Summarized Procurement Plan I. General 1. Project Name: Integrated Cities and Urban Development Project ( ICUD) 2. Period covered by this procurement plan: First 18 months II. Goods and Non-consulting Services 1. Procurement Methods and Prior Review Thresholds: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Category Method of Threshold (US$ Prior Review Threshold (US$ Procurement Equivalent) Equivalent) Goods ICB No threshold All contracts above $1,000,000 NCB <500,000 None Shopping <100,000 None Direct No threshold All contracts Contracting Non- ICB No threshold All contracts above $1,000,000 consulting services NCB <1,000,000 None Shopping <100,000 None Direct No threshold All contracts Contracting III. Selection of Consultants 1. Selection Methods and Prior Review Thresholds: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Category Selection Threshold Prior Review Threshold Method (US$ Equivalent) (US$ Equivalent) Consulting QCBS/QBS No threshold All contracts above $500,000 Services Firms FBS/CQS/LCS <200,000 None Sole Source No threshold All contracts Individuals IC No threshold All contracts above $200,000 Sole Source No threshold All contracts 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than US$300,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. All Terms of Reference shall be subject to the World Bank’s clearance. PROCUREMENT West Bank and Gaza : GZ-Integrated Cities and Urban Development Project PLAN General Information Country: West Bank and Gaza Bank’s Approval Date of the Original Procurement Plan: 2016-08-17 2021-07-26 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P150991 GPN Date: 2016-08-17 Project Name: GZ-Integrated Cities and Urban Development Project Loan / Credit No: / , TF / A2846 M Executing Agency(ies): unicipal Development and Lending Fund WORKS Procureme Activity Reference No. / Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH nt Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) Justification for Award Type Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component No. 2: Project GZ-MDLF-841-GO-RFQ / Request for Single Stage - One / Implementation Support and Post Limited 3,109.96 Completed 2016-10-06 2017-03-16 2016-12-01 2017-03-30 2017-05-30 2017-04-12 Supply of Office Furniture. Quotations Envelope Management Cost Component No. 2: Project GZ-MDLF-840-GO-RFQ / Request for Single Stage - One / Implementation Support and Post Limited 20,518.00 Completed 2016-10-05 2017-03-01 2016-11-30 2017-03-20 2017-05-29 2017-05-03 Supply of Hardware Quotations Envelope Management Cost GZ-MDLF-2666-GO-RFQ / Component No. 1: Planning Request for Single Stage - One Supply of Hardware for the / Post Limited 1,767.00 Completed 2016-10-23 2016-10-25 2016-12-18 2016-11-03 2017-06-16 2016-11-08 for Sustainable Urban Growth Quotations Envelope Technical Supervisor. GZ-MDLF-5595-GO-RFQ / Component No. 2: Project Provision of Adobe Design Request for Single Stage - One TF / A2846 Implementation Support and Post Open - National 0.00 Canceled 2017-03-06 2017-05-01 2017-10-28 Package and GIS software for Quotations Envelope Management Cost the project. GZ-MDLF-33859-GO-RFQ / Component No. 1: Planning Request for Single Stage - One Supply of Total Station for TF / A2846 Post Limited 0.00 Terminated 2017-11-10 2017-12-03 2018-01-05 2017-12-26 2018-07-04 for Sustainable Urban Growth Quotations Envelope