Sample Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan [This is the first procurement plan) 2. Date of General Procurement Notice: April 25, 2017 3. Period covered by this procurement plan: September 2016 to June 2017 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Procurement Method Prior Review Threshold Comments US$ 1. ICB and LIB (Goods) Above US$ 1,500,000 All 2. NCB (Goods) NA 3. ICB (Works) Above US$ 7 million All 4. NCB (Works) NA 5. ICB and LIB (Non-Consultant Services) Above US$ 1,500,000 All 6 NCB (Non-Consultant Services) NA [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: [CDD project implementation Manual to be issued by DRDIP PIU, MoANR for Bank approval) 4. Reference to (if any) Project Operational/Procurement Manual: DRDIP Procurement Manual to be issued by DRDIP PIU. 5. Any Other Special Procurement Arrangements: NA 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) [List the Packages which require Bank’s prior review first and then the other packages] July 9, 2010 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domest Review Comments No. Cost ic by Bank US$ Prefere (Prior / Post) million nce (yes/no) Summary of NA NA NA NA the ICB (Works) Summary of 6.69 4 No Prior the ICB (Goods) Summary of 3.8 9 No Post All the NCB (Works) Summary of 14.70 14 No Post All the NCB (Goods) Summary of NA NA NA NA the ICB (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Commentes 1. Competitive Methods (Firms) Above US$ 500,000 2. Single Source (Firms) All 3. Individual Above US$ 200,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: NA 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description of Estimated Packages Review Comments Assignment Cost by Bank US$ (Prior / million Post) Summary of 0.35 2 Prior number of contracts that July 9, 2010 will be let under QCBS Summary of 1.4 38 Post LCS/ IC number of contracts that will be let under other methods July 9, 2010 PROCUREMENT Africa : Development Response to Displacement Impacts Project in the HoA PLAN General Information Country: Africa Bank’s Approval Date of the Original Procurement Plan: 2017-08-10 2019-11-04 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P152822 GPN Date: Project Name: Development Response to Displacement Impacts Project in the HoA Loan / Credit No: IDA / 58210 Executing Agency(ies): Office of the Prime Minister WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UG-OPM-22288-CW-RFQ / Pending Project Management, and Single Stage - One Partitioning of offices at IDA / 58210 Post Request for Bids Limited 32,877.00 0.00 Implementati 2017-11-30 2017-12-05 2018-01-16 2018-02-15 2018-03-22 2018-09-18 Monitoring and Evaluation Envelope Kampala on GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UG-OPM-22297-GO-RFQ / Installation of Air Project Management, and Request for Single Stage - One IDA / 58210 Post Limited 19,178.00 12,369.46 Completed 2017-10-28 2017-12-23 2018-06-21 conditioners at the DRDIP Monitoring and Evaluation Quotations Envelope Kampala office UG-OPM-22304-GO-RFQ / Installation of Window Project Management, and Request for Single Stage - One IDA / 58210 Post Limited 2,740.00 2,567.46 Completed 2017-10-28 2017-12-23 2018-06-21 Blinds at the Kampala Monitoring and Evaluation Quotations Envelope offices UG-OPM-22312-GO-DIR / Pending Project Management, and Request for Single Stage - One Assorted office stationery IDA / 58210 Post Limited 19,178.00 0.00 Implementati 2017-11-05 2017-12-31 2018-06-29 Monitoring and Evaluation Quotations Envelope and other office consumables on UG-OPM-22310-GO-RFQ / Procurement of Assorted Office Furniture (1.No. Conference Table plus 26 Visitors Chairs, 13 No.Office Project Management, and Request for Single Stage - One Desks, 13 No. Office Chairs, IDA / 58210 Post Limited 73,973.00 33,021.06 Completed 2017-10-25 2017-12-20 2018-06-18 