EQUALS PPA PROCUREMENT PLAN I. General 1. Project Information Country: Malawi Project Name: PPA for Equity with Quality & Learning at Secondary (EQUALS) Project ID: 2. Project Implementation Agency: Ministry of Education, Science and Technology 3. Date of the Procurement Plan: 28th August 2018 4. Period Covered by this procurement plan: September 2018-January 2019 II. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016 revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations as set forth in STEP. III. Bank’s Standard Procurement Documents: The Bank’s Standard Procurement Documents shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. IV. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in The Public Procurement and Disposal of Assets Act, 2018 and its subsidiary instruments namely: The Public Procurement Regulations, 2004, Desk Instructions (2005), Standard bidding Documents and Circulars for the 1 Public Procurement and Disposal of Assets (PPDA) Authority such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations under the following conditions: o Provision of “set-asides” contracts for small enterprises shall not be applied. o Criteria such as environmental aspect, extent of local content, technology transfer, and managerial, scientific & operational skills development shall not be used in the evaluation of bids unless specifically agreed by the Bank on case to case basis. o Procurement Documents include provisions, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. In accordance with paragraph 5.4(c) and 5.5 of the Procurement Regulations, the request for bids/request for proposals/request for quotations document shall require that Bidders/Proposers submitting Bids/Proposals/quotations present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. The form of the Letter of Acceptance is attached in Appendix 1. V. Prequalification: N/A VI. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable. VII. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable. VIII. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). (a) Goods: N/A (b) Works: N/A 2 Domestic preference is not applicable for National Open Competitive Procurement IX. Other Relevant Procurement Information Provide any other relevant procurement information such as procedures for CDD components, Procurement in Situations of Urgent Need of Assistance or Capacity Constraints etc.--NONE X. Procurement Prior Review Thresholds (US$ millions): The overall Project procurement Risk is High. The project being a non-emergency project, there would be generally prior reviews of cases unless specifically indicated in the Procurement Plan as a special measure. Post Review: All contracts not subject to prior review shall be subject to post review. XI. Procurement Prior Review Thresholds Based on High Risk Rating (US$ millions) Type of Procurement Threshold (Million USD) Works (including turnkey, supply & installation of plant and 5 equipment, and PPP) Goods, information technology and non-consulting services 1.5 Consultants: firms 0.5 Consultants: Individuals 0.2 XII. Thresholds for procurement approaches and methods Works Goods, IT and Non- Shortlist of Consulting Services National Consultants 3 Open Open Request Open Open Request Consultin Engineering Internation Nation for Internation National for g Services & al al Quotatio al Quotation Construction n < < Supervision ≧ < ≧ ≦ ≦ ≦ 7 7 0.2 1 1 0.1 0.2 0.3 4 PROCUREMENT PACKAGES WITH METHODS AND TIME SCHEDULES OF GOOD AND NON CONSULTANCY PROCUREMENT OF GOODS WORKS AND NON CONSULTANCY SERVICES A. GOODS Sr. Contract Est. Cost Review Market Selectio Evaluation Procureme Prequalifi Domestic Expected date Expected No Description (US$) by Approach n Options nt Process cation Preference of bid/ date of BanGG Method (Yes/ No) (Yes/No) proposal Contract k opening Signature (Prior/ Post) Procurement of office equipment (computers, printers, photocopiers, G.1.0 Qualifying Single stage scanners, internet 212,517 Post Open- RFB No No 11/10/2018 25/10/2018 1 criteria one connections, National Envelope furniture) for DSDE, TTIs, Division Offices, PFT G.1.0 TOMPRO accounting Direct Qualifying Single stage 66,892 Post DIRECT No No 11/10/2018 25/10/2018 2 package Selection criteria one Envelope 5 A. CONSULTANCY Sr. No Contract Description Est. Cost Revie Market Selecti Evaluatio Shortlistin Expected Expected (US$) w by Approach on n Options g date of bid/ date of Bank Method (Yes/ No) proposal Contract (Prior/ opening Signature Post) C.1.01 TA to Establish baseline values for results framework 70,000.00 Post LIMITED INDV Rated No 26/09/2018 24/10/2018 including all M&E tools development C.1.02 TA to establish baseline values for minimum 143,568.0 Post Open- CQS Rated No 16/10/2018 13/11/2018 standards at CDSSs and teacher effectiveness 0 National C.1.03 TA to carry out textbook and teacher materials 24,343.00 Post LIMITED INDV Rated No 26/09/2018 24/10/2018 assessment C.1.04 TA to assess and refine secondary education school 13,195.00 Post DIRECT INDV Rated No 2/10/2018 9/10/2018 leadership training program by SDI/MIM to suit MoEST DSDE requirements C.1.05 TA to update existing 5 day curriculum orientation and 54,463.00 Post LIMITED INDV Rated No 26/09/2018 24/10/2018 printing training manuals C.1.06 Review of SMASSE training materials by Teacher 256,888.0 Post DIRECT CDS Rated No 2/10/2018 9/10/2018 Training Institutions (TTIs) to align with curriculum and 0 fill identified gaps in teacher content knowledge (Chancellor College, Nalikule and Domasi, Bunda and the Polytechnic) TA to improve material/modules introducing project 100,000.0 Post OPEN – INDV Rated No 30/10/2018 27/11/2018 C.1.07 based learning & application of virtual labs 0 INTERATI ONAL TA to train MANEB staff on the implementation of Item 42,000.00 Post LIMITED INDV Rated No 26/09/2018 24/10/2018 C.1.08 Response Theory TA to update DIAS online inspection tool for 18,257.00 Post OPEN – INDV Rated No 30/10/2018 27/11/2018 C.1.09 secondary INTERATI ONAL TA assesses needs of TTIs based on expectations to 40,000.00 Post LIMITED INDV Rated No 26/09/2018 24/10/2018 C.1.10 deliver on improved