Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan: March 21, 2017 2. Date of General Procurement Notice: June 11, 2013 3. Period covered by this procurement plan: March 2017 to Feb 2018 II. Goods, Works, Consultant and Non-Consulting Services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Type of Procurement Prior Review Comments Threshold (PRT) US$ (Millions) 1. Works (Including turnkey, supply & 10 Substantial risk installation of plant and equipment and PPP) 2. (Goods; Information Technology & 2 Substantial risk Non-Consulting Services) 3. Consultant Services (Firms) 1 Substantial risk 4. Consultant Services (Individual 0.3 Substantial risk Consultants) 2. Prequalification. NA 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: NA 4. Reference to (if any) Project Operational/Procurement Manual: Available in Project files 5. Any Other Special Procurement Arrangements: NA 6. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 7. All TORs for the procurement of consultants services irrespective of the estimated cost of the assignment shall be reviewed and cleared by the TTL 8. Operating expenditures are neither subject to the Procurement and Consultant Guidelines nor prior or post reviews. Operating expenditures are normally verified by TTLs and FM specialists and obtained using the Borrower’s national procurement and administrative procedures. March 21, 2017 9. Renewal or extension of individual consultant’s contracts hired for technical assistance and which are intended for a long-term period but signed for an initial period shorter than the duration of the project, and that have been prior reviewed, do not require procurement clearance if there is no substantial change in the terms and conditions of the contract. March 21, 2017 PROCUREMENT Kenya : Kenya Water Security and Climate Resilience Project PLAN General Information Country: Kenya Bank’s Approval Date of the Original Procurement Plan: 2017-03-01 2021-08-27 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P117635 GPN Date: Project Name: Kenya Water Security and Climate Resilience Project Loan / Credit No: IDA / 52680, IDA / 56740 Ministry of Water and Irrigation Executing Agency(ies): WORKS Procureme Activity Reference No. / Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH nt Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) Justification for Award Type Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-MOWI-7904-CW-RFB / Program for the Improvement C1: Water Resources Single Stage - One 5,266,602.8 2019-12- IDA / 52680 Post Request for Bids Open - National Signed 2017-02-21 2017-03-07 2017-04-18 2017-05-18 2016-12-23 2017-06-22 2017-02-02 of Water Services in Mombasa Development Envelope 4 09 County Likoni Area - Phase 1 KE-MOWI-11092-CW-RFB / Program for the Improvement C1: Water Resources Single Stage - One 4,334,704.6 2018-11- of Water Services in Mombasa IDA / 52680 Post Request for Bids Open - National Signed 2017-04-28 2018-08-23 2017-05-12 2017-06-23 2017-10-05 2017-07-23 2018-10-17 2017-09-05 2017-12-22 Development Envelope 0 29 County West Mainland Area-Phase I KE-MOWI-13183-CW-RFB / Minor Construction Works and C1: Water Resources Single Stage - One 2018-03- IDA / 56740 Post Request for Bids Open - National 0.00 Canceled 2017-05-30 2017-06-13 2017-07-25 2017-08-24 2017-09-28 Renovation of Storage Yards Development Envelope 27 at MOWASCO KE-MOWI-16584-CW-RFB / CONSTRUCTION WORKS OF THE LOWER NZOIA PROJECT IN TWO LOTS LOT 1 LOWER C1: Water Resources Single Stage - One 51,295,364. 