Sample Procurement Plan (Text in italic font is meant for instruction to staff and should be deleted in the final version of the PP) (This is only a sample with the minimum content that is required to be included in the PAD. The detailed procurement plan is still mandatory for disclosure on the Bank’s website in accordance with the guidelines. The initial procurement plan will cover the first 18 months of the project and then updated annually or earlier as necessary). I. General 2. Bank’s approval Date of the procurement Plan 3. Date of General Procurement Notice: 4. Period covered by this procurement plan: II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) 2. NCB (Goods) 3. ICB (Works) 4. NCB (Works) 5. (Non-Consultant Services) [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: [Refer to the relevant CDD project implementation document approved by the Bank or delete if not applicable] July 9, 2010 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project XYZ 04/01/2010 issued by 5. Any Other Special Procurement Arrangements: [including advance procurement and retroactive financing, if applicable] 5 ICB works packages will be financed under retroactive financing 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) [List the Packages which require Bank’s prior review first and then the other packages] 1 2 3 4 5 6 7 Ref. Descriptio Estimate Packages Dome Review Commen No. n d stic by Bank ts Cost Prefer (Prior / US$ ence Post) million (yes/n o) Summary of the ICB (Works) Summary of the ICB (Goods) Summary of the NCB (Works) Summary of the NCB (Goods) Summary of the ICB (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) 2. Single Source (Firms) July 9, 2010 3. Individual 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimate Packages Review Comments of d by Bank Assignment Cost (Prior / US$ Post) million Summary of number of contracts that will be let under QCBS Summary of number of contracts that will be let under other methods July 9, 2010 PROCUREMENT Nepal : Earthquake Housing Reconstruction Project PLAN General Information Country: Nepal Bank’s Approval Date of the Original Procurement Plan: 2017-05-12 2020-12-23 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P155969 GPN Date: Project Name: Earthquake Housing Reconstruction Project Loan / Credit No: IDA / 57060, IDA / 61640 Nepal Reconstruction Authority Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NP-NRA-GO-RFB-5 / Under Procurement of Tablets for Project Implementation Single Stage - One IDA / 57060 Post Request for Bids Open - National 300,000.00 0.00 Implementati 2017-05-12 2017-05-17 2017-06-01 2017-05-31 2017-06-16 2017-06-13 2017-06-30 2017-09-28 digitization of PA form and Support Envelope on Inspection form. NP-NRA-GO-RFQ-2-1 / 6 Project Implementation Request for Single Stage - One IDA / 57060 Post Limited 14,577.00 12,195.17 Signed 2017-05-16 2017-06-21 2017-06-23 2017-07-21 units of Motorcycles Support Quotations Envelope NP-NRA-GO-RFQ-2-2 / 4 Project Implementation Request for Single Stage - One IDA / 57060 Post Limited 7,006.00 5,557.96 Signed 2017-05-16 2017-06-21 2017-06-23 2017-07-21 units of Scooter Support Quotations Envelope Pending NP-NRA-GO-DIR-3 / 2 units Project Implementation IDA / 57060 Post Direct Selection Direct 3,000.00 0.00 Implementati 2017-05-11 2017-05-16 2017-05-31 2017-06-07 of DSLR Camera Support on NP-NRA-GO-RFB-4 / 1 unit Project Implementation Single Stage - One of High-end SAN Storage for IDA / 57060 Post Request for Bids Open - National 35,000.00 0.00 Canceled 2017-05-11 2017-05-16 2017-05-31 2017-06-07 2017-06-11 2017-06-21 2017-07-21 Support Envelope MIS EHRP/NRA/G/SH-04/2074- Project Implementation Request for Single Stage - One 75 / Procurement of 5 Video IDA / 57060 Post Limited 3,678.00 0.00 Canceled 2018-01-05 2018-02-02 2018-03-04 Support Quotations Envelope Cameras EHRP/NRA/G/DC-02/2074- Project Implementation 75 / Procurement of 10 IDA / 57060 Post Direct Selection Direct 352,500.00 337,219.40 Signed 2017-12-22 2017-12-26 2017-12-29 2018-01-02 2018-01-23 2018-01-12 2018-02-22 Support Double Cab Pickup Vehicles EHRP/NRA/G/DC-03/2074- Project Implementation 75 / Procurement of 1 SUV IDA / 57060 Post Direct Selection Direct 43,000.00 41,237.12 Signed 2017-12-22 2017-12-26 2017-12-27 2018-01-02 2018-01-23 2018-01-12 2018-02-22 Support Vehicle. EHRP/NRA/G/NCB-05/2074- 75 / Procurement of 10 Project Implementation Single Stage - One Laptop Computers and 10 IDA / 57060 Post Request for Bids Open - National 15,500.00 0.00 Canceled 2017-12-31 2018-01-02 2018-02-04 2018-02-14 2018-03-11 2018-04-25 Support Envelope Sets Desktop Computers with UPS and Accessories EHRP/NRA/G/NCB-06/2074- 75 / Procurement of 22 Black Project Implementation Single Stage - One and White LaserJet Printers IDA / 57060 Post Request for Bids Open - National 10,000.00 0.00 Canceled 2017-12-31 2018-01-03 2018-02-04 2018-02-14 2018-03-11 2018-04-25 Support Envelope and 2 Heavy duty Photocopy Machines EHRP/NRA/G/NCB-07/2074- Project Implementation Single Stage - One 75 / Procurement of 14 IDA / 57060 Post Request for Bids Open - National 10,500.00 0.00 Canceled 2017-12-29 2018-01-02 2018-02-04 2018-02-14 2018-03-11 2018-04-25 Support Envelope Portable Projectors EHRP/NRA/G/SH-08/2074- 75 / Publication of Bulletine Request for Single Stage - One IDA / 57060 Housing Reconstruction Post Limited 15,000.00 0.00 Canceled 2018-01-12 2018-02-09 2018-03-26 (Notice and Communication Quotations Envelope Program)-3 EHRP/NRA/G/DC-9/2074-75 / Publication of IDA / 57060 Housing Reconstruction Post Direct Selection Direct 2,000.00 0.00 Canceled 2018-03-30 2018-04-06 2018-04-27 2018-05-27 Reconstruction Profile-1 NP-NRA-GO-RFB-7 / 5 units Project Implementation Single Stage - One IDA / 57060 Post Request for Bids Open - National 299,450.00 0.00 Canceled 2017-05-19 2017-05-24 2017-06-23 2017-06-30 2017-07-14 2017-08-13 of Four Wheel Drive Jeep Support Envelope NP-NRA-GO-RFB-6 / 2 units Project Implementation Single Stage - One IDA / 57060 Post Request for Bids Open - National 239,560.00 0.00 Canceled 2017-05-19 2017-06-16 2017-05-24 2017-06-23 2017-06-30 2017-07-14 2017-08-13 of Four Wheel Drive SUV Support Envelope NP-NRA-GO-RFB-1-2 / 5 Project Implementation Single Stage - One units of Four Wheel Drive Jeep IDA / 57060 Post Request for Bids Open - National 299,450.00 0.00 Canceled 2017-05-11 2017-06-16 2017-05-16 2017-05-31 2017-06-07 2017-06-21 2017-07-21 Support Envelope vehicle NRA/3018014/IDA/2073/74/ Project Implementation Single Stage - One 02 / 5 units of Four Wheel IDA / 57060 Post Request for Bids Open - National 299,450.00 268,300.71 Signed 2018-02-12 2017-03-23 2018-02-17 2018-03-31 2017-07-17 2018-04-30 2017-07-21 2018-06-04 2017-08-18 2018-07-04 