Overall Implementation and Procurement Plan for the Vietnam COVID-19 Emergency Response Project Project code: P174389 Prepared by NIHE, July 2020 1. Project information: Country: Viet Nam Borrower/Recipient: Socialist Republic of Viet Nam Project Name: Vietnam COVID-19 Emergency Response Project Project ID No: P174389 Project Implementing Agency: NIHE 2. Bank’s approval date of the Procurement Plan: to be approved in the STEP. 3. Date of General Procurement Notice: to be inserted before project implementation. 4. Period covered by this procurement plan: the whole project implementation period I. Works and Goods and Non-Consultant Services: 1. Prior Review Threshold and Procurement Method Thresholds: The proposed procurement approach for this emergency project prioritizes fast track emergency procurement for the emergency goods and services needed. Key measures to fast track procurement include: (i) use of simple and fast procurement and selection methods fit for an emergency situation including direct contracting, as appropriate, (ii) streamlined competitive procedures with shorter bidding time, (iii) force account, as appropriate, and (iv) unlimited thresholds for Requests For Quotations and national procurement among others, as well as no prior review for emergency procurement.. 2. Prequalification. Not expected for the works/goods packages. 3. Any Other Special Procurement Arrangements: National procurement procedures as specified under paragraph 5.4 of the Procurement Regulations and the conditions specified in Annex 1 to this Procurement Plan 4. Leased assets as specified under paragraph 5.10 of the Procurement Regulations: Not applicable. 5. Procurement of second hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not applicable. 6. Hands-on Expanded Implementation Support (HEIS) as specified under paragraph 3.10 and 3.11 of the Procurement Regulations: Not Applicable. 1 II. Selection of Consultants 1. Prior Review Threshold and Selection Method Thresholds: Simple and fast method will be used including: (i) Direct Selection, as appropriate, (ii) CQS, and (iii) national procurement among others, as well as no prior review for emergency procurement. 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than US$ 500,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 7.1, Section VII of the Procurement Regulations. III. Procurement packages with method and Time Schedule Pack Selection Evaluation Expected time No. Comp. No1 Estimated Market method methods for Contract Description WB Remarks price (USD) approach Implementation review Consulting services IC 7/2020 National Open/ Best Hiring consultants Post 1 TV1 253.238 Limited qualified Including: Review Competitive candiadate Selection/DS TV1.1 Coordinator 14.847 TV1.2 Finance and procurement consultant 34.560 TV1.3 Receiving and equipment management consultant 8.687 TV1.4 Accountant Manager 17.374 TV1.5 Disbursement consultant 17.374 TV1.6 Project monitoring & evaluation consultant 17.374 2 TV1.7 Communication consultant 11.520 TV1.8 Research Consultant 18.900 TV1.9 Training consultant 23.040 TV1.10 Community research consultant 23.040 TV1.11 Data management and analysing consultant 7.680 Consultant to develop standard Post Direct 7/2020 2 TV2 procedure for operation and 4.608 DS maintenance of new equipment National Evaluate capacity of testing Direct 7/2020 and biosafety assurance of laboratories at provincial Post National 3 TV3 hospitals and provincial centers 5.760 DS for disease control engaged in surveillance and response to the COVID-19 pandemic Consultant on developing plans Direct 7/2020 and assessment tools; on collecting information, entering Post National 4 TV4 5.760 DS data, analysing data and writing reports on testing capacity and biosafety of laboratories Consultant on developing the Post Direct 7/2020 protocol to the Institutional 5 TV5 Review Board (IRB), and adapt 2.880 National DS the protocol according to the recommendations