Monitoring and Evaluation Quotations Envelope 26 No. Visitors chairs, 2No Sofa Sets, 2No. Coffee set, 1No. Round Table, 1No. Reception/ Front Desk Unit, 1No. Paper trim UG-OPM-29346-GO-RFB / Procurement of Motorvehicles (Lot 1: 1 No Station Wagon Type A (Not exceeding Project Management, and Single Stage - One 3000cc), Station Wagon Type IDA / 58210 Prior Request for Bids Open - National 1,064,600.00 0.00 Canceled 2017-11-24 2017-11-29 2018-01-10 2018-02-09 2018-03-16 2018-09-12 Monitoring and Evaluation Envelope B (Not exceeding 2800cc), Lot 2: 15 No Double Cabin Pickups, Lot 3: 17 No Motorcycles) Page 1 UG-OPM-39369-GO-RFB / Procurement of Assorted Motor vehicles - 6 Double Project Management, and Single Stage - One IDA / 58210 Post Request for Bids Open - National 1,008,705.00 390,961.72 Completed 2018-02-02 2018-02-07 2018-03-21 2018-04-20 2018-05-25 2018-07-09 cabins, 1 station wagon and Monitoring and Evaluation Envelope 23 motorcycles for field operations UG-OPM-22084-GO-RFB / Procurement of ICT Hardware/ Equipment (31 Laptops, 3 Desktop Computers, 17 Small and Project Management, and Single Stage - One IDA / 58210 Post Request for Bids Open - National 170,693.00 161,492.06 Completed 2018-02-05 2018-02-10 2018-03-24 2018-04-23 2018-05-28 2018-11-24 Medium Duty Photocopiers, Monitoring and Evaluation Envelope 2 Printers, 15 Scanners, 1 Projector, 17 Internet Modems, 29 computer Tablets) UG-OPM-72397-GO-RFQ / Pending Project Management, and Request for Single Stage - One Purchase of 30 Electronic IDA / 58210 Post Limited 13,077.00 0.00 Implementati 2018-08-25 2018-10-20 2019-04-18 Monitoring and Evaluation Quotations Envelope Tablets on UG-OPM-81114-GO-RFB / Project Management, and Single Stage - One purchase of 8 Double Cabin IDA / 58210 Post Request for Bids Open - National 328,205.10 380,179.59 Signed 2019-01-14 2019-01-19 2019-03-02 2019-04-01 2019-05-06 2019-11-02 Monitoring and Evaluation Envelope Pickups UG-OPM-110980-GO-DIR / Under Project Management, and Single Stage - One Purchase of 23 Motor Cycles IDA / 58210 Post Request for Bids Open - National 84,736.84 96,899.98 Implementati 2019-05-06 2019-05-11 2019-06-22 2019-07-22 2019-08-26 2020-02-22 Monitoring and Evaluation Envelope for Project Operations on UG-OPM-120099-GO-RFQ / Purchase of 13 Multipurpose Project Management, and Request for Single Stage - One IDA / 58210 Post Limited 3,448.00 4,119.41 Signed 2019-07-05 2019-08-30 2020-02-26 Power Stabilizers for District Monitoring and Evaluation Quotations Envelope Photocopier Machines UG-OPM-124188-GO-RFQ / Pending Project Management, and Request for Single Stage - One Purchase of Assorted ICT IDA / 58210 Post Limited 92,308.00 0.00 Implementati 2019-08-30 2019-10-25 2020-04-22 Monitoring and Evaluation Quotations Envelope Equipment on UG-OPM-124418-GO-RFQ / Project Management, and Request for Single Stage - One Purchase of construction IDA / 58210 Post Limited 2,718.00 2,846.34 Signed 2019-08-10 2019-10-05 2020-04-02 Monitoring and Evaluation Quotations Envelope Safety Gear UG-OPM-124420-GO-RFQ / Pending Purchase of Material Testing Project Management, and Request for Single Stage - One IDA / 58210 Post Limited 10,102.00 0.00 Implementati 2019-08-24 2019-10-19 2020-04-16 Equipment for Project Monitoring and Evaluation Quotations Envelope on Operations UG-OPM-125409-GO-RFQ / Pending Project Management, and Request for Single Stage - One Purchase of 4 Motorcycles IDA / 58210 Post Limited 15,384.00 0.00 Implementati 2019-08-30 2019-10-25 2020-04-22 Monitoring and Evaluation Quotations Envelope for District Operations on UG-OPM-125412-GO-RFB / Pending Project Management, and Single Stage - One Purchase of 4 station wagon IDA / 58210 Post Request for Bids Open - National 272,547.00 0.00 Implementati 2019-08-26 2019-08-31 2019-10-12 2019-11-11 2019-12-16 2020-06-13 Monitoring and Evaluation