Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan: March 21, 2017 2. Date of General Procurement Notice: July 15, 2014 3. Period covered by this procurement plan: March 2017 to Feb 2018 II. Goods, Works, Consultant and Non-Consulting Services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Type of Procurement Prior Review Comments Threshold (PRT) US$ (Millions) 1. Works (Including turnkey, supply & 5 High risk installation of plant and equipment and PPP) 2. (Goods; Information Technology & 1.5 High risk Non-Consulting Services) 3. Consultant Services (Firms) 0.5 High risk 4. Consultant Services (Individual 0.2 High risk Consultants) 2. Prequalification. NA 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: NA 4. Reference to (if any) Project Operational/Procurement Manual: Available in Project files 5. Any Other Special Procurement Arrangements: NA 6. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 7. All TORs for the procurement of consultants services irrespective of the estimated cost of the assignment shall be reviewed and cleared by the TTL 8. Operating expenditures are neither subject to the Procurement and Consultant Guidelines nor prior or post reviews. Operating expenditures are normally verified by TTLs and FM specialists and obtained using the Borrower’s national procurement and administrative procedures. March 21, 2017 9. Renewal or extension of individual consultant’s contracts hired for technical assistance and which are intended for a long-term period but signed for an initial period shorter than the duration of the project, and that have been prior reviewed, do not require procurement clearance if there is no substantial change in the terms and conditions of the contract. March 21, 2017 PROCUREMENT Eastern Africa : RI-Regional Pastoral Livelihoods Resilience Project PLAN General Information Country: Eastern Africa Bank’s Approval Date of the Original Procurement Plan: 2018-01-18 2021-09-30 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P129408 GPN Date: Project Name: RI-Regional Pastoral Livelihoods Resilience Project Loan / Credit No: IDA / 55450, IDA / Q8400 Oromia - Regional Pastoral Livelihoods Resilience Project Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned ET-OROMIA-RPLRP-41119- Natural Resources Request for Single Stage - One 2018-07- CW-RFQ / Construction of IDA / 55450 Post Limited 186,000.00 76,543.03 Completed 2018-01-06 2018-12-23 2018-03-26 2019-03-07 Management Quotations Envelope 24 pond (50,000m3) ET-OROMIA-RPLRP-41121- CW-RFB / Construction of 6 Natural Resources Single Stage - One 2018-08- IDA / 55450 Post Request for Bids Open - National 652,800.00 410,231.88 Completed 2018-02-05 2017-09-20 2018-02-10 2018-03-12 2017-10-30 2018-04-11 2018-01-18 2018-05-16 2018-02-07 Community water pans Management Envelope 14 (30,000m3 each) ET-OROMIA-RPLRP-41131- Natural Resources Request for Single Stage - One 2018-08- CW-RFQ / Construction of IDA / 55450 Post Limited 15,513.00 0.00 Canceled 2018-02-10 2018-04-07 Management Quotations Envelope 05 Sand dams in Dilo Woreda ET-OROMIA-RPLRP-41159- CW-RFQ / Construction of Natural Resources Request for Single Stage - One 2018-05- fences and gates for IDA / 55450 Post Limited 