of the IRB Review of Viet Nam's COVID- Post Direct 7/2020 6 TV6 19 pandemic risk 4.068 DS communication National Independent financial audit Post 7/2020 7 TV7 21.621 National CQS consultant 3 Goods and Non-consulting services Limited/ 7/2020 Delivery Supply and completely install Open time: 06 the system of Transmission Lowest National RFB or RFQ months 1 TB1 electron microscope (TEM) 1.398.000 Post evaluated or DS from the cost signing of the contract Supply and completely install Limited 8/2020 Delivery the specialized refrigerator National time: 04 Lowest system for microbiological months 2 TB2 345.300 Post RFQ evaluated samples storage and the from the cost temperature monitoring and signing of control system the contract Supply and completely install Limited 8/2020 Delivery the air-conditioning system for National time: 04 standardized laboratory animal RFQ Lowest months 3 TB3 rearing area for testing of new 165.000 Post evaluated from the pandemic and pandemic agents cost signing of the contract Supply and completely install Limited 8/2020 Delivery 1,000 KVA standby generators National time: 04 TB4 for the entire operation of the Lowest months 4 Biosafety laboratories systems 289.000 Post RFQ evaluated from the level 2 and 3 cost signing of the contract Upgrade and install completely Direct 8/2020 Delivery Lowest HVAC control and monitoring time: 04 5 TB5 84.500 Post National DS evaluated system for Level 3 Biosafety months cost laboratory system from the 4 signing of the contract Limited 8/2020 Delivery Supply and completely install National time: 04 Lowest equipment of the Biosafety RFQ months 6 TB6 781.040 Post evaluated laboratories systems level 2 and from the cost 3 signing of the contract Limited RFQ 8/2020 Delivery Supply and completely install National time: 04 SARS-CoV-2 virus research Lowest months 7 TB7 equipment 1.278.160 Post evaluated from the cost signing of the contract Limited RFQ 8/2020 Delivery Supply and completely install National time: 04 equipment for COVID-19 Lowest months 8 TB8 vaccine research and 866.000 Post evaluated from the production, and for COVID-19 cost signing of test kit production the contract Limited RFQ 7/2020 Delivery time: 02 Post National Lowest Consumables, test kit for months 9 SPNC1 118.800 evaluated ELISA testing from the cost signing of the contract Consumables and materials for Limited RFQ Lowest 7/2020 Delivery 10 SPNC2 PRNT testing 99.000 evaluated time: 02 Post National cost months from the 5 signing of the contract Post Direct DS 7/2020 Delivery Consumables and materials for time: 02 National TOT courses on ELISA testing weeks from 11 SPDT1 1.000 technique for SARS-CoV2 the signing diagnostic of the contract Consumables and materials for Post Direct DS 7/2020 Delivery training courses on ELISA time: 02 National testing technique for SARS- weeks from 12 SPDT 2 2.000 CoV2 diagnostic for laboratory the signing staff in provinces and hospitals of the in the North contract Consumables and materials for Post Direct DS 7/2020 Delivery training courses on ELISA time: 02 National testing technique for SARS- weeks from 13 SPDT3 1.000 CoV2 diagnostic for laboratory the signing staff in provinces and hospitals of the in the Central contract Consumables and materials for Post Direct DS 7/2020 Delivery training courses on ELISA time: 02 National testing technique for SARS- weeks from 14 SPDT4 1.000 CoV2 diagnostic for laboratory the signing staff in provinces and hospitals of the in the Highland contract Consumables and materials for Post Direct DS 7/2020 Delivery training courses on ELISA time: 02 15 SPDT5 1.000 National testing technique for SARS- weeks from CoV2 diagnostic for laboratory the signing 6 staff in provinces and hospitals of the in the South contract Consumables and materials for Post Direct DS 7/2020 Delivery training courses on techniques time: 02 of sampling, storing and National weeks from transporting of samples the signing 16 SPDT6 suspicious