FINAL GEWEL PROCUREMENT PLAN Date of this revision: May 26, 2016 Zambia Girls Education and Women’s Empowerment (GEWEL) Project. (Project ID No P151451) 1. General: The project development objective (PDO) is to support the Government of Zambia to increase access to livelihood support for women and access to secondary education for disadvantaged adolescent girls in extremely poor households in selected districts. The Project consists of the following three components: Component 1. Supporting Women's Livelihoods(US$36 million) The objective of this component is to provide them with access to opportunities that will increase the productivity of their livelihood activities and their economic empowerment. Component 2. : Keeping Girls in School (US$25.78 million) The objective of this component is to support adolescent girls in extremely poor households to access secondary education. Component 3. Institutional Strengthening and Systems Building (US$3.22 million) The main objectives of this component is to strengthen institutional capacity and build systems to increase efficiency and improve coordination of targeted programs. 2. Project ID No:P151451 3. Project Implementing Agencies: Component 1: Ministry of Community Development and Social Welfare (MCDSW) Component 2: Ministry of Education, Science Vocational Training and Early Education (MGE) Component 3: Ministry of Gender (MOG); and MCDSW 4. Bank’s approval Date of the Procurement Plan: April 10, 2015 5. Date of General Procurement Notice: April, 2014, revised August 13, 2015 6. Period covered by this Procurement Plan: September 2015 to February 2017 I. Goods and Works and Non-Consulting Services 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by IDA as stated in Appendix 1 to the Guidelines for Procurement: Table 1: Thresholds for Procurement Methods and Prior Review Goods, Works and Non Consultant Services Expenditu Procurement Method Contract Value Contracts Subject to re Threshold For use of Prior Review (US$) Category Method (US$) 1. Works ICB (Works/Supply & >=10,000,000 All contracts Installation) 1 NCB >=200,000 - As in procurement plan <10,000,000 Shopping <200,000 None Direct Contracting All values All contracts 2. Goods ICB >=2,000,000 All contracts NCB >=100,000 <2,000,000 As in procurement plan Shopping <300,000 (motor vehicles None only) Shopping <100,000 000 (rest not None motor vehicles) Direct Contracting All values All contracts Procurement from All values None UNOPS Agency Note: Contracts with a cost estimate below US$300,000 for motor vehicles only may be procured on basis of Shopping procurement method 2. Prequalification. N/A 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines). N/A 4. Reference to (if any) Project Operational/Procurement Manual: The components will besides provisions of the Banks Guidelines for Selection and Employment of Consultants under IBRD Loans and IDA Credits & Grants by World Bank Borrowers, dated January 2011, revised April 2014 and the Banks Guidelines Procurement of Goods, works, and Non-Consulting Services under IDRD Loans and IDA Credits & Grants by World bank Borrowers, dated January 2011, revised April 2014 and will also make use of the additional information and guidance provided in Manual – Guidance for Procurement of Small Contracts; World Bank Africa Region Procurement February 2011, revised March 2014 and in the case of all contracts entered into using NCB based on use of National standard Bidding Documents, additional provisions of the attachments and standard clauses of the Bank’s Policy – Corrupt and Fraudulent Practices whose text may not be modified will be used in both the bidding documents and the ensuing contracts. 5. Any Other Special Procurement Arrangements. None 6. Procurement Packages with Methods and Time Schedule. Procurement of Good and Non Services Do Commen me ts Packag Prior Expecte Preq sti Expected e Plan/ Est Proc or d Descriptio (yes c Contract Actua Amount in Post Bid n / Pre Signature Numbe l US $ Method Revie Opening no) fer Date r w Date en ce Component 1: Supporting Women's Livelihoods(Ministry of Community Development and Social Welfare) Printing of MCDSW Plan NCB No No Post Feb April 2016 May teaching /NCS/0 448,300 2016 require and 01 Actua to split learning l between 2 materials MCDSW Plan 1,255,000 NCB No No Prior Nov Feb 2016 Purchase of /NCS/0 2015 motor 02 Actua vehicles l MCDSW Plan Aug Aug 2016 550,000 Prior /NCS/0 Procure 2016 03 Actua ment l from UN Yes No Agencie Purchase of s motor (UNOPS vehicles ) MCDSW Plan NCB No No Post Nov Feb 2016 230,000 Purchase of /NCS/0 2015 Motor 04 Actua Bikes l MCDSW Plan Shoppi No No Post Nov Feb 2016 16,000 /NCS/0 ng 2015 Purchase of 05 Actua Bicycles l MCDSW Plan Shoppi No No Post Nov Feb 2016 82,000 /NCS/0 ng 2015 06 Actua Purchase of l Boats Purchase of MCDSW Plan 100,000 Shoppi No No Post Mar Apr 2016 Various /NCS/0 ng 2016 Office 07 Actua Furniture l and Equipment for H/Q and Districts Computers, MCDSW Plan March May 2016 Needed 281,300 Post Laptops, /NCS/0 2016 for the Scanners, 08 Actua SWL Printers, l NCB No No operation Projectors, s Cameras, UPS Launching Plan 535,000 Post April 2016 and Actua Equipment l NCB No No for MCDSW operation /NCS/0 of GRS 09 Equipment MCDSW Plan April June 2016 200,000 Post for ICT- /NCS/0 2016 based 10 Actua NCB No No learning l tools 3 Developme MCDSW Plan 120,000 Post Jan 2016 June 2016 nt of /NCS/0 Actua software 11 l and database for real- time NCB No No registration of SWL beneficiarie s and monitoring of activities. Sub Total Component 1; Goods and Non Consultant 3,817,600 Services Component 2. Keeping Girls in School (Ministry of Education, Science Vocational Training and Early Education ) Purchase of MGE/G Plan 60,000 Shoppi No No Post Jan 2016 Feb 2016 Hand Laptops, /01 ng held Tablets Actua devices and l for the Routers Impleme ntation of the model to capture real-time informati on in the field. IT MGE/G Plan 100,000 Shoppi No No Post Jan 2016 March (includin Equipment /02 ng 2016 g Actua computer l s and other IT equipme nt) Vehicles MGE/G Plan Shoppi Nov Jan 2016 250,000 No No Post for /03 ng 2015 selected Actua districts l Component 2. Keeping Girls in School (Ministry of Community Development ) Procureme MCDSW Plan Shoppi Nov Jan 2016 37,500 No No Post nt of /NCS/0 ng 2015 4 Project 01 Actua Vehicle l Sub Total Component 2; Goods and Non Consultant 447,500 Services Component 3 (a): Institutional Strengthening and Systems Building: (Ministry of Gender) Setting up MOG/G Plan Shoppi No No Post Jun 2016 July 2016 IT /01 100,000 ng infrastructu Actua re for M&E l in MOG vehicle for MOG/G Plan 50,000 Shoppi No No Post Nov Jan 2016 training, /02 ng 2015 and M&E Actua l Purchase of MOG/G Plan 40,000.00 Shoppi No No Post Jun, July, 2016 IT /03 ng 2016 Equipment Actua (Laptop l Computer, Desk top Computers, LAN, Camera, Projector and other IT Equipment s Purchase of MOG/0 Plan 3,000 Shoppi No No Post Jun, July, 2016 Office 4 ng 2016 Furniture Actua l Sub Total Component 3 A- Goods and Non Consultant 193,000 Services Component 3 (b) Institutional Strengthening and Systems: (Ministry of Community Development and Social Welfare) IT MCDSW Plan 400,000 NCB No No Post Aug Dec 2015 Infrastructu /G/01 2016 re for Actua informatio l n systems for MCDSW business at various levels Hardware MCDSW Plan 150,000 NCB No No Post Nov Jan 2017 and /G/02 2016 Software Actua for unique l identificati 5 on solution Procureme MCDSW Plan 60,000 Shoppi No No Post May June 2016 nt of /G/03 ng 2016 devices for Actua field and l identificati on of beneficiarie s Purchase of MCDSW Plan 100,000 Shoppi No No Post May July 2016 Goods office /G/04 ng 2016 for the furniture Actua National and l Social equpment Protectio n Co- ordinatio n Unit Purchase MCDSW Plan 150,000 Shoppi No No Post July July 2016 For of Motor /G/05 ng 2016 National Vehicles Actua Co- for l dination, National M&E and Social MIS. Protection Co- ordination Unit Sub Total Component 3 (b) : Goods and Non 860,000 Consultant Services Procurement of Works Sub Component 1: Supporting Women's Livelihoods(Ministry of Community Development and Social Welfare) MCDSW Plan Shoppi No No Post Oct Oct 2016 45,000.00 Office /W/00 ng 2016 refurbishm 1 Actual ent Sub Component 3(b): Institutional Strengthening and Systems: (Ministry of Community Development and Social Welfare) Support to MCDSW Plan 70,000 Shoppi No No Post Aug Aug 2016 office /G/02 ng 2016 refurbishm Actual ent Component 3 a). Institutional Strengthening and Systems: (Ministry of Gender ) Partitionin MOG/ Plan 2,000 Shoppi No No Post Sep Sep 2016 g of the W/01 ng 2016 Foyer for Actual the Conferenc 6 e Room Sub Total: Works 127,000 II. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Table 2: Thresholds for Consultants Selection Methods and Prior Review Contract Value Contracts Subject to Expenditure Procurement Method Threshold for use of Prior Review (US$ Category selection method (US$) millions) QCBS, QBS >=200,000 All contracts Consulting As in procurement CQS, LCS, QBS, FBS <200,000 Firms plan SSS All values All Contracts Competitive selection Individual >=100,000 All contracts Consultants (IC) IC Single Source All values All contracts Selection NOTE: Contracts selected on basis of CQS should not exceed US$200,000 equivalent. Note: Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than US$200,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. Engineering and contract management contracts with cost estimates of less than US$300,000 may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. The procurement plan will indicate those contracts using CQS whose short lists by exception may not comprise entirely national firms. Terms of Reference (TOR) for all consultancy contracts as well as all single source selections, irrespective of the contract value, will be subject to prior review. Any Other Special Selection Arrangements: N/A 2. Consultancy Assignments with Selection Methods and Time 1 2 3 4 5 6 7 Expected Plan Prior / proposal Selectio Estimated Ref. / Post submissio Description n Cost in Comments No. Actua Revie n Method US$ l w /opening Date Component 1: Supporting Women’s Livelihoods(Ministry of Community Development and Social Welfare) Adoption and Roll-out of SWL sub component 1(a) MCDSW/ Survey Enumeration Plan March QCBS 937,500 Prior C/001 of SWL beneficiaries 2016 7 Actua l MCDSW/ Information, Plan CQS 200,000 Post May 2016 C/002 education and communications Actua outreach at local l and national level Service provider to Plan 845,000 Jan 2016 MCDSW/ pay productivity Actua QCBS Prior C/003 grants to l beneficiaries Sub-component 1b – Building National Implementation and Monitoring Capacity MCDSW/ Plan 112,500 Prior April 2016 C/004 Hiring of SWL Actua Contract Duration IC manager l is 24 Months MCDSW/ Plan IC 97,500 Post April 2016 C/005 Hiring of SWL M&E Actua Contract Duration Specialist l is 24 Months 97,500 April 2016 MCDSW/ Plan IC 89,100 Post Nov 2015 C/006 Contract Duration M&E Officer Actua is 24 Months l 89,100 July 2016 MCDSW/ Plan IC 97,500 Post Nov 2015 C/007 Contract Duration ICT Specialist Actua is 24 Months l July 2016 MCDSW/ Plan IC 89,100 Post Nov 2015 C/008 Contract Duration ICT Officer Actua is 24 Months l 89,100 July 2016 MCDSW/ Plan IC 89,100 Post Nov 2015 C/009 Contract Duration Program Officer Actua is 24 Months l 89,100 July 2016 MCDSW/ Plan IC 89,100 Post Nov 2015 C/010 Contract Duration Program Officer Actua is 24 Months l 89,100 July 2016 MCDSW/ Plan IC 89,100 Post Nov 2015 C/011 Contract Duration Program Officer Actua is 24 Months l 89,100 July 2016 8 MCDSW/ Plan IC 89,100 Post Nov 2015 C/012 Contract Duration Program Officer Actua is 24 Months l 89,100 July 2016 MCDSW/ Plan IC 89,100 Post Nov 2015 C/013 Contract Duration Program Officer Actua is 24 Months l 89,100 July 2016 MCDSW/ Plan IC 97,200 Post April 2016 C/014 Contract Duration Program Accountant Actua is 24 Months l 97,200 April 2016 MCDSW/ Assistant Plan IC 77,760 Post Nov 2015 C/015 Accountant Contract Duration Actua is 24 Months l 77,760 July 2016 MCDSW/ Plan Notes: assignment QBS 1,300,000 Prior May 2016 C/016 will include Actua finalizing SWL l training curriculum, design of communications strategy for Consultancy to outreach awareness support roll out and raising and support implementation of for implementation SWL of SWL activities (Short list will comprise for profit and not for profit firms i.e. Private sector and NGOs hence use of QBS) MCDSW/ Design of and Plan CQS 90,000 Post Jan 2016 C/017 operational guidelines for Actua targeting and l identification of SWL beneficiaries MCDSW/ Plan Development of CQS 120,000 Post Jan 2016 C/018 strategy and tools Actua for SWL GRS, and l support to launch and operate the GRS MCDSW/ Strategy for Plan IC 60,000 Post June 2016 C/019 harmonization of MCDSW empowerment/liveli hood programs 9 Actua l MCDSW/ Plan January Implementation QCBS 200,000 Post C/020 2017 evaluation and Actua beneficiary l satisfaction survey MCDSW/ Plan QCBS 1,030,000 Prior June 2016 C/021 Impact evaluation data collection Actua l Sub Total Component 1; Consulting Services 5,702,060 Component 2. Keeping Girls in School (Ministry of Education, Science Vocational Training and Early Education ) Assessment for the Plan IC 45,000 Post Sept 2015 MGE/C/ identification of 001 technological Actua innovations l MGE/C/ Development of a Plan IC 50,000 Post Dec 2015 002 beneficiary awareness strategy Actua for Keeping Girls in l School MGE/C/ Design of Plan QCBS 200,000 Prior Jan 2016 003 Complaints & Grievance Mechanism for the Actua Keeping Girls in l School Initiative MGE/C/ Plan CQS 60,000 Post Sept 2016 004 Actua TA to harmonize existing bursary and l assessment, strategy MGE/C/ Plan CQS 51,000 Post March 005 2017 Support to Actua implement the l action plan to harmonize existing secondary school support schemes MGE/C/ Information System Plan QCBS 500,000 Prior February 006 Module, 2016 Development of the software to capture real time information in the field and testing of 10 Real time Data Actual Sub Total Component 2: Consulting Services 906,000 Component 3 (a). Institutional Strengthening and Systems Building: (Ministry of Gender) MOG/C/ Development of a Plan CQS 50,000 Post Oct 2015 01 monitoring Actua framework l MOG/C/ Development of Plan CQS 100,000 Post Jun 2016 02 software for a M&E Actua and evaluation l system MOG/C/ Technical assistance Plan CQS /IC 100,000 Post Sept 2015 Various over the 03 to the National life of the project. Secretariat for Actua Activity may be project management l split when defined Sub Total Component 3(a): 250,000 Consulting Services Component 3 (b). Institutional Strengthening and Systems Building: (Ministry of Community Development and Social Welfare MCDSW Development of M&E Plan CQS 150,000 Prior Aug 2015 /C/01 framework Actua l MCDSW Development of a Plan QCBS 350,000 Prior July 2016 /C/02 MIS module for SWL and non formal Actua Literacy l MCDSW Enhancement of Plan CQS 150,000 Prior Jan 2017 /C/03 MIS/SRB Actua l MCDSW Update the training Plan IC 20,000 Post March /C/04 strategy for MCDSW 2016 staff in M&E and Actua develop a strategy for l capacity development in policy analysis MCDSW Updating Operations Plan CQS 100,000 Post Dec 2015 /C/05 Manuals Actua l MCDSW Assessment of Actua CQS 100,000 Post Jul 2016 /C/06 options to identifying l beneficiaries of Plan NRCs, 11 MCDSW Inventory of existing Plan CQS 40,000 Jan 2016 /C/07 complimentary Post activities Actua l MCDSW Software design and Actua CQS 150,000 Feb March /C/08 implementation l Post Plan MCDSW TA to National Social Plan IC 40,000 Post Oct 2016 /C/10 Protection Co- Various TA Actua ordination Unit, l MCDSW Development of a Plan IC 15,000 Post Jan 2016 /C/9 strategy for good Actua practice l Sub Total Component 3 (b): 1,115,000 Consulting Services III. Training, workshops and consultations Estimated Ref. Training, workshop Estimated Expected Training/wo Duration No. and study tours Cost (US$) Date (Days) Component 1: Supporting Women’s Livelihoods(Ministry of Community Development and Social Welfare) Sub-component 1a – Adoption and Roll-out of SWL