Support Envelope Drive Jeep vehicle EHRP/NRA/G/DC-16/2074- Project Implementation 75 / Procurement of 1000 IDA / 57060 Post Direct Selection Direct 384,900.00 345,101.83 Signed 2018-03-19 2018-02-21 2018-03-26 2018-03-23 2018-04-20 2018-03-30 2018-06-19 Support Tablets EHRP/NRA/G/DC-19/2074- Pending Project Implementation 75 / Procurement of 1000 IDA / 57060 Post Direct Selection Direct 390,000.00 0.00 Implementati 2018-06-28 2018-07-05 2018-07-30 2018-08-29 Support Tablets. on EHRP/NRA/G/SH-18/2074- Pending Project Implementation Request for Single Stage - One 75 / Procurement of 8 Units IDA / 57060 Post Limited 16,000.00 0.00 Implementati 2018-07-03 2018-08-08 2018-08-23 Support Quotations Envelope of Scooters for PMU and on CLPIUs Page 1 EHRP/NRA/G/DC-17/2074- Pending 75 / Procurement of 5 Double IDA / 57060 Housing Reconstruction Post Direct Selection Direct 350,000.00 0.00 Implementati 2018-06-28 2018-06-29 2018-07-07 2018-07-17 Cab Pickup Vehicles for on DLPIUs EHRP/NRA/G/SH-22/2074- 75 / Procurement of Office equipment for EHRP-PMU: 5 Desktops for PMU, Pending Project Implementation Request for Single Stage - One 1 Multimedia Projector for IDA / 57060 Post Limited 19,000.00 0.00 Implementati 2018-07-01 2018-08-08 2018-09-07 Support Quotations Envelope PMU, on 1 Photocopy Machine for PMU, 5 Duplex Printers for PMU and 5 Laptops for PMU. EHRP/NRA/G/DC-13/2074- Project Implementation 75 / Procurement of MIS IDA / 57060 Post Direct Selection Direct 110,000.00 82,327.41 Signed 2018-08-10 2018-09-13 2018-08-13 2018-10-05 2018-09-29 2018-10-11 2018-10-29 Support Server & Network Upgrades EHRP/NRA/G/DC-01/2075- Under 76 / Procurement of 4 units of IDA / 57060 Housing Reconstruction Post Direct Selection Direct 276,000.00 0.00 Implementati 2018-08-31 2018-09-03 2018-10-01 2018-10-16 Double Cab Pick Up Vehicles on EHRP/NRA/G/DC-02/2075- Pending 76 / Procurement of 1 unit of IDA / 57060 Housing Reconstruction Post Direct Selection Direct 74,000.00 0.00 Implementati 2018-08-30 2018-09-02 2018-09-30 2018-10-15 Four Wheel Drive Jeep Vehicle on EHRP/NRA/G/DC-03/2075- Pending 76 / Procurement of 14 units IDA / 57060 Housing Reconstruction Post Direct Selection Direct 42,000.00 0.00 Implementati 2018-09-05 2018-09-10 2018-10-15 2018-12-14 of Motorcycles on EHRP/NRA/G/DC-04/2075- Pending 76 / Procurement of 4 units of IDA / 57060 Housing Reconstruction Post Direct Selection Direct 8,000.00 0.00 Implementati 2018-09-05 2018-09-10 2018-10-15 2018-11-29 Scooters on EHRP/NRA/G/DC-05/2075- 76 / Procurement of 5 units of IDA / 57060 Housing Reconstruction Post Direct Selection Direct 15,000.00 10,791.96 Signed 2019-05-17 2019-06-30 2019-05-22 2019-07-02 2019-06-12 2019-07-10 2019-07-12 Motorcycles EHRP-AF/NRA/G/NCB- 01/2076-77 / Procurement of Furniture for Local level Disaster Risk Management Single Stage - One IDA / 61640 Post Request for Bids Open - National 443,300.00 0.00 Canceled 2019-12-15 2019-12-20 2020-01-19 2020-02-09 2020-03-02 2020-05-01 government (283 Tables, 283 Systems Envelope Chairs and 566 File Cabinets/racks) EHRP-AF/NRA/G/NCB- 03/2076-77 / Procurement of Disaster Risk Management Single Stage - One IDA / 61640 Post Request for Bids Open - National 192,300.00 0.00 Canceled 2019-12-15 2019-12-20 2020-01-19 2020-02-09 2020-03-02 2020-05-01 54000 Index files for local Systems Envelope level government EHRP-AF/NRA/G/NCB- 02/2076-77 / Procurement of Disaster Risk Management Single Stage - One office equipment for local IDA / 61640 Post Request for Bids Open - National 671,600.00 0.00 Canceled 2020-03-29 2020-04-01 2020-05-01 2020-05-15 2020-06-12 2020-09-10 Systems Envelope level government (283 Desktops, 283-3 in 1 Printers) EHRP-AF/NRA/G/NCB- 04/2076-77 / Procurement of Office Materials for Local Pending Disaster Risk Management Single Stage - One Government (868 File IDA / 61640 Post Request for Bids Open - National 693,000.00 0.00 Implementati 2020-06-04 2020-06-11 2020-07-16 2020-07-30 2020-09-03 2020-12-02 Systems Envelope Cabinets/racks, 32200 Box on Magazine Files and 804991 Business Files) NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NRA/EHRP/NC/SH-01/2074- Request for Single Stage - One 75 / Documentary and Jingles IDA / 57060 Housing Reconstruction Post Limited 9,000.00 0.00 Canceled 2018-01-02 2018-02-11 2018-05-13 Quotations Envelope Production-1 EHRP/NRA/NC/DC-02/2074- 75 / Procurement for IDA / 57060 Housing Reconstruction Post Direct Selection Direct 5,000.00 0.00 Canceled 2017-12-28 2017-12-31 2018-02-11 2018-04-12 Nonconsulting Service for Website Update-1 EHRP/NRA/NC/DC-01/2075- 76 / Procurement of SMS Service to 500,000 beneficiaries SMS 1: 'Third Inspection' SMS sent twice. IDA / 57060 Housing Reconstruction Post Direct Selection Direct 88,140.00 69,672.81 Signed 2019-06-03 2019-06-20 2019-06-05 2019-06-26 2019-06-26 2019-07-01 2019-07-26 SMS 2: 'Completion of reconstruction certificate' SMS sent once. SMS 3: 'Free Technical Support and Housing Grant' SMS sent once. EHRP-AF/NRA/NC/DC- Pending 01/2076-77 / Procurement of Project Implementation IDA / 61640 Post Direct Selection Direct 28,000.00 0.00 Implementati 2019-10-31 2019-11-05 2019-12-01 2020-01-15 IT Infrastructure Software Support on License Support EHRP-AF/NRA/NC/DC- 02/2076-77 / Hiring Firm for Pending Project Implementation Production and Broadcasting IDA / 61640 Post Direct Selection Direct 59,800.00 0.00 Implementati 2020-06-12 2020-06-15 2020-07-13 2020-08-27 Support of Audio Jingle and Television on Commercial (TVC) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 EHRP/NRA/S/CQS-44/2074- 75 / Procurement of consultancy service through CQS method, WB procedure Consultant Project Implementation For " Housing Reconstruction IDA / 57060 Post Qualification Open - International 452,874.00 0.00 Canceled 2017-09-22 2017-10-07 2017-12-06 2018-01-05 2018-02-11 2020-02-11 Support Scio-Technical Assistance Selection Team" for Bigu GP and Kalinchok GP of Dolakha district. EHRP/NRA/S/CQS-45/2074- 75 / Procurement of consultancy service through CQS method, WB procedure Consultant Project Implementation For " Housing Reconstruction IDA / 57060 Prior Qualification Open - International 582,032.00 0.00 Canceled 2017-09-22 2017-10-07 2017-12-06 2018-01-05 2018-02-11 2020-02-11 Support Scio-Technical Assistance Selection Team" for Baiteshwor GP and Bhimeshwor NP of Dolakha districts. EHRP/NRA/S/CQS-46/2074- 75 / Procurement of consultancy service through Consultant CQS method, WB procedure Project Implementation IDA / 57060 Post Qualification Open - International 430,861.00 0.00 Canceled 2017-09-22 2017-10-07 2017-12-06 2018-01-05 2018-02-11 2020-02-11 For " Housing Reconstruction Support Selection Scio-Technical Assistance Team" for Melung GP and Sailung GP of Dolakha