2020-09- IDA / 52680 Prior Request for Bids Open - International Signed 2017-06-05 2017-06-10 2017-06-10 2017-06-15 2017-07-22 2017-08-15 2017-08-21 2017-10-30 2017-09-25 2017-11-22 NZOIA IRRIGATION PROJECT Development Envelope 44 09 PHASE 1 AND LOT 2 IMPROVEMENT OF FLOOD MITIGATION STRUCTURES KE-MOWI-10752-CW-RFB / Construction Works of the C1: Water Resources Single Stage - One 2022-02- IDA / 52680 Prior Request for Bids Open - International 0.00 Canceled 2017-04-20 2017-07-29 2017-07-29 2017-05-04 2017-10-07 2017-11-06 2017-12-27 Lower Nzoia Irrigation Project Development Envelope 04 - Phase I KE-MOWI-10755-CW-RFB / Construction Works for C1: Water Resources Single Stage - One 2020-01- Improvement of Flood IDA / 52680 Prior Request for Bids Open - International 0.00 Canceled 2017-04-20 2017-07-29 2017-07-29 2017-05-04 2017-10-07 2017-11-06 2017-12-20 Development Envelope 09 Mitigation Structures on the Lower Nzoia River KE-MOWI-19433-CW-RFB / Program for the Improvement C1: Water Resources Single Stage - One 3,897,597.9 2020-07- of Water Services in Mombasa IDA / 52680 Post Request for Bids Open - National Signed 2017-09-14 2017-08-23 2017-09-28 2017-11-09 2017-10-05 2017-12-09 2017-10-17 2018-01-13 2017-12-22 Development Envelope 2 01 County Mombasa West Mainland - Phase 1 KE-MOWI-30787-CW-RFB / Refurbishishment offices at a) the National Flood Forecasting and Early Warning Center (N- C1: Water Resources Single Stage - One 2018-09- IDA / 52680 Post Request for Bids Open - National 66,764.53 Signed 2017-11-15 2018-02-21 2017-11-29 2018-01-10 2018-04-04 2018-02-09 2018-04-12 2018-03-16 2018-06-28 FFEWC), b) Flood Mapping and Development Envelope 12 Impact Assessment Center (FMIAC) and c) the Regional Management Center (R-FMC). KE-MOWI-47916-CW-RFB / Drilling, Construction, Pending Installation (Data Loggers) and C2: Effective Water Sector Single Stage - One 2018-12- IDA / 52680 Post Request for Bids Open - National 0.00 Implementat 2018-02-22 2018-02-27 2018-04-10 2018-05-10 2018-06-14 Commissioning of Ground Institutions Envelope 11 ion Water Monitoring Wells - 25 No. GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-MOWI-13142-GO-RFQ / Supply, Installation, Training C1: Water Resources Request for Single Stage - One IDA / 56740 Post Limited 0.00 Canceled 2017-05-30 2017-08-08 2017-10-07 and Commission of SCADA for Development Quotations Envelope MOWASCO KE-MOWI-13145-GO-RFB / Supply and Delivery of Motor C1: Water Resources Single Stage - One IDA / 56740 Post Request for Bids Open - National 515,866.57 Signed 2017-05-19 2019-01-21 2017-06-02 2017-07-14 2019-04-10 2017-08-13 2019-04-19 2017-09-17 2020-04-07 2018-03-16 Vehicles, Motor Cycles and Development Envelope Service Vans for MOWASCO KE-MOWI-13168-GO-RFQ / Supply and Delivery of Leak Pending Detection Equipment, C1: Water Resources Request for Single Stage - One IDA / 56740 Post Limited 0.00 Implementati 2017-05-26 2017-08-04 2018-01-31 Associated Accessories, Development Quotations Envelope on Pressure Pumps and Safety Gears KE-MOWI-13868-GO-RFB / Design, Supply, Installation, Under C1: Water Resources Single Stage - One