MCDSW/T/01 Training of Trainers (ToT) 2,416,000 Recurrent (July 2016; Jul workshop July 2018) MCDSW/T/02 1,172,000 Recurrent (July-Feb 2016 Training of beneficiaries in life, July-Feb 2017/8; July-Fe business and savings 2018/9) MCDSW/T/03 Training of beneficiaries in agri- 186,000 Recurrent (Sept-Feb 201 business and other sector- Sept-Feb 2017/8; Sept- specific topics 2018/9) MCDSW/T/04 Recurrent (September 20 Provision of safe space for September 2017; Septem training and follow-up meetings 375,000 2018) MCDSW/T/05 Launching and operation of GRS 735,000 Recurrent MCDSW/T/06 Launching and operation of ICT- Recurrent (August 2016, based learning tools 325,000 2017, August 2018) MCDSW/T/07 Launching and Equipment for operation of GRS 100,000 MCDSW/T/08 Launching and operation of ICT- based learning tools 125,000 12 Sub-component 1b – Building National Implementation and Monitoring Capacity MCDSW/T/009 Workshop for preparation of the March 2016 Operations Manual 20,000 MCDSW/T/010 Training of DCD staff on POM and Recurrent training curriculum 60,000 MCDSW/T/11 Training of DCD staff on Recurrent (August 2016; beneficiary enumeration and 2017; August 2018) registration 50,000 MCDSW/T/12 Training of DCD staff on Recurrent (August 2016; monitoring and reporting 50,000 2017; August 2018) MCDSW/T/13 Recurrent (March 2017; Annual review 30,000 2018; March 2019) MCDSW/T/14 Training of HQ and district staff Recurrent (April-August training prior to SWL activities 270,000 2017, 2018) MCDSW/T/15 Study tours to learn from international experience in the implementation of livelihood support programs 100,000 MCDSW/T/16 Capacity Building of SWL Staff in January 2017 Bank Procurement and regulations and implementation 150,000 Institutional Strengthening and Systems Building MCDSW/T/14 South-south exchange on social 35,000 May 2016 protection policy and implementation issues. Sub Total Training , Workshops and Capacity 6,199,000 Building Component 1 Supporting Women’s Livelihoods(Ministry of Community Development and Social Welfare Component 2. Keeping Girls in School (Ministry of Education, Science Vocational Training and Early Education Sub-component 2b - System Strengthening and Consolidation Training Plan for MGE to implement the Keeping Girls in MGE /T/01 School initiative 40,000 March 2016 to May 2016 MGE /T/02 Training of staff as per the training plan 135,000 Feb 2017 MGE /T/03 Training of the primary users of the Keeping Girls in School Information System Module 25,000 Dec 2015 MGE /T/04 Workshops and consultations for the action plan. 20,000 Feb 2017 MGE /T/05 South-south exchange on Keeping Girls in School initiative. 70,000 Dec 2016 MGE /T/06 Sharing of lessons learned between district officers 124,000 June 2016 – Sept 2020 Sub Total Training , Workshops and Capacity 414,000 Building Component 2 13 Subcomponent 2c: - System Strengthening for MCDSW to support Keeping Girls in School Initiative MCDSW/T/15 Trainers of Trainers workshop 100,000 November 2015 for District Social Welfare Officers to train officers in the implementation of the Project MCDSW/T/16 Awareness raising and 25,000 November – December 2 sensitization of Community onwards Welfare Assistance Committees (CWACs) MCDSW/T/17 Conduct inception visits to 65,000 December 2015 respective Districts and communities for programme buy-in particularly from traditional leaders, District Government officials and other stake holders. MCDSW/T/18 Hold a workshop to develop 10,000 November 2015 protocols for the implementation of the programme MCDSW/T/19 Verification of Girls on the list 70,000 December 2015 (Headcount) both in communities and villages. MCDSW/T/20 Quality Assurance, Monitoring 130,000 March 2016 onwards and mentoring of girls in school MCDSW/T/21 Follow up on girls in school 100,000 January 2016 by the CWACs, Districts, Provincial offices and Headquarters. MCDSW/T/22 Monitoring and supervision of 171,250 March 2016 follow up outcomes by the districts, provincial offices and Headquarters MCDSW/T/23 Hold community validation 71,250 December 2015 meetings to provide feedback on enlisted girls Sub Total Subcomponent 2c 742,500 System Strengthening for MCDSW to support Keeping Girls in School Initiative Component 3 a). Institutional Strengthening and Systems: (Ministry of Gender ) MOG /T/01 Training of the primary users 50,000 Sept 2016 – March 2 of the monitoring and evaluation system in MOG MOG /T/02 Competency-based training 70,000 in co-ordination skills, gender analysis and gender mainstreaming June 2016 – Dec 20 MOG /T/03 Learning exchange on 70,000 empowerment programs March 2016 – May 2 14 MOG /T/04 Short-course local training of 4,000 staff in Project Management- 4 Staff Jan 2016 – June 20 MOG /T/05 Regional staff training in 28,000 impact evaluation • Master of Arts in Economic Policy Management – 2 Staff • Advanced M & E; Integrating Planning, Implementation, Budgeting, M&E-2 Staff • Project Management – 3 Staff Jan 2016 – Dec 20 MOG /T/06 Training of at least 10 district 65,000 gender sub-committees per province in all 10 provinces in national provincial centres Jan 2016- Dec 201 MOG/T/07 Competency-based training 20,000 in Women Economic Entrepreneurship skills Nov - Dec 2016 Sub Total Training , Workshops and Capacity 327,000 Building Component 3(a) Component 3 a). Institutional Strengthening and Systems: (Ministry of Community Development ) MCDSW/T/01 Training and support for 90,000 Jun 2016 – Dec 2019 capacity development in line with training strategy for senior, middle-level and operational staff in MCDSW MCDSW/T/02 Training of the primary users 10,000 May 2017 – Aug 2017 of the unique identification solution Sub Total Training , Workshops and Capacity Building Component 3(a) 100,000 GENERAL NOTES 1. Training and capacity building: The institutions charged with implementation responsibility for the componentswill identify the total cost of required training and prepare and submit to the Bank, for its prior review, a detailed training program. The training program will, inter alia, identify: (i) the training envisaged; (ii) the justification for the training, how it will lead to effective performance and implementation of the project (iii) the personnel to be trained; (iv) the selection methods of institutions or individuals conducting such training; (v) the institutions which will conduct training, if already selected; (vi) the duration of proposed training; and (vii) the cost estimate or specified cost of the training. 15 Preparation and submission of a report, including to the Bank by the trainee upon completion of training would be mandatory. 2. Operating costs: For this project, the Bank has agreed with the implementing agencies of the various components that the procurement methods for works, goods and non-consulting services as described in the Procurement Guidelines do not have to be followed for payments made for operating costs arising from the implementation of the project. Instead, the Bank has assessed the Governments and other implementing agency own procurement and administrative procedures for these expenditures (during appraisal) and agrees that these procedures are adequate for procuring items for operating costs. The operating costs constitute recurrent costs (excluding purchase of motor vehicles, computers etc.) and typically include equipment rental and maintenance, vehicle operating costs, maintenance and repair, office rental and maintenance, office materials and supplies, utility costs (including electricity, water and gas) communications (including telephone and internet charges) equipment rent, operation and maintenance and cost of banking services (bank charges), travel cost and transport of the staff associated with project implementation. The Project Appraisal Document (PAD) and the Financing Agreement (FA) will include a list of the eligible items to be covered under the project. These items will be procured using the implementing Government agency’s administrative procedures, which have been reviewed and found acceptable to the Bank. Contracts