Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan: March 21, 2017 2. Date of General Procurement Notice: February 17, 2017 3. Period covered by this procurement plan: March 2017 to Feb 2018 II. Goods, Works, Consultant and Non-Consulting Services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Type of Procurement Prior Review Comments Threshold (PRT) US$ (Millions) 1. Works (Including turnkey, supply & 10 Substantial risk installation of plant and equipment and PPP) 2. (Goods; Information Technology & Non- 2 Substantial risk Consulting Services) 3. Consultant Services (Firms) 1 Substantial risk 4. Consultant Services (Individual Consultants) 0.3 Substantial risk 2. Prequalification. NA 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: NA 4. Reference to (if any) Project Operational/Procurement Manual: Available in Project files 5. Any Other Special Procurement Arrangements: NA 6. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 7. All TORs for the procurement of consultants services irrespective of the estimated cost of the assignment shall be reviewed and cleared by the TTL 8. Operating expenditures are neither subject to the Procurement and Consultant Guidelines nor prior or post reviews. Operating expenditures are normally verified by TTLs and FM specialists and obtained using the Borrower’s national procurement and administrative procedures. 9. Renewal or extension of individual consultant’s contracts hired for technical assistance and which are intended for a long-term period but signed for an initial period shorter than the duration of the project, and that have been prior reviewed, do not require procurement clearance if there is no substantial change in the terms and conditions of the contract. March 21, 2017 PROCUREMENT Kenya : Kenya Informal Settlements Improvement Project (KISIP) PLAN General Information Country: Kenya Bank’s Approval Date of the Original Procurement Plan: 2017-02-14 2019-03-04 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P113542 GPN Date: 2017-02-17 Project Name: Kenya Informal Settlements Improvement Project (KISIP) Loan / Credit No: IDA / 48730 Executing Agency(ies): Ministry of Transport and Infrastructure WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-MOTI-20144-CW-RFB / CONSTRUCTION OF NAIROBI CITY SETTLEMENT'S Under Open - Single Stage - Two INFRASTRUCTURE IDA / 48730 Prior Request for Bids 9,388,294.56 Implementati 2017-07-18 2017-07-23 2017-09-03 2017-11-16 2017-12-21 2018-06-19 International Envelope IMPROVEMENT WORKS on (ROADS/FOOTPATHS & DRAINAGE WORKS FOR KAYOLE AND KCC) KE-MOTI-70252-CW-RFB / Construction of Nakuru Single Stage - One Town Settlement's IDA / 48730 Post Request for Bids Open - National 0.00 Canceled 2018-07-25 2018-07-30 2018-09-10 2018-10-10 2018-11-14 2019-02-14 Envelope Infrastructure Improvement Works - Kaptembwa KE-MOTI-83898-CW-DIR / COMPLETION OF NAKURU TOWN SETTLEMENT'S IDA / 48730 Prior Direct Selection Direct 3,619,223.95 Signed 2018-11-01 2018-11-06 