to be infected with 2.000 of the SARS-CoV2, on biosafety and contract quality control at biosafety level 2 laboratories in Northern provinces Consumables and materials for Post Direct DS 7/2020 Delivery training courses on techniques time: 02 of sampling, storing and National weeks from transporting of samples the signing 17 SPDT7 suspicious to be infected with 1.000 of the SARS-CoV2, on biosafety and contract quality control at biosafety level 2 laboratories in Central provinces Consumables and materials for Post Direct DS 7/2020 Delivery training courses on techniques time: 02 of sampling, storing and National weeks from transporting of samples the signing 18 SPDT8 suspicious to be infected with 500 of the SARS-CoV2, on biosafety and contract quality control at biosafety level 2 laboratories in Highland provinces Consumables and materials for Post Direct DS 7/2020 Delivery training courses on techniques time: 02 of sampling, storing and National 19 SPDT9 1.000 weeks from transporting of samples the signing suspicious to be infected with SARS-CoV2, on biosafety and 7 quality control at biosafety level of the 2 laboratories in Southern contract provinces Post Direct DS 7/2020 Delivery Supplies, consumables and time: 02 tools for sampling, preserving National weeks from 20 VT1 5.500 and transporting samples in the the signing North of the contract Post Direct DS 7/2020 Delivery Supplies, consumables and time: 02 National tools for sampling, preserving weeks from 21 VT2 5.500 and transporting samples in the the signing Central of the contract Post Direct DS 7/2020 Delivery Supplies, consumables and time: 02 National tools for sampling, preserving weeks from 22 VT3 5.500 and transporting samples in the the signing South of the contract Renting classroom for training Post Direct DS 8/2020 courses on ELISA testing technique for SARS-CoV2 National 23 HT1 4.872 diagnostic for laboratory staff in provinces and hospitals in the North Renting classroom for training Post Direct DS 8/2020 courses on ELISA testing technique for SARS-CoV2 National 24 HT2 2.184 diagnostic for laboratory staff in provinces and hospitals in the Central 8 Post Limited RFQ 8/2020 Contract time: 04 Documentary film about the National months 25 PTL battle against COVID-19 in 40.000 from the Vietnam signing of the contract Sample collection for Post Direct FA 8/2020 26 TTM1 community immunity study in 22.800 the north National Sample collection for Post Direct FA 8/2020 27 TTM2 community immunity study in 24.300 the central National Sample collection for Post Direct FA 8/2020 28 TTM3 community immunity study in 24.300 the south National Post Direct FA 8/2020 29 XN Perform serological tests 78.750 National TOTAL Note: The bidding package price includes all import 5.954.941 taxes, VAT and all kinds of expenses. The Procurement Plan shall be updated or adjusted during the project implementation as required to reflect the actual project implementation. CQS: Consultant Qualification Based Selection DS: Direct Selection RFQ: Request for Quotations BFP: Bank Facilitated Procurement FA: Force Account 9 Annex 1 - Additional National Procurement Provisions. In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. 1. Open Competitive Procurement: When the Recipient uses its own national open competitive procurement arrangements as set forth in (a) Article 20 on Open Bidding of the Recipient’s Law on Procurement No. 43/2013/QH13 dated November 26, 2013 and related provisions necessary to effect the same; and (b) the Recipient’s Decree No. 63/2014/ND-CP dated June 26, 2014 Guiding Implementation of the Law on the Procurement (collectively, “National Procurement Laws”), such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. (i) No domestic preference over foreign bidders shall be granted to national bidders in bid evaluation, nor shall foreign bidders be asked or required to form joint ventures with or be subcontractors to national bidders in order