-03 2020-01-23 2020-04-29 Envelope 08 yehia alkaya de Tombouctou » région de Tombouctou CW-MEN-02 / Travaux de construction et équipement de 3 salles de classes Single Stage - One 2020-01- IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 50,695.00 53,513.15 Signé 2019-11-20 2020-04-06 2020-01-09 2020-06-04 équipées à Echaghane Envelope 13 commune de Tidèrmène dans la région de Ménaka CW-TOM-08 / Tv réalisation et équipement 1 forage en pompe solaire à Tabaye- Single Stage - One 2020-02- IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 60,734.00 42,662.98 Signé 2019-11-19 2020-06-15 2020-01-08 2020-10-01 barite commune de Tilemsi Envelope 22 cercle Goundam région de Tombouctou CW-TOM-03 / Tv. de réhabilitation d'une AES par soufflage Tindaydaye GOSSI et Single Stage - One 2020-01- IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 45,348.00 53,810.60 Signé 2019-11-02 2020-04-30 2019-12-05 2020-08-24 Tv. réalisation AES à Envelope 19 Tintahaten Gossi dans la région de Tombouctou CW-MOP-01 / Tv. d'Aménag. périmètre maraîcher avec mini adduction d’eau pour Single Stage - One 2019-12- IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 51,080.00 53,745.67 Signé 2019-10-20 2021-03-05 2019-11-22 2020-04-03 l'association djiguiya de Envelope 22 Saoula à Djenne région de Mopti CW-TOM-10 / Travaux de réalisation et équipement d’un forage moderne en Single Stage - One 2020-07- château d’eau et panneaux IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 42,362.00 38,587.68 Signé 2020-03-11 2020-04-14 2020-04-30 2020-07-17 Envelope 29 solaires à Djiri berra goungou cercle de Gourma-Rharous dans la région de Tombouctou CW-GAO-09 / Travaux de réalisation d'éclairage public à Single Stage - One 2020-01- IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 67,839.00 68,430.32 Signé 2019-11-05 2020-03-19 2019-12-25 2020-05-20 Borno dans le cercle de Envelope 24 Bourem region de gao CW-MEN-01 / Tv. Const.salle de formation et de bureaux pour les femmes d'Anderaboukane Single Stage - One 2020-02- IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 51,724.00 51,133.22 Signé 2019-11-20 2020-04-30 2020-01-09 2020-06-02 Tv const.maison et centre de Envelope 08 formation les jeunes d'Anderaboukane dans la région de Ménaka CW-GAO-15 / Travaux de réalisation deux forages Single Stage - One En cours 2021-01- équipés de pompe solaire à IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 79,151.00 0.00 2020-08-26 2021-05-05 2020-10-15 Envelope d'exécution 13 Taffassilite et à Injaguel dans la région de Gao CW-MEN-04 / Travaux de réalisation de deux forages dont un de 180mn à Agadèye Single Stage - One 2020-12- et à Inaghade et d’un château IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 87,063.00 100,729.15 Signé 2020-07-29 2021-02-25 2020-09-17 2021-05-03 Envelope 16 d’eau sur puits existant à Tamtak dans la région de Ménaka CW-MOP-03 / TTravaux de Réalisation d’un forage avec Single Stage - One 2020-01- adduction d’eau sommaire de IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 67,845.00 70,334.21 Signé 2019-10-20 2020-04-10 2019-11-22 2020-06-30 Envelope 06 Kende à Bondy région de Mopti CW-TOM-09 / Travaux de réhabilitation d’un CSCOM, d’une école et d’un puit à Single Stage - One 2020-03- IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 86,170.00 90,190.92 Signé 2019-12-04 2020-03-19 2020-01-23 2020-05-13 Teberent, Cercle de Gourma- Envelope 08 Rharous dans la région de Tombouctou CW-TOM-05 / Tv de réalisation et équipement d’un forage en pompe solaire Single Stage - One 2020-01- à Tin Afferene à Gargando et IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 103,443.00 96,671.88 Signé 2019-11-02 2020-04-14 2019-12-05 2020-05-21 Envelope 19 Tv de réalisation d’une AES à Gargando dans la région de Tombouctou Page 3 CW-TAO-01 / Tv. F/P Single Stage - One 2020-01- Poteaux élect. Compt. Bouge IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 69,551.00 61,294.42 Signé 2019-10-30 2020-04-23 2019-12-02 2020-07-27 Envelope 01 Beha Taoudénit CW-GAO-06 / Travaux de réalisation et équipement d'un Single Stage - One 2020-01- forage équipé d’une pompe IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 39,655.00 42,664.95 Signé 2019-11-05 2020-04-14 2019-12-08 2020-07-01 Envelope 22 solaire à Intilit commune de Tilemsi dans la région de Gao CW-KID-04 / Tv. réalisation et équip. 2 forages avec système solaire à Guljiat Single Stage - One 2020-03- IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 90,258.00 90,327.27 Signé 2019-11-27 2020-04-27 2020-01-16 2020-07-03 Tinessako et Tagoraste Envelope 01 Achibogho dans la région de Kidal CW-GAO-02 / Tv const. 03 magasins de stockage de 4 m X 4 m chacun à Bara, Tabangaw et Tanal dans la Commune de BARA cercle Single Stage - One 2020-01- IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 41,379.00 21,239.00 Signé 2019-11-02 2020-03-30 2019-12-05 2020-05-21 Ansongo , Tv const. d'un Envelope 04 magasin de stockage de 4 m X 4 m à Talataye dans la Commune de Talataye cercle Ansongo région de Gao CW-KID-13 / Travaux de réalisation d'un puit avec Single Stage - One 2020-12- IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 26,002.00 27,568.46 Signé 2020-07-18 2020-10-15 2020-09-06 2020-12-24 équipement solaire à Tassick Envelope 05 dans la région de Kidal CW-TOM-16 / Travaux de construction d'un parc de Single Stage - One 2020-12- IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 20,700.00 22,211.76 Signé 2020-08-08 2020-10-09 2020-09-27 2020-12-21 vaccination à Habougara dans Envelope 11 la région de Tombouctou CW-GAO-16 / Travaux de réalisation et équipement d'un Single Stage - One 2021-02- forage sur le site de Zanzan à IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 