teacher support program SUMMARY 6 NO CATEGORY OF VALUE (US$) PROCUREMENT A Goods 279,409 B Works NIL C Consultancy 762,714.00 D Non-Consultancy NIL TOTAL 1,042,123.00 7 PROCUREMENT Malawi : Equity with Quality and Learning at Secondary (EQUALS) PLAN General Information Country: Malawi Bank’s Approval Date of the Original Procurement Plan: 2019-03-05 2020-03-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P164223 GPN Date: Project Name: Equity with Quality and Learning at Secondary (EQUALS) Loan / Credit No: IDA / 63790, / , IDA / V2350 Executing Agency(ies): Equity with Quality and Learning at Secondary School WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MW-EQUALS-145563-CW- RFB / Construction of Infrastructure and Associated Component 2.Enhancing Under Single Stage - One Works at Nansomba Sec. IDA / 63790 equitable access to Post Request for Bids Open - National 695,000.00 0.00 Implementati 2019-12-13 2020-01-31 2020-01-08 2020-02-19 2020-03-11 2020-04-10 2021-02-10 Envelope School and Thuchila CDSS secondary education on in Mulanje District (SHED) (Lot 33) MW-EQUALS-145634-CW- RFB / Construction of Component 2.Enhancing Pending Infrastructure and Associated Single Stage - One IDA / 63790 equitable access to Post Request for Bids Open - National 500,000.00 0.00 Implementati 2020-04-16 2020-04-26 2020-06-07 2020-06-28 2020-07-28 2021-05-30 Works at Meru CDSS and Envelope secondary education on Njerengwa CDSS in Chitipa District (NED) Lot 1 MW-EQUALS-145662-CW- RFB / Construction of Infrastructure and Associated Component 2.Enhancing Pending Single Stage - One Works at Phalombe Sec. IDA / 63790 equitable access to Post Request for Bids Open - National 690,000.00 0.00 Implementati 2020-04-16 2020-04-26 2020-06-07 2020-06-28 2020-07-28 2021-05-30 Envelope School and Michesi Sec secondary education on school in Phalombe District (SHED) (Lot 34b) MW-EQUALS-145659-CW- RFB / Construction of Component 2.Enhancing Pending Infrastructure and Associated Single Stage - One IDA / 63790 equitable access to Post Request for Bids Open - National 620,000.00 0.00 Implementati 2020-04-16 2020-04-26 2020-06-07 2020-06-28 2020-07-28 2021-05-30 Works at Chambidzi CDSS Envelope secondary education on and Misale CDSS in Mchinji District (CWED) (Lot 18) MW-EQUALS-145645-CW- RFB / Construction of Infrastructure and Associated Component 2.Enhancing Pending Single Stage - One Works at Thunduti CSS, IDA / 63790 equitable access to Post Request for Bids Open - National 900,000.00 0.00 Implementati 2020-04-16 2020-04-26 2020-06-07 2020-06-28 2020-07-28 2021-05-30 Envelope Khwawa CDSS and secondary education on Chilumba CDSS in Karonga District (NED) (Lot 6) MW-EQUALS-145686-CW- RFB / Construction of Infrastructure and Associated Component 2.Enhancing Pending Works at Chilinda CDSS, Single Stage - One IDA / 63790 equitable access to Post Request for Bids Open - National 970,000.00 0.00 Implementati 2020-04-16 2020-04-26 2020-06-07 2020-06-28 2020-07-28 2021-05-30 Kapelura CDSS and Envelope secondary education on Mbongodzi CDSS in Kasungu District (CEED) (Lot 9) Page 1 MW-EQUALS-145683-CW- RFB / Construction of Infrastructure and Associated Component 2.Enhancing Pending Single Stage - One Works at Kamwanya CDSS, IDA / 63790 equitable access to Post Request for Bids Open - National 830,000.00 0.00 Implementati 2020-04-16 2020-04-26 2020-06-07 2020-06-28 2020-07-28 2021-05-30 Envelope Gandali CDSS and secondary education on Takondwa CDSS in Mchinji District (CWED) (Lot 20) MW-EQUALS-145650-CW- RFB / Construction of Infrastructure and Associated Component 2.Enhancing Pending Single Stage - One Works at Rivirivi CDSS, IDA / 63790 equitable access to Post Request for Bids Open - National 700,000.00 0.00 Implementati 2020-04-16 2020-04-26 2020-06-07 2020-06-28 2020-07-28 2021-05-30 Envelope Chendausiku CDSS and secondary education on Ulongwe CDSS in Balaka District (SEED) (Lot 24) MW-EQUALS-145571-CW- RFB / Construction of Infrastructure and Associated Component 2.Enhancing Pending Single Stage - One Works at Wilore CDSS, IDA / 63790 equitable access to Post Request for Bids Open - National 900,000.00 0.00 Implementati 2020-04-16 2020-04-26 2020-06-07 2020-06-28 2020-07-28 2021-05-30 Envelope Iponga CDSS, Ngerenge secondary education on CDSS in Karonga District (NED) (Lot 7) MW-EQUALS-145576-CW- RFB / Construction of Component 2.Enhancing Pending Infrastructure and Associated Single Stage - One IDA / 63790 equitable access to Post Request for Bids Open - National 500,000.00 0.00 Implementati 2020-04-16 2020-04-26 2020-06-07 2020-06-28 2020-07-28 2021-05-30 Works at Namatubi CDSS Envelope secondary education on and Chinunkha CDSS in Chitipa District (NED) Lot 3 MW-EQUALS-145657-CW- RFB / Construction of Infrastructure and Associated Component 2.Enhancing Pending Single Stage - One Works at Limphangwi CDSS IDA / 63790 equitable access to Post Request for Bids Open - National 450,000.00 0.00 Implementati 2020-04-16 2020-04-26 2020-06-07 2020-06-28 2020-07-28 2021-05-30 Envelope and Livunzu CDSS in secondary education on Chikwawa District (SWED) (Lot 40) MW-EQUALS-145667-CW- RFB / Construction of Infrastructure and Associated Component 2.Enhancing Pending Single Stage - One Works at Mwanza Sec. IDA / 63790 equitable access to Post Request for Bids Open - National 740,000.00 0.00 Implementati 2020-04-16 2020-04-26 2020-06-07 2020-06-28 2020-07-28 2021-05-30 Envelope School, Futsa CDSS and secondary education on Mphande CDSS in Mwanza District (SWED) (Lot 42) MW-EQUALS-145681-CW- RFB / Construction of Infrastructure and Associated Component 2.Enhancing Pending Works at Chadza 1 CDSS Single Stage - One IDA / 63790 equitable access to Post Request for Bids Open - National 930,000.00 0.00 Implementati 2020-04-16 2020-04-26 2020-06-07 2020-06-28 2020-07-28 2021-05-30 and Chingombe CDSS in Envelope secondary education on Lilongwe Rural East, Lilongwe District (CWED) (Lot 16) MW-EQUALS-145637-CW- RFB / Construction of Infrastructure and Associated Component 2.Enhancing Pending Single Stage - One Works at Gumba CDSS and IDA / 63790 equitable access to Post Request for Bids Open - National 550,000.00 