PROCUREMENT PLAN (Textual Part) Project information: Country: Bolivia Project name: Bolivia Climate Resilience - Integrated Basin Management - PPCRII P-number: P129640 Project Implementation Agencies: Unidad Coordinadora del Proyecto UCP – PPCR Fondo Nacional de Inversión Productiva y Social - FPS Date of the Procurement Plan: May 21, 2018 Period covered by this Procurement Plan: June 30, 2020 PROCUREMENT Bolivia : Bolivia Climate Resilience - Integrated Basin Management PLAN General Information Country: Bolivia Bank’s Approval Date of the Original Procurement Plan: 2018-05-30 2020-11-23 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P129640 GPN Date: Project Name: Bolivia Climate Resilience - Integrated Basin Management Loan / Credit No: TF / 16083, TF / 18119 Ministry of Environment and Water Executing Agency(ies): WORKS Activity Reference No. / Procurement Estimated Actual Draft Pre- Draft Bidding Bid Evaluation Report Loan / Credit Market Procurement Prequalificatio High SEA/SH Process Prequalification Specific Procurement Bidding Documents Proposal Submission Contract Description Component Review Type Method Document Amount Amount qualification Document / and Signed Contract No. Approach Process n (Y/N) Risk Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Completion Type (US$) (US$) Documents Justification Recommendation for Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PlannedAwardActual Planned Actual Planned GOODS Activity Reference No. / Draft Pre- Draft Bidding Bid Evaluation Report Loan / Credit Market Procurement Prequalificatio Estimated Actual Process Prequalification Specific Procurement Bidding Documents Proposal Submission Description Component Review Type Method qualification Document / and Signed Contract Contract Completion No. Approach Process n (Y/N) Amount (US$) Amount (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Documents Justification Recommendation for Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PlannedAwardActual Planned Actual Planned Actual GO-PPCR-RFB-003 / Adquisicion de Centros de B. Strengthening capacity for Solicitud de Single Stage - One 2018-09- 2018-09- 2018-10- 2018-11- 2018-12- 2019-03- Procesamiento de Datos y TF / 16083 adaptation to climate change Posterior Open - National 57,380.00 0.00 Cancelado ofertas Envelope 24 29 29 08 13 13 Sistemas de Alerta Temprana in the Rio Grande River Basin para Inundaciones y Sequias GO-PPCR-RFQ-004 / A. Strengthening national Adquisicion de Vehiculo de Solicitud de Single Stage - One 2018-02- 2018-04- 2018-06- TF / 16083 capacity for climate change Posterior Open - National 45,000.00 0.00 Cancelado Doble Traccion para la UCP - cotizaciones Envelope 23 10 09 adaptation PPCR GO-PPCR-RFQ-012 / Adquisicion de Equipos de Computacion para el B. Strengthening capacity for Solicitud de Single Stage - One 2018-06- 2018-07- 2018-09- Fortalecimiento del SENAMHI TF / 16083 adaptation to climate change Posterior Open - National 30,000.00 18,668.60 En ejecución cotizaciones Envelope 09 20 03 en Apoyo a las Redes de in the Rio Grande River Basin Observacion en las Cuencas piloto PPCR C. Design and BS-CC-C2-D-3-1 / implementation of Adquisicion de 3 Vehículos - Solicitud de Single Stage - One 2017-10- 2017-08- 2017-11- 2017-12- 2017-10- 2017-12- 2017-10- 2018-01- 2017-10- 2018-04- TF / 18119 subprojects that improve Posterior Open - National 120,000.00 65,873.23 Firmado SDC ofertas Envelope 27 30 01 01 02 11 10 15 27 15 climate resilience in the Rio 2 Mizque y 1 Rocha Grande River Basin C. Design and BS-CC-C2-D-3-6A / implementation of Adquisicion de Equipos de Solicitud de Single Stage - One Ejecución 2017-10- 2017-12- 2018-02- TF / 18119 subprojects that improve Posterior Open - National 25,583.00 0.00 Computacion, Comunicación cotizaciones Envelope pendiente 23 03 01 climate resilience in the Rio y otros equipos Grande River Basin BS-CC-C2-D-3-6B / C. Design and Adquisicion de Equipos de implementation of Solicitud de Single Stage - One Ejecución 2017-12- 2018-01- 2018-02- Computacion, Comunicación TF / 18119 subprojects that improve Posterior Open - National 5,612.00 0.00 cotizaciones Envelope pendiente 24 28 12 y otros equipos (Segunda climate resilience in the Rio Convocatoria) Grande River Basin C. Design and BS-CC-C2-D-3-7 / implementation of Solicitud de Single Stage - One Ejecución 2018-07- 2018-08- 2018-09- Adquisicion de 2 Plotters y 1 TF / 18119 subprojects that improve Posterior Open - National 30,612.00 0.00 cotizaciones Envelope pendiente 03 13 27 Servidor climate resilience in the Rio Grande River Basin BS-CC-C2-D-3-8 / C. Design and Adquisicion de muebles de implementation of Solicitud de Single Stage - One 2018-07- 2018-08- 2018-12- 2018-10- oficina 3 escritorios, 2 sillas TF / 18119 subprojects that improve Posterior Open - National 4,898.00 2,274.11 Firmado cotizaciones Envelope 03 13 26 12 giratorias, 5 estantes, 1 mesa climate resilience in the Rio de reuniones y 12 sillas Grande River Basin BS-CC-C2-D-3-9 / Adquisicion de Equipos de C. Design and Computacion y otros 2 implementation of Solicitud de Single Stage - One 2018-07- 2018-08- 2018-12- 2018-10- Computadoras, 2 Impresoras TF / 18119 subprojects that improve Posterior Open - National 18,950.00 18,635.83 Firmado cotizaciones Envelope 03 13 27 12 a color, 1 Fotocopiadora climate resilience in the Rio multifuncional, 2 impresoras Grande River Basin laser a b/n y 4 escaners C. Design and BS-CC-C2-D-3-10 / implementation of Solicitud de Single Stage - One Ejecución 2018-10- 2018-11- 2019-02- Adquisicion de 3 TF / 18119 subprojects that improve Posterior Open - National 5,542.00 0.00 cotizaciones Envelope pendiente 15 25 23 distanciometros laser climate resilience in the Rio Grande River Basin C. Design and implementation of BS-CC-C2-D-3-11B / Solicitud de Single Stage - One Ejecución 2018-07- 2018-08- 2018-08- 2018-09- 2018-10- 2019-01- TF / 18119 subprojects that improve Posterior Open - National 48,000.00 0.00 Adquisicion de 1 Dron ofertas Envelope pendiente 27 01 31 10 15 13 climate resilience in the Rio Grande River Basin GO-PPCR-RFB-001 / Equipamiento del Centro de A. Strengthening national Solicitud de Single Stage - One 2018-06- 2018-06- 2018-07- 2018-08- 2018-09- 2018-12- Desarrollo de herramientas TF / 16083 capacity for climate change Posterior Open - National 223,000.00 0.00 Cancelado ofertas Envelope 18 23 23 02 06 05 para Monitoreo y adaptation planificacion de Recursos Hidricos 001 -2015 / Licencias A. Strengthening national Adquisición Ejecución 2015-12- 2015-12- 2016-01- 2016-02- ArcGIS for Desktop Basic + TF / 16083 capacity for climate change Posterior Direct 5,783.09 0.00 directa pendiente 24 29 23 22 Extension Spatial Analyst adaptation B. Strengthening capacity for BO-MAA-62405-GO-RFQ / Solicitud de Single Stage - One 2017-11- 2018-01- 2017-12- 2018-02- TF / 16083 adaptation to climate change Posterior Open - National 8,017.00 7,959.48 Firmado Adquisicion de Servidor cotizaciones Envelope 29 06 27 20 in the Rio Grande River Basin GO-PPCR-RFQ-013 / Adquisicion de un Equipo de Medicion Hidrologica - B. Strengthening capacity for Molinete de Helice para el Solicitud de Single Stage - One 2018-05- 2018-06- 2018-08- 2018-08- 2018-12- TF / 16083 adaptation to climate change Posterior Open - National 42,000.00 33,147.22 Finalizado Fortalecimiento del SENAMHI cotizaciones Envelope 12 22 20 21 14 in the Rio Grande River Basin en Apoyo a las Redes de Observacion en las Cuencas piloto PPCR GO-PPCR-RFB-012 / A. Strengthening national Adquisicion de equipamiento Solicitud de Single Stage - One 2018-10- 2018-11- 2018-12- 2018-12- 2019-01- 2019-04- TF / 16083 capacity for climate change Posterior Open - National 100,000.00 0.00 Cancelado para fortalecimiento centro ofertas Envelope 29 03 03 13 17 17 adaptation de procesamiento de datos GO-PPCR-RFB-011 / B. Strengthening capacity for Adquisición de Estaciones Solicitud de Single Stage - One 2018-09- 2019-08- 2018-10- 2018-11- 2018-11- 2018-12- 2019-03- TF / 16083 adaptation to climate change Posterior Open - National 200,000.00 0.00 Cancelado Meteorologicas e ofertas Envelope 28 23 03 02 12 17 17 in the Rio Grande River Basin Hidrologicas para la Cuenca Arque Tapacari GO-PPCR-RFB-010 / B. Strengthening capacity for Adquisición de Estaciones Solicitud de Single Stage - One 2018-05- 2018-05- 2018-05- 2018-06- 2018-06- 2018-06- 2018-06- 2018-07- 2018-09- TF / 16083 adaptation to climate change Posterior Open - National 205,598.00 204,110.29 En ejecución Meteorologicas e ofertas Envelope 04 02 09 08 05 18 22 23 21 in the Rio Grande River Basin Hidrologicas para la Cuenca del Rio Mizque BO-MAA-63418-GO-RFQ / Adquisicion equipos de A. Strengthening national Solicitud de Single Stage - One 2018-06- 2018-07- 2017-12- 2019-01- computacion, comunicacion y TF / 16083 capacity for climate change Posterior Open - National 1,880.47 1,879.88 Firmado cotizaciones Envelope 15 26 22 22 otros similares -Televisor de adaptation 56' para Video Conferencia GO-PPCR-RFB-006 / Adquisicion de equipamiento B. Strengthening capacity for para instrumentacion Solicitud de Single Stage - One 2016-11- 2017-08- 2016-11- 2016-12- 2017-09- 2017-01- 2017-09- 2017-01- 2017-10- 2017-03- 2017-12- TF / 16083 adaptation to climate change Posterior Open - National 125,068.00 124,162.74 Finalizado hidrometeorologica e ofertas Envelope 07 02 17 16 12 04 20 27 06 27 05 in the Rio Grande River Basin hidrometrica, red de observacion Cuenca Rocha C. Design and BS-CC-C2-D-3-11A / implementation of Adquisicion de 1 Camara Solicitud de Single Stage - One 2018-07- 2018-08- 2018-10- TF / 18119 subprojects that improve Posterior Open - National 5,977.00 0.00 Cancelado Fotografica, 1 Camara cotizaciones Envelope 03 10 09 climate resilience in the Rio Filmadora y 2 Data Displays Grande River Basin BS-CC-C2-D-3-12 / Adquisición de 1 Cámara C. Design and Fotográfica Profesional, 3 implementation of Solicitud de Single Stage - One Ejecución 2018-09- 2018-10- 2018-11- Cámaras Fotográficas TF / 18119 subprojects that improve Posterior Open - National 11,079.00 0.00 cotizaciones Envelope pendiente 13 18 07 (Cuenca Arque Tapacari), 3 climate resilience in the Rio GPS (Cuenca Arque Tapacari) Grande River Basin y 2 Datas Displays BS-CC-C2-D-3-2 / B. Strengthening capacity for Adquisicion Equipos de Solicitud de Single Stage - One 2017-10- 2017-11- 2017-09- 2018-01- TF / 18119 adaptation to climate change Posterior Open - National 7,289.00 5,992.75 Firmado Oficina y Muebles (PPCR - cotizaciones Envelope 04 14 29 13 in the Rio Grande River Basin SDC) GO-PPCR-RFQ-014 / Equipamiento SDC: Compra B. Strengthening capacity for Solicitud de Single Stage - One 2018-09- 2018-11- 2019-02- de un bote para facilitar la TF / 16083 adaptation to climate change Posterior Open - National 8,000.00 0.00 Cancelado cotizaciones Envelope 26 06 04 medición de caudales en ríos in the Rio Grande River Basin menores. BO-MAA-78030-GO-RFQ / Adquisicion de equipamiento para fortalecimiento centro A. Strengthening national Solicitud de Single Stage - One 2018-10- 2018-11- 2018-12- 2018-12- 2019-02- de procesamiento de datos TF / 16083 capacity for climate change Posterior Open - National 52,000.00 48,953.93 Finalizado cotizaciones Envelope 03 17 12 17 14 (Proyector, Videoconferencia, adaptation Impresora Blanco y Negro, Impresora a Color y Servidor) GO-PPCR-RFQ-005 / Adquisicion equipos de A. Strengthening national computacion, comunicacion y Solicitud de Single Stage - One 2018-06- 2018-08- 2018-08- 2018-09- TF / 16083 capacity for climate change Posterior Open - National 49,800.00 23,828.37 Firmado otros similares -Video cotizaciones Envelope 25 10 22 24 adaptation Conferencia- Laptops- Camara Filmadora y GPS BO-MAA-81371-GO-RFB / IMPLEMENTACION DE RED DE ESTACIONES PARA EL MONITOREO METEOROLOGICO E A. Strengthening national HIDROLOGICO EN FUENTES Solicitud de Single Stage - One 2018-10- 2018-11- 2018-11- 2018-12- 2018-12- 2018-12- 2018-12- 2018-12- 2019-01- 2019-03- TF / 16083 capacity for climate change Posterior Open - National 400,000.00 389,720.61 Firmado DE AGUA POTABLE DE LAS ofertas Envelope 30 15 07 07 17 14 21 21 24 11 adaptation CIUDADES DE POTOSI, COCHABAMBA Y SUCRE, Y EN SISTEMAS DE RIEGO EN CHUQUISACA, TARIJA, ORURO Y COCHABAMBA (SNICA FASE II) MMAYA-PPCR-LPN-002- 2018 / IMPLEMENTACION DE RED DE ESTACIONES PARA EL MONITOREO METEOROLOGICO E B. Strengthening capacity for Solicitud de Single Stage - One 2018-07- 2018-07- 2018-07- 2018-08- 2018-09- 2018-09- 2018-09- 2018-10- 2018-09- 2018-12- 2018-12- HIDROLOGICO EN FUENTES TF / 16083 adaptation to climate change Posterior Open - National 400,000.00 301,667.22 Finalizado ofertas Envelope 26 16 31 30 04 14 14 01 24 20 20 DE AGUA POTABLE DE LAS in the Rio Grande River Basin CIUDADES DE POTOSI COCHABAMBA Y SUCRE Y EN SISTEMAS DE RIEGO EN CHUQUISACA TARIJA ORURO Y COCHABAMBA - SNICA FASE I Page 1 GO-PPCR-RFB-002 / Implementacion de red de estaciones para el monitoreo meteorologico e hidrologico A. Strengthening national en fuentes de Agua Potable Solicitud de Open - Single Stage - One 2018-06- 2018-06- 2018-07- 2018-08- 2018-09- 2018-12- TF / 16083 capacity for climate change Previa 520,000.00 0.00 Cancelado de las ciudades de Potosi, La ofertas International Envelope 04 09 21 20 24 13 adaptation Paz, Cochabamba y Sucre, y en tres sistemas de riego en Chuquisaca, Tarija y Cochabamba BO-MAA-86183-GO-RFQ / Adquisición de Computadora A. Strengthening national Solicitud de Single Stage - One Ejecución 2018-11- 2019-01- 2019-02- Portátil, Computadora Portátil TF / 16083 capacity for climate change Posterior Open - National 27,000.00 0.00 cotizaciones Envelope pendiente 25 10 19 para Procesamiento y Disco adaptation de Almacenamiento para Storage BO-MAA-86185-GO-RFQ / A. Strengthening national Adquisición de Accesorios Solicitud de Single Stage - One 2018-11- 2019-01- 2018-12- 2019-02- TF / 16083 capacity for climate change Posterior Open - National 6,000.00 4,874.55 Firmado para Servidor y Dispositivos cotizaciones Envelope 24 13 31 22 adaptation de Almacenamiento BO-MAA-86187-GO-RFQ / A. Strengthening national Solicitud de Single Stage - One 2018-11- 2019-01- 2018-12- 2019-02- 2018-12- Adquisición de Sillas para TF / 16083 capacity for climate change Posterior Open - National 5,300.00 2,995.66 Finalizado cotizaciones Envelope 28 17 12 26 19 Auditorium (SNICA) adaptation BO-MAA-100637-GO-RFQ / A. Strengthening national Solicitud de Single Stage - One Ejecución 2019-04- 2019-05- 2019-06- Adquisición equipos de TF / 16083 capacity for climate change Posterior Open - National 6,706.00 0.00 cotizaciones Envelope pendiente 02 18 17 Escaner para la UCP PPCR adaptation BO-MAA-108729-GO-RFB / B. Strengthening capacity for Ampliación Red Solicitud de Single Stage - One Ejecución 2019-05- 2019-05- 2019-06- 2019-07- 2019-08- 2019-10- TF / 16083 adaptation to climate change Posterior Open - National 150,000.00 0.00 Hidrometeorologica Cuenca ofertas Envelope pendiente 23 23 20 05 03 22 in the Rio Grande River Basin Rocha - Cuenca Taquiña BO-MAA-109189-GO-RFQ / Adquisición de sillas operativas semiejecutivas, B. Strengthening capacity for Solicitud de Single Stage - One Ejecución 2019-05- 2019-06- 2019-08- Sillas para mesa de TF / 16083 adaptation to climate change Posterior Open - National 17,100.00 0.00 cotizaciones Envelope pendiente 05 24 23 Reuniones, Mesa de in the Rio Grande River Basin Reuniones Circular y Mesa plegable para Auditorio, para el SNICA BO-MAA-109190-GO-RFQ / B. Strengthening capacity for Adquisición de Muebleria Solicitud de Single Stage - One Ejecución 2019-05- 2019-06- 2019-08- TF / 16083 adaptation to climate change Posterior Open - National 29,500.00 0.00 para el SNICA (Escritorios, cotizaciones Envelope pendiente 05 24 23 in the Rio Grande River Basin Estantes) BO-MAA-109335-GO-RFB / Adquisición de Equipos B. Strengthening capacity for Solicitud de Single Stage - One 2019-05- 2019-05- 2019-06- 2019-07- 2019-08- 2019-09- Topobabatimetricos, Stock de TF / 16083 adaptation to climate change Posterior Open - National 240,400.00 0.00 Cancelado ofertas Envelope 21 26 25 15 13 27 Discos Duros y Servidor para in the Rio Grande River Basin el SENAMHI GO-PPCR-RFB-007 / Adquisicion de equipamiento B. Strengthening capacity for hidrologico para monitoreo Solicitud de Single Stage - One 2018-10- 2018-10- 2018-11- 2018-12- 2019-01- 2019-04- TF / 16083 adaptation to climate change Posterior Open - National 200,000.00 0.00 Cancelado de aguas subterraneas en las ofertas Envelope 21 26 25 05 09 09 in the Rio Grande River Basin Subcuencas Mizque, Rocha y Arque Tapacari C. Design and BS-CC-C2-D-3-13 / implementation of Adquisición de Vehículo tipo Solicitud de Single Stage - One 2019-06- 2019-07- 2019-11- 2019-08- TF / 18119 subprojects that improve Posterior Open - National 40,584.00 28,835.50 Firmado Camioneta para la Cuenca cotizaciones Envelope 08 18 29 18 climate resilience in the Rio Arque Tapacari Grande River Basin BO-MAA-108738-GO-RFB / Adquisición de Estaciones meteorológicas e B. Strengthening capacity for Solicitud de Single Stage - One Ejecución 2019-05- 2019-06- 2019-07- 2019-07- 2019-08- 2019-11- hidrológicas en regiones con TF / 16083 adaptation to climate change Posterior Open - National 300,000.00 0.00 ofertas Envelope pendiente 28 02 02 22 19 12 mayor escasez hidriaca y in the Rio Grande River Basin vulnerabilidad a sequías en el Chaco BO-MAA-112205-GO-RFB / A. Strengthening national Adquisición de Equipos de Solicitud de Single Stage - One 2019-06- 2019-06- 2019-07- 2019-07- 2019-08- 2019-11- TF / 16083 capacity for climate change Posterior Open - National 400,000.00 0.00 Cancelado Monitoreo Geotecnico para la ofertas Envelope 03 08 06 21 19 12 adaptation cuenca Taquiña BO-MAA-108741-GO-RFB / Adquisición de Estaciones meteorológicas e B. Strengthening capacity for Solicitud de Single Stage - One Ejecución 2019-06- 2019-06- 2019-07- 2019-08- 2019-09- 2019-11- hidrológicas en regiones con TF / 16083 adaptation to climate change Posterior Open - National 300,000.00 0.00 ofertas Envelope pendiente 18 23 23 07 05 29 mayor escasez hidrica y in the Rio Grande River Basin vulnerabilidad a sequías en el Altiplano BO-MAA-108739-GO-RFB / Adquisición de Estaciones meteorológicas e B. Strengthening capacity for Solicitud de Single Stage - One Ejecución 2019-05- 2019-06- 2019-07- 2019-07- 2019-08- 2019-11- hidrológicas en regiones con TF / 16083 adaptation to climate change Posterior Open - National 300,000.00 0.00 ofertas Envelope pendiente 29 08 08 28 26 19 mayor escasez hidrica y in the Rio Grande River Basin vulnerabilidad a sequías en valles BO-MAA-112211-GO-RFQ / A. Strengthening national Solicitud de Single Stage - One 2019-06- 2019-07- 2019-09- Adquisición de TF / 16083 capacity for climate change Posterior Open - National 35,000.00 0.00 Cancelado cotizaciones Envelope 03 18 01 Computadoras Estación de adaptation Trabajo BO-MAA-138651-GO-RFB / Implementación de A. Strengthening national Estaciones de Monitoreo Solicitud de Single Stage - One Ejecución 2019-12- 2019-12- 2020-01- 2020-02- 2020-02- 2020-05- TF / 16083 capacity for climate change Posterior Open - National 365,000.00 0.00 Hidrológico en Principales ofertas Envelope pendiente 20 25 22 01 29 09 adaptation Ríos del Balance Hídrico Superficial de Bolivia, en el marco del SNICA BO-MAA-138652-GO-RFB / Adquisición de Equipos A. Strengthening national Solicitud de Single Stage - One Ejecución 2019-11- 2019-11- 2019-12- 2019-12- 2020-01- 2020-03- Portátiles de Fluorescencia de TF / 16083 capacity for climate change Posterior Open - National 313,050.00 0.00 ofertas Envelope pendiente 20 25 23 30 20 30 Rayos X y Cromatografo de adaptation Gases BO-MAA-138655-GO-RFB / Adquisición de Equipos de Campo para Evaluación de Redes de Monitoreo (Multimetro, GPS Navegador, A. Strengthening national Solicitud de Single Stage - One Ejecución 2019-12- 2019-12- 2020-01- 2020-01- 2020-02- 2020-04- Distanciometro, Equipo TF / 16083 capacity for climate change Posterior Open - National 50,117.00 0.00 ofertas Envelope pendiente 16 21 18 25 15 25 Computacional Resistente a adaptation Condiciones Extremas, Equipos Portátiles de Contraste de Variables Meteorológicas) BO-MAA-138656-GO-RFQ / Adquisición de Repuestos A. Strengthening national para Sostenibilidad de las Solicitud de Single Stage - One Ejecución 2019-12- 2020-01- 2020-03- TF / 16083 capacity for climate change Posterior Open - National 35,200.00 0.00 Estaciones Meteorológicas e cotizaciones Envelope pendiente 03 05 05 adaptation Hidrológicas