PROCUREMENT PLAN (Textual Part) Project information: Brazil: Integrated Landscape Management in the Cerrado Biome Project – P164602 Project Implementation agency: DEUTSCHE GESELLSCHAFT FÜR INTERNATIONALE ZUSAMMENARBEIT GmbH (GIZ) Date of the Procurement Plan: August 21, 2018 Period covered by this Procurement Plan: October 2018- March 2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in [insert appropriate references to the national procurement legislation], such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. List only the applicable conditions required to ensure consistency with paragraph 5.4 of the Procurement Regulations. If no conditions apply, delete the phrase “and the following conditions”. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Otherwise state “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Otherwise state “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables] Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. [Include this sentence only if the Bank has formally agreed to provide the Borrower with HEIS. Otherwise delete] Other Relevant Procurement Information. Provide any other relevant procurement information such as procedures for CDD components, Procurement in Situations of Urgent Need of Assistance or Capacity Constraints etc. PROCUREMENT Brazil : Integrated Landscape Management in the Cerrado Biome Project PLAN General Information Country: Brazil Bank’s Approval Date of the Original Procurement Plan: 2018-09-03 2021-09-23 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P164602 GPN Date: Project Name: Integrated Landscape Management in the Cerrado Biome Project Loan / Credit No: / , TF / A8532 German Society for International Cooperation Executing Agency(ies): WORKS Procureme Activity Reference No. / Actual Draft Bidding Bid Evaluation Report Loan / Credit Market Procurement Prequalification High SEA/SH nt Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Amount Document / and Recommendation Signed Contract No. Approach Process (Y/N) Risk Document Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) Justification for Award Type Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual EMBRAPA 2 BR-GIZ-76279- CW-APA / Contratação de empresa da área de Mainstreaning Landscape Alternative Single Stage - One 2019-05- construção civil para execução / Practices into Selected Posterior Procurement Open - National 0.00 Cancelado 2018-10-01 2018-10-06 2018-10-27 2018-11-03 2018-11-24 Envelope 23 de reforma do auditório e Watersheds Arrangement salas de aula da EMBRAPA Cerrados. EMBRAPA 2 BR-GIZ-76268- CW-APA / Contratação de empresa da área de Mainstreaning Landscape Alternative construção civil para reforma Single Stage - One 2019-05- / Practices into Selected Posterior Procurement Open - National 0.00 Cancelado 2018-10-01 2018-10-06 2018-10-27 2018-11-03 2018-11-24 e adequação do Viveiro de Envelope 23 Watersheds Arrangement P&D da Embrapa Cerrados para operar também como Unidade de Aprendizagem EMBRAPA 2 BR-GIZ-76209- CW-APA / Contratação de empresa da área de construção civil para reforma Mainstreaning Landscape Alternative Single Stage - One 2019-05- e adequação e manutenção do / Practices into Selected Posterior Procurement Open - National 0.00 Cancelado 2018-10-01 2018-10-06 2018-10-27 2018-11-03 2018-11-24 Envelope 23 Studio para Watersheds Arrangement produção/gravação de vídeos para TT, inclusive EAD, da Embrapa Cerrados EMBRAPA BR-GIZ-161546- CW-RFQ / Contratação de Institutional Development Other (with empresa para obra de reforma Solicitação de Single Stage - One Implementaç 2022-06- TF / A8532 and Capacity Building for Posterior Open - National field for 0.00 2021-10-09 2021-12-04 de construção civil de Cotações Envelope ão Pendente 02 Landscape Management explanation) auditório para capacitação na Embrapa Cerrados. EMBRAPA BR-GIZ-242453- CW-RFQ / Contratação de Institutional Development Other (with empresa da área de Solicitação de Single Stage - One Implementaç 2022-06- TF / A8532 and Capacity Building for Posterior Open - National field for 0.00 2021-10-09 2021-12-04 construção civil para reforma Cotações Envelope ão Pendente 02 Landscape Management explanation) e adequação do Viveiro de Mudas da Embrapa Cerrados. GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Document / and Recommendation Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual EMBRAPA 1 BR-GIZ-76233- GO-APA / Aquisição de equipamentos de informatica Institutional Development Alternative computadores etc.. Para a Single Stage - One / and Capacity Building for Posterior Procurement Open - National 0.00 Cancelado 2018-10-10 2018-10-15 2018-11-05 2018-11-12 2018-12-03 2019-06-01 equipe de processamento e Envelope Landscape Management Arrangement sistematização da informação tecnológica da paisagem da Embrapa Cerrados. EMBRAPA 2 BR-GIZ-76255- GO-APA / Aquisição de Mainstreaning Landscape Alternative equipamentos de informatica Single Stage - One / Practices into Selected Posterior Procurement Open - National 0.00 Cancelado 2018-10-10 2018-10-15 2018-11-05 2018-11-12 2018-12-03 2019-06-01 computadores, etc.. para a Envelope Watersheds Arrangement sala de treinamento (EAD) da Embrapa Cerrados. EMBRAPA 1 BR-GIZ-76272- GO-APA / Aquisição de maquinas e equipamentos tecnicos para analises de Institutional Development Alternative Single Stage - One campo para avaliar o / and Capacity Building for Posterior Procurement Open - National 0.00 Cancelado 2018-10-10 2018-10-15 2018-11-05 2018-11-12 2018-12-03 2019-06-01 Envelope processamento e Landscape Management Arrangement sistematização da informação tecnológica da paisagem da Embrapa Cerrados. EMBRAPA 2 BR-GIZ-76207- GO-APA / Aquisição de Mainstreaning Landscape Alternative Single Stage - One mobiliário para auditorio e / Practices into Selected Posterior Procurement Open - National 0.00 Cancelado 2018-10-10 2018-10-15 2018-11-05 2018-11-12 2018-12-03 2019-06-01 Envelope sala de treinamento (EAD) da Watersheds Arrangement Embrapa Cerrados. EMBRAPA 2 BR-GIZ-76257- GO-APA / Aquisição de Mainstreaning Landscape Alternative material didatico impresso Single Stage - One / Practices into Selected Posterior Procurement Open - National 0.00 Cancelado 2019-03-10 2019-03-15 2019-04-05 2019-04-12 2019-05-03 2019-10-30 para distribuição nos cursos Envelope Watersheds Arrangement de conservação para os diferentes atores/públicos. EMBRAPA 1 BR-GIZ-76283- GO-APA / Aquisição de equipamentos Institutional Development Alternative Single Stage - One eletroeletronicos para o / and Capacity Building for Posterior Procurement Open - National 0.00 Cancelado 2019-01-20 2019-01-25 2019-02-15 2019-02-22 2019-03-15 2019-09-11 Envelope auditorio e as salas de Landscape Management Arrangement treinamento da Embrapa Cerrados. Page 1 EMBRAPA 2 BR-GIZ-76256- GO-APA / Aquisição de material (toner, tinta, papel Mainstreaning Landscape Alternative etc..) para impressao de Single Stage - One / Practices into Selected Posterior Procurement Open - National 0.00 Cancelado 2018-10-01 2018-10-06 2018-10-27 2018-11-03 2018-11-24 2019-05-23 material didatico (audiovisual) Envelope Watersheds Arrangement para os cursos de conservação para os diferentes atores/públicos. EMBRAPA 1 BR-GIZ-76250- GO-APA / Aquisição de Institutional Development Alternative equipamentos de audio visual Single Stage - One / and Capacity Building for Posterior Procurement Open - National 0.00 Cancelado 2019-02-10 2019-02-15 2019-03-08 2019-03-15 2019-04-05 2019-10-02 etc.. para auditorio e sala de Envelope Landscape Management Arrangement treinamento (EAD) da Embrapa Cerrados. EMBRAPA 1 BR-GIZ-76258- GO-APA / Aquisição de material de consumo para estudos prospectivos de Institutional Development Alternative cenários de conservação e Single Stage - One / and Capacity Building for Posterior Procurement Open - National 0.00 Cancelado 2019-01-20 2019-01-25 2019-02-15 2019-02-22 2019-03-15 2019-09-11 produção com tecnologias Envelope Landscape Management Arrangement disponíveis sobre o CAR, PRA, tecnologias do ABC, BPAs, RAD, Legislação de Proteção da Vegetação Nativa EMBRAPA 2 BR-GIZ-76291- GO-APA / Aquisição de material de consumo para a realização do componente de Mainstreaning Landscape Alternative conservação da paisagem nos Single Stage - One / Practices into Selected Posterior Procurement Open - National 0.00 Cancelado 2019-01-20 2019-01-25 2019-02-15 2019-02-22 2019-03-15 2019-09-11 cursos, treinamentos, dias de Envelope Watersheds Arrangement campo etc.sobre o CAR, PRA, tecnologias do ABC, BPAs, RAD, Legislação de Proteção da Vegetação Nativa EMBRAPA 1 BR-GIZ-76269- GO-APA / Aquisição de combustível para a realização dos estudos prospectivos de Institutional Development Alternative cenários e paisagens de Single Stage - One / and Capacity Building for Posterior Procurement Open - National 0.00 Cancelado 2019-01-20 2019-01-25 2019-02-15 2019-02-22 2019-03-15 2019-09-11 conservação e produção com Envelope Landscape Management Arrangement tecnologias disponíveis sobre o CAR, PRA, tecnologias do ABC, BPAs, RAD, Legislação de Proteção da Vegetação Nativa EMBRAPA 2 BR-GIZ-76208- GO-APA / Aquisição de combustível para a realização dos cursos e estudos de Mainstreaning Landscape Alternative conservação da paisagem nos Single Stage - One / Practices into Selected Posterior Procurement Open - National 0.00 Cancelado 2019-01-20 2019-01-25 2019-02-15 2019-02-22 2019-03-15 2019-09-11 cursos, treinamentos, dias de Envelope Watersheds Arrangement campo etc.sobre o CAR, PRA, tecnologias do ABC, BPAs, RAD, Legislação de Proteção da Vegetação Nativa SFB 2 BR-GIZ-76245-GO- Mainstreaning Landscape Alternative APA / Aquisicao de Kits Single Stage - One / Practices into Selected Posterior Procurement Open - National 0.00 Cancelado 2019-03-15 2019-03-20 2019-04-10 2019-04-17 2019-05-08 2019-11-04 promocionais de comunicacao