IN: NATIONLA CYCLONE RISK MITIGATION PROJECT II (P144726) I. General 1. Bank’s approval Date of the procurement Plan: Original: May 21, 2015 2. Date of General Procurement Notice: May 5, 2015 3. Period covered by this procurement plan: The procurement period of project covered from Year May 5, 2015 to October 2016 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Threshold Comments US$ 1. ICB (Goods) Above US$ 2 million All 2. NCB (Goods) Above US$ 2 million All 3. ICB (Works) Above US$ 10 million All 4. NCB (Works) Above US$ 10 million All 5. Services (non-consultant) Above US$ 2 million All 6. LIB Above US$ 30,000 Procurement Methods and Threshold Category Method of Procurement Threshold (US$ Equivalent) Goods and Non-consultant ICB >3,000,000 services LIB Wherever agreed by the Bank NCB Up to 3,000,000 (with NCB conditions) Shopping Up to 100,000 DC As per Para 3.7 of the Bank Guidelines Force Account As per Para 3.9 of Guidelines Framework Agreements As per Para 3.6 of Guidelines Works ICB >40,000,000 NCB Up to 40,000,000 (with NCB conditions) Shopping Up to 200,000 Force Account As per Para 3.9 of Guidelines DC As per Para 3.7 of Guidelines Community Participation As per Para 3.19 of Guidelines Page 1 of 4 Prior Review by the Bank. The Bank will prior review the following contracts: • Works: All contracts more than US$ 10.0 million equivalent; • Goods: All contracts more than US$ 2.0 million equivalent; • Non-Consulting Services: All contracts more than US$ 2.0 million equivalent; The PMU shall prior review the first contract issued by each implementing agency, if the estimate of those contracts are below the prior review threshold value. The Bank will conduct prior review for only those contract whose estimate falls in prior review threshold value. In addition, the justifications for all contracts to be issued on LIB, single-source (>US$ 30,000) or direct contracting (>US$ 30,000) basis will be subject to Banks prior review. These thresholds are for the initial 18 months period and are based on the procurement performance of the project, these thresholds will be modified. In addition, the Bank will carry out an annual ex post procurement review of the procurement falling below the prior review threshold mentioned above. All contracts below the specified prior review threshold value shall be subject to Post Procurement Review (PPR). For the avoidance of doubts, the Bank shall be entitled to conduct, at any time, independent procurement reviews of all the contracts financed under the Credit. The IA shall prepare a list of contract and submit it to the Bank for conducting PPR. The PPR will be conducted on annual basis. All contracts not covered under prior review will be subject to post review during supervision missions, and/or review by consultants to be appointed by the by Bank. 2. Pre-qualification. Not applicable 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Not applicable 4. Reference to Project Operational/Procurement Manual: The Project Operations/Procurement Manual was prepared and agreed by the Bank to be used as guidance note while conducting project procurement. All the contracts issued under the project will follow the World Bank’s Guidelines: Bank’s “Guidelines: Procurement under IBRD Loans and IDA Credits” dated January 2011and revised in July 2014and “Guidelines: Selection and Employment of Consultants by World Bank Borrowers” dated January 2011 and revised in July 2014, In case of any inconsistency between the Project Operation/Procurement Manual, the Bank Guidelines shall prevail. 5. Any Other Special Procurement Arrangements: Procurement of goods, works and non- consulting services shall be conducted through e-procurement portal in all the participating states using Bank’s standard bidding documents. International Competitive Bidding (ICB) is the preferred method for procurement of goods, works and non-consulting services. However, it is unlikely that there will be any ICB contract. All National Competitive Bidding (NCB) shall be conducted in accordance with paragraph 3.3 and 3.4 of the Guidelines. In addition, following additional provisions as agreed with GOI task force (as amended form time to time) shall apply: Page 2 of 4 • Only the model bidding documents for NCB as agreed with the GoI Task Force (and as amended from time to time), shall be used for bidding; • Invitation to bid shall be advertised in at least one widely circulated national daily newspaper (or on a widely used website or electronic portal with free national and international access along with an abridged version of the said advertisement published in a widely circulated national daily inter-alia giving the website/electronic portal details from which the details of the invitation to bid can be downloaded), at least 30 days prior to the deadline for the submission of bids; • No special preference will be accorded to any bidder either for price or for other terms and conditions when competing with foreign bidders, state-owned enterprises, small-scale enterprises or enterprise from any given State; • Except with the prior concurrence of the Bank, there shall be no negotiation of price with the bidders, even with the lowest evaluated bidder; • For prior review contracts, extension of bid validity shall not be allowed with reference to Contracts subject to Bank prior review without the prior concurrence of the Bank (i) for the first request for extension if it is longer than four weeks; and (ii) for all subsequent requests for extension irrespective of the period (such concurrence will be considered by Bank only in cases of Force Majeure and circumstance beyond the control of the Purchaser/Employer); • For prior review contracts , re-bidding shall not be carried out with reference to Contracts subject to Bank prior review without the prior concurrence of the Bank; • The system of rejecting bids outside a pre-determined margin or “bracket” of prices shall not be used in the project; • Rates contract entered into by Directorate General of Supplies and Disposal (DGS & D) will not be acceptable as a substitute for NCB procedures unless agreed with the Bank on case to case basis. Such contracts will be acceptable however, for any procurement under the Shopping procedure; • Two or three envelop system will not be used (expect when suing e-procurement system assessed and agreed by the Bank. To meet the Bank's requirements for right to audit and F&C, these clauses may be included in the Purchase Orders, in case the purchasers are directly placing the purchase orders to DGS&D rate contract holders. On the other hand, if indent is placed through DGS&D, the Purchaser has the option to sign a separate undertaking with DGS&D rate contract holder, where Bank’s right to audit and F&C clauses could be mentioned; 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness: Available in STEP. III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comment 1. Competitive Methods (Firms) Above US$ 1 million All contract 2. Single Source (Firms) Above US$ 1 million All contract 3. Individual Above US$ 300,000 All contracts Page 3 of 4 4. CQS/LCS Up to US$ 300,000 All contracts 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $ 800,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: The implementation of component 1 (designating of Early Warning Development System) is foreseen as challenge as there are limited consulting firms in the market. M/s Telecommunications Consultant India Ltd. (TCIL) a government owned public sector has been designing EWDS system for Andhra Pradesh and Odisha under NCRMP I project. Many participating states have requested to single source designing of EWDS to TCIL as they do not have capacity to conduct selection process for such firm. NDMA suggested that while it will be an advantage to use TCIL in all the states, an option will be given to the respective states to either single source TCIL or choose competitive selection