Instaladas por el PPCR en Gestión 2020 BO-MAA-108742-GO-RFB / Implementación de Red de Estaciones para el Monitoreo B. Strengthening capacity for Meteorológico e Hidrológico Solicitud de Single Stage - One Ejecución 2019-06- 2019-06- 2019-07- 2019-08- 2019-09- 2019-12- TF / 16083 adaptation to climate change Posterior Open - National 350,000.00 0.00 en Fuentes de Agua Potable y ofertas Envelope pendiente 24 29 29 13 11 05 in the Rio Grande River Basin Sistemas de Riego Priorizados a Nivel Nacional. SNICA FASE III BO-MAA-138657-GO-RFQ / Adquisición de Repuestos A. Strengthening national Básicos para Garantizar Solicitud de Single Stage - One Ejecución 2019-12- 2020-02- 2020-04- TF / 16083 capacity for climate change Posterior Open - National 4,500.00 0.00 Funcionamiento de la Red de cotizaciones Envelope pendiente 22 09 19 adaptation Monitoreo Implementada por el PPCR C. Design and BO-MAA-138660-GO-RFQ / implementation of Adquisición de Equipos de Solicitud de Single Stage - One Ejecución 2019-10- 2019-11- 2019-12- TF / 18119 subprojects that improve Posterior Open - National 583.00 0.00 Comunicación - Router cotizaciones Envelope pendiente 13 11 11 climate resilience in the Rio Inalambrico Grande River Basin BO-MAA-108735-GO-RFB / Adquisición de Herramientas y Repuestos para Asegurar la B. Strengthening capacity for Solicitud de Single Stage - One 2019-05- 2019-06- 2019-07- 2019-07- 2019-08- 2019-11- Funcionalidad de las TF / 16083 adaptation to climate change Posterior Open - National 200,000.00 0.00 Cancelado ofertas Envelope 30 04 04 19 17 05 Estaciones Meteorológicas e in the Rio Grande River Basin Hidrológicas Instaladas por el PPCR BO-MAA-138654-GO-RFB / A. Strengthening national Solicitud de Single Stage - One Ejecución 2019-12- 2019-12- 2020-01- 2020-01- 2020-02- 2020-04- Adquisición de Equipos para TF / 16083 capacity for climate change Posterior Open - National 58,761.00 0.00 ofertas Envelope pendiente 19 24 21 28 18 18 Análisis de Calidad de Aguas adaptation BO-MAA-142907-GO-RFQ / A. Strengthening national Solicitud de Single Stage - One Ejecución 2019-11- 2019-12- 2019-12- Adquisición de Mobiliario TF / 16083 capacity for climate change Posterior Open - National 1,588.00 0.00 cotizaciones Envelope pendiente 04 10 30 para la UCP-PPCR adaptation BO-MAA-142913-GO-RFQ / A. Strengthening national ADQUISICIÓN DE ESTANTES Solicitud de Single Stage - One Ejecución 2019-11- 2019-12- 2020-01- TF / 16083 capacity for climate change Posterior Open - National 45,000.00 0.00 PARA EL ÁREA DE cotizaciones Envelope pendiente 10 16 30 adaptation CONTRATACIONES DE LA UCP MMAYA/PPCR/SD/001/2020 A. Strengthening national Adquisición Ejecución 2020-02- 2020-02- 2020-03- 2020-03- / Adquisición de un disco TF / 16083 capacity for climate change Posterior Direct 200.00 0.00 directa pendiente 19 24 08 09 duro externo adaptation MMAYA/PPCR/ADQ/SDC/002 A. Strengthening national Solicitud de Single Stage - One Ejecución 2020-05- 2020-06- 2020-06- /2020 / Adquisicion de TF / 16083 capacity for climate change Posterior Limited 11,662.00 0.00 cotizaciones Envelope pendiente 27 07 27 Muebles para la UCP-PPCR adaptation MMAYA/PPCR/SDO/BIENES/N AL/02/2020 / Adquisición de A. Strengthening national equipo de Evaluación Solicitud de Single Stage - One Ejecución 2020-08- 2020-08- 2020-09- 2020-10- 2020-10- 2020-11- TF / 16083 capacity for climate change Posterior Open - National 198,260.64 0.00 Geotécnica para el Sistema ofertas Envelope pendiente 27 30 29 03 11 30 adaptation Nacional de Clima y Agua (SNICA) BS-CC-C2-D-3-14 / C. Design and Adquisición de Muebles de implementation of Solicitud de Single Stage - One 2020-09- 2020-10- 2020-10- Oficina (Vagón Móvil y TF / 18119 subprojects that improve Posterior Open - National 10,205.00 0.00 En ejecución cotizaciones Envelope 27 09 20 Estantes para Archivos climate resilience in the Rio Proyecto PPCR) Grande River Basin MMAYA/PPCR/ADQ/SDC/001 /2020 / Adquisición de Equipos de Computación para la UCP-PPCR (10 computadoras portátiles, 1 A. Strengthening national Solicitud de Single Stage - One 2020-01- 2020-03- 2020-05- UPS para servidor, 1 disco TF / 18119 capacity for climate change Previa Open - National 28,312.00 0.00 Cancelado cotizaciones Envelope 29 07 06 duro externo, 1 impresora adaptation láser negro, 1 impresora láser color, 5 discos duros, 1 escáner, 1 escáner para libros, 7 mouse) BO-MAA-108737-GO-RFB / Implementación de Fortalecimiento a la Red de B. Strengthening capacity for Monitoreo del Proyecto Solicitud de Single Stage - One 2019-10- 2020-09- 2019-11- 2019-12- 2020-11- 2019-12- 2020-01- 2020-04- TF / 16083 adaptation to climate change Posterior Open - National 240,661.00 0.00 Cancelado Múltiple Misicuni (Estaciones ofertas Envelope 24 10 08 08 04 23 21 15 in the Rio Grande River Basin Meteorologicas e Hidrologicas, Rehabilitación y Pluviotermica) Page 2 MMAYA/PPCR/SDO/BIENES/N AL/01/2020 / Adquisición de equipos de calidad de aguas para el Sistema Nacional de A. Strengthening national Solicitud de Single Stage - One 2020-05- 2020-09- 2020-05- 2020-06- 2020-10- 2020-06- 2020-06- 2020-06- Clima y Agua (SNICA) : TF / 16083 capacity for climate change Posterior Open - National 300,655.98 0.00 Cancelado ofertas Envelope 20 01 23 22 05 24 28 30 Equipo Analizador Portátil de adaptation Fluorescencia de Rayos X y Equipo Cromatógrafo de Gases Portátil MMAYA/PPCR/SDO/BIENES/N AL/03/2020 / Adquisición de 3 Servidores para el A. Strengthening national Solicitud de Single Stage - One 2020-09- 2020-09- 2020-09- 2020-10- 2020-10- 2020-10- 2020-10- 2020-12- SENAMHI: Sistemas de TF / 16083 capacity for climate change Posterior Open - National 240,233.20 0.00 Cancelado ofertas Envelope 11 11 13 13 09 17 25 09 Protocolos de adaptation Interoperabilidad, Pronósticos Estacionales y Monitor de Sequias NON CONSULTING SERVICES Activity Reference No. / Draft Pre- Draft Bidding Bid Evaluation Report Loan / Credit Market Procurement Prequalificatio Estimated Actual Process Prequalification Specific Procurement Bidding Documents Proposal Submission Description Component Review Type Method qualification Document / and Signed Contract Contract Completion No. Approach Process n (Y/N) Amount (US$) Amount (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Documents Justification Recommendation for Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PlannedAwardActual Planned Actual Planned Actual NC-PPCR-RFB-001 / A. Strengthening national Impresion de material de Solicitud de Single Stage - One Ejecución 2017-10- 2017-11- 2017-12- TF / 16083 capacity for climate change Posterior Open - National 30,000.00 0.00 comunicacion y difusion de cotizaciones Envelope pendiente 20 30 20 adaptation acciones del Proyecto BM NC-PPCR-RFQ-002 / Fortalecimiento de capacidades en monitoreo del A. Strengthening national personal de la UCP en Solicitud de Single Stage - One 2018-08- 2018-10- 2019-01- TF / 16083 capacity for climate change Posterior Open - National 30,000.00 0.00 Cancelado proyectos y temas tecnico - cotizaciones Envelope 27 07 05 adaptation administrativos relacionados con el cumplimiento de los objetivos del proyecto NC-PPCR-RFQ-006 / B. Strengthening capacity for Capacitacion a los grupos Solicitud de Single Stage - One 2018-12- 2019-01- 2019-03- TF / 16083 adaptation to climate change Posterior Open - National 15,000.00 0.00 Cancelado beneficiarios sobre sistemas cotizaciones Envelope 12 22 23 in the Rio Grande River Basin de alerta temprana -CBBA - NC-PPCR-RFQ-010 / Capacitacion a grupos tecnicos del SDC en las tematicas de: - Monitoreo de sequia, B. Strengthening capacity for modelacion hidrologica Solicitud de Single Stage - One 2018-07- 2018-08- 2018-09- TF / 16083 adaptation to climate change Posterior Open - National 30,000.00 0.00 Cancelado - Supervision Fiscalizacion y cotizaciones Envelope 07 17 16 in the Rio Grande River Basin Acompañamiento de proyectos de inversion con enfoque de resiliencia y ACC - Otros relacionados a la tematica NC-PPCR-RFQ-011 / B. Strengthening capacity for Fortalecimiento de las Solicitud de Single Stage - One 2018-09- 2018-10- 2018-11- TF / 16083 adaptation to climate change Posterior Open - National 20,000.00 0.00 Cancelado capacidades locales en cotizaciones Envelope 08 19 18 in the Rio Grande River Basin Planificacion de PDC NC-PPCR-RFQ-013 / Fortalecimiento de capacidades tecnicas del personal del MMAyA, UCP- B. Strengthening capacity for Solicitud de Single Stage - One 2018-10- 2018-11- 2019-01- PPCR y FPS en temas de TF / 16083 adaptation to climate change Posterior Open - National 40,000.00 0.00 Cancelado cotizaciones Envelope 03 13 12 monitoreo del clima, agua, in the Rio Grande River Basin resiliencia y ACC, para la implementacion de los componentes del proyecto SNC-CC-C2-C-3-1 / C. Design and Componente Estructural y No implementation of Estructural -Conservacion y Solicitud de Single Stage - One 2018-07- 2018-08- 2018-07- 2018-08- 2018-09- 2018-08- 2018-10- 2018-09- 2018-10- 2020-06- TF / 18119 subprojects that improve Posterior Open - National 465,926.00 462,817.59 Firmado Control de la Microcuenca ofertas Envelope 02 16 07 18 17 28 02 14 29 30 climate resilience in the Rio Arenales - Municipio de Grande River Basin Omereque SNC-CC-C2-C-3-2 / C. Design and Componente Estructural y No implementation of Estructural - Conservacion y Solicitud de Single Stage - One 2018-07- 2018-08- 2018-07- 2018-08- 2018-09- 2018-08- 2018-10- 2018-09- 2018-10- 2020-06- TF / 18119 subprojects that improve Posterior Open - National 480,493.00 467,243.24 Firmado Control de la Microcuenca ofertas Envelope 02 16 07 06 17 16 02 20 18 30 climate resilience in the Rio Mokontullo - Municipio de Grande River Basin Mizque SNC-CC-C2-C-3-3 / C. Design and Componente Estructural y No implementation of Estructural -Conservacion y Solicitud de Single Stage - One 2018-07- 2018-08- 2018-07- 2018-08- 2018-09- 2018-08- 2018-10- 2018-09- 2018-10- 2020-06- TF / 18119 subprojects that improve Posterior Open - National 407,551.00 404,913.40 Firmado Control de la Microcuenca ofertas Envelope 02 16 07 18 17 28 02 25 31 30 climate resilience in the Rio Moyapampa - Municipio de Grande River Basin Totora SNC-CC-C2-C-3-31 / C. Design and Componente Estructural y no implementation of Solicitud de Single Stage - One Ejecución 2018-10- 2018-10- 2018-11- 2018-12- 2019-01- 2020-06- Estructural para el Manejo TF / 18119 subprojects that improve Posterior Open - National 423,203.00 0.00 ofertas Envelope pendiente 22 27 26 06 10 30 Integral de la Microcuenca climate resilience in the Rio Panama Grande River Basin SNC-CC-C2-C-3-32 / C. Design and Componente Estructural y no implementation of Solicitud de Single Stage - One Ejecución 2018-08- 2018-08- 2018-09- 2018-09- 2018-11- 2020-06- Estructural para el Manejo TF / 18119 subprojects that improve Posterior Open - National 408,550.00 0.00 ofertas Envelope pendiente 15 20 19 29 03 30 Integral de la Microcuenca climate resilience in the Rio Challwani Grande River Basin SNC-CC-C2-C-3-38 / C. Design and Componente Estructural y no implementation of Solicitud de Single Stage - One Ejecución 2018-08- 2018-08- 2018-09- 2018-09- 2018-11- 2020-06- Estructural para el Manejo TF / 18119 subprojects that improve Posterior Open - National 390,000.00 0.00 ofertas Envelope pendiente 15 20 19 29 03 30 Integral de la Microcuenca climate resilience in the Rio Samancha Grande River Basin SNC-CC-C2-C-3-50 / C. Design and Componente Estructural y no implementation of Solicitud de Single Stage - One Ejecución 2018-09- 2018-09- 2018-10- 2018-10- 2018-12- 2020-06- Estructural para el Manejo TF / 18119 subprojects that improve Posterior Open - National 425,231.00 0.00 ofertas Envelope pendiente 12 17 17 27 01 30 Integral de la Microcuenca climate resilience in the Rio Acero Kocha Grande River Basin SNC-CC-C2-C-3-52 / C. Design and Componente Estructural y no implementation of Solicitud de Single Stage - One Ejecución 2018-09- 2018-09- 2018-10- 2018-10- 2018-12- 2020-06- Estructural para el Manejo TF / 18119 subprojects that improve Posterior Open - National 391,408.00 0.00 ofertas Envelope pendiente 12 17 17 27 01 30 Integral de la Microcuenca climate resilience in the Rio Koturi Grande River Basin SNC-CC-C2-C-3-53 / C. Design and Componente Estructural y no implementation of Solicitud de Single Stage - One Ejecución 2018-09- 2018-09- 2018-10- 2018-10- 2018-12- 2020-06- Estructural para el Manejo TF / 18119 subprojects that improve Posterior Open - National 424,993.00 0.00 ofertas Envelope pendiente 12 17 17 27 01 30 Integral de la Microcuenca climate resilience in the Rio Pocona Grande River Basin SNC-CC-C2-C-3-54 / C. Design and Componente Estructural y no implementation of Solicitud de Single Stage - One Ejecución 2018-09- 2018-09- 2018-10- 2018-10- 2018-12- 2020-06- Estructural para el Manejo TF / 18119 subprojects that improve Posterior Open - National 431,180.00 0.00 ofertas Envelope pendiente 12 17 17 27 01 30 Integral de la Microcuenca climate resilience in the Rio Pucara mayu Grande River Basin NC-PPCR-RFQ-007 / Fortalecimiento de los mecanismos de participacion B. Strengthening capacity for -a traves de la Solicitud de Single Stage - One 2018-08- 2018-09- 2018-11- TF / 16083 adaptation to climate change Posterior Open - National 5,000.00 0.00 Cancelado Mancomunidad del Cono Sur cotizaciones Envelope 22 29 28 in the Rio Grande River Basin - de actores locales de la cuenca del Mizque, a efecto de operativizar el PDC Mizque NC-PPCR-RFQ-004 / Difusion de documento A. Strengthening national Solicitud de Single Stage - One Ejecución 2018-09- 2018-09- 2018-09- 2018-10- 2018-10- 2018-12- tecnico sobre medidas GIRH - TF / 16083 capacity for climate change Posterior Open - National 50,000.00 0.00 ofertas Envelope pendiente 10 15 29 06 18 17 MIC, en base al catalogo del adaptation MMAyA -VRHR -PNC NC-PPCR-RFQ-005 / Capacitacion a los tomadores B. Strengthening capacity for Solicitud de Single Stage - One Ejecución 2018-11- 2018-12- 2019-02- de decisiones y grupos TF / 16083 adaptation to climate change Posterior Open - National 40,624.81 0.00 cotizaciones Envelope pendiente 13 24 22 tecnicos sobre el uso de in the Rio Grande River Basin sistemas de alerta temprana NC-PPCR-RFQ-012 / Fortalecimiento a OGCs - B. Strengthening capacity for Organismos de Gestion de Solicitud de Single Stage - One Ejecución 2018-08- 2018-08- 2018-09- 2018-09- 2018-10- 2018-11- TF / 16083 adaptation to climate change Posterior Open - National 202,842.56 0.00 Cuencas - para las ofertas Envelope pendiente 01 06 05 15 20 19 in the Rio Grande River Basin Subcuencas Mizque, Rocha y Arque Tapacari NC-PPCR-RFQ-008 / Apoyo a la difusion de metodologias de analisis cuantitativo en B. Strengthening capacity for Solicitud de Single Stage - One 2018-09- 2018-09- 2018-10- 2018-10- 2018-11- 2019-01- riesgos a desastres y TF / 16083 adaptation to climate change Posterior Open - National 50,000.00 0.00 Cancelado ofertas Envelope 23 28 12 19 03 02 adaptacion al Cambio in the Rio Grande River Basin Climatico en proyectos de inversion Pública BO-MAA-82020-NC-RFQ / IMPRESION DEL MANUAL A. Strengthening national Solicitud de Single Stage - One 2017-11- 2017-11- 2017-12- 2018-01- PARA LA TOMA DE TF / 16083 capacity for climate change Posterior Limited 15,000.00 6,729.38 En ejecución cotizaciones Envelope 15 17 12 11 DECISIONES EN adaptation INFRAESTRUCTURA RESILIENTE DE PROYECTOS DE RIEGO BO-MAA-82018-NC-RFQ / A. Strengthening national IMPRESION DE LA GUIA PARA Solicitud de Single Stage - One 2018-08- 2018-08- 2018-09- 2018-10- 2018-10- 2018-11- TF / 16083 capacity for climate change Posterior Limited 15,000.00 9,058.61 Finalizado LA ELABORACIÓN DE cotizaciones Envelope 09 31 06 23 06 27 adaptation PROYECTOS DE RIEGO NC-PPCR-RFQ-001 / Taller de Difusion y Capacitación A. Strengthening national Manual para la Toma de Solicitud de Single Stage - One Ejecución 2017-10- 2017-11- 2017-11- TF / 16083 capacity for climate change Posterior Limited 3,222.00 0.00 Decisiones en Proyectos de cotizaciones Envelope pendiente 22 05 10 adaptation Infraestructura Resiliente de Proyectos de Riego CP-007-2018 / TALLER CAPACITACION EN A. Strengthening national OPERACION DE ESTACIONES Y Solicitud de Single Stage - One Ejecución 2018-09- 2018-09- 2018-10- TF / 16083 capacity for climate change Posterior Limited 400.00 0.00 ADMINISTRACIÓN DE cotizaciones Envelope pendiente 09 21 01 adaptation INFORMACIÓN DE DATOS HIDROMETEOROLOGICOS CP-008-2018 / CONTRATACION DE SERVICIO DE ALIMENTACION PARA EL TALLER DE CAPACITACION REFERIDO A LA A. Strengthening national Solicitud de Single Stage - One Ejecución 2018-09- 2018-10- 2018-10- IMPLEMENTACION DE TF / 16083 capacity for climate change Posterior Limited 200.00 0.00 cotizaciones Envelope pendiente 29 10 20 ESTACIONES adaptation METEOROLOGICAS E HIDROMETRICAS AUTOMATICAS EN LA CUENCA DEL RIO MIZQUE CP-003-2017 / TALLER INFORMATIVO A LOS GAMS DEL DEPARTAMENTO DE LA A. Strengthening national PAZ SOBRE EL MANUAL PARA Solicitud de Single Stage - One Ejecución 2017-11- 2017-12- 2017-12- TF / 16083 capacity for climate change Posterior Limited 4,155.00 0.00 LA TOMA DE DECISIONES EN cotizaciones Envelope pendiente 22 06 11 adaptation PROYECTOS DE INFRAESTRUCTURA RESILIENTE DE PROYECTOS DE RIEGO Page 3 NC-PPCR-RFQ-009 / A. Strengthening national Solicitud de Single Stage - One 2018-09- 2018-09- 2018-10- 2018-11- 2018-11- 2020-06- Impresion de guias, planes, TF / 16083 capacity for climate change Posterior Open - National 78,600.58 0.00 Cancelado ofertas Envelope 18 23 23 02 19 30 manuales, etc adaptation BO-MAA-82022-NC-RFQ / A. Strengthening national Solicitud de Single Stage - One 2018-11- 2019-10- 2019-01- 2020-10- 2020-06- Impresion de guias, planes, TF / 16083 capacity for climate change Posterior Limited 48,600.00 12,965.92 Firmado cotizaciones Envelope 24 16 05 12 30 manuales, etc adaptation NC-PPCR-RFQ-003 / A. Strengthening national Socializacion de Solicitud de Single Stage - One 2017-10- 2017-10- 2017-11- 2017-11- 2017-11- 2018-01- TF / 16083 capacity for climate change Posterior Open - National 52,000.00 0.00 Cancelado herramientas -instrumentos ofertas Envelope 20 25 08 15 27 11 adaptation -guias -planes orientadores de ACC BO-MAA-82023-NC-RFQ / A. Strengthening national Socializacion de herramientas Solicitud de Single Stage - One Ejecución 2018-11- 2018-12- 2019-06- TF / 16083 capacity for climate change Posterior Limited 45,000.00 0.00 -instrumentos -guias -planes cotizaciones Envelope pendiente 25 24 22 adaptation orientadores de ACC BO-MAA-82220-NC-RFQ / A. Strengthening national Solicitud de Single Stage - One Ejecución 2018-10- 2018-11- 2018-11- Presentación de las Nuevas TF / 16083 capacity for climate change Posterior Limited 5,000.00 0.00 cotizaciones Envelope pendiente 28 18 28 Guías de Riego adaptation BO-MAA-82541-NC-RFQ / Impresión de la Guía de A. Strengthening national Solicitud de Single Stage - One 2019-01- 2019-03- 2019-04- Evaluación expost de TF / 16083 capacity for climate change Posterior Limited 5,000.00 0.00 Cancelado cotizaciones Envelope 30 02 01 Defensivos para el Sector de adaptation Recursos Hidricos y Riego SNC-CC-C2-C-3-36 / C. Design and Componente Estructural y no implementation of Estructural para el Manejo Solicitud de Single Stage - One 2018-08- 2018-10- 2018-08- 2018-09- 2018-12- 2018-09- 2019-01- 2018-11- 2019-03- 2020-06- TF / 18119 subprojects that improve Posterior Open - National 390,000.00 598,117.75 Firmado Integral de la microcuenca ofertas Envelope 15 21 20 19 10 29 25 03 28 30 climate resilience in the Rio Intinimayu y Gestion Integral Grande River Basin de recursos Hídricos SNC-CC-C2-C-3-34 / C. Design and Componente Estructural y no implementation of Solicitud de Single Stage - One 2018-08- 2018-12- 2018-08- 2018-09- 2019-01- 2018-09- 2019-02- 2018-11- 2019-03- 2020-06- Estructural para el Manejo TF / 18119 subprojects that improve Posterior Open - National 395,250.00 449,519.04 Firmado ofertas Envelope 15 21 20 19 24 29 28 03 28 30 Integral de la cuenca Millu climate resilience in the Rio Mayu Grande River Basin SNC-CC-C2-C-3-35 / C. Design and Componente Estructural y no implementation of Solicitud de Single Stage - One 2018-08- 2018-12- 2018-08- 2018-09- 2019-01- 2018-09- 2019-02- 2018-11- 2019-04- 2020-06- Estructural para la Gestion y TF / 18119 subprojects that improve Posterior Open - National 395,250.00 419,086.93 Firmado ofertas Envelope 15 21 20 19 24 29 13 03 02 30 Manejo Integral de la cuenca climate resilience in the Rio Rinconada (Tolata) Grande River Basin