to submit a bid. (ii) The model bidding documents (harmonized model bidding documents) agreed with the Association shall be used. (iii) No bid shall be eliminated from detailed evaluation on the basis of minor, non-substantive deviations. The evaluation of bidder’s qualifications shall be conducted separately subsequent to the technical and commercial evaluation of the bid. (iv) A bidder shall neither be required nor permitted, as a condition for award, to undertake obligations not specified in the bidding documents or otherwise to modify the bid as originally submitted. (v) No bid shall be rejected on the basis of a comparison with the employer’s estimate and budget ceiling. (vi) The Recipient shall implement an effective mechanism allowing bidders to complaint and have their complaints handled in a timely manner. The complaints mechanism shall allow the submission of anonymous complaints. 10 PROCUREMENT Vietnam : Vietnam COVID-19 Emergency Response Project PLAN General Information Country: Vietnam Bank’s Approval Date of the Original Procurement Plan: 2020-08-12 2020-08-14 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P174389 GPN Date: Project Name: Vietnam COVID-19 Emergency Response Project Loan / Credit No: TF / B3197 Executing Agency(ies): National Institute of Hygiene and Epidemiology WORKS Bid Evaluation Activity Reference No. / Procurement Estimated Actual Draft Bidding Loan / Credit Market Procurement Prequalification High SEA/SH Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Contract Description Component Review Type Method Document Amount Amount Document / Signed Contract No. Approach Process (Y/N) Risk Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Completion Type (US$) (US$) Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 3: DCVP / Procure Office Pending Communication, Project Request for Single Stage - One furniture (table, bookshelf, TF / B3197 Post Open - National 3,500.00 0.00 Implementati 2020-08-17 2020-09-01 2020-09-15 management, monitoring Quotations Envelope chair…) on and evaluation TBVP / Procure Office Component 3: Pending equipments and supplies Communication, Project Request for Single Stage - One TF / B3197 Post Open - National 15,100.00 0.00 Implementati 2020-08-17 2020-09-05 2020-09-19 (computer, printer, scanner, management, monitoring Quotations Envelope on photocopier…) and evaluation TB3 / Supply and completely install the air- conditioning system for Component 1: Strengthening Pending Request for Single Stage - One standardized experimental TF / B3197 surveillance and testing Post Open - National 165,000.00 0.00 Implementati 2020-09-04 2020-09-25 2021-01-23 Quotations Envelope animal laboratory area for capacities on testing of emerging and pandemic agents TB2 / Supply and completely install the specialized refrigerator Component 1: Strengthening Pending Single Stage - One system for microbiological TF / B3197 surveillance and testing Post Request for Bids Open - National 345,300.00 0.00 Implementati 2020-08-27 2020-09-01 2020-10-01 2020-10-15 2020-10-19 2021-01-17 Envelope samples storage and the capacities on temperature monitoring and control system TB1 / Supply and Component 1: Strengthening Pending completely install the system Single Stage - One TF / B3197 surveillance and testing Post Request for Bids Open - National 1,389,792.00 0.00 Implementati 2020-08-27 2020-08-30 2020-09-29 2020-10-06 2020-10-14 2021-01-30 of Transmission electron Envelope capacities on microscope (TEM) TB4 / Supply and completely install 1,000 KVA Component 1: Strengthening Pending standby generators for the Single Stage - One TF / B3197 surveillance and testing Post Request for Bids Open - National 289,000.00 0.00 Implementati 2020-08-30 2020-09-02 2020-10-02 2020-10-09 2020-10-15 2021-01-13 entire operation of the Envelope capacities on Biosafety laboratories systems level 2 and 3 Page 1 TB5 / Upgrade and install completely HVAC control Component 1: Strengthening