Gaza Municipality GZ-MDLF-41088-GO-RFQ / Supply of Hardware for the Component No. 1: Planning Request for Single Stage - One TF / A2846 Post Limited 1,487.00 Completed 2018-01-01 2018-01-30 2018-02-19 2018-02-12 2018-03-21 2018-03-06 Technical Coordinator at for Sustainable Urban Growth Quotations Envelope MOLG GZ-MDLF-842-GO-RFQ / Component No. 1: Planning Request for Single Stage - One / Post Limited 0.00 Canceled 2016-10-05 2016-11-30 2017-05-29 Supply of Hardware for Gaza for Sustainable Urban Growth Quotations Envelope GZ-MDLF-57568-GO-RFQ / Supply of hardware to support Component No. 1: Planning Request for Single Stage - One TF / A2846 Post Limited 29,991.00 Completed 2018-06-06 2018-06-24 2018-08-01 2018-08-08 2018-09-30 2018-10-31 development of Integrated GIS for Sustainable Urban Growth Quotations Envelope database/Hebron Urban Area GZ-MDLF-57569-GO-RFQ / Supply of Hardware to support Component No. 1: Planning Request for Single Stage - One TF / A2846 Post Limited 13,990.00 Completed 2018-04-25 2018-07-23 2018-06-20 2018-08-28 2018-08-19 2019-01-13 Integrated Planning in Gaza for Sustainable Urban Growth Quotations Envelope Municipality GZ-MDLF-67743-GO-RFQ / Component No. 1: Planning Supply of Tow Total Stations TF / A2846 Post Direct Selection Direct 37,324.00 Completed 2018-06-25 2018-07-15 2018-06-30 2018-07-17 2018-08-04 2018-07-24 2019-01-31 2018-08-02 for Sustainable Urban Growth for Gaza Municipality GZ-MDLF-185208-GO-RFQ / Pending Supply of a Central Component No. 1: Planning Request for Single Stage - One TF / A2846 Post Open - National 0.00 Implementati 2021-02-20 2021-04-17 2021-08-15 Cardboard Baler Machine for for Sustainable Urban Growth Quotations Envelope on Bethlehem Urban Area GZ-MDLF-185237-GO-DIR / Pending Component No. 1: Planning Supply of Software for Traffic TF / A2846 Post Direct Selection Direct 0.00 Implementati 2020-08-01 2020-08-06 2020-09-10 2021-03-09 for Sustainable Urban Growth Modelling-Ramallah & Al Bireh on GZ-MDLF-164011-GO-DIR / Component No. 1: Planning Supply of Software for Traffic TF / A2846 Post Direct Selection Direct 87,472.10 Completed 2020-09-01 2020-04-19 2020-09-06 2020-11-23 2020-10-11 2020-12-20 2021-04-09 2021-04-29 for Sustainable Urban Growth Modelling GZ-MDLF-201708-GO-RFQ / Component No. 2: Project Request for Single Stage - One Supply of hardware for the TF / A2846 Implementation Support and Post Limited 10,575.00 Completed 2020-11-09 2020-11-30 2021-01-04 2021-02-02 2021-02-03 2021-03-30 Quotations Envelope ICUD team Management Cost GZ-MDLF-222287-GO-RFQ / Component No. 1: Planning Request for Single Stage - One Acquisition of an aerial photo TF / A2846 Post Limited 58,800.00 Signed 2021-03-15 2021-03-24 2021-05-10 2021-06-16 2021-09-07 for Sustainable Urban Growth Quotations Envelope for Gaza city GZ-MDLF-222290-GO-RFQ / Supply of IT hardware for Component No. 1: Planning Request for Single Stage - One Gaza city Infrastructure TF / A2846 Post Limited 44,085.00 Signed 2021-03-15 2021-03-15 2021-05-10 2021-04-15 2021-08-08 for Sustainable Urban Growth Quotations Envelope management and planning optimization GZ-MDLF-222293-GO-RFQ / SCADA system software for Component No. 1: Planning Request for Single Stage - One TF / A2846 Post Limited 0.00 Canceled 2021-03-15 2021-05-10 2021-08-08 water maintenance and for Sustainable Urban Growth Quotations Envelope monitoring