SNC-CC-C2-C-3-37 / C. Design and Componente Estructural y no implementation of Solicitud de Single Stage - One 2018-08- 2019-01- 2018-08- 2018-09- 2019-02- 2018-09- 2019-02- 2018-11- 2019-04- 2020-06- Estructural para el Manejo TF / 18119 subprojects that improve Posterior Open - National 390,000.00 446,260.77 Firmado ofertas Envelope 15 04 20 19 04 29 28 03 08 30 Integral de la Microcuenca climate resilience in the Rio Carcel Mayu Grande River Basin SNC-CC-C2-C-3-33 / C. Design and Componente Estructural y no implementation of Estructural para la Gestion Solicitud de Single Stage - One 2018-08- 2019-02- 2018-08- 2018-09- 2019-03- 2018-09- 2019-04- 2018-11- 2019-05- 2020-06- TF / 18119 subprojects that improve Posterior Open - National 395,250.00 600,580.83 Firmado Integrada de los Recursos ofertas Envelope 15 04 20 19 07 29 10 03 20 30 climate resilience in the Rio Hídricos y el Manejo Integral Grande River Basin de la Cuenca Laka Laka. SNC-CC-C2-C-3-51 / C. Design and Componente Estructural y no implementation of Solicitud de Single Stage - One 2018-09- 2018-09- 2018-10- 2018-10- 2018-12- 2020-06- Estructural para el Manejo TF / 18119 subprojects that improve Posterior Open - National 362,624.00 0.00 Cancelado ofertas Envelope 12 17 17 27 01 30 Integral de la Microcuenca climate resilience in the Rio Collpas Grande River Basin C. Design and SNC-CC-C2-C-3-56 / implementation of Manejo Integral de la Solicitud de Single Stage - One 2019-05- 2019-05- 2019-05- 2019-06- 2019-06- 2019-06- 2019-06- 2019-07- 2019-07- 2020-05- TF / 18119 subprojects that improve Posterior Open - National 415,662.00 411,948.19 Firmado Microcuenca Collpas, ofertas Envelope 10 13 12 11 11 17 18 18 17 28 climate resilience in the Rio Municipio de Pasorapa Grande River Basin C. Design and BO-MAA-114185-NC-RFB / implementation of Solicitud de Single Stage - One 2019-05- 2019-06- 2019-05- 2019-06- 2019-08- 2019-06- 2019-08- 2019-08- 2019-09- 2020-05- Manejo Integral de la TF / 18119 subprojects that improve Posterior Open - National 430,603.91 440,767.13 Firmado ofertas Envelope 15 28 19 18 02 24 07 01 10 27 Microcuenca Acero Kocha climate resilience in the Rio Grande River Basin C. Design and BO-MAA-114186-NC-RFB / implementation of Manejo Integral de la Solicitud de Single Stage - One 2019-05- 2019-05- 2019-05- 2019-06- 2019-06- 2019-06- 2019-07- 2019-08- 2019-08- 2020-05- TF / 18119 subprojects that improve Posterior Open - National 463,477.95 429,368.22 Firmado Microcuenca Qotumayu - ofertas Envelope 15 24 19 20 27 26 04 02 09 28 climate resilience in the Rio Municipio de Tacopaya Grande River Basin C. Design and BO-MAA-114187-NC-RFB / implementation of Manejo Integral de la Solicitud de Single Stage - One 2019-05- 2019-05- 2019-05- 2019-06- 2019-06- 2019-06- 2019-07- 2019-08- 2019-08- 2020-05- TF / 18119 subprojects that improve Posterior Open - National 463,238.49 430,181.51 Firmado Microcuenca Aquerana - ofertas Envelope 16 24 19 18 26 25 03 02 09 28 climate resilience in the Rio Municipio de Tacopaya Grande River Basin C. Design and BO-MAA-114188-NC-RFB / implementation of Manejo Integral de la Solicitud de Single Stage - One 2019-05- 2019-05- 2019-05- 2019-06- 2019-06- 2019-06- 2019-07- 2019-08- 2019-08- 2020-05- TF / 18119 subprojects that improve Posterior Open - National 463,396.33 424,781.73 Firmado Microcuenca Corral Pampa - ofertas Envelope 16 24 19 19 26 25 04 02 08 28 climate resilience in the Rio Cona Cona Grande River Basin C. Design and BO-MAA-114189-NC-RFB / implementation of Solicitud de Single Stage - One 2019-05- 2019-07- 2019-05- 2019-06- 2019-08- 2019-06- 2019-08- 2019-08- 2019-09- 2020-05- Manejo Integral de la TF / 18119 subprojects that improve Posterior Open - National 469,296.26 470,977.75 Firmado ofertas Envelope 17 05 19 18 07 24 16 01 20 27 Microcuenca Pocona climate resilience in the Rio Grande River Basin C. Design and SNC-CC-C2-C-3-57 / implementation of Solicitud de Single Stage - One 2019-05- 2019-05- 2019-05- 2019-06- 2019-06- 2019-06- 2019-06- 2019-07- 2019-07- 2020-05- Manejo Integrado de la TF / 18119 subprojects that improve Posterior Open - National 459,117.00 463,387.98 Firmado ofertas Envelope 10 12 12 11 11 17 25 18 25 28 Cuenca Sapanani climate resilience in the Rio Grande River Basin C. Design and SNC-CC-C2-C-3-58 / implementation of Solicitud de Single Stage - One 2019-05- 2019-05- 2019-05- 2019-09- 2019-06- 2019-06- 2019-06- 2019-06- 2019-07- 2019-07- 2020-05- Manejo Integrado de la TF / 18119 subprojects that improve Posterior Open - National 458,551.00 460,700.72 Firmado ofertas Envelope 10 10 12 11 12 12 18 19 19 12 29 Cuenca Wara Wara climate resilience in the Rio Grande River Basin C. Design and SNC-CC-C2-C-3-59 / implementation of Solicitud de Single Stage - One 2019-05- 2019-05- 2019-05- 2019-06- 2019-06- 2019-06- 2019-06- 2019-07- 2019-07- 2020-05- Manejo Integrado de la TF / 18119 subprojects that improve Posterior Open - National 458,920.00 460,506.74 Firmado ofertas Envelope 10 13 12 12 12 18 19 19 19 29 Cuenca Chungara climate resilience in the Rio Grande River Basin BO-MAA-117933-NC-RFQ / A. Strengthening national 5to. Foro Taller de Resiliencia Solicitud de Single Stage - One Ejecución 2019-06- 2019-07- 2019-07- TF / 16083 capacity for climate change Posterior Limited 5,900.00 0.00 y Adaptación al Cambio cotizaciones Envelope pendiente 10 02 17 adaptation Climático MMAYA/PPCR/ADQ/SDC/005 /2020 / Elaboración de un A. Strengthening national Solicitud de Single Stage - One Ejecución 2020-10- 2020-11- 2020-12- Video Documental del TF / 16083 capacity for climate change Posterior Limited 7,288.63 0.00 cotizaciones Envelope pendiente 23 11 11 Programa Piloto de adaptation Resiliencia Climática (PPCR) MMAYA/PPCR/ADQ/SDC/006 /2020 / Servicio de A. Strengthening national Organización, Solicitud de Single Stage - One Ejecución 2020-10- 2020-11- 2020-12- TF / 18119 capacity for climate change Posterior Limited 36,210.00 0.00 Compaginación, cotizaciones Envelope pendiente 31 08 23 adaptation sistematización y Empastado de documentos del PPCR para el Cierre del Programa CONSULTING FIRMS Activity Reference No. / Short List and Draft Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Request for Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Request for Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Interest Notice Proposals as Issued Proposals / Minutes Technical Proposal Proposals Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CS-PPCR-QCBS-006 / Analisis de eventos extremos y generacion de mapas generales de riesgo climatico A. Strengthening national Selección basada 2018-09- 2018-09- 2018-10- 2018-11- 2018-11- 2019-01- 2019-06- e hidrico a escala subnacional TF / 16083 capacity for climate change Posterior Open - National 120,000.00 0.00 Cancelado 2018-08-20 en calidad y costo 04 28 26 02 27 01 30 en las Cuencas piloto -en el adaptation marco del SPIE, y los estudios de escenarios climaticos de la Autoridad de la Madre Tierra - CS-PPCR-QCBS-007 / Diseño y estructuracion del B. Strengthening capacity for sistema de alerta temprana Selección basada 2018-10- 2018-11- 2018-12- 2018-12- 2019-01- 2019-02- 2019-08- TF / 16083 adaptation to climate change Posterior Open - National 30,000.00 0.00 Cancelado 2018-10-01 para monitoreo de sequias en en calidad y costo 15 04 02 12 10 14 13 in the Rio Grande River Basin subcuencas piloto -Mizque, Rocha y Arque Tapacari - CS-PPCR-QCBS-008 / Elaboracion de un Sistema de B. Strengthening capacity for Selección basada 2018-10- 2018-11- 2018-12- 2018-12- 2019-01- 2019-02- 2019-06- Indicadores especiales TF / 16083 adaptation to climate change Posterior Open - National 25,000.00 0.00 Cancelado 2018-10-01 en calidad y costo 16 09 07 14 08 12 12 conforme Convenios de in the Rio Grande River Basin financiamiento del PPCR C. Design and FC-CC-C2-C-3-60 / implementation of Elaboracion de estudios de Selección basada Ejecución 2018-07- 2018-08- 2018-09- 2018-09- 2018-10- 2018-11- 2019-03- TF / 18119 subprojects that improve Posterior Open - National 189,504.00 0.00 2018-06-29 preinversion en en calidad y costo pendiente 14 07 04 11 06 10 10 climate resilience in the Rio Infraestructura Grande River Basin C. Design and FC-CC-C2-C-3-62 / implementation of Elaboracion de estudios de Selección basada Ejecución 2018-07- 2018-08- 2018-09- 2018-09- 2018-10- 2018-11- 2019-03- TF / 18119 subprojects that improve Posterior Open - National 58,309.00 0.00 2018-06-29 preinversion en Defensivos en calidad y costo pendiente 14 07 04 11 06 10 10 climate resilience in the Rio en la cuenca del río Rocha Grande River Basin FC-CC-C2-C-3-63 / C. Design and Elaboracion de estudios de implementation of Selección basada Ejecución 2018-07- 2018-08- 2018-09- 2018-09- 2018-10- 2018-11- 2019-03- preinversion en Defensivos TF / 18119 subprojects that improve Posterior Open - National 29,155.00 0.00 2018-06-29 en calidad y costo pendiente 14 07 04 11 06 10 10 en la cuenca del Arque climate resilience in the Rio Tapacarí Grande River Basin MMAYA -PPCR -FC -001 - 2018 / Auditoria de A. Strengthening national Financiera por los periodos Selección basada 2019-02- 2018-04- 2018-04- 2018-05- 2018-05- 2018-05- 2018-05- 2018-06- TF / 16083 capacity for climate change Posterior Open - National 47,561.00 0.00 En ejecución 2018-04-06 comprendidos 07/05/2015 y en el menor costo 14 06 08 06 08 12 14 20 adaptation el 31/12/2016, Gestión 2017 y Gestión 2018 C. Design and FC-CC-C2-C-3-61 / implementation of Elaboracion de estudios de Selección basada 2018-07- 2018-08- 2018-09- 2018-09- 2018-10- 2018-11- 2019-03- TF / 18119 subprojects that improve Posterior Open - National 157,857.00 0.00 Cancelado 2018-06-29 preinversion en Defensivos en calidad y costo 14 07 04 11 06 10 10 climate resilience in the Rio en la cuenca del río Mizque Grande River Basin FC-CC-C2-C-3-65 / C. Design and Elaboración de Estudios de implementation of Diseño Técnico de Pre- Selección basada 2018-10- 2018-09- 2018-10- 2018-11- 2018-12- 2018-12- 2019-01- 2019-04- TF / 18119 subprojects that improve Posterior Open - National 68,996.00 0.00 En ejecución 2018-09-06 Inversión para la en calidad y costo 17 27 22 19 04 29 17 04 climate resilience in the Rio Construcción de Defensivos Grande River Basin en el Municipio de Mizque FC-CC-C2-C-3-66 / C. Design and Elaboración de Estudios de implementation of Diseño Técnico de Pre- Selección basada 2018-10- 2018-09- 2018-10- 2018-11- 2018-12- 2018-12- 2019-01- 2019-04- TF / 18119 subprojects that improve Posterior Open - National 31,733.00 0.00 En ejecución 2018-09-06 inversión para la construcción en calidad y costo 17 27 22 19 04 25 23 04 climate resilience in the Rio de defensivos en el Municipio Grande River Basin de Omereque Page 4 BO-MAA-77143-CS-QCBS / A. Strengthening national Linea Base de los Selección basada 2018-10- 2018-11- 2018-12- 2018-12- 2019-01- 2019-02- 2019-04- TF / 16083 capacity for climate change Posterior Open - National 27,000.00 0.00 Cancelado 2018-10-01 Subproyectos de en calidad y costo 22 16 14 24 14 07 08 adaptation Infraestructura y MIC del PPCR CS-PPCR-QCBS-004 / Desarrollo e implementacion sistema operativo gestion agua para generacion A. Strengthening national Selección basada 2018-08- 2018-09- 2018-10- 2018-10- 2018-11- 2018-12- 2019-06- pronosticos de caudales de TF / 16083 capacity for climate change Posterior Open - National 200,000.00 0.00 Cancelado 2018-08-10 en calidad y costo 25 18 16 23 17 22 20 aporte y niveles de embalses adaptation en sistemas de agua potable y fuentes de agua de tres sistemas de riego BO-MAA-81488-CS-QCBS / A. Strengthening national Actualización del Sistema de Selección basada 2019-02- 2018-11- 2018-11- 2018-12- 2018-12- 2019-01- 2019-02- 2019-08- TF / 16083 capacity for climate change Posterior Open - National 250,000.00 0.00 En ejecución 2018-10-22 Monitoreo de Embales (SNICA en calidad y costo 14 05 24 24 29 06 03 02 adaptation FASE II) BO-MAA-81489-CS-QCBS / A. Strengthening national Selección basada Ejecución 2018-11- 2018-11- 2018-12- 2018-12- 2019-01- 2019-01- 2019-07- Desarrollo del Monitor de TF / 16083 capacity for climate change Posterior Open - National 250,000.00 0.00 2018-10-22 en calidad y costo pendiente 05 24 24 29 06 18 17 Sequia adaptation BO-MAA-82330-CS-QCBS / A. Strengthening national Selección basada Ejecución 2018-10- 2018-11- 2018-12- 2018-12- 2019-01- 2019-01- 2019-04- Actualización del software TF / 16083 capacity for climate change Posterior Open - National 70,000.00 0.00 2018-10-22 en calidad y costo pendiente 27 18 18 23 04 18 18 Abro - Área bajo riego adaptation optimo BO-MAA-100636-CS-LCS / AUDITORIA FINANCIERA DEL PROYECTO RESILIENCIA CLIMÁTICA EN BOLIVIA- A. Strengthening national Selección basada Ejecución 2019-02- 2019-02- 2019-03- 2019-04- 2019-04- 2019-04- 2019-06- MANEJO INTEGRADO DE TF / 16083 capacity for climate change Posterior Open - National 20,000.00 0.00 2019-02-27 en el menor costo pendiente 27 27 29 08 18 30 29 CUENCAS EN EL MARCO DEL adaptation PPCR, POR EL PERIODO COMPRENDIDO ENTRE EL 01/01/2018 AL 31/12/2018 FC-CC-C2-C-3-68 / C. Design and Elaboración de Estudios de implementation of Diseño Técnico de Pre- Selección basada Ejecución 2019-04- 2019-05- 2019-06- 2019-06- 2019-07- 2019-07- 2019-10- TF / 18119 subprojects that improve Posterior Open - National 28,989.00 0.00 2019-03-29 Inversión Manejo Integral de en calidad y costo pendiente 13 13 12 24 08 31 29 climate resilience in the Rio Cuenca Pukara Mayu Grande River Basin (Cuchumuela) FC-CC-C2-C-3-69 / C. Design and Elaboración de Estudios de implementation of Diseño Técnico de Pre- Selección basada Ejecución 2019-04- 2019-05- 2019-06- 2019-06- 2019-07- 2019-07- 2019-10- TF / 18119 subprojects that improve Posterior Open - National 28,043.00 0.00 2019-03-29 Inversión Manejo Integral de en calidad y costo pendiente 26 13 12 24 08 31 29 climate resilience in the Rio la Microcuenca Qocha Qocha Grande River Basin - Buena Vista FC-CC-C2-C-3-70 / C. Design and Elaboración de Estudios de implementation of Diseño Técnico de Pre- Selección basada 2019-04- 2019-05- 2019-06- 2019-06- 2019-07- 2019-07- 2019-10- TF / 18119 subprojects that improve Posterior Open - National 22,931.00 0.00 Cancelado 2019-03-29 Inversión Manejo Integral de en calidad y costo 13 13 12 24 08 31 29 climate resilience in the Rio la Microcuenca Torancali - Grande River Basin Challamayu FC-CC-C2-C-3-71 / C. Design and Elaboración de Estudios de implementation of Selección basada 2019-04- 2019-05- 2019-06- 2019-06- 2019-07- 2019-07- 2019-10- Diseño Técnico de Pre- TF / 18119 subprojects that improve Posterior Open - National 26,344.00 0.00 Cancelado 2019-03-29 en calidad y costo 13 13 12 24 08 31 29 Inversión Manejo Integral de climate resilience in the Rio la Microcuenca Kangani Grande River Basin FC-CC-C2-C-3-72 / C. Design and Elaboración de Estudios de implementation of Selección basada 2019-04- 2019-05- 2019-06- 2019-06- 2019-07- 2019-07- 2019-10- Diseño Técnico de Pre- TF / 18119 subprojects that improve Posterior Open - National 25,200.00 0.00 Cancelado 2019-04-01 en calidad y costo 16 13 12 24 08 31 29 Inversión Manejo Integral de climate resilience in the Rio Cuenca Khora Tiquipaya Grande River Basin FC-CC-C2-C-3-73 / C. Design and Elaboración de Estudios de implementation of Selección basada 2019-04- 2019-05- 2019-06- 2019-06- 2019-07- 2019-07- 2019-10- Diseño Técnico de Pre- TF / 18119 subprojects that improve Posterior Open - National 37,172.00 0.00 Cancelado 2019-04-01 en calidad y costo 16 13 12 24 08 31 29 Inversión Manejo Integral de climate resilience in the Rio Cuenca Taquiña Grande River Basin FC-CC-C2-C-3-74 / C. Design and Elaboración de Estudios de implementation of Selección basada Ejecución 2019-04- 2019-05- 2019-06- 2019-06- 2019-07- 2019-07- 2019-10- Diseño Técnico de Pre- TF / 18119 subprojects that improve Posterior Open - National 20,751.00 0.00 2019-04-01 en calidad y costo pendiente 16 13 12 24 08 31 29 Inversión Manejo Integral de climate resilience in the Rio la Microcuenca Kaquerema Grande River Basin FC-CC-C2-C-3-75 / C. Design and Elaboración de Estudios de implementation of Selección basada Ejecución 2019-04- 2019-05- 2019-06- 2019-06- 2019-07- 2019-07- 2019-10- Diseño Técnico de Pre- TF / 18119 subprojects that improve Posterior Open - National 20,751.00 0.00 2019-04-01 en calidad y costo pendiente 16 13 12 24 08 31 29 Inversión Manejo Integral de climate resilience in the Rio la Microcuenca Locosti Grande River Basin FC-CC-C2-C-3-76 / C. Design and Elaboración de Estudios de implementation of Selección basada Ejecución 2019-04- 2019-05- 2019-06- 2019-06- 2019-07- 2019-07- 2019-10- Diseño Técnico de Pre- TF / 18119 subprojects that improve Posterior Open - National 28,043.00 0.00 2019-04-01 en calidad y costo pendiente 16 13 12 24 08 31 29 Inversión Manejo Integral de climate resilience in the Rio la Cuenca Collpa Mayu Grande River Basin FC-CC-C2-C-3-67 / Elaboración de Estudios de C. Design and Diseño Técnico de implementation of Selección basada Ejecución 2019-04- 2019-05- 2019-05- 2019-06- 2019-06- 2019-07- 2020-01- Preinversión Mejoramiento TF / 18119 subprojects that improve Posterior Open - National 26,720.00 0.00 2019-04-02 en calidad y costo pendiente 17 21 26 15 27 17 13 del Sistema de Riego climate resilience in the Rio Comunidad Sarco Cuchu - Grande River Basin Municipio Capinota CS-PPCR-QCBS-002 / Desarrollo e implementacion A. Strengthening national de herramienta para la Selección basada 2018-08- 2018-09- 2018-10- 2018-10- 2018-11- 2018-12- 2019-06- TF / 16083 capacity for climate change Posterior Open - National 300,000.00 0.00 Cancelado 2018-08-10 generacion de pronosticos en calidad y costo 25 18 16 23 17 22 20 adaptation trimestrales de precipitacion y temperatura a nivel nacional CS-PPCR-QCBS-003 / Desarrollo e implementacion A. Strengthening national Selección basada 2018-07- 2018-08- 2018-09- 2018-09- 2018-10- 2018-11- 2019-05- de herramienta operacional TF / 16083 capacity for climate change Posterior Open - National 150,000.00 0.00 Cancelado 2018-07-12 en calidad y costo 27 20 17 24 19 23 22 para el monitoreo de sequias adaptation a nivel nacional CS-PPCR-QCBS-001 / Desarrollo e implementacion de protocolos para la transferencia de datos A. Strengthening national Selección basada 2018-09- 2018-10- 2018-11- 2018-11- 2018-12- 2019-01- 2019-07- meteorologicos e TF / 16083 capacity for climate change Posterior Open - National 50,000.00 0.00 Cancelado 2018-09-10 en calidad y costo 25 19 16 23 18 22 21 hidrologicos de todas las adaptation instituciones, publicas y privadas generadoras de datos al SENAMHI BO-MAA-109181-CS-CQS / ESTUDIO PARA GENERACIÓN DE MODELO DIGITAL DE ELEVACIÓN DEL EMBALSE LA B. Strengthening capacity for Selección basada 2019-08- 2019-05- 2019-06- 2019-07- 2019-08- 2019-09- ANGOSTURA, MEDIANTE TF / 16083 adaptation to climate change Posterior en calificaciones Open - National 100,000.00 0.00 En ejecución 2019-04-25 05 10 23 08 06 15 LEVANTAMIENTO TOPO- in the Rio Grande River Basin de consultores BATIMÉTRICO Y FORTALECIMIENTO A ASOCIACIÓN DE REGANTES BO-MAA-109185-CS-CQS / B. Strengthening capacity for Selección basada Estudio de Caracterización 2019-06- 2019-07- 2019-08- 2019-09- 2020-05- TF / 16083 adaptation to climate change Posterior en calificaciones Open - National 90,000.00 0.00 Cancelado 2019-05-27 Fisiográfico en el Embalse la 11 25 09 07 04 in the Rio Grande River Basin de consultores Angostura BO-MAA-109186-CS-CQS / Estudio de Caracterización B. Strengthening capacity for Selección basada 2019-09- 2019-06- 2019-07- 2019-08- 2019-09- 2020-05- Fisiografico en los Embalses TF / 16083 adaptation to climate change Posterior en calificaciones Open - National 35,000.00 0.00 Cancelado 2019-05-29 11 13 27 11 09 06 de Lahuachama, Wara Wara, in the Rio Grande River Basin de consultores Escalerani y Totora Qhocha BO-MAA-86458-CS-QCBS / Desarrollo Investigativo sobre A. Strengthening national el Desempeño de Riego en Selección basada 2018-12- 2019-01- 2019-02- 2019-02- 2019-03- 2019-04- 2019-10- TF / 16083 capacity for climate change Posterior Open - National 55,000.00 0.00 Cancelado 2018-11-30 Área Cultivada Bajo Riego y en calidad y costo 14 12 09 24 25 23 20 adaptation Eficiencias del Sistema de Riego CS-PPCR-QCBS-005 / Diagnostico Hidrogeologico General e Implementacion de Acciones Basicas para el A. Strengthening national Selección basada 2018-10- 2018-11- 2018-12- 2018-12- 2019-01- 2019-02- 2019-08- Aprovechamiento Sostenible TF / 16083 capacity for climate change Posterior Open - National 