PROCUREMENT PLAN (Textual Part) Project information: Benin Energy Services Improvement Project P161015 Project Implementation agency: Ministry of Energy Date of the Procurement Plan: 10/11/2017 Period covered by this Procurement Plan: 01/01/2018 – 30/06/2019 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in [insert appropriate references to the national procurement legislation], such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. List only the applicable conditions required to ensure consistency with paragraph 5.4 of the Procurement Regulations. If no conditions apply, delete the phrase “and the following conditions”. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Otherwise state “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Otherwise state “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables] Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. [Include this sentence only if the Bank has formally agreed to provide the Borrower with HEIS. Otherwise delete] Other Relevant Procurement Information. Provide any other relevant procurement information such as procedures for CDD components, Procurement in Situations of Urgent Need of Assistance or Capacity Constraints etc. PROCUREMENT Benin : Energy Service Improvement Project PLAN General Information Country: Benin Bank’s Approval Date of the Original Procurement Plan: 2017-12-20 2021-07-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P161015 GPN Date: 2017-12-20 Project Name: Energy Service Improvement Project Loan / Credit No: IDA / 61050 P Executing Agency(ies): ROJECTS IMPLEMENTATION UNIT WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned BJ-PIU-36390-CW-RFB / Travaux de construction de quatorze (14) mielleries dans Component 3: Community- Single Stage - One En attente 2020-06- les communes de Bassila, IDA / 61050 Based Management of Wood A posteriori Appel d'offres Open - National 350,000.00 0.00 2019-08-12 2019-09-01 2019-10-01 2019-10-21 2019-12-04 Envelope d'exécution 01 Djidja, Djougou, N'dali et Fuels Pèrèrè et de réfection d'anciennes mielleries BJ-PIU-36387-CW-RFB / Component 4 : Sector Travaux de réfection des Single Stage - One 2020-03- IDA / 61050 Development and A posteriori Appel d'offres Open - National 200,000.00 0.00 Annulé 2019-05-15 2019-06-04 2019-07-04 2019-07-24 2019-09-06 locaux de l'Unité de Envelope 04 Implementation Support Coordination du PASE BJ-PIU-36465-CW-RFB / Construction de quatorze (14) forages d'eau équipés de Component 3: Community- Single Stage - One En attente 2020-04- pompes à motricité humaine IDA / 61050 Based Management of Wood A posteriori Demande de prix Limited 140,000.00 0.00 2019-08-10 2019-10-06 Envelope d'exécution 03 dans les communes de Fuels Bassila, Djidja, Djoudou, N'dali et Pèrèrè BJ-PIU-36372-CW-RFB / Travaux de construction du Component 3: Community- Single Stage - One En attente 2020-04- siège de la Communauté IDA / 61050 Based Management of Wood A posteriori Demande de prix Limited 150,000.00 0.00 2019-08-17 2019-10-13 Envelope d'exécution 10 Forestière de l'Ouémé Fuels Supérieur (CoFOS) BJ-PIU-200262-CW-RFB / Travaux de mise aux normes des postes HT/MT des sous- Component 2: Distribution Single Stage - One En cours 2021-09- stations de DASSA-ZOUNME, IDA / 61050 Network Strengthening in A posteriori Appel d'offres Open - International 6,000,000.00 0.00 2020-12-01 2021-01-04 2020-12-06 2021-01-14 2021-01-17 2021-02-16 2021-03-23 Envelope d'exécution 19 GLAZOUE et PAOUIGNAN et Targeted Areas des réseaux souterrains de la ville de PORTO-NOVO BJ-PIU-36369-CW-RFB / Travaux de mise aux normes des postes HT/MT des sous- Component 2: Distribution Single Stage - One 2020-09- stations de DASSA-ZOUNME, IDA / 61050 Network Strengthening in A posteriori Appel d'offres Open - National 5,800,000.00 0.00 Annulé 2019-05-15 2020-03-17 2019-06-04 2019-07-19 2020-07-16 2019-08-08 2020-08-31 2019-09-21 Envelope 15 GLAZOUE et PAOUIGNAN et Targeted Areas des réseaux souterrains de la ville de PORTO-NOVO BJ-PIU-36361-CW-RFB / Travaux de normalisation et d'extension des réseaux de Component 2: Distribution distribution de la SBEE dans Single Stage - One 14,000,000.0 2021-05- IDA / 61050 Network Strengthening in A priori Appel d'offres Open - International 0.00 Annulé 2019-05-08 2020-04-06 2019-06-07 2020-06-15 2019-08-21 2020-07-16 2019-09-30 2019-11-13 les quartiers périphériques Envelope 0 06 Targeted Areas des villes de COTONOU, PORTO-NOVO, PARAKOU et NATITINGOU BJ-PIU-200617-CW-RFB / Travaux de normalisation et d'extension des réseaux de Component 2: Distribution distribution de la SBEE dans Single Stage - One 14,000,000.0 En cours 2021-09- IDA / 61050 Network Strengthening in A posteriori Appel d'offres Open - International 0.00 2020-12-10 2021-01-04 2020-12-15 2021-01-14 2021-01-26 2021-02-25 2021-04-01 les quartiers périphériques Envelope 0 d'exécution 28 Targeted Areas des villes de COTONOU, PORTO-NOVO, PARAKOU et NATITINGOU BJ-PIU-204076-CW-RFQ / Component 4 : Sector Travaux de réfection des Single Stage - One En attente 2021-07- IDA / 61050 Development and A posteriori Demande de prix Limited 160,000.00 0.00 2020-12-06 2021-01-31 locaux de l'Unité de Envelope