37,333.00 4,310.49 Completed 2018-01-20 2018-05-16 2018-03-17 2018-06-29 Management Quotations Envelope 16 rehabilitated 4 water schemes in Dire Woreda ET-OROMIA-RPLRP-41192- CW-RFB / Construction of 3 Natural Resources Single Stage - One 1,967,642.5 2018-12- fodder banks (on 100 ha land) IDA / 55450 Post Request for Bids Open - National 480,000.00 Signed 2018-03-26 2019-03-19 2018-03-31 2018-04-30 2019-04-17 2018-05-30 2019-05-10 2018-07-04 2019-06-21 Management Envelope 7 31 in Taltale,Dilo and Yabelo Woredas ET-OROMIA-RPLRP-41124- CW-RFQ / Rehabilitation of Natural Resources Request for Single Stage - One 2018-08- IDA / 55450 Post Open - National 175,000.00 96,823.68 Completed 2018-02-18 2018-04-27 2019-03-07 existing water supply Management Quotations Envelope 25 structures in Dilo woreda ET-OROMIA-RPLRP-41197- CW-RFB / Construction of two Primary Markets and one secondary market Lot 1: Priymary market in Single Stage - One 2018-10- IDA / 55450 Market Access and Trade Post Request for Bids Open - National 300,000.00 337,472.42 Completed 2018-03-12 2018-05-04 2018-03-17 2018-04-16 2018-06-04 2018-05-16 2018-07-06 2018-06-20 2018-08-03 Taltale woreda Envelope 18 Lot 2: primary market in Dilo woreda lot 3 Secondary market in Miyo Woreda ET-OROMIA-RPLRP-41163- CW-RFQ / Construction of Natural Resources Request for Single Stage - One 2018-06- fences and gates for IDA / 55450 Post Open - National 102,667.00 11,278.76 Completed 2018-02-05 2018-04-14 2018-06-30 Management Quotations Envelope 13 rehabilitated 11 water schemes in Miyo Woreda ET-OROMIA-RPLRP-41184- CW-RFQ / Establishment of nursery sites Natural Resources Request for Single Stage - One 2018-09- IDA / Q8400 Post Open - National 90,000.00 71,099.21 Completed 2018-03-20 2018-06-19 2020-06-24 Lot 1: In Miyo Woeda Management Quotations Envelope 17 Lot 2: In Dillo Woreda Lot 3: In Taltale Woreda's ET-OROMIA-RPLRP-41204- CW-RFQ / Maintenance of the Existing One Secondary markets in Dire woreda Request for Single Stage - One 2018-08- Maintenance of existing IDA / 55450 Market Access and Trade Post Open - National 20,000.00 71,160.59 Completed 2018-02-25 2018-05-20 2019-05-02 Quotations Envelope 18 livestock market centers refers to refurbishing of the failed and un-functional market infrastructures. i ET-OROMIA-RPLRP-82440- CW-RFB / Rehabilitation of Single Stage - One 2020-01- IDA / 55450 Market Access and Trade Post Request for Bids Open - National 250,000.00 81,617.17 Completed 2019-03-01 2019-01-15 2019-03-13 2019-04-12 2019-02-13 2019-05-27 2019-04-04 2019-09-26 2019-05-03 Market Center ( Dire Megado Envelope 24 and Moyale) ET-OROMIA-RPLRP-82446- Natural Resources Single Stage - One 2019-10- CW-RFB / Rehabilitation of IDA / 55450 Post Request for Bids Open - National 231,481.00 126,170.40 Completed 2019-03-04 2018-12-06 2019-03-09 2019-04-08 2019-02-04 2019-05-08 2019-02-13 2019-06-12 2019-05-13 Management Envelope 10 Existing two Boreholes ET-OROMIA-RPLRP-82436- CW-RFB / Construction of two Single Stage - One 2019-10- new primer market IDA / 55450 Market Access and Trade Post Request for Bids Open - National 444,000.00 150,773.94 Completed 2019-01-31 2019-01-15 2019-02-08 2019-03-11 2019-02-13 2019-04-05 2019-04-04 2019-05-04 