district. EHRP/NRA/S/CQS-47/2074- 75 / Procurement of consultancy service through CQS method, WB procedure Consultant For " Housing Reconstruction Project Implementation IDA / 57060 Post Qualification Open - International 499,542.00 0.00 Canceled 2017-09-22 2017-10-07 2017-12-06 2018-01-05 2018-02-11 2020-02-11 Scio-Technical Assistance Support Selection Team" for Kispang GP, Meghang GP, Bidur GP, Tarkeshwor GP and Belkotgadi NP of Nuwakot district. EHRP/NRA/S/CQS-48/2074- 75 / Procurement of consultancy service through CQS method, WB procedure Consultant Project Implementation For " Housing Reconstruction IDA / 57060 Post Qualification Open - International 419,012.00 0.00 Canceled 2017-09-22 2017-10-07 2017-12-06 2018-01-05 2018-02-11 2020-02-11 Support Scio-Technical Assistance Selection Team" for Kakani GP, Suryagadhi GP, and Tadi GP of Nuwakot district. EHRP/NRA/S/CQS-49/2074- 75 / Procurement of consultancy service through CQS method, WB procedure Consultant For " Housing Reconstruction Project Implementation IDA / 57060 Prior Qualification Open - International 574,284.00 0.00 Canceled 2017-09-22 2017-10-07 2017-12-06 2018-01-05 2018-02-11 2020-02-11 Scio-Technical Assistance Support Selection Team" for Dupcheshwor GP, Panchkanya GP, Likhu GP, and Shvapuri GP of Nuwakot district. EHRP/NRA/S/CQS-50/2074- 75 / Procurement of consultancy service through CQS method, WB procedure Consultant For " Housing Reconstruction Project Implementation IDA / 57060 Prior Qualification Open - International 530,578.00 0.00 Canceled 2017-09-22 2017-10-07 2017-12-06 2018-01-05 2018-02-11 2020-02-11 Scio-Technical Assistance Support Selection Team" for Ruby Valley GP, Gangajamuna GP, Khaniyabas GP and Netrawati GP of Dhading district. EHRP/NRA/S/CQS-51/2074- 75 / Procurement of consultancy service through CQS method, WB procedure Consultant Project Implementation For " Housing Reconstruction IDA / 57060 Prior Qualification Open - International 570,501.00 0.00 Canceled 2017-09-22 2017-10-07 2017-12-06 2018-01-05 2018-02-11 2020-02-11 Support Scio-Technical Assistance Selection Team" for Nilkantha NP and Tripurasundari GP of Dhading district. EHRP/NRA/S/QCBS-15/2074- Quality And Cost- 75 / Monitoring of IDA / 57060 Housing Reconstruction Post Open - National 60,000.00 0.00 Canceled 2017-12-26 2017-12-29 2018-01-22 2018-02-21 2018-03-07 2018-03-21 2018-04-08 2018-07-07 Based Selection Reconstruction Activities Consultant EHRP/NRA/S/CQS-66/2074- Project Implementation IDA / 57060 Post Qualification Open - National 300,000.00 176,825.70 Signed 2018-04-16 2018-05-10 2018-05-16 2018-07-06 2018-07-04 2018-08-05 2018-08-17 2018-09-09 2018-08-26 2020-08-29 75 / Selection of MIS Firm Support Selection EHRP-AF-PMU/S/CQS-07 / Consultant Project Implementation Selection of M&E Firm at NRA- IDA / 61640 Post Qualification Open - National 300,000.00 0.00 Canceled 2018-04-30 2018-05-21 2018-07-04 2018-08-03 2018-09-07 2021-02-23 Support PMU Selection EHRP-AF-PMU/S/QCBS-01 / Disaster Risk Management Quality And Cost- Selection of DRM Consulting IDA / 61640 Prior Open - National 900,000.00 0.00 Canceled 2018-04-30 2018-05-21 2018-07-04 2018-08-01 2018-08-31 2018-10-05 2018-11-09 2021-04-27 Systems Based Selection Firm EHRP-AF-PMU/S/QCBS-06 / Selection of Project Project Implementation Quality And Cost- IDA / 61640 Prior Open - National 900,000.00 0.00 Canceled 2018-05-11 2018-06-01 2018-07-15 2018-08-12 2018-09-11 2018-10-16 2018-11-20 2021-05-08 Management Consulting Firm Support Based Selection for NRA/PMU EHRP/NRA/S/QCBS-32/2075- Quality And Cost- 76 / Selection of M&E Firm at IDA / 57060 Housing Reconstruction Prior Open - National 933,000.00 732,829.45 Signed 2018-08-30 2018-09-07 2018-09-09 2018-09-10 2018-10-23 2018-12-17 2018-11-20 2019-01-21 2018-12-20 2019-03-15 2019-01-24 2019-04-30 2019-02-28 2019-05-17 2020-08-21 Based Selection NRA-PMU EHRP-AF/CLPIU- EDUCATION/S/QCBS-39/75- 76 / Selection of monitoring and analysis consulting firm (with international expert) to Disaster Risk Management Quality And Cost- IDA / 61640 Prior Open - International 1,050,746.00 0.00 Canceled 2018-10-10 2018-10-31 2018-12-14 2019-01-11 2019-02-10 2019-03-17 2019-04-21 2019-12-17 carry out supervision of Systems Based Selection engineering firms, data analysis for finding out the vulnerability and to prepare Priority Investment Plan Page 3 EHRP-AF/CLPIU- EDUCATION/S/QCBS-40/75- Disaster Risk Management Quality And Cost- 76 / Selection of Civil IDA / 61640 Prior Open - International 1,545,455.00 0.00 Canceled 2018-10-10 2018-10-31 2018-12-14 2019-01-11 2019-02-10 2019-03-17 2019-04-21 2019-12-17 Systems Based Selection Engineering Firm for SIA- Package-1 EHRP-AF/CLPIU- EDUCATION/S/QCBS-41/75- Disaster Risk Management Quality And Cost- 76 / Selection of Civil IDA / 61640 Prior Open - International 1,545,455.00 0.00 Canceled 2018-10-10 2018-10-31 2018-12-14 2019-01-11 2019-02-10 2019-03-17 2019-04-21 2019-12-17 Systems Based Selection Engineering Firm for SIA- Package-2 EHRP-AF/CLPIU- EDUCATION/S/QCBS- Disaster Risk Management Quality And Cost- 42/75/76 / Selection of Civil IDA / 61640 Prior Open - International 1,545,455.00 0.00 Canceled 2018-10-10 2018-10-31 2018-12-14 2019-01-11 2019-02-10 2019-03-17 2019-04-21 2020-04-20 Systems Based Selection Engineering Firm for SIA- Package-3 EHRP-AF/CLPIU- EDUCATION/S/QCBS- Disaster Risk Management Quality And Cost- 43/75/76 / Selection of Civil IDA / 61640 Prior Open - International 1,545,455.00 0.00 Canceled 2018-10-10 2018-10-31 2018-12-14 2019-01-11 2019-02-10 2019-03-17 2019-04-21 2019-12-17 Systems Based Selection Engineering Firm for SIA- Package-4 EHRP-AF/CLPIU- EDUCATION/S/QCBS- Disaster Risk Management Quality And Cost- 44/75/76 / Selection of Civil IDA / 61640 Prior Open - International 1,545,455.00 0.00 Canceled 2018-10-10 2018-10-31 2018-12-14 2019-01-11 2019-02-10 2019-03-17 2019-04-21 2019-12-17 Systems Based Selection Engineering Firm for SIA- Package-5 EHRP/CLPIU- EDUCATION/S/QCBS-39/75- 76 / Selection of monitoring and analysis consulting firm (with international expert) to Disaster Risk Management Quality And Cost- IDA / 57060 Prior Open - International 1,050,746.00 0.00 Canceled 2018-12-21 2019-01-11 2019-02-24 2019-03-24 2019-04-23 2019-05-28 2019-07-02 2020-02-27 carry out supervision of Systems Based Selection engineering firms, data analysis for finding out the vulnerability and to prepare Priority Investment Plan EHRP/CLPIU- EDUCATION/S/QCBS-40/75- Disaster Risk Management Quality And Cost- 76 / Selection of Civil IDA / 57060 Prior Open - International 1,545,455.00 0.00 Canceled 2018-12-21 2019-01-11 2019-02-24 2019-03-24 2019-04-23 2019-05-28 2019-07-02 2020-02-27 Systems Based Selection Engineering Firm for SIA- Package-1 