d'exécution 30 Implementation Support Coordination du PASE GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BJ-PIU-35998-GO-RFB / Fourniture de 75 000 Component 2: Distribution Single Stage - One compteurs électroniques à IDA / 61050 Network Strengthening in A priori Appel d'offres Open - International 6,000,000.00 4,279,222.67 Signé 2017-12-01 2018-04-03 2017-12-31 2018-05-04 2018-03-16 2018-07-03 2018-04-15 2018-11-02 2018-06-09 2019-01-21 2018-12-06 Envelope prépaiement de type STS au Targeted Areas profit de la SBEE. BJ-PIU-36002-GO-RFB / Fourniture d'accessoires de branchement pour 75 000 Component 2: Distribution Single Stage - One compteurs électroniques à IDA / 61050 Network Strengthening in A priori Appel d'offres Open - International 9,500,000.00 8,597,094.00 Signé 2017-12-01 2018-03-30 2017-12-31 2018-05-04 2018-03-16 2018-07-03 2018-04-15 2018-11-06 2018-06-09 2019-01-21 2018-12-06 Envelope prépaiement de type STS et Targeted Areas leurs transport et installation au profit de la SBEE. BJ-PIU-36505-GO-RFB / Fourniture de dix mille (10 Component 2: Distribution 000) lampes à diode Single Stage - One IDA / 61050 Network Strengthening in A posteriori Appel d'offres Open - International 1,500,000.00 1,271,916.53 Signé 2017-12-15 2018-01-19 2018-01-14 2019-01-21 2018-03-15 2019-03-20 2018-04-14 2019-03-21 2018-05-28 2019-12-06 2018-11-24 électroluminescente (LED) Envelope Targeted Areas pour l'éclairage public au profit de la SBEE Page 1 BJ-PIU-36050-GO-DIR / Passation de Acquisition de matériels Component 3: Community- marchés auprès roulants pour le IDA / 61050 Based Management of Wood A posteriori Direct 900,000.00 439,402.34 Signé 2018-06-15 2018-10-03 2018-07-15 2018-10-10 2018-11-02 2018-10-10 2019-05-01 des agences de renforcement des capacités Fuels l'ONU des structures du secteur de l'énergie. BJ-PIU-36045-GO-DIR / Acquisition d'un véhicule de Component 2: Distribution Passation de recherche de défauts sur les IDA / 61050 Network Strengthening in A posteriori marché de gré à Direct 250,000.00 0.00 Annulé 2018-05-21 2018-06-13 2018-06-20 2018-08-23 2019-02-19 câbles souterrains au profit de Targeted Areas gré la SBEE BJ-PIU-83862-GO-RFQ / Component 4 : Sector Single Stage - One En attente Fourniture et pose de rideaux IDA / 61050 Development and A posteriori Demande de prix Limited 25,000.00 0.00 2018-12-14 2019-01-13 2019-02-12 Envelope d'exécution pour les bureaux du PASE Implementation Support BJ-PIU-36143-GO-RFB / Component 4 : Sector Acquisition de matériels Single Stage - One IDA / 61050 Development and A posteriori Appel d'offres Open - National 100,000.00 0.00 Annulé 2018-03-15 2018-04-14 2018-05-14 2018-06-13 2018-07-28 2018-09-26 informatiques pour l'Unité de Envelope Implementation Support Coordination du projet BJ-PIU-95476-GO-RFQ / Acquisition de matériels Component 4 : Sector Single Stage - One En cours informatiques et bureautiques IDA / 61050 Development and A posteriori Demande de prix Limited 100,000.00 0.00 2019-02-08 2019-02-20 2019-03-26 2019-05-10 Envelope d'exécution pour l'Unité de Coordination Implementation Support du projet BJ-PIU-36109-GO-RFB / Acquisition de matériels et de Component 3: Community- mobiliers de bureau au profit Single Stage - One IDA / 61050 Based Management of Wood A posteriori Appel d'offres Open - National 300,000.00 0.00 Annulé 2018-03-15 2018-03-30 2018-04-29 2018-05-29 2018-07-13 2018-09-11 de l'ARE, de la DGE, de Envelope Fuels l'ABERME, de la SBEE, de la CoFOS et de l'UCP BJ-PIU-95478-GO-RFQ / Acquisition de mobiliers de Component 4 : Sector Single Stage - One En cours bureau au profit de l'ARE, de IDA / 61050 Development and A posteriori Demande de prix Limited 100,000.00 0.00 2019-02-05 2019-02-20 2019-03-14 2019-04-28 Envelope d'exécution la DGE, de l'ABERME, de la Implementation Support SBEE, de la CoFOS et de l'UCP BJ-PIU-36256-GO-RFB / Fourniture et installation de six mille (6 000) compteurs Component 1: Improvement Single Stage - One intelligents et d'équipements IDA / 61050 of SBEE’s Commercial A priori Appel d'offres Open - International 2,000,000.00 0.00 Annulé 2018-04-01 2020-01-20 2018-05-01 2020-02-03 2018-06-30 2020-03-10 2018-07-15 2020-07-20 2018-09-08 2019-03-07 Envelope pour l'installation d'un centre Performance de comptage au profit de la SBEE BJ-PIU-36327-GO-RFB / Fourniture d'équipements et Component 1: Improvement mise en place d'un centre Single Stage - One En attente IDA / 61050 of SBEE’s Commercial A posteriori Appel d'offres Open - National 200,000.00 0.00 2019-07-15 2019-07-30 2019-08-29 2019-09-03 2019-10-13 2020-04-10 d'appels et de conduite Envelope d'exécution Performance d'enquêtes de satisfaction de la clientèle de la SBEE BJ-PIU-36333-GO-RFB / Fourniture et installation d'un Component 2: Distribution Single Stage - One En cours atelier de réparation de IDA / 61050 Network Strengthening in A posteriori Appel d'offres Open - International 800,000.00 0.00 2019-01-31 2021-02-09 2019-02-15 2021-02-12 2019-03-17 2019-04-06 2019-05-21 2019-11-17 Envelope d'exécution transformateurs au profit de Targeted Areas la SBEE BJ-PIU-36235-GO-RFQ / Acquisition de fournitures de Component 3: Community- Single