GZ-MDLF-233807-GO-RFQ / Pending Supply and Install of Solar Component No. 1: Planning Request for Single Stage - One TF / A2846 Post Limited 0.00 Implementati 2021-08-21 2021-10-16 2022-01-14 Photovoltaic Systems for Gaza for Sustainable Urban Growth Quotations Envelope on Urban Area Page 1 GZ-MDLF-233805-GO-RFB / Supply and Install of Solar Pending Component No. 1: Planning Single Stage - One Photovoltaic Systems for TF / A2846 Post Request for Bids Open - National 0.00 Implementati 2021-09-15 2021-09-20 2021-11-01 2021-12-01 2022-01-05 2022-05-05 for Sustainable Urban Growth Envelope Targeted Urban Areas in West on Bank" NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GZ-MDLF-79395-NC-RFQ / Component No. 1: Planning Request for Single Stage - One Geographic Information TF / A2846 Post Limited 15,070.70 Completed 2018-10-25 2018-10-07 2018-12-20 2018-10-31 2019-02-03 2019-01-31 for Sustainable Urban Growth Quotations Envelope System (GIS) Training GZ-MDLF-78354-NC-RFQ / Component No. 1: Planning Request for Single Stage - One TF / A2846 Post Open - National 18,453.00 Completed 2018-10-20 2018-12-15 2019-01-17 2019-04-14 2019-05-12 Beit Sahour Photogrammetry for Sustainable Urban Growth Quotations Envelope GZ-MDLF-112708-NC-RFQ / Training Courses for IT officers (Administrator & Component No. 1: Planning Request for Single Stage - One TF / A2846 Post Limited 10,892.60 Completed 2019-05-14 2019-05-21 2019-07-09 2019-06-17 2019-10-07 2019-09-12 Developers ): To Manage and for Sustainable Urban Growth Quotations Envelope Develop the Urban Performance Tool GZ-MDLF-843-NC-RFQ / Supply of Updated Areal Component No. 1: Planning Request for Single Stage - One / Post Limited 0.00 Canceled 2017-04-06 2017-06-01 2017-11-28 Photogrammetric or Satellite for Sustainable Urban Growth Quotations Envelope Images for Gaza City GZ-MDLF-185216-NC-RFQ / Public Awareness Campaign Component No. 1: Planning Request for Single Stage - One TF / A2846 Post Limited 0.00 Canceled 2020-08-15 2021-03-18 2021-09-14 Cardboard and paper sorting- for Sustainable Urban Growth Quotations Envelope Bethlehem Urban Area CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GZ-MDLF-850-CS-QCBS / Assessment and Collection of Component No. 1: Planning Quality And Cost- Missing Data and Analysis to / Post Open - National 0.00 Canceled 2017-03-01 2017-03-22 2017-05-05 2017-06-02 2017-07-02 2017-08-06 2017-09-10 2018-09-10 for Sustainable Urban Growth Based Selection Develop Urban Growth Footprint in Gaza City GZ-MDLF-7705-CS-QCBS / Component No. 1: Planning Quality And Cost- Urban Growth Scenario TF / A2846 Prior Open - International 486,956.17 Signed 2017-03-19 2017-08-14 2017-04-09 2017-08-16 2017-05-23 2017-11-22 2017-06-20 2017-12-31 2017-07-20 2018-02-05 2017-08-24 2018-02-26 2017-09-28 2018-02-22 2018-09-28 for Sustainable Urban Growth Based Selection Exercise GZ-MDLF-57571-CS-CQS / Prepare a Comprehensive Public Transportation Plan for Component No. 1: Planning Quality And Cost- Ramallah and Al Bireh Urban TF / A2846 Post Open - National 0.00 Canceled 2018-07-20 2018-08-06 2018-08-03 2018-08-24 2018-09-23 2018-10-07 2018-10-21 2018-11-25 2019-05-24 for Sustainable Urban Growth Based Selection Area and Expand the RAB Mobility Plan to include Surda Abu Qush Town GZ-MDLF-57572-CS-QCBS / Prepare the Environmental Component No. 1: Planning Quality And Cost- TF / A2846 Post Open - National 0.00 Canceled 2018-06-01 2018-06-15 2018-07-06 2018-08-03 2018-08-17 2018-08-31 2018-10-05 2019-04-03 Impact Assessment study for Sustainable Urban Growth Based Selection /Nablus and Bethlehem Area GZ-MDLF-57573-CS-QCBS / Prepare a Mobility Component No. 1: Planning Quality And Cost- Study/Traffic study for TF / A2846 Post Open - National 81,174.00 Completed 2018-06-01 2018-11-22 2018-06-22 2018-07-13 2019-01-03 2018-08-10 2019-02-10 2018-08-24 2019-02-17 2018-09-28 2019-02-20 2018-11-02 2019-03-10 2019-05-01 2019-10-04 for Sustainable Urban Growth Based Selection Hebron and Nablus Urban Areas GZ-MDLF-849-CS-CQS / Consultant Component No. 1: Planning Capacity Development for / Post Qualification Open - National 0.00 Canceled 2016-12-01 2016-12-22 2017-02-04 2017-03-06 2017-04-10 2017-10-07 for Sustainable Urban Growth LGUs, MDLF and MoLG Selection GZ-MDLF-226-CS-QCBS / Assessment and Collection of Existing Urban Growth Data Component No. 1: Planning Quality And Cost- / Post Open - International 0.00 Canceled 2016-10-01 2016-10-22 2016-12-05 2017-01-02 2017-02-01 2017-03-08 2017-04-12 2017-08-13 and Development of Urban for Sustainable Urban Growth Based Selection Growth Planning Roadmaps in West Bank and Gaza GZ-MDLF-78337-CS-QCBS / Demographic Change and Component No. 1: Planning Quality And Cost- TF / A2846 Post Open - National 0.00 Canceled 2018-11-15 2018-12-06 2019-01-19 2019-02-16 2019-03-18 2019-04-22 2019-05-27 2019-11-23 service demand Study for for Sustainable Urban Growth Based Selection Bethlehem Urban Area GZ-MDLF-105921-CS-QCBS / Prepare a Comprehensive Component No. 1: Planning Quality And Cost- Public Transportation Plan for TF / A2846 Post Open - International 238,480.00 Completed 2019-03-31 2019-06-10 2019-04-21 2019-06-16 2019-06-04 2019-07-15 2019-07-02 2019-09-09 2019-08-01 2019-09-19 2019-09-05 2019-09-25 2019-10-10 2019-11-05 2020-10-09 2021-06-16 for Sustainable Urban Growth Based Selection Ramallah and Al Bireh Urban Area GZ-MDLF-105935-CS-CQS / Extension of the Traffic and Consultant Transportation Plan for Component No. 1: Planning TF / A2846 Post Qualification Open - National 29,998.00 Completed 2019-03-31 2019-04-30 2019-04-21 2019-06-04 2019-06-10 2019-07-04 2019-07-01 2019-08-08 2019-07-10 2019-12-06 2019-11-10 Ramallah, Al-Bireh, and for Sustainable Urban Growth Selection Betunia to include Surda-Abu Qush. GZ-MDLF-105937-CS-QCBS / Strategic Environmental and Component No. 1: Planning Quality And Cost- Social Assessment for the five TF / A2846 Post Open - International 214,704.00 Signed 2019-03-31 2019-06-26 2019-04-21 2019-07-08 2019-06-04 2019-08-26 2019-07-02 2019-10-21 2019-08-01 2019-11-19 2019-09-05 2019-11-14 2019-10-10 2019-12-15 2020-06-06 for Sustainable Urban Growth Based Selection targeted urban areas in West Bank & Gaza GZ-MDLF-106015-CS-CQS / Consultant Component No. 1: Planning Development Plan for the TF / A2846 Post Qualification Open - National 0.00 Canceled 2020-09-01 2020-09-22 2020-11-05 2020-12-05 2021-01-26 2021-05-26 for Sustainable Urban Growth Water Front for Gaza City Selection Page 2 GZ-MDLF-153610-CS-QCBS / Developing a Sustainable Component No. 1: Planning Quality And Cost- TF / A2846 Post Open - International 382,730.44 Signed 2020-06-01 2020-07-29 2020-06-22 2020-08-05 2020-09-09 2020-09-02 2020-11-01 2020-10-02 2020-11-24 2020-11-06 2020-12-24 2020-12-11 2021-02-09 2021-08-08 