Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan [Original: April 2016]: Revision of Updated Procurement Plan, December 2019] 2. Date of General Procurement Notice: November 1 2016 3. Period covered by this procurement plan: The procurement period of project covered from year 2016 to 2021 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Threshold Comments US$ 1. ICB and LIB (Goods) Above US$ 4 million All 2. NCB (Goods) Above US$ 4 million All 3. ICB (Works) Above US$ 15 million All July 9, 2010 4. NCB (Works) Above US$ 15 million All 5. (Non-Consultant Services) Above US$ 4 million 0 All 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Ningbo Sustainable Urbanization Project 01/20/2016 issued by Ningbo PMO 4. Any Other Special Procurement Arrangements: None 5. Summary of the Procurement Packages planned during the first 18 months after project effectiveness (including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Ref. No. Description Estimated Packages Domestic Review Comments Preference Cost by Bank (yes/no) US$ million (Prior / Post) XGP3 Purchase of 30 2.344 1 No Prior Signed new-energy buses (Goods) July 9, 2010 XCP3 Huancheng 34.7 1 No Prior Signed Road West construction (from Danshan Road to Binhai Avenue): main road with total length 2952m, L652m/2300m, W36m/25m, and related municipal pipeline facilities. (Works) XGP1 Traffic 8.65 1 No Prior Signed management: intelligence traffic (Goods) XGP4-1 Purchase of 65 7.30 1 No Prior Signed new-energy buses (Goods) NCP1 Taoyuan Road 5.625 1 No Post Signed Middle reconstruction: urban primary road, lenght 1.3km, width 60m/55m, cross section optimization, four motor lanes broden to six motor lanes, drainage inlet reconstruction, lighting facilites, greening and landscape (Works) XCP5 Overall renewal 10.56 1 No Post Signed of Tian'an Road (Xiangshan Harbour Road to July 9, 2010 Binhai Avenue section), public space improvement along Dannan Road, commercial area renovation (Jianshe Road to Xiangshan Harbour Road). (Works) XCP7 Tashan Terminal 1.95 1 No Post Signed (Works) NCP3 Renmin Road 5.11 1 No Post Signed reconstruction (from Taoyuan Road Middle to Xinghai Road Middle) (Works) NCP5 Ninghai Central 1.31 1 No Post Signed Urban Area bus terminal construction: Qiaotouhu Terminal (Works) FCP1 Xikou old town 7.26 1 No Post Signed public space improvement: Wuling Road reconstruction and improvement (Works) NCP4 Qianhuang 0.75 1 No Post Canceled Terminal construction (Works) July 9, 2010 XGP1-1 Traffic signal 0.75 1 No Post Signed controller (Goods) XCP3-1 Huancheng 19.00 1 No Prior Signed Road West construction (from Danshan Road to Binhai Avenue): main road with total length 2952m, L652m/2300m, W36m/25m, and related municipal pipeline facilities. (Works) FCP2 Wulinfang Area 2.907 1 No Post reconstruction and improvement (Works) XCP2 Jinnan Street 2.946 1 No Post reconstruction (Works) NCP10 Upper reach of 1.75 1 No Post Huailu River (Works) NCP11 Longyan Creek 4.15 1 No Post (Works) NCP9 Zhu Creek 3.29 1 No Post (300m from Qian'ao village to the downstream of Xinghailu Bridge) (Works) XCP4 Baohai Road 7.1 1 No Post NEW July 9, 2010 (Works) XCP5-1 Tian’an Road 3.0 1 No Post NEW Urban Regeneration (Works) XCP10 Juying Road 15.25 1 No Prior NEW (Tashan road to Binhai Avenue) (Works) XCP11 Juying Road 13.33 1 No Post NEW (Binhai Avenue to Damuwan) (Works) XCP12 Binhai Avenue 5.97 1 No Post NEW (Tian'an Road to Juying Road) (Works) XCP13 