2019-05-07 Envelope 01 Construction at Moyale and Dillo Districts ET-OROMIA-RPLRP-120292- Natural Resources Single Stage - One 2019-12- CW-RFB / Construction of IDA / 55450 Post Request for Bids Open - National 1,000,000.00 695,076.02 Completed 2019-07-15 2019-09-20 2019-07-21 2019-10-02 2019-08-11 2019-10-15 2019-08-26 2019-11-15 2019-09-12 2019-12-23 Management Envelope 11 Ponds With Treatment system ET-OROMIA-RPLRP-120293- Natural Resources Single Stage - One 2019-12- CW-RFB / Construction of IDA / 55450 Post Request for Bids Open - National 862,068.00 0.00 Canceled 2019-07-15 2019-07-20 2019-08-11 2019-08-26 2019-09-19 Management Envelope 18 Case Landed Sand Dams ET-OROMIA-RPLRP-120296- Natural Resources Single Stage - One 2019-11- CW-RFB / Rehabilitation of IDA / 55450 Post Request for Bids Open - National 830,000.00 515,855.54 Completed 2019-07-15 2019-09-20 2019-07-22 2019-08-12 2019-10-15 2019-08-27 2019-11-15 2019-09-12 2020-02-21 Management Envelope 11 Existing 4 Boreholes Page 1 ET-OROMIA-RPLRP-122247- CW-RFB / Construction of Single Stage - One 2019-12- New primary livestock market IDA / 55450 Market Access and Trade Post Request for Bids Open - National 356,428.00 90,548.47 Completed 2019-07-16 2019-09-06 2019-07-21 2019-08-12 2019-09-27 2019-08-22 2019-04-02 2019-09-03 2019-04-16 Envelope 02 ( Yabelo Woreda Surupha Kebele) ET-OROMIA-RPLRP-120295- Natural Resources 2019-10- CW-RFB / Rehabilitation of IDA / 55450 Post Force Account Direct 21,285.00 0.00 Canceled 2019-07-31 2019-08-05 2019-08-22 Management 21 exciting 20 hand pumps ET-OROMIA-RPLRP-195715- CW-RFQ / Construction of Roofing metal steel structure Natural Resources Request for Single Stage - One 2021-03- IDA / 55450 Post Limited 140,100.00 0.00 Canceled 2020-10-11 2020-11-24 parts and Finishing works for Management Quotations Envelope 24 Taltale woreda Mermero site Fodder Bank consultation ET-OROMIA-RPLRP-246683- Request for Bids - Under CW-RFB / Construction of Natural Resources Single Stage - One Small Works SPD 2021-12- IDA / 55450 Post Request for Bids Open - National 483,590.00 0.00 Implementat 2021-08-13 2021-09-07 2021-08-18 2021-09-08 2021-09-28 2021-09-20 2021-10-04 Bore hole distribution systems Management Envelope (1 envelope 03 ion at Miyo Woreda Meti Site. process) ET-OROMIA-RPLRP-247271- Request for Bids - Under CW-RFB / Construction of Natural Resources Single Stage - One Small Works SPD 2021-12- IDA / 55450 Post Request for Bids Open - National 314,340.00 0.00 Implementat 2021-08-10 2021-09-07 2021-08-16 2021-09-06 2021-09-28 2021-09-20 2021-10-04 Borehole Distribution system Management Envelope (1 envelope 03 ion at Dillo Woreda Omore Site. process) ET-OROMIA-RPLRP-247272- Request for Bids - CW-RFB / Construction of Under Natural Resources Single Stage - One Small Works SPD 2021-12- Borehole Distribution system IDA / 55450 Post Request for Bids Open - National 241,800.00 0.00 Implementat 2021-08-16 2021-09-07 2021-08-21 2021-09-13 2021-09-28 2021-09-23 2021-10-07 Management Envelope (1 envelope 06 at Dire Woreda Fuloromso ion process) Site. ET-OROMIA-RPLRP-249113- Request for Bids - CW-RFB / Construction of Pending Natural Resources Single Stage - One Small Works SPD 2021-12- Store for