0.00 Implementati 2020-04-16 2020-04-26 2020-06-07 2020-06-28 2020-07-28 2021-05-30 Envelope Mkanda Day Sec.School in secondary education on Mchinji District (CWED) (Lot 22) Page 2 MW-EQUALS-145642-CW- RFB / Construction of Infrastructure and Associated Component 2.Enhancing Pending Works at Namisonga CDSS, Single Stage - One IDA / 63790 equitable access to Post Request for Bids Open - National 900,000.00 0.00 Implementati 2020-04-16 2020-04-26 2020-06-07 2020-06-28 2020-07-28 2021-05-30 Nanjiri CDSS and Nsala Envelope secondary education on CDSS in Zomba Rural, Zomba District (SEED) (Lot 28) MW-EQUALS-145679-CW- RFB / Construction of Infrastructure and Associated Component 2.Enhancing Pending Works at Chiwamba CDSS Single Stage - One IDA / 63790 equitable access to Post Request for Bids Open - National 620,000.00 0.00 Implementati 2020-04-16 2020-04-26 2020-06-07 2020-06-28 2020-07-28 2021-05-30 and Mbirira CDSS in Envelope secondary education on Lilongwe Rural East, Lilongwe District (CWED) (Lot 14) MW-EQUALS-145669-CW- RFB / Construction of Component 2.Enhancing Pending Infrastructure and Associated Single Stage - One IDA / 63790 equitable access to Post Request for Bids Open - National 695,000.00 0.00 Implementati 2020-04-16 2020-04-26 2020-06-07 2020-06-28 2020-07-28 2021-05-30 Works at Misuku CDSS and Envelope secondary education on Chisansu CDSS in Chitipa District (NED) Lot 2 MW-EQUALS-145689-CW- RFB / Construction of Infrastructure and Associated Component 2.Enhancing Pending Single Stage - One Works at Santhe Sec. IDA / 63790 equitable access to Post Request for Bids Open - National 930,000.00 0.00 Implementati 2020-04-16 2020-04-26 2020-06-07 2020-06-28 2020-07-28 2021-05-30 Envelope School, Manyani CDSS and secondary education on Kakhome CDSS in Kasungu District (CEED) (Lot 11) MW-EQUALS-145688-CW- RFB / Construction of Infrastructure and Associated Component 2.Enhancing Pending Single Stage - One Works at Chamakala CDSS, IDA / 63790 equitable access to Post Request for Bids Open - National 950,000.00 0.00 Implementati 2020-04-16 2020-04-26 2020-06-07 2020-06-28 2020-07-28 2021-05-30 Envelope Mathandani CDSS and secondary education on Kaluluma CDSS in Kasungu District (CEED) (Lot 10) MW-EQUALS-145636-CW- RFB / Construction of Component 2.Enhancing Pending Infrastructure and Associated Single Stage - One IDA / 63790 equitable access to Post Request for Bids Open - National 695,000.00 0.00 Implementati 2020-04-16 2020-04-26 2020-06-07 2020-06-28 2020-07-28 2021-05-30 Works at Kabzala CDSS and Envelope secondary education on Sopa CDSS in Mchinji District (CWED) (Lot 19) MW-EQUALS-145684-CW- RFB / Construction of Infrastructure and Associated Component 2.Enhancing Pending Single Stage - One Works at Mchinji Sec. IDA / 63790 equitable access to Post Request for Bids Open - National 550,000.00 0.00 Implementati 2020-04-16 2020-04-26 2020-06-07 2020-06-28 2020-07-28 2021-05-30 Envelope School and Kholoni CDSS in secondary education on Mchinji District (CWED) (Lot 21) MW-EQUALS-145661-CW- RFB / Construction of Infrastructure and Associated Component 2.Enhancing Pending Single Stage - One Works at Namphungo CDSS IDA / 63790 equitable access to Post Request for Bids Open - National 620,000.00 0.00 Implementati 2020-04-16 2020-04-26 2020-06-07 2020-06-28 2020-07-28 2021-05-30 Envelope and Satemwa CDSS in secondary education on Mulanje District (SHED) (Lot 34a) Page 3 MW-EQUALS-145635-CW- RFB / Construction of Infrastructure and Associated Component 2.Enhancing Pending Single Stage - One Works at Chifunga CDSS IDA / 63790 equitable access to Post Request for Bids Open - National 350,000.00 0.00 Implementati 2020-04-16 2020-04-26 2020-06-07 2020-06-28 2020-07-28 2021-05-30 Envelope and Chiwale Sec. School in secondary education on Neno District (SWED) (Lot 43) MW-EQUALS-145682-CW- RFB / Construction of Infrastructure and Associated Component 2.Enhancing Pending Works at Nchalo CDSS, Single Stage - One IDA / 63790 equitable access to Post Request for Bids Open - National 830,000.00 0.00 Implementati 2020-04-16 2020-04-26 2020-06-07 2020-06-28 2020-07-28 2021-05-30 Chifunda CDSS and Envelope secondary education on Bwabwali CDSS in Chikwawa District (SWED) (Lot 39) MW-EQUALS-145677-CW- RFB / Construction of Infrastructure and Associated Component 2.Enhancing Pending Single Stage - One Works at Nkhumano CDSS, IDA / 63790 equitable access to Post Request for Bids Open - National 950,000.00 0.00 Implementati 2020-04-16 2020-04-26 2020-06-07 2020-06-28 2020-07-28 2021-05-30 Envelope Wenya CDSS and Mibanga secondary education on CDSS in Chitipa District (NED) Lot 4 MW-EQUALS-145647-CW- RFB / Construction of Infrastructure and Associated Component 2.Enhancing Pending Single Stage - One Works at Lupembe CDSS, IDA / 63790 equitable access to Post Request for Bids Open - National 840,000.00 0.00 Implementati 2020-04-16 2020-04-26 2020-06-07 2020-06-28 2020-07-28 2021-05-30 Envelope Maghemo Sec. School and secondary education on Karonga CDSS in Karonga District (NED) (Lot 5) MW-EQUALS-145653-CW- RFB / Construction of Infrastructure and Associated Component 2.Enhancing Pending Single Stage - One Works at Chapananga Sec. IDA / 63790 equitable access to Post Request for Bids Open - National 450,000.00 0.00 Implementati 2020-04-16 2020-04-26 2020-06-07 2020-06-28 2020-07-28 2021-05-30 Envelope School and Kakoma CDSS secondary education on in Chikwawa District (SWED) (Lot 37) MW-EQUALS-145666-CW- RFB / Construction of Infrastructure and Associated Component 2.Enhancing Pending Single Stage - One Works at Songani CDSS and IDA / 63790 equitable access to Post Request for Bids Open - National 550,000.00 0.00 Implementati 2020-04-16 2020-04-26 2020-06-07 2020-06-28 2020-07-28 2021-05-30 Envelope Katamba CDSS in Zomba secondary education on Rural, Zomba District (SEED) (Lot 26) MW-EQUALS-145652-CW- RFB / Construction of Infrastructure and Associated Component 2.Enhancing Pending Single Stage - One Works at Mulanje Sec. IDA / 63790 equitable access to Post Request for Bids Open - National 695,000.00 0.00 Implementati 2020-04-16 2020-04-26 2020-06-07 2020-06-28 2020-07-28 