PROCUREMENT PLAN (Textual Part) Project information: Democratic Republic Democratic of Congo: Strengthening PFM And Accountability Project (P145747) Project Implementation Agency : Ministry of Finances, Comité d’Orientation des Réformes des Finances Publiques (COREF) Date of the Procurement Plan: January 25, 2018 Period covered by this Procurement Plan: January – December 2018 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Borrower’s Procurement Code of April 27, 2010, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. (a) Standard Bidding Documents: All standard bidding documents to be used for the Project under NCB shall be found acceptable to the World Bank before their use during the implementation of Project; (b) Eligibility: Eligibility of bidders and acceptability of their goods and services shall not be based on their nationality and/or their origin; and association with a national firm shall not be a condition for participation in a bidding process. Therefore, except for the ineligibility situations referred to in paragraphs 1.10(a) (i) and 1.10(a) (ii) of the Procurement Guidelines, the eligibility of bidders must be based solely on their qualification, experience and capacity to carry out the contract related to the specific bidding process; (c) Advertising and Bid Preparation Time: Bidding opportunities shall be advertised at least in a national newspaper of wide circulation and on the website of the Recipient’s Procurement Regulator (Autorité de Régulation des Marchés Publics) and bidders should be given at least 30 days from the date of invitation to bid or the date of availability of the bidding documents, whichever is later; (d) Criteria for Qualification of Bidders: Qualification criteria shall only concern the bidder’s capability and resources to perform the contract taking into account objective and measurable factors. Such criteria for qualification of bidders shall be clearly specified in the bidding documents; (e) Bid Evaluation and Contract Award: A contract shall be awarded to the substantially responsive and lowest evaluated bidder provided that such bidder meets the qualification criteria specified in the bidding documents. No scoring system shall be allowed for the evaluation of bids, and no “blanket” limitation to the number of lots which can be awarded to a bidder shall apply. The criteria for bid evaluation and the contract award conditions shall be clearly specified in the bidding documents; (f) Preferences: No preference shall be given to domestic/regional bidders; to domestically/regionally manufactured goods; and to bidders forming a joint venture with a national firm or proposing national sub-contractors or carrying out economic activities in the territory of the Recipient; (g) Publication of Contract Award: Information on all contract awards shall be published in at least a national newspaper of wide circulation or in the Recipient’s Procurement Regulator (Autorité de Régulation des Marchés Publics) web-site; (h) Fraud and Corruption: In accordance with the Procurement Guidelines, each bidding document and contract shall include provisions stating the World Bank’s policy to sanction firms or individuals found to have engaged in fraud and corruption as set forth in the Procurement Guidelines; (i) Inspection and Audit Rights: In accordance with the Procurement Guidelines, each bidding document and contract shall include provisions stating the World Bank’s policy with respect to inspection and audit of accounts, records and other documents relating to the bid submission and contract performance; (j) Requirement for administrative documents and/or tax clearance certificate: The bidding documents shall not require foreign bidders to produce any administrative or tax related certificates prior to confirmation of awarding a contract; and (k) Modifications of a Signed Contract: Any change in the contract amount which, singly or combined with all previous changes, increases the original contract amount by fifteen (15) percent or more must be done through an amendment to the signed contract instead of signing a new contract. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is applicable for those contracts identified in the Procurement Plan tables; Other Relevant Procurement Information. “Not Applicable” PROCUREMENT Congo, Democratic Republic of : DRC: Strengthening PFM and Accountability PLAN General Information Country: Congo, Democratic Republic of Bank’s Approval Date of the Original Procurement Plan: 2018-02-07 2020-02-10 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P145747 GPN Date: Project Name: DRC: Strengthening PFM and Accountability Loan / Credit No: IDA / D1650, IDA / H9070 Executing Agency(ies): Comité d'Orientation de la Reforme des Finances Publiques WORKS Bid Evaluation Activity Reference No. Estimated Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalificatio Actual Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and / Description Component Review Type Method Amount qualification Document / Signed Contract Contract Completion No. Approach Process n (Y/N) Amount (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for (US$) Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-COREF-42839-CW-RFQ / Petits travaux de Component 3 - réhabilitation légère des Strengthening public Single Stage - One bâtiments abritant les IDA / D1650 A posteriori Demande de prix Limited 70,000.00 0.00 Annulé 2018-04-25 2018-06-20 2018-12-17 financial management Envelope bureaux de la DGRPEQ systems at provincial level dans la province de l'Equateur ZR-COREF-42851-CW-RFQ / Petits travaux de Component 3 - Réhabilitation des bâtiments Strengthening public Single Stage - One IDA / D1650 A posteriori Demande de prix Limited 20,000.00 0.00 Annulé 2018-04-21 2018-06-16 2018-12-13 abritant les buraux des financial management Envelope Coordinations provinciales systems at provincial level de PROFIT cONGO KWILU ZR-COREF-42866-CW-RFQ / Réhabilitation des Component 3 - bâtiments abritant les Strengthening public Single Stage - One IDA / D1650 A posteriori Demande de prix Limited 80,000.00 0.00 Annulé 2018-02-15 2018-04-12 2018-10-09 buraux des Coordinations financial management Envelope provinciales de PROFIT systems at provincial level CONGO Kasai Or ZR-COREF-42873-CW-RFQ / Petits travaux de Component 3 - Réhabilitation des bâtiments Strengthening public Single Stage - One abritant les bureaux des IDA / D1650 A posteriori Demande de prix Limited 100,000.00 0.00 Annulé 2018-03-20 2018-05-15 2018-11-11 financial management Envelope Coordinations provinciales systems at provincial level de PROFIT cONGO dans la province de l'Equateur ZR-COREF-42694-CW-RFQ / Travaux de Réhabilitation Component 4- Project Single Stage - One du bâtiment abritant les IDA / D1650 A posteriori Demande de prix Limited 300,000.00 330,696.81 Signé 2018-01-30 2018-03-27 2018-09-23 management Envelope bureaux de la Coordination Nationale du projet ZR-COREF-141957-CW-RFQ / Travaux de Rafraîchissement des Murs Component 4- Project Single Stage - One IDA / D1650 A posteriori Demande de prix Limited 75,000.00 74,974.26 Signé 2019-11-21 2020-01-29 2020-03-14 de l'Aile Centrale de la management Envelope Coordination Nationale du PROFIT-CONGO ZR-COREF-96640-CW-RFQ / Petits travaux d'installation de + 450 Panneaux solaires, par les structures métalliques, dans Component 1- Improving Single Stage - One les Directions Provinciales IDA / D1650 A posteriori Demande de prix Limited 290,000.00 0.00 Annulé 2019-05-13 2019-07-08 2020-01-04 budget execution processes Envelope de la DGRAD à Matadi, Lubumbashi, Kisangani, Goma, Bukavu, Kananga, Mbuji-Mayi, Bandundu, Kindu, Mbandaka ZR-COREF-141961-CW-RFQ / Travaux d'Aménagement de deux Locaux Devant Component 4- Project Single Stage - One Servir d'Archivage des IDA / D1650 A posteriori Demande de prix Limited 50,000.00 0.00 Annulé 2019-11-08 2019-12-12 2020-01-26 management Envelope Dossiers de la Coordination Nationale du PROFIT- CONGO ZR-COREF-155174-CW-RFQ / Petits travaux de Component 4- Project Single Stage - One En attente Réhabilitation du mur IDA / D1650 A posteriori Demande de prix Limited 25,000.00 0.00 2020-04-23 2020-05-25 2020-07-09 management Envelope d'exécution mitoyen de la Coordination Nationale du projet GOODS Bid Evaluation Activity Reference No. Estimated Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalificatio Actual Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and / Description Component Review Type Method Amount qualification Document / Signed Contract Contract Completion No. Approach Process n (Y/N) Amount (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for (US$) Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-COREF-42637-GO-RFQ / Acquisition des équipements usuels pour le Component 1- Improving Single Stage - One IDA / D1650 A posteriori Demande de prix Limited 30,000.00 29,450.00 Achevé 2018-03-20 2018-05-04 2018-06-18 besoin d'archivage de la budget execution processes Envelope DGDP (armoires ignifuges (15), classeurs, ...etc. ZR-COREF-42638-GO-RFQ / "Acquisition des matériels Component 2 - Single Stage - One et outils informatiques en IDA / D1650 Strengthening budget A posteriori Demande de prix Limited 100,000.00 0.00 Annulé 2018-03-06 2018-04-13 2018-05-28 Envelope faveur des ECOFIN du oversight Parlement ZR-COREF-42688-GO-RFQ / Acquisition des matériels Component 4- Project Single Stage - One IDA / D1650 A posteriori Demande de prix Limited 30,000.00 29,789.26 Signé 2018-02-04 2018-03-11 2018-04-25 spécialisés pour le service management Envelope de communication du Projet ZR-COREF-42689-GO-RFQ Component 4- Project Single Stage - One / Impression et diffusion du IDA / D1650 A posteriori Demande de prix Limited 30,000.00 0.00 Annulé 2018-09-04 2018-10-30 2018-12-14 management Envelope rapport annuel du projet ZR-COREF-42691-GO-RFQ / Acquisition de 2 véhicules de service pour renforcer la Component 4- Project Single Stage - One IDA / D1650 A posteriori Demande de prix Limited 120,000.00 106,700.00 Achevé 2018-01-30 2018-03-13 2018-05-12 mobilité du personnel du management Envelope projet dans l'exercice de leurs tâches quotidiennes Page 1 ZR-COREF-42692-GO-RFQ / Acquisition des mobiliers Component 4- Project Single Stage - One de bureaux et accessoires IDA / D1650 A posteriori Demande de prix Limited 15,000.00 0.00 Annulé 2018-02-10 2018-04-07 2018-10-04 management Envelope pour la coordination