Envelope Watersheds Arrangement e informativos INPE 1 BR-GIZ-76271-GO- Institutional Development Alternative APA / Aquisição de material Single Stage - One / and Capacity Building for Posterior Procurement Open - National 0.00 Cancelado 2018-10-15 2018-10-20 2018-11-10 2018-11-17 2018-12-08 2019-06-06 de Campo (mapeamento Envelope Landscape Management Arrangement orbital e análise da paisagem) INPE 1 BR-GIZ-76287-GO- Institutional Development Alternative APA / Aquisição de Material Single Stage - One / and Capacity Building for Posterior Procurement Open - National 0.00 Cancelado 2018-10-15 2018-10-20 2018-11-10 2018-11-17 2018-12-08 2019-06-06 de Escritório (mapeamento Envelope Landscape Management Arrangement orbital e análise da paisagem) INPE 1 BR-GIZ-76192-GO- APA / Aquisição de Institutional Development Alternative Single Stage - One equipamentos de Informática / and Capacity Building for Posterior Procurement Open - National 0.00 Cancelado 2018-10-15 2018-10-20 2018-11-10 2018-11-17 2018-12-08 2019-06-06 Envelope (mapeamento orbital e análise Landscape Management Arrangement da paisagem) INPE 1 BR-GIZ-76218-GO- Institutional Development Alternative APA / Aquisição de Single Stage - One / and Capacity Building for Posterior Procurement Open - National 0.00 Cancelado 2018-10-15 2018-10-20 2018-11-10 2018-11-17 2018-12-08 2019-06-06 equipamento Fotográfico Envelope Landscape Management Arrangement (mapeamento orbital) GIZ 3 BR-GIZ-76225-GO-APA Project Management, Alternative / Aquisição de equipamentos Single Stage - One / Monitoring, Evaluation and Posterior Procurement Open - National 0.00 Cancelado 2018-10-15 2018-10-20 2018-11-10 2018-11-17 2018-12-08 2019-06-06 de informática para equipe Envelope Communication Arrangement base da GIZ INPE BR-GIZ-109966-GO- RFQ / Aquisição de Institutional Development Solicitação de Single Stage - One equipamentos de Informática TF / A8532 and Capacity Building for Posterior Open - National 9,464.01 Assinado 2019-06-08 2019-08-03 2019-07-08 2020-01-30 Cotações Envelope (mapeamento orbital e análise Landscape Management da paisagem) INPE BR-GIZ-109967-GO- Institutional Development RFQ / Aquisição de Solicitação de Single Stage - One TF / A8532 and Capacity Building for Posterior Open - National 3,003.44 Assinado 2019-08-10 2019-10-05 2019-08-27 2020-04-02 equipamento Fotográfico Cotações Envelope Landscape Management (mapeamento orbital) GIZ BR-GIZ-109985-GO-RFQ Project Management, / Aquisição de equipamentos Solicitação de Single Stage - One TF / A8532 Monitoring, Evaluation and Posterior Open - National 0.00 Cancelado 2019-04-15 2019-06-10 2019-12-07 de informática para equipe Cotações Envelope Communication base da GIZ EMBRAPA BR-GIZ-123501- GO-RFQ / Adquirir equipamentos para edicao de Institutional Development Solicitação de Single Stage - One videos para a TF / A8532 and Capacity Building for Posterior Open - National 8,053.30 Assinado 2019-08-06 2019-10-01 2019-11-11 2020-03-29 Cotações Envelope Embrapa/Cerrados que Landscape Management atenderao demandas do treinamento dos tecnicos do SENAR GIZ-BR-GIZ-143344-GO-RFQ Project Management, / Aquisicao de uma licenca de Solicitação de Single Stage - One TF / A8532 Monitoring, Evaluation and Posterior Open - National 369.85 Assinado 2019-11-16 2020-01-11 2019-11-26 2020-07-09 software para gerenciamento Cotações Envelope Communication de projeto Page 2 INPE BR-GIZ-161547-GO- Institutional Development RFQ / Equipamentos de Solicitação de Single Stage - One TF / A8532 and Capacity Building for Posterior Open - National 592.74 Assinado 2020-04-06 2020-06-01 2020-04-13 2020-11-28 escritório (ar-condicionado, Cotações Envelope Landscape Management cadeiras, etc.) INPE BR-GIZ-162147-GO- Institutional Development Em fase de Solicitação de Single Stage - One RFQ / Equipamentos de TF / A8532 and Capacity Building for Posterior Open - National 1,915.01 Implementaçã 2020-07-10 2020-09-04 2021-03-03 Cotações Envelope informática Landscape Management o EMBRAPA BR-GIZ-109842- GO-RFQ / Aquisição de combustível para a realização dos estudos prospectivos de Institutional Development cenários e paisagens de Solicitação de Single Stage - One TF / A8532 and Capacity Building for Posterior Open - National 0.00 Cancelado 2019-07-13 2019-09-07 2020-03-05 conservação e produção com Cotações Envelope Landscape Management tecnologias disponíveis sobre o CAR, PRA, tecnologias do ABC, BPAs, RAD, Legislação de Proteção da Vegetação Nativa. INPE BR-GIZ-109958-GO- Institutional Development APA / Aquisição de Material Solicitação de Single Stage - One TF / A8532 and Capacity Building for Posterior Open - National 0.00 Cancelado 2019-09-07 2019-11-02 2020-04-30 de Escritório (mapeamento Cotações Envelope Landscape Management orbital e análise da paisagem) INPE BR-GIZ-109957-GO- Institutional Development RFQ / Aquisição de material Solicitação de Single Stage - One TF / A8532 and Capacity Building for Posterior Open - National 0.00 Cancelado 2019-09-07 2019-11-02 2020-04-30 de Campo (mapeamento Cotações Envelope Landscape Management orbital e análise da paisagem) INPE BR-GIZ-201636-GO- Institutional Development Solicitação de Single Stage - One RFQ / Aquisição de TF / A8532 and Capacity Building for Posterior Open - National 8,018.21 Concluído 2020-11-03 2020-12-29 2021-01-27 2021-06-27 2021-01-28 Cotações Envelope equipamentos de informática Landscape Management EMBRAPA BR-GIZ-240326- GO-RFQ / Aquisição de Software Adobe EDU Named Institutional Development Em fase de Acrobat Pro DC for Teams - Solicitação de Single Stage - One TF / A8532 and Capacity Building for Posterior Open - National 0.00 Implementaçã 2021-07-03 2021-08-28 2022-02-24 Multiplataforma ML para a Cotações Envelope Landscape Management o Embrapa Cerrados, parceira do Projeto Paisagens Rurais (FIP-Paisagens) INPE BR-GIZ-240327-GO- RFQ / Aquisição de HDs Institutional Development externos portáteis para a Solicitação de Single Stage - One TF / A8532 and Capacity Building for Posterior Open - National 848.97 Assinado 2021-07-03 2021-08-28 2021-07-29 2022-02-24 Embrapa Informática Cotações Envelope Landscape Management Agropecuária, parceira do Projeto Paisagens Rurais SFB BR-GIZ-109849-GO-RFQ Mainstreaning Landscape / Aquisicao de Kits Solicitação de Single Stage - One Implementaçã TF / A8532 Practices into Selected Posterior Open - National 0.00 2021-10-08 2021-12-03 2022-06-01 promocionais de comunicacao Cotações Envelope o Pendente Watersheds e informativos EMBRAPA BR-GIZ-162133- GO-RFQ / Compra de materiais, insumos e Institutional Development equipamentos para Solicitação de Single Stage - One TF / A8532 and Capacity Building for Posterior Open - National 0.00 Cancelado 2021-08-07 2021-10-02 2022-03-31 manutenção da Unidades Cotações Envelope Landscape Management Demonstrativas na Embrapa Cerrados. (ILP - Experimento longa duração-Chapadao + ILPF e pastagem solteira) EMBRAPA BR-GIZ-204510- GO-RFQ / Aquisição de sementes forrageiras para plantio nas Unidades de Referencia Tecnológica (URT) Institutional Development Solicitação de Single Stage - One utilizada nos treinamentos TF / A8532 and Capacity Building for Posterior Open - National 0.00 Cancelado 2020-11-20 2021-01-15 2021-07-14 Cotações Envelope sobre recuperação de Landscape Management vegetação nativa e pastagens para os 230 técnicos de ATeG que atenderão os 4 mil proprietários rurais EMBRAPA BR-GIZ-161606- GO-RFQ / Aquisição de bens e equipamentos para o Mainstreaning Landscape Solicitação de Single Stage - One Implementaçã auditorio para capacitação na TF / A8532 Practices into Selected Posterior Open - National 0.00 2021-08-07 2021-10-02 2022-03-31 Cotações Envelope o Pendente Embrapa Cerrados. (Som + Watersheds Imagem + piso + ar condicionado + cadeiras) EMBRAPA BR-GIZ-109840- GO-RFQ / Aquisição de Mainstreaning Landscape material didático impresso Solicitação de Single Stage - One TF / A8532 Practices into Selected Posterior Open - National 0.00 Cancelado 2021-01-04 2021-03-01 2021-08-28 para distribuição nos cursos Cotações Envelope Watersheds de conservação para os diferentes atores/públicos. EMBRAPA BR-GIZ-162145- GO-RFQ / Compra de Institutional Development materiais e insumos (gesso) Solicitação de Single Stage - One TF / A8532 and Capacity Building for Posterior Open - National 0.00 Cancelado 2021-08-07 2021-10-02 2022-03-31 para manutenção da URT na Cotações Envelope Landscape Management Fazenda Entre Rios PA-DF (BPA + RAD + Guzerá ). EMBRAPA BR-GIZ-162144- GO-RFQ / Compra de materiais, insumos e Institutional Development Em fase de Solicitação de Single Stage - One equipamentos para TF / A8532 and Capacity Building for Posterior Open - National 0.00 Implementaçã 2021-10-09 2021-12-04 2022-06-02 Cotações Envelope manutenção da URT na Landscape Management o Embrapa Cerrados (CTZL - Centro de Tecnologias de Raças Zebuínas Leiteiras). EMBRAPA BR-GIZ-242450- GO-RFQ / Aquisição de bens e Institutional Development equipamentos para estúdio Solicitação de Single Stage - One Implementaçã TF / A8532 and Capacity Building for Posterior Open - National 0.00 2021-10-09 2021-12-04 2022-06-02 para produção/gravação de Cotações Envelope o Pendente Landscape Management vídeos para TT, inclusive EAD, da Embrapa Cerrados. EMBRAPA BR-GIZ-242454- GO-RFQ / Compra de materiais, insumos e Institutional Development Solicitação de Single Stage - One equipamentos para TF / A8532 and Capacity Building for Posterior Open - National 0.00 Cancelado 2021-10-09 2021-12-04 2022-06-02 Cotações Envelope manutenção da URT da Landscape Management Embrapa Cerrados na Fazenda Experimental da ABCZ, Uberaba-MG Page 3 EMBRAPA BR-GIZ-109835- GO-RFQ / Aquisição de Institutional Development Em fase de Solicitação de Single Stage - One equipamentos de informática TF / A8532 and Capacity Building for Posterior Open - National 0.00 Implementaçã 2019-05-11 