48,000.00 0.00 Cancelado 2018-10-15 en calidad y costo 30 23 21 28 22 26 25 de Agua Subterranea en areas adaptation Criticas de Bolivia bajo Escenarios de Escasez y Cambio Climatico BO-MAA-82331-CS-QCBS / Desarrollo Investigativo del A. Strengthening national Selección basada 2018-10- 2018-11- 2018-12- 2018-12- 2019-01- 2019-01- 2019-04- indicador de evaluación de TF / 16083 capacity for climate change Posterior Open - National 50,000.00 0.00 Cancelado 2018-10-22 en calidad y costo 27 15 15 20 04 18 18 desempeño de riego área adaptation cultivada bajo riego BO-MAA-112019-CS-QCBS A. Strengthening national Selección basada 2019-05- 2019-06- 2019-07- 2019-07- 2019-08- 2019-08- 2020-04- / Consultoria de análisis de TF / 16083 capacity for climate change Posterior Open - National 180,000.00 0.00 Cancelado 2019-05-10 en calidad y costo 25 11 09 19 05 29 25 eventos extremos adaptation BO-MAA-112020-CS-QCBS A. Strengthening national / Plan de Gestión como Selección basada 2019-06- 2019-07- 2019-08- 2019-08- 2019-08- 2019-09- 2020-03- TF / 16083 capacity for climate change Posterior Open - National 180,000.00 0.00 Cancelado 2019-05-30 modelo para el Proyecto en calidad y costo 14 04 01 11 28 21 19 adaptation Múltiple Misicuni BO-MAA-112013-CS-QCBS / DESARROLLO E A. Strengthening national Selección basada Open - 2019-04- 2019-05- 2019-06- 2019-07- 2019-07- 2019-08- 2019-09- 2020-06- IMPLEMENTACIÓN DEL TF / 16083 capacity for climate change Posterior 423,000.00 0.00 Cancelado 2019-05-03 en calidad y costo International 29 18 04 19 29 15 18 14 SISTEMA DE PRONÓSTICOS adaptation ESTACIONALES PARA BOLIVIA BO-MAA-112014-CS-QCBS / DESARROLLO E A. Strengthening national IMPLEMENTACION DEL Selección basada Open - 2019-04- 2019-05- 2019-06- 2019-07- 2019-07- 2019-08- 2019-09- 2020-06- TF / 16083 capacity for climate change Posterior 492,000.00 0.00 Cancelado 2019-05-03 SISTEMA DE MONITOREO Y en calidad y costo International 29 18 04 19 29 15 18 14 adaptation ALERTA TEMPRANA DE SEQUIAS PARA BOLIVIA BO-MAA-112015-CS-QCBS / IMPLEMENTACIÓN DE PROTOCOLOS DE COORDINACIÓN, B. Strengthening capacity for INTEROPERABILIDAD Y Selección basada Open - 2019-05- 2019-05- 2019-05- 2019-06- 2019-07- 2019-07- 2019-08- 2019-09- 2020-06- TF / 16083 adaptation to climate change Posterior 385,000.00 0.00 En ejecución 2019-05-03 PLATAFORMA INFORMÁTICA en calidad y costo International 07 18 10 04 19 29 15 18 14 in the Rio Grande River Basin DE TRANSFERENCIA DIGITAL DE INFORMACIÓN HIDROMETEOROLOGICA Y CLIMÁTICA BO-MAA-112207-CS-QCBS A. Strengthening national Selección basada 2019-05- 2019-06- 2019-07- 2019-08- 2019-08- 2019-09- 2020-05- / Generación del Mapa de TF / 16083 capacity for climate change Posterior Open - National 200,000.00 0.00 Cancelado 2019-05-13 en calidad y costo 28 21 19 03 20 13 10 Riesgos adaptation BO-MAA-113185-CS-QCBS / DESARROLLO E A. Strengthening national IMPLEMENTACION DEL Selección basada Open - 2019-05- 2019-05- 2019-05- 2019-06- 2019-06- 2019-08- 2019-07- 2019-08- 2019-08- 2019-09- 2019-08- 2019-10- 2019-10- 2020-06- TF / 16083 capacity for climate change Posterior 491,810.00 339,504.12 En ejecución 2019-05-09 SISTEMA DE MONITOREO Y en calidad y costo International 03 24 07 22 06 06 22 21 02 04 16 03 11 29 adaptation ALERTA TEMPRANA DE SEQUIAS PARA BOLIVIA Page 5 BO-MAA-113186-CS-QCBS / DESARROLLO E A. Strengthening national Selección basada Open - 2019-05- 2019-05- 2019-05- 2019-06- 2019-05- 2019-07- 2019-07- 2019-08- 2019-08- 2019-08- 2019-08- 2019-09- 2020-06- IMPLEMENTACIÓN DEL TF / 16083 capacity for climate change Posterior 422,342.00 0.00 En ejecución 2019-05-09 en calidad y costo International 03 24 07 10 24 25 23 04 01 21 13 24 20 SISTEMA DE PRONÓSTICOS adaptation ESTACIONALES PARA BOLIVIA FC-CC-C2-C-3-64 / C. Design and Elaboración de Estudios de implementation of Diseño Técnico de Pre- Selección basada 2019-05- 2018-09- 2018-10- 2018-11- 2018-11- 2018-12- 2019-01- 2019-04- TF / 18119 subprojects that improve Posterior Open - National 60,797.00 0.00 Cancelado 2018-09-05 inversión para la en calidad y costo 02 20 10 07 22 16 07 04 climate resilience in the Rio Construcción de Defensivos Grande River Basin en los Municipios de Totora y Pocona FC-CC-C2-C-3-64-A / Elaboración de Estudios de C. Design and Diseño Técnico de implementation of Selección basada 2019-05- 2019-05- 2019-06- 2019-07- 2019-08- 2019-08- 2019-09- 2020-06- Preinversión para la TF / 18119 subprojects that improve Posterior Open - National 68,086.00 0.00 En ejecución 2019-05-15 en calidad y costo 27 30 28 26 10 22 11 30 Construcción de Defensivos climate resilience in the Rio en los Municipios de Totora y Grande River Basin Pocona FC-CC-C2-C-3-77 / Elaboración de Estudio de C. Design and Diseño Técnico de implementation of Preinversión para Selección basada 2019-06- 2019-06- 2019-07- 2019-08- 2019-08- 2019-08- 2019-09- 2020-02- TF / 18119 subprojects that improve Posterior Open - National 89,591.00 0.00 En ejecución 2019-06-17 Mejoramiento de Sistemas de en calidad y costo 13 24 11 12 15 23 10 07 climate resilience in the Rio Riego para el Municipio de Grande River Basin Santivañez: Poquera, Saucini, Calaconto, Muyurina Caporaya FC-CC-C2-C-3-80 / Elaboración de Estudios de C. Design and Diseño Técnico de implementation of Preinversión para la Selección basada 2020-05- 2019-06- 2019-07- 2019-08- 2019-08- 2019-08- 2019-09- 2019-12- TF / 18119 subprojects that improve Posterior Open - National 25,208.00 0.00 En ejecución 2019-06-17 Construcción de Defensivos en calidad y costo 02 24 11 12 17 23 10 09 climate resilience in the Rio de Protección para las Áreas Grande River Basin Productivas en el Rió Mizque del Municipio de Pasorapa FC-CC-C2-C-3-81 / Elaboración de Estudios de C. Design and Diseño Técnico de implementation of Selección basada 2020-05- 2019-06- 2019-07- 2019-08- 2019-08- 2019-08- 2019-09- 2019-12- Preinversión para el TF / 18119 subprojects that improve Posterior Open - National 65,658.00 0.00 En ejecución 2019-06-17 en calidad y costo 02 24 11 12 19 23 10 09 Mejoramiento de Sistemas de climate resilience in the Rio Riego en el Municipio de Grande River Basin Mizque FC-CC-C2-C-3-78 / C. Design and Elaboración de Estudios de implementation of Diseño Técnico de Selección basada 2019-07- 2019-06- 2019-07- 2019-08- 2019-08- 2019-08- 2019-09- 2020-01- TF / 18119 subprojects that improve Posterior Open - National 49,627.00 0.00 En ejecución 2019-06-17 Preinversión Manejo Integral en calidad y costo 29 24 11 12 17 23 10 08 climate resilience in the Rio de las Microcuencas Torancali Grande River Basin - Ch´allamayu y Kangani FC-CC-C2-C-3-79 / C. Design and Elaboración de Estudios de implementation of Diseño Técnico de Selección basada 2020-05- 2019-06- 2019-07- 2019-08- 2019-08- 2019-08- 2019-09- 2020-02- TF / 18119 subprojects that improve Posterior Open - National 68,397.00 0.00 En ejecución 2019-06-17 Preinversión Manejo Integral en calidad y costo 02 24 11 12 17 23 10 07 climate resilience in the Rio de las Cuencas Khora Grande River Basin Tiquipaya y Taquiña FC-CC-C2-C-3-82 / C. Design and Elaboración de Estudio de implementation of Diseño Técnico de Selección basada 2019-07- 2019-07- 2019-08- 2019-08- 2019-09- 2019-09- 2020-02- TF / 18119 subprojects that improve Posterior Open - National 55,803.00 0.00 Cancelado 2019-06-27 Preinversión para Protección en calidad y costo 04 22 22 27 03 20 17 climate resilience in the Rio de Riberas del Rio Tapacari, Grande River Basin Municipio Sipe Sipe FC-CC-C2-C-3-83 / Elaboración de Estudio de Diseño técnico de C. Design and Preinversión para implementation of Selección basada 2019-07- 2019-07- 2019-08- 2019-08- 2019-09- 2019-09- 2020-02- Mejoramiento de Sistemas de TF / 18119 subprojects that improve Posterior Open - National 75,580.00 0.00 Cancelado 2019-06-27 en calidad y costo 04 22 22 27 03 20 17 Riego para los Municipios de climate resilience in the Rio Arque Capinota, Caramarca Grande River Basin Huayllahuju, Vila Vila, Sarco Cucho BO-MAA-112018-CS-QCBS / Fortalecimiento de Capacidades de Unidades de A. Strengthening national Selección basada 2019-06- 2019-06- 2019-07- 2019-08- 2019-08- 2019-09- 2020-05- Gestión de Riego Municipal TF / 16083 capacity for climate change Posterior Open - National 200,000.00 0.00 Cancelado 2019-05-21 en calidad y costo 05 25 23 02 19 17 14 en las Cuencas de los Ríos adaptation Rocha, Mizque y Arque Tapacari FC-CC-C2-C-3-85 / Elaboración de Estudio de Diseño Técnico de C. Design and Preinversión Mejoramiento implementation of Sistemas de Riego Selección basada 2020-05- 2019-08- 2019-09- 2019-10- 2019-11- 2019-11- 2019-11- 2020-03- TF / 18119 subprojects that improve Posterior Open - National 80,862.00 0.00 En ejecución 2019-08-19 Tecnificado Muyurina, Flor en calidad y costo 02 26 26 24 04 07 29 30 climate resilience in the Rio del Valle, Arce Rancho, Grande River Basin Huerta Pampa, Esquina, Cala Caja, Villa Rosario, Rocha Rancho (Santivañez). FC-CC-C2-C-3-86 / Elaboración de Estudios de Diseño Técnico de Preinversión Mejoramiento C. Design and Sistemas de Riego implementation of Selección basada 2020-05- 2019-08- 2019-09- 2019-10- 2019-11- 2019-11- 2019-11- 2020-03- Comunidades Molle Molle TF / 18119 subprojects that improve Posterior Open - National 60,857.00 0.00 En ejecución 2019-08-20 en calidad y costo 02 26 26 24 04 07 29 30 Laguna 1, Molle Molle Laguna climate resilience in the Rio 2 y la Comunidad de Juzgado Grande River Basin del D-1, Colca, Collpas, Sivingani, Collca Claco del D- 5 (Arani) FC-CC-C2-C-3-87 / Elaboración de Estudios de C. Design and Diseño Técnico de implementation of Preinversión Mejoramiento Selección basada 2020-05- 2019-08- 2019-09- 2019-10- 2019-11- 2019-11- 2019-11- 2020-03- TF / 18119 subprojects that improve Posterior Open - National 54,472.00 0.00 En ejecución 2019-08-20 Sistema de Riego Comunidad en calidad y costo 02 26 26 24 04 07 29 30 climate resilience in the Rio Pantipata Municipio Vinto y Grande River Basin Comunidad Chaguarani Municipio Tarata. FC-CC-C2-C-3-88 / Elaboración de Estudios de C. Design and Diseño Técnico de implementation of Selección basada 2020-05- 2019-08- 2019-09- 2019-10- 2019-11- 2019-11- 2019-11- 2020-03- Preinversión Mejoramiento TF / 18119 subprojects that improve Posterior Open - National 54,406.00 0.00 En ejecución 2019-08-20 en calidad y costo 02 26 26 24 04 07 29 30 Sistemas de Riego de los climate resilience in the Rio Municipios Arbieto y Villa Grande River Basin Rivero FC-CC-C2-C-3-89 / Elaboración de Estudios de Diseño Técnico de C. Design and Preinversión para la implementation of Selección basada 2020-05- 2019-08- 2019-09- 2019-10- 2019-11- 2019-11- 2019-11- 2020-03- Construcción de Obras TF / 18119 subprojects that improve Posterior Open - National 52,168.00 0.00 En ejecución 2019-08-20 en calidad y costo 02 26 26 24 04 07 29 30 Hidráulicas para la Reducción climate resilience in the Rio de Riesgos de Inundación en Grande River Basin los Municipios de Vinto y Cochabamaba FC-CC-C2-C-3-90 / Elaboración de Estudios de Diseño Tecnico de C. Design and Preinversión para la implementation of Selección basada 2020-05- 2019-08- 2019-09- 2019-10- 2019-11- 2019-11- 2019-11- 2020-03- COnstrucción de Obras TF / 18119 subprojects that improve Posterior Open - National 71,706.00 0.00 En ejecución 2019-08-20 en calidad y costo 02 26 26 24 04 07 29 30 Hidraulicas para la Reducción climate resilience in the Rio de Riesgos de Inundación en Grande River Basin los Municipios de Arani, Arbieto y San Benito FC-CC-C2-C-3-91 / Elaboración de Estudios de Diseño Técnico de C. Design and Preinversión para el implementation of Selección basada 2020-05- 2019-08- 2019-09- 2019-10- 2019-11- 2019-11- 2019-11- 2020-03- Mejoramiento de Sistemas de TF / 18119 subprojects that improve Posterior Open - National 80,648.00 0.00 En ejecución 2019-08-20 en calidad y costo 02 26 26 24 04 07 29 30 Riego en las Comunidades climate resilience in the Rio Coluyo Grande, Moyapampa, Grande River Basin Challa y Antaqhawa (Municipio de Totora) FC-CC-C2-C-3-92 / Elaboración de Estudios de C. Design and Diseño Técnico de implementation of Preinversión para la Selección basada 2020-05- 2019-08- 2019-09- 2019-10- 2019-11- 2019-11- 2019-11- 2020-03- TF / 18119 subprojects that improve Posterior Open - National 75,484.00 0.00 En ejecución 2019-08-20 Construcción de Muros en calidad y costo 02 26 26 24 04 07 29 30 climate resilience in the Rio Defensivos sobre los Ríos Grande River Basin Tipajara, Tucma y Lampasillos en el Municipio de Mizque FC-CC-C2-C-3-94 / Elaboración de Estudios de C. Design and Diseño Técnico de implementation of Selección basada 2020-05- 2019-08- 2019-09- 2019-10- 2019-11- 2019-11- 2019-11- 2020-03- Preinversión Mejoramiento: TF / 18119 subprojects that improve Posterior Open - National 69,504.00 0.00 En ejecución 2019-08-20 en calidad y costo 02 26 26 24 04 07 29 30 Sistema de Riego Muro Kollpa climate resilience in the Rio y Wuayllani (Arque) Sarco Grande River Basin Cucho (Capinota) FC-CC-C2-C-3-95 / Elaboración de Estudios de C. Design and Diseño Técnico de implementation of Preinversión Construcción de Selección basada 2020-05- 2019-08- 2019-09- 2019-10- 2019-11- 2019-11- 2019-11- 2020-03- TF / 18119 subprojects that improve Posterior Open - National 86,269.00 0.00 En ejecución 2019-08-20 Defensivos en Riberas: del en calidad y costo 02 26 26 24 04 07 29 30 climate resilience in the Rio Rio Tapacari (Sipe SIpe) y Río Grande River Basin Samana Uma, Khoyu Khotani (Tapacari) FC-CC-C2-C-3-84 / Elaboración de Estudios de C. Design and Diseño Técnico de implementation of Preinversión Mejoramiento Selección basada 2020-05- 2019-08- 2019-09- 2019-10- 2019-11- 2019-11- 2019-11- 2020-04- TF / 18119 subprojects that improve Posterior Open - National 70,654.00 0.00 En ejecución 2019-08-19 Sistemas de Riego en calidad y costo 02 26 26 24 04 07 29 06 climate resilience in the Rio Comunidades Llulluchani, Grande River Basin Muña Mayu, Pajchata Lux (Anzaldo) FC-CC-C2-C-3-93 / Elaboración de Estudios de C. Design and Diseño Técnico de implementation of Preinversión Mejoramineto: Selección basada 2020-05- 2019-08- 2019-09- 2019-10- 2019-11- 2019-11- 2019-11- 2020-03- TF / 18119 subprojects that improve Posterior Open - National 92,738.00 0.00 En ejecución 2019-08-20 Sistemas de Riego Caramarca en calidad y costo 02 26 26 24 04 07 29 30 climate resilience in the Rio - Huayllahuju - Vila Vila Grande River Basin (Arque), Kjarkas Pongo Chironi (Tapacarí) y Vila Vila (Bolivar) BO-MAA-112018-CS-QCBS- 2 / Fortalecimiento de Capacidades de Unidades de A. Strengthening national Selección basada 2019-09- 2019-10- 2019-11- 2019-11- 2019-11- 2019-12- 2020-06- Gestión de Riego Municipal TF / 16083 capacity for climate change Posterior Open - National 200,000.00 0.00 Cancelado 2019-09-11 en calidad y costo 26 06 03 08 16 05 22 en las Cuencas de los Ríos adaptation Rocha, Mizque y Arque Tapacari BO-MAA-138650-CS-QCBS / Estudios de Caracterización A. Strengthening national Selección basada 2019-10- 2019-11- 2019-12- 2019-12- 2019-12- 2020-01- 2020-05- Fisiográfica para Cuerpos, TF / 16083 capacity for climate change Posterior Open - National 220,000.00 0.00 Cancelado 2019-10-21 en calidad y costo 23 12 10 17 31 28 15 Indicadores Hidrológicos para adaptation el Monitor de Sequia BO-MAA-112203-CS-QCBS / Estudio "Modelo de Gestión A. Strengthening national Selección basada Open - 2019-06- 2019-07- 2019-08- 2019-09- 2019-10- 2019-11- 2020-05- de Embalses" (4 embalses TF / 16083 capacity for climate change Posterior 440,000.00 0.00 Cancelado 2019-05-29 en calidad y costo International 13 12 26 10 08 11 09 prioritarios) (la cañada, el adaptation tranque, angostura y tacagua) BO-MAA-112017-CS-QCBS B. Strengthening capacity for / Sistema de Alerta Temprana Selección basada Open - 2019-06- 2019-05- 2019-06- 2019-07- 2019-08- 2019-08- 2019-09- 2020-06- TF / 16083 adaptation to climate change Posterior 495,000.00 0.00 Cancelado 2019-05-10 ante Eventos Extremos para en calidad y costo International 05 25 14 29 08 25 21 17 in the Rio Grande River Basin la Cuenca del Rió Rocha Page 6 BO-MAA-138659-CS-QCBS / Desarrollo e Implementación de A. Strengthening national Selección basada 2019-10- 2019-11- 2019-11- 2019-12- 2019-12- 2020-01- 2020-01- 2020-06- Herramientas para la TF / 16083 capacity for climate change Posterior Open - National 220,000.00 0.00 En ejecución 2019-10-23 en calidad y costo 23 07 19 17 24 07 31 15 Modelación Oferta/Demanda adaptation y Optimización de Operación en Embalses La Cañada y Tacagua BO-MAA-138658-CS-QCBS / Desarrollo e Implementación de A. Strengthening national Selección basada 2019-10- 2019-11- 2019-11- 2019-12- 2019-12- 2020-01- 2020-02- 2020-06- Herramientas para la TF / 16083 capacity for climate change Posterior Open - National 220,000.00 0.00 En ejecución 2019-10-24 en calidad y costo 23 08 22 20 30 13 06 21 Modelación Oferta/Demanda adaptation y Optimización de Operación en Embalses la Angostura y El Tranque MMAYA/PPCR/SC/SBCC/001/ 2020 / ESTUDIO DE CARACTERIZACION A. Strengthening national Selección basada 2020-08- 2020-09- 2020-10- 2020-10- 2020-10- 2020-11- 2020-12- FISIOGRAFICA PARA CUERPOS TF / 16083 capacity for climate change Posterior Open - National 220,000.00 0.00 En ejecución 2020-08-10 en calidad y costo 26 05 05 10 20 12 31 DE AGUA, INDICADORES adaptation HIDROLOGICOS PARA EL MONITOR DE SEQUIA FC-CC-C2-C-3-96 / Elaboración de Estudios de Diseño Técnico de C. Design and Preinversión para la implementation of Selección basada 2020-09- 2020-09- 2020-09- 2020-10- 2020-11- 2020-12- Construcción de Defensivos TF / 18119 subprojects that improve Posterior en calificaciones Open - National 29,965.89 0.00 En ejecución 2020-09-01 06 16 24 24 01 31 para la Protección de Riberas climate resilience in the Rio de consultores en el Cauce Principal de la Grande River Basin Microcuenca Thola P'ujru (Municipio de Tiquipaya) FC-CC-C2-C-3-97 / Elaboración de Estudios de Diseño Técnico de Preinversión para la C. Design and Construcción de Defensivos implementation of Selección basada 2020-09- 2020-09- 2020-09- 2020-10- 2020-11- 2020-12- para la Protección de Riberas TF / 18119 subprojects that improve Posterior en calificaciones Open - National 49,959.33 0.00 En ejecución 2020-09-01 06 16 24 24 01 31 en el Cauce Principal de las climate resilience in the Rio de consultores Microcuencas: Chijllawiri Grande River Basin (Municipio de Quillacollo) - Khotu Mayu (Municipio de Tiquipaya) FC-CC-C2-C-3-98 / Elaboración de Estudios de Diseño Técnico de C. Design and Preinversión para la implementation of Selección basada Construcción de Defensivos 2020-09- 2020-09- 2020-09- 2020-10- 2020-11- 2020-12- TF / 18119 subprojects that improve Posterior en calificaciones Open - National 49,983.53 0.00 En ejecución 2020-09-01 para la Protección de Riberas 06 16 24 24 01 31 climate resilience in the Rio de consultores en el cauce Principal de las Grande River Basin Microcuencas: Locosti (Municipio Sacaba) - Chuta Kawa (Municipio de Tiquipaya) BO-MAA-138649-CS-QCBS / DESARROLLO Y SISTEMATIZACIÓN DE MODELOS NUMÉRICOS PARA A. Strengthening national Selección basada Open - 2019-10- 2019-11- 2019-11- 2019-11- 2020-01- 2020-01- 2020-01- 2020-02- 2020-06- EL MONITOREO TF / 16083 capacity for climate change Posterior 338,053.00 0.00 Cancelado 2019-10-24 en calidad y costo International 18 08 08 20 04 11 23 21 25 HIDROMETEOROLÓGICO DE adaptation LA CUENCA DEL RIO ROCHA (VALLE CENTRAL – VALLE BAJO) BO-MAA-109188-CS-CQS / B. Strengthening capacity for Selección basada Estudio de Caracterización 2019-08- 2019-06- 2019-07- 2019-08- 2019-09- 2020-05- TF / 16083 adaptation to climate change Posterior en calificaciones Open - National 28,000.00 0.00 Cancelado 2019-05-30 Fisiográfico en los Embalses 09 14 28 12 10 07 in the Rio Grande River Basin de consultores de Quivincha y Tacagua BO-MAA-109187-CS-CQS / Estudio de Caracterización B. Strengthening capacity for Selección basada Fisográfico en los Embalses 2019-09- 2019-06- 2019-07- 2019-08- 2019-09- 2020-05- TF / 16083 adaptation to climate change Posterior en calificaciones Open - National 40,000.00 0.00 Cancelado 2019-05-30 de Escana, Escaleras, 11 14 28 27 29 26 in the Rio Grande River Basin de consultores Challhuamayu, La Cañada y Guadalupe INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MMAYA -PPCR -F2 -CCV N002 -2015 / Incorporacion de los criterios de ACC -RRD A. Strengthening national en las guias subsectoriales de Ejecución 2016-02- 2016-03- 2016-03- 2016-07- TF / 16083 capacity for climate change Posterior Individual Open 