nationale du projet ZR-COREF-42693-GO-RFQ / Acquisition des Component 4- Project Single Stage - One équipements informatiques IDA / D1650 A posteriori Demande de prix Limited 85,000.00 88,305.00 Achevé 2018-02-10 2018-03-27 2018-05-11 management Envelope pour la coordination nationale du projet ZR-COREF-42812-GO-RFQ Component 3 - / Acquisition des matériels Strengthening public Single Stage - One informatiques de 6 Centres IDA / D1650 A posteriori Demande de prix Limited 150,000.00 149,992.20 Achevé 2018-03-20 2018-05-02 2018-07-01 financial management Envelope opérationnels de la DGRK systems at provincial level Kinshasa ZR-COREF-42815-GO-RFQ Component 3 - / Acquisition des matériels Strengthening public Single Stage - One IDA / H9070 A posteriori Demande de prix Limited 31,400.00 31,320.00 Achevé 2018-03-20 2018-05-15 2018-11-11 informatiques pour les 24 financial management Envelope ETD de la ville Kinshasa systems at provincial level ZR-COREF-42817-GO-RFQ Component 3 - / Acquisition de 10 motos Strengthening public Single Stage - One pour le contrôle des services IDA / D1650 A posteriori Demande de prix Limited 30,000.00 0.00 Annulé 2018-02-20 2018-04-17 2018-10-14 financial management Envelope d'assiettes et la DPMER au systems at provincial level Sud Kivu ZR-COREF-42820-GO-RFQ / Acquisition des Component 3 - équipements des services de Strengthening public Single Stage - One IDA / D1650 A posteriori Demande de prix Limited 36,000.00 0.00 Annulé 2018-03-20 2018-05-15 2018-11-11 la chaîne de la dépense (6 financial management Envelope Kits pour la chaine des systems at provincial level dépenses de la province du Kasaï-Central) ZR-COREF-42821-GO-RFQ / Acquisition d'un serveur Component 1- Improving Single Stage - One IDA / D1650 A posteriori Demande de prix Limited 250,000.00 99,835.00 Achevé 2018-03-10 2018-05-05 2018-11-01 et des matériels budget execution processes Envelope informatiques pour la centrale de Bilan ZR-COREF-42823-GO-RFQ Component 1- Improving Single Stage - One / Acquisition des IDA / D1650 A posteriori Demande de prix Limited 50,000.00 0.00 Annulé 2018-02-25 2018-04-22 2018-10-19 budget execution processes Envelope équipements pour le SYGMAP ZR-COREF-42826-GO-RFQ Component 3 - / Acquisition des imprimés Strengthening public Single Stage - One IDA / D1650 A posteriori Demande de prix Limited 70,000.00 0.00 Annulé 2018-03-25 2018-05-20 2018-11-16 de valeur sécurisés (2 financial management Envelope provinces Kwilu et Kwango) systems at provincial level ZR-COREF-42830-GO-RFQ / Acquisition des Component 2 - équipements pour le Single Stage - One IDA / D1650 Strengthening budget A posteriori Demande de prix Limited 100,000.00 89,050.00 Achevé 2018-04-25 2018-06-20 2018-12-17 renouvellement du parc Envelope oversight informatique de l'IGF (en faveur des inspecteurs généraux) ZR-COREF-43023-GO-RFQ / Acquisition des Component 3 - équipements informatiques Strengthening public Single Stage - One en faveur des 5 régies IDA / D1650 A posteriori Demande de prix Limited 300,000.00 299,800.00 Achevé 2018-02-20 2018-04-17 2018-07-16 financial management Envelope provinciales Equateur, systems at provincial level Mongala, Sud Ubangui, Nord Ubangui et Tshuapa ZR-COREF-43024-GO-RFQ / Acquisition des mobiliers Component 3 - de bureaux en faveur des 5 Strengthening public Single Stage - One IDA / D1650 A posteriori Demande de prix Limited 200,000.00 199,898.11 Achevé 2018-02-20 2018-04-17 2018-07-16 régies provinciales Equateur, financial management Envelope Mongala, Sud Ubangui, systems at provincial level Nord Ubangui et Tshuapa ZR-COREF-43045-GO-RFQ / Acquisition des mobiliers Component 3 - de bureaux en faveur de 3 Strengthening public Single Stage - One IDA / D1650 A posteriori Demande de prix Limited 150,000.00 149,925.00 Achevé 2018-02-20 2018-04-17 2018-07-16 régies provinciales (de l'ex- financial management Envelope KOR: Lomami, Sankuru et systems at provincial level Kasai Oriental) ZR-COREF-43065-GO-RFQ / Acquisition des petites fournitures de bureau en faveur des Directions Component 3 - provinciales des recettes des Strengthening public Single Stage - One IDA / D1650 A posteriori Demande de prix Limited 200,000.00 198,377.41 Achevé 2018-02-20 2018-04-17 2018-07-16 provinces: Nord Kivu, financial management Envelope Kasai Oriental, Sankuru, systems at provincial level Lomami, Equateur, Sud Ubangui, Nord Ubangui, Tsuapa et Mongala ZR-COREF-43087-GO-RFQ / Reproduction, impression Component 1- Improving Single Stage - One IDA / D1650 A posteriori Demande de prix Limited 70,000.00 0.00 Annulé 2018-04-25 2018-06-20 2018-12-17 et diffusion des guides PEB budget execution processes Envelope et PTR ZR-COREF-43089-GO-RFQ / Reproduction, impression Component 1- Improving Single Stage - One IDA / D1650 A posteriori Demande de prix Limited 70,000.00 69,600.00 Signé 2018-06-20 2018-08-15 2018-10-14 et diffusion des guides PEB budget execution processes Envelope et PTR ZR-COREF-43090-GO-RFQ / Production et impression de 500 exemplaires du Guide technique relatif à la Component 2 - méthodologie et outils de Single Stage - One IDA / D1650 Strengthening budget A posteriori Demande de prix Limited 20,000.00 19,700.00 Signé 2018-03-20 2018-05-15 2018-07-14 conduite d'une mission Envelope oversight d'audit basé sur les risques selon les normes d'exercice professionnelles de l'IIA (160 pages NB) ZR-COREF-43091-GO-RFQ / Production et impression de 500 exemplaires du Component 2 - Single Stage - One Guide méthodologique IDA / D1650 Strengthening budget A posteriori Demande de prix Limited 20,000.00 19,700.00 Signé 2018-03-20 2018-05-15 2018-07-14 Envelope d'élaboration de la oversight cartographie et du plan d'audit basé sur les risques (128 pages NB) ZR-COREF-43093-GO-RFQ / Impression et reproduction Component 2 - des 1000 exemplaires des Single Stage - One IDA / D1650 Strengthening budget A posteriori Demande de prix Limited 30,000.00 29,980.00 Signé 2018-03-25 2018-05-20 2018-07-19 manuels des procédures Envelope oversight d'examen des lois de finances (90 pages NB) Page 2 ZR-COREF-43094-GO-RFQ / Production, Impression et Component 3 - diffusion de 250 exemplaires Strengthening public Single Stage - One IDA / D1650 A posteriori Demande de prix Limited 10,000.00 0.00 Annulé 2018-04-25 2018-06-20 2018-08-19 des projets d'Edits portant financial management Envelope reddition des comptes dans systems at provincial level les 5 nouvelles provinces ZR-COREF-43096-GO-RFQ Component 3 - / Impression, reproduction, Strengthening public Single Stage - One et diffusion de 200 copies IDA / D1650 A posteriori Demande de prix Limited 10,000.00 0.00 Annulé 2018-04-25 2018-06-20 2018-08-19 financial management Envelope de l'édit budgétaire 2018 systems at provincial level NKV en format simplifié ZR-COREF-43103-GO-RFQ Component 3 - / Impression, reproduction Strengthening public Single Stage - One et à la diffusion de 200 IDA / D1650 A posteriori Demande de prix Limited 15,000.00 0.00 Annulé 2018-03-05 2018-04-30 2018-06-29 financial management Envelope copies de l'édit budgétaire systems at provincial level 2018 HKTGA en format simplifié ZR-COREF-43109-GO-RFQ Component 3 - / Impresssion, Reproduction, Strengthening public Single Stage - One et diffusion de 100 copies IDA / D1650 A posteriori Demande de prix Limited 10,000.00 0.00 Annulé 2018-03-05 2018-04-30 2018-06-29 financial management Envelope de l'édit budgétaire 2018 systems at provincial level KWILU en format simplifié ZR-COREF-43112-GO-RFQ Component 3 - / Impression, Reproduction, Strengthening public Single Stage - One et diffusion de 100 copies IDA / D1650 A posteriori Demande de prix Limited 10,000.00 0.00 Annulé 2018-03-15 2018-05-10 2018-07-09 financial management Envelope de l'édit budgétaire 2018 systems at provincial level SKV en format simplifié ZR-COREF-45312-GO-RFQ / Acquisition des consommables informatiques Component 4- Project Single Stage - One IDA / D1650 A posteriori Demande de prix Limited 70,000.00 24,860.00 Achevé 2018-02-24 2018-04-21 2018-10-18 pour le bureau de la management Envelope coordination nationale de PROFIT CONGO ZR-COREF-45311-GO-RFQ / Acquisition des fournitures Component 4- Project Single Stage - One de bureau pour la IDA / D1650 A posteriori Demande de prix Limited 50,000.00 30,000.00 Achevé 2018-02-24 2018-04-21 2018-10-18 management Envelope Coordination Nationale du PROFIT-CONGO ZR-COREF-45330-GO-RFB / Acquisition des équipements Component 3 - pour l'installation de Strengthening public Single Stage - One l'énergie photovoltaïque dans IDA / D1650 A posteriori Appel d'offres Open - National 500,000.00 0.00 Annulé 2018-06-01 2018-06-06 2018-07-18 2018-08-17 2018-09-21 2019-03-20 financial management Envelope le cadre de la mise en systems at provincial level place du système intégré dans les provinces. ZR-COREF-45334-GO-RFQ / Acquisition des mobiliers Component 1- Improving Single Stage - One IDA / D1650 A posteriori Demande de prix Limited 300,000.00 299,992.00 Achevé 2018-02-20 2018-04-17 2018-10-14 de bureau pour l'ARMP, la budget execution processes Envelope DGCMP et les CGPMP. ZR-COREF-43155-GO-RFB / Acquisition des matériels Component 1- Improving Single Stage - One IDA / D1650 A posteriori Demande de prix Limited 450,000.00 176,196.00 Achevé 2018-02-20 2018-04-17 2018-10-14 informatiques en faveur de budget execution processes Envelope l’ARMP et de la DGCMP ZR-COREF-69877-GO-RFQ / FOURNITURE DE LA CONNEXION INTERNET Component 4- Project Single Stage - One IDA / D1650 A posteriori Demande de prix Limited 40,000.00 38,325.00 Signé 2018-10-11 2018-11-07 2019-11-07 DE LA COORDINATION management Envelope NATIONALE DU PROFIT CONGO ZR-COREF-80320-GO-RFQ / Impression des rapports Component 2 - Passation de publics de la cour des IDA / D1650 Strengthening budget A posteriori marché de gré à Direct 50,000.00 25,000.00 Signé 2018-10-30 2018-11-04 2018-12-09 2019-06-07 comptes et du rapport de oversight gré l'exécution du budget ZR-COREF-80322-GO-RFQ / Acquisition des équipements informatiques en faveur des commissions Component 2 - Single Stage - One ECOFIN du Parlement dont IDA / D1650 Strengthening budget A posteriori Demande de prix Limited 100,000.00 0.00 Annulé 2018-11-02 2018-11-24 2019-05-23 Envelope 4 Ordinateurs fixes , 27 oversight Ordinateurs , 4 Imprimantes , 2 Photocopieuses à grand tirage et 2 Scanners, etc. ZR-COREF-80325-GO-RFQ / Production, impression et Component 4- Project Single Stage - One diffusion de