procedure to select such firms as reflected in the procurement plan in STEP. 4. Consultancy Assignments with Selection Methods and Time Schedule Available on STEP. Page 4 of 4 PROCUREMENT India : National Cyclone Risk Mitigation Project-II PLAN General Information Country: India Banks Approval Date of the Original Procurement Plan: 2016-06-20 Revised Plan Date(s): (comma delineated, leave blank if none) 2017-08-09 Project ID: P144726 GPN Date: Project Name: National Cyclone Risk Mitigation Project-II Loan / Credit No: IDA / 56930 Executing Agency(ies): West Bengal Disaster Management Department (WB), Gujarat State Disaster Management Authority, SPIU, Kerala State Disaster Management Authority, Water Resources Department (Goa), Department of Revenue Management (Karnataka), SPIU - Relief and Rehabilitation Department, Govt. of Maharashtra, National Disaster Management Authority WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Early Warning Dissemination Systems Project Management and NCRMP/WB/BAS/P1 / Implementation Support Single Stage - One Construction of MPCS (12 MPCS IDA / 56930 Prior Request for Bids Open - National 7,389,984.00 7,955,091.22 Signed 2015-07-09 2015-08-06 Technical Assistance for Multi- Envelope under Package 1) Hazard Risk Management Cyclone Risk Mitigation Infrastructure Early Warning Dissemination Systems Package No. Project Management and NCRMP/Gujarat/AND/KHM/01 / Implementation Support Single Stage - One Upgradtaion/Reconstructing of IDA / 56930 Prior Request for Bids Open - National 704,919.73 430,553.47 Signed 2015-08-25 2015-05-05 Technical Assistance for Multi- Envelope Various road Ta. Khambhat Dist. Hazard Risk Management Anand Cyclone Risk Mitigation Infrastructure IN-KSDMA-201-CW-RFB / Construction of Multi purpose Cyclone Risk Mitigation Single Stage - Two Pending cyclone shelter at Muttahara IDA / 56930 Post Request for Bids Open - National 666,666.67 0.00 2016-11-21 2016-11-26 2017-01-07 2017-03-22 2017-04-26 2017-10-23 Infrastructure Envelope Implementation village of Trivandrum district in Kerala IN-KSDMA-202-CW-RFB / Construction of Multi purpose Cyclone Risk Mitigation Single Stage - Two Pending IDA / 56930 Post Request for Bids Open - National 666,666.67 0.00 2016-12-19 2016-12-24 2017-02-04 2017-04-19 2017-05-24 2017-11-20 Cyclone shelter at Infrastructure Envelope Implementation Karunagappally IN-KSDMA-203-CW-RFB / Construction of Multi purpose Cyclone Risk Mitigation Single Stage - Two Pending IDA / 56930 Post Request for Bids Open - National 666,666.67 0.00 2016-12-19 2016-12-24 2017-02-04 2017-04-19 2017-05-24 2017-11-20 cyclone shelter at Kumarapuram Infrastructure Envelope Implementation village of Alappuzha District IN-KSDMA-204-CW-RFB / Construction of Multi Purpose Cyclone Risk Mitigation Single Stage - Two Pending IDA / 56930 Post Request for Bids Open - National 666,666.67 0.00 2016-12-19 2016-12-24 2017-02-04 2017-04-19 2017-05-24 2017-11-20 Cyclone Shelter at Cheruthana Infrastructure Envelope Implementation village of Alappuzha district. IN-KSDMA-205-CW-RFB / Construction of Multi Purpose Cyclone Risk Mitigation Single Stage - Two Pending IDA / 56930 Post Request for Bids Open - National 666,666.67 0.00 2016-12-19 2016-12-24 2017-02-04 2017-04-19 2017-05-24 2017-11-20 Cyclone Shelter at Vadakkevila Infrastructure Envelope Implementation village of Kollam district. IN-WRD -GOA-900-CW-RFB / Construction of Multi Purpose Cyclone Risk Mitigation Single Stage - Two Pending IDA / 56930 Post Request for Bids Open - National 310,000.00 0.00 2016-10-17 2016-10-22 2016-12-03 2017-02-15 2017-03-22 2017-09-18 Cyclone Shelter at GPS Infrastructure Envelope Implementation Junaswada Mandrem Goa IN-WRD-GOA-943-CW-RFQ / Carrying of Foundation Project Management and Request for Single Stage - One Pending IDA / 56930 Post Limited 23,000.00 0.00 2016-09-17 2016-11-12 2017-05-11 Exploration For Saline Implementation Support Quotations Envelope Implementation Embankment Works IN-WRD-GOA-948-CW-RFB / Construction of Multi Purpose Cyclone Risk Mitigation Single Stage - Two Pending IDA / 56930 Post Request for Bids Open - National 300,000.00 0.00 2016-12-26 2016-12-31 2017-02-11 2017-04-26 2017-05-31 2017-11-27 Construction Cyclone Shelter at Infrastructure Envelope Implementation Parvem IN-WRD-GOA-952-CW-RFB / Construction of Multi Purpose Cyclone Risk Mitigation Single Stage - Two Pending IDA / 56930 Post Request for Bids Open - National 300,000.00 0.00 2016-12-26 2016-12-31 2017-02-11 2017-04-26 2017-05-31 2017-11-27 Cyclone Construction Shelter at Infrastructure Envelope Implementation Shelhi Loliem IN-WRD-GOA-954-CW-RFB / Cyclone Risk Mitigation Single Stage - Two Pending Construction of Multi Purpose IDA / 56930 Post Request for Bids Open - National 300,000.00 0.00 2016-12-26 2016-12-31 2017-02-11 2017-04-26 2017-05-31 2017-11-27 Infrastructure Envelope Implementation Cyclone Shelter at Ashwem IN-DRM-KAR-1388-CW-RFB / Package 1: Construction of Multipurpose Cyclone Shelter Cyclone Risk Mitigation Single Stage - Two Under IDA / 56930 Post Request for Bids Open - National 375,000.00 0.00 2016-10-30 2017-06-19 2016-11-04 2016-12-16 2017-02-28 2017-04-04 2019-10-04 near Govt. Higher Primary School Infrastructure Envelope Implementation and PU college in Padu Kapu village, Udupi taluk, Udupi district IN-DRM-KAR-1947-CW-RFB / Package 5:Construction all weather road from Herikudru Cyclone Risk Mitigation Single Stage - Two Under temple to NH (2.12 km) and road IDA / 56930 Post Request for Bids Open - National 376,700.00 0.00 2016-10-31 2017-05-25 2016-11-05 2016-12-17 2017-03-01 2017-04-05 2018-03-05 Infrastructure Envelope Implementation from Herikudru school to NH (0.82 km), Anagalli in Kundapura taluk, Udupi IN-DRM-KAR-1948-CW-RFB / Package 3: Construction and improvements of Hejamadi-Kodi Cyclone Risk Mitigation Single Stage - Two Pending Fisheries Road and Construction IDA / 56930 Post Request for Bids Open - National 701,700.00 0.00 2016-10-31 2016-11-05 2016-12-17 2017-03-01 2017-04-05 2018-03-05 Infrastructure Envelope Implementation and improvements of Tenka Yermal Fisheries Road in Udupi taluk Page 1 IN-DRM-KAR-1949-CW-RFB / Package 4:Construction and Cyclone Risk Mitigation Single Stage - Two Pending improvements to Malpe - Tottam IDA / 56930 Post Request for Bids Open - National 516,700.00 0.00 2016-10-31 2016-11-05 2016-12-17 2017-03-01 2017-04-05 2018-03-05 Infrastructure Envelope Implementation - Gujjarabettu Fisheries Road in Udupi taluk, Udupi District. IN-DRM-KAR-1950-CW-RFB / Package 6:Construction and improvement of Thekkatte to Cyclone Risk Mitigation Single Stage - Two Under Kome fisheries road (2.10 Km); IDA / 56930 Post Request for Bids Open - National 618,400.00 0.00 2016-10-31 2017-07-10 2016-11-05 2016-12-17 2017-03-01 2017-04-05 2018-03-05 Infrastructure Envelope Implementation Beejadi fisheries road (2.15 Km) Kundapura Taluk, Udupi Total Length-4.25 km IN-DRM-KAR-1951-CW-RFB / Package 7: Construction and improvements Road from Gangolli light house to Trasi Gangolli Main road; Bengeri Cyclone Risk Mitigation Single Stage - Two Under IDA / 56930 Post Request for Bids Open - National 618,400.00 0.00 2016-10-31 2017-07-10 2016-11-05 2016-12-17 2017-03-01 2017-04-05 2018-03-05 Naga temple to Trasi Gangolli Infrastructure Envelope Implementation Main road; Uppunda Madical Alvekodi fisheries road; Koderi fisheries road, Kundapura taluk, Udupi District IN-DRM-KAR-1952-CW-RFB / Package 8:Construction and improvements Road from Yedthare Paduvari customs to Cyclone Risk Mitigation Single Stage - Two Pending IDA / 56930 Post Request for Bids Open - National 660,000.00 0.00 2016-10-31 2016-11-05 2016-12-17 2017-03-01 2017-04-05 2018-03-05 NH 66; Road from Yedthare Infrastructure Envelope Implementation Market road; Road from NH 66 to Shirur under bridge approach road, Kundapura, Udupi District IN-DRM-KAR-1953-CW-RFB / Package 9: Construction and Cyclone Risk Mitigation Single Stage - Two Under improvements Shirur Alvegadde IDA / 56930 Post Request for Bids Open - National 753,400.00 0.00 2016-10-31 2017-07-10 2016-11-05 2016-12-17 2017-03-01 2017-04-05 2018-03-05 Infrastructure Envelope Implementation fisheries road ; Yedthare to Paduvari Someshwara road IN-DRM-KAR-1985-CW-RFB / Package 10: Construction of bridge and approach road Cyclone Risk Mitigation Single Stage - Two Pending IDA / 56930 Post Request for Bids Open - National 375,000.00 0.00 2017-01-31 2017-02-05 2017-03-19 2017-06-01 2017-07-06 2019-12-31 Manooru to Nadubettu across Infrastructure Envelope Implementation Boodanagundi River in Udupi taluk IN-DRM-KAR-1986-CW-RFB / Package 11: Construction of Cyclone Risk Mitigation Single Stage - Two Pending bridge and approach road @ IDA / 56930 Post Request for Bids Open - National 1,350,000.00 0.00 2017-01-31 2017-02-05 2017-03-19 2017-06-01 2017-07-06 2019-12-31 Infrastructure Envelope Implementation Kelageri to Kodi Kanyana Temple Udupi taluk. IN-DRM-KAR-1992-CW-RFB / Package 12:Construction of Multipurpose cyclone shelter Cyclone Risk Mitigation Single Stage - Two Pending IDA / 56930 Post Request for Bids Open - National 375,000.00 0.00 2016-10-31 2016-11-05 2016-12-17 2017-03-01 2017-04-05 2019-10-02 near Zilla Panchayath Higher Infrastructure Envelope Implementation Primary School, Hosabettu in Mangalore Taluk IN-DRM-KAR-1996-CW-RFB / Package 13: Construction and improvements to Mukka- Cyclone Risk Mitigation Single Stage - Two Pending IDA / 56930 Post Request for Bids Open - National 733,400.00 0.00 2016-10-31 2016-11-05 2016-12-17 2017-03-01 2017-04-05 2018-03-05 Sashihithlu road from Km. 0.00 Infrastructure Envelope Implementation to 5.50 Km. in Mangalore Taluk, Dakshina Kannada District IN-DRM-KAR-1998-CW-RFB / Package 14:Improvements to road from Chitrapura River side Cyclone Risk Mitigation Single Stage - Two Pending IDA / 56930 Post Request for Bids Open - National 316,700.00 0.00 2016-10-31 2016-11-05 2016-12-17 2017-03-01 2017-04-05 2018-03-05 towards East Upto NH, Mulki Infrastructure Envelope Implementation Town in Mangalore Taluk, Dakshina Kannada District. IN-DRM-KAR-2000-CW-RFB / Package 15:Construction and improvements of KFDC Hoige Bazaar 3rd stage to Fisheries Cyclone Risk Mitigation Single Stage - Two Pending Jetty road and road from Hoige IDA / 56930 Post Request for Bids Open - National 450,000.00 0.00 2016-10-31 2016-11-05 2016-12-17 2017-03-01 2017-04-05 2018-03-05 Infrastructure Envelope Implementation Bazaar to Railway gate to Marigudi Temple, Bolar Leewel Feery Road in Mangalore Taluk, Dakshina Kannada District IN-DRM-KAR-2001-CW-RFB / Package 16: Construction and improvements to road from Cyclone Risk Mitigation Single Stage - Two Pending Someshwara Temple sea shore IDA / 56930 Post Request for Bids Open - National 500,000.00 0.00 2016-10-31 2016-11-05 2016-12-17 2017-03-01 2017-04-05 2018-03-05 Infrastructure Envelope Implementation to Thokkottu in Mangalore Taluk, Dakshina Kannada District. (3 km) IN-DRM-KAR-2019-CW-RFB / Package 17: Construction and improvements to road from Ullala Cyclone Risk Mitigation Single Stage - Two Pending IDA / 56930 Post Request for Bids Open - National 550,000.00 0.00 2016-10-31 2016-11-05 2016-12-17 2017-03-01 2017-04-05 2018-03-05 Beach, Ullal Dargha via to Infrastructure Envelope Implementation Thokkottu in Mangalore Taluk, Dakshina Kannada District. IN-DRM-KAR-2020-CW-RFB / Package 18:Construction of Cyclone Risk Mitigation Single Stage - Two Pending Multipurpose Cyclone Shelter at IDA / 56930 Post Request for Bids Open - National 375,000.00 0.00 2016-10-31 2016-11-05 2016-12-17 2017-03-01 2017-04-05 2019-10-02 Infrastructure Envelope Implementation Chittakula village, Chittakula GP Karwar Taluk, Uttara Kannada IN-DRM-KAR-2092-CW-RFB / Package 19: Construction of Cyclone Risk Mitigation Single Stage - Two Pending Multipurpose Cyclone Shelter at IDA / 56930 Post Request for Bids Open - National 375,000.00 0.00 2016-10-31 2016-11-05 2016-12-17 2017-03-01 2017-04-05 2019-10-02 Infrastructure Envelope Implementation Amadalli Village, Amadalli GP, Karwar Taluk, Uttara Kannada IN-DRM-KAR-2093-CW-RFB / Package 20: Construction of Cyclone Risk Mitigation Single Stage - Two Under Multipurpose Cyclone Shelter at IDA / 56930 Post Request for Bids Open - National 375,000.00 0.00 2016-10-31 2017-06-09 2016-11-05 2016-12-17 2017-03-01 2017-04-05 2019-10-02 Infrastructure Envelope Implementation Pujgeri Gram Panchyat Shetgeri, Ankola, Uttara Kannada Page 2 IN-DRM-KAR-2094-CW-RFB / Package 21: Construction of Cyclone Risk Mitigation Single Stage - Two Under Multipurpose Cyclone Shelter at IDA / 56930 Post Request for Bids Open - National 375,000.00 0.00 2016-10-31 2017-06-09 2016-11-05 2016-12-17 2017-03-01 2017-04-05 2019-10-02 Infrastructure Envelope Implementation Govt. HPS, Kharviwada Belekeri GP, Ankola, Uttara Kannada IN-DRM-KAR-2095-CW-RFB / Package 22: Construction of Cyclone Risk Mitigation Single Stage - Two Under Multipurpose Cyclone Shelter at IDA / 56930 Post Request for Bids Open - National 375,000.00 0.00 2016-10-31 2017-06-09 2016-11-05 2016-12-17 2017-03-01 2017-04-05 2019-10-02 Infrastructure Envelope Implementation Manaki, Kumta, Uttara Kannada District IN-DRM-KAR-2096-CW-RFB / Package 23: Construction of Cyclone Risk Mitigation Single Stage - Two Under Multipurpose Cyclone Shelter at IDA / 56930 Post Request for Bids Open - National 375,000.00 0.00 2016-10-31 2017-06-09 2016-11-05 2016-12-17 2017-03-01 2017-04-05 2019-10-02 Infrastructure Envelope Implementation Manki High School, Honnavar, Uttara Kannada District IN-DRM-KAR-2097-CW-RFB / Package 24: Construction of Multipurpose Cyclone Shelter at Cyclone Risk Mitigation Single Stage - Two Pending IDA / 56930 Post Request for Bids Open - National 375,000.00 0.00 2016-10-31 2016-11-05 2016-12-17 2017-03-01 2017-04-05 2019-10-02 Shirali Village (Tattlihakkal), Infrastructure Envelope Implementation Shirali GP, Bhatkal, Uttara Kannada IN-DRM-KAR-2099-CW-RFB / Package 25: Improvements to Cyclone Risk Mitigation Single Stage - Two Pending Manki Banasale to Halemath IDA / 56930 Post Request for Bids Open - National 333,400.00 0.00 2016-10-31 2016-11-05 2016-12-17 2017-03-01 2017-04-05 2018-03-05 Infrastructure Envelope Implementation Fisheries Link Road in Honavar Taluka of UK Dist. IN-DRM-KAR-2100-CW-RFB / Package 26: Improvements to Manki Banasale Hosahitlu Cyclone Risk Mitigation Single Stage - Two Pending IDA / 56930 Post Request for Bids Open - National 416,700.00 0.00 2016-10-31 2016-11-05 2016-12-17 2017-03-01 2017-04-05 2018-03-05 Doddagunda Talmakki Fisheries Infrastructure Envelope Implementation Link Road in Honavar Taluka of UK Dist. IN-DRM-KAR-2101-CW-RFB / Package 27: Improvement to Cyclone Risk Mitigation Single Stage - Two Pending IDA / 56930 Post Request for Bids Open - National 458,400.00 0.00 2016-10-31 2016-11-05 2016-12-17 2017-03-01 2017-04-05 2018-03-05 Murudeshwar-Tudalli fisheries Infrastructure Envelope Implementation link road, Bhatkal Taluk IN-DRM-KAR-2102-CW-RFB / Package 28: Construction of Saline embankment near Manikatta from ch. 0.0m to Cyclone Risk Mitigation Single Stage - Two Pending IDA / 56930 Post Request for Bids Open - National 1,666,700.00 0.00 2017-01-31 2017-02-05 2017-03-19 2017-06-01 2017-07-06 2019-12-17 3.0Km and protection work near Infrastructure Envelope Implementation Aganashini 3.0 to 7.00 km in Kumta Taluka, Uttara Kannada District. IN-RRD-MAH-2620-CW-RFB / Cyclone Risk Mitigation Single Stage - Two Pending Underground cabling works at IDA / 56930 Prior Request for Bids Open - National 12,935,000.00 0.00 2017-02-01 2017-02-06 2017-03-20 2017-06-02 2017-07-07 2019-07-07 Infrastructure Envelope Implementation Alibag - P1. IN-RRD-MAH-2621-CW-RFB / Cyclone Risk Mitigation Single Stage - Two Pending Underground cabling work at IDA / 56930 Prior Request for Bids Open - National 14,615,000.00 0.00 2017-03-01 2017-03-06 2017-04-17 2017-06-30 2017-08-04 2019-08-04 Infrastructure Envelope Implementation Ratnagiri - P2. IN-RRD-MAH-2622-CW-RFB / Cyclone Risk Mitigation Single Stage - Two Pending Underground cabling work at IDA / 56930 Post Request for Bids Open - National 1,769,000.00 0.00 2017-03-15 2017-03-20 2017-05-01 2017-07-14 2017-08-18 2019-02-19 Infrastructure Envelope Implementation Saatpati - P3 IN-RRD-MAH-2624-CW-RFB / Cyclone Risk Mitigation Single Stage - Two Pending Renovation of saline IDA / 56930 Post Request for Bids Open - National 1,153,000.00 0.00 2017-01-02 2017-01-07 2017-02-18 2017-05-03 2017-06-07 2019-06-07 Infrastructure Envelope Implementation embankment at Kokeri - P2 IN-RRD-MAH-2625-CW-RFB / Cyclone Risk Mitigation Single Stage - Two Pending Renovation of saline IDA / 56930 Post Request for Bids Open - National 835,000.00 0.00 2017-01-02 2017-01-07 2017-02-18 2017-05-03 2017-06-07 2019-06-07 Infrastructure Envelope Implementation embankment at Mora Kotha - P3 IN-RRD-MAH-2626-CW-RFB / Renovation of saline Cyclone Risk Mitigation Single Stage - Two Pending IDA / 56930 Post Request for Bids Open - National 419,500.00 0.00 2017-01-02 2017-01-07 2017-02-18 2017-05-03 2017-06-07 2019-06-07 embankment at Nandgaon Infrastructure Envelope Implementation Mazgaon- P4 IN-RRD-MAH-2627-CW-RFB / Renovation of saline Cyclone Risk Mitigation Single Stage - Two Pending IDA / 56930 Post Request for Bids Open - National 1,774,537.00 0.00 2017-01-02 2017-01-07 2017-02-18 2017-05-03 2017-06-07 2019-06-07 embankment at Phansapur Infrastructure Envelope Implementation Kurdus - P5 IN-RRD-MAH-2628-CW-RFB / Renovation of saline Cyclone Risk Mitigation Single Stage - Two Pending IDA / 56930 Post Request for Bids Open - National 2,095,800.00 0.00 2017-01-02 2017-01-07 2017-02-18 2017-05-03 2017-06-07 2019-06-07 embankment at Kachali Pitkari - Infrastructure Envelope Implementation P6 IN-RRD-MAH-2629-CW-RFB / Cyclone Risk Mitigation Single Stage - Two Pending Renovation of saline IDA / 56930 Post Request for Bids Open - National 3,490,900.00 0.00 2017-01-02 2017-01-07 2017-02-18 2017-05-03 2017-06-07 2019-06-07 Infrastructure Envelope Implementation embankment at Vadhiv - P7 IN-RRD-MAH-2630-CW-RFB / Cyclone Risk Mitigation Single Stage - Two Pending Construction of saline IDA / 56930 Post Request for Bids Open - National 2,174,000.00 0.00 2017-01-02 2017-01-07 2017-02-18 2017-05-03 2017-06-07 2019-06-07 Infrastructure Envelope Implementation embankment at Panju - P8 IN-RRD-MAH-2631-CW-RFB / Cyclone Risk Mitigation Single Stage - Two Under Construction of Multipurpose IDA / 56930 Post Request for Bids Open - National 507,700.00 0.00 2017-02-01 2017-02-06 2017-03-20 2017-06-02 2017-07-07 2019-07-07 Infrastructure Envelope Implementation Cyclone Shelter at Saitwade - P1 IN-RRD-MAH-2632-CW-RFB / Cyclone Risk Mitigation Single Stage - Two Pending Construction of Multi purpose IDA / 56930 Post Request for Bids Open - National 507,700.00 0.00 2017-02-01 2017-02-06 2017-03-20 2017-06-02 2017-07-07 2019-07-07 Infrastructure Envelope Implementation Shelter at Vaishvi - P2 IN-RRD-MAH-2633-CW-RFB / Cyclone Risk Mitigation Single Stage - Two Pending Construction of Multi purpose IDA / 56930 Post Request for Bids Open - National 507,700.00 0.00 2017-02-01 2017-02-06 2017-03-20 2017-06-02 2017-07-07 2019-07-07 Infrastructure Envelope Implementation Shelter at Dabhol - P3 IN-RRD-MAH-2634-CW-RFB / Cyclone Risk Mitigation Single Stage - Two Pending Construction of Multi purpose IDA / 56930 Post Request for Bids Open - National 507,700.00 0.00 2017-02-01 2017-02-06 2017-03-20 2017-06-02 2017-07-07 2019-07-07 Infrastructure Envelope Implementation Shelter at Veldur - P4 Page 3 IN-RRD-MAH-2635-CW-RFB / Cyclone Risk Mitigation Single Stage - Two Pending Construction of Multi purpose IDA / 56930 Post Request for Bids Open - National 507,700.00 0.00 2017-02-01 2017-02-06 2017-03-20 2017-06-02 2017-07-07 2019-07-07 Infrastructure Envelope Implementation Shelter at Kihim - P5 IN-RRD-MAH-2636-CW-RFB / Cyclone Risk Mitigation Single Stage - Two Pending Construction of Multi purpose IDA / 56930 Post Request for Bids Open - National 507,700.00 0.00 2017-02-01 2017-02-06 2017-03-20 2017-06-02 2017-07-07 2019-07-07 Infrastructure Envelope Implementation Shelter at Shriwardhan - P6 IN-RRD-MAH-2637-CW-RFB / Cyclone Risk Mitigation Single Stage - Two Pending Construction of Multi purpose IDA / 56930 Post Request for Bids Open - National 507,700.00 0.00 2017-02-01 2017-02-06 2017-03-20 2017-06-02 2017-07-07 2019-07-07 Infrastructure Envelope Implementation Shelter at Vijaydurg - P7 IN-RRD-MAH-2638-CW-RFB / Cyclone Risk Mitigation Single Stage - Two Pending Construction of Multi purpose IDA / 56930 Post Request for Bids Open - National 507,700.00 0.00 2017-02-01 2017-02-06 2017-03-20 2017-06-02 2017-07-07 2019-07-07 Infrastructure Envelope Implementation Shelter at Kunkeshwar - P8 IN-RRD-MAH-2639-CW-RFB / Cyclone Risk Mitigation Single Stage - Two Pending Construction of Multi purpose IDA / 56930 Post Request for Bids Open - National 507,700.00 0.00 2017-02-01 2017-02-06 2017-03-20 2017-06-02 2017-07-07 2019-07-07 Infrastructure Envelope Implementation Shelter at Achra - P9 IN-RRD-MAH-2640-CW-RFB / Cyclone Risk Mitigation Single Stage - Two Pending Construction of Multi purpose IDA / 56930 Post Request for Bids Open - National 507,700.00 0.00 2017-02-01 2017-02-06 2017-03-20 2017-06-02 2017-07-07 2019-07-07 Infrastructure Envelope Implementation Shelter at Kalethar - P10 IN-RRD-MAH-2642-CW-RFB / Construction of Multi purpose Cyclone Risk Mitigation Single Stage - Two Pending IDA / 56930 Post Request for Bids Open - National 507,700.00 0.00 2017-02-01 2017-02-06 2017-03-20 2017-06-02 2017-07-07 2019-07-07 cyclone shelter at Jamsunday - Infrastructure Envelope Implementation P11 IN-DRM-KAR-1390-CW-RFB / Package 2: Construction of Multipurpose Cyclone Shelter at Cyclone Risk Mitigation Single Stage - Two Under IDA / 56930 Post Request for Bids Open - National 433,400.00 0.00 2016-10-30 2017-04-22 2016-11-04 2016-12-16 2017-02-28 2017-04-04 2019-10-04 Govt. Higher Primary Kuvempu Infrastructure Envelope Implementation School, Thekkatte, Kundapura Taluk, Udupi District IN-WRD-GOA-953-CW-RFB / Cyclone Risk Mitigation Single Stage - Two Construction of Multi Purpose IDA / 56930 Post Request for Bids Open - National 300,000.00 0.00 Canceled 2016-12-26 2016-12-31 2017-02-11 2017-04-26 2017-05-31 2017-11-27 Infrastructure Envelope Cyclone Shelter atDabolim IN-WRD GOA-4493-CW-RFB / Construction of MPCS at Cyclone Risk Mitigation Single Stage - Two Under IDA / 56930 Prior Request for Bids Open - National 625,000.00 0.00 2016-12-21 2017-04-07 2016-12-26 2017-02-06 2017-04-21 2017-05-26 2017-11-22 Dabolim Mormugao taluka South Infrastructure Envelope Implementation Goa IN-DMD-WB-2701-CW-RFB / Erection of 33 KV line and Cyclone Risk Mitigation Single Stage - Two Pending augmentation of 33/11 KV line for IDA / 56930 Post Request for Bids Open - National 1,005,773.00 0.00 2017-01-31 2017-02-05 2017-03-19 2017-06-01 2017-07-06 2019-02-26 Infrastructure Envelope Implementation Digha Underground Cabling Projecct INDRMKAR6088CWRFB / Package 29: Construction and improvements to road from Cyclone Risk Mitigation Single Stage - Two Pending IDA / 56930 Post Request for Bids Open - National 250,000.00 0.00 2017-03-31 2017-04-05 2017-05-17 2017-07-30 2017-09-03 2018-05-31 Adamkudru School to Infrastructure Envelope Implementation Adamkudru Church in Mangaluru City South Constituency. IN-RRD-MAH-2623-CW-RFB / Renovation of Saline Cyclone Risk Mitigation Single Stage - Two Pending IDA / 56930 Post Request for Bids Open - National 7,526,000.00 0.00 2017-01-01 2017-01-06 2017-02-17 2017-05-02 2017-06-06 2019-11-23 Embankment at Narvel Benavale Infrastructure Envelope Implementation - P1 IN-DMD-WB-2705-CW-RFB / Erection of 11 KV lines and LT Cyclone Risk Mitigation Single Stage - Two Under lines with DTRs and RMU for the IDA / 56930 Prior