Training and Commissioning IDA / 56740 Post Request for Bids Open - National 0.00 Implementati 2017-06-21 2018-02-16 2017-07-05 2017-08-16 2018-03-15 2017-09-15 2018-06-14 2017-10-20 2018-10-20 Development Envelope of an ERP system for on MOWASCO Page 1 KE-MOWI-19437-GO-RFB / SUPPLY, DELIVERY, INSTALLATION& COMMISSIONING OF AN INTEGRATED REAL-TIME C2: Effective Water Sector Single Stage - One HYDRO-METEOROLOGICAL IDA / 52680 Post Request for Bids Open - National 1,148,745.52 Signed 2017-09-14 2017-01-24 2017-09-19 2017-10-31 2017-11-14 2017-11-30 2017-11-22 2018-01-04 2017-12-20 2018-12-30 Institutions Envelope MONITORING SYSTEM FOR UPGRADING THE NZOIA RIVER BASIN FLOOD EARLY WARNING SYSTEM IN LAKE VICTORIA NORTH CATCHMENT AREA KE-MOWI-7607-GO-RFB / Supply, Delivery, Installation & Commissioning of an Integrated Real-Time Hydro- C2: Effective Water Sector Single Stage - One Meteorological Monitoring IDA / 52680 Post Request for Bids Open - National 0.00 Canceled 2017-02-17 2017-01-25 2017-03-03 2017-04-14 2017-03-23 2017-05-14 2017-05-05 2017-06-28 2018-06-23 Institutions Envelope System for Upgrading The Nzoia River Basin Flood Early Warning System in Lake Victoria North Catchment Area KE-MOWI-30789-GO-RFB / Procurement of Flood Analysis Pending C2: Effective Water Sector Single Stage - One and Mapping Workstations at IDA / 52680 Post Request for Bids Open - National 0.00 Implementati 2018-04-20 2018-05-04 2018-06-15 2018-07-15 2018-08-19 2019-02-15 Institutions Envelope WRA (FMIAC) and KMD (N- on FFEWC) KE-MOWI-47909-GO-RFB / SUPPLY AND DELIVERY OF C2: Effective Water Sector Single Stage - One IDA / 52680 Post Request for Bids Open - National 0.00 Canceled 2018-02-28 2018-03-05 2018-04-16 2018-05-16 2018-06-20 2018-12-17 GROUND WATER & WATER Institutions Envelope QUALITY EQUIPMENT KE-MOWI-47910-GO-RFB / Supply and Delivery of C2: Effective Water Sector Single Stage - One IDA / 52680 Post Request for Bids Open - National 0.00 Canceled 2018-02-27 2018-03-04 2018-04-15 2018-05-15 2018-06-19 2018-12-16 Information, Communication Institutions Envelope and Technology for WRA KE-MOWI-47915-GO-RFB / Supply, Delivery, Installation C2: Effective Water Sector Single Stage - One and Training of Hydromet IDA / 52680 Post Request for Bids Open - National 2,151,205.69 Signed 2018-03-13 2018-03-02 2018-03-18 2018-04-29 2018-04-27 2018-05-29 2018-06-29 2018-07-03 2018-08-20 2018-12-30 Institutions Envelope Monitoring Equipment and Instruments KE-MOWI-85760-GO-RFB / Supply, Delivery and C2: Effective Water Sector Single Stage - One Installation of Surface Water, IDA / 52680 Prior Request for Bids Open - National 0.00 Canceled 2018-11-15 2018-11-20 2019-01-01 2019-01-31 2019-03-07 2020-03-06 Institutions Envelope Water Quality and Weather Stations Equipment In 6 Lots KE-MOWI-125348-GO-RFB / Installation & Commissioning of Automatic Water Level (AWL) Equipment in Five (5) Basins, Automatic Weather C2: Effective Water Sector Single Stage - One Station (AWS) Equipment in IDA / 52680 Post Request for Bids Open - National 556,922.91 Signed 2019-08-09 2019-09-12 2019-08-14 2019-10-09 2019-09-25 2019-10-24 2019-10-25 2020-04-07 2019-11-29 2020-06-17 2020-11-23 Institutions Envelope Five (5) Basins and Atomic Absorption Spectrophotometer (AAS) Equipment in Central Water Testing Laboratory Nairobi