la Revue IDA / D1650 A posteriori Demande de prix Limited 45,000.00 7,500.00 Signé 2018-10-25 2018-11-20 2019-01-04 management Envelope trimestrielle « Echos des Finances Publiques »  ZR-COREF-80711-GO-RFQ Component 3 - / Acquisition des Strengthening public Single Stage - One IDA / D1650 A posteriori Demande de prix Limited 130,000.00 0.00 Annulé 2018-10-26 2018-11-16 2019-05-15 équipements informatiques financial management Envelope de 3 régies provinciales (de systems at provincial level l'ex- KOR) ZR-COREF-80713-GO-RFQ / Acquisition de 2 véhicules Component 4- Project Single Stage - One utilitaires pour la Cellule IDA / D1650 A posteriori Demande de prix Limited 45,000.00 45,000.00 Achevé 2018-10-15 2018-11-07 2019-03-07 management Envelope de Suivi des Projets et Programmes (CSPP) ZR-COREF-81031-GO-RFQ / Marché de production et Component 1- Improving Single Stage - One IDA / D1650 A posteriori Demande de prix Limited 12,000.00 59,200.00 Signé 2018-11-15 2018-12-11 2019-12-06 diffusion du magazine des budget execution processes Envelope marchés publics ZR-COREF-96253-GO-RFQ / Acquisition des imprimés Component 3 - de valeur sécurisés en Strengthening public Single Stage - One faveur des régies IDA / D1650 A posteriori Demande de prix Limited 150,000.00 146,351.80 Achevé 2019-04-25 2019-06-20 2019-12-17 financial management Envelope provinciales de ces 2 systems at provincial level provinces de l'ex province du Kasai Occidental ZR-COREF-96411-GO-DIR / Component 2 - Passation de Fourniture de l'abonnement IDA / D1650 Strengthening budget A posteriori marché de gré à Direct 30,000.00 29,982.00 Achevé 2019-02-15 2019-02-17 2019-02-26 2020-02-26 internet de la Cour des oversight gré comptes (12 mois) ZR-COREF-96619-GO-RFQ / Acquisition des équipements informatiques Component 1- Improving Single Stage - One pour renforcer le IDA / D1650 A posteriori Demande de prix Limited 100,000.00 99,800.00 Achevé 2019-04-15 2019-06-10 2019-12-07 budget execution processes Envelope SYGECPAF (Système de Gestion Centralisée de la Paie des Agents et Fonctionnaires) Page 3 ZR-COREF-96743-GO-RFQ / Acquisition des fournitures Component 4- Project Single Stage - One de bureau pour la IDA / D1650 A posteriori Demande de prix Limited 12,000.00 10,119.00 Achevé 2019-02-08 2019-02-28 2019-03-07 management Envelope Coordination Nationale du PROFIT-CONGO ZR-COREF-96752-GO-RFQ / Acquisition des consommables informatiques Component 4- Project Single Stage - One IDA / D1650 A posteriori Demande de prix Limited 18,000.00 16,160.00 Achevé 2019-02-08 2019-02-28 2019-03-07 pour la Coordination management Envelope Nationale du PROFIT- CONGO ZR-COREF-96761-GO-RFQ / Acquisition des mobiliers de bureau et équipements Component 4- Project Single Stage - One IDA / D1650 A posteriori Demande de prix Limited 120,000.00 119,895.04 Signé 2019-07-06 2019-07-28 2019-08-04 informatiques pour la management Envelope Coordination Nationale du PROFIT-CONGO ZR-COREF-103214-GO-RFQ / Acquisition de la connexion internet de 3MB Component 4- Project Single Stage - One IDA / D1650 A posteriori Demande de prix Open - National 50,000.00 66,630.00 Achevé 2019-07-06 2019-08-10 2020-08-09 pour la Coordination management Envelope Nationale du PROFIT- CONGO ZR-COREF-107927-GO-RFQ / Acquisition des matériels informatiques (6 ordinateurs Component 1- Improving Single Stage - One portables et disques durs IDA / D1650 A posteriori Demande de prix Limited 8,400.00 8,400.00 Achevé 2019-04-03 2019-05-02 2019-06-01 budget execution processes Envelope externes) en faveur des équipes d'évaluation MAPS II ZR-COREF-141993-GO-RFQ / Acquisition des Component 3 - équipements informatiques Strengthening public Single Stage - One (lap top, tablette, IDA / D1650 A posteriori Demande de prix Limited 150,000.00 156,000.00 Signé 2019-11-09 2019-12-13 2020-01-27 financial management Envelope rétroprojecteur...) en faveur systems at provincial level du Projet E Tax de la Province du Sud-Kivu. ZR-COREF-96385-GO-RFQ / Acquisition des équipements, matériels informatiques, matériels et Component 3 - logiciels informatiques pour Strengthening public Single Stage - One le guichet unique spécial IDA / D1650 A posteriori Demande de prix Limited 100,000.00 0.00 Annulé 2019-07-20 2019-09-14 2020-03-12 financial management Envelope d'encaissement des droits systems at provincial level dus par les petits commerçants et les personnes physiques de la ville province de Kinshasa ZR-COREF-96622-GO-RFQ / Impression et duplication du manuel des procédures Component 1- Improving Single Stage - One IDA / D1650 A posteriori Demande de prix Limited 30,000.00 0.00 Annulé 2019-04-15 2019-06-03 2019-09-01 administratives et budget execution processes Envelope financières des DAF (220 pages) ZR-COREF-43084-GO-RFQ / Marché de Production des 300 exemplaires du plan de la mise en place de la Component 1- Improving Single Stage - One déconcentration de IDA / D1650 A posteriori Demande de prix Limited 60,000.00 0.00 Annulé 2018-06-20 2018-08-06 2018-09-20 budget execution processes Envelope l'ordonnancement et de la Direction Générale du Trésor et de la Comptabilité publique ZR-COREF-42639-GO-RFQ / Acquisition des imprimés Component 3 - de valeur en faveur des 2 Strengthening public Single Stage - One IDA / D1650 A posteriori Demande de prix Limited 100,000.00 0.00 Annulé 2018-03-06 2018-05-01 2018-06-30 régies provinciales de l'ex- financial management Envelope Equateur (Nord - Ubangi et systems at provincial level Equateur) ZR-COREF-56444-GO-RFQ / Acquisition des Component 3 - équipements informatiques, Strengthening public Single Stage - One IDA / D1650 A posteriori Demande de prix Limited 100,000.00 0.00 Annulé 2018-04-15 2018-06-10 2018-12-07 des mobiliers de bureaux et financial management Envelope de petites fournitures de la systems at provincial level DGR - NK ZR-COREF-80319-GO-RFQ / Renouvellement du parc Component 1- Improving Single Stage - One IDA / D1650 A posteriori Demande de prix Limited 60,000.00 0.00 Annulé 2018-11-05 2018-11-25 2019-05-24 informatique de la Direction budget execution processes Envelope de la Paie ZR-COREF-96380-GO-RFQ Component 3 - / Acquisition des Strengthening public Single Stage - One équipements informatiques IDA / D1650 A posteriori Demande de prix Limited 130,000.00 0.00 Annulé 2019-05-20 2019-07-15 2020-01-11 financial management Envelope pour la Direction des systems at provincial level recettes du Maïndombe ZR-COREF-96425-GO-DIR / Fourniture et Impression de 1000 exemplaires de la loi Component 2 - Passation de organique de la Cour des IDA / D1650 Strengthening budget A posteriori marché de gré à Direct 60,000.00 0.00 Annulé 2019-05-15 2019-05-20 2019-05-30 2019-08-28 comptes au journal officiel oversight gré et de 1000 exemplaires du rapport public de la Cour des comptes exercice 2018 ZR-COREF-153955-GO-RFQ / Acquisition des ordinateurs en faveur de la Component 1- Improving Single Stage - One En attente DGCMP pour finaliser la IDA / D1650 A posteriori Demande de prix Limited 35,000.00 0.00 2020-03-20 2020-05-04 2020-06-18 budget execution processes Envelope d'exécution dématérialisation du contrôle a priori des marchés publics ZR-COREF-153961-GO-RFQ / Acquisition des matériels informatiques en vue des Component 1- Improving Single Stage - One En attente IDA / D1650 A posteriori Demande de prix Limited 15,000.00 0.00 2020-02-15 2020-03-22 2020-03-23 tests du Logiciel SIGMAP budget execution processes Envelope d'exécution en vue de sa réception définitive ZR-COREF-153968-GO-RFQ / Acquisition des équipements informatiques Component 1- Improving Single Stage - One En attente IDA / D1650 A posteriori Demande de prix Limited 90,000.00 0.00 2020-06-20 2020-08-15 2020-10-14 en vue du déploiement du budget execution processes Envelope d'exécution logiciel de gestion de la trésorerie de l’Etat Page 4 ZR-COREF-154928-GO-DIR / Impression de 500 Component 2 - Passation de exemplaires du rapport En attente IDA / D1650 Strengthening budget A posteriori marché de gré à Direct 30,000.00 0.00 2020-06-15 2020-06-20 2020-07-01 2020-08-15 public de la Cour des d'exécution oversight gré comptes des exercices 2016- 2017 et 2018 ZR-COREF-154935-GO-RFQ / Acquisition en faveur de Component 2 - la commission ECOFIN de Single Stage - One En attente IDA / D1650 Strengthening budget A posteriori Demande de prix Limited 50,000.00 0.00 2020-03-25 2020-05-07 2020-11-03 l'Assemblée Nationale et du Envelope d'exécution oversight Sénat des équipements informatiques et accessoires ZR-COREF-154938-GO-RFQ / Acquisition des équipements de bureaux et matériels informatiques en vue de l’installation du Component 2 - Single Stage - One En attente centre de documentation du IDA / D1650 Strengthening budget A posteriori Demande de prix Limited 80,000.00 0.00 2020-04-25 2020-06-03 2020-09-01 Envelope d'exécution Parlement (Serveur, moteur oversight de recherche, procédures, alimentation et entretien de la base ; bibliothèque, internet, intranet) ZR-COREF-154963-GO-RFQ / Acquisition des matériels Component 3 - informatiques et en Strengthening public Single Stage - One En attente IDA / D1650 A posteriori Demande de prix Limited 12,000.00 0.00 2020-03-25 2020-04-24 2020-07-23 mobiliers de bureau à la financial management Envelope d'exécution coordination provinciale de systems at provincial level l’Equateur ZR-COREF-155150-GO-RFQ / Acquisition des imprimés Component 3 - de valeur en faveur de la Strengthening public Single Stage - One En attente IDA / D1650 A posteriori Demande de prix Limited 120,000.00 0.00 2020-04-25 2020-05-24 2020-07-23 DGRLO, DPMER et financial management Envelope d'exécution DGREM dans les Provinces systems at provincial level de LOMAMI et Mai Ndombe ZR-COREF-155178-GO-RFQ / Acquisition des extincteurs Component 4- Project Single Stage - One En attente IDA / D1650 A posteriori Demande de prix Limited 5,000.00 0.00 2020-04-25 2020-06-05 2020-06-08 à CO² pour la sécurisation management Envelope d'exécution des biens et documents ZR-COREF-155180-GO-RFQ / Acquisition mobilier de Component 4- Project Single Stage - One En attente bureaux et équipements IDA / D1650 A posteriori Demande de prix Limited 90,000.00 0.00 2020-04-25 2020-06-06 2020-12-03 management Envelope d'exécution informatiques de la Coordination nationale ZR-COREF-155188-GO-RFQ / Achat de 25 tablettes Component 4- Project Single Stage - One En attente IDA / D1650 A posteriori Demande de prix Limited 10,000.00 0.00 2020-03-30 