15,716.00 53,861.22 Signé 2020-11-07 2021-02-25 2020-12-12 2021-04-09 Envelope 10 Bamba, cercle de Bourem dans la région de Gao CW-KID-16 / Travaux de réalisation de trois (3) forages Single Stage - One 2021-02- de système solaire à Etambar, IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 154,201.00 156,709.85 Signé 2020-11-14 2021-02-22 2020-12-19 2021-04-26 Envelope 17 Inktikwa, Tamtack dans la commune urbaine de Kidal CW-GAO-18 / Construction de deux (2) forages équipés au profit des populations Single Stage - One 2021-02- déplacées de retour des IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 90,576.00 97,837.06 Signé 2020-11-07 2021-02-05 2020-12-12 2021-04-08 Envelope 10 quartiers de Gadèye et Farandjirèye dans la commune urbaine de Gao CW-GAO-21 / Travaux de réhabilitation du PIV de TONDOTHIRO (canal et OSC) Single Stage - One 2021-03- IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 32,266.00 27,377.19 Signé 2020-11-14 2021-02-23 2020-12-19 2021-04-15 dans la commune de Envelope 19 Gounzourèye dans le cercle de Gao, Région de Gao CW-GAO-22 / Travaux de réhabilitation du Centre de santé communautaire des villages de Zindiga-Berrah Single Stage - One 2021-03- IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 190,986.00 180,939.59 Signé 2020-11-14 2021-03-08 2020-12-19 2021-04-08 dans la commune Sony Ali Ber Envelope 19 et de réalisation d'une AES à Azalala Gindo - cercle de Gao, Région de Gao. CW-TOM-17 / Réalisation de deux forages de système de pompage avec mini réseau d’adduction d’eau pour le Single Stage - One 2021-03- IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 141,037.00 146,528.82 Signé 2020-12-05 2021-03-08 2021-01-09 2021-04-16 village de Sondage et Envelope 10 Tejakanite, commune de Léré, cercle de Niafunké dans la région de Tombouctou. CW-TOM-19 / Travaux de réhabilitation d’une école et de construction d’un poste de Single Stage - One 2021-04- santé à Nya Fraction Kel IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 56,265.00 65,068.03 Signé 2020-12-05 2019-10-14 2021-01-09 2021-04-20 Envelope 09 Tinakawwatt dans la commune rurale de Léré dans la région de Tombouctou. CW-GAO-23 / Construction de trois (3) salles de classe bureau, magasin et 2 blocs de Single Stage - One En cours 2021-04- latrine au profit des IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 72,121.00 0.00 2020-12-02 2021-06-14 2021-01-06 Envelope d'exécution 06 populations déplacées dans la Commune de Inchawadji Région de Gao CW-KID-18 / Travaux de réalisation d'une mini adduction d'eau à Teknewene Single Stage - One 2021-07- IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 90,000.00 90,798.97 Signé 2020-11-07 2021-03-30 2021-01-02 2021-06-01 dans la commune rurale Envelope 01 d'Anafis dans la région de Kidal CW-TAO-38 / Travaux de réalisation de deux (02) foragés équipés de systèmes solaires à Boukarcha Single Stage - One 2021-04- IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 127,273.00 127,753.04 Signé 2020-11-10 2021-02-09 2021-01-05 2021-03-31 (commune de Liraka) et Envelope 05 Alfakrouna (commune de Alfakrouna) dans la région de Taoudéni Page 4 CW-TAO-39 / Travaux d'electrification du CSCOM d'Arouane, d'éclairage de la rue principale du village Single Stage - One 2021-07- d'Arouane et Réalisation d'une IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 69,090.00 70,289.74 Signé 2020-11-18 2021-02-25 2021-01-13 2021-03-31 Envelope 12 AES en forage équipé à Hassi Ouldad Sleymane (cercle de Arouane) dans la région de Taoudénit CW-TAO-23 / Travaux de réalisation de dix (10) adductions d'eau sommaire respectivement dans les Single Stage - One 2021-09- IDA / D1680 Community Rehabilitation A posteriori Appel d'offres Open - National 447,212.00 220,949.28 Signé 2020-11-20 2021-02-01 2020-11-25 2021-06-02 2021-01-06 2021-03-19 2021-02-05 2021-03-23 2021-03-12 2021-05-20 cercles de Al Ourch, Foum Envelope 08 Elba, Achourate, Bouge Béha et Taoudénit dans la région de Taoudénit CW-MOP-02 / Travaux d'Aménag. de la marre de Single Stage - One 2019-12- IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 78,144.00 80,065.36 Signé 2019-10-20 2020-03-09 2019-11-22 2020-04-17 Bergue Kounari à Manaco Envelope 22 région de Mopti CW-KID-40 / Travaux de réalisation de deux forages équipés de système solaire à Single Stage - One 2021-07- IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 138,182.00 139,228.38 Signé 2020-11-11 2021-02-22 2021-01-06 2021-04-06 TAZARGHAFT et INFEFELE Envelope 05 dans la commune de Kidal, région de Kidal CW-MEN-45 / Aménagement de la marre de la ville de Single Stage - One 2021-07- MENAKA contre les IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 81,818.00 89,189.22 Signé 2020-11-21 2021-04-16 2021-01-16 2021-06-01 Envelope 15 inondations - Région de Ménaka CW-MEN-37 / Travaux de réalisation de deux (02) forages équipés de système Single Stage - One 2021-07- IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 127,273.00 131,526.44 Signé 2020-11-10 2021-02-25 2021-01-05 2021-05-10 solaire à Charbaley et Ibaram Envelope 04 Dabakar dans la commune de Ménaka - Région de Ménaka CW-GAO-44 / Travaux de réalisation d'éclairage public à Single Stage - One 2021-07- IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 71,455.00 69,932.20 Signé 2020-11-25 2021-02-23 2021-01-20 2021-04-13 Bara - commune rurale de Envelope 19 Bara - Région de Gao CW-TOM-48 / Travaux de construction de magasin de stockage à Kadago Commune Single Stage - One 2021-03- IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 14,532.00 14,328.34 Signé 2020-11-07 2021-02-22 2021-01-02 2021-03-31 rurale de de Ouinerden - Envelope 03 cercle de Gourma Rharous - Région de Tombouctou CW-TAO-37 / Travaux de réalisation et