for these items should not be included in the procurement plan. 16 PROCUREMENT Zambia : Girls Education and Womens Empowerment and Livelihood Project PLAN General Information Country: Zambia Bank’s Approval Date of the Original Procurement Plan: 2016-11-18 2021-04-28 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P151451 GPN Date: Project Name: Girls Education and Womens Empowerment and Livelihood Project Loan / Credit No: IDA / 56580, IDA / 65690 Ministry of Community Development and Social Welfare Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Pending MCDSW/W/002 / Support to Supporting Women's Request for Single Stage - One 2017-07- IDA / 56580 Post Open - National 70,000.00 0.00 Implementat 2016-08-20 2017-01-20 Office Refurbishment Livelihoods Quotations Envelope 19 ion Pending MCDSW/W/001 / Office Supporting Women's Request for Single Stage - One 2017-06- IDA / 56580 Post Open - National 45,000.00 0.00 Implementat 2016-10-14 2016-12-09 Refurbishment Livelihoods Quotations Envelope 07 ion GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Pending MCDSW/NCS/005 / Purchase Supporting Women's Request for Single Stage - One IDA / 56580 Post Open - National 16,000.00 0.00 Implementati 2016-11-21 2017-01-16 2017-07-15 of Bicyles Livelihoods Quotations Envelope on Pending MCDSW/NCS/006 / Purchase Supporting Women's Request for Single Stage - One IDA / 56580 Post Open - National 41,000.00 0.00 Implementati 2015-11-12 2016-01-07 2016-07-05 of Boats Livelihoods Quotations Envelope on MCDSW/NCS/007 / Purchase Pending of various office furniture and Supporting Women's Request for Single Stage - One IDA / 56580 Post Open - National 100,000.00 0.00 Implementati 2016-03-14 2016-05-09 2016-11-05 equipment for HQ and Livelihoods Quotations Envelope on Districts MCDSW/NCS/009 / Supporting Women's Single Stage - One Launching and Equipment for IDA / 56580 Post Request for Bids Open - National 535,000.00 0.00 Canceled 2016-04-04 2016-04-09 2016-05-21 2016-06-20 2016-12-07 2017-06-05 Livelihoods Envelope Operation of GRS MCDSW/NCS/010 / Pending Supporting Women's Single Stage - One Equipment for ICT based IDA / 56580 Post Request for Bids Open - National 200,000.00 0.00 Implementati 2017-01-25 2017-01-30 2017-03-13 2017-04-12 2017-05-17 2017-11-13 Livelihoods Envelope learning tools on MCDSW/NCS/011 / Development of software and database for real-time Supporting Women's Single Stage - One IDA / 56580 Post Request for Bids Open - National 120,000.00 0.00 Canceled 2017-06-05 2017-06-10 2017-07-22 2017-08-21 2017-09-25 2018-03-24 registration of SWL Livelihoods Envelope beneficiaries and monitoring of activities MCDSW/G/01 / IT Infrastructure for Information Supporting Women's Single Stage - Two IDA / 56580 Post Request for Bids Open - National 400,000.00 0.00 Canceled 2015-12-09 2015-12-14 2016-01-25 2016-04-08 2016-05-13 2016-11-09 system for MCDSW business Livelihoods Envelope at various levels MCDSW/G/02 / Hardware Supporting Women's Single Stage - One and Software for unique IDA / 56580 Post Request for Bids Open - National 150,000.00 0.00 Canceled 2017-01-03 2017-01-08 2017-02-19 2017-03-21 2017-04-25 2017-10-22 Livelihoods Envelope identification solution MCDSW/G/03 / Procurement Pending Supporting Women's Request for Single Stage - One of devices for field and IDA / 56580 Post Open - National 60,000.00 0.00 Implementati 2016-05-14 2016-07-09 2017-01-05 Livelihoods Quotations Envelope identification of beneficiaries on MCDSW/G/04 / Purchase of Pending Supporting Women's Request for Single Stage - One Office furniture and IDA / 56580 Post Open - National 100,000.00 0.00 Implementati 2016-07-13 2016-09-07 2017-03-06 Livelihoods Quotations Envelope equipment on MCDSW/G/05 / Purchase of Pending Motor Vehicles for National Supporting Women's Request for Single Stage - One IDA / 56580 Post Open - National 150,000.00 0.00 Implementati 2016-07-20 2016-09-14 2017-03-13 Social Protection Co- Livelihoods Quotations Envelope on ordination Unit Pending MCDSW/NCS/004 / Purchase Supporting Women's Single Stage - One IDA / 56580 Post Request for Bids Open - National 230,000.00 0.00 Implementati 2016-04-15 2016-04-20 2016-06-01 2016-07-01 2016-12-07 2017-06-05 of Motor Bikes Livelihoods Envelope on MCDSW/NCS/008 / Purchase of Pending Supporting Women's Single Stage - One Computers,Laptops,Scanners, IDA / 56580 Post Request for Bids Open - National 281,300.00 0.00 Implementati 2016-07-09 2016-07-14 2016-08-25 2016-09-24 2016-12-07 2017-06-05 Livelihoods Envelope Printers,Projectors,Cameras,U on PS Pending MCDSW/NCS/002 / Purchase Supporting Women's Single Stage - One IDA / 56580 Post Request for Bids Open - National 1,255,000.00 0.00 Implementati 2016-04-14 2016-04-19 2016-05-31 2016-06-30 2016-12-06 2017-06-04 of Motor Vehicles Livelihoods Envelope on Pending MCDSW/NCS/003 / Purchase Supporting Women's UN Agencies IDA / 56580 Post Direct 300,000.00 0.00 Implementati 2016-11-15 2016-11-15 2016-11-15 2016-11-15 of Motor Vehicles Livelihoods (Direct) on MCDSS/NCS/004 / Pending Supporting Women's Single Stage - One Procurement of Mobile Phones IDA / 56580 Post Request for Bids Open - National 180,000.00 0.00 Implementati 2017-07-22 2017-07-27 2017-08-24 2017-08-31 2017-09-21 2018-03-20 Livelihoods Envelope for SWL beneficiaries on MCDSS/NCS/18 / Supporting Women's Request for Single Stage - One Procurement of T Shirts for IDA / 56580 Post Limited 9,000.00 0.00 Canceled 2017-11-29 2018-01-24 2018-07-23 Livelihoods Quotations Envelope CBVs Page 1 MCDSS/NCS/020/17 / Supporting Women's Request for Single Stage - One Procurement of Gum Boots for IDA / 56580 Post Limited 3,000.00 7,736.57 Completed 2017-11-29 2017-11-17 2018-01-24 2018-01-03 2018-07-23 2018-01-08 Livelihoods Quotations Envelope Community Based Volunteers MCDSS/NCS/022/17 / Supporting Women's Request for Single Stage - One Procurement of Helmets for IDA / 56580 Post Limited 16,000.00 15,670.96 Completed 2017-11-29 2017-12-14 2018-01-24 2018-02-26 2018-07-23 2018-03-07 Livelihoods Quotations Envelope motorcycles MCDSS/NCS/023/17 / Supporting Women's Request for Single Stage - One Procurement of Rain Coats for IDA / 56580 Post Limited 12,000.00 23,326.35 Completed 2017-11-29 2017-12-01 2018-01-24 2017-12-27 2018-07-23 2018-01-12 Livelihoods Quotations Envelope Community Based Volunteers MCDSS/NCS/024/17 / Supporting Women's Request for Single Stage - One Procurement of Umbrellas for IDA / 56580 Post Limited 18,000.00 23,326.35 Completed 2017-11-29 2017-10-25 2018-01-24 2017-11-30 2018-07-23 2018-01-05 Livelihoods Quotations Envelope CBVs MCDSS/NCS/025/17 / Supporting Women's Request for Single Stage - One Procurement of two small IDA / 56580 Post Limited 75,000.00 0.00 Canceled 2017-12-06 2018-01-31 2018-07-30 Livelihoods Quotations Envelope boats for Lunga MCDSS/NCS/027/17 / Procurement of Executive T Supporting Women's Request for Single Stage - One Shirts and Shirts for SWL and IDA / 56580 Post Limited 7,500.00 4,137.08 Completed 2017-12-06 2017-11-27 2018-01-31 2017-12-27 2018-07-30 2018-02-13 Livelihoods Quotations Envelope DPI staff and Pop up banner for SRB official Launch MCDSS/NCS/028/17 / Procurement of Vehicle Supporting Women's Request for Single Stage - One Carriers, Bull Bars for DPI and IDA / 56580 Post Limited 10,000.00 0.00 Canceled 2017-12-06 2018-01-31 2018-07-30 Livelihoods Quotations Envelope Canopies for SWL Project Vehicle MCDSS/NCS/029/17 / Pending Institutional Strengthening Request for Single Stage - One Procurement of three motor IDA / 56580 Post Limited 150,000.00 0.00 Implementati 2017-12-06 2018-01-31 2018-07-30 and Systems Building Quotations Envelope vehicles for ISSB on MCDSS/NCS/030 / Procurement of Internet Institutional Strengthening Request for Single Stage - One IDA / 56580 Post Limited 8,000.00 0.00 Canceled 2017-12-06 2018-01-31 2018-07-30 Accessories for Phase 1 and Systems Building Quotations Envelope Districts for DPI MCDSS/NCS/031/17 / Supporting Women's Request for Single Stage - One IDA / 56580 Post Limited 1,200.00 0.00 Canceled 2017-12-06 2018-01-31 2018-07-30 