2020-05-04 2020-05-10 pour l'utilisation du logiciel management Envelope d'exécution KOBO ZR-COREF-155190-GO-RFQ / Acquisition de petites Component 4- Project Single Stage - One En attente IDA / D1650 A posteriori Demande de prix Limited 18,000.00 0.00 2020-03-15 2020-04-13 2020-05-13 Fournitures de bureau de la management Envelope d'exécution Coordination nationale ZR-COREF-155195-GO-RFQ Component 4- Project Single Stage - One En attente / Acquisition des IDA / D1650 A posteriori Demande de prix Limited 24,000.00 0.00 2020-03-27 2020-05-13 2020-05-16 management Envelope d'exécution Consommables informatiques ZR-COREF-156534-GO-RFQ / Acquisition des mobiliers de bureaux et des matériels informatiques ainsi que de Component 1- Improving Single Stage - One En attente petites fournitures de IDA / D1650 A posteriori Demande de prix Limited 100,000.00 0.00 2020-04-25 2020-06-07 2020-08-06 budget execution processes Envelope d'exécution bureaux en vue de l'opérationnalisation des structures d'audit interne dans 5 ministères ZR-COREF-156551-GO-RFQ / Acquisition de petits Component 4- Project Single Stage - One En attente matériels et outils de IDA / D1650 A posteriori Demande de prix Limited 3,000.00 0.00 2020-03-04 2020-04-02 2020-04-23 management Envelope d'exécution dépannage pour la Coordination nationale ZR-COREF-157764-GO-RFQ Component 3 - / Acquisition des imprimés Strengthening public Single Stage - One En attente de valeurs sécurisés et IDA / D1650 A posteriori Demande de prix Limited 60,000.00 0.00 2020-03-05 2020-04-03 2020-06-02 financial management Envelope d'exécution cachets secs en faveur de systems at provincial level la DPMER ZR-COREF-157765-GO-DIR / Acquisition des imprimés Component 3 - de valeurs sécurisés Passation de Strengthening public En attente (complément) en faveur de IDA / D1650 A posteriori marché de gré à Direct 40,000.00 0.00 2020-04-10 2020-04-15 2020-05-09 2020-06-23 financial management d'exécution la Direction des recettes du gré systems at provincial level Kasai Central (Entreprise MIRAK) NON CONSULTING SERVICES Bid Evaluation Activity Reference No. Estimated Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalificatio Actual Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and / Description Component Review Type Method Amount qualification Document / Signed Contract Contract Completion No. Approach Process n (Y/N) Amount (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for (US$) Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-COREF-43153-NC-DIR / Recrutement des Consultants pour les Passation de Component 4- Project missions de mise à niveau IDA / D1650 A posteriori marché de gré à Direct 30,000.00 0.00 Annulé 2018-01-23 2018-01-28 2018-03-04 2018-08-31 management et du paramétrage du gré logiciel TOM²PRO (TOMATE) ZR-COREF-45326-NC-RFQ / Sélection d'une firme Component 4- Project Single Stage - One d'entretien des bureaux de IDA / D1650 A posteriori Demande de prix Limited 14,400.00 19,200.00 Signé 2018-02-20 2018-04-17 2018-10-14 management Envelope la Coordination Nationale du PROFIT-CONGO ZR-COREF-103079-NC-DIR / Renouvellement contrat de Passation de Service d'entretien des Component 4- Project IDA / D1650 A posteriori marché de gré à Direct 19,200.00 19,200.00 Signé 2019-03-12 2019-03-14 2019-03-31 2020-03-31 bureaux de la Coordination management gré Nationale du PROFIT- CONGO (BAM'S CLEAN) Page 5 ZR-COREF-103210-NC-DIR / Renouvellement contrat du Passation de service de gardiennage et Component 4- Project IDA / D1650 A posteriori marché de gré à Direct 24,000.00 24,000.00 Signé 2019-03-11 2019-03-13 2019-03-30 2020-03-30 sécurité des bureaux de la management gré Coordination Nationale du PROFIT-CONGO ZR-COREF-96247-NC-RFQ / Prestataire de service d'Audit et des inventaires des Immobilisations et Component 4- Project Single Stage - One IDA / D1650 A posteriori Demande de prix Limited 60,000.00 0.00 Annulé 2019-02-06 2019-03-04 2021-02-21 acquisitions du PROJET au management Envelope profit des bénéficiaires et pour son fonctionnement (2ans) ZR-COREF-43123-NC-DIR / Component 2 - Passation de Service de maintenance des IDA / D1650 Strengthening budget A posteriori marché de gré à Direct 92,000.00 0.00 Annulé 2018-11-15 2018-11-20 2018-12-05 2019-11-30 logiciels IDEA et TeamMate oversight gré CONSULTING FIRMS Activity Reference No. Actual Short List and Draft Combined Evaluation Loan / Credit Market Contract Type Estimated Process Expression of Request for Opening of Technical Evaluation of / Description Component Review Type Method Amount Terms of Reference Request for Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Status Interest Notice Proposals as Issued Proposals / Minutes Technical Proposal (US$) Proposals Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-COREF-42674-CS-CQS / Sélection d'un consultant Sélection fondée cabinet pour la réalisation Component 1- Improving sur les Open - IDA / D1650 A posteriori 120,000.00 0.00 Annulé 2018-03-30 2018-04-20 2018-06-03 2018-07-03 2018-08-07 2019-02-03 d'une étude sur l'extension budget execution processes qualifications des International de la chaîne des dépenses consultants vers les services dépensiers ZR-COREF-42680-CS-QCBS / Sélection d'un Consultant Sélection fondée cabinet d'audit en faveur de Component 1- Improving Open - IDA / D1650 A posteriori sur la qualité et 250,000.00 219,370.00 Signé 2018-02-20 2018-03-13 2018-04-26 2018-05-24 2018-06-23 2018-07-28 2018-09-01 2019-09-01 l'ARMP pour les mission budget execution processes International le coût d'audit des marchés publics exercice 2014, 2015 et 2016 ZR-COREF-45939-CS-QBS / Sélection d'un consultant (cabinet) chargé de Component 3 - Sélection fondée recrutement et de la Strengthening public sur les IDA / D1650 A posteriori Open - National 100,000.00 0.00 Annulé 2018-03-01 2018-03-22 2018-05-05 2018-06-04 2018-07-09 2019-01-05 formation des agents et financial management qualifications des cadres de la Direction systems at provincial level consultants Générale des Recettes de la province du Kwilu (DGREK) ZR-COREF-45328-CS-CQS / Selection Consultant Cabinet chargé de l'étude de faisabilité et de Component 3 - Sélection fondée dimensionnement des Strengthening public sur les systèmes de production IDA / D1650 A posteriori Open - National 300,000.00 294,042.00 Signé 2018-03-20 2018-04-10 2018-05-24 2018-06-23 2018-07-28 2019-01-24 financial management qualifications des d'énergie photovoltaïque systems at provincial level consultants pour l'alimentation du système intégré des Finances Publiques dans les provinces ZR-COREF-83914-CS-FBS / Consultant firme pour assurer l'audit financier et comptable du Projet de Sélection fondée Renforcement de la Component 4- Project Open - IDA / D1650 A posteriori sur la qualité et 90,000.00 72,565.00 Achevé 2018-11-20 2018-11-27 2018-12-09 2018-12-16 2018-12-23 2019-01-11 2019-01-20 2021-06-30 Redevabilité et de la management International le coût Gestion des Finances Publiques (PROFIT-CONGO) pour les exercices 2018, 2019 et 2020. ZR-COREF-155157-CS-CQS / Sélection d'un cabinet Component 3 - Sélection fondée chargé du recrutement du Strengthening public sur les En attente personnel de la régie IDA / D1650 A posteriori Open - National 120,000.00 0.00 2020-04-20 2020-05-11 2020-06-10 2020-06-30 2020-07-20 2020-11-17 financial management qualifications des d'exécution provinciale de Mai - systems at provincial level consultants Ndombé et de la DGRKAC au kasai central INDIVIDUAL CONSULTANTS Activity Reference No. Actual Invitation to Loan / Credit Market Contract Type Estimated Process Draft Negotiated / Description Component Review Type Method Amount Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Status Contract (US$) Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-COREF-42700-CS-CDS / Renouvellement contrat Sélection de Component 4- Project Coordonnateur Provincial du IDA / D1650 A posteriori consultants par Direct 34,200.00 34,200.00 Signé 2018-11-01 2018-11-03 2018-12-01 2019-12-01 management Kasaï-Oriental (Alfred entente directe KAMBA) ZR-COREF-43120-CS-INDV / Recrutement chauffeur de Component 4- Project IDA / D1650 A posteriori Individuel Limited 8,400.00 0.00 Annulé 2018-01-20 2018-01-25 2018-02-04 2018-02-28 2019-02-28 la Coordination Provinciale management de l'Equateur ZR-COREF-43151-CS-INDV / Sélection 2ème Assistant Component 4- Project IDA / D1650 A posteriori Individuel Open 54,000.00 54,000.00 Signé 2017-10-02 2018-01-15 2018-01-25 2018-02-01 2019-02-01 Technique chargé de la management Décentralisation Financière ZR-COREF-44312-CS-CDS / Renouvellement Contrat Sélection de Component 4- Project Coordonnateur Provincial IDA / D1650 A posteriori consultants par Direct 34,200.00 34,200.00 Signé 2017-12-01 2017-12-11 2018-02-14 2018-08-13 management Kasaï-Central (Jean Claude entente directe MUSAS) ZR-COREF-42707-CS-INDV / Renouvellement Contrat Component 4- Project Assistant Administratif et IDA / D1650 A posteriori Individuel Direct 18,000.00 18,000.00 Signé 2018-10-01 2018-10-10 2018-10-20 2018-10-31 2019-10-30 management Financier du Katanga (Cedrick KAPANGA) ZR-COREF-42640-CS-CQS / Sélection d'un consultant cabinet pour la mise en place d'un dispositif de gestion des risques et Component 2 - Sélection de d'optimisation de la IDA / D1650 Strengthening budget A posteriori consultants par Direct 330,000.00 372,600.00 Achevé 2018-02-28 2018-03-10 2018-05-14 2018-11-10 mobilisation des recettes oversight entente directe publiques au sein des régies financières (DGI, DGDA, DGRAD) avec le cabinet PANAUDIT BURKINA Page 6 ZR-COREF-42641-CS-INDV / Sélection d'un Consultant Component 1- Improving international pour appuyer IDA / D1650 A priori Individuel Limited 240,000.00 0.00 Annulé 2018-02-20 2018-02-25 2018-03-18 2018-04-22 2020-04-11 budget execution processes le pilier de la mise en œuvre des réformes fiscales ZR-COREF-42676-CS-INDV / Sélection d'un Consultant International chargé de Component 1- Improving IDA / D1650 A posteriori Individuel Limited 80,000.00 0.00 Annulé 2018-02-12 2018-02-17 2018-03-10 2018-04-14 2018-10-11 mettre en place un système budget execution processes fiscal de référence des administrations fiscales ZR-COREF-42677-CS-INDV / Sélection d'un Consultant international pour la réalisation d'une étude sur Component 1- Improving IDA / D1650 A posteriori Individuel Limited 90,000.00 0.00 Annulé 2018-04-10 2018-04-15 2018-05-06 2018-06-10 2018-12-07 la