équipement d'une unité pour la valorisation de la gomme Single Stage - One 2021-04- IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 51,455.00 50,759.96 Signé 2020-11-07 2021-02-08 2021-01-02 2021-03-31 arabique au profit de Envelope 02 l'association des femmes de Nibkit - cercle de Al Ourche dans la région de Taoudénit CW-GAO-19 / Travaux de réalisation d'un (1) forage Single Stage - One 2021-02- équipé à Taziguizit Commune IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 49,140.00 48,959.02 Signé 2020-11-07 2021-02-24 2020-12-12 2021-03-30 Envelope 10 de Talataye, cercle d'Ansongo dans la région de Gao. CW-KID-17 / Travaux de réalisation de deux (2) forages équipés d'un système solaire Single Stage - One 2021-03- sur le site de Weilalam dans la IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 96,019.00 95,707.24 Signé 2020-11-14 2021-02-22 2020-12-19 2021-03-10 Envelope 19 commune d'Aguelhoc, cercle de Tessalit dans la région de Kidal CW-TOM-20 / Travaux de réalisation de deux forages équipés au profit des réfugiés installés à Gossi et là 'école Single Stage - One 2021-03- IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 88,461.00 88,467.80 Signé 2020-12-05 2021-02-09 2021-01-19 2021-03-25 fondamentale publique de Envelope 20 Gourzouguèye, cercle de Gourma Rharous dans la région de Tombouctou CW-TOM-49 / Travaux de réalisation de deux forages Request for équipés de pompe solaire à Quotations - Small Single Stage - One En cours 2021-09- Tadarasse /Acharane et IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited Works 90,637.00 0.00 2021-05-29 2021-06-16 2021-07-17 Envelope d'exécution 15 Louteid, commune rurale (Emergency) SPD - d'Essakane dans la région de Competitive Tombouctou CW-GAO-31 / Réalisation Request for d'un périmètre maraicher à Quotations - Small Single Stage - One 2021-03- Tin Joulgame dans la IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited Works 89,839.00 91,972.44 Signé 2020-10-11 2021-02-24 2020-12-06 2021-04-19 Envelope 06 commune rurale de Tilemsi - (Emergency) SPD - Région de Gao Competitive CW-GAO-45 / Travaux de Request for réalisation d'un forage équipé Quotations - Small Single Stage - One En cours 2021-08- à Inkourou dans la commune IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited Works 39,478.00 0.00 2021-05-29 2021-07-10 Envelope d'exécution 24 rurale de Anchawadji dans la (Emergency) SPD - région de Gao Competitive CW-TOM-41 / Construction d'un centre de formation et Request for d'encadrement des jeunes à Quotations - Small Zendjina Koyra et de la clôture Single Stage - One En cours 2021-09- IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited Works 56,364.00 0.00 2021-05-31 2021-06-14 2021-07-26 du second cycle Abdoulaye Envelope d'exécution 24 (Emergency) SPD - Soumaguel de Gourma Competitive Rharous - Région de Tombouctou Page 5 CW-KID-08 / Travaux de réalisation de deux (02) Single Stage - One 2020-11- forages équipés à Djalguit et IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 81,896.00 0.00 Annulé 2020-07-20 2020-08-25 Envelope 23 Tagorast dans la région de Kidal CW-TOM-18 / Réalisation d’un forage équipé au 2021-03- bénéfice de la fraction Dag IDA / D1680 Community Rehabilitation A posteriori Demande de prix 57,028.00 0.00 Annulé 2020-12-05 2021-01-09 10 Baya sis à Goundam dans la région de Tombouctou. CW-GAO-17 / Construction de 4 Hangars, 02 blocs de 3 latrines et une adduction d’eau sommaire (AES) au Single Stage - One 2021-02- IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 92,491.00 0.00 Annulé 2020-11-07 2020-12-12 marché à bétail de Forgho, Envelope 10 Commune Rurale de SONI ALI BER, cercle de Gao, Région de Gao CW-TOM-32 / Travaux de réhabilitation d'un périmètre rizicole de 15 HA au profit de Single Stage - One 2021-07- IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 40,964.00 0.00 Annulé 2020-11-21 2021-01-16 l'association paysanne Envelope 15 "CONDEYE" de Toya dans la Région de Tombouctou CW-TOM-23 / Travaux de réalisation d'un forage équipé de système solaire pour la coopérative des producteurs Single Stage - One 2021-07- IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 27,849.00 0.00 Annulé 2020-11-14 2021-01-09 de gomme arabique sur 10H à Envelope 08 Rharous/Sidi Oumar Adiawiakoye - Région de Tombouctou CW-GAO-35 / Travaux de réalisation d'un forage équipé de système solaire avec château d'eau à Timbargotane, Commune Single Stage - One 2021-07- IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 88,175.00 0.00 Annulé 2020-11-15 2021-01-10 d'Anchawadj, et d'une Envelope 09 d'adduction d'eau potable par le pompage solaire à Tilemsi , Commune rurale de Telemsi, cercle de Gao,région de GaO CW-GAO-20 / Travaux de réalisation d'un forage équipé de système solaire avec Single Stage - One 2021-02- IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 46,478.00 0.00 Annulé 2020-11-07 2020-12-22 château d'eau à Envelope 20 Timbargotane, Commune d'Anchawadj, dans la région de Gao CW-KID-15 / Travaux de construction de la digue de Single Stage - One 2020-12- IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 86,207.00 0.00 Annulé 2020-07-18 2020-09-06 protection d'Aguelhock dans Envelope 05 la région de Kidal CW-MOP-06 / Travaux de réalisation de trois périmètres maraichers à simérou, à Mopti Single Stage - One 2020-11- pour les femmes et à Dia pour IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 158,814.00 0.00 Annulé 2020-07-06 2020-08-25 Envelope 23 l’association des femmes de Dia BENKOLA dans la région de Mopti GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GO-REF-7 / Achat de matériels informatiques pour Project Management Support Single Stage - One En attente l’UEP et de matériels de IDA / D1680 to Project