Tourism Development Plan for for Sustainable Urban Growth Based Selection Bethlehem Urban area GZ-MDLF-164003-CS-CQS / Local Technical consultant for Consultant Component No. 1: Planning Pilot Project for Cardboard TF / A2846 Post Qualification Open - National 19,923.00 Signed 2020-10-01 2020-12-17 2020-10-22 2020-12-05 2021-02-03 2021-01-04 2021-03-23 2021-02-08 2021-03-29 2022-02-07 for Sustainable Urban Growth and Paper Sorting- Bethlehem Selection Urban Area GZ-MDLF-201725-CS-CQS / Consultant Assessment of IT-GIS Component No. 1: Planning TF / A2846 Post Qualification Open - National 17,400.00 Signed 2020-11-04 2020-11-12 2020-11-25 2021-01-08 2020-12-07 2021-02-07 2021-01-10 2021-03-14 2021-01-10 2021-09-10 Environment for the ICUD for Sustainable Urban Growth Selection Targeted Urban Areas GZ-MDLF-210299-CS-CQS / Consultant Public Awareness Campaign Component No. 1: Planning TF / A2846 Post Qualification Open - National 21,450.00 Signed 2020-12-20 2020-12-27 2021-01-10 2021-02-23 2021-02-02 2021-03-25 2021-05-12 2021-04-29 2021-05-24 2021-07-28 Cardboard and paper sorting- for Sustainable Urban Growth Selection Bethlehem Urban Area GZ-MDLF-164006-CS-QCBS / LTC for Sustainable Urban Component No. 1: Planning Quality And Cost- Growth Pilot Projects: Gaza, TF / A2846 Post Open - International 68,998.59 Signed 2020-05-01 2021-01-21 2020-05-22 2020-07-05 2021-03-04 2020-08-02 2021-04-11 2020-09-01 2021-04-26 2020-10-06 2021-04-28 2020-11-10 2021-05-20 2021-07-08 for Sustainable Urban Growth Based Selection Hebron, Ramallah-Al-Bireh, and Nablus Urban Areas GZ-MDLF-222297-CS-CQS / Consultant Providing Capacity Building Component No. 1: Planning Pending TF / A2846 Post Qualification Open - National 0.00 2021-03-10 2021-03-31 2021-05-14 2021-06-13 2021-07-18 2022-01-14 Training for ICUD Targeted for Sustainable Urban Growth Implementation Selection Urban Areas GZ-MDLF-222299-CS-QCBS Component No. 1: Planning Quality And Cost- Pending / City center development TF / A2846 Post Open - National 0.00 2021-03-25 2021-04-15 2021-05-29 2021-06-26 2021-07-26 2021-08-30 2021-10-04 2022-10-04 for Sustainable Urban Growth Based Selection Implementation plan for Gaza GZ-MDLF-222301-CS-QCBS / Joint strategic spatial & Component No. 1: Planning Quality And Cost- TF / A2846 Post Open - International 0.00 Canceled 2021-03-31 2021-04-21 2021-06-04 2021-07-02 2021-08-01 2021-09-05 2021-10-10 2022-10-10 investment plan for the for Sustainable Urban Growth Based Selection targeted urban areas GZ-MDLF-163991-CS-QCBS / Joint Spatial Framework with Component No. 1: Planning Quality And Cost- TF / A2846 Post Open - International 0.00 Canceled 2020-10-01 2020-10-22 2020-12-05 2021-01-02 2021-02-01 2021-03-08 2021-04-12 2022-01-07 Capital investment Plans for for Sustainable Urban Growth Based Selection the targeted Urban areas GZ-MDLF-242981-CS-CQS / Consultant Joint strategic spatial & Component No. 1: Planning Pending TF / A2846 Post Qualification Open - National 0.00 2021-07-15 2021-08-05 2021-09-18 2021-10-18 2021-11-22 2022-06-20 investment plan for the for Sustainable Urban Growth Implementation Selection targeted urban areas INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GZ-MDLF-851-CS-INDV / Individual Component No. 1: Planning Hiring of Technical GIS Data / Post Consultant Open - National 145,848.00 Signed 2017-01-01 2017-01-01 2017-02-19 2017-01-26 