gestion de la paie dans budget execution processes le cadre de la déconcentration de l'ordonnancement ZR-COREF-42678-CS-INDV / Sélection d'un consultant international chargé de Component 1- Improving l'assistance technique à la IDA / D1650 A posteriori Individuel Limited 120,000.00 180,000.00 Signé 2018-01-30 2018-02-04 2018-02-25 2018-04-01 2018-09-28 budget execution processes Direction Générale du Contrôle des Marchés Publics « DGCMP » ZR-COREF-42679-CS-INDV / Sélection d'un consultant international pour le Component 1- Improving IDA / D1650 A posteriori Individuel Limited 100,000.00 104,145.00 Signé 2018-01-30 2018-02-04 2018-02-25 2018-04-01 2018-09-28 développement du système budget execution processes intégré de gestion des marchés publics « SIGMAP » ZR-COREF-42681-CS-INDV / Sélection d'un consultant Component 1- Improving individuel pour la IDA / D1650 A posteriori Individuel Limited 50,000.00 0.00 Annulé 2018-02-20 2018-02-25 2018-03-18 2018-04-22 2018-10-19 budget execution processes rédaction du guide d'élaboration du TOFE ZR-COREF-42683-CS-INDV / Sélection d' un consultant pour produire les modèles Component 2 - des Budgets Citoyen pour IDA / D1650 Strengthening budget A posteriori Individuel Limited 60,000.00 40,000.00 Signé 2018-02-20 2018-02-25 2018-03-18 2018-04-22 2018-10-19 chacun des documents oversight budgétaires clés du pouvoir central et des provinces dans toutes les langues ZR-COREF-42684-CS-INDV / Recrutement des Component 2 - Consultants pour la IDA / D1650 Strengthening budget A posteriori Individuel Limited 50,000.00 0.00 Annulé 2018-03-05 2018-03-10 2018-03-31 2018-05-05 2018-11-01 formation des formateurs oversight sur le processus et l'analyse budgétaires ZR-COREF-42686-CS-INDV / Sélection d'un Consultant individuel international chargé du suivi des DAF, Component 2 - Sélection de de la déconcentration de IDA / D1650 Strengthening budget A posteriori consultants par Direct 45,000.00 0.00 Annulé 2018-02-19 2018-03-01 2018-05-05 2018-11-01 l'ordonnancement et d'appui oversight entente directe aux AT (2ème phase de 3 mois de contrat avec Ibrahima NDIAYE) ZR-COREF-42690-CS-INDV / Recrutement d' un web designer (web master) pour Component 4- Project le développement et la mise IDA / D1650 A posteriori Individuel Limited 30,000.00 6,000.00 Signé 2018-01-30 2018-02-04 2018-02-25 2018-04-01 2018-05-01 management à jour quotidienne d'un site web interactif à grande capacité du COREF ZR-COREF-42695-CS-INDV / Sélection d'un consultant international devant mener Component 4- Project IDA / D1650 A posteriori Individuel Limited 80,000.00 0.00 Annulé 2018-02-20 2018-02-25 2018-03-18 2018-04-22 2018-10-19 conjointement au COREF management une évaluation à mi - parcours du projet ZR-COREF-42709-CS-CDS / Sélection de Renouvellement contrat de Component 4- Project IDA / D1650 A posteriori consultants par Direct 18,000.00 18,000.00 Signé 2018-03-01 2018-03-09 2018-04-01 2019-04-01 l'Assistante en PM (Gisèle management entente directe MUAHUKA) ZR-COREF-42710-CS-CDS / Sélection de Renouvellement contrat de Component 4- Project IDA / D1650 A posteriori consultants par Direct 18,000.00 18,000.00 Signé 2018-02-01 2018-02-10 2018-03-01 2019-03-01 la trésorière (Sylvie management entente directe NGEVESISE) ZR-COREF-42711-CS-CDS / Sélection de Renouvellement contrat du Component 4- Project IDA / D1650 A posteriori consultants par Direct 30,000.00 30,000.00 Signé 2018-11-01 2018-11-10 2018-12-01 2019-12-01 Comptable (Déo management entente directe MUGARUKA) ZR-COREF-42854-CS-INDV Component 3 - / Sélection d'un consultant Strengthening public pour la réalisation de IDA / D1650 A posteriori Individuel Limited 50,000.00 0.00 Annulé 2018-04-10 2018-04-15 2018-05-06 2018-06-10 2018-12-07 financial management l'audit de la chaîne de la systems at provincial level dépense installée au KWILU ZR-COREF-42685-CS-INDV / Renouvellement Contrat Consultant National pour Component 2 - appuyer et superviser la IDA / D1650 Strengthening budget A posteriori Individuel Direct 24,000.00 24,000.00 Signé 2018-03-01 2018-03-05 2018-03-10 2018-04-01 2019-04-01 mise en œuvre du Budget oversight Participatif au niveau provincial (Florence MOGBEKUMA) ZR-COREF-42706-CS-INDV / Renouvellement contrat Component 4- Project IDA / D1650 A posteriori Individuel Direct 34,200.00 34,200.00 Signé 2018-11-01 2018-11-06 2018-11-10 2018-12-01 2019-12-01 Coordonnateur Provincial du management Nord-Kivu (David KAMUHA) ZR-COREF-42704-CS-INDV / Renouvellement contrat du Component 4- Project IDA / D1650 A posteriori Individuel Direct 51,600.00 51,600.00 Signé 2018-11-01 2018-11-06 2018-11-10 2018-12-01 2019-11-26 Responsable Administratif et management Financier(Emile ASELE) ZR-COREF-42705-CS-INDV Component 4- Project / Renouvellement contrat du IDA / D1650 A posteriori Individuel Direct 51,600.00 51,600.00 Signé 2018-02-01 2018-02-07 2018-02-10 2018-03-01 2019-03-01 management SPM (Luc MBAYO SUKADI) Page 7 ZR-COREF-42708-CS-CDS / Renouvellement contrat Component 4- Project IDA / D1650 A posteriori Individuel Direct 34,200.00 34,200.00 Signé 2019-11-05 2019-11-15 2019-11-20 2019-12-01 2020-11-30 Coordonnateur Provincial de management l'équateur(Boenga EFONGE) ZR-COREF-42696-CS-CDS / Renouvellement contrat de l’Assistante du Component 4- Project IDA / D1650 A posteriori Individuel Direct 34,200.00 34,200.00 Signé 2018-08-02 2018-08-05 2018-08-09 2018-09-01 2019-09-01 Coordonnateur National du management PROFIT-CONGO Véronique MANYA ZR-COREF-42701-CS-CDS / Renouvellement contrat du Component 4- Project IDA / D1650 A posteriori Individuel Direct 51,600.00 51,600.00 Signé 2018-11-06 2018-11-16 2018-11-21 2018-12-01 2019-12-01 Chargé de Suivi et management Evaluation (Jule KWILU) ZR-COREF-42702-CS-CDS / Renouvellement contrat de Component 4- Project IDA / D1650 A posteriori Individuel Direct 30,000.00 30,000.00 Signé 2018-08-06 2018-08-11 2018-08-14 2018-09-01 2019-09-01 la Chargée de management Communication(Flora DILU) ZR-COREF-42699-CS-INDV / Renouvellement Contrat Component 4- Project IDA / D1650 A posteriori Individuel Direct 34,200.00 34,200.00 Signé 2018-10-01 2018-10-04 2018-10-07 2018-11-01 2019-11-01 Coordonnateur Provincial management Sud-Kivu (Sylvie MALIONA) ZR-COREF-42697-CS-INDV / Renouvellement Contrat Component 4- Project IDA / D1650 A posteriori Individuel Direct 34,200.00 34,200.00 Signé 2018-10-01 2018-10-04 2018-10-07 2018-11-01 2019-11-01 Coordonnateur Provincial management Bandundu (Thierry BETU) ZR-COREF-42698-CS-INDV / Renouvellment Contrat Component 4- Project IDA / D1650 A posteriori Individuel Direct 34,200.00 34,200.00 Signé 2018-10-01 2018-10-04 2018-10-07 2018-11-01 2019-11-01 Coordonnateur Provincial management Katanga (José MWANIA) ZR-COREF-42634-CS-INDV / Renouvellement Contrat Component 4- Project Assistant Administratif et IDA / D1650 A posteriori Individuel Direct 18,000.00 18,000.00 Signé 2018-10-01 2018-10-10 2018-10-20 2018-10-31 2019-10-31 management Financier du Bandundu (Bonny Longala) ZR-COREF-42632-CS-INDV / Renouvellement contrat Component 4- Project Assistant Administratif IDA / D1650 A posteriori Individuel Direct 18,000.00 18,000.00 Signé 2018-10-01 2018-10-10 2018-10-20 2018-10-31 2019-10-31 management Financier Kasaï-Central (Léandre KIBONGE) ZR-COREF-42635-CS-INDV / Renouvellement Contrat Component 4- Project Assistant Administratif et IDA / D1650 A posteriori Individuel Direct 18,000.00 18,000.00 Signé 2018-10-01 2018-10-10 2018-10-20 2018-10-31 2019-10-30 management Financier du Sud-Kivu (Faray ASSUMANI) ZR-COREF-43030-CS-CDS / Renouvellement contrat Component 4- Project secrétaire-logisticienne/NK IDA / D1650 A posteriori Individuel Direct 12,000.00 12,000.00 Signé 2018-10-01 2018-10-11 2018-10-16 2018-11-05 2019-11-05 management (Thérèse MWENGE MBAMBU) ZR-COREF-43032-CS-CDS / Renouvellement contrat Component 4- Project IDA / D1650 A posteriori Individuel Direct 8,400.00 8,400.00 Signé 2018-11-01 2018-11-10 2018-11-13 2018-12-01 2019-12-01 chauffeur-coursier/KWILU management (JIRESSE KAKANA) ZR-COREF-43034-CS-CDS / Renouvellement contrat Component 4- Project chauffeur-coursier/NK IDA / D1650 A posteriori Individuel Direct 8,400.00 8,400.00 Signé 2018-10-01 2018-10-11 2018-10-16 2018-11-01 2019-11-01 management (Jeannot KAMBALE VASIKANIA) ZR-COREF-42888-CS-CDS / Renouvellement contrat du Component 4- Project IDA / D1650 A posteriori Individuel Direct 60,000.00 60,000.00 Signé 2018-09-01 2018-09-07 2018-09-10 2018-10-01 2019-10-01 Coordonnateur Adjoint du management COREF (Babi VANGU) ZR-COREF-42892-CS-CDS / Renouvellement contrat du Component 4- Project chauffeur-coursier de la IDA / D1650 A posteriori Individuel Direct 9,000.00 9,000.00 Signé 2018-02-15 2018-02-17 2018-02-19 2018-03-01 2019-03-01 management Coordination Nationale (Claude ISEKUSU) ZR-COREF-42898-CS-CDS / Renouvellement contrat Component 4- Project AT/Renforcement dispositif IDA / D1650 A posteriori Individuel Direct 54,000.00 54,000.00 Signé 2018-02-15 2018-02-18 2018-02-20 2018-03-01 2019-03-01 management de contrôle des FP (Etienne MAFWENI) ZR-COREF-42903-CS-CDS / Renouvellement contrat de Component 4- Project l'AT/Réforme de la Gestion IDA / D1650 A posteriori Individuel Direct 54,000.00 54,000.00 Signé 2018-02-15 2018-02-17 2018-02-19 2018-03-01 2019-03-01 management de la dépense publique (Jean-Baptiste VEKO) ZR-COREF-42906-CS-CDS / Renouvellement contrat Component 4- Project AT/Réforme comptabilité et IDA / D1650 A posteriori Individuel Direct 54,000.00 54,000.00 Signé 2018-02-15 2018-02-17 2018-02-20 2018-03-01 2019-03-01 management gestion de la trésorerie (Robert BAMBA) ZR-COREF-42909-CS-CDS / Renouvellement contrat de l'expert en FP en charge Component 4- Project IDA / D1650 A posteriori Individuel Direct 54,000.00 54,000.00 Signé 2018-02-15 2018-02-16 2018-02-18 2018-03-01 2019-03-01 du suivi de la société civile management et du budget participatif (Georges TSHIONZA MATA) ZR-COREF-42910-CS-CDS / Renouvellement contrat Component 4- Project IDA / D1650 A posteriori Individuel Direct 54,000.00 54,000.00 Signé 2018-06-01 2018-06-11 2018-06-16 2018-07-01 2019-07-01 AT/Réforme Budgétaire management (SASSE KEMBE) ZR-COREF-42912-CS-CDS / Renouvellement contrat de Component 4- Project l'AT/Décentralisation IDA / D1650 A posteriori Individuel Direct 54,000.00 54,000.00 Signé 2018-08-02 2018-08-08 2018-08-12 2018-09-01 2019-09-01 management Financière (Moïse ASSANI SENGI) ZR-COREF-42916-CS-CDS / Renouvellement Contrat