The World Bank Implementation Status & Results Report SABESP - IMPROVING WATER SERVICE ACCESS AND SECURITY IN THE METROPOLITAN REGION OF SÃO PAULO PROJECT (P165695) SABESP - IMPROVING WATER SERVICE ACCESS AND SECURITY IN THE METROPOLITAN REGION OF SÃO PAULO PROJECT (P165695) LATIN AMERICA AND CARIBBEAN | Brazil | Water Global Practice | IBRD/IDA | Investment Project Financing | FY 2019 | Seq No: 5 | ARCHIVED on 21-Dec-2020 | ISR44094 | Implementing Agencies: SABESP, SABESP Key Dates Key Project Dates Bank Approval Date: 18-Dec-2018 Effectiveness Date: 19-Dec-2019 Planned Mid Term Review Date: 15-Jun-2022 Actual Mid-Term Review Date: Original Closing Date: 16-Jun-2025 Revised Closing Date: 16-Jun-2025 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) The Project Development Objectives are to increase access of vulnerable people to water services and to contribute to the reduction of water losses and pollution loads in the Metropolitan Region of São Paulo. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Components Table Name Expand access to water services, reduce water losses, and increase system resilience in the MRSP:(Cost $255.20 M) Reduce pollution loads to scarce water resources in the Guarapiranga Water Basin:(Cost $59.90 M) Technical assistance and Project management and supervision:(Cost $34.30 M) Contingent Emergency Response Component – CERC Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Satisfactory Overall Implementation Progress (IP) Moderately Satisfactory Moderately Satisfactory Overall Risk Rating Moderate Moderate Implementation Status and Key Decisions Signing of the loan took place on December 4th, 2019 and effectiveness on December 18, 2019. Counterpart funded activities, particularly the Água Legal Program, performance-based contracts for water loss reduction, and a few studies are currently being implemented. Implemented actions have already reached 195,766 beneficiaries with access to improved water sources and 7,897 new sewerage connections in the Metropolitan Region of São Paulo. Selection processes for consultancy services to support Project management and supervision are under way (one has been contracted already). Publication of procurement notices for some of the loan-financed activities were already launched in 2020 and will continue in 2021. 12/21/2020 Page 1 of 7 The World Bank Implementation Status & Results Report SABESP - IMPROVING WATER SERVICE ACCESS AND SECURITY IN THE METROPOLITAN REGION OF SÃO PAULO PROJECT (P165695) Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance Substantial Substantial Substantial Macroeconomic Substantial Substantial Substantial Sector Strategies and Policies Substantial Substantial Substantial Technical Design of Project or Program Substantial Substantial Substantial Institutional Capacity for Implementation and Moderate Moderate Moderate Sustainability Fiduciary Moderate Low Low Environment and Social Moderate Moderate Moderate Stakeholders Moderate Moderate Moderate Other -- -- Moderate Overall Moderate Moderate Moderate Results PDO Indicators by Objectives / Outcomes Increase access of vulnerable people to water services IN00912831 ►People provided with access to improved water sources (Number, Corporate) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 126,644.00 195,766.00 532,000.00 Date 27-Aug-2018 31-Dec-2019 30-Nov-2020 31-Mar-2025 This indicator measures the cumulative number of people who benefited from improved water supply Comments: services that have been constructed through the Project. Contribute to the reduction of water losses IN00912832 ►Volume of non-revenue water reduction (millions of cubic meters per year) (Cubic meters/year, Custom) Baseline Actual (Previous) Actual (Current) End Target 12/21/2020 Page 2 of 7 The World Bank Implementation Status & Results Report SABESP - IMPROVING WATER SERVICE ACCESS AND SECURITY IN THE METROPOLITAN REGION OF SÃO PAULO PROJECT (P165695) Value 0.00 1.47 16.00 33.30 Date 27-Aug-2018 31-Dec-2019 30-Nov-2020 31-Mar-2025 Volume (millions of cubic meters per year) of water saved due to water losses reduction interventions carried out through subcomponents 1.1, 1.2, and 1.3. The following expected contributions per subcomponent for last year of Project implementation are: 1.1 = 18.5 million m3/year; 1.2 = 8.4 million Comments: m3/year; and 1.3 = 6.4 million m3/year. The team is reassessing the current data for consistency. Contribute to the reduction of pollution loads IN00912833 ►Volume of wastewater removed from the Guarapiranga basin sent to treatment (millions of cubic meters/year) (Cubic meters/year, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 1.90 Date 27-Aug-2018 31-Dec-2019 30-Nov-2020 31-Mar-2025 Consolidation of the data from the Project interventions in Embu and Itapecerica sanitation systems; Pumping Stations (Talamanca, Iporã and Embu 4); and Collectors. The total volume (millions of cubic Comments: meters per year) of wastewater collected by the Embu and Itapecerica sanitation systems, plus the volume of wastewater transported through Guavirituba main trunk line, and the volume of wastewater transported by the pumping stations (only Talamanca, Iporã and Embu 4, to avoid double counting). Intermediate Results Indicators by Components 1 - Expand access to water services, reduce water losses, and increase system resilience in the MRSP IN00912835 ►Volume of micro metered water from new service connections to the formal water supply system (millions of cubic meters per year) (Cubic meters/year, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 6.44 18.50 Date 27-Aug-2018 31-Dec-2019 30-Nov-2020 31-Mar-2025 Volume (millions of cubic meters per year) of consumed water measured through the micrometers Comments: installed in the neighborhoods benefiting from the Agua Legal Program financed under the Project. The expected volume for the last year of Project implementation is 18.50 million of cubic meter per year. IN00912839 ►People provided with access to improved sanitation services (Number, Corporate) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 12,607.00 27,640.00 