11,500.00 0.00 2016-02-15 elaboracion de proyectos de pendiente 23 08 28 26 adaptation riego de acuerdo al nuevo Reglamento Basico de Preinversion CS-PPCR-INDV-009 / Linea base forestal e identificacion B. Strengthening capacity for de zonas potenciales para la 2018-03- 2018-06- 2018-06- 2018-06- 2018-06- 2018-07- 2018-07- 2018-11- TF / 16083 adaptation to climate change Posterior Individual Open 15,000.00 14,471.78 Firmado 2018-05-24 reforestación a gran escala 29 01 17 15 29 05 30 02 in the Rio Grande River Basin (mayor a 300 has) en la cuenca del Rio Mizque CS-PPCR-INDV-015 / Consultor por producto para la Difusion y capacitación del A. Strengthening national Manual para la toma de 2018-04- 2018-05- 2018-08- 2018-06- 2018-08- 2018-06- 2018-08- 2018-08- TF / 16083 capacity for climate change Posterior Individual Open 20,000.00 14,471.78 Firmado 2018-05-14 Decisiones en Infraestructura 11 22 05 05 15 25 28 24 adaptation Resiliente de proyectos de riego en las Cuencas Piloto del PPCR BO-MAA-63420-CS-INDV / Supervisión Formulacion - B. Strengthening capacity for Actualizacion del Plan Ejecución 2017-11- 2017-11- 2017-12- 2018-08- TF / 16083 adaptation to climate change Posterior Individual Open 100,000.00 0.00 2017-10-25 Director de la Cuenca del rio pendiente 02 16 06 03 in the Rio Grande River Basin Rocha, con enfoque de adaptacion al cambio climatico MMAYA -PPCR -F2 -CIP - 001 -2017 / Consultor Individual por Producto para C. Design and la Supervision del Equipo implementation of Tecnico para la Formulacion Ejecución 2017-09- 2017-10- 2017-10- 2018-06- TF / 18119 subprojects that improve Posterior Individual Open 100,000.00 0.00 2017-09-11 de la Actualizacion del Plan pendiente 19 03 23 20 climate resilience in the Rio Director de la Cuenca del Rio Grande River Basin Rocha con Enfoque de Adaptacion al Cambio Climatico -ACC - CS-PPCR-INDV-001A / A. Strengthening national Consultor Individual de Linea 2018-06- 2018-07- 2018-07- 2018-08- 2018-07- 2020-06- TF / 16083 capacity for climate change Posterior Individual Open 101,444.00 1,911.72 En ejecución 2018-05-15 Especialista en Riego e 17 22 01 17 21 30 adaptation Infraestructura Hidráulica MMAYA -PPCR -F2 SSFN 006 -2016 / Estructuracion del A. Strengthening national Selección directa Ejecución 2016-04- 2016-06- 2016-09- Sistema Nacional de TF / 16083 capacity for climate change Posterior Direct 32,903.00 0.00 2016-04-08 de consultores pendiente 18 22 20 Informacion sobre Clima y adaptation Agua -SNICA - en Bolivia CIL-CC-C2-D-3-2 / C. Design and Consultor Individual de Linea implementation of 2020-06- 2018-06- 2018-06- 2018-07- 2020-06- Especialista y responsable de TF / 18119 subprojects that improve Posterior Individual Open 29,843.00 0.00 En ejecución 2018-06-13 12 21 26 06 30 los procesos de preinversion climate resilience in the Rio PPCR Mizque Grande River Basin C. Design and CIL-CC-C2-D-3-3 / implementation of Consultor Individual de Linea 2020-06- 2018-07- 2018-06- 2018-07- 2018-08- 2018-07- 2018-08- 2020-08- TF / 18119 subprojects that improve Posterior Individual Open 29,843.00 4,169.23 Firmado 2018-06-28 Especialista Hidráulico PPCR - 12 09 10 11 09 16 21 23 climate resilience in the Rio SDC Grande River Basin C. Design and CIL-CC-C2-D-3-4 / implementation of Consultor Individual de Linea 2020-06- 2017-05- 2017-03- 2017-06- 2017-03- 2017-06- 2017-05- 2020-06- TF / 18119 subprojects that improve Posterior Individual Open 48,082.00 9,483.59 Firmado 2017-05-15 Coordinador Unidad Técnica 12 23 16 06 31 26 12 30 climate resilience in the Rio PPCR Rocha Grande River Basin CIL-CC-C2-D-3-5 / C. Design and Consultor Individual de Linea implementation of 2020-06- 2017-05- 2017-03- 2017-06- 2017-03- 2017-06- 2017-05- 2020-06- Especialista y Responsable de TF / 18119 subprojects that improve Posterior Individual Open 30,649.00 6,054.02 Firmado 2017-05-15 12 23 19 06 31 30 12 30 los Procesos de Preinversion climate resilience in the Rio PPCR Rocha Grande River Basin C. Design and CIL-CC-C2-D-3-6 / implementation of Consultor Individual de Linea 2020-06- 2017-05- 2017-03- 2017-06- 2017-03- 2017-06- 2017-05- 2020-06- TF / 18119 subprojects that improve Posterior Individual Open 48,082.00 9,672.36 Firmado 2017-05-15 Responsable Unidad 12 23 19 06 31 26 12 30 climate resilience in the Rio Financiera PPCR Grande River Basin CIL-CC-C2-D-3-7 / C. Design and Consultor Individual de Linea implementation of 2020-06- 2018-06- 2018-06- 2018-07- 2021-06- Responsable Unidad TF / 18119 subprojects that improve Posterior Individual Open 48,082.00 0.00 En ejecución 2018-05-31 12 08 22 12 30 Adquisiciones y climate resilience in the Rio Contrataciones PPCR Grande River Basin C. Design and CIL-CC-C2-D-3-8 / implementation of 2020-06- 2017-05- 2017-05- 2017-06- 2020-06- Consultor Individual de Línea TF / 18119 subprojects that improve Posterior Individual Open 30,649.00 0.00 En ejecución 2017-05-15 12 23 30 13 30 Responsable Jurídico PPCR climate resilience in the Rio Grande River Basin C. Design and CIL-CC-C2-D-3-9 / implementation of Consultor Individual de Linea 2020-06- 2018-06- 2018-04- 2018-06- 2018-04- 2018-07- 2018-05- 2020-06- TF / 18119 subprojects that improve Posterior Individual Open 46,816.00 6,894.05 Firmado 2018-05-31 Especialista Social PPCR - 12 08 15 22 27 12 25 30 climate resilience in the Rio SDC Grande River Basin C. Design and CIL-CC-C2-D-3-10 / implementation of Consultor Individual de Linea 2020-06- 2018-06- 2018-06- 2018-06- 2018-06- 2018-07- 2018-06- 2020-06- TF / 18119 subprojects that improve Posterior Individual Open 46,816.00 5,793.59 Firmado 2018-05-31 Especialista Ambiental PPCR - 12 08 10 22 18 12 29 30 climate resilience in the Rio SDC Grande River Basin C. Design and CIL-CC-C2-D-3-11 / implementation of Consultor Individual de Linea 2018-08- 2018-08- 2018-11- 2018-08- 2018-11- 2018-08- 2018-11- 2020-08- TF / 18119 subprojects that improve Posterior Individual Open 28,455.00 1,068.09 Firmado 2018-07-24 Especialista Hidráulico PPCR - 22 01 06 08 15 22 27 05 climate resilience in the Rio Mizque Grande River Basin C. Design and CIL-CC-C2-D-3-12 / implementation of Consultor Individual de Linea 2020-06- 2018-08- 2018-10- 2018-08- 2018-10- 2018-09- 2018-11- 2020-06- TF / 18119 subprojects that improve Posterior Individual Open 39,096.00 1,772.01 Firmado 2018-07-26 Coordinador Unidad Técnica 12 03 14 17 29 06 19 30 climate resilience in the Rio PPCR Arque Tapacari Grande River Basin CIL-CC-C2-D-3-13 / C. Design and Consultor Individual de linea implementation of 2020-06- 2018-08- 2018-10- 2018-08- 2018-10- 2018-09- 2018-11- 2020-08- Especialista y responsable de TF / 18119 subprojects that improve Posterior Individual Open 25,163.00 1,057.06 Firmado 2018-07-24 12 01 14 15 29 04 22 05 los procesos de preinversion climate resilience in the Rio PPCR Arque-Tapacari Grande River Basin CIP-CC-C2-C-3-39 / C. Design and Supervision Componente implementation of Estructural -Conservación y 2020-06- 2018-07- 2018-11- 2018-07- 2018-11- 2018-08- 2018-12- 2019-04- TF / 18119 subprojects that improve Posterior Individual Open 9,451.00 9,389.86 Firmado 2018-07-02 Control de la Microcuenca 12 10 18 24 29 13 10 10 climate resilience in the Rio Arenales - Municipio de Grande River Basin Omereque Page 7 CIP-CC-C2-C-3-40 / C. Design and Supervision Componente implementation of Estructural -Conservación y 2020-07- 2018-07- 2018-09- 2018-07- 2018-10- 2018-08- 2018-10- 2019-04- TF / 18119 subprojects that improve Posterior Individual Open 8,184.00 8,142.42 Firmado 2018-07-02 Control de la Microcuenca 09 10 17 24 10 13 18 10 climate resilience in the Rio Mokontullo - Municipio de Grande River Basin Mizque CIP-CC-C2-C-3-41 / C. Design and Supervision Componente implementation of 2020-07- 2018-07- 2018-07- 2018-07- 2018-07- 2018-08- 2018-10- 2019-04- Estructural -Conservación y TF / 18119 subprojects that improve Posterior Individual Open 8,815.00 8,757.71 Firmado 2018-07-02 09 10 08 24 25 13 31 10 Control de la Microcuenca - climate resilience in the Rio Municipio de Totora Grande River Basin CIP-CC-C2-C-3-42 / C. Design and Supervision Componente implementation of Ejecución 2018-10- 2018-11- 2018-12- 2019-07- Estructural -Conservación y TF / 18119 subprojects that improve Posterior Individual Open 34,000.00 0.00 2018-10-22 pendiente 30 13 03 31 Control de la Microcuenca climate resilience in the Rio Panama Grande River Basin CIP-CC-C2-C-3-43 / C. Design and Supervision Componente implementation of Ejecución 2018-08- 2018-09- 2018-09- 2019-05- Estructural -Conservación y TF / 18119 subprojects that improve Posterior Individual Open 32,684.00 0.00 2018-08-15 pendiente 23 06 26 24 Control de la Microcuenca climate resilience in the Rio Challwani Grande River Basin CIP-CC-C2-C-3-44 / C. Design and Supervision Componente implementation of 2018-08- 2018-09- 2018-09- 2019-05- Estructural -Conservación y TF / 18119 subprojects that improve Posterior Individual Open 29,750.00 0.00 Cancelado 2018-08-15 23 06 26 24 Control de la Microcuenca climate resilience in the Rio Laka Laka. Grande River Basin CIP-CC-C2-C-3-45 / C. Design and Supervision Componente implementation of 2018-08- 2018-09- 2018-09- 2019-05- Estructural -Conservación y TF / 18119 subprojects that improve Posterior Individual Open 29,750.00 0.00 Cancelado 2018-08-15 23 06 26 24 Control de la Microcuenca climate resilience in the Rio Millu Mayu Grande River Basin CIP-CC-C2-C-3-46 / C. Design and Supervision Componente implementation of 2018-08- 2018-09- 2018-09- 2019-05- Estructural -Conservación y TF / 18119 subprojects that improve Posterior Individual Open 29,750.00 0.00 Cancelado 2018-08-15 23 06 26 24 Control de la Microcuenca climate resilience in the Rio Rinconada Tolata Grande River Basin CIP-CC-C2-C-3-47 / C. Design and Supervision Componente implementation of Estructural -Conservación y 2018-08- 2018-09- 2018-09- 2019-05- TF / 18119 subprojects that improve Posterior Individual Open 35,000.00 0.00 Cancelado 2018-08-15 Control de la Microcuenca 23 06 26 24 climate resilience in the Rio Intinimayu y Gestion Integral Grande River Basin de recursos Hídricos CIP-CC-C2-C-3-49 / C. Design and Supervision Componente implementation of Ejecución 2018-08- 2018-09- 2018-09- 2019-05- Estructural -Conservación y TF / 18119 subprojects that improve Posterior Individual Open 35,000.00 0.00 2018-08-15 pendiente 23 06 26 24 Control de la Microcuenca climate resilience in the Rio Samancha Grande River Basin C. Design and CIP-CC-C2-C-3-55 / implementation of Supervision Manejo Integral 2018-09- 2018-10- 2018-10- 2019-06- TF / 18119 subprojects that improve Posterior Individual Open 34,018.00 0.00 Cancelado 2018-09-12 de la Microcuenca Acero 20 04 24 21 climate resilience in the Rio Kocha Grande River Basin C. Design and CIP-CC-C2-C-3-56 / implementation of Ejecución 2018-09- 2018-10- 2018-10- 2019-06- Supervision Manejo Integral TF / 18119 subprojects that improve Posterior Individual Open 31,597.00 0.00 2018-09-12 pendiente 20 04 24 21 de la Microcuenca Collpas climate resilience in the Rio Grande River Basin C. Design and CIP-CC-C2-C-3-57 / implementation of Ejecución 2018-09- 2018-10- 2018-10- 2019-06- Supervision Manejo Integral TF / 18119 subprojects that improve Posterior Individual Open 31,313.00 0.00 2018-09-12 pendiente 20 04 24 21 de la Microcuenca Koturi climate resilience in the Rio Grande River Basin C. Design and CIP-CC-C2-C-3-58 / implementation of 2018-09- 2018-10- 2018-10- 2019-06- Supervision Manejo Integral TF / 18119 subprojects that improve Posterior Individual Open 33,999.00 0.00 Cancelado 2018-09-12 20 04 24 21 de la Microcuenca Pocona climate resilience in the Rio Grande River Basin C. Design and CIP-CC-C2-C-3-59 / implementation of Supervision Manejo Integral Ejecución 2018-09- 2018-10- 2018-10- 2019-06- TF / 18119 subprojects that improve Posterior Individual Open 34,494.00 0.00 2018-09-12 de la Microcuenca Pucara pendiente 20 04 24 21 climate resilience in the Rio mayu Grande River Basin MMAYA/PPCR/CD/001/2018 / SISTEMATIZACION DE LOS RESULTADOS DEL IV FORO A. Strengthening national TALLER RESILIENCIA Y Selección directa 2018-06- 2018-06- 2018-07- 2018-07- TF / 16083 capacity for climate change Posterior Direct 1,581.00 1,569.03 En ejecución 2018-06-29 ADAPTACION AL CAMBIO de consultores 29 29 04 19 adaptation CLIMATICO, Y EVALUACION DE INDICADORES CIF PARA EL PPCR MMAYA -PPCR -SSF -001 - 2017 / Formulacion - B. Strengthening capacity for Actualizacion del Plan Selección directa 2017-08- 2017-10- 2017-09- 2018-01- 2018-01- 2018-09- TF / 16083 adaptation to climate change Posterior Direct 415,277.00 412,272.10 Firmado 2017-08-31 Director de la Cuenca del rio de consultores 10 23 06 31 16 28 in the Rio Grande River Basin Rocha, con enfoque de adaptacion al cambio climatico MMAYA -PPCR -CIL -N 016 - 2017 / Consultor Individual A. Strengthening national 2017-03- 2015-07- 2017-03- 2015-07- 2017-03- 2015-08- 2020-06- de Linea Coordinador del TF / 16083 capacity for climate change Posterior Individual Open 187,780.31 2,504.49 En ejecución 2015-07-01 20 09 22 23 30 12 30 Programa Piloto de adaptation Resiliencia Climática MMAYA -PPCR -CIL -N 019 - 2017 / Consultor Individual A. Strengthening national 2017-02- 2015-07- 2017-02- 2015-07- 2017-03- 2015-08- 2017-04- 2020-06- de Linea Especialista en TF / 16083 capacity for climate change Posterior Individual Open 122,326.14 3,638.21 Firmado 2015-07-01 10 09 20 23 24 12 26 30 Administración Financiera BM adaptation - PPCR MMAYA -PPCR -CIL -N 020 - 2017 / Consultor Individual A. Strengthening national 2017-02- 2016-07- 2017-04- 2016-07- 2017-03- 2016-08- 2017-05- 2020-06- 2019-12- de Linea Especialista en TF / 16083 capacity for climate change Posterior Individual Open 114,364.76 61,256.37 Finalizado 2016-07-01 17 09 19 23 24 12 11 30 31 Adquisiciones y adaptation Contrataciones BM - PPCR MMAYA -PPCR -CIL -N 021 - 2017 / Consultor Individual A. Strengthening national de Linea Especialista en 2016-09- 2016-10- 2017-07- 2016-10- 2017-08- 2016-11- 2017-09- 2020-06- 2018-12- TF / 16083 capacity for climate change Posterior Individual Open 102,009.11 1,880.61 Finalizado 2016-09-23 planificación, monitoreo, 02 01 09 15 09 04 06 30 31 adaptation evaluación y gestión del conocimiento BM-PPCR MMAYA -PPCR -CIL -001 - A. Strengthening national 2018 / Consultor Individual 2018-01- 2015-07- 2018-01- 2015-07- 2018-02- 2015-08- 2018-03- 2020-06- 2019-10- TF / 16083 capacity for climate change Posterior Individual Open 118,235.80 1,880.61 Finalizado 2015-06-30 de Linea Asesor Legal BM - 05 08 07 22 05 11 01 30 20 adaptation PPCR MMAYA -PPCR -CIL -N 023 - 2017 / Consultor Individual A. Strengthening national 2017-01- 2015-07- 2017-02- 2015-07- 2018-04- 2015-08- 2017-05- 2020-06- 2019-12- de Linea Profesional en TF / 16083 capacity for climate change Posterior Individual Open 112,462.81 58,232.46 Finalizado 2015-06-30 10 08 21 22 04 11 25 30 31 Adquisiciones y adaptation Contrataciones BM - PPCR CS-PPCR-INDV-000 / Consultor Individual de Linea A. Strengthening national 2014-03- 2015-07- 2014-03- 2015-07- 2014-04- 2015-08- 2014-06- 2020-06- Profesional Técnico BM - TF / 16083 capacity for climate change Posterior Individual Open 127,810.57 1,389.29 Firmado 2015-06-30 05 08 20 22 22 11 06 30 PPCR - Encargado del adaptation seguimiento a las Consultorías por Producto MMAYA -PPCR -F2 -CIL - A. Strengthening national 025 -2017 / Consultor 2017-12- 2015-07- 2017-12- 2015-07- 2018-01- 2015-08- 2018-02- 2020-06- TF / 16083 capacity for climate change Posterior Individual Open 111,547.28 1,625.90 En ejecución 2015-06-30 Individual de Linea 13 08 17 22 26 11 01 30 adaptation Profesional Contable BM - PPCR MMAYA -PPCR -CIL -002 - 2018 / Consultor Individual A. Strengthening national de Linea Profesional 2018-03- 2016-05- 2018-03- 2016-06- 2018-04- 2016-06- 2020-04- 2020-06- TF / 16083 capacity for climate change Posterior Individual Open 105,384.99 1,812.01 Firmado 2016-05-18 Encargado en Sistemas 21 26 25 09 09 29 17 30 adaptation Informáticos y Geográficos BM - PPCR CS-PPCR-INDV-003 / A. Strengthening national Consultor Individual de Linea 2019-02- 2018-09- 2019-03- 2018-10- 2019-03- 2018-10- 2019-04- 2020-06- TF / 16083 capacity for climate change Posterior Individual Open 41,531.41 2,880.69 Firmado 2018-09-16 Asistente Administrativo 14 24 25 08 28 28 01 30 adaptation Financiero CS-PPCR-INDV-011 / Linea base forestal e identificacion B. Strengthening capacity for de zonas potenciales para la Ejecución 2018-11- 2018-11- 2018-12- 2019-04- TF / 16083 adaptation to climate change Posterior Individual Open 15,000.00 0.00 2018-11-04 reforestacion a gran escala pendiente 12 26 16 15 in the Rio Grande River Basin mayor 300 has - en la cuenca del Rio Arque Tapacari CS-PPCR-INDV-010 / Linea base forestal e identificacion B. Strengthening capacity for de zonas potenciales para la Ejecución 2018-11- 2018-11- 2018-12- 2019-04- TF / 16083 adaptation to climate change Posterior Individual Open 15,000.00 0.00 2018-11-04 reforestacion a gran escala pendiente 12 26 16 15 in the Rio Grande River Basin mayor 300 has - en la cuenca del Rio Rocha BO-MAA-76759-CS-INDV / Evaluación de la aplicabilidad A. Strengthening national de los instrumentos 2019-02- 2019-02- 2019-03- 2019-07- TF / 16083 capacity for climate change Posterior Individual Open 60,000.00 0.00 Cancelado 2019-02-01 desarrollados para la 09 23 10 01 adaptation reducción de Riesgos y la ACC (Manual, Guía de PDC y otros) BO-MAA-76766-CS-INDV / Difusión de las guías de A. Strengthening national Riego y eventos de Ejecución 2018-10- 2018-11- 2018-11- 2020-04- TF / 16083 capacity for climate change Posterior Individual Open 65,000.00 0.00 2018-10-22 Capacitación para el manejo pendiente 30 13 28 17 adaptation de la ficha FIV - ITCP y Manual de infraestructura Resiliente CS-PPCR-INDV-014A / FASE I: Consultor Especialista en Medio Ambiente para la B. Strengthening capacity for Recopilacion, Analisis y 2018-03- 2018-05- 2018-04- 2018-05- 2018-05- 2018-05- 2018-05- 2018-07- TF / 16083 adaptation to climate change Posterior Individual Open 4,374.00 4,341.53 Firmado 2018-04-27 Evaluacion de Informacion 28 05 22 06 04 08 08 07 in the Rio Grande River Basin para la Elaboracion del Plan Director de la Cuenca del Rio Arque Tapacari CS-PPCR-INDV-012 / FASE I: Consultor Articulador Estrategico para la B. Strengthening capacity for Recopilacion, Analisis y 2018-03- 2018-05- 2018-04- 2018-05- 2018-04- 2018-05- 2018-05- 2018-07- TF / 16083 adaptation to climate change Posterior Individual Open 8,747.00 8,683.07 Firmado 2018-04-25 Evaluacion de Informacion 27 03 08 04 20 08 08 07 in the Rio Grande River Basin para la Elaboracion del Plan Director de la Cuenca del Rio Arque Tapacari CS-PPCR-INDV-013A / FASE I: Consultor Especialista Hidrólogo para la B. Strengthening capacity for Recopilacion, Analisis y 2018-03- 2018-05- 2018-04- 2018-05- 2018-05- 2018-05- 2018-05- 2018-07- TF / 16083 adaptation to climate change Posterior Individual Open 5,831.00 5,788.71 Firmado 2018-04-26 Evaluacion de Informacion 28 04 22 16 04 21 17 20 in the Rio Grande River Basin para la Elaboracion del Plan Director de la Cuenca del Rio Arque Tapacari Page 8 CS-PPCR-INDV-006 / Evaluacion de la aplicabilidad A. Strengthening national 2018-09- 2018-09- 2018-09- 2018-12- de la Guia para la TF / 16083 capacity for climate change Posterior Individual Open 30,000.00 0.00 Cancelado 2018-08-30 07 14 30 29 planificacion de adaptation intervenciones en cuencas piloto C. Design and CIL-CC-C2-D-3-1 / implementation of Consultor Individual de Linea 2020-06- 2017-05- 2017-03- 2017-05- 2017-03- 2017-06- 2017-05- 2020-06- TF / 18119 subprojects that improve Posterior Individual Open 48,082.00 9,672.36 Firmado 2017-05-15 Coordinador Unidad Técnica 12 23 19 30 31 14 12 30 climate resilience in the Rio PPCR Mizque Grande River Basin CS-PPCR-INDV-014B / B. Strengthening capacity for Evaluacion de Indicadores de 2018-09- 2018-10- 2018-10- 2019-02- TF / 16083 adaptation to climate change Posterior Individual Open 12,000.00 0.00 Cancelado 2018-09-11 Eficiencia en Sistemas de 19 03 23 20 in the Rio Grande River Basin riego mejorados CS-PPCR-INDV-008 / A. Strengthening national Estudio de sistemas de riego 2018-10- 2018-10- 2018-11- 2019-02- TF / 16083 capacity for climate change Posterior Individual Open 10,000.00 0.00 Cancelado 2018-10-01 tecnificado como medida de 09 23 12 10 adaptation resiliencia y ACC CS-PPCR-INDV-001B / Consultor Individual de Linea A. Strengthening national 2019-04- 2018-09- 2019-05- 2018-09- 2019-05- 2018-10- 2019-05- 