EHRP/CLPIU- EDUCATION/S/QCBS-41/75- Disaster Risk Management Quality And Cost- 76 / Selection of Civil IDA / 57060 Prior Open - International 1,545,455.00 0.00 Canceled 2018-12-21 2019-01-11 2019-02-24 2019-03-24 2019-04-23 2019-05-28 2019-07-02 2020-02-27 Systems Based Selection Engineering Firm for SIA- Package-2 EHRP/CLPIU- EDUCATION/S/QCBS-42/75- Disaster Risk Management Quality And Cost- 76 / Selection of Civil IDA / 57060 Prior Open - International 1,545,455.00 0.00 Canceled 2018-12-21 2019-01-11 2019-02-24 2019-03-24 2019-04-23 2019-05-28 2019-07-02 2020-07-01 Systems Based Selection Engineering Firm for SIA- Package-3 EHRP/CLPIU- EDUCATION/S/QCBS-43/75- Disaster Risk Management Quality And Cost- 76 / Selection of Civil IDA / 57060 Prior Open - International 1,545,455.00 0.00 Canceled 2018-12-21 2019-01-11 2019-02-24 2019-03-24 2019-04-23 2019-05-28 2019-07-02 2020-02-27 Systems Based Selection Engineering Firm for SIA- Package-4 EHRP/CLPIU- EDUCATION/S/QCBS-44/75- Disaster Risk Management Quality And Cost- 76 / Selection of Civil IDA / 57060 Prior Open - International 1,545,455.00 0.00 Canceled 2018-12-21 2019-01-11 2019-02-24 2019-03-24 2019-04-23 2019-05-28 2019-07-02 2020-02-27 Systems Based Selection Engineering Firm for SIA- Package-5 EHRP/NRA/S/CQS-1/20176- 77 / Consulting Service for Third Party Monitoring of Consultant Under Project level compliance IDA / 57060 Housing Reconstruction Post Qualification Open - National 170,000.00 0.00 2019-10-31 2019-11-24 2019-11-14 2020-01-01 2020-01-15 2020-01-25 2020-12-15 Implementation Monitoring on Implementation Selection of Environmental and Social Safeguard. EHRP/NRA/S/CQS-02/2076- Consultant 77 / Selection of Firm for Disaster Risk Management Under IDA / 61640 Post Qualification Open - National 105,900.00 84,396.76 2019-12-15 2019-12-05 2019-12-25 2020-02-08 2020-02-24 2020-03-14 2020-03-22 2020-04-05 2020-05-26 2020-07-04 Capacity building Training Systems Implementation Selection Manual preparation EHRP/NRA/S/CQS-03/2076- 77 / Selection of firm for Capacity building Training of Local Government Consultant representatives and staffs Disaster Risk Management Under IDA / 61640 Post Qualification Open - National 290,970.00 0.00 2020-02-25 2020-03-11 2020-03-17 2020-05-15 2020-06-24 2020-07-16 2021-01-12 (Kathmandu, Lalitpur, Systems Implementation Selection Bhaktapur, Kavre, Sindhupalchowk, Rasuwa, Nuwakot and Dolakha districts) EHRP/NRA/S/CQS-05/2076- 77 / Selection of firm for Capacity building Training of Consultant Local Government Disaster Risk Management Under IDA / 61640 Post Qualification Open - National 295,550.00 0.00 2020-02-25 2020-03-22 2020-03-17 2020-05-15 2020-06-24 2020-07-16 2021-01-12 representatives and staffs Systems Implementation Selection (Tanahu, Lamjung, Kaski, Parbat, Myagdi, Baglung, Gorkha and Dhading districts) EHRP/NRA/S/CQS-06/2076- 77 / Selection of firm for Capacity building Training of Local Government Consultant representatives and staffs Disaster Risk Management Under IDA / 61640 Post Qualification Open - National 290,970.00 0.00 2020-02-25 2020-03-11 2020-03-17 2020-05-15 2020-06-24 2020-07-16 2021-01-12 (Bhojpur, Sankhuwasabha, Systems Implementation Selection Dhankuta, Khotang, Solukhumbu, Ramechhap Sindhuli and Okhaldhunga districts) Page 4 EHRP/NRA/S/CQS-04/2076- 77 / Selection of firm for Capacity building Training of Consultant Local Government Disaster Risk Management Under IDA / 61640 Post Qualification Open - National 278,300.00 0.00 2020-02-25 2020-03-17 2020-03-17 2020-05-15 2020-06-24 2020-07-16 2021-01-12 representatives and staffs Systems Implementation Selection (Gulmi, Palpa, Arghakhachi, Syanja, Nawalparasi, Chitwon and Makawanpur districts) EHRP-AF/NRA/S/CQS- 01/2077-78 / Hiring of Consultant Consulting Firm for Disaster Risk Management Under IDA / 61640 Post Qualification Open - National 91,100.00 0.00 2020-07-30 2020-07-29 2020-08-20 2020-10-03 2020-11-02 2020-12-07 2021-06-05 Development of a Responsive Systems Implementation Selection Web Portal/Platform for “2015 Earthquake Reconstruction” INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NP-NRA-CS-QBS-01 / Individual Financial Management Project Implementation Under IDA / 57060 Post Consultant Open 54,531.00 0.00 2017-06-14 2017-08-25 2021-08-24 Consultant Long Term 48 Support Implementation Selection person Months NP-NRA-CS-CDS-05 / Social Specialist Intermittent with 3 Project Implementation IDA / 57060 Post Direct Selection Direct 8,792.00 6,055.28 Terminated 2017-05-19 2017-05-31 2017-06-17 2017-08-22 2018-06-17 person months input over 12 Support months period NP-NRA-CS-QBS-02 / MIS Individual Project Implementation Under Consultant Long Term 48 IDA / 57060 Post Consultant Open 109,603.00 0.00 2017-05-19 2017-07-30 2021-07-29 Support Implementation Person Months Selection NP-NRA-CS-CDS-04 / Environment Specialist Project Implementation Under Intermittent with 3 person IDA / 57060 Post Direct Selection Direct 8,792.00 0.00 2017-05-19 2017-05-31 2017-06-02 2017-06-17 2018-06-17 Support Implementation months input over 12 months period NP-NRA-CS-QBS-03 / Procurement Consultant Long Individual Project Implementation Term Intermittant 24 person IDA / 57060 Prior Consultant Open 27,265.00 0.00 Canceled 2017-05-19 2017-07-30 2021-07-29 Support months input over 48 months Selection period EHRP/NRA/IND/SSS-1 / Hiring of Individual Project Implementation Pending IDA / 57060 Prior Direct Selection Direct 12,000.00 0.00 2017-09-17 2017-09-24 2017-09-25 2018-04-11 Procurement Consultant Support Implementation (short term) EHRP/NRA/S/IND-7/2074-75 Individual Project Implementation / Individual Training IDA / 57060 Post Consultant Open 24,000.00 0.00 Canceled 2017-12-27 2018-02-07 2018-02-24 2018-03-20 2020-03-19 Support Coordinator Consultant-1 Selection EHRP/NRA/S/IND-12/2074- Individual Project Implementation 75 / Individual Infrastructure IDA / 57060 Post Consultant Open 24,000.00 0.00 Canceled 2017-12-31 2018-01-28 2018-02-04 2018-02-14 2020-02-14 Support Development Consultant-1 Selection EHRP/NRA/S/SSS-13/2074- 75 / Preparation of IDA / 57060 Housing Reconstruction Post Direct Selection Direct 8,000.00 0.00 Canceled 2017-12-29 2018-01-08 2018-02-09 2018-03-26 Reconstruction Profile-1 EHRP/NRA/S/IND/SSS- Project Implementation 3/2074-75 / Procurement of IDA / 57060 Post Direct Selection Direct 12,000.00 0.00 Canceled 2017-12-29 2018-01-08 2018-02-16 2018-08-15 Support Individual Legal Consultant-1 EHRP/NRA/S/IND/SSS- 6/2074-75 / Individual Project Implementation IDA / 57060 Post Direct Selection Direct 12,000.00 0.00 Canceled 2017-12-29 2018-01-08 2018-02-16 2018-08-15 Structural Engineer Consultant- Support 1 EHRP/NRA/S/SSS-8/2074-75 Project Implementation / Consulting Service for IDA / 