Component 4- Project IDA / D1650 A posteriori Individuel Direct 18,000.00 18,000.00 Signé 2018-06-01 2018-06-04 2018-06-07 2018-07-01 2019-07-01 AAF Equateur (Bruno management BAKANSEKA) Page 8 ZR-COREF-42918-CS-CDS / Renouvellement Contrat Component 4- Project IDA / D1650 A posteriori Individuel Direct 18,000.00 18,000.00 Signé 2018-06-01 2018-06-11 2018-06-16 2018-07-01 2019-07-01 AAF NKV (Jean Claude management SIMPENZE) ZR-COREF-42920-CS-CDS / Renouvellement Contrat Component 4- Project IDA / D1650 A posteriori Individuel Direct 18,000.00 0.00 Annulé 2018-06-01 2018-06-11 2018-06-15 2018-11-18 2018-12-24 AAF Kasaï-Or (Willy management MAKIADI) ZR-COREF-42894-CS-CDS / Renouvellement contrat Component 4- Project AT/Réforme et IDA / D1650 A posteriori Individuel Direct 54,000.00 54,000.00 Signé 2018-02-15 2018-02-18 2018-02-19 2018-03-01 2019-03-01 management Administration Fiscale (Jean- Pierre SAMOLIA) ZR-COREF-50018-CS-INDV / Selection d'un consultant individuel chargé des études et surveillance des petits Component 4- Project IDA / D1650 A posteriori Individuel Limited 90,000.00 180,000.00 Signé 2018-03-05 2018-03-10 2018-03-31 2018-05-05 2018-11-01 travaux de rehabilitation management des bâtiments abritant la coordination nationale du Projet PROFIT CONGO ZR-COREF-42703-CS-CDS / Renouvellement contrat Component 4- Project secrétaire de la IDA / D1650 A posteriori Individuel Direct 12,000.00 12,000.00 Signé 2018-08-02 2018-08-12 2018-09-02 2018-09-30 2019-09-30 management Coordination Provinciale de l'Equateur (Lisette ITOMA) ZR-COREF-56368-CS-INDV / Consultant Individuel d'assurer le coaching des Component 4- Project inspecteurs des finances qui IDA / D1650 A posteriori Individuel Limited 30,000.00 15,000.00 Achevé 2018-03-28 2018-03-30 2018-04-04 2018-04-10 2018-10-07 management assument la fonction d'audit interne au sein du PROFIT CONGO ZR-COREF-80879-CS-INDV / CONSULTANT POUR L'APPUI A L'ANALYSE Component 2 - DES RAPPORTS IDA / D1650 Strengthening budget A posteriori Individuel Limited 25,000.00 0.00 Annulé 2018-10-25 2018-10-27 2018-10-31 2018-11-08 2019-01-07 D'EXECUTION DES oversight MARCHES PUBLICS PAR LES OSC ZR-COREF-80908-CS-INDV / CONSULTANT POUR L'APPUI A L'ANALYSE DE Component 2 - L'EXECUTION DE LA LOI IDA / D1650 Strengthening budget A posteriori Individuel Limited 40,000.00 0.00 Annulé 2018-11-10 2018-11-12 2018-11-16 2018-11-22 2019-01-21 DE FINANCES 2017 PAR oversight LES ORGANISATIONS DE LA SOCIETE CIVILE ZR-COREF-80917-CS-INDV / Recrutement de 2 Component 4- Project IDA / D1650 A posteriori Individuel Limited 3,000.00 0.00 Annulé 2018-11-05 2018-11-07 2018-11-09 2018-11-14 2019-02-12 chauffeurs temporaires pour management le Projet PROFIT CONGO ZR-COREF-96389-CS-INDV / Recrutement d'une Assistante Nationale pour Component 2 - appuyer la mise en œuvre IDA / D1650 Strengthening budget A posteriori Individuel Direct 24,000.00 24,000.00 Signé 2019-03-03 2019-03-07 2019-03-09 2019-04-01 2020-03-31 du Budget Participatif au oversight niveau provincial (Florence MOGBEKUMA) ZR-COREF-96392-CS-INDV / Recrutement d'un(e) Component 4- Project IDA / D1650 A posteriori Individuel Limited 12,000.00 9,000.00 Achevé 2019-03-03 2019-03-06 2019-03-19 2019-04-01 2020-03-31 Assistant(e) pour le suivi management du Budget Participatif (6 mois) ZR-COREF-96399-CS-INDV Component 4- Project / Renouvellement contrat du IDA / D1650 A posteriori Individuel Direct 84,000.00 168,000.00 Signé 2019-03-04 2019-03-08 2019-03-11 2019-03-31 2020-03-30 management Coordonnateur National ZR-COREF-96404-CS-INDV Component 4- Project / Renouvellement contrat du IDA / D1650 A posteriori Individuel Direct 60,000.00 60,000.00 Signé 2019-09-02 2019-09-06 2019-09-13 2019-10-01 2020-09-30 management Coordonnateur Adjoint ZR-COREF-96407-CS-INDV Component 4- Project / Renouvellement contrat du IDA / D1650 A posteriori Individuel Direct 51,600.00 51,600.00 Signé 2019-11-01 2019-11-06 2019-11-13 2019-12-01 2020-11-30 management Responsable Administratif ZR-COREF-96413-CS-INDV / Renouvellement contrat du Component 4- Project IDA / D1650 A posteriori Individuel Direct 51,600.00 51,600.00 Signé 2019-02-01 2019-02-06 2019-02-13 2019-02-28 2020-02-28 Spécialiste en Passation des management Marchés ZR-COREF-96415-CS-INDV / Renouvellement contrat du Component 4- Project IDA / D1650 A posteriori Individuel Direct 51,600.00 51,600.00 Signé 2019-11-01 2019-11-06 2019-11-11 2019-12-01 2020-11-30 Chargé de Suivi et management Evaluation ZR-COREF-96417-CS-INDV Component 4- Project / Renouvellement contrat du IDA / D1650 A posteriori Individuel Direct 30,000.00 30,000.00 Signé 2019-11-01 2019-11-06 2019-11-13 2019-12-01 2020-11-30 management comptable ZR-COREF-96421-CS-INDV / Renouvellement contrat de l'Assistant Technique en Component 4- Project IDA / D1650 A posteriori Individuel Direct 54,000.00 54,000.00 Signé 2019-02-01 2019-02-06 2019-02-11 2019-03-31 2020-03-30 charge de la réforme de la management comptabilité et de la gestion de la trésorerie ZR-COREF-96423-CS-INDV / Renouvellement contrat de Component 4- Project l'assistant technique en IDA / D1650 A posteriori Individuel Direct 54,000.00 54,000.00 Signé 2019-02-01 2019-02-06 2019-02-11 2019-03-31 2020-03-30 management charge de la réforme fiscale et de l'administration fiscale ZR-COREF-96428-CS-INDV / Renouvellement contrat de l'Assistant Technique chargé Component 4- Project IDA / D1650 A posteriori Individuel Direct 54,000.00 54,000.00 Signé 2019-02-02 2019-02-07 2019-02-12 2019-02-28 2020-02-28 de Renforcement du management Dispositif de Contrôle des Finances Publiques ZR-COREF-96433-CS-INDV / Renouvellement contrat de l'Assistant Technique chargé Component 4- Project IDA / D1650 A posteriori Individuel Direct 54,000.00 54,000.00 Signé 2019-02-01 2019-02-06 2019-02-11 2019-02-28 2020-02-28 de la Réforme de la management Gestion de la Dépense Publique Page 9 ZR-COREF-96431-CS-CDS / Recrutement d'un Consultant international cabinet pour la cartographie des risques dans 5 Component 2 - Sélection de nouveaux ministères, faire IDA / D1650 Strengthening budget A posteriori consultants par Direct 380,000.00 377,000.00 Signé 2019-03-15 2019-03-25 2019-05-29 2019-11-25 la revue qualité des guides oversight entente directe d'audit sectoriel de l'IGF et du manuel des procédures, proposer un cadre organique, etc ZR-COREF-96438-CS-INDV / Renouvellement contrat de l'Assistant Technique en Component 4- Project charge de la Transparence IDA / D1650 A posteriori Individuel Direct 54,000.00 54,000.00 Signé 2019-02-01 2019-02-06 2019-02-11 2019-02-28 2020-02-28 management des Finances Publiques et du suivi de la société civile (TSHIONZA MATA) ZR-COREF-96623-CS-INDV / Renouvellement contrat de Component 4- Project l'Assistant Technique IDA / D1650 A posteriori Individuel Direct 54,000.00 54,000.00 Signé 2019-08-01 2019-08-05 2019-08-06 2019-09-01 2020-08-31 management Chargé de la Décentralisation Financière ZR-COREF-96627-CS-INDV / Renouvellement contrat de Component 4- Project IDA / D1650 A posteriori Individuel Direct 34,200.00 34,200.00 Signé 2019-08-01 2019-08-05 2019-08-06 2019-09-01 2020-08-31 l'Assistante du management Coordonnateur National ZR-COREF-96629-CS-INDV / Renouvellement contrat de Component 4- Project IDA / D1650 A posteriori Individuel Direct 30,000.00 30,000.00 Signé 2019-08-01 2019-08-05 2019-08-06 2019-09-01 2020-08-31 la Chargée de management Communication ZR-COREF-96631-CS-INDV / Renouvellement contrat de Component 4- Project l'Assistant Technique en IDA / D1650 A posteriori Individuel Direct 54,000.00 54,000.00 Signé 2019-06-01 2019-06-04 2019-06-22 2019-07-01 2020-06-30 management charge de la Réforme Budgétaire ZR-COREF-96634-CS-INDV / Selection consultant individuel pour élaborer le manuel des procédures de paiement des impôts, droits, Component 1- Improving IDA / D1650 A posteriori Individuel Limited 40,000.00 39,500.00 Signé 2019-05-15 2019-05-20 2019-06-10 2019-07-15 2020-01-11 taxes et redevances des budget execution processes provinces ainsi que droits, taxes et redevances du pouvoir central par secteur d'activités ZR-COREF-96635-CS-INDV / Renouvellement contrat de Component 4- Project l'assistant technique chargé IDA / D1650 A posteriori Individuel Direct 54,000.00 54,000.00 Signé 2019-01-25 2019-01-28 2019-01-29 2019-01-31 2020-01-31 management de la Décentralisation Financière ZR-COREF-96643-CS-INDV / Renouvellement contrat du Component 4- Project IDA / D1650 A posteriori Individuel Direct 12,000.00 12,000.00 Signé 2019-01-25 2019-01-28 2019-01-29 2019-01-31 2020-01-31 secrétaire logisticien du management Kasaï-Oriental ZR-COREF-96646-CS-INDV / Renouvellement contrat de Component 4- Project IDA / D1650 A posteriori Individuel Direct 12,000.00 12,000.00 Signé 2019-01-25 2019-01-28 2019-01-29 2019-01-31 2020-01-31 la secrétaire logisticienne du management Sud-Kivu ZR-COREF-96647-CS-INDV / Renouvellement contrat du Component 4- Project chauffeur coursier de la IDA / D1650 A posteriori Individuel Direct 8,400.00 8,400.00 Signé 2019-01-25 2019-01-28 2019-01-29 2019-01-31 2020-01-31 management Coordination Provinciale du Kasaï-Oriental ZR-COREF-96650-CS-INDV / Renouvellement contrat du Component 4- Project chauffeur-coursier de la IDA / D1650 A posteriori Individuel Direct 8,400.00 8,400.00 Signé 2019-01-25 2019-01-28 2019-01-29 2019-01-31 2020-01-31 management coordination provinciale du Sud-Kivu ZR-COREF-96651-CS-INDV Component 4- Project / Renouvellement contrat IDA / D1650 A posteriori Individuel Direct 18,000.00 18,000.00 Signé 2019-02-01 2019-02-05 2019-02-11 2019-02-28 2020-02-28 management trésorière ZR-COREF-96658-CS-INDV / Renouvellement contrat du Component 4- Project chauffeur-coursier de la IDA / D1650 A posteriori Individuel Direct 9,000.00 9,000.00 Signé 2019-02-01 2019-02-05 2019-02-11 2019-02-28 2020-02-28 management Coordination nationale du PROFIT-CONGO ZR-COREF-96662-CS-INDV / Renouvellement contrat de Component 4- Project IDA / D1650 A posteriori Individuel Direct 18,000.00 18,000.00 Signé 2019-03-01 2019-03-05 2019-03-08 2019-04-01 2020-03-31 l'Assistante en Passation management des Marchés ZR-COREF-96664-CS-INDV Component 4- Project / Renouvellement contrat de IDA / D1650 A posteriori Individuel Direct 12,000.00 12,000.00 Signé 2019-02-01 2019-02-05 2019-02-08 2019-03-04 2020-03-03 management la Réceptionniste ZR-COREF-96666-CS-INDV / Renouvellement contrat de Component 4- Project la secrétaire logisticienne de IDA / D1650 A