Procurement of Life Jackets Livelihoods Quotations Envelope MCDSS/NCS/032 / Procurement of Computer Laptops and Printers for Supporting Women's Request for Single Stage - One IDA / 56580 Post Limited 8,200.00 7,728.07 Completed 2017-11-29 2017-11-30 2018-01-24 2018-02-19 2018-07-23 2018-01-12 Procurement Specialist, Livelihoods Quotations Envelope Logistics Officer and Project Officer MCDSS/NCS/034 / Supporting Women's Request for Single Stage - One Procurement of bicycles for IDA / 56580 Post Limited 9,500.00 8,769.19 Completed 2017-12-06 2017-11-14 2018-01-31 2017-12-18 2018-07-30 2018-01-12 Livelihoods Quotations Envelope CDAs MCDSS/NCS/36/17 / Supporting Women's Request for Single Stage - One Procurement of an 82 IDA / 56580 Post Limited 42,000.00 0.00 Canceled 2017-12-06 2018-01-31 2018-07-30 Livelihoods Quotations Envelope Computer Tablets MCDSS/NCS/37/17 / Institutional Strengthening Request for Single Stage - One Procurement of ten computers IDA / 56580 Post Limited 14,000.00 0.00 Canceled 2017-12-06 2018-01-31 2018-07-30 and Systems Building Quotations Envelope and two printers MCDSS/NCS/38/17 / Pending Supporting Women's Request for Single Stage - One Procurement of Mobile Phones IDA / 56580 Post Limited 7,000.00 0.00 Implementati 2017-12-06 2018-01-31 2018-07-30 Livelihoods Quotations Envelope for CBVs on MCDSW/SWL/010/18 / PROCUREMENT OF MOBILE PHONES FOR BENEFICIARIES Supporting Women's Single Stage - One IDA / 56580 Post Request for Bids Limited 325,000.00 234,232.64 Completed 2018-06-10 2018-06-12 2018-06-15 2018-08-27 2018-07-27 2018-09-05 2018-08-26 2018-09-28 2018-09-30 2018-11-09 2019-03-29 2018-12-11 FOR PHASE TWO FOR THE Livelihoods Envelope SUPPORING WOMENS LIVELIHOODS . ZM-MCDSW-65762-GO-RFQ / PROCUREMENT OF 86 COMPUTER TABLETS, 27 COMPUTER LAPTOPS, Supporting Women's Request for Single Stage - One IDA / 56580 Post Limited 71,500.00 32,557.66 Completed 2018-06-12 2018-04-20 2018-08-07 2018-06-04 2019-02-03 2018-07-04 INTERNET SECURITY (99 Livelihoods Quotations Envelope LICENCES) AND 86 SOLAR CHARGER POWER BANKS FOR DATA COLLECTION MCDSS/SWL/004/18 / PROCUREMENT OF FURNITURE Supporting Women's Request for Single Stage - One IDA / 56580 Post Limited 45,000.00 30,941.48 Completed 2018-06-18 2018-06-18 2018-08-13 2018-08-03 2019-02-09 2018-08-14 FOR THE THIRTY (30) SWL Livelihoods Quotations Envelope IMPLEMENTING DISTRICTS MCDSS/SWL/005/18 / PROCUREMENT OF IT EQUIPMENT (23 DESKTOPS, 23 Supporting Women's Request for Single Stage - One IDA / 56580 Post Limited 62,000.00 53,751.65 Signed 2018-06-20 2018-08-23 2018-08-15 2018-10-19 2019-02-11 2018-12-28 PRINTERS AND MICROSOFT Livelihoods Quotations Envelope OFFICE LICENCES (66 LICENCES) ) MCDSS/SWL/006/18 / PROCUREMENT OF CANOPIES Supporting Women's Request for Single Stage - One IDA / 56580 Post Limited 18,000.00 12,609.97 Signed 2018-06-20 2018-07-26 2018-08-15 2018-08-03 2019-02-11 FOR THE SWL PROJECT Livelihoods Quotations Envelope VEHICLES MCDSS/SWL/007/18 / PROCUREMENT OF TWO Supporting Women's Request for Single Stage - One IDA / 56580 Post Limited 24,000.00 0.00 Canceled 2018-07-11 2018-09-05 2019-03-04 SMALL BOATS FOR LUNGA Livelihoods Quotations Envelope DISTRICTS FOR THE CHANNELS MCDSS/SWL/008/18 / PROCUREMENT OF SIXTY (60) MOTOR BIKES FOR THE Supporting Women's Request for Single Stage - One IDA / 56580 Post Limited 294,000.00 0.00 Canceled 2018-06-16 2018-08-11 2019-02-07 COMMUNITY DEVELOPMENT Livelihoods Quotations Envelope ASSISTANTS (CDA) FOR THE SWL PHASE II DISTRICTS Page 2 MCDSS/SWL/009/18 / Procurement of 1050 Bicycles Supporting Women's Request for Single Stage - One IDA / 56580 Post Limited 99,800.00 79,832.64 Completed 2018-06-20 2018-04-30 2018-08-15 2018-08-03 2019-02-11 2018-12-05 for Community based Livelihoods Quotations Envelope Volunteers (CBVS) MCDSS/SWL/011/18 / PROCUREMENT OF SIM CARDS Supporting Women's Request for Single Stage - One IDA / 56580 Post Limited 13,000.00 18,577.40 Signed 2018-07-11 2018-11-02 2018-09-05 2018-08-03 2019-03-04 AND AIRTIME FOR SWL PHASE Livelihoods Quotations Envelope II BENEFICIARIES MCDSS/SWL/012/81 / Procurement of Umbrellas and Supporting Women's Request for Single Stage - One IDA / 56580 Post Limited 59,000.00 48,472.81 Completed 2018-07-11 2018-09-13 2018-09-05 2018-09-24 2019-03-04 2018-10-30 Branded T Shirts for CDAs and Livelihoods Quotations Envelope CBVs MCDSS/SWL/013/18 / Procurement of Rain Coats Supporting Women's Request for Single Stage - One IDA / 56580 Post Limited 95,000.00 53,087.87 Completed 2018-08-08 2018-09-07 2018-10-03 2018-09-24 2019-04-01 2018-10-19 and Gum Boots for CDAs and Livelihoods Quotations Envelope CBVS MCDSS/SWL/014/18 / Procurement of 300 Branded Supporting Women's Request for Single Stage - One Diaries, 300 Branded IDA / 56580 Post Limited 30,000.00 0.00 Canceled 2018-07-11 2018-09-05 2019-03-04 Livelihoods Quotations Envelope Organizers and 300 Calendars for 2019 MCDSS/SWL/015/18 / Procurement of Ten (10) 13 Supporting Women's UN Agencies Seaters Toyota Landcruiser IDA / 56580 Post Direct 400,000.00 329,171.96 Signed 2018-06-15 2018-10-11 2018-06-20 2018-12-17 2018-07-25 2019-02-14 2019-01-21 Livelihoods (Direct) Motor Vehicles for SWL Phase Three Districts MCDSS/SWL/016/18 / Procurement of a Motor Supporting Women's Request for Single Stage - One IDA / 56580 Post Limited 45,000.00 33,260.78 Completed 2018-06-20 2018-06-18 2018-08-15 2018-08-03 2019-02-11 2018-09-18 Vehicle for Procurement and Livelihoods Quotations Envelope Logistics MCDSS/SWL/006/19 / Supporting Women's Request for Single Stage - One Procurement of forty (40) IDA / 56580 Post Limited 230,000.00 215,800.00 Signed 2019-02-23 2019-02-27 2019-04-20 2019-07-26 2019-10-17 Livelihoods Quotations Envelope Motor - Bikes for CDAs MCDSS/003/19 / Procurement of 42,127 Mobile Supporting Women's Single Stage - One IDA / 56580 Post Request for Bids Limited 632,000.00 0.00 Canceled 2019-03-11 2019-03-16 2019-04-27 2019-05-27 2019-07-01 2019-12-28 Phones for SWL Phase 3 Livelihoods Envelope Beneficiaries MCDSS/SWL/004/19 / Supporting Women's Request for Single Stage - One Procurement of networking IDA / 56580 Post Limited 38,000.00 0.00 Canceled 2019-03-09 2019-05-04 2019-10-31 Livelihoods Quotations Envelope tools for SWL MCDSS/SWL/001/19 / Procurement of Data Supporting Women's Request for Single Stage - One Collection Tools (Tablets and IDA / 56580 Post Limited 54,000.00 34,183.79 Completed 2019-04-17 2019-04-24 2019-06-12 2019-07-23 2019-12-09 2020-01-20 Livelihoods Quotations Envelope Solar Chargers) for the SWL Phase 3 activities MCDSS/SWL/005/19 / Procurement of 20 Desktop Computers, 20 Computer Supporting Women's Request for Single Stage - One IDA / 56580 Post Limited 72,000.00 22,052.65 Completed 2019-04-17 2019-04-24 2019-06-12 2019-08-19 2019-12-09 2019-09-02 Laptops and 20 Printers for Livelihoods Quotations Envelope SWL Phase 3 Implementing Districts MCDSS/SWL/003/19 / Supply Supporting Women's Single Stage - One and Delivery of 42,127 mobile IDA / 56580 Post Request for Bids Limited 632,000.00 475,188.71 Completed 2019-08-09 2019-07-29 2019-08-14 2019-08-01 2019-09-25 2019-08-16 2019-10-25 2019-08-27 2019-11-29 2019-09-18 2020-05-27 2019-12-13 Livelihoods Envelope Phones for Phase Three MCDSS/SWL/011/19 / Supporting Women's Request for Single Stage - One IDA / 56580 Post Limited 98,700.00 71,603.84 Completed 2019-10-09 2019-10-03 2019-12-04 2020-01-30 2020-06-01 2020-05-26 Procurement of 1050 Bicycles Livelihoods Quotations Envelope MCDSS/SWL/012/19 / Supporting Women's Request for Single Stage - One Procurement of a Double Cab IDA / 56580 Post Limited 45,000.00 0.00 Canceled 2019-10-25 2019-12-20 2020-06-17 Livelihoods Quotations Envelope 4 x 4 Motor Vehicle MCDSS/ISSB//013/19 / Procurement of 710 mobile Institutional Strengthening Request for Single Stage - One IDA / 56580 Post Limited 98,500.00 71,933.18 Signed 2019-11-22 2019-11-01 2020-01-17 2019-10-15 2020-07-15 phones for the ZISPIS Pilot and Systems Building Quotations Envelope Program MCDSS/ISSB/014/19 / Procurement of Seventeen Institutional Strengthening