2021-05-30 Envelope School and Chambe Sec. secondary education on School in Mulanje District (SHED) (Lot 30) MW-EQUALS-145665-CW- RFB / Construction of Infrastructure and Associated Component 2.Enhancing Pending Single Stage - One Works at Chipoka Sec. IDA / 63790 equitable access to Post Request for Bids Open - National 550,000.00 0.00 Implementati 2020-04-16 2020-04-26 2020-06-07 2020-06-28 2020-07-28 2021-05-30 Envelope School and Msalura CDSS secondary education on in Salima District (CEED) (Lot 12) Page 4 MW-EQUALS-145668-CW- RFB / Construction of Infrastructure and Associated Component 2.Enhancing Pending Single Stage - One Works at Milonde CDSS and IDA / 63790 equitable access to Post Request for Bids Open - National 695,000.00 0.00 Implementati 2020-04-16 2020-04-26 2020-06-07 2020-06-28 2020-07-28 2021-05-30 Envelope Gawani Sec School in secondary education on Mulanje District (SHED) (Lot 31) MW-EQUALS-145685-CW- RFB / Construction of Infrastructure and Associated Component 2.Enhancing Pending Single Stage - One Works at Mpasa CDSS, IDA / 63790 equitable access to Post Request for Bids Open - National 600,000.00 0.00 Implementati 2020-04-16 2020-04-26 2020-06-07 2020-06-28 2020-07-28 2021-05-30 Envelope Sambanjati CDSS and Ngozi secondary education on CDSS in Phalombe District (SHED) (Lot 36) MW-EQUALS-145656-CW- RFB / Construction of Infrastructure and Associated Component 2.Enhancing Pending Works at Chowo CDSS and Single Stage - One IDA / 63790 equitable access to Post Request for Bids Open - National 620,000.00 0.00 Implementati 2020-04-16 2020-04-26 2020-06-07 2020-06-28 2020-07-28 2021-05-30 Kamphandira Ulongwe CDSS Envelope secondary education on in Lilongwe Rural East, Lilongwe District (CWED) (Lot 17) MW-EQUALS-145678-CW- RFB / Construction of Infrastructure and Associated Component 2.Enhancing Pending Single Stage - One Works at Chikwawa Sec. IDA / 63790 equitable access to Post Request for Bids Open - National 450,000.00 0.00 Implementati 2020-04-16 2020-04-26 2020-06-07 2020-06-28 2020-07-28 2021-05-30 Envelope School and Dzumila Sec. secondary education on School in Chikwawa District (SWED) (Lot 38) MW-EQUALS-145649-CW- RFB / Construction of Infrastructure and Associated Component 2.Enhancing Pending Single Stage - One Works at Ngabu Sec School, IDA / 63790 equitable access to Post Request for Bids Open - National 740,000.00 0.00 Implementati 2020-04-16 2020-04-26 2020-06-07 2020-06-28 2020-07-28 2021-05-30 Envelope Mbiya CDSS and Makande secondary education on CDSS in Chikwawa District (SWED) (Lot 41) MW-EQUALS-145639-CW- RFB / Construction of Infrastructure and Associated Component 2.Enhancing Pending Single Stage - One Works at Chingale IDA / 63790 equitable access to Post Request for Bids Open - National 460,000.00 0.00 Implementati 2020-04-16 2020-04-26 2020-06-07 2020-06-28 2020-07-28 2021-05-30 Envelope Secondary and Naisi CDSS secondary education on in Zomba Rural, Zomba District (SEED) (Lot 25) MW-EQUALS-145664-CW- RFB / Construction of Infrastructure and Associated Component 2.Enhancing Pending Works at Chayamba Sec. Single Stage - One IDA / 63790 equitable access to Post Request for Bids Open - National 650,000.00 0.00 Implementati 2020-04-16 2020-04-26 2020-06-07 2020-06-28 2020-07-28 2021-05-30 School, Kasungu Sec. School Envelope secondary education on and Mphomwa CDSS in Kasungu District (CEED) (Lot 8) MW-EQUALS-145643-CW- RFB / Construction of Infrastructure and Associated Component 2.Enhancing Pending Works at Maera CDSS, Single Stage - One IDA / 63790 equitable access to Post Request for Bids Open - National 800,000.00 0.00 Implementati 2020-04-16 2020-04-26 2020-06-07 2020-06-28 2020-07-28 2021-05-30 Mswaswa CDSS and Envelope secondary education on Namadidi CDSS in Zomba Rural, Zomba District (SEED) (Lot 29) Page 5 MW-EQUALS-145655-CW- RFB / Construction of Infrastructure and Associated Component 2.Enhancing Pending Works at Mitundu Sec. Single Stage - One IDA / 63790 equitable access to Post Request for Bids Open - National 620,000.00 0.00 Implementati 2020-04-16 2020-04-26 2020-06-07 2020-06-28 2020-07-28 2021-05-30 School and Chadabwa CDSS Envelope secondary education on in Lilongwe Rural East, Lilongwe District (CWED) (Lot 15) MW-EQUALS-145660-CW- RFB / Construction of Infrastructure and Associated Component 2.Enhancing Pending Single Stage - One Works at Balaka Sec. School IDA / 63790 equitable access to Post Request for Bids Open - National 700,000.00 0.00 Implementati 2020-04-16 2020-04-26 2020-06-07 2020-06-28 2020-07-28 2021-05-30 Envelope Mpirisi CDSS and Toleza secondary education on CDSS in Balaka District (SEED) (Lot 23) MW-EQUALS-145693-CW- RFB / Construction of Infrastructure and Associated Component 2.Enhancing Pending Single Stage - One Works at Likanani CDSS IDA / 63790 equitable access to Post Request for Bids Open - National 620,000.00 0.00 Implementati 2020-04-16 2020-04-26 2020-06-07 2020-06-28 2020-07-28 2021-05-30 Envelope and Migowi CDSS in secondary education on Phalombe District (SHED) (Lot 35) MW-EQUALS-145690-CW- RFB / Construction of Component 2.Enhancing Pending Infrastructure and Associated Single Stage - One IDA / 63790 equitable access to Post Request for Bids Open - National 695,000.00 0.00 Implementati 2020-04-16 2020-04-26 2020-06-07 2020-06-28 2020-07-28 2021-05-30 Works at Mafco CDSS and Envelope secondary education on Parachute CDSS in Salima District (CEED) (Lot 13) MW-EQUALS-145692-CW- RFB / Construction of Infrastructure and Associated Component 2.Enhancing Pending Single Stage - One Works at Chikonde CDSS IDA / 63790 equitable access to Post Request for Bids Open - National 460,000.00 0.00 Implementati 2020-04-16 2020-04-26 2020-06-07 2020-06-28 2020-07-28 2021-05-30 Envelope and Misanjo CDSS in secondary education on Mulanje District (SHED) (Lot 32) GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MW-EQUALS-102788-GO- Component 3.Project DIR / TOMPRO accounting IDA / 63790 Coordination, Learning, Post Direct Selection Direct 67,000.00 63,192.00 Signed 2019-03-01 2019-07-25 2019-03-06 2019-08-18 2019-04-03 2019-10-09 2019-06-02 package Monitoring & Evaluation