Danyang Park 1.61 1 No Post NEW (Works) XCP14 Xinyi Road, 13.6 3 No Post NEW Fengrao Road, Xingyang Road (Works) NCP8 Xunan Creek 2.99 1 No Post NEW (Works) NCP9-1 Zhu Creek 2.32 1 No Post NEW (890m upstream of the Taoyuan North Road) (Works) NCP10-1 Huailu River 5.43 1 No Post NEW upstream section (Science and Technology Park) (Works) NCP10-2 Huailu River 7.0 1 No Post NEW upstream section (Qiaotouhu Street) July 9, 2010 (Works) NCP12 Meilin Creek 11.61 1 No Post NEW (Works) NCP13 Pu Lake (water 2.86 1 No Post NEW diversion project) (Works) NCP13-1 Pu Lake (lake 25.71 1 No Prior NEW restoration) (Works) NCP14 Xujia River 4.44 1 No Post NEW (Works) NCP15 Lingjiao Aoli 3.82 1 No Post NEW River (Works) NCP16 Qiaoxiapan 1.72 1 No Post NEW River (Works) NCP17 Dongshan flood 3.0 1 No Post NEW discharge channel (Works) NCP18 Dianqianwang 1.79 1 No Post NEW Creek (Works) FCP5 Reconstruction 14.28 1 No Post NEW of blocks around Chiang's ancestral hall (Works) XGP2 Intelligent bus 2.86 1 No Post NEW system (Goods) XGP5 Tian'an Road 0.71 1 No Post NEW guardrail July 9, 2010 (Goods) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) Above US$ 2,000,000 2. Single Source (Firms) All 3. Individual Above US$ 400,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: None 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Description of July 9, 2010 Ref. No. Assignment Estimated Packages Review Comments Cost by Bank US$ million (Prior / Post) NBTA1 Project 1.2 1 Prior QCBS Management, Institutional Signed Strengthening and Training NBTA3-1 Study on 0.25 1 Post CQS Fenghua intelligence Signed transportation and pilot implementation NBTA2 Public facilities 0.8 1 Post QCBS and service fund support Canceled NBTA5-1 Strategic study 0.295 1 Post CQS on Xiangshan public Signed transportation development NBTA6 Flood risk 0.075 1 Post SSS assessment in Ninghai county Signed NBTA4 Study on Blue 0.295 1 Post CQS Asset Management NEW and O&M Investment in Ninghai NBTA7 Study on 0.94 1 Post QCBS Ningbo 2035 in July 9, 2010 Sustainable NEW Urbanization NBTA8 Study on 0.28 1 Post CQS Ningbo Urban Resilience NEW NBTA9 Study and 0.66 1 Post QCBS Overview of Contract NEW Management introduced with WB Project Management Method July 9, 2010 PROCUREMENT China : Ningbo Sustainable Urbanization Project PLAN General Information Country: China Bank’s Approval Date of the Original Procurement Plan: 2016-09-27 2020-10-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P149485 GPN Date: 2016-11-01 Project Name: Ningbo Sustainable Urbanization Project Loan / Credit No: IBRD / 86220 Executing Agency(ies): Ningbo sustainable urbanization PMO WORKS Bid Evaluation Activity Reference No. / Procurement Estimated Actual Draft Bidding Loan / Credit Market Procurement Prequalification High SEA/SH Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Contract Description Component Review Type Method Document Amount Amount Document / Signed Contract No. Approach Process (Y/N) Risk Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Completion Type (US$) (US$) Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned NCP1 / Taoyuan Road Middle reconstruction: urban primary road, lenght 1.3km, width 60m/55m, cross section optimization, four motor Component 2: Urban Single Stage - One IBRD / 86220 Post Request for Bids Open - National 5,625,000.00 3,614,570.73 Signed 2017-01-16 2017-01-18 2017-01-23 2017-03-06 2017-02-23 2017-04-05 