Pending and monitoring system for TF / B3197 surveillance and testing Post Direct Selection Direct 84,500.00 0.00 Implementati 2020-08-31 2020-09-14 2020-09-23 2021-01-21 Level 3 Biosafety laboratory capacities on system TB6 / Supply and Component 1: Strengthening Pending completely install equipment Single Stage - One TF / B3197 surveillance and testing Post Request for Bids Open - National 781,210.00 0.00 Implementati 2020-08-31 2020-09-03 2020-10-03 2020-10-17 2020-10-22 2021-01-20 of the Biosafety laboratories Envelope capacities on systems level 2 and 3 TB7 / Supply and Component 1: Strengthening Pending Single Stage - One completely install SARS-CoV- TF / B3197 surveillance and testing Post Request for Bids Open - National 1,278,160.00 0.00 Implementati 2020-09-06 2020-09-11 2020-10-11 2020-10-25 2020-10-29 2021-01-27 Envelope 2 virus research equipment capacities on TB8 / Supply and completely install equipment Component 1: Strengthening Pending for COVID-19 vaccine Single Stage - One TF / B3197 surveillance and testing Post Request for Bids Open - National 874,000.00 0.00 Implementati 2020-09-06 2020-09-09 2020-10-09 2020-10-23 2020-10-29 2021-01-27 research and production, and Envelope capacities on for COVID-19 test kit production NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 3: Consultant TV19 / Recruit Independent Communication, Project Pending TF / B3197 Post Qualification Open - National 21,621.00 0.00 2020-08-23 2020-09-06 2020-09-25 2020-10-25 2020-11-04 2021-02-02 financial audit management, monitoring Implementation Selection and evaluation INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 3: Individual TV1 / Recruit a project Communication, Project Under TF / B3197 Post Consultant Direct 14,400.00 0.00 2020-08-12 2020-08-14 2020-08-24 2020-08-29 2020-09-01 2021-01-29 coordinator management, monitoring Implementation Selection and evaluation Component 3: Individual TV2 / Recruit a project Communication, Project Under TF / B3197 Post Consultant Direct 14,400.00 0.00 2020-08-12 2020-08-14 2020-08-24 2020-08-29 2020-09-01 2021-01-29 Planning consultant management, monitoring Implementation Selection and evaluation Component 3: Individual TV3 / Recruit a language Communication, Project Pending TF / B3197 Post Consultant Direct 14,400.00 0.00 2020-08-11 2020-08-18 2020-08-25 2020-08-28 2021-01-25 and interpretation consultant management, monitoring Implementation Selection and evaluation Page 2 Component 3: Individual TV4 / Recruit a Communication, Project Pending TF / B3197 Post Consultant Direct 14,400.00 0.00 2020-08-11 2020-08-18 2020-08-25 2020-08-28 2021-01-25 procurement consultant management, monitoring Implementation Selection and evaluation Component 3: Individual TV5 / Recruit Senior Communication, Project Pending TF / B3197 Post Consultant Direct 8,100.00 0.00 2020-08-11 2020-08-18 2020-08-25 2020-08-28 2021-01-25 procurement consultant management, monitoring Implementation Selection and evaluation Component 3: Individual TV6 / Recruit equipment Communication, Project Pending TF / B3197 Post Consultant Direct 14,400.00 0.00 2020-08-12 2020-08-19 2020-08-26 2020-08-29 2021-01-26 management consultant management, monitoring Implementation Selection and evaluation Component 3: TV7 / Recruit biosafety and Individual Communication, Project Pending equipment calibration TF / B3197 Post Consultant Direct 14,400.00 0.00 2020-08-12 2020-08-19 2020-08-26 2020-08-29 2021-01-26 management, monitoring Implementation consultant Selection and evaluation Component 3: Individual TV8 / Recruit finance Communication, Project Pending TF / B3197 Post Consultant Direct 14,400.00 0.00 2020-08-12 2020-08-19 2020-08-26 2020-08-29 2021-01-26 management consultant management, monitoring Implementation Selection and evaluation Component 3: Individual TV9 / Recruit disbursement Communication, Project Pending TF / B3197 Post Consultant Direct 8,775.00 0.00 2020-08-12 2020-08-19 2020-08-26 2020-08-29 