57060 Post Direct Selection Direct 3,000.00 0.00 Canceled 2017-12-31 2018-01-06 2018-01-28 2018-06-27 Support Development of PIS-1 EHRP/NRA/S/IND/SSS- Project Implementation 10/2074-75 / Individual IDA / 57060 Post Direct Selection Direct 12,000.00 0.00 Canceled 2017-12-31 2018-01-06 2018-02-04 2018-07-04 Support NGO/INGO Activity Analyst-1 EHRP/NRA/S/SSS-11/2074- Project Implementation 75 / Consultancy Service for IDA / 57060 Post Direct Selection Direct 5,000.00 0.00 Canceled 2017-12-29 2018-01-08 2018-02-12 2018-06-12 Support Map analysis-1 EHRP/NRA/S/SSS-14/2074- IDA / 57060 Housing Reconstruction Post Direct Selection Direct 5,000.00 0.00 Canceled 2017-12-31 2018-01-10 2018-02-19 2018-06-19 75 / Survey Data Analysis-1 Individual EHRP/NRA/S/IND/SSS- Project Implementation IDA / 57060 Post Consultant Direct 12,000.00 10,757.26 Signed 2018-02-13 2018-02-11 2018-02-21 2018-02-27 2018-03-03 2018-02-28 2018-03-18 2018-03-04 2019-03-13 34/2074-75 / ICT Expert-1 Support Selection EHRP/NRA/S/IND/SSS- 4/2074-75 / Individual Project Implementation IDA / 57060 Post Direct Selection Direct 12,000.00 11,456.00 Signed 2018-02-12 2018-02-11 2018-02-20 2018-02-27 2018-03-12 2018-03-04 2019-03-07 Land/Resettlement Consultant- Support 1 EHRP/NRA/S/IND/SSS-35- 64/2074-75 / Selection of 30 Individual individual consultants to work IDA / 57060 Housing Reconstruction Post Consultant Direct 301,472.00 8,593.11 Signed 2018-03-30 2018-03-26 2018-04-05 2018-03-30 2018-04-12 2018-03-30 2018-04-26 2018-04-01 2018-10-23 as District Support Engineers Selection DSEs EHRP/NRA/S/IND/SSS- Individual 65/2074-75 / Selection of Project Implementation IDA / 57060 Post Consultant Direct 10,950.00 8,512.46 Signed 2018-03-30 2018-04-30 2018-04-09 2018-05-08 2018-04-16 2018-05-09 2018-04-30 2018-05-10 2018-10-27 individual financial Support Selection management consultant Page 5 EHRP/NRA/S/SSS-67- Individual 69/2074-75 / Selection of 3 IDA / 57060 Housing Reconstruction Post Consultant Direct 50,000.00 12,770.60 Signed 2018-04-09 2018-04-11 2018-04-23 2018-05-03 2018-04-30 2018-05-04 2018-05-21 2018-05-06 2018-11-17 M&E Experts Selection Individual EHRP-AF-PMU/S/IND/DS-02 Disaster Risk Management IDA / 61640 Post Consultant Direct 15,000.00 12,483.47 Signed 2018-04-13 2018-11-21 2018-04-23 2019-01-08 2018-05-14 2019-01-09 2018-06-18 2019-01-10 2018-12-15 / Selection of DRM Specialist Systems Selection EHRP-AF-PMU/S/IND/LCS-04 Individual Disaster Risk Management / Selection of Structure IDA / 61640 Post Consultant Limited 15,000.00 0.00 Canceled 2018-05-16 2018-05-21 2018-06-11 2018-07-16 2019-01-12 Systems Engineer Selection EHRP-AF-PMU/S/IND/LCS-05 Individual Project Implementation / Selection of Urban Planner IDA / 61640 Post Consultant Limited 15,000.00 0.00 Canceled 2018-05-16 2018-05-21 2018-06-11 2018-07-16 2019-01-12 Support Engineer Selection Individual EHRP-AF-PMU/S/IND/LCS-03 Disaster Risk Management IDA / 61640 Post Consultant Limited 15,000.00 0.00 Canceled 2018-05-16 2018-05-21 2018-06-11 2018-07-16 2019-01-12 / Selection of GIS Specialist Systems Selection Individual EHRP/NRA/S/SSS-72/2074- Disaster Risk Management Under IDA / 57060 Post Consultant Direct 15,000.00 0.00 2018-04-17 2018-04-27 2018-05-18 2018-06-22 2018-12-19 75 / Selection of GIS Specialist Systems Implementation Selection EHRP/NRA/S/SSS-75/2074- Individual Project Implementation 75 / Selection of Banking IDA / 57060 Post Consultant Direct 10,500.00 7,420.40 Signed 2018-04-17 2018-04-30 2018-04-27 2018-05-08 2018-05-18 2018-05-09 2018-06-22 2018-05-10 2018-12-19 Support Coordination Specialist Selection EHRP/NRA/S/SSS-76/2074- Individual Project Implementation 75 / Selection of Fiduciary IDA / 57060 Post Consultant Direct 21,000.00 0.00 Canceled 2018-04-17 2018-04-27 2018-05-18 2018-06-22 2018-12-19 Support Risk Management Specialist Selection EHRP/NRA/S/IND-70/2074- Individual Project Implementation Under 75 / Selection of Procurement IDA / 57060 Prior Consultant Limited 14,500.00 0.00 2018-04-09 2018-05-04 2018-04-23 2018-04-26 2018-04-30 2018-05-14 2018-05-21 2018-11-17 Support Implementation Specialist Selection EHRP/NRA/S/SSS-73/2074- Individual Project Implementation 75 / Selection of NGO IDA / 57060 Post Consultant Direct 10,500.00 8,334.90 Signed 2018-05-11 2018-05-21 2018-05-21 2018-05-23 2018-06-11 2018-05-25 2018-07-16 2018-05-27 2019-01-12 Support Coordination Specialist Selection EHRP/NRA/S/IND/IND-79- Individual 98/2074-75 / Selection of 20 IDA / 57060 Housing Reconstruction Post Consultant Open 804,000.00 34,728.16 Signed 2018-05-11 2018-05-15 2018-06-29 2018-06-07 2018-07-20 2018-06-14 2018-08-24 2018-06-18 2019-08-19 District Support Engineers Selection (DSEs) EHRP/NRA/S/SSS-77- Individual Project Implementation 78/2074-75 / Selection of 2 IDA / 57060 Post Consultant Direct 21,000.00 8,512.46 Signed 2018-05-10 2016-05-15 2018-05-20 2018-05-21 2018-06-10 2018-05-21 2018-07-15 2018-05-22 2019-01-11 Support Communication Specialists Selection NP-NRA-CS-CDS-05-01 / Individual Social Specialist Intermittent Project Implementation Pending IDA / 57060 Post Consultant Direct 8,792.00 0.00 2018-06-07 2018-06-19 2018-06-26 2018-07-06 2019-07-06 with 3 person months input Support Implementation Selection over 12 months period EHRP/NRA/S/SSS-99/2074- Individual 75 / Selection of Procurement Disaster Risk Management Under IDA / 57060 Prior Consultant Direct 14,500.00 0.00 2018-07-18 2018-07-19 2018-07-28 2018-07-23 2018-08-18 2018-08-02 2018-09-22 2019-03-21 & Contract Management Systems Implementation Selection Specialist EHRP/NRA/S/SSS-100- Individual Disaster Risk Management 101/2074-75 / Selection of 2 IDA / 57060 Post Consultant Direct 30,000.00 12,601.62 Signed 2018-07-18 2018-07-18 2018-07-28 2018-07-25 2018-08-18 2018-07-29 2018-09-22 2018-07-31 2019-03-21 Systems Structural Engineers Selection EHRP/NRA/S/IND-1-20/2075- Individual 76 / Selection of 20 District IDA / 57060 Housing Reconstruction Post Consultant Open 650,000.00 0.00 Canceled 2018-08-21 2018-10-05 2018-10-15 2018-11-05 2020-04-28 Support Engineers (DSEs) Selection EHRP/NRA/S/IND-21/2075- Individual Project Implementation 76 / Selection of Project IDA / 57060 Post Consultant Open 90,000.00 56,487.40 Signed 2018-08-20 2018-09-17 2018-10-01 2018-12-25 2018-10-15 2019-01-02 2018-11-05 2019-01-03 2020-10-25 Support Management Specialist Selection EHRP/NRA/S/IND-22/2075- Individual Project Implementation 76 / Selection of Procurement IDA / 57060 Prior Consultant Open 68,000.00 36,765.42 Signed 2018-08-21 2018-09-13 2018-10-02 2019-01-08 2018-10-16 2019-01-14 2018-11-06 2019-01-14 2020-10-26 Support Specialist Selection EHRP/NRA/S/IND-23/2075- Individual Pending 76 / Selection of Structure IDA / 57060 Housing Reconstruction Post Consultant