2017-04-07 2017-05-10 2017-04-11 2017-11-06 lanes broden to six motor Transport Envelope lanes, drainage inlet reconstruction, lighting facilites, greening and landscape XCP5 / Overall renewal of Tian'an Road (Xiangshan Harbour Road to Binhai Avenue section), public space Component 2: Urban Single Stage - One IBRD / 86220 Post Request for Bids Open - National 10,560,000.00 7,407,935.17 Signed 2017-08-07 2017-08-04 2017-08-12 2017-08-13 2017-09-23 2017-09-15 2017-10-23 2017-10-21 2017-11-27 2017-11-08 2018-05-26 improvement along Dannan Transport Envelope Road, commercial area renovation (Jianshe Road to Xiangshan Harbour Road). XCP3 / Huancheng Road West construction (from Danshan Road to Binhai Avenue): main road with Component 2: Urban Single Stage - One 23,466,602.9 IBRD / 86220 Prior Request for Bids Open - National 34,700,000.00 Signed 2017-08-14 2017-09-14 2017-09-01 2017-09-22 2017-10-13 2017-11-01 2017-11-12 2017-11-30 2017-12-17 2018-03-01 2018-06-15 total length 2952m, Transport Envelope 2 L652m/2300m, W36m/25m, and related municipal pipeline facilities. XCP7 / Tashan terminal Component 2: Urban Single Stage - One IBRD / 86220 Post Request for Bids Open - National 1,950,000.00 1,669,152.11 Signed 2017-11-01 2018-02-09 2017-11-06 2017-12-18 2018-03-29 2018-01-17 2018-04-03 2018-02-21 2018-07-11 2019-03-21 construction Transport Envelope NCP3 / Renmin Road reconstruction (from Taoyuan Component 2: Urban Single Stage - One IBRD / 86220 Post Request for Bids Open - National 5,110,000.00 4,379,951.50 Signed 2017-10-09 2017-10-19 2017-10-14 2017-10-29 2017-11-25 2017-11-24 2017-12-25 2017-12-25 2018-01-29 2017-12-29 2019-01-31 Road Middle to Xinghai Transport Envelope Road Middle) NCP5 / Ninghai Central Urban Area bus terminal Component 2: Urban Single Stage - One IBRD / 86220 Post Request for Bids Open - National 1,310,000.00 798,107.68 Signed 2017-11-01 2017-12-01 2017-11-06 2017-12-18 2018-01-02 2018-01-17 2018-01-19 2018-02-21 2018-02-09 2019-02-28 construction: Qiaotouhu Transport Envelope Terminal FCP1 / Xikou old town public space improvement: Component 1: Urban Single Stage - One IBRD / 86220 Post Request for Bids Open - National 7,260,000.00 6,167,937.32 Signed 2017-09-30 2017-09-30 2017-10-09 2017-11-20 2017-11-14 2017-12-20 2017-12-09 2018-01-24 2018-01-09 2019-01-31 Wuling Road reconstruction Regeneration Envelope and improvement NCP4 / Qianhuang Component 2: Urban Single Stage - One IBRD / 86220 Post Request for Bids Open - National 750,000.00 0.00 Canceled 2018-08-06 2018-08-11 2018-09-22 2018-10-22 2018-11-26 2019-12-03 Terminal construction Transport Envelope Page 1 XCP3-1 / Huancheng Road West construction (from Danshan Road to Binhai Avenue): main road with Component 2: Urban Single Stage - One 18,835,982.9 IBRD / 86220 Prior Request for Bids Limited 19,000,000.00 Signed 2019-01-31 2019-02-01 2019-02-11 2019-02-19 2019-03-04 2019-03-11 2019-04-03 2019-03-25 2019-05-08 2019-04-18 2020-10-29 total length 2952m, Transport Envelope 7 L652m/2300m, W36m/25m, and related municipal pipeline facilities. FCP2 / Wulinfang Area Component 1: Urban Single Stage - One reconstruction and IBRD / 86220 Post Request for Bids Open - National 2,907,000.00 1,873,622.79 Signed 2019-08-30 2019-08-29 2019-09-08 2019-10-20 2019-10-10 2019-11-19 2019-11-19 2019-12-24 2020-01-13 2020-12-26 Regeneration Envelope improvement XCP2 / Jinnan Street Component 1: Urban Single Stage - One IBRD / 86220 Post