Implementation A posteriori Demande de prix Limited 47,681.00 0.00 2018-03-09 2018-05-04 2018-05-19 Envelope d'exécution communication et de Unit sensibilisation GO-REF-4 / Acquisition de 2 Project Management Support Single Stage - One En attente Véhicules station wagon pour IDA / D1680 to Project Implementation A posteriori Demande de prix Limited 144,928.00 0.00 2018-04-09 2018-06-04 2018-07-04 Envelope d'exécution les missions de l'UEP Unit GO-REF-5 / Acquisition de Project Management Support Single Stage - One En attente groupe électrogène de 50 KVA IDA / D1680 to Project Implementation A posteriori Demande de prix Limited 24,155.00 0.00 2018-03-25 2018-05-20 2018-06-04 Envelope d'exécution pour l’UEP Unit GO-REF-6 / Aquisition de 3 Project Management Support Single Stage - One En attente motos pour chauffeurs et IDA / D1680 to Project Implementation A posteriori Demande de prix Limited 2,899.00 0.00 2018-05-29 2018-07-24 2018-08-08 Envelope d'exécution coursier Unit GO-TOM-01 / Acq Grpes Moto pompes à Gourzouguèye et Tourchawane; à 10 groupement maraichers Single Stage - One IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 129,656.00 113,998.90 Résilié 2019-12-18 2020-02-10 2020-02-06 2020-04-10 2020-03-07 féminins Banikane Niafunké; Envelope pour les ass.« Aniya de thiaye et diékabara de sandy » de Koumayra ; à 10 groupements féminins de Ngorkou région de Tombouctou GO-TOM-02 / Acquisition de 3 moulins et de 7 décortiqueuses aux Single Stage - One IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 25,483.00 21,592.32 Signé 2019-11-02 2020-02-10 2019-12-05 2020-03-24 2020-01-04 associations de femmes de Envelope Diré dans la région de Tombouctou Page 6 GO-TOM-06 / Acquisition d'animaux pour la reconstitution de cheptel au profit des jeunes à risques de Single Stage - One 4 fractions d’éleveurs à Lafia IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 42,414.00 39,880.09 Signé 2019-11-02 2020-07-30 2019-12-05 2020-10-12 2019-12-08 Envelope et au profit des communautés d’éleveurs de Gossi cercle de Gourma-Rharous dans la région de Tombouctou GO-MEN-04 / Acquisition d’animaux pour la reconstitution de cheptel à Single Stage - One Tiderméne au profit de 107 IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 34,229.00 20,606.59 Signé 2020-07-25 2020-12-07 2020-09-13 2021-04-15 2020-10-13 Envelope familles et des communautés de Tinabaw dans la région de Ménaka GO-REF-2 / Acquisition équipement du Système Reinsertion Support to Single Stage - One En attente IDA / D1680 A posteriori Demande de prix Limited 64,412.00 0.00 2018-04-07 2018-05-17 2018-07-01 d’Information et de Gestion Demobilized Ex-combatants Envelope d'exécution (SIG) GO-MOP-04 / Acq. Mob. Scolaires des écoles Single Stage - One IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 12,036.00 12,819.83 Signé 2019-10-20 2020-06-04 2019-11-22 2020-07-08 2019-12-22 Commune Soubala cercle de Envelope bankass région de Mopti GO-MEN-03 / Acq Equip CSCOM de Emiss-Emiss Single Stage - One IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 34,479.00 33,093.19 Signé 2019-10-27 2020-06-03 2019-11-29 2020-08-20 2019-12-29 commune de Inékar région de Envelope Ménaka GO-GAO-01 / Acquisition d’animaux au bénéfice de Single Stage - One En cours trois groupements d’éleveurs IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 11,379.00 13,262.98 2020-08-26 2021-01-04 2020-10-15 2020-11-14 Envelope d'exécution de Tinahamma dans la région de Gao GO-MEN-01 / Acq.petits ruminants reconst.cheptel , 540 personnes victimes à Izgarate ; 40 personnes victimes à Tabankort ; 30 Single Stage - One IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 86,007.00 88,326.20 Signé 2019-10-12 2020-02-12 2019-11-14 2020-04-13 2019-12-14 personnes victimes à Envelope Infoukaretane ; 317 personnes victimes à Wassaifi et 107 familles à Tidermène dans la région de Menaka GO-MOP-01 / Acq. animaux Comm.villag Diankabou Kombomé; comm.villag Gathilomou; femmes Diondiori ; coop Teninkou; Single Stage - One coop multif Hairé Boni ; grpmt IDA / D1680 Community Rehabilitation A posteriori Appel d'offres Open - National 296,931.00 318,540.32 Signé 2019-10-31 2020-06-10 2019-11-05 2021-06-06 2019-12-05 2020-07-30 2019-12-20 2020-08-10 2020-01-10 2020-12-01 2020-02-24 Envelope village mondoro ; éleveurs Hairé Boni ; ass. « yankouna haw ga goy Hombori; jeunes éleveurs de fatoma région Mopti GO-REF-1 / Acquisition des matériels, équipments et Reinsertion Support to Single Stage - One moyens de formation des Ex- IDA / D1680 A posteriori Appel d'offres Open - National 240,000.00 187,657.46 Signé 2018-04-15 2020-07-06 2018-04-20 2021-06-06 2018-05-20 2020-08-24 2018-05-27 2020-09-04 2018-06-24 2021-01-06 2018-07-24 Demobilized Ex-combatants Envelope Combattants dans les 6 régions GO-TAO-02 / Acquisition de petits ruminants pour les Single Stage - One femmes de Taoudéni et les IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 82,844.00 84,913.59 Signé 2020-08-01 2020-10-09 2020-09-20 2020-12-21 2020-10-20 Envelope jeunes à Al Ourch dans la région de Taoudénit GO-REF-8 / Equipement de Project Management Support Single Stage - One En attente la salle de conférence de l’UEP IDA / D1680 to Project Implementation A posteriori Demande de prix Limited 8,293.00 0.00 2018-03-25 2018-05-20 2018-06-09 Envelope d'exécution et petits equipements Unit ML-PREC-175183-GO-DIR / Project Management Support Passation de Equipement de la salle de En attente IDA / D1680 to Project Implementation A posteriori marché de gré à Direct 20,000.00 0.00 2020-05-28 2020-06-02 2020-06-17 2020-06-24 conférence de l'UEP PREC en d'exécution Unit gré solution de vidéoconférence GO-MOP-06 / Acquisition d’animaux pour la reconstitution du cheptel au profit de