Stage - One En attente bureau et de produits IDA / 61050 Based Management of Wood A posteriori Demande de prix Limited 10,000.00 0.00 2019-03-05 2019-04-11 2019-05-11 Envelope d'exécution d'entretien au profit de l'UCP, Fuels de la CoFoMO et de la CoFOS BJ-PIU-36247-GO-RFQ / Acquisition de consommables Component 3: Community- Single Stage - One En attente informatiques et bureautiques IDA / 61050 Based Management of Wood A posteriori Demande de prix Limited 18,000.00 0.00 2019-04-20 2019-05-27 2019-06-26 Envelope d'exécution au profit de l'UCP, de la Fuels CoForMO et de la CoFOS BJ-PIU-36331-GO-RFB / Acquisition d'une machine de Component 2: Distribution Single Stage - One En attente traitement d'huile et de divers IDA / 61050 Network Strengthening in A posteriori Appel d'offres Open - National 500,000.00 0.00 2019-02-04 2019-02-09 2019-03-23 2019-04-22 2019-06-05 2020-05-30 Envelope d'exécution autres équipements au profit Targeted Areas de la SBEE BJ-PIU-105394-GO-RFB / Acquisition d'un véhicule de Component 2: Distribution Single Stage - One En cours recherche de défauts sur les IDA / 61050 Network Strengthening in A posteriori Appel d'offres Open - International 270,000.00 0.00 2019-05-15 2019-11-04 2019-05-20 2019-11-06 2019-07-01 2019-07-31 2019-09-04 2020-03-02 Envelope d'exécution câbles souterrains au profit de Targeted Areas la SBEE BJ-PIU-172049-GO-RFQ / Fourniture de matériels Component 3: Community- informatiques et de Bureau au Single Stage - One En attente IDA / 61050 Based Management of Wood A posteriori Demande de prix Limited 100,000.00 0.00 2020-07-07 2020-09-01 2021-02-28 profit de la DGRE, DAF/ME, Envelope d'exécution Fuels DSI/ME, EAT/SBEE et de la DGEFC BJ-PIU-172058-GO-RFQ / Component 3: Community- Fourniture de Motos au profit Single Stage - One En attente IDA / 61050 Based Management of Wood A posteriori Demande de prix Limited 70,000.00 0.00 2020-07-07 2020-09-01 2021-02-28 de la DGEFC, de la DGRE et de Envelope d'exécution Fuels l'UCP BJ-PIU-200261-GO-RFB / Fourniture et installation de six mille (6 000) compteurs Component 1: Improvement Single Stage - One intelligents et divers autres IDA / 61050 of SBEE’s Commercial A priori Appel d'offres Open - International 3,000,000.00 0.00 Annulé 2020-11-15 2020-11-20 2021-01-01 2021-01-31 2021-03-07 2021-09-03 Envelope équipements pour Performance l'installation d'un centre de comptage au profit de la SBEE BJ-PIU-204075-GO-RFB / Fourniture et installation de six mille (6 000) compteurs Component 1: Improvement Single Stage - One En cours intelligents et divers autres IDA / 61050 of SBEE’s Commercial A posteriori Appel d'offres Open - International 3,000,000.00 0.00 2020-12-01 2020-12-08 2020-12-06 2020-12-11 2021-01-17 2021-02-16 2021-03-23 2021-09-19 Envelope d'exécution équipements pour Performance l'installation d'un centre de comptage au profit de la SBEE Page 2 BJ-PIU-227647-GO-RFQ / Acquisition d'équipements communautaires au profit de Component 3: Community- Single Stage - One En attente 14 groupements apicoles IDA / 61050 Based Management of Wood A posteriori Demande de prix Limited 60,000.00 0.00 2021-05-25 2021-07-20 2022-01-16 Envelope d'exécution dans les communes de Djidja, Fuels Bassila, Djougou, N'Dali et Pèrèrè BJ-PIU-227656-GO-RFQ / Réalisation de plaques d'identification des forêts et Component 3: Community- Single Stage - One En attente des MRB, réaménagement et IDA / 61050 Based Management of Wood A posteriori Demande de prix Limited 100,000.00 0.00 2021-05-25 2021-07-20 2022-01-16 Envelope d'exécution réalisation de toîtures et Fuels acquisition de mobiliers de bureau au profit des 09 MRB NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BJ-PIU-83807-NC-RFQ / Entretien et nettoyage des locaux et de la cour du PASE Component 4 : Sector Single Stage - One En cours et de la Direction Générale IDA / 61050 Development and A posteriori Demande de prix Limited 20,000.00 0.00 2018-11-17 2019-02-08 2018-12-17 2020-12-06 Envelope d'exécution des Ressources Énergétiques Implementation Support (DGRE) pour les années 2019 et 2020 BJ-PIU-83825-NC-RFQ / Component 4 : Sector Entretien et maintenance des Single Stage - One En cours IDA / 61050 Development and A posteriori Demande de prix Limited 10,000.00 0.00 2018-11-17 2019-02-08 2018-12-17 2020-12-06 des ordinateurs et accessoires Envelope d'exécution Implementation Support pour les années 2019 et 2020 BJ-PIU-83826-NC-RFQ / Surveillance et gardiennage du siège du PASE et de la Component 4 : Sector Single Stage - One En cours Direction Générale des IDA / 61050 Development and A posteriori Demande de prix Limited 30,000.00 0.00 2018-11-18 2019-02-08 2018-12-15 2020-12-04 Envelope d'exécution Ressources Energétiques Implementation Support (DGRE) pour les années 2019 et 2020 BJ-PIU-83832-NC-RFQ / Component 4 : Sector Entretien et maintenance des Single Stage - One En cours IDA / 61050 Development and A posteriori Demande de prix Limited 4,000.00 0.00 2018-11-22 2019-02-08 2018-12-19 2020-12-08 climatiseurs du PASE pour les Envelope d'exécution Implementation Support années 2019 et 2020 BJ-PIU-83860-NC-RFQ / Nettoyage et entretien des locaux de la cour et des Component 4 : Sector Single Stage - One En cours gazons de la Direction des IDA / 61050 Development and A posteriori Demande de prix Limited 4,000.00 0.00 2018-11-29 2019-02-08 2018-12-26 2020-12-15 Envelope d'exécution Service Intercommunaux (DSI) Implementation Support de la CoForMO pendant les années 2019 et 2020 BJ-PIU-82016-NC-RFQ / Acquisition d'un logiciel de Component 4 : Sector gestion comptable et Single Stage - One IDA / 61050 Development and A posteriori Demande de prix Limited 25,000.00 17,123.15 Signé 2018-11-20 2019-03-08 2019-01-15 2019-05-27 2019-02-14 financière du projet Envelope Implementation Support d'amélioration des services énergétiques. BJ-PIU-94806-NC-RFQ / Service d'un transitaire pour Component 4 : Sector Single Stage - One En cours les formalités d'enlèvement IDA / 61050 Development and A posteriori Demande de prix Limited 50,000.00 0.00 2019-01-27 2019-02-20 2019-02-26 2019-03-28 Envelope d'exécution des matériels roulants à Implementation Support acquérir par le biais de UNOPS BJ-PIU-94808-NC-RFB / Transport et pose de 75 000 Component 2: Distribution Single Stage - One compteurs électroniques à IDA / 61050 Network Strengthening in A posteriori Appel d'offres Open - National 1,700,000.00 1,323,594.27 Signé 2019-01-22 2019-01-24 2019-01-27 2019-03-06 2019-03-10 2019-04-03 2019-04-09 2019-04-04 2019-05-19 2019-09-26 2020-11-09 Envelope prépaiement de type STS au Targeted Areas profit de la SBEE BJ-PIU-229033-NC-DIR / Elaboration et mise en oeuvre de 11 conventions de reboisement avec les SLG Component 3: Community- Passation de En attente dans les parcelles IDA / 61050 Based Management of Wood A posteriori marché de gré à Direct 800,000.00 0.00 2021-06-15 2021-06-20 2021-07-25 2022-01-21 d'exécution d'exploitation forestières des Fuels gré communes de Dassa, Savè, Glazoué, Ouèssè, Tchaourou, Savalou, Bantè, Bassila, et Djidja CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BJ-PIU-36557-CS-QCBS / Etude et mise en place d'un Component 1: Improvement Sélection fondée système de comptabilité IDA / 61050 of SBEE’s Commercial A posteriori sur la qualité et le Open - International 350,000.00 0.00 Annulé 2017-12-15 2018-05-03 2018-01-05 2018-02-03 2018-03-20 2018-04-19 2018-05-24 2018-07-07 2019-07-07 analytique/apurement de Performance coût porte-feuille de la SBEE BJ-PIU-36565-CS-CQS / Recrutement d'un cabinet Sélection fondée pour l'élaboration de plans Component 3: Community- sur les En cours d'aménagement forestier sur IDA / 61050 Based Management of Wood A posteriori Open - International 280,000.00 0.00 2018-02-01 2018-11-07 2018-02-22 2019-01-22 2018-04-07 2018-05-07 2018-06-20 2018-12-17 qualifications des d'exécution 150 000 hectares dans les Fuels consultants communes de DJOUGOU, de N'DALI et de PERERE Page 3 BJ-PIU-36568-CS-CQS / Recrutement d'un cabinet pour les études, la supervision Sélection fondée et le contrôle des travaux de Component 3: Community- sur les En cours construction de huit (08) IDA / 61050 Based Management of Wood A posteriori Open - National 25,000.00 0.00 2018-01-15 2018-05-19 2018-02-05 2019-08-07 2018-03-11 2018-04-10 2018-05-24 2018-11-20 qualifications des d'exécution forages d'eau équipés de Fuels consultants pompes à motricité humaine dans les mielleries des communes de la CoFOS BJ-PIU-36569-CS-CQS / Recrutement d'un cabinet pour les études, la supervision Sélection fondée Component 3: Community- et le contrôle des travaux de sur les IDA / 61050 Based Management of Wood A posteriori Open - National 25,000.00 50,323.22 Signé 2018-01-15 2019-12-03 2018-02-05 2018-03-11 2020-04-30 2018-04-10 2020-07-29 2018-05-24 2020-11-30 2018-11-20 construction des mielleries qualifications des Fuels des communes de la CoFOS et consultants de réfection des anciennes mielleries BJ-PIU-36510-CS-LCS / Component 4 : Sector Sélection au En cours Audit des comptes du PASE, IDA / 61050 Development and A posteriori Open - National 50,000.00 0.00 2018-07-02 2018-07-16 2018-07-23 2018-09-05 2019-01-15 2018-10-20 2018-11-19 2018-12-24 2019-02-06 2019-05-07 moindre coût d'exécution gestions 2018, 2019 et 2020 Implementation Support BJ-PIU-82013-CS-CQS / Un consultant pour les PAR des travaux d'extension des réseaux de distribution de la Sélection fondée Component 2: Distribution SBEE dans les quartiers sur les En cours IDA / 61050 Network Strengthening in A posteriori Open - National 125,000.00 0.00 2018-10-15 2018-10-23 2018-10-23 2018-12-06 2019-01-05 2019-02-18 2019-04-04 périphériques de COTONOU, qualifications des d'exécution Targeted Areas PORTO-NOVO, PARAKOU ET consultants NATITINGOU et de mise aux normes des postes de DASSA, GLAZOUE et de PAOUIGNAN BJ-PIU-82015-CS-CQS / Un consultant pour les EIES des travaux d'extension des réseaux de distribution de la Sélection fondée Component 2: Distribution SBEE dans les quartiers sur les En cours IDA / 61050 Network Strengthening in A posteriori Open - National 125,000.00 0.00 2018-10-15 2018-10-23 2018-10-23 2018-12-06 2019-01-05 2019-02-18 2019-04-04 périphériques de COTONOU, qualifications des d'exécution Targeted Areas PORTO-NOVO, PARAKOU ET consultants NATITINGOU et de mise aux normes des postes de DASSA, GLAZOUE et de