2018-12-11 2019-06-09 INFRASTRUCTURE IMPROVEMENT WORKS (ROADS & DRAINAGE) KE-MOTI-11505-CW-RFB / CONSTRUCTION OF NAKURU TOWN SETTLEMENTS (GILANI, KWA RHONDA AND KAPTEMBWA) Open - Single Stage - Two INFRASTRUCTURE IDA / 48730 Prior Request for Bids 0.00 Canceled 2017-04-17 2017-04-22 2017-06-03 2017-08-16 2017-09-20 2018-03-19 International Envelope IMPROVEMENT WORKS (ROADS/FOOTPATHS & DRAINAGE, HIGH MAST FLOOD LIGHTS AND SANITATION WORKS) IN 3 LOTS KE-MOTI-14314-CW-RFB / CONSTRUCTION OF NAKURU TOWN SETTLEMENTS Open - Single Stage - One INFRUSTRUCTURE IDA / 48730 Prior Request for Bids 0.00 Canceled 2017-05-08 2017-05-13 2017-06-24 2017-07-24 2017-08-28 2018-02-24 International Envelope IMPROVEMENT WORKS- ADDITIONAL SEWERAGE WORKS IN GILANI AND KAPTEMBWO Page 1 KE-MOTI-14675-CW-RFB / EXTENSION OF TIME FOR CONSTRUCTION OF NAKURU TOWN Open - Single Stage - One SETTLEMENT IDA / 48730 Prior Request for Bids 0.00 Canceled 2017-05-15 2017-05-15 2017-05-15 2017-05-15 2017-06-05 2017-12-02 International Envelope IMPROVEMENT WORKS - LOT 1 - ROADS/FOOTPATHS AND DRAINAGE WORKS KE-MOTI-25816-CW-RFB / Open - Single Stage - One Infrastructure works for IDA / 48730 Prior Request for Bids 0.00 Canceled 2017-09-04 2017-09-09 2017-10-21 2017-11-20 2017-12-25 2018-06-23 International Envelope settlements in Machakos KE-MOTI-70245-CW-RFB / Construction of Machakos Town Settlement's Single Stage - One (Kariobangi & Swahili IDA / 48730 Post Request for Bids Open - National 0.00 Canceled 2018-08-08 2018-08-13 2018-09-24 2018-10-24 2018-11-28 2019-02-27 Envelope Village) Additional Works - Machakos Sewage Pumping Station KE-MOTI-70249-CW-RFB / Construction of Kisumu Town Settlement's Single Stage - One IDA / 48730 Post Request for Bids Open - National 0.00 Canceled 2018-08-08 2018-08-13 2018-09-24 2018-10-24 2018-11-28 2019-07-29 Infrastructure Improvement Envelope Works - Additional Road & Drainage Works in Bandani KE-MOTI-70248-CW-RFB / Construction of Nairobi Town Settlement's Single Stage - One IDA / 48730 Post Request for Bids Open - National 0.00 Canceled 2018-08-08 2018-08-13 2018-09-24 2018-10-24 2018-11-28 2019-07-29 Infrastructure Improvement Envelope Works - Additional Road Works in KCC and Kayole KE-MOTI-70250-CW-RFB / Construction of Embu Town Settlement's Infrastructure Single Stage - One IDA / 48730 Post Request for Bids Open - National 0.00 Canceled 2018-08-08 2018-08-13 2018-09-24 2018-10-24 2018-11-28 2019-05-28 Improvement Works - Envelope Additional Road & Drainage Works in Dallas KE-MOTI-70241-CW-RFB / Construction of Naivasha Town Settlement's (Kihoto, Single Stage - One IDA / 48730 Post Request for Bids Open - National 0.00 Canceled 2018-08-08 2018-08-13 2018-09-24 2018-10-24 2018-11-28 2019-05-29 Karagita, Kamere & Envelope Kasarani) Extra Works (water Supply) KE-MOTI-89753-CW-RFB / CONSTRUCTION OF Pending Single Stage - One ADDITIONAL WATER IDA / 48730 Post Request for Bids Open - National 0.00 Implementati 2019-02-28 2019-03-05 2019-04-16 