2021-01-26 and accountant consultant management, monitoring Implementation Selection and evaluation Component 3: TV10 / Recruit project Individual Communication, Project Pending monitoring & evaluation TF / B3197 Post Consultant Direct 10,560.00 0.00 2020-08-23 2020-09-04 2020-09-11 2020-09-18 2021-01-16 management, monitoring Implementation consultant Selection and evaluation Component 3: TV11 / Recruit Individual Communication, Project Pending communication and TF / B3197 Post Consultant Direct 10,560.00 0.00 2020-08-23 2020-09-04 2020-09-09 2020-09-16 2021-01-14 management, monitoring Implementation safeguards consultant Selection and evaluation Component 3: TV14.1 / Recruit consultant Individual Communication, Project Pending for training on serological TF / B3197 Post Consultant Direct 12,150.00 0.00 2020-08-16 2020-08-23 2020-08-30 2020-09-02 2020-12-01 management, monitoring Implementation testing and other technique Selection and evaluation Component 3: Individual TV15.1 / Recruit consultant Communication, Project Pending TF / B3197 Post Consultant Direct 12,150.00 0.00 2020-08-16 2020-08-23 2020-08-30 2020-09-02 2020-12-31 on epidemiology management, monitoring Implementation Selection and evaluation Component 3: TV16.1 / Recruit consultant Individual Communication, Project Pending for quality assurance of TF / B3197 Post Consultant Direct 9,600.00 0.00 2020-08-16 2020-08-23 2020-08-30 2020-09-01 2020-12-30 management, monitoring Implementation sample collection Selection and evaluation Component 3: Individual TV17.1 / Recruit consultant Communication, Project Pending TF / B3197 Post Consultant Direct 5,760.00 0.00 2020-08-23 2020-09-04 2020-09-09 2020-09-16 2021-01-14 on data management report management, monitoring Implementation Selection and evaluation TV12 / Consultant to develop standard procedure Component 1: Strengthening Individual Pending for operation and TF / B3197 surveillance and testing Post Consultant Direct 4,608.00 0.00 2020-10-01 2020-10-06 2020-10-09 2020-10-12 2021-01-10 Implementation maintenance of new capacities Selection equipment Page 3 TV13 / Consultant to evaluate capacity of testing and biosafety assurance of laboratories at provincial Component 1: Strengthening Individual Pending hospitals and provincial TF / B3197 surveillance and testing Post Consultant Direct 5,760.00 0.00 2020-08-12 2020-08-19 2020-08-26 2020-08-29 2020-10-28 Implementation centers for disease control capacities Selection engaged in surveillance and response to the COVID-19 pandemic TV18 / Consultant to Component 1: Strengthening Individual Pending review Viet Nam's COVID-19 TF / B3197 surveillance and testing Post Consultant Direct 7,680.00 0.00 2020-09-01 2020-09-08 2020-09-15 2020-09-19 2020-11-18 Implementation pandemic risk communication capacities Selection TV14.2 / Recruit consultant Component 3: Individual on sample collection, Communication, Project Pending TF / B3197 Post Consultant Direct 12,150.00 0.00 2020-08-16 2020-08-28 2020-09-04 2020-09-07 2020-12-06 biosafety and quality management, monitoring Implementation Selection management and evaluation Component 3: Individual TV15.2 / Recruit consultant Communication, Project Pending TF / B3197 Post Consultant Direct 12,150.00 0.00 2020-08-16 2020-08-23 2020-08-30 2020-09-14 2020-12-13 on medical microbiology management, monitoring Implementation Selection and evaluation Component 3: TV16.2 / Recruit a Individual Communication, Project Pending consultant for quality TF / B3197 Post Consultant Direct 9,600.00 0.00 2020-08-16 2020-08-23 2020-08-30 2020-09-04 2021-01-02 management, monitoring Implementation assurance of lab testing Selection and evaluation Component 3: TV17.2 / Recruit a Individual Communication, Project Pending consultant on data analysis TF / B3197 Post Consultant Direct 5,760.00 0.00 2020-08-23 2020-09-04 2020-09-09 2020-09-16 2021-01-14 management, monitoring Implementation and report Selection and evaluation Page 4