Request for Bids Open - National 2,946,000.00 2,780,670.98 Signed 2019-08-30 2019-09-10 2019-09-04 2019-10-16 2019-10-30 2019-11-15 2019-11-19 2019-12-20 2019-12-26 2020-06-17 reconstruction Regeneration Envelope NCP10 / Upper reach of Huailu River: Yonglin Line to Shenhai Expressway Component 3: Flood Risk Single Stage - One Section, 380 meters long, IBRD / 86220 Post Request for Bids Open - National 1,750,000.00 1,024,935.01 Signed 2019-09-30 2019-09-29 2019-10-08 2019-11-19 2019-11-01 2019-12-19 2019-11-29 2020-01-23 2019-12-19 2020-07-21 Management Envelope with box culvert 183 meters, open channel 199.6 meters, culvert laying, etc. NCP11 / Longyan Creek: The total length 2180m, of which the main river channel 1259m, the new diversion section 145m, and Component 3: Flood Risk Single Stage - One the tributary 776m; IBRD / 86220 Post Request for Bids Open - National 4,150,000.00 2,006,432.60 Signed 2019-09-30 2019-09-29 2019-10-08 2019-11-19 2019-11-01 2019-12-19 2019-12-05 2020-01-23 2020-01-02 2021-01-22 Management Envelope construction of the embankment 3450m, of which main channel 1984m, new diversion section 290m, the tributary 1176m. NCP9 / Zhuxi construction: dyke building, barrage construction, manhole works, Component 3: Flood Risk Single Stage - One culvert and diversion IBRD / 86220 Post Request for Bids Open - National 3,100,000.00 2,250,417.09 Signed 2020-01-02 2019-12-30 2020-01-07 2020-02-18 2020-04-15 2020-03-19 2020-05-07 2020-04-23 2020-06-03 2021-04-23 Management Envelope channel works, stairs design, landscape and greening works XCP4 / Baohai Road (Xinyi Road to Laixun Road Pending section): secondary trunk Component 2: Urban Single Stage - One IBRD / 86220 Post Request for Bids Open - National 7,100,000.00 0.00 Implementat 2020-06-25 2020-06-30 2020-08-11 2020-09-10 2020-10-15 2021-10-15 road, L702m, W24m, and Transport Envelope ion related municipal pipeline facilities Pending XCP5-1 / Tian’an Road Component 1: Urban Single Stage - One IBRD / 86220 Post Request for Bids Open - National 3,000,000.00 0.00 Implementat 2020-06-10 2020-06-15 2020-07-27 2020-08-26 2020-09-30 2021-09-30 Urban Regeneration Regeneration Envelope ion XCP10 / Juying Road Pending Component 1: Urban Single Stage - One (Tashan road to Binhai IBRD / 86220 Prior Request for Bids Open - National 15,250,000.00 0.00 Implementat 2020-08-10 2020-08-28 2020-10-09 2020-11-08 2020-12-13 2021-11-13 Regeneration Envelope Avenue) ion XCP11 / Juying Road Pending Component 1: Urban Single Stage - One (Binhai Avenue to IBRD / 86220 Post Request for Bids Open - National 13,330,000.00 0.00 Implementat 2020-06-10 2020-06-15 2020-07-27 2020-08-26 2020-09-30 2021-09-30 Regeneration Envelope Damuwan) ion XCP12 / Binhai Avenue Pending Component 1: Urban Single Stage - One (Tian'an Road to Juying IBRD / 86220 Post Request for Bids Open - National 5,970,000.00 0.00 Implementat 2020-06-10 2020-06-15 2020-07-27 2020-08-26 2020-09-30 2021-09-30 Regeneration Envelope Road) ion Pending Component 1: Urban Single Stage - One XCP13 / Danyang Park IBRD / 86220 Post Request for Bids Open - National 1,610,000.00 0.00 Implementat 2020-06-25 2020-06-30 2020-08-11 2020-09-10 2020-10-15 2021-10-15 Regeneration Envelope ion Page 2 Under Component 3: Flood Risk Single Stage - One NCP8 / Xunan Creek IBRD / 86220 Post Request for Bids Open - National 2,990,000.00 0.00 Implementat 2020-05-15 2020-09-17 2020-05-20 2020-07-01 2020-07-31 