MW-EQUALS-125961-GO- Component 3.Project Under Request for Single Stage - One RFQ / Supply and Delivery IDA / V2350 Coordination, Learning, Post Limited 16,000.00 0.00 Implementati 2019-08-14 2019-09-11 2019-10-02 Quotations Envelope of Office Furniture Monitoring & Evaluation on MW-EQUALS-125755-GO- Component 3.Project Pending Request for Single Stage - One RFQ / Supply and Delivery IDA / V2350 Coordination, Learning, Post Limited 1,500.00 0.00 Implementati 2019-08-07 2019-09-04 2019-09-18 Quotations Envelope of Routers Monitoring & Evaluation on MW-EQUALS-116215-GO- Component 3.Project Under RFB / 17 No. Double Cabin Single Stage - One IDA / V2350 Coordination, Learning, Post Request for Bids Open - National 880,000.00 0.00 Implementati 2019-09-23 2019-10-24 2019-10-08 2019-11-07 2019-11-21 2019-12-19 2020-03-18 4 x 4 off road vehicles Envelope Monitoring & Evaluation on complete with canopy Page 6 MW-EQUALS-125737-GO- RFB / Supply and Delivery Component 3.Project Pending of Office Equipment Single Stage - One IDA / V2350 Coordination, Learning, Post Request for Bids Open - National 182,000.00 0.00 Implementati 2019-09-30 2019-10-05 2019-11-04 2019-11-18 2019-12-16 2019-12-30 (Computers, Laptops, Heavy Envelope Monitoring & Evaluation on duty Photocopiers, Printers and Scanners) Component 1. Improving the Pending MW-EQUALS-145768-GO- Open - Single Stage - One IDA / 63790 quality of science and Prior Request for Bids 1,750,000.00 0.00 Implementati 2020-03-05 2020-03-10 2020-04-21 2020-05-21 2020-06-18 2020-12-15 RFB / Text Books (Batch 1) International Envelope mathematics instruction on Component 1. Improving the Pending MW-EQUALS-145770-GO- Open - Single Stage - One IDA / 63790 quality of science and Prior Request for Bids 1,750,000.00 0.00 Implementati 2020-09-13 2020-09-18 2020-10-30 2020-11-29 2021-01-12 2021-07-11 RFB / Text Books (Batch 2) International Envelope mathematics instruction on MW-EQUALS-145838-GO- RFQ / Printing of Pilot Component 1. Improving the Pending Request for Single Stage - One Teacher Support Program IDA / 63790 quality of science and Post Limited 9,500.00 0.00 Implementati 2020-09-06 2020-10-25 2020-12-09 Quotations Envelope Materials and Training mathematics instruction on Modules for Leadership MW-EQUALS-145793-GO- Component 1. Improving the Pending DIR / Teacher Guides and IDA / 63790 quality of science and Post Direct Selection Direct 2,500.00 0.00 Implementati 2020-09-10 2020-09-15 2020-10-27 2021-01-25 Syllabi mathematics instruction on MW-EQUALS-145842-GO- RFB / Science and maths Component 1. Improving the Pending kits to resource mobile labs Single Stage - One IDA / 63790 quality of science and Post Request for Bids Open - National 233,000.00 0.00 Implementati 2020-08-17 2020-08-22 2020-10-03 2020-11-02 2020-12-07 2021-03-07 and Science and maths kits Envelope mathematics instruction on for selected cluster lead schools MW-EQUALS-145843-GO- RFQ / ICT Equipmnet for 5 Component 1. Improving the Pending Request for Single Stage - One public TTIs (Domasi, IDA / 63790 quality of science and Post Limited 70,000.00 0.00 Implementati 2020-08-08 2020-09-26 2020-11-10 Quotations Envelope Chancellor, Polytechnic, mathematics instruction on Nalikule and Mzuzu) MW-EQUALS-145870-GO- Component 1. Improving the Pending Request for Single Stage - One RFQ / CDs and Flash Disks IDA / 63790 quality of science and Post Limited 10,000.00 0.00 Implementati 2020-08-21 2020-10-09 2020-11-08 Quotations Envelope for TTIs mathematics instruction on MW-EQUALS-145802-GO- RFQ / Printing of guidelines for teacher management, Component 2.Enhancing Pending Request for Single Stage - One recruitment and deployment; IDA / 63790 equitable access to Post Limited 5,600.00 0.00 Implementati 2020-08-11 2020-09-29 2020-10-29 Quotations Envelope of policy documents; and secondary education on Pamphlets for Community Awareness MW-EQUALS-145835-GO- Component 2.Enhancing Pending RFQ / Procurement of push Request for Single Stage - One IDA / 63790 equitable access to Post Limited 23,500.00 0.00 Implementati 2020-08-23 2020-10-11 2020-11-25 bicycles for Mother Groups Quotations Envelope secondary education on (MG) in each school MW-EQUALS-145814-GO- Component 2.Enhancing Pending RFB / Loose Furniture for Single Stage - One IDA / 63790 equitable access to Post Request for Bids Open - National 500,000.00 0.00 Implementati 2020-10-22 2020-10-27 2020-12-08 2021-01-07 2021-02-11 2021-05-12 the constructed 39 classroom Envelope secondary education on blocks and libraries MW-EQUALS-151343-GO- Component 2.Enhancing Pending RFB / Supply and Delivery Single Stage - One IDA / 63790 equitable access to Post Request for Bids Open - National 208,000.00 0.00 Implementati 2020-01-10 2020-01-17 2020-02-28 2020-03-29 2020-04-26 2020-06-10 of Motor Cycles for Civil Envelope secondary education on Works Site Supervision MW-EQUALS-151348-GO- Component 2.Enhancing Pending RFQ / Printing of Grievance Request for Single Stage - One IDA / 63790 equitable access to Post Limited 2,000.00 0.00 Implementati 2020-01-09 2020-02-27 2020-03-28 Redress Mechanism Quotations Envelope secondary education on Materials Page 7 MW-EQUALS-145831-GO- RFB / Teacher Guides for Component 1. Improving the Pending Maths and Sciences for Single Stage - One IDA / 63790 quality of science and Post Request for Bids Open - National 190,000.00 0.00 Implementati 2020-04-30 2020-05-05 2020-06-16 2020-07-16 2020-08-20 2020-10-19 Schools and Syllabi for Envelope mathematics instruction on Maths and Sciences for Schools MW-EQUALS-145847-GO- Component 3.Project Pending RFB / Tablets for digitized Single Stage - One IDA / 63790 Coordination, Learning, Post Request for Bids Open - National 250,000.00 0.00 Implementati 2020-04-30 2020-06-01 2020-07-13 2020-08-03 2020-08-31 2020-10-15 EMIS and digitized data Envelope Monitoring & Evaluation on collection MW-EQUALS-145695-GO- Component 1. Improving the Pending RFQ / Procurement of Request for Single Stage - One IDA / 63790 quality of science and Post Limited 48,000.00 0.00 Implementati 2020-05-03 2020-06-28 2020-07-28 tablets for 43 cluster lead Quotations Envelope mathematics instruction on