Open 45,000.00 0.00 2018-08-24 2018-10-05 2018-10-26 2018-11-30 2020-05-23 Implementation Engineer Selection EHRP/NRA/S/IND-24/2075- Individual Project Implementation 76 / Selection of MIS IDA / 57060 Post Consultant Open 45,000.00 0.00 Canceled 2018-08-24 2018-10-05 2018-10-15 2018-11-05 2020-10-25 Support Specialist Selection EHRP/NRA/S/IND-25/2075- Individual Project Implementation 76 / Selection of Financial IDA / 57060 Post Consultant Open 45,000.00 0.00 Canceled 2018-08-22 2018-10-03 2018-10-13 2018-11-03 2020-10-23 Support Management Consultant Selection EHRP/NRA/S/IND-26/2075- Individual Project Implementation 76 / Selection of Banking IDA / 57060 Post Consultant Open 45,000.00 0.00 Canceled 2018-08-21 2018-10-05 2018-10-15 2018-11-08 2020-10-28 Support Coordination Specialist Selection EHRP/NRA/S/IND-27/2075- Individual Project Implementation 76 / Selection of Social IDA / 57060 Post Consultant Open 60,000.00 39,081.38 Signed 2018-08-21 2018-09-27 2018-10-02 2018-12-16 2018-10-16 2018-12-18 2018-11-06 2018-12-19 2020-10-26 Support Development Specialist Selection EHRP/NRA/S/IND-28/2075- Individual Project Implementation 76 / Selection of IDA / 57060 Post Consultant Open 60,000.00 38,899.97 Signed 2018-08-22 2018-09-26 2018-10-03 2018-12-16 2018-10-13 2018-12-18 2018-11-03 2018-12-19 2020-10-23 Support Environmental Specialist Selection Individual EHRP/NRA/S/IND-29/2075- Project Implementation IDA / 57060 Post Consultant Open 45,000.00 0.00 Canceled 2018-08-27 2018-10-08 2018-10-18 2018-11-11 2020-10-31 76 / Selection of ICT Expert Support Selection EHRP/NRA/S/IND-30/2075- Individual Project Implementation 76 / Selection of IDA / 57060 Post Consultant Open 45,000.00 0.00 Canceled 2018-08-23 2018-10-04 2018-10-14 2018-11-04 2020-10-24 Support Land/Resettlement Specialist Selection Page 6 EHRP/NRA/S/IND-31/2075- Individual Project Implementation 76 / Selection of NGO IDA / 57060 Post Consultant Open 45,000.00 0.00 Canceled 2018-08-28 2018-10-07 2018-10-14 2018-11-04 2020-10-24 Support Coordination Specialist Selection EHRP/NRA/S/IND-33-1- Individual 27/2075-76 / Selection of 27 IDA / 57060 Housing Reconstruction Post Consultant Open 876,000.00 29,212.02 Signed 2018-08-31 2018-09-05 2018-10-15 2018-10-26 2018-10-25 2018-10-30 2018-11-15 2018-10-31 2020-05-08 District Support Engineers Selection (DSEs). EHRP/NRA/S/IND-34/2075- Individual Project Implementation 76 / Selection of Banking IDA / 57060 Post Consultant Limited 40,000.00 34,642.90 Signed 2018-10-04 2018-11-22 2018-10-09 2018-12-06 2018-10-23 2018-12-14 2018-11-20 2018-12-16 2020-07-12 Support Coordination Specialist Selection EHRP/NRA/S/IND-35/2075- Individual Project Implementation 76 / Selection of Financial IDA / 57060 Post Consultant Limited 40,000.00 27,586.39 Signed 2018-10-04 2018-10-29 2018-10-09 2018-12-28 2018-10-23 2018-12-30 2018-11-20 2018-12-31 2020-07-12 Support Management Consultant Selection EHRP/NRA/S/IND-36/2075- Individual Project Implementation 76 / Selection of MIS IDA / 57060 Post Consultant Limited 40,000.00 14,750.46 Signed 2018-10-04 2019-05-28 2018-10-09 2019-06-28 2018-10-23 2019-07-05 2018-11-20 2019-07-05 2020-07-12 Support Consultant Selection EHRP/NRA/S/SSS-37/2075- Individual 76 / Selection of Livelihood IDA / 57060 Housing Reconstruction Post Consultant Direct 14,500.00 13,823.46 Signed 2018-10-04 2019-02-22 2018-10-14 2019-02-25 2018-10-19 2019-02-27 2018-11-16 2019-03-01 2019-05-15 Support Consultant Selection EHRP-AF/CLPIU- EDUCATION/S/DS-38/2075- Disaster Risk Management 76 / Selection of MIS IDA / 61640 Post Direct Selection Direct 43,403.00 0.00 Canceled 2018-10-08 2018-10-15 2018-11-08 2019-07-09 Systems Consulting Firm to prepare Survey Apps EHRP/NRA/S/IND-38/2075- Individual Project Implementation 76 / Selection of IDA / 57060 Post Consultant Limited 33,600.00 28,691.23 Signed 2018-11-12 2019-01-30 2018-11-17 2019-02-17 2018-12-08 2019-02-18 2019-01-12 2019-02-19 2020-07-05 Support Communication Specialist Selection Individual EHRP/NRA/S/IND-39/2075- Project Implementation IDA / 57060 Post Consultant Limited 33,600.00 32,036.73 Signed 2018-11-12 2019-01-02 2018-11-17 2019-02-27 2018-12-08 2019-03-01 2019-01-12 2019-03-01 2020-07-05 76 / Selection of ICT Expert Support Selection EHRP/NRA/S/IND-40/2075- Individual Project Implementation Under 76 / Selection of Land IDA / 57060 Post Consultant Limited 33,600.00 0.00 2018-11-12 2018-11-17 2018-12-08 2019-01-12 2020-07-05 Support Implementation Resettlement Specialist Selection EHRP/NRA/S/IND-41/2075- Individual Under 76 / Selection of NGO IDA / 57060 Housing Reconstruction Post Consultant Limited 33,600.00 0.00 2018-11-12 2018-11-17 2018-12-08 2019-01-12 2020-07-05 Implementation Coordination Specialist Selection EHRP/CLPIU- EDUCATION/S/SSS-38/2075- Disaster Risk Management 76 / Selection of MIS IDA / 57060 Post Direct Selection Direct 43,403.00 33,841.13 Signed 2018-12-17 2018-12-24 2019-01-03 2019-01-17 2019-02-03 2019-09-17 Systems Consulting Firm to prepare Survey Apps EHRP/NRA/S/SSS-42/2075- 76 / Selection of Consulting Pending IDA / 57060 Housing Reconstruction Post Direct Selection Direct 26,500.00 0.00 2018-12-28 2019-01-04 2019-02-01 2019-05-02 Firm to Prepare Re-Survey and Implementation Re-verification App Individual EHRP/NRA/S/IND-43/2075- Project Implementation Pending IDA / 57060 Post Consultant Limited 33,600.00 0.00 2019-01-18 2019-01-23 2019-02-13 2019-03-20 2020-09-10 76 / Selection of GIS Specialist Support Implementation Selection EHRP/NRA/S/IND-44/2075- Individual Project Implementation 76 / Selection of Financial IDA / 57060 Post Consultant Limited 54,000.00 39,268.82 Signed 2019-02-19 2019-02-22 2019-02-24 2019-02-27 2019-03-10 2019-03-01 2019-03-24 2019-03-01 2021-03-13 Support Management Consultant Selection EHRP-AF-PMU/S/IND- Individual 01/2076-77 / Selection of Project Implementation IDA / 61640 Post Consultant Limited 18,000.00 16,055.57 Signed 2019-07-31 2019-08-04 2019-08-03 2019-10-15 2019-08-17 2019-10-18 2019-09-11 2019-10-20 2020-11-04 Implementation & Support Support Selection Consultant EHRP-AF-PMU/S/IND- Individual Disaster Risk Management 02/2076-77 / Selection of IDA / 61640 Post Consultant Limited 31,000.00 24,288.39 Signed 2019-08-30 2019-08-04 2019-09-02 2019-10-18 2019-09-16 2019-10-20 2019-10-11 2019-11-01 2020-11-04 Systems DRM Specialist Selection EHRP-AF-PMU/S/IND- Individual Project Implementation 03/2076-77 / Selection of IT IDA / 61640 Post Consultant Limited 24,000.00 0.00 Canceled 2019-07-31 2019-08-04 2019-08-03 2019-08-17 2019-09-11 2020-11-04 Support Specialist Selection EHRP-AF-PMU/NRA/S/IND- Individual Project Implementation 03-1/2076-77 / Selection of IDA / 61640 Post Consultant Limited 37,000.00 32,124.50 Signed 2019-10-31 2019-11-24 