157,150.00 Date 27-Aug-2018 31-Dec-2019 30-Nov-2020 31-Mar-2025 The indicator measures the cumulative number of people who benefited from improved sanitation facilities Comments: that have been constructed through operations supported by the World Bank. 12/21/2020 Page 3 of 7 The World Bank Implementation Status & Results Report SABESP - IMPROVING WATER SERVICE ACCESS AND SECURITY IN THE METROPOLITAN REGION OF SÃO PAULO PROJECT (P165695) IN00912842 ►Number of bursts on the water distribution mains per 100km per year in the Project targeted area (reported and unreported) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 115.00 115.00 115.00 19.00 Date 27-Aug-2018 31-Dec-2019 30-Nov-2020 31-Mar-2025 Comments: Decrease in number of reported and unreported bursts per 100 km per year in the Project targeted area. IN00912843 ►Number of bursts on serviced connections per 1,000 connections per year in the Project targeted area (reported and unreported) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 31.00 31.00 31.00 5.00 Date 27-Aug-2018 31-Dec-2019 30-Nov-2020 31-Mar-2025 Decrease in number of reported and unreported bursts per 1,000 serviced connections per year in the Comments: Project targeted area. IN00912844 ►Km of water distribution mains rehabilitated in the Project targeted area (Kilometers, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 850.00 Date 27-Aug-2018 31-Dec-2019 30-Nov-2020 31-Mar-2025 Comments: Number of kilometers of water distribution mains replaced under the Project. IN00912845 ►Number of serviced connections rehabilitated in the Project targeted area (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 9,348.00 113,000.00 Date 27-Aug-2018 31-Dec-2019 30-Nov-2020 31-Mar-2025 Number of water supply connections replaced under the Project. Comments: 2 - Reduce pollution loads to scarce water resources in the Guarapiranga Water Basin IN00912834 ►Period of time that the wastewater pumping stations rehabilitated by the Project are operational (percentage of time per year) (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 93.09 93.09 93.09 98.00 Date 27-Aug-2018 31-Dec-2019 30-Nov-2020 31-Mar-2025 12/21/2020 Page 4 of 7 The World Bank Implementation Status & Results Report SABESP - IMPROVING WATER SERVICE ACCESS AND SECURITY IN THE METROPOLITAN REGION OF SÃO PAULO PROJECT (P165695) Electromechanical availability index: compares the total number of hours per year that the pumping station (panel, motor, and pumps) supported by the Project was operation versus the total number of hours per Comments: year that the pumping station was expected to stay operational (arithmetic average of the six pumping stations) calculated per year. This indicator precludes events that are not related to the operation of the pumping stations such as due to problems upwards and downwards of the stations. IN00912838 ►Km of sewerage main trunk line and discharge pipeline rehabilitated under the Project (Kilometers, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 3.10 Date 27-Aug-2018 31-Dec-2019 30-Nov-2020 31-Mar-2025 Comments: Number of kilometers of sewerage main trunk line and discharge pipeline replaced under the Project. 3 - Technical assistance and Project management and supervision IN00912836 ►Automation system pilot implemented and operational (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No No No Yes Date 27-Aug-2018 31-Dec-2019 30-Nov-2020 31-Mar-2025 Automation system pilot of the Barueri System implemented and operational. Activity is advancing: ToR has been approved by the Bank and Sabesp is currently working on the bidding Comments: document. IN00912840 ►Energy micro generation study developed and implemented (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No No No Yes Date 27-Aug-2018 31-Dec-2019 30-Nov-2020 31-Mar-2025 Comments: Energy micro generation study developed and two pilots implemented during Project implementation Citizen Engagement and Gender – Beneficiary feedback IN00912837 ►Beneficiaries that feel that water and sanitation services reflect their needs in the Água Legal areas of interventions supported by the Project (beneficiary survey informed disaggregated per gender) (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 80.00 Date 27-Aug-2018 31-Dec-2019 30-Nov-2020 31-Mar-2025 Percentage of Água Legal beneficiaries supported by the Project that have positively assessed the Comments: Project. The reduction on the gender gap will also be monitored by comparing the satisfaction per gender 12/21/2020 Page 5 of 7 The World Bank Implementation Status & Results Report SABESP - IMPROVING WATER SERVICE ACCESS AND SECURITY IN THE METROPOLITAN REGION OF SÃO PAULO PROJECT (P165695) before and after the contracts are carried out. This indicator would be measuring and monitoring the changes in perceptions among men and women. IN00912841 ►Beneficiaries satisfied with social activities carried out by the Água Legal areas of interventions (beneficiary survey informed disaggregated per gender) (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 70.00 Date 27-Aug-2018 31-Dec-2019 30-Nov-2020 31-Mar-2025 Percentage of Agua Legal beneficiaries supported by the Project that have positively assessed the social Comments: activities carried out by Project. The reduction on the gender gap will also be monitored by compering the satisfaction per gender before and after the contracts are carried out. Performance-Based Conditions Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P165695 IBRD-89160 Effective USD 250.00 250.00 0.00 0.63 249.38 0.3% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P165695 IBRD-89160 Effective 18-Dec-2018 04-Dec-2019 19-Dec-2019 16-Jun-2025 16-Jun-2025 Cumulative Disbursements 12/21/2020 Page 6 of 7 The World Bank Implementation Status & Results Report SABESP - IMPROVING WATER SERVICE ACCESS AND SECURITY IN THE METROPOLITAN REGION OF SÃO PAULO PROJECT (P165695) PBC Disbursement Achievement Disbursed amount in Disbursement % PBC ID PBC Type Description Coc PBC Amount Status Coc for PBC Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 12/21/2020 Page 7 of 7