Envelope Vehicles on UG-OPM-125414-GO-RFB / Pending Project Management, and Single Stage - One Purchase of 3 Double Cabin IDA / 58210 Post Request for Bids Open - National 163,461.00 0.00 Implementati 2019-08-30 2019-09-04 2019-10-16 2019-11-15 2019-12-20 2020-06-17 Monitoring and Evaluation Envelope Pickups on UG-OPM-125415-GO-RFQ / Regional Support for Pending Request for Single Stage - One purchase of Furniture for IDA / 58210 Coordination, Capacity and Post Limited 25,641.00 0.00 Implementati 2019-09-07 2019-11-02 2020-04-30 Quotations Envelope Districts Operations Knowledge on Page 2 UG-OPM-125420-GO-DIR / Purchase of Biometric Based Pending Project Management, and Tablets for the Management IDA / 58210 Post Direct Selection Direct 51,282.00 0.00 Implementati 2019-08-26 2019-08-31 2019-10-05 2020-04-02 Monitoring and Evaluation Information System and on Data Collection NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UG-OPM-22095-NC-DIR / Project Management, and LAN set up/ extension to IDA / 58210 Prior Direct Selection Direct 10,959.00 11,824.67 Signed 2017-08-21 2017-08-26 2017-09-30 2018-03-29 Monitoring and Evaluation the DRDIP Offices UG-OPM-22307-NC-DIR / Procurement of Additional Project Management, and Office Space for DRDIP IDA / 58210 Prior Direct Selection Direct 68,493.00 69,120.00 Completed 2017-08-14 2017-08-19 2017-09-23 2018-03-22 Monitoring and Evaluation TST at Ruth Towers (One years Contract) UG-OPM-22306-NC-RFQ / Project Management, and Request for Single Stage - One Office Branding for the IDA / 58210 Post Limited 548.00 1,316.80 Completed 2017-10-28 2017-12-23 2018-06-21 Monitoring and Evaluation Quotations Envelope Kampala Offices UG-OPM-22287-NC-DIR / Development of a Project Project Management, and IDA / 58210 Prior Direct Selection Direct 300,905.00 287,226.00 Signed 2017-12-08 2017-12-13 2018-01-17 2018-07-16 Management Information Monitoring and Evaluation System (MIS) UG-OPM-45668-NC-DIR / Purchase and Installation of Project Management, and IDA / 58210 Prior Direct Selection Direct 9,642.00 8,090.36 Completed 2018-02-05 2018-02-10 2018-03-17 2018-09-13 Wireless internet for DRDIP Monitoring and Evaluation Offices UG-OPM-73171-NC-RFQ / Project Management, and Request for Single Stage - One Development of a Website IDA / 58210 Post Limited 15,385.00 0.00 Canceled 2018-09-01 2018-10-27 2019-04-25 Monitoring and Evaluation Quotations Envelope for DRDIP UG-OPM-73186-NC-RFQ / Pending Project Management, and Request for Single Stage - One Office Branding for Kampala IDA / 58210 Post Limited 1,282.00 0.00 Implementati 2018-08-31 2018-10-26 2019-04-24 Monitoring and Evaluation Quotations Envelope Offices on UG-OPM-91818-NC-RFQ / Project Management, and Request for Single Stage - One Purchase of Printed IDA / 58210 Post Limited 12,279.00 12,501.94 Signed 2018-12-29 2019-02-23 2019-08-22 Monitoring and Evaluation Quotations Envelope Materials ( Assorted ) UG-OPM-91819-NC-RFQ / Project Management, and Request for Single Stage - One Purchase of T- Shirts and IDA / 58210 Post Limited 4,423.00 4,054.73 Completed 2018-12-29 2019-02-23 2019-08-22 Monitoring and Evaluation Quotations Envelope Caps UG-OPM-124185-NC-RFQ / Pending Project Management, and Request for Single Stage - One Development of DRDIP/OPM IDA / 58210 Post Limited 15,385.00 0.00 Implementati 2019-08-30 2019-10-25 2020-04-22 Monitoring and Evaluation Quotations Envelope Website on UG-OPM-125416-NC-RFQ / Pending upgrade of the Existing Project Management, and Request for Single Stage - One IDA / 58210 Post Limited 3,846.00 0.00 Implementati 2019-09-01 2019-10-27 2020-04-24 Local Area Network at Ruth Monitoring and Evaluation Quotations Envelope on Towers UG-OPM-125419-NC-RFQ / Pending Purchase and Installation of Project Management, and Request for Single Stage - One IDA / 58210 Post Limited 10,256.00 0.00 