PROCUREMENT PLAN (Textual Part) Project information: Ethiopia, Urban Productive Safety Net and Jobs Project (P169943) Project Implementation agency: Ministry of Labor and Social Affairs (MoLSA), Ministry of Urban Development and Construction (MoUDC), Urban Job Creation and Food Security Agency (UJCFSA) Date of the Procurement Plan: November 2020. Period covered by this Procurement Plan: December 2020 to December 2021. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016 revised August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Section 33(1)(a) from page 35-48 of the Proclamation Number 649/2009 of the Ethiopian Federal Government Procurement and Property Administration Proclamation, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. • Open Advertising of the procurement opportunity at the national level; • The procurement is open to eligible firms from any country; • The request for bids/Proposal documents shall require that bidders/proposers submitting Bids/Proposal present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of and compliance with the Bank’s Anti-Corruption Guidelines, including without limitation the bank’s right to sanction and the Bank’s inspection and audit right; • Contracts with an appropriate allocation of responsibilities, risks and liabilities; • Application of Standstill period and Publication of contract award information; • Maintenance of records of the procurement process; and • The Bank has the right to review procurement documentation and activities. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Is applicable for those contracts identified in the Procurement Plan; Works: Is applicable for those contracts identified in the Procurement Plan. Other Relevant Procurement Information. None PROCUREMENT Ethiopia : Urban Productive Safety Net and Jobs Project PLAN General Information Country: Ethiopia Bank’s Approval Date of the Original Procurement Plan: 2021-08-27 2021-08-27 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P169943 GPN Date: 2020-12-18 Project Name: Urban Productive Safety Net and Jobs Project Loan / Credit No: IDA / D7320 O Executing Agency(ies): romya Regional State Urban Development and Housing Bureau WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-OROMIA-248276-GO- Institutional Strengthening, Pending RFQ / Procurement of Request for Single Stage - One IDA / D7320 Project Management and Post Limited 33,300.00 0.00 Implementati 2021-09-10 2021-10-11 2021-11-10 furniture for regional hub and Quotations Envelope Monitoring and Evaluation on project beneficiary cities ET-OROMIA-ADAMA-250173- Expand the Urban Productive Pending GO-RFB / Procurement of Single Stage - One IDA / D7320 Safety Net to Improve the Post Request for Bids Open - National 231,500.00 0.00 Implementati 2021-09-10 2021-09-15 2021-10-15 2021-11-14 2021-12-09 2022-02-07 safety materials for Adama Envelope Urban Environment on city ET-OROMIA-ADAMA-248287- Expand the Urban Productive Pending GO-RFQ / Procurement of Request for Single Stage - One IDA / D7320 Safety Net to Improve the Post Limited 29,800.00 0.00 Implementati 2021-09-15 2021-10-16 2021-11-15 Hand Tools Materials for Quotations Envelope Urban Environment on Adama City ET-OROMIA-ADAMA-248297- Expand the Urban Productive Pending GO-RFQ / Procurement of Request for Single Stage - One IDA / D7320 Safety Net to Improve the Post Limited 36,300.00 0.00 Implementati 2021-09-15 2021-10-17 2021-11-16 Industrial construction Quotations Envelope Urban Environment on Materials for Adama City ET-OROMIA-JIMA-250081- Expand the Urban Productive Pending Request for Single Stage - One GO-RFQ / Procurement of IDA / D7320 Safety Net to Improve the Post Limited 69,600.00 0.00 Implementati 2021-09-15 2021-10-16 2021-11-15 Quotations Envelope Safety Materials for Jima City Urban Environment on ET-OROMIA-JIMA-248311- Expand the Urban Productive Pending Request for Single Stage - One GO-RFQ / Procurement of IDA / D7320 Safety Net to Improve the Post Limited 13,500.00 0.00 Implementati 2021-09-15 2021-10-19 2021-11-18 Quotations Envelope Hand Tools for Jima City Urban Environment on ET-OROMIA-SHASHAMANE- Expand the Urban Productive Pending 248314-GO-RFQ / Request for Single Stage - One IDA / D7320 Safety Net to Improve the Post Limited 73,400.00 0.00 Implementati 2021-09-13 2021-10-20 2021-11-19 Procurement of Safety Quotations Envelope Urban Environment on Materials for shashamane City ET-OROMIA-SHASHAMANE- Expand the Urban Productive Pending 248318-GO-RFQ / Request for Single Stage - One IDA / D7320 Safety Net to Improve the Post Limited 17,200.00 0.00 Implementati 2021-09-14 2021-10-21 2021-11-20 Procurement of Hand Tools Quotations Envelope Urban Environment on for Shashamane City ET-OROMIA-BISHOFTU- Expand the Urban Productive Pending 248321-GO-RFQ / Request for Single Stage - One IDA / D7320 Safety Net to Improve the Post Limited 73,700.00 0.00 Implementati 2021-09-15 2021-10-22 2021-11-21 Procurement of Safety Quotations Envelope Urban Environment on Materials for Bishoftu City ET-OROMIA-BISHOFTU- Expand the Urban Productive Pending 248324-GO-RFQ / Request for Single Stage - One IDA / D7320 Safety Net to Improve the Post Limited 73,300.00 0.00 Implementati 2021-09-15 2021-10-22 2021-11-21 procurement of Hand Tools Quotations Envelope Urban Environment on Materials for Bishoftu City ET-OROMIA-NEKEMTE- Expand the Urban Productive Pending 248327-GO-RFQ / Request for Single Stage - One IDA / D7320 Safety Net to Improve the Post Limited 50,100.00 0.00 Implementati 2021-09-15 2021-10-22 2021-11-21 procurement of Safety Quotations Envelope Urban Environment on Materials for Nekemte City ET-OROMIA-NEKEMTE- Expand the Urban Productive Pending 248329-GO-RFQ / Request for Single Stage - One IDA / D7320 Safety Net to Improve the Post Limited 17,200.00 0.00 Implementati 2021-09-15 2021-10-22 2021-11-21 Procurement of Hand Tools Quotations Envelope Urban Environment on Materials for Nekemte City ET-OROMIA-ASELA-248334- Expand the Urban Productive Pending Request for Single Stage - One GO-RFQ / Procurement of IDA / D7320 Safety Net to Improve the Post Limited 44,800.00 0.00 Implementati 2021-09-15 2021-10-22 2021-11-21 Quotations Envelope Safety Materials for Asela City Urban Environment on ET-OROMIA-ASELA-248341- Expand the Urban Productive Pending GO-RFQ / Procurement of Request for Single Stage - One IDA / D7320 Safety Net to Improve the Post Limited 14,300.00 0.00 Implementati 2021-09-15 2021-10-22 2021-11-21 Hand Tools Materials fo Asela Quotations Envelope Urban Environment on City ET-OROMIA-SEBETA-248349- Expand the Urban Productive Pending GO-RFQ / Procurement of Request for Single Stage - One IDA / D7320 Safety Net to Improve the Post Limited 35,100.00 0.00 Implementati 2021-09-15 2021-10-22 2021-11-21 Safety Materials for Sebeta Quotations Envelope Urban Environment on City ET-OROMIA-SEBETA-248353- Expand the Urban Productive Pending GO-RFQ / Procurement of Request for Single Stage - One IDA / D7320 Safety Net to Improve the Post Limited 7,200.00 0.00 Implementati 2021-09-15 2021-10-22 2021-11-21 Hand Tools Materials for Quotations Envelope Urban Environment on Sebeta City ET-OROMIA-BURAYU- Expand the Urban Productive Pending 248354-GO-RFQ / Request for Single Stage - One IDA / D7320 Safety Net to Improve