2019-07-06 2020-01-02 Cotações Envelope computadores, softwares, Landscape Management o imagens, equipamentos, etc.. EMBRAPA BR-GIZ-162146- GO-RFQ / Compra de Institutional Development Solicitação de Single Stage - One Implementaçã materiais e insumos para TF / A8532 and Capacity Building for Posterior Open - National 0.00 2021-10-16 2021-12-11 2022-06-09 Cotações Envelope o Pendente manutenção da URT na Landscape Management Fazenda Entre Rios PA-DF (BPA + RAD + Guzerá ). EMBRAPA BR-GIZ-254481- Institutional Development GO-RFQ / Compra de insumos Solicitação de Single Stage - One Implementaçã TF / A8532 and Capacity Building for Posterior Open - National 0.00 2021-10-15 2021-12-10 2022-06-08 (SULFATO DE AMÔNIO) para Cotações Envelope o Pendente Landscape Management manutenção da URT EMBRAPA BR-GIZ-254483- GO-RFQ / Aquisição de Institutional Development Solicitação de Single Stage - One Implementaçã agroquímicos para Unidades TF / A8532 and Capacity Building for Posterior Open - National 0.00 2021-10-29 2021-12-24 2022-06-22 Cotações Envelope o Pendente de Referência Tecnológica Landscape Management (URTs) NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Document / and Recommendation Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual EMBRAPA 2 BR-GIZ-76293- NC-APA / Fornecimento de coffee break e/ou almoço para todas as capacitações do Mainstreaning Landscape Alternative comp de conserv da paisagem Single Stage - One / Practices into Selected Posterior Procurement Open - National 0.00 Cancelado 2019-01-20 2019-01-25 2019-02-15 2019-02-22 2019-03-15 2019-09-11 em cursos, dias de campo etc Envelope Watersheds Arrangement dos técnicos rurais e/ou produtores durante todos os cursos, seminarios regionais, excursoes tecnicas EMBRAPA 1 BR-GIZ-76234- NC-APA / Loc. de veiculos para a realização de estudos prospectivos de cenários de Institutional Development Alternative Single Stage - One conservação e produção com / and Capacity Building for Posterior Procurement Open - National 0.00 Cancelado 2019-01-20 2019-01-25 2019-02-15 2019-02-22 2019-03-15 2019-09-11 Envelope tecnologias disponíveis sobre Landscape Management Arrangement o CAR, PRA, tecnologias do ABC, BPAs, RAD, Legislação de Proteção da Vegetação Nativa EMBRAPA 2 BR-GIZ-76262- NC-APA / Loc de veic para a realização do comp de estudos e cursos de conserv Mainstreaning Landscape Alternative da paisagem nos cursos, Single Stage - One / Practices into Selected Posterior Procurement Open - National 0.00 Cancelado 2019-01-20 2019-01-25 2019-02-15 2019-02-22 2019-03-15 2019-09-11 treinam, dias de campo etc Envelope Watersheds Arrangement com tecnol disponíveis sobre o CAR, PRA, tecnologias do ABC, BPAs, RAD, Legislação de Proteção da Vegetação Nativa EMBRAPA 2 BR-GIZ-76236- NC-APA / Contratação de empresa gráfica para a Mainstreaning Landscape Alternative Single Stage - One impressao de material / Practices into Selected Posterior Procurement Open - National 0.00 Cancelado 2019-01-20 2019-01-25 2019-02-15 2019-02-22 2019-03-15 2019-09-11 Envelope didatico para os cursos de Watersheds Arrangement conservação para os diferentes atores/públicos. SFB 1 BR-GIZ-76238-NC-APA / Contratação de empresa para realização de eventos, Institutional Development Alternative cursos, oficinas e reuniões de Single Stage - One / and Capacity Building for Posterior Procurement Open - National 0.00 Cancelado 2018-10-15 2018-10-20 2018-11-10 2018-11-17 2018-12-08 2019-06-06 promoção do empoderamento Envelope Landscape Management Arrangement local e integração multi- institucional por Bacia selecionada SFB 2 BR-GIZ-76275-NC-APA / Contratação de pessoa jurídica para realizar 10 Mainstreaning Landscape Alternative oficinas participativas de Single Stage - One / Practices into Selected Posterior Procurement Open - National 0.00 Cancelado 2018-10-15 2018-10-20 2018-11-10 2018-11-17 2018-12-08 2019-06-06 elaboração e pactuação do Envelope Watersheds Arrangement plano, para o lançamento e a difusão do plano de ação de cada uma das bacias Mainstreaning Landscape Alternative SFB 2 BR-GIZ-76286-NC-APA Single Stage - One / Practices into Selected Posterior Procurement Open - National 0.00 Cancelado 2019-01-15 2019-01-20 2019-02-10 2019-02-17 2019-03-10 2019-09-06 / Aluguel de veiculos do SFB Envelope Watersheds Arrangement INPE 1 BR-GIZ-76273-NC- APA / Serviços de organização Institutional Development Alternative Single Stage - One de eventos, publicação e / and Capacity Building for Posterior Procurement Open - National 0.00 Cancelado 2018-10-15 2018-10-20 2018-11-10 2018-11-17 2018-12-08 2019-06-06 Envelope divulgação de resultados Landscape Management Arrangement (mapeamento orbital) INPE 1 BR-GIZ-76292-NC- Institutional Development Alternative APA / Locação de Veículo Single Stage - One / and Capacity Building for Posterior Procurement Open - National 0.00 Cancelado 2018-10-15 2018-10-20 2018-11-10 2018-11-17 2018-12-08 2019-06-06 (mapeamento orbital e análise Envelope Landscape Management Arrangement da paisagem) GIZ 3 BR-GIZ-76290-NC-APA / Contratação de serviços para Project Management, Alternative Single Stage - One produção dos materiais e / Monitoring, Evaluation and Posterior Procurement Open - National 0.00 Cancelado 2018-10-15 2018-10-20 2018-11-10 2018-11-17 2018-12-08 2019-06-06 Envelope peças de comunicação do Communication Arrangement Projeto GIZ 3 BR-GIZ-76276-NC-APA Project Management, Alternative Single Stage - One / Auditorias Externas / Monitoring, Evaluation and Posterior Procurement Open - National 0.00 Cancelado 2018-10-15 2018-10-20 2018-11-10 2018-11-17 2018-12-08 2019-06-06 Envelope Independentes do projeto Communication Arrangement Mainstreaning Landscape SFB BR-GIZ-109851-NC-RFQ Solicitação de Single Stage - One TF / A8532 Practices into Selected Posterior Open - National 0.00 Cancelado 2019-08-10 2019-10-05 2020-04-02 / Aluguel de veículos do SFB Cotações Envelope Watersheds Page 4 INPE BR-GIZ-109968-NC- Institutional Development RFQ / Aluguel de sala Solicitação de Single Stage - One TF / A8532 and Capacity Building for Posterior Open - National 17,449.76 Assinado 2019-05-11 2019-07-06 2019-06-20 2020-01-02 comercial para equipe de Cotações Envelope Landscape Management técnicos em Campinas/SP GIZ BR-GIZ-109987-NC-RFQ / Contratação de serviços para Project Management, Solicitação de Single Stage - One produção dos materiais e TF / A8532 Monitoring, Evaluation and Posterior Open - National 0.00 Cancelado 2019-12-07 2020-02-01 2020-07-30 Cotações Envelope peças de comunicação do Communication Projeto GIZ BR-GIZ-109989-NC-RFQ Project Management, Solicitação de Single Stage - One / Auditorias Externas TF / A8532 Monitoring, Evaluation and Posterior Open - National 4,214.35 Assinado 2019-11-23 2020-01-18 2020-01-15 2020-07-16 Cotações Envelope Independentes do projeto Communication EMBRAPA BR-GIZ-109841- NC-RFQ / Contratação de serviço de locação de veiculos para a realização de estudos Institutional Development prospectivos de cenários de Solicitação de Single Stage - One TF / A8532 and Capacity Building for Posterior Open - National 0.00 Cancelado 2019-08-10 2019-10-05 2020-04-02 conservação e produção com Cotações Envelope Landscape Management tecnologias disponíveis sobre o CAR, PRA, tecnologias do ABC, BPAs, RAD, Legislação de Proteção da Vegetação Nativa INPE BR-GIZ-162154-NC- Institutional Development RFQ / Contrato ferramentas TI Solicitação de Single Stage - One TF / A8532 and Capacity Building for Posterior Open - National 0.00 Cancelado 2020-04-10 2020-06-05 2020-12-02 para armazenamento de Cotações Envelope Landscape Management dados e comunicação INPE BR-GIZ-109960-NC- RFQ / Serviços de organização Institutional Development Solicitação de Single Stage - One de eventos, publicação e TF / A8532 and Capacity Building for Posterior Open - National 0.00 Cancelado 2019-11-09 2020-01-04 2020-07-02 Cotações Envelope divulgação de resultados Landscape Management (mapeamento orbital) INPE BR-GIZ-109964-NC- Institutional Development RFQ / Locação de Veículo Solicitação de Single Stage - One TF / A8532 and Capacity Building for Posterior Open - National 0.00 Cancelado 2019-11-09 2020-01-04 2020-07-02 (mapeamento orbital e análise Cotações Envelope Landscape Management da paisagem) BR-GIZ-207801-NC-RFQ / Project Management, Auditorias Externas Solicitação de Single Stage - One TF / A8532 Monitoring, Evaluation and Posterior Open - National 14,745.42 Assinado 2020-12-07 2021-02-01 2021-01-05 2021-07-31 Independentes do projeto Cotações Envelope Communication Exercícios 2020/2021 SFB BR-GIZ-161627-NC-RFQ Institutional Development / Aquisicao de Kits Solicitação de Single Stage - One TF / A8532 and Capacity Building for Posterior Open - National 0.00 Cancelado 2020-06-07 2020-08-02 2021-01-29 promocionais de comunicacao Cotações Envelope Landscape Management e informativos SFB BR-GIZ-161619-NC-RFQ / Produção de material Institutional Development informativo e vídeo para Solicitação de Single Stage - One Implementaçã TF / A8532 and Capacity Building for Posterior Open - National 0.00 2021-10-08 2021-12-03 2022-06-01 divulgação das atuações do Cotações Envelope o Pendente Landscape Management SFB incluindo o projeto FIP Paisagem. EMBRAPA BR-GIZ-161972- Institutional Development NC-RFQ / Alimentação  para Solicitação de Single Stage - One TF / A8532 and Capacity Building for Posterior Open - National 0.00 Cancelado 2020-04-10 2020-06-05 2020-12-02 os dois cursos presenciais de Cotações Envelope Landscape Management capacitação BPA e RAD. EMBRAPA BR-GIZ-161975- Institutional Development NC-RFQ / Material de apoio Solicitação de Single Stage - One TF / A8532 and Capacity Building for Posterior Open - National 0.00 Cancelado 2021-07-05 2021-08-30 2022-02-26 para os dois cursos Cotações Envelope Landscape Management presenciais de capacitação BPA e RAD. EMBRAPA BR-GIZ-242452- NC-RFQ / Contratação de empresa da área de Institutional Development construção civil para reforma Solicitação de Single Stage - One Implementaçã TF / A8532 and Capacity Building for Posterior Open - National 0.00 2021-10-09 2021-12-04 2022-06-02 e adequação e manutenção do Cotações Envelope o Pendente Landscape Management estúdio para produção/gravação de vídeos para TT, inclusive EAD, da Embrapa Cerrados. EMBRAPA BR-GIZ-164514- CW-RFQ / Contratação de Institutional Development empresa para instalações de Solicitação de Single Stage - One Implementaçã TF / A8532 and Capacity Building for Posterior Open - National 0.00 2021-10-09 2021-12-04 2022-06-02 equipamentos de Som + Cotações Envelope o Pendente Landscape Management Imagem + piso + ar condicionado + cadeiras CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual EMBRAPA 1 BR-GIZ-76228- CS-CAPA / CI na area de engenharia para elaboracao Institutional Development Alternative de projeto basico e executivo / and Capacity Building for Posterior Procurement Direct 0.00 Cancelado 2018-10-30 2018-12-09 2018-12-30 2019-06-28 para as reformas do Landscape Management Arrangement auditorio, salas de aula, salas de video e viveiro da EMBRAPA Cerrados. EMBRAPA 1 BR-GIZ-76229- CS-CAPA / CI para o processamento e sistem da informação tecnol para a Institutional Development Alternative caracterização e análise da / and Capacity Building for Posterior Procurement Open - National 0.00 Cancelado 2018-10-30 2018-11-20 2019-01-03 2019-01-31 2019-03-02 2019-04-06 2019-04-27 2020-04-26 estrutura e da dinâmica das Landscape Management Arrangement unidades de paisagem para replicabilidade das intervenções de BPA e RAD em diferentes escalas Page 5 EMBRAPA 2 BR-GIZ-76270- CS-CAPA / CI para coord, elaboração de cont e apresentação de cursos presenciais e a distância no Mainstreaning Landscape Alternative tema conserv dos rec nat em / Practices into Selected Posterior Procurement Open - National 0.00 Cancelado 2018-11-15 2018-12-06 2019-01-19 2019-02-16 2019-03-18 2019-04-22 2019-05-13 2020-05-12 temas como tecnol de manejo Watersheds Arrangement e uso controlado do fogo, estrat de recomp da vegetação nativas e boas praticas agropecuárias EMBRAPA 2 BR-GIZ-76204- CS-CAPA / Contratação de Consultoria Individual para Mainstreaning Landscape Alternative apresentação de cursos / Practices into Selected Posterior Procurement Open - National 0.00 Cancelado 2018-11-15 2018-12-06 2019-01-19 2019-02-16 2019-03-18 2019-04-22 2019-05-13 2020-05-12 presenciais e a distância no Watersheds Arrangement tema conservação dos recursos naturais (instrutores/equipe de apoio). EMBRAPA 2 BR-GIZ-76254- CS-CAPA / CI para coordenação da coleta de dados na implantação de tecnologias de manejo e uso Mainstreaning Landscape Alternative controlado do fogo; / Practices into Selected Posterior Procurement Open - National 0.00 Cancelado 2018-11-15 2018-12-06 2019-01-19 2019-02-16 2019-03-18 2019-04-22 2019-05-13 2020-05-12 estratégias de recomposição Watersheds Arrangement da vegetação nativa e boas praticas agropecuárias, em imoveis rurais assistidos pelo Projeto EMBRAPA 2 BR-GIZ-76205- CS-CAPA / CI para execução da coleta de dados na implant Mainstreaning Landscape Alternative de tecnologias de manejo e / Practices into Selected Posterior Procurement Open - National 0.00 Cancelado 2018-11-15 2018-12-06 2019-01-19 2019-02-16 2019-03-18 2019-04-22 2019-05-13 2020-05-12 uso controlado do fogo; Watersheds Arrangement estratégias de recomp da veg. nativa e boas praticas agropecuárias EMBRAPA 2 BR-GIZ-76277- CS-CAPA / 3 CIs para apoio na coleta de dados na implantação de tecnologias Mainstreaning Landscape Alternative de manejo e uso controlado / Practices into Selected Posterior Procurement Open - National 0.00 Cancelado 2018-10-10 2018-10-31 2018-12-14 2019-01-11 2019-02-10 2019-03-17 2019-04-07 2020-04-06 do fogo, estratégias de Watersheds Arrangement recomposição da vegetação nativa e boas praticas agropecuárias. EMBRAPA 2 BR-GIZ-76232- CS-CAPA / CI para levantar Mainstreaning Landscape Alternative subsidios para incentivar à / Practices into Selected Posterior Procurement Open - National 0.00 Cancelado 2018-10-10 2018-10-31 2018-12-14 2019-01-11 2019-02-10 2019-03-17 2019-04-07 2020-04-06 cadeia produtiva da Watersheds Arrangement restauração SFB 1 BR-GIZ-76252-CS- CAPA / Serviços de Consultoria jurídica para Institutional Development Alternative Classificações para o SICAR no / and Capacity Building for Posterior Procurement Open - National 0.00 Cancelado 2018-10-15 2018-11-05 2018-12-19 2019-01-16 2019-02-15 2019-03-22 2019-04-12 2020-04-11 Cerrado, SENTINEL ou Sensor Landscape Management Arrangement Compatível 1:10.000 - 2016, 2017, 2018, 2019 SFB 1 BR-GIZ-76264-CS- CAPA / CPJ para realizar diag, mapeam e elaborar portif de divulgação da sistematiz de Institutional Development Alternative exp de imóveis rurais públ e / and Capacity Building for Posterior Procurement Open - National 0.00 Cancelado 2018-10-15 2018-11-05 2018-12-19 2019-01-16 2019-02-15 2019-03-22 2019-04-12 2020-04-11 priv qto às ativ e empreend de Landscape Management Arrangement recuperação/recomposição de áreas degradadas, silvicultura e soluções tecnol BPA SFB 1 BR-GIZ-76213-CS- CAPA / CPJ para promoção de uma melhor comunicacao e melhoria institucional das organizações Institutional Development Alternative (Compatibilização de / and Capacity Building for Posterior Procurement Open - National 0.00 Cancelado 2018-10-15 2018-11-05 2018-12-19 2019-01-16 2019-02-15 2019-03-22 2019-04-12 2020-04-11 informações sobre o Cerrado Landscape Management Arrangement entre o SFB (Inventário Florestal), INPE (Prodes), EMBRAPA (TerraClass), SENAR, MAPA e MMA) SFB 1 BR-GIZ-76266-CS- CAPA / Contratacao de pessoa juridica para Elaboracao e Institutional Development Alternative disponibilizacao na / and Capacity Building for Posterior Procurement Open - National 0.00 Cancelado 2018-10-15 2018-11-05 2018-12-19 2019-01-16 2019-02-15 2019-03-22 2019-04-12 2020-04-11 plataforma Saberes da Landscape Management Arrangement Floresta de 10 cursos com tematica relativa as acoes do projeto SFB 1 BR-GIZ-76237-CS- CAPA / Consultoria pessoa Institutional Development Alternative jurídica (OS) para mobilização / and Capacity Building for Posterior Procurement Open - National 0.00 Cancelado 2018-10-15 2018-11-05 2018-12-19 2019-01-16 2019-02-15 2019-03-22 2019-04-12 2020-04-11 e apoio à instalação e Landscape Management Arrangement fortalecimento de Comitês de Bacia Hidrográfica SFB 2 BR-GIZ-76243-CS- CAPA / Contratação de Pessoa Jurídica (OS) para instalar Mainstreaning Landscape Alternative viveiros permanentes e / Practices into Selected Posterior Procurement Open - National 0.00 Cancelado 2018-10-15 2018-11-05 2018-12-19 2019-01-16 2019-02-15 2019-03-22 2019-04-12 2020-04-11 temporarios, casa de Watersheds Arrangement sementes, produção e comercialização de sementes e mudas. SFB 2 BR-GIZ-76249-CS- CAPA / Contratação de pessoa jurídica para desenvolver metodologia de monitoramento de áreas Mainstreaning Landscape Alternative restauradas (fortalecer a / Practices into Selected Posterior Procurement Open - National 0.00 Cancelado 2018-10-15 2018-11-05 2018-12-19 2019-01-16 2019-02-15 2019-03-22 2019-04-12 2020-04-11 oferta de serviços de Watersheds Arrangement monitoramento) e aplicação por dois ciclos de monitoramento (T.0, T.1 e T.2). Page 6 SFB 1 BR-GIZ-76274-CS- CAPA / CI para a elaboração de método, treinamento e apoio à execução da Análise Institutional Development Alternative técnica sobre o CAR e PRAs na / and Capacity Building for Posterior Procurement Open - National 0.00 Cancelado 2018-10-15 2018-11-05 2018-12-19 2019-01-16 2019-02-15 2019-03-22 2019-04-12 2020-04-11 área de abrangência do Landscape Management Arrangement projeto no SICAR e elaboração de materiais específicos da área de abrangência do Projeto . SFB 1 BR-GIZ-76280-CS- CAPA / CI pra a sistematização de informações sobre a área selecionada, com a definição Institutional Development Alternative da área de abrangência do / and Capacity Building for Posterior Procurement Open - National 0.00 Cancelado 2018-10-15 2018-11-05 2018-12-19 2019-01-16 2019-02-15 2019-03-22 2019-04-12 2020-04-11 projeto, considerando Landscape Management Arrangement passivos florestais em APP, RL, áreas passíveis de restauração e análise multicritérios. SFB 2 BR-GIZ-76288-CS- CAPA / Consultoria Individual Mainstreaning Landscape Alternative para a definição da estrutura e / Practices into Selected Posterior Procurement Open - National 0.00 Cancelado 2018-10-15 2018-11-05 2018-12-19 2019-01-16 2019-02-15 2019-03-22 2019-04-12 2020-04-11 escopo do plano de ação nas Watersheds Arrangement 10 bacias selecionadas. SFB 2 BR-GIZ-76244-CS- CAPA / CI para apoiar os treinamento para funcionários públicos em legislação Mainstreaning Landscape Alternative ambiental, especialmente / Practices into Selected Posterior Procurement Open - National 0.00 Cancelado 2018-10-15 2018-11-05 2018-12-19 2019-01-16 2019-02-15 2019-03-22 2019-04-12 2020-04-11 Código Florestal e as relativas Watersheds Arrangement ao CAR, PRA e licenciamento ambiental, bem como sobre as etapas e procedimentos para realização de CAR e PRA INPE 1 BR-GIZ-76253-CS- CAPA / Contratação de 04 Institutional Development Alternative (quatro) consultorias / and Capacity Building for Posterior Procurement Open - National 0.00 Cancelado 2018-10-15 2018-11-05 2018-12-19 2019-01-16 2019-02-15 2019-03-22 2019-04-12 2020-04-11 individuais - Serviços de Landscape Management Arrangement Geoprocessamento (mapeamento orbital) INPE 1 BR-GIZ-76241-CS- CAPA / Contratação de Institutional Development Alternative Consultor individual - / and Capacity Building for Posterior Procurement Open - National 0.00 Cancelado 2018-10-15 2018-11-05 2018-12-19 2019-01-16 2019-02-15 2019-03-22 2019-04-12 2020-04-11 