2020-09-04 2021-09-04 Management Envelope ion NCP9-1 / Zhu Creek (890m Pending Component 3: Flood Risk Single Stage - One upstream of the Taoyuan IBRD / 86220 Post Request for Bids Open - National 2,320,000.00 0.00 Implementat 2020-06-15 2020-06-20 2020-08-01 2020-08-31 2020-10-05 2021-10-05 Management Envelope North Road) ion NCP10-1 / Huailu River Pending Component 3: Flood Risk Single Stage - One upstream section (Science IBRD / 86220 Post Request for Bids Open - National 5,430,000.00 0.00 Implementat 2020-08-10 2020-08-15 2020-09-26 2020-10-26 2020-11-30 2021-11-30 Management Envelope and Technology Park) ion NCP10-2 / Huailu River Pending Component 3: Flood Risk Single Stage - One upstream section (Qiaotouhu IBRD / 86220 Post Request for Bids Open - National 7,000,000.00 0.00 Implementat 2020-07-15 2020-07-20 2020-08-31 2020-09-30 2020-11-04 2021-11-04 Management Envelope Street) ion Pending Component 3: Flood Risk Single Stage - One NCP12 / Meilin Creek IBRD / 86220 Post Request for Bids Open - National 11,610,000.00 0.00 Implementat 2020-07-20 2020-07-25 2020-09-05 2020-10-05 2020-11-09 2022-05-08 Management Envelope ion Pending NCP13 / Pu Lake (water Component 3: Flood Risk Single Stage - One IBRD / 86220 Post Request for Bids Open - National 2,860,000.00 0.00 Implementat 2020-07-20 2020-07-25 2020-09-05 2020-10-05 2020-11-09 2021-11-09 diversion project) Management Envelope ion Pending NCP13-1 / Pu Lake (lake Component 3: Flood Risk Single Stage - One IBRD / 86220 Prior Request for Bids Open - National 25,710,000.00 0.00 Implementat 2020-09-10 2020-09-25 2020-11-06 2020-12-06 2021-01-10 2022-07-09 restoration) Management Envelope ion Pending Component 3: Flood Risk Single Stage - One NCP14 / Xujia River IBRD / 86220 Post Request for Bids Open - National 4,440,000.00 0.00 Implementat 2020-09-01 2020-09-06 2020-10-18 2020-11-17 2020-12-22 2021-12-22 Management Envelope ion Under NCP15 / Lingjiao Aoli Component 3: Flood Risk Single Stage - One IBRD / 86220 Post Request for Bids Open - National 3,820,000.00 0.00 Implementat 2020-09-01 2020-09-06 2020-10-18 2020-11-17 2020-12-22 2021-12-22 River Management Envelope ion Pending Component 3: Flood Risk Single Stage - One NCP16 / Qiaoxiapan River IBRD / 86220 Post Request for Bids Open - National 1,720,000.00 0.00 Implementat 2020-09-01 2020-09-06 2020-10-18 2020-11-17 2020-12-22 2021-12-22 Management Envelope ion Pending NCP17 / Dongshan flood Component 3: Flood Risk Single Stage - One IBRD / 86220 Post Request for Bids Open - National 3,000,000.00 0.00 Implementat 2020-09-15 2020-09-20 2020-11-01 2020-12-01 2021-01-05 2022-01-05 discharge channel Management Envelope ion Under NCP18 / Dianqianwang Component 3: Flood Risk Single Stage - One IBRD / 86220 Post Request for Bids Open - National 1,790,000.00 0.00 Implementat 2020-08-10 2020-09-17 2020-08-15 2020-09-26 2020-10-26 2020-11-30 2021-11-30 Creek Management Envelope ion FCP5 / Reconstruction of Pending Component 1: Urban Single Stage - One blocks around Chiang's IBRD / 86220 Post Request for Bids Open - National 14,280,000.00 0.00 Implementat 2020-09-30 2020-10-09 2020-11-20 2020-12-20 2021-01-24 2022-07-23 Regeneration Envelope ancestral hall ion Pending XCP14 / Fengrao Road, Component 2: Urban Single Stage - One IBRD / 86220 Post Request for Bids Open - National 7,350,000.00 0.00 Implementat 2020-11-30 2020-12-05 2021-01-16 2021-02-15 2021-03-22 2022-01-16 Xingyang Road construction