PAOUIGNAN BJ-PIU-95239-CS-CQS / Recrutement d'un cabinet Sélection fondée Component 4 : Sector pour les études, la supervision sur les En cours IDA / 61050 Development and A posteriori Limited 17,000.00 0.00 2019-01-24 2019-02-13 2019-01-31 2019-02-10 2019-02-25 2019-05-26 et le contrôle des travaux de qualifications des d'exécution Implementation Support réfection des bâtiments du consultants PASE BJ-PIU-36575-CS-QBS / Etudes de faisabilité détaillées Component 4 : Sector Sélection fondée relatives aux investissements IDA / 61050 Development and A posteriori sur la qualité et le Open - International 700,000.00 0.00 Annulé 2018-10-15 2018-11-05 2018-12-19 2019-01-18 2019-02-17 2019-03-24 2019-04-28 2019-10-25 prioritaires issus du plan de Implementation Support coût production et de distribution de l'électricité BJ-PIU-36564-CS-QBS / Recrutement d'un cabinet pour la formation d'une Component 1: Improvement Sélection fondée équipe de la SBEE à la gestion IDA / 61050 of SBEE’s Commercial A posteriori Open - International 200,000.00 0.00 Annulé 2018-03-15 2018-04-05 2018-05-19 2018-07-03 2018-07-23 2018-08-22 2018-10-05 2019-10-05 sur la qualité des systèmes à installer pour Performance l'amélioration de la gestion de ladite société BJ-PIU-36567-CS-CQS / Recrutement d'un cabinet Sélection fondée Component 3: Community- pour la formation, sur les En cours IDA / 61050 Based Management of Wood A posteriori Open - International 150,000.00 0.00 2019-01-31 2019-02-25 2019-02-21 2019-08-07 2019-04-06 2019-05-06 2019-06-19 2019-12-16 l'encadrement et l'équipement qualifications des d'exécution Fuels des apiculteurs des consultants communes de DJOUGOU, N'DALI et de PERERE BJ-PIU-36574-CS-CQS / Sélection fondée Component 3: Community- Etude de faisabilité pour la sur les En attente IDA / 61050 Based Management of Wood A posteriori Open - International 100,000.00 0.00 2019-02-15 2019-03-08 2019-04-21 2019-05-21 2019-06-25 2019-12-22 mise en place de centres qualifications des d'exécution Fuels emplisseurs de gaz hors consultants dépôt BJ-PIU-68552-CS-INDV / Sélection fondée Component 4 : Sector Recrutement d'un cabinet sur les En cours IDA / 61050 Development and A posteriori Open - International 150,000.00 0.00 2019-01-31 2019-02-18 2019-02-21 2019-04-11 2019-04-06 2019-05-17 2019-05-06 2019-06-19 2019-12-16 pour l'étude sur la qualifications des d'exécution Implementation Support sécurisation de la fourniture consultants en gaz au Bénin BJ-PIU-68557-CS-INDV / Recrutement d'un consultant Sélection fondée Component 1: Improvement pour la réalisation de sur les IDA / 61050 of SBEE’s Commercial A posteriori Open - International 200,000.00 0.00 En cours d'examen 2019-01-31 2021-07-08 2019-02-21 2019-04-06 2019-05-06 2019-06-19 2019-09-17 l'enquête de référence de qualifications des Performance satisfaction des clients de la consultants SBEE BJ-PIU-36573-CS-CQS / Recrutement d'un cabinet Sélection fondée pour l'élaboration et la mise Component 3: Community- sur les En attente en œuvre d'un plan de IDA / 61050 Based Management of Wood A posteriori Open - National 60,000.00 0.00 2019-06-17 2019-07-08 2019-08-11 2019-09-10 2019-10-24 2020-04-21 qualifications des d'exécution communication sur la Fuels consultants normalisation des foyers améliorés BJ-PIU-36572-CS-CQS / Recrutement d'un cabinet Sélection fondée Component 3: Community- pour l'étude sur l'avant-projet sur les En cours IDA / 61050 Based Management of Wood A posteriori Open - International 100,000.00 0.00 2019-01-30 2019-02-25 2019-02-20 2019-08-07 2019-04-05 2019-05-05 2019-06-09 2019-12-06 de normes et proposition qualifications des d'exécution Fuels d'une stratégie pour consultants l'organisation de la filière "foyers améliorés" BJ-PIU-36566-CS-CQS / Recrutement d'un cabinet Sélection fondée Component 3: Community- pour les études, la supervision sur les En cours IDA / 61050 Based Management of Wood A posteriori Open - National 30,000.00 0.00 2019-01-31 2019-03-04 2019-02-21 2019-03-27 2019-04-26 2019-06-09 2019-12-06 et le contrôle des travaux de qualifications des d'exécution Fuels construction du siège de la consultants CoFOS Page 4 BJ-PIU-36494-CS-QCBS / Supervision et contrôle des travaux de mise aux normes Sélection fondée Component 2: Distribution des postes HT/MT des sous- sur les IDA / 61050 Network Strengthening in A posteriori Open - International 122,000.00 1,314,781.43 Signé 2019-02-04 2020-01-13 2019-02-25 2020-03-20 2019-04-10 2020-07-07 2019-04-25 2021-01-07 2019-06-08 2021-04-28 2020-06-02 stations de Dassa-Zounmè, qualifications des Targeted Areas Glazoué, Paouignan et des consultants réseaux souterrains de la ville de Porto-Novo BJ-PIU-36482-CS-QCBS / Supervision et contrôle des travaux de normalisation et Sélection fondée Component 2: Distribution d'extension des réseaux de sur les En cours IDA / 61050 Network Strengthening in A posteriori Open - International 250,000.00 0.00 2019-02-04 2020-01-13 2019-02-18 2020-03-20 2019-03-24 2019-04-23 2019-06-06 2020-05-31 distribution de la SBEE dans qualifications des d'exécution Targeted Areas les quartiers périphériques consultants des villes de Cotonou, Porto- Novo, Parakou et Natitingou