posteriori Individuel Direct 12,000.00 12,000.00 Signé 2019-03-01 2019-03-05 2019-03-08 2019-04-01 2020-03-31 management la Coordination Provinciale du Kwilu ZR-COREF-96668-CS-INDV / Renouvellement contrat du Component 4- Project chauffeur-coursier de la IDA / D1650 A posteriori Individuel Direct 8,400.00 8,400.00 Signé 2019-02-01 2019-02-05 2019-02-11 2019-02-28 2020-02-28 management coordination provinciale du Kasaî-Central ZR-COREF-96669-CS-INDV / Renouvellement contrat du Component 4- Project secrétaire-logisticien de la IDA / D1650 A posteriori Individuel Direct 12,000.00 12,000.00 Signé 2019-02-01 2019-02-05 2019-02-11 2019-02-28 2020-02-28 management coordination provinciale du Kasaï-Central ZR-COREF-96670-CS-INDV / Renouvellement contrat de Component 4- Project la secrétaire-logisticienne de IDA / D1650 A posteriori Individuel Direct 12,000.00 12,000.00 Signé 2019-09-02 2019-09-06 2019-09-13 2019-10-01 2020-09-30 management la Coordination Provinciale de l'Equateur Page 10 ZR-COREF-96673-CS-INDV / Renouvellement contrat du Component 4- Project IDA / D1650 A posteriori Individuel Direct 34,200.00 34,200.00 Signé 2019-11-01 2019-11-06 2019-11-11 2019-12-01 2020-11-30 coordonnateur provincial de management l'Equateur ZR-COREF-96675-CS-INDV / Renouvellement contrat du Component 4- Project IDA / D1650 A posteriori Individuel Direct 34,200.00 34,200.00 Signé 2019-11-01 2019-11-06 2019-11-11 2019-12-01 2020-11-30 coordonnateur provincial du management Kasaï-Oriental ZR-COREF-96678-CS-INDV / Renouvellement contrat du Component 4- Project IDA / D1650 A posteriori Individuel Direct 34,200.00 34,200.00 Signé 2019-10-01 2019-10-03 2019-10-11 2019-10-31 2020-10-30 Coordonnateur Provincial de management Kwilu ZR-COREF-96681-CS-INDV / Renouvellement contrat du Component 4- Project IDA / D1650 A posteriori Individuel Direct 34,200.00 34,200.00 Signé 2019-10-01 2019-10-03 2019-10-11 2019-10-31 2020-10-30 coordonnateur provincial du management Haut Katanga ZR-COREF-96682-CS-INDV / Renouvellement contrat de Component 4- Project IDA / D1650 A posteriori Individuel Direct 34,200.00 34,200.00 Signé 2019-10-01 2019-10-03 2019-10-11 2019-10-31 2020-10-30 la coordonnatrice provinciale management du Sud-Kivu ZR-COREF-96684-CS-INDV / Renouvellement contrat du Component 4- Project IDA / D1650 A posteriori Individuel Direct 34,200.00 34,200.00 Signé 2019-10-01 2019-10-03 2019-10-11 2019-10-31 2020-10-30 coordonnateur provincial du management Kasaï-Central ZR-COREF-96687-CS-INDV / Renouvellement contrat de Component 4- Project l'assistant administratif et IDA / D1650 A posteriori Individuel Direct 18,000.00 18,000.00 Signé 2019-06-01 2019-06-04 2019-06-22 2019-07-01 2020-06-30 management financier de la coordination provinciale de l'Equateur ZR-COREF-96690-CS-INDV / Renouvellement contrat de Component 4- Project l'assistant administratif et IDA / D1650 A posteriori Individuel Direct 18,000.00 18,000.00 Signé 2019-06-01 2019-06-04 2019-06-22 2019-07-01 2020-06-30 management financier de la coordination provinciale du Nord-Kivu ZR-COREF-96691-CS-INDV / Renouvellement contrat de Component 4- Project la secrétaire-logisticienne de IDA / D1650 A posteriori Individuel Direct 12,000.00 12,000.00 Signé 2019-10-01 2019-10-03 2019-10-11 2019-10-31 2020-10-30 management la Coordination provinciale du Nord-Kivu ZR-COREF-96692-CS-INDV / Renouvellement contrat du Component 4- Project chauffeur-coursier de la IDA / D1650 A posteriori Individuel Direct 8,400.00 8,400.00 Signé 2019-10-01 2019-10-03 2019-10-11 2019-10-31 2020-10-30 management coordination provinciale du Nord-Kivu ZR-COREF-96693-CS-INDV / Renouvellement contrat du Component 4- Project chauffeur-coursier de la IDA / D1650 A posteriori Individuel Direct 8,400.00 8,400.00 Signé 2019-11-01 2019-11-06 2019-11-11 2019-12-01 2020-11-30 management coordination provinciale de Kwilu ZR-COREF-96712-CS-INDV / Renouvellement contrat de Component 4- Project l'Assistant Administratif et IDA / D1650 A posteriori Individuel Direct 18,000.00 18,000.00 Signé 2019-10-01 2019-10-03 2019-10-11 2019-10-31 2020-10-30 management Financier de la Coordination Provinciale du Sud-Kivu ZR-COREF-96713-CS-INDV / Renouvellement contrat de Component 4- Project l'assistant Administratif et IDA / D1650 A posteriori Individuel Direct 18,000.00 18,000.00 Signé 2019-10-01 2019-10-03 2019-10-11 2019-10-31 2020-10-30 management Financier de la Coordination Provinciale du Haut-Katanga ZR-COREF-96714-CS-INDV / Renouvellement contrat de Component 4- Project l'Assistant Administratif et IDA / D1650 A posteriori Individuel Direct 18,000.00 18,000.00 Signé 2019-10-01 2019-10-03 2019-10-11 2019-10-31 2020-10-30 management Financier de la coordination provinciale du Kasaï-Central ZR-COREF-96715-CS-INDV / Renouvellement de Component 4- Project l'Assistant Administratif et IDA / D1650 A posteriori Individuel Direct 18,000.00 34,200.00 Signé 2019-10-01 2019-10-03 2019-10-11 2019-10-31 2020-10-30 management Financier de la Coordination Provinciale de KWILU ZR-COREF-96716-CS-INDV / Renouvellement contrat de Component 4- Project l'Assistant Administratif et IDA / D1650 A posteriori Individuel Direct 18,000.00 9,000.00 Signé 2019-09-02 2019-09-05 2019-09-06 2019-10-01 2020-09-30 management Financier de la Coordination Provinciale du Kasaï-Oriental ZR-COREF-96717-CS-INDV Component 4- Project / Recrutement d'un second IDA / D1650 A posteriori Individuel Limited 30,000.00 30,000.00 Signé 2019-02-01 2019-02-06 2019-02-20 2019-02-28 2020-02-28 management comptable ZR-COREF-96720-CS-INDV / Recrutement de deux Component 4- Project chauffeur-coursiers pour la IDA / D1650 A posteriori Individuel Limited 18,000.00 16,800.00 Signé 2019-02-01 2019-02-06 2019-02-20 2019-02-28 2020-02-28 management Coordination Nationale du PROFIT-CONGO ZR-COREF-98996-CS-CDS / sélection d'un consultant en vue d'élaborer le plan de Component 2 - Sélection de formation et de mettre en IDA / D1650 Strengthening budget A posteriori consultants par Direct 60,000.00 60,000.00 Achevé 2019-03-15 2019-03-25 2019-04-21 2019-08-19 œuvre le programme de oversight entente directe formation des DAF (IBrahima Ndiaye) ZR-COREF-96439-CS-INDV / Sélection d'un consultant chargé d'accompagner la Component 1- Improving mise en place des services IDA / D1650 A priori Individuel Limited 200,000.00 124,000.00 Signé 2019-03-11 2019-03-25 2019-04-04 2019-04-10 2020-04-09 budget execution processes de la Direction Générale du Tresor, de la Comptabilité et de la Paie ZR-COREF-107885-CS-CDS / Sélection d'un Consultant Sélection de Evaluateur (01) de l'équipe Component 1- Improving IDA / D1650 A posteriori consultants par Direct 3,000.00 3,000.00 Achevé 2019-03-31 2019-04-03 2019-04-09 2019-06-08 d'évaluation MAPS II budget execution processes entente directe (KALUKIKA KABIONA Désiré) Page 11 ZR-COREF-107890-CS-CDS / Sélection d'un Consultant Sélection de Evaluateur (02) dans le Component 1- Improving IDA / D1650 A posteriori consultants par Direct 3,000.00 3,000.00 Achevé 2019-03-31 2019-04-03 2019-04-09 2019-06-08 cadre de l'Evaluation MAPS budget execution processes entente directe II (LUSALEMVO TUTALA Big) ZR-COREF-107892-CS-CDS / Sélection d'un Consultant Sélection de Evaluateur (03) dans le Component 1- Improving IDA / D1650 A posteriori consultants par Direct 3,000.00 3,000.00 Achevé 2019-03-31 2019-04-03 2019-04-09 2019-06-08 cadre de l'Evaluation MAPS budget execution processes entente directe II (BUABUA ILUNGA Georges) ZR-COREF-107893-CS-CDS / Sélection d'un Consultant Sélection de Expert Evaluateur (04) dans Component 1- Improving IDA / D1650 A posteriori consultants par Direct 3,000.00 3,000.00 Achevé 2019-03-31 2019-04-03 2019-04-09 2019-06-08 le cadre de l'Evaluation budget execution processes entente directe MAPS II (MEKE A SOLOKO Jean Clair) ZR-COREF-107895-CS-CDS / Sélection d'un Consultant Sélection de Expert Evaluateur (05) dans Component 1- Improving IDA / D1650 A posteriori consultants par Direct 3,000.00 3,000.00 Achevé 2019-03-31 2019-04-03 2019-04-09 2019-06-08 le cadre de l'évaluation budget execution processes entente directe MAPS II (KABUNDA WA KABUNDA Jonas) ZR-COREF-107897-CS-CDS / Sélection d'un Consultant Sélection de Expert Evaluateur (06) dans Component 1- Improving IDA / D1650 A posteriori consultants par Direct 3,000.00 3,000.00 Achevé 2019-03-31 2019-04-03 2019-04-09 2019-06-08 le cadre de l'évaluation budget execution processes entente directe MAPS II (BARUTI LISUNGI Don de Dieu) ZR-COREF-107899-CS-CDS / Sélection d'un Consultant Sélection de Expert Evaluateur (07) dans Component 1- Improving IDA / D1650 A posteriori consultants par Direct 3,000.00 3,000.00 Achevé 2019-03-31 2019-04-03 2019-04-09 2019-06-08 le cadre de l'Evaluation budget execution processes entente directe MAPS II (MANGOMBE MAKENGO Paola) ZR-COREF-107901-CS-CDS / Sélection d'un Consultant Sélection de Expert Evaluateur (08) dans Component 1- Improving IDA / D1650 A posteriori consultants par Direct 3,000.00 3,000.00 Achevé 2019-03-31 2019-04-03 2019-04-09 2019-06-08 le cadre de l'évaluation budget execution processes entente directe MAPS II (GBETELE MOKULONGO Aimé) ZR-COREF-107903-CS-CDS / Sélection d'un Consultant Sélection de Expert Evaluateur (09) dans Component 1- Improving IDA / D1650 A posteriori consultants par Direct 3,000.00 3,000.00 Achevé 2019-03-31 2019-04-03 2019-04-09 2019-06-08 le cadre de l'évaluation budget execution processes entente directe MAPS II (PERO NGWAMASHI Alain) ZR-COREF-107906-CS-CDS / Sélection d'un Consultant Sélection de Expert Evaluateur (10) dans Component 1- Improving IDA / D1650 A posteriori consultants par Direct 3,000.00 3,000.00 Achevé 2019-03-31 2019-04-03 2019-04-09 2019-06-08 le cadre de l'évaluation budget execution processes entente directe MAPS II (NKULI MBALI Basile) ZR-COREF-107909-CS-CDS / Sélection d'un Consultant Sélection de Expert Evaluateur (11) dans Component 1- Improving IDA / D1650 A posteriori consultants par Direct 3,000.00 3,000.00 Achevé 2019-03-31 2019-04-03 2019-04-09 2019-06-08 le cadre de l'évaluation budget execution processes entente directe MAPS II (KALUME KAYEMBE Christian) ZR-COREF-107912-CS-CDS / Sélection d'un Consultant Sélection de Expert Evaluateur (12) dans Component 1- Improving IDA / D1650 A posteriori consultants par Direct 3,000.00 3,000.00 Achevé 2019-03-31 2019-04-03 2019-04-09 2019-06-08 le cadre de l'évaluation budget execution processes entente directe MAPS II (KIBUAKA KILUSAMBO