Transport Envelope ion Pending XCP14-1 / XinyI Road Component 2: Urban Single Stage - One IBRD / 86220 Post Request for Bids Open - National 3,980,000.00 0.00 Implementat 2021-01-15 2021-01-20 2021-03-03 2021-04-02 2021-05-07 2022-03-03 construction Transport Envelope ion GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Page 3 Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual XGP3 / purchase of 30 new- Component 2: Urban Single Stage - One IBRD / 86220 Prior Request for Bids Open - National 2,344,000.00 2,142,527.84 Signed 2016-10-27 2016-11-09 2016-11-01 2016-12-13 2017-03-09 2017-01-12 2017-06-09 2017-02-16 2017-07-07 2017-06-16 energy buses Transport Envelope XGP1 / Traffic Component 2: Urban Single Stage - One management: intelligence IBRD / 86220 Prior Request for Bids Open - National 8,650,000.00 6,650,266.36 Signed 2017-11-01 2018-03-16 2017-11-06 2018-07-12 2017-12-18 2018-09-05 2018-01-17 2018-11-15 2018-02-21 2018-12-19 2018-12-21 Transport Envelope traffic XGP4 / purchase of 65 new- Component 2: Urban Single Stage - One IBRD / 86220 Prior Request for Bids Open - National 7,300,000.00 0.00 Canceled 2018-08-20 2018-09-12 2018-09-17 2018-10-29 2018-10-29 2018-11-28 2019-01-09 2019-01-02 2019-12-31 engery buses Transport Envelope XGP1-1 / Traffic signal controller, platform software upgrade, mobile handheld terminal, vehicle GPS positioning equipment, Component 2: Urban IBRD / 86220 Post Direct Selection Direct 750,000.00 592,738.64 Signed 2018-11-12 2018-11-02 2018-12-05 2019-01-12 2019-01-31 2019-04-12 integrated video command Transport system, disaster recovery backup, signal timing optimization, traffic detection system XGP4-1 / Purchase of 65 Component 2: Urban Single Stage - One IBRD / 86220 Prior Request for Bids Open - National 7,300,000.00 7,000,790.00 Signed 2019-02-12 2019-02-19 2019-03-12 2019-04-23 2019-03-28 2019-05-23 2019-04-11 2019-06-27 2019-05-09 2020-01-13 new-engery buses Transport Envelope Pending XGP2 / Intelligent bus Component 2: Urban Single Stage - One IBRD / 86220 Post Request for Bids Open - National 2,860,000.00 0.00 Implementati 2020-06-15 2020-06-20 2020-08-01 2020-08-31 2020-10-05 2022-04-03 system Transport Envelope on Pending XGP5 / Tian'an Road Component 2: Urban Single Stage - One IBRD / 86220 Post Request for Bids Open - National 710,000.00 0.00 Implementati 2020-06-01 2020-06-06 2020-07-18 2020-08-17 2020-09-21 2021-02-18 guardrail Transport Envelope on NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NBTA1 / Project Component 4: Technical Quality And Cost- Open - Management, Institutional IBRD / 86220 Assistance and Capacity Prior 1,200,000.00 1,073,666.18 Signed 2016-10-10 2016-10-19 2016-10-31 2016-11-03 2016-12-14 2017-04-26 2017-01-11 2017-06-12 2017-02-10 2017-07-24 2017-03-17 2017-09-04 2017-04-21 2017-09-05 2020-12-31 Based Selection International Strengthening and Training Building NBTA3 / Study on Component 4: Technical Fenghua intelligence Quality And Cost- Open - IBRD / 86220 Assistance and Capacity Post 300,000.00 0.00 Canceled 2018-05-07 2018-05-28 2018-07-11 2018-08-08 2018-09-07 2018-10-12 2018-11-16 2019-11-16 transportation and pilot Based Selection International Building implementation NBTA3-1 / Study on Component 4: Technical Consultant Fenghua intelligence IBRD / 86220 Assistance and Capacity Post Qualification Open - National 250,000.00 251,921.08 Signed 2018-06-04 2018-07-11 2018-06-25 2018-08-08 2019-01-02 