KE-MOWI-246790-GO-RFB / Pending C1: Water Resources Single Stage - One Supply and delivery of Water IDA / 52680 Post Request for Bids Open - National 0.00 Implementati 2021-08-18 2021-08-25 2021-09-24 2021-10-24 2021-11-28 2022-02-26 Development Envelope Meters on NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-MOWI-7909-CS-CQS / Consulting services to Consultant Conduct Baseline Survey for C1: Water Resources Under IDA / 52680 Post Qualification Open - National 0.00 2017-02-21 2016-09-15 2017-03-14 2017-04-27 2017-05-27 2017-07-01 2017-12-28 Impact Evaluation for Lower Development Implementation Selection Nzoia Irrigation Project - Phase 1 KE-MOWI-7941-CS-CQS / Consulting services for the preparation and updating of Consultant C1: Water Resources Under Resettlement Action Plan IDA / 52680 Post Qualification Open - National 0.00 2017-02-21 2016-09-24 2017-03-14 2017-04-27 2017-05-27 2017-07-01 2017-11-28 Development Implementation (RAP) for Lower Nzoia Selection Irrigation Project and Nzoia Flood Protection Structures KE-MOWI-7948-CS-CQS / Consultancy services for environmental and social impact assessment (ESIA) and Consultant C1: Water Resources Under Resettlement Action Plan IDA / 52680 Post Qualification Open - National 0.00 2017-02-21 2016-09-27 2017-03-14 2017-04-27 2017-05-27 2017-07-01 2017-11-28 Development Implementation (RAP) for proposed Selection rehabilitation, extension and construction of North Mainland pipelines, Mombasa county. KE-MOWI-7950-CS-CQS / Consultancy services for environmental and social impact assessment (ESIA) and Consultant Resettlement Action Plan C1: Water Resources Under IDA / 52680 Post Qualification Open - National 0.00 2017-02-21 2016-09-24 2017-03-14 2017-04-27 2017-05-27 2017-07-01 2017-11-28 (RAP) for proposed Development Implementation Selection rehabilitation, extension and construction of west mainland pipelines West Mainland pipelines, Mombasa county Page 2 KE-MOWI-7951-CS-QCBS / Consultancy services for developing a National Water Infrastructure Investment C1: Water Resources Quality And Cost- Pipeline, Feasibility Study for IDA / 52680 Prior Open - International 3,824,379.10 Signed 2017-02-21 2017-03-14 2017-05-13 2017-04-12 2017-07-12 2017-06-21 2017-08-11 2017-08-06 2017-10-10 2017-11-10 2017-11-30 2017-12-04 2019-06-03 Development Based Selection Malewa Dam and Water Supply to Ol Kalou, Naivasha and Gilgil Towns in Nyandarua and Nakuru Counties KE-MOWI-8302-CS-QCBS / Consultancy Services for Implementation Support C2: Effective Water Sector Quality And Cost- IDA / 52680 Prior Open - International 5,611,318.79 Signed 2017-02-24 2017-03-17 2017-04-30 2017-06-25 2017-07-25 2017-08-29 2017-04-25 2017-10-03 2017-05-11 2020-09-17 Consultants (ISC) for Water Institutions Based Selection Resources Planning and Management KE-MOWI-8332-CS-CQS / Consultancy Services for Social Impact Assessment Consultant C1: Water Resources Under Study combining downstream IDA / 52680 Post Qualification Open - National 0.00 2017-02-28 2017-03-14 2017-03-21 2017-05-04 2017-07-03 2017-08-07 2017-11-05 Development Implementation of Lower Nzoia Irrigation Selection Project and Mwache Dam projects KE-MOWI-8291-CS-QCBS / Consultancy Services for Design and Construction Supervision of Lunga Lunga, C1: Water Resources Quality And Cost- IDA / 52680 Prior Open - International 