schools and TTIs MW-EQUALS-145824-GO- Component 2.Enhancing Pending RFQ / Software for testing Request for Single Stage - One IDA / 63790 equitable access to Post Limited 50,000.00 0.00 Implementati 2020-05-05 2020-06-23 2020-08-22 of digital student selection Quotations Envelope secondary education on platform MW-EQUALS-145833-GO- RFQ / Printing of guidelines Component 2.Enhancing Pending for reformed student Request for Single Stage - One IDA / 63790 equitable access to Post Limited 4,800.00 0.00 Implementati 2020-05-05 2020-06-23 2020-07-23 selection process, Code of Quotations Envelope secondary education on Conduct Modules and Referral structures materials MW-EQUALS-145869-GO- RFB / Print Modules for Component 1. Improving the Pending Single Stage - One MIE, Modules for School IDA / 63790 quality of science and Post Request for Bids Open - National 160,000.00 0.00 Implementati 2020-04-30 2020-05-05 2020-06-16 2020-07-16 2020-08-20 2020-11-18 Envelope Leadership and CA mathematics instruction on Guidelines MW-EQUALS-145865-GO- Component 2.Enhancing Pending RFQ / Tablets for Civil Request for Single Stage - One IDA / 63790 equitable access to Post Limited 15,000.00 0.00 Implementati 2020-05-05 2020-06-30 2020-08-14 works monitoring with ICT Quotations Envelope secondary education on enabled platform MW-EQUALS-125758-GO- Component 3.Project Pending Request for Single Stage - One RFQ / Supply and Delivery IDA / V2350 Coordination, Learning, Post Limited 5,000.00 0.00 Implementati 2020-05-05 2020-06-02 2020-06-09 Quotations Envelope of Shredders and Pin boards Monitoring & Evaluation on NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MW-EQUALS-145819-CS- CQS / TA to conduct an Component 1. Improving the Consultant Pending independent assessment of IDA / 63790 quality of science and Post Qualification Open - National 31,000.00 0.00 2020-07-26 2020-08-16 2020-09-20 2020-10-20 2020-11-24 2021-03-04 Implementation curriculum implementation mathematics instruction Selection (A group of think tanks) Page 8 MW-EQUALS-145846-CS- Component 2.Enhancing Consultant CQS / Consultancy to Pending IDA / 63790 equitable access to Post Qualification Open - National 30,000.00 0.00 2020-08-04 2020-08-25 2020-10-08 2020-11-07 2020-12-05 2021-12-05 develop database linked to Implementation secondary education Selection UBR (Y2) MW-EQUALS-145867-CS- QCBS / Recruitment of Component 3.Project independent verification firm Quality And Cost- Pending IDA / 63790 Coordination, Learning, Post Open - National 400,000.00 0.00 2020-06-04 2020-06-25 2020-07-24 2020-09-04 2020-09-25 2020-10-30 2020-12-04 2024-12-03 to bi-annually verify Based Selection Implementation Monitoring & Evaluation achieved results as per DLI protocol (Y2-Y5) MW-EQUALS-145779-CS- Component 3.Project Least Cost Pending LCS / Procurement of Audit IDA / 63790 Coordination, Learning, Post Open - National 24,000.00 0.00 2020-06-19 2020-07-10 2020-08-07 2020-09-04 2020-09-18 2020-10-16 2020-11-13 2021-01-12 Selection Implementation Firm (Y2) Monitoring & Evaluation MW-EQUALS-146051-CS- CQS / Consultancy to Component 2.Enhancing Consultant Pending develop and finalize IDA / 63790 equitable access to Post Qualification Open - National 50,000.00 0.00 2020-07-16 2020-08-06 2020-09-19 2020-10-03 2020-10-31 2021-03-30 Implementation operational strategy for OSS secondary education Selection (Y2) MW-EQUALS-146052-CS- CQS / Consultancy to Component 2.Enhancing Consultant Pending develop and finalize IDA / 63790 equitable access to Post Qualification Open - National 50,000.00 0.00 2020-07-17 2020-08-07 2020-09-20 2020-10-04 2020-11-01 2021-03-31 Implementation operational strategy for PPPs secondary education Selection (Y2) MW-EQUALS-146053-CS- Component 2.Enhancing Consultant CQS / Develop and finalize Pending IDA / 63790 equitable access to Post Qualification Open - National 32,000.00 0.00 2020-07-17 2020-08-07 2020-09-20 2020-10-20 2020-11-24 2021-02-22 financial reform strategy Implementation secondary education Selection (Y2) MW-EQUALS-146054-CS- CQS / Consultancy to develop and finalize Component 2.Enhancing Consultant Pending sustainable secondary IDA / 63790 equitable access to Post Qualification Open - National 66,000.00 0.00 2020-06-26 2020-07-17 2020-08-30 2020-09-13 2020-10-11 2021-01-09 Implementation education plan including secondary education Selection costing and M&E framework (Y2) MW-EQUALS-146059-CS- CQS / Monitoring and Component 2.Enhancing Consultant Under Evaluation of scholarship IDA / 63790 equitable access to Post Qualification Open - National 156,000.00 0.00 2019-12-16 2020-01-24 2020-01-15 2020-02-19 2020-04-01 2020-04-29 2024-08-06 Implementation programme - Evaluation Y1- secondary education Selection Y5 MW-EQUALS-146048-CS- QCBS / TA to improve material/modules introducing Component 1. Improving the Quality And Cost- Open - Pending project based learning & IDA / 63790 quality of science and Post 140,000.00 0.00 2020-04-30 2020-06-05 2020-06-26 2020-08-07 2020-08-21 2020-09-18 2020-10-16 2021-04-14 Based Selection International Implementation application of virtual labs mathematics instruction (Teacher Support Program) (Y1) MW-EQUALS-145771-CS- CQS / Consultancy to Component 2.Enhancing Consultant Pending develop and finalize IDA / 63790 equitable access to Post Qualification Open - National 18,500.00 0.00 2020-04-30 2020-05-30 2020-06-20 2020-07-20 2020-08-17 2020-10-16 Implementation guidelines - reformed and secondary education Selection digitized bursary system (Y1) MW-EQUALS-146058-CS- CQS / Design and development of platform (e- registration, e-exam fees Component 2.Enhancing Consultant payment and automated Open - Pending IDA / 63790 equitable access to Post Qualification 84,000.00 0.00 2020-04-30 2020-05-21 2020-06-18 2020-07-30 2020-09-03 2021-01-31 analysis and feedback on International Implementation secondary education Selection test items to schools) & development of training package for users (MANEB staff and students)(Y1,Y2) Page 9 MW-EQUALS-146062-CS- QCBS / TA for development Component 3.Project Quality And Cost- Pending of digitized EMIS IDA / 63790 Coordination, Learning, Post