2017-03-12 2017-01-31 2017-04-16 2017-03-01 2017-10-13 for Sustainable Urban Growth Storage Specialist Selection GZ-MDLF-225-CS-INDV / Individual Component No. 1: Planning Technical Supervisor within / Post Consultant Open - National 32,000.00 Terminated 2016-06-29 2016-06-22 2016-08-16 2016-10-09 2016-09-06 2016-10-10 2016-10-11 2016-10-15 2017-04-09 for Sustainable Urban Growth MOLG. Selection GZ-MDLF-844-CS-INDV / Individual Component No. 1: Planning Hiring of Local Coordinator- / Post Consultant Open - National 32,775.00 Terminated 2016-11-29 2016-11-17 2017-01-17 2017-02-20 2017-02-07 2017-02-22 2017-03-14 2017-03-01 2017-09-10 for Sustainable Urban Growth Bethlehem Urban Area Selection GZ-MDLF-845-CS-INDV / Individual Component No. 1: Planning Hiring of Local Coordinator - / Post Consultant Open - National 139,245.00 Signed 2016-11-29 2016-11-17 2017-01-17 2017-01-30 2017-02-07 2017-01-30 2017-03-14 2017-03-01 2017-09-10 for Sustainable Urban Growth Hebron Urban Area Selection GZ-MDLF-848-CS-INDV / Individual Component No. 1: Planning Hiring of Local Coordinator - / Post Consultant Open - National 126,000.00 Signed 2016-11-29 2016-11-17 2017-01-17 2017-01-19 2017-02-07 2017-01-26 2017-03-14 2017-02-01 2017-09-10 for Sustainable Urban Growth Nablus Urban Area Selection GZ-MDLF-15955-CS-INDV / Individual Component No. 1: Planning Institutional Assesment of TF / A2846 Post Consultant Open 3,782.00 Terminated 2017-05-25 2017-07-12 2017-07-13 2017-09-14 2017-08-03 2017-09-14 2017-09-07 2017-09-20 2018-03-06 for Sustainable Urban Growth RAB Joint Cooperation Unit Selection GZ-MDLF-33862-CS-INDV / Individual Component No. 1: Planning Hiring of Local Coordinator at TF / A2846 Post Consultant Open 51,527.00 Terminated 2017-11-05 2017-12-03 2017-12-24 2017-12-03 2018-01-14 2017-12-04 2018-02-18 2017-12-14 2019-02-18 for Sustainable Urban Growth MOLG Selection Individual GZ-MDLF-24713-CS-INDV / Component No. 1: Planning TF / A2846 Post Consultant Open 0.00 Canceled 2017-08-13 2017-09-17 2017-09-22 2017-10-01 2018-10-01 ICUD Technical Supervisor for Sustainable Urban Growth Selection GZ-MDLF-57570-CS-INDV / Prepare the TOR for a Comprehensive Public Individual Transportation Plan for Component No. 1: Planning TF / A2846 Post Consultant Limited 4,200.00 Completed 2018-05-15 2018-05-28 2018-05-20 2018-05-19 2018-05-27 2018-06-11 2018-06-17 2018-07-11 2018-07-17 2018-08-10 Ramallah and Al Bireh Urban for Sustainable Urban Growth Selection Area and Expand the RAB Mobility Plan to include Surda Abu Qush Town GZ-MDLF-63644-CS-INDV / Individual Component No. 1: Planning Hiring of Local Coordinator - TF / A2846 Post Consultant Open 58,764.00 Signed 2018-05-25 2018-05-29 2018-06-23 2018-06-28 2018-07-14 2018-08-01 2018-08-18 2018-08-01 2019-03-16 for Sustainable Urban Growth Bethlehem Urban Area Selection GZ-MDLF-69297-CS-INDV / Individual Prepare a conceptual Spatial Component No. 1: Planning TF / A2846 Post Consultant Limited 7,680.00 Completed 2018-07-19 2018-07-15 2018-07-24 2018-07-18 2018-08-14 2018-07-22 2018-09-18 2018-07-22 2018-10-18 2018-10-07 Framework for the urban for Sustainable Urban Growth Selection areas targeted with ICUD project Page 3 GZ-MDLF-78343-CS-INDV / Individual Component No. 1: Planning Personnel Skills & Team TF / A2846 Post Consultant Limited 1,600.00 Completed 2018-12-01 2019-05-22 2018-12-06 2019-05-29 2018-12-27 2019-07-10 