Request for Bids Open - National 14,563,763.00 0.00 2017-04-30 2017-05-05 2017-06-16 2017-08-29 2017-10-03 2020-09-17 Infrastructure Envelope Implementation Digha Underground Electrical Cabling Project IN-GSDMA-4723-CW-RFB / Cyclone Risk Mitigation Single Stage - Two Under Construction of one Type-II IDA / 56930 Post Request for Bids Open - National 850,000.00 0.00 2017-05-03 2017-07-27 2017-05-08 2017-08-03 2017-06-19 2017-09-01 2017-10-06 2018-12-30 Infrastructure Envelope Implementation MPCS in Gir Somnath (GS-06R) IN-GSDMA-4733-CW-RFB / Cyclone Risk Mitigation Single Stage - Two Under Construction of two Type-II IDA / 56930 Post Request for Bids Open - National 1,700,000.00 0.00 2017-05-03 2017-07-24 2017-05-08 2017-08-03 2017-06-19 2017-09-01 2017-10-06 2018-12-30 Infrastructure Envelope Implementation MPCS in Gir Somnath (GS-13R) IN-GSDMA-4734-CW-RFB / Cyclone Risk Mitigation Single Stage - Two Under Construction of two Type-I MPCS IDA / 56930 Post Request for Bids Open - National 1,380,000.00 0.00 2017-05-03 2017-06-19 2017-05-08 2017-06-23 2017-06-19 2017-09-01 2017-10-06 2018-10-06 Infrastructure Envelope Implementation in Gir Somnath (GS-14R) IN-GSDMA-4731-CW-RFB / Cyclone Risk Mitigation Single Stage - Two Under Construction of three Type-II IDA / 56930 Post Request for Bids Open - National 2,550,000.00 0.00 2017-05-03 2017-07-24 2017-05-08 2017-08-03 2017-06-19 2017-09-01 2017-10-06 2018-12-30 Infrastructure Envelope Implementation MPCS in Gir Somnath (GS-12R) IN-GSDMA-4729-CW-RFB / Cyclone Risk Mitigation Single Stage - Two Pending Construction of two Type-II IDA / 56930 Post Request for Bids Open - National 1,700,000.00 0.00 2017-07-03 2017-07-08 2017-08-19 2017-11-01 2017-12-06 2019-03-01 Infrastructure Envelope Implementation MPCS in Gir Somnath (GS-07R) IN-GSDMA-13468-CW-RFB / Cyclone Risk Mitigation Single Stage - Two Under Construction of two Type II IDA / 56930 Post Request for Bids Open - National 1,740,000.00 0.00 2017-06-03 2017-07-24 2017-06-08 2017-08-03 2017-07-20 2017-10-02 2017-11-06 2019-01-30 Infrastructure Envelope Implementation MPCS in Gir Somnath (GS-08R) IN-GSDMA-13470-CW-RFB / Cyclone Risk Mitigation Single Stage - Two Under Construction of two Type II IDA / 56930 Post Request for Bids Open - National 1,740,000.00 0.00 2017-06-03 2017-07-24 2017-06-08 2017-08-03 2017-07-20 2017-10-02 2017-11-06 2019-01-30 Infrastructure Envelope Implementation MPCS in Gir Somnath (GS-11R) IN-GSDMA-13481-CW-RFB / Cyclone Risk Mitigation Single Stage - Two Under Construction of three Type I IDA / 56930 Post Request for Bids Open - National 2,136,500.00 0.00 2017-06-03 2017-06-19 2017-06-08 2017-06-23 2017-07-20 2017-10-02 2017-11-06 2018-10-02 Infrastructure Envelope Implementation MPCS in Gir Somnath (GS-15R) IN-GSDMA-13482-CW-RFB / Cyclone Risk Mitigation Single Stage - Two Under Construction of two Type I MPCS IDA / 56930 Post Request for Bids Open - National 1,425,000.00 0.00 2017-06-03 2017-06-19 2017-06-08 2017-06-23 2017-07-20 2017-10-02 2017-11-06 2018-10-02 Infrastructure Envelope Implementation in Gir Somnath (GS-16R) IN-GSDMA-13483-CW-RFB / Cyclone Risk Mitigation Single Stage - Two Under Construction of two Type I MPCS IDA / 56930 Post Request for Bids Open - National 1,425,000.00 0.00 2017-06-03 2017-06-19 2017-06-08 2017-06-23 2017-07-20 2017-10-02 2017-11-06 2018-10-02 Infrastructure Envelope Implementation in Gir Somnath (GS-17R) Page 4 IN-GSDMA-13488-CW-RFB / Cyclone Risk Mitigation Single Stage - Two Under Construction of two Type I MPCS IDA / 56930 Post Request for Bids Open - National 1,425,000.00 0.00 2017-06-03 2017-06-03 2017-06-08 2017-06-16 2017-07-20 2017-10-02 2017-11-06 2018-10-02 Infrastructure Envelope Implementation in Gir Somnath (GS-20) IN-GSDMA-13491-CW-RFB / Cyclone Risk Mitigation Single Stage - Two Under Construction of two Type I MPCS IDA / 56930 Post Request for Bids Open - National 1,425,000.00 0.00 2017-07-03 2017-06-19 2017-07-08 2017-06-23 2017-08-19 2017-11-01 2017-12-06 2018-11-01 Infrastructure Envelope Implementation in Gir Somnath (GS-22) IN-GSDMA-13494-CW-RFB / Cyclone Risk Mitigation Single Stage - Two Under Construction of one Type II IDA / 56930 Post Request for Bids Open - National 870,000.00 0.00 2017-06-03 2017-07-24 2017-06-08 2017-08-03 2017-07-20 2017-10-02 2017-11-06 2019-01-30 Infrastructure Envelope Implementation MPCS in Gir Somnath (GS-23) IN-GSDMA-13495-CW-RFB / Cyclone Risk Mitigation Single Stage - Two Under Construction of two Type II IDA / 56930 Post Request for Bids Open - National 1,740,000.00 0.00 2017-06-03 2017-07-18 2017-06-08 2017-08-05 2017-07-20 2017-10-02 2017-11-06 2019-01-30 Infrastructure Envelope Implementation MPCS in Jungadh (JND-06R) IN-GSDMA-13497-CW-RFB / Cyclone Risk Mitigation Single Stage - Two Under Construction of one Type II IDA / 56930 Post Request for Bids Open - National 870,000.00 0.00 2017-06-03 2017-07-18 2017-06-08 2017-08-05 2017-07-20 2017-10-02 2017-11-06 2019-01-30 Infrastructure Envelope Implementation MPCS in Jungadh (JND-11) IN-GSDMA-13499-CW-RFB / Construction of three Type I Cyclone Risk Mitigation Single Stage - Two Under IDA / 56930 Post Request for Bids Open - National 2,136,500.00 0.00 2017-06-03 2017-07-24 2017-06-08 2017-08-05 2017-07-20 2017-10-02 2017-11-06 2018-10-02 MPCS in Devbhumi Dwarka (DD- Infrastructure Envelope Implementation 1) IN-GSDMA-13506-CW-RFB / Cyclone Risk Mitigation Single Stage - Two Under Construction of three Type I IDA / 56930 Post Request for Bids Open - National 2,136,500.00 0.00 2017-06-03 2017-07-05 2017-06-08 2017-07-12 2017-07-20 2017-10-02 2017-11-06 2018-10-02 Infrastructure Envelope Implementation MPCS in Porbandar (PBR-01) IN-GSDMA-13469-CW-RFB / Cyclone Risk Mitigation Single Stage - Two Under Construction of two Type I MPCS IDA / 56930 Post Request for Bids Open - National 1,425,000.00 0.00 2017-07-03 2017-06-12 2017-07-08 2017-06-16 2017-08-19 2017-11-01 2017-12-06 2018-11-01 Infrastructure Envelope Implementation in Gir Somnath (GS-10R) IN-GSDMA-13486-CW-RFB / Cyclone Risk Mitigation Single Stage - Two Under Construction of one Type II IDA / 56930 Post Request for Bids Open - National 870,000.00 0.00 2017-06-03 2017-07-24 2017-06-08 2017-08-03 2017-07-20 2017-10-02 2017-11-06 2019-01-30 Infrastructure Envelope Implementation MPCS in Gir Somnath (GS-18R) IN-GSDMA-13489-CW-RFB / Cyclone Risk Mitigation Single Stage - Two Under Construction of two Type II IDA / 56930 Post Request for Bids Open - National 1,740,000.00 0.00 2017-06-03 2017-07-24 2017-06-08 2017-08-03 2017-07-20 2017-10-02 2017-11-06 2019-01-30 Infrastructure Envelope Implementation MPCS in Gir Somnath (GS-21) IN-GSDMA-13510-CW-RFB / Cyclone Risk Mitigation Single Stage - Two Under Construction of one Type II IDA / 56930 Post Request for Bids Open - National 870,000.00 0.00 2017-06-03 2017-07-15 2017-06-08 2017-07-20 2017-07-20 2017-10-02 2017-11-06 2019-01-30 Infrastructure Envelope Implementation MPCS in Porbandar (PBR-03R) IN-GSDMA-13515-CW-RFB / Cyclone Risk Mitigation Single Stage - Two Under Construction of two Type I MPCS IDA / 56930 Post Request for Bids Open - National 1,425,000.00 0.00 2017-06-03 2017-07-05 2017-06-08 2017-07-11 2017-07-20 2017-10-02 2017-11-06 2018-10-02 Infrastructure Envelope Implementation in Amreli (AMR-01) IN-WRD-GOA-15969-CW-RFB / Construction of Multi-Purpose Cyclone Shelter (G+2) at Survey Cyclone Risk Mitigation Single Stage - Two Pending IDA / 56930 Post Request for Bids Open - National 399,141.00 0.00 2017-06-19 2017-06-23 2017-07-28 2017-09-22 2017-10-27 2019-04-20 No. 122/1 of Zuarinagar in V.P. Infrastructure Envelope Implementation Sancoale of Mormugao Taluka, South Goa IN-WRD-GOA-947-CW-RFB / Construction of Multi-Purpose Cyclone Shelter (G+2) at Survey Cyclone Risk Mitigation Single Stage - Two Pending IDA / 56930 Post Request for Bids Open - National 402,365.00 0.00 2017-06-19 2017-06-23 2017-07-28 2017-09-22 2017-10-27 2019-04-20 No. 76/1 of Chapoli in