Fodder Development IDA / 55450 Post Request for Bids Open - National 207,317.00 0.00 Implementat 2021-08-30 2021-09-04 2021-09-24 2021-10-01 2021-10-13 Management Envelope (1 envelope 13 /Forage Storage/ at Yabelo ion process) woreda galchet Site GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-OROMIA-RPLRP-41166- GO-RFQ / Procurement of Hand Tools & Sign Boards for Natural Resources Request for Single Stage - One IDA / 55450 Post Limited 13,670.00 3,625.40 Completed 2018-01-27 2018-07-25 2018-03-24 2019-07-31 2018-04-23 2019-07-31 Range land rehabilitation - Management Quotations Envelope biological and physical conversations ET-OROMIA-RPLRP-41175- GO-RFQ / Procurement of Natural Resources Request for Single Stage - One IDA / 55450 Post Limited 54,700.00 19,559.56 Completed 2018-01-20 2018-03-15 2018-03-17 2018-04-02 2018-05-01 2018-04-04 Forage seeds ( 15 Quntal) and Management Quotations Envelope Distribution to the project site ET-OROMIA-RPLRP-41262- GO-RFQ / Procurement of Request for Single Stage - One IDA / 55450 Livelihood Support Post Limited 11,260.00 8,505.14 Completed 2018-01-06 2018-03-08 2018-03-03 2018-05-08 2018-04-17 2018-07-02 Veterinary Equipment and Quotations Envelope Drugs ET-OROMIA-RPLRP-41265- Natural Resources Request for Single Stage - One GO-RFQ / Procurement of GPS IDA / 55450 Post Limited 2,000.00 1,032.73 Completed 2018-01-20 2018-06-28 2018-03-17 2018-07-02 2018-04-16 2018-07-04 Management Quotations Envelope 62S antenna and Dumpy level ET-OROMIA-RPLRP-41248- GO-RFQ / Procurement of IT Equipment ( LCD Projector, Project Management and Request for Single Stage - One Photo Copy Machine, Printer, IDA / 55450 Post Limited 18,355.00 1,149.18 Completed 2018-01-02 2018-06-22 2018-02-27 2018-07-02 2018-04-13 2018-07-04 Institutional Support Quotations Envelope Lap Top computers and color printer for RPCU,MST and Woredas ) by RPCU ET-OROMIA-RPLRP-45525- GO-RFQ / Procurement of Project Management and Request for Single Stage - One IDA / 55450 Post Limited 6,000.00 2,966.51 Completed 2018-02-20 2018-06-20 2018-04-17 2018-06-29 2018-05-08 2018-07-02 Generator for Dilo and Taltale Institutional Support Quotations Envelope Woreda's by RPCU ET-OROMIA-RPLRP-45528- GO-RFQ / procurement of Project Management and Request for Single Stage - One IDA / 55450 Post Limited 2,077.00 490.99 Completed 2018-02-20 2018-06-20 2018-04-17 2018-07-02 2018-05-07 2018-07-06 Furniture( Shelf) for Woreda Institutional Support Quotations Envelope ,Zone & RPCU ) ET-OROMIA-RPLRP-45530- GO-RFQ / procurement of Project Management and Request for Single Stage - One IDA / 55450 Post Limited 23,355.00 266.85 Completed 2018-02-03 2018-01-17 2018-03-31 2018-02-06 2018-04-10 2018-02-06 Tyre and Tube for RPCU and Institutional Support Quotations Envelope MST's ET-OROMIA-RPLRP-82451- Natural Resources Request for Single Stage - One GO-RFB / Procurement of IDA / 55450 Post Limited 88,000.00 71,524.32 Completed 2018-11-25 2019-02-07 2019-02-13 2019-04-09 2019-04-14 2019-05-29 Management Quotations Envelope Tractor ET-OROMIA-RPLRP-82455- GO-RFQ / Procurement of Natural Resources Request for Single Stage - One IDA / 55450 Post Limited 29,629.00 28,907.43 Completed 2018-12-10 2019-02-07 2019-02-11 