Assistente Geoprocessamento Landscape Management Arrangement júnior (análise da paisagem) INPE 1 BR-GIZ-76289-CS- CAPA / Contratação de Institutional Development Alternative Consultor individual - Serviços / and Capacity Building for Posterior Procurement Open - National 0.00 Cancelado 2018-10-15 2018-11-05 2018-12-19 2019-01-16 2019-02-15 2019-03-22 2019-04-12 2020-04-11 de Geoprocessamento (análise Landscape Management Arrangement da paisagem) INPE 3 BR-GIZ-76278-CS- CAPA / Contratação de Consultoria pessoa jurídica Project Management, Alternative para a difusão e comunicação / Monitoring, Evaluation and Posterior Procurement Open - National 0.00 Cancelado 2018-10-15 2018-11-05 2018-12-19 2019-01-16 2019-02-15 2019-03-22 2019-04-12 2020-04-11 dos resultados do projeto em Communication Arrangement eventos e reuniões nacionais ou internacionais técnicos, acadêmicos e políticos GIZ 3 BR-GIZ-76242-CS- Project Management, Alternative CAPA / Consultoria Individual / Monitoring, Evaluation and Posterior Procurement Open - National 0.00 Cancelado 2018-10-15 2018-11-05 2018-12-19 2019-01-16 2019-02-15 2019-03-22 2019-04-12 2020-04-11 para elaborar Relatório Final Communication Arrangement de Revisão de Meio Termo GIZ 3 BR-GIZ-76246-CS- CAPA / Consultorias para Project Management, Alternative Suporte Administrativo e de / Monitoring, Evaluation and Posterior Procurement Open - National 0.00 Cancelado 2018-10-15 2018-11-05 2018-12-19 2019-01-16 2019-02-15 2019-03-22 2019-04-12 2020-04-11 Aquisições ao Projeto (equipe Communication Arrangement base GIZ) GIZ 3 BR-GIZ-76247-CS- Project Management, Alternative CAPA / Consultorias para / Monitoring, Evaluation and Posterior Procurement Open - National 0.00 Cancelado 2019-01-15 2019-02-05 2019-03-21 2019-04-18 2019-05-18 2019-06-22 2019-07-13 2020-07-12 Suporte Técnico ao Projeto Communication Arrangement (equipe base GIZ) GIZ 3 BR-GIZ-76203-CS- Project Management, Alternative CAPA / Elaboração do Plano / Monitoring, Evaluation and Posterior Procurement Open - National 0.00 Cancelado 2018-10-15 2018-11-05 2018-12-19 2019-01-16 2019-02-15 2019-03-22 2019-04-12 2020-04-11 de comunicação do projeto - Communication Arrangement comuncação geral do Projeto GIZ BR-GIZ-109973-CS-CQS / Contratação de Consultoria pessoa jurídica para a difusão Project Management, Seleção Baseada e comunicação dos resultados TF / A8532 Monitoring, Evaluation and Posterior nas Qualificações Open - National 0.00 Cancelado 2019-12-02 2019-12-23 2020-02-05 2020-03-06 2020-04-10 2020-10-07 do projeto em eventos e Communication dos Consultores reuniões nacionais ou internacionais técnicos, acadêmicos e políticos SFB BR-GIZ-201637-CS-INDV / Contratação de consultoria pessoa jurídica para mapeamento da cobertura do uso do solo, hidrografia, Institutional Development Seleção Baseada Em fase de relevo e servidões TF / A8532 and Capacity Building for Posterior nas Qualificações Open - National 25,525.40 2020-11-04 2021-06-18 2020-11-25 2021-01-08 2021-09-14 2021-02-07 2021-09-17 2021-03-14 2021-09-10 Implementação administrativas das Bacias Landscape Management dos Consultores Hidrográficas, nos estados do Tocantins, Maranhão, Bahia, Minas Gerais, Goiás e Mato Grosso SFB BR-GIZ-223586-CS-CQS / Contratação de empresa para realização de retificação (e/ou atendimentos de notificações) dos imóveis Institutional Development Seleção Baseada na Em fase de rurais já cadastrados na Base TF / A8532 and Capacity Building for Posterior Open - National 169,149.12 2021-03-14 2021-03-17 2021-04-04 2021-05-18 2021-04-23 2021-06-15 2021-06-24 2021-07-15 2021-08-03 2021-08-19 2021-08-18 2021-09-23 2022-09-23 Qualidade e Custo Implementação do SICAR, bem como a Landscape Management inscrição de imóveis rurais que ainda não possuam o Cadastro Ambiental Rural (CAR) Page 7 INPE BR-GIZ-239970-CS- QCBS / Reformulação do Institutional Development Seleção Baseada Em fase de "layout" e codificação da nova TF / A8532 and Capacity Building for Posterior nas Qualificações Open - National 29,344.75 2021-07-25 2021-07-14 2021-08-15 2021-09-28 2021-08-27 2021-10-28 2021-09-10 2021-12-02 2022-05-31 Implementação interface do geoportal e do Landscape Management dos Consultores WebGIS TerraClass SFB BR-GIZ-201638-CS-INDV / Contratação de consultoria pessoa jurídica para mapeamento da cobertura do Institutional Development Seleção Baseada uso do solo, hidrografia, TF / A8532 and Capacity Building for Posterior nas Qualificações Open - National 0.00 Cancelado 2020-11-04 2020-12-17 2020-11-25 2021-01-08 2021-02-07 2021-03-14 2021-09-10 relevo e servidões Landscape Management dos Consultores administrativas da Bacia Hidrográfica 8652, no estado de Mato Grosso do Sul. SFB BR-GIZ-204513-CS-CQS / Contratação de pessoa jurídica para mapeamento de Institutional Development Seleção Baseada cobertura do solo, hidrografia, TF / A8532 and Capacity Building for Posterior nas Qualificações Open - National 0.00 Cancelado 2020-11-15 2020-12-17 2020-12-06 2021-01-19 2021-02-18 2021-03-25 2021-09-21 relevo e servidões Landscape Management dos Consultores administrativas das áreas de Cerrado nos estados do Maranhão e Piauí EMBRAPA BR-GIZ-242457-CS- CQS / Contratação de empresa na área de engenharia para elaboração Institutional Development Seleção Baseada Implementação de projeto básico e executivo TF / A8532 and Capacity Building for Posterior nas Qualificações Open - National 0.00 2021-10-04 2021-10-25 2021-12-08 2022-01-07 2022-02-11 2022-08-10 Pendente para as reformas do Landscape Management dos Consultores auditório, salas de aula, salas de video e viveiro da Embrapa Cerrados GIZ BR-GIZ-245677-CS-CQS / Contratação de consultoria Project Management, Seleção Baseada PJ para o desenvolvimento do Em fase de TF / A8532 Monitoring, Evaluation and Posterior nas Qualificações Open - National 0.00 2021-10-04 2021-08-12 2021-10-25 2021-12-08 2022-01-07 2022-02-11 2022-08-10 Painel Estratégico de Implementação Communication dos Consultores Monitoramento do Projeto FIP Paisagens Rurais INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Actual Amount Draft Negotiated Description Component Review Type Method Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. Approach (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INPE 1 BR-GIZ-76216-CS- CAPA / Contratação de 01 (uma) consultoria individual - Especialista em Geoprocessamento Pleno I Institutional Development (mapeamento orbital) - Pelas TF / A8532 and Capacity Building for Posterior Individual Open 107,512.82 Assinado 2019-04-22 2019-04-12 2019-06-10 2019-05-14 2019-07-01 2019-06-02 2019-08-05 2019-06-24 2020-02-01 regras da GIZ, trata-se de Landscape Management contrato CLT conforme acordado com o Banco Mundial na documentação do Projeto. INPE 1 BR-GIZ-76239-CS- CAPA / Contratação de 01 (uma) consultoria individual - Assistente em Geoprocessamento Júnior Institutional Development (mapeamento orbital) - Pelas TF / A8532 and Capacity Building for Posterior Individual Open 62,476.22 Rescindido 2019-04-22 2019-04-10 2019-06-10 2019-05-14 2019-07-01 2019-05-14 2019-08-05 2019-06-24 2020-02-01 regras da GIZ, trata-se de Landscape Management contrato CLT conforme acordado com o Banco Mundial na documentação do Projeto. GIZ 3 BR-GIZ-76281-CS- CAPA / Consultoria para Gerenciamento e Monitoramento Geral do Project Management, Projeto (equipe base GIZ) - TF / A8532 Monitoring, Evaluation and Posterior Individual Open 339,274.24 Assinado 2019-04-04 2019-09-01 2019-05-23 2018-12-05 2019-06-13 2019-01-02 2019-07-18 2019-01-10 2020-01-14 Pelas regras da GIZ, trata-se Communication de contrato CLT conforme acordado com o Banco Mundial na documentação do Projeto. INPE BR-GIZ-105361-CS- CAPA / Contratação de 01 (uma) consultoria individual - Especialista em Geoprocessamento Pleno I Institutional Development (mapeamento orbital) - Pelas TF / A8532 and Capacity Building for Posterior Individual Open 107,970.17 Assinado 2019-04-22 2019-04-22 2019-06-10 2019-06-09 2019-07-01 2019-06-09 2019-08-05 2019-06-24 2020-02-01 regras da GIZ, trata-se de Landscape Management contrato CLT conforme acordado com o Banco Mundial na documentação do Projeto. INPE BR-GIZ-105364-CS- CAPA / Contratação de 01 (uma) consultoria individual - Especialista em Geoprocessamento Pleno I Institutional Development (mapeamento orbital) - Pelas TF / A8532 and Capacity Building for Posterior Individual Open 108,502.36 Rescindido 2019-04-22 2019-04-18 2019-06-10 2019-06-05 2019-07-01 2019-06-09 2019-08-05 2019-06-24 2020-02-01 regras da GIZ, trata-se de Landscape Management contrato CLT conforme acordado com o Banco Mundial na documentação do Projeto. INPE BR-GIZ-105365-CS- CAPA / Contratação de 01 (uma) consultoria individual - Especialista em Geoprocessamento Pleno I Institutional Development (mapeamento orbital) - Pelas TF / A8532 and Capacity Building for Posterior Individual Open 107,970.17 Assinado 2019-04-22 2019-04-12 2019-06-10 2019-06-09 2019-07-01 2019-06-09 2019-08-05 2019-06-24 2020-02-01 regras da GIZ, trata-se de Landscape Management contrato CLT conforme acordado com o Banco Mundial na documentação do Projeto. Page 8 INPE BR-GIZ-105366-CS- CAPA / Contratação de 01 (uma) consultoria individual - Especialista em Geoprocessamento Pleno I Institutional Development (mapeamento orbital) - Pelas TF / A8532 and Capacity Building for Posterior Individual Open 107,970.17 Assinado 2019-04-30 2019-03-06 2019-06-18 2019-06-09 2019-07-09 2019-06-09 2019-08-13 2019-06-24 2020-02-09 regras da GIZ, trata-se de Landscape Management contrato CLT conforme acordado com o Banco Mundial na documentação do Projeto. INPE BR-GIZ-105367-CS- CAPA / Contratação de 01 (uma) consultoria individual - Especialista em Geoprocessamento Pleno I Institutional Development (mapeamento orbital) - Pelas TF / A8532 and Capacity Building for Posterior Individual Open 107,970.17 Rescindido 