2020-06- Profesional Técnico BM - TF / 16083 capacity for climate change Posterior Individual Open 65,664.84 14,454.91 Firmado 2018-08-30 26 07 08 21 08 11 14 30 PPCR - Encargado del adaptation seguimiento a los MICs BO-MAA-81494-CS-INDV / SUPERVISIÓN TÉCNICA A LA C. Design and ELABORACIÓN DE ESTUDIOS implementation of DE DISEÑO TÉCNICO DE 2018-11- 2018-10- 2019-05- 2018-11- 2019-06- 2018-11- 2019-06- 2019-02- TF / 18119 subprojects that improve Posterior Individual Open 9,250.00 9,150.33 Firmado 2018-10-22 PREINVERSIÓN PARA LA 06 30 19 09 10 19 26 17 climate resilience in the Rio CONSTRUCCIÓN DE Grande River Basin DEFENSIVOS EN EL MUNICIPIO DE MIZQUE BO-MAA-81495-CS-INDV / SUPERVISIÓN SOCIAL A LA C. Design and ELABORACIÓN DE ESTUDIOS implementation of DE DISEÑO TÉCNICO DE 2018-11- 2018-10- 2018-11- 2018-11- 2019-02- TF / 18119 subprojects that improve Posterior Individual Open 8,000.00 0.00 En ejecución 2018-10-22 PREINVERSIÓN PARA LA 06 30 09 19 17 climate resilience in the Rio CONSTRUCCIÓN DE Grande River Basin DEFENSIVOS EN EL MUNICIPIO DE MIZQUE BO-MAA-81496-CS-INDV / SUPERVISIÓN TÉCNICA A LA C. Design and "ELABORACIÓN DE ESTUDIOS implementation of DE DISEÑO TÉCNICO DE 2019-02- 2018-10- 2019-05- 2018-11- 2019-06- 2018-11- 2019-06- 2019-02- TF / 18119 subprojects that improve Posterior Individual Open 7,200.00 7,129.51 Firmado 2018-10-22 PREINVERSION PARA LA 28 30 20 09 10 19 26 17 climate resilience in the Rio CONSTRUCCIÓN DE Grande River Basin DEFENSIVOS EN EL MUNICIPIO DE OMEREQUE" BO-MAA-81497-CS-INDV / SUPERVISIÓN SOCIAL A LA C. Design and "ELABORACIÓN DE ESTUDIOS implementation of DE DISEÑO TÉCNICO DE 2019-01- 2018-10- 2018-11- 2018-11- 2019-02- TF / 18119 subprojects that improve Posterior Individual Open 6,000.00 0.00 En ejecución 2018-10-22 PREINVERSION PARA LA 31 30 09 19 17 climate resilience in the Rio CONSTRUCCIÓN DE Grande River Basin DEFENSIVOS EN EL MUNICIPIO DE OMEREQUE" BO-MAA-81619-CS-INDV / SUPERVISIÓN TÉCNICA A LA C. Design and "ELABORACIÓN DE ESTUDIO implementation of DE DISEÑO TÉCNICO DE 2018-11- 2018-10- 2019-12- 2018-11- 2020-01- 2018-11- 2020-02- 2019-05- TF / 18119 subprojects that improve Posterior Individual Open 8,700.00 8,655.84 Firmado 2018-10-22 PREINVERSIÓN PARA LA 21 30 28 13 16 25 10 24 climate resilience in the Rio CONSTRUCCIÓN DE Grande River Basin DEFENSIVOS EN EL MUNICIPIO DE TOTORA Y POCONA" BO-MAA-82024-CS-INDV / A. Strengthening national Difusión y Capacitación de las 2018-10- 2018-11- 2018-11- 2018-12- TF / 16083 capacity for climate change Posterior Individual Limited 12,000.00 0.00 Cancelado 2018-10-25 Guías de Riego: Santa Cruz - 30 07 19 19 adaptation Cochabamba BO-MAA-82204-CS-INDV / A. Strengthening national 2018-10- 2018-11- 2018-11- 2018-12- Difusión y Capacitación de las TF / 16083 capacity for climate change Posterior Individual Limited 12,000.00 0.00 Cancelado 2018-10-26 31 03 13 13 Guías de Riego: La Paz - adaptation Oruro BO-MAA-82206-CS-INDV / A. Strengthening national Difusión y Capacitación de las 2018-11- 2018-11- 2018-11- 2018-12- TF / 16083 capacity for climate change Posterior Individual Limited 18,000.00 0.00 Cancelado 2018-10-29 Guías de Riego: Potosí - 01 08 18 18 adaptation Chuquisaca - Tarija BO-MAA-76764-CS-INDV / A. Strengthening national 2018-11- 2018-09- 2018-10- 2018-10- 2019-03- Actualización del software TF / 16083 capacity for climate change Posterior Individual Open 70,000.00 0.00 Cancelado 2018-09-10 08 18 02 17 11 Abro - Área bajo riego adaptation optimo BO-MAA-76754-CS-INDV / Desarrollo Investigativo del A. Strengthening national 2018-09- 2018-10- 2018-10- 2019-05- indicador de evaluación de TF / 16083 capacity for climate change Posterior Individual Open 50,000.00 0.00 Cancelado 2018-09-14 22 06 21 15 desempeño de riego área adaptation cultivada bajo Riego BO-MAA-82539-CS-INDV / Elaboración de la Guía de A. Strengthening national 2018-11- 2018-11- 2018-12- 2019-01- Evaluación expost de TF / 16083 capacity for climate change Posterior Individual Open 30,000.00 0.00 Cancelado 2018-11-05 15 25 09 08 Defensivos para el Sector de adaptation Recursos Hidricos y y Riego BO-MAA-82744-CS-INDV / ARTICULADOR ESTRATÉGICO PARA LA ELABORACIÓN DEL B. Strengthening capacity for PLAN DIRECTOR DE LA 2019-06- 2018-11- 2018-11- 2018-12- 2019-07- TF / 16083 adaptation to climate change Posterior Individual Open 50,000.00 0.00 En ejecución 2018-10-29 CUENCA ARQUE TAPACARÍ, 27 08 22 06 04 in the Rio Grande River Basin BAJO UN ENFOQUE DE ADAPTACIÓN AL CAMBIO CLIMÁTICO BO-MAA-82748-CS-INDV / CONSULTOR ESPECIALISTA AGRONOMO/AMBIENTAL B. Strengthening capacity for PARA LA ELABORACIÓN DEL 2019-08- 2018-11- 2018-11- 2018-12- 2019-07- TF / 16083 adaptation to climate change Posterior Individual Open 25,000.00 0.00 En ejecución 2018-10-29 PLAN DIRECTOR DE LA 15 08 22 06 04 in the Rio Grande River Basin CUENCA DEL RÍO ARQUE TAPACARÍ, BAJO UN ENFOQUE DE ADAPTACIÓN AL CAMBIO CLIMÁTICO BO-MAA-82756-CS-INDV / ESPECIALISTA EN RECURSOS HIDRICOS PARA LA B. Strengthening capacity for ELABORACIÓN DEL PLAN 2019-08- 2018-11- 2018-11- 2018-12- 2019-07- TF / 16083 adaptation to climate change Posterior Individual Open 28,000.00 0.00 En ejecución 2018-10-29 DIRECTOR DE LA CUENCA 09 08 22 06 04 in the Rio Grande River Basin DEL RÍO ARQUE TAPACARI, BAJO UN ENFOQUE DE ADAPTACIÓN AL CAMBIO CLIMÁTICO BO-MAA-82760-CS-INDV / ESPECIALISTA EN GESTIÓN MUNICIPAL O DESARROLLO RURAL PARA LA B. Strengthening capacity for 2019-06- 2018-11- 2018-11- 2018-12- 2019-07- ELABORACIÓN DEL PLAN TF / 16083 adaptation to climate change Posterior Individual Open 32,000.00 0.00 Cancelado 2018-10-29 27 08 22 06 04 DIRECTOR DE LAS CUENCAS in the Rio Grande River Basin ARQUE Y TAPACARÍ, BAJO UN ENFOQUE DE ADAPTACIÓN AL CAMBIO CLIMÁTICO BO-MAA-82762-CS-INDV / ESPECIALISTA EN DESARROLLO SIG Y BASE DE B. Strengthening capacity for DATOS PARA LA 2019-08- 2018-11- 2018-11- 2018-12- 2019-07- TF / 16083 adaptation to climate change Posterior Individual Open 25,000.00 0.00 En ejecución 2018-10-29 ELABORACIÓN DEL PLAN 09 08 22 06 04 in the Rio Grande River Basin DIRECTOR DE LA CUENCA DEL RÍO ARQUE TAPACARI, BAJO UN ENFOQUE DE ADAPTACIÓN AL CAMBIO CLIMÁTICO BO-MAA-82764-CS-INDV / CONSULTOR ESPECIALISTA GEOLOGO PARA LA B. Strengthening capacity for ELABORACIÓN DEL PLAN 2019-08- 2018-11- 2018-11- 2018-12- 2019-03- TF / 16083 adaptation to climate change Posterior Individual Open 20,000.00 0.00 Cancelado 2018-10-29 DIRECTOR DE LA CUENCA 12 08 22 06 06 in the Rio Grande River Basin DEL RÍO ARQUE TAPACARÍ, BAJO UN ENFOQUE DE ADAPTACIÓN AL CAMBIO CLIMÁTICO BO-MAA-82770-CS-INDV / SUPERVISIÓN PARA LA ELABORACIÓN DEL PLAN B. Strengthening capacity for 2019-08- 2018-11- 2018-11- 2018-12- 2019-07- DIRECTOR DE LA CUENCA TF / 16083 adaptation to climate change Posterior Individual Open 35,000.00 0.00 En ejecución 2018-10-29 01 08 22 06 04 DEL RÍO ARQUE TAPACARÍ, in the Rio Grande River Basin BAJO UN ENFOQUE DE ADAPTACIÓN AL CAMBIO CLIMÁTICO CS-PPCR-INDV-013B / Fase II Formulacion del Plan B. Strengthening capacity for Director de la Cuenca Arque 2018-07- 2018-07- 2018-07- 2019-01- TF / 16083 adaptation to climate change Posterior Individual Open 200,000.00 0.00 Cancelado 2018-07-03 Tapacari, con enfoque de 11 18 28 24 in the Rio Grande River Basin adaptacion al cambio climatico CIL-CC-C2-D-3-14 / C. Design and Consultor Individual de Linea implementation of 2019-04- 2018-12- 2019-04- 2018-12- 2019-04- 2019-01- 2019-04- 2020-06- Especialista y Responsable de TF / 18119 subprojects that improve Posterior Individual Open 18,453.00 7,832.68 Firmado 2018-11-22 02 02 10 16 22 09 26 30 los Procesos de Inversión climate resilience in the Rio PPCR Rocha Grande River Basin CIL-CC-C2-D-3-15 / C. Design and Consultor Individual de Linea implementation of Ejecución 2018-12- 2018-12- 2019-01- 2020-06- Gestor de los Procesos de TF / 18119 subprojects that improve Posterior Individual Open 18,453.00 0.00 2018-11-26 pendiente 06 20 17 30 Preinversión e Inversión PPCR climate resilience in the Rio Rocha Grande River Basin C. Design and CIL-CC-C2-D-3-16 / implementation of Consultor Individual de Linea 2019-02- 2018-12- 2019-03- 2018-12- 2019-03- 2019-01- 2019-04- 2020-06- TF / 18119 subprojects that improve Posterior Individual Open 13,931.00 5,628.19 Firmado 2018-11-23 Apoyo Administrativo 04 03 10 17 21 14 02 30 climate resilience in the Rio Financiero PPCR Grande River Basin C. Design and BO-MAA-82810-CS-INDV / implementation of Consultor Linea Responsable 2018-12- 2018-10- 2018-11- 2018-11- 2018-12- TF / 18119 subprojects that improve Posterior Individual Open 1,678.00 0.00 En ejecución 2018-10-22 en Hidrometeorologia PPCR- 06 30 04 06 31 climate resilience in the Rio SDC Grande River Basin MMAYA-PPCR-CD-002- 2018 / Consultoria Individual por Producto para la Difusion A. Strengthening national Selección directa 2017-10- 2017-11- 2017-12- y Capacitacion del Manual TF / 16083 capacity for climate change Posterior Direct 38,500.00 34,732.27 En ejecución 2017-10-16 de consultores 26 14 22 para la Toma de Decisiones adaptation en Infraestructura Resiliente de Proyectos de Riego BO-MAA-86454-CS-INDV / CONSULTOR PARA LA DIFUSIÓN Y CAPACITACIÓN DE LAS NUEVAS GUÍAS PARA A. Strengthening national LA ELABORACIÓN DE 2018-11- 2018-12- 2019-01- 2019-01- 2019-03- TF / 16083 capacity for climate change Posterior Individual Open 17,500.00 0.00 En ejecución 2018-11-30 ESTUDIOS DE DISEÑO 22 15 05 25 06 adaptation TÉCNICO DE PREINVERSIÓN DE PROYECTOS DE RIEGO (MENORES, MEDIANOS Y MAYORES) Page 9 CIL-CC-C2-D-3-17 / C. Design and CONSULTOR INDIVIDUAL DE implementation of 2020-10- 2019-02- 2019-02- 2019-02- 2020-06- LINEA ESPECIALISTA TF / 18119 subprojects that improve Posterior Individual Open 17,567.00 0.00 Bajo Revision 2019-01-28 01 05 08 12 30 HIDRÁULICO PPCR- climate resilience in the Rio ARQUE/TAPACARI Grande River Basin CIP-CC-C2-C-3-60 / C. Design and SUPERVISIÓN TÉCNICA - implementation of MANEJO INTEGRAL DE LA 2019-03- 2019-02- 2019-04- 2019-02- 2019-04- 2019-02- 2019-05- 2020-06- TF / 18119 subprojects that improve Posterior Individual Open 27,988.00 27,846.26 Firmado 2019-01-28 CUENCA INTINIMAYU Y 19 05 14 08 23 12 10 30 climate resilience in the Rio GESTIÓN INTEGRAL DE Grande River Basin RECURSOS HIDRICOS MMAYA/PPCR/CIL/003/2019 A. Strengthening national / CONSULTOR DE LINEA 2020-01- 2019-01- 2019-01- 2019-02- 2019-02- 2019-03- 2019-03- 2020-06- 2019-12- TF / 16083 capacity for climate change Posterior Individual Open 32,737.00 19,525.90 Finalizado 2019-01-21 PROFESIONAL TÉCNICO BM - 09 30 13 09 21 01 01 30 31 adaptation PPCR MMAYA/PPCR/CIL/002/2019 / CONSULTOR DE LINEA A. Strengthening national 2019-01- 2019-01- 2019-01- 2019-02- 2019-02- 2019-03- 2019-02- 2020-06- "ESPECIALISTA EN RIEGO E TF / 16083 capacity for climate change Posterior Individual Open 33,976.00 1,984.08 Firmado 2019-01-21 09 30 20 09 04 01 06 30 INFRAESTRUCTURA adaptation HIDRAULICA BM - PPCR" MMAYA/PPCR/CIP/004/2019 / CONSULTOR DE LINEA A. Strengthening national "ESPECIALISTA EN Ejecución 2019-01- 2019-02- 2019-03- 2020-06- TF / 16083 capacity for climate change Posterior Individual Open 33,976.00 0.00 2019-01-21 PLANIFICACIÓN, MONITOREO, pendiente 30 09 01 30 adaptation EVALUACIÓN Y GESTIÓN DEL CONOCIMIENTO BM - PPCR" CIL-CC-C2-D-3-18 / C. Design and Consultor Individual de Linea implementation of 2020-10- 2019-01- 2019-01- 2019-02- 2020-06- Especialista y Responsable de TF / 18119 subprojects that improve Posterior Individual Open 14,301.00 0.00 En ejecución 2019-01-28 01 29 30 01 30 los Procesos de Preinversión climate resilience in the Rio PPCR Rocha Grande River Basin C. Design and CIL-CC-C2-D-3-19 / implementation of Consultor Individual de Linea 2019-03- 2019-02- 2019-03- 2019-02- 2019-04- 2019-02- 2019-04- 2020-06- 2019-12- TF / 18119 subprojects that improve Posterior Individual Open 14,301.00 8,855.55 Finalizado 2019-02-01 Profesional de Adquisiciones 08 01 28 13 01 20 05 30 31 climate resilience in the Rio y Contrataciones PPCR Grande River Basin CIP-CC-C2-C-3-61 / Supervisión Componente No C. Design and Estructural Conservación y implementation of Ejecución 2019-02- 2019-03- 2019-03- 2020-04- Control de las Microcuencas TF / 18119 subprojects that improve Posterior Individual Open 36,449.00 0.00 2019-02-20 pendiente 24 11 25 23 Mokontullo, Moyapampa y climate resilience in the Rio Arenales en la Cuenca del Rio Grande River Basin Mizque C. Design and CIL-CC-C2-D-3-20 / implementation of Consultor Individual de Linea 2019-02- 2019-02- 2019-03- 2019-02- 2019-03- 2019-03- 2019-03- 2020-06- TF / 18119 subprojects that improve Posterior Individual Open 15,616.00 6,916.39 Firmado 2019-02-15 Especialista y Responsable 25 15 03 23 18 01 26 30 climate resilience in the Rio Juridico PPCR Grande River Basin CIP-CC-C2-C-3-64 / C. Design and Supervisión Tecnica implementation of 2020-06- 2019-04- 2019-03- 2019-04- 2019-04- 2019-04- 2019-04- 2019-11- Componente Estructural TF / 18119 subprojects that improve Posterior Individual Open 17,553.06 17,382.45 Firmado 2019-02-28 12 08 24 10 17 15 30 11 Manejo Integral de la Cuenca climate resilience in the Rio Rinconada Grande River Basin CIP-CC-C2-C-3-65 / C. Design and Supervisión Tecnica implementation of 2020-07- 2019-04- 2019-03- 2019-04- 2019-05- 2019-04- 2019-05- 2019-11- Componente Estructural TF / 18119 subprojects that improve Posterior Individual Open 10,633.67 8,701.96 Firmado 2019-02-28 09 08 24 10 06 15 17 11 Manejo Integral de la Cuenca climate resilience in the Rio Millu Mayu Grande River Basin CIP-CC-C2-C-3-66 / C. Design and Supervisión Técnica implementation of 2020-07- 2019-04- 2019-03- 2019-04- 2019-04- 2019-04- 2019-05- 2019-11- Componente Estructural TF / 18119 subprojects that improve Posterior Individual Open 20,268.95 18,219.29 Firmado 2019-02-28 09 08 24 10 24 15 17 11 Manejo Integral de la Cuenca climate resilience in the Rio Laka Laka Grande River Basin CIP-CC-C2-C-3-67 / C. Design and Supervisión Técnica implementation of 2019-05- 2019-04- 2019-05- 2019-04- 2019-06- 2019-04- 2019-07- 2019-11- Componente No Estructural TF / 18119 subprojects that improve Posterior Individual Open 29,934.40 18,826.94 Firmado 2019-02-28 09 08 26 10 07 15 04 11 Manejo Integral de la Cuenca climate resilience in the Rio Rinconada Grande River Basin CIP-CC-C2-C-3-68 / C. Design and Supervisión Técnica implementation of 2020-07- 2019-04- 2019-05- 2019-04- 2019-06- 2019-04- 2019-07- 2019-11- Componente No Estructural TF / 18119 subprojects that improve Posterior Individual Open 21,469.24 19,551.05 Firmado 2019-02-28 09 08 26 10 24 15 04 11 Manejo Integral de la Cuenca climate resilience in the Rio Millu Mayu Grande River Basin CIP-CC-C2-C-3-69 / C. Design and Supervisión Técnica implementation of 2020-07- 2019-04- 2019-05- 2019-04- 2019-06- 2019-04- 2019-07- 2019-11- Componente No Estructural TF / 18119 subprojects that improve Posterior Individual Open 35,138.63 21,723.39 Firmado 2019-02-28 09 08 26 10 13 15 02 11 Manejo Integral de la Cuenca climate resilience in the Rio Laka Laka Grande River Basin CIP-CC-C2-C-3-48 / C. Design and Supervision Componente implementation of 2018-08- 2018-09- 2018-09- 2019-05- Estructural -Conservación y TF / 18119 subprojects that improve Posterior Individual Open 35,000.00 0.00 Cancelado 2018-08-15 23 06 26 24 Control de la Microcuenca climate resilience in the Rio Carcel Mayu Grande River Basin C. Design and CIP-CC-C2-C-3-62 / implementation of Supervisión Componente 2020-07- 2019-04- 2019-04- 2019-04- 2019-05- 2019-04- 2019-05- 2019-10- TF / 18119 subprojects that improve Posterior Individual Open 12,530.00 12,446.78 Firmado 2019-03-29 Estructural Manejo Integral de 09 03 21 08 08 18 16 21 climate resilience in the Rio la Cuenca Cárcel Mayu Grande River Basin C. Design and CIP-CC-C2-C-3-63 / implementation of Supervisión Componente No 2020-07- 2019-04- 2019-05- 2019-04- 2019-06- 2019-04- 2019-07- 2020-06- TF / 18119 subprojects that improve Posterior Individual Open 24,145.00 22,480.06 Firmado 2019-03-29 Estructural Manejo Integral de 09 03 26 08 14 18 04 17 climate resilience in the Rio la Cuenca Cárcel Mayu Grande River Basin CIP-CC-C2-C-3-70 / Supervisión Técnica C. Design and Elaboración de Estudios de implementation of Ejecución 2019-04- 2019-05- 2019-07- 2019-10- Diseño Técnico de TF / 18119 subprojects that improve Posterior Individual Open 5,798.00 0.00 2019-04-05 pendiente 22 13 31 29 Preinversión Manejo Integral climate resilience in the Rio de Cuenca Pukara Mayu Grande River Basin (Cuchumuela) CIP-CC-C2-C-3-71 / Supervisión Técnica C. Design and Elaboración de Estudios de implementation of Ejecución 2019-04- 2019-05- 2019-07- 2019-10- Diseño Técnico de TF / 18119 subprojects that improve Posterior Individual Open 5,609.00 0.00 2019-04-05 pendiente 22 13 31 29 Preinversión Manejo Integral climate resilience in the Rio de la Microcuenca Qocha Grande River Basin Qocha - Buena Vista CIP-CC-C2-C-3-72 / Supervisión Técnica C. Design and Elaboración de Estudios de implementation of 2019-04- 2019-05- 2019-07- 2019-10- Diseño Técnico de TF / 18119 subprojects that improve Posterior Individual Open 4,586.00 0.00 Cancelado 2019-04-05 22 13 31 29 Preinversión Manejo Integral climate resilience in the Rio de la Microcuenca Torancali Grande River Basin Challamayu CIP-CC-C2-C-3-73 / C. Design and Supervisión Técnica implementation of Elaboración de Estudios de 2019-04- 2019-05- 2019-07- 2019-10- TF / 18119 subprojects that improve Posterior Individual Open 5,269.00 0.00 Cancelado 2019-04-05 Diseño Técnico de 22 13 31 29 climate resilience in the Rio Preinversión Manejo Integral Grande River Basin de Microcuenca Kangani CIP-CC-C2-C-3-74 / C. Design and Supervisión Técnica implementation of Elaboración de Estudios de 2019-04- 2019-05- 2019-07- 2019-10- TF / 18119 subprojects that improve Posterior Individual Open 5,040.09 0.00 Cancelado 2019-04-05 Diseño Técnico de 22 13 31 29 climate resilience in the Rio Preinversión Manejo Integral Grande River Basin de la Cuenca Khora Tiquipaya CIP-CC-C2-C-3-75 / C. Design and Supervisión Técnica implementation of Elaboración de Estudios de 2019-04- 2019-05- 2019-07- 2019-10- TF / 18119 subprojects that improve Posterior Individual Open 7,434.00 0.00 Cancelado 2019-04-05 Diseño Técnico de 22 13 31 29 climate resilience in the Rio Preinversión Manejo Integral Grande River Basin de la Cuenca Taquiña CIP-CC-C2-C-3-76 / C. Design and Supervisión Técnica implementation of Elaboración de Estudios de Ejecución 2019-04- 2019-05- 2019-07- 2019-10- TF / 18119 subprojects that improve Posterior Individual Open 4,150.00 0.00 2019-04-05 Diseño Técnico de pendiente 22 13 31 29 climate resilience in the Rio Preinversión Manejo Integral Grande River Basin de la Microcuenca Kaquerema CIP-CC-C2-C-3-77 / C. Design and Supervisión Técnica implementation of Elaboración de Estudios de Ejecución 2019-04- 2019-05- 2019-07- 2019-10- TF / 18119 subprojects that improve Posterior Individual Open 4,150.00 0.00 2019-04-05 Diseño Técnico de pendiente 22 13 31 29 climate resilience in the Rio Preinversión Manejo Integral Grande River Basin de la Microcuenca Locosti CIP-CC-C2-C-3-78 / Supervisión Técnica C. Design and Elaboración de Estudios de implementation of Ejecución 2019-04- 2019-05- 2019-07- 2019-10- Diseño Técnico de TF / 18119 subprojects that improve Posterior Individual Open 5,609.00 0.00 2019-04-02 pendiente 22 13 31 29 Preinversión Manejo Integral climate resilience in the Rio de la Microcuenca Collpa Grande River Basin Mayu BO-MAA-108668-CS-INDV / A. Strengthening national Consultor Individual para la Ejecución 2019-05- 2019-05- 2019-06- 2019-12- TF / 16083 capacity for climate change Posterior Individual Open 30,000.00 0.00 2019-05-09 Evaluación de Aplicabilidad pendiente 17 31 14 11 adaptation del Manual de Resiliencia BO-MAA-108672-CS-INDV / Actualización del SISMET A. Strengthening national 2019-05- 2019-06- 2019-06- 2019-10- (Incluye análisis y TF / 16083 capacity for climate change Posterior Individual Open 50,000.00 0.00 Cancelado 2019-05-13 21 04 18 16 actualización de la base de adaptation datos) BO-MAA-108733-CS-INDV / Modelamiento para B. Strengthening capacity for inundaciones subcuenca 2019-05- 2019-06- 2019-07- 2020-01- TF / 16083 adaptation to climate change Posterior Individual Open 50,000.00 0.00 Cancelado 2019-05-23 Maylanco (UEE relevara 31 15 06 02 in the Rio Grande River Basin información sobre trabajos similares en la subcuenca) BO-MAA-109191-CS-INDV / Preparación de las B. Strengthening capacity for actividades de 2019-06- 2019-06- 2019-07- 2019-09- TF / 16083 adaptation