Willy) ZR-COREF-107914-CS-CDS / Sélection d'un Consultant Expert Evaluateur et Sélection de membre du secrétariat Component 1- Improving IDA / D1650 A posteriori consultants par Direct 5,000.00 4,320.00 Achevé 2019-03-31 2019-04-03 2019-04-09 2019-06-08 technique (01) dans le cadre budget execution processes entente directe de l'évaluation MAPS II (SENGABO BAKUNZI Patrick) ZR-COREF-107918-CS-CDS / Sélection d'un Consultant Expert évaluateur et Sélection de membre du secrétariat Component 1- Improving IDA / D1650 A posteriori consultants par Direct 5,000.00 4,320.00 Achevé 2019-03-31 2019-04-03 2019-04-09 2019-06-08 technique (02) dans le cadre budget execution processes entente directe de l'évaluation MAPS II ( MUKAMBA KIZOGU Patrick) ZR-COREF-107919-CS-CDS / Sélection d'un Consultant expert évaluateur et Sélection de Component 1- Improving membre du secrétariat IDA / D1650 A posteriori consultants par Direct 5,000.00 4,320.00 Achevé 2019-03-31 2019-04-03 2019-04-09 2019-06-08 budget execution processes technique (03) dans le cadre entente directe de l'évaluation MAPS II (KALONJI KAMBWA Roger) ZR-COREF-107920-CS-CDS / Sélection d'un Consultant Expert Evaluateur et Sélection de Component 1- Improving membre du Secrétariat IDA / D1650 A posteriori consultants par Direct 5,000.00 4,320.00 Achevé 2019-03-31 2019-04-03 2019-04-09 2019-07-08 budget execution processes technique (04) dans le cadre entente directe de l'évaluation MAPS II (YUMBA NGOY Raymond) ZR-COREF-107921-CS-CDS / Sélection d'un Consultant Expert Evaluateur et Sélection de superviseur du secrétariat Component 1- Improving IDA / D1650 A posteriori consultants par Direct 5,500.00 4,680.00 Achevé 2019-03-31 2019-04-03 2019-04-09 2019-07-08 technique dans le cadre de budget execution processes entente directe l'évaluation MAPS II (KUZIKESA KASWENGI Céleste) ZR-COREF-107923-CS-CDS / Sélection d'un Consultant expert Evaluateur et Coordonnateur du Sélection de Component 1- Improving Secrétariat technique dans IDA / D1650 A posteriori consultants par Direct 5,500.00 4,680.00 Achevé 2019-03-31 2019-04-03 2019-04-09 2019-07-08 budget execution processes le cadre de la mission entente directe d'évaluation MAPS II (NGUNZA BENGA SAKA Magloire) Page 12 ZR-COREF-42682-CS-INDV / Sélection d'un Consultant international pour la revue Component 1- Improving IDA / D1650 A posteriori Individuel Limited 50,000.00 0.00 Annulé 2018-09-03 2018-09-08 2018-09-29 2018-11-03 2019-05-02 qualité des cartographies budget execution processes produites dans les 5 Ministères cibles ZR-COREF-96632-CS-INDV / Sélection d'un consultant national chargé de la formation sur les techniques documentaires et la mise en place du système Component 1- Improving IDA / D1650 A posteriori Individuel Limited 50,000.00 0.00 Annulé 2019-04-10 2019-04-15 2019-04-22 2019-05-09 2019-09-06 d'archivage en vue budget execution processes d'améliorer l'organisation, la conservation, la gestion et la traçabilité de l'information au sein de la DGDP ZR-COREF-96644-CS-INDV / Sélection d'un consultant en vue de réaliser la formation au bénéfice des Component 1- Improving agents sur l'inspection et le IDA / D1650 A posteriori Individuel Limited 30,000.00 0.00 Annulé 2019-04-25 2019-04-30 2019-05-21 2019-06-25 2019-12-22 budget execution processes contrôle des télécommunications et l'évaluation des produits Miniers ZR-COREF-96408-CS-INDV / Sélection Consultant Individuel pour appuyer le suivi de l'exécution Component 2 - trimestrielle et annuelle des IDA / D1650 Strengthening budget A posteriori Individuel Limited 25,000.00 0.00 Annulé 2019-06-10 2019-06-15 2019-06-22 2019-07-06 2019-11-03 dépenses publiques dans les oversight ministères pro-pauvres : collecte des données, analyse, ZR-COREF-96401-CS-INDV / Selection Consultant Individuel pour appuyer la Component 2 - production d'un rapport sur IDA / D1650 Strengthening budget A posteriori Individuel Limited 25,000.00 0.00 Annulé 2019-06-10 2019-06-15 2019-06-22 2019-07-06 2019-11-03 l'exécution de la loi des oversight finances : collecte des données, analyse, atelier de validation, plaidoyer ZR-COREF-80870-CS-INDV / CONSULTANT POUR REALISER LA MISSION DE SUIVI DE L'EXECUTION Component 2 - TRIMESTRIELLE ET IDA / D1650 Strengthening budget A posteriori Individuel Limited 50,000.00 0.00 Annulé 2018-11-10 2018-11-12 2018-11-26 2018-12-15 2019-06-13 ANNUELLE DES oversight DEPENSES DANS LES MINISTERES PRO- PAUVRES 2018 PAR LES ORGANISATIONS DE LA SOCIETE CIVILE ZR-COREF-96676-CS-INDV / Renouvellement contrat du Component 4- Project IDA / D1650 A posteriori Individuel Direct 34,200.00 0.00 Annulé 2019-11-01 2019-11-06 2019-11-11 2019-12-01 2020-11-30 Coordonnateur Provincial du management Nord-Kivu ZR-COREF-96710-CS-INDV / Recrutement d'un Component 4- Project chauffeur-coursier pour la IDA / D1650 A posteriori Individuel Limited 8,400.00 0.00 Annulé 2019-01-25 2019-01-28 2019-01-29 2019-01-31 2020-01-31 management coordination provincial du Haut-Katanga ZR-COREF-96711-CS-INDV / Recrutement d'un Component 4- Project chauffeur-coursier pour la IDA / D1650 A posteriori Individuel Limited 8,400.00 0.00 Annulé 2019-01-25 2019-01-28 2019-01-29 2019-01-31 2020-01-31 management coordination provinciale de l'Equateur ZR-COREF-96708-CS-INDV / Recrutement d'un(e) Component 4- Project Secrétaire-Logisticien(ne) IDA / D1650 A posteriori Individuel Limited 12,000.00 0.00 Annulé 2019-01-25 2019-01-28 2019-01-29 2019-01-31 2020-01-31 management pour la coordination provinciale du Haut-Katanga ZR-COREF-153965-CS- INDV / Sélection d’un consultant en vue de développer en faveur du Component 1- Improving En attente IDA / D1650 A posteriori Individuel Limited 60,000.00 0.00 2020-04-15 2020-04-20 2020-05-11 2020-06-09 2020-09-07 Secrétariat technique du budget execution processes d'exécution Comité PTR, un logiciel de traitement des données de la gestion de trésorerie ZR-COREF-154947-CS- INDV / sélection de consultants individuels pour Component 3 - produire un modèle d'édit Strengthening public En attente IDA / D1650 A posteriori Individuel Limited 40,000.00 0.00 2020-06-15 2020-06-20 2020-07-11 2020-08-15 2021-02-11 budgétaire type conforme à financial management d'exécution la nomenclature budgétaire systems at provincial level et présentation dans les provinces ZR-COREF-155169-CS- INDV / Sélection d'un Consultant chargé d'appuyer Component 4- Project En attente l'élaboration de la stratégie IDA / D1650 A posteriori Individuel Limited 30,000.00 0.00 2020-06-15 2020-06-20 2020-07-11 2020-08-15 2021-02-11 management d'exécution de communication de la stratégie de la réforme des finances publiques ZR-COREF-156231-CS- INDV / Sélection d'un Consultant international pour assurer l’actualisation du plan d’orientation globale Component 1- Improving En attente IDA / D1650 A posteriori Individuel Limited 90,000.00 0.00 2020-04-20 2020-04-25 2020-05-09 2020-05-29 2020-08-27 de l’informatisation du budget execution processes d'exécution système de gestion des Finances Publiques et de l'Administration Publique(POG) ZR-COREF-156243-CS- INDV / Sélection d'un Premier Consultant national pour assurer l’actualisation du plan d’orientation globale Component 1- Improving En attente IDA / D1650 A posteriori Individuel Limited 30,000.00 0.00 2020-04-20 2020-04-25 2020-05-09 2020-05-29 2020-08-27 de l’informatisation du budget execution processes d'exécution système de gestion des finances publiques et de l'administration publique(POG) Page 13 ZR-COREF-156245-CS- INDV / Sélection d'un Deuxième Consultant national pour assurer l’actualisation du plan Component 1- Improving En attente IDA / D1650 A posteriori Individuel Limited 30,000.00 0.00 2020-04-20 2020-04-25 2020-05-09 2020-05-29 2020-08-27 d’orientation globale de budget execution processes d'exécution l’informatisation du système de gestion des finances publiques et de l'administration publique(POG) ZR-COREF-156293-CS- INDV / Sélection du Component 2 - Consultant National pour En attente IDA / D1650 Strengthening budget A posteriori Individuel Direct 9,000.00 0.00 2020-06-15 2020-06-25 2020-06-30 2020-07-10 2021-01-06 appuyer la mise en œuvre d'exécution oversight du Budget Participatif au niveau national ZR-COREF-156532-CS- INDV / Sélection d'un consultant international pour la revue qualité de la Component 1- Improving En attente feuille de route pour la IDA / D1650 A posteriori Individuel Limited 30,000.00 0.00 2020-04-06 2020-04-11 2020-05-02 2020-05-22 2020-07-06 budget execution processes d'exécution migration vers le budget- programme et du plan de formation sur la mise en œuvre du Budget-Proramme ZR-COREF-156541-CS- Component 3 - INDV / Sélection d'un Strengthening public En attente IDA / D1650 A posteriori Individuel Limited 20,000.00 0.00 2020-03-15 2020-03-20 2020-04-03 2020-04-18 2020-06-17 consultant pour produire un financial management d'exécution modèle type du PEB systems at provincial level ZR-COREF-156542-CS- Component 3 - INDV / Sélection d'un Strengthening public En attente consultant pour produire un IDA / D1650 A posteriori Individuel Limited 20,000.00 0.00 2020-03-15 2020-03-20 2020-04-03 2020-04-18 2020-06-17 financial management d'exécution modèle type du PTR (Plan systems at provincial level de Trésorerie) ZR-COREF-156544-CS- INDV / Sélection d'un consultant individuel Component 3 - international Spécialiste en Strengthening public En attente IDA / D1650 A posteriori Individuel Limited 90,000.00 0.00 2020-02-25 2020-03-01 2020-03-15 2020-03-30 2020-06-14 Décentralisation Financière financial management d'exécution pour élaborer la stratégie systems at provincial level des réformes des finances publiques en provinces ZR-COREF-156546-CS- INDV / Sélection d'un Component 3 - consultant national Strengthening public En attente Spécialiste en Gestion IDA / D1650 A posteriori Individuel Limited 30,000.00 0.00 2020-02-25 2020-03-01 2020-03-15 2020-03-30 2020-05-29 financial management d'exécution Budgétaire pour élaborer la systems at provincial level stratégie des réformes des finances publiques en provinces ZR-COREF-156547-CS- INDV / Sélection d'un consultant national Component 3 - Spécialiste en Système Strengthening public En attente IDA / D1650 A posteriori Individuel Limited 30,000.00 0.00 2020-02-25 2020-03-01 2020-03-15 2020-03-30 2020-05-29 d'information des Finances financial management d'exécution Publiques pour élaborer la systems at provincial level stratégie des réformes des finances publiques en provinces Page 14