Ass de femmes et jeunes des villages de Single Stage - One Darawal,Wamy et Koubel; Ass IDA / D1680 Community Rehabilitation A posteriori Appel d'offres Open - National 192,636.00 196,010.10 Signé 2020-10-05 2021-06-02 2020-10-10 2021-06-04 2020-11-21 2021-01-22 2020-12-21 2021-01-27 2021-01-25 2021-02-19 2021-07-24 Envelope des femmes et jeunes du village de Boni ; groupement de femmes des villages de Douna et de Niagassadiou Cercle Douenza GO-MOP-08 / Acquisition d’animaux pour la reconstitution de cheptel au profit des groupements Single Stage - One /associations des femmes et IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 106,355.00 104,070.65 Signé 2020-11-07 2020-11-02 2021-01-01 2020-12-24 2021-03-02 Envelope jeunes des villages d’Aldouma, Tonou et de Toungourou, cercle de Koro dans la région de Mopti GO-GAO-02 / Acquisition d'une ambulance médicalisée Single Stage - One En cours de type 4x4 pour l'hopital IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 60,041.00 0.00 2020-11-07 2020-12-12 2021-02-10 Envelope d'exécution Hangadoumba Moulaye TOURE de Gao GO-MEN-25 / équipements et Réinsertion de 20 Single Stage - One IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 50,591.00 50,734.57 Signé 2020-11-07 2021-05-05 2021-01-02 2021-06-07 2021-07-01 associations de femmes en Envelope coupe couture à Alfakrou Page 7 GO-GAO-44 / Acquisition d'équipement médical pour le Single Stage - One IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 89,091.00 89,163.08 Signé 2020-11-22 2021-02-22 2021-01-17 2021-04-09 2021-07-16 Centre de référence du cercle Envelope de Gao GO-MEN-05 / Acquisition d’équipements pour les unités de savonnerie et de tannerie, des moulins au profit des Single Stage - One IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 72,115.00 74,032.66 Signé 2020-09-06 2021-04-06 2020-10-18 2021-05-28 2020-12-17 groupements de femmes des Envelope communes de Ménaka, Andéranboukane et Intadeyné dans la région de Ménaka GO-GA0-28 / Equipement Single Stage - One En cours d'une unité laitière à Ansongo IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 19,135.00 0.00 2021-05-31 2021-06-28 2021-07-12 2021-08-11 Envelope d'exécution dans la région de Gao GO-MEN-44 / Acquisition d'animaux pour la reconstitution du cheptel respectivement pour 40 familles dans le village de Single Stage - One IDA / D1680 Community Rehabilitation A posteriori Appel d'offres Open - National 220,909.00 0.00 Annulé 2020-10-12 2020-10-27 2020-11-26 2020-12-16 2021-01-06 2021-03-07 Inwelane, 20 familles du Envelope village d'Inticha, 20 familles du villages de Tabankorte,, 20 familles du village du village de Imisdounane - Ménaka GO-GAO-22 / Fourniture de : matériels de maraichage et agricole aux femmes de l'Ass du Sahel - Bourem; matériel de séchage et Single Stage - One commercialisation de poisson IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 85,285.00 0.00 Annulé 2020-11-17 2021-01-12 2021-07-11 Envelope à la coopérative des vendeuses de poissons de Gao; de matériels agro sylvo pastoral pour jeunes de bamba GO-MOP-05 / Acquisition d’animaux pour la société coopérative à Guidjo Sare, Single Stage - One l'association alliance à IDA / D1680 Community Rehabilitation A posteriori Appel d'offres Open - National 151,456.00 0.00 Annulé 2020-05-31 2020-06-07 2020-07-19 2020-08-18 2020-09-22 2021-03-21 Envelope Teninkou et l’association Yiriwere mayo Togoro à Sossobe de la région de Mopti Project Management Support GO-REF-10 / Fourniture de Single Stage - One IDA / D1680 to Project Implementation A posteriori Demande de prix Limited 11,667.00 0.00 Annulé 2018-12-12 2018-12-29 2019-01-13 Comsommables de Bureau Envelope Unit GO-TAO-01 / Acq 20 Single Stage - One décortiqueuses Almatla région IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 44,414.00 0.00 Annulé 2019-10-30 2019-12-02 2020-05-30 Envelope de Taoudénit GO-REF-11 / Confection Project Management Support Agenda, Calendrier, cartes de Single Stage - One IDA / D1680 to Project Implementation A posteriori Demande de prix Limited 10,000.00 0.00 Annulé 2018-12-14 2019-01-02 2019-01-17 visites et gadgets de Envelope Unit communication ML-PREC-51762-GO-RFB / Acquisition, transport, Stockage, distribution de Kits Reinsertion Support to Single Stage - One de demarrage pour la IDA / D1680 A posteriori Appel d'offres Open - International 1,920,000.00 0.00 Annulé 2018-06-15 2018-06-20 2018-08-01 2018-08-11 2018-09-08 2018-12-07 Demobilized Ex-combatants Envelope réinsertion des Ex combattants dans les 6 régions NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GO-REF-9 / Acquisition et Project Management Support installation d'un logiciel de Single Stage - One En attente IDA / D1680 to Project Implementation A posteriori Demande de prix Open - National 59,581.00 0.00 2018-04-14 2018-05-26 2021-05-25 comptabilité pour le projet et Envelope d'exécution Unit formation des utilisateurs NC-TAO-01 / Formation en Single Stage - One chantier école de 120 jeunes IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 48,906.00 95,816.28 Signé 2020-11-22 2021-02-16 2021-01-17 2021-04-15 2021-05-17 Envelope dans la région de Taoudénit CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CS-REF-2 / P.E pour l'Encadrement, l'Appui conseil, Sélection fondée l'Orientation et dispense de Reinsertion Support to IDA / D1680 A priori sur la qualité et le Open - International 1,000,000.00 0.00 Annulé 2018-02-06 2018-02-11 2018-03-12 2018-04-21 2018-04-28 2018-05-15 2018-06-19 2019-06-19 Kit de formation aux ex- Demobilized Ex-combatants coût combattants démobilisés dans la région de Mopti. CS-REF-3 / P.E pour l'Encadrement, l'Appui conseil, Sélection fondée l'Orientation et dispense de Reinsertion Support to IDA / D1680 A priori sur la qualité et le Open - International 1,000,000.00 0.00 Annulé 2018-02-06 2018-02-11 2018-03-12 2018-04-21 2018-04-28 2018-05-15 2018-06-19 2019-06-19 Kit de formation aux ex- Demobilized Ex-combatants coût combattants démobilisés dans la région de Gao CS-REF-5 / P.E pour l'Encadrement, l'Appui conseil, Sélection fondée l'Orientation et dispense de Reinsertion Support to IDA / D1680 A priori sur la qualité et le Open - International 1,000,000.00 0.00 Annulé 2018-02-06 2018-02-11 2018-03-12 2018-04-21 2018-04-28 2018-05-15 2018-06-19 2019-06-19 Kit de formation aux ex- Demobilized Ex-combatants coût combattants démobilisés dans la région de Kidal. Page 8 CS-REF-7 / P.E pour l'Encadrement, l'Appui conseil, Sélection fondée l'Orientation et dispense de Reinsertion Support to IDA / D1680 A priori sur la qualité et le Open - International 1,000,000.00 0.00 Annulé 2018-02-06 2018-02-11 2018-03-12 2018-04-21 2018-04-28 2018-05-15 2018-06-19 2019-06-19 Kit de formation aux ex- Demobilized Ex-combatants coût combattants démobilisés dans la région de Taoudenit. Sélection fondée CS-REF-11 / Contrat de Reinsertion Support to sur les En attente l'évaluation annuelle IDA / D1680 A posteriori Open - National 60,000.00 0.00 2018-06-19 2018-07-10 2018-08-23 2018-09-22 2018-10-27 2019-04-25 Demobilized Ex-combatants qualifications des d'exécution Indépendante (Audit externe) consultants CS-REF-8 / Recrutement d'un consultant pour l'appui Sélection fondée psycho social en faveur des ex Reinsertion Support to sur les En attente combattants démobilisés IDA / D1680 A posteriori Open - International 45,480.00 0.00 2018-04-22 2018-05-06 2018-05-27 2018-06-03 2018-07-04 2019-07-04 Demobilized Ex-combatants qualifications des d'exécution souffrant de maladies psycho consultants sociales et de troubles mentaux CS-REF-25 / P.E N°02 pour l'Encadrement, l'Appui conseil, Sélection fondée l'Orientation et dispense de Reinsertion Support to sur les En attente IDA / D1680 A posteriori Open - National 120,000.00 0.00 2019-10-15 2019-10-30 2019-11-24 2019-12-09 2019-12-30 2020-12-29 Kit de formation aux ex- Demobilized Ex-combatants qualifications des d'exécution combattants démobilisés dans consultants la région de Taoudenit. CS-REF-22 / P.E N°02 pour l'Encadrement, l'Appui conseil, Sélection fondée l'Orientation et dispense de Reinsertion Support to sur les En cours IDA / D1680 A posteriori Open - National 120,000.00 0.00 2019-10-15 2019-02-27 2019-10-30 2019-11-24 2019-12-09 2019-12-30 2020-12-29 Kit de formation aux ex- Demobilized Ex-combatants qualifications des d'exécution combattants démobilisés dans consultants la région de Tombouctou. CS-REF-23 / P.E N°02 pour l'Encadrement, l'Appui conseil, Sélection fondée l'Orientation et dispense de Reinsertion Support to sur les En cours IDA / D1680 A posteriori Open - National 120,000.00 0.00 2019-10-15 2019-02-27 2019-10-30 2019-11-24 2019-12-09 2019-12-30 2020-12-29 Kit de formation aux ex- Demobilized Ex-combatants qualifications des d'exécution combattants démobilisés dans consultants la région de Kidal. CS-REF-18 / P.E pour l'Encadrement, l'Appui conseil, Sélection fondée l'Orientation et dispense de Reinsertion Support to sur les En cours IDA / D1680 A posteriori Open - National 120,000.00 0.00 2019-10-06 2019-02-27 2019-10-21 2019-11-15 2019-11-30 2019-12-21 2020-12-20 Kit de formation aux ex- Demobilized Ex-combatants qualifications des d'exécution combattants démobilisés dans consultants la région de Taoudenit. CS-REF-17 / P.E N°01 pour l'Encadrement, l'Appui conseil, Sélection fondée l'Orientation et dispense de Reinsertion Support to sur les IDA / D1680 A posteriori Open - National 120,000.00 0.00 En cours d'examen 2019-10-16 2019-02-27 2019-10-31 2019-11-25 2019-12-10 2019-12-31 2020-12-30 Kit de formation aux ex- Demobilized Ex-combatants qualifications des combattants démobilisés dans consultants la région de Kidal. CS-REF-24 / P.E N°02 pour l'Encadrement, l'Appui conseil, Sélection fondée l'Orientation et dispense de Reinsertion Support to sur les IDA / D1680 A posteriori Open - National 120,000.00 0.00 En cours d'examen 2019-10-15 2019-02-27 2019-10-30 2019-11-24 2019-12-09 2019-12-30 2020-12-29 Kit de formation aux ex- Demobilized Ex-combatants qualifications des combattants démobilisés dans consultants la région de Menaka. CS-REF-20 / P.E N°02 pour l'Encadrement, l'Appui conseil, Sélection fondée l'Orientation et dispense de Reinsertion Support to sur les En cours IDA / D1680 A posteriori Open - National 120,000.00 0.00 2019-10-15 2019-02-27 2019-10-30 2019-11-24 2019-12-09 2019-12-30 2020-12-29 Kit de formation aux ex- Demobilized Ex-combatants qualifications des d'exécution combattants démobilisés dans consultants la région de Mopti. CS-REF-21 / P.E N°02 pour l'Encadrement, l'Appui conseil, Sélection fondée l'Orientation et dispense de Reinsertion Support to sur les En cours IDA / D1680 A posteriori Open - National 120,000.00 0.00 2019-10-16 2019-02-27 2019-10-31 2019-11-25 2019-12-10 2019-12-31 2020-12-30 Kit de formation aux ex- Demobilized Ex-combatants qualifications des d'exécution combattants démobilisés dans consultants la région de Gao. CS-REF-14 / P.E N°01 pour l'Encadrement, l'Appui conseil, Sélection fondée l'Orientation et dispense de Reinsertion Support to sur les IDA / D1680 A posteriori Open - National 120,000.00 0.00 En cours d'examen 2019-10-15 2019-02-27 2019-10-30 2019-11-24 2019-12-09 2019-12-30 2020-12-29 Kit de formation aux ex- Demobilized Ex-combatants qualifications des combattants démobilisés dans consultants la région de Mopti. CS-REF-15 / PE N°01 pour l'Encadrement l'Appui conseil Sélection fondée l'Orientation et dispense de Reinsertion Support to sur les En cours IDA / D1680 