2019-01-31 2019-07-25 2019-03-02 2019-09-24 for Sustainable Urban Growth Building Training Selection GZ-MDLF-82654-CS-CDS / Component No. 1: Planning Introductory Training Course TF / A2846 Post Direct Selection Direct 11,645.00 Completed 2018-11-01 2018-10-16 2018-11-11 2019-01-15 2018-11-01 2019-03-12 2018-12-20 for Sustainable Urban Growth in Transportation Planning GZ-MDLF-82673-CS-CDS / Component No. 1: Planning Introductory Training Course TF / A2846 Post Direct Selection Direct 16,440.00 Completed 2018-11-01 2018-10-16 2018-11-11 2019-01-15 2018-11-01 2019-03-12 2018-12-20 for Sustainable Urban Growth in Urban Planning GZ-MDLF-153582-CS-CDS / Individual Component No. 1: Planning Institutional Development TF / A2846 Post Consultant Direct 40,800.00 Completed 2020-02-02 2020-01-22 2020-02-12 2020-01-27 2020-03-04 2020-02-11 2020-04-08 2020-02-15 2020-10-05 2020-12-15 for Sustainable Urban Growth Adviser Selection Individual GZ-MDLF-163998-CS-CDS / Component No. 1: Planning TF / A2846 Post Consultant Direct 30,120.00 Signed 2020-05-01 2020-05-27 2020-05-11 2020-06-02 2020-06-01 2020-06-02 2020-07-06 2020-06-15 2021-01-02 Senior Urban Adviser for Sustainable Urban Growth Selection GZ-MDLF-185235-CS-INDV Individual Component No. 1: Planning / Hiring of Local Coordinator TF / A2846 Post Consultant Limited 15,200.00 Signed 2020-08-01 2020-07-29 2020-08-06 2020-09-02 2020-08-27 2020-08-30 2020-10-01 2020-09-06 2021-06-28 for Sustainable Urban Growth at MOLG Selection GZ-MDLF-185236-CS-INDV Individual Component No. 1: Planning / Communication and Public TF / A2846 Post Consultant Open 5,250.00 Signed 2020-08-01 2020-07-29 2020-09-19 2020-11-05 2020-10-10 2020-11-19 2020-11-14 2020-11-22 2021-08-11 for Sustainable Urban Growth Relation Specialist Selection GZ-MDLF-164008-CS-QCBS Individual / Prepare the Spatial Component No. 1: Planning Pending TF / A2846 Post Consultant Open 0.00 2020-10-01 2020-11-19 2020-12-10 2021-01-14 2021-09-11 development Framework for for Sustainable Urban Growth Implementation Selection Gaza City GZ-MDLF-201721-CS-INDV Individual Component No. 1: Planning / Junior Urban Planner @ TF / A2846 Post Consultant Limited 11,550.00 Signed 2020-11-04 2020-11-12 2020-11-09 2020-11-30 2020-11-30 2020-11-30 2021-01-04 2020-12-01 2021-07-03 for Sustainable Urban Growth MOLG Selection GZ-MDLF-222304-CS-INDV Individual Component No. 1: Planning / Practical Training on Market- TF / A2846 Post Consultant Direct 17,325.00 Signed 2021-03-15 2021-03-24 2021-03-25 2021-03-31 2021-04-15 2021-03-29 2021-05-20 2021-04-06 2021-11-16 for Sustainable Urban Growth Oriented Urban Planning Selection GZ-MDLF-233801-CS-INDV / Technical Support and Capacity Building for the Pilot Individual Component No. 1: Planning Project "Installation of Solar TF / A2846 Post Consultant Limited 31,200.00 Signed 2021-06-01 2021-05-27 2021-06-06 2021-06-10 2021-06-27 2021-06-14 2021-08-01 2021-06-25 2022-04-28 for Sustainable Urban Growth Photovoltaic Systems for Selection Targeted Urban Areas in West Bank" GZ-MDLF-233803-CS-INDV / Technical Support and Individual Capacity Building for the Pilot Component No. 1: Planning Under TF / A2846 Post Consultant Limited 0.00 2021-06-01 2021-05-27 2021-06-06 2021-06-27 2021-08-01 2022-01-28 Project "Installation of Solar for Sustainable Urban Growth Implementation Selection Photovoltaic Systems for Gaza Urban Area Page 4