Request for Single Stage - One IDA / 56580 Post Limited 20,000.00 15,282.46 Completed 2019-11-22 2019-11-01 2020-01-17 2019-11-15 2020-07-15 2019-11-20 (17) Tablet Computers for the and Systems Building Quotations Envelope ZISPIS Pilot Program ZM-MCDSW-166581-GO-DIR Pending / Procurement of Routers , Supporting Women's Request for Single Stage - One IDA / 56580 Post Limited 12,000.00 0.00 Implementati 2020-04-04 2020-05-30 2020-11-26 Talk Time and internet Livelihoods Quotations Envelope on subscription for SWL Officers MCDSS/SWL/002/2020 / Procurement of Various Supporting Women's Request for Single Stage - One COVID 19 Materials (face IDA / 56580 Post Limited 33,837.83 28,943.29 Completed 2020-08-19 2020-08-14 2020-10-14 2020-09-14 2021-04-12 2020-09-17 Livelihoods Quotations Envelope masks, soaps and hand sanitizers) ZM-MCDSW-180338-GO- RFQ / Procurement of 10 Institutional Strengthening Request for Single Stage - One IDA / 56580 Post Limited 9,000.00 0.00 Canceled 2020-08-19 2020-10-14 2021-04-12 Computer Laptops for various and Systems Building Quotations Envelope ministry staff ZM-MCDSW-188206-GO- RFQ / Procurement of Motor Supporting Women's Request for Single Stage - One IDA / 56580 Post Limited 40,000.00 34,811.38 Signed 2020-08-26 2020-09-03 2020-10-21 2020-09-14 2021-04-19 Vehicle for the SWL Project Livelihoods Quotations Envelope office MCDSS/003/19-2 / Supporting Women's Request for Single Stage - One Procurement of Various ICT IDA / 56580 Post Limited 13,500.00 11,321.00 Completed 2020-08-22 2020-06-01 2020-10-17 2020-07-17 2021-04-15 2020-08-12 Livelihoods Quotations Envelope Equipment Page 3 MCDSS/004/20 / Supporting Women's Request for Single Stage - One Procurement of additional IDA / 56580 Post Limited 19,000.00 16,209.73 Completed 2020-09-09 2020-09-09 2020-11-04 2020-09-23 2021-05-03 2020-09-28 Livelihoods Quotations Envelope 1900 mobile phones for CBVS MCDSS/SWL/005/20 / Supporting Women's Request for Single Stage - One Procurement of additional 980 IDA / 56580 Post Limited 99,690.00 83,340.21 Signed 2020-09-09 2020-09-03 2020-11-04 2020-09-23 2021-05-03 Livelihoods Quotations Envelope bicycles for CBVS MCDSS/SWL/007/20 / Supporting Women's Request for Single Stage - One Procurement of Rain suits for IDA / 56580 Post Limited 32,000.00 24,663.30 Completed 2020-09-16 2020-09-03 2020-11-11 2020-09-23 2021-05-10 2020-09-25 Livelihoods Quotations Envelope CBVs MCDSS/SWL/010/20 / Supporting Women's Request for Single Stage - One Procurement of 3 IDA / 56580 Post Limited 1,946.00 1,800.71 Completed 2020-09-05 2020-09-08 2020-10-31 2020-09-17 2021-04-29 2020-09-23 Livelihoods Quotations Envelope Multifunctional Printers MCDSS/SWL/011/20 / Procurement of 300 Supporting Women's Request for Single Stage - One Calendars, 250 Diaries and IDA / 56580 Post Limited 15,500.00 11,881.28 Completed 2020-09-16 2020-09-07 2020-11-11 2020-09-23 2021-05-10 2020-12-10 Livelihoods Quotations Envelope 250 Organizers for the 2021 calendar year MCDSS/SWL/012/20 / Procurement of 17 Laptop Supporting Women's Request for Single Stage - One IDA / 56580 Post Limited 68,647.06 57,673.57 Completed 2020-10-21 2020-11-24 2020-12-16 2021-01-20 2021-06-14 2021-01-22 Computers and 180 Tablet Livelihoods Quotations Envelope Computers for the SWL MCDSS/SCT/001/20 / Request for Single Stage - One Procurement of various COVID IDA / 65690 Keeping Girls in School Post Limited 40,000.00 31,664.02 Completed 2020-10-28 2020-10-12 2020-12-23 2020-11-03 2021-06-21 2020-11-04 Quotations Envelope 19 materials MCDSS/SCT/004/20 / Pending Procurement of 7,800 Single Stage - One IDA / 65690 Keeping Girls in School Post Request for Bids Limited 200,000.00 0.00 Implementati 2020-10-30 2020-11-04 2020-12-16 2021-01-15 2021-02-19 2021-08-18 Grievance Mechanism Redress Envelope on Boxes MCDSS/SWL/016/2020 / Supporting Women's Single Stage - One Procurement of 1145 bicycles IDA / 65690 Post Request for Bids Limited 127,970.59 119,562.97 Signed 2020-11-20 2020-12-14 2020-11-25 2020-12-17 2021-01-06 2020-12-24 2021-02-05 2021-01-13 2021-03-12 2021-02-09 2021-09-08 Livelihoods Envelope for Phase 4 CBVs MCDSS/SWL/015/20 / Procurement of various ICT Supporting Women's Request for Single Stage - One IDA / 65690 Post Limited 34,428.24 27,628.70 Completed 2020-11-25 2020-11-18 2021-01-20 2020-12-15 2021-07-19 2021-01-28 equipment for SWL Phase 4 Livelihoods Quotations Envelope activities MCDSS/SCT/003/20 / Pending Request for Single Stage - One Procurement of Various ICT IDA / 65690 Keeping Girls in School Post Limited 135,000.00 0.00 Implementati 2020-12-02 2021-01-27 2021-07-26 Quotations Envelope equipment for ZISPIS on MCDSS/SCT/014/20 / Pending Procurement of additional Request for Single Stage - One IDA / 65690 Keeping Girls in School Post Limited 72,000.00 0.00 Implementati 2020-12-23 2021-02-17 2021-08-16 Covid -19 materials for SCT Quotations Envelope on Districts MCDSS/SCT/015/20 / Pending Procurement of 1,800 rain Request for Single Stage - One IDA / 65690 Keeping Girls in School Post Limited 86,000.00 0.00 Implementati 2020-12-23 2021-02-17 2021-08-16 suits, 1,800 umbrellas Quotations Envelope on and1,800 gumboots MCDSS/SWL/018/20 / Supporting Women's Request for Single Stage - One Procurement of Office IDA / 65690 Post Limited 7,800.00 9,270.90 Completed 2020-12-23 2020-12-09 2021-02-17 2020-12-15 2021-08-16 2020-12-16 Livelihoods Quotations Envelope Furniture MCDSS/SWL/014/2020 / Supporting Women's Request for Single Stage - One Procurement of 1,145 IDA / 65690 Post Limited 15,154.41 11,486.55 Completed 2020-12-29 2021-01-07 2021-02-23 2021-01-27 2021-08-22 2021-02-08 Livelihoods Quotations Envelope Branded Umbrellas MCDSS/SWL/004/21 / Pending Supporting Women's Request for Single Stage - One Procurement of COVID 19 IDA / 65690 Post Limited 25,000.00 0.00 Implementati 2021-03-03 2021-04-28 2021-10-25 Livelihoods Quotations Envelope materials on MCDSS/SWL/005/21 / Pending Procurement of 10,012 Supporting Women's Request for Single Stage - One IDA / 65690 Post Limited 99,750.00 0.00 Implementati 2021-03-02 2021-04-27 2021-10-24 Complaint form books and Livelihoods Quotations Envelope on 110 Manuals MCDSS/SWL/007/21 / Pending Supporting Women's Request for Single Stage - One Procurement of 1,000 mobile IDA / 65690 Post Limited 90,000.00 0.00 Implementati 2021-03-03 2021-04-28 2021-10-25 Livelihoods Quotations Envelope phones on MCDSS/SWL002/21 / Under Supporting Women's UN Agencies Procurement of Twelve (12) IDA / 65690 Prior Direct 550,000.00 0.00 Implementati 2021-02-26 2021-02-11 2021-03-03 2021-04-07 2021-10-04 Livelihoods (Direct) Landcruiser Motor vehicles on MCDSS/SWL/003/21 / Pending Supporting Women's Single Stage - One Procurement of 30 Motor IDA / 65690 Post Request for Bids Open - National 195,000.00 0.00 Implementati 2021-02-26 2021-03-03 2021-04-14 2021-05-14 2021-06-18 2021-12-15 Livelihoods Envelope Bikes for SWL on MCDSS/SWL/008/21 / Pending Supporting Women's Single Stage - One Procurement of 23, 017 IDA / 65690 Post Request for Bids Open - National 211,537.19 0.00 Implementati 2021-03-12 2021-03-17 2021-04-28 2021-05-28 2021-07-02 2021-12-29 Livelihoods Envelope Mobile Phones on Pending MCDSS/SWL/009/21 / Supporting Women's Request for Single Stage - One IDA / 65690 Post Limited 11,500.00 0.00 Implementati 2021-03-17 2021-05-12 2021-11-08 Procurement of sim cards Livelihoods Quotations Envelope on MCDSS/SWL/010/21 / Pending Supporting Women's Request for Single Stage - One Procurement of 150 boxes IDA / 65690 Post Limited 10,000.00 0.00 Implementati 2021-03-24 2021-05-19 2021-11-15 Livelihoods Quotations Envelope and CBT manuals English on version MCDSS/SWL/012/21 / Pending procurement of pull banners, Supporting Women's Request for Single Stage - One IDA / 65690 Post Limited 6,000.00 0.00 Implementati 2021-05-19 2021-07-14 2022-01-10 branded shirts, golf shirts and Livelihoods Quotations Envelope on caps NON CONSULTING SERVICES Page 4 Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MCDSW/NCS/001 / Printing Pending Supporting Women's Single Stage - One of