Implementati 2019-08-31 2019-10-26 2020-04-23 a CCTV Camera System at Monitoring and Evaluation Quotations Envelope on Ruth Towers Page 3 UG-OPM-22104-NC-RFQ / Project Management, and Request for Single Stage - One PABX Upgrade/ extension to IDA / 58210 Post Limited 13,699.00 0.00 Canceled 2017-10-28 2017-12-23 2018-06-21 Monitoring and Evaluation Quotations Envelope the refugees office UG-OPM-126639-NC-RFQ / Pending Project Management, and Request for Single Stage - One Wireless Internet for DRDIP IDA / 58210 Post Limited 9,642.00 0.00 Implementati 2019-08-30 2019-10-25 2020-04-22 Monitoring and Evaluation Quotations Envelope Offices (one Year Contract) on UG-OPM-143186-NC-RFQ / Pending Project Management, and Request for Single Stage - One Video Production services for IDA / 58210 Post Limited 2,261.00 0.00 Implementati 2019-11-09 2020-01-04 2020-07-02 Monitoring and Evaluation Quotations Envelope DRDIP Commissioning on UG-OPM-143324-NC-RFQ / Pending Project Management, and Request for Single Stage - One Purchase of Car Tracking IDA / 58210 Post Limited 2,564.00 0.00 Implementati 2019-11-09 2020-01-04 2020-07-02 Monitoring and Evaluation Quotations Envelope devices for Project Vehicles on CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Individual UG-OPM-22326-CS-INDV / Project Management, and IDA / 58210 Post Consultant Open 76,010.88 93,857.95 Signed 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 M & E Officer Monitoring and Evaluation Selection Individual UG-OPM-22332-CS-INDV / Project Management, and Pending IDA / 58210 Post Consultant Open 98,367.12 0.00 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 Project Engineer Monitoring and Evaluation Implementation Selection Individual UG-OPM-22344-CS-INDV / Project Management, and Under IDA / 58210 Post Consultant Open 76,010.88 0.00 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 Livelihood Officer Monitoring and Evaluation Implementation Selection Individual UG-OPM-22345-CS-INDV / Project Management, and IDA / 58210 Post Consultant Open 76,010.88 93,857.95 Signed 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 Environment Officer Monitoring and Evaluation Selection Individual UG-OPM-22347-CS-INDV / Project Management, and IDA / 58210 Post Consultant Open 76,010.88 93,857.95 Signed 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 Social Safeguards Officer Monitoring and Evaluation Selection Individual UG-OPM-22349-CS-INDV / Project Management, and IDA / 58210 Post Consultant Open 43,651.20 0.00 Canceled 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 Communication Assistant Monitoring and Evaluation Selection Individual UG-OPM-22352-CS-INDV / Project Management, and Pending IDA / 58210 Post Consultant Open 43,651.20 0.00 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 Administrative Assistant Monitoring and Evaluation Implementation Selection UG-OPM-22355-CS-INDV / Individual Project Management, and Engineering Assistant 1 IDA / 58210 Post Consultant Open 43,651.20 53,958.09 Signed 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 Monitoring and Evaluation (Kampala Office) Selection Page 4 UG-OPM-22357-CS-INDV / Individual Project Management, and Engineering Assistant 2 IDA / 58210 Post Consultant Open 43,651.20 53,900.33 Signed 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 Monitoring and Evaluation (Kampala Office) Selection UG-OPM-22360-CS-INDV / Individual Project Management, and Social Safeguards Assistant IDA / 58210 Post Consultant Open 43,651.20 0.00 Canceled 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 Monitoring and Evaluation 1 Selection UG-OPM-22361-CS-INDV / Individual Project Management, and Social Safeguards Assistant IDA / 58210 Post Consultant Open 43,651.20 0.00 Canceled 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 Monitoring and Evaluation 2 Selection