Open - National 130,000.00 0.00 2020-04-30 2020-05-30 2020-06-27 2020-08-08 2020-08-29 2020-10-03 2020-10-31 2021-08-27 Based Selection Implementation (Performance Management Monitoring & Evaluation System) (Y1,Y2) MW-EQUALS-145785-CS- CQS / Consultancy to Component 2.Enhancing Consultant Open - Pending develop and finalize IDA / 63790 equitable access to Post Qualification 83,000.00 0.00 2020-04-30 2020-05-30 2020-07-13 2020-07-27 2020-08-24 2021-08-24 International Implementation guidelines for MANEB secondary education Selection reformed selection process MW-EQUALS-146055-CS- CQS / Consultancy to develop and finalize guidelines for secondary Component 2.Enhancing Consultant Pending education teacher strategy IDA / 63790 equitable access to Post Qualification Open - National 72,000.00 0.00 2020-04-30 2020-05-30 2020-06-20 2020-08-01 2020-08-29 2021-02-25 Implementation with clear guidelines for secondary education Selection management, recruitment and deployment; and clear teacher supply needs (Y1,Y2) MW-EQUALS-146056-CS- CQS / Consultancy to develop and implement new Component 2.Enhancing Consultant digital system (develop Pending IDA / 63790 equitable access to Post Qualification Open - National 34,000.00 0.00 2020-04-30 2020-06-09 2020-07-07 2020-08-18 2020-09-15 2020-12-24 revised automated selection Implementation secondary education Selection policy & time bound implementation strategy) (Y1) MW-EQUALS-145766-CS- CQS / TA to carry out Component 1. Improving the Consultant textbook and teacher Pending IDA / 63790 quality of science and Post Qualification Limited 25,000.00 0.00 2020-04-30 2020-05-14 2020-06-13 2020-07-11 2020-09-09 materials assessment Implementation mathematics instruction Selection (Subject specialists for each of the target subjects) MW-EQUALS-145807-CS- CQS / Consultancy for Component 2.Enhancing Consultant implementation reviews for Pending IDA / 63790 equitable access to Post Qualification Open - National 46,000.00 0.00 2020-04-30 2020-05-21 2020-06-18 2020-07-18 2020-08-15 2021-01-12 OSS, Double Shift, private Implementation secondary education Selection secondary and secondary education financing (Y1) MW-EQUALS-102807-CS- QCBS / TA to establish Component 1. Improving the Quality And Cost- Pending baseline values for minimum IDA / 63790 quality of science and Post Open - National 144,000.00 0.00 2020-05-15 2020-05-25 2020-06-29 2020-07-27 2020-08-10 2020-09-21 2020-10-19 2021-01-17 Based Selection Implementation standards at CDSSs and mathematics instruction teacher effectiveness MW-EQUALS-167031-CS- CQS / Consultancy Services Component 2.Enhancing Consultant to Undertake Policy and Pending IDA / 63790 equitable access to Post Qualification Open - National 195,000.00 0.00 2020-04-14 2020-05-05 2020-06-18 2020-07-18 2020-08-22 2022-08-22 Regulatory Reforms Implementation secondary education Selection Targeting Expansion of Secondary Education INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MW-EQUALS-102966-CS- INDV / TA assesses needs Component 1. Improving the Individual of TTIs based on Under / quality of science and Post Consultant Open 40,000.00 0.00 2019-03-01 2019-04-29 2019-05-13 2019-06-10 2019-06-10 expectations to deliver on Implementation mathematics instruction Selection improved teacher support program Page 10 MW-EQUALS-103207-CS- Component 3.Project Individual Under INDV / Monitoring and IDA / 63790 Coordination, Learning, Post Consultant Open 84,000.00 0.00 2019-03-01 2019-03-24 2019-04-29 2019-05-13 2019-06-10 2025-06-08 Implementation Evaluation Specialist Monitoring & Evaluation Selection MW-EQUALS-103228-CS- Component 3.Project Individual Under INDV / Financial IDA / 63790 Coordination, Learning, Prior Consultant Open 84,000.00 0.00 2019-03-01 2019-03-26 2019-04-29 2019-05-13 2019-06-10 2025-06-08 Implementation Management Specialist Monitoring & Evaluation Selection MW-EQUALS-102815-CS- Component 3.Project Individual Under INDV / Procurement IDA / 63790 Coordination, Learning, Prior Consultant Open 84,000.00 0.00 2019-03-01 2019-03-26 2019-04-21 2019-10-31 2019-04-28 2019-05-26 2019-11-22 Implementation Specialist -Headquarters Monitoring & Evaluation Selection MW-EQUALS-103372-CS- Component 3.Project Individual Under INDV / Procurement IDA / 63790 Coordination, Learning, Prior Consultant Open 84,000.00 0.00 2019-03-01 2019-03-12 2019-04-29 2019-10-31 2019-05-20 2019-06-17 2025-06-15 Implementation Specialist -EIMU Monitoring & Evaluation Selection Component 3.Project Individual MW-EQUALS-122551-CS- Pending IDA / V2350 Coordination, Learning, Post Consultant Open 84,000.00 0.00 2019-07-12 2019-08-30 2019-09-20 2019-10-25 2020-04-22 INDV / Project Accountant Implementation Monitoring & Evaluation Selection Component 3.Project Individual MW-EQUALS-103215-CS- IDA / 63790 Coordination, Learning, Prior Consultant Open 360,000.00 0.00 Canceled 2019-03-01 2019-03-26 2019-04-29 2019-05-13 2019-06-10 2025-06-08 INDV / Project Cordinator Monitoring & Evaluation Selection MW-EQUALS-125406-CS- Component 3.Project Individual Under INDV / Recruitment of IDA / V2350 Coordination, Learning, Prior Consultant Open 360,000.00 0.00 2019-07-30 2019-09-18 2019-08-21 2019-08-23 2019-09-11 2020-09-10 Implementation EQUALS Project Manager Monitoring & Evaluation Selection Component 3.Project Individual MW-EQUALS-125763-CS- Under IDA / V2350 Coordination, Learning, Post Consultant Limited 76,000.00 0.00 2019-08-04 2019-08-29 2019-08-09 2019-10-08 2019-08-30 2019-09-20 2019-11-19 INDV / ESMP Specialist (3) Implementation Monitoring & Evaluation Selection MW-EQUALS-108207-CS- Component 3.Project Individual Under INDV / TA - Architect at IDA / V2350 Coordination, Learning, Post Consultant Open 124,000.00 0.00 2019-09-27 2020-01-24 2019-11-15 2019-11-22 2019-12-06 2020-12-06 Implementation EIMU Monitoring & Evaluation Selection Component 3.Project Individual MW-EQUALS-108250-CS- Under IDA / V2350 Coordination, Learning, Post Consultant Open 186,000.00 0.00 2019-09-27 2020-01-24 2019-11-15 2019-11-22 2019-12-13 2020-12-13 INDV / IT Specialist Implementation Monitoring & Evaluation Selection MW-EQUALS-108249-CS- Component 3.Project