1,294,075.28 Signed 2017-02-24 2017-03-26 2017-05-09 2017-06-20 2017-07-20 2017-08-24 2017-05-10 2017-09-28 2017-05-26 2020-05-15 Msambweni, Kwale and Development Based Selection Ukunda Water Supplies Rehabilitation and Expansion Work - R35/ KE-MOWI-10756-CS-QCBS / Consultancy Services for C1: Water Resources Quality And Cost- Upgrading of Flood IDA / 52680 Prior Open - International 1,232,336.59 Signed 2017-04-20 2017-05-11 2017-07-10 2017-04-25 2017-09-08 2017-11-07 2017-10-08 2017-12-07 2017-12-03 2018-03-12 2018-01-07 2018-04-04 2021-01-11 Development Based Selection Forecasting and Early Warning Systems for Nzoia River Basin KE-MOWI-11087-CS-QCBS / Consultancy Services for Implementation Support Consultant (ISC) For C1: Water Resources Quality And Cost- Pending Improvement of Flood IDA / 52680 Prior Open - International 0.00 2017-03-31 2017-04-21 2017-06-04 2017-08-13 2017-09-12 2017-10-26 2017-11-30 2023-12-09 Development Based Selection Implementation Mitigation Structures (IFMS) on Lower Nzoia River and Lower Nzoia Irrigation Project (LNIP) Phase 1 KE-MOWI-27582-CS-QCBS / consulting services to Support to Water Sector Reforms - Development of a Costed Water Sector Transition Plan - C2: Effective Water Sector Quality And Cost- including a Transfer Plan IDA / 52680 Prior Open - International 1,898,250.00 Signed 2017-09-08 2017-10-08 2017-09-20 2017-11-28 2018-01-09 2018-02-08 2018-03-19 2018-03-22 2018-05-16 2018-05-03 2018-07-02 2019-05-03 Institutions Based Selection Conduct Organizational Reviews, Study on Water Works Development Agencies and Development of Subsidiary Legislation KE-MOWI-27585-CS-QCBS / Consulting services to Support C2: Effective Water Sector Quality And Cost- Water Sector Reform IDA / 52680 Prior Open - International 1,397,034.00 Signed 2017-09-08 2017-10-08 2017-09-20 2017-11-28 2018-01-09 2018-02-08 2018-03-19 2018-03-22 2018-05-29 2018-04-26 2018-07-24 2018-12-22 Institutions Based Selection Communication and Staff Inductions KE-MOWI-13141-CS-QCBS / consulting services to Support to Water Sector Reforms Development of a Costed Water Sector Transition Plan C2: Effective Water Sector Quality And Cost- including a Transfer Plan IDA / 52680 Prior Open - International 0.00 Canceled 2017-05-26 2017-06-16 2017-06-09 2017-08-15 2017-10-10 2017-11-09 2018-01-08 2018-02-12 2019-02-12 Institutions Based Selection Conduct Organizational Reviews Study on Water Works Development Agencies and Development of Subsidiary Legislation KE-MOWI-9275-CS-QCBS / Consultancy to Support Water C2: Effective Water Sector Quality And Cost- IDA / 52680 Prior Open - International 0.00 Canceled 2017-04-27 2017-04-03 2017-05-18 2017-06-09 2017-07-17 2017-08-28 2017-09-27 2017-12-08 2018-01-12 2018-09-09 Sector Reform Communication Institutions Based Selection and Staff Induction KE-MOWI-40043-CS-CQS / CONSULTANCY SERVICES FOR PROVISION OF LEGAL Consultant C1: Water Resources SERVICES TOWARDS PROJECT IDA / 52680 Post Qualification Open - National 284,200.35 Signed 2017-12-22 2017-12-20 2018-01-12 2018-02-25 2018-02-06 2018-03-27 2018-03-09 2018-05-01 2019-03-27 2019-04-26 Development AFFECTED PERSONS (PAPS) Selection SUCCESSION GRANTS AND CONFIRMATION BY COURTS KE-MOWI-42455-CS-CQS / CONSULTANCY SERVICES FOR THE PREPARATION OF ENVIRONMENTAL AND SOCIAL Consultant IMPACT ASSESSMENT (ESIA) C1: Water Resources IDA / 52680 Post Qualification Open - National 274,822.05 Signed 2018-01-30 2018-02-05 2018-02-20 2018-04-05 2018-04-06 2018-05-05 2018-05-28 2018-06-09 2018-06-28 2018-11-06 AND Development Selection RESETTLEMENT ACTION PLAN (RAP) FOR KWALE WATER SUPPLIES REHABILITATION AND EXPANSION PROJECT KE-MOWI-44326-CS-CQS / CONSULTANCY SERVICES FOR THE PREPARATION OF ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT (ESIA) Consultant AND RESETTLEMENT ACTION C1: Water Resources IDA / 52680 Post Qualification Open - National 284,685.66 Signed 2018-01-30 2018-02-05 2018-02-20 2018-04-21 2018-04-06 2018-05-21 2017-02-23 2018-06-25 2018-06-28 2018-10-23 PLAN (RAP) FOR LUNGA Development Selection LUNGA, MSAMBWENI AND UKUNDA WATER SUPPLIES REHABILITATION AND EXPANSION PROJECT Page 3 KE-MOWI-47880-CS-QCBS / Consultancy services for Consultant design and construction C2: Effective Water Sector Under IDA / 52680 Post Qualification Open - National 0.00 2018-03-08 2018-03-29 2018-05-12 2018-10-12 2018-06-11 2018-07-16 2020-07-05 supervision of flood control Institutions Implementation Selection operational centres in sub basins KE-MOWI-47898-CS-QCBS / Consultancy services for C2: Effective Water Sector Quality And Cost- design and construction IDA / 52680 Prior Open - International 676,619.06 Signed 2018-03-15 2018-04-05 2018-05-19 2018-05-19 2018-10-05 2018-06-30 2018-07-30 2019-01-24 2018-09-03 2019-10-02 2018-10-08 2019-12-17 2020-09-27 Institutions Based Selection supervision of National Data and Information Centre KE-MOWI-57276-CS-QCBS / Consulting Services for Transaction Advisor for the development of an C2: Effective Water Sector Quality And Cost- IDA / 52680 Prior Open - International 501,218.39 Signed 2018-04-12 2018-05-12 2018-05-23 2018-07-02 2018-08-08 2018-08-13 2018-09-12 2018-11-08 2018-10-24 2019-04-27 2018-12-05 2019-06-26 2019-12-05 institutional framework and Institutions Based Selection delivery structure for the bulk water services in the Coastal counties KE-MOWI-84310-CS-QCBS / Consultancy for Resettlement C1: Water Resources Quality And Cost- IDA / 52680 Post Open - International 858,789.14 Signed 2018-11-02 2019-01-29 2018-11-23 2019-03-13 2019-01-06 2019-05-10 2019-02-17 2019-06-18 2019-03-19 2019-07-25 2019-04-23 2019-11-18 2019-05-28 2019-11-18 2022-05-22 Action Plan Implementation Development Based Selection for Lower Nzoia Project KE-MOWI-166152-CS-CQS / Consultancy Services for The Preparation of Resettlement Consultant C1: Water Resources Under Action Plan No. 4 (RAP 4) for IDA / 52680 Post Qualification Open - National 0.00 2020-04-10 2020-04-02 2020-05-01 2020-05-11 2020-06-30 2020-08-04 2020-07-30 2020-09-03 2021-01-01 Development Implementation Tertiary Canals in Lower Nzoia Selection Irrigation Project (LNIP) – Phase I INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Individual KE-MOWI-8061-CS-INDV / C3: Support for Project IDA / 52680 Prior Consultant Open 877,500.00 Signed 2017-02-22 2017-04-28 2017-04-20 2017-05-19 2018-07-31 2017-06-23 2018-08-24 2020-06-07 PMU Chief Operations Officer Implementation Selection KE-MOWI-8062-CS-INDV / Individual C1: Water Resources Social Development Specialist IDA / 52680 Post Consultant Open 199,170.14 Signed 2017-02-22 2016-11-28 2017-04-28 2017-04-12 2017-05-19 2017-05-17 2017-06-23 2017-05-17 