BJ-PIU-95475-CS-CQS / Mise à jour de l'étude diagnostique institutionnelle du ministère Sélection fondée en charge de l'énergie, des Component 4 : Sector sur les En attente structures associées (cabinet IDA / 61050 Development and A posteriori Open - National 150,000.00 0.00 2019-02-20 2019-03-13 2019-04-11 2019-04-21 2019-05-31 2019-11-27 qualifications des d'exécution du Ministre, Direction Implementation Support consultants Générale des Ressources Energétiques (DGRE) ex DGE, ABERME, , ARE) BJ-PIU-105019-CS-CQS / Etude d'Impact Environnemental des travaux Sélection fondée de construction d'un atelier de Component 4 : Sector sur les En cours réparation des IDA / 61050 Development and A posteriori Open - National 150,000.00 0.00 2019-04-15 2019-03-18 2019-05-06 2019-08-07 2019-06-19 2019-07-19 2019-08-23 2020-02-19 qualifications des d'exécution transformateurs et Implementation Support consultants d'installation d'une machine de traitement d'huile au profit de la SBEE à Abomey Calavi BJ-PIU-105034-CS-CQS / Plans d'Actions de Réinstallation des Populations pour les Travaux de Sélection fondée Construction d'un Atelier de Component 4 : Sector sur les En cours Réparation des IDA / 61050 Development and A posteriori Open - National 150,000.00 0.00 2019-04-15 2019-03-18 2019-05-06 2019-08-07 2019-06-19 2019-07-19 2019-08-23 2020-02-19 qualifications des d'exécution Transformateurs et Implementation Support consultants d'Installation d'une Machine de Traitement d' Huile au profit de la SBEE à Abomey Calavi BJ-PIU-105036-CS-CQS / Sélection fondée Etude d'impact Component 4 : Sector sur les En attente environnemental et social des IDA / 61050 Development and A posteriori Open - National 55,000.00 0.00 2019-10-01 2019-10-22 2019-12-05 2020-01-04 2020-02-08 2020-08-06 qualifications des d'exécution Travaux de Construction du Implementation Support consultants Siège de la CoFOS BJ-PIU-105041-CS-CQS / Élaboration du Plans d'Actions Sélection fondée Component 4 : Sector de Réinstallation des sur les En attente IDA / 61050 Development and A posteriori Open - National 35,000.00 0.00 2019-10-01 2019-10-22 2019-12-05 2020-01-04 2020-02-08 2020-08-06 Populations des Travaux de qualifications des d'exécution Implementation Support Construction du Siège de la consultants CoFOS BJ-PIU-105047-CS-CQS / Étude d'impact Sélection fondée Component 4 : Sector environnemental et social des sur les En attente IDA / 61050 Development and A posteriori Open - National 35,000.00 0.00 2019-10-01 2019-10-22 2019-12-05 2020-01-04 2020-02-08 2020-08-06 travaux de construction de 14 qualifications des d'exécution Implementation Support forages d'eau équipés de consultants pompe à motricité humaine BJ-PIU-105049-CS-CQS / Élaboration du Plan d'Actions Sélection fondée de Réinstallation des Component 4 : Sector sur les En attente Populations des Travaux de IDA / 61050 Development and A posteriori Open - National 35,000.00 0.00 2019-10-01 2019-10-22 2019-12-05 2020-01-04 2020-02-08 2020-08-06 qualifications des d'exécution Construction de 14 forages Implementation Support consultants équipés de pompe à motricité humaine BJ-PIU-105052-CS-CQS / Étude d'impact Sélection fondée Component 4 : Sector environnemental et social des sur les En attente IDA / 61050 Development and A posteriori Open - National 70,000.00 0.00 2019-10-01 2019-10-22 2019-12-05 2020-01-04 2020-02-08 2020-08-06 travaux de construction de 14 qualifications des d'exécution Implementation Support miellerie dans les espaces consultants CoForMO et CoFOS BJ-PIU-105054-CS-CQS / Élaboration du Plan d'Actions Sélection fondée de Réinstallation des Component 4 : Sector sur les En attente Populations des Travaux de IDA / 61050 Development and A posteriori Open - National 35,000.00 0.00 2019-10-01 2019-10-22 2019-12-05 2020-01-04 2020-02-08 2020-08-06 qualifications des d'exécution Construction de 14 Miellerie Implementation Support consultants dans les espaces CoForMO et CoFOS BJ-PIU-105391-CS-CQS / Sélection fondée Component 4 : Sector Audit du fonctionnement de la sur les En cours IDA / 61050 Development and A posteriori Open - International 200,000.00 0.00 2019-05-06 2019-03-18 2019-05-27 2019-07-10 2019-08-09 2019-09-13 2020-03-11 Station de Vedoko en vue de qualifications des d'exécution Implementation Support sa numérisation consultants BJ-PIU-106345-CS-QCBS / Component 1: Improvement Sélection fondée Etude et mise en place d'un IDA / 61050 of SBEE’s Commercial A posteriori sur la qualité et le Open - International 350,000.00 207,465.67 Signé 2019-04-03 2019-03-28 2019-04-24 2019-05-28 2019-06-07 2019-09-10 2019-07-05 2019-10-10 2019-08-04 2019-10-10 2019-09-08 2020-03-19 2019-10-22 2020-07-15 2020-04-19 système de comptabilité Performance coût analytique au profit de la SBEE BJ-PIU-150026-CS-CQS / Sélection fondée Component 4 : Sector Élaboration de la stratégie sur les IDA / 61050 Development and A posteriori Open - International 250,000.00 303,924.22 Signé 2020-02-06 2019-12-16 2020-02-27 2020-01-24 2020-04-11 2020-04-22 2020-05-11 2020-06-08 2020-06-15 2020-09-29 2020-12-12 nationale d'électrification au qualifications des Implementation Support Bénin consultants BJ-PIU-150027-CS-CQS / Sélection fondée Component 4 : Sector Etude sur les normes et sur les IDA / 61050 Development and A posteriori Open - International 200,000.00 348,777.63 Signé 2020-02-10 2020-01-21 2020-03-02 2020-02-28 2020-04-15 2020-06-22 2020-05-15 2020-07-27 2020-06-19 2020-11-04 2020-12-16 Standard de distribution de qualifications des Implementation Support l'électricité au Bénin consultants BJ-PIU-155075-CS-CQS / Sélection fondée Component 4 : Sector Mise à Jour du Plan de sur les IDA / 61050 Development and A posteriori Limited 150,000.00 424,894.51 Signé 2020-02-25 2020-02-07 2020-03-10 2020-03-11 2020-04-09 2020-07-15 2020-05-14 2020-11-04 2020-11-10 Développement de Production qualifications des Implementation Support à Moindre Coût (PDMC) consultants Page 5 BJ-PIU-172060-CS-CQS / Sélection fondée Component 4 : Sector Mise en Ouvre d'activités de sur les En cours IDA / 61050 Development and A posteriori Open - National 100,000.00 0.00 2020-07-02 2020-07-15 2020-07-23 2020-09-05 2020-10-05 2020-11-09 2021-05-08 Communication pour la qualifications des d'exécution Implementation Support Visibilité des Actions du PASE consultants BJ-PIU-227661-CS-CQS / Sélection fondée Component 3: Community- Recrutement d'un cabinet sur les En attente IDA / 61050 Based Management of Wood A posteriori Open - International 200,000.00 0.00 2021-06-10 2021-07-01 2021-08-14 2021-09-13 2021-10-18 2022-04-16 pour l'opérationnalisation des qualifications des d'exécution Fuels SLG et Développement des consultants AGR BJ-PIU-227664-CS-CQS / Appui à l'amélioration des Sélection fondée Component 3: Community- rendements agricoles et sur les En attente IDA / 61050 Based Management of Wood A posteriori Open - International 150,000.00 0.00 2021-07-08 2021-07-29 2021-09-11 2021-10-11 2021-11-15 2022-05-14 sensibilisation des éleveurs qualifications des d'exécution Fuels transhumants (sur respect des consultants couloirs de passage BJ-PIU-227665-CS-CQS / Sélection fondée Component 3: Community- Recrutement d'un cabinet de sur les En attente IDA / 61050 Based Management of Wood A posteriori Limited 55,000.00 0.00 2021-08-05 2021-08-19 2021-09-18 2021-10-23 2022-04-21 recrutement du personnel DSI qualifications des d'exécution Fuels CoFOS consultants INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BJ-PIU-36513-CS-INDV / Component 4 : Sector Recrutement d'un consultant IDA / 61050 Development and A posteriori Individuel Open 150,000.00 108,403.31 Signé 2017-11-30 2018-01-26 2018-01-24 2018-05-15 2018-02-14 2018-06-18 2018-03-30 2018-09-21 2019-03-25 individuel pour l'audit interne Implementation Support du PSAE BJ-PIU-36558-CS-INDV / Recrutement d'un consultant individuel chargé d'élaborer le Component 1: Improvement En cours plan d'amélioration de la IDA / 61050 of SBEE’s Commercial A posteriori Individuel Open 50,000.00 0.00 2017-12-15 2018-05-23 2018-02-02 2019-03-15 2018-02-23 2019-04-30 2018-04-08 2018-10-05 d'exécution gestion de la SBEE, le cahier Performance des charges et le DAO pour sa mise en oeuvre BJ-PIU-68547-CS-INDV / Recrutement d'un consultant Component 4 : Sector individuel pour l'étude En cours IDA / 61050 Development and A posteriori Individuel Limited 120,000.00 75,000.00 2018-07-12 2018-08-08 2018-07-17 2018-11-22 2018-08-07 2019-02-28 2018-09-20 2019-05-21 2018-12-19 d'impact économique et social d'exécution Implementation Support de la fourniture d'électricité au Bénin BJ-PIU-36586-CS-QBS / Recrutement d'experts pour Component 4 : Sector appuyer le cabinet du IDA / 61050 Development and A priori Individuel Open 350,000.00 0.00 Annulé 2018-09-03 2018-10-22 2018-11-12 2018-12-17 2019-06-15 Ministère en charge de Implementation Support l'énergie BJ-PIU-36588-CS-INDV / Un consultant individuel pour les PAR des travaux d'extension des réseaux de distribution de Component 2: Distribution la SBEE dans les quartiers IDA / 61050 Network Strengthening in A posteriori Individuel Open 75,000.00 0.00 Annulé 2018-01-02 2018-06-01 2018-02-10 2018-03-03 2018-04-16 2018-10-13 périphériques de COTONOU, Targeted Areas PORTO-NOVO, PARAKOU ET NATITINGOU et de mise aux normes des postes de DASSA, GLAZOUE et de PAOUIGNAN BJ-PIU-36587-CS-INDV / Un consultant individuel pour les EIES des travaux d'extension des réseaux de distribution de Component 2: Distribution la SBEE dans les quartiers IDA / 61050 Network Strengthening in A posteriori Individuel Open 75,000.00 0.00 Annulé 2018-01-02 2018-05-03 2018-02-10 2018-03-03 2018-04-16 2018-10-13 périphériques de COTONOU, Targeted Areas PORTO-NOVO, PARAKOU ET NATITINGOU et de mise aux normes des postes de DASSA, GLAZOUE et de PAOUIGNAN BJ-PIU-36514-CS-INDV / Recrutement d'un consultant individuel pour l'élaboration Component 1: Improvement du cahier des charges IDA / 61050 of SBEE’s Commercial A posteriori Individuel Open 100,000.00 0.00 Annulé 2017-11-30 2018-01-19 2018-01-24 2018-02-14 2018-03-30 2018-09-26 relatives à la mise en place Performance d'un centre d'appels à la SBEE et suivi des prestations BJ-PIU-68554-CS-INDV / Recrutement d'un consultant individuel pour la préparation Component 4 : Sector d'un plan stratégique de IDA / 61050 Development and A posteriori Individuel Limited 