teaching and learning IDA / 56580 Post Request for Bids Open - National 448,300.00 0.00 Implementati 2017-01-25 2017-01-30 2017-03-13 2017-04-12 2017-05-17 2017-11-13 Livelihoods Envelope materials on MCDSS/SWL/003/18 / PRINTING OF LIFE SKILSS, Supporting Women's Request for Single Stage - One BUSINESS SKILLS AND IDA / 56580 Post Limited 52,000.00 3,352,422.08 Completed 2018-06-12 2018-04-02 2018-08-07 2018-06-04 2019-02-03 2018-07-04 Livelihoods Quotations Envelope REFRESHER TRAINING MATERIALS MCDSS/SWL/002/18 / Supporting Women's Request for Single Stage - One PRINTING OF VARIOUS IEC IDA / 56580 Post Limited 20,000.00 0.00 Canceled 2018-06-12 2018-08-07 2019-02-03 Livelihoods Quotations Envelope MATERIALS MCDSS/002/19 / Printing of Life Skills, Business Skills and Supporting Women's Request for Single Stage - One IDA / 56580 Post Limited 72,000.00 0.00 Canceled 2019-03-16 2019-05-11 2019-11-07 Refresher Training Materials Livelihoods Quotations Envelope for Phase 3 MCDSS/SWL/007/19 / Design and Printing of ICE Materials Supporting Women's Request for Single Stage - One IDA / 56580 Post Limited 15,000.00 10,541.55 Completed 2019-04-13 2019-02-18 2019-06-08 2019-03-04 2019-12-05 2019-03-15 (Brochures, Posters and Livelihoods Quotations Envelope Factsheets) MCDSS/002/19-2 / Tender for the Printing of Life Skills, Supporting Women's Request for Single Stage - One IDA / 56580 Post Limited 72,000.00 55,901.94 Completed 2019-05-29 2019-05-09 2019-07-24 2019-07-25 2020-01-20 2019-09-02 Business Skills and Refresher Livelihoods Quotations Envelope Course Training Materials MCDSS/SWL/015/19 / Design, Printing and Supply of Supporting Women's GRM Manuals, Complaint IDA / 56580 Prior Direct Selection Direct 150,000.00 0.00 Canceled 2019-11-24 2019-11-29 2020-01-03 2020-07-01 Livelihoods Forms and A! Illustration Posters MCDSS/SWL/016/19 / Supporting Women's Request for Single Stage - One Design, Printing and Supply of IDA / 56580 Post Limited 82,000.00 33,448.94 Completed 2019-11-30 2019-11-11 2020-01-25 2020-01-30 2020-07-23 2020-03-27 Livelihoods Quotations Envelope GRM Brochures and Fliers MCDSS/SWL/001/20 / Printing of 7,312 Complaint Supporting Women's Single Stage - One IDA / 56580 Post Request for Bids Limited 118,572.97 80,323.94 Completed 2020-08-21 2020-08-12 2020-08-26 2020-08-14 2020-10-07 2020-08-21 2020-11-06 2020-08-31 2020-12-11 2020-09-14 2021-06-09 2020-09-17 form Books for the Grievance Livelihoods Envelope Redress Mechanism (GRM) MCDSS/SWL/013/2020 / Printing of 5,784 Life Skills, Supporting Women's Request for Single Stage - One IDA / 56580 Post Limited 44,117.65 40,438.72 Completed 2020-10-21 2020-11-10 2020-12-16 2020-12-18 2021-06-14 2020-12-28 Business Skills and Refresher Livelihoods Quotations Envelope course training materials MCDSS/SWL/017/20 / Supporting Women's Request for Single Stage - One Printing for IEC Materials for IDA / 65690 Post Limited 24,390.24 22,760.28 Completed 2020-12-23 2020-12-09 2021-02-17 2021-01-27 2021-08-16 2021-02-04 Livelihoods Quotations Envelope Phase 4 activities MDSS/SWL/019/20 / Printing and Delivery of 2407 CBT Supporting Women's Request for Single Stage - One IDA / 65690 Post Limited 39,000.00 72,353.37 Completed 2021-01-05 2021-01-07 2021-03-02 2021-01-27 2021-08-29 2021-02-06 manuals and 1928 Picture Livelihoods Quotations Envelope Books MCDSS/SWL/001/21 / Pending Procurement of services for Supporting Women's Request for Single Stage - One IDA / 65690 Post Limited 34,000.00 0.00 Implementati 2021-02-03 2021-03-31 2021-09-27 the translation of training Livelihoods Quotations Envelope on materials MCDSS/SWL/006/21 / Design Pending and printing of IEC materials Supporting Women's Request for Single Stage - One IDA / 65690 Post Limited 65,600.00 0.00 Implementati 2021-03-03 2021-04-28 2021-10-25 for savings, payments and Livelihoods Quotations Envelope on GRM MCDSS/SWL/011/21 / Pending Supporting Women's Request for Single Stage - One Procurement of IDA / 65690 Post Limited 11,000.00 0.00 Implementati 2021-05-19 2021-07-14 2022-01-10 Livelihoods Quotations Envelope communication materials on CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MCDSW/C/001 / Survey Supporting Women's Quality And Cost- Emuneration of SWL IDA / 56580 Prior Open - National 937,500.00 0.00 Canceled 2017-03-06 2017-03-27 2017-05-10 2017-06-07 2017-07-07 2017-08-11 2017-09-15 2018-09-15 Livelihoods Based Selection beneficiaries MCDSW/C/002 / Information, Consultant education and Supporting Women's IDA / 56580 Post Qualification Open - National 200,000.00 0.00 Canceled 2016-05-16 2016-06-06 2016-07-20 2016-08-19 2016-09-23 2017-03-22 communications outreach at Livelihoods Selection local and national level MCDSW/C/003 / Service Supporting Women's Quality And Cost- provider to pay productivity IDA / 56580 Prior Open - International 845,000.00 0.00 Canceled 2016-01-04 2016-01-25 2016-11-30 2016-12-28 2017-01-27 2017-03-03 2017-04-07 2018-04-07 Livelihoods Based Selection grants to beneficiaries MCDSW/C/016 / Consultancy Supporting Women's Quality Based to support roll-out and IDA / 56580 Prior Open - National 1,300,000.00 0.00 Canceled 2016-05-09 2016-05-30 2016-07-13 2016-12-02 2017-01-28 2017-01-01 2017-02-07 2017-01-31 2017-03-07 2018-03-07 Livelihoods Selection implementation of SWL MCDSW/C/017 / Design of Consultant and operational guidelines for Supporting Women's IDA / 56580 Post Qualification Open - National 90,000.00 0.00 Canceled 2016-01-18 2016-02-08 2016-03-23 2016-04-22 2016-05-27 2016-11-23 targeting and identification of Livelihoods Selection SWL beneficiaries MCDSW/C/018 / Consultant Development of strategy ad Supporting Women's IDA / 56580 Post Qualification Open - National 120,000.00 0.00 Canceled 2017-01-25 2017-02-15 2017-03-31 2017-04-30 2017-06-04 2017-12-01 tools for SWL GRS, and suppirt Livelihoods Selection to launch and operate the GRS Page 5 MCDSW/C/021 / Impact Supporting Women's Quality And Cost- IDA / 56580 Prior Open - National 1,030,000.00 437,168.00 Completed 2017-06-06 2017-05-21 2017-06-27 2017-08-10 2017-10-13 2017-09-07 2017-12-19 2017-10-07 2018-03-13 2017-11-11 2018-08-06 2017-12-16 2018-08-26 2018-12-16 2019-03-29 evaluation data collection Livelihoods Based Selection Consultant MCDSW/C/05 / Updating Supporting Women's IDA / 56580 Post Qualification Open - National 100,000.00 0.00 Canceled 2016-11-16 2016-12-07 2017-01-20 2017-02-19 2017-03-26 2017-09-22 Operations Manual Livelihoods Selection MCDSW/C/06 / Assessment Consultant Supporting Women's of options to identifying IDA / 56580 Post Qualification Open - National 100,000.00 0.00 Canceled 2017-07-17 2017-08-07 2017-09-20 2017-10-20 2017-11-24 2018-05-23 Livelihoods beneficiaries of NRCs Selection MCDSW/C/07 / Inventory of Consultant Supporting Women's existing complimentary IDA / 56580 Post Qualification Open - National 40,000.00 0.00 Canceled 2017-01-19 2017-02-09 2017-03-25 2017-04-24 2017-05-29 2017-11-25 Livelihoods activities Selection Consultant MCDSW/C/08 / Software Supporting Women's IDA / 56580 Post Qualification Open - National 150,000.00 0.00 Canceled 2017-03-28 2017-04-18 2017-06-01 2017-07-01 2017-08-05 2018-02-01 design and implementation Livelihoods Selection Consultant MCDSW/C/01 / Development Supporting Women's IDA / 56580 Post Qualification Open - National 150,000.00 0.00 Canceled 2016-12-04 2017-01-13 2016-12-25 2017-02-07 2017-03-09 2017-04-13 2017-10-10 of M&E framework Livelihoods Selection MCDSW/C/020 / Implementation evaluation Supporting Women's Quality And Cost- IDA / 56580 Prior Open - National 200,000.00 0.00 Canceled 2017-01-03 2017-01-24 2017-03-09 2017-04-06 2017-05-06 2017-06-10 2017-07-15 2018-07-15 and beneficiary satisfaction Livelihoods Based Selection survey MCDSW/C/02 / Development Supporting Women's Quality And Cost- of MIS module for SWL and IDA / 56580 Prior Open - National 350,000.00 0.00 Canceled 2016-07-18 2016-08-08 2016-09-21 2017-02-17 2017-03-19 2017-08-11 2017-04-23 2017-05-28 2018-05-28 Livelihoods Based Selection non-formal Literacy MCDSW/C/03 / Enhancement Consultant Supporting