the Post Limited 34,200.00 0.00 Implementati 2021-09-15 2021-10-22 2021-11-21 Procurement of Safety Quotations Envelope Urban Environment on Materials for Burayu City Page 1 ET-OROMIA-BURAYU- Expand the Urban Productive Pending 248355-GO-RFQ / Request for Single Stage - One IDA / D7320 Safety Net to Improve the Post Limited 7,400.00 0.00 Implementati 2021-09-15 2021-10-22 2021-11-21 Procurement of Hand Tools Quotations Envelope Urban Environment on Materials for Burayu City ET-OROMIA-AMBO-248356- Expand the Urban Productive Pending Request for Single Stage - One GO-RFQ / Procurement of IDA / D7320 Safety Net to Improve the Post Limited 33,900.00 0.00 Implementati 2021-09-15 2021-10-22 2021-11-21 Quotations Envelope Safety Materials for Ambo City Urban Environment on ET-OROMIA-AMBO-248357- Expand the Urban Productive Pending GO-RFQ / Procurement of Request for Single Stage - One IDA / D7320 Safety Net to Improve the Post Limited 74,300.00 0.00 Implementati 2021-09-15 2021-10-22 2021-11-21 Hand Tools Materials for Quotations Envelope Urban Environment on Ambo City ET-OROMIA-ARSI NEGELE- Expand the Urban Productive Pending 248372-GO-RFQ / Request for Single Stage - One IDA / D7320 Safety Net to Improve the Post Limited 33,900.00 0.00 Implementati 2021-09-15 2021-10-24 2021-11-23 Procurement of Safety Quotations Envelope Urban Environment on Materials for Arsi Negele City ET-OROMIA-ARSI NEGELE- Expand the Urban Productive Pending 248376-GO-RFQ / Request for Single Stage - One IDA / D7320 Safety Net to Improve the Post Limited 7,300.00 0.00 Implementati 2021-09-15 2021-10-22 2021-11-21 Procurement of Hand Tools Quotations Envelope Urban Environment on Materials for Arsi Negele City ET-OROMIA-ROBE-248377- Expand the Urban Productive Pending Request for Single Stage - One GO-RFQ / Procurement of IDA / D7320 Safety Net to Improve the Post Limited 32,300.00 0.00 Implementati 2021-09-15 2021-10-22 2021-11-21 Quotations Envelope Safety Materials for Robe City Urban Environment on ET-OROMIA-ROBE-248379- Expand the Urban Productive Pending GO-RFQ / Procurement of Request for Single Stage - One IDA / D7320 Safety Net to Improve the Post Limited 6,200.00 0.00 Implementati 2021-09-15 2021-10-24 2021-11-23 Hand Tools Materials for Robe Quotations Envelope Urban Environment on City ET-OROMIA-BATU-248380- Expand the Urban Productive Pending GO-RFQ / Procurement of Request for Single Stage - One IDA / D7320 Safety Net to Improve the Post Limited 29,800.00 0.00 Implementati 2021-09-15 2021-10-21 2021-11-20 Safety Materials for Ziway Batu Quotations Envelope Urban Environment on City ET-OROMIA-BATU-248382- Expand the Urban Productive Pending GO-RFQ / Procurement of Request for Single Stage - One IDA / D7320 Safety Net to Improve the Post Limited 7,200.00 0.00 Implementati 2021-09-15 2021-10-22 2021-11-21 Hand Tools Materials for Quotations Envelope Urban Environment on Ziway Batu City ET-OROMIA-WELISO-248384- Expand the Urban Productive Pending GO-RFQ / Procurement of Request for Single Stage - One IDA / D7320 Safety Net to Improve the Post Limited 45,200.00 0.00 Implementati 2021-09-15 2021-10-22 2021-11-21 Safety Materials for Weliso Quotations Envelope Urban Environment on City ET-OROMIA-WELISO-248387- Expand the Urban Productive Pending GO-RFQ / Procurement of Request for Single Stage - One IDA / D7320 Safety Net to Improve the Post Limited 14,300.00 0.00 Implementati 2021-09-15 2021-10-19 2021-11-18 Hand Tools Materials for Quotations Envelope Urban Environment on Weliso ET-OROMIA-MEKI-248388- Expand the Urban Productive Pending Request for Single Stage - One GO-RFQ / Procurement of IDA / D7320 Safety Net to