2019-05-16 2019-06-20 2019-11-15 Envelope SUPPLY IN NAIVASHA on TOWN KE-MOTI-89755-CW-RFB / CONSTRUCTION WORKS Pending Single Stage - One ON MACHAKOS ROAD - IDA / 48730 Post Request for Bids Open - National 0.00 Implementati 2018-12-13 2018-12-18 2019-01-29 2019-02-28 2019-04-04 2019-06-28 Envelope REMEDIAL WORKS ON on ROAD R1001 GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 KE-MOTI-6680-GO-RFB / Procurement of additional Pending Single Stage - One Office Equipment for KISIP IDA / 48730 Post Request for Bids Open - National 0.00 Implementati 2017-02-28 2017-03-05 2017-04-16 2017-05-16 2017-06-20 2017-12-17 Envelope National Office and on Municipalites KE-MOTI-6681-GO-RFB / Procurement of additional Pending Single Stage - One Office Furniture and fittings IDA / 48730 Post Request for Bids Open - National 0.00 Implementati 2017-02-28 2017-03-05 2017-04-16 2017-05-16 2017-06-20 2017-12-17 Envelope for KISIP National Office on and Counties KE-MOTI-89756-GO-RFB / SUPPLY AND Under Single Stage - One INSTALLATION OF A IDA / 48730 Post Request for Bids Open - National 0.00 Implementati 2018-12-13 2018-12-18 2019-01-29 2019-02-28 2019-04-04 2019-06-20 Envelope WASTE WATER PUMP IN on MACHAKOS NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-MOTI-6591-CS-QCBS / Consultancy services for Socio-Economic surveys, Infrastructure upgrading Quality And Cost- Plan and Engineering IDA / 48730 Prior Open - National 1,543,825.75 Signed 2017-02-13 2017-03-06 2017-04-19 2017-05-17 2017-06-16 2017-07-21 2017-08-25 2018-08-25 Based Selection designs of Infrastructure in informal settlements MLHUD/KISIP/CS/004B/2013 - 2014 KE-MOTI-6659-CS-QCBS / CONSULTANCY FOR Quality And Cost- Open - Under PLANNING AND SURVEY IDA / 48730 Prior 0.00 2017-02-13 2017-03-06 2017-04-19 2017-05-17 2017-06-16 2017-07-21 2017-08-25 2018-08-25 Based Selection International Implementation OF INFORMAL SETTLEMENT KE-MOTI-6616-CS-QCBS / CONSULTANCY Quality And Cost- Open - IDA / 48730 Prior 0.00 Canceled 2017-02-13 2017-03-06 2017-04-19 2017-05-17 2017-06-16 2017-07-21 2017-08-25 2018-08-25 SUPERVISION FOR WORKS Based Selection International - KISUMU AND KERICHO KE-MOTI-6412-CS-QCBS / Consultancy on Technical Assistance to Mombasa Quality And Cost- IDA / 48730 Post Open - National 0.00 Canceled 2017-03-15 2017-04-05 2017-05-19 2017-06-16 2017-07-16 2017-08-20 2017-09-24 2018-09-24 County Government - Based Selection Affordable Housing Strategies KE-MOTI-6397-CS-QCBS / Consultancy on Technical Quality And Cost- Open - Assistance for Housing to IDA / 48730 Prior 0.00 Canceled 2017-03-01 2017-03-22 2017-05-05 2017-06-02 2017-07-02 2017-08-06 2017-09-10 2018-09-10 Based Selection International Kisumu and Nairobi Counties Page 3 KE-MOTI-9414-CS-QCBS / CONSULTANCY Quality And Cost- Open - IDA / 48730 Prior 644,416.95 Signed 2017-03-08 2017-03-29 2017-05-12 2017-06-09 2017-07-09 2017-08-13 2017-09-17 2018-09-17 SUPERVISION WORKS FOR Based Selection International ELDORET KE-MOTI-9425-CS-QCBS / PLANNING AND Quality And Cost- Open - SURVEYING OF KISUMU IDA / 48730 Prior 953,176.22 Signed 2017-03-08 2017-03-29 2017-05-12 2017-06-09 2017-07-09 2017-08-13 2017-09-17 2018-09-17 Based Selection International AND UASIN GISHU- CLUSTER 1 KE-MOTI-9426-CS-QCBS / CONSULTANCY SERVICES Quality And Cost- Open - FOR PLANNING AND IDA / 48730 Prior 1,104,168.72 Signed 2017-03-08 2017-03-29 2017-05-12 2017-06-09 2017-07-09 2017-08-13 2017-09-17 2018-09-17 Based Selection International SURVEY FOR MOMBASA AND KILIFI - CLUSTER 2 KE-MOTI-9428-CS-QCBS / CONSULTANCY SERVICES Quality And Cost- Open - FOR PLANNING AND IDA / 48730 Prior 1,435,672.10 Signed 2017-03-08 2017-03-29 2017-05-12 2017-06-09 2017-07-09 2017-08-13 2017-09-17 2018-09-17 Based Selection International SURVEYING FOR NAKURU - CLUSTER 3 KE-MOTI-9429-CS-QCBS / CONSULTANCY SERVICES Quality And Cost- Open - FOR PLANNING AND IDA / 48730 Prior 1,094,290.96 Signed 2017-03-08 2017-03-29 2017-05-12 2017-06-09 2017-07-09 2017-08-13 2017-09-17 2018-09-17 Based Selection International SURVEYING FOR GARISSA CLUSTER 4 KE-MOTI-9430-CS-QCBS / CONSULTANCY SERVICES Quality And Cost- Open - FOR PLANNING AND IDA / 48730 Prior 952,338.88 Signed 2017-03-08 2017-03-29 2017-05-12 2017-06-09 2017-07-09 2017-08-13 2017-09-17 2018-09-17 Based Selection International SURVEYING FOR NYERI - CLUSTER 5 KE-MOTI-11498-CS-CQS / CONSULTANCY SERVICES FOR PLANNING AND SURVEY OF SELECTED Consultant INFORMAL SETTLEMENTS Open - IDA / 48730 Prior Qualification 1,259,127.08 Signed 2017-04-17 2017-04-17 2017-04-17 2017-04-17 2017-04-17 2017-04-17 IN KISUMU, KAKAMEGA, International Selection KERICHO, KILIFI AND NAIROBI COUNTIES IN LOT 3- CLUSTERS 1 AND 2 KE-MOTI-12706-CS-QCBS / CONSULTANCY SERVICES FOR PLANNING AND Quality And Cost- Open - SURVEY OF SELECTED IDA / 48730 Prior 674,854.10 Signed 2017-04-19 2017-05-10 2017-06-23 2017-07-21 2017-08-20 2017-09-24 2017-10-29 2018-10-29 Based Selection International INFORMAL SETTLEMENTS IN KITUI AND GARISSA LOT 3 CLUSTER 3 KE-MOTI-12709-CS-QCBS / CONSULTANCY SERVICES FOR PLANNING AND Quality And Cost- Open - SURVEY OF SELECTED IDA / 48730 Prior 0.00 Canceled 2017-04-19 2017-05-10 2017-06-23 2017-07-21 2017-08-20 2017-09-24 2017-10-29 2018-10-29 Based Selection International INFORMAL SETTLEMENTS IN NYERI COUNTY LOT 3 CLUSTER 4 KE-MOTI-17261-CS-QCBS / PLANNING AND SURVEYING - CLUSTER 2 KILIFI COUNTY -In informal settlements of Quality And Cost- Shingila (Kilifi town), Jiwe IDA / 48730 Prior Open - National 678,294.40 Signed 2017-06-13 2017-07-04 2017-08-17 2017-09-14 2017-10-14 2017-11-18 2017-12-23 2018-12-23 Based Selection Leupe (Watamu), Muyeye Phase II, Dingwini (Malindi), Njoro ya Chini, Njoro Takatifu, Jakaba, Makaburini and Tab Page 4 KE-MOTI-25693-CS-QCBS / Consultancy services for preparation of Manual to Quality And Cost- Open - IDA / 48730 Prior 0.00 Canceled 2017-09-01 2017-09-22 2017-11-05 2017-12-03 2018-01-02 2018-02-06 2018-03-13 2019-03-13 Guide to Land Tenure Based Selection