120,000.00 0.00 Annulé 2019-01-25 2019-01-30 2019-02-20 2019-04-05 2019-07-04 développement du secteur de Implementation Support l'énergie pour les cinq (05) prochaines années. BJ-PIU-36580-CS-CDS / Component 4 : Sector Audit de fonctionnement du IDA / 61050 Development and A posteriori Individuel Open 200,000.00 0.00 Annulé 2019-09-02 2019-10-21 2019-11-11 2019-12-25 2020-06-22 poste de VEDOKO en vue de Implementation Support sa numérisation BJ-PIU-36571-CS-INDV / Recrutement d'un consultant individuel pour la réalisation Component 3: Community- d'une étude sur les chaînes de En cours IDA / 61050 Based Management of Wood A posteriori Individuel Limited 55,000.00 0.00 2019-02-11 2019-09-19 2019-02-16 2019-03-09 2019-04-13 2019-07-12 valeur de la filière apicole et d'exécution Fuels d'une étude de faisabilité pour l'installation d'une miellerie centrale BJ-PIU-105056-CS-INDV / Component 4 : Sector En cours Mise en place d'un site Web IDA / 61050 Development and A posteriori Individuel Limited 20,000.00 0.00 2019-05-02 2019-05-24 2019-05-07 2019-05-28 2019-07-02 2019-12-29 d'exécution pour le PASE Implementation Support Page 6 BJ-PIU-36584-CS-QBS / Mise à jour de l'étude diagnostique institutionnelle du ministère en charge de l'énergie, des Component 4 : Sector Sélection de En attente structures associées (cabinet IDA / 61050 Development and A posteriori consultants par Direct 150,000.00 0.00 2019-04-25 2019-05-05 2019-07-18 2019-11-15 d'exécution du Ministre, Direction Implementation Support entente directe Générale des Ressources Energétiques (DGRE) ex DGE, ABERME, , ARE) BJ-PIU-114724-CS-INDV / Réalisation de l'audit de la mise en œuvre du Plan d'Actions de Réinstallation Component 4 : Sector En cours (PAR) des populations IDA / 61050 Development and A posteriori Individuel Open 60,000.00 0.00 2019-05-20 2019-05-28 2019-07-08 2019-07-29 2019-09-02 2019-10-07 d'exécution affectées du projet de Implementation Support construction de la ligne 330 kv Ghana-Togo-Bénin (partie béninoise des travaux) BJ-PIU-146740-CS-INDV / Component 4 : Sector Etude d'impact Économique et En attente IDA / 61050 Development and A posteriori Individuel Open 120,000.00 0.00 2020-01-15 2020-03-04 2020-03-25 2020-04-29 2020-10-26 Social de la Fourniture d'exécution Implementation Support d'Electricité au Bénin BJ-PIU-150028-CS-INDV / Assistance au Ministère pour Component 4 : Sector En cours l'élaboration et le suivi des IDA / 61050 Development and A posteriori Individuel Limited 120,000.00 0.00 2020-03-16 2020-12-14 2020-03-21 2020-04-11 2020-05-16 2020-11-12 d'exécution tableaux de bord des Projets Implementation Support du Secteur BJ-PIU-154001-CS-INDV / Actualisation du Cadre Procédural de gestion durable des ressources forestières Component 3: Community- En cours dans les espaces de la IDA / 61050 Based Management of Wood A posteriori Individuel Limited 20,000.00 0.00 2020-02-20 2020-01-21 2020-02-25 2020-03-17 2020-04-21 2020-10-18 d'exécution Communauté Forestière du Fuels Moyen Ouémé (CoForMO) et de la Communauté Forestière de l’Ouémé Supérieur (CoFOS) BJ-PIU-150029-CS-CDS / Sélection d'un Coordinateur Component 4 : Sector En cours pour le Projet d'Amélioration IDA / 61050 Development and A posteriori Individuel Open 120,000.00 0.00 2020-02-11 2020-02-25 2020-03-31 2020-04-21 2020-05-26 2020-11-22 d'exécution des Services Energétiques Implementation Support (PASE) BJ-PIU-200619-CS-INDV / Component 4 : Sector Sélection d'un auditeur En cours IDA / 61050 Development and A posteriori Individuel Limited 100,000.00 0.00 2020-11-19 2021-01-13 2020-11-24 2020-12-15 2021-01-19 2021-07-18 interne du projet pour les d'exécution Implementation Support années 2021 et 2022 BJ-PIU-205120-CS-INDV / ELABORATION DU CADRE DE POLITIQUE DE Component 4 : Sector En cours RÉINSTALLATION (CPR) DU IDA / 61050 Development and A posteriori Individuel Limited 35,000.00 0.00 2020-12-14 2020-11-16 2020-12-19 2021-01-09 2021-02-13 2021-08-12 d'exécution PROJET D’AUGMENTATION DE Implementation Support L’ACCES A L’ELECTRICITE (P2AE) BJ-PIU-205122-CS-INDV / ÉLABORATION DU CADRE DE GESTION ENVIRONNEMENTALE Component 4 : Sector En cours ET SOCIALE DU PROJET IDA / 61050 Development and A posteriori Individuel Limited 35,000.00 0.00 2020-12-14 2020-11-16 2020-12-19 2021-01-09 2021-02-13 2021-08-12 d'exécution D’AUGMENTATION DE Implementation Support L’ACCES A L’ELECTRICITE (P2AE) BJ-PIU-245839-CS-INDV / Component 1: Improvement Assistance à la mise en place En attente IDA / 61050 of SBEE’s Commercial A posteriori Individuel Limited 100,000.00 0.00 2021-08-20 2021-08-25 2021-09-15 2021-10-20 2022-04-18 d’un Programme de Protection d'exécution Performance des Revenus (PPR). BJ-PIU-245842-CS-INDV / Audit de la mise en oeuvre des PARs relatifs aux travaux de normalisation dans les villes de Parakou, Natitngou, Component 2: Distribution En attente Cotonou et Porto Novo, de IDA / 61050 Network Strengthening in A posteriori Individuel Limited 45,000.00 0.00 2021-08-25 2021-08-30 2021-09-20 2021-10-25 2022-04-23 d'exécution mise aux aux normes des Targeted Areas Postes de Paouignan et de Glazoué et de Construction d'un atelier de réparation des transfo Page 7