Improve the Post Limited 43,700.00 0.00 Implementati 2021-09-15 2021-10-22 2021-11-21 Quotations Envelope Safety Materials for Meki City Urban Environment on ET-OROMIA-MEKI-248390- Expand the Urban Productive Pending GO-RFQ / Procurement of Request for Single Stage - One IDA / D7320 Safety Net to Improve the Post Limited 14,600.00 0.00 Implementati 2021-09-15 2021-10-22 2021-11-21 Hand Tools Materials for Meki Quotations Envelope Urban Environment on City ET-OROMIA-BULEHORA- Expand the Urban Productive Pending 248395-GO-RFQ / Request for Single Stage - One IDA / D7320 Safety Net to Improve the Post Limited 41,200.00 0.00 Implementati 2021-09-15 2021-10-22 2021-11-21 Procurement of Safety Quotations Envelope Urban Environment on Materials for Bulehora City ET-OROMIA-BULEHORA- Expand the Urban Productive Pending 248396-GO-RFQ / Request for Single Stage - One IDA / D7320 Safety Net to Improve the Post Limited 14,900.00 0.00 Implementati 2021-09-15 2021-10-22 2021-11-21 Procurement of Hand Tools Quotations Envelope Urban Environment on Materials for Bulehora City ET-OROMIA-BORENA- 248397-GO-RFQ / Expand the Urban Productive Pending Request for Single Stage - One Procurement of Safety IDA / D7320 Safety Net to Improve the Post Limited 41,200.00 0.00 Implementati 2021-09-15 2021-10-19 2021-11-18 Quotations Envelope Materials for Negele Borena Urban Environment on City ET-OROMIA-BORENA- 248398-GO-RFQ / Expand the Urban Productive Pending Request for Single Stage - One Procurement of Hand Tools IDA / D7320 Safety Net to Improve the Post Limited 14,900.00 0.00 Implementati 2021-09-15 2021-10-22 2021-11-21 Quotations Envelope Materials for Negele Borena Urban Environment on City ET-OROMIA-CHIRO-248399- Expand the Urban Productive Pending Request for Single Stage - One GO-RFQ / Procurement of IDA / D7320 Safety Net to Improve the Post Limited 40,200.00 0.00 Implementati 2021-09-15 2021-10-19 2021-11-18 Quotations Envelope Safety Materials for Chiro City Urban Environment on ET-OROMIA-CHIRO-248400- Expand the Urban Productive Pending GO-RFQ / Procurement of Request for Single Stage - One IDA / D7320 Safety Net to Improve the Post Limited 13,900.00 0.00 Implementati 2021-09-15 2021-10-22 2021-11-21 Hand Tools Materials for Chiro Quotations Envelope Urban Environment on City ET-OROMIA-GIMBI-248401- Expand the Urban Productive Pending Request for Single Stage - One GO-RFQ / procurement of IDA / D7320 Safety Net to Improve the Post Limited 38,600.00 0.00 Implementati 2021-09-15 2021-10-22 2021-11-21 Quotations Envelope Safety Materials for Gimbi City Urban Environment on ET-OROMIA-GIMBI-248402- Expand the Urban Productive Pending GO-RFQ / Procurement of Request for Single Stage - One IDA / D7320 Safety Net to Improve the Post Limited 10,500.00 0.00 Implementati 2021-09-15 2021-10-22 2021-11-21 Hand Tools Materials for Quotations Envelope Urban Environment on Gimbi City ET-OROMIA-DEMBIDOLO- Expand the Urban Productive Pending 248403-GO-RFQ / Request for Single Stage - One IDA / D7320 Safety Net to Improve the Post Limited 36,600.00 0.00 Implementati 2021-09-15 2021-10-22 2021-11-21 Procurement of Safety Quotations Envelope Urban Environment on Materials for Dembidolo City Page 2 ET-OROMIA-DEMBIDOLO- Expand the Urban Productive Pending 248404-GO-RFQ / Request for Single Stage - One IDA / D7320 Safety Net to Improve the Post Limited 8,500.00 0.00 Implementati 2021-09-15 2021-10-22 2021-11-21 Procurement of Hand Tools Quotations Envelope Urban Environment on Materials for Dembidolo City ET-OROMIA-HARAMAYA- Expand the Urban Productive Pending 248405-GO-RFQ / Request for Single Stage - One IDA / D7320 Safety Net to