2019-04-09 2019-03-28 2019-05-29 Baler Machine for Livestock Management Quotations Envelope Forage Production ET-OROMIA-RPLRP-82460- GO-RFQ / Procurement of Natural Resources Request for Single Stage - One IDA / 55450 Post Limited 29,629.00 0.00 Canceled 2018-12-05 2019-01-30 2019-05-30 baler machine for Forage Management Quotations Envelope production ET-OROMIA-RPLRP-82463- Natural Resources Request for Single Stage - One GO-RFQ / Procurement of IDA / 55450 Post Limited 10,000.00 0.00 Canceled 2018-11-26 2019-01-21 2019-02-20 Management Quotations Envelope water pump Page 2 ET-OROMIA-RPLRP-82492- GO-RFQ / Procurement of Natural Resources Request for Single Stage - One Hand tools for nursery site IDA / 55450 Post Limited 74,960.00 11,883.28 Completed 2018-12-10 2018-06-26 2019-01-21 2019-08-26 2019-02-05 2019-08-31 Management Quotations Envelope establishment and Bush Clearing ET-OROMIA-RPLRP-82512- Natural Resources Request for Single Stage - One GO-RFQ / Procurement of IDA / 55450 Post Limited 20,000.00 12,406.67 Completed 2019-01-21 2018-03-05 2019-03-04 2019-03-05 2019-03-19 2019-03-14 Management Quotations Envelope forage seeds ET-OROMIA-RPLRP-82538- GO-RFQ / Procurement of Request for Single Stage - One IDA / 55450 Market Access and Trade Post Limited 27,777.00 0.00 Canceled 2018-12-17 2019-01-28 2019-02-27 Equipment for Regional Quotations Envelope Veterinary laboratory. ET-OROMIA-RPLRP-83058- GO-RFQ / Procurement of Request for Single Stage - One IDA / 55450 Livelihood Support Post Limited 72,000.00 0.00 Canceled 2019-01-02 2019-02-11 2019-03-13 Equipment for Regional Quotations Envelope animal Breeding Centers ET-OROMIA-RPLRP-83061- GO-RFQ / Procurement of IT Project Management and Request for Single Stage - One IDA / 55450 Post Limited 10,370.00 335.31 Completed 2018-12-23 2018-07-22 2019-02-04 2018-07-02 2019-03-06 2018-07-05 Equipment for regional and Institutional Support Quotations Envelope Worda's ET-OROMIA-RPLRP-83065- Project Management and Request for Single Stage - One GO-RFQ / Procurement of IDA / 55450 Post Limited 4,148.00 5,081.24 Completed 2019-02-17 2019-04-23 2019-04-01 2019-05-10 2019-04-16 2019-05-23 Institutional Support Quotations Envelope office Stationery ET-OROMIA-RPLRP-83068- Project Management and Request for Single Stage - One GO-RFQ / Procurement of IDA / 55450 Post Limited 22,000.00 17,385.80 Completed 2018-11-26 2018-12-12 2019-01-07 2018-12-20 2019-01-22 2018-12-25 Institutional Support Quotations Envelope TYRE and Tube ET-OROMIA-RPLRP-83072- GO-RFQ / Procurement of Project Management and Request for Single Stage - One IDA / 55450 Post Limited 2,000.00 1,803.26 Completed 2018-11-19 2019-02-02 2018-12-31 2019-02-22 2019-01-30 2019-03-12 Uniform cloth for Janitor and Institutional Support Quotations Envelope Drivers ET-OROMIA-RPLRP-83075- GO-RFQ / Procurement of Natural Resources Request for Single Stage - One IDA / 55450 Post Limited 13,259.00 9,513.69 Completed 2018-12-17 2018-06-20 2019-01-28 2019-02-06 2019-02-12 2019-02-13 safety kit for Bush clearing an Management Quotations Envelope Nursery site ET-OROMIA-RPLRP-86378- Natural Resources Request for Single Stage - One GO-RFQ / Procurement of IDA / 55450 Post Limited 57,000.00 