A posteriori Open - National 120,000.00 0.00 2019-10-15 2019-02-27 2019-10-30 2019-11-24 2019-12-09 2019-12-30 2020-12-29 Kit de formation aux ex- Demobilized Ex-combatants qualifications des d'exécution combattants démobilisés dans consultants la région de Gao CS-REF-31 / Recrutement d'un Consultant dans la Sélection fondée région de Mopti pour sur les IDA / D1680 Community Rehabilitation A posteriori Open - National 45,208.00 38,337.14 Signé 2019-10-14 2019-10-16 2019-10-29 2021-05-10 2019-11-20 2020-02-20 2019-12-05 2020-03-12 2019-12-26 2021-05-06 2020-06-23 Etudes/Suivi et Contrôle dans qualifications des le cadre de l'execution des consultants sous projets de la composante 3 CS-REF-32 / Recrutement d'un Consultant dans la Sélection fondée région de Gao pour sur les IDA / D1680 Community Rehabilitation A posteriori Open - National 30,731.00 0.00 En cours d'examen 2019-10-04 2019-10-16 2019-10-19 2019-11-13 2019-11-28 2019-12-19 2020-06-16 Etudes/Suivi et Contrôle dans qualifications des le cadre de l'execution des consultants sous projets de la composante 3 CS-REF-33 / Recrutement d'un Consultant dans la Sélection fondée région de Kidal pour sur les IDA / D1680 Community Rehabilitation A posteriori Open - National 27,166.00 0.00 En cours d'examen 2019-10-04 2019-10-21 2019-10-19 2019-11-13 2019-11-28 2019-12-19 2020-06-16 Etudes/Suivi et Contrôle dans qualifications des le cadre de l'execution des consultants sous projets de la composante 3 Page 9 CS-REF-34 / Recrutement d'un Consultant dans la Sélection fondée région de Tombouctou pour sur les Etudes/Suivi et Contrôle dans IDA / D1680 Community Rehabilitation A posteriori Open - National 45,283.00 49,961.52 Signé 2019-10-04 2019-10-21 2019-10-19 2020-11-03 2019-11-13 2020-02-12 2019-11-28 2020-04-28 2019-12-19 2020-06-30 2020-06-16 qualifications des le cadre de l'execution des consultants sous projets de la composante 3 CS-REF-35 / Recrutement d'un Consultant dans la Sélection fondée région de Menaka pour sur les IDA / D1680 Community Rehabilitation A posteriori Open - National 18,089.00 0.00 En cours d'examen 2019-10-04 2019-10-21 2019-10-19 2019-11-13 2019-11-28 2019-12-19 2020-06-16 Etudes/Suivi et Contrôle dans qualifications des le cadre de l'execution des consultants sous projets de la composante 3 CS-REF-36 / Recrutement d'un Consultant dans la Sélection fondée région de Toudenit pour sur les IDA / D1680 Community Rehabilitation A posteriori Open - National 18,119.00 27,838.27 Signé 2019-10-04 2019-10-21 2019-10-19 2020-11-18 2019-11-13 2020-02-10 2019-11-28 2020-03-16 2019-12-19 2020-05-18 2020-06-16 Etudes/Suivi et Contrôle dans qualifications des le cadre de l'execution des consultants sous projets de la composante 3 CS-REF-4 / P.E pour l'Encadrement, l'Appui conseil, Sélection fondée l'Orientation et dispense de Reinsertion Support to IDA / D1680 A priori sur la qualité et le Open - International 1,000,000.00 0.00 Annulé 2018-02-06 2018-10-01 2018-02-11 2018-03-12 2018-04-21 2018-04-28 2018-05-15 2018-06-19 2019-06-19 Kit de formation aux ex- Demobilized Ex-combatants coût combattants démobilisés dans la région de Tombouctou CS-REF-6 / P.E pour l'Encadrement, l'Appui conseil, Sélection fondée l'Orientation et dispense de Reinsertion Support to IDA / D1680 A priori sur la qualité et le Open - International 1,000,000.00 0.00 Annulé 2018-02-06 2018-09-17 2018-02-11 2018-03-12 2018-04-21 2018-04-28 2018-05-15 2018-06-19 2019-06-19 Kit de formation aux ex- Demobilized Ex-combatants coût combattants démobilisés dans la région de Menaka CS-REF-50 / P.E N°01 pour l'Encadrement, l'Appui conseil, Sélection fondée l'Orientation et dispense de Reinsertion Support to sur les IDA / D1680 A posteriori Open - International 120,000.00 0.00 En cours d'examen 2019-10-25 2019-02-27 2019-10-26 2019-12-02 2019-12-17 2020-01-21 2021-01-20 Kit de formation aux ex- Demobilized Ex-combatants qualifications des combattants démobilisés dans consultants la région de Tombouctou CS-REF-51 / P.E N°01 pour l'Encadrement, l'Appui conseil, Sélection fondée l'Orientation et dispense de Reinsertion Support to sur les IDA / D1680 A posteriori Open - International 120,000.00 0.00 En cours d'examen 2019-10-25 2019-02-27 2019-11-09 2019-12-09 2019-12-24 2020-01-28 2021-01-27 Kit de formation aux ex- Demobilized Ex-combatants qualifications des combattants démobilisés dans consultants la région de Menaka CS-REF-56 / Recrutement Sélection fondée d’un Consultant pour l’étude Project Management Support sur les En cours situation de référence pour IDA / D1680 to Project Implementation A posteriori Open - National 17,241.00 0.00 2020-03-16 2020-04-17 2020-03-31 2020-05-10 2020-05-25 2020-06-14 2020-08-13 qualifications des d'exécution l’évaluation des Unit consultants effets/impacts du PREC CS-REF-9 / Recrutement des Prestataires d'appui au Sélection fondée Reinsertion Support to démarrage des associations IDA / D1680 A posteriori sur la qualité et le Open - International 300,000.00 0.00 Annulé 2018-07-18 2018-07-23 2018-08-20 2018-09-17 2018-09-22 2018-10-11 2018-11-15 2018-12-30 Demobilized Ex-combatants économiques et des coût coopératives CS-REF-10 / Recrutement Sélection fondée des Prestataires pour Reinsertion Support to IDA / D1680 A posteriori sur la qualité et le Open - International 600,000.00 0.00 Annulé 2018-03-30 2018-04-04 2018-05-02 2018-05-30 2018-06-06 2018-06-23 2018-07-28 2019-07-28 Dispense des activités d'appui Demobilized Ex-combatants coût à la réinsertion sociale INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CS-REF-19 / Contrat Project Management Support En attente recrutement de Secrétaire IDA / D1680 to Project Implementation A posteriori Individuel Open 16,000.00 0.00 2019-01-06 2019-02-11 2019-02-16 