2019-11-03 2019-12-27 2019-11-10 2019-12-29 2019-11-24 2020-01-31 2020-12-18 Support IT Specialist Selection EHRP-AF/NRA/S/CDS- 01/2076-77 / Hiring of Project Implementation Under Consulting Firm for Fiduciary IDA / 61640 Post Direct Selection Direct 62,500.00 0.00 2020-05-22 2020-05-31 2020-05-28 2020-07-02 2020-12-29 Support Implementation Risk Assessment and Reconciliation EHRP-AF/NRA/S/CDS- 03/2076-77 / Hiring of Project Implementation Consulting Firm for Review IDA / 61640 Post Direct Selection Direct 105,000.00 89,747.44 Signed 2020-05-25 2020-05-25 2020-05-31 2020-06-08 2020-06-28 2020-06-10 2020-12-25 Support and Verification of Data in NRA-MIS of IDA Beneficiary EHRP-AF/NRA/S/CDS- 02/2076-77 / Hiring of Consulting Firm for Disaster Risk Management IDA / 61640 Post Direct Selection Direct 91,100.00 0.00 Canceled 2020-06-07 2020-06-18 2020-06-13 2020-07-28 2021-01-24 Development of a Responsive Systems Web Portal/Platform for “2015 Earthquake Reconstruction” EHRP-AF/NRA/S/SSS- Individual 01/2076-77 / Selection of Project Implementation IDA / 61640 Post Consultant Direct 9,200.00 8,727.28 Signed 2020-07-20 2020-07-26 2020-07-30 2020-08-27 2020-08-20 2020-08-28 2020-09-06 2020-08-28 2021-03-05 Banking Coordination Support Selection Specialist Page 7 EHRP-AF/NRA/S/SSS- Individual Project Implementation 02/2076-77 / Selection of IDA / 61640 Post Consultant Direct 12,400.00 11,770.34 Signed 2020-07-20 2020-08-05 2020-07-30 2020-08-27 2020-08-20 2020-08-28 2020-09-06 2020-08-28 2021-03-05 Support Social Development Specialist Selection EHRP-AF/NRA/S/SSS- Individual Project Implementation 03/2076-77 / Selection of IDA / 61640 Post Consultant Direct 12,400.00 11,665.12 Signed 2020-07-20 2020-08-04 2020-07-30 2020-08-22 2020-08-20 2020-08-28 2020-09-06 2020-08-28 2021-03-05 Support Environmental Specialist Selection EHRP-AF/NRA/S/SSS- Individual 04/2076-77 / Selection of Project Implementation Under IDA / 61640 Post Consultant Direct 9,700.00 0.00 2020-07-20 2020-07-30 2020-08-20 2020-09-06 2021-03-05 Financial Management Support Implementation Selection Consultant EHRP-AF/NRA/S/SSS- Individual Project Implementation 05/2076-77 / Selection of IDA / 61640 Post Consultant Direct 7,300.00 6,855.99 Signed 2020-07-20 2020-08-16 2020-07-30 2020-08-27 2020-08-20 2020-08-28 2020-09-06 2020-08-28 2021-03-05 Support MIS Consultant Selection EHRP-AF/NRA/S/SSS-1- Individual 1/2077-78 / Selection of Project Implementation Under IDA / 61640 Post Consultant Direct 26,300.00 0.00 2020-07-31 2020-12-11 2020-08-06 2020-08-27 2020-09-24 2021-03-23 District Support Engineers Support Implementation Selection (DSE) EHRP-AF/NRA/S/SSS-1- Individual 2/2077-78 / Selection of Project Implementation Under IDA / 61640 Post Consultant Direct 26,300.00 0.00 2020-07-31 2020-12-11 2020-08-06 2020-08-27 2020-09-24 2021-03-23 District Support Engineers Support Implementation Selection (DSE) EHRP-AF/NRA/S/SSS-1- Individual 4/2077-78 / Selection of Project Implementation Under IDA / 61640 Post Consultant Direct 26,300.00 0.00 2020-07-31 2020-12-11 2020-08-06 2020-08-27 2020-09-24 2021-03-23 District Support Engineers Support Implementation Selection (DSE) EHRP-AF/NRA/S/SSS-1- Individual 5/2077-78 / Selection of Project Implementation Under IDA / 61640 Post Consultant Direct 26,300.00 0.00 2020-07-31 2020-12-11 2020-08-06 2020-08-27 2020-09-24 2021-03-23 District Support Engineers Support Implementation Selection (DSE) EHRP-AF/NRA/S/SSS-1- Individual 6/2077-78 / Selection of Project Implementation Under IDA / 61640 Post Consultant Direct 26,300.00 0.00 2020-07-31 2020-12-11 2020-08-06 2020-08-27 2020-09-24 2021-03-23 District Support Engineers Support Implementation Selection (DSE) EHRP-AF/NRA/S/SSS-1- Individual 7/2077-78 / Selection of Project Implementation Under IDA / 61640 Post Consultant Direct 26,300.00 0.00 2020-07-31 2020-12-11 2020-08-06 2020-08-27 2020-09-24 2021-03-23 District Support Engineers Support Implementation Selection (DSE) EHRP-AF/NRA/S/SSS-1- Individual 8/2077-78 / Selection of Project Implementation Under IDA / 61640 Post Consultant Direct 26,300.00 0.00 2020-07-31 2020-12-11 2020-08-06 2020-08-27 2020-09-24 2021-03-23 District Support Engineers Support Implementation Selection (DSE) EHRP-AF/NRA/S/SSS-1- Individual 9/2077-78 / Selection of Project Implementation Under IDA / 61640 Post Consultant Direct 26,300.00 0.00 2020-07-31 2020-12-11 2020-08-06 2020-08-27 2020-09-24 2021-03-23 District Support Engineers Support Implementation Selection (DSE) EHRP-AF/NRA/S/SSS-1- Individual 10/2077-78 / Selection of Project Implementation Under IDA / 61640 Post Consultant Direct 26,300.00 0.00 2020-07-31 2020-12-11 2020-08-06 2020-08-27 2020-09-24 2021-03-23 District Support Engineers Support Implementation Selection (DSE) EHRP-AF/NRA/S/SSS-1- Individual 11/2077-78 / Selection of Project Implementation Under IDA / 61640 Post Consultant Direct 26,300.00 0.00 2020-07-31 2020-12-11 2020-08-06 2020-08-27 2020-09-24 2021-03-23 District Support Engineers Support Implementation Selection (DSE) EHRP-AF/NRA/S/SSS-1- Individual 12/2077-78 / Selection of Project Implementation Under IDA / 61640 Post Consultant Direct 26,300.00 0.00 2020-07-31 2020-12-11 2020-08-06 2020-08-27 2020-09-24 2021-03-23 District Support Engineers Support Implementation Selection (DSE) EHRP-AF/NRA/S/SSS-1- Individual 13/2077-78 / Selection of Project Implementation Under IDA / 61640 Post Consultant Direct 26,300.00 0.00 2020-07-31 2020-12-11 2020-08-06 2020-08-27 2020-09-24 2021-03-23 District Support Engineers Support Implementation Selection (DSE) EHRP-AF/NRA/S/SSS-1- Individual 14/2077-78 / Selection of Project Implementation Under IDA / 61640 Post Consultant Direct 26,300.00 0.00 2020-07-31 2020-12-11 2020-08-06 2020-08-27 2020-09-24 2021-03-23 District Support Engineers Support Implementation Selection (DSE) EHRP-AF/NRA/S/SSS-1- Individual 15/2077-78 / Selection of Project Implementation Under IDA / 61640 Post Consultant Direct 26,300.00 0.00 2020-07-31 2020-12-11 2020-08-06 2020-08-27 2020-09-24 2021-03-23 District Support Engineers Support Implementation Selection (DSE) EHRP-AF/NRA/S/SSS-1- Individual 16/2077-78 / Selection of Project Implementation Under IDA / 61640 Post Consultant Direct 26,300.00 0.00 2020-07-31 2020-12-11 2020-08-06 2020-08-27 2020-09-24 2021-03-23 District Support Engineers Support Implementation Selection (DSE) EHRP-AF/NRA/S/SSS-1- Individual 17/2077-78 / Selection of Project Implementation Under IDA / 61640 Post Consultant Direct 26,300.00 0.00 2020-07-31 2020-12-11 2020-08-06 2020-08-27 2020-09-24 2021-03-23 District Support Engineers Support Implementation Selection (DSE) EHRP-AF/NRA/S/SSS-1- Individual 18/2077-78 / Selection of Project Implementation Under IDA / 61640 Post