30,361.48 Completed 2018-11-27 2019-02-12 2019-01-23 2019-04-09 2019-03-09 2019-05-29 Management Quotations Envelope Mower Machine ET-OROMIA-RPLRP-86379- Natural Resources Request for Single Stage - One GO-RFQ / Procurement of IDA / 55450 Post Limited 35,000.00 9,065.41 Terminated 2018-11-27 2019-02-11 2019-01-22 2019-04-09 2019-03-08 Management Quotations Envelope Mower Machine ET-OROMIA-RPLRP-86382- Natural Resources Request for Single Stage - One GO-RFQ / Procurement of IDA / 55450 Post Limited 29,500.00 0.00 Canceled 2018-11-27 2019-01-22 2019-03-08 Management Quotations Envelope Tailer Machine ET-OROMIA-RPLRP-83057- GO-RFQ / Procurement of IDA / 55450 Livelihood Support Post Direct Selection Direct 88,234.00 66,531.42 Completed 2018-12-28 2018-12-11 2019-01-02 2019-06-01 2019-01-26 2020-09-03 2019-02-25 2020-09-03 Animal Grant ET-OROMIA-RPLRP-121955- GO-RFQ / Procurement of Natural Resources Request for Single Stage - One IDA / 55450 Post Limited 3,600.00 0.00 Canceled 2019-07-29 2019-08-18 2019-08-21 signboards for Constructed Management Quotations Envelope Projects ET-OROMIA-RPLRP-161007- Project Management and Request for Single Stage - One GO-RFQ / Procurement of IDA / 55450 Post Limited 6,000.00 455.39 Completed 2020-06-26 2020-06-23 2020-07-10 2020-06-24 2020-07-15 2020-07-07 Institutional Support Quotations Envelope office Stationeries ET-OROMIA-RPLRP-180966- Project Management and Request for Single Stage - One GO-RFQ / Procurement of IDA / 55450 Post Limited 23,437.00 9,048.55 Completed 2020-06-26 2020-08-11 2020-07-08 2020-10-13 2020-07-13 2020-10-19 Institutional Support Quotations Envelope Tyre and Tube ET-OROMIA-RPLRP-180974- GO-RFQ / Procurement of Project Management and Request for Single Stage - One IDA / 55450 Post Limited 3,000.00 1,320.23 Completed 2020-06-26 2020-06-22 2020-07-05 2020-06-30 2020-07-19 2020-07-07 Uniform For Drivers and Institutional Support Quotations Envelope Janitors ET-OROMIA-RPLRP-82877- GO-RFB / Procurement Single Stage - One Veterinary health equipment IDA / 55450 Livelihood Support Post Request for Bids Open - National 133,333.00 0.00 Canceled 2019-01-21 2019-01-28 2019-02-27 2019-03-29 2019-04-22 2019-07-21 Envelope fo 6 woreda health post and clinic ET-OROMIA-RPLRP-124166- GO-RFQ / Procurement of Natural Resources Request for Single Stage - One Pipes and Pumps for IDA / 55450 Post Limited 95,715.00 0.00 Canceled 2019-08-04 2019-08-28 2019-10-12 Management Quotations Envelope rehabilitation of 20 Hand Pumps ET-OROMIA-RPLRP-164010- GO-RFQ / procurement of Natural Resources Request for Single Stage - One IDA / 55450 Post Limited 46,875.00 0.00 Canceled 2020-07-07 2020-08-07 2020-09-21 Pump for Borhole Management Quotations Envelope Rehabilitations ET-OROMIA-RPLRP-121939- GO-RFQ / Procurement of Natural Resources Request for Single Stage - One IDA / 55450 Post Limited 100,000.00 0.00 Canceled 2019-07-24 2019-10-01 2019-08-26 2019-09-25 Tractor for Fodder Bank Management Quotations Envelope Development ET-OROMIA-RPLRP-121941- Natural Resources Request for Single Stage - One GO-RFQ / Procurement of IDA / 55450 Post Limited 25,000.00 0.00 Canceled 2019-07-24 2019-10-01 2019-08-26 2019-09-25 Management Quotations Envelope Disc Harrow