to climate change Posterior Individual Open 10,000.00 0.00 Cancelado 2019-05-27 fortalecimiento para los OGCs 01 16 15 13 in the Rio Grande River Basin de los MICS ejecutados por el SDC en la Cuenca Piloto del PPCR BO-MAA-109624-CS-INDV / SUPERVISIÓN A LA IMPLEMENTACIÓN DE PROTOCOLOS DE COORDINACIÓN, B. Strengthening capacity for 2019-07- 2019-05- 2019-05- 2019-06- 2020-02- INTEROPERABILIDAD Y TF / 16083 adaptation to climate change Posterior Individual Open 40,000.00 0.00 En ejecución 2019-04-30 24 05 20 18 13 PLATAFORMA INFORMÁTICA in the Rio Grande River Basin DE TRANSFERENCIA DIGITAL DE INFORMACIÓN HIDROMETEOROLOGICA Y CLIMÁTICA CS-PPCR-INDV-004 / A. Strengthening national 2018-09- 2018-09- 2018-10- 2019-01- Asistencia Informatica para la TF / 16083 capacity for climate change Posterior Individual Open 20,000.00 0.00 Cancelado 2018-09-10 18 28 10 08 operativizacion del SNICA adaptation Page 10 CS-PPCR-INDV-005 / Apoyo A. Strengthening national 2018-10- 2018-10- 2018-11- 2019-03- al Desarrollo del Geovisor del TF / 16083 capacity for climate change Posterior Individual Open 30,000.00 0.00 Cancelado 2018-09-28 06 20 09 09 MMAyA adaptation CS-PPCR-INDV-016 / B. Strengthening capacity for Elaboracion de la Estrategia 2018-07- 2018-07- 2018-08- 2018-12- TF / 16083 adaptation to climate change Posterior Individual Open 50,000.00 0.00 Cancelado 2018-06-25 Departamental de Cuencas 03 17 06 04 in the Rio Grande River Basin para el SDC-GAD-CBBA BO-MAA-76763-CS-INDV / A. Strengthening national Desarrollo de la Metodología 2018-09- 2018-10- 2018-10- 2019-03- TF / 16083 capacity for climate change Posterior Individual Open 20,000.00 0.00 Cancelado 2018-09-14 y manual de eficiencias del 22 06 21 14 adaptation sistema de Riego BO-MAA-76757-CS-INDV / Desarrollo del indicador de A. Strengthening national desempeño sobre el aumento 2018-10- 2018-10- 2018-11- 2019-04- TF / 16083 capacity for climate change Posterior Individual Open 15,000.00 0.00 Cancelado 2018-09-25 del ingreso bruto anual por 03 17 01 24 adaptation hectárea con intervención del Riego CS-PPCR-INDV-007 / Desarrollo de instrumentos A. Strengthening national para el seguimiento y 2018-08- 2018-09- 2018-09- 2019-01- TF / 16083 capacity for climate change Posterior Individual Open 35,000.00 0.00 Cancelado 2018-08-16 monitoreo de la ACC en la 24 07 27 25 adaptation planificacion nacional y sectorial BO-MAA-108727-CS-INDV / B. Strengthening capacity for Fortalecimiento de 2019-05- 2019-06- 2019-06- 2019-12- TF / 16083 adaptation to climate change Posterior Individual Open 100,000.00 0.00 Cancelado 2019-05-16 Organizaciones de Gestión de 24 08 25 22 in the Rio Grande River Basin Cuencas BO-MAA-112016-CS-INDV / Fortalecimiento de las capacidades del SENAMHI y B. Strengthening capacity for 2019-05- 2019-06- 2019-06- 2019-09- MMAyA para mantenimiento TF / 16083 adaptation to climate change Posterior Individual Open 80,000.00 0.00 Cancelado 2019-05-23 31 10 30 28 de las estaciones in the Rio Grande River Basin meteorologicas instaladas por el PPCR BO-MAA-108723-CS-INDV / Ajuste de la Guía para la Formulación de Planes A. Strengthening national 2019-05- 2019-05- 2019-06- 2019-06- 2019-12- Directores de Cuenca en el TF / 16083 capacity for climate change Posterior Individual Open 8,000.00 0.00 Cancelado 2019-05-16 28 24 08 22 19 Marco Orientador para la adaptation Formulación del Plan Director de Cuenca del MMAyA C. Design and CIL-CC-C2-D-3-21 / implementation of Consultor Individual de Linea 2019-06- 2019-05- 2019-06- 2019-06- 2019-07- 2019-06- 2019-07- 2020-06- TF / 18119 subprojects that improve Posterior Individual Open 12,688.00 5,146.27 Firmado 2019-05-17 Especializada en Fiscalización 07 31 17 03 02 10 19 30 climate resilience in the Rio de Proyectos PPCR Grande River Basin BO-MAA-81620-CS-INDV / SUPERVISIÓN SOCIAL A LA C. Design and "ELABORACIÓN DE ESTUDIO implementation of DE DISEÑO TÉCNICO DE 2018-11- 2018-10- 2018-11- 2018-11- 2019-05- TF / 18119 subprojects that improve Posterior Individual Open 7,500.00 0.00 Cancelado 2018-10-22 PREINVERSIÓN PARA LA 06 30 13 22 21 climate resilience in the Rio CONSTRUCCIÓN DE Grande River Basin DEFENSIVOS EN EL MUNICIPIO DE TOTORA Y POCONA" BO-MAA-116719-CS-INDV / A. Strengthening national 2019-07- 2019-06- 2019-06- 2019-07- 2019-12- Profesional Técnico el TF / 16083 capacity for climate change Posterior Individual Open 10,368.00 0.00 Cancelado 2019-06-11 29 19 24 04 31 Adquisiciones II adaptation A. Strengthening national BO-MAA-116720-CS-INDV / 2019-08- 2019-06- 2019-10- 2019-06- 2019-10- 2019-07- 2019-10- 2020-01- TF / 16083 capacity for climate change Posterior Individual Open 23,108.00 4,436.95 Firmado 2019-06-12 Profesional Técnico Hidrólogo 07 20 07 27 07 11 24 07 adaptation BO-MAA-116737-CS-INDV / A. Strengthening national Profesional Técnico de 2019-09- 2019-06- 2019-09- 2019-06- 2019-10- 2019-07- 2019-10- 2020-01- TF / 16083 capacity for climate change Posterior Individual Direct 11,554.00 5,099.19 Firmado 2019-06-13 seguimiento de Proyectos 10 23 20 28 01 08 14 04 adaptation MIC III BO-MAA-116722-CS-INDV / A. Strengthening national Profesional Técnico de 2019-06- 2019-06- 2019-06- 2019-06- 2019-06- 2019-07- 2019-06- 2020-01- TF / 16083 capacity for climate change Posterior Individual Direct 11,554.00 1,911.72 Firmado 2019-06-11 Seguimiento a Proyectos MIC 06 23 10 28 11 08 13 04 adaptation II BO-MAA-116717-CS-INDV / A. Strengthening national 2019-06- 2019-06- 2019-07- 2020-06- Profesional Técnico en TF / 16083 capacity for climate change Posterior Individual Open 25,668.00 0.00 Cancelado 2019-06-10 18 23 03 30 Archivo adaptation CIL-CC-C2-D-3-22 / C. Design and Consultor Individual de Linea implementation of 2020-10- 2019-07- 2019-06- 2019-07- 2019-06- 2019-07- 2019-07- 2020-06- Especialista y Responsable de TF / 18119 subprojects that improve Posterior Individual Open 11,712.00 5,153.74 Firmado 2019-06-17 01 02 16 02 28 22 19 30 los Procesos de Inversión climate resilience in the Rio PPCR Mizque Grande River Basin CIP-CC-C2-C-3-81 / C. Design and Supervisión Técnica implementation of Componente No Estructural 2020-07- 2019-06- 2019-07- 2019-06- 2019-08- 2019-07- 2019-08- 2020-05- TF / 18119 subprojects that improve Posterior Individual Open 21,866.00 17,403.92 Firmado 2019-06-10 Manejo Integral de la 10 24 22 24 07 15 26 10 climate resilience in the Rio Microcuenca Aquerana - Grande River Basin Municipio de Tacopaya CIP-CC-C2-C-3-82 / C. Design and Supervisión Técnica implementation of Componente Estructural 2020-07- 2019-06- 2019-07- 2019-06- 2019-08- 2019-07- 2019-08- 2020-03- TF / 18119 subprojects that improve Posterior Individual Open 14,736.00 14,068.17 Firmado 2019-06-10 Manejo Integral de la 09 24 22 24 14 15 28 11 climate resilience in the Rio Microcuenca Aquerana - Grande River Basin Municipio de Tacopaya CIP-CC-C2-C-3-83 / C. Design and Supervisión Técnica implementation of Componente No Estructural 2020-07- 2019-06- 2019-07- 2019-06- 2019-09- 2019-07- 2019-09- 2020-03- TF / 18119 subprojects that improve Posterior Individual Open 21,866.00 17,403.92 Firmado 2019-06-10 Manejo Integral de la 10 24 07 24 10 15 18 11 climate resilience in the Rio Microcuenca Qotumayu - Grande River Basin Municipio de Tacopaya CIP-CC-C2-C-3-84 / C. Design and Supervisión Técnica implementation of Componente Estructural 2020-07- 2019-06- 2019-07- 2019-06- 2019-08- 2019-07- 2019-08- 2020-03- TF / 18119 subprojects that improve Posterior Individual Open 14,657.00 14,503.26 Firmado 2019-06-10 Manejo Integral de la 09 24 07 24 07 15 26 11 climate resilience in the Rio Microcuenca Qotumayu - Grande River Basin Municipio de Tacopaya CIP-CC-C2-C-3-85 / C. Design and Supervisión Técnica implementation of Componente No Estructural 2020-07- 2019-06- 2019-07- 2019-06- 2019-08- 2019-07- 2019-09- 2020-03- TF / 18119 subprojects that improve Posterior Individual Open 21,866.00 17,403.92 Firmado 2019-06-10 Manejo Integral de la 09 24 22 24 23 15 02 11 climate resilience in the Rio Microcuenca Corral Pampa Grande River Basin Cona Cona CIP-CC-C2-C-3-86 / C. Design and Supervisión Técnica implementation of Componente Estructural 2020-07- 2019-06- 2019-07- 2019-06- 2019-08- 2019-07- 2019-09- 2020-03- TF / 18119 subprojects that improve Posterior Individual Open 14,736.00 13,052.94 Firmado 2019-06-10 Manejo Integral de la 09 24 07 24 05 15 02 11 climate resilience in the Rio Microcuenca Corral Pampa Grande River Basin Cona Cona CIP-CC-C2-C-3-80 / C. Design and Supervisión Componente No implementation of 2020-07- 2019-07- 2019-07- 2019-07- 2019-08- 2019-07- 2019-09- 2020-06- Estructural del Proyecto TF / 18119 subprojects that improve Posterior Individual Open 14,578.00 10,137.58 Firmado 2019-06-17 10 02 07 02 14 22 09 19 Conservación y Control de la climate resilience in the Rio Microcuenca Mokontullo Grande River Basin CIP-CC-C2-C-3-87 / Supervisión a la Elaboración C. Design and de los Estudios de Diseño implementation of 2019-11- 2019-06- 2019-06- 2019-07- 2019-11- Técnico de Preinversión TF / 18119 subprojects that improve Posterior Individual Open 4,963.00 0.00 En ejecución 2019-06-10 14 24 24 15 12 Manejo Integral de la climate resilience in the Rio Microcuencas Torancali - Grande River Basin Challamayu y Kangani CIP-CC-C2-C-3-88 / Supervisión a la Elaboración C. Design and de los Estudios de Diseño implementation of 2020-07- 2019-06- 2019-12- 2019-06- 2020-01- 2019-07- 2019-03- 2019-12- Técnico de Preinversión TF / 18119 subprojects that improve Posterior Individual Open 6,156.00 6,124.75 Firmado 2019-06-10 23 24 02 24 14 15 19 12 Manejo Integral de las climate resilience in the Rio Cuencas Khora Tiquipaya y Grande River Basin Taquiña BO-MAA-116716-CS-INDV / A. Strengthening national 2019-07- 2019-06- 2019-06- 2019-06- 2020-06- Profesional Técnico en TF / 16083 capacity for climate change Posterior Individual Open 20,735.00 0.00 Cancelado 2019-06-10 29 15 20 30 29 Tesorería adaptation CIP-CC-C2-C-3-89 / C. Design and Supervisor Componente implementation of Estructural del Proyecto 2020-07- 2019-07- 2019-07- 2019-07- 2019-08- 2019-07- 2019-08- 2020-06- TF / 18119 subprojects that improve Posterior Individual Open 14,519.00 13,034.03 Firmado 2019-06-17 Manejo Integral de la 09 02 15 02 02 22 28 19 climate resilience in the Rio Microcuenca Collpas, Grande River Basin Municipio de Pasorapa CIP-CC-C2-C-3-90 / C. Design and Supervisor Componente No implementation of Estructural del Proyecto 2020-07- 2019-07- 2019-06- 2019-07- 2019-07- 2019-07- 2019-08- 2020-06- TF / 18119 subprojects that improve Posterior Individual Open 21,733.00 20,304.57 Firmado 2019-06-17 Manejo Integral de la 09 02 30 02 26 22 28 19 climate resilience in the Rio Microcuenca Collpas, Grande River Basin Municipio Pasorapa BO-MAA-118742-CS-INDV / A. Strengthening national 2019-06- 2019-06- 2019-06- 2019-06- 2019-12- Consultor por Producto TF / 16083 capacity for climate change Posterior Individual Direct 1,600.00 0.00 En ejecución 2019-06-14 18 18 20 25 22 Moderador para el 5to. Foro adaptation CIP-CC-C2-C-3-91 / C. Design and Supervisión Estructural del implementation of 2020-07- 2019-07- 2019-06- 2019-07- 2019-07- 2019-07- 2019-08- 2020-02- Subproyecto Manejo TF / 18119 subprojects that improve Posterior Individual Open 20,436.00 17,378.71 Firmado 2019-06-17 09 02 30 02 24 22 05 27 Integrado de la Cuenca climate resilience in the Rio Sapanani Grande River Basin CIP-CC-C2-C-3-92 / C. Design and Supervisión No Estructural implementation of 2020-07- 2019-07- 2019-06- 2019-07- 2019-07- 2019-07- 2019-08- 2020-05- del Subproyecto Manejo TF / 18119 subprojects that improve Posterior Individual Open 17,797.00 15,953.59 Firmado 2019-06-17 09 02 30 02 24 22 05 12 Integrado de la Cuenca climate resilience in the Rio Sapanani Grande River Basin CIP-CC-C2-C-3-93 / C. Design and Supervisión Estructural del implementation of 2020-07- 2019-07- 2019-06- 2019-07- 2019-07- 2019-07- 2019-08- 2020-02- Subproyecto Manejo TF / 18119 subprojects that improve Posterior Individual Open 18,014.00 17,341.04 Firmado 2019-06-17 09 02 30 02 22 22 05 27 Integrado de la Cuenca climate resilience in the Rio Chungara Grande River Basin CIP-CC-C2-C-3-94 / C. Design and Supervisión No Estructural implementation of 2020-07- 2019-07- 2019-06- 2019-07- 2019-07- 2019-07- 2019-08- 2020-05- del Subproyecto Manejo TF / 18119 subprojects that improve Posterior Individual Open 18,217.00 15,895.95 Firmado 2019-06-17 09 02 30 02 22 22 05 12 Integrado de la Cuenca climate resilience in the Rio Chungara Grande River Basin CIP-CC-C2-C-3-95 / C. Design and Supervisión Estructural del implementation of 2020-07- 2019-07- 2019-06- 2019-07- 2019-07- 2019-07- 2019-08- 2020-02- Subproyecto Manejo TF / 18119 subprojects that improve Posterior Individual Open 18,122.00 17,378.71 Firmado 2019-06-17 09 02 30 02 24 22 05 27 Integrado de la Cuenca Wara climate resilience in the Rio Wara Grande River Basin CIP-CC-C2-C-3-96 / C. Design and Supervisión No Estructural implementation of 2020-07- 2019-07- 2019-06- 2019-07- 2019-07- 2019-07- 2019-08- 2020-05- del Subproyecto Manejo TF / 18119 subprojects that improve Posterior Individual Open 19,370.00 16,654.60 Firmado 2019-06-17 10 02 30 02 26 22 16 12 Integrado de la Cuenca Wara climate resilience in the Rio Wara Grande River Basin Page 11 BO-MAA-122140-CS-INDV / A. Strengthening national Supervisión Actualización del 2019-07- 2019-08- 2019-08- 2020-06- TF / 16083 capacity for climate change Posterior Individual Open 40,000.00 0.00 Cancelado 2019-07-18 Modulo de Monitoreo de 26 05 25 20 adaptation Embalses (SNICA FASE II) C. Design and CIP-CC-C2-C-3-97 / implementation of Supervisión No Estructural 2020-07- 2019-08- 2019-08- 2019-08- 2019-09- 2019-08- 2019-09- 2020-06- TF / 18119 subprojects that improve Posterior Individual Open 21,856.00 14,503.26 Firmado 2019-07-31 Manejo Integral de la 10 05 12 07 03 12 11 30 climate resilience in the Rio Microcuenca Acero Kocha Grande River Basin C. Design and CIP-CC-C2-C-3-98 / implementation of Supervisión Estructural 2020-07- 2019-08- 2019-08- 2019-08- 2019-09- 2019-08- 2019-09- 2020-06- TF / 18119 subprojects that improve Posterior Individual Open 21,811.00 15,953.59 Firmado 2019-07-31 Manejo Integral de la 09 05 12 07 02 12 12 30 climate resilience in the Rio Microcuenca Acera Kocha Grande River Basin C. Design and CIP-CC-C2-C-3-99 / implementation of Supervisión No Estructural 2020-07- 2019-08- 2019-08- 2019-08- 2019-09- 2019-08- 2019-09- 2020-06- TF / 18119 subprojects that improve Posterior Individual Open 18,996.00 14,503.26 Firmado 2019-07-31 Manejo Integral de la 10 05 12 07 02 12 10 30 climate resilience in the Rio Microcuenca Pocona Grande River Basin C. Design and CIP-CC-C2-C-3-100 / implementation of Supervisión Estructural 2020-07- 2019-08- 2019-08- 2019-08- 2019-09- 2019-08- 2019-09- 2020-06- TF / 18119 subprojects that improve Posterior Individual Open 8,787.00 8,742.32 Firmado 2019-07-31 Manejo Integral de la 09 05 12 07 09 12 20 30 climate resilience in the Rio Microcuenca Pocona Grande River Basin BO-MAA-125444-CS-INDV / A. Strengthening national 2019-08- 2019-08- 2019-10- 2019-09- 2019-10- 2019-09- 2019-11- 2020-06- Profesional Contable BM- TF / 16083 capacity for climate change Posterior Individual Open 19,767.00 14,103.30 Rescindido 2019-08-15 29 23 03 02 15 12 04 30 PPCR adaptation BO-MAA-126185-CS-INDV / CONSULTOR ESPECIALISTA AGRONOMO - AMBIENTAL II PARA LA ELABORACIÓN DEL B. Strengthening capacity for 2019-08- 2019-08- 2019-08- 2019-09- 2020-03- PLAN DIRECTOR DE LA TF / 16083 adaptation to climate change Posterior Individual Open 25,000.00 0.00 En ejecución 2019-08-11 15 21 31 10 28 CUENCA DEL RÍO ARQUE in the Rio Grande River Basin TAPACARÍ, BAJO UN ENFOQUE DE ADAPTACIÓN AL CAMBIO CLIMÁTICO A. Strengthening national BO-MAA-126194-CS-INDV / 2019-10- 2019-08- 2019-08- 2019-09- 2020-06- TF / 16083 capacity for climate change Posterior Individual Open 25,668.00 0.00 Cancelado 2019-08-11 Profesional en Archivo 25 21 31 10 30 adaptation A. Strengthening national BO-MAA-126195-CS-INDV / 2019-08- 2019-08- 2019-08- 2019-09- 2020-06- TF / 16083 capacity for climate change Posterior Individual Open 20,735.00 0.00 En ejecución 2019-08-11 Profesional en Tesorería 27 21 31 10 30 adaptation CIP-CC-C2-C-3-101 / Supervisión a la Elaboración C. Design and de Estudios de Diseño implementation of Técnico de preinversión 2020-07- 2019-10- 2019-10- 2019-10- 2020-02- TF / 18119 subprojects that improve Posterior Individual Open 6,358.89 0.00 En ejecución 2019-10-01 Mejoramiento Sistemas de 23 17 19 22 19 climate resilience in the Rio Riego Comunidades Grande River Basin Llulluchani, Muña Mayu, Pajchata Lux (Anzaldo) CIP-CC-C2-C-3-102 / Supervisión a la elaboración de estudios de Diseño técnico C. Design and de preinversión Mejoramiento implementation of Sistemas de Riego 2020-07- 2019-10- 2019-10- 2019-10- 2020-02- TF / 18119 subprojects that improve Posterior Individual Open 7,277.55 0.00 En ejecución 2019-10-01 Tecnificado Muyurina, Flor 23 17 19 22 19 climate resilience in the Rio del Valle, Arce Rancho, Grande River Basin Huerta Pampa, Esquina, Cala Caja, Villa Rosario, Rocha Rancho (Santivañez) CIP-CC-C2-C-3-103 / Supervisión a la Elaboración de Estudios de Diseño Técnico de Preinversión C. Design and Mejoramiento Sistemas de implementation of 2020-07- 2019-10- 2019-10- 2019-10- 2020-02- Riego Comunidades Molle TF / 18119 subprojects that improve Posterior Individual Open 5,477.26 0.00 En ejecución 2019-10-01 23 17 19 22 19 Molle Laguna 1, Molle Molle climate resilience in the Rio Laguna 2 y la Comunidad de Grande River Basin Juzgado del D-1, Colca, Collpas, Sivingani, Collca Ciaco del D-5 (Arani) CIP-CC-C2-C-3-104 / Supervisión a la Elaboración C. Design and de Estudios de Diseño implementation of Técnico de Preinversión 2020-07- 2019-10- 2019-10- 2019-10- 2020-02- TF / 18119 subprojects that improve Posterior Individual Open 4,902.62 0.00 En ejecución 2019-10-01 Mejoramiento Sistema de 23 17 19 22 19 climate resilience in the Rio Riego Comunidad Pantipata Grande River Basin Municipio Vinto y Comunidad Chaguarani Municipio Tarata CIP-CC-C2-C-3-105 / Supervisión a la elaboración C. Design and de Estudios de Diseño implementation of 2020-07- 2019-10- 2019-10- 2019-11- 2020-02- Técnico de Preinversión TF / 18119 subprojects that improve Posterior Individual Open 4,896.65 0.00 En ejecución 2019-10-01 23 17 19 22 19 Mejoramiento Sistemas de climate resilience in the Rio Riego de los Municipios Grande River Basin Arbieto y Villa Rivero CIP-CC-C2-C-3-106 / Supervisión del Estudio de Diseño Técnico de C. Design and Preinversión para la implementation of 2020-07- 2019-10- 2019-10- 2019-10- 2020-02- Construcción de Obras TF / 18119 subprojects that improve Posterior Individual Open 4,695.19 0.00 En ejecución 2019-10-01 23 17 19 22 19 Hidráulicas para la Reducción climate resilience in the Rio de Riesgos de Inundación en Grande River Basin los Municipios de Vinto y Cochabamba CIP-CC-C2-C-3-107 / Supervisión del Estudio de Diseño Técnico de C. Design and Preinversión para la implementation of 2020-09- 2019-10- 2019-10- 2019-10- 2020-02- Construcción de Obras TF / 18119 subprojects that improve Posterior Individual Open 6,453.79 0.00 En ejecución 2019-10-01 17 17 18 22 19 Hidráulicas para al Reducción climate resilience in the Rio de Riesgos de Inundación en Grande River Basin los Municipios de Arani, Arbieto y San Benito CIP-CC-C2-C-3-108 / Supervisión del Estudio Elaboración de Estudios de C. Design and Diseño Técnico de implementation of Preinversión para el 2020-07- 2019-10- 2019-10- 2019-10- 2020-02- TF / 18119 subprojects that improve Posterior Individual Open 8,960.90 0.00 En ejecución 2019-10-01 Mejoramiento de Sistemas de 23 17 18 22 19 climate resilience in the Rio Riego en las Comunidades Grande River Basin Coluyo Grande, Moyapampa, Challa y Antaqhawa (Municipio de Totora) CIP-CC-C2-C-3-109 / Supervisión a la Elaboración de Estudios de Diseño C. Design and Técnico de Preinversión implementation of 2020-07- 2019-10- 2019-10- 2019-10- 2020-02- Mejoramiento: Sistemas de TF / 18119 subprojects that improve Posterior Individual Open 9,273.85 0.00 En ejecución 2019-10-01 23 17 18 22 19 Riego Caramarca - climate resilience in the Rio Huayllahuju - Vila Vila Grande River Basin (Arque), Kjarkas Pongo Pata Chironi (Tapacari) y Vila Vila (Bolívar) CIP-CC-C2-C-3-110 / Supervisión a la Elaboración C. Design and de Estudios de Diseño implementation of 2020-07- 2019-10- 2019-10- 2019-10- 2020-02- Técnico de Preinversión TF / 18119 subprojects that improve Posterior