Consultant Direct 26,300.00 0.00 2020-07-31 2020-12-11 2020-08-06 2020-08-27 2020-09-24 2021-03-23 District Support Engineers Support Implementation Selection (DSE) EHRP-AF/NRA/S/SSS-1- Individual 19/2077-78 / Selection of Project Implementation Under IDA / 61640 Post Consultant Direct 26,300.00 0.00 2020-07-31 2020-12-11 2020-08-06 2020-08-27 2020-09-24 2021-03-23 District Support Engineers Support Implementation Selection (DSE) Page 8 EHRP-AF/NRA/S/SSS-1- Individual 20/2077-78 / Selection of Project Implementation Under IDA / 61640 Post Consultant Direct 26,300.00 0.00 2020-07-31 2020-12-11 2020-08-06 2020-08-27 2020-09-24 2021-03-23 District Support Engineers Support Implementation Selection (DSE) EHRP-AF/NRA/S/SSS-1- Individual 21/2077-78 / Selection of Project Implementation Under IDA / 61640 Post Consultant Direct 26,300.00 0.00 2020-07-31 2020-12-11 2020-08-06 2020-08-27 2020-09-24 2021-03-23 District Support Engineers Support Implementation Selection (DSE) EHRP-AF/NRA/S/SSS-1- Individual 22/2077-78 / Selection of Project Implementation Under IDA / 61640 Post Consultant Direct 26,300.00 0.00 2020-07-31 2020-12-12 2020-08-06 2020-08-27 2020-09-24 2021-03-23 District Support Engineers Support Implementation Selection (DSE) EHRP-AF/NRA/S/SSS-1- Individual 23/2077-78 / Selection of Project Implementation Under IDA / 61640 Post Consultant Direct 26,300.00 0.00 2020-07-31 2020-12-12 2020-08-06 2020-08-27 2020-09-24 2021-03-23 District Support Engineers Support Implementation Selection (DSE) EHRP-AF/NRA/S/SSS-1- Individual 24/2077-78 / Selection of Project Implementation Under IDA / 61640 Post Consultant Direct 26,300.00 0.00 2020-07-31 2020-12-12 2020-08-06 2020-08-27 2020-09-24 2021-03-23 District Support Engineers Support Implementation Selection (DSE) EHRP-AF/NRA/S/SSS-1- Individual 25/2077-78 / Selection of Project Implementation Under IDA / 61640 Post Consultant Direct 26,300.00 0.00 2020-07-31 2020-12-12 2020-08-06 2020-08-27 2020-09-24 2021-03-23 District Support Engineers Support Implementation Selection (DSE) EHRP-AF/NRA/S/SSS-1- Individual 26/2077-78 / Selection of Project Implementation Under IDA / 61640 Post Consultant Direct 26,300.00 0.00 2020-07-31 2020-12-13 2020-08-06 2020-08-27 2020-09-24 2021-03-23 District Support Engineers Support Implementation Selection (DSE) EHRP-AF/NRA/S/SSS-1- Individual 27/2077-78 / Selection of Project Implementation Under IDA / 61640 Post Consultant Direct 26,300.00 0.00 2020-07-31 2020-12-13 2020-08-06 2020-08-27 2020-09-24 2021-03-23 District Support Engineers Support Implementation Selection (DSE) EHRP-AF/NRA/S/SSS-1- Individual 28/2077-78 / Selection of Project Implementation Under IDA / 61640 Post Consultant Direct 26,300.00 0.00 2020-07-31 2020-12-13 2020-08-06 2020-08-27 2020-09-24 2021-03-23 District Support Engineers Support Implementation Selection (DSE) EHRP-AF/NRA/S/SSS-1- Individual 29/2077-78 / Selection of Project Implementation Under IDA / 61640 Post Consultant Direct 26,300.00 0.00 2020-07-31 2020-12-13 2020-08-06 2020-08-27 2020-09-24 2021-03-23 District Support Engineers Support Implementation Selection (DSE) EHRP-AF/NRA/S/SSS-1- Individual 30/2077-78 / Selection of Project Implementation Under IDA / 61640 Post Consultant Direct 26,300.00 0.00 2020-07-31 2020-12-13 2020-08-06 2020-08-27 2020-09-24 2021-03-23 District Support Engineers Support Implementation Selection (DSE) EHRP-AF/NRA/S/SSS-1- Individual 31/2077-78 / Selection of Project Implementation Under IDA / 61640 Post Consultant Direct 26,300.00 0.00 2020-07-31 2020-12-13 2020-08-06 2020-08-27 2020-09-24 2021-03-23 District Support Engineers Support Implementation Selection (DSE) EHRP-AF/NRA/S/SSS-1- Individual 32/2077-78 / Selection of Project Implementation Under IDA / 61640 Post Consultant Direct 26,300.00 0.00 2020-07-31 2020-12-13 2020-08-06 2020-08-27 2020-09-24 2021-03-23 District Support Engineers Support Implementation Selection (DSE) EHRP-AF/NRA/S/SSS-1- Individual 33/2077-78 / Selection of Project Implementation Under IDA / 61640 Post Consultant Direct 26,300.00 0.00 2020-07-31 2020-12-13 2020-08-06 2020-08-27 2020-09-24 2021-03-23 District Support Engineers Support Implementation Selection (DSE) EHRP-AF/NRA/S/SSS-1- Individual 3/2077-78 / Selection of Project Implementation Under IDA / 61640 Post Consultant Direct 26,300.00 0.00 2020-07-31 2020-12-11 2020-08-06 2020-08-27 2020-09-24 2021-03-23 District Support Engineers Support Implementation Selection (DSE) EHRP-AF/NRA/S/SSS- Individual Project Implementation Under 02/2077-78 / Selection of IDA / 61640 Post Consultant Direct 9,500.00 0.00 2020-08-21 2020-12-13 2020-08-27 2020-09-10 2020-10-15 2021-04-13 Support Implementation Communication Specialist Selection EHRP-AF/NRA/S/SSS- Individual Project Implementation Under 03/2077-78 / Selection of IDA / 61640 Prior Consultant Direct 14,900.00 0.00 2020-10-30 2020-12-17 2020-11-09 2020-11-30 2021-01-04 2021-07-03 Support Implementation Procurement Specialist Selection EHRP-AF/NRA/S/SSS- Individual Project Implementation 04/2077-78 / Selection of IDA / 61640 Post Consultant Direct 18,900.00 0.00 Under Review 2020-10-30 2020-12-23 2020-11-09 2020-11-30 2021-01-04 2021-07-03 Support Project Management Specialist Selection EHRP-AF/NRA/S/SSS- Individual Disaster Risk Management 05/2077-78 / Selection of IDA / 61640 Post Consultant Direct 24,900.00 0.00 Under Review 2020-10-30 2020-12-23 2020-11-09 2020-11-30 2021-01-04 2021-07-03 Systems DRM Specialist Selection EHRP-AF/NRA/S/SSS- Individual 06/2077-78 / Selection of Project Implementation IDA / 61640 Post Consultant Limited 12,900.00 0.00 Canceled 2020-10-30 2020-12-13 2020-11-04 2020-11-18 2020-12-02 2022-11-22 Financial Management Support Selection Specialist EHRP-AF/NRA/S/SSS- Individual Project Implementation Under 07/2077-78 / Selection of IDA / 61640 Post Consultant Direct 10,200.00 0.00 2020-10-30 2020-12-18 2020-11-09 2020-11-30 2021-01-04 2021-07-03 Support Implementation ICT Expert Selection EHRP-AF/NRA/S/SSS- Individual 08/2077-78 / Selection of Project Implementation Under IDA / 61640 Post Consultant Direct 7,600.00 0.00 2020-10-30 2020-12-21 2020-11-09 2020-11-30 2021-01-04 2021-07-03 Project Implementation & Support Implementation Selection Support Consultant EHRP-AF/NRA/S/SSS- Individual Project Implementation 09/2077-78 / Selection of IT IDA / 61640 Post Consultant Direct 14,900.00 0.00 Under Review 2020-10-30 2020-12-23 2020-11-09 2020-11-30 2021-01-04 2021-07-03 Support Specialist Selection Page 9 EHRP-AF/NRA/S/SSS-06- Individual 1/2077-78 / Selection of Project Implementation Pending IDA / 61640 Post Consultant Direct 12,900.00 0.00 2020-12-21 2020-12-27 2021-01-17 2021-01-31 2021-07-30 Financial Management Support Implementation Selection Specialist Page 10