2018-09-07 2019-01-25 2018-10-12 2019-03-06 2019-04-10 transportation and pilot Building Selection implementation Component 4: Technical NBTA2 / Public facilities Quality And Cost- Open - IBRD / 86220 Assistance and Capacity Post 800,000.00 0.00 Canceled 2018-10-08 2018-10-29 2018-12-12 2019-01-09 2019-02-08 2019-03-15 2019-04-19 2022-12-29 and service fund support Based Selection International Building Page 4 NBTA5 / Strategic study on Component 4: Technical Consultant Xiangshan public IBRD / 86220 Assistance and Capacity Post Qualification Open - National 200,000.00 0.00 Canceled 2018-09-10 2018-10-15 2018-11-28 2018-12-28 2019-02-01 2020-02-01 transportation development Building Selection NBTA5-1 / Strategic study Component 4: Technical Consultant on Xiangshan public IBRD / 86220 Assistance and Capacity Post Qualification Open - National 295,000.00 292,593.32 Signed 2018-11-19 2018-11-12 2018-11-26 2019-01-09 2018-12-18 2019-02-08 2019-01-24 2019-03-15 2019-02-22 2020-03-14 transportation development Building Selection NBTA4 / Study on Blue Component 4: Technical Consultant Pending Asset Management and IBRD / 86220 Assistance and Capacity Post Qualification Open 295,000.00 0.00 2020-06-10 2020-07-01 2020-08-14 2020-09-13 2020-10-18 2021-08-14 Implementation O&M Investment in Ninghai Building Selection NBTA7 / Study on Ningbo Component 4: Technical Quality And Cost- Open - 2035 in Sustainable IBRD / 86220 Assistance and Capacity Post 940,000.00 0.00 Canceled 2020-09-10 2020-08-05 2020-10-09 2020-09-10 2020-11-22 2020-12-20 2021-01-19 2021-02-23 2021-03-30 2022-03-30 Based Selection International Urbanization Building Component 4: Technical Consultant NBTA8 / Study on Ningbo Under IBRD / 86220 Assistance and Capacity Post Qualification Open 280,000.00 0.00 2020-09-10 2020-09-02 2020-09-30 2020-11-13 2020-12-13 2021-01-17 2022-01-17 Urban Resilience Implementation Building Selection NBTA9 / Study and Overview of Contract Component 4: Technical Quality And Cost- Open - Under Management introduced with IBRD / 86220 Assistance and Capacity Post 660,000.00 0.00 2020-06-30 2020-05-22 2020-07-29 2020-06-23 2020-09-11 2020-09-17 2020-10-09 2020-11-08 2020-12-13 2021-01-17 2022-01-17 Based Selection International Implementation WB Project Management Building Method NBTA7-1 / Study on Component 4: Technical Quality Based Open - Pending Ningbo 2035 in Sustainable IBRD / 86220 Assistance and Capacity Post 940,000.00 0.00 2020-10-29 2020-11-19 2021-01-02 2021-01-30 2021-03-01 2021-03-31 2021-05-05 2022-05-05 Selection International Implementation Urbanization Building INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NBTA6 / Flood Risk Component 4: Technical Assessment in Ninghai IBRD / 86220 Assistance and Capacity Post Direct Selection Direct 75,000.00 75,000.00 Signed 2019-01-04 2018-12-17 2019-01-14 2019-03-20 2018-12-20 2019-09-16 County Building NBTA10 / Agency service Component 4: Technical of selection and employment IBRD / 86220 Assistance and Capacity Post Direct Selection Direct 15,000.00 14,636.90 Signed 2020-09-01 2020-09-20 2020-09-11 2020-09-06 2020-11-15 2020-09-10 2021-11-15 of consultants Building NBTA11 / Investigation on Component 4: Technical spatial satisfaction, Pending IBRD / 86220 Assistance and Capacity Post Direct Selection Direct 60,000.00 0.00 2020-09-06 2020-09-16 2020-11-20 2022-11-20 pedestrian standing time and Implementation Building non motor vehicle flow Page 5