2019-04-22 2019-04-10 2019-06-10 2019-05-14 2019-07-01 2019-06-02 2019-08-05 2019-06-24 2020-02-01 regras da GIZ, trata-se de Landscape Management contrato CLT conforme acordado com o Banco Mundial na documentação do Projeto. INPE BR-GIZ-105369-CS- CAPA / Contratação de 01 (uma) consultoria individual - Assistente em Geoprocessamento Júnior Institutional Development (mapeamento orbital) - Pelas TF / A8532 and Capacity Building for Posterior Individual Open 62,476.22 Assinado 2019-04-22 2019-04-10 2019-06-10 2019-05-14 2019-07-01 2019-06-09 2019-08-05 2019-06-24 2020-02-01 regras da GIZ, trata-se de Landscape Management contrato CLT conforme acordado com o Banco Mundial na documentação do Projeto. EMBRAPA BR-GIZ-109805-CS- INDV / Contratação de Consultoria Individual para sistematização de informações sobre Mainstreaning Landscape recuperação de vegetação TF / A8532 Practices into Selected Posterior Individual Open 15,617.86 Concluído 2019-06-03 2019-04-22 2019-07-22 2019-07-29 2019-08-12 2019-05-02 2019-09-16 2019-05-06 2020-03-14 2019-11-26 nativa - Pelas regras da GIZ, Watersheds trata-se de contrato de consultoria conforme acordado com o Banco Mundial na documentação do Projeto EMBRAPA BR-GIZ-109831-CS- INDV / Contratação de Consultoria Individual para sistematização de informações sobre ILPF, BPA e Mainstreaning Landscape recuperação de áreas TF / A8532 Practices into Selected Posterior Individual Open 15,710.01 Concluído 2019-05-20 2019-05-08 2019-07-08 2019-06-28 2019-07-29 2019-09-03 2019-09-02 2019-07-05 2020-02-29 2020-09-15 produtivas degradadas - Pelas Watersheds regras da GIZ, trata-se de contrato CLT conforme acordado com o Banco Mundial na documentação do Projeto SFB BR-GIZ-109844-CS-INDV / Contratação de Consultira Individual para elaborar diagnóstico e caracterização por sensoriamento remoto Mainstreaning Landscape das 53 bacias hidrográficas e TF / A8532 Practices into Selected Posterior Individual Open 6,161.37 Concluído 2019-08-05 2019-04-25 2019-09-23 2019-05-02 2019-10-14 2019-05-06 2019-11-18 2019-05-06 2020-05-16 2020-01-01 o DF do Projeto Watersheds FIP/Paisagem.Pelas regras da GIZ, trata-se de contrato de consultoria conforme acordado com o BM SFB BR-GIZ-109845-CS-INDV / Contratação de Consultira Individual para elaborar diagnóstico socio economico ambiental das 53 bacias Mainstreaning Landscape hidrográficas e o DF do TF / A8532 Practices into Selected Posterior Individual Open 6,198.71 Concluído 2019-08-05 2019-04-11 2019-09-23 2019-07-05 2019-10-14 2019-05-02 2019-11-18 2019-05-02 2020-05-16 2020-01-01 Projeto FIP/Paisagem. - Pelas Watersheds regras da GIZ, trata-se de contrato de consultoria conforme acordado com o Banco Mundial INPE BR-GIZ-109862-CS- INDV / Contratação de Consultor individual - Assistente Geoprocessamento Institutional Development júnior (análise da paisagem) - TF / A8532 and Capacity Building for Posterior Individual Open 68,160.53 Assinado 2019-08-05 2020-09-28 2019-09-23 2020-11-27 2019-10-14 2020-12-02 2019-11-18 2021-01-18 2020-05-16 Pelas regras da GIZ, trata-se Landscape Management de contrato CLT conforme acordado com o Banco Mundial na documentação do Projeto. GIZ BR-GIZ-109975-CS-INDV Project Management, / Consultoria Individual para Implementação TF / A8532 Monitoring, Evaluation and Posterior Individual Open 0.00 2022-01-03 2022-02-21 2022-03-14 2022-04-18 2022-10-15 elaborar Relatório Final de Pendente Communication Revisão de Meio Termo GIZ BR-GIZ-109979-CS-INDV / Consultorias para Suporte Administrativo e de Aquisições ao Projeto (equipe Project Management, base GIZ) - Consultoria TF / A8532 Monitoring, Evaluation and Posterior Individual Open 149,828.12 Assinado 2019-04-10 2018-09-14 2019-05-29 2019-02-18 2019-06-19 2019-01-18 2019-07-24 2019-01-21 2020-01-20 Individual. Pelas regras da GIZ, Communication trata-se de contrato CLT conforme acordado com o Banco Mundial na documentação do Projeto. GIZ BR-GIZ-109980-CS-INDV / Consultorias para Suporte Técnico ao Projeto (equipe base GIZ) - Consultoria Project Management, Individual. Pelas regras da GIZ, TF / A8532 Monitoring, Evaluation and Posterior Individual Open 67,462.18 Assinado 2019-11-04 2020-07-23 2019-12-23 2020-09-17 2020-01-13 2020-09-17 2020-02-17 2020-10-13 2020-08-15 trata-se de contrato CLT Communication conforme acordado com o Banco Mundial na documentação do Projeto. Page 9 GIZ BR-GIZ-109986-CS-INDV Project Management, / Elaboração do Plano de TF / A8532 Monitoring, Evaluation and Posterior Individual Open 0.00 Cancelado 2019-08-05 2019-09-23 2019-10-14 2019-11-18 2020-05-16 comunicação do projeto - Communication comuncicação geral do Projeto SFB BR-GIZ-109990-CS-INDV / Cont de Cons de Pessoa Física para analisar as inform cartográficas de inscrições de Institutional Development imóveis rurais com até 4 TF / A8532 and Capacity Building for Posterior Individual Open 15,295.68 Assinado 2019-04-22 2019-05-19 2019-06-10 2019-05-15 2019-07-01 2019-06-06 2019-08-05 2019-05-23 2020-02-01 módulos fiscais no Cadastro Landscape Management Ambiental Rural do estado do Maranhão (sub lote 1, 2 e 3) para subsídio da qualificação da cobertura do uso do solo SFB BR-GIZ-109991-CS-INDV / Cont de Consultoria de Pessoa Física para analisar as informações cartográficas de Institutional Development inscrições de imóveis rurais TF / A8532 and Capacity Building for Posterior Individual Open 4,592.07 Concluído 2019-04-15 2019-05-03 2019-06-03 2019-05-15 2019-06-24 2019-05-15 2019-07-29 2019-05-22 2020-01-25 2020-06-08 com até 4 módulos fiscais no Landscape Management Cadastro Ambiental Rural do estado do Minas Gerais (sub- lote 1,2 e 3)o para subsídio da qualificação da cob do sol SFB BR-GIZ-109992-CS-INDV / Cont de Consultoria de Pessoa Física para analisar as informações cartográficas de Institutional Development inscrições de imóveis rurais TF / A8532 and Capacity Building for Posterior Individual Open 3,365.43 Concluído 2019-04-22 2019-05-02 2019-06-10 2019-05-15 2019-07-01 2019-05-20 2019-08-05 2019-05-20 2020-02-01 2020-06-08 com até 4 módulos fiscais no Landscape Management Cadastro Ambiental Rural do estado do Minas Gerais (sub- lote 4,5 e 6)o para subsídio da qualificação da cob do sol SFB BR-GIZ-109993-CS-INDV / Consultoria de Pessoa Física para analisar as informações documentais de inscrições de Institutional Development imóveis rurais com até 4 TF / A8532 and Capacity Building for Posterior Individual Open 14,413.97 Assinado 2019-04-22 2019-04-25 2019-06-10 2019-05-15 2019-07-01 2019-05-16 2019-08-05 2019-05-16 2020-02-01 módulos fiscais no Cadastro Landscape Management Ambiental Rural do estado do Maranhão (sub lote 1,2 e 3) para subsídio da qualificação da cobertura do uso do solo SFB BR-GIZ-109996-CS-INDV / Consultoria de Pessoa Física para analisar as informações documentais de inscrições de Institutional Development imóveis rurais com até 4 TF / A8532 and Capacity Building for Posterior Individual Open 4,751.27 Concluído 2019-04-22 2019-04-25 2019-06-10 2019-05-10 2019-07-01 2019-05-15 2019-08-05 2019-05-20 2020-02-01 2020-06-08 módulos fiscais no Cadastro Landscape Management Ambiental Rural do estado de Minas Gerais (sub lote 1 e 2) para subsídio da qualificação da cobertura do uso do sol SFB BR-GIZ-109997-CS-INDV / Consultoria de Pessoa Física para analisar as informações documentais de inscrições de Institutional Development imóveis rurais com até 4 TF / A8532 and Capacity Building for Posterior Individual Open 4,003.88 Concluído 2019-04-22 2019-04-25 2019-06-10 2019-05-10 2019-07-01 2019-05-20 2019-08-05 2019-05-20 2020-02-01 2020-06-08 módulos fiscais no Cadastro Landscape Management Ambiental Rural do estado de Minas Gerais (sub lote 3 e 4) para subsídio da qualificação da cobertura do uso do sol SFB BR-GIZ-109998-CS-INDV / Consultoria de Pessoa Física para analisar as informações documentais de inscrições de Institutional Development imóveis rurais com até 4 TF / A8532 and Capacity Building for Posterior Individual Open 4,009.84 Concluído 2019-04-22 2019-04-22 2019-06-10 2019-05-15 2019-07-01 2019-05-20 2019-08-05 2019-05-30 2020-02-01 2020-06-02 módulos fiscais no Cadastro Landscape Management Ambiental Rural do estado de Minas Gerais (sub lote 5 e 6) para subsídio da qualificação da cobertura do uso do sol SFB BR-GIZ-112004-CS-INDV / Cont de Consultoria de Pessoa Física para analisar as informações cartográficas de Institutional Development inscrições de imóveis rurais TF / A8532 and Capacity Building for Posterior Individual Open 2,024.44 Concluído 2019-05-29 2019-05-02 2019-07-17 2019-05-09 2019-08-07 2019-05-14 2019-09-11 2019-05-19 2020-03-09 2020-06-08 com até 4 módulos fiscais no Landscape Management Cadastro Ambiental Rural do estado do Minas Gerais (sub- lote 6)o para subsídio da qualificação da cob do sol EMBRAPA CERRADO BR-GIZ- 150287-CS-INDV / Contratação de assessor técnico para monitoramento Institutional Development nas áreas de referência do TF / A8532 and Capacity Building for Posterior Individual Open 50,523.58 Assinado 2019-12-16 2020-02-18 2020-02-03 2020-02-19 2020-02-24 2020-02-20 2020-03-30 2020-03-03 2020-09-26 Projeto Paisagens Rurais – Landscape Management Gestão Integrada da Paisagem, na Embrapa Cerrado e em outras Unidades de Referência Tecnológica definidas. SFB BR-GIZ-152976-CS-INDV / Contratação de Assessor(a) Técnico(a) para apoio à Institutional Development implementação da TF / A8532 and Capacity Building for Posterior Individual Open 54,122.00 Assinado 2020-01-12 2020-01-08 2020-03-01 2020-02-21 2020-03-22 2020-02-21 2020-04-26 2020-03-02 2020-10-23 Regularização Ambiental nas Landscape Management bacias prioritárias do projeto Paisagens Rurais SFB BR-GIZ-160378-CS-INDV / Elaborar o Plano de Institutional Development Continuidade de Negócio do TF / A8532 and Capacity Building for Posterior Individual Open 0.00 Cancelado 2020-02-21 2020-02-20 2020-04-10 