2020-06-07 Development - Western Kenya Selection KE-MOWI-8143-CS-INDV / Individual C1: Water Resources Under Project Engineer, Western IDA / 52680 Post Consultant Open 0.00 2017-02-24 2017-01-31 2017-04-23 2017-05-14 2017-06-18 2018-06-13 Development Implementation Kenya Selection KE-MOWI-8144-CS-INDV / Individual C1: Water Resources Under Inspector of Works, Western IDA / 52680 Post Consultant Open 0.00 2017-02-24 2017-01-31 2017-04-23 2017-05-14 2017-06-18 2018-06-13 Development Implementation Kenya Selection KE-MOWI-8329-CS-INDV / Individual C1: Water Resources Under Assistant Resident Engineer - IDA / 52680 Post Consultant Open 0.00 2017-02-28 2017-02-21 2017-04-27 2017-05-18 2017-06-22 2018-12-14 Development Implementation Likoni Area-Phase 1 Selection KE-MOWI-8331-CS-INDV / Individual C1: Water Resources Under Resident Engineer - Likoni IDA / 52680 Post Consultant Open 0.00 2017-02-28 2017-02-21 2017-04-27 2017-05-18 2017-06-22 2018-12-14 Development Implementation Area-Phase 1 Selection Individual KE-MOWI-8942-CS-INDV / C1: Water Resources IDA / 52680 Prior Consultant Open 139,467.31 Signed 2017-03-16 2017-05-13 2017-01-18 2017-06-03 2017-04-25 2017-07-08 2017-04-26 2020-06-22 Procurement Specialist 1 Development Selection Individual KE-MOWI-8943-CS-INDV / C1: Water Resources IDA / 52680 Prior Consultant Open 139,467.31 Signed 2017-03-16 2017-05-13 2017-01-18 2017-06-03 2017-04-25 2017-07-08 2017-04-26 2020-06-22 Procurement Specialist 2 Development Selection KE-MOWI-9280-CS-INDV / Consultant to provide legal Individual C2: Effective Water Sector Under and policy support for IDA / 52680 Post Consultant Open 0.00 2017-04-12 2017-03-09 2017-06-09 2017-06-30 2017-08-04 2018-08-04 Institutions Implementation development of National Selection Water Policy KE-MOWI-13139-CS-INDV / Consultancy services of Individual C3: Support for Project Under Environmental and Social IDA / 52680 Prior Consultant Open 0.00 2017-05-11 2017-07-15 2017-08-05 2017-09-09 2019-09-29 Implementation Implementation Panel of Experts - Selection Environmental Specialist KE-MOWI-13140-CS-INDV / Consultancy services for Individual C3: Support for Project Under Environmental and Social IDA / 52680 Prior Consultant Open 0.00 2017-05-18 2017-07-22 2017-08-12 2017-09-16 2019-10-06 Implementation Implementation Panel of Experts - Social Selection Specialist Individual KE-MOWI-57281-CS-INDV / C3: Support for Project IDA / 52680 Prior Consultant Open 304,023.85 Signed 2018-04-05 2018-06-09 2018-06-30 2018-05-29 2018-08-04 2018-06-20 2021-07-19 Social Safeguards Officer Implementation Selection Individual KE-MOWI-57278-CS-INDV / C3: Support for Project IDA / 52680 Prior Consultant Open 0.00 Canceled 2018-05-29 2018-08-02 2018-08-23 2018-09-27 2021-09-11 Planning and M&E Specialist Implementation Selection KE-MOWI-71899-CS-INDV / Individual C3: Support for Project Under Planning and Monitoring & IDA / 52680 Prior Consultant Open 0.00 2018-08-03 2018-10-07 2019-02-12 2018-10-28 2019-03-05 2018-12-02 2021-11-16 Implementation Implementation Evaluation Specialist Selection KE-MOWI-83366-CS-CDS / CONSULTANCY SERVICES FOR PROVISION OF LEGAL C1: Water Resources SERVICES TOWARDS PROJECT IDA / 56740 Prior Direct Selection Direct 329,774.30 Signed 2018-10-23 2018-11-02 2019-01-06 2019-04-09 2020-01-06 Development AFFECTED PERSONS (PAPS) SUCCESSION GRANTS BY COURTS -RAP III Page 4 KE-MOWI-84304-CS-INDV / Individual Consultancy services for C3: Support for Project IDA / 52680 Prior Consultant Open 134,221.42 Signed 2018-11-08 2018-12-10 2019-01-12 2019-02-02 2019-03-05 2019-03-09 2019-06-14 2022-02-21 Communication Expert - Implementation Selection Lower Nzoia Project KE-MOWI-112692-CS-INDV Individual / Consultancy Services for C3: Support for Project IDA / 52680 Prior Consultant Open 101,556.46 Signed 2019-04-30 2019-10-10 2019-07-04 2019-10-01 2019-07-25 2019-10-31 2019-08-29 2019-11-26 2021-08-18 Social Safeguards Expert - Implementation Selection LNIP and IFMS KE-MOWI-126348-CS-INDV / Consultancy Services of Two (2) Members to Sit in the Individual Dispute Board of Construction C1: Water Resources IDA / 52680 Prior Consultant Open 205,999.09 Signed 2019-08-07 2019-09-01 2019-10-11 2019-12-19 2019-11-01 2020-03-10 2019-12-06 2020-07-21 2022-12-05 Works of Lower Nzoia Development Selection Irrigation Project Phase 1 and Improvement of Flood Mitigation Structures KE-MOWI-167474-CS-INDV Individual / Business Process C1: Water Resources Under IDA / 52680 Post Consultant Open 0.00 2020-04-09 2020-05-04 2020-05-28 2020-09-18 2020-06-18 2020-07-23 2021-01-19 Management/Re-Engineering Development Implementation Selection Specialist Individual KE-MOWI-167476-CS-INDV C1: Water Resources Under IDA / 52680 Post Consultant Open 0.00 2020-04-09 2020-05-04 2020-05-28 2020-09-18 2020-06-18 2020-07-23 2021-01-27 / IT Specialist (ERP systems) Development Implementation Selection KE-MOWI-189077-CS-INDV Individual C1: Water Resources Under / Contract Management and IDA / 52680 Prior Consultant Open 0.00 2020-08-21 2020-09-13 2020-10-25 2020-11-27 2020-11-15 2021-01-22 2020-12-20 2023-01-09 Development Implementation Procurement Specialist Selection KE-MOWI-189082-CS-INDV Individual C1: Water Resources Under / Knowledge Management IDA / 52680 Prior Consultant Open 0.00 2020-08-21 2020-09-13 2020-10-25 2020-11-26 2020-11-15 2021-01-08 2020-12-20 2023-01-09 Development Implementation Specialist Selection Individual KE-MOWI-189086-CS-INDV C1: Water Resources Under IDA / 52680 Post Consultant Open 0.00 2020-08-21 2020-08-31 2020-10-09 2020-10-30 2020-12-04 2022-12-24 / Accounts Assistant Development Implementation Selection KE-MOWI-192385-CS-CDS / Consultancy Services for a Chairman of Dispute Board of Construction Works of the C1: Water Resources Under IDA / 52680 Prior Direct Selection Direct 0.00 2020-11-20 2021-01-13 2020-11-30 2021-01-13 2021-02-03 2023-02-23 Lower Nzoia Project - Lot 1: Development Implementation and Improvement of Flood Mitigation Structures (IFMS) - Lot 2 KE-MOWI-236557-CS-CDS / Consultancy Services for Provision of Additional Legal Services in LNIP RAP 2 Areas C1: Water Resources Under IDA / 52680 Post Direct Selection Direct 0.00 2021-05-26 2021-05-23 2021-06-05 2021-08-09 2022-02-05 Towards Project Affected Development Implementation Persons (PAPs) Having Succession Grants Issued By The Courts KE-MOWI-249507-CS-CDS / Consultancy services for implementation of Lower C3: Support for Project Pending IDA / 52680 Post Direct Selection Direct 0.00 2021-08-27 2021-09-08 2021-10-27 2022-10-27 Nzoia IrrigationProject Implementation Implementation Resettlement Action Plan (RAP) 4 for the Tertiary Canals Page 5