ET-OROMIA-RPLRP-121946- Natural Resources Request for Single Stage - One GO-RFQ / Procurement of IDA / 55450 Post Limited 29,500.00 0.00 Canceled 2019-07-24 2019-10-01 2019-08-26 2019-09-25 Management Quotations Envelope Baler Machine Page 3 ET-OROMIA-RPLRP-121940- Natural Resources Request for Single Stage - One GO-RFQ / Procurement of IDA / 55450 Post Limited 17,857.00 0.00 Canceled 2019-07-24 2019-10-01 2019-08-26 2019-09-25 Management Quotations Envelope Disc P lough ET-OROMIA-RPLRP-121945- Natural Resources Request for Single Stage - One GO-RFQ / Procurement of IDA / 55450 Post Limited 29,629.00 0.00 Canceled 2019-07-24 2019-08-26 2019-09-25 Management Quotations Envelope trailers Machine ET-OROMIA-RPLRP-121942- Natural Resources Request for Single Stage - One GO-RFQ / Procurement of IDA / 55450 Post Limited 25,500.00 0.00 Canceled 2019-07-24 2019-08-26 2019-09-25 Management Quotations Envelope Mower Machine ET-OROMIA-RPLRP-41210- GO-RFQ / Procurement of Request for Single Stage - One IDA / 55450 Livelihood Support Post Limited 6,400.00 0.00 Canceled 2018-01-20 2018-03-17 2018-04-16 Equipment for CAHWs Quotations Envelope (through PPP) ET-OROMIA-RPLRP-83054- Request for Single Stage - One GO-RFQ / Procurement of IDA / 55450 Livelihood Support Post Limited 7,000.00 0.00 Canceled 2018-11-05 2018-12-13 2019-01-14 Quotations Envelope Equipment For CAHWs ET-OROMIA-RPLRP-121951- GO-RFQ / Procurement of Natural Resources Request for Single Stage - One IDA / 55450 Post Limited 9,000.00 0.00 Canceled 2019-08-20 2019-09-16 2019-09-23 safety kits for Range land and Management Quotations Envelope Fodder Bank Development ET-OROMIA-RPLRP-121949- Natural Resources Request for Single Stage - One GO-RFQ / Procurement of 500 IDA / 55450 Post Limited 5,000.00 0.00 Canceled 2019-08-17 2019-09-13 2019-09-23 Management Quotations Envelope kg forage seeds ET-OROMIA-RPLRP-41219- GO-DIR / Provide Startup animal( Grant) /Procurement of animals / The animals will Request for Single Stage - One IDA / 55450 Livelihood Support Post Limited 28,800.00 0.00 Canceled 2018-03-19 2018-05-14 2018-06-28 be procured from different Quotations Envelope supplies in local markets based on the need of the community. ET-OROMIA-RPLRP-160998- GO-RFQ / Procurement of Generetor to Borehole water Natural Resources Request for Single Stage - One IDA / 55450 Post Limited 59,507.00 0.00 Canceled 2020-07-06 2020-08-10 2020-09-24 Distribution for errgantion ( Management Quotations Envelope Fodder Bank Development ) at Hara wayu Site ET-OROMIA-RPLRP-82857- Project Management and Request for Single Stage - One GO-RFQ / Procurement of IDA / 55450 Post Limited 2,000.00 0.00 Canceled 2019-01-22 2019-03-03 2019-03-18 Institutional Support Quotations Envelope Office furniture for RPCU ET-OROMIA-RPLRP-246686- Under Project Management and Request for Single Stage - One GO-RFQ / Procurement of IDA / 55450 Post Limited 1,125.00 0.00 Implementati 2021-09-06 2021-09-27 2021-10-04 Institutional Support Quotations Envelope Store Shelf on ET-OROMIA-RPLRP-246688- GO-RFB / Procurement of two Pending Natural Resources Single Stage - One Diesel Generator 100KVA IDA / 55450 Post Request for Bids Open - National 97,560.00 0.00 Implementati 2021-08-30 