Improve the Post Limited 36,600.00 0.00 Implementati 2021-09-15 2021-10-22 2021-11-21 Procurement of Safety Quotations Envelope Urban Environment on Materials for Haramaya City ET-OROMIA-HARAMAYA- Expand the Urban Productive Pending 248406-GO-RFQ / Request for Single Stage - One IDA / D7320 Safety Net to Improve the Post Limited 10,500.00 0.00 Implementati 2021-09-15 2021-10-22 2021-11-21 Procurement of Hand Tools Quotations Envelope Urban Environment on Materials for Haramaya City ET-OROMIA-MATTU-248411- Expand the Urban Productive Pending Request for Single Stage - One GO-RFQ / Procurement of IDA / D7320 Safety Net to Improve the Post Limited 38,700.00 0.00 Implementati 2021-09-15 2021-10-22 2021-11-21 Quotations Envelope Safety Materials for Mattu City Urban Environment on ET-OROMIA-MATTU-248413- Expand the Urban Productive Pending GO-RFQ / Procurement of Request for Single Stage - One IDA / D7320 Safety Net to Improve the Post Limited 7,000.00 0.00 Implementati 2021-09-15 2021-10-22 2021-11-21 Hand Tools Materials for Quotations Envelope Urban Environment on Mattu City ET-OROMIA-FICHE-248422- Expand the Urban Productive Pending Request for Single Stage - One GO-RFQ / Procurement of IDA / D7320 Safety Net to Improve the Post Limited 33,500.00 0.00 Implementati 2021-09-15 2021-10-22 2021-11-21 Quotations Envelope Safety Materials for Fiche City Urban Environment on ET-OROMIA-FICHE-248429- Expand the Urban Productive Pending GO-RFQ / Procurement of Request for Single Stage - One IDA / D7320 Safety Net to Improve the Post Limited 8,600.00 0.00 Implementati 2021-09-15 2021-10-22 2021-11-21 Hand Tools Materials for Fiche Quotations Envelope Urban Environment on City ET-OROMIA-AGARO-248430- Expand the Urban Productive Pending Request for Single Stage - One GO-RFQ / Procurement of IDA / D7320 Safety Net to Improve the Post Limited 33,500.00 0.00 Implementati 2021-09-15 2021-10-22 2021-11-21 Quotations Envelope Safety Materials for Agaro City Urban Environment on ET-OROMIA-AGARO-248431- Expand the Urban Productive Pending GO-RFQ / Procurement of Request for Single Stage - One IDA / D7320 Safety Net to Improve the Post Limited 6,300.00 0.00 Implementati 2021-09-15 2021-10-22 2021-11-21 Hand Tools Materials for Quotations Envelope Urban Environment on Agaro City ET-OROMIA-HOLETA- Expand the Urban Productive Pending 248432-GO-RFQ / Request for Single Stage - One IDA / D7320 Safety Net to Improve the Post Limited 62,200.00 0.00 Implementati 2021-09-15 2021-10-22 2021-11-21 Procurement of Safety Quotations Envelope Urban Environment on Materials for Holeta city ET-OROMIA-HOLETA- Expand the Urban Productive Pending 248433-GO-RFQ / Request for Single Stage - One IDA / D7320 Safety Net to Improve the Post Limited 22,300.00 0.00 Implementati 2021-09-15 2021-10-22 2021-11-21 Procurement of Hand Tools Quotations Envelope Urban Environment on Materials for Holeta City ET-OROMIA-BEDELE-248434- Expand the Urban Productive Pending GO-RFQ / Procurement of Request for Single Stage - One IDA / D7320 Safety Net to Improve the Post Limited 62,200.00 0.00 Implementati 2021-09-15 2021-10-22 2021-11-21 Safety Materials for Bedele Quotations Envelope Urban Environment on City ET-OROMIA-BEDELE-248437- Expand the Urban Productive Pending GO-RFQ / Procurement of Request for Single Stage - One IDA / D7320 Safety Net to Improve the Post Limited 8,500.00 0.00 Implementati 2021-09-15 2021-10-22 2021-11-21 Hand Tools Materials for Quotations Envelope Urban Environment on Bedele city ET-OROMIA-BADESA-248439- Expand the Urban Productive Pending GO-RFQ / Procurement of Request for Single Stage - One IDA / D7320 Safety Net to Improve the