V.P. Infrastructure Envelope Implementation Shristal of Canacona Taluka, South Goa IN-WRD-GOA-951-CW-RFB / Construction of Multi-Purpose Cyclone shelter (G+2) at Survey Cyclone Risk Mitigation Single Stage - Two Pending IDA / 56930 Post Request for Bids Open - National 351,901.00 0.00 2017-06-19 2017-06-23 2017-07-28 2017-09-22 2017-10-27 2019-04-20 No. 137/17 of Mahalwada V.P. Infrastructure Envelope Implementation Poinguinim of Canacona Taluka, South Goa IN-WRD-GOA-955-CW-RFB / Construction of Multi-Purpose Cyclone shelter (G+2) at Survey Cyclone Risk Mitigation Single Stage - Two Pending No. 128/2, of Nagarcem in the IDA / 56930 Post Request for Bids Open - National 382,112.00 0.00 2017-06-19 2017-06-23 2017-07-28 2017-09-22 2017-10-27 2019-04-20 Infrastructure Envelope Implementation jurisdiction of Canacona Municipal Council, Canacona Taluka, South Goa IN-WRD GOA-18063-CW-RFB / Construction of Multi-Purpose Cyclone Shelter (G+2) at Survey Cyclone Risk Mitigation Single Stage - Two Pending IDA / 56930 Post Request for Bids Open - National 513,822.00 0.00 2017-06-19 2017-06-23 2017-07-28 2017-09-22 2017-10-27 2019-04-20 No. 117/1 of Cuelim in V.P. Infrastructure Envelope Implementation Cuelim of Mormugao Taluka, South Goa IN-WRD GOA-18065-CW-RFB / Construction of Multipurpose Cyclone Risk Mitigation Single Stage - Two Pending Cyclone Shelter (MPCS) Pilerne IDA / 56930 Post Request for Bids Open - National 388,550.00 0.00 2017-06-19 2017-06-23 2017-07-28 2017-09-22 2017-10-27 2019-04-20 Infrastructure Envelope Implementation under Survey no. 115/1 in Saligao village, Bardez-Goa IN-GSDMA-21129-CW-RFB / Cyclone Risk Mitigation Single Stage - Two Under Construction of two Type-I MPCS IDA / 56930 Post Request for Bids Open - National 1,150,000.00 0.00 2017-08-01 2017-07-17 2017-08-06 2017-07-29 2017-09-17 2017-11-30 2018-01-04 2018-07-03 Infrastructure Envelope Implementation in Porbandar District (PBR-02R) IN-GSDMA-23772-CW-RFB / Construction of Multi Purpose Cyclone Shelters at Vadodara Cyclone Risk Mitigation Single Stage - Two Pending IDA / 56930 Post Request for Bids Open - National 1,184,620.00 0.00 2017-08-10 2017-08-15 2017-09-26 2017-12-09 2018-01-13 2018-07-12 Jhala and Singsar in Sutrapada Infrastructure Envelope Implementation taluka in Gir Somnath District GS-15 GOODS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 5 IN-KSDMA-402-GO-RFQ / Procurement of Office Project Management and Request for Single Stage - One Pending IDA / 56930 Post Open - National 40,000.00 0.00 2016-10-08 2016-12-03 2017-06-01 equipement to State Project Implementation Support Quotations Envelope Implementation Implementation Unit IN-WRD- GOA-913-GO-RFQ / Project Management and Request for Single Stage - One Pending Procurement of survey IDA / 56930 Post Limited 30,000.00 0.00 2016-10-01 2016-11-26 2017-05-25 Implementation Support Quotations Envelope Implementation instruments IN-DRM-KAR-1190-GO-RFQ / Purchase of office equipment and Project Management and Request for Single Stage - One Pending IDA / 56930 Post Open - National 20,000.00 0.00 2016-11-05 2016-12-31 2017-06-29 stationary, computers, laptops, Implementation Support Quotations Envelope Implementation etc for SPIU IN-DRM-KAR-1189-CW-RFB / Early Warning Dissemination Single Stage - Two Pending Implementation of EWDS in three IDA / 56930 Prior Request for Bids Open - National 1,850,000.00 0.00 2017-09-30 2017-10-05 2017-11-16 2018-01-29 2018-03-05 2018-09-01 Systems Envelope Implementation coastal districts. IN-DRM-KAR-1184-GO-DIR / Furnishing and renovation of Project Management and IDA / 56930 Post Direct Selection Direct 30,000.00 0.00 Canceled 2016-10-31 2016-11-05 2016-12-10 2017-06-08 SPIU and Implementing agencies Implementation Support office IN-GSDMA-2597-GO-RFB / Early Warning Dissemination Single Stage - Two Pending IDA / 56930 Prior Request for Bids Open - International 3,300,000.00 0.00 2017-11-01 2017-11-06 2017-12-18 2018-03-02 2018-04-06 2018-10-03 Procurement of EWDS Systems Envelope Implementation IN-RRD-MAH-2649-GO-RFB / Project Management and Request for Single Stage - One Pending Purchase of Engineering Design IDA / 56930 Post Open - National 99,000.00 0.00 2016-11-12 2017-01-07 2017-02-06 Implementation Support Quotations Envelope Implementation & survey equipments IN-RRD-MAH-2651-GO-RFQ / Project Management and Request for Single Stage - One Pending IDA / 56930 Post Open - National 82,000.00 0.00 2016-11-15 2017-01-10 2017-02-09 Procurement of Office equipment Implementation Support Quotations Envelope Implementation IN-RRD-MAH-2653-GO-RFB / Early Warning Dissemination Single Stage - Two Pending Supply & installation of EWDS IDA / 56930 Prior Request for Bids Open - International 4,400,000.00 0.00 2017-09-01 2017-09-06 2017-10-18 2017-12-31 2018-02-04 2018-11-01 Systems Envelope Implementation system in Maharashtra. IN-DMD-WB-2700-GO-RFB / Procurement of the equipment, installation, training of users and Early Warning Dissemination Single Stage - Two Pending IDA / 56930 Prior Request for Bids Open - International 3,300,000.00 0.00 2017-09-01 2017-09-06 2017-10-18 2017-12-31 2018-02-04 2019-12-26 commissioning and maintenance Systems Envelope Implementation during the warranty for the early warning dissemination systm IN-RRD-MAH-3348-GO-RFQ / Project Management and Request for Single Stage - One Under IDA / 56930 Post Open - National 60,000.00 0.00 2016-12-20 2017-02-14 2017-08-13 Procurement of office furniture Implementation Support Quotations Envelope Implementation IN-KSDMA-404-GO-RFP / Project Management and Single Stage - One Pending Procurement of Generators for IDA / 56930 Post Request for Bids Open - National 210,000.00 0.00 2017-11-15 2017-11-20 2018-01-01 2018-01-31 2018-03-07 2018-09-03 Implementation Support Envelope Implementation Multi Purpose Cyclone Shelters NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-KSDMA-301-NC-RFQ / Hiring Non consulting services for Project Management and Request for Single Stage - One Pending IDA / 56930 Post Open - National 7,500.00 0.00 2016-08-27 2016-10-22 2017-04-20 conducting Survey using Total Implementation Support Quotations Envelope Implementation Station IN-KSDMA-304-NC-RFQ / Hiring a vehicle to State Project Project Management and Request for Single Stage - One Pending IDA / 56930 Post Open - National 30,000.00 0.00 2016-12-03 2017-01-28 2017-07-27 Implementation Unit for the Implementation Support Quotations Envelope Implementation project period IN-WRD-GOA-917-NC-RFQ / Project Management and Request for Single Stage - One Pending IDA / 56930 Post Limited 60,000.00 0.00 2016-09-10 2016-10-24 2017-04-22 Hiring of Vehicles for project use Implementation Support Quotations Envelope Implementation IN-WRD-GOA-958-NC-RFQ / Project Management and Request for Single Stage - One Pending Preparation of survey Report For IDA / 56930 Post Limited 10,000.00 0.00 2016-10-29 2016-12-24 2017-06-22 Implementation Support Quotations Envelope Implementation Saline Embankments IN-DRM-KAR-1196-NC-RFQ / Project Management and Request for Single Stage - One Pending Hiring of vehicles on contract for IDA / 56930 Post Open - National 50,000.00 0.00 2016-11-05 2016-12-31 2017-06-29 Implementation Support Quotations Envelope Implementation SPIU officers IN-RRD-MAH-2646-NC-RFQ / Project Management and Request for Single Stage - One Pending IDA / 56930 Post Open - National 20,000.00 0.00 2017-01-07 2017-03-04 2018-03-04 Hiring of Speed boat Implementation Support Quotations Envelope Implementation IN-KSDMA-102-NC-RFQ / Soil Project Management and Request for Single Stage - One Investigation Work for 22 MPCS IDA / 56930 Post Open - National 50,000.00 42,722.98 Signed 2017-07-18 2017-09-14 2017-08-01 2018-08-08 Implementation Support Quotations Envelope in 9 coastal districts of Kerala. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Early Warning Dissemination Systems Pkg NCRMP-II/WB/CONS Project Management and 1/TPQA / Selection of Third Party Implementation Support Quality And Cost- IDA / 56930 Prior Open - International 1,000,000.00 874,669.18 Signed 2016-01-29 2016-01-25 Quality Auditor (TPQA) for SPIU - Technical Assistance for Multi- Based Selection West Bengal. Hazard Risk Management Cyclone Risk Mitigation Infrastructure Page 6 Early Warning Dissemination Systems NCRMP/PMSC/01 / Project Management and Appointment of Project Implementation Support Quality And Cost- Management Support IDA / 56930 Prior Open - International 565,000.00 694,647.36 Signed 2015-08-05 2016-01-30 Technical Assistance for Multi- Based Selection Consultants (PMSC) for NCRMP Hazard Risk Management II - Gujarat Cyclone Risk Mitigation Infrastructure IN-KSDMA-101-CS-QCBS / Project Management and Quality And Cost- Pending Hiring Third Party Auditing IDA / 56930 Post Open - International 700,000.00 0.00 2016-11-22 2016-12-13 2017-01-26 2017-02-23 2017-03-25 2017-04-29 2017-06-03 2018-06-03 Implementation Support Based Selection Implementation services for the project IN-WRD- GOA-902-CS-QCBS / Project Management and Quality And Cost- Under Selection of Third Party Quality IDA / 56930 Prior Open - International 520,000.00 0.00 2016-09-12 2017-01-17 2016-10-03 2017-02-02 2016-11-16 2017-07-13 2016-12-14 2017-01-13 2017-02-17 2017-03-24 2019-09-30 Implementation Support Based Selection Implementation Auditors in Goa IN-WRD-GOA-941-CS-QCBS / Project Management and Quality And Cost- Under IDA / 56930 Post Open - National 25,000.00 0.00 2016-09-26 2016-12-29 2016-10-17 2017-02-02 2016-11-30 2016-12-28 2017-01-27 2017-03-03 2017-04-07 2018-04-07 Selection of Internal Auditor Implementation Support Based Selection Implementation IN-KSDMA-103-CS-QCBS / Project Management and Quality And Cost- Under Engagement of Internal Audit IDA / 56930 Post Open - National 300,000.00 0.00 2016-11-29 2016-12-20 2016-12-20 2017-02-02 2017-02-23 2017-03-02 2017-04-01 2017-05-06 2017-06-10 2018-06-10 Implementation Support Based Selection Implementation services IN-DRM-KAR-1067-CS-CQS / Consultant Hiring structural consultant to Cyclone Risk Mitigation Pending IDA / 56930 Post Qualification Open - National 20,000.00 0.00 2016-09-30 2016-10-21 2016-12-04 2017-01-03 2017-02-07 2017-08-06 assist engineers in designing Infrastructure Implementation Selection MPCS IN-DRM-KAR-1068-CS-CQS / Consultant Hiring of structural engineering to Cyclone Risk Mitigation Pending IDA / 56930 Post Qualification Open - National 10,000.00 0.00 2016-09-30 2016-10-21 2016-12-04 2017-01-03 2017-02-07 2017-08-06 assist engineering with bridge Infrastructure Implementation Selection design IN-DRM-KAR-1069-CS-CQS / Consultant Hiring services of consultant for Cyclone Risk Mitigation Pending IDA / 56930 Post Qualification Open - National 20,000.00 0.00 2016-09-30 2016-10-21 2016-12-04 2017-01-03 2017-02-07 2017-08-06 assisting engineers in road Infrastructure Implementation Selection design IN-DRM-KAR-274-CS-QCBS / Selection of Consultant for conducting Environmental Impact Cyclone Risk Mitigation Quality And Cost- Under IDA / 56930 Post Open - National 80,000.00 0.00 2016-09-15 2017-01-12 2016-10-06 2017-01-16 2016-11-19 2016-12-17 2017-01-16 2017-02-20 2017-03-27 2018-03-27 Assessment (EIA) for Infrastructure Based Selection Implementation construction of Saline Embankment IN-WRD-GOA-942-CS-QCBS / Selection of Consultants for Project Management and Quality And Cost- Environment & Social IDA / 56930 Post Open - National 40,000.00 0.00 Canceled 2016-12-05 2016-12-26 2017-02-08 2017-03-08 2017-04-07 2017-05-12 2017-06-16 2018-06-16 Implementation Support Based Selection Assessment for NCRMP II in the State of Goa IN-DRMKAR-343-CS-QCBS / Hiring of THIRD PARTY QUALITY Project Management and Quality And Cost- Pending IDA / 56930 Post Open - International 150,000.00 0.00 2016-09-29 2016-10-20 2016-12-03 2016-12-31 2017-01-30 2017-03-06 2017-04-10 2018-04-10 AUDITOR FOR NCRMP-II in Implementation Support Based Selection Implementation Karnataka IN-DRM-KAR-2594-CS-QCBS / Hiring of internal auditor to audit Project Management and Quality And Cost- Under IDA / 56930 Post Open - National 85,000.00 0.00 2016-12-31 2016-12-20 2017-01-21 2017-03-06 2017-04-03 2017-05-03 2017-06-07 2017-07-12 2019-12-31 finances of SPIU and District Implementation Support Based Selection Implementation implementation unit Consultant IN-RRD-MAH-2645-CS-CQS / Project Management and Under IDA / 56930 Post Qualification Open - National 100,000.00 0.00 2017-01-02 2016-12-09 2017-01-23 2017-03-08 2017-04-07 2017-05-12 2019-10-31 Engagement of Internal Auditor Implementation Support Implementation Selection IN-DMD -WB-2695-CS-QCBS / A Technical Services Provider for the management of the contract to install an Early Warning Project Management and Quality And Cost- Under Disaster Management System IDA / 56930 Post Open - International 150,000.00 0.00 2016-11-18 2017-01-31 2016-12-09 2017-07-18 2017-01-22 2017-02-19 2017-03-21 2017-04-25 2017-05-30 2019-09-17 Implementation Support Based Selection Implementation which will develop the strategy, develop the bid document and the contract till the expiry of the warranty period IN-RRD-MAH-3358-CS-QCBS / Selection of Project Management Project Management and Quality And Cost- Under IDA / 56930 Prior Open - International 900,000.00 0.00 2016-11-15 2017-02-03 2016-12-06 2017-01-19 2017-03-15 2017-02-16 2016-08-23 2017-03-18 2017-04-22 2017-05-27 2020-05-26 Consultant(PMC) for NCRMP-II Implementation Support Based Selection Implementation Maharashtra IN-RRD-MAH-3362-CS-QCBS / Selection of consulting firm for providing services of Project Management and Quality And Cost- Under Environmental and Social Impact IDA / 56930 Post Open - National 250,000.00 0.00 2016-11-15 2016-12-06 2017-01-19 2017-02-16 2017-03-18 2017-04-22 2017-05-27 2017-11-25 Implementation Support Based Selection Implementation Assessment Consultancy for Saline Embankment and Underground Cabling IN-RRD-MAH-3367-CS-QCBS / Selection of consulting firm for providing Micro level DGPS (Differential Global Positioning System) Project Management and Quality And Cost- Pending IDA / 56930 Post Open - National 300,000.00 0.00 2016-11-15 2016-12-06 2017-01-19 2017-02-16 2017-03-18 2017-04-22 2017-05-27 2017-08-25 survey for Maharashtra State Implementation Support Based Selection Implementation Electricity Distribution Company LTD (MSDCEL) in the state of Maharashtra. IN-RRD-MAH-271-CS-QCBS / Selection of consultating Firm Project Management and Quality And Cost- Under IDA / 56930 Post Open - International 800,000.00 0.00 2016-08-11 2016-09-01 2016-10-15 2016-11-12 2016-12-12 2017-01-16 2017-02-20 2019-08-21 for providing Third Party Quality Implementation Support Based Selection Implementation Audit (TPQA) IN-GSDMA-4541-CS-QCBS / Design and Supervision Project Management and Quality And Cost- Under Consultants (DSC) for IDA / 56930 Prior Open - International 1,538,500.00 0.00 2017-01-11 2017-01-17 2017-02-01 2017-01-24 2017-03-17 2017-04-04 2017-04-14 2017-05-14 2017-06-18 2017-07-23 2019-07-23 Implementation Support Based Selection Implementation Component B-1 (MPCS) and B-2 (Missing Roads & Bridges) Page 7 IN-GSDMA-5613-CS-QCBS / Appointment of Consultancy Services for conducting Environment Impact Assessment (EIA), Social Impact Assessment Project Management and Quality And Cost- Under IDA / 56930 Post Open - National 150,000.00 0.00 2017-01-16 2016-05-30 2017-02-06 2017-01-12 2017-03-22 2016-11-07 2017-04-19 2016-12-09 2017-05-19 2016-12-20 2017-06-23 2017-07-28 2017-11-25 (SIA) and preparation of Implementation Support Based Selection Implementation Environment Management Plans (EMP) & Resettlement Action Plans for Underground Cabling in Gandhidham-Adipur (Kutch). IN-WRD-GOA-9081-CS-CQS / NCRMP II - Soil Exploration for Consultant Project Management and Improvement to Saline IDA / 56930 Post Qualification Open - National 40,000.00 36,994.72 Signed 2017-03-04 2017-03-08 