2020-05-01 2020-06-05 2020-12-02 CAR, suas integrações e o Landscape Management SICAR. Page 10 SFB BR-GIZ-160383-CS-INDV / Contratar consultor para revisar a topologia, configuração e desenho da Institutional Development rede de dados atual do SICAR, TF / A8532 and Capacity Building for Posterior Individual Open 0.00 Cancelado 2020-02-21 2020-02-20 2020-04-10 2020-05-01 2020-06-05 2020-12-02 com o objetivo de ampliar, Landscape Management agilizar e maximizar o tráfego de dados internamente dentro da rede dados dos servidores. SFB BR-GIZ-160389-CS-INDV / Contratar consultor para Institutional Development redesenhar a arquitetura do TF / A8532 and Capacity Building for Posterior Individual Open 0.00 Cancelado 2020-02-21 2020-02-20 2020-04-10 2020-05-01 2020-06-05 2020-12-02 ambiente de hardware de Landscape Management servidores para o CAR SFB BR-GIZ-164470-CS-INDV / Consultoria para redesenhar todo ambiente de TI que Institutional Development sustenta todos os TF / A8532 and Capacity Building for Posterior Individual Open 17,130.78 Assinado 2020-03-15 2020-03-26 2020-05-03 2020-05-27 2020-05-24 2020-06-12 2020-06-28 2020-06-12 2020-12-25 componentes do SICAR Landscape Management através do Projeto Paisagens Rurais (FIP/Paisagem). EMBRAPA BR-GIZ-166991-CS- INDV / Contratação de Consultoria CLT para organizar e elaborar conteúdo técnico para cursos de Institutional Development capacitação de TF / A8532 and Capacity Building for Posterior Individual Open 59,650.48 Assinado 2020-03-31 2020-03-30 2020-05-19 2020-05-14 2020-06-09 2020-05-18 2020-07-14 2020-06-01 2021-01-10 multiplicadores sobre Landscape Management recuperação de áreas com vegetação nativa degradada em paisagem rural no Bioma Cerrado BR-GIZ-179870-CS-INDV SFB / Contratação de Assessor(a) Project Management, Técnico(a) para apoio à TF / A8532 Monitoring, Evaluation and Posterior Individual Open 44,613.36 Assinado 2020-06-14 2020-06-24 2020-08-02 2020-09-10 2020-08-23 2020-10-02 2020-09-27 2020-10-20 2021-03-26 implementação do Plano de Communication Comunicação do projeto Paisagens Rurais SFB BR-GIZ-181728-CS-INDV / Consultoria para realizar a organização e compilação das ações realizadas, resultados Institutional Development alcançados e impactos TF / A8532 and Capacity Building for Posterior Individual Open 21,463.72 Assinado 2020-06-28 2020-11-20 2020-08-16 2021-01-05 2020-09-06 2021-01-11 2020-10-11 2021-01-21 2021-04-09 observados na implementação Landscape Management do Plano ABC que podem ser estratégicos para o Projeto Paisagens Rurais (FIP/Paisagem). SFB BR-GIZ-182522-CS-INDV / Consultor 04 – Realizar o levantamento, análise e compilação dos resultados de execução de metas, das Institutional Development experiencias, perspectivas e TF / A8532 and Capacity Building for Posterior Individual Open 19,883.06 Assinado 2020-06-30 2020-07-08 2020-08-18 2020-09-15 2020-09-08 2020-10-02 2020-10-13 2020-10-13 2021-04-11 compromissos em nível Landscape Management estadual no âmbito do Plano ABC executadas pelos Grupos Gestores Estaduais na região Nordeste SFB BR-GIZ-183115-CS-INDV / Consultor 02 – Organizar e Institutional Development compilar as propostas para o TF / A8532 and Capacity Building for Posterior Individual Open 20,472.81 Assinado 2020-07-12 2020-12-08 2020-08-30 2021-01-29 2020-09-20 2021-02-04 2020-10-25 2021-02-15 2021-04-23 desenvolvimento e Landscape Management implementação do Plano ABC 2020-2030 SFB BR-GIZ-183116-CS-INDV / Consultor 03 – Realizar o levantamento, análise e Institutional Development compilação das experiências, TF / A8532 and Capacity Building for Posterior Individual Open 15,836.01 Assinado 2020-07-12 2020-07-16 2020-08-30 2020-09-15 2020-09-20 2020-09-17 2020-10-25 2020-10-01 2021-04-23 perspectivas e compromissos Landscape Management de instituições públicas e privadas parceiras na implementação do Plano ABC SFB BR-GIZ-183117-CS-INDV / Consultor 05 – Realizar o levantamento, análise e compilação dos resultados de execução de metas, das Institutional Development experiencias, perspectivas e TF / A8532 and Capacity Building for Posterior Individual Open 20,270.09 Assinado 2020-07-12 2020-07-08 2020-08-30 2020-09-17 2020-09-20 2020-09-21 2020-10-25 2020-10-09 2021-04-23 compromissos em nível Landscape Management estadual no âmbito do Plano ABC executadas pelos Grupos Gestores Estaduais nas regiões Norte e Cent SFB BR-GIZ-183119-CS-INDV / Consultor 06 – Realizar o levantamento, análise e compilação dos resultados de execução de metas, das Institutional Development experiencias, perspectivas e TF / A8532 and Capacity Building for Posterior Individual Open 14,589.57 Assinado 2020-07-12 2021-02-08 2020-08-30 2021-04-06 2020-09-20 2021-04-06 2020-10-25 2021-04-08 2021-04-23 compromissos em nível Landscape Management estadual no âmbito do ABC executadas pelos Grupos Gestores Estaduais nas regiões Sul e Sudeste EMBRAPA BR-GIZ-183568-CS- INDV / Contratação de Institutional Development Consultoria Pessoa Física para TF / A8532 and Capacity Building for Posterior Individual Open 0.00 Cancelado 2020-07-10 2020-07-10 2020-08-28 2020-09-18 2020-10-23 2021-04-21 elaborar o logotipo do Projeto Landscape Management Paisagens Rurais projeto Paisagens Rurais Page 11 SFB BR-GIZ-184435-CS-INDV / Técnico 3 - Contratação de Assessor(a) Técnico(a) para apoio na compilação de dados Institutional Development do CAR e em soluções de TF / A8532 and Capacity Building for Posterior Individual Open 67,462.18 Assinado 2020-07-17 2020-07-22 2020-09-04 2020-10-02 2020-09-25 2020-10-02 2020-10-30 2020-10-20 2021-04-28 geoprocessamento / Landscape Management sensoriamento remoto no âmbito do projeto Paisagens Rurais SFB BR-GIZ-184442-CS-INDV / Contratação de Assessor(a) Institutional Development Técnico(a) para apoio ao TF / A8532 and Capacity Building for Posterior Individual Open 72,080.70 Assinado 2020-07-17 2020-07-22 2020-09-04 2020-09-14 2020-09-25 2020-09-14 2020-10-30 2020-10-01 2021-04-28 desenvolvimento de soluções Landscape Management para Regularização Ambiental INPE BR-GIZ-137983-CS- INDV / Assistente Institutional Development Administrativo para apoiar as TF / A8532 and Capacity Building for Posterior Individual Open 0.00 Cancelado 2019-10-18 2019-12-06 2019-12-27 2020-01-31 2020-07-29 atividades relacionadas ao Landscape Management mapeamento do projeto INPE BR-GIZ-109857-CS- INDV / Contratação de consultoria individual - Serviços de Geoprocessamento Institutional Development (mapeamento orbital) - Pelas TF / A8532 and Capacity Building for Posterior Individual Open 0.00 Cancelado 2019-08-05 2019-09-23 2019-10-14 2019-11-18 2020-05-16 regras da GIZ, trata-se de Landscape Management contrato de consultoria conforme acordado com o Banco Mundial na documentação do Projeto. INPE BR-GIZ-109854-CS- INDV / Contratação Institutional Development consultoria individual - TF / A8532 and Capacity Building for Posterior Individual Open 0.00 Cancelado 2019-08-05 2019-09-23 2019-10-14 2019-11-18 2020-05-16 Serviços de Landscape Management Geoprocessamento (mapeamento orbital) INPE BR-GIZ-109859-CS- INDV / Contratação de consultoria individual - Serviços de Geoprocessamento Institutional Development (mapeamento orbital) - Pelas TF / A8532 and Capacity Building for Posterior Individual Open 0.00 Cancelado 2019-08-05 2019-09-23 2019-10-14 2019-11-18 2020-05-16 regras da GIZ, trata-se de Landscape Management contrato de consultoria conforme acordado com o Banco Mundial na documentação do Projeto. INPE BR-GIZ-109950-CS- INDV / Contratação de Consultor individual - Serviços de Geoprocessamento (análise Institutional Development da paisagem) - Pelas regras TF / A8532 and Capacity Building for Posterior Individual Open 0.00 Cancelado 2019-09-02 2019-10-21 2019-11-11 2019-12-16 2020-06-13 da GIZ, trata-se de contrato Landscape Management de consultoria conforme acordado com o Banco Mundial na documentação do Projeto INPE BR-GIZ-109860-CS- INDV / Contratação de consultoria individual - Serviços de Geoprocessamento Institutional Development (mapeamento orbital) - Pelas TF / A8532 and Capacity Building for Posterior Individual Open 0.00 Cancelado 2019-08-05 2019-09-23 2019-10-14 2019-11-18 2020-05-16 regras da GIZ, trata-se de Landscape Management contrato de consultoria conforme acordado com o Banco Mundial na documentação do Projeto. INPE BR-GIZ-196031-CS- INDV / Contratação de 01 (uma) consultoria individual - Assistente em Geoprocessamento Júnior Institutional Development (mapeamento orbital) - Pelas TF / A8532 and Capacity Building for Posterior Individual Open 36,584.88 Assinado 2020-09-28 2020-09-30 2020-11-16 2021-01-06 2020-12-07 2021-01-06 2021-01-11 2021-01-25 2021-07-10 regras da GIZ, trata-se de Landscape Management contrato CLT conforme acordado com o Banco Mundial na documentação do Projeto. INPE EMB BR-GIZ-198052-CS- INDV / Assessor (a) Técnico (a) / Analista Junior (a) de Institutional Development geoprocessamento para TF / A8532 and Capacity Building for Posterior Individual Open 36,584.88 Assinado 2020-10-13 2020-10-07 2020-12-01 2020-11-23 2020-12-22 2020-11-23 2021-01-26 2021-01-18 2021-07-25 atividades de mapeamento do Landscape Management projeto FIP Paisagem – “MAPEAMENTO TERRACLASS INPE EMBR BR-GIZ-198053- CS-INDV / Assessor (a) Técnico (a) / Analista Junior Institutional Development (a) de sistemas para atividades TF / A8532 and Capacity Building for Posterior Individual Open 0.00 Cancelado 2020-10-13 2021-02-24 2020-12-01 2020-12-22 2021-01-26 2021-07-25 de apoio ao mapeamento do Landscape Management projeto FIP Paisagem – “MAPEAMENTO TERRACLASS”. INPE BR-GIZ-213289-CS- INDV / Contratação de 01 (uma) consultoria individual - Especialista em Geoprocessamento Pleno I Institutional Development (mapeamento orbital) - Pelas TF / A8532 and Capacity Building for Posterior Individual Open 63,213.89 Assinado 2021-01-25 2021-01-12 2021-03-15 2021-03-01 