Post Limited 48,900.00 0.00 Implementati 2021-09-15 2021-10-22 2021-11-21 Safety Materials for Badesa Quotations Envelope Urban Environment on City ET-OROMIA-BADESA-248440- Expand the Urban Productive Pending GO-RFQ / Procurement of Request for Single Stage - One IDA / D7320 Safety Net to Improve the Post Limited 15,800.00 0.00 Implementati 2021-09-15 2021-10-22 2021-11-21 Hand Tools Materials for Quotations Envelope Urban Environment on Badesa City ET-OROMIA-GINCHI-248442- Expand the Urban Productive Pending GO-RFQ / Procurement fo Request for Single Stage - One IDA / D7320 Safety Net to Improve the Post Limited 46,700.00 0.00 Implementati 2021-09-15 2021-10-22 2021-11-21 Safety Materials for Ginchi Quotations Envelope Urban Environment on City ET-OROMIA-GINCHI-248445- Expand the Urban Productive Pending GO-RFQ / Procurement of Request for Single Stage - One IDA / D7320 Safety Net to Improve the Post Limited 17,200.00 0.00 Implementati 2021-09-15 2021-10-22 2021-11-21 Hand Tools Materials for Quotations Envelope Urban Environment on Ginchi City ET-OROMIA-YABELO-248448- Expand the Urban Productive Pending GO-RFQ / Procurement of Request for Single Stage - One IDA / D7320 Safety Net to Improve the Post Limited 45,700.00 0.00 Implementati 2021-09-15 2021-10-22 2021-11-21 Safety Materials for Yabello Quotations Envelope Urban Environment on City ET-OROMIA-YABELO-248451- Expand the Urban Productive Pending GO-RFQ / Procurement of Request for Single Stage - One IDA / D7320 Safety Net to Improve the Post Limited 16,500.00 0.00 Implementati 2021-09-15 2021-10-22 2021-11-21 Hand Tools Materials for Quotations Envelope Urban Environment on Yabello City ET-OROMIA-DERA-248454- Expand the Urban Productive Pending Request for Single Stage - One GO-RFQ / Procurement of IDA / D7320 Safety Net to Improve the Post Limited 42,875.00 0.00 Implementati 2021-09-15 2021-10-22 2021-11-21 Quotations Envelope Safety Materials for Dera City Urban Environment on ET-OROMIA-DERA-248459- Expand the Urban Productive Pending GO-RFQ / Procurement of Request for Single Stage - One IDA / D7320 Safety Net to Improve the Post Limited 9,800.00 0.00 Implementati 2021-09-15 2021-10-22 2021-11-21 Hand Tools Materials for Dera Quotations Envelope Urban Environment on City ET-OROMIA-SHAMBU- Expand the Urban Productive Pending 248462-GO-RFQ / Request for Single Stage - One IDA / D7320 Safety Net to Improve the Post Limited 39,200.00 0.00 Implementati 2021-09-15 2021-10-22 2021-11-21 Procurement of Safety Quotations Envelope Urban Environment on Materials for Shambu City ET-OROMIA-SHAMBU- Expand the Urban Productive Pending 248465-GO-RFQ / Request for Single Stage - One IDA / D7320 Safety Net to Improve the Post Limited 13,800.00 0.00 Implementati 2021-09-15 2021-10-22 2021-11-21 Procurement of Hand Tools Quotations Envelope Urban Environment on Materials for Shambu City Page 3 NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-OROMIA-UDHB-248184- CS-INDV / Recruitment of Institutional Strengthening, Individual individual consultant/ Public Pending IDA / D7320 Project Management and Post Consultant Open 5,400.00 0.00 2021-09-08 2021-10-12 2021-10-27 2021-11-21 2022-11-21 work specialist with ability to Implementation Monitoring and Evaluation Selection handle livelihood for Oromia Regional Hub ET-OROMIA-UDHB-248186- CS-INDV / Recruitment of Institutional Strengthening, Individual Pending individual consultant/ IDA / D7320 Project Management and Post Consultant Open 5,300.00 0.00 2021-09-08 2021-10-12 2021-10-27 2021-11-21 2022-11-21 Implementation safeguard specialist for Monitoring and Evaluation Selection Oromya regional Hub Page 4