2019-02-24 2021-03-15 d'exécution Administratif Financier (SAF) Unit CS-REF-26 / Recrutement Project Management Support Sélection de En attente d'un Consultant pour l'Etude IDA / D1680 to Project Implementation A posteriori consultants par Direct 20,000.00 0.00 2019-01-08 2019-01-18 2019-02-03 2019-03-05 d'exécution du CGES du PREC Unit entente directe CS-REF-27 / Recrutement Project Management Support Sélection de En attente d'un Consultant pour l'Etude IDA / D1680 to Project Implementation A posteriori consultants par Direct 20,000.00 0.00 2019-01-08 2019-01-18 2019-02-03 2019-03-05 d'exécution du CPRP du PREC Unit entente directe CS-REF-28 / Consultant pour l'élaboration du manuel Project Management Support Sélection de En attente technique de la composante 2 IDA / D1680 to Project Implementation A posteriori consultants par Direct 10,000.00 0.00 2019-04-30 2019-05-05 2019-05-20 2019-06-09 d'exécution des projets à la demande du Unit entente directe PREC CS-REF-43 / Recrutement Project Management Support En attente Spécialiste en Développement IDA / D1680 to Project Implementation A posteriori Individuel Open 32,148.00 0.00 2019-08-07 2019-09-16 2019-10-07 2019-11-07 2021-10-31 d'exécution Social (SDS) de l'UEP du PREC Unit CS-REF-44 / Recrutement Project Management Support Spécialiste en Sauvegarde En attente IDA / D1680 to Project Implementation A posteriori Individuel Open 32,148.00 0.00 2019-08-07 2019-09-16 2019-10-07 2019-11-07 2021-10-31 Environnemental (SSEv) de d'exécution Unit l'UEP du PREC Project Management Support CS-REF-12 / Contrat du En attente IDA / D1680 to Project Implementation A posteriori Individuel Open 32,148.00 0.00 2018-04-16 2018-05-17 2018-05-24 2018-06-03 2019-06-03 spécialiste en suivi évaluation d'exécution Unit CS-REF-53 / Recrutement Project Management Support Specialiste en Passation de En cours IDA / D1680 to Project Implementation A posteriori Individuel Limited 41,400.00 0.00 2019-12-23 2020-01-14 2019-12-28 2020-01-04 2020-01-15 2021-01-14 marches pour le compte de d'exécution Unit l’UEP du PREC Page 10 CS-REF-54 / Recrutement Project Management Support Specialiste en Gestion En cours IDA / D1680 to Project Implementation A posteriori Individuel Limited 41,400.00 0.00 2019-12-23 2020-01-14 2019-12-28 2020-01-04 2020-01-15 2021-01-14 Financiere pour le compte de d'exécution Unit l’UEP du PREC CS-REF-55 / Recrutement Ingénieur en Infrastructures En cours IDA / D1680 Community Rehabilitation A posteriori Individuel Limited 20,700.00 0.00 2019-12-23 2020-01-14 2019-12-28 2020-01-04 2020-01-15 2020-07-13 communautaires pour le d'exécution compte de l’UEP du PREC CS-REF-39 / Recrutement assistant en suivi et IDA / D1680 Community Rehabilitation A posteriori Individuel Open 23,077.00 1,176.62 Signé 2020-04-01 2020-04-17 2020-04-28 2020-07-15 2020-05-13 2020-09-07 2020-06-10 2020-11-16 2021-06-10 évaluation dans la région Tombouctou CS-REF-42 / Recrutement assistant en suivi et IDA / D1680 Community Rehabilitation A posteriori Individuel Open 23,077.00 1,176.62 Signé 2019-10-27 2020-04-17 2019-11-23 2020-07-15 2019-12-08 2020-09-07 2020-01-05 2020-11-16 2021-01-04 évaluation dans la région Taoudenit CS-REF-37 / Recrutement assistant en suivi et IDA / D1680 Community Rehabilitation A posteriori Individuel Open 23,077.00 1,176.62 Signé 2019-10-27 2020-04-17 2019-11-23 2020-07-16 2019-12-08 2020-09-07 2020-01-05 2020-11-16 2021-01-04 évaluation dans la région Mopti CS-REF-38 / Recrutement assistant en suivi et IDA / D1680 Community Rehabilitation A posteriori Individuel Open 23,077.00 1,176.62 Signé 2019-10-27 2020-04-17 2019-11-23 2020-07-17 2019-12-08 2020-09-07 2020-01-05 2020-11-16 2021-01-04 évaluation dans la région de Gao CS-REF-40 / Recrutement assistant en suivi et IDA / D1680 Community Rehabilitation A posteriori Individuel Open 23,077.00 1,176.62 Signé 2019-10-27 2020-04-17 2019-11-23 2020-07-15 2019-12-08 2020-09-07 2020-01-05 2020-11-16 2021-01-04 évaluation dans la région Kidal CS-REF-41 / Recrutement assistant en suivi et IDA / D1680 Community Rehabilitation A posteriori Individuel Open 23,077.00 1,176.62 Signé 2020-04-01 2020-04-17 2020-04-28 2020-07-15 2020-05-13 2020-09-07 2020-05-28 2020-11-16 2021-05-28 évaluation dans la région Menaka CS-REF-52 / Recrutement Project Management Support d’un consultant national pour IDA / D1680 to Project Implementation A posteriori Individuel Limited 5,172.00 0.00 Annulé 2019-11-06 2019-11-11 2019-11-26 2019-12-25 2020-02-23 appui à la passation des Unit marchés à L’UEP/PREC CS-REF-57 / Recrutement d’un Spécialiste en Violences IDA / D1680 Community Rehabilitation A posteriori Individuel Open 41,400.00 0.00 Annulé 2020-02-28 2020-04-02 2020-04-09 2020-04-21 2021-04-21 basées sur le Genre (VBG) pour le PREC CS-REF-13 / Consultant pour Project Management Support l'élaboration de la stratégie de IDA / D1680 to Project Implementation A posteriori Individuel Open 22,544.00 0.00 Annulé 2018-02-26 2018-04-03 2018-04-10 2018-05-08 2018-06-07 communication Unit CS-REF-1 / Recrutement d'un consultant pour l'étude récapitulative socio- économique sur les filières Project Management Support porteuses et les Kits de IDA / D1680 to Project Implementation A posteriori Individuel Open 24,155.00 0.00 Annulé 2018-02-15 2018-03-23 2018-03-30 2018-04-27 2018-05-27 Réinsertion dans toutes les Unit régions sur la base d’anciennes études réalisées au Mali CS-REF-60 / Recrutement par entente directe à temps Project Management Support Sélection de En attente partiel d'un spécialiste en IDA / D1680 to Project Implementation A posteriori consultants par Direct 4,000.00 0.00 2021-08-23 2021-08-27 2021-09-06 2021-11-30 d'exécution sauvegarde sociale pour le Unit entente directe compte du PREC Page 11