Individual UG-OPM-22362-CS-INDV / Project Management, and IDA / 58210 Post Consultant Open 43,651.20 53,900.33 Signed 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 Accounts Assistant Monitoring and Evaluation Selection Individual UG-OPM-22363-CS-INDV / Project Management, and IDA / 58210 Post Consultant Open 43,651.20 0.00 Canceled 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 Executive Assistant Monitoring and Evaluation Selection UG-OPM-22367-CS-INDV / Individual Project Management, and District Engineering IDA / 58210 Post Consultant Open 13,150.56 16,238.40 Signed 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 Monitoring and Evaluation Assistant 1 Selection UG-OPM-22368-CS-INDV / Individual Project Management, and District Engineering IDA / 58210 Post Consultant Open 13,150.56 16,238.40 Signed 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 Monitoring and Evaluation Assistant 2 Selection UG-OPM-22369-CS-INDV / Individual Project Management, and District Engineering IDA / 58210 Post Consultant Open 13,150.56 16,238.40 Signed 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 Monitoring and Evaluation Assistant 3 Selection UG-OPM-22372-CS-INDV / Individual Project Management, and District Engineering IDA / 58210 Post Consultant Open 13,150.56 16,238.40 Signed 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 Monitoring and Evaluation Assistant 4 Selection UG-OPM-22373-CS-INDV / Individual Project Management, and District Engineering IDA / 58210 Post Consultant Open 13,150.56 16,238.40 Signed 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 Monitoring and Evaluation Assistant 5 Selection UG-OPM-22374-CS-INDV / Individual Project Management, and District Engineering IDA / 58210 Post Consultant Open 13,150.56 16,238.40 Signed 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 Monitoring and Evaluation Assistant 6 Selection UG-OPM-22377-CS-INDV / Individual Project Management, and District Engineering IDA / 58210 Post Consultant Open 13,150.56 16,238.40 Signed 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 Monitoring and Evaluation Assistant 7 Selection UG-OPM-22379-CS-INDV / Individual Project Management, and District Engineering IDA / 58210 Post Consultant Open 13,150.56 16,238.40 Signed 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 Monitoring and Evaluation Assistant 8 Selection UG-OPM-22382-CS-INDV / Individual Project Management, and District Engineering IDA / 58210 Post Consultant Open 13,150.56 16,238.40 Signed 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 Monitoring and Evaluation Assistant 9 Selection UG-OPM-22384-CS-INDV / Individual Project Management, and District Engineering IDA / 58210 Post Consultant Open 13,150.56 16,238.40 Signed 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 Monitoring and Evaluation Assistant 10 Selection UG-OPM-22387-CS-INDV / Individual Project Management, and District Engineering IDA / 58210 Post Consultant Open 13,150.56 16,357.80 Signed 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 Monitoring and Evaluation Assistant 11 Selection Page 5 Individual UG-OPM-22505-CS-INDV / Project Management, and Pending IDA / 58210 Post Consultant Open 11,835.60 0.00 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 Office Attendant 1 Monitoring and Evaluation Implementation Selection Individual UG-OPM-22509-CS-INDV / Project Management, and Pending IDA / 58210 Post Consultant Open 11,835.60 0.00 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 Office Attendant 2 Monitoring and Evaluation Implementation Selection Individual UG-OPM-22515-CS-INDV / Project Management, and Pending IDA / 58210 Post Consultant Open 9,863.01 0.00 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 Driver 1 Monitoring and Evaluation Implementation Selection Individual UG-OPM-22517-CS-INDV / Project Management, and