2021-09-04 2021-09-24 2021-09-29 2021-10-08 2021-10-25 Management Envelope Each for Fodder development on of Range lands ET-OROMIA-RPLRP-246691- GO-RFQ / Procurement of 4 Pending inch and 16 pin HDPE Pipes Natural Resources Request for Single Stage - One IDA / 55450 Post Limited 75,000.00 0.00 Implementati 2021-09-04 2021-09-29 2021-10-29 to Upgrade Harawayu Bore Management Quotations Envelope on hole Water Distributions system. ET-OROMIA-RPLRP-246692- Project Management and Request for Single Stage - One GO-RFQ / Procurement of Car IDA / 55450 Post Limited 14,375.00 9,122.05 Completed 2021-08-20 2021-09-09 2021-09-02 2021-09-14 2021-09-09 2021-09-16 Institutional Support Quotations Envelope Tyre ET-OROMIA-RPLRP-246696- Natural Resources Request for Single Stage - One GO-RFQ / Procurement of IDA / 55450 Post Limited 6,890.00 8,232.66 Completed 2021-08-21 2021-09-09 2021-09-08 2021-09-14 2021-09-23 2021-09-20 Management Quotations Envelope Forage Seeds ET-OROMIA-RPLRP-246697- Pending Project Management and Request for Single Stage - One GO-RFQ / Procurement of IDA / 55450 Post Limited 4,800.00 0.00 Implementati 2021-08-30 2021-09-15 2021-09-30 Institutional Support Quotations Envelope office Stationery on ET-OROMIA-RPLRP-246698- Pending GO-RFQ / Procurement of Natural Resources Request for Single Stage - One IDA / 55450 Post Limited 6,030.00 0.00 Implementati 2021-09-04 2021-09-17 2021-10-01 Safety kits for Rangeland Management Quotations Envelope on development site ET-OROMIA-RPLRP-248585- GO-RFQ / Procurement of Under Natural Resources Request for Single Stage - One hand tools for Fodder Bank IDA / 55450 Post Limited 5,100.00 0.00 Implementati 2021-09-06 2021-10-08 2021-10-22 Management Quotations Envelope Development and Nursery on sits. ET-OROMIA-RPLRP-249087- GO-RFQ / Procurement of Pending Natural Resources Request for Single Stage - One Plastic ropes/Stings for Baler IDA / 55450 Post Limited 11,600.00 0.00 Implementati 2021-09-08 2021-09-27 2021-10-11 Management Quotations Envelope Machine to bale harvested on fodder or forage ET-OROMIA-RPLRP-249101- GO-RFQ / Procurement of Eco Under Natural Resources Request for Single Stage - One green liquids fertilizer IDA / 55450 Post Limited 7,317.00 0.00 Implementati 2021-09-20 2021-10-08 2021-10-24 Management Quotations Envelope application for Fodder bank on development. ET-OROMIA-RPLRP-249102- Pending GO-RFQ / Procurement of Natural Resources Request for Single Stage - One IDA / 55450 Post Limited 2,000.00 0.00 Implementati 2021-10-05 2021-10-27 2021-11-19 uniform for Drivers and Management Quotations Envelope on Jointers Page 4 ET-OROMIA-RPLRP-249012- GO-RFQ / Procurement of Pending Natural Resources Request for Single Stage - One Tyre and Tube for IDA / 55450 Post Limited 24,199.65 0.00 Implementati 2021-09-19 2021-10-04 2021-10-18 Management Quotations Envelope Agricultural Machineries to on Fodder Development NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-OROMIA-RPLRP-83081- Natural Resources Request for Single Stage - One NC-RFQ / Rant of Baler IDA / 55450 Post Limited 13,259.00 0.00 Canceled 2018-12-17 2019-01-28 2019-02-27 Management Quotations Envelope Machine CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 5