2021-04-05 2021-03-03 2021-05-10 2021-04-05 2021-11-06 regras da GIZ, trata-se de Landscape Management contrato CLT conforme acordado com o Banco Mundial na documentação do Projeto. Page 12 SFB BR-GIZ-228499-CS-INDV / Contratação de Assessor/a Técnico/a para análise de CAR e desenvolvimento de soluções de Institutional Development geoprocessamento / TF / A8532 and Capacity Building for Posterior Individual Open 66,898.04 Assinado 2021-04-12 2021-04-13 2021-05-31 2021-06-22 2021-06-21 2021-06-22 2021-07-26 2021-07-05 2022-01-22 sensoriamento remoto - Landscape Management Pelas regras da GIZ, trata-se de contrato CLT conforme acordado com o Banco Mundial na documentação do Projeto. SFB BR-GIZ-228500-CS-INDV / Contratação de Assessor(a) Técnico(a) para análise de documentação de imóveis Institutional Development rurais inscritos e retificados TF / A8532 and Capacity Building for Posterior Individual Open 40,884.49 Assinado 2021-04-12 2021-04-13 2021-05-31 2021-06-11 2021-06-21 2021-06-17 2021-07-26 2021-07-05 2022-01-22 no CAR - Pelas regras da GIZ, Landscape Management trata-se de contrato CLT conforme acordado com o Banco Mundial na documentação do Projeto. GIZ 3.2 BR-GIZ-238979-CS- INDV / Contratação de consultor individual para Project Management, elaborar o Relatório de TF / A8532 Monitoring, Evaluation and Posterior Individual Open 17,699.17 Assinado 2021-06-14 2021-06-24 2021-08-02 2021-07-16 2021-08-23 2021-07-21 2021-09-27 2021-08-09 2022-03-26 Avaliação para a Revisão de Communication Meio Termo do Projeto FIP Paisagens Rurais SFB BR-GIZ-161952-CS-INDV Institutional Development / Retificação dos CARs de TF / A8532 and Capacity Building for Posterior Individual Open 0.00 Cancelado 2020-10-04 2020-11-22 2020-12-13 2021-01-17 2021-07-16 imóveis rurais contemplados Landscape Management pelo Projeto SFB BR-GIZ-161969-CS-INDV / Contratação de consultor individual para realizar oficinas participativas de Institutional Development elaboração e pactuação do TF / A8532 and Capacity Building for Posterior Individual Open 0.00 Cancelado 2020-06-01 2020-07-20 2020-08-10 2020-09-14 2021-03-13 plano, para o lançamento e a Landscape Management difusão do plano de ação de cada uma das bacias e mobilização dos Comitês de Bacias SFB BR-GIZ-161615-CS-INDV / Elaboracão de conteúdo para 4 cursos com temática relativa às ações do projeto para Institutional Development Implementação disponibilização na TF / A8532 and Capacity Building for Posterior Individual Open 0.00 2021-10-04 2021-11-22 2021-12-13 2022-01-17 2022-07-16 Pendente plataforma Saberes da Landscape Management Floresta (RAD, ISA, RPD, CapCAR Mod. Análise Dinamizada). SFB BR-GIZ-161951-CS-INDV / Desenvolvimento de metodologia de monitoramento de áreas Institutional Development restauradas (fortalecer a TF / A8532 and Capacity Building for Posterior Individual Open 0.00 Cancelado 2020-06-01 2020-07-20 2020-08-10 2020-09-14 2021-03-13 oferta de serviços de Landscape Management monitoramento) e aplicação por dois ciclos de monitoramento (T.0, T.1 e T.2). SFB BR-GIZ-110007-CS-INDV / Consultoria Individual para Produção de material informativo para divulgação das atuação do SFB incluindo Institutional Development Implementação o projeto FIP Paisagem - Pelas TF / A8532 and Capacity Building for Posterior Individual Open 0.00 2021-10-04 2021-11-22 2021-12-13 2022-01-17 2022-07-16 Pendente regras da GIZ, trata-se de Landscape Management contrato de consultoria conforme acordado com o Banco Mundial na documentação SFB BR-GIZ-110005-CS-INDV / Consultoria Individual para Produção de videos informativos para divulgação Institutional Development do SFB, incluindo o projeto FIP Implementação TF / A8532 and Capacity Building for Posterior Individual Open 0.00 2021-10-04 2021-11-22 2021-12-13 2022-01-17 2022-07-16 Paisagem - Pelas regras da Pendente Landscape Management GIZ, trata-se de contrato de consultoria conforme acordado com o Banco Mundial na documentação SFB BR-GIZ-161954-CS-INDV / Consultoria Individual para o Institutional Development levantamento, sistematização TF / A8532 and Capacity Building for Posterior Individual Open 0.00 Cancelado 2020-07-05 2020-08-23 2020-09-13 2020-10-18 2021-04-16 e divulgação de dados e Landscape Management informações (incluindo econômicos); SFB BR-GIZ-161618-CS-INDV Institutional Development / Apoio o fortalecimento de TF / A8532 and Capacity Building for Posterior Individual Open 0.00 Cancelado 2020-05-03 2020-06-21 2020-07-12 2020-08-16 2021-02-12 redes de sementes Landscape Management SFB BR-GIZ-161944-CS-INDV / Diagnósticos, mapeamento e elaboração de portifólio de divulgação da sistematização de experiências práticas de Institutional Development imóveis rurais públicos e TF / A8532 and Capacity Building for Posterior Individual Open 0.00 Cancelado 2020-05-03 2020-06-21 2020-07-12 2020-08-16 2021-02-12 privados quanto às atividades Landscape Management e empreendimentos de recuperação/recomposição de áreas degradadas, silvicultura, e solu SFB BR-GIZ-161936-CS-INDV Institutional Development / Monitoramento e avaliaçao Implementação TF / A8532 and Capacity Building for Posterior Individual Open 0.00 2021-10-04 2021-11-22 2021-12-13 2022-01-17 2022-07-16 das açoes de regularizaçao e Pendente Landscape Management recuperaçaoambiental Page 13 EMBRAPA BR-GIZ-161599-CS- INDV / Contratação de Consultoria Pessoa Física (analista) para coordenar a assistencia tecnica virtual no Mainstreaning Landscape monitoramento de indicadores TF / A8532 Practices into Selected Posterior Individual Open 0.00 Cancelado 2021-07-30 2021-09-17 2021-10-08 2021-11-12 2022-05-11 tecnicos e socioeconomicos Watersheds da recuperação das pastagens e de APP e de Reserva Legal das URTs e nas bacias hidrograficas. EMBRAPA BR-GIZ-161526-CS- INDV / Contratação consultor individual (Pessoa Física - analista) para realizar estudo prospectivo de análise Institutional Development Implementação socioeconômica da cadeia da TF / A8532 and Capacity Building for Posterior Individual Open 0.00 2021-10-04 2021-11-22 2021-12-13 2022-01-17 2022-07-16 Pendente restauração e recomposição Landscape Management da vegetação nativa em APP e ARL nas propriedades rurais e URTs do Distrito Federal e das bacia EMBRAPA BR-GIZ-161529-CS- INDV / Contratação consultor individual (Pessoa Física - analista) para caracterização e análise da estrutura e da Institutional Development Implementação dinâmica das unidades de TF / A8532 and Capacity Building for Posterior Individual Open 0.00 2021-10-04 2021-11-22 2021-12-13 2022-01-17 2022-07-16 Pendente paisagem por meio de Landscape Management levantamento de campo, processamento e análise de fotografias digitais verticais e panorâmicas em pro EMBRAPA BR-GIZ-161602-CS- INDV / Contratação de consultoria individual (Pessoa Física - analista) para coordenação do diagnostico, Institutional Development Implementação implantação e monitoramento TF / A8532 and Capacity Building for Posterior Individual Open 0.00 2021-10-04 2021-11-22 2021-12-13 2022-01-17 2022-07-16 Pendente das atividades de restauração Landscape Management de vegetação nativa em APP e Reserva Legal em propriedades rurais e nas URTs do Distrito Federal e EMBRAPA BR-GIZ-161542-CS- INDV / Contratação de analista (CLT) para realização do diagnostico, implantação e monitoramento de indicadores Institutional Development Implementação tecnicos e socioeconomicos TF / A8532 and Capacity Building for Posterior Individual Open 0.00 2021-10-04 2021-11-22 2021-12-13 2022-01-17 2022-07-16 Pendente de boas práticas e sistemas de Landscape Management produção agropecuária (recuperação das pastagens) nas propriedades rurais e URTs do DF e da EMBRAPA BR-GIZ-109803-CS- INDV / Contratação de analista (CLT) para o processamento e sistematização da informação Institutional Development tecnológica para a Implementação TF / A8532 and Capacity Building for Posterior Individual Open 0.00 2021-10-04 2021-11-22 2021-12-13 2022-01-17 2022-07-16 caracterização da estrutura e Pendente Landscape Management da dinâmica das unidades de paisagem com intervenções técnicas de boas práticas e sistemas de produção agropecuária (recupe EMBRAPA BR-GIZ-109839-CS- INDV / Contratação de Consultoria individual na área de engenharia para elaboração de projeto básico e Institutional Development executivo para as reformas TF / A8532 and Capacity Building for Posterior Individual Open 0.00 Cancelado 2021-04-29 2021-06-17 2021-07-08 2021-08-12 2022-02-08 do auditório, salas de aula, Landscape Management salas de video e viveiro da EMBRAPA Cerrados - Pelas regras da GIZ, trata-se de contrato de consultor SFB BR-GIZ-242063-CS-INDV / Contratação de consultoria individual para apoio no Institutional Development Implementação desenvolvimento e analise de TF / A8532 and Capacity Building for Posterior Individual Open 0.00 2021-10-04 2021-11-22 2021-12-13 2022-01-17 2022-07-16 Pendente documentos referentes a Landscape Management implementação e execução das ações do SFB no Projeto. SFB BR-GIZ-242068-CS-INDV / Contratação de Assessor/a Técnico/a Sênior para Institutional Development fortalecimento da agenda de Em fase de TF / A8532 and Capacity Building for Posterior Individual Open 0.00 2021-08-24 2021-08-30 2021-10-12 2021-11-02 2021-12-07 2022-06-05 regularização ambiental e Implementação Landscape Management articulação institucional junto a parceiros estratégicos do Projeto FIP Paisagens Rurais INPE BR-GIZ-254480-CS- INDV / Contratação de 01 (uma) consultoria individual - Especialista em Geoprocessamento Pleno I Institutional Development Implementação (mapeamento orbital) - Pelas TF / A8532 and Capacity Building for Posterior Individual Open 0.00 2021-09-21 2021-11-09 2021-11-30 2022-01-04 2022-07-03 Pendente regras da GIZ, trata-se de Landscape Management contrato CLT conforme acordado com o Banco Mundial na documentação do Projeto. Page 14