Pending IDA / 58210 Post Consultant Open 9,863.01 0.00 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 Driver 2 Monitoring and Evaluation Implementation Selection Individual UG-OPM-22519-CS-INDV / Project Management, and Pending IDA / 58210 Post Consultant Open 9,863.01 0.00 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 Driver 3 Monitoring and Evaluation Implementation Selection Individual UG-OPM-22524-CS-INDV / Project Management, and Pending IDA / 58210 Post Consultant Open 9,863.01 0.00 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 Driver 4 Monitoring and Evaluation Implementation Selection Individual UG-OPM-22527-CS-INDV / Project Management, and Pending IDA / 58210 Post Consultant Open 9,863.01 0.00 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 Driver 5 Monitoring and Evaluation Implementation Selection UG-OPM-22316-CS-CDS / Project Management, and IDA / 58210 Prior Direct Selection Direct 120,723.12 0.00 Under Review 2017-10-02 2017-10-12 2017-12-16 2018-06-14 Project Manager - DRDIP Monitoring and Evaluation UG-OPM-30462-CS-CDS / Procurement of Consulting services for Updating of the Environmental and Social Project Management, and Under Management Framework and IDA / 58210 Prior Direct Selection Direct 41,551.00 0.00 2017-10-05 2017-10-09 2017-10-27 2017-11-24 Monitoring and Evaluation Implementation Resettlement Policy Framework for the Development Response to Displacement Impact Project. UG-OPM-22353-CS-CDS / Project Management, and Procurement Assistant IDA / 58210 Prior Direct Selection Direct 43,651.20 0.00 Canceled 2017-08-18 2017-08-28 2017-11-01 2018-04-30 Monitoring and Evaluation Officer Individual UG-OPM-22343-CS-CDS / Project Management, and Pending IDA / 58210 Post Consultant Limited 76,010.88 0.00 2017-10-20 2017-10-25 2017-11-15 2017-12-20 2018-06-18 Project Accountant Monitoring and Evaluation Implementation Selection Individual UG-OPM-22350-CS-CDS / Project Management, and IDA / 58210 Post Consultant Limited 43,651.20 0.00 Canceled 2017-10-27 2017-11-01 2017-11-22 2017-12-27 2018-06-25 ICT Assistant Officer Monitoring and Evaluation Selection UG-OPM-52236-CS-INDV / Individual Project Management, and Consulting Services for IDA / 58210 Post Consultant Open 76,010.00 0.00 Canceled 2018-03-05 2018-04-23 2018-05-14 2018-06-18 2018-12-15 Monitoring and Evaluation Communications Officer Selection UG-OPM-52238-CS-INDV / Individual Project Management, and Consultant services for ICT IDA / 58210 Post Consultant Open 76,010.00 93,857.95 Signed 2018-03-05 2018-04-23 2018-05-14 2018-06-18 2018-12-15 Monitoring and Evaluation Officer Selection UG-OPM-61708-CS-INDV / Individual Project Management, and Consulting Services for a IDA / 58210 Post Consultant Limited 76,010.00 93,982.80 Under Review 2018-05-22 2018-05-27 2018-06-17 2018-07-22 2019-01-18 Monitoring and Evaluation Procurement Officer Selection Page 6 UG-OPM-22319-CS-CDS / Project Management, and IDA / 58210 Prior Direct Selection Direct 164,383.56 0.00 Canceled 2017-08-18 2017-08-28 2017-11-01 2018-04-30 Baseline survey Monitoring and Evaluation UG-OPM-22349-CS-INDV-2 / Individual Individual consulting services Project Management, and IDA / 58210 Post Consultant Open 43,651.20 0.00 Canceled 2019-08-26 2019-10-14 2019-11-04 2019-12-09 2020-06-06 for a communication Monitoring and Evaluation Selection Assistant Individual UG-OPM-143192-CS-INDV / Project Management, and Pending IDA / 58210 Post Consultant Limited 76,010.00 0.00 2019-11-04 2019-11-09 2019-11-30 2020-01-04 2020-07-02 Communications officer Monitoring and Evaluation Implementation Selection Individual UG-OPM-143193-CS-INDV / Project Management, and Pending IDA / 58210 Post Consultant Limited 43,651.20 0.00 2019-11-04 2019-11-09 2019-11-30 2020-01-04 2020-07-02 Communications Assistant Monitoring and Evaluation Implementation Selection Page 7