Individual Under INDV / TA - Communication IDA / V2350 Coordination, Learning, Post Consultant Open 178,200.00 0.00 2019-12-09 2020-01-24 2020-02-15 2020-03-16 2020-04-13 2023-07-15 Implementation Specialist Monitoring & Evaluation Selection Component 3.Project Individual MW-EQUALS-108218-CS- Under IDA / V2350 Coordination, Learning, Prior Consultant Open 237,000.00 0.00 2019-12-09 2020-02-26 2020-02-22 2020-04-04 2020-05-02 2023-05-25 INDV / Quantity Surveyor Implementation Monitoring & Evaluation Selection MW-EQUALS-135069-CS- Component 3.Project Individual Pending CDS / Environmental and IDA / V2350 Coordination, Learning, Post Consultant Direct 178,200.00 0.00 2019-12-03 2019-12-17 2019-12-31 2020-01-09 2023-04-11 Implementation Safeguards Specialist Monitoring & Evaluation Selection MW-EQUALS-151353-CS- Component 3.Project Individual INDV / Technical Assistance Under IDA / 63790 Coordination, Learning, Post Consultant Open 50,160.00 0.00 2020-01-10 2020-01-23 2020-03-09 2020-03-30 2020-05-04 2022-05-04 for Provision of Clerk of Implementation Monitoring & Evaluation Selection Works Services MW-EQUALS-151349-CS- CDS / Consultancy Services Component 2.Enhancing Under for Updating of the Civil IDA / 63790 equitable access to Post Direct Selection Direct 100,000.00 0.00 2020-01-13 2020-01-31 2020-02-01 2020-02-28 2020-04-06 2020-10-03 Implementation Works Monitoring Software secondary education Platform Page 11 MW-EQUALS-145840-CS- INDV / Development of teachers' code of conduct Component 2.Enhancing Individual Pending and development of referral IDA / 63790 equitable access to Post Consultant Limited 9,500.00 0.00 2020-04-30 2020-05-05 2020-05-26 2020-06-30 2020-07-30 Implementation structures for Mitigation of secondary education Selection School Related Gender Based Violence (GBV) (Y1) MW-EQUALS-146049-CS- INDV / TA for development Component 1. Improving the Individual of web-based repository for Pending IDA / 63790 quality of science and Post Consultant Limited 7,000.00 0.00 2020-04-30 2020-05-05 2020-06-14 2020-07-12 2020-08-01 CPD modules and uploading Implementation mathematics instruction Selection of all modules aligned with curriculum MW-EQUALS-146061-CS- Component 3.Project Individual Pending INDV / TA to DIAS IDA / 63790 Coordination, Learning, Post Consultant Open 66,000.00 0.00 2020-04-30 2020-06-18 2020-07-09 2020-08-06 2022-11-14 Implementation digitization support(Y1-Y3) Monitoring & Evaluation Selection MW-EQUALS-146047-CS- INDV / TA for assessing of Component 1. Improving the Individual Pending existing workbooks for IDA / 63790 quality of science and Post Consultant Limited 15,500.00 0.00 2020-04-30 2020-05-05 2020-06-14 2020-07-12 2020-08-31 Implementation Junior physics &Chemistry mathematics instruction Selection (Y1,Y2) MW-EQUALS-146050-CS- Component 1. Improving the Individual INDV / TA consultancy to Pending IDA / 63790 quality of science and Post Consultant Limited 7,000.00 0.00 2020-04-30 2020-05-07 2020-06-16 2020-07-14 2020-08-03 Conduct needs assessment Implementation mathematics instruction Selection on teachers skill set (Y1) MW-EQUALS-108212-CS- Component 3.Project Individual Pending INDV / TA Civil Engineer IDA / V2350 Coordination, Learning, Prior Consultant Open 237,000.00 0.00 2020-04-30 2020-07-14 2020-08-13 2020-09-10 2023-12-12 Implementation at EIMU Monitoring & Evaluation Selection MW-EQUALS-126130-CS- Component 3.Project Pending CDS / TA - DIAS online IDA / V2350 Coordination, Learning, Post Direct Selection Direct 30,000.00 0.00 2020-04-30 2020-05-14 2020-06-18 2020-08-17 Implementation inspection tool Monitoring & Evaluation MW-EQUALS-126127-CS- Component 3.Project CDS / TA - SMASSE IDA / V2350 Coordination, Learning, Post Direct Selection Direct 140,000.00 0.00 Under Review 2020-04-30 2020-03-30 2020-05-14 2020-07-02 2020-08-31 materials review Monitoring & Evaluation MW-EQUALS-102952-CS- INDV / TA to improve Component 1. Improving the Individual Pending material/modules introducing IDA / 63790 quality of science and Post Consultant Open 100,000.00 0.00 2020-04-30 2020-07-05 2020-07-19 2020-08-16 2020-11-14 Implementation project based learning & mathematics instruction Selection application of virtual labs MW-EQUALS-102951-CS- Component 1. Improving the Individual INDV / TA to update DIAS Pending IDA / 63790 quality of science and Post Consultant Open 18,500.00 0.00 2020-04-30 2020-06-28 2020-07-12 2020-08-09 2020-10-08 online inspection tool for Implementation mathematics instruction Selection secondary MW-EQUALS-102804-CS- Component 1. Improving the Individual INDV / TA to carry out Pending IDA / 63790 quality of science and Post Consultant Limited 24,500.00 0.00 2019-03-01 2019-03-06 2019-04-03 2019-05-01 2019-06-30 textbook and teacher Implementation mathematics instruction Selection materials assessment MW-EQUALS-103238-CS- INDV / TA to update Component 1. Improving the Individual Pending existing 5 day curriculum IDA / 63790 quality of science and Post Consultant Open 54,500.00 0.00 2020-05-15 2020-07-13 2020-07-27 2020-08-24 2020-10-23 Implementation orientation and printing mathematics instruction Selection training manuals MW-EQUALS-103380-CS- Component 1. Improving the Individual INDV / TA to train MANEB Pending IDA / 63790 quality of science and Post Consultant Limited 42,000.00 0.00 2020-05-15 2020-05-29 2020-07-06 2020-08-03 2020-10-02 staff on the implementation Implementation mathematics instruction Selection of Item Response Theory Page 12 MW-EQUALS-103013-CS- INDV / TA to Establish Component 1. Improving the Individual Pending baseline values for results IDA / 63790 quality of science and Post Consultant Open 70,000.00 0.00 2020-05-15 2020-07-13 2020-07-27 2020-08-24 2020-10-23 Implementation framework including all mathematics instruction Selection M&E tools development MW-EQUALS-167032-CS- Component 3.Project Individual INDV / Consultancy Services Pending IDA / 63790 Coordination, Learning, Post Consultant Open 79,200.00 0.00 2020-04-16 2020-06-09 2020-06-30 2020-08-04 2022-08-04 for Environmental and Social Implementation Monitoring & Evaluation Selection Safeguards Specialist 2 Page 13