2017-03-25 2017-05-08 2017-03-30 2017-06-07 2017-04-14 2017-07-12 2017-04-14 2018-01-08 Implementation Support Embankment at Diwar Island & Selection Poinguinim, Goa IN-GSDMA-8548-CS-LCS / Appointment of Internal Auditor Project Management and Under for NCRMP II in Gujarat for the IDA / 56930 Post Least Cost Selection Open - National 95,000.00 0.00 2017-03-08 2017-03-03 2017-03-29 2017-04-01 2017-05-12 2017-06-16 2017-06-09 2017-07-09 2017-08-13 2017-09-17 2019-06-30 Implementation Support Implementation audit period April 1, 2017 to March 31, 2019. IN-NDMA-8677-CS-QCBS / Selection of Consultant for development of Dynamic Web Based Composite Risk Atlas and Technical Assistance for Multi- Quality And Cost- Under IDA / 56930 Post Open - National 295,800.00 0.00 2017-05-15 2017-05-11 2017-06-05 2017-06-23 2017-07-19 2017-08-16 2017-09-15 2017-10-20 2017-11-24 2018-11-24 Decision Support Tool for Hazard Risk Management Based Selection Implementation Cyclone and associated impacts including Storm Surge and Inland Flooding under NCRMP-II IN-DRM-KAR-2593-CS-QCBS / Hiring of Consultant to assist Early Warning Dissemination Quality And Cost- IDA / 56930 Post Open - National 170,000.00 0.00 Canceled 2016-11-30 2017-04-17 2016-12-21 2017-02-03 2017-03-03 2017-04-02 2017-05-07 2017-06-11 2019-12-11 KSNDMC in implementing Systems Based Selection EWDS in three coastal districts IN-GSDMA-18968-CS-CQS / Consultant Appointment of External Auditor Project Management and Under IDA / 56930 Post Qualification Open - National 50,000.00 0.00 2017-07-10 2017-07-10 2017-07-31 2017-09-13 2017-10-13 2017-11-17 2018-11-17 for the audit period April 1, 2017 Implementation Support Implementation Selection to March 31, 2019 for NCRMP-II INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Contract Type Estimated Actual Amount Draft Negotiated Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Early Warning Dissemination NCRMP/DSC/FRP/03 / Systems Appointment of Design and Project Management and Supervision Consultants (DSC) Implementation Support Under for Multi-Purpose Cyclone IDA / 56930 Prior Direct Selection Direct 620,462.00 669,230.66 Technical Assistance for Multi- Implementation Shelters (MPCS), Missing Roads Hazard Risk Management and Bridges for NCRMP II - Cyclone Risk Mitigation Gujarat Infrastructure IN-WRD-GOA-924-CS-INDV / Project Management and Individual Consultant Under IDA / 56930 Post Open - National 10,154.00 0.00 2016-09-05 2017-02-07 2016-10-24 2016-11-14 2016-12-19 2017-06-17 Hiring of MIS Specialist 1 number Implementation Support Selection Implementation IN-WRD-GOA-926-CS-INDV / Project Management and Individual Consultant Under Financial Management Specialist IDA / 56930 Post Open - National 10,154.00 0.00 2016-09-05 2016-06-08 2016-10-24 2016-11-14 2016-12-19 2017-06-17 Implementation Support Selection Implementation 1 number IN-WRD-GOA-927-CS-INDV / Project Management and Individual Consultant Under IDA / 56930 Post Open - National 7,615.00 0.00 2016-09-05 2016-06-15 2016-10-24 2016-11-14 2016-12-19 2017-06-17 Appointment of Accountant Implementation Support Selection Implementation IN-WRD-GOA-944-CS-INDV / Selection of Structural consultant Project Management and Individual Consultant Pending IDA / 56930 Post Open - National 40,000.00 0.00 2016-11-21 2017-01-09 2017-01-30 2017-03-06 2017-09-02 for Multi Purpose Construction Implementation Support Selection Implementation Shelter IN-WRD-GOA-2490-CS-CDS / Conducting Environmental & Project Management and Social Impact Assessment for IDA / 56930 Post Direct Selection Direct 18,000.00 14,710.07 Signed 2016-10-14 2016-10-10 2016-10-24 2016-10-11 2016-12-28 2016-11-18 2017-06-26 Implementation Support Saline Embankment at two locations IN-DRM-KAR-1070-CS-CQS / Hiring structural engineer to Cyclone Risk Mitigation Individual Consultant Pending IDA / 56930 Post Open - National 10,000.00 0.00 2016-10-31 2017-02-03 2017-03-10 2017-09-06 assist engineers in designing Infrastructure Selection Implementation saline embankment IN-WRD-GOA-4519-CS-CDS / Appointment of Consultant for Component A Development of Project Management and Last Mile Connectivity and Early IDA / 56930 Prior Direct Selection Direct 250,000.00 234,278.32 Signed 2016-12-20 2017-02-03 2016-12-30 2017-02-06 2017-03-05 2017-05-15 2017-09-01 Implementation Support Warning Dissemination System and Capacity building for Coastal Communities in Goa IN-R&RD-MAH-4988-CS-CDS / Project Management and Under IDA / 56930 Prior Direct Selection Direct 150,000.00 0.00 2017-02-06 2017-03-01 2017-02-16 2017-04-22 2017-10-19 Hiring of consultant for EWDS Implementation Support Implementation IN-WRD-GOA-929-CS-INDV / Project Management and Individual Consultant Consulting Civil Engineer 1 IDA / 56930 Post Open - National 10,154.00 0.00 Canceled 2016-09-05 2016-10-24 2016-11-14 2016-12-19 2017-06-17 Implementation Support Selection number IN-DRM-KAR-13542-CS-CDS / Hiring consultant to assist Early Warning Dissemination Under IDA / 56930 Post Direct Selection Direct 170,000.00 0.00 2017-04-27 2017-04-28 2017-05-07 2017-05-15 2017-07-11 2018-01-07 KSNDMC in implementing Systems Implementation Component A IN-WRD-GOA-920-CS-INDV / Procurement of Sector Expert- IT Specialist for consultancy in Project Management and Individual Consultant Pending State Project Implementation IDA / 56930 Post Open - National 13,000.00 0.00 2017-06-22 2017-08-10 2017-08-31 2017-10-05 2018-08-31 Implementation Support Selection Implementation Unit (SPIU) for National Cyclone Risk Mitigation Project (NCRMP)- II, Goa - 1 No Page 8 IN-WRD GOA-5239-CS-INDV / Procurement of Sector Expert- Environment Expert for Project Management and Individual Consultant Pending consultancy in State Project IDA / 56930 Post Open 12,000.00 0.00 2017-06-22 2017-08-03 2017-08-24 2017-09-28 2018-08-24 Implementation Support Selection Implementation Implementation Unit (SPIU) for National Cyclone Risk Mitigation Project (NCRMP)-II, Goa - 1 No IN-WRD GOA-5240-CS-INDV / Procurement of Sector Expert- GIS Consultant for consultancy Project Management and Individual Consultant Pending in State Project Implementation IDA / 56930 Post Open 12,000.00 0.00 2017-01-03 2017-08-03 2017-08-24 2017-09-28 2018-08-24 Implementation Support Selection Implementation Unit (SPIU) for National Cyclone Risk Mitigation Project (NCRMP)- II, Goa - 1 No IN-WRD GOA-5241-CS-INDV / Procurement of Sector Expert- Electrical Engineer for Project Management and Individual Consultant Pending consultancy in State Project IDA / 56930 Post Open 24,000.00 0.00 2017-01-03 2017-09-01 2017-09-22 2017-10-27 2018-09-22 Implementation Support Selection Implementation Implementation Unit (SPIU) for National Cyclone Risk Mitigation Project (NCRMP)-II, Goa - 2 Nos IN-WRD-GOA-5242-CS-INDV / Procurement of Sector Expert- Civil Engineer for consultancy in Project Management and Individual Consultant Pending State Project Implementation IDA / 56930 Post Open 56,000.00 0.00 2017-01-03 2017-09-01 2017-09-22 2017-10-27 2018-09-22 Implementation Support Selection Implementation Unit (SPIU) for National Cyclone Risk Mitigation Project (NCRMP)- II, Goa - 5 Nos IN-WRD GOA-18073-CS-CQS / Procurement of Sector Expert- Social Expert for consultancy in Project Management and Individual Consultant Pending State Project Implementation IDA / 56930 Post Open 12,000.00 0.00 2017-06-22 2017-09-11 2017-10-16 2018-09-11 Implementation Support Selection Implementation Unit (SPIU) for National Cyclone Risk Mitigation Project (NCRMP)- II, Goa IN-WRD GOA-18078-CS-INDV / Procurement of Sector Expert- Senior Auditor for consultancy for forming CSMMC and bye-laws for Project Management and Individual Consultant Pending IDA / 56930 Post Open 12,000.00 0.00 2017-07-20 2017-09-07 2017-09-28 2017-11-02 2018-09-28 each MPCS in State Project Implementation Support Selection Implementation Implementation Unit (SPIU) for National Cyclone Risk Mitigation Project (NCRMP)-II, Goa Page 9