Women's of Management Information IDA / 56580 Post Qualification Open - National 150,000.00 0.00 Canceled 2017-10-09 2017-10-30 2017-12-13 2018-01-12 2018-02-16 2018-08-15 Livelihoods System /Single Registry B Selection MCDSS/C/023 / Technical Supporting Women's Quality Based Assistance for Roll-Out and IDA / 56580 Prior Open - National 1,300,000.00 0.00 Canceled 2017-10-12 2017-10-17 2017-10-26 2017-10-31 2017-11-05 2017-12-21 2017-12-03 2018-04-06 2017-12-08 2018-04-17 2017-12-20 2018-01-24 2019-01-24 Livelihoods Selection Implementation of SWL MCDSS/C/026/17 / Consultancy Services for the Consultant Institutional Strengthening Service Level Agreement for IDA / 56580 Post Qualification Open - National 15,000.00 0.00 Canceled 2017-12-08 2017-12-29 2018-02-11 2018-03-13 2018-04-17 2018-10-14 and Systems Building the Single Registry of Selection Household Beneficiaries (SRB) INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MCDSW/C/019 / Strategy for Individual harmonization of MCDSW Supporting Women's IDA / 56580 Post Consultant Open 60,000.00 0.00 Canceled 2017-02-15 2017-04-05 2017-04-26 2017-05-31 2017-11-27 empowerment/livelihood Livelihoods Selection programs MCDSW/C/04 / Updating the trainig strategy for MCDSW Individual Supporting Women's staff in M&E and develop a IDA / 56580 Post Consultant Open 20,000.00 0.00 Canceled 2017-01-10 2017-02-28 2017-03-21 2017-04-25 2017-10-22 Livelihoods strategy for capacity Selection development in policy analysis MCDSW/C/09 / TA to Individual Supporting Women's National Social Protection Co- IDA / 56580 Post Consultant Open 40,000.00 0.00 Canceled 2016-11-17 2017-01-05 2017-01-26 2017-03-02 2017-08-29 Livelihoods ordination Unit Selection Individual MCDSW/C/9 / Development Supporting Women's IDA / 56580 Post Consultant Open 15,000.00 0.00 Canceled 2017-01-09 2017-02-27 2017-03-20 2017-04-24 2017-10-21 of a strategy for good practice Livelihoods Selection Individual MCDSW/C/004 / Hiring of Supporting Women's IDA / 56580 Prior Consultant Open 112,500.00 0.00 Canceled 2015-11-04 2015-12-23 2016-04-04 2016-05-09 2018-03-31 SWL Manager Livelihoods Selection Individual Supporting Women's Pending MCDSW/C/006 / M&E Officer IDA / 56580 Post Consultant Open 89,100.00 0.00 2015-11-04 2015-12-23 2016-06-06 2016-07-11 2018-07-31 Livelihoods Implementation Selection Individual MCDSW/C/009 / Program Supporting Women's IDA / 56580 Post Consultant Open 89,100.00 0.00 Canceled 2015-11-04 2015-12-23 2016-06-06 2016-07-11 2018-07-31 Officer Livelihoods Selection Individual MCDSW/C/011 / Program Supporting Women's IDA / 56580 Post Consultant Open 89,100.00 0.00 Canceled 2015-11-04 2015-12-23 2016-06-06 2016-07-11 2018-07-31 Officer Livelihoods Selection Individual MCDSW/C/012 / Program Supporting Women's IDA / 56580 Post Consultant Open 89,100.00 0.00 Canceled 2015-11-04 2015-12-23 2016-06-06 2016-07-11 2018-07-31 Officer Livelihoods Selection Individual MCDSW/C/013 / Program Supporting Women's IDA / 56580 Post Consultant Open 89,100.00 0.00 Canceled 2015-11-04 2015-12-23 2016-06-06 2016-07-11 2018-07-31 Officer Livelihoods Selection Individual MCDSW/C/014 / Program Supporting Women's Pending IDA / 56580 Post Consultant Open 97,200.00 0.00 2015-11-04 2015-12-23 2016-04-04 2016-05-09 2018-03-31 Accountant Livelihoods Implementation Selection Individual MCDSW/C/007 / ICT Supporting Women's Pending IDA / 56580 Post Consultant Open 97,500.00 0.00 2015-11-04 2015-12-23 2016-06-06 2016-07-11 2018-07-31 Specialist Livelihoods Implementation Selection Page 6 Individual MCDSW/C/005 / Hiring of Supporting Women's Pending IDA / 56580 Post Consultant Open 97,500.00 0.00 2015-11-03 2015-12-22 2016-04-03 2016-05-08 2018-03-30 SWL M&E Specialist Livelihoods Implementation Selection Individual Supporting Women's MCDSW/C/008 / ICT Officer IDA / 56580 Post Consultant Open 89,100.00 0.00 Canceled 2015-11-03 2015-12-22 2016-06-05 2016-07-10 2018-07-30 Livelihoods Selection Individual MCDSW/C/010 / Program Supporting Women's IDA / 56580 Post Consultant Open 89,100.00 0.00 Canceled 2015-11-03 2015-12-22 2016-06-05 2016-07-10 2018-07-30 Officer Livelihoods Selection Individual ZM-MCDSW-4860-CS-INDV / Supporting Women's IDA / 56580 Post Consultant Open 44,550.00 0.00 Canceled 2017-01-09 2017-03-14 2017-02-27 2017-03-20 2017-04-24 2017-10-21 Procurement Specialist Livelihoods Selection Individual ZM MCDSW-4860CS-INDV / Supporting Women's Under IDA / 56580 Post Consultant Limited 85,800.00 0.00 2017-03-14 2017-03-24 2017-03-19 2017-04-09 2017-05-14 2017-11-10 Procurement Specialist Livelihoods Implementation Selection Individual ZM MCDSW/C/022 / Logistics Supporting Women's Under IDA / 56580 Post Consultant Open 66,000.00 0.00 2017-04-06 2017-04-05 2017-05-25 2017-06-15 2017-07-20 2018-01-16 Officer Livelihoods Implementation Selection Individual MCDSW/C/015 / Assistant Supporting Women's IDA / 56580 Post Consultant Open 77,760.00 0.00 Canceled 2017-11-22 2017-12-07 2018-01-10 2018-05-30 2018-07-04 2020-07-23 Accountant Livelihoods Selection Individual MCDSS/C/025/17 / Hiring of Supporting Women's IDA / 56580 Post Consultant Limited 77,000.00 0.00 Canceled 2017-12-08 2017-12-07 2017-12-13 2018-01-03 2018-02-07 2018-08-06 a Data Management Specialist Livelihoods Selection MCDSS/SWL/C/003/18 / Consultancy services for the Supporting Women's Under IDA / 56580 Prior Direct Selection Direct 170,000.00 0.00 2018-05-11 2018-05-22 2018-05-21 2018-06-05 2018-07-25 2019-01-21 development of a Livelihoods Implementation Management Information System MCDSS/SWL/C/001/19 / Consultancy services for the Supporting Women's Mid line Survey for the Impact IDA / 56580 Prior Direct Selection Direct 480,000.00 589,995.00 Signed 2019-04-22 2019-05-20 2019-05-02 2019-08-15 2019-07-06 2020-08-26 2020-01-02 Livelihoods Evaluation for the Supporting Women's Livelihoods MCDSS/SWL/013/19 / Individual Supporting Women's Employment of an Assistant IDA / 56580 Post Consultant Limited 45,000.00 0.00 Canceled 2020-10-16 2020-10-21 2020-11-11 2020-12-16 2021-06-14 Livelihoods Accountant for the SWL Selection MCDSS/SWL/C/001/2020 / Individual Consultancy Services for the Supporting Women's Under IDA / 56580 Post Consultant Open 39,000.00 0.00 2020-09-11 2020-08-27 2020-10-30 2020-10-26 2020-11-20 2020-12-02 2020-12-25 2021-06-23 recruitment of a Payment Livelihoods Implementation Selection Specialist for the SWL MCDSS/SWL/C/002/2020 / Individual Consultancy Services for the Supporting Women's Under IDA / 56580 Post Consultant Open 32,400.00 0.00 2020-09-11 2020-08-27 2020-10-30 2020-11-20 2020-12-25 2021-06-23 recruitment of an Monitoring Livelihoods Implementation Selection and Evaluation Officer MCDSS/SWL/C/003/20 / Individual Consultancy Services for the Supporting Women's Under IDA / 56580 Post Consultant Open 32,400.00 0.00 2020-09-11 2020-08-27 2020-10-30 2020-11-20 2020-12-25 2021-06-23 Recruitment of the Livelihoods Implementation Selection Accountant MCDSS/SWL/C/004/2020 / Consultancy Services for Individual Supporting Women's engagement of a Monitoring IDA / 56580 Post Consultant Open 39,000.00 0.00 Canceled 2020-10-23 2020-12-11 2021-01-01 2021-02-05 2021-08-04 Livelihoods and Evaluation (M&E) Selection Specialist for the SWL MCDSS/SCT/001/C/21 / Individual Consultancy for the Individual Under engagement of a Financial IDA / 65690 Keeping Girls in School Prior Consultant Direct 72,000.00 0.00 2021-01-22 2021-02-01 2021-02-01 2021-02-22 2021-03-29 2021-09-25 Implementation Management Specialist for the Selection Social Cash Transfer (SCT) MCDSS/SCT/002/C/2021 / Individual Engagement of ten (10) Under IDA / 65690 Keeping Girls in School Prior Consultant Direct 528,000.00 0.00 2021-01-27 2021-02-01 2021-02-06 2021-02-27 2021-04-03 2021-09-30 provincial project accountants Implementation Selection for the SCT. MCDSS/SWL/C/005/20 / Individual Consultancy Services for the Supporting Women's IDA / 56580 Post Consultant Open 72,000.00 0.00 Canceled 2020-10-23 2020-12-11 2021-01-01 2021-02-05 2021-08-04 engagement of a Program Livelihoods Selection Officer for the SWL Page 7