Individual Open 6,950.36 0.00 En ejecución 2019-10-01 23 17 18 22 19 Mejoramiento: Sistema de climate resilience in the Rio Riego Muro Kollpa y Grande River Basin Wuayllani (Arque) Sarco Cucho (Capinota) CIP-CC-C2-C-3-111 / Supervisión a la Elaboración C. Design and de Estudios de Diseño implementation of Técnico de Preinversión 2020-07- 2019-10- 2019-10- 2019-10- 2020-02- TF / 18119 subprojects that improve Posterior Individual Open 8,626.94 0.00 En ejecución 2019-10-01 Construcción de Defensivos 23 17 18 22 19 climate resilience in the Rio en Riberas: del Rio Tapacari Grande River Basin (Sipe Sipe) y Río Semana Uma, Khoyu Khotani (Tapacari) CIP-CC-C2-C-3-112 / Supervisión a la Elaboración C. Design and de Estudio de Diseño Técnico implementation of de Preinversión para 2019-12- 2019-10- 2019-10- 2019-10- 2020-02- TF / 18119 subprojects that improve Posterior Individual Open 7,660.35 0.00 En ejecución 2019-10-01 Mejoramiento de Sistemas de 16 17 18 22 19 climate resilience in the Rio Riego para el Municipio de Grande River Basin Santivañez: Poquera, Saucini, Calaconto, Muyurina Caporaya BO-MAA-132972-CS-INDV / A. Strengthening national 2019-09- 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2020-04- 2019-12- Profesional en Adquisiciones TF / 16083 capacity for climate change Posterior Individual Direct 10,368.00 3,981.24 Finalizado 2019-09-22 23 02 18 12 21 24 24 21 31 y Contrataciones II adaptation BO-MAA-140613-CS-INDV / ESPECIALISTA EN RECURSOS HIDRICOS PARA LA A. Strengthening national ELABORACIÓN DEL PLAN Ejecución 2019-10- 2019-11- 2019-11- 2020-05- TF / 16083 capacity for climate change Posterior Individual Direct 28,000.00 0.00 2019-10-21 DIRECTOR DE LA CUENCA pendiente 31 05 15 13 adaptation DEL RÍO ARQUE TAPACARI, BAJO UN ENFOQUE DE ADAPTACIÓN AL CAMBIO CLIMÁTICO A. Strengthening national BO-MAA-141404-CS-INDV / 2019-11- 2019-11- 2019-11- 2020-06- TF / 16083 capacity for climate change Posterior Individual Limited 18,706.00 0.00 Cancelado 2019-10-25 ASESOR LEGAL BM-PPCR 02 12 24 30 adaptation A. Strengthening national BO-MAA-142898-CS-INDV / 2019-12- 2019-11- 2020-01- 2019-11- 2020-01- 2019-12- 2020-03- 2020-06- TF / 16083 capacity for climate change Posterior Individual Open 16,628.00 8,121.86 Firmado 2019-10-30 ASESOR LEGAL BM-PPCR 12 07 29 17 29 07 03 30 adaptation BO-MAA-142912-CS-INDV / A. Strengthening national AJUSTE DE LA “GUÍA PARA LA 2019-10- 2019-11- 2019-11- 2019-12- 2020-02- TF / 16083 capacity for climate change Posterior Individual Open 15,161.00 0.00 Cancelado 2019-10-30 FORMULACIÓN DE PLANES 29 09 19 03 16 adaptation DIRECTORES DE CUENCA” BO-MAA-143400-CS-INDV / A. Strengthening national AJUSTE DE LA “GUÍA PARA LA 2019-11- 2019-11- 2019-11- 2019-11- 2020-02- TF / 16083 capacity for climate change Posterior Individual Direct 15,161.00 0.00 Cancelado 2019-11-04 FORMULACIÓN DE PLANES 21 14 19 29 12 adaptation DIRECTORES DE CUENCA” CIP-CC-C2-C-3-79 / C. Design and Supervisión Componente No implementation of 2019-07- 2019-07- 2019-07- 2020-06- Estructural del Proyecto TF / 18119 subprojects that improve Posterior Individual Open 13,052.00 0.00 Cancelado 2019-06-17 02 02 22 19 Conservación y Control de la climate resilience in the Rio Microcuenca Moyapampa Grande River Basin A. Strengthening national BO-MAA-150291-CS-INDV / 2019-12- 2019-12- 2019-12- 2020-01- 2019-12- 2020-01- 2019-12- 2020-06- TF / 16083 capacity for climate change Posterior Individual Limited 8,120.00 358.46 Firmado 2019-12-18 Profesional en Archivo 13 23 20 02 20 12 23 30 adaptation BO-MAA-150293-CS-INDV / A. Strengthening national Consultor Individual de Linea 2019-12- 2019-12- 2020-01- 2020-01- 2020-01- 2020-01- 2020-01- 2020-06- TF / 16083 capacity for climate change Posterior Individual Open 12,475.00 10,530.89 Firmado 2019-12-19 Especialista en 13 27 14 06 14 18 28 30 adaptation Administración Financiera BM - PPCR MMAYA/PPCR/CIL/001/2020 A. Strengthening national / PROFESIONAL EN 2020-01- 2020-01- 2020-01- 2020-01- 2020-01- 2020-01- 2020-01- 2020-04- TF / 16083 capacity for climate change Posterior Individual Direct 5,500.00 5,363.45 Firmado 2020-01-09 ADQUISICIONES Y 24 11 27 12 27 18 28 17 adaptation CONTRATACIONES II Page 12 MMAYA/PPCR/CIL/002/2020 A. Strengthening national / ESPECIALISTA EN RIEGO E 2020-01- 2020-01- 2020-01- 2020-01- 2020-01- 2020-01- 2020-02- 2020-06- TF / 16083 capacity for climate change Posterior Individual Limited 12,600.00 9,567.28 Firmado 2020-01-10 INFRAESTRUCTURA 29 13 30 16 31 19 12 30 adaptation HIDRAULICA BM - PPCR MMAYA/PPCR/CIL/003/2020 A. Strengthening national / Profesional Técnico BM - 2020-01- 2020-01- 2020-02- 2020-02- 2020-02- 2020-02- 2020-03- 2020-06- TF / 16083 capacity for climate change Posterior Individual Limited 12,200.00 7,621.18 Firmado 2020-01-12 PPCR - Encargado del 31 22 11 01 12 11 06 30 adaptation seguimiento a los MICs MMAYA/PPCR/CIL/004/2020 A. Strengthening national 2020-02- 2020-01- 2020-02- 2020-02- 2020-02- 2020-02- 2020-03- 2020-06- / Asistente Administrativo TF / 16083 capacity for climate change Posterior Individual Limited 6,100.00 3,900.56 Firmado 2020-01-12 11 22 21 01 26 11 04 30 Financiero BM - PPCR adaptation MMAYA/PPCR/CIL/006/2020 / PROFESIONAL TECNICO BM A. Strengthening national - PPCR ENCARGADO DEL 2020-02- 2020-01- 2020-02- 2020-02- 2020-02- 2020-03- 2020-02- 2020-06- TF / 16083 capacity for climate change Posterior Individual Limited 12,100.00 8,754.12 Firmado 2020-01-19 SEGUIMIENTO A 10 24 10 14 11 20 19 30 adaptation CONSULTORIAS POR PRODUCTO MMAYA/PPCR/CIL/007/2020 A. Strengthening national / Profesional en 2020-01- 2020-02- 2020-02- 2020-06- TF / 16083 capacity for climate change Posterior Individual Limited 12,100.00 0.00 Cancelado 2020-01-21 Adquisiciones y 26 16 22 01 adaptation Contrataciones BM - PPCR MMAYA/PPCR/CIL/008/2020 A. Strengthening national / ESPECIALISTA EN 2020-02- 2020-02- 2020-03- 2020-02- 2020-05- 2020-02- 2020-06- 2020-07- TF / 16083 capacity for climate change Posterior Individual Open 12,300.00 1,996.05 Firmado 2020-01-20 ADQUISICIONES Y 20 05 20 19 21 29 02 08 adaptation CONTRATACIONES BM - PPCR BO-MAA-109330-CS-INDV / SUPERVISIÓN DE PROYECTO - DESARROLLO E B. Strengthening capacity for 2019-10- 2019-05- 2019-05- 2019-06- 2020-02- IMPLEMENTACION DEL TF / 16083 adaptation to climate change Posterior Individual Open 39,100.00 0.00 Cancelado 2019-04-29 23 04 25 23 18 SISTEMA DE MONITOREO Y in the Rio Grande River Basin ALERTA TEMPRANA DE SEQUÍAS PARA BOLIVIA MMAYA/PPCR/CIP/001/2020 / SUPERVISIÓN DE PROYECTO - DESARROLLO E A. Strengthening national 2020-02- 2020-02- 2020-06- 2020-02- 2020-07- 2020-03- 2020-07- 2020-06- IMPLEMENTACION DEL TF / 16083 capacity for climate change Posterior Individual Open 27,000.00 7,852.43 Firmado 2020-02-02 03 22 08 25 15 02 31 30 SISTEMA DE MONITOREO Y adaptation ALERTA TEMPRANA DE SEQUIAS PARA BOLIVIA BO-MAA-109321-CS-INDV / SUPERVISION PROYECTO - B. Strengthening capacity for DESARROLLO E 2019-07- 2019-05- 2019-05- 2019-06- 2020-02- TF / 16083 adaptation to climate change Posterior Individual Open 39,100.00 0.00 Cancelado 2019-04-30 IMPLEMENTACION DEL 11 05 20 18 13 in the Rio Grande River Basin SISTEMA DE PRONÓSTICOS ESTACIONALES PARA BOLIVIA MMAYA/PPCR/CIP/002/2020 / SUPERVISION PROYECTO – DESARROLLO E A. Strengthening national 2020-02- 2020-02- 2020-06- 2020-02- 2020-06- 2020-03- 2020-06- IMPLEMENTACION DEL TF / 16083 capacity for climate change Posterior Individual Open 27,000.00 0.00 Cancelado 2020-02-03 03 23 03 26 03 03 30 SISTEMA DE PRONOSTICOS adaptation CLIMATICOS ESTACIONALES PARA BOLIVIA CIP-CC-C2-C-3-113 / SUPERVISIÓN DE C. Design and ELABORACIÓN DE ESTUDIOS implementation of DE DISEÑO TÉCNICO DE 2020-07- 2020-02- 2020-02- 2020-02- 2020-06- TF / 18119 subprojects that improve Posterior Individual Open 6,493.73 0.00 En ejecución 2020-01-31 PREINVERSIÓN PARA EL 23 20 23 29 28 climate resilience in the Rio MEJORAMIENTO DE SISTEMAS Grande River Basin DE RIEGO EN EL MUNICIPIO DE MIZQUE CIP-CC-C2-C-3-114 / SUPERVISIÓN DE ELABORACIÓN DE ESTUDIOS DE DISEÑO TÉCNICO DE C. Design and PREINVERSIÓN PARA LA implementation of 2020-07- 2020-02- 2020-02- 2020-02- 2020-05- CONSTRUCCIÓN DE TF / 18119 subprojects that improve Posterior Individual Open 4,373.18 0.00 En ejecución 2020-01-31 23 20 23 29 29 DEFENSIVOS DE PROTECCIÓN climate resilience in the Rio PARA LAS ÁREAS Grande River Basin PRODUCTIVAS EN EL RÍO MIZQUE DEL MUNICIPIO DE PASORAPA CIP-CC-C2-C-3-115 / SUPERVISIÓN DE ELABORACIÓN DE ESTUDIOS C. Design and DE DISEÑO TÉCNICO DE implementation of PREINVERSIÓN PARA LA 2020-07- 2020-02- 2020-02- 2020-02- 2020-05- TF / 18119 subprojects that improve Posterior Individual Open 8,387.00 0.00 En ejecución 2020-01-31 CONSTRUCCIÓN DE MUROS 23 20 23 29 29 climate resilience in the Rio DEFENSIVOS SOBRE LOS RÍOS Grande River Basin TIPAJARA, TUCMA Y LAMPASILLOS EN EL MUNICIPIO DE MIZQUE C. Design and CIL-CC-C2-D-3-23 / implementation of Ejecución 2020-02- 2020-02- 2020-02- 2020-06- Consultor Individual de Línea TF / 18119 subprojects that improve Posterior Individual Open 6,091.00 0.00 2020-01-31 pendiente 20 23 29 30 Especialista Hidráulico PPCR climate resilience in the Rio Grande River Basin CIL-CC-C2-D-3-24 / C. Design and Consultor Individual de Línea implementation of Ejecución 2020-02- 2020-02- 2020-02- 2020-06- Especialista y Responsable de TF / 18119 subprojects that improve Posterior Individual Open 6,091.00 0.00 2020-01-31 pendiente 20 23 29 30 los Procesos de Inversión climate resilience in the Rio PPCR Grande River Basin C. Design and CIL-CC-C2-D-3-25 / implementation of Consultor Individual de Línea 2020-02- 2020-02- 2020-02- 2020-02- 2020-06- 2020-02- 2020-07- 2020-06- TF / 18119 subprojects that improve Posterior Individual Open 5,234.00 3,471.50 Firmado 2020-01-31 Profesional Analista 11 20 26 23 01 29 16 30 climate resilience in the Rio Financiero PPCR Grande River Basin C. Design and implementation of CIL-CC-C2-D-3-26 / 2020-02- 2020-03- 2020-03- 2020-03- 2020-06- TF / 18119 subprojects that improve Posterior Individual Open 2,927.00 0.00 En ejecución 2020-02-10 Técnico en Archivos PPCR 28 01 04 10 30 climate resilience in the Rio Grande River Basin C. Design and CIL-CC-C2-D-3-27 / implementation of 2020-03- 2020-03- 2020-03- 2020-03- 2020-06- 2020-03- 2020-07- 2020-06- Profesional en Adquisiciones TF / 18119 subprojects that improve Posterior Individual Open 5,234.00 3,037.56 Firmado 2020-02-10 12 01 19 04 26 10 24 30 PPCR climate resilience in the Rio Grande River Basin MMAYA/PPCR/CIP/003/2020 A. Strengthening national / AJUSTE DE LA GUIA PARA LA 2020-05- 2020-03- 2020-06- 2020-03- 2020-07- 2020-04- 2020-07- 2020-06- TF / 16083 capacity for climate change Posterior Individual Open 12,758.00 12,665.69 Firmado 2020-03-05 FORMULACION DE PLANES 08 25 05 28 02 03 13 17 adaptation DIRECTORES DE CUENCA MMAYA/PPCR/SC/SD/001/20 20 / AUDITORIA FINANCIERA DEL PROYECTO RESILIENCIA CLIMATICA EN BOLIVIA- MANEJO INTEGRADO DE A. Strengthening national Selección directa 2020-04- 2020-04- 2020-05- 2020-04- 2020-08- 2020-06- CUENCAS EN EL MARCO DEL TF / 18119 capacity for climate change Posterior Direct 35,500.00 21,851.85 Firmado 2020-03-25 de consultores 21 02 06 12 20 30 PPCR, POR EL PERIODO adaptation COMPRENDIDO ENTRE EL 01/01/2019 AL 31/12/2019 Y HASTA EL CIERRE DEL PROYECTO MMAYA/PPCR/CIL/009/2020 A. Strengthening national / PROFESIONAL EN 2020-04- 2020-04- 2020-04- 2020-04- 2020-04- 2020-04- 2020-04- 2020-06- TF / 16083 capacity for climate change Posterior Individual Direct 4,673.00 4,178.10 Firmado 2020-04-20 ADQUISICIONES Y 21 22 27 23 28 25 28 30 adaptation CONTRATACIONES BM- PPCR MMAYA/PPCR/CIL/016/2020 A. Strengthening national 2020-05- 2020-05- 2020-05- 2020-06- / Profesional en TF / 16083 capacity for climate change Posterior Individual Limited 3,593.88 0.00 Cancelado 2020-05-11 16 18 21 30 Adquisiciones y adaptation Contrataciones II PPCR- BM MMAYA/PPCR/CIL/012/2020 A. Strengthening national 2020-05- 2020-05- 2020-05- 2020-06- / Profesional Técnico TF / 16083 capacity for climate change Posterior Individual Limited 3,312.54 0.00 Cancelado 2020-05-11 16 18 21 30 Ambiental adaptation MMAYA/PPCR/CIL/013/2020 A. Strengthening national 2020-05- 2020-05- 2020-05- 2020-06- / Profesional Técnico en TF / 16083 capacity for climate change Posterior Individual Limited 3,117.49 0.00 Cancelado 2020-05-08 13 15 18 30 Meteorología e Hidrología adaptation MMAYA/PPCR/CIL/014/2020 A. Strengthening national / Profesional Técnico 2020-05- 2020-05- 2020-05- 2020-06- TF / 16083 capacity for climate change Posterior Individual Limited 4,005.25 0.00 Cancelado 2020-05-08 responsable de seguimiento a 13 15 18 30 adaptation proyectos MIC II (Cbba) A. Strengthening national MMAYA/PPCR/CIL/015/2020 2020-05- 2020-05- 2020-05- 2020-06- TF / 16083 capacity for climate change Posterior Individual Limited 3,312.54 0.00 Cancelado 2020-05-08 / Profesional Abogado 13 15 18 30 adaptation MMAYA/PPCR/CIP/004/2020 / ESPECIALISTA GEOLOGO PARA LA ELABORACION DEL B. Strengthening capacity for PLAN DIRECTOR DE LA 2020-06- 2020-05- 2020-07- 2020-05- 2020-07- 2020-05- 2020-07- 2020-06- TF / 16083 adaptation to climate change Posterior Individual Direct 11,228.23 12,170.38 Firmado 2020-05-08 CUENCA DEL RIO ARQUE 25 12 09 16 14 20 15 30 in the Rio Grande River Basin TAPACARÍ (PDCAT), BAJO UN ENFOQUE DE ADAPTACIÓN AL CAMBIO CLIMÁTICO A. Strengthening national MMAYA/PPCR/CIL/011/2020 2020-05- 2020-05- 2020-05- 2020-05- 2020-06- TF / 16083 capacity for climate change Posterior Individual Limited 2,965.89 0.00 Cancelado 2020-05-08 / Asistente en Planificación 20 13 15 18 30 adaptation MMAYA/PPCR/CIL/010/2020 A. Strengthening national 2020-05- 2020-05- 2020-05- 2020-06- / Asesor de Apoyo TF / 16083 capacity for climate change Posterior Individual Limited 2,706.12 0.00 Cancelado 2020-05-08 13 15 18 30 Coordinador PPCR adaptation MMAYA/PPCR/CIL/010/ A. Strengthening national 2020-09- 2020-07- 2020-09- 2020-07- 2020-09- 2020-07- 2020-09- 2020-12- 2020 / Asesor de Apoyo TF / 16083 capacity for climate change Posterior Individual Limited 7,441.84 4,925.33 Firmado 2020-07-14 04 22 04 24 11 28 11 31 Coordinador BM - PPCR adaptation MMAYA/PPCR/CIL/011/ A. Strengthening national 2020-07- 2020-07- 2020-07- 2020-07- 2020-09- 2020-07- 2020-10- 2020-12- 2020 / Asistente en TF / 16083 capacity for climate change Posterior Individual Limited 8,156.20 4,416.64 Firmado 2020-07-14 20 22 23 24 25 28 01 31 Planificación BM - PPCR adaptation MMAYA/PPCR/CIL/016/ A. Strengthening national 2020-07- 2020-07- 2020-07- 2020-07- 2020-09- 2020-07- 2020-09- 2020-12- 2020 / Profesional en TF / 16083 capacity for climate change Posterior Individual Limited 9,883.16 6,783.87 Firmado 2020-07-14 20 22 23 24 04 28 07 31 Adquisiciones y adaptation Contrataciones II BM - PPCR MMAYA/PPCR/CIL/012/ A. Strengthening national 2020-09- 2020-07- 2020-09- 2020-07- 2020-10- 2020-07- 2020-10- 2020-12- 2020 / Profesional Técnico TF / 16083 capacity for climate change Posterior Individual Limited 9,109.48 4,175.16 Firmado 2020-07-14 24 22 25 24 15 28 15 31 Socio - Ambiental adaptation MMAYA / PPCR / CIL / A. Strengthening national 013/2020 / Profesional 2020-07- 2020-07- 2020-09- 2020-07- 2020-09- 2020-07- 2020-09- 2020-12- TF / 16083 capacity for climate change Posterior Individual Open 8,753.10 5,312.97 Firmado 2020-07-14 Técnico en Meteorología e 23 25 04 27 15 31 18 31 adaptation Hidrología MMAYA/PPCR/CIL/014/ A. Strengthening national 2020 / Profesional Técnico 2020-07- 2020-07- 2020-07- 2020-12- TF / 16083 capacity for climate change Posterior Individual Limited 11,014.43 0.00 En ejecución 2020-07-14 responsable de seguimiento a 22 24 28 31 adaptation proyectos MIC II (Cbba) MMAYA/PPCR/CIL/015/ A. Strengthening national 2020-09- 2020-07- 2020-09- 2020-07- 2020-07- 2020-12- 2020 / Profesional Abogado TF / 16083 capacity for climate change Posterior Individual Limited 9,109.48 0.00 Cancelado 2020-07-14 02 22 02 24 28 31 BM - PPCR adaptation Page 13 MMAYA/PPCR/CIL/017/2020 A. Strengthening national / COORDINADOR DEL 2020-05- 2020-05- 2020-05- 2020-05- 2020-06- 2020-06- 2020-06- TF / 16083 capacity for climate change Posterior Individual Limited 3,075.04 0.00 Cancelado 2020-05-21 PROGRAMA PILOTO DE 21 29 21 31 05 04 30 adaptation RESILIENCIA CLIMÁTICA MMAYA/PPCR/CIL/018/2020 A. Strengthening national 2020-08- 2020-08- 2020-08- 2020-08- 2020-09- 2020-09- 2020-09- 2020-12- / PROFESIONAL CONTABLE TF / 16083 capacity for climate change Posterior Individual Direct 8,086.22 6,184.31 Firmado 2020-08-24 27 28 27 30 15 03 17 31 BM – PPCR adaptation CIP-CC-C2-C-3-116 / Supervisión a la Elaboración de Estudios de Diseño C. Design and Técnico de Preinversión para implementation of Ejecución 2020-09- 2020-09- 2020-10- 2020-12- la Construcción de TF / 18119 subprojects that improve Posterior Individual Open 2,996.65 0.00 2020-09-07 pendiente 21 25 01 31 Defensivos para la Protección climate resilience in the Rio de Riberas en el Cauce Grande River Basin Principal de la Microcuenca Thola P'ujru (Municipio de Tiquipaya) CIP-CC-C2-C-3-117 / Supervisión a la Elaboración de Estudios de Diseño Técnico de Preinversión para C. Design and la Construcción de implementation of Ejecución 2020-09- 2020-09- 2020-10- 2020-12- Defensivos para la Protección TF / 18119 subprojects that improve Posterior Individual Open 4,996.06 0.00 2020-09-07 pendiente 21 25 01 31 de Riberas en el Cauce climate resilience in the Rio Principal de las Microcuencas: Grande River Basin Chijllawiri (Municipio de Quillacollo) - Khotu Mayu (Municipio de Tiquip CIP-CC-C2-C-3-118 / Supervisión a la Elaboración de Estudios de Diseño C. Design and Técnico de Preinversión para implementation of la Construcción de Ejecución 2020-09- 2020-09- 2020-10- 2020-12- TF / 18119 subprojects that improve Posterior Individual Open 4,998.40 0.00 2020-09-07 Defensivos para la Protección pendiente 21 25 01 31 climate resilience in the Rio de Riberas en el cauce Grande River Basin Principal de las Microcuencas: Locosti (Municipio Sacaba) - Chuta Kawa (Municipio de Tiquipaya) MMAYA/PPCR/CIP/005/2020 / Supervisión Proyecto – A. Strengthening national Desarrollo e Implementación 2020-09- 2020-09- 2020-09- 2020-09- 2020-09- 2020-09- 2020-10- 2020-11- TF / 16083 capacity for climate change Posterior Individual Direct 5,541.00 5,504.56 Firmado 2020-09-02 del Sistema de Pronósticos 03 12 04 15 29 19 02 03 adaptation Climáticos Estacionales para Bolivia MMAYA/PPCR/CIP/006/2020 / Elaboración del Informe A. Strengthening national 2020-10- 2020-11- 2020-11- 2020-12- Final del Proyecto "Resiliencia TF / 18119 capacity for climate change Posterior Individual Limited 6,644.02 0.00 En ejecución 2020-10-21 26 02 08 23 Climática en Bolivia - Manejo adaptation Integrado de Cuencas" MMAYA/PPCR/CIP/007/2020 / Sistematización de los Resultados del Sexto “Foro A. Strengthening national 2020-10- 2020-11- 2020-11- 2020-12- Virtual – Taller: Resiliencia y TF / 18119 capacity for climate change Posterior Individual Limited 2,507.29 0.00 En ejecución 2020-10-21 26 02 08 08 Adaptación al Cambio adaptation Climático, y Evaluación de los Indicadores CIF – PPCR” CIL-CA-A3-(A)-5-1 / A. Strengthening national COORDINADOR DEL 2017-01- 2017-01- 2017-01- 2017-01- 2017-01- 2017-01- 2017-01- 2017-02- TF / 16083 capacity for climate change Posterior Individual Direct 5,045.48 4,021.73 Firmado 2016-12-24 PROGRAMA PILOTO DE 03 02 03 05 13 13 13 28 adaptation RESILIENCIA CLIMATICA MMAYA/PPCR/F2/CCV N° 006/2016 / Profesional A. Strengthening national 2020-04- 2016-02- 2016-05- 2016-02- 2016-05- 2016-02- 2016-05- 2016-12- Encargado de Sistemas TF / 16083 capacity for climate change Posterior Individual Open 88,320.00 11,919.24 Firmado 2016-01-30 06 16 06 19 06 23 18 30 Informáticos y Geográficos adaptation BM-PPCR MMAYA/PPCR/F2/CIL/N° 018/2016 / ESPECIALISTA EN A. Strengthening national 2016-02- 2016-02- 2016-02- 2016-12- PLANIFICACION, MONITOREO, TF / 16083 capacity for climate change Posterior Individual Open 13,358.60 0.00 Bajo Revision 2016-01-30 18 21 27 30 EVALUACION Y GESTION DEL adaptation CONOCIMIENTO BM-PPCR MMAYA/PPCR/SC/SD/002/20 20 / Auditoria Financiera del Proyecto Resiliencia Climática en Bolivia - Manejo Integrado de Cuencas en el Marco del A. Strengthening national Selección directa Ejecución 2020-11- 2020-12- 2021-01- PPCR, por el Periodo TF / 18119 capacity for climate change Posterior Direct 40,000.00 0.00 2020-11-19 de consultores pendiente 27 05 24 Comprendido entre el adaptation 01/01/2020 al 31/12/2020 y hasta el cierre del proyecto, Donación TF 18119 y préstamo TF 16083 Page 14