International Regularization in informal Settlements KE-MOTI-28613-CS-QCBS / CONSULTANCY SERVICES ON REVIEW OF LAND TENURE GUIDELINES IN Quality And Cost- Open - IDA / 48730 Prior 541,308.11 Signed 2017-09-21 2017-10-12 2017-11-25 2017-12-23 2018-01-22 2018-02-26 2018-04-02 2019-04-02 INFORMAL SETTLEMENTS Based Selection International IN NAIROBI, KISUMU,NAKURU,MOMBAS A AND UASIN GISHU KE-MOTI-70299-CS-QCBS / RE PLANNING AND Quality And Cost- IDA / 48730 Post Open - National 0.00 Canceled 2018-07-25 2018-08-15 2018-09-28 2018-10-26 2018-11-25 2018-12-30 2019-02-03 2020-02-03 SURVEY OF LOT 3 - Based Selection KILIFI TOWN KE-MOTI-70301-CS-QCBS / RE PLANNING AND Quality And Cost- IDA / 48730 Post Open - National 0.00 Canceled 2018-07-25 2018-08-15 2018-09-28 2018-10-26 2018-11-25 2018-12-30 2019-02-03 2020-02-03 SURVEY OF LOT 3 - Based Selection GARISSA KE-MOTI-70300-CS-QCBS / RE PLANNING AND Quality And Cost- SURVEY OF LOT 1 - IDA / 48730 Post Open - National 0.00 Canceled 2018-07-25 2018-08-15 2018-09-28 2018-10-26 2018-11-25 2018-12-30 2019-02-03 2020-02-03 Based Selection MUYEYE,KWA NDOMO, AMALEMBA AND KAHITA KE-MOTI-70305-CS-QCBS / Quality And Cost- RE SURVEY OF LOT 4 - IDA / 48730 Post Open - National 0.00 Canceled 2018-07-25 2018-08-15 2018-09-28 2018-10-26 2018-11-25 2018-12-30 2019-02-03 2020-02-03 Based Selection GARRISA KE-MOTI-70298-CS-QCBS / Quality And Cost- COMPLETION OF LOT 2 IDA / 48730 Prior Open - National 0.00 Canceled 2018-07-25 2018-08-15 2018-09-28 2018-10-26 2018-11-25 2018-12-30 2019-02-03 2020-02-03 Based Selection PLANNING AND SURVEY KE-MOTI-98464-CS-QCBS / CONSULTANCY SERVICES FOR SOCIO ECONOMIC SURVEYS AND Quality And Cost- Open - Pending INFRASTRUCTURE IDA / 48730 Prior 0.00 2017-02-13 2017-03-06 2017-04-19 2017-05-17 2017-06-16 2017-07-21 2017-08-25 2018-08-25 Based Selection International Implementation UPGRADING PLAN AND ENGINEERING DESIGNS OF INFRASTRUCTURE IN INFORMAL SETTLEMENTS KE-MOTI-6654-CS-QCBS / CONSULTANCY SERVICE FOR REVIEW OF Quality And Cost- Open - IDA / 48730 Prior 0.00 Canceled 2017-02-20 2017-03-13 2017-04-26 2017-05-24 2017-06-23 2017-07-28 2017-09-01 2018-09-01 GUIDELINES FOR LAND Based Selection International TENURE REGULARIZATION KE-MOTI-98466-CS-QCBS / CONSULTANCY SERVICE FOR REVIEW OF Quality And Cost- Open - Pending IDA / 48730 Post 0.00 2017-02-20 2017-03-13 2017-04-26 2017-05-24 2017-06-23 2017-07-28 2017-09-01 2018-09-01 GUIDELINES FOR LAND Based Selection International Implementation TENURE REGULARIZATION KE-MOTI-6679-CS-QCBS / Consultancy for Quality And Cost- Open - Computerization of KISIP, IDA / 48730 Prior 0.00 Canceled 2017-02-24 2017-03-17 2017-04-30 2017-05-28 2017-06-27 2017-08-01 2017-09-05 2018-09-05 Based Selection International M&E System for Project Management Standards Page 5 KE-MOTI-6652-CS-QBS / Quality Based Open - CONSULTANCY FOR GIS IDA / 48730 Post 0.00 Canceled 2017-02-27 2017-03-20 2017-05-03 2017-05-31 2017-06-30 2017-07-30 2017-09-03 2018-09-03 Selection International EXPERT KE-MOTI-9419-CS-QCBS / CONSULTANCY SERVICES TO SUPORT THE Quality And Cost- IDA / 48730 Post Open - National 0.00 Canceled 2017-03-08 2017-03-29 2017-05-12 2017-06-09 2017-07-09 2017-08-13 2017-09-17 2018-09-17 FORMULATION OF Based Selection HOUSING POLICY FOR KISUMU COUNTY KE-MOTI-98475-CS-QCBS / CONSULTANCY SERVICES TO SUPORT THE Quality And Cost- Open - Pending IDA / 48730 Post 0.00 2017-03-08 2017-03-29 2017-05-12 2017-06-09 2017-07-09 2017-08-13 2017-09-17 2018-09-17 FORMULATION OF Based Selection International Implementation HOUSING POLICY FOR KISUMU COUNTY KE-MOTI-9421-CS-QCBS / CONSULTANCY SERVICES TO SUPPORT THE Quality And Cost- IDA / 48730 Post Open - National 0.00 Canceled 2017-03-08 2017-03-29 2017-05-12 2017-06-09 2017-07-09 2017-08-13 2017-09-17 2018-09-17 FORMULATION OF URBAN Based Selection DEVELOPMENT POLICY FOR KISUMU COUNTY KE-MOTI-9423-CS-QCBS / CONSULTANCY SERVICES TO SUPPORT THE Quality And Cost- IDA / 48730 Post Open - National 0.00 Canceled 2017-03-08 2017-03-29 2017-05-12 2017-06-09 2017-07-09 2017-08-13 2017-09-17 2018-09-17 FORMULATION OF A Based Selection HOUSING POLICY FOR NAIROBI CITY COUNTY KE-MOTI-9424-CS-QCBS / CONSULTANCY SERVICES TO DEVELOP AN Quality And Cost- IDA / 48730 Post Open - National 0.00 Canceled 2017-03-08 2017-03-29 2017-05-12 2017-06-09 2017-07-09 2017-08-13 2017-09-17 2018-09-17 AFFORDABLE HOUSING Based Selection DELIVERY STRATEGY FOR MOMBASA COUNTY KE-MOTI-70251-CS-QCBS / Supervision of infrastructure improvement in informal Quality And Cost- IDA / 48730 Post Open - National 0.00 Canceled 2018-08-08 2018-08-29 2018-10-12 2018-11-09 2018-12-09 2019-01-13 2019-02-17 2020-02-17 settlements in Nairobi, Based Selection Naivasha, Machakos, Nakuru, Kisumu and Embu KE-MOTI-30165-CS-QCBS / Supervision of infrastructure Quality And Cost- Open - IDA / 48730 Prior 0.00 Canceled 2017-10-09 2017-10-30 2017-12-13 2018-01-10 2018-02-09 2018-03-16 2018-04-20 2019-04-20 improvement in informal Based Selection International settlements in Nairobi KE-MOTI-24769-CS-QCBS / Supervision of infrastructure Quality And Cost- Open - IDA / 48730 Prior 0.00 Canceled 2017-08-25 2017-09-15 2017-10-29 2017-11-26 2017-12-26 2018-01-30 2018-03-06 2019-03-06 improvement in informal Based Selection International settlements in Nakuru KE-MOTI-29059-CS-QCBS / Planning and Surveying of Quality And Cost- Open - selected informal settlements- IDA / 48730 Prior 0.00 Canceled 2017-09-29 2017-10-20 2017-12-03 2017-12-31 2018-01-30 2018-03-06 2018-04-10 2019-04-10 Based Selection International Nairobi, Mombasa, Embu, Thika- Cluster 2 Page 6 KE-MOTI-6594-CS-QCBS / Consultancy services for socio economic surveys and infrastructure upgrading plan Quality And Cost- and engineering designs of IDA / 48730 Prior Open - National 0.00 Canceled 2017-02-13 2017-03-06 2017-04-19 